Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Upload: haley-freeman

Post on 26-Mar-2015

229 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Construction Mgmt & Economics

CONTRACT ADMINISTRATION 341

Kee Bee Kheng (Ms)

Page 2: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Unit Outline

• General Introduction• Introduction To The Unit• Teaching And Learning Objectives• Method Of Study• Prescribed Texts• Recommended Reading• Structure Of Unit• Point Of Access To Topic Notes

Page 3: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Twelve (12) Study Topics• Introduction And Contract Law

• Core Clauses, Strategies & Characteristics

• Tendering And Risk

• Sub Contracting

• Variations (Changes)

• Payments

• Insurances

• Time

• Claims

• Contract Completion & Close Out

• Disputes

• Computer Aided Contract Administration

Page 4: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Learning Objectives

• Identify Core Characteristics of Standard Forms;• Know Various Contractual Identities & Their

Roles;• Know Types Of Contracts;• Recognise Contract Admin Practices &

Procedures; and• Become Familiar With Contractual

Documentation & Its Interconnectivity.

Page 5: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

References• Accompany Text

– JCC-C Standard Forms Of Contract (Australian)

• References– AS 4000, AS 2124, NEC and C21 (Australian)

– PSSCOC, SIA (Singapore)

– JTC (United Kingdom)

• Recommended Texts– Constrn Industry Terminology, David Standen

– Bldg & Constrn Contracts In Australia, Dorter & Sharkety

– Constrn Law In Australia, Ian I Bailey

– Contract Mgmt In Australia, John F. James

Page 6: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Types of Contract• Formal Contract

– under deed or company seal (signed, sealed & delivered);

– do not require any consideration (value);

– rarely used in construction contracts;

– have to be signed by all parties, all signatures witnessed and signed.

• Simple Contract– parties in the contract identify their required elements;

– perform their duties under the contract to deliver those elements.

Page 7: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Topic 1 - Contract LawLearning Objectives

• What is Law?• Branches Of Law.• What is a Contract? (Simple)• The Basic Elements Of A Binding Contract.• Offer & Acceptance.• Counter Offers.• Shortcomings Of “Letters Of Intent”.• Legal Concept Of “Privity Of Contract” & How It

Affects Sub-Contractors.• Self Assessment Questions.

Page 8: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

What Is LAW?• Is A Body Of Rules Aimed To Guide One’s

Action In Society.

• It Includes:– Common Law

• Is governed by the Doctrine of “Stare Decisis”.

– Statue Law• Laws approved by Parliament in the form of an act.

– Equity• fairness or justice. Is based on principles of conscience.

• to supplement the statute or common law.

Page 9: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Branches Of Law• Criminal Law (Is public law)

• Civil Law (Private Law)

THE STATE

Person Person

Person

SuccessionFamilyContractTortPropertyEmployment

Person

Page 10: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

What Is A Contract?

A legally binding agreement between two or more parties, by which rights are acquired by one or more to act or forebearances on the part of the other or others.

Page 11: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Basic Elements Of A Binding Contract

• Offer & Acceptance

• Intention

• Capacity

• Consent

• Legality

• Possibility

• Consideration

Page 12: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Formation Of A Contract

• Orally

• By Conduct or “Implied Action”

• By Deed

• In Writing

Page 13: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Offer

An offer is an expression of willingness to contract on certain terms made within the intention that it shall become binding as soon as it is accepted by the person to whom the offer is addressed.

Page 14: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Invitations To Treat/ Offer

• Invitations To Treat– Advertisement– Invitation To Tender– Supply “As and when required”

• Offer– to supply a specific quantity on specific date.– To supply a specific quantity over a period of

time.

Page 15: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Acceptance

Acceptance may be defined as an unconditional agreement, communicated by the offeree to the offeror, to all the terms of the offer, made with the intention of accepting that offer. Whether an acceptance has in fact occurred is determined from the behaviour of the parties including any correspondence that has passed between the parties.

Page 16: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Basic Elements of An Acceptance

• Knowledge of the Offer.

• If there is an acceptance.

• How an acceptance is made?

• Acceptance or Counter-offer.

• Is there a communication?

• According to specific instruction?

• No acceptance by silence.

Page 17: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Counter Offer

• A “Conditional Instruction To Proceed”.

• An Attempt To Negotiate Price Or Specification.

• “Paper War”

• Subject To Client’s Terms & Conditions (often happen between main & sub contractors).

Page 18: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Withdrawal Of Offer

• Can be anytime before acceptance UNLESS there is a condition for the offer be kept open for a period of time;

• Must be communicated to the person making an offer;

• Must reach the person before it was accepted;

• Postal rule does not apply; and

• If by fax or telex, it must be received by the person in person.

Page 19: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Discharge

• Performance

• Agreement

• Operation of Law

• Frustration or subsequent impossibility

Page 20: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Breach - Remedies

• Refusal of further performance;

• Rescission;

• An action for specific performance;

• An action for an injunction;

• An action for damages; and

• An action for a ‘Quantum Meruit”

Page 21: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Privity Of Contract

• Only persons who are parties to the contract are affected.

• Cannot impose obligations nor confer rights on others who are not privity to it.

Page 22: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Letter Of Intent

• Where immediate signing of contracts not possible;

• If works were done, contractor can claim ‘Quantum Meruit”;

• Exception, where Letter Of Intent combines with Instruction To Proceed. The latter is a conditional acceptance of a tender (e.g. subject to acceptance of client.)

Page 23: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Is There A Contract?

Example:

1 We are pleased to inform you that, subject to an acceptance of our main contract by the Client, the contract for the work will be placed with your company.

2 We are pleased to inform you that, subject to a satisfactory outcome to negotiations between us on certain points in your tender as above, the contract for the work will be placed with your company.

Page 24: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Self Assessment QuestionsExplain how a contract may exist because one of

the essential criteria is said to be implied.A road bridge over a river collapses sending the

cars on the bridge into the water below. One of the drivers in one of the cars is seriously injured as a result of the fall. Is the injured driver of the vehicle prevented from claiming compensation for his injuries as a result of not being privy to the contract for the design and construction of the bridge.

Page 25: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Self Assessment Questions -2Under what circumstances should consideration be

given to the use of a Letter of Intent?A contractor builds a house for his mother which

he sells 5 years later when his mother dies. The purchaser subsequently sells the house after 4 years to a purchaser who has various inspections undertaken to ensure the house is in sound and good condition. Two years later the house develops serious and substantial cracks. To what degree do you consider the contractor to be liable?

Page 26: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Topic 2 - Strategies & Characteristics

• Learning Objectives;

• Background To Standard Forms Of Contract;

• Contract Strategies;

• Self Assessment Questions.

Page 27: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

2-Learning Objectives

• Different Contract Philosophies;

• Core Characteristics Of Standard Forms Of Contract;

• Typical Contract Clauses; and

• A System Approach To Contract Components.

Page 28: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Contract Philosophies - 1

• JCC-C– Proprietor/Builder– Fair apportionment of responsibility;– Aim the party best able to deal with a

responsibility bear the risk;– e.g. Proprietor is responsible for accuracy of

information whilst Builder is responsible for means & methods of construction. Neutral risks are equally shared.

Page 29: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Contract Philosophies - 2

• AS 2124 - 1992– Based on NPWC/NBCC Joint Working Party

Paper on “No Disputes”;– Set out rights & obligations of the parties;– Set out 100 circumstances where written notice

may be required from one party to another;– Emphasises contract is the essential means of

communication to enable proper & orderly admin of the contract.

Page 30: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Contract Philosophies - 3

• NEC (New Engineering Contract) from New South Wales;– Presume “Win-Win” scenario;– Use plain English & easily comprehensed

language with guidance notes;– Separate the roles of contract administrator

from certifier & assessor;– Apportion risk to the party best able to

manage it.

Page 31: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Contract Philosophies - 4

• C21 – widely use in UK;– provides a clear distinction between

contract management & administration;– allows up front incentive payments to

contractor;– simplify delay procedures;– no Superintendent - rep of Principal &

Contractor act for themselves.

Page 32: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Contract Philosophies - 5

• AS 4000 - 1997– derives from AS 2124;– writes in plain English;– some clauses vary from AS 2124 e.g. include

Intellectual Property and Novation of part of the work; and

– roles & responsibilities remain unchanged.

Page 33: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Contract Philosophies - 6

• PSSCOC 95– Adaptability– Sound Construction Management– Construction Quality– Allocation of Risks– Clarity of Language

Page 34: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Conditions of Contract• JCC-C 94

1 General2 Documents3 The Site4 Sub-Contracts5 Administration6 Execution Of The Works7 Separate Contracts8 Insurances9 Time10 Payment & Adj CS11 Final Certificate & Final Payment12 Determination13 Dispute Resolution14 Notices15 Special Conditions16 Appendix

• SIA 991 Architect’s Directions & Instruction2 Methods of Working & Temp Works3 Design & Completion Responsibilities4 Programme5 Make-Up Of Contractor’s Prices6 Administration7 Statutory Obligations8 Setting Out9 Access For Architect10 Possession of Site & Commencement11 Quality of Materials & Workmanship12 Variations & Valuation of Additional Pay’t13 Measurement & BQ14 Discrepancy Or Divergence15 Assignment & Subcontracting16 Plant & Materials17 Artists, Tradesmen & Other Contractors18 Indemnities To Employer19 Injury (Persons, Property) & W C20 Insurance Of Works21 Due Diligence By Contractor22 Time for Completion23 Extension of Time24 Delay & LAD25 Phase & Stage Completion26 Partial Re-occupation27 Maintenance28 Designated NSC29 Nomination & Rights of Objection30 Payment of NSC31 Payment of Contractor32 Termination by Employer33 Termination by Contractor34 Outbreak of war35 War Damage36 Antiquities37 Arbitration38 Optimal Cl (Fluctuations)39 Optimal Cl (Excess)40 Appendix

PSSCOC 95

1 Definitions & Interpretation2 S.O. & S.O. Representative3 Contract Documents4 General Obligations Of Contractor5 Sub-Surface & Ground Conditions6 Permanent Work Designed by Contractor7 Notices & Fees8 Setting Out9 Programme For the Works10 Quality In Construction11 Administration12 Possession Of Site13 Suspension14 Time For Completion15 Expedition Progress Of Works16 Liquidated Damages17 Substantial Completion18 Defects19 Variations To The Works20 Valuation Of Variations21 Measurement22 Claims For Loss & Expense23 Procedure For Claims24 Constrn Equipment Temp Wks Mat & Goods25 General Responsibilities26 Indemnity Provisions27 Injury (Person & Property) & W C28 Insurance Of The Works29 Damage To Property Of Employer Or Govt30 Assignment & Subcontracting31 Termination By The Employer32 Progress Payments & Final Account33 Final Completion Certificate34 Settlement Of Disputes35 Recovery By The Employer36 Governing Law & Notices37 Appendix

Page 35: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Conditions of Contract• JCC-C 94

1 General2 Documents3 The Site4 Sub-Contracts5 Administration6 Execution Of The Works7 Separate Contracts8 Insurances9 Time10 Payment & Adj CS11 Final Certificate & Final

Payment12 Determination13 Dispute Resolution14 Notices

• SIA 991 Architect’s Directions

& Instruction2 Methods of Working &

Temp Works3 Design & Completion

Responsibilities4 Programme5 Make-Up Of

Contractor’s Prices6 Administration7 Statutory Obligations8 Setting Out9 Access For Architect10 Possession of Site &

Commencement11 Quality of Materials &

Workmanship12 Variations & Valuation

of Additional Pay’t13 Measurement & BQ14 Discrepancy Or

Divergence

PSSCOC 951 Definitions & Interpretation2 S.O. & S.O. Representative3 Contract Documents4 General Obligations Of Contractor5 Sub-Surface & Ground Conditions6 Permanent Work Designed by Contractor7 Notices & Fees8 Setting Out9 Programme For the Works10 Quality In Construction11 Administration12 Possession Of Site13 Suspension14 Time For Completion

Page 36: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Conditions of Contract• JCC-C 94

15 Special Conditions

16 Appendix

• SIA 9915 Assignment &

Subcontracting16 Plant & Materials17 Artists, Tradesmen &

Other Contractors18 Indemnities To

Employer19 Injury (Persons,

Property) & W C20 Insurance Of Works21 Due Diligence By

Contractor22 Time for Completion23 Extension of Time24 Delay & LAD25 Phase & Stage

Completion26 Partial Re-occupation27 Maintenance28 Designated NSC

PSSCOC 9515 Expedition Progress Of Works16 Liquidated Damages17 Substantial Completion18 Defects19 Variations To The Works20 Valuation Of Variations21 Measurement22 Claims For Loss & Expense23 Procedure For Claims24 Constrn Equipment Temp Wks Mat & Goods25 General Responsibilities26 Indemnity Provisions27 Injury (Person & Property) & W C28 Insurance Of The Works

Page 37: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Conditions of Contract• JCC-C 94 • SIA 99

29 Nomination & Rights of Objection

30 Payment of NSC31 Payment of Contractor32 Termination by

Employer33 Termination by

Contractor34 Outbreak of war35 War Damage36 Antiquities37 Arbitration38 Optimal Cl

(Fluctuations)39 Optimal Cl (Excess)40 Appendix

PSSCOC 9529 Damage To Property Of Employer Or Govt30 Assignment & Subcontracting31 Termination By The Employer32 Progress Payments & Final Account33 Final Completion Certificate34 Settlement Of Disputes35 Recovery By The Employer36 Governing Law & Notices37 Appendix

Page 38: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Usual Conditions• Scope of Work

• Price

• Time

• Quality

• Risk

• Disputes

• Owner’s Responsibility

• Contractor’s Responsibility

Page 39: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Grouping• Performance

– Obligation– Right– Time

• Risks– Document– Site Possession– Ground Condition– Information Supplied– Insurance

• Adaptatory– Variations– Work Types– Organisations

• Adjudicatory– Dispute Resolution– Loss/Expenses– Determination

• Recognitory– Definition– Representations– Administration– Programme– Notice– Antiquities– Subcontracts/Assignment

• Quality– Temporary Works– Design– Materials– Workmanship– Defects– Statutory Obligations– Setting Out

Page 40: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Contracts Strategies

Conventional

Cost-Reim bursableContracts

Serial Contracts

Continuity Contracts

Negotiation

T w o-Stage SelectiveT endering

Variants

Separated & Co-operative

Design & Build

Develope & Construct

T urnkey

PackageDeals

Variants

Integrated

M gm t Contracting Constrn M gm t Design & M anage

M anagem ent-Orientated Build Ow n Operate& T ransfer (BOOT )

Procurem ent System s

Page 41: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Project Procurement Method - Development

• The Needs to secure:– Project Mgmt Services

– Design Mgmt Services

– Construction Mgmt Services

• Factors Affecting Change– Types of Clients

– Client’s Objectives

– Design Requirements

– Other Requirements

Page 42: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Client’s Objectives

• Time

• Cost

• Quality

• Risk Avoidance

Page 43: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Time

• How long to complete?

• Site availability.

• Justifiable delay?

• Key deliverables & dates.

• Suspension of the work.

• Extensions to finish dates.

• Notices.

Page 44: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Cost

• How much to complete?

• Justifiable increase.

• Justifiable decrease.

• Key stages & costs (milestones).

• Suspension of the work.

• Extensions to finish work.

• Notices.

Page 45: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Quality

• Supervision of the work.

• What if work is poor or sub standard.

• Who has obligation to ensure work is satisfactory?

• Changes to the work.

• Suspension of the work.

• Notices.

Page 46: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Traditional System

• Project Leader Usually The Architect

• Client - Designer - Contractor

• Suitable For Projects:– with long lead time available– where specialist designer is not required– building type is simple

• Contractor will construct & Designer will supervise on behalf of the Client

Page 47: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Advantages & Disadvantages

• Clear demarcation between designer & construct functions.

• Parties are clear about their mechanics.

• Well & truly tested.

• Risks are relatively low.

• Modified method (remeasurement)allows flexibility with partially design, thus, overlapping for design & construction.

• Brief usually sketchy.

• Design, tendering & construction virtually done sequentially.

Page 48: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Design & Build

• Client wants the design & construct by one party.• Single party contract with Client to complete the

building, guarantee workmanship, cost & time.• Client - Builder (Client retains some supervision).• Suitable for simple type of projects, though

preferred for some complex projects.• 1992 Tasks Force Report on Construction

Productivity in Singapore recommends the method.

Page 49: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

D&B - Advantages & Disadvantages• Client commits

requirements in advance.

• Incorporate builder’s experience.

• Integrate design & construct foster co-operation & close gap in communication & control.

• Client deals with one party.

• Overlap D & C improve speed.

• Client pays one fees.

• Changes later on may be costly.

• Builder carries risks, client liable for extra if design changes initiated by him.

• Method not fully tested.• May not lead to better

quality construction.• Tendency for cost overrun.

Page 50: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Management

• Set up within the traditional JCT contractual framework.

• 2 versions:– Mgmt Contracting : Client - Manager - Builder

(I.e. Builder as sub-contractor).– Construction Mgmt: Client - Builder.

Page 51: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Construction Mgmt - Advantages & Disadvantages

• Clarity of roles, risks & relations for all parties.

• Only one layer of “Mgmt” responsibility.

• Develop of D & C can run concurrently.

• Client has distinct obligations to resolve conflicts.

• Implicate the professional roles.

• Not fully tested.

• Legal & cost fees may required for “claims”.

• Not suitable for rehabilitation project.

• Client must be involved.

Page 52: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Self Assessment Questions 1 Two parties C & P agreed over the phone that if one of

them, C, the Contractor could get the finance then other, P, the Principal would instruct their QS to negotiate a fair and reasonable contract with C.

The contract sums would be based upon agreed estimates of net cost + cost of general overheads + 5% profit.

C got the necessary finance but after negotiations between the QS and C broke down P got the work done by other contractors.

C brought an action against P contending that a contract to negotiate existed and claimed Breach of Contract and loss of profit.

Did a contract exist between C & P?

Page 53: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Self Assessment Questions 2A NSC had a tender unconditionally accepted by

the Superintendent. When the Contractor ordered the work to be done by the Sub-contractor the Contractor added some new terms not previously mentioned. One of those terms said the Sub-Contractor would not be paid until the Contractor had been paid. Despite the uncertainty of when they were entitled to be paid the Sub-Contractor commenced the work.

Did a contract exist between the NSC and the Contractor and if it did what were their terms of payment?

Page 54: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Topic 3 - Learning Objectives

• Best Practice In Tender Processes & Documentation;

• Links Between Contract Strategies & Tendering;

• Value Vs Cost; and

• Risk In Relation To Standard Forms Of Contract.

Page 55: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Codes of Tendering

• Tendering Procedures - The Principal

• Tender Documents

• Tender Processes

• Cost of Tendering

• Time

• Tender Evaluation

• Express & Implied Terms of Contract

Page 56: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Tendering Evaluation Criteria• Conformity;• Innovation;• Value for Money;• Construction Period;• Quality Assurance;• Price Tendered Versus Estimate;• Management Ability;• Performance Record; and• Industrial Relations & Safety Records

Page 57: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Tender Documents• Clear definition of contractual obligations;• Full details of scope of works;• Information especially those affects the risks; • Clear identification of special conditions &

obligations;• Particulars of a person to contact for queries;• Time & lodgment details of the tender;• Version of Standard Forms of Contract

attached; and• Tender evaluation criteria to be based on.

Page 58: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Terms Of Contracts

• Express– By Signature– By Course of Dealing– Incorporate By Reference

• Implied– Terms Implied By Law– Terms Implied By Statute

Page 59: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Contra Proferentem

The doctrine that the construction least favourable to the person putting forward an instrument should be adopted against him.

Example: Form of Condition of Contract

Bills of Quantities

Specification

Page 60: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Novation/Assigned Contract

• Novation– A tripartite agreement whereby a contract

between 2 parties is rescinded & a new contract is formed based on same rights & obligations.

• Assignment– Similar, but only the benefits are assigned. E.g.

right to receive payment (both parties agree).

Page 61: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Lecture Objectives

• Key Difference Between Nominated & Domestic Sub Contractors

• Meaning, Difference & Effects On Sub-contractors

– Vicarious Performance

– Novation

– Assignment

• The “Pay when Paid” Concept; and

• Sub-contractor’s Rights in Respect of Materials Delivered to Site.

Page 62: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Sub-contracting

Defined as a delegation of part of responsibilities acquired under a contract without transferring any of the contractual accountability.

Page 63: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Sub-Contract

Is a contract between two parties where one contracts to do for the other, part of the work which that other has contracted to do for a third party.

Page 64: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Reasons For Sub-Contract System

• Better productivity & economies;

• Reduced capital outlay;

• Conservation of management resources;

• Better estimation of likely cost of work; and

• Smaller workforce to accommodate in times of recession.

Page 65: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Types Of Sub-Contractor

• Nominated Sub-Contractors;

• Domestic Sub-Contractors; and

• Designated Sub-Contractors.

Page 66: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Nominated Sub-Contractors (NSC)• Often specialist skills for particular elements of the work;

• Principal nominates & main contractor signed contract;

• A Prime Cost/Provisional Sum is included in the tender document to cover their cost;

• Contracts for NSC often called after main contracts are awarded;

• In JCC-C, builder is allowed to object but with reasons;

• Builder ensures NSC enters into a sub-contract with terms and conditions consistent with main contract; and

• Proprietor has control over NSC.

Page 67: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Factors Affecting Choice For NSC• Proprietor gets sub-contractor of choice;• Relationship between builder & NSC imposed;• Part of risk is transferred to Proprietor;• NSC is in a more powerful negotiating position at

tender time;and• NSC has greater security.

Page 68: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Payment To NSC

• Specific payment conditions are imposed on builder.

• BWIC (Builder’s Work In Connection) or Attendance is work in attendance on NSC e.g. chasing plaster for electrical conduits.

• An allowance is made for this and for profit.• The allowance can be in percentage or lump sum.

Page 69: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Domestic Sub-Contracts

• Sub-contractors employed by Proprietor direct.• Why?

– Builder does not have the required skill.

• Proprietor plays no part in the selection process;

• Builder provides details of sub-contract in Tender Documents .

Page 70: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Privity Of Contract

• Proprietor and Sub-Contractors has no privity of contract.

• i.e. sub-contractors has no rights of redress with Proprietor.

• Thus, builder ensures “Back to Back” arrangement is in place.

• This means neither builder nor sub-contractor is disadvantaged as a result of actions by either proprietor or the builder.

Page 71: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Sub-Contract Formation• Like main contract, ample time must be given to sub-

contractor to tender.

• Advantages to sub-contracting:

– Works carried out by expert & responsibility still remain with builder;

– Sub-contracting reduces builder’s overheads;

– Improved productivity; and

– Improved efficiency;

Page 72: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Sub-Contract Formation

• Disadvantages– Lack of training & opportunities for apprentices;

– Lack of onsite supervision and control;

– Builder can become a middle man only & become a bottle neck in the process;

– Contractual problems can develop from an over extended contractual chain;

– Sub-contractor may lack resources for the tasks - capital, equipment, people, business acumen and mgmt skills.

Page 73: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Vicarious Performance

• Execution of a contractual obligation by a person not contracted to do it;

• Performance of sub-contractor is “Vicarious Performance”

• Builder secure vicarious performance of another through sub-contractors depending on terms of main contract;

• Builder is vicariously liable for actions of sub-contractor; and

• Most standard forms has provision for sub-contract but not when the contract is assigned.

Page 74: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Assignment

• Transfer to another of its rights under the contract;• And retain its duties and obligations;• Example - Factoring services;• Requires consent of both parties to the contract.

Page 75: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Novation

• A third party is involved and a fresh contract is requires;

• Transfer all rights, duties and obligations to the third party through a fresh contract;

• The fresh contract is a “Contract of Novation”;• The existing contract is being substituted; and• All three parties by agree to the novation.

Page 76: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Contractual Chains• If sub-contract fails to perform, then:

– Proprietor takes action against builder under main contract and builder takes action against sub through sub-contract;

– Sub claims payment from builder and builder claims payment from Proprietor;

• Requires “back to back” terms and conditions incorporated in sub-contract;

• Basic elements to contract formation applied in sub-contract;

• A sub can withdraw up until acceptance & builder will not accept until his tender is being accepted.

Page 77: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Pay When Paid

• No expressed clause in JCC-C, but NSC should be paid within 6 days after builder is paid;

• Without PWP, problem will exist if proprietor fails to pay;

• Sub is allowed to claim from builder even the latter is not being paid.

Page 78: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Rights Over Materials

• By implied term, once materials are fixed, they become the property of the proprietor.

• By implied term, once delivered to site but not fixed, they become the property of builder even the proprietor has paid for them unless there is an expressed term to the opposite, which is usually is.

• However, for nominated supplier, once delivered to site, they become the property of proprietor unless the sub-contractor invokes a “Retention of Title” clause.

Page 79: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Self Assessment• Define, distinguish and give an example for the following

terms:– Novation

– Assignment

– Sub-Contracting

• A clause in a contract empowers the proprietor to order the work to be stopped at any time in which case the builder will receive an extension of time for the time it was stopped, but no compensation for loss or expense. Acting under this clause, the proprietor stops the work and the builder passes the instruction on to his sub who is performing the work. The sub then claimed for loss and expense as well as an extension of time.

Is the Sub entitled to payment of his L&E?

Page 80: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Self Assessment - 2

• What would be the outcome if a builder uses a sub’s price in their tender and wins the tender but the sub withdraws their offer in the interim?

• A sub delivers a quantity of roof tiles to site for inclusion in the works. The client pays the builder for the tiles. However, the builder goes broke before paying the sub for the tiles. Who owns the tiles?

Page 81: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Lecture Objectives

• Definition of Contract Variations & Examples;• Application of Standard Contract Variation Clauses;• Authorisation, Measurement & Payment of

Variations;• Strategies to Minimise Variations; and • Valuation of a Variation.

Page 82: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Reasons For A Variation Clause/Disadvantage

• Allows proprietor to order changes and additional works;

• If no provision, proprietor is restricted to agreed specification;

• Builder would not be obliged to carry out the works;

• Builder would be allowed to negotiate a new price for the whole contract each time a change is made;

• Disadvantage: - consultants may leave decision to latter stage.

Page 83: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Definition

Any agreed change which adds to or subtracts from the terms and conditions or intent of the original contract.

No variation will vitiate the contract.

“Vitiate” means to make invalid or ineffectual.

Page 84: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Definition in JCC-C

• Increases or decreases in or omissions from the Works.

• Changes in the character or quality of any material or work.

• Changes in the levels, lines, positions or dimensions of any part of the Works.

• Execution of additional work.

Page 85: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

AS 4000 Definition

“The contractor shall not vary … except as directed in writing.”

The S.O. may … of a character and extent contemplated by, and capable of being carried out..”

Same as JCC-C with an addition to allow for:– Demolish or remove material or work no longer

required by the Principal.

Page 86: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Conditions - 1

• Be “within the general scope” of the contract;• In AS 4000, limited to similar in character and

extent to the original contract & what parties reasonably have contemplated would be a variation;

• be “capable of being executed” within the terms of the contract;

• be used for “unforeseen” changes;• be adjusted to the Contract Sum;

Page 87: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Conditions - 2

• be given due consideration for EOT/OT/L&E;• be issued (i.e notice is required) or confirmed

(emergency cases) in writing;• be “specific” and ordered “prior” to the works

commencement;• be within the “power” of the Architect (includes

Instruction from COW & confirmed by Architect);• be excluded instructions (directives) to cure

defects or breach of builder or requested by builder himself (e.g. to ease method of working).

Page 88: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

JCC-C’s Valuation Of Variations

• Application both for Additions & Omissions– By Agreement (If price is agreed, no further

adjustment is allowed) [AS 4000 - applicable [comparable] rates in the contract];

– By Applying Bills of Quantities/Schedule of Rates

• under similar conditions

• pro-rated rate

– By Otherwise [AS 4000 - Reasonable rates or prices]

• Daywork/Cost Plus [Exclude Rise & Fall]

• Accepted Specialist Quotations

Page 89: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Valuing Variations

• By Derivations

• By Reconciliation Of Analysis

Page 90: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Procedures For Processing Variations

• A variation is considered to be warranted;

• The Architect issues advice of variation requesting prices;

• The builder prices the work & advises the Architect of the cost;

• If the cost is acceptable, the proprietor is advised of the variation together with the cost;

• Of proprietor agrees, the Architect instructs the builder to proceed; and

• The contract is varied accordingly, in both time & cost.

Page 91: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Commonly Occurring Variations - 1

• Under-measurement of provisional or prime cost sums;

• Unavailability of specified materials;• Lack of coordination of trades and consultants;• Change in user requirements (works & materials,

quantity and specification);• Design changes by the Architect;• Changes in site condition not shown in test

data/subsurface condition;

Page 92: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Commonly Occurring Variations - 2

• Mistakes by the contractor;• Latent defects;• Lack of research into local conditions;• Changes by authorities;• Errors in documentation/contract docu/BQ; and• Lack of proper communication between parties.

Page 93: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Steps In Minimising Variations - 1

• Take care in establishing the contract documentation;

• Read and respond to the brief;

• Examine precedence;

• Prepare check lists on all phases of the works;

• Make adequate provision for the unknown;

• Ensure that there is adequate site testing;

• Consult with authorities;

• Coordinate consultants and listen to them;

• Work as a team, obtain building advice when unsure;

Page 94: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Steps In Minimising Variations - 2

• Examine climatic and local conditions;

• Resist the temptation to be too innovative;

• Test specified materials before use;

• Construct prototypes and samples;

• Do resource planning on labour and materials;

• Build in flexibility; and

• Carry out post occupancy evaluation &disseminate resulting information.

MaLagan (1991)

Page 95: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Topics For Discussion

• Work included in the contract (expressed & implied terms);

• Where actual quantities differ from those in the bills;• Where work is not mentioned in the bills;• Mistakes of contractor in the bills;• Necessary work in contracts at schedule of rates;• Promise to pay when contractor already bound;• Instructions to assist builders in difficulty;• Instructions as to Method of Working.

Page 96: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Self Assessment Questions - 1

• Indicate which of the following variations would be admissible under a standard form of contract and provide your reasons:– A change in the size of window.– The increase in the floor area of a proposed

warehouse from 200 m2 to 2000 m2.

Page 97: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Self Assessment Questions - 2• Are the following examples a variation? Give your

reasons for your decision.– 8 houses are to be built & a variations amending this to

12 is issued.– 1008 houses are to be built and then a variation

amending this to 1012 is issued.– A variation order is issued amending the contract from

the construction of a house to the construction of a swimming pool.

• List ways in which you think variations could be minimised.

Page 98: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Victoria Construction Management Pte Ltd has recently been awarded for the following proposed project. Thedeveloper is Alliance International (A) Ltd. You will be appointed by Victoria as a Construction Manager forthe project.

Victoria Construction Management Pte Ltd has recently been awarded for the following proposed project. Thedeveloper is Alliance International (A) Ltd. You will be appointed by Victoria as a Construction Manager forthe project.

Victoria Construction Management Pte Ltd has recently been awarded for the following proposed project. The developer is Alliance International (A) Ltd. You will be appointed by Victoria as a Construction Manager for the project.

Project DescriptionFive thirty-storey prestigious condominium blocks will be constructed on a prime land in central Perth. Every apartment unit will be able to overlook the Swan River. The whole building will be fully air-conditioned and protected by closed-circuit television 24 hours throughout. The lift will stop at every floor and is fully automatic.

ASSIGNMENT 1

Page 99: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

The estate will have three-store basement carparks, an Olympic size swimming pool, three tennis courts, one squash court, a three-storey clubhouse and an unique landscape fronting the building. On completion, the whole estate will be run and managed by a management corporation.

The total built in floor area of the estate will be 90,000 m2 and it is estimated to cost about $200 million.

Your task is to source the respective sub-contractors for the projects.

Page 100: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

AssignmentAssuming that Victoria Construction Management Pte Ltd’s primary business is construction management. Before you are deployed for the task, you are to evaluate and propose suitable types of sub-contracts for the project. Additionally, you are to study and report on the rights, duties and remedies of the sub-contractors if JCC-C Standard Form of Contract For Building Works would to be used. Your Senior Manager would want you to put your recommendation in a form of a report so that he could present it to the Project Management Committee..In your report, you are to consider the common problems in employing sub-contractors and recommend precautionary measures in minimising the problems for the project.

Page 101: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Curtin University of TechnologyAccredited Professional Development Programme

Bachelor of Applied Science(Construction Management & Economic)

CONTRACT ADMINISTRATION 341

Assignment 1TOPIC:

Submitted By: (Registration No. )Name of Lecturer: Ms Kee Bee KhengDate of Submission

Page 102: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Topic 6 - PaymentsLearning Objective

• Payment procedures for standard forms;

• Assessment of interim payments;

• Methods of administering prelims;

• Obligations with regards to unfixed materials;

• Contract sum adjustments for V.O. & P.S.;

• Final adjusted contract sums; and

• A Financial control system.

Page 103: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Payments - 1

• Purpose;

• Types of contracts;

• Method of payment;

• Payment procedure/Timing of claims;

• Failure to pay;

• Assessing Payment - The process & inclusions;

Page 104: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Payments - 2

• Preliminaries Breakdown;

• Cash flows;

• Unfixed Materials;

• Retention;

• Contract sum adjustment/final account;

• Financial control; and

• Right to payment in non-completion.

Page 105: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Purpose

• What is payment?– Payment is consideration for the works

undertaken by the builder;

• What is the purpose?– To relieve builders from heavy financial outlay.

Page 106: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Types of Contract

• Lump Sum with provisional sum for unknown items;

• Measurement & value contracts (with approximate quantities or schedule of rates)

Page 107: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Methods of Payments

• Payment upon completion of entire contract;

• Payments by installments or at predetermined stages:– Period e.g. monthly payments;– Interim/progress payments:

• payment on account

• payment by percentage completion

• milestone e.g. stage payments

Page 108: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Payment Procedures

• When interim payment due (see flow chart);

• When final payment due (substantial completion); and

• Release of retention fund (end of DLP).

Page 109: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Progress Payment Procedure

• The builder completes a quantity of work;

• The builder submits a progress claim to the Architect according to JCC-C’s conditions;

• The PQS examines the claim & assesses the work completed compared to the work claimed;

• The certificate is forwarded to the Architect for certification;

• A progress certificate is issued in accordance with the contract documents (Architect may amend if he thinks fit);

• The certificate is presented to the employer for payment; and

• The employer pays the builder in accordance with the contract document.

Page 110: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Amendment to Progress Certificates

• Final Certificate is the only conclusive certificate;

• Progress Certificate may be subject to amendment in a later certificate.

Page 111: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Assessing Payments

• Often, paid based on account as works proceeds;

• JCC-C states “Once each month and on a date as stated in the Appendix the builder shall submit to the Architect a progress claim”;

• If builder fails to claim, the Architect may issue a certificate using PQS’s assessment & process it the same way.

Page 112: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Timing of Progress Claims

• JCC-C states 10 days from the date of claim submitted by the builder for the Architect to certify payments; the employer has further 5 days to pay the amount certified by the Architect;

• If period differs, it will be stated in the Appendix of JCC-C;

• Claim prepared by builder & Architect certifies correct & employer pays

Page 113: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Failure to Pay

• Interest accrue at the rate stated in the Appendix of JCC-C.

Page 114: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

The Process & Inclusions (JCC-C) - 1

• Joint site measurement between builder & PQS;

• Extent of works carried out since beginning of the contract and previous measurement deducted;

• Valuation of the following works carried out:– Preliminaries;– Builder’s work;– Variations;

Page 115: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

The Process & Inclusions (JCC-C) - 2

• Valuation of the following works carried out:– Unfixed materials (JCC-C - 80% or as in Appendix);– Rise & Fall;– Retention amount;– Amount previously certified;– Total amount previously paid;– Amount for NSC including variations; and– Evidence of payments to NSC previously certified

and payment to works.

Page 116: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Preliminaries Breakdown - 1

• By apportionment:– Over contract period;– Over contract sum after deducting the prelim & P.S.;– Percentage of work carried out;– Breakdown under 4 headings:

• cost related;

• time related;

• single payment (spot items); or

• combination of two or more.

Page 117: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Preliminaries Breakdown - 2

• Cost related depends on the contract sum expended for their value;

• Time related items depend on the contract duration expired for their value; and

• Single payment items have no relationship to either duration or value of the works and are selected at a particular point in the contract.

• Example: scaffolding - erection cost, dismantling cost, weekly hire charge in between.

Page 118: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Cash Flows

• ‘S’ Curve

Page 119: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Self Assessment Question

• See the attached progress claim and calculate the amount due “this claim”.

Page 120: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Topic 7 - Insurances (Learning Objectives)

• Definition of 3 types of insurance;

• The Risks requiring cover by insurance;

• Characteristics that differentiate annual & specific insurance;

• Implications of early occupation on insurance liabilities; and

• Workers compensation & professional indemnity insurance.

Page 121: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Course Content

• Introduction;• Insurance - General Principles;• Types of Insurance;• Risks to be insured;• Period of insurance (Annual/Specific);• Early Occupation;• Professional Indemnity; • Provision for Insurance in JCC-C;• and • Self Assessment Questions.

Page 122: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

IntroductionContracts & Risks

• Controllable & Uncontrollable Risks;

• Insurable & Uninsurable Risks;

• Property & Liability;

• Party in control & party not in control of risk; and

• Interference within control of one party & beyond control of both parties.

Page 123: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

General Principles

• 2 classification of insurance:– Liability Insurance Policy; and– Loss Insurance Policy.

• The Insured Persons & the Insurer;• The Policy (A Contract):

– Endorsement– Extension– Exclusions– Excess

• The Premium;• The Claim Procedure; and• Fraudulent claims - insurer not liable.

Page 124: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Types of Insurance

• Comprehensive (contractor’s all risk);

• Public Liability (risk),

• Third Party (common law); and

• Workers’ Compensation (Statutory Law - Workers’ Compensation & Rehabilitation Act).

Page 125: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Risks To Be Included

• Increases in labour & material costs;

• Temporary works & plant;

• Demolition & clearance of damaged areas;

• Removal of debris; and

• Additional consultancy fees for reconstruction works.

Page 126: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Insurance Conditions - 1

• To comply with obligations of the policy;• To inform the insurer of any changes to the risk

insured such as the final cost, variations and increased costs (R&F) if applicable;

• To take reasonable precaution to avoid loss or damage (an implied condition). Builder needs to carefully consider its approach to the works; selecting plant, training of the workforce, etc.

Page 127: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Insurance Conditions - 2

• Insurer is not liable if the claim were found to be fraudulent;

• To ensure claim procedure is followed. This will help to preserve insured person right to claim under the policy or insurer’s rights against other parties responsible for the loss or damage; and

• To pay the premium within stipulated time.

Page 128: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Periods of Insurance - 1

• Annual Basis (automatically covered all contracts, except exclusions).

– Advantages• Tailored to suit annual turnover. Builder may include in

its tender the exact required value;• Small jobs are automatically covered without prior

arrangement.– Disadvantages

• Lock with one insurer, thus less competitive premium.• Often, include exclusions such as demolition, tunnelling,

wet risks (e.g. on, below, over water or adjacent to water). Need prior notice before commencement if extension being given.

Page 129: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Periods of Insurance - 2

• Specific– Advantages

• Premiums attached to specific risks on particular jobs. Premium may be cheaper.

• Insurance companies in competition may quote unusual jobs.

• Get a feel for the market-competition.

– Disadvantage• Time-lag;

• Need vetting for every policy received.

Page 130: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Early Occupation

• Most standard forms allowed early occupation, except certain obligations are met.

• Additional cover may be required due to additional risks, because more people occupying the place.

• Prior notice to insurer may be needed to compute additional premium or to determine party responsible for payment.

Page 131: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Professional Indemnity - 1

• It protects the professional from financial consequences of any claim brought against him;

• It covers liability in both contract & tort (in negligence);• It requires disclosure on types of activities to be carried

out by the insured;• Any variation, the insured should be advised to ensure

adequate cover exists.• Normally, it includes contingent professional liability

coverage where design work is sub-contracted to outsiders.

Page 132: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Professional Indemnity - 2

• The Nature of the Liability– Opinion or design of a person who has

specialist knowledge & training;– Until 1963, the person owes the duty of care

only to the party in the contract;– Now, professional liability extends to third

party, not a party in the contract, if his opinion or design could be reasonably foreseen and is relied upon. E.g. design of a bridge.

Page 133: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Provision in JCC-C - 1

• Section P8 - Insurance Effected by Proprietor; and

• Section B8 - Insurance Effected by Builder.

• The Clauses:– Liability for Damage to Property– Liability for Injury to Persons– Insurance of the Works– Public Liability Insurance

Page 134: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Provision in JCC-C - 2

– Workers’ Compensation & Employers’ Liability Insurance;

– Cross Liability;

– Insurances Notices;

– Exclusions, Conditions and Excesses;

– Periods of Insurance;

– Occupation;

– Evidence of Insurances;

– Procedure as to Claims, and

– Settlement of Claims.

Page 135: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Self Assessment Questions - 1

• List some risks that you consider insurable and those that you consider would be non-insurable in a building contract.

• What special considerations might apply in the case of a contract for?– Alterations,

– Additions to an existing building.

• Why is there a provision in the appendix of the Contract for “Excesses”?

Page 136: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Self Assessment Questions - 2

• If the Principal is to insure the works, why is it necessary for all the information to be included in the Contract?

• List some of the items and risks for which a builder should consider insurance.

• List some of the insurance policies that, as a builder, you would be required to take up.

Page 137: Construction Mgmt & Economics CONTRACT ADMINISTRATION 341 Kee Bee Kheng (Ms)

Self Assessment Questions - 3

• As a consultant, who covers the risks for the work that you undertake?

• What is the difference between Third Party insurance & Public Liability insurance?