cmp cr scr121305-01 - implement xml interface for ima (new app to app) - timeline
DESCRIPTION
CMP CR SCR121305-01 - Implement XML Interface for IMA (New App to App) - Timeline. Draft Interface Technical Specifications Submitted to CLECs. Final Interface Technical Specifications Issued. Walk-through Ends. Walk-through Begins. CLEC Testing Begins. CLEC Comments Due. - PowerPoint PPT PresentationTRANSCRIPT
1
Draft Interface Technical Specifications Submitted to CLECs
Walk-through Begins
Walk-through Ends
Qwest Response to CLEC
Comments
Final Interface Technical Specifications Issued
CLEC Testing
73 Calendar Day Timeline
Day 73 Day 58Day 68 Day 45 Day 30
10 Calendar Days
Qwest Reply and Final Notification
18 Calendar Days
CLEC Comments
5 Days 10 Days 10 Days 15 Days 30 Days
Walk-through
CLEC Testing Begins
CLEC Comments Due
3 Days
Day 55
8/4/06 8/9/06 8/18/06 8/22/06 9/1/06 9/16/06 10/16/06
Day 0
UserCutoverComplete
CMP CR SCR121305-01 - Implement XML Interface for IMA (New App to App) - Timeline
2
CLEC Comments Due
Release Production Date
New App to App Timeline
Day 270 (Approximately) Day 30 Day 0
30 Days
Day 120
Qwest Issues InitialRelease Announcement and Preliminary Implementation Plan
CLEC Testing Begins
Qwest Response to CLEC Comments
14 Days 7 Days
Qwest Response to CLEC Comments
Qwest Issues Initial Interface Technical Specifications
Day 110
CLEC Walk Through Begins
Day 106
CLEC Walk Through Ends
CLEC Comments Due
Day 104
Qwest Response to CLEC Comments
Qwest Issues Final Interface Technical Specifications
Day 100
7 Days
Qwest Conducts Preliminary Implementation Plan Review Meeting
Day 242 Day 249
8/4/06 8/9/06 8/18/06 8/22/06 9/1/06 9/16/06 10/16/06
Day 73 Day 58Day 68 Day 45 Day 30 Day 55 Day 0Day 79Day 86Day 93Day 100
7/28/067/21/067/14/067/7/06
CMP CR SCR121305-01 - Implement XML Interface for IMA (New App to App) - Timeline