cmp cr scr121305-01 - implement xml interface for ima (new app to app) - timeline

2
1 Draft Interface Technical Specifications Submitted to CLECs Walk- through Begins Walk-through Ends Qwest Response to CLEC Comments Final Interface Technical Specifications Issued CLEC Testing 73 Calendar Day Timeline Day 73 Day 58 Day 68 Day 45 Day 30 10 Calendar Days Qwest Reply and Final Notification 18 Calendar Days CLEC Comments 5 Days 10 Days 10 Days 15 Days 30 Days Walk-through CLEC Testing Begins CLEC Comments Due 3 Days Day 55 8/4/06 8/9/06 8/18/06 8/22/06 9/1/06 9/16/06 10/16/06 Day 0 User Cutover Complete CMP CR SCR121305-01 - Implement XML Interface for IMA (New App to App) - Timeline

Upload: ramiro

Post on 24-Jan-2016

19 views

Category:

Documents


0 download

DESCRIPTION

CMP CR SCR121305-01 - Implement XML Interface for IMA (New App to App) - Timeline. Draft Interface Technical Specifications Submitted to CLECs. Final Interface Technical Specifications Issued. Walk-through Ends. Walk-through Begins. CLEC Testing Begins. CLEC Comments Due. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: CMP CR SCR121305-01 - Implement XML Interface for IMA (New App to App) - Timeline

1

Draft Interface Technical Specifications Submitted to CLECs

Walk-through Begins

Walk-through Ends

Qwest Response to CLEC

Comments

Final Interface Technical Specifications Issued

CLEC Testing

73 Calendar Day Timeline

Day 73 Day 58Day 68 Day 45 Day 30

10 Calendar Days

Qwest Reply and Final Notification

18 Calendar Days

CLEC Comments

5 Days 10 Days 10 Days 15 Days 30 Days

Walk-through

CLEC Testing Begins

CLEC Comments Due

3 Days

Day 55

8/4/06 8/9/06 8/18/06 8/22/06 9/1/06 9/16/06 10/16/06

Day 0

UserCutoverComplete

CMP CR SCR121305-01 - Implement XML Interface for IMA (New App to App) - Timeline

Page 2: CMP CR SCR121305-01 - Implement XML Interface for IMA (New App to App) - Timeline

2

CLEC Comments Due

Release Production Date

New App to App Timeline

Day 270 (Approximately) Day 30 Day 0

30 Days

Day 120

Qwest Issues InitialRelease Announcement and Preliminary Implementation Plan

CLEC Testing Begins

Qwest Response to CLEC Comments

14 Days 7 Days

Qwest Response to CLEC Comments

Qwest Issues Initial Interface Technical Specifications

Day 110

CLEC Walk Through Begins

Day 106

CLEC Walk Through Ends

CLEC Comments Due

Day 104

Qwest Response to CLEC Comments

Qwest Issues Final Interface Technical Specifications

Day 100

7 Days

Qwest Conducts Preliminary Implementation Plan Review Meeting

Day 242 Day 249

8/4/06 8/9/06 8/18/06 8/22/06 9/1/06 9/16/06 10/16/06

Day 73 Day 58Day 68 Day 45 Day 30 Day 55 Day 0Day 79Day 86Day 93Day 100

7/28/067/21/067/14/067/7/06

CMP CR SCR121305-01 - Implement XML Interface for IMA (New App to App) - Timeline