CONSTRUCTION OF TEMPORARY CLASS ROOM SHED FOR TRIRATNA COOPERATIVE SCHOOL, BUNGAMATI PROJECT COST ESTIMATE S.N. Item Quantity Unit Rate in NRs. Amount in NRs. Amount in USD Remarks 1 Earth Work Excavation for Foundation Pad and Walls 3,560 CFT 8.00 28,480.00 284.80 Locally managed 2 Flat Brick Soling 1,133 SFT 35.00 39,655.00 396.55 Locally managed 3 2" thk PCC (1:3:6) 1,133 SfFT 240.00 271,920.00 2,719.20 Locally managed - 4 Bricks for 14" Brick Wall For Toe Wall and 22,000 Pcs 14.00 308,000.00 3,080.00 Support Needed 5 Floor Finishing 2,840 SFT 120.00 340,800.00 3,408.00 Support Needed 6 Partition Work ( Cement Board or other suitable Boards) 4,400 SFT 160.00 704,000.00 7,040.00 Support Needed 7 Truss for Class Room and Passage - 3"x3" Pipe For Main Post 320 FT 125.00 40,000.00 400.00  Already procured 2" ø Post and Rafter 680 Ft 60.00 40,800.00 408.00  Already procured 1.5" ø Purline 1,474 Ft 45.00 66,330.00 663.30  Already procured 1"ø Pipe Frame Bracing For Poles (1'-0" ht) Hor. Member ( Top & Bottom) 1,140 Ft. 35.00 39,900.00 399.00  Already procured 8 CGI Sheet, assorted size 24 bundle 9,070.00 217,680.00 2,176.80  Already procured 9 Plain Sheet( 4'-0" X 8'-0") 14 Nos 1,440.00 20,160.00 201.60  Already procured - 10 Doors, Windows & Ventilators - Door (3'-0" X 7'-0") 231 SFT 350.00 80,850.00 808.50 Support Needed Win (4'-0" X 4'-0") 368 SFT 350.00 128,800.00 1,288.00 Support Needed Vent (5'-0" X 2'-0") 110 SFT 35 0.00 38,500.00 385.00 Support Needed TOTAL COST 2,337,395.00 23,373.95 (In Words Two million three hundred thirty seven thousand three hundred ninty five only)

Upload: spellbindguy

Post on 13-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Construction of Temporary Class Room Shed

7/26/2019 Construction of Temporary Class Room Shed

http://slidepdf.com/reader/full/construction-of-temporary-class-room-shed 1/2

CONSTRUCTION OF TEMPORARY CLASS ROOM SHEDFOR TRIRATNA COOPERATIVE SCHOOL, BUNGAMATI

PROJECT COST ESTIMATE

S.N. Item Quantity UnitRate inNRs.

Amount inNRs.

Amountin USD Remarks

1Earth Work Excavation forFoundation Pad and Walls 3,560 CFT 8.00 28,480.00 284.80

Locallymanaged

2Flat Brick Soling 1,133 SFT 35.00 39,655.00 396.55

Locallymanaged

32" thk PCC (1:3:6) 1,133 SfFT 240.00 271,920.00 2,719.20

Locallymanaged

-

4 Bricks for 14" Brick Wall ForToe Wall and 22,000 Pcs 14.00 308,000.00 3,080.00

SupportNeeded

5Floor Finishing 2,840 SFT 120.00 340,800.00 3,408.00

SupportNeeded

6 Partition Work ( Cement

Board or other suitableBoards) 4,400 SFT 160.00 704,000.00 7,040.00

SupportNeeded

7 Truss for Class Room andPassage -

3"x3" Pipe For Main Post 320 FT 125.00 40,000.00 400.00 Alreadyprocured

2" ø Post and Rafter 680 Ft 60.00 40,800.00 408.00 Alreadyprocured

1.5" ø Purline 1,474 Ft 45.00 66,330.00 663.30 Alreadyprocured

1"ø Pipe Frame Bracing ForPoles (1'-0" ht) Hor. Member (Top & Bottom) 1,140 Ft. 35.00 39,900.00 399.00

 Alreadyprocured

8CGI Sheet, assorted size 24 bundle 9,070.00 217,680.00 2,176.80

 Alreadyprocured

9Plain Sheet( 4'-0" X 8'-0") 14 Nos 1,440.00 20,160.00 201.60

 Alreadyprocured

-

10Doors, Windows & Ventilators -

Door (3'-0" X 7'-0") 231 SFT 350.00 80,850.00 808.50SupportNeeded

Win (4'-0" X 4'-0") 368 SFT 350.00 128,800.00 1,288.00SupportNeeded

Vent (5'-0" X 2'-0") 110 SFT 350.00 38,500.00 385.00SupportNeeded

TOTAL COST2,337,395.00 23,373.95

(In Words Two million three hundred thirty seven thousand three hundred ninty five only)

Page 2: Construction of Temporary Class Room Shed

7/26/2019 Construction of Temporary Class Room Shed

http://slidepdf.com/reader/full/construction-of-temporary-class-room-shed 2/2

 

SUMMERY OF BUDGET:

1TOTAL ESTIMATED COST

2,337,395.00 23,373.95

2 Amount Managed to date or item already procured

(424,870.00) (4,248.70)

3

Item supported locally

(340,055.00) (3,400.55)

4SUPPORT REQUIRED

1,572,470.00 15,724.70