city council 9-18-12 avenue p

17
City Council September 18, 2012

Upload: city-of-san-angelo-texas

Post on 27-May-2015

197 views

Category:

Sports


0 download

TRANSCRIPT

Page 1: City Council 9-18-12 Avenue P

City CouncilSeptember 18, 2012

Page 2: City Council 9-18-12 Avenue P

Avenue P Background• True neighborhood with many residents having lived

there for generations• Most houses built in 1940’s and 1950’s• Long history of flooding

• reports dating back decades• exacerbated by continued development with increased

impervious cover

Page 3: City Council 9-18-12 Avenue P

Avenue P Background• 2000 Master Drainage Plan

• Developed by Freese & Nichols, Inc.• Analyzed 57 drainage problem areas• Top 25 problem areas ranked/prioritized according to

• amount and velocity of flow• capacity of existing facilities• traffic issues (disruption/emergency response)• history of flooded structures• cost-benefit analysis

• Avenue P Drainage Problem Area Ranked #2

Page 4: City Council 9-18-12 Avenue P

Avenue P Background• Ave P neighborhood meeting – September 19, 2011

• Attendees• Then-City Manager Harold Dominguez• City Councilman Johnny Silvas• City Engineer Clinton Bailey• Approximately 25 area residents

• Area residents discussed history of neighborhood drainage issues

• City Officials discussed remediation options and funding opportunities

Page 5: City Council 9-18-12 Avenue P

Avenue P Background• City Council meeting – November 1, 2011

• Presentation on Capital Planning Projects• Top 5 drainage problems presented

• Council approved funding ($1.7 million) for Ave P• $700,000 from fiscal year 2011-2012• $1,000,000 from fiscal year 2012-2013

Page 6: City Council 9-18-12 Avenue P

Avenue P Flooding

Page 7: City Council 9-18-12 Avenue P

Avenue P Flooding

Page 8: City Council 9-18-12 Avenue P

Avenue P Flooding

Page 9: City Council 9-18-12 Avenue P

Avenue P Flooding

Page 10: City Council 9-18-12 Avenue P

Avenue P Flooding

Page 11: City Council 9-18-12 Avenue P

Avenue P Flooding

Page 12: City Council 9-18-12 Avenue P

Avenue P Flooding

Page 13: City Council 9-18-12 Avenue P

Drainage Areas

ASU

Cemeteries

W Avenue N

John

son

St

Knicker

bocker

Rd

S Br

yant

Blvd

S Ch

adbo

urne

Page 14: City Council 9-18-12 Avenue P

Avenue P Drainage Improvement Project• Take drainage underground from S. Bryant Blvd to

the east side of S. Chadbourne St.

Begin

End

Avenue P

S B

ryan

t Blv

d

S C

hadb

ourn

e

Page 15: City Council 9-18-12 Avenue P

Avenue P Drainage Improvement Project• 2,300 linear feet of storm drain under Ave P• 300 linear feet of improved open channel• Curb inlets along Avenue P to pick up street drainage• Storm drain crosses under S Chadbourne St.• Discharges into an open channel on the east side of

S Chadbourne St.• Flows directly into the Red Arroyo

Page 16: City Council 9-18-12 Avenue P

S Bryant Boulevard Culvert

Page 17: City Council 9-18-12 Avenue P

Project Timeline2012

• Mid-October – Complete design• November – Advertise for bid• Early December – Open and award bid• Mid-late December – Begin construction

2013• Late summer – Project completion