CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015 "R.R. SEISMUNDO CONSTRUCTION & SUPPLY" 10961 Construction of Flood Control, Mainit Section Protecting Nabunturan – Mainit Park Road 8/8/2014 XI 11.147 150 C 0.343 0.200 0.300 - - - 84.30 84.30% Satisfactory "R.R. SEISMUNDO CONSTRUCTION & SUPPLY" 10961 Const./Widening/Upgrading/Rehab. of Del Pilar (san Juan) New Cortez – San Jose Carcor Panas Road. 8/9/2014 XI 45.784 205 C 0.344 0.200 0.300 - - - 84.40 83.32% Satisfactory "R.R. Seismundo Construction & Supply" 10961 Widening of Montevista-Compostela-New Bataan- Maragusan-Mati Bdry. Rd., Pob. Sect. 08/14/13 XI 22.917 180 C 0.353 0.200 0.300 - - - 85.30 85.30% Satisfactory "R.R. Seismundo Construction & Supply" 10961 Const./Widening/Upgrading/Rehab. of Del Pilar (San Juan)- New Cortez-San Jose Carcor Panas Rd. 08/12/13 XI 45.784 205 O 0.245 0.300 0.150 0.030 0.050 0.033 80.80 - "R.R. Seismundo Construction & Supply" 10961 Widening of Surigao-Davao Coastal Rd., Km.1822+(-423)- Km.1822+821, Apokon Sect. 03/18/13 XI 17.793 125 O 0.355 0.240 0.150 0.030 0.045 0.050 87.00 - "R.R. Seismundo Construction & Supply" 10961 Const./Widening/Upgrading/Rehab. of Del Pilar (San Juan)- New Cortez-San Jose Carcor Panas Rd. 03/18/13 XI 45.784 179 O 0.338 0.231 0.150 0.030 0.045 0.050 84.40 - "R.R. Seismundo Construction & Supply" / Davao Concrete Products Joint Venture JV-12-116 Const. of Flood Control Structure (Sheet Piles & Grouted Riprap) Agusan River, Brgy. Inambatan 11/27/12 XI 27.838 240 O 0.333 0.240 0.150 0.030 0.040 0.050 84.30 - 121 CONSTRUCTION CORPORATION (Formerly: 121 Construction) 21686 Improvement/Concreting with Drainage System along Ballesteros Street 11/29/2014 NCR 6.684 120 O 0.355 0.240 0.150 0.030 0.035 0.033 84.30% 84.30% Satisfactory 2H2L Construction 16293 Prev. Maint. (Asphalt Overlay) of Manila East Rd., K0032+050-K0032+737 08/15/13 IVA 3.926 121 C 0.461 0.139 0.300 - - - 90.00 90.00% Very Satisfactory 2M Construction & Enterprises 33331 Slope Protection (Grouted Riprap) along Isabela-Maluso Rd., Matarling Sect. at K15+190-K15+249 03/13/13 IX 4.842 75 O 0.328 0.240 0.150 0.030 0.040 0.050 83.80 - 2-R CONSTRUCTION & SUPPLY 15304 Preventive Maintenance along Pangasinan-Zambales Road K0365+690 to K0367+000 10/28/2014 I 13.528 16 C 0.405 0.200 0.300 - - - 90.50% 90.50% Very Satisfactory 2-R Construction & Supply 15304 Prev. Maint. of Lingayen Capitol Loop Rd. (right), K0364+(- 810)-K0364+240 03/16/13 I 10.871 60 C 0.477 0.133 0.300 - - - 91.00 91.00% Very Satisfactory 3C'SL CONSTRUCTION AND SUPPLY 36393 Rehabilitation of Local Road, Brgy. Poblacion 10/20/2014 XIII 2.447 45 C 0.394 0.200 0.300 - - - 89.40% 89.40% Very Satisfactory 3Diamonds Construciton Corporation 35457 Road Widening along Daan Maharlika 8/13/2014 V 2.997 45 C 0.419 0.133 0.300 85.20 85.20% Satisfactory 3K ROCK ENGINEERING 27908 Local Infrastructure Program - Construction of Multi- Purpose Building, West Quirino Hill 11/17/2014 CAR 4.300 110 C 0.469 0.133 0.300 - - - 90.20% 90.20% Very Satisfactory 3K ROCK ENGINEERING 27908 Construction and Maintenance of Bridges along National Roads, Construction of Bridges-New, Box Culvert along Kennon Road 11/17/2014 CAR 8.289 127 C 0.463 0.133 0.300 - - - 89.60% 89.60% Very Satisfactory 3K ROCK ENGINEERING/RVC CONSTRUCTION (J.V.) 27908 Road Upgrading (Gravel to Concrete) of Asin -Nanganban - San Pascual Road K0270+594 - K0272+220 ; K0275+5311 - K0275+7178 8/16/2014 CAR 91.358 237 OG 0.379 0.240 0.150 0.024 0.060 0.050 90.30 - 3RB CONSTRUCTION & SUPPLY 19541 Prieto Diaz Port Development Project 08/19/15 DOTC 8.512 124 O 0.367 0.300 0.150 0.030 0.054 0.050 95.10 - 3RB CONSTRUCTION & SUPPLY 19541 Prieto Diaz Port Development Project 09/22/15 DOTC 8.512 124 C 0.480 0.200 0.300 - - - 98.00 96.30% Outstanding 3RB CONSTRUCTION & SUPPLY 19541 Construction/Rehabilitation of Flood Control in Laguna 2nd DEO/1st LD along Manila South Road 11/28/2014 IV 13.726 210 C 0.325 0.200 0.300 - - - 82.50% 82.50% Satisfactory 4 B CONSTRUCTION 23445 Asphalt Overlay with Correction at Liberty Avenue ( Chainage 0+000 - Chainage 0+840) 11/27/2014 NCR 8.361 120 C 0.483 0.133 0.300 - - - 91.60% 91.60% Very Satisfactory 401 DEVELOPMENT AND CONSTRUCTION CORP. 26375 Pavers Block Plaza Libertad 02/26/14 TIEZA 4.909 60 C 0.437 0.200 0.300 - - - 93.70 93.80% Very Satisfactory 4-B CONSTRUCTION CORP. 23445 Repair Maintenance of Road within Morong Special Economic Zone (MSEZ) 11/26/2014 III 8.045 90 C 0.470 0.133 0.300 - - - 90.30% 90.30% Very Satisfactory 4B CONSTRUCTION CORPORATION 23445 Preventive Maintenance along Balanga-Poblacion Road 8/13/2014 III 9.067 50 C 0.474 0.133 0.300 90.70 90.70% Very Satisfactory 4B Construction Corporation 2014 heavy maintenance works along SCTEX lot 2 - Bridge revetment, slope and drainage repair works 10/31/14 BCDA 12.430 90 O 0.298 0.288 0.135 0.000 0.035 0.050 80.53 - 4B Construction Corporation 2014 heavy maintenance works along SCTEX lot 2 - Bridge revetment, slope and drainage repair works 02/04/15 BCDA 12.430 90 C 0.369 0.200 0.300 - - - 86.91 83.08% Satisfactory 4B Construction Corporation Gumain Bridges Pier 5 & 6 Protection Works 11/20/14 BCDA 18.951 120 O 0.400 0.271 0.105 0.000 0.032 0.033 84.10 - ESH RDR STATUS CPES VISIT RATING WMS MTL TIME FAC FINAL RATING/ QUALITATIVE DESCRIPTION AMOUNT (Php, M) DUR (C.D.) CONTRACT *IMPL. AGENCY NAME OF CONSTRUCTOR LICENSE NO. PROJECT DATE OF EVALUATION *1st/Final * For DPWH, only the region and PMO office are listed 21st CPES Release Page1

Upload: others

Post on 18-Mar-2020

25 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

"R.R. SEISMUNDO CONSTRUCTION & SUPPLY" 10961 Construction of Flood Control, Mainit Section Protecting

Nabunturan – Mainit Park Road 8/8/2014 XI 11.147 150 C 0.343 0.200 0.300 - - - 84.30 84.30% Satisfactory

"R.R. SEISMUNDO CONSTRUCTION & SUPPLY" 10961 Const./Widening/Upgrading/Rehab. of Del Pilar (san Juan)

– New Cortez – San Jose Carcor Panas Road. 8/9/2014 XI 45.784 205 C 0.344 0.200 0.300 - - - 84.40 83.32% Satisfactory

"R.R. Seismundo Construction & Supply" 10961 Widening of Montevista-Compostela-New Bataan-

Maragusan-Mati Bdry. Rd., Pob. Sect. 08/14/13 XI 22.917 180 C 0.353 0.200 0.300 - - - 85.30 85.30% Satisfactory

"R.R. Seismundo Construction & Supply" 10961 Const./Widening/Upgrading/Rehab. of Del Pilar (San Juan)-

New Cortez-San Jose Carcor Panas Rd. 08/12/13 XI 45.784 205 O 0.245 0.300 0.150 0.030 0.050 0.033 80.80 -

"R.R. Seismundo Construction & Supply" 10961 Widening of Surigao-Davao Coastal Rd., Km.1822+(-423)-

Km.1822+821, Apokon Sect. 03/18/13 XI 17.793 125 O 0.355 0.240 0.150 0.030 0.045 0.050 87.00 -

"R.R. Seismundo Construction & Supply" 10961 Const./Widening/Upgrading/Rehab. of Del Pilar (San Juan)-

New Cortez-San Jose Carcor Panas Rd. 03/18/13 XI 45.784 179 O 0.338 0.231 0.150 0.030 0.045 0.050 84.40 -

"R.R. Seismundo Construction & Supply" / Davao Concrete Products

Joint VentureJV-12-116 Const. of Flood Control Structure (Sheet Piles & Grouted

Riprap) Agusan River, Brgy. Inambatan 11/27/12 XI 27.838 240 O 0.333 0.240 0.150 0.030 0.040 0.050 84.30 -

121 CONSTRUCTION CORPORATION (Formerly: 121

Construction)21686 Improvement/Concreting with Drainage System along

Ballesteros Street 11/29/2014 NCR 6.684 120 O 0.355 0.240 0.150 0.030 0.035 0.033 84.30% 84.30% Satisfactory

2H2L Construction 16293 Prev. Maint. (Asphalt Overlay) of Manila East Rd., K0032+050-K0032+737 08/15/13 IVA 3.926 121 C 0.461 0.139 0.300 - - - 90.00 90.00%

Very Satisfactory

2M Construction & Enterprises 33331 Slope Protection (Grouted Riprap) along Isabela-Maluso Rd., Matarling Sect. at K15+190-K15+249 03/13/13 IX 4.842 75 O 0.328 0.240 0.150 0.030 0.040 0.050 83.80 -

2-R CONSTRUCTION & SUPPLY 15304 Preventive Maintenance along Pangasinan-Zambales Road K0365+690 to K0367+000 10/28/2014 I 13.528 16 C 0.405 0.200 0.300 - - - 90.50% 90.50%

Very Satisfactory

2-R Construction & Supply 15304 Prev. Maint. of Lingayen Capitol Loop Rd. (right), K0364+(-810)-K0364+240 03/16/13 I 10.871 60 C 0.477 0.133 0.300 - - - 91.00 91.00%

Very Satisfactory3C'SL CONSTRUCTION AND

SUPPLY 36393 Rehabilitation of Local Road, Brgy. Poblacion 10/20/2014 XIII 2.447 45 C 0.394 0.200 0.300 - - - 89.40% 89.40% Very Satisfactory

3Diamonds Construciton Corporation 35457 Road Widening along Daan Maharlika 8/13/2014 V 2.997 45 C 0.419 0.133 0.300 85.20 85.20%

Satisfactory

3K ROCK ENGINEERING 27908 Local Infrastructure Program - Construction of Multi-Purpose Building, West Quirino Hill 11/17/2014 CAR 4.300 110 C 0.469 0.133 0.300 - - - 90.20% 90.20%

Very Satisfactory

3K ROCK ENGINEERING 27908Construction and Maintenance of Bridges along National Roads, Construction of Bridges-New, Box Culvert along

Kennon Road11/17/2014 CAR 8.289 127 C 0.463 0.133 0.300 - - - 89.60% 89.60%

Very Satisfactory

3K ROCK ENGINEERING/RVC CONSTRUCTION (J.V.) 27908

Road Upgrading (Gravel to Concrete) of Asin -Nanganban - San Pascual Road K0270+594 - K0272+220 ; K0275+5311 -

K0275+71788/16/2014 CAR 91.358 237 OG 0.379 0.240 0.150 0.024 0.060 0.050 90.30 -

3RB CONSTRUCTION & SUPPLY 19541 Prieto Diaz Port Development Project 08/19/15 DOTC 8.512 124 O 0.367 0.300 0.150 0.030 0.054 0.050 95.10 -

3RB CONSTRUCTION & SUPPLY 19541 Prieto Diaz Port Development Project 09/22/15 DOTC 8.512 124 C 0.480 0.200 0.300 - - - 98.00 96.30% Outstanding

3RB CONSTRUCTION & SUPPLY 19541 Construction/Rehabilitation of Flood Control in Laguna 2nd DEO/1st LD along Manila South Road 11/28/2014 IV 13.726 210 C 0.325 0.200 0.300 - - - 82.50% 82.50%

Satisfactory

4 B CONSTRUCTION 23445 Asphalt Overlay with Correction at Liberty Avenue ( Chainage 0+000 - Chainage 0+840) 11/27/2014 NCR 8.361 120 C 0.483 0.133 0.300 - - - 91.60% 91.60%

Very Satisfactory401 DEVELOPMENT AND CONSTRUCTION CORP. 26375 Pavers Block Plaza Libertad 02/26/14 TIEZA 4.909 60 C 0.437 0.200 0.300 - - - 93.70 93.80%

Very Satisfactory

4-B CONSTRUCTION CORP. 23445 Repair Maintenance of Road within Morong Special Economic Zone (MSEZ) 11/26/2014 III 8.045 90 C 0.470 0.133 0.300 - - - 90.30% 90.30%

Very Satisfactory4B CONSTRUCTION

CORPORATION 23445 Preventive Maintenance along Balanga-Poblacion Road 8/13/2014 III 9.067 50 C 0.474 0.133 0.300 90.70 90.70% Very Satisfactory

4B Construction Corporation 2014 heavy maintenance works along SCTEX lot 2 - Bridge revetment, slope and drainage repair works 10/31/14 BCDA 12.430 90 O 0.298 0.288 0.135 0.000 0.035 0.050 80.53 -

4B Construction Corporation 2014 heavy maintenance works along SCTEX lot 2 - Bridge revetment, slope and drainage repair works 02/04/15 BCDA 12.430 90 C 0.369 0.200 0.300 - - - 86.91 83.08%

Satisfactory

4B Construction Corporation Gumain Bridges Pier 5 & 6 Protection Works 11/20/14 BCDA 18.951 120 O 0.400 0.271 0.105 0.000 0.032 0.033 84.10 -

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page1

Page 2: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

4B Construction Corporation Gumain Bridges Pier 5 & 6 Protection Works 02/05/15 BCDA 18.951 120 O 0.377 0.293 0.000 0.030 0.041 0.033 77.44 -

4B Construction Corporation Gumain Bridges Pier 5 & 6 Protection Works 03/20/15 BCDA 18.951 120 C 0.420 0.200 0.300 - - - 91.99 85.26% Satisfactory

511 BUILDERS 34324 Repair/Rehab. Of Multi-Purpose Bldg. @ Brgy. Hall 11/20/2014 III 1.870 105 C 0.478 0.133 0.300 - - - 91.10% 91.10% Very Satisfactory

626 CONSTRUCTION AND TRADING 34990 Improvement of Balungao Hot and Cold Spring Resort 5/27/15 TIEZA 11.800 180 O 0.397 0.299 0 0.030 0.045 0.017 78.74

626 CONSTRUCTION AND TRADING INC. 34990 Rehabilitation of Local Road, Maya-Maya St., Brgy. Longos 11/21/2014 NCR 5.865 121 C 0.401 0.133 0.300 - - - 83.40% 83.40%

Satisfactory

6RM CONSTRUCTION AND DEVELOPMENT CORP. (Formerly:

R.R. Maurico Construction)174

Rehab./Reconst./Replacement/Retrofitting of Existing Permanent Bridge: Sagumayon Bridge along DM Jct.-

Legaspi-Sto. Domingo-Tabaco-Camarines Sur Bdry. Road11/15/2014 V 19.697 210 C 0.457 0.133 0.300 - - - 89.00% 89.00%

Satisfactory

722 CONSTRUCITON, INC.(Formerly: 722 Construction) 21923 Repair/Rehabilitation/Improvement along Baliuag-Candaba

Road K0054+000 to K0057+000 11/24/2014 III 12.104 72 O 0.295 0.240 0.150 0.030 0.037 0.033 78.50% 78.50% Unsatisfactory

722 CONSTRUCTION, INC. (Formerly: 722 Construction) 21923

Rehabilitation/Reconstruction of Damaged Paved National Roads including Drainage (Intermittent Section) along Mac

Arthur Highway11/22/2014 NCR 11.413 217 C 0.415 0.133 0.300 - - - 84.80% 84.80%

Satisfactory

811 Trading & Construction 21215 Construction of Baroc River Control, Mansalay, Oriental Mindoro 8/13/2014 IV-B 7.489 95 C 0.469 0.133 0.300 90.20 90.20%

Very Satisfactory

830 BUILDERS & DEVELOPERS CORP. 29781 Construction of Multi-Purpose Building, Barangay Bawi, Padre Garcia, Batangas 12/5/2014 IV 4.223 90 C 0.468 0.133 0.300 - - - 90.10% 90.10%

Very Satisfactory

888 ACY ENTERPRISES 32898 Construction of Sogod NHS 6-CL School Building 8/6/2014 VIII 6.579 210 C 0.449 0.133 0.300 88.20 88.20% Satisfactory

A B APONESTO CONSTRUCTION, PARTS & SUPPLY 22998

Repair/Rehab of Agusan River Flood Control, Osmena Section, Compostela along Montevista – Compostela –

New Bataan – Maragusan – Mati Bdry. Road.8/9/2014 XI 30.533 183 OG 0.384 0.219 0.123 0.030 0.042 0.033 83.10 -

A C O Construction 13105

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved

Road Standards (HDM-4 Project Analysis) Crossing Sta. Clara-Sandayong Road Km. 1808+925 - Km. 1810+355

8/7/2014 IX 32.087 466 C 0.402 0.200 0.300 90.20 85.22% Satisfactory

A J LAVA BUILDERS CORP. (Formerly A.J. Lava Builders) 22265

Construction/Maintenance of Flood Control and Drainage System along Marikina-Infanta Road, Piedra Blanca

Section11/28/2014 IV 17.982 181 C 0.451 0.133 0.300 - - - 88.40% 88.40%

Satisfactory

A. DE GUIA CONSTRUCTION 18228Construction of Drainage System / Protection Works along Daang Maharlika, Isabela 4th LD K0311+590 - K0314+350,

San Luis - Caquilingan10/27/2014 II 19.403 231 O 0.347 0.300 0.150 0.030 0.029 0.033 88.90% 88.90%

Satisfactory

A. DE GUIA CONSTRUCTION 18228Rehabilitation/Reconstruction of Damaged Paved National

Roads along Gamu-Roxas Road @ KO394+000 - KO394+788

10/25/2014 II 12.195 95 C 0.371 0.200 0.300 - - - 87.10% 87.10% Satisfactory

A. De Guia Construction 18228Rehabilitation/ Reconstruction of Damaged Paved national

Roads along Gamu-Roxas Road at K0394+000 to K0394+788

8/9/2014 II 12.195 95 C 0.420 0.133 0.300 85.30 85.30% Satisfactory

A. De Guia Construction 18228Construction/ Rehabilitation of Flood Control Projects, Nagassican Flood Control Projects, Sta. 0+000 to Sta.

0+2248/12/2014 II 19.500 184 OG 0.288 0.248 0.150 0.030 0.055 0.050 82.10 -

A. Sandoval Construction and Supply 35991 Construction of 2 Storey 4 Classroom School Building at

Sta. Clara National High School, Sto. Tomas 8/8/2014 IV-A 4.719 150 C 0.487 0.200 0.300 98.70 88.62% Satisfactory

A. Y. U. ENGINEERING AND CONSTRUCTION 25632 Concreting of Roads for Package C, Brgy. 76-A 10/30/2014 XI 4.950 113 C 0.364 0.186 0.300 - - - 85.00% 85.00%

Satisfactory

A.A. DE VERA CONSTRUCTION 6191Rehab/Reconst./Upgrading of Jct. (TNR) Maribojoc - Antequera - Catagbacan (Loon) Road a.) K0016+925 -

K0016+985 and b.) K0018+652 to K0018+890.508/13/2014 VII 8.500 145 C 0.464 0.143 0.300 90.70 90.70%

Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page2

Page 3: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

A.B. Taylan Construction & Development 25273

Const./Widening/Upgrading/Rehab. Of Access Road to Declared Tourism Destinations, Kapurpurawan Rock

Formation Road, Sta. 0+000 to Sta. 3+4668/10/2014 I 60.479 300 C 0.425 0.133 0.300 85.80 87.24%

Satisfactory

A.B. Taylan Construction & Development/ Fiat Construction

Services (JV)JV-11-392

Construction of Laoag City By-Pass Road, including RROW Sta. 0+000 to Sta. 1+640 & Sta. 2+400 to Sta.

3+164.198/9/2014 I 65.139 330 C 0.470 0.129 0.300 89.90 89.90%

Very Satisfactory

A.C. RIVERO DEVELOPMENT CORPORATION (Formerly: A.C.

RIVERO Construction)5122

Rehab.Strengthening of Divisoria Bridge along Bdry. Southern Leyte - Maasin - Macrohon - Sogod - Daang

Maharlika Road8/6/2014 VIII 14.853 234 C 0.470 0.133 0.300 90.30 89.94%

Very Satisfactory

A.C. RIVERO DEVELOPMENT CORPORATION (Formerly: A.C.

RIVERO Construction)5122 Road Upgrading of San Ricardo - Bil-atan Road Km.

1098+746 - Km. 1100+632 8/5/2014 VIII 40.937 323 C 0.402 0.200 0.300 90.20 90.20% Very Satisfactory

A.C. Rivero Development Corporation (Formerly: A.C. Rivero

Construction)5122 Const. of Subang Daku Bridge, Phase II 08/08/12 VIII 18.890 360 C 0.439 0.200 0.300 - - - 93.90 93.60%

Very Satisfactory

A.C. Rivero Development Corporation (Formerly: A.C. Rivero

Construction)5122 Const./Completion of Subang Daku Bridge, Subang Daku

River, San Miguel 08/17/12 VIII 42.820 220 O 0.383 0.300 0.150 0.030 0.040 0.033 93.60 -

A.C. Rivero Development Corporation (Formerly: A.C. Rivero

Construction)5122 Const./Impv't. of San Miguel-Jct. Buac Rd., Daang

Maharlika Rd (Km1207+000 - Km1209+454.40) 08/19/12 VIII 35.731 220 O 0.349 0.289 0.150 0.030 0.045 0.033 89.60 -

A.C. Rivero Development Corporation (Formerly: A.C. Rivero

Construction)5122 Roadslip at Km.1059+200 along Jct. Himay-angan-Silago

Abuyog Rd., Brgy. Lepanto St. 08/17/12 VIII 6.586 205 C 0.462 0.200 0.300 - - - 96.20 79.58% Unsatisfactory

A.C. Rivero Development Corporation (Formerly: A.C. Rivero

Construction)5122 Upgrading/Conc. of San Juanico-Basey-Sohoton Rd.,

K0913+721.75-K0917+915.72, w/ exceptions 08/07/12 VIII 47.065 200 O 0.357 0.240 0.150 0.030 0.040 0.033 85.00 -

A.C. SOLIVEN CONSTRUCTION & GENERAL MERCHANDISE 19278 Construction of Road at Sitio Kasulukan, Brgy. Aranguren,

Sta.0+000 - Sta.0+263 8/5/2014 III 1.900 17 C 0.426 0.133 0.300 85.90 85.90% Satisfactory

A.C. Soliven Construction & General Merchandise 19278 Add'l Pvmt. Width along Capas-Concepcion Rd.

(Concepcion Sect.) 08/07/13 III 4.829 32 C 0.426 0.133 0.300 - - - 85.90 85.90% Satisfactory

A.D.P Construction & Supply 3466 Impvt./Conc. of Access Road, Tubalan Port, Tubalan 06/14/10 XI 58.261 320 O 0.338 0.300 0.000 0.030 0.040 0.033 74.10 -

A.D.P Construction & Supply 3466Rehab./Reconst./Upgrading of Damaged Paved National

Road, Roxas City Boundary-Panitan Road-Jct. Bailan Road, Capiz (KM.112+750-Km.122+705) with exception

08/31/10 VI 53.673 225 O 0.364 0.240 0.150 0.030 0.051 0.050 88.50 -

A.D.P. CONST. & SUPPLY 3466 Rehabilitation of Miag-ao - Cadre Road, Miag-ao, Iloilo 10/30/2014 VI 10.065 209 C 0.416 0.133 0.300 - - - 84.90% 84.90% Satisfactory

A.D.P. CONST. & SUPPLY 3466Malag-it Box Culvert along Iloilo East Coast-Capiz Road (Construction of Malag-it Bridge along Iloilo East Coast-

Capiz Road)10/29/2014 VI 35.132 240 O 0.388 0.249 0.000 0.030 0.054 0.033 75.40% 75.40%

Unsatisfactory

A.D.P. CONST. & SUPPLY 3466 Widening of Caradio-an Bridge alog Bacolod South Road, Barangay Caradio-an 10/23/2014 VI 24.804 273 O 0.378 0.221 0.034 0.030 0.045 0.033 74.10% 74.10%

Poor

A.D.P. CONST. & SUPPLY 3466 Construction/Rehab. Of Drainage System along Balasan-Carles Road, Brgy. Barosbos 10/29/2014 VI 43.954 274 O 0.373 0.218 0.150 0.030 0.054 0.050 87.50% 87.50%

Satisfactory

A.D.P. CONST. & SUPPLY 3466 Construction of Multi-Purpose Building 10/28/2014 VI 4.227 120 O 0.362 0.214 0.121 0.030 0.049 0.050 82.60% 82.60% Satisfactory

A.D.P. CONST. & SUPPLY 3466Road Upgrading (Gravel to Paved) along Davao-Sarangani Coastal Road km. 1671+600 to km. 1673+060, Biton-Lanao

Section8/7/2014 XI 40.082 208 OG 0.014 0.300 0.000 0.030 0.014 0.000 35.80 -

A.D.P. Const. & Supply 3466 Rd. Upgrading (Gravel to Paved) of San Dionisio-Capinang Rd. K0198+(-640)-K0198+460 w/ exceptions 08/21/13 VI 21.258 131 C 0.471 0.133 0.300 - - - 90.40 90.40%

Very Satisfactory

A.D.P. Const. & Supply 3466Const.n/Repair/Rehab. of Educational Facilities/Sch.

Bldgs., Jordan NHS (Const. of Covered Gym-18.00m x 30.00m)

08/05/13 VI 4.507 120 C 0.464 0.133 0.300 - - - 89.70 89.70% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page3

Page 4: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

A.D.P. Const. & Supply 3466 Rd. Upgrading (Gravel to Paved) along Davao-Sarangani Coastal Rd., Km.1671+600-Km.1673+060, Biton-Lanao Sect. 08/06/13 XI 40.082 179 O 0.322 0.248 0.000 0.030 0.033 0.033 66.60 -

A.D.P. Const. & Supply 3466 Const. of Slope Protection along Jct. Bancal-Leon-Antique Bdry. Rd., K0031+722-K0031+891 08/22/13 VI 13.801 203 C 0.457 0.133 0.300 - - - 89.00 90.44%

Very Satisfactory

A.D.P. Const. & Supply 3466 Const. of Slope Protection along Jct. Bancal-Leon-Antique Boundary Rd., K0031+722-K0031+891 03/22/13 VI 13.802 188 O 0.388 0.241 0.150 0.030 0.055 0.050 91.40 -

A.F.G. CONSTRUCTION AND CONSTRUCTION SUPPLY 17161 Const. of Two (2) Storey Eight (8) Classroom School

Building, Leonora Salapantan National High School 8/12/2014 VI 8.949 150 C 0.429 0.200 0.300 92.90 80.37% Unsatisfactory

A.F.G. Construction and Construction Supply 17161

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. along Bacolod North Rd.; a)K0056+100-K0057+000;

b)K0057+000-K0057+338 (Cluster VIII)08/12/13 VI 21.830 179 C 0.425 0.133 0.300 - - - 85.80 85.80%

Satisfactory

A.F.G. Construction and Construction Supply 17161 Rehab. of Binalbagan Bridge along Bacolod South Rd. 08/10/13 VI 11.563 117 C 0.409 0.133 0.300 - - - 84.20 84.20%

SatisfactoryA.F.G. Construction and

Construction Supply 17161 Replacement/Const. of Tubog Bridge, Brgy. Tubog 08/15/13 VI 7.886 210 C 0.496 0.155 0.300 - - - 95.10 87.84% Satisfactory

A.F.G. Construction and Construction Supply 17161 Odiong-Sibalom-San Remegio-Leon Rd. Upgrading (Gravel

to Paved), Km. 129+328-Km. 131+275 08/15/13 VI 40.453 179 O 0.336 0.240 0.150 0.030 0.037 0.033 82.60 -

A.F.G. Construction and Construction Supply 17161 Const. of Two (2) Storey, Eight (8) Cl Sch. Bldg., Leonora

Salapantan NHS 08/22/13 VI 8.949 150 O 0.347 0.200 0.108 0.030 0.032 0.033 75.00 -

A.F.G. Construction and Construction Supply 17161 Const. of Tangalan-Ibajay Rd. 03/19/13 VI 45.834 179 O 0.387 0.259 0.150 0.024 0.030 0.033 88.30 -

A.F.G. Construction and Construction Supply 17161 Replacement/Const. of Tubog Bridge, Brgy. Tubog 08/15/12 VI 7.587 180 O 0.372 0.230 0.150 0.010 0.035 0.033 83.00 -

A.G. Herrera Construction Corp. 34166 Conc. of Rd. Brgy. Graceville 03/21/13 III 0.985 30 C 0.402 0.133 0.300 - - - 83.50 83.50% Satisfactory

A.J Taylan Construction Corporation 2336 Road Opening/Const. of Missing Links of National Road,

Solsona-Kabugao Road, Ilocos Norte Side 09/09/09 I 48.199 300 O 0.379 0.250 0.150 0.030 0.050 0.033 89.20 -

A.J. LAVA BUILDERS 22265Construction/Rehabilitation of Flood Control (Drainage System) at Quirino Highway, Quezon City (Pazvil & near

Caloocan Boundary) with exceptions 11/26/2014 NCR 17.273 210 C 0.437 0.133 0.300 - - - 87.00% 87.00%

Satisfactory

A.J. Lava Builders 22265 Impv't of Flood Control & Drainage System along San Mateo-Rodriguez Rd., K0021+(-493)-K0025+800, Int. Sect. 08/16/13 IVA 11.283 180 C 0.433 0.133 0.300 - - - 86.60 86.60%

Satisfactory

A.J. Lava Builders 22265 Repair/Rehab./Impv't. (Asphalt Overlay) of Angono Diversion Rd., Km.28+400-Km.28+905 (w/ exceptions) 08/15/13 IVA 9.900 60 C 0.428 0.133 0.300 - - - 86.10 86.10%

Satisfactory

A.J. Lava Builders 22265 Widening of Tanay-Sampaloc Rd., K0057+(-685)-K0071+510.93 (Int. Sect.) 08/17/13 IVA 19.642 158 C 0.373 0.177 0.300 - - - 85.00 85.00%

Satisfactory

A.J. Lava Builders 22265 Repair & Maint. of Flood Control & Drainage Structures along Rodriguez-San Jose-Quezon City Rd. 08/16/13 IVA 2.449 90 C 0.410 0.133 0.300 - - - 84.30 86.22%

Satisfactory

A.J. Lava Builders 22265 Repair & Maint. of Flood Control & Drainage Structures along Rofriguez-San Jose-Quezon City Rd. 11/19/12 IVA 2.449 90 O 0.337 0.300 0.150 0.030 0.025 0.033 87.50 -

A.J. TAYLAN CONST CORP/FR ESPIRITU JR. BUILDERS (JV) JV-14-074 Additional Priority Flood Control Project 10/21/2014 I 41.179 163 O 0.299 0.276 0.150 0.030 0.056 0.050 86.10% 86.10%

Satisfactory

A.J. TAYLAN CONST CORP/MSF CONST (JV) JV-13-603

Construction/ Rehabilitation of Drainage/Protection Works along National Roads, Construction of Lined Canal Along

Badoc, MNR, Badoc-San Nicolas Section10/22/2014 I 8.213 180 C 0.394 0.133 0.300 - - - 82.70% 82.70%

Satisfactory

A.J. Taylan Construction Corporation/Zedik Builders (JV) JV-13-345

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved

Standard (HDM-4 Project Analysis) of Piniti-Banna (Espiritu) Road

8/8/2014 I 28.942 236 OG 0.380 0.240 0.150 0.030 0.055 0.033 88.80 -

A.J. TAYLAN CONSTUCTION CORPORATION 2336 Rehabilitation/ Reconstruction/ Replacement of Irrigation

Bridge 2, along MNR 10/21/2014 I 6.048 132 C 0.415 0.145 0.300 - - - 86.00% 86.00% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page4

Page 5: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

A.L Gantuangco Construction 30872 Construction of the Diversion Works and Canal System of Libertad CIP - Phase 2 11/15-20/2010 NIA 16.060 202 O 0.373 0.264 0.150 0.023 0.038 0.050 89.69 -

A.L Gantuangco Construction 30872 Benolho CIS 10/6-10/08 NIA 3.720 90 O 0.277 0.180 0.050 0.020 0.038 0.100 66.50 -

A.L. DARE CONSTRUCTION 11932

Preventive Maintenance based on Pavement Management System/Highway Development and Management-4 (Intermittent Section) at Bahay Pare-San Luis-Sto.

Domingo Road K0065+181 - K0065+596

11/17/2014 III 3.287 35 C 0.469 0.133 0.300 - - - 90.20% 90.20% Very Satisfactory

A.L. Dare Construction 11932Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd.

(Int. Sect.) at Candaba-San Miguel Rd., K0070+290-K0071+184

07/29/13 III 11.909 139 O 0.319 0.240 0.136 0.030 0.055 0.033 81.30

A.L. SALAZAR CONSTRUCTION, INC. 3899 Rehabiliation/Improvement of drainage System along C-3

Road 11/22/2014 NCR 17.425 209 O 0.380 0.240 0.150 0.030 0.045 0.033 87.80% 87.80% Satisfactory

A.L. Salazar Construction, Inc. 3899 Const./Widening/Upgrading/Rehab. of Access Rd. to Taytay-Bantulan Port (Km.210+000-Km.214+211) 03/12/13 IVB 89.312 450 O 0.364 0.300 0.030 0.030 0.055 0.033 81.20 -

A.L. Salazar Construction, Inc. 3899 Const./Widening/Upgrading/Rehab. of Access Road (Km.210+000-Km.214+211) 08/03/12 IVB 81.362 349 O 0.332 0.240 0.150 0.030 0.045 0.050 84.70 -

A.L.R. Construction Corporation 24110 Completion of 2-Storey 4-CL @ Landayan E/S 02/24/10 IVA 5.030 225 O 0.354 0.300 0.150 0.015 0.018 0.033 87.00 -

A.M. Chua Jr. Engineering & Construction 33734 Proposed Drainage Impv't. along Roxas Blvd. North &

South Bound at EDSA Flyover 08/01/13 NCR 1.350 60 C 0.449 0.133 0.300 - - - 88.20 88.20% Satisfactory

A.M. Chua Jr. Engineering & Construction 33734 Proposed Const./Rehab. of Rds. & Drainage along Comet

& Sunflower Streets, Brgys. 187 03/13/13 NCR 1.918 60 C 0.463 0.067 0.300 - - - 83.00 83.00% Satisfactory

A.M. ORETA & CO., INC./IBC INT'L BUILDERS CORP. (JV) JV-07096 Kalibo Airport Development Project 06/17/15 DOTC 287.056 360 O 0.381 0.300 0.150 0.020 0.044 0.033 92.80 -

A.M. Oreta / IBC (Joint Venture) JV-09-227Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. Iloilo-Capiz Rd. (Old Route), Catatuan-Janiuay-Lambunao-

Calinog Sect.08/24/12 VI 143.043 390 C 0.416 0.200 0.300 - - - 91.60 88.81%

Satisfactory

A.M. Oreta / IBC (Joint Venture) JV-11-210 Const. of Drainage System along Iloilo-Capiz Rd. (Old Route) Nat'l Rd. CPU Sect., Iloilo City 08/06/12 VI 42.875 240 O 0.321 0.239 0.150 0.030 0.055 0.050 84.50 -

A.M. TABAYAG BUILDERS 15008 Construction of Local Road, Brgy. Lower Bayao 10/27/2014 IX 2.895 75 C 0.446 0.139 0.300 - - - 88.50% 88.50% Satisfactory

A.P Palacios Construction 29021 Rehab./Impvt. of Dikidit-Suguit FTMR 09/08/09 III 4.723 150 O 0.300 0.300 0.150 0.030 0.050 0.033 86.30 -A.P. Consebido Construction and

Trading 33618 Const. of Two (2) Classroom Elem. Sch. Bldg. 08/10/13 IVB 1.192 120 C 0.464 0.133 0.300 - - - 89.70 89.70% Very Satisfactory

A.P.B. CONSTRUCTION 17055

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Roads including Drainage Based on

Pavement Management System/Highway Development and Management-4 (HDM-4) (Intermittent Sections), Quirino

Highway (Baguio-Bauang Road), KO300+140-KO300+372 and KO301+195-KO301+350

11/17/2014 CAR 5.042 84 C 0.474 0.133 0.300 - - - 90.70% 90.70% Very Satisfactory

A.P.B. CONSTRUCTION 17055

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Roads including Drainage Based on

Pavement Management System/Highway Development and Management - (HDM-4) (Intermittent Sections), Quirino

Highway (Baguio-Bauang Road), K0301+350 - K0301+780

11/17/2014 CAR 7.910 119 C 0.467 0.133 0.300 - - - 90.00% 90.00% Very Satisfactory

A.P.B. Construction 17055 Repair/Rehab. 0f Drainage Protection Works along Kennon Rd. K0242+000-K0243+000 w/ exception 08/17/13 CAR 5.423 90 C 0.470 0.133 0.300 - - - 90.30 90.30%

Very Satisfactory

A.P.B. Construction 17055 Rehab./Reconst./Upgrading of Damaged Paved National Road, PMA cut-off Road 2 K0+000-K0+360 08/18/11 CAR 5.610 102 O 0.370 0.240 0.000 0.030 0.042 0.033 71.50 -

A.P.O. GENERAL CONSTRUCTION 7010

Road Upgrading (Gravel to Paved) along Acop-Kapangan-Kibungan-Bakun Road, K0283+636 - K0283+796, K0287+621 - K0287+685, K0289+214 - K0289+473, K0289+549 - K0289+709, K0290+901 - K0291+000, K0292+016 - K0292+114, K0298+781 - K0299+514,

K0299+531 - K0299+816

11/20/2014 CAR 72.026 267 O 0.362 0.240 0.150 0.030 0.061 0.050 89.30% 89.30% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page5

Page 6: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

A.P.O. GENERAL CONSTRUCTION 7010

Road Upgrading (Gravel to Concrete) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to

Paved National Road Standards (HDM-4 Project Analysis), Intermittent Section, Acop - Kapangan - Kibungan - Bakun

Road, K0348+000 - K0349+000

8/13/2014 CAR 25.554 267 C 0.433 0.133 0.300 86.60 86.60% Satisfactory

A.P.O. General Construction 7010 Rd. Upgrading (Gravel to Paved) Int. Sect., Acop-Kapangan-Kibungan-Bakun Rd., K0348+000-K0349+000 08/01/13 CAR 23.654 207 O 0.356 0.239 0.150 0.023 0.048 0.050 86.60 -

A.P.O. General Construction 7010

Rd. Upgrading (Gravel to Conc.) along Acop-Kapangan-Kibungan-Bakun Rd., K0285+444-K0286+840 v.s.

(K0285+423-K0286+836 as per RBIA) & K0345+470-K0348+000 v.s. (K0345+500-K0348+000 as per RBIA)

07/31/13 CAR 57.280 285 C 0.391 0.200 0.300 - - - 89.10 85.74% Satisfactory

A.P.O. General Construction 7010

Rd. Upgrading (gravel to concrete) along Acop-Kapangan-Kibungan-Bakun Rd., K0285+444-K0286+840 V.S.

(K0285+423-K0286+836 as per RBIA) & K0345+470-K0348+000 V.S. (K0345+500-K0348+000 as per RBIA)

11/21/12 CAR 59.896 237 O 0.333 0.240 0.150 0.015 0.047 0.050 83.50 -

A.R. & MARK BUILDERS 31673 Const. of Multi-Purpose Building, BUSECO Compound 10/21/2014 X 7.920 124 O 0.304 0.240 0.017 0.010 0.022 0.033 62.60% 62.60% Poor

A.R. & MARK BUILDERS 31673 1 Sty-1CL & 1CL Kinder @ Maramag South PS, South Poblacion 8/7/2014 X 12.530 187 C 0.446 0.200 0.300 94.60 86.76%

Satisfactory

A.R. & Mark Builders 31673 Const. of 1-Storey, 1-CL & 1-Storey, 1-CL Kinder at Maramag South PS, Pob. 08/08/13 X 1.448 187 O 0.393 0.235 0.120 0.030 0.023 0.033 83.40 -

A.R. & Mark Builders 31673 Const./Conc./Repair of Roads Brgy. Bugo 03/18/13 X 3.369 45 C 0.386 0.200 0.300 - - - 88.60 88.60% Satisfactory

A.R. Lustre Jr. Construction 7680 Conc. of Puerto Princesa South Rd. (Aborlan Sect. Km.60+024.80-Km.64+000 w/ exceptions) 03/15/13 IVB 62.614 240 O 0.362 0.240 0.150 0.030 0.055 0.033 87.00 -

A.R. Lustre Jr. Construction 7680 Rd. Upgrading (Gravel to Conc.) Conc. of Puerto Princesa South Rd. (Labog-Punag Sect., Km.144+517-Km.147+454) 03/14/13 IVB 60.671 265 C 0.417 0.133 0.300 - - - 85.00 86.65%

Satisfactory

A.R. Lustre Jr. Construction 7680 Conc. of Tapul-Bahile Road, Km. 39+903.50-Km.40+560 03/19/12 IVB 8.567 75 C 0.417 0.200 0.300 - - - 91.70 90.02% Very Satisfacfory

A.R. Lustre Jr. Construction 7680Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds.,

Pulilan-Calumpit Rd., Km.47+741.10-Km.49+766 w/ exception, Pulilan & Calumpit

03/14/12 III 21.726 113 C 0.426 0.151 0.300 - - - 87.70 87.40% Satisfactory

A.R. LUSTRE JR. CONSTRUCTION          7680 Construction of Multi-Purpose Building 11/24/2014 IV 3.858 195 C 0.489 0.133 0.300 - - - 92.20% 92.20% Very Satisfactory

A.R. Lustre, Jr. Construction 7680 Construction of Taguiliat Bridge along PPSR - Jct. Napsan -Apurawan Road, K0037+675 8/8/2014 IV-B 18.839 651 C 0.417 0.130 0.300 84.70 83.38%

Satisfactory

A.R. Lustre, Jr. Construction 7680 Const. of Taguliat Bridge along PPSR-JCT-Napsan-Apurawan Rd., K0037+675 08/15/13 IVB 18.839 515 O 0.373 0.300 0.047 0.030 0.042 0.033 82.50 -

A.R.L. CONSTRUCTION 27645 Channel Improvement of Hagonoy River 11/7/2014 III 9.310 120 C 0.400 0.133 0.300 - - - 83.30% 83.30% Satisfactory

A.S.S. Construction 31509 Completion of ACA Building II 05/14-15/09 DOST 9.631 210 O 0.380 0.296 0.150 0.030 0.062 0.050 96.80 -A.S.V. Construction Supply and

Services 13490 Const./Impvt. of MPB 03/20/12 III 2.794 117 C 0.436 0.126 0.300 - - - 86.20 87.81% Satisfactory

A.S.V. Construction Supply and Services 13490 Concrete Reblocking Junction Layac-Balanga-Mariveles

Port Rd., K0106+151-K0107+000 03/24/12 III 4.778 122 C 0.411 0.133 0.300 - - - 84.40 85.90% Satisfactory

A.S.V. Construction Supply and Services 13490 Repair/Maint. of Naparing River Control 03/12/13 III 1.407 60 C 0.430 0.133 0.300 - - - 86.30 86.30%

Satisfactory

A.T. DUMLAO CONSTRUCTION, INC. (Formerly: Andoni T. Dumalao

Civil Engineer - Contractor)34028

Construction/Widening of Adlayan Bridge along Daang Maharlika (Agusan - Davao Section) K1307+585 -

K1307+614.88/8/2014 XIII 36.650 196 OG 0.400 0.240 0.060 0.030 0.065 0.033 82.80 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page6

Page 7: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

A.T. Dumlao Construction, Inc. (Formerly: Andoni T. Dumlao Civil

Engineer-Contractor)34028 Replacement of San Pedro Bridge along Daang Maharlika

(Surigao-Agusan Rd.) Brgy. San Pedro 11/21/12 XIII 14.945 390 O 0.360 0.231 0.127 0.030 0.055 0.033 83.60 -

A.T. DUMLAO CONSTRUCTION, INC. (Formerly: Andoni T. Dumlao,

Civil Engineer - Contractor)34028

Replacement of Lengigon Bridge (Temporary to Permanent) along Argao - Moalboal Road, Municipality of

Argao10/24/2014 VII 12.230 270 O 0.400 0.300 0.000 0.030 0.055 0.000 78.50% 78.50%

Unsatisfactory

A.T. DUMLAO CONSTRUCTION, INC. (Formerly: Andoni T. Dumlao,

Civil Engineer - Contractor)34028

Construction and Maintenance of Bridges along National Roads, Repair/Maintenance/Strengthening of Alimpatayan Bridge along Daang Maharlika (Surigao - Agusan Section)

10/26/2014 XIII 1.892 69 C 0.425 0.133 0.300 - - - 85.80% 85.80% Satisfactory

A.T. Dumlao Construction, INC. (Formerly: Andoni T. Dumlao, Civil

Engineer - Contractor)34028

Repair/Reconst. Of Boan Bridge along Daang Maharlika (Agusan-Davao Road) Km.1331+632 - Km.1380+770 w/

exceptions03/18/13 XIII 12.910 315 C 0.416 0.133 0.300 - - - 84.90 86.82%

Satisfactory

A.T. Dumlao Construction, Inc. (Formerly: Andoni T. Dumlao, Civil

Engineer - Contractor)34028 Reconst. of Timamana Bridge along Daang Maharlika

Highway (Surigao-Agusan Rd.), Brgy. Timamana 03/14/13 XIII 24.213 496 O 0.305 0.252 0.150 0.030 0.056 0.050 84.30 -

A.T. Dumlao Construction, Inc. (Formerly: Andoni T. Dumlao, Civil

Engineer-Contractor)34028 Rehab./Strengthening of Agong-Ongan Bridge along

Magpayang-Mainit Rd., Brgy. Roxas 08/08/13 XIII 2.820 75 C 0.450 0.133 0.300 - - - 88.30 88.30% Satisfactory

A.T. Dumlao Construction, Inc. (Formerly: Andoni T. Dumlao, Civil

Engineer-Contractor)34028 Replacement of San Pedro Bridge along Daang Maharlika

(Surigao-Agusan Rd.) Brgy. San Pedro 08/07/13 XIII 15.781 435 C 0.428 0.133 0.300 - - - 86.10 85.84% Satisfactory

A.T. Dumlao Construction, Inc. (Formerly: Andoni T. Dumlao, Civil

Engineer-Contractor)34028 Reconst. of Timamana Bridge along Daang Maharlika

Highway (Surigao-Agusan Rd.) Brgy. Timamana 08/07/13 XIII 24.213 496 C 0.390 0.133 0.300 - - - 82.30 83.50% Satisfactory

A.T. Dumlao Construction, Inc. (Formerly: Andoni T. Dumlao, Civil

Engineer-Contractor)34028 Rehab./Reconst. of Hubang Bridge along Daang Maharlika

(Agusan-Davao Rd.) 08/19/13 XIII 19.141 445 C 0.476 0.133 0.300 - - - 90.90 81.90% Unsatisfactory

A.T. Dumlao Construction, Inc. (Formerly: Andoni T. Dumlao, Civil

Engineer-Contractor)34028 Replacement of San Pedro Bridge along Daang Maharlika

(Surigao-Agusan Rd.), Brgy. San Pedro 03/14/13 XIII 15.781 435 O 0.355 0.223 0.150 0.030 0.035 0.033 82.60 -

A.T. Dumlao Construction, Inc. (Formerly: Andoni T. Dumlao, Civil

Engineer-Contractor)34028 Rehab./Reconst. of Hubang Bridge along Daang Maharlika

(Agusan-Davao Rd.) Km.1307+369-Km.1307+536 03/09/13 XIII 19.141 380 O 0.338 0.300 0.000 0.030 0.058 0.033 75.90 -

A.V.M. Construction and Supplies 114114 NHA Bayside Subdivision Housing Project 10/24/14 NHA 19.225 330 O 0.376 0.300 0.095 0.030 0.023 0.033 85.74 -

A.Y.U. Engineering and Construction 25632 Package 5 - Conc. of FMR at Balengaeng, Tugbok Rd. 08/07/13 XI 4.975 80 C 0.344 0.200 0.300 - - - 84.40 84.40%

Satisfactory

A.Y.U. Engineering and Construction 25632 Widening of Rd. from Luis Tatad Sr. St., Purok San Miguel

passing through Sto. Niño to Santol St., Brgy. Buhangin 03/21/13 XI 4.790 66 C 0.453 0.133 0.300 - - - 88.60 88.60% Satisfactory

A.Y.U. Engineering and Construction 25632 Const. of MPB at Brgy. Sto. Niño, Tugbok District 03/12/13 XI 3.133 120 C 0.450 0.133 0.300 - - - 88.30 88.30%

SatisfactoryAB Aponesto Construction, Parts &

Supply 22998 Conc. of Lublub-Bolilac-Salad Road, Km.277+707.50-Km.278+711 09/05/10 VI 14.425 192 O 0.356 0.240 0.150 0.030 0.042 0.033 85.10 -

AB TAYLAN CONSTRUCTION AND DEVELOPMENT (formerly ADSM

Construction)25273

Preventive Maintenance Based on Pavement Management System/Highway Development and Management-4 (HDM-

4)(Int. Section, Pasuquin Radar Airstation Road K0508+235 to K0508+881 to K0511+510

10/21/2014 I 19.286 126 C 0.441 0.149 0.300 - - - 89.00% 89.00% Satisfactory

Abulug Construction Company, Inc. 5593 Const. of Colony Road 11/13/08 II 2.894 120 O 0.329 0.240 0.100 0.030 0.033 0.100 83.20 -

Abulug Developers & Builders Co., Inc. 2366 Reblocking along Manila North Road (Fugu Bdry.-Bangag

Section) 05/21/09 II 19.299 210 O 0.368 0.240 0.150 0.030 0.051 0.033 87.20 -

AC RIVERO DEVELOPMENT CORPORATION (Formerly: AC

Rivero Construction)5122 Const. of Bridge at Dodiongan Box Culvert along Sta.

Felomina-Bonbon-Digkilaan-Rogongon Road 10/29/2014 X 24.567 295 O 0.339 0.278 0.150 0.010 0.051 0.050 87.80% 87.80% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page7

Page 8: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

ACCURACY BUILDERS ENTERPRISE 27507 Rehabilitation of Banaue Hotel Roofing 1/13/15 TIEZA 19.900 180 C 0.471 0.200 0.300 97.10 78.90

UnsatisfactoryACCURACY BUILDERS

ENTERPRISE 27507 Rehabilitation of Banaue Hotel Roofing 01/13/14 TIEZA 19.880 180 S 0.304 0.300 0.052 0.150 0.008 0.033 71.14 -

ACJ Construction Resources 10635Road Upgrading of Nat'l Rd. (Gravel to Concrete) Nat'l

Secondary Rd., Km.1628+584-Km.1630+803 along Kidapawan-Magpet-Pangao-an Rd.

08/17/11 XII 24.178 180 O 0.342 0.300 0.000 0.030 0.045 0.033 75.00 -

ACJ Construction Resources 10635 Conc. of Paco-Roxas-Arakan Road Kiyaab-Antipas Section (Km. 1648+300-Km.1649+385.63) 09/05/09 XII 16.826 150 O 0.324 0.300 0.150 0.015 0.042 0.050 88.10 -

ACJ Construction Resources 10635 Concreting of Poblacion Magpet-Nowa Road (Nowa Basak Sect.) 03/10/09 XII 18.798 180 O 0.356 0.284 0.150 0.030 0.035 0.050 90.50 -

ACJ Construction Resources 10635Rd. Upgrading (Gravel to Conc.) Nat'l Secondary Rd.,

K1657+(-247)-K1659+824 along Paco-Roxas-Arakan Valley Rd.

08/10/12 XII 46.844 384 O 0.354 0.244 0.150 0.030 0.051 0.050 87.90 -

ACJ Construction Resources 10635Rd. Upgrading of Nat'l Rd. (gravel to concrete) Nat'l Secondary Rd. , Km.1629+(-124)-Km.1630+133 along

Magpet, Nowa-Doroluman-Greenfield Rd08/11/12 XII 22.850 259 C 0.486 0.177 0.300 - - - 96.30 82.38%

Satisfactory

ACME BUILDERS CORPORATION 6442 Road Upgrading of Tigbao - Sta. Fe - San Miguel Road KO910+000 - KO915+500 & KO913+000 - KO913+900 8/16/2014 VIII 56.481 270 C 0.429 0.133 0.300 86.20 86.20%

Satisfactory

ACME BUILDERS CORPORATION 6442 Rehab./Strengthening of Rosales Bridge along Daang Maharlika SM (San Isidro - San Juanico Bridge) 8/11/2014 VIII 25.251 165 C 0.500 0.133 0.300 93.30 91.80%

Very Satisfactory

Acme Builders Corporation 6442 Rd. Upgrading of Tigbao-Sta. Fe-San Miguel Rd., K0910+000-K0911+500 & K0913+000-K0913+900 08/22/13 VIII 55.416 270 O 0.383 0.240 0.150 0.012 0.042 0.050 87.70 -

Acme Builders Corporation 6442 Rehab./Strengthening of Rosales Bridge along Daang Maharlika (SM) (San Isidro-San Juanico Bridge) 08/14/13 VIII 25.251 165 O 0.393 0.242 0.150 0.030 0.060 0.033 90.80 -

Acme Builders Corporation 6442 Replacement of Caglinapao Bridge along Daang Maharlika (SM) San Isidro-San Juanico Bridge, Brgy. Caglinapao 03/19/13 VIII 45.818 274 C 0.446 0.103 0.300 - - - 84.90 85.68%

Satisfactory

Acme Builders Corporation 6442 Rehab./Reconst./Impvt./Upgrading of Damaged Pavement, Tacloban Baybay South Rd. 06/17/10 VIII 34.600 150 O 0.366 0.300 0.150 0.030 0.032 0.033 91.10 -

Acme Builders Corporation 6442 Construction of Bagacay Bridge 03/02/09 VIII 39.122 332 O 0.319 0.288 0.000 0.030 0.023 0.050 71.00 -

Acme Builders Corporation 6442 Const. of Nijaga Bridge along Calbayog Diversion Road (Phase II) 03/24/12 VIII 38.813 320 C 0.466 0.133 0.300 - - - 89.90 87.44%

Satisfactory

Acme Builders Corporation 6442 Rehab./Reconst. along Tacloban-Baybay South Rd, K915+(-1250)-K915+(-247) 08/22/12 VIII 19.358 180 C 0.439 0.133 0.300 - - - 87.20 87.80%

SatisfactoryAcme Builders Corporation / B.

Vicencio Construction JV-07-066 Const. of Palo East By Pass Road (Const. of Bernard Reed II Bridge) 08/31/09 VIII 57.823 616 O 0.384 0.240 0.150 0.030 0.047 0.033 88.40 -

Acme Builders Corporation / MWJ Construction (JV) JV-08-243 Const. of Albuera-Burauen Road including Bridges,

Burauen Sect. 09/02/09 VIII 47.235 240 O 0.352 0.245 0.150 0.030 0.045 0.050 87.20 -

ADFIL CORPORATION 14437Widening/Concreting of Additional Lane both directions

along Butuan City - Cagayan de Oro - Iligan Road, K1249+461 - K1253+310.50

8/5/2014 XIII 89.512 370 C 0.447 0.133 0.300 88.00 88.78% Satisfactory

ADFIL CORPORATION 14437Rehab./Reconstruction/Upgrading of Butuan City -

Malaybalay Road, Butuan City, a.) K1240+(-995) - K1240+(-771); b.) K1240+(-375) - K1240+800, (Intermittent Section)

8/14/2014 XIII 22.919 147 C 0.442 0.133 0.300 87.50 87.50% Satisfactory

ADFIL CORPORATION 14437 Const./Improvement of Road to Support River Rhine Cruise leading to Banza Ruins, Barangay Banza 8/14/2014 XIII 26.706 148 OG 0.332 0.254 0.150 0.030 0.070 0.050 88.60 -

ADFIL CORPORATION 14437Rehab./Reconstruction/Replacement/Retrofitting of

Magsaysay Bridge along Butuan - Cagayan de Oro - Iligan (Agusan - Misamis Oriental)

8/15/2014 XIII 36.843 234 OG 0.384 0.234 0.150 0.030 0.047 0.050 89.50 -

ADFIL CORPORATION 14437Rehab./Reconstruction of Ampayon Bridge along Daang

Maharlika, K1232+540 - K1232+888, K1232+841 - K1232+884

8/14/2014 XIII 19.207 251 C 0.489 0.133 0.300 92.20 92.44% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page8

Page 9: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

ADFIL CORPORATION 14437Rehab./Reconstruction/Strengthening of Minusong Bridge along Butuan - Cagayan de Oro - Iligan (Agusan - Misamis Oriental), Km. 1269+217, Aclan, Nasipit, Agusan del Norte

8/4/2014 XIII 28.848 300 C 0.495 0.133 0.300 92.80 92.80% Very Satisfactory

ADFIL CORPORATION 14437 Construction of Agusan - Bukidnon Road, Sta. 1262+260 - Sta. 1265+120 8/5/2014 XIII 40.140 209 OG 0.360 0.264 0.150 0.030 0.037 0.050 89.10 -

ADFIL CORPORATION 14437 Construction and Repair/ Rehabilitation of Irrigation Package I 06/07/14 NIA 19.655 150 C 0.411 0.160 0.300 - - - 87.10 87.10%

Satisfactory

Adfil Corporation 14437 Repair/Maintenance with Asphalt Overlay of Tabon-Tabon Slip along Agusan- Davao Road 06/17/10 XIII 32.364 225 O 0.371 0.240 0.150 0.030 0.055 0.033 87.90 -

Adfil Corporation 14437 Rehab. of Magsaysay Bridge along Iligan City 09/09/10 XIII 48.161 300 O 0.352 0.300 0.150 0.030 0.055 0.050 93.70 -

Adfil Corporation 14437 Rehab./Reconst. of Damaged Paved National Roads Gingoog-Calveria-Villanueva Road 09/10/09 X 96.400 405 O 0.259 0.300 0.150 0.030 0.061 0.050 85.00 -

Adfil Corporation 14437Rehab./Reconst. of Damaged Paved National Rd. along Butuan City-CDO-Iligan Rd.,(Agusan-Misamis Oriental

Sect.)Libertad-Bancasi Sect.09/16/09 XIII 54.954 285 O 0.371 0.300 0.150 0.030 0.055 0.050 95.60 -

Adfil Corporation 14437 Const./Completion/Continuation of Unfinished Bridge and Approaches, Brgy. Libertad 09/16/09 XIII 23.830 195 O 0.364 0.300 0.150 0.030 0.055 0.050 94.90 -

Adfil Corporation 14437 Concreting of NRJ-Bahbah-Talacogon Rd. 09/13/09 XIII 15.872 225 O 0.371 0.244 0.150 0.030 0.065 0.050 91.00 -

Adfil Corporation (Formerly: Adfil Construction) 14437

Widening/Conc. of Add'l. Lane along Daang Maharlika (Agusan-Surigao Rd.) Cabadbaran City Sect., Sta.1213+540-

Sta.1215+52008/15/13 XIII 29.059 142 C 0.458 0.130 0.300 - - - 88.80 91.20%

Very Satisfactory

Adfil Corporation (Formerly: Adfil Construction) 14437 Completion of Maraput Bridge along Daang Maharlika

(Surigao-Agusan Rd.) Km.1207+192 08/05/13 XIII 9.113 120 C 0.481 0.133 0.300 - - - 91.40 90.44% Very Satisfactory

Adfil Corporation (Formerly: Adfil Construction) 14437 Rehab./Reconst. of Ampayon Bridge along Daang

Maharlika 08/23/13 XIII 19.207 219 O 0.397 0.240 0.150 0.018 0.040 0.050 89.50 -

Adfil Corporation (Formerly: Adfil Construction) 14437

Widening/Conc. of Add'l. Lane Both Directions along Butuan City-Cagayan de Oro-Iligan Rd., K1249+461-

K1253+310.5008/06/13 XIII 86.661 240 O 0.390 0.238 0.150 0.030 0.035 0.050 89.30 -

Adfil Corporation (Formerly: Adfil Construction) 14437 Const. of Rd. to Support River Rhine Cruise, Banza Ruins 08/23/13 XIII 30.629 185 C 0.457 0.133 0.300 - - - 89.00 88.40%

SatisfactoryAdfil Corporation (Formerly: Adfil

Construction) 14437 Completion of La Union Bridge along Pandanon-Magallanes Rd. 08/05/13 XIII 15.886 150 C 0.440 0.133 0.300 - - - 87.30 86.64%

Satisfactory

ADFIL CORPORATION (Formerly: Adfil Construction) 14437 Road Upgrading (Gravel to Paved) of Butuan City-Pianing-

Tandag Road, K1237+055 - K1240+040, with exceptions 10/30/2014 XIII 127.287 270 O 0.346 0.240 0.150 0.024 0.056 0.050 86.60% 86.60% Satisfactory

ADFIL CORPORATION (Formerly: Adfil Construction) 14437

Reconstruction/Replacement/Completion of Minusong Bridge along Butuan-Cagayan de Oro-Iligan Road (Agusan--

Misamis Oriental), Km1269+21710/21/2014 XIII 34.627 270 O 0.343 0.286 0.150 0.030 0.065 0.050 92.40% 92.40%

Very Satisfactory

ADFIL CORPORATION (Formerly: Adfil Construction) 14437 Construction of Agusan-Bukidnon Road, Sta. 1262+260 -

Sta. 1265+120 10/21/2014 XIII 40.140 271 O 0.387 0.182 0.150 0.024 0.065 0.050 85.80% 85.80% Satisfactory

ADFIL CORPORATION (Formerly: Adfil Construction) 14437

Rehab./Reconst./Replacement/Retrofitting of Salvacion Bridge along NRJ Cuevas - Bislig Road, K1374+670 -

K1374+7318/8/2014 XIII 36.656 196 OG 0.400 0.200 0.150 0.030 0.042 0.050 87.20 -

Adfil Corporation (Formerly: Adfil Construction) 14437

Rehab./Reconst./Upgrading of Butuan City-Cagayan de Oro-Iligan City Rd., a)K1494+049-K1495+240; b)K1499+692-

K1499+712; c)K1500+678-K1500+902; d)K1501+905-K1507+000; e)K1508+000-K1508+919

08/19/13 X 48.167 285 C 0.474 0.133 0.300 - - - 90.70 88.06% Satisfactory

Adfil Corporation (Formerly: Adfil Construction) 14437

Rehab./Reconst./Upgrading of Butuan City-Cagayan de Oro-Iligan City Rd. a)K1494+049-K1495+240; b)K1499+692-

K1499+712; c)K1500+678-K1500+902; d)K1501+905-K1507+000; e)K1508+000-K1508+919

03/12/13 X 48.167 285 O 0.293 0.271 0.150 0.010 0.050 0.050 82.40 -

Adfil Corporation (Formerly: Adfil Construction) 14437 Rehab./Reconst. of Ampayon Bridge along Daang

Maharlika 03/21/13 XIII 18.426 171 O 0.390 0.300 0.150 0.030 0.054 0.033 95.70 -

Adfil Corporation (Formerly: Adfil Construction) 14437

Widening/Conc. of Add'l Lane along Daang Maharlika (Agusan-Surigao Rd.) Cabadbaran City Sect., Sta.1213+540-

Sta.1215+52003/11/13 XIII 29.059 142 O 0.365 0.300 0.150 0.030 0.050 0.033 92.80 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page9

Page 10: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Adfil Corporation (Formerly: Adfil Construction) 14437 Completion of Maraput Bridge along Daang Maharlika

(Surigao-Agusan Rd.), Sta.1207+192 03/11/13 XIII 9.115 120 O 0.348 0.300 0.150 0.030 0.037 0.033 89.80 -

Adfil Corporation (Formerly: Adfil Construction) 14437 Conc. of NRJ Cuevas-Sampaguita Rd., Km.1382+082-

Km.1384+555.134 03/18/13 XIII 48.082 345 C 0.361 0.200 0.300 - - - 86.10 89.40% Very Satisfactory

Adfil Corporation (Formerly: Adfil Construction) 14437 Const./Impv't of Rd. to Support River Rhine Cruise, Banza

Ruins 03/21/13 XIII 29.509 155 O 0.313 0.300 0.150 0.024 0.060 0.033 88.00 -

Adfil Corporation (Formerly: Adfil Construction) 14437 Conc. of Asuncion-San Isidro-Laak-Veruela Rd.,

Km.1547+000-Km.1547+620; Km.1553+760-Km.1555+159 03/18/13 XIII 46.405 353 C 0.344 0.191 0.300 - - - 83.50 87.97% Satisfactory

Adfil Corporation (Formerly: Adfil Construction) 14437 Completion of La Union Bridge along Pandanon-

Magallanes Rd. 03/11/13 XIII 15.889 150 O 0.312 0.300 0.150 0.020 0.047 0.033 86.20 -

Adfil Corporation (Formerly: Adfil Construction) 14437 Completion of Bislig Bridge along Surigao-Davao Coastal

Rd. (Demolition of Old Bridge-Phase I) 03/26/12 XIII 13.043 285 C 0.500 - 0.500 - - - 100.00 93.76% Very Satisfactory

Adfil Corporation (Formerly: Adfil Construction) 14437 Conc. of Agusan-Malaybalay Road, Km. 1283+183.50-

Km.1284+780 03/31/12 XIII 39.495 300 O 0.351 0.300 0.150 0.030 0.040 0.050 92.10 -

Adfil Corporation (Formerly: Adfil Construction) 14473 Conc. of Butuan City-Pianing/Tandag Road 03/31/12 XIII 14.808 180 C 0.472 0.133 0.300 - - - 90.50 91.34%

Very SatisfactoryAdfil Corporation (Formerly: Adfil

Construction) 14473 Reconst. of Road Slip Sect. along Daang Maharlika (Agusan-Davao Rd.) Lapinigan Sect. 03/27/12 XIII 17.325 220 C 0.462 0.133 0.300 - - - 89.50 90.64%

Very Satisfactory

Adfil Corporation (Formerly: Adfil Construction) 14437

Widening/Conc. of Add'l Lane Both Directions along Butuan City-Cagayan de Oro-Iligan Rd., Ampayon-Baan

Sect.03/31/12 XIII 26.232 240 C 0.454 0.133 0.300 - - - 88.70 90.44%

Very Satisfactory

Adfil Corporation (Formerly: Adfil Construction) 14437 Reconst. of Maglambing Bridge and Approaches 03/26/12 XIII 65.519 601 C 0.490 0.133 0.300 - - - 92.30 89.45%

Very SatisfactoryAdfil Corporation (Formerly: Adfil

Construction) 14437 Conc. of NRJ Cuevas-Bislig Road, Phase II, Sta. 1375+369-Sta.1380+840 03/27/12 XIII 26.309 245 C 0.385 0.200 0.300 - - - 88.50 89.25%

Satisfactory

Adfil Corporation (Formerly: Adfil Construction) 14437

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds., Butuan City-Cagayan de Oro City-Iligan City Rd.:

a.)K1494+049-K1495+240; b.)K1499+692-K1499+712; c.)k1500+678-K1500+902; d.)K1501+905-K1507+000;

e.)K1508+000-K1508+919

11/23/12 X 44.537 255 O 0.332 0.300 0.150 0.030 0.040 0.050 90.20 -

Adfil Corporation (Formerly: Adfil Construction) 14437

Rehab./Reconst./Strengthening of Minusong Bridge along Butuan-Cagayan de Oro-Iligan (Agusan-Misamis Oriental)

Km1269+21711/19/12 XIII 28.848 300 C 0.475 0.196 0.300 - - - 97.10 91.67%

Very Satisfactory

Adfil Corporation (Formerly: Adfil Construction) 14437

Rehab./Reconst./Strengthening of Maraput Bridge along Daang Maharlika (Surigao-Agusan Rd.) Km.1207+192,

Brgy. Victory11/19/12 XIII 24.216 285 C 0.498 0.193 0.300 - - - 99.10 91.42%

Very Satisfactory

Adfil Corporation (Formerly: Adfil Construction) 14437 Rehab. of Salvacion (Crossing Luna Flood Control) 11/25/12 XIII 17.434 285 C 0.492 0.150 0.300 - - - 94.20 91.38%

Very Satisfactory

Adfil Corporation (Formerly: Adfil Construction) 14437 Widening of Butuan-Cagayan de Oro-Iligan Rd. (Agusan-

Misamis Oriental Sect.), Pob., Buenavista Sect.) 11/19/12 XIII 24.129 270 C 0.449 0.184 0.300 - - - 93.30 91.32% Very Satisfactory

Adfil Corporation (Formerly: Adfil Construction) 14437 Widening of Daang Maharlika (Agusan-Surigao Rd.) Pob.,

Cabadbaran Sect. 11/19/12 XIII 27.390 255 C 0.451 0.124 0.300 - - - 87.50 88.76% Satisfactory

Adfil Corporation (Formerly: Adfil Construction) 14437 Rehab/Reconst./Strengthening of Minusuang Bridge along

Daang Maharlika (Surigao-Agusan Road) Km.1206+561 11/19/12 XIII 24.513 270 C 0.497 0.133 0.300 - - - 93.00 88.26% Satisfactory

Adfil Corporation (Formerly: Adfil Construction) 14437 Reconst. Of Rd. Slip Sect. along Cuevas-Sta. Josefa Rd.

Km.1370+643.90-Km.1371+536.10 08/17/12 XIII 49.023 232 C 0.452 0.146 0.300 - - - 89.80 92.08% Very Satisfactory

Adfil Corporation (Formerly: Adfil Construction) 14437 Const./Rehab. of Cabadbaran River Dike 08/20/12 XIII 16.763 135 C 0.430 0.200 0.300 - - - 93.00 92.04%

Very SatisfactoryAdfil Corporation (Formerly: Adfil

Construction) 14437 Rehab./Reconst./Strengthening of Maglambing Bridge along SDCR 08/16/12 XIII 1.300 154 C 0.459 0.200 0.300 - - - 95.90 92.00%

Very SatisfactoryAdfil Corporation (Formerly: Adfil

Construction) 14437 Conc. of Agusan-Malaybalay Rd., Km.1283+183.50-Km.1284+780 08/20/12 XIII 42.366 345 C 0.443 0.143 0.300 - - - 88.60 90.70%

Very Satisfactory

Adfil Corporation (Formerly: Adfil Construction) 14437 Widening of Butuan-Cagayan de Oro-Iligan Rd. (Agusan-

Misamis Oriental Sect.) Pob., Buenavista Sect. 08/06/12 XIII 24.129 255 O 0.336 0.296 0.150 0.030 0.055 0.033 90.00 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page10

Page 11: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Adfil Corporation (Formerly: Adfil Construction) 14437 Rehab./Reconst. Of Butuan-Cagayn de Oro-Iligan (Agusan-

Misamis Oriental Rd.) K1248+640-K1249+400 08/23/12 XIII 13.102 105 C 0.457 0.138 0.300 - - - 89.50 89.68% Very Satisfactory

Adfil Corporation (Formerly: Adfil Construction) 14437 Rehab. of Salvacion (Crossing Luna Flood Control) 08/20/12 XIII 16.733 285 O 0.375 0.240 0.150 0.030 0.050 0.050 89.50 -

Adfil Corporation (Formerly: Adfil Construction) 14437 Widening of Daang Maharlika (Agusan-Usrigao Rd.) Pob.,

Cabadbaran Sect. 08/06/12 XIII 27.390 255 O 0.370 0.240 0.150 0.030 0.050 0.050 89.00 -

Adfil Corporation (Formerly: Adfil Construction) 14437 Rehab. of Magallanes River Dike, Magallanes 08/06/12 XIII 26.123 204 C 0.438 0.133 0.300 - - - 87.10 88.84%

Satisfactory

Adfil Corporation (Formerly: Adfil Construction) 14437

Rehab./Reconst./Strengthening of Minusong Bridge along Butuan-Cagayan de Oro-Iligan (Agusan Misamis Oriental)

Km.1269+217, Aclan, Nasipit08/06/12 XIII 28.848 270 O 0.383 0.246 0.150 0.030 0.045 0.033 88.70 -

Adfil Corporation (Formerly: Adfil Construction) 14437 Rehab./Reconst. Of Butuan-Cagayan de Oro-Iligan (Agusan-

Misamis Oriental Rd.) K1233+000-K1235+360 (IS) 08/20/12 XIII 19.913 165 C 0.433 0.136 0.300 - - - 86.90 88.10% Satisfactory

Adfil Corporation (Formerly: Adfil Construction) 14437 Rehab./Reconst./Strengthening of Minusuang Bridge along

Daang Maharlika (Surigao-Agusan Rd.) Km.1206+561 08/07/12 XIII 23.512 270 O 0.326 0.240 0.150 0.030 0.055 0.050 85.10 -

Adfil Corporation (Formerly: Adfil Construction) 14437

Rehab./Reconst./Strengthening of Maraput Bridge along Daang Maharlika (Surigao-Agusan Rd.) Km.1207+192,

Brgy. Victory08/07/12 XIII 23.512 285 O 0.325 0.240 0.150 0.030 0.055 0.050 85.00 -

Adige Sta. Clara (JV) JV-06-032 DPWH Component Project under the Help for Catubig Agricultural Advancement Proj. 05/30/09 VIII 519.663 1,073 O 0.378 0.300 0.150 0.030 0.050 0.050 95.80 -

Adige Sta. Clara (JV) JV-06-032 DPWH Component Project under the HELP for Catubig Agricultural Project (HCAAP) 08/25/08 VIII 448.581 734 O 0.377 0.300 0.070 0.030 0.050 0.067 89.40 -

ADIMRE CONSTRUCTION 25534 Taytay Airport Development Project 07/22/15 DOTC 10.794 154 O 0.390 0.300 0.033 0.030 0.044 0.050 84.70 -ADIMRE CONSTRUCTION 25534 Marinduque Airport Development Project 08/07/15 DOTC 6.293 120 O 0.384 0.300 0.150 0.015 0.035 0.050 93.40 -

ADIMRE CONSTRUCTION 25534 Construction of Three Storey Six Classroom Building Tibagan National H/S 11/7/2014 III 7.027 180 C 0.441 0.133 0.300 - - - 87.40% 87.40%

SatisfactoryADIMRE CONSTRUCTION 25534 Balagtas Port Development Project 07/10/14 DOTC 7.802 180 O 0.385 0.300 0.150 0.020 0.040 0.033 92.80 -

ADIMRE CONSTRUCTION 25534 Castilla Port Development Project 07/23/14 DOTC 4.873 120 C 0.466 0.200 0.300 - - - 96.60 96.60% Outstanding

ADIMRE CONSTRUCTION 25534 Obando Port Development Project 08/18/14 DOTC 8.109 194 O 0.378 0.300 0.150 0.010 0.016 0.033 88.65 -

ADIMRE CONSTRUCTION 25534 Malolos Port Development Project 08/19/14 DOTC 9.625 254 O 0.397 0.300 0.150 0.010 0.009 0.050 91.56 -

ADIMRE Construction 25534 Imus LTO District Office Building Project 05/10/14 DOTC 8.124 180 C 0.458 0.200 0.300 - - - 95.80 95.80% Very Satisfactory

Adimre CONSTRUCTION 25534 Tuguegarao LTFRB Regional Office Project 02/05/14 DOTC 4.981 150 C 0.470 0.200 0.300 - - - 96.95 96.95% Outstanding

Adimre Construction 25534 Cagayan de Oro LTFRB Reg'l Office Development Project 01/28/14 DOTC 1.886 120 C 0.497 0.200 0.300 - - - 99.65 99.65% Outstanding

Adimre Construction 25534 Const. of Three Storey Six CL Sch. Bldg. Tibagan NHS 08/14/13 III 7.027 180 O 0.326 0.240 0.150 0.030 0.047 0.033 82.60 -

Adimre Construction 25534 Const. of Drainage Canal along Pulilan-Calumpit Rd. 11/30/12 III 11.886 180 C 0.444 0.200 0.300 - - - 94.40 92.22% Very Satisfactory

Adimre Construction 25534 Const. of Drainage Canal along Pulilan-Calumpit Rd., Pulilan Section Km. 46+000-Km. 47+200 08/02/12 III 11.886 170 O 0.376 0.283 0.150 0.022 0.060 0.050 94.10 -

Adimre Construction 25534 Const./Rehab. of MPB of Basilica Minore (Historical Landmark) 03/18/13 III 1.895 72 C 0.445 0.133 0.300 - - - 87.80 87.80%

Satisfactory

Adimre Construction 25534 Boac, LTO District Office Development Project 09/04/13 DOTC 1.953 90 C 0.388 0.200 0.300 - - - 88.81 88.81% Satisfactory

Adimre Construction 25534 San Fernando, Pampanga LTFRB Regional Office Project 10/23/13 DOTC 3.284 120 C 0.496 0.133 0.300 - - - 92.86 92.86% Very Satisfactory

Adimre Construction 25534 Buenavista, Guimaras PCG Detachment 12/11/13 DOTC 2.016 120 C 0.492 0.200 0.000 - - - 69.17 69.17% Poor

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page11

Page 12: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

ADIMRE CONSTRUCTON 25534 Malolos Port Development Project 01/22/15 DOTC 9.625 180 C 0.471 0.200 0.300 - - - - 93.76% Very Satisfactory

ADIMRE CONSTRUCTON 25534 Balagtas Port Development Project 01/28/15 DOTC 7.802 180 C 0.473 0.177 0.300 - - - - 93.69% Very Satisfactory

ADIMRE CONSTRUCTON 25534 Meycauayan Port Development Project 01/29/15 DOTC 8.300 150 C 0.452 0.200 0.300 - - - - 93.45% Very Satisfactory

ADIMRE CONSTRUCTON 25534 Obando Port Development Project 02/26/15 DOTC 8.109 268 C 0.469 0.200 0.300 - - - - 92.00% Very Satisfactory

ADMIRE CONSTRUCTION 25534 Meycauayan Port Development Project 07/09/14 DOTC 8.300 150 O 0.385 0.300 0.150 0.020 0.035 0.033 92.30 -

ADP Construction & Supply 3466 Const. of Sta. Barbara Catching DAM and Canal Struc. 04/05/14 NIA 16.962 150 O 0.327 0.245 0.150 0.018 0.032 0.050 82.20 -

ADP Construction & Supply 3466 Const. of Various CIP's Package 1 - Badbaran CIP 04/13/13 NIA 24.770 210 O 0.348 0.249 0.150 0.000 0.027 0.050 82.40 -

ADP Construction & Supply 3466 Improvement of NIA-Region VI Office 11/15/13 NIA 13.825 112 C 0.273 0.300 0.300 - - - 87.34 87.34% Satisfactory

ADROIT CONSTRUCTION 11169Preventive Maintenance of San Jose City-Rizal Road via Pinili-Porais Villa Joson, KO160+(-827) to KO160+000;

KO161+300 to KO161+91711/21/2014 III 9.864 75 C 0.499 0.133 0.300 - - - 93.20% 93.20%

Very Satisfactory

Adroit Construction 11169Preventive Maintenance of San Jose City-Rizal Road via Pinili-Porais-Villa Joson, KO 160+(-827) to KO160+000;

KO161+300 to KO161+9179/25/2014 Special 3 14.894 75 C 0.465 0.133 0.300 89.80 89.80%

Very Satisfactory

Adroit Construction 11169 Repair/Rehab./Impv't. of San Jose-Lupao Rd., K0160+464.10-K0162+356.80 08/13/13 III 9.305 35 C 0.412 0.133 0.300 - - - 84.50 84.50%

Satisfactory

Advance Foundation Const. System Corp. / Abulug Developer

Builders Const. Inc. (JV)JV-09-289 Const. of Gov. Edgar R. Lara Bridge along Cagayan-

Apayao Road 03/30/11 II 112.029 240 O 0.360 0.300 0.000 0.023 0.051 0.017 75.10 -

ADVANCE TECH CONSTRUCTION & TRADING CORP. 35288 Cabucgayan Seaport Construction 08/11/15 DOTC 8.606 240 O 0.400 0.300 0.150 0.015 0.029 0.050 94.42 -

ADVANCE TECH CONSTRUCTION & TRADING CORP. 35288 Placer Port Development Project 09/15/15 DOTC 8.490 90 C 0.496 0.200 0.300 - - - 99.63 99.63%

Outstanding

ADVANCE TECH CONSTRUCTION & TRADING CORPORATION 35288 Brgy. Ruben Ecleo, Sr. Wharf Development Project 10/14/14 DOTC 4.588 90 C 0.500 0.200 0.150 - - - 85.00 85.00%

Satisfactory

ADVANCE TECH CONSTRUCTION & TRADING CORPORATION 35288 Zamboanga Airport Development Project 07/17/14 DOTC 5.739 161 C 0.433 0.200 0.300 - - - 93.27 93.27%

Very Satisfactory

Advance Tech Construction & Trading Corporation 35288 Guimbal Port Development Project 06/04/14 DOTC 1.988 75 C 0.469 0.200 0.300 - - - 96.90 96.90%

OutstandingAdvance Tech Construction &

Trading Corporation 35288 Lubang Port Development Project 06/19/14 DOTC 4.089 120 C 0.463 0.200 0.300 - - - 96.30 96.30% Outstanding

ADVANCE TECH CONSTRUCTION & TRADING CORPORATION 35288 Mercedes Port Development Project 03/05/14 DOTC 7.158 120 C 0.441 0.200 0.300 - - - 94.10 94.10%

Very Satisfactory

Advanced Foundation - IBC (JV) JV-09-265 Replacement of E. Marcos Bridge Km.28+310 along Maasin-Cabatuan Road (Over Tigan River) 03/20/12 VI 162.908 460 C 0.489 0.200 0.300 - - - 98.90 92.72%

Very SatisfactoryADVANCED FOUNDATION CONSTRUCTION SYSTEM

CORP./PULSAR CONSTRUCTION (JV)

JV-13-601Construction and Maintenance of Bridges along National

Roads - Construction of Bridges - On going; Lucban Bridge along Manila North Road

10/22/2014 II 253.267 650 O 0.456 0.225 0.150 0.030 0.033 0.033 92.70% 92.70% Very Satisfactory

Advanced Foundation Construction System Corporation 15449 Lucban Bridge & Approaches Phase I along Manila North

Road 8/6/2014 II 146.442 450 C 0.500 0.133 0.300 93.30 91.14% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page12

Page 13: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Advanced Foundation Construction System, Corp. 15449 Lucban Bridge & Approaches Phase I along Manila North

Rd. 08/01/13 II 153.067 450 O 0.328 0.300 0.150 0.030 0.056 0.033 89.70 -

Advanced Matrix Construction Incorporated 32873

Proposed Renovation of Executive Offices Located at 2nd Flr & 5th Flr, 5-Storey Building and 3rd Flr, Multi-Storey

Building (Phase II)12/03/13 BPS 13.785 120 C 0.484 0.200 0.300 - - - 98.40 98.40%

Outstanding

Advanced Matrix Construction Incorporated 32873 Rehabilitation of Building B Lighting System 10/08/13 BPS 2.000 60 O 0.346 0.279 0.150 0.030 0.035 0.050 89.00 -

Advanced Matrix Construction Incorporated 32873 Rehabilitation of Building B Lighting System 06/04/14 BPS 2.000 60 C 0.341 0.195 0.165 - - - - 83.30%

Satisfactory

Advanced Matrix Construction, Inc. 32873 Installation of New Air-Handling Units and Upgrading/ Rehabilitation of SPC Male and Female Lockers 09/26/14 BSP 12.322 174 C 0.474 0.200 0.284 - - - 95.80 95.80%

Very Satisfactory

Advanced Matrix Construction, Inc. 32873 New Roofing System for Building E Roofdeck 11/19/14 BSP 22.300 120 O 0.389 0.300 0.071 0.020 0.030 0.025 83.50 -

Advanced Matrix Construction, Incorporated

Improvement of BSP-SPC Parking Lot at BSP Security Plant Complex 01/13/14 BSP 13.800 180 C 0.499 0.132 0.300 - - - 93.10 88.83%

Satisfactory

Advanced Matrix Construction, Incorporated

Improvement of BSP-SPC Parking Lot at BSP Security Plant Complex 03/31/13 BSP 13.800 180 O 0.399 0.190 0.150 0.030 0.051 0.050 87.00 -

AEJ Hardware Construction & Enterprises 34740

Repair/Rehab. of Licomo Failed Rd. Shoulder along Maria Clara Lobregat H-way (Pagadian ZC Rd.), Km.1851+500-

Km.1851+60008/06/13 IX 1.883 60 C 0.370 0.200 0.300 - - - 87.00 84.30%

Satisfactory

AEJ Hardware Construction & Enterprises 34740

Repair/Rehab. of Licomo Failed Rd. Shoulder along Maria Clara Lobregat Highway (Pagadian-ZC Rd.), K1851+500-

K1851+60003/11/13 IX 1.880 64 O 0.363 0.240 0.124 0.030 0.035 0.033 82.50 -

AFG CONSTRUCTION 17161 Development of Dagsaan Eco-Park 04/24/14 TIEZA 4.708 90 C 0.452 0.189 0.300 94.23 94.23% Very Satisfactory

AFG Construction Development of Dagsaan Eco-Park 02/27/14 TIEZA 4.709 90 C 0.453 0.190 0.300 - - - 94.23 94.23% Very Satisfactory

AFG CONSTRUCTION AND CONSTRUCTION SUPPLY 17161 Odiong - Sibalom - San Remigio - Leon Road Upgrading

(Gravel to Paved) Km. 129+328 -km. 131+275 8/13/2014 VI 42.621 239 C 0.377 0.200 0.300 87.70 84.64% Satisfactory

Agafer Construction 7912 Dummun River Irrigation System, Cagayan - Batanes IMO, Region 2 PIDP2-C-DRISN-2 04/26/14 NIA 12.184 521 C 0.392 0.200 0.300 - - - 89.21 89.21%

SatisfactoryAgafer Construction 7912 Const. of Cagayan River Control 11/11/08 II 14.241 240 O 0.318 0.160 0.030 0.030 0.033 0.133 70.40 -

Ahnex Builders & Ready Mix Corporation 32296 Widening of Cavite-Batangas Rd., Km.22+000-Km.23+653 08/14/13 IVA 30.797 369 C 0.341 0.200 0.300 - - - 84.10 85.42%

Satisfactory

Ahnex Builders & Ready Mix Corporation 32296

Widening of Governor's Drive (Carmona-Dasmariñas-TMC Rd.) inc. Drainage System (RROW acquisition), Km.39+508-

Km.46+625.50, 5th LD11/24/12 IVA 38.813 222 C 0.458 0.200 0.300 - - - 95.80 90.22%

Very Satisfactory

Ahnex Builders & Ready Mix Corporation 32296 Widening of Cavite-Batangas Rd., Km.22+000-Km.23+653 11/23/12 IVA 30.797 369 O 0.352 0.300 0.106 0.022 0.050 0.033 86.30 -

Ahnex Builders & Ready Mix Corporation 32296 Widening of Governors Drive (Carmona-Dasmariñas-Trece

Martires City Rd.) inc. Drainage System 08/15/12 IVA 38.813 190 O 0.366 0.300 0.081 0.030 0.055 0.033 86.50 -

Al Chris Construction 12406 PW-BHL-13-07 Emergency Repair & Rehabilitation of Rizal (Catigbian)- Causwagan Sur (SAN ISIDRO) 05/15/15 Bohol 13.298 288 C 0.447 0.200 0.300 - - - 94.70 94.70% Very

Satisfactory

AJ TAYLAN CONST, CORP/DJCM CONST/VVH CONST, CORP/ZEDIK

BUILDERS (DAVZ JV)JV-13-702

Construction and Maintenance of Bridges along National Roads-Widening of Permanent Bridges, Subec Bridge

along MNR10/21/2014 I 36.706 304 O 0.330 0.249 0.150 0.030 0.056 0.050 86.50% 86.50%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page13

Page 14: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Ajan Jaeda, inc. 17869 Corollary Works for Banquerohan Resettlement Project, Ph. 2 9/14-18/09 NHA 30.991 150 O 0.398 0.245 0.015 0.024 0.070 0.050 80.15 -

Ajan Jeada, Inc (Formerly: Jeada Construction) 17869 Const. of Coastal Protection (Sampalro-Mahingan-Cabid-

an Sect.) 03/16/13 V 14.119 150 C 0.470 0.133 0.300 - - - 90.30 87.48% Satisfactory

Ajan Jeada, Inc (Formerly: Jeada Construction) 17869 Repair/Impv't of DM Jct. Legazpi-Sto.Domingo-Tabaco-

Cam. Sur Rd., K0529+944.45-K0530+966.79 w/ exception 03/16/13 V 9.252 90 C 0.422 0.200 0.200 - - - 82.20 82.20% Satisfactory

Ajan Jeada, Inc. 17869 Impv't. of Bahi-Cagubulacao Rd. (Cagraray Eco Park) 08/03/11 V 18.989 221 O 0.317 0.300 0.150 0.030 0.045 0.033 87.50 -

Ajan Jeada, Inc. (Formerly: Jeada Construction) 17869 Completion of Pili Bridge along DM Jct. Legazpi-Sto-

Domingo-Tabaco-Camarnes Sur Bdry. Rd. 08/10/13 V 15.215 180 C 0.426 0.133 0.300 - - - 85.90 85.90% Satisfactory

Ajan Jeada, Inc. (Formerly: Jeada Construction) 17869

Rehab./Reconst. of Damaged Paved Nat'l Road Legazpi City, Km.559+468-Km.559+698, Km.559+849-Km.560+000,

Km.560+716-Km.561+005, Km.565+520-Km.565+100003/16/12 V 17.070 240 C 0.450 0.141 0.300 - - - 89.10 83.04%

Satisfactory

Ajan Jeada, Inc. (Formerly: Jeada Construction) 17869 Upgrading of Asphalt to Concrete of Ariman Jct.-Bulusan

Lake Rd. (K0628+660-K0629+360) 08/03/12 V 13.292 140 C 0.420 0.133 0.300 - - - 85.30 88.96% Satisfactory

AJYSC MARKETING 26924 Widening of Midsayap - Marbel Road, K1780+128 - K1780+528 8/5/2014 XII 9.533 110 C 0.450 0.200 0.300 95.00 95.00%

Very Satisfactory

AJYSC MARKETING 26924Rehab./Reconst./Replacement /Retrofitting of Existing

Permanent Bridges, London Bridge along Makar - Kiamba Road

8/16/2014 XII 8.576 102 C 0.500 0.133 0.300 93.30 93.30% Very Satisfactory

AJYSC Marketing 26924 Construction of Perimeter Fence & Gates 10/30/14 DOST 9.342 120 C 0.432 0.200 0.300 - - - 93.23 94.30% Very Satisfactory

AJYSC Marketing 26924 Completion of Dormitory BLDG. I-PH2 02/03/15 DOST C 0.480 0.190 0.300 - - - 97.00 83.91% Satisfactory

AJYSC Marketing 26924 Completion of Drainage Canal along Dulawan-Marbel Rd. (New Carmen Sect.) 08/17/13 XII 17.419 256 C 0.391 0.200 0.300 - - - 89.10 85.68%

Satisfactory

AJYSC Marketing 26924 Nat'l Rds. Traffic Decongestion: Widening of Marbel-Cotabato Rd. 03/19/13 XII 38.138 323 C 0.433 0.133 0.300 - - - 86.60 88.88%

Satisfactory

AJYSC Marketing 26924 Completion of Drainage Canal along Dulawan-Marbel Rd. (New Carment Sect.) 03/11/13 XII 17.419 214 O 0.364 0.300 0.000 0.030 0.050 0.033 77.70 -

AJYSC Marketing 26924Road Upgrading (Gravel to Concrete) along Surallah-Lake Sebu-Maitum Road, Km.1756+000-Km.1757+153, Realigned

to Km.1758+607-Km.1769+097.42 w/ exception03/28/12 XII 22.657 215 C 0.435 0.133 0.000 - - - 56.80 74.44%

Poor

AJYSC Marketing 26924 Const./Replacement of Banga Bridge and Approaches Phase II 03/08/10 XII 24.657 240 O 0.350 0.240 0.150 0.030 0.040 0.033 84.30 -

AJYSC Marketing 26924 Rehab./Improvement of Bulok Bridge along Marbel-Makar Road 06/05/09 R-XII 4.764 90 O 0.271 0.300 0.150 0.030 0.059 0.050 86.00 -

AJYSC Marketing 26924Road Upgrading (Gravel to Concrete), Based on Gravel

Road Strategies/HDM-4, Dulawan-Marbel Road, Km.1747+817- Km.1748+512

03/27/12 XII 13.000 165 C 0.431 0.133 0.300 - - - 86.40 87.42% Satisfactory

AJYSC Marketing 26924

Repair/Rehab. of Rd. Slip along Malalag-Malita-JAS Road, Malalag-Malita Sect., Km.1599+670-Km.1599+690;

Km.1600+300-Km.1600+330; Km.1632+860-Km.1632+890; Km.1633+060-Km.1633+080; Km.1634+060-Km.1634+100

11/21/12 XI 18.567 240 C 0.428 0.133 0.300 - - - 86.10 85.50% Satisfactory

AJYSC Marketing 26924 Nat'l Rds. Traffic Decongestion: Widening of Marbel-Midsayap Rd., K1789+200-K1785+200, w/ Exception 11/25/12 XII 28.275 239 C 0.442 0.133 0.300 - - - 87.50 87.68%

Satisfactory

AJYSC Marketing 26924 Completion of Drainage Canal along Dulawan-Marbel Rd., New Carmen Sect. 11/24/12 XII 17.419 214 O 0.359 0.300 0.102 0.030 0.055 0.000 84.60 -

AJYSC Marketing 26924 Completion of Drainage Canal along Dulawqan-Marbel Rd. (New Carment Sect.) 08/08/12 XII 17.419 196 O 0.386 0.300 0.085 0.030 0.045 0.033 87.90 -

AKH CONSTRUCTION AND TRADING CORPORATION 20579 Construction of Parañaque River Diversion Channel

(Phase I), Barangay Moonwalk 11/18/2014 NCR 17.347 190 C 0.321 0.200 0.300 - - - 82.10% 82.10% Satisfactory

AKH CONSTRUCTION AND TRADING CORPORATION 20759 Proposed Construction of Multi-Purpose Building, Zone

100 11/20/2014 NCR 5.232 90 C 0.439 0.133 0.300 - - - 87.20% 87.20% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page14

Page 15: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

AKH CONSTRUCTION AND TRADING CORPORATION 20759 Proposed Repair/Rehabilitation of Road along Jalandoni

St., CCP Complex 11/20/2014 NCR 8.100 116 C 0.493 0.133 0.300 - - - 92.60% 92.60% Very Satisfactory

AKH CONSTRUCTION AND TRADING CORPORATION 20759

Preventive Maintenance Based on Pavement Management System/Highway Development and Management-4 (HDM-4)

along V. Mapa Street11/24/2014 NCR 22.598 206 O 0.381 0.240 0.150 0.030 0.045 0.033 87.90% 87.90%

Satisfactory

AKH CONSTRUCTION AND TRADING CORPORATION 20759 Proposed Repair/Rehab. Of Road along Jalandoni St.,

CCP Complex 8/17/2014 NCR 8.100 90 OG 0.446 0.215 0.150 0.030 0.040 0.030 91.10 -

AKH Construction and Trading Corporation 20759

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. (Int. Sect.) of Mendiola Extension (Chainage 0000-

Chainage 0119, A) Prev. Maint. (Int. Sect.) of Mendiola (Chainage 0119-085)

03/13/13 NCR 2.678 69 O 0.366 0.200 0.150 0.030 0.048 0.033 82.70 -

AKN CONSTRUCTION CORPORATION (Formerly: AKN

Construction)11845 Slope Protection of Estero Tripa De Gallina, Barangay

Bangkal 11/19/2014 NCR 17.321 150 O 0.357 0.300 0.059 0.030 0.049 0.050 84.50% 84.50% Satisfactory

AKN Construction Corporation (Formerly: AKN Construction) 11845 Const. of Flood Control Wall along Meycauayan River 03/18/13 NCR 31.251 162 C 0.425 0.138 0.300 - - - 86.30 85.88%

SatisfactoryAKN Construction Corporation (Formerly: AKN Construction) 11845 Widening/Conc. of R-10 inc. ROW, (Const. of Footbridge at

corner Pacheco) 04/15/11 NCR 17.977 248 O 0.371 0.296 0.150 0.030 0.035 0.050 93.20 -

AKN Construction Corporation (Formerly: AKN Construction) 11845 Rehab./Reconstruction of Muntinlupa Insular Prison Road

and its Vicinity, Brgy. Poblacion 09/09/09 NCR 19.113 100 O 0.297 0.219 0.150 0.023 0.035 0.050 77.40 -

AKN Construction Corporation (Formerly: AKN Construction) 11845

Cluster 111: Asphalt Overlay of Zapote-Alabang, (S03271LZ), D=50mm, K0023 -K0023+535, K0024+640-

K0024+819 (E.B.) & K0024+859-K0025+09808/03/12 NCR 9.208 30 C 0.426 0.200 0.300 - - - 92.60 87.44%

Satisfactory

AKN Construction Corporation (Formerly: AKN Construction) 11845 Impv't. of Earthdike along Meycauayan River 03/18/13 NCR 4.474 120 C 0.417 0.133 0.300 - - - 85.00 85.00%

Satisfactory

AL Chris Construction 12406 BERRRP-Candumayao (Catigbian) - Cabanugan (San Isidro) rd. 01/19/15 Bohol 8.874 209 O 0.338 0.300 0.066 0.030 0.051 0.050 83.50 -

AL Hussein Construction 18438Road Upgrading (gravel to paved) based on Gravel Rd.

Strategies/HDM-4 @ Jct. SH Aglayan-Alanib Ticalaan Rd. (Aglayan-Basak) Km.1520+479-Km.1522+247

03/31/12 X 35.522 278 C 0.438 0.133 0.181 - - - 75.20 70.22% Poor

Al Hussein Construction 18438Rd. Upgrading (Gravel to Paved), Jct. SH Aglayan-Alanib-

Ticalaan Rd. (Aglayan-Basak), Bugkaon Sect., Km.1519+1015-Km.1520+479

08/10/12 X 11.334 120 C 0.340 0.200 0.300 - - - 84.00 84.54% Satisfactory

AL HUSSEN CONSTRUCTION 18438 Reconstruction of Narciso Ramos Highway, Raising of Grade with Drainage Improvement, K1919+000 - K1921+400 6/5/2014 X 95.090 244 C 0.356 0.200 0.300 85.60 85.60%

Satisfactory

Al Niño Const. & Supply Const. of One-Unit, Three-Seater Toilet with Handwashing Facility and Septic Vault at Mayon NHS 8/13/2014 V 0.311 120 C 0.395 0.152 0.300 84.70 84.70%

Satisfactory

AL NINO CONSTRUCTION & SUPPLY 18378 CONSTRUCTION OF TONDOL CIP 04/17/15 NIA 9.357 240 C 0.446 0.133 0.300 - - - - 87.98%

SatisfactoryAL NIÑO CONSTRUCTION &

SUPPLY 18378 Cluster II-Concreting of Dinapa-Tomalaytay Road 11/5/2014 V 4.825 75 C 0.436 0.133 0.300 - - - 86.90% 86.90% Satisfactory

AL NIÑO CONSTRUCTION AND SUPPLY 18378

Repair /Rehab./Improvement (Additional Pavement) Along Daang Maharlika K0547+960-K0548+560 with exceptions

Salvacion - Del Rosario, Pilar, Sorsogon11/5/2014 V 13.050 135 C 0.460 0.133 0.300 - - - 89.30% 89.30%

Very Satisfactory

Al-B Construction 11740 Rehab./Reconst./Upgrading along Angeles-Porac-Floridablanca-Dinalupihan Rd. 06/01/10 III 18.839 90 O 0.389 0.240 0.150 0.030 0.047 0.033 88.90 -

AL-B DEV'T CORP. / PING-ANN'S CONSTRUCTION AND TRADING

(JV)JV-14-075 Reconstruction of Loboc River Terminal 6/24/15 TIEZA 19.550 240 O 0.375 0.300 0.097 0.030 0.070 0.050 92.10 -

Alberto Uy Construction & Development 20924 Construction/Rehabilitation of Flood Control, Mapang

River Control, Bongabong, Oriental Mindoro 8/13/2014 IV-B 9.111 135 C 0.400 0.133 0.300 83.30 83.30% Satisfactory

Alberto Uy Construction & Development 20924 Const. of Quinabigan Flood Control 07/31/13 IVB 9.099 165 C 0.453 0.133 0.300 - - - 88.60 88.60%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page15

Page 16: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Alberto Uy Construction & Development 20924

Const./Impvt. of Bongabong River Control (Upstream of Abutment "A" of Orconuma Bridge), Brgy. Orconuma

along Bongabong-Sagana-Roxas-San Aquilino Rd.03/20/13 IVB 8.037 175 C 0.380 0.193 0.300 - - - 87.30 87.54%

Satisfactory

Alberto Uy Construction & Development 20924 Repair/Rehab. of Bansud River Control 08/08/12 IVB 3.396 115 C 0.396 0.200 0.300 - - - 89.60 84.26%

SatisfactoryALBERTO UY CONSTRUCTION AND 

DEVELOPMENT                         20924 Construction of Cagancan River Control 11/27/2014 IV 9.108 112 C 0.441 0.133 0.300 - - - 87.40% 87.40% Satisfactory

Alcatrem Construction Corporation 31834 Reapir/Rehab./Impv't. of Pulilan-Calumpit Rd. (Pulilan Sect.) 03/18/13 III 9.431 60 C 0.396 0.133 0.300 - - - 82.90 82.90%

Satisfactory

ALCEL CONSTRUCTION 15129Road Upgrading (Gravel - Paved) along Gurel-Bokod-

Kabayan-Buguias-Abatan Road, K0338+481 - K0339+838, Kabayan, Benguet

11/19/2014 CAR 46.461 270 C 0.371 0.200 0.300 - - - 87.10% 87.28% Satisfactory

ALCEL CONSTRUCTION 15129Upgrading of Ambiong-Lubas-Tawang Road leading to Mt.

Kallogong, Stone Church, Bahong Roase Garden & Strawberry Fields

11/20/2014 CAR 44.617 240 C 0.431 0.133 0.300 - - - 86.40% 86.40% Satisfactory

ALCEL CONSTRUCTION 15129Road Upgrading (Gravel-Paved) Along Gurel-Bokod-

Kabayan-Buguias-Abatan Road, K0338+481-K0339+838, Kabayan, Benguet

8/14/2014 CAR 46.461 240 OG 0.361 0.240 0.150 0.023 0.050 0.050 87.40 -

ALCEL CONSTRUCTION 15129Off-Carriageway Improvement (Paving of Shoulders-Seal Widening), Butaun City-Cagayan de Oro City-Iligan City

Road, Magsaysay Section, Misamis Oriental8/11/2014 X 18.418 138 C 0.477 0.200 0.300 97.70 97.70%

Outstanding

Alcel Construction 15129 Asphalt Overlay along Kennon Rd. K0227+458-K0228+081 07/30/13 CAR 3.737 16 C 0.459 0.133 0.300 - - - 89.20 89.20% Very Satisfactory

Alcel Construction 15129 Prev. Maint. of Pangasinan-La Union Rd. K0379+615-K0381+030 08/06/13 I 17.301 120 C 0.493 0.133 0.300 - - - 92.60 92.60%

Very Satisfactory

Alcel Construction 15129 Const. of Access Rd. to Airport, Alaminos City Airport 08/07/13 I 1.821 45 C 0.486 0.133 0.300 - - - 91.90 91.12% Very Satisfactory

Alcel Construction 15129 Const. of Access Rd. to Airport, Alaminos City Airport 03/15/13 I 1.821 45 O 0.390 0.300 0.150 0.010 0.023 0.033 90.60 -

Alcel Construction 15129 Rehab. of Carlos P. Romulo Bridge 03/14/13 I 31.658 320 C 0.463 0.133 0.300 - - - 89.60 90.08% Very Satisfactory

Alcel Construction 15129Rehab./Reconst. of Damaged Pvt. along Baguio-Bontoc

Rd. (Concrete Reblocking along Baguio-Bontoc Rd.) K0297+000-K0299+000

03/14/12 CAR 8.112 180 C 0.352 0.200 0.300 - - - 85.20 83.88% Satisfactory

Alcel Construction 15129 Const. of Access Rd. for Alaminos Airport (Phase I) 11/30/12 I 17.991 267 C 0.392 0.200 0.300 - - - 89.20 88.60% Satisfactory

Alcel Construction 15129Prev. Maint. along Baguio-Bontoc (Concrete Reblocking)

w/ Overlay along Baguio-Bontoc Rd., K0282+000-K0286+000

08/02/12 CAR 13.811 64 C 0.409 0.200 0.000 - - - 60.90 67.86% Poor

Alcel Construction 15129 Const. of Access Rd. for Alaminos Airport (Phase I) 08/16/12 I 17.991 253 O 0.384 0.240 0.150 0.030 0.045 0.033 88.20 -

Alcel Construction 15129 Widening of CDO-Airport Road, Upper Balulang Sect. 08/23/12 X 17.351 240 C 0.373 0.133 0.300 - - - 80.60 82.22% Satisfactory

Alcel Construction 15129 Repair/Rehab./Impv't. of Manila North Rd., Km.203+000-Km.203+447, w/ exceptions 03/13/13 I 4.937 25 C 0.464 0.133 0.300 - - - 89.70 89.70%

Very Satisfactory

Alcel Construction/Oriental Sales Center and Contractor (J.V.) JV-12-432 Prev. Maint. of Manila North Rd. K0169+700-K0172+105 w/

exception w/n the District 08/09/13 I 34.285 150 O 0.345 0.300 0.150 0.030 0.047 0.033 90.50 -

ALE BUILDERS CONSTRUCTION & DEVELOPMENT CORP. 5180 Proposed Rehabilitation of F.B. Harrison Road Street with

Drainage Improvement Sta. 0+000 - Sta. 0+791 8/16/2014 NCR 23.561 289 C 0.397 0.186 0.300 88.30 88.30% Satisfactory

Ale Builders Construction & Development Corp. 5180 Proposed Rehab./Const. of MPB at J. Lukban Elem.

School, Apacible St. 03/13/13 NCR 4.800 180 C 0.493 0.192 0.300 - - - 98.50 88.56% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page16

Page 17: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Ale Builders Construction & Development Corp. 5180

Proposed Assets Preservation of Nat'l Roads Generated from Pav't. Mgt. System/ Highway Dev't. & Mgt.-4 (HDM-4),

Taft Ave.: Km. 0004+1569.30-Km.0006+384)03/19/12 NCR 5.005 30 C 0.356 0.200 0.300 - - - 85.60 86.74%

Satisfactory

Ale Builders Construction & Development Corp. 5180 Proposed Repair/Rehab./Const. of MPB, San Andres

Sports Complex 03/19/12 NCR 5.783 120 C 0.252 0.030 0.300 - - - 58.20 76.68% Unsatisfactory

ALEBON GENUINE MERCHANDISING 26300 Widening of Butuan City - Cagayan de Oro City - Iligan City

Road Km. 1425+500 - Km. 1426+500 10/25/2014 X 20.000 221 C 0.433 0.137 0.166 - - - 73.60% 86.62% Satisfactory

ALEBON GENUINE MERCHANDISING 26300 Widening of Butuan City - Cagayan de Oro City - Ilagan

City Road Km1425+500 - Km.1426+500 8/4/2014 X 18.578 191 OG 0.383 0.300 0.150 0.030 0.040 0.050 95.30 -

ALEBON GENUINE MERCHANDISING 26300 Construction of Concrete Revetment along Kinoguitan By-

Pass Road 8/11/2014 X 13.482 210 OG 0.383 0.300 0.150 0.030 0.047 0.033 94.30 -

Alebon Genuine Merchandising 26300 Widening of Carmen-Patag-Bulua Rd., Bulua-Patag Sect., Km.1443+550.49-Km.1443+810.85 w/ exception 08/11/13 X 4.201 67 C 0.427 0.133 0.300 - - - 86.00 86.12%

Satisfactory

Alebon Genuine Merchandising 26300 Widening of Carmen-Patag-Bulua Rd., Bulua-Patag Sect. 03/11/13 X 4.198 37 O 0.371 0.244 0.150 0.010 0.037 0.050 86.20 -

Al-Fahdel Const. and Eng'g 17953 Conc./Impvt. of Tubod-Ganassi Road (Caniogan Sect.) Sta. 1602+000-Sta. 1603+000 with exception 06/05/09 X 18.126 150 O 0.344 0.265 0.150 0.015 0.043 0.050 86.70 -

Al-Fahdel Const. and Eng'g. 17953 Repair/Rehab. of Rd. Slip (down) along Dobleston-Butadon Nat'l Rd. (Secondary Rd.), K2007+860-K2007+900 11/28/12 X 3.790 59 O 0.363 0.226 0.150 0.030 0.023 0.033 82.50 -

Al-Fahdel Const. and Eng'g. 17953Rehab./Reconst./Upgrading of LDNICR, (IS) Sta.1527+(-

567)-Sta.1527+153; Sta.1531+936-Sta.1532+106, Brgy. Tubod

08/18/12 X 13.158 180 C 0.396 0.200 0.300 - - - 89.60 88.76% Satisfactory

Alfalfa Construction 29712 Road Upgrading of Banaue-Hungduan Benguet Bdry. Road Hapao-Abatan Section 04/08/11 CAR 16.560 177 O 0.385 0.300 0.090 0.010 0.054 0.017 85.60 -

Alfalfa Construction 29712 Const. of Munggayang Road 03/17/12 CAR 0.975 77 C 0.493 0.184 0.300 - - - 97.70 83.66% Satisfactory

Alfalfa Construction 29712Prev. Maint./Impv't. along Nva. Vizcaya-Ifugao-Mt. Province

Bdry. Rd. (Reblocking w/ Add'l. Pvmt. width) K0305+800-K0323+000, Kiangan-Lagawe

03/17/13 CAR 9.816 166 C 0.474 0.133 0.300 - - - 90.70 90.70% Very Satisfactory

ALFALFA CONSTRUCTION & WERR CORP (International) JV JV-12-313 Asphalt Overlay along Nueva Vizcaya-Ifugao-Mt. Province

Bdry Road, K0315+800 to K0318+000, Lagawe, Ifugao 8/5/2014 CAR 32.240 56 C 0.487 0.133 0.300 92.00 92.00% Very Satisfactory

Alfie's Const. & Const. Supply, Inc. (Formerly: Alfie's Construction &

Const. Supply)17162 Completion of Binalbagan Bridge 2 - Km. 66+910 along

Hinigaran-Isabela Road 03/05/09 VI 45.049 809 O 0.316 0.300 0.150 0.030 0.040 0.033 86.90 -

Alfie's Const. & Const. Supply, Inc. (Formerly: Alfie's Construction &

Const. Supply)17162 Road Upgrading, Jct. Palencia-Boy Scout, Campsite Road 03/05/09 VI 66.624 553 O 0.263 0.296 0.150 0.030 0.050 0.033 82.20 -

Alfie's Construction & Const. Supply, Inc. (Formerly: Alfie's Construction & Construction

Supply)

17162 Const. of Access Rd. for Himoga-an Bridge, Bacolod North Rd., Sta. 71+035.20-Sta. 74+557.20 08/12/13 VI 109.290 310 O 0.342 0.240 0.150 0.030 0.042 0.050 85.40 -

Alfie's Construction & Const. Supply, Inc. (Formerly: Alfie's Construction & Construction

Supply)

17162 Road Upgrading of Villahermoso-Canla-on City-La Castellana Road, K0074+205-K0074+995 08/10/13 VI 23.131 182 O 0.356 0.206 0.047 0.030 0.035 0.033 70.70 -

Alfie's Construction & Const. Supply, Inc. (Formerly: Alfie's Construction & Construction

Supply)

17162

Rehab./ Reconst./ Upgrading (Reblocking PCC) of Intermittent Sect. along Jct. Murcia-Cansilayan-Damsite-

Abuanan-Bago City Rd.; a) K0017+0-K0018+3 w/ exception; b) K0019+0-K0020+3 w/ exception (Cluster II)

03/27/12 VI 25.989 215 C 0.408 0.200 0.300 - - - 90.80 86.90% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page17

Page 18: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Alfie's Construction & Const. Supply, Inc. (Formerly: Alfie's Construction & Construction

Supply)

17162Reconst./Upgrading (Conc.) of Jct. Balintawak-Old

Escalante Rd. a) K0097+101-K0097+608 b) K0097+608-K0097+823, K0098+524-K0099+502 (Cluster III)

03/27/12 VI 36.721 225 C 0.413 0.200 0.300 - - - 91.30 86.80% Satisfactory

ALFIE'S CONSTRUCTION & CONSTRUCTION SUPPLY INC.

(Formerly: ALFIE'S CONSTRUCTION &

CONSTRUCTION SUPPLY

17162 Construction of the Remaining Structures : Himogan Bridge Sta. 71+035.20 to Sta. 74+557.20 8/6/2014 VI 116.246 507 C 0.344 0.200 0.300 84.40 87.04%

Satisfactory

Alfie's Construction & Construction Supply Inc.

(Formerly: Alfie's Construction and Construction Supply)

17162 Conc. of Nat'l Rd. along Bacolod South Rd. K0086+061-K0088+003 11/29/12 VI 32.631 222 C 0.415 0.149 0.300 - - - 86.40 83.88%

Satisfactory

Alfie's Construction & Construction Supply Inc.

(Formerly: Alfie's Construction and Construction Supply)

17162 Conc. of Nat'l Rd. along Bacolod South Rd., K0086+061-K0088+003 08/11/12 VI 32.631 222 O 0.242 0.300 0.150 0.030 0.050 0.050 82.20 -

Alfies Construction & Construction Supply, Inc. 17162

Conc. of Junction Bearin-Salong-Tapi-Dacongcogon-Bantayan Raod (Km. 99+675.50-Km.131+142.75 w/

exception, Brgy. Salong & Batayan09/17/09 VI 79.400 400 O 0.304 0.300 0.150 0.030 0.035 0.033 85.20 -

ALFIE'S CONSTRUCTION & CONSTRUCTION SUPPLY, INC.

(Formerly: Alfie's Construction & Construction Supply)

17162

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road Standard (HDM-4 Project Analysis - Intermittent Sections) National Secondary Road, Kabankalan Jct.

Salong Tapi Dacongcogon Bantayan Road - Package B

10/24/2014 VI 48.461 209 O 0.361 0.232 0.150 0.030 0.048 0.033 85.40% 0% Poor

Alfie's Construction & Construction Supply, Inc.

(Formerly: Alfie's Construction & Construction Supply)

17162 Const. of the Remaining Structures: Himogaan Bridge, Sta. 71+035.20-Sta. 74+557.20 08/12/13 VI 116.246 505 O 0.376 0.240 0.150 0.030 0.042 0.050 88.80 -

Alfie's Construction & Construction Supply, Inc.

(Formerly: Alfie's Construction & Construction Supply)

17162 Upgrading/Conc. of Bacolod North Rd. (Cadiz Sect.) Km.65+516-Km.68+482 03/15/13 VI 55.413 265 C 0.352 0.200 0.300 - - - 85.20 87.06%

Satisfactory

Alfie's Construction & Construction Supply, Inc.

(Formerly: Alfie's Construction & Construction Supply)

17162 Upgrading/Conc. of Bacolod North Rd., K0050+000-K0079+300 03/15/13 VI 68.793 320 C 0.356 0.200 0.300 - - - 85.60 85.00%

Satisfactory

Alfrego Builders & Supply 19284 Improvement/Riprapping of Sasa Creek Second Congressional District 06/11/09 XI 4.720 150 O 0.343 0.300 0.150 0.030 0.047 0.050 92.00 -

Algamon Construction 30704 Protection Works along Daang Maharlika, (Surigao-Ipil-Lipata Rd.) Kinabutan Bridge II, Brgy. Rizal 11/21/12 XIII 4.735 120 O 0.395 0.268 0.071 0.020 0.045 0.017 81.60 -

ALGIMAR CONSTRUCTION 15232Rehabiltation/Reconstruction/Upgrading of Paved National Roads including Drainage along Naic Junction-Caylabne

Roads11/7/2014 IV 9.282 250 C 0.334 0.200 0.300 - - - 83.40% 83.40%

Satisfactory

Algimar Construction 15232 Conc. of Parpagoha (Marigondon)-Binoog Rd., K0017+(-200)-K0017+689, K0018+324-K0019+261 08/06/13 IVB 34.422 93 C 0.366 0.200 0.300 - - - 86.60 86.60%

Satisfactory

Algimar Construction 15232 Repair of Damaged Rd. Sect. along Looc-Odiongan-San Andres Rd., Km.104+400-Km.122+400 (Int. Sect.) 08/05/13 IVB 15.860 210 C 0.381 0.200 0.300 - - - 88.10 86.24%

Satisfactory

Algimar Construction 15232 Conc. of Tablas Circumferential Road (Doña Juana-Binunga-an Section) 08/27/09 IVB 19.652 180 O 0.319 0.291 0.150 0.030 0.047 0.033 87.00 -

Algimar Construction 15232 Concreting of Tablas Circumferential Road (Hinugasan-Camantaya Section) 05/21/09 IV-B 19.298 180 O 0.312 0.236 0.150 0.030 0.040 0.033 80.10 -

Algimar Construction 15232 Const. of 1 Unit 7x7 S/B at Teofilo Tamabago E/S, Palanas South realigned to Dimasalang C/S 05/26/09 V 0.843 90 O 0.292 0.300 0.150 0.030 0.032 0.033 83.70 -

Algimar Construction 15232 Const. of Bridge Approaches @ Maingaran Bridge 02/27/09 V 9.495 87 O 0.337 0.235 0.000 0.030 0.056 0.033 69.10 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page18

Page 19: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Algimar Construction 15232 Repair of Damaged Rd. Sect. along Looc-Odiongan-San Andres Rd., Km.104+400-Km.122+400 (IS) 11/29/12 IVB 15.860 210 O 0.306 0.291 0.150 0.030 0.040 0.033 85.00 -

Algimar Construction 15232 Repair/Rehab./Impvt. along Masbate-Milagros Rd (K000+375.85-K0007+75.45) (w/ exception) 03/12/13 V 9.890 87 C 0.325 0.200 0.300 - - - 82.50 82.50%

Satisfactory

ALGIMAR CONSTRUCTION  15232 Road Upgrading ( Gravel to Paved) Quezon-Aramaywan Road, K0154+950-K0156+851.20 with Exception 11/22/2014 IV 34.958 209 O 0.360 0.240 0.130 0.030 0.054 0.050 86.40% 86.40%

Satisfactory

Algimar Construction 15232 Upgrading of Balud-Tawad-Milagros-Aroroy Road (Bangad Sect.) 08/09/11 V 96.100 360 O 0.382 0.237 0.150 0.030 0.061 0.033 89.30 -

Algon Engineering Construction Corp. 270 Construction of Overhead Water Tank with Cistern 4/29/09 DOST 3.153 124 O 0.373 0.291 0.12 0.03 0.07 0.05 93.40 -

ALGON ENGINEERING CONSTRUCTION CORPORATION 270

Preventive Maint. along Davao-Cotabato Road (Davao City-Junction Digos Section) a.) K 1538+000 - K 1538+378; b.) K

1539+004 - K 1539+987 realigned to Widening of Roads along Davao-Cotabato Road (Davao City-Junction Digos

Section) K 1535+336 - K 1536+311

10/25/2014 XI 24.089 93 C 0.432 0.132 0.300 - - - 86.40% 86.40% Satisfactory

ALGON ENGINEERING CONSTRUCTION CORPORATION 270 Preventive Maintenance - Davao - Cotabato By-Pass Road (

KO1549+622 - KO1550+286) 8/7/2014 XI 7.765 72 C 0.474 0.133 0.300 90.70 90.70% Very Satisfactory

ALGON ENGINEERING CONSTRUCTION CORPORATION 270 Widening of Davao - Bukidnon Road, Davao City, Tugbok -

Mintal Section, Km.1693+400 - Km. 1697+335.40 8/5/2014 XI 46.956 209 C 0.453 0.133 0.300 88.60 88.30% Satisfactory

Algon Engineering Construction Corporation 270

Prev. Maint. Asphalt Overlay along Davao-Cotabato Rd. (Davao City-Junction Digos Sect.) K1554+075-K1554+1010

realigned to Prev. Maint. Asphalt Overlay along Davao-Cotabato Rd. (Davao City-Jct. Digos Sect.), Sta. Cruz,

K1541+175-K1542+000

08/10/13 XI 14.222 55 C 0.411 0.133 0.300 - - - 84.40 84.40% Satisfactory

Algon Engineering Construction Corporation 270 Prev. Maint. (Int. Sect.), ABS-CBN Quimpo Blvd. Diversion

Rd., K1512+807-K1513+591 08/19/13 XI 28.470 64 C 0.343 0.200 0.300 - - - 84.30 84.30% Satisfactory

Algon Engineering Construction Corporation 270

Prev. Maint. (Int. Sect.) along Pres. Diosdado P. Macapagal National Highways a)Km.1712+000-Km.1712+802.90

b)Km.1714+016.50-Km.1714+356.8208/16/13 XI 24.973 52 C 0.439 0.133 0.300 - - - 87.20 88.16%

Satisfactory

Algon Engineering Construction Corporation 270 Widening of Davao-Bukidnon Rd., Davao City, Tugbok-

Mintal Sect., Km.1693+400-Km.1697+335.40 08/07/13 XI 46.965 209 O 0.352 0.298 0.143 0.030 0.025 0.033 88.10 -

Algon Engineering Construction Corporation 270

Prev. Maint. (Int. Sects.) along Pres. Diosdado Macapagal Highway, a)Km.1712+000-Km.1712+802.90; b)Km.1713+303-

Km.1713+815.6403/20/13 XI 24.973 52 O 0.319 0.299 0.150 0.030 0.040 0.050 88.80 -

Algon Engineering Construction Corporation 270 Widening of Davao-Bukidnon Road 03/20/13 XI 21.860 269 C 0.432 0.133 0.300 - - - 86.50 87.52%

SatisfactoryAlgon Engineering Construction

Corporation 270 Conc. of NRJ Bayugan-Calaitan-Tandag Rd. (Km.1273+491.80-Km.1281+040 w/ exception) 03/20/13 XIII 159.496 495 O 0.312 0.300 0.150 0.030 0.051 0.050 89.30 -

Algon Engineering Construction Corporation 270

Cluster 3 - Preventive Maint. along Davao-Bukidnon Rd., Davao City, a)Km.1667+820-Km.1669+00; b)Km.1671+000-

Km.1671+97503/19/12 XI 23.490 90 C 0.446 0.133 0.300 - - - 87.90 91.14%

Very Satisfactory

Algon Engineering Construction Corporation 270

Cluster 4 - Preventive Maint. along Davao-Bukidnon Rd., Davao City, a)Km.1676+000-Km.1676+910; b)Km.1681+300-

Km.1682+17003/19/12 XI 20.817 90 C 0.439 0.137 0.300 - - - 87.60 88.98%

Satisfactory

Algon Engineering Construction Corporation 270

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. along Davao-Cotabato Rd. (Davao City-Jct. Digos)

Sta.1556+000-Sta.1561+24903/24/12 XI 46.285 249 O 0.360 0.300 0.100 0.030 0.041 0.033 86.40 -

Algon Engineering Construction Corporation 270 Widening of Davao-Bukidnon Rd. 11/19/12 XI 36.342 210 C 0.479 0.133 0.300 - - - 91.20 87.90%

SatisfactoryAlgon Engineering Construction

Corporation 270 Const./Widening of Nabunturan Bridge along Maharlika Rd. 08/14/12 XI 17.267 240 C 0.411 0.200 0.300 - - - 91.10 92.54%

Very SatisfactoryAlgon Engineering Construction

Corporation 270 Widening of Davao-Bukidnon Rd. 08/17/12 XI 36.342 210 O 0.379 0.213 0.147 0.030 0.055 0.033 85.70 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page19

Page 20: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Algon Engineering Construction Corporation 270 Repair/Rehab./Impv't. of Davao-Cotabato Rd., Km.1533+(-

086)-K1541+000 w/ exception 03/16/13 XI 9.713 30 C 0.402 0.133 0.300 - - - 83.50 83.50% Satisfactory

Algon Engineering Construction Corporation 270 Asphalt Overlay/Repair & Rehab. along Digos-Makar Rd.,

Km.1564+299-Km.1564+429 w/ exceptions 03/16/13 XI 1.027 45 C 0.397 0.133 0.300 - - - 83.00 83.00% Satisfactory

Algon Engineering Construction Corporation 270 Conc. of NRJ Bayugan-Lalaitan-Tandag Rd. Km.

1273+491.80-Km. 1281+040 (w/ exceptions) 11/29/12 XIII 159.496 435 O 0.332 0.289 0.150 0.030 0.060 0.050 91.10 -

Alinab Construction & Supplies 29901 Const. of Sch. Bldg. Taboo ES 08/14/13 X 1.132 90 C 0.487 0.133 0.300 - - - 92.00 92.00% Very Satisfactory

Alinab Construction & Supplies 29901 Const. of Sch. Bldg., Dalumpinas ES 08/14/13 X 1.137 90 C 0.483 0.133 0.300 - - - 91.60 91.60% Very Satisfactory

Alinab Construction & Supplies 29901 Const. of Flood Control Dike, Sitio Lapucon Southern Pob. 08/14/13 X 1.845 105 C 0.438 0.133 0.300 - - - 87.10 87.10% Satisfactory

ALJON CONSTRUCTION & SUPPLY 34481 Construction/Maintenance of Flood Mitigation Structures

and Drainage System, Bato River Control 11/16/2014 V 4.767 121 C 0.393 0.133 0.300 - - - 82.60% 82.60% Satisfactory

Aljon Construction & Supply 34481 Construction/Maintenance of Flood Mitigation Structures and Drainage System, Viga River Control 8/14/2014 V 4.792 121 C 0.369 0.200 0.300 86.90 86.90%

Satisfactory

Aljon Construction & Supply 34481 Guinobatan Flood Control & Drainage 07/30/13 V 2.628 79 C 0.388 0.200 0.300 - - - 88.80 88.80% Satisfactory

Allado Construction Company, Inc. 073-667 Rehabilitation of Jct Sayre Highway (Kibawe) - Natulongan - Bukangliwayway Footbridge P1C 11/23/11 Bukidnon 19.145 226 O 0.310 0.290 0.090 0.030 0.060 0.050 83.00 -

ALLEN CONSTRUCTION 12584 Preventive Maintenance along Mt. Province-Nueva Vizcaya Road, K0378+362 to K0380+000 8/12/2014 CAR 17.874 97 C 0.408 0.133 0.300 84.10 84.10%

Satisfactory

Allen Construction 12584 Rehab./Reconst./Upgrading of Damaged Paved Nat'l. Rd., Nueva Ecija-Pangasinan Rd., K0166+799-K0167+827 08/13/13 III 12.483 60 C 0.431 0.133 0.300 - - - 86.40 *86.40%

Satisfactory

Allen Construction 12584 Restoration of Embankment @ D-Main & Const. of Thresher Crossing with Turn-out @ Div II Service Area 07/21/12 NIA 8.653 90 O 0.358 0.293 0.150 0.030 0.057 0.050 93.77 -

Allen Construction 12584 Concrete Pavement 07/23/13 NIA 3.966 75 C 0.438 0.200 0.300 - - - 93.75 93.75% Very Satisfactory

ALLENCON DEVELOPMENT CORPORATION 12302 Preventive Maintenance of National Secondary Road North

Capitol Road, K0000+094 to K0000+601 10/27/2014 VI 8.565 75 C 0.450 0.133 0.300 - - - 88.30% 88.30% Satisfactory

ALLENCON DEVELOPMENT CORPORATION 12302 Preventive Maintenance of National Secondary Road South

Capitol Road K0000+085 - K0000+587 10/27/2014 VI 6.118 30 C 0.434 0.133 0.300 - - - 86.70% 86.70% Satisfactory

ALLENCON DEVELOPMENT CORPORATION 12302 Const. of Coastal Protection Works along Iloilo Antique

Road K0026+700 K0027+151 8/4/2014 VI 7.301 254 C 0.392 0.200 0.300 89.20 89.20% Very Satisfactory

Allencon Development Corporation 12302 Repair & Maint.of Balasan-Carles Rd., K0174+(099)-K0174+841 08/21/13 VI 9.348 45 C 0.486 0.133 0.300 - - - 91.90 91.90%

Very Satisfactory

Allencon Development Corporation 12302 Completion of Cabasi Bridge Approaches K0030+534 08/14/13 VI 1.895 21 C 0.428 0.133 0.300 - - - 86.10 86.10% Satisfactory

Allencon Development Corporation 12302 Const. of Coastal Protection Works along Iloilo-Antique Rd. K0026+700-K0027+151 08/14/13 VI 7.301 244 O 0.269 0.300 0.150 0.030 0.037 0.050 83.60 -

Allencon Development Corporation 12302 Reconst. of Cabasi Bridge along Iloilo-Antique Rd., Km.30+534 08/14/12 VI 4.978 240 O 0.279 0.300 0.150 0.030 0.040 0.050 84.90 -

ALLEYWAY CONSTRUCTION 15310

Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects-

Construction/Rehabilitation of various Projects in Manila City 2nd LD - Rehabilitation with Drainage Improvement of

Torres Bugallon St. And Vicinity

11/24/2014 NCR 9.099 120 O 0.365 0.229 0.150 0.030 0.045 0.033 85.20% 85.20% Satisfactory

Allied Trade Resources Multi-Purpose Cooperative 31667 DOTC CARAGA Regional Office Development Project 08/27/13 DOTC 10.258 180 O 0.389 0.300 0.150 0.015 0.004 0.050 90.71 -

Allied Trade Resources Multi-Purpose Cooperative 31667 PATIN-AY LTO District Office Development Project 08/28/13 DOTC 5.147 180 O 0.391 0.240 0.150 0.015 0.030 0.050 87.64 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page20

Page 21: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Allied Trade Resources Multi-Purpose Cooperative 31667 Rehabilitation of Patin-ay LTO District Office 11/26/13 DOTC 5.147 180 C 0.374 0.190 0.300 - - - 86.43 87.27% Satisfactory

Allied Trade Resources Multi-Purpose Cooperative 31667 Const'n. & Completion of DOTC-Caraga Reg'l Pffice Bldg. 11/27/13 DOTC 10.258 180 C 0.494 0.200 0.300 - - - 99.37 99.31%

Outstanding Allied Trade Resources Multi-

Purpose Cooperative 31667 Improvement of Butuan City LTO District Office Building 11/27/13 DOTC 6.986 180 C 0.422 0.199 0.300 - - - 92.04 92.04% Very Satisfactory

Almakar Builders and Metal Works 21929 Const. of MPB in Poblacion I-A 08/14/13 IVA 0.681 135 C 0.476 0.133 0.300 - - - 90.90 89.29% Very Satisfactory

Almakar Builders and Metal Works 21929 Const. of MPB in Poblacion I-A 11/23/12 IVA 0.681 135 O 0.342 0.300 0.150 0.020 0.041 0.033 88.60 -

ALPHA RYDER CONSTRUCTION AND SUPPLIES 12197 Construction of Flood Control System, Binanuahan River 11/6/2014 V 18.931 140 C 0.398 0.133 0.300 - - - 83.10% 83.10%

Satisfactory

Alpha Ryder Construction and Supplies 12197 Construction of Flood Control System, Binanuahan River 8/12/2014 V 18.931 140 C 0.425 0.149 0.300 87.40 87.40%

SatisfactoryAlpha Ryder Construction and

Supplies 12197 Road Widening along Daan Maharlika, Brgy. Rizal-Bucalbucalan 8/13/2014 V 28.406 210 C 0.390 0.180 0.300 87.00 87.00%

SatisfactoryAlpha Ryder Construction and

Supplies 12197 Rehab./Reconst. of Damaged Paved Nat'l Rds. (Int. Sect.) along Bacon-Sawanga-Prieto Diaz Rd. 08/02/13 V 24.937 155 C 0.445 0.155 0.300 - - - 90.00 90.00%

Very Satisfactory

Alpha Ryder Construction and Supplies 12197 Rehab./Reconst. of Damaged Paved Nat.l Rds. of Bacon-

Sawanga-Pto. Diaz Rd., Pto Diaz (K0603+927.5-K0614+251) 08/15/13 V 6.207 73 C 0.400 0.184 0.300 - - - 88.40 88.40% Satisfactory

ALPIZ CONSTRUCTION AND DEVELOPMENT CORP. 11039 Drainage Improvement of Roosvelt Avenue, (K0007+940 to

K0010+811) Intermittent Section 8/14/2014 NCR 12.152 162 C 0.480 0.133 0.300 91.30 91.30% Very Satisfactory

Alraf Consruction & Enterprises 17297 Repair/Maintenance of Pamingitan Bridge #2 along Pagadian City - Zamboanga City Road 8/5/2014 IX 4.172 172 C 0.489 0.133 0.300 92.20 92.20%

Very SatisfactoryALRAF CONSTRUCTION &

ENTERPRISES 17297 Repair/Maintenance of Pamingitan Bridge #2 along Pagadian City-Zamboanga City Road 10/21/2014 IX 4.434 172 C 0.476 0.133 0.300 - - - 90.90% 90.90%

Very Satisfactory

ALRAF CONSTRUCTION & ENTERPRISES 17297

Widening of Pagadian City-Zamboanga City Road, K1931+000 to K1932+540 Realigned to K1923+460 to

K1924+26010/21/2014 IX 28.944 195 O 0.381 0.237 0.031 0.030 0.040 0.033 75.20% 75.20%

Unsatisfactory

Alraf Construction & Enterprises 17297Settled/Collapsed PCCP along Maria Clara L. Lobregat

Highway (Pagadian ZC Rd.) w/n Km.1867+000-Km.1868+000, Mangusu Sect.

08/06/13 IX 2.494 93 C 0.383 0.165 0.300 - - - 84.80 87.02% Satisfactory

Alraf Construction & Enterprises 17297 Upgrading/Concrete Paving of Nat'l Rd. along Liloy-Siocon Rd., Kipit-La Libertad-Loay-Imelda-San Roque Sect. 08/12/13 IX 64.478 285 C 0.314 0.200 0.300 - - - 81.40 82.42%

Satisfactory

Alraf Construction & Enterprises 17297 Rehab./Retrofitting of Gubawan Bridge, Basilan Circ. Rd. Isabela-Lamitan Rd. 03/13/13 IX 31.743 300 C 0.493 0.133 0.300 - - - 92.60 92.60%

Very Satisfactory

Alraf Construction & Enterprises 17297 Upgrading/Concrete Paving of Liloy-Siocon Rd., Panganuran-Mamawan Sect. 03/16/13 IX 89.452 327 C 0.453 0.133 0.300 - - - 88.60 89.14%

Very Satisfactory

Alraf Construction & Enterprises 17297Settled/Collapsed PCCP along Maria Clara L. Lobregat H-way (Pagadian ZC Road) w/n Km.1867+000 to K1868+000,

Mangusu Sect.03/12/13 IX 2.514 78 O 0.400 0.240 0.144 0.030 0.038 0.033 88.50 -

Alraf Construction & Enterprises 17297 Rehab./Const./Impvt. of Zamboanga City-Pagadian Road 05/26/09 IX 44.695 253 O 0.396 0.300 0.150 0.030 0.042 0.050 96.80 -

Alraf Construction & Enterprises 17297 Rehab./Const./Impvt. of Zambaonga City-Pagadian Road (with Intermittent Section) 09/02/09 IX 46.408 295 O 0.338 0.300 0.150 0.030 0.055 0.050 92.30 -

Alraf Construction & Enterprises 17297 Upgrading/Concrete Paving of Nat'l Rd. along Liloy-Siocon Rd., Kipit-La Libertad-Loay-Imelda San Roque Sect. 11/27/12 IX 64.478 244 O 0.264 0.300 0.145 0.030 0.059 0.033 83.10 -

Alraf Construction & Enterprises 17297 Rehab./Reconst./Reblocking of PCCP Pagadian Zamboanga City Rd. Mala-Bolong Sect. 08/31/12 IX 88.159 351 C 0.450 0.133 0.300 - - - 88.30 90.88%

Very SatisfactoryAlro Const. & Dev't. Corp. / Hi-Tone

Const. and Dev't. Corp. Joint Venture

JV-11-001 Const./Ext. of Libamanan Revetment Dike (Pob. Sect.) & Completion of Kuyapi Ring Dike 11/28/12 V 43.000 210 C 0.411 0.184 0.300 - - - 89.50 91.00%

Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page21

Page 22: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Alro Construction & Development Corporation 18361 Guicadale Road Network to International Airport, Albay

(Comun-Cotmon-Del Rosario Road Section) 8/11/2014 V 46.044 234 C 0.419 0.178 0.300 89.70 88.20% Satisfactory

Alro Construction & Development Corporation 18361 Revetment of Agos Creek 8/7/2014 V 18.424 149 C 0.350 0.200 0.300 85.00 85.00%

SatisfactoryAlro Construction & Development

Corporation 18361 Guicadale Rd. Network to Int'l Airport, Albay (Comun-Cotmon-Del Rosario Rd. Sect.) 08/11/13 V 46.044 215 O 0.362 0.245 0.150 0.030 0.052 0.033 87.20 -

Alro Construction and Development Corp. 18361 Rehab./Reconst. of Damaged Paved Nat'l Road at Comun-

Inarado-Peñafrancia Rd. 03/16/12 V 25.359 240 C 0.440 0.133 0.300 - - - 87.30 83.28% Satisfactory

ALRO CONSTRUCTION AND DEVELOPMENT CORPORATION 18361 Construction of Flood Control System, Mararag River 11/6/2014 V 10.510 120 C 0.439 0.133 0.300 - - - 87.20% 87.20%

Satisfactory

Alro Construction and Development Corporation 18361

Prev. Maint. (Asphalt Overlay) of DM. Jct. Legazpi-Sto. Domingo-Tabaco-Cam Sur Bdry. Road, K0528+000-K0

528+90007/30/12 V 6.542 45 C 0.454 0.133 0.300 - - - 88.70 89.18%

Very Satisfactory

Alro Construction and Development Corporation 18361 Upgrading of Legazpi City-Punta de Jesus Rd., K0569+970-

K0570+464 w/ exception (Bridge) 07/31/12 V 8.475 120 C 0.440 0.133 0.300 - - - 87.30 83.22% Satisfactory

Al's Enterprise and Construction 9721 Const./Rehab. of Hospital (Felipe Abrigo Memorial Hospital) 03/17/09 VIII 4.775 151 O 0.349 0.240 0.000 0.010 0.000 0.000 59.90 -

Alta Negros Industrial Supply Corporation 33806 Repair/Rehab. of Lacson Street 11/30/12 VI 6.465 145 C 0.471 0.133 0.300 - - - 90.40 87.52%

SatisfactoryAlta Negros Industrial Supply

Corporation 33806 Repair/Rehab. of Lacson Street 08/13/12 VI 6.465 145 O 0.332 0.297 0.150 0.015 0.029 0.033 85.60 -

ALXM Construction 33436 Upgrading Asphalt to Concrete of Ariman Jct.-Bulusan Lake Rd. (K0616+820-K0618+013) 08/03/12 V 13.110 135 C 0.423 0.133 0.300 - - - 85.60 84.40%

Satisfactory

ALZAM ENTERPRISES 19113Road Upgrading (Gravel/Asphalt to Concrete) of Mintal

(Davao - Bukidnon Road) Bago Oshiro - Bago Gallera (old Davao - Cotabato Road)

8/7/2014 XI 72.933 303 C 0.478 0.133 0.300 91.10 89.36% Very Satisfactory

ALZAM ENTERPRISES 19113 Widening of Davao - Cotabato Road, Davao City, Lizada Section Km.1525+920 - Km. 1527+800 8/5/2014 XI 35.389 179 C 0.435 0.133 0.300 86.80 86.92%

Satisfactory

Alzam Enterprises 19113 Const. of Davao River Flood Control Proj. 08/20/13 XI 24.180 251 C 0.419 0.133 0.300 - - - 85.20 85.20% Satisfactory

Alzam Enterprises 19113Rd. Upgrading (Gravel/Asphalt to Concrete) of Mintal (Davao-Bukidnon Rd.) Bago Oshiro-Bago Gallera (Old

Davao-Cotabato Rd.)08/21/13 XI 72.933 269 O 0.374 0.300 0.123 0.030 0.025 0.030 88.20 -

Alzam Enterprises 19113 Widening of Davao-Cotabato Rd., Davao City, Lizada Sect., Km.1525+920-Km.1527+800 08/05/13 XI 37.443 179 O 0.343 0.292 0.147 0.030 0.025 0.033 87.00 -

Alzam Enterprises 19113 Rd. Upgrading (Gravel to Paved) of Inawayan-Baracatan Rd. Km.1538+770-Km.1539+110 08/15/13 XI 6.854 85 C 0.442 0.200 0.300 - - - 94.20 84.42%

SatisfactoryAlzam Enterprises 19113 Const. of Davao River Control Proj. 03/21/13 XI 22.942 221 O 0.377 0.240 0.150 0.020 0.045 0.050 88.20 -

Alzam Enterprises 19113 Rd. Upgrading (Gravel to Paved) of Inawayan-Baracatan Rd., Km.1538+770-Km.1539+110 03/12/13 XI 6.854 55 O 0.269 0.235 0.150 0.030 0.045 0.050 77.90 -

Alzam Enterprises 19113Rehab./Reconst./Upgrading of Damaged Nat'l Rd. (IS)/

Impvt./Widening of Davao-Bukidnon Rd. leading to Phil. Eagle Foundation, Km.1698+780-Km.1701+828

11/29/12 XI 45.680 250 C 0.467 0.133 0.300 - - - 90.00 88.56% Satisfactory

Alzam Enterprises 19113 Widening of Davao-Cotabato Rd. 11/29/12 XI 43.791 250 C 0.439 0.133 0.300 - - - 87.20 86.12% Satisfactory

Alzam Enterprises 19113Road Upgrading (Gravel to Paved) I, IS of Inawayan-

Baracatan Rd.: a)Km.1536+696-Km.1536+997; b)Km.1538+498-Km.1538+650

08/16/12 XI 10.118 150 C 0.392 0.133 0.300 - - - 82.50 87.90% Satisfactory

Alzam Enterprises 19113Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. (IS)/ Imprv't./Widening of Davao-Bukidnon Rd. leading to

Phil. Eagle Foundation, Km.1698+780-Km.1701+82808/21/12 XI 45.680 250 O 0.387 0.221 0.150 0.030 0.055 0.033 87.60 -

Alzam Enterprises 19113 Widening of Davao-Cotabato Rd. 08/21/12 XI 43.791 250 O 0.292 0.287 0.150 0.030 0.045 0.050 85.40 -

ALZEN ENGINEERING & CONSTRUCTION SUPPLIES 13911

Widening of Road along Bukidnon - Cotabato - Road, Kitulaan -Manarapan Section, Carmen, Cotabato Km.

1638+000 - Km. 1640+00010/25/2014 XII 45.666 208 C 0.426 0.133 0.300 - - - 85.90% 85.90%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page22

Page 23: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Alzen Engineering & Construction Supplies 13911 Const. of Pedestrian Overpass fronting Kidapawan Pilot

Elem. School to Kidapawan City Hospital 03/26/12 XII 7.609 112 C 0.497 0.133 0.300 - - - 93.00 85.08% Satisfactory

ALZEN ENGINEERING AND CONSTRUCTION SUPPLIES 13911 Widening of Road along Bukidnon-Cotabato Road,

Kitulaan - Manarapan Section 8/11/2014 XII 45.666 193 C 0.348 0.299 0.132 0.018 0.037 0.050 88.40 88.40% Satisfactory

Ameg Construction & Supply 21556 Rehab. of Flood Control along Bulawan River, San Jose Sect. 08/12/13 V 4.667 100 C 0.463 0.133 0.300 - - - 89.60 89.60%

Very Satisfactory

Ameg Construction & Supply 21556 Const. of San Isidro-Poblacion Rd. 08/04/12 V 17.109 150 C 0.418 0.133 0.300 - - - 85.10 84.92% Satisfactory

AMIANAN CONSTRUCTION 1484 Restoration/Rehabilitation Works of Camiling RIS 08/15/15 NIA 10.894 120 C 0.432 0.115 0.300 - - - 84.71 84.71% Satisfactory

Amianan Construction 27624 Dibuluan River Irrigation Project 04/27/13 NIA 4.670 208 C 0.349 0.186 0.300 - - - 83.44 83.44% Satisfactory

ANAS CONSTRUCTION 31655 Construction of Bridge, Brgy. Parasipis, Tabaan Norte 11/20/2014 CAR 4.810 60 C 0.439 0.133 0.300 - - - 87.20% 87.20% Satisfactory

Andoni T. Dumlao Civil Engineer - Contractor 34028 Replacement of San Pedro Bridge along Daang Maharlika

(Surigao-Agusan Rd.), Brgy. San Pedro 08/08/12 XIII 14.945 375 O 0.328 0.290 0.150 0.030 0.060 0.050 90.80 -

Andoni T. Dumlao Civil Engineer - Contractor 34028

Repair/Reconst. Of Boan Bridge along Daang Maharlika (Agusan-Davao Rd.) Km.1331+632-Km.1380+775 w/

exceptions08/18/12 XIII 12.163 240 O 0.312 0.262 0.150 0.030 0.050 0.033 83.70 -

Andoni T. Dumlao Civil Engineer - Contractor 34028 Repair/Rehab. of Sianib Bridge along Daang Maharlika

(Agusan-Davao Rd.) 08/19/12 XIII 9.551 260 C 0.325 0.200 0.300 - - - 82.50 83.16% Satisfactory

ANGEL & SAM CONSTRUCTION & GENERAL MERCHANDISE 19968 Const. of 2 units, 1 Storey, 1 Classroom School Building,

Aglayan ES 10/24/2014 X 2.022 105 O 0.250 0.278 0.150 0.010 0.016 0.033 73.70% 73.70% Poor

ANGEL & SAM CONSTRUCTION & GENERAL MERCHANDISE 19968

Road Upgrading (Gravel to Paved) based on Gravel to Paved Road Strategies, Traffic Benchmark for Upgrading

to Paved Road Standard (HDM-4 Project Analysis) (Intermittent Section)

8/15/2014 X 0.983 52 C 0.461 0.200 0.300 96.10 96.10% Outstanding

Angel & Sam Construction & General Merchandise 19968 Rehab. of ICBR Puerto-Cugman Section 03/02/09 X 13.912 198 O 0.298 0.240 0.144 0.030 0.040 0.050 80.20 -

Angel & Sam Construction & General Merchandise 19968

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. Gen. from Pvt. Mgt. System/ HDM-4 (IS), CDO-Port Road;

a)Km.1438+000-Km.1439+000 b)Km.1439+000-Km.1440+00303/22/12 X 16.994 180 C 0.456 0.133 0.300 - - - 88.90 85.78%

Satisfactory

Angel & Sam Construction & General Merchandise 19968 Rehab. of Corrales Extension St. - Port Road 08/07/12 X 5.732 165 C 0.436 0.200 0.300 - - - 93.60 91.68%

Very Satisfactory

Angel & Sam Construction and General Merchandise 19968

Cluster 2012-20; Const. of 2-CL Sch. Bldg. a)Initao CS, Initao, b)Laguindingan CS, Laguindingan, c)Const. of 2-CL

Sch. Bldg., Tangkub ES, Libertad, d)Taytay ES08/19/13 X 4.593 60 C 0.459 0.133 0.300 - - - 89.20 89.20% Very

Satisfactory

ANIMAS BROS CONSTRUCTION 35002 Road Leading to Tourism Destination (Upgrading of Road), Capalaran - Villaba Road, Tangub City 8/14/2014 X 4.033 120 C 0.442 0.182 0.300 92.40 92.40%

Very Satisfactory

Annasor Construction & Trading 30825 Repair/Rehab./Impv't. of North Diversion Rd. Km.68+377.60-Km.68+672.80 07/30/13 III 4.806 30 C 0.425 0.133 0.300 - - - 85.80 85.80%

Satisfactory

Anrol Construction 10136 Prev. Maint. of Manila East Rd. (K0057+1250-K0059+000) 03/23/13 IVA 10.571 60 C 0.489 0.133 0.300 - - - 92.20 92.20% Very Satisfactory

Antonio V. Nidea Construction 6382 Const. of Iriga Flood Control Project (Consolidation Dam, Ground Sill, Slope Protection & Damage Canal) 02/28/10 V 28.505 240 O 0.352 0.240 0.150 0.030 0.035 0.033 84.00 -

Antonio V. Nidea Construction Inc. (Formerly; Antonio V. Nidea

Construction)6382 Const. of Cawayan River Control, West District 03/16/13 V 46.078 240 C 0.438 0.133 0.300 - - - 87.10 87.22%

Satisfactory

Antonio V. Nidea Construction Inc. (Formerly; Antonio V. Nidea

Construction)6382 Rehab. of Binatagan Dike 03/20/13 V 3.288 120 C 0.414 0.133 0.300 - - - 84.70 83.02%

Satisfactory

Antonio V. Nidea Construction, Inc. (Formerly: Antonio V. Nidea

Construction)6382 Const./Repair/Rehab. of MPB, Albay III DEO 08/09/13 V 3.679 90 O 0.334 0.286 0.150 0.030 0.040 0.033 87.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page23

Page 24: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Antonio V. Nidea Construction, Inc. (Formerly: Antonio V. Nidea

Construction)6382 Guicadale Platform Rd., Cotmon-Maninila-Taplacon-Taloto

Rd., (Cotmon-Maninila Sect.) 08/10/13 V 22.843 206 O 0.366 0.241 0.117 0.030 0.041 0.033 82.80 -

APB Construction 17055 Rehab./Reconst./Upgrading of Damaged Nat'l. Rd., PMA Cut-off Rd. K00+000-K00+350 03/22/12 CAR 5.610 114 C 0.485 0.200 0.300 - - - 98.50 82.30%

Satisfactory

APD CONSTRUCTION 17467 Construction of Diduyon Bridge along Cordon-Aurora Bndry. Road (jct. Dumabato-Aurora Road) 10/28/2014 II 13.163 162 C 0.392 0.200 0.300 - - - 89.20% 89.20%

Very Satisfactory

APD CONSTRUCTION 17467 Repair/Restoration of Diduyon Flood Control & Related Facilities (Diduyon Bridge) KO375+509 10/28/2014 II 8.486 150 C 0.370 0.200 0.300 - - - 87.00% 87.00%

Satisfactory

APD Construction 17467

Rehab./Reconstruction of Damaged Paved National Roads including Drainage Based on Pavement Management

System/Highway Development and Management-4 (HDM-4) Intermittent Section) Cordon-Aurora Bdry. Road (Isabela

Bdry.-Jct. Dumabato)

8/13/2014 II 17.804 105 C 0.376 0.199 0.300 87.50 87.50% Satisfactory

APD Construction 17467 Impv't. of Road, Mangadingay 08/13/13 II 1.750 45 C 0.431 0.133 0.300 - - - 86.40 86.40% Satisfactory

Apex Builders 32329 Conc. of Anislag-Canarom, Phase II 07/30/12 V 4.776 120 C 0.439 0.133 0.300 - - - 87.20 82.34% Satisfactory

Aqua Dragon Construction & Supply 36405 Const. of DepEd Standard Type Sch. Bldg. @ Carol-an

NHS 08/08/13 VI 1.904 60 C 0.399 0.133 0.300 - - - 83.20 83.20% Satisfactory

Aqualine Construction 2011-1220 Calbiga Irrigation Project 11/22/14 NIA 9.235 305 C 0.456 0.200 0.300 - - - 95.55 95.55% Very Satisfactory

AQUALINE Construction/C.R. DOMINGO Construction, Inc. (JV) 2992 Nueva Viscaya Bagabag Irrigation System 09/29/15 NIA 74.478 866 O 0.373 0.296 0.047 0.030 0.045 0.050 84.05 -

Aquino-Dela Cruz Eng'g & Construction 16751 Widening of Pangasinan-Nueva Ecija Rd. (PNVR) Km.

171+138-Km. 204+500 w/ exception 08/09/13 I 19.351 104 C 0.479 0.133 0.300 - - - 91.20 86.58% Satisfactory

Aquino-Dela Cruz Eng'g & Construction 16751

Replacement/Rehab./Strengthening of Quintans Bridge along Camiling-Wawa-Bayambang-Malasiqui-Sta. Barbara

Rd.08/03/13 I 11.081 225 O 0.400 0.200 0.150 0.030 0.047 0.033 86.00 -

Aquino-Dela Cruz Eng'g & Construction 16751 Prev. Maint. along Calasiao Old Rd., K0204+(-030)-

K0206+305 w/ exception 08/02/13 I 40.758 75 C 0.377 0.200 0.300 - - - 87.70 85.48% Satisfactory

Aquino-Dela Cruz Eng'g & Construction 16751 Widening/Rehab./Reconst./Upgrading of MNR 08/09/13 I 36.320 242 O 0.390 0.300 0.046 0.030 0.042 0.033 84.10 -

Aquino-Dela Cruz Eng'g Construction 16751

Replacement/Rehabilitation/Strengthening of Quintans Bridge along Camiling-Wawa-Bayambang-Malasiqui-Sta.

Barbara Road8/12/2014 I 11.468 225 C 0.417 0.133 0.300 85.00 85.60%

Satisfactory

Aquino-Dela Cruz Eng'g. & Construction 16751 Prev. Maint. along Calasiao Old Rd., K0204+(-030)-

K0206+305 w/ exception 03/14/13 I 38.759 75 O 0.375 0.300 0.098 0.020 0.030 0.017 84.00 -

Aquino-Dela Cruz Eng'g. & Construction 16751 Widening of Pangasinan-Nueva Vizcaya Rd. (PNVR),

Km.171+138-Km.204+550 w/ exception 03/13/13 I 19.351 104 O 0.317 0.300 0.150 0.015 0.020 0.033 83.50 -

Aquino-dela Cruz Eng'g. & Construction 16751 Rehab./Reconst./Upgrading of Pangasinan-Nueva Ecija

Road, IS K0184+000-K0185+667 w/ exceptions 11/26/12 I 20.375 148 C 0.443 0.200 0.300 - - - 94.30 87.70% Satisfactory

Aquino-dela Cruz Eng'g. & Construction 16751 Rehab./Reconst./Upgrading of Pangasinan-Nueva Ecija

Road, IS K0184+000-K0185+667 w/ exceptions 08/10/12 I 20.375 133 O 0.290 0.300 0.125 0.030 0.055 0.033 83.30 -

AQUINO-DELA CRUZ ENGINEERING & CONSTRUCTION 16751

Rehabilitation/ Reconstruction/Upgrading of Bakit-Bakit Jct. Umingan Road, K0204+000 - K0204+1032 With

Exceptions Including Bridge Approaches(From: Rehabilitation/ Reconstruction/Upgrading of Bakit-Bakit Jct-Umingan Road, K0204+000 to K0204+500 Including Udiao Bridge Approaches KO204+000 to KO1032 With

Exceptions)

10/30/2014 I 9.669 117 C 0.433 0.148 0.300 - - - 88.10% 88.10% Satisfactory

AQUINO-DELA CRUZ ENGINEERING & CONSTRUCTION 16751 Replacement of Sapang Bridge I along Camiling-Wawa-

Bayambang-Malasiqui-Sta. Barbara Road 10/29/2014 I 13.759 285 C 0.436 0.152 0.300 - - - 88.80% 88.80% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page24

Page 25: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Aquino-Dela Cruz Engineering & Construction 16751 Construction of San Carlos City District Office 07/19/13 DOTC 8.671 180 O 0.391 0.240 0.150 0.030 0.050 0.050 91.07 -

Aquino-Dela Cruz Engineering & Construction 16751 San Fernando, La Union LTFRB Regional Office Project 07/30/13 DOTC 7.949 180 O 0.390 0.240 0.150 0.030 0.035 0.050 89.50 -

Aquino-Dela Cruz Engineering & Construction 16751 Construction of San Carlos City District Office 10/24/13 DOTC 8.671 180 C 0.475 0.133 0.300 - - - 90.78 90.98%

Very Satisfactory Aquino-Dela Cruz Engineering &

Construction 16751 San Fernando, La Union LTFRB Regional Office Project 11/19/13 DOTC 7.949 180 C 0.453 0.200 0.300 - - - 95.30 91.80% Very Satisfactory

AR ADLAWAN CONSTRUCTION 13108

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Road Including Drainage Based on

Pavement Management System/Highway Development-4 (HDM-4), Argao - Moalboal, K0060+000 to K0062+728

10/24/2014 VII 38.420 151 C 0.335 0.200 0.300 - - - 83.50% 83.50% Satisfactory

AR Adlawan Construction 13108Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd.

along Natalio Bacalso Ave. (Cebu South Rd.), K0108+200-K0109+000

08/09/13 VII 16.856 110 C 0.373 0.200 0.300 - - - 87.30 87.30% Satisfactory

AR Adlawan Construction 13108 Preventive Maint. along Natalio Bacalso (Cebu South Road) Km.77+ -Km.81+1 03/23/12 VII 37.985 179 C 0.391 0.133 0.300 - - - 82.40 90.50%

Very SatisfactoryAR Adlawan Construction 13108 Widening of Natalio Bacalso Avenue 11/20/12 VII 71.121 265 O 0.350 0.239 0.150 0.030 0.035 0.050 85.40 -

AR Adlawan Construction 13108 Widening of Natalio Bacalso Ave., Naga to Carcar Sect. 08/20/12 VII 71.121 265 O 0.368 0.256 0.150 0.024 0.045 0.033 87.60 -

Arca Builders 34537Const./Impv't. of Drainage System along Palompon-Isabel-

Merida-Ormoc Rd., Km.1132+700-Km.1133+763 w/ exceptions

08/10/13 VIII 1.512 105 C 0.486 0.133 0.300 - - - 91.90 88.78% Satisfactory

Arca Builders 34537Const./Impvt. of Drainage System along Palompon-Isabel-

Merida-Ormoc Rd., Km.1132+700-Km.1133+763 w/ exceptions

11/22/12 VIII 1.512 105 O 0.334 0.300 0.150 0.030 0.020 0.033 86.70 -

Arcinue Commercial NHA - Tambo Resettlement Project 05/01/15 NHA 19.591 268 C 0.436 0.200 0.300 - - - 93.55 90.42% Very Satisfactory

Arcinue Commercial NHA-Tambo Resettlement Project 11/29/13 NHA 19.600 313 O 0.390 0.300 0.082 0.030 0.065 0.050 91.74 -

Arcinue Commercial 6746 Rehab. of National Road along Bacolod South Road, K0122+830-K0123+549, Brgy. Masaling 08/09/13 VI 9.306 67 C 0.498 0.133 0.300 - - - 93.10 93.10%

Very Satisfactory

Arcinue Commercial 6746Installation/Application/Const. of Rd. Safety Devices,

Km.1500+513-Km.1525+116, Babak-Samal Kaputian w/ exception

08/13/13 XI 4.930 35 C 0.408 0.133 0.300 - - - 84.10 84.10% Satisfactory

Arcinue Commercial NHA-Tambo Resettlement Project 05/30/14 NHA 19.600 268 O 0.398 0.300 0.032 0.030 0.056 0.033 84.93 -

Arcinue Commercial 6746 Widening of San Fernando By Pass Rd. inc. Rd. Righ-of-Way 07/30/13 I 19.068 148 C 0.437 0.133 0.300 - - - 87.00 87.84%

Satisfactory

Arcinue Commercial 6746Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd.

along Camiling-Wawa-Bayambang-Sta. Barbara Rd., K0172+(-006)-K0172+594

08/03/13 I 10.031 105 C 0.425 0.133 0.300 - - - 85.80 86.70% Satisfactory

Arcinue Commercial 6746 Prev. Maint. along Bacnotan-Luna Balaoan Rd. (Clustered) K0286+000-K0287+498 w/ exception 07/29/13 I 6.729 113 C 0.470 0.133 0.300 - - - 90.30 84.60%

Satisfactory

Arcinue Commercial 6746 Widening of San Fernando By Pass Rd. inc. Rd. Right-of-Way 03/11/13 I 19.364 120 O 0.356 0.300 0.150 0.015 0.030 0.033 88.40 -

Arcinue Commercial 6746Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd..

along Camiling-Wawa-Bayambang-Sta. Barbara Rd., K0172+(-006)-K0172+594

03/14/13 I 10.031 105 O 0.372 0.289 0.150 0.015 0.030 0.017 87.30 -

Arcinue Commercial 6746 Prev. Maint. along Bacnotan-Luna Balaoan Rd. (Clustered) K0286+000-K0287+498 w/ exception 03/11/13 I 6.729 113 O 0.37 0.200 0.150 0.015 0.040 0.033 80.80 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page25

Page 26: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Arcinue Commercial 6746 Rehab./Reconts./Upgrading along Bacnoton-Luna-Balaoan Road, Km. 283+221-Km. 307+896 w/exception 05/27/09 I 16.169 90 O 0.358 0.207 0.150 0.030 0.040 0.033 81.80 -

Arcinue Commercial 6746 Widening/Reconst. of San Fernando By-Pass Road (Sta. 0+000-Sta. 3+840) w/ exceptions 03/12/12 I 44.687 270 O 0.374 0.240 0.111 0.030 0.042 0.033 83.00 -

Arcinue Commercial 6746

Preventive Maint. Daang Maharlika (MN) Cluster 1 a)Km.1468+135-Km.1470+(-)392, b)Km.1470+(-)392-

Km.1470+124, realigned to Km.1471+124 c)Km.1472+(-)185.81-Km.1475+000

03/26/12 XI 27.583 105 C 0.395 0.198 0.300 - - - 89.30 85.28% Satisfactory

Arcinue Commercial 6746 Widening/Reconst. of San Fernando By-Pass Rd., Sta.0+000-Sta.3+840 w/ exception 11/23/12 I 46.334 252 C 0.451 0.200 0.300 - - - 95.10 90.00%

Very Satisfactory

Arcinue Commercial 6746 Repair/Rehab. Of MNR, Patac, Sto. Tomas and Urayong Sections 11/24/12 I 8.834 280 O 0.300 0.300 0.150 0.020 0.030 0.033 83.30 -

Arcinue Commercial 6746 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. along MNR, K0370+000-K0371+249 11/22/12 I 22.295 263 C 0.409 0.200 0.300 - - - 90.90 81.54%

Satisfactory

Arcinue Commercial 6746 Widening/Reconst. of San Fernando By-Pass Rd., Sta.0+000-Sta.3+840 w/ exception 08/07/12 I 46.334 224 O 0.362 0.272 0.150 0.030 0.055 0.033 90.20 -

Arcinue Commercial 6746 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. along MNR K0390+000-K0392+000 07/31/12 I 22.839 115 C 0.336 0.166 0.300 - - - 80.20 82.36%

Satisfactory

Arcinue Commercial 6746 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. along MNR, K0370+000-K0371+249 07/31/12 I 22.295 251 O 0.253 0.300 0.107 0.020 0.040 0.033 75.30 -

Arcinue Commercial 6746 Const. of Malita Seawall at SPAMAST-SAMTALIKA Sect., Pob. 08/09/12 XI 33.521 285 O 0.334 0.220 0.150 0.030 0.057 0.033 82.40 -

Arcinue Commercial 6746 Installation/Application/Const. of Rd. Safety Devices along Loakan Rd., K0245+(-158) - K0247+3766 w/ exception 03/24/13 CAR 9.702 45 C 0.420 0.133 0.300 - - - 85.30 85.30%

Satisfactory

Arcinue Commercial 6746 Repair/Rehab./Impv't. of Legarda Rd., K0251+(-360)-K0251+980 w/ exception 03/11/13 CAR 9.603 27 C 0.418 0.133 0.300 - - - 85.10 85.10%

Satisfactory

Arcinue Commercial 6746 Prev. Maint. along Manila North Rd., K0326+000-K0326+454 03/19/13 I 5.301 29 C 0.439 0.133 0.300 - - - 87.20 87.20% Satisfactory

AREX BUILDERS & CONSTRUCTION SUPPLY 35696 Construction of Local Road, La Perla Access Road, Sta.

0+000.00 - Sta. 0+580.00 10/20/2014 VIII 5.523 75 C 0.431 0.200 0.041 - - - 67.20% 67.20% Poor

ARG Cecilia Construction 31602 Conc. of Multi-Purpose Pavement Brgy. Patag 03/14/13 VIII 0.995 45 C 0.364 0.189 0.300 - - - 85.30 85.30% Satisfactory

Arik Construction 32786 Rehab./Impv't. of Drainage System & Slope Protection Works along Daet-Bagasbas Rd. 03/23/13 V 4.800 120 C 0.321 0.200 0.300 - - - 82.10 82.10%

SatisfactoryARMANDO U. KHONG HUN

GENERAL CONTRACTOR, INC. 16163 Construction of Four (4) Storey, Twelve (12) Classroom Building at R.P. Cruz Elementary School 8/7/2014 NCR 21.781 150 C 0.441 0.200 0.300 94.10 87.24%

Satisfactory

Armando U. Khong Hun General Contractor, Inc. 16163 Prev. Maint. (Int. Sect.) San Marcelino St., 5th District,

Manila A) K0003+783 B) K0003+78 -K0003+836 03/13/13 NCR 14.517 104 O 0.344 0.240 0.150 0.030 0.048 0.033 84.50 -

Armando U. Khong Hun General Contractor, Inc. (Formerly:

Armando U Khong Hun General Contractor)

16163Proposed Rehab/Reconst/Upgrading of Damaged Paved

Nat'l Rd. (Int. Sect.) Bonifacio Drive, Port Area, Manila from 25th St. to Katigbak Drive, L=204.30 L.M.

07/31/13 NCR 10.620 60 C 0.365 0.200 0.300 - - - 86.50 86.50% Satisfactory

Armando U. Khong Hun General Contractor, Inc. (Formerly:

Armando U Khong Hun General Contractor)

16163 Prev. Maint. of Del Monte Ave. 08/02/13 NCR 19.670 150 C 0.420 0.133 0.300 - - - 85.30 85.30% Satisfactory

Armando U. Khong Hun General Contractor, Inc. (Formerly:

Armando U Khong Hun General Contractor)

16163 Prev. Maint. (Int. Sect.) San Marcelino St. 5th District, Manila K0003+000-K0003+783 b) K0003+783-K0003+836 07/31/13 NCR 14.516 149 C 0.364 0.200 0.300 - - - 86.40 85.26%

Satisfactory

Armando U. Khong Hun General Contractor, Inc. (Formerly:

Armando U Khong Hun General Contractor)

16163 Const./Widening of Pres. Garcia Ave. (C-5), Sta. 0+000-Sta. 2+897.20 07/27/13 NCR 33.084 120 O 0.329 0.240 0.150 0.030 0.050 0.050 84.90 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page26

Page 27: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Armando U. Khong Hun General Contractor, Inc. (Formerly:

Armando U Khong Hun General Contractor)

16163 Const. of Four (4) Storey, Twelve (12) Cl. at R.P. Cruz Elem. Sch. 08/07/13 NCR 21.781 178 O 0.326 0.240 0.150 0.030 0.047 0.050 84.30 -

Armando U. Khong Hun General Contractor, Inc. (Formerly:

Armando U Khong Hun General Contractor)

16163 Const. of Four (4) storey, Twenty (20) Cl. Bldg. at San Antonio Elem. Sch. 08/08/13 NCR 36.242 233 O 0.332 0.240 0.150 0.030 0.058 0.033 84.30 -

ARMANDO U. KHONG HUN GENERAL CONTRACTOR, INC.

(Formerly: Armando U. Khong Hun General Contractor)

16163Improvement/Clearing & Desilting including Right of Way (ROW) of Zapote River, Manila Bay towards Alido Bridge

(Vice Versa), Sta. 0+000 to Sta. 1+54011/17/2014 NCR 43.675 195 O 0.263 0.250 0.150 0.030 0.054 0.050 79.70% 79.70%

Unsatisfactory

ARMANDO U. KHONG HUN GENERAL CONTRACTOR, INC.

(Formerly: Armando U. Khong Hun General Contractor)

16163 Asphalt Overlay with corrections at Main Avenue (Chainage 0+000 (EDSA)-Chainage 0+855 (15th Avenue) 11/27/2014 NCR 9.945 120 C 0.424 0.133 0.300 - - - 85.70% 85.70%

Satisfactory

Armando U. Khong Hun General Contractor, Inc. (Formerly:

Armando U. Khong Hun General Contractor)

16163 Proposed Const. of Diokno Blvd. incl. Bridge Approaches 11/19/12 NCR 47.316 135 C 0.440 0.200 0.300 - - - 94.00 89.26% Very Satisfactory

Armando U. Khong Hun General Contractor, Inc. (Formerly:

Armando U. Khong Hun General Contractor)

16163 Proposed Const. of Diokno Blvd. incl. Bridge Approaches 07/30/12 NCR 43.663 120 O 0.380 0.240 0.150 0.023 0.035 0.033 86.10 -

ARN BUILDERS 18930 Construction of Alburquerque Cluster Sanitary Landfill 03/06/14 TIEZA 93.586 365 C 0.492 0.200 0.300 99.15 99.15% Outstanding

Arn Builders 18930 Const. of Lugusan Bridge & Approaches along Surigao del Sur Bdry., Davao Oriental Coastal Rd. 08/16/13 XI 27.687 351 O 0.376 0.259 0.000 0.030 0.025 0.033 72.30 -

Arn Builders 18930 Const. of Flood Control Disakan Bridge 08/22/13 IX 6.549 146 C 0.449 0.133 0.300 - - - 88.20 87.42% Satisfactory

Arn Builders 18930 Const. of Flood Control along Left Bank of Dipolog River Looc 08/22/13 IX 62.300 437 O 0.191 0.300 0.150 0.020 0.042 0.050 75.30 -

ARN Builders 18930 Rehab./Reconstruction of Aklan East Road 11/30/08 VI 19.283 180 O 0.218 0.240 0.100 0.015 0.032 0.100 70.50 -ARN Builders 18930 Rehab./Reconst./Upgrading of Aklan East Road 09/05/09 VI 31.795 240 O 0.335 0.240 0.150 0.000 0.032 0.100 72.50 -

Arn Builders 18930 Const. of Flood Control along Left Bank of Dipolog River 11/28/12 IX 62.300 408 O 0.388 0.239 0.150 0.030 0.054 0.050 91.10 -

ARN Builders 18930 Repair/Rehab./Impvt. of Roman Expressway Km.135+410 -Km.137+500 w/ exception 08/10/12 III 9.434 20 C 0.392 0.200 0.300 - - - 89.20 89.20%

Very Satisfactory

ARN Builders 18930 Const. of Lugusan Bridge & Approaches along Surigao del Sur Bdry., Davao Oriental Coastal Rd. 08/17/12 XI 27.687 244 O 0.400 0.200 0.077 0.022 0.051 0.017 76.70 -

ARN Builders 18930 Mabini Cayacay SRIP 07/13/13 NIA 4.922 150 O 0.365 0.300 0.000 0.020 0.045 0.050 78.00 -

Arn Builders 18930 Repair of Langkilaan Rd. along Daang Maharlika Rd. (Agusan-Davao Sect.) Km. 1375+302.90-Km. 1375+460 11/26/12 XIII 9.356 235 O 0.390 0.220 0.135 0.030 0.035 0.033 84.30 -

ARN Builders, Inc. 18930 Const. of Flood Control along Left Bank of Dipolog River Looc 03/23/13 IX 62.300 408 O 0.365 0.240 0.150 0.030 0.042 0.050 87.70 -

ARN Builders, Inc. 18930 Const. of Flood Control Disakan Bridge, Jose Dalman 03/23/13 IX 6.549 146 O 0.383 0.240 0.150 0.030 0.033 0.033 86.90 -

Arrow Construction 32834 Conc. of Brgy. Road, Purok 1, Mabical 08/01/13 III 1.931 60 C 0.446 0.133 0.300 - - - 87.90 87.90% Satisfactory

Arthur Blanco Construction and Development Corp. 33999 Const. of MPB, Brgy. Kumintang Ilaya, Capitol Site 03/12/13 IVA 3.997 167 C 0.481 0.133 0.300 - - - 91.40 90.42%

Very SatisfactoryArthur Blanco Construction and

Development Corp. 33999 Const. of MPB, Brgy. Kumintang Ilaya, Capitol Site 11/23/12 IVA 3.997 167 O 0.364 0.300 0.150 0.030 0.023 0.033 90.00 -

ASAND CONST. & DEV'T 21691 COMPLETION OF ACADEMIC BUILDING II 12/13/12 DOST 9.082 C 0.454 0.200 0.090 - - - - 82.00% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page27

Page 28: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Asand Construction 21691 Bukidnon Irrigation Management Office / Region 10 03/31/12 NIA 15.181 360 C 0.476 0.200 0.210 - - - 88.56 88.01% Satisfactory

Asand Construction & Devt. 21691 Completion of Academic Bldg. II 08/25/11 DOST 9.082 O 0.376 0.300 0.090 0.030 0.018 0.033 84.63 -

ASC Construction 26788 Colocol Integrated CIS Rehabilitation & Extension Project 05/12/12 NIA 8.428 224 C 0.416 0.196 0.300 - - - 91.25 91.08% Very Satisfactory

ASC CONSTRUCTION & CONCRETE PRODUCTS/DJD

CONSTRUCTION (JV)JV-12-523

Road Upgrading (Gravel to Paved), KO587+500 - KO589+761.50, Junction Gattaran-Cumao-Capissayan-Sta.

Margarita-Bolos Point Road10/21/2014 II 39.151 224 C 0.449 0.133 0.250 - - - 83.20% 83.20%

Satisfactory

ASC Construction and Concrete Product 26788 Pinacanauan River Irrigation System 10/01/15 NIA 82.643 743 C 0.439 0.153 0.300 - - - 89.23 90.62% Very

SatisfactoryASC Construction and Concrete

Product 26788 Banurbur Creek Irrigation System 10/01/15 NIA 62.724 730 C 0.439 0.153 0.300 - - - 89.23 92.60% Very Satisfactory

ASC Construction and Concrete Product 26788 Banurbur Creek Irrigation System 04/26/14 NIA 65.410 730 O 0.383 0.300 0.150 0.018 0.042 0.050 94.33 -

ASC Construction and Concrete Product 26788 Rehab./Restoration and extension of Pinacanauan RIS

Including Suppy, Delivery Installation of Steel Gates 04/26/14 NIA 77.856 640 O 0.360 0.270 0.150 0.020 0.050 0.050 90.00 -

ASC Construction and Concrete Products 26788 Const. of Cataggaman River Control System 07/29/13 II 47.042 245 O 0.383 0.300 0.077 0.030 0.055 0.050 89.50 -

ASC Construction and Concrete Products / D.J.D. Construction (JV) JV-12-522

Rd. Upgrading (Gravel to Paved) K0548+500-K0551+271, Baybayog-San Jose-Dalin-Abusag-Sta. Margarita-Bolos

Point Rd.07/30/13 II 46.277 179 O 0.372 0.300 0.031 0.030 0.055 0.050 83.80 -

ASHLEE CONSTRUCTION & ALLIED ENGINEERING SERVICES 36738 Construction of Multi-Purpose Building, Puntian 8/9/2014 X 1.980 91 OG 0.319 0.241 0.076 0.020 0.035 0.033 72.40 -

ASHLEE CONSTRUCTION AND ALLIED ENGINEERING SERVICES 36738 Const. of Multi-Purpose Bldg. (Fibelo Compound) Brgy.

Anahawon 10/22/2014 X 4.937 120 O 0.322 0.240 0.083 0.010 0.032 0.033 72.00% 72.00% Poor

ASHLEE CONSTRUCTION AND ALLIED ENGINEERING SERVICES 36738 Const. of Classroom - Northern Bukidnon Community

College 10/21/2014 X 1.980 104 O 0.342 0.269 0.055 0.010 0.022 0.033 73.10% 73.10% Poor

Asia Konstrakt Philippines, Inc. 32706 Const. of Talomo Flood Control Proj. 08/20/13 XI 6.353 170 C 0.407 0.133 0.300 - - - 84.00 84.18% Satisfactory

Asia Konstrakt Philippines, Inc. 32706 Const. of Talomo Flood Control Proj. 03/22/13 XI 6.353 111 O 0.263 0.300 0.150 0.030 0.028 0.050 82.10 -

Asia Konstrakt Philippines, Inc. 32706 Const. of Talomo Flood Control Proj. 11/29/12 XI 6.353 96 O 0.360 0.240 0.150 0.030 0.035 0.050 86.50 -

ASJ BUILDERS 35988 Construction of Multi-Purpose Building, Brgy. Banban, Tagana-an, Surigao del Norte 10/28/2014 XIII 2.413 90 O 0.327 0.240 0.150 0.020 0.048 0.050 83.50% 83.50%

SatisfactoryASM Francisco Const. & Devt.

Corporation Manila Museum and Archives Project Phase 1 02/17/11 UP 15.698 150 O 0.384 0.299 0.150 0.030 0.056 0.050 96.90 -

Atlantic Construction 24232 Const. of Multi-Purpose Building at San Andres E/S 8/8/2014 II 2.886 97 OG 0.282 0.300 0.150 0.030 0.035 0.033 83.00 -

Atlantic Construction 24232Const. of Flood Control Structure (Drainage System) at

a)Sta.0+148-Sta.0+250 (Stretch 1) b)Sta.0+000-Sta.0+085, c)Sta.0+000-Sta.0+270.65 (Stretch 3), Pob.

08/05/13 II 1.904 90 C 0.354 0.133 0.300 - - - 78.70 78.70% Unsatisfactory

ATLAS CONSTRUCTION Sta. Josefa Pump Irrigation Project 08/30/14 NIA 15.560 270 C 0.382 0.195 0.300 - - - - 87.70% Satisfactory

Atlas Gen. Const. & Enterprises Corp. / VRF Construction Joint

VentureJV-12-330

Rehab./Reconst./Upgrading of Damage Paved Nat'l. Rd. (Int. Sect.) Sta. Rosa - Tarlac Rd., K0120+000-K0121+000;

K0122+000-K0122+944; K0123+720-K0124+00008/12/13 III 38.997 150 C 0.441 0.133 0.300 - - - 87.40 87.28%

Satisfactory

Atlas General Contractors and Enterprises Corporation

Package X-D: Construction of lateral "N" (Sta. 10+000) Sub-lat. R "N-6" (Sta. 0+000-1+200). "N-6a" (Sta. 0+000-1+480)

and "N-6b" (Sta. 0+000-1+940) including related structures and supply, delivery and installation of steel gates

02/07/15 NIA 38.176 246 O 0.328 0.275 0.150 0.030 0.023 0.050 85.56 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page28

Page 29: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

ATOLBA CONSTRUCTION 33768

Const of Various Drainage & Box Culvert J. Banaue-Hungduan-Benguet Bdry Rd, K0360+060, Hungduan, 2.

Banaue-Hungduan-Benguet Bdry Rd, K0398+497 3. Nueva Vizcaya-Ifugao-Mt. Province Bdry Rd, K0311+976, Kiangan`

8/5/2014 CAR 1.161 109 OG 0.391 0.240 0.150 0.022 0.035 0.050 88.80 -

Atolba Construction 33768 Replacement/Rehab./Strengthening of Adunot Bridge, K0275+350, Brgy. Ambuclao 07/30/13 CAR 4.563 120 C 0.471 0.133 0.300 - - - 90.40 90.40%

Very Satisfactory

Avatar Construction Company 31455 Replacement of Pangi Bridge 2 along Dinagat-Loreto Road 11/22/12 XIII 7.006 212 C 0.447 0.133 0.300 - - - 88.00 85.36% Satisfactory

Avatar Construction Company 31455 Conc. of Magsaysay-Cagdianao Road, 11/22/12 XIII 9.361 193 C 0.483 0.200 0.000 - - - 68.30 71.72% Poor

AVATAR CONSTRUCTIONS COMPANY 31455 Protection Works along Dinagat - Loreto Road (San Jose

Section), Brgy. Don Ruben, San Jose, Dinagat Islands 10/27/2014 XIII 9.436 70 O 0.355 0.300 0.000 0.020 0.042 0.033 75.00% 75.00% Poor

Avatar Constructions Company 31455 Replacement of Pangi Bridge 2 along Dinagat-Loreto Rd. 08/10/12 XIII 6.447 165 O 0.363 0.300 0.033 0.030 0.060 0.050 83.60 -

AVIC Construction and Supply (Formerly: Avic Construciton) 28784

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Road including Drainage based on

Pavement Management System/HDM-4 (Intermittent Section) along Ligao-Pioduran Road, K0519+000 -

K0519+664

8/11/2014 V 1.590 80 C 0.427 0.133 0.300 86.00 86.00% Satisfactory

AYLAN CONSTRUCTION AND TRADING 11884 Construction of 4-Storey 20 Classroom Building at

Novaliches H/S 11/27/2014 NCR 36.205 395 C 0.450 0.133 0.300 - - - 88.30% 88.30% Satisfactory

AYLAN CONSTRUCTION AND TRADING 11884 Construction of 4 Storey Twenty (20) Classroom Building

at Novaliches H/S 8/14/2014 NCR 36.205 395 OG 0.371 0.240 0.150 0.018 0.051 0.020 85.00 -

Aylan Construction and Trading 11884 Const. of Two (2) Sch. Bldg. Four (4) Storey Sixteen (16) Cl. at Amparao H/S 08/13/13 NCR 46.300 330 O 0.298 0.221 0.150 0.030 0.046 0.050 79.50 -

AYU ENGINEERING & CONSTRUCTION 25832

Widening of Davao Regional Medical Training Center Junction Davao Agusan – Davao Medical Center,

K1506+116 – K1506+416, Davao City8/15/2014 XI 13.839 110 C 0.381 0.200 0.300 88.10 88.10%

Satisfactory

Azul Builders 21870 Const. of MPB, Brgy. Citrus Elem. & H/S 03/21/13 III 2.450 80 C 0.456 0.133 0.300 - - - 88.90 88.90% Satisfactory

B Y A Builders and Construction Supply 24158 Conc. of Rds. Southern Leyte State University-Main

Campus 03/16/13 VIII 1.896 57 C 0.464 0.138 0.300 - - - 90.20 90.20% Very Satisfactory

B. BERNARDO CONSTRUCTION 6196 Construction/Rehabilitation of Igay-Kaybanban San Isidro Road 11/28/2014 III 18.600 141 C 0.484 0.133 0.300 - - - 91.70% 91.70%

Very Satisfactory

B. K. SY TU CONSTRUCTION 12665 CONSTRUCTION OF PSHSCLC ACA BLDG I PHASE I 05/15/14 DOST 14.404 212 C 0.487 0.200 0.300 - - - - 92.55% Very Satisfactory

B. M. Marketing 9852 Tacloban Airport Development Project 12/11/14 DOTC 123.417 240 O 0.385 0.300 0.150 0.020 0.031 0.050 93.56 -

B. M. Marketing 9852 Borongan Airport Development Project 11/27/12 DOTC 14.283 120 O 0.380 0.300 0.150 0.030 0.070 0.050 98.00 -

B. M. Marketing 9852 Borongan Airport Development Project 03/14/13 DOTC 14.283 120 C 0.457 0.200 0.300 - - - 95.70 97.10% Outstanding

B. M. MARKETING - B. VICENCIO CONSTRUCTION JOINT VENTURE JV-12-673 First District of Samar Ports Cluster Development Project 10/29/14 DOTC 13.588 210 C 0.428 0.200 0.300 - - - 92.80 92.80%

Very Satisfactory

B. M. Marketing & Fiat Construction Services (JV) 9852 Tacloban Airport Development Project 10/08/14 DOTC 176.112 360 C 0.454 0.200 0.300 - - - - 92.72%

Very Satisfactory

B. P. CRUZ BUILDERS & TRADING 33272 Rehabilitation of Songkoy-Honrado-Sering Road 4/21/15 TIEZA 15.900 225 O 0.400 0.300 0 0.015 0.058 0.050 82.33 -

B. P. CRUZ BUILDERS & TRADING 33272 Development of Town Plaza and Sukol River Baywalk Project 02/06/14 TIEZA 4.988 90 C 0.439 0.190 0.300 92.90 92.90% Very

SatisfactoryB. Valencerina Trading &

Construction 22147 Repair and Rehab. of Sch. Bldg. at Bambang E/S 08/06/13 NCR 2.413 60 C 0.436 0.200 0.300 - - - 93.60 93.60% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page29

Page 30: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

B. Vicencio Construction 9687 Calbayog Airport Development Project 06/25/15 DOTC 23.784 90 C 0.450 0.200 0.300 - - - 95.00 95.00% Very Satisfactory

B. VICENCIO CONSTRUCTION 9687 Completion of Padog Bridge along Dinagat - Loreto Road, Tubajon, Dinagat Islands 10/27/2014 XIII 7.469 219 O 0.326 0.300 0.044 0.020 0.042 0.033 76.50% 76.50%

Unsatisfactory

B. VICENCIO CONSTRUCTION 9687Rehab./Reconst. Along Tacloban Baybay South Road

KO915+(-267) - KO915+(-118.20) and KO915+(-118.20) - KO915+607.80

8/15/2014 VIII 13.054 153 OG 0.334 0.300 0.120 0.022 0.040 0.017 83.30 -

B. VICENCIO CONSTRUCTION 9687 Replacement of Bugtong Bridge along Daang Maharlika (SM) (San Juanico Bridge) 8/11/2014 VIII 32.855 235 C 0.473 0.133 0.300 90.60 88.77%

Satisfactory

B. Vicencio Construction 9687 Const. of River Control at Poblacion Ilawod 08/19/13 VI 13.875 215 C 0.337 0.200 0.300 - - - 83.70 83.70% Satisfactory

B. Vicencio Construction 9687 Rehab.Strengthening of Malago Bridge along Daang Maharlika (SM) San Isidro-San Juanico Bridge 08/13/13 VIII 19.187 150 C 0.421 0.171 0.300 - - - 89.20 89.20%

Very Satisfactory

B. VICENCIO CONSTRUCTION Help for Catubig Agricultural Advancement Project HCAAP-LCB-C2-2012 03/15/14 NIA 15.995 597 SUSPEND

ED 0.366 0.177 0.150 0.030 0.070 0.050 84.23 -

B. Vicencio Construction 9687 Replacement of Bugtong Bridge along Daang Maharlika (SM) (San Isidro-San Juanico Bridge) 08/13/13 VIII 32.855 205 O 0.345 0.258 0.150 0.030 0.060 0.033 87.60 -

B. Vicencio Construction 9687 Const. of Altavas-Jamindan Rd., K0324+085-K0324+844 03/19/13 VI 20.307 142 O 0.333 0.300 0.150 0.018 0.040 0.033 87.40 -

B. Vicencio Construction 9687 Replacement of Bugtong Bridge along Daang Maharlika (SM) (San Isidro-San Juanico Bridge) 03/19/13 VIII 31.952 160 O 0.370 0.225 0.150 0.030 0.050 0.050 87.50 -

B. Vicencio Construction 9687 Replacement of Cagnipa Bridge along Daang Maharlika (SM) (San Isidro-San Juancio Bridge), Brgy. Cagnipa 03/19/13 VIII 37.689 274 C 0.446 0.121 0.300 - - - 86.70 86.88%

Satisfactory

B. Vicencio Construction 9687 Rd. Opening/Upgrading/Concrete Paving of Calbayog Diversion Rd. (inc. RROW), Sta.12+074.46-Sta.15+120.00 03/19/13 VIII 98.781 300 C 0.395 0.148 0.300 - - - 84.30 84.63%

Satisfactory

B. Vicencio Construction 9687 Replacement of Bulongto Bridge along Daang Maharlika (SM) (San Isidro-San Juanico Bridge) 03/19/13 VIII 38.495 260 C 0.461 0.057 0.300 - - - 81.80 84.50%

Satisfactory

B. Vicencio Construction 9687 Rehab./Reconst. of Catbalogan Diversion Rd. (Sta.0+468.25-Sta.5+530.59) w/ exception 03/18/13 VIII 95.459 390 O 0.296 0.253 0.150 0.030 0.060 0.050 83.90 -

B. Vicencio Construction 9687 Concreting of Antequera-Catagbacan (Loon) Rd. 09/01/09 VII 18.313 172 O 0.375 0.246 0.150 0.030 0.042 0.050 89.30 -

B. Vicencio Construction 9687 Rehab./Reconst./Upgrading of Damaged Paved National Roads Calbayog-Catarman Road 06/02/09 VIII 94.550 300 O 0.303 0.238 0.089 0.030 0.045 0.033 73.80 -

B. Vicencio Construction 9687 Const. (Road Opening) of Missing Link of Calbayog Diversion Road, Cagsalaosao-Gadgaran Road Section 06/02/09 VIII 18.794 150 O 0.223 0.240 0.150 0.030 0.050 0.033 72.60 -

B. Vicencio Construction 9687 Const. of Maasin Shore Protection/Seawall 08/29/08 VIII 3.809 240 O 0.300 0.100 0.100 0.000 0.022 0.200 72.20 -

B. Vicencio Construction 9687 Rehab./Impvt. of Brdy. Mahaplag-Sogod Road (Dampoy) 05/27/09 VIII 9.446 310 O 0.345 0.258 0.150 0.030 0.047 0.033 86.30 -

B. Vicencio Construction 9687 Concreting of Villaba-Leyte Road Km. 1015+820-Km. 1017+420 06/02/09 VIII 31.694 330 O 0.339 0.240 0.150 0.022 0.037 0.033 82.10 -

B. Vicencio Construction 9687 Concreting of Tawid-Guadalupe Circumferential Road 03/06/09 VIII 7.517 180 O 0.338 0.238 0.150 0.015 0.030 0.050 82.10 -

B. Vicencio Construction 9687 Rehab./Impv't of Brgy. Mahaplag-Sogod Road (Dampoy) 03/06/09 VIII 9.446 310 O 0.300 0.180 0.150 0.015 0.033 0.050 72.80 -

B. Vicencio Construction 9867 Road Upgrading of Junction Himay-Angan-Silago-Abuyog Road 09/08/09 VIII 53.210 365 O 0.350 0.300 0.150 0.008 0.035 0.050 89.30 -

B. Vicencio Construction 9867 Rehab./Reconst./Upgrading of Calbayog-Catarman Road 09/10/09 VIII 94.551 300 O 0.320 0.300 0.150 0.023 0.050 0.050 89.30 -

B. Vicencio Construction 9687 Conc. of Villaba-Leyte Road, Km. 1015+820-Km. 1017+420 09/05/09 VIII 31.695 330 O 0.354 0.248 0.150 0.018 0.045 0.050 86.50 -

B. Vicencio Construction 9687 Road Opening/Impvt. (Conc.) of Calbayog Diversion Road (IS) Sta.1+247.50-Sta.15+530 w/ exceptions 03/26/12 VIII 88.358 270 O 0.303 0.300 0.150 0.030 0.045 0.050 87.80 -

B. Vicencio Construction 9687Rehab./Reconst./Upgrading od Damaged Paved Nat'l Roads Sulat, Brgy. Del Remedio, Km. 902+700-Km.

907+000 w/ exceptions03/29/12 VIII 48.192 350 C 0.389 0.200 0.300 - - - 88.90 82.42%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page30

Page 31: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

B. Vicencio Construction 9687Rehab./Reconst./Upgrading of Damage Paved Nat'l. Roads,

Bulalacao Bridge-Naubay, Km.961+695-Km.983+500 w/ exceptions

03/29/12 VIII 48.234 406 C 0.347 0.200 0.300 - - - 84.70 83.26% Satisfactory

B. Vicencio Construction 9687Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds.

Sto. Niño-Nabuangan, K.899+300-Km.901+638 w/ exceptions

03/29/12 VIII 38.481 359 C 0.320 0.200 0.300 - - - 82.00 81.43% Unsatisfactory

B. Vicencio Construction 9687 Concrete Paving of Biliran Circ. Road, (Cabibihan-Calambis Sect.), Km.1077+807-Km.1082+800 w/ exceptions 03/21/12 VIII 16.477 250 C 0.287 0.133 0.300 - - - 72.00 85.14%

Satisfactory

B. Vicencio Construction 9687 Concrete Paving of Biliran Circ. Rd. Madao-Tucdao Sect. Km.1056+800-Km.1060+780 w/ exception 08/09/12 VIII 34.233 280 C 0.436 0.200 0.300 - - - 93.60 84.54%

Satisfactory

B. Vicencio Construction 9687 Road Opening/Impvt. (Conc.) of Calbayog Diversion Rd., (IS), Sta.1+247.50-Sta.15+530 w/ exceptions 08/09/12 VIII 93.325 300 C 0.467 0.161 0.300 - - - 92.80 89.80%

Very Satisfactory

B. Vicencio Construction 9687 Rehab/Conc. of Unpaved Portion of Catubig-Las Navas Rd. 08/16/12 VIII 9.152 120 C 0.421 0.133 0.300 - - - 85.40 86.18% Satisfactory

B. Vicencio Construction 9687 Rehab./Reconst. of Catbalogan Diversion Rd., (Sta.0+468.25-Sta.5+530.59 w exceptions) 08/09/12 VIII 95.459 270 O 0.336 0.300 0.121 0.030 0.037 0.033 85.70 -

B. Vicencio Construction / Ezjones Construction Inc. (JV) JV-11-120 Const./Extension of Catarman River Control 08/08/13 VIII 85.828 290 C 0.376 0.200 0.300 - - - 87.60 88.92%

Satisfactory

B. Vicencio Construction / EZJones Construction, Inc. (JV) JV-11-120 Const./Extension of Catarman River Flood Control 03/21/13 VIII 85.828 290 O 0.370 0.300 0.120 0.030 0.045 0.033 89.80 -

B. Vicencio Construction / Jet Construction Supply (JV) JV-11-186 Conc. of Guimaras Circ. Rd., K067+380-K073+100 w/

exceptions 08/05/13 VI 102.300 450 C 0.466 0.133 0.300 - - - 89.90 89.42% Very Satisfactory

B. Vicencio Construction / Jet Construction Supply (JV) JV-11-186 Conc. of Guimaras Circ. Rd., K067+380-K073+100 w/

exceptions 11/19/12 VI 102.300 450 O 0.366 0.240 0.150 0.030 0.055 0.050 89.10 -

B. Vicencio Construction / Victoria Development and Construction

Supply (JV)Const. of 2-Storey, 2-CL Catbalogan NCHS 08/15/13 VIII 2.104 168 O 0.324 0.226 0.150 0.030 0.058 0.033 82.10 -

B. VICENCIO CONSTRUCTION/JQD CONSTRUCTION AND GENERAL

SERVICES JOINT VENTUREJV-13-371 Road Upgrading (gravel to Paved) along San Ricardo - Bil-

atan Km. 1101+000 - Km. 1102+000 8/5/2014 VIII 35.212 179 OG 0.382 0.222 0.150 0.022 0.045 0.017 83.80 -

B.A. LAGAZO BUILDERS Rehabilitation of Cross Drainage along MNR KO594+200 to KO594+700 w/ exception 10/22/2014 II 3.600 152 C 0.455 0.133 0.300 - - - 88.80% 88.80%

Satisfactory

B.C. Cuerpo Construction Corp. 11898Repair/Rehab. and Heightening of Dike w/ Slope Protection in Consuelo Norte, San Marcelino under POPSTIRP, Flood

Control Component03/23/12 III/BOM 8.915 113 C 0.371 0.148 0.300 - - - 81.90 77.40%

Unsatisfactory

B.C. CUERPO CONSTRUCTION CORPORATION 11898 Local Infrastructure Program: Construction of Multi-

Purpose Building 10/21/2014 XII 4.702 150 O 0.391 0.230 0.150 0.020 0.048 0.033 87.20% 87.20% Satisfactory

B.G. GIRON CONSTRUCTION & SUPPLY 15197 Construction of Multi-Purpose Building with Stage at Brgy.

Murcia (San Agustin) 11/20/2014 III 3.324 90 C 0.364 0.200 0.300 - - - 86.40% 86.40% Satisfactory

B.G. Giron Construction & Supply 15197 Const. of FMR at Brgys. Sta. Rita-Estrada, Sta.0+000-Sta.0+713 08/07/13 III 4.790 32 C 0.424 0.133 0.300 - - - 85.70 85.70%

Satisfactory

B.M Marketing 9852 Tacloban Airport Development Project 07/09/15 DOTC 128.741 240 C 0.469 0.200 0.300 - - - 96.94 95.15% Very Satisfactory

B.M. Marketing 9852 Tacloban Airport Development Project 07/08/15 DOTC 46.606 340 C 0.487 0.200 0.300 - - - 98.73 92.98% Very Satisfactory

B.M. MARKETING 9852 Rehab./Repair/Impv't of Baras - Candahug - Manlurip DZR Airport Road 8/10/2014 VIII 19.009 130 C 0.443 0.133 0.300 87.60 85.80%

Satisfactory

B.M. Marketing 9852 Tacloban Airport Development Project (Immediate Rehabilitation of Tacloban Airport) 03/18/15 DOTC 46.606 270 O 0.395 0.300 0.099 0.030 0.042 0.050 91.58 -

B.M. Marketing 9852 Tacloban Airport Development Project (Asphalt Overlay of Runway and Construction of Turn-Around Pad 03/19/15 DOTC 123.417 240 O 0.389 0.300 0.150 0.020 0.035 0.050 94.35 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page31

Page 32: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

B.M. Marketing 9852 Tacloban Airport Development Project 06/24/14 DOTC 42.467 180 O 0.379 0.300 0.150 0.030 0.035 0.050 94.36 -

B.M. Marketing 9852 Concrete Paving of Biliran Circ. Rd., Km.1061+100-Km.1061+800 (Acaban-Bool Rd. Sect.) 08/15/13 VIII 15.901 160 C 0.494 0.133 0.300 - - - 92.70 92.70%

Very Satisfactory

B.M. Marketing 9852 Rehab./Repair/Improvement of Baras-Candahug-Manlurip-DZR Airport Rd. 08/20/13 VIII 19.009 130 O 0.377 0.209 0.150 0.030 0.047 0.033 84.60 -

B.M. Marketing 9852 Concrete Paving of Biliran Circ. Rd., Km.1073+760-Km.1074+640 (Pinamihagan-Tanghas Rd. Sect.) 03/12/13 VIII 20.089 150 O 0.312 0.141 0.130 0.030 0.045 0.033 69.10 -

B.M. Marketing 9852 Const. (Completion) of Tigbao-Pulak Rd. 03/30/12 VIII 16.051 195 C 0.435 0.133 0.300 - - - 86.80 86.26% Satisfactory

B.M. Marketing 9852Concrete Paving of Biliran Circ. Rd., Tanghas-

Kaulangohan Rd. Sect., Km.1074+580-Km.1077+761 w/ exceptions

11/20/12 VIII 47.981 280 C 0.462 0.133 0.300 - - - 89.50 90.04% Very Satisfactory

B.M. Marketing 9852Concrete Paving of Biliran Circ. Road, Tanghas-

Kaulangohan Rd. Sect., Km.1074+580-Km.1077+761 w/ exceptions

08/07/12 VIII 47.981 280 O 0.334 0.300 0.150 0.030 0.040 0.050 90.40 -

B.M. Marketing 9852 Rd. Upgrading (Gravel to Paved) IS: Bagahupi-Babatngon-Sta. Cruz-Barugo-Carigara Rd. Chainage 585-2360 08/23/12 VIII 33.647 179 C 0.446 0.200 0.300 - - - 94.60 87.64%

Satisfactory

B.M. Marketing 9852 Concrete Paving of Biliran Circ.Road Tucdao-Inasuyan Sect. 08/07/12 VIII 16.283 215 C 0.433 0.200 0.300 - - - 93.30 86.94%

Satisfactory

B.M. Marketing 9852 Const. of Caraycaray Bridge & Approaches 08/20/12 VIII 31.139 260 C 0.473 0.200 0.300 - - - 97.30 82.78% Satisfactory

B.M. Marketing - B. Vicencio Construction JV-12-673 First District of Samar Ports Cluster Development Project 02/24/15 DOTC 26.995 210 C 0.428 0.200 0.300 - - - - 92.80%

Very SatisfactoryB.M. Marketing & Fiat Construction

Services (JV) 9852 Tacloban Airport Development Project 08/15/13 DOTC 176.112 300 O 0.329 0.277 0.150 0.030 0.056 0.050 89.20 -

B.M.K Construction 8292 Impvt. of Lingayen-Binmaley (via Matalava), Lingayen-Binmaley 08/28/09 I 23.809 359 O 0.349 0.300 0.077 0.030 0.055 0.033 84.40 -

B.M.K CONSTRUCTION/VIKING CONSTRUCTION & SUPPLIES (JV) JV-12-294 Repair/Rehabilitation/Construction of Flood Control

Structures, Bangbangar, Bangued, Abra 8/11/2014 CAR 37.853 260 C 0.431 0.133 0.300 86.40 88.85% Satisfactory

B.M.K. CONSTRUCTION 8292

Construction/Improvement of Sabangan-Sagada Road Leading to Poblacion Sagada, Sumaguing Cave, Hanging Coffins, Bomod-ok Falls, Bokong Falls, "MARCOS" Cave

(Declared Tourist Destination)

11/22/2014 CAR 135.100 421 O 0.346 0.238 0.150 0.030 0.056 0.050 87.00% 87.00% Satisfactory

B.M.K. Construction 8291 Widening of Pangasinan-Nueva Ecija Rd., K0181+749-K0184+000 (w/ exception), Bakit-Bakit 08/09/13 I 26.768 250 C 0.481 0.133 0.300 - - - 91.40 91.40%

Very Satisfactory

B.M.K. Construction 8291 Const./Continuation/Completion of Bagulin Bridge (Phase III) 07/31/13 I 109.073 645 C 0.481 0.133 0.300 - - - 91.40 91.34%

Very Satisfactory

B.M.K. Construction 8292 Const. of Shore Protection/Flood Control in La Union 2nd District-Groins & Extension of Groins, Brgy. San Carlos 07/31/13 I 27.358 240 C 0.429 0.133 0.300 - - - 86.20 87.04%

Satisfactory

B.M.K. Construction 8292 Const./Continuation/Completion of Bagulin Bridge (Phase III) 03/18/13 I 109.073 645 O 0.328 0.300 0.150 0.030 0.055 0.050 91.30 -

B.M.K. Construction 8292 Const. of Slope Protection/Flood Control in La Union 2nd Dist.-Groins & Extension of Groins, Brgy. San Carlos 03/12/13 I 27.359 240 O 0.379 0.300 0.150 0.015 0.015 0.017 87.60 -

B.M.K. Construction 8292CP 45, Restoration/Rehab. of Flood Control Facilities along Banila River in Umingan, under POPSTIRP, Flood Control

Component08/14/11 I / MFCP II-

PMO 29.035 90 O 0.320 0.240 0.150 0.030 0.060 0.050 85.00 -

B.M.K. Construction 8292 Road Upgrading along Baguio-Itogon Road K0254+(-622)-K0254+865 03/20/12 CAR 26.018 266 C 0.420 0.133 0.300 - - - 85.30 84.34%

Satisfactory

B.M.K. Construction 8292Restoration of Collapsed Retaining Wall & Damaged PCCP

along Baguio-Bontoc Rd., Km.267+700-Km.279+830 (POPSTIRP)

11/21/12 CAR 87.101 345 O 0.370 0.300 0.044 0.030 0.055 0.033 83.20 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page32

Page 33: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

B.M.K. Construction 8292 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd., K0251+000-K0253+600 MNR 11/24/12 I 44.805 240 C 0.394 0.200 0.300 - - - 89.40 87.78%

Satisfactory

B.M.K. Construction 8292 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds., K0214+243-K0216+613, Manila North Rd. 11/24/12 I 36.908 195 C 0.420 0.200 0.300 - - - 92.00 86.06%

Satisfactory

B.M.K. Construction 8292 Rd. Upgrading along Baguio-Itogon Rd. K0254+(-655)-K0260+531 07/30/12 CAR 26.018 266 C 0.374 0.194 0.300 - - - 86.80 84.94%

Satisfactory

B.M.K. Construction 8292 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd., K0251+000-K0253+600 Manila North Road 08/08/12 I 44.805 240 O 0.304 0.300 0.150 0.030 0.050 0.033 86.70 -

B.M.K. Construction 8292 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds., K0214+243-K0216+613, Manila North Rd. 08/08/12 I 36.908 195 O 0.231 0.300 0.150 0.030 0.060 0.050 82.10 -

B.M.K. Construction 8292 Rehab./Reconst./Upgrading of Pangasinan-La Union Inter-Prov'l Rd., K0382+330-K0385+600 03/16/13 I 58.500 285 C 0.439 0.133 0.300 - - - 87.20 87.20%

Satisfactory

B.M.K. Construction 8292Restoration of Collapsed Retaining Wall & Damaged PCCP

along Baguio-Bontoc Rd., Km.267+700-Km.279+830 (POPSTIRP), Roads & Bridges Component, Cluster RB4

08/01/13 CAR 87.101 345 C 0.475 0.133 0.300 - - - 90.80 86.24% Satisfactory

B.M.K. Construction / Jann-Norris Construction & Supplies (JV) JV-12-367 Repair/Maint. of Flood Control Structure along Magat

River, Batu Sect. 03/20/13 II 18.585 120 O 0.324 0.300 0.150 0.030 0.047 0.033 88.40 -

B.M.K. Construction / Jasa Builders (JV) JV-11-394

Rehab./Reconst./Upgrading of Pangasinan-Zambales Rd. a)Km.324+035-Km.324+895; b)Km.325+108-Km.326+552; c)Km.327+033-Km.327+293; d)Km.332+084-Km.332+560; e)Km.335+000-Km.337+500; f)Km.339+700-Km.339+780

03/15/13 I 98.561 360 O 0.375 0.223 0.150 0.030 0.055 0.050 88.30 -

B.M.K. Construction / R.N.G.M. Construction Joint Venture JV-12-655 Const./Widening/Upgrading of Access Rd. Leading to

Tourist Destination, Sabang 08/10/13 III 43.292 214 O 0.309 0.240 0.150 0.030 0.050 0.050 82.90 -

B.M.K. Construction / Viking Construction and Builders (JV) JV-12-296 Replacement of Bimmeclat Bridge K0436-386 03/20/13 I 27.325 180 O 0.382 0.262 0.096 0.030 0.043 0.033 84.60 -

B.M.K. Construction / Viking Construction and Supplies (JV) JV-12-294 Repair/Rehab./Const. of Flood Control Structure,

Banbangar 08/14/13 CAR 37.853 260 O 0.333 0.300 0.150 0.030 0.053 0.033 89.90 -

B.M.K. Construction / Viking Construction and Supplies (JV) JV-12-296 Replacement of Bimmeclat, KO436-386 08/13/13 I 27.325 202 O 0.394 0.300 0.065 0.030 0.047 0.033 86.90 -

B.P. Cruz Builders & Trading Development of Town Plaza and Sukol River Baywalk Project 02/06/14 TIEZA 4.988 90 C 0.437 0.190 0.300 - - - 92.63 92.63%

Very Satisfactory

B.P. Cruz Builders and Trading 33272 Rechanneling of River, Abacan River along Angeles-Mexico Sect. 08/06/13 III 16.588 120 C 0.375 - 0.500 - - - 87.50 87.50%

Satisfactory

B.P. Cruz Builders and Trading 33272 Rechanneling of Taug River 08/06/13 III 14.714 110 C 0.333 - 0.500 - - - 83.30 83.30% Satisfactory

B.P. Cruz Builders and Trading 33272Repair/Rehab. (incl. facilities) Phase II of Jose S. Lapid

District Hospital (formerly Porac District Hospital), Babo Sacan

07/31/13 III 18.594 75 C 0.491 0.133 0.300 - - - 92.40 85.82% Satisfactory

B.P. Cruz Builders and Trading 33272Flood Control & Drainage Project along Manila North Road

(MNR) @ K082+(-750)-K094+000 (w/ exception) Angeles City to Mabalacat

08/06/13 III 22.797 180 O 0.343 0.240 0.150 0.030 0.051 0.033 84.70 -

B.P. Cruz Builders and Trading 33272 Repair/Rehab. of Jose S. Lapid District Hospital, Phase II (Formerly Porac District Hospital), Babo Sacan 03/11/13 III 18.594 75 O 0.391 0.200 0.150 0.015 0.041 0.033 83.00 -

B.P. Cruz Builders and Trading 33272 Repair/Rehab. of Porac District Hospital, Babo Sect. 03/11/13 III 23.730 180 C 0.470 0.133 0.300 - - - 90.30 90.30% Very Satisfactory

B.P. CRUZBUILDERS AND TRADING 33272 Restoration of Porac-Gumain River Slope Protection, Sta.

Rita. Lubao, Pampanga 8/11/2014 III 13.607 120 C 0.427 0.135 0.300 86.20 86.20% Satisfactory

B.R.G. Construction 21931 Repair/Reconstruction of Damaged Paved National Roads along Daang Maharlika, K0292+000 to K0292+481 8/14/2014 II 7.523 75 C 0.406 0.133 0.300 83.90 83.90%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page33

Page 34: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

B.R.G. Construction 21931 Construction of Bridges, New (along Arterial Road) Pacquet Bridge along Aritao-Quirino Road 8/15/2014 II 9.129 150 OG 0.311 0.240 0.085 0.024 0.025 0.017 70.20 -

B.R.G. Construction 21931 Concreting of Aritao-Quirino Road, Bua Section 06/04/09 II 9.650 104 O 0.375 0.240 0.150 0.030 0.047 0.050 89.20 -B.S. BENIN CONSTRUCTION &

SUPPLIES 4537 Expansion of Quezon City General Hospital, Quezon City 8/14/2014 NCR 4.750 120 C 0.485 0.133 0.300 91.80 91.80% Very Satisfactory

B.VICENCIO CONSTRUCTION 9687 Construction/Rehabilitation of Drainage System Calbayog City Samar 1st 10/23/2014 VIII 9.470 240 C 0.363 0.200 0.300 - - - 86.30% 86.30%

Satisfactory

B.VICENCIO CONSTRUCTION 9687Rehabilitation /Reconstruction along Tacloban-Baybay South Road, K0915+(-267) - K0915+(-118.20) & K0915+(-

118.20)+K0915+607.8010/30/2014 VIII 13.054 183 C 0.298 0.200 0.300 - - - 79.80% 79.80%

Unsatisfactory

B.VICENCIO CONSTRUCTION 9687 Construction of Bridge, Rawis RCBC along Daang Maharlika (SM) San Isidro-San Juanico Bridge 10/23/2014 VIII 8.326 190 C 0.423 0.133 0.300 - - - 85.60% 85.60%

Satisfactory

B.VICENCIO CONSTRUCTION 9687 Construction/Rehabilitation of Flood Control Projects, Bato, Leyte 10/28/2014 VIII 12.972 150 C 0.429 0.133 0.300 - - - 86.20% 86.20%

Satisfactory

B.VICENCIO CONSTRUCTION 9687Rehabilitation/Reconstruction of Roadslip along Daang

Maharlika (SM) (San Isidro-San Juanico Bridge), K0778+400-K0788-500

10/23/2014 VIII 9.430 160 C 0.433 0.133 0.300 - - - 86.60% 86.60% Satisfactory

B.VICENCIO CONSTRUCTION 9687 Construction of Flood Control Structure along Burayan River 10/30/2014 VIII 9.874 110 O 0.360 0.300 0.100 0.030 0.055 0.033 87.80% 87.80%

Satisfactory

B.VICENCIO CONSTRUCTION 9687 Rehabilitation of Flood Control Structure, Brgy. San Policarpio 10/23/2014 VIII 13.954 202 C 0.445 0.133 0.000 - - - 57.80% 57.80%

Poor

B.VICENCIO CONSTRUCTION 9687 Rehabilitation of Flood Control Structure, 1st LD Brgy. San Policarpio Calbayog City, Samar 8/11/2014 VIII 13.954 172 OG 0.356 0.240 0.150 0.030 0.052 0.033 86.10 -

B-12 CONSTRUCTION AND TRADING CORPORATION 31997

Road Opening Capas-Botolan Road, Tarlac Section 2nd LD Realigned to Paving of Shoulder along Tarlac-Sta. Rosa

Road, Tarlac City, KO144+066.80 - KO147+778.00 w/ exception

11/20/2014 III 27.923 160 O 0.396 0.240 0.150 0.030 0.037 0.033 88.60% 88.60% Satisfactory

B-12 CONSTRUCTION AND TRADING CORPORATION 31997 Concreting of Road 11/20/2014 III 14.578 150 O 0.372 0.240 0.150 0.024 0.035 0.033 85.40% 85.40%

Satisfactory

B-12 CONSTRUCTION AND TRADING CORPORATION 31997 Repair/Rehabilitation of Gapan-San Fernando-Olongapo

Road, K0119+133 to K0119+1033 w/ exception 11/27/2014 III 17.803 120 C 0.399 0.176 0.300 - - - 87.50% 87.50% Satisfactory

B-12 Construction and Trading Corporation 31997

Prev. Maint. of Angeles-Porac-Floridablanca-Dinalupihan Rd. (Int. Sect.) 1.K0093+000-K0094+000 2.K0096+761-

K0097+84408/01/13 III 12.371 58 C 0.427 0.200 0.300 - - - 92.70 84.66%

Satisfactory

B-12 Construction and Trading Corporation 31997 Prev. Maint. of Angeles-Porac-Floridablanca-Dinalupihan

Rd. 03/11/13 III 12.371 58 O 0.348 0.202 0.150 0.020 0.040 0.033 79.30 -

B-12 Construction and Trading Corporation 31997 Prev. Maint. of Tabacan-Poblacion 03/12/13 III 8.705 60 C 0.434 0.133 0.300 - - - 86.70 86.70%

Satisfactory

B2K Lumber Construction Supplies and Services 33069

a. Prev. Maint. (Int. Sect.) Secondary Daet-Mercedes Rd. K0343+(-531)-K0343+469, K0343+469, K0344+369,

K0369+165-K0345+165 & K0346+000-K0348+661 ERRATA to: Rd. Widening Daang Maharlika (w/ exceptions)

K0340+174-K0343+679

03/23/13 V 40.491 150 O 0.286 0.290 0.150 0.024 0.040 0.033 82.30 -

B2K LUMBER, CONSTRUCTION SUPPLIES AND SERVICES 33069

Construction/Improvement of Access Roads leading to Airports, Seaports & Tourism Destinations, Pres. Cory

Aquino Blvd. to Bagabas Beach, Daet, Camarines Norte, Brgy. San Jose, Talisay

11/8/2014 V 14.351 135 C 0.447 0.133 0.300 - - - 88.00% 88.00% Satisfactory

B2K Lumber, Construction Supplies and Services 33069

Construction/Improvement of Access Roads leading to Airports, Seaports & Tourism Destinations, Pres. Cory

Aquino Blvd. to Bagasbas Beach8/5/2014 V 14.351 105 OG 0.322 0.300 0.150 0.020 0.025 0.050 86.70 -

B2K Lumber, Construction Supplies and Services 33069

Nat'l Rds. to other Strategic Tourist Destinations Pres. Cory Aquino Blvd. (Bagasbas to Mercedes Sect.), Brgy.

Bagasbas08/08/13 V 47.775 210 C 0.382 0.200 0.300 - - - 88.20 88.20%

Satisfactory

Badoc Builders & Supply (Formerly: Badoc Builders) 31564 Rd. Upgrading (Gravel to Paved), Batac-Pinili via Maipalig

Rd., K01480+112-K0481+104 08/14/13 I 9.309 80 C 0.439 0.174 0.300 - - - 91.30 85.66% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page34

Page 35: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Badoc Builders & Supply (Formerly: Badoc Builders) 31564 Rd. Upgrading (Gravel to Paved), Batac-Pinili via Maipalig

Rd., K0480+112-K0481+104 03/21/13 I 9.309 80 O 0.350 0.227 0.150 0.024 0.035 0.033 81.90 -

Badoc Builders & Supply / C.T. Leoncio Construction Trading (JV) JV-10-140 Rehab./Reconst./Upgrading of Nat'l Arterial Rd. MNR 08/04/12 I 64.955 240 C 0.272 0.200 0.300 - - - 77.20 82.36%

Satisfactory

BADOC BUILDERS AND SUPPLY (Formerly Builders) 31564

Rehabilitation/ Reconstruction/Upgrading of Damaged Paved National Roads Including Drainage Based on

Pavement Management System/Highway Development and Management-4 (HDM-4) of MNR Jct-Baay-Suba Road

K0482+754 to K0484+212

10/22/2014 I 24.343 213 C 0.363 0.200 0.300 - - - 86.30% 86.30% Satisfactory

BADSBRO CONSTRUCTION AND GENERAL MERCHANDISE 32876

Const. of Flood Control Structure (Revetment) along Imelda-Bayog-Kumalarang-Lapuyan-Margasatubig Rd, Brgy. Pilar, Diplahan, (K1763+793.95 - K1763+833.50),

Zamboanga Sibugay

10/25/2014 IX 3.893 80 O 0.000 0.150 0.150 0.030 0.040 0.033 40.30% 40.30% Poor

Bantay Construction 35290Repair/Rehab. of DPWH, Cebu 6th DEO (Phase II) Bldg. a)C. Cortes Ave. b)Repair/Maint. of DENR 7 Information

Center Bldg.08/13/13 VII 1.163 89 C 0.480 0.133 0.300 - - - 91.30 92.14%

Very Satisfactory

Bantay Construction 35290 Repair/Rehab. of DPWH Cebu 6th District Eng'g Office (Phase II) Bldg. A.C. Cortes Ave. 03/20/13 VII 1.162 73 O 0.369 0.300 0.150 0.030 0.028 0.050 92.70 -

BAQPRINCE CONSTRUCTION 28337Construction of Flood Control Projects, Cavite 1st LD,

Construction of Flood Control along Manila-Cavite Road, Brgy. San Juan (West Side). Noveleta Phase I

11/5/2014 IV 9.161 126 C 0.340 0.200 0.300 - - - 84.00% 84.00% Satisfactory

Baqprince Construction 28337

Assets Preservation of National Roads, Preventive Maintenance Based on Pavement Management

System/Highway Development and Management (HDM-4), (Intermittent Sections), National Arterial, Dasmarinas-

Trece Martires City-Naic Road, K0038+758-K0039+740 (6-5 lanes) & Tejero-Gen. Trias-Amadeo-Tagaytay Road,

K0045+600-K0045+870

8/5/2014 IV-A 16.669 55 C 0.408 0.200 0.300 90.80 90.80% Very Satisfactory

Bascon Bros & Development Co. 31387Construction of Lamo-Bulit Road, Brgy. Lamo & Anting

Road, Brgy. Malasin A. Construction of Lamo-Bulit Road, B. Construction of Anting Road

8/15/2014 II 4.297 60 C 0.322 0.133 0.300 75.50 75.50% Unsatisfactory

BC INTERNATIONAL BUILDERS CORPORATION 8576 Kalibo Airport Development Office 06/16/15 DOTC 24.550 120 C 0.450 0.200 0.300 - - - 95.00 95.00%

V.SatisfactoryBCT Trading & Construction 15199 Proposed Coron port Expansion Project 05/23/12 PPA 95.289 360 O 0.400 0.300 0.024 0.024 0.061 0.050 85.90 -BCT Trading & Construction 15199 Proposed Coron Port Expansion Project 09/28/12 PPA 95.289 360 O 0.394 0.294 0.076 0.024 0.061 0.050 89.90 -

BCT TRADING AND CONSTRUCTION 15199 Replacement of Camuran Bridge along Puerto Princesa Road 11/24/2014 IV 15.383 304 O 0.383 0.240 0.150 0.030 0.047 0.050 90.00% 90.00%

Very Satisfactory

BCT Trading and Construction 15199 Replacement of Caramuran Bridge along Puerto Princesa South Road 8/8/2014 IV-B 14.511 275 OG 0.368 0.267 0.150 0.030 0.040 0.033 88.80 -

BCT TRADING AND CONSTRUCTION 15199 San Vicente Airport Development Project 01/29/14 DOTC 50.161 360 O 0.378 0.300 0.150 0.010 0.045 0.050 82.80 -

BCT Trading and Construction 15199 Conc. of Puerto Princesa North Rd. (PPNR) Taytay (Pancol)-El Nido Rd. (Km.222+700-Km.225+000 w/ E) 08/09/13 IVB 49.791 270 C 0.445 0.197 0.300 - - - 94.20 89.64%

Very Satisfactory

BCT Trading and Construction 15199Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd.,

Puerto Princesa South Rd. (Mambalot-Ipilan Sect.) Km.176+000-Km.179+700 w/ exception

11/20/12 IVB 83.565 258 C 0.439 0.154 0.300 - - - 89.30 89.54% Very Satisfactory

BCT Trading and Construction 15199 Rd. Upgrading of (Gravel to Paved) of Puerto Princesa South Rd. (PPSR), (IS), K0113+736-K0114+000 11/21/12 IVB 5.400 207 C 0.450 0.142 0.300 - - - 89.20 89.44%

Very Satisfactory

BCT Trading and Construction 15199 Rehab./Reconst./Strengthening of Cabongan Bridge 1 along PPSR, K0010+058 11/19/12 IVB 9.753 228 C 0.435 0.133 0.300 - - - 86.80 88.84%

Satisfactory

BCT Trading and Construction 15199 Conc. of Puerto Princesa North Rd. (PPNR) Taytay (Pancol)-El Nido Rd. (Km.222+700-Km.225+000 w/ E) 11/22/12 IVB 49.791 270 O 0.319 0.284 0.150 0.030 0.050 0.033 86.60 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page35

Page 36: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

BCT Trading and Construction 15199 Rehab./Reconst./Strengthening of Cabongan Bridge I along PPSR, K0010+058 07/31/12 IVB 10.803 228 O 0.372 0.272 0.150 0.030 0.045 0.033 90.20 -

BCT Trading and Construction 15199 Rehab./Reconst./Upgrading Paved Nat'l Rd. (Mambalot-Ipilan Sect.) Km.176+000-Km.179+700) w/ exception 08/01/12 IVB 76.502 240 O 0.322 0.300 0.150 0.030 0.045 0.050 89.70 -

BCT Trading and Construction 15199 Roa Upgrading of (Gravel to Paved) of Puerto Princesa South Road (PPSR), (IS) b)K0113+736-K0114+000 08/04/12 IVB 5.399 180 O 0.331 0.290 0.150 0.030 0.045 0.050 89.60 -

BCT Trading and Construction 15199 Replacement of Banong Bridge along PPSR-Jct-Napsan-Apurawan Rd., K0041+015 03/15/13 IVB 11.508 266 C 0.441 0.133 0.300 - - - 87.40 87.40%

Satisfactory

BCT Trading and Construction 15199 Repair/Maint. of Puerto Princesa South Rd. Drainage Channel, Km.0+528-K0+667 (PPSR) 03/15/13 IVB 1.414 80 C 0.419 0.133 0.300 - - - 85.20 85.20%

SatisfactoryBCT TRADING AND

CONSTRUCTION 15199 Northern Palawan (Taytay) Airport Development Project 07/22/15 DOTC 45.825 240 C 0.491 0.200 0.000 - - - 69.10 69.10% Poor

BCT Trading and Construction 15199 San Vicente Airport Development Project 10/16/13 DOTC 56.132 360 O 0.400 0.300 0.150 0.010 0.045 0.050 95.45 -

Bemkar Construction 33047Prev. Maint. of Daang Maharlika, Km.337+000-Km.339+000

& Km.342+000-Km.344+500 Realigned to Km.340+(-60)-Km.341+058 & Km.341+058-Km.341+929

08/16/12 V 31.408 210 C 0.459 0.133 0.300 - - - 89.20 89.86% Very Satisfactory

Bench Construction and Supply 35899 Const. of MPB in Brgy. Mantang 08/19/13 VIII 2.460 90 C 0.479 0.133 0.300 - - - 91.20 91.20% Very Satisfactory

Bendimil Construction & Development Corporation 6135

Upgrading of Zamboanga City-Labuan-Limpapa Road (Gravel to Conrete) K1975+000 - K1977+100 w/ RCDG

Bridge Const. (Latap Bridge)8/5/2014 IX 45.954 806 C 0.432 0.134 0.300 86.60 78.23%

Unsatisfactory

Bendimil Construction & Development Corporation 6135

Upgrading of Zamboanga City-Labuan-Limpapa Rd (Gravel to Concrete) K1975+000-K1977+100 w/ RCDG Bridge

Const. (Latap Bridge)08/05/13 IX 43.655 435 O 0.130 0.240 0.000 0.020 0.047 0.033 47.00 -

Bendimil Construction & Development Corporation 6135

Upgrading of Zamboanga City-Labuan-Limpapa Rd. (Gravel to Concrete) K1975+000-K1977+100 w/ RCDG

Bridge Const. (Latap Bridge)03/12/13 IX 43.655 360 O 0.364 0.240 0.108 0.030 0.051 0.033 82.60 -

Bendimil Construction & Development Corporation 6135

Upgrading Zamboanga City-Labuan-Limpapa Rd. (Gravel to Concrete) K1975+000-K1977+100 w/ RCDG Bridge

Const. (Latap Bridge)11/19/12 IX 43.655 330 O 0.192 0.253 0.150 0.030 0.060 0.050 73.50 -

Bendimil Construction & Development Corporation 6135

Upgrading of Zamboanga City-Labuan-Limpapa Rd. (Gravel to Concrete) K1975+000-K1977+100 w/ RCDG

Bridge Const. (Latap Bridge)08/13/12 IX 43.655 330 O 0.400 0.237 0.150 0.023 0.032 0.033 87.50 -

Bendimil Construction and Development Corp. 6135 Impvt./Gravelling of Siocon-Sirawai Road (Sirawai Side) 08/26/08 IX 47.894 300 O 0.158 0.225 0.000 0.030 0.033 0.067 51.30 -

Berson's Const. & Trading 31181 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. K0258+000-K0259+730, Manila North Rd. 11/24/12 I 32.035 210 C 0.401 0.200 0.300 - - - 90.10 86.86%

Satisfactory

BERSON's CONSTRUCTION & TRADING 31181

Preventive Maintenance Based PMS/HDM-4 (Intermittent Section) Pangasinan-Zambales Road K0328+367 to K0329+533, K0337+823 to K0339+704/K0337+400 to

K0339+300(New Station)

10/27/2014 I 24.929 159 C 0.433 0.135 0.300 - - - 86.80% 86.80% Satisfactory

BERSON's CONSTRUCTION & TRADING 31181 Rehabilitation/Reconstruction along Binmaley Beach Road

K0368+608 to K0369+201 10/28/2014 I 9.553 133 C 0.345 0.200 0.300 - - - 84.50% 84.50% Satisfactory

Berson's Construction & Trading 31181 Widening of Urdaneta Jct.-Dagupan Road, K0190+734 - K0192+096 8/12/2014 I 18.159 210 C 0.403 0.133 0.300 83.60 84.53%

Satisfactory

Berson's Construction & Trading 31181 Widening of San-Carlos Road (San Carlos Section), Km. 203+960 to Km. 204+330 8/12/2014 I 8.539 140 C 0.415 0.200 0.000 61.50 71.52%

Poor

Berson's Construction & Trading 31181Prev. Maint. (Int. Sect.) along Pangasinan-Zambales Rd.

K0318+000 w/ exception, K0318+1000-K0319+734 w/ exception K0320+742-K0322+451 w/ exception

08/08/13 I 28.664 100 C 0.458 0.133 0.300 - - - 89.10 89.10% Very Satisfactory

Berson's Construction & Trading 31181Prev. Maint. along Alaminos-Lucap Rd., K0321+(-107)-

K0321+00 w/ exception; K0321+000-K0322+446 w/ exception

08/08/13 I 14.318 71 C 0.479 0.133 0.300 - - - 91.20 91.26% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page36

Page 37: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Berson's Construction & Trading 31181 Widening of Urdaneta Jct.-Dagupan Rd., K0190+734-K0192+096 w/ exception 08/02/13 I 16.512 210 S 0.331 0.233 0.150 0.030 0.042 0.050 83.60 -

Berson's Construction & Trading 31181 Widening of San Carlos-Calasiao Rd. (San Carlos Sect.) Km.203+960-Km.204+330 08/03/13 I 8.539 183 O 0.350 0.300 0.018 0.030 0.051 0.033 78.20 -

Berson's Construction & Trading 31181Prev. Maint. along Alaminos-Lucap Rd., K0321+(-107)-

K0321+000 w/ exception; K0321+000-K0322+446 w/ exception

03/15/13 I 14.318 71 O 0.385 0.300 0.150 0.015 0.030 0.033 91.30 -

Berson's Construction & Trading 31181 Widening of Urdaneta Jct.-Dagupan Rd., K0190+734-K0192+096 w/ exception 03/14/13 I 16.512 180 O 0.345 0.291 0.150 0.018 0.030 0.033 86.70 -

Berson's Construction & Trading 31181 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. K0258+000-K0259+730, Manila North Rd. 08/08/12 I 30.881 195 O 0.269 0.300 0.150 0.030 0.065 0.033 84.70 -

Berson's Construction & Trading 31181Rehab./Impvt./Upgrading along Camiling-Wawa-

Bayambang-Malasiqui-Sta. Barbara Rd., Km.183+050-Km.184+000 Nalsian Norte, Bayambang Sect.

08/13/12 I 9.366 105 C 0.339 0.184 0.300 - - - 82.30 82.30% Satisfactory

BET CONSTRUCTION & SUPPLY 31764 Widening of Urdaneta Jctn.-Lingayen Road via Zambales, K0373+507-K0374+900 10/28/2014 I 25.775 180 O 0.312 0.300 0.150 0.030 0.047 0.050 88.90% 88.90%

Satisfactory

BET Construction & Supply 31764 Preventive Maintenance of Pangasinan-La Union Inter-Provincial Road, K0399+495 to K0403+025 with exceptions 8/13/2014 I 44.119 180 C 0.428 0.133 0.300 86.10 85.68%

Satisfactory

BET Construction & Supply 31764Rehabilitation/ Reconstruction/Upgrading of Damaged

Paved National Road (A.B. Fernandez Ave., Dagupan City) (Pangasinan-Zambales Road, K0377+612 to K0378+700)

8/13/2014 I 46.039 210 C 0.455 0.078 0.300 83.30 84.32% Satisfactory

BET Construction & Supply 31764 River Bank Protection along Mangueragday River (Phase II) 8/13/2014 I 28.036 210 C 0.412 0.108 0.300 82.00 83.50%

Satisfactory

Bet Construction & Supply 31764 Rehab./Reconst./Upgrading of Paved Nat'l Rd., Widening of Mangaldan-Manaoag-Binalonan Rd. 08/05/13 I 18.528 195 C 0.480 0.133 0.300 - - - 91.30 91.30%

Very Satisfactory

Bet Construction & Supply 71764 Prev. Maint. of Pangasinan-La Union Inter-Prov. Rd., K0399+495-K0403+025 w/ exception 08/06/13 I 44.119 180 O 0.382 0.217 0.150 0.030 0.042 0.033 85.40 -

Bet Construction & Supply 31764Rehab./Reconst./Upgrading of Damaged Paved Nat' Rd.

(Pangasinan-Zambales Rd.) Jct. Lingayen Rd. (K0377+612-K0378+700 A.B. Fernandez Ave.)

08/05/13 I 45.764 180 O 0.355 0.240 0.150 0.030 0.042 0.033 85.00 -

Bet Construction & Supply 31764 River Bank Protection along Mangueragtay River (Phase II), Bonoan 08/06/13 I 28.040 180 O 0.350 0.240 0.150 0.030 0.042 0.033 84.50 -

Bet Construction & Supply 31764 Prev. Maint. of Dagupan-Bonuan-San Fabian Rd., K0383+720-K0385+733 03/16/13 I 13.882 54 C 0.472 0.133 0.300 - - - 90.50 90.50%

Very Satisfactory

Better Work Construction 24432Replacement/Rehab./Strengthening of Permanent Bridges Gen. from Bridge Mgt. System (BMS), Sapu-Masla Bridge

along Sarangani-Davao del Sur Coastal Rd.08/20/13 XII 4.514 130 C 0.391 0.200 0.300 - - - 89.10 89.10%

Very Satisfactory

Bicol Goldrock Construction Corp./GCI. Construction and

Development Corp. (JV)JV-11-625 Rd. Upgrading (Gravel to Paved), Catanduanes Circ. Rd. 07/30/13 V 52.691 282 C 0.420 0.133 0.300 - - - 85.30 85.30%

Satisfactory

BICOL GOLDROCK CONSTRUCTION CORPORATION 32376

Const./Imprvt. Of Access Road Leading to Declared Tourism Destination along Pili-Tigaon-Albay Road (Pili-

Ocampo Section), Ocampo, Camarines Sur11/11/2014 V 18.030 149 C 0.463 0.134 0.300 - - - 89.70% 89.70%

Very Satisfactory

BICOL GOLDROCK CONSTRUCTION CORPORATION 32376 Const./Imprvt. Of Magarao River Control, Magarao,

Camarines Sur 11/11/2014 V 17.681 168 C 0.460 0.133 0.300 - - - 89.30% 89.30% Very Satisfactory

BICOL GOLDROCK CONSTRUCTION CORPORATION 32376 Dredging/Revetment at Lake Bato, Western Side, Bato,

Camarines Sur, Sta. 0+000 to Sta. 0+443 11/12/2014 V 45.655 244 C 0.460 0.133 0.300 - - - 89.30% 89.30% Very Satisfactory

BICOL GOLDROCK CONSTRUCTION CORPORATION 32376

Paving of Shoulders (Seal Widening) along Nabua-Balatan Road including Slope Protection (Binodegahan Section),

Balatan, Camarines Sur, K0487+942-K0488+356 w/ exception

11/12/2014 V 18.153 207 C 0.466 0.133 0.300 - - - 89.90% 89.90% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page37

Page 38: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Bicol Goldrock Construction Corporation 32376 Construction of Flood Control, Camarines Sur 1st DEO,

Milaor Flood Control 8/7/2014 V 9.150 100 C 0.375 0.200 0.300 87.50 87.50% Satisfactory

Bicol Goldrock Construction Corporation 32376 Construction/Rehabilitation/Improvement of Magarao River

Control 8/8/2014 V 17.681 168 OG 0.304 0.300 0.141 0.020 0.051 0.033 84.90 -

Bicol Goldrock Construction Corporation 32376 Contract Package XIX (B)-Drainage Protecton Woks along

National Rds., Sta. Maria Sect. 08/01/13 V 5.393 239 C 0.462 0.120 0.300 - - - 88.20 88.20% Satisfactory

Bicol Goldrock Construction Corporation 32376 BRBWMP (Flood Mitigation Component II:2012 a) Buhi

Flood Control, Buhi, b) Bula Flood Control 03/21/13 V 47.990 256 C 0.420 0.133 0.300 - - - 85.30 87.94% Satisfactory

Bicol Goldrock Construction Corporation / EGB Construction

(JV)JV-11-574 Rehab. of Cagayan-Apayao (CAR), Fugu Sect. 08/04/13 II 48.694 360 C 0.426 0.200 0.300 - - - 92.60 92.66%

Very Satisfactory

Bicol Goldrock Construction Corporation / EGB Construction

Joint VentureJV-11-574 Rehab. of Cagayan-Apayao Rd. (CAR), Fugu Sect. 11/19/12 II 45.231 300 O 0.398 0.240 0.150 0.030 0.059 0.050 92.70 -

Bicol Goldrock Construction Corporation/GCI Construction and

Development Corp. (JV)JV-12-286

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved

Road Standard (HDM-4 Project Analysis), CCR, Cabungahan Section, (K0156+850 - K0159+000)

8/14/2014 V 48.247 206 C 0.385 0.200 0.300 88.50 86.40% Satisfactory

Bicol Goldrock Construction Corporation/GCI. Construction and

Development Corp. (JV)JV-12-173 Prev. Maint. Asphalt Overlay along Naga-Calabanga-

Balongay Road (Int. Sect.), Bombon & Calabanga 08/06/13 V 18.266 54 C 0.325 0.200 0.300 - - - 82.50 82.50% Satisfactory

Bicol Goldrock Construction Corporation/GCI. Construction and

Development Corp. (JV)JV-12-286 Road Upgrading (Gravel to Paved), CCR Cabungahan Sect,

(K0156+850 - K0159+000) 07/30/13 V 48.247 184 O 0.361 0.283 0.085 0.030 0.058 0.033 85.00 -

BIG JOE'S ENTERPRISES 33601 Cluster I - Rehabiliation of Barangay Road at; 1) Barangay Canmoros, Binalbagan 10/23/2014 VI 1.866 60 C 0.430 0.133 0.300 - - - 86.30% 86.30%

Satisfactory

BIG JOE'S ENTERPRISES 33601

Road Upgrading of Vallehermoso - Canla-on City - La Castellana Road (Intermittent Section), a) K0081+702 -

K0081+819, b) K0082+808 - K0082+905 & c) K0083+138 - K0083+218 (Gravel to Paved) Barangay Biak na Bato

10/24/2014 VI 19.942 153 C 0.451 0.133 0.300 - - - 88.40% 88.40% Satisfactory

Big Joe's Enterprises 33601 Reconst. of Nat'l Sec. Rd. along Binalbagan-Isabela Rd., a)K0065+004-K0065+146, b)K0067+200-K0067+866 08/10/13 VI 11.438 179 O 0.350 0.300 0.017 0.030 0.042 0.050 78.90 -

Big Joe's Enterprises 33601 Reconst. of Nat'l Secondary Rd. along Binalbagan-Isabela Rd., a) K0065+004-K0065+146, b) K0067+200-K0067+866 03/12/13 VI 11.438 119 O 0.345 0.295 0.150 0.015 0.040 0.033 87.80 -

Billena Construction 7431 Rehab. of Morocco-Particion-Anono-o-Cabubugan Rd. 03/17/13 VI 4.726 60 O 0.367 0.200 0.300 - - - 86.70 86.70% Satisfactory

Billena Construction/D.M. House Construction, Inc. (JV) JV-08-145 Conc. of Bantayan-San Pedro-Cubay Road, San Jose and

Sibalom 09/02/09 VI 27.016 360 O 0.356 0.239 0.150 0.015 0.025 0.033 81.80 -

Billfinger Builders Development Corporation 35802 Impv't./Riprapping along Don Jose Creek (P. Tuazon-

Evangelista Creek) 08/02/13 NCR 1.338 60 C 0.458 0.133 0.300 - - - 89.10 89.10% Very Satisfactory

Billhill Construction and Supply 18046 Conc. of Road, Brgy. Tolingon 08/08/13 XIII 1.934 84 C 0.427 0.133 0.300 - - - 86.00 86.00% Satisfactory

Bilrey Const./Eddmari Const./CS Garcia Const.-JV

Procurement of Fully Developed Lots & Completed Housing Units Under the NHA's Yolanda Permanent

Housing Program at Ridge View Park Phase 103/13/15 NHA 289.938 405 O 0.363 0.000 0.150 0.030 0.023 0.050 61.60 -

Bilrey Construction Z3R Tulungatung Housing Project 03/27/15 NHA 78.620 210 O 0.360 0.300 0.035 0.030 0.057 0.033 81.58 -

Bilrey Construction 32877 Construction of Livelihood, Production & Training Center (Building) 09/29/10 NHA 4.990 90 O 0.391 0.300 0.150 0.030 0.065 0.050 98.67 -

Bilrey Construction/Eddmari Construction & Trading JV Antonino Heights 09/11/15 NHA 289.932 365 O 0.294 0.256 0.150 0.030 0.059 0.050 83.89 -

BISLIG VENTURE CONSTRUCTION & DEVT, INC. 36370 Local Infrastructure Program-Construction of Three (3)

Barrel Box Culvert, Brgy. Mangagoy 10/24/2014 XIII 2.680 90 O 0.297 0.265 0.150 0.020 0.051 0.050 83.30% 83.30% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page38

Page 39: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

BISLIG VENTURE CONSTRUCTION & DEV'T, INC. 36370 Local Infrastructure Program-Construction of Multi-

Purpose Building, DepEd, Bislig City Division Office 10/24/2014 XIII 4.701 175 O 0.338 0.250 0.150 0.020 0.059 0.050 86.70% 86.70% Satisfactory

BISLIG VENTURES CONSTRUCTION & DEVELOPMENT

INC36370 Bislig City IDP-IC LCB-SDS-BCIDP-IC(LP-5)-10-2013 06/07/14 NIA 7.026 200 C 0.407 0.199 0.300 - - - 90.60 90.60%

Very Satisfactory

BL Jadulco Construction & Supply 33684 Const. of Dainage in the Municipality of Naval 08/26/10 VIII 1.926 100 O 0.397 0.240 0.150 0.030 0.042 0.033 89.20 -

BLACKRAM BUILDERS, INC. 33899

Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects-

Construction/Rehabilitation of various Projects in 6th LD - Rehab. Of Road/Drainage along V. Mapa Extension and

Vicinity, Zone 59

11/24/2014 NCR 4.594 90 C 0.466 0.133 0.300 - - - 89.90% 89.90% Very Satisfactory

BLACKRAM BUILDERS, INC. 33899 Repair/Rehabilitation of Ragay District Hospital 11/9/2014 V 4.751 284 C 0.464 0.133 0.254 - - - 85.10% 85.10% Satisfactory

BLC Construction & Aggregates 16424 Upgrading of Dantay-Sagada Rd. (K0391+000-K0391+677 & K0392+603-K0393+048.2) 08/03/13 CAR 30.600 159 O 0.365 0.240 0.150 0.023 0.040 0.033 85.10 -

BLC Construction & Aggregates 16424 Upgrading of Dantay-Sagada Rd., K0387+782-K0388+694 & K0389+415-K0390+465 03/16/13 CAR 36.794 240 C 0.345 0.184 0.000 - - - 52.90 63.43%

Poor

BLIMEX CONSTRUCTION AND SUPPLY 27259

Road Upgrading (Gravel to Concrete) Based on Gravel Road Strategies, Traffic Benchmarks (HDM-4 Project

Analysis), Argao - Moalboal Road, K0072+630 to K0073+564

10/24/2014 VII 26.194 127 C 0.377 0.200 0.300 - - - 87.70% 87.70% Satisfactory

BLIMEX CONSTRUCTION AND SUPPLY 27259

Repair/Restoration of Damaged Slope Protection and Slope Lined Canal along Santande - Barili - Toledo Road

(SBTR)8/5/2014 VII 9.733 140 C 0.428 0.151 0.300 87.90 85.74%

Satisfactory

BLIMEX CONSTRUCTION AND SUPPLY 27259

Road Upgrading (Gravel to Concrete) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road Standard (HDM-4 Project Analysis) along

Awang-Upi-Lebak - Kalamansig - Palimbang - Sarangani Road, Km.2036+896 - Km. 2038+728 with exception

8/14/2014 XII 39.234 172 C 0.464 0.133 0.300 89.70 86.80% Satisfactory

Blimex Construction and Supply 27259Repair/Restoration of Damaged Slope Protection & Slope Line Canal along Santander-Barili-Toledo Rd., K0170+250-

K0221+869 (Int. Sect.)08/09/13 VII 9.733 140 O 0.310 0.248 0.150 0.030 0.055 0.050 84.30 -

Blimex Construction and Supply 27259Rd. Upgrading (Gravel to Concrete) along Awang-Upi-

Lebak-Kalamansig-Palimbang-Sarangani Rd. (Km.2036+896-Km.2038+728 w/ exception)

08/18/13 XII 39.234 172 O 0.339 0.236 0.150 0.023 0.051 0.050 84.90 -

Blimex Construction and Supply 27259 Const. of Public Market, Poblacion 03/18/13 VII 0.981 60 C 0.437 0.133 0.300 - - - 87.00 87.00% Satisfactory

Blimex Construction and Supply 27259Slope Protection at Intermittent Sect. along Contract Package 3 Maguindanao/Sultan Kudarat Bdry.-Lebak-

Kalamansig Rd. (Km.1925+000-Km.1938+000)03/14/13 XII 18.809 160 C 0.350 0.198 0.300 - - - 84.80 84.80%

Satisfactory

BLUE EAGLE CONSTRUCTION COMPANY 10915 Marinduque Airport Development Project 08/06/15 DOTC 6.061 150 O 0.382 0.300 0.055 0.000 0.012 0.000 74.90 -

BLUE EAGLE CONSTRUCTION COMPANY 10915 Marinduque Airport Development Project 04/08/15 DOTC 4.028 150 O 0.341 0.300 0.000 0.010 0.009 0.033 69.30 -

Blue Eagle Construction Company 10915 Boac LTO District Office Development Project 11/27/14 DOTC 4.028 150 C 0.440 0.200 0.300 - - - 94.03 94.03% Very Satisfactory

Blue Mountain Builders & General Mdse Rehabilitation of Caruan Protection Works, MNR 8/9/2014 I 7.187 67 C 0.491 0.133 0.300 92.40 92.40%

Very Satisfactory

BMJ Construction 14571 Conc. of Ilagan-Delfin, Albano-Mallig Road, Delfin Albano Sect., K0341+067-K0431+670, K0431+670-K0433+491 03/16/12 II 22.292 202 C 0.235 0.200 0.300 - - - 73.50 76.08%

Unsatisfactory

BMJ Construction 14571 Conc. of Ilagan-Delfin, Albano-Mallig Road, Tumauini Section, K0421+175-K0421+997 03/16/12 II 7.597 97 C 0.082 0.200 0.300 - - - 58.20 72.60%

Unsatisfactory

BMJ Construction 14571 MARIIS Sivision 3 - Improvement Projects 07/27/12 NIA 9.441 120 O 0.360 0.300 0.081 0.030 0.032 0.050 85.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page39

Page 40: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

BMK Construction 8292 Const. San Angel Small Reservoir Irrigation Project (Canal Structures) 05/12-14/11 NIA 12.808 180 O 0.351 0.276 0.150 0.024 0.037 0.050 88.85 -

BMK Construction / E.T. Latawan Construction (JV) JV-09-115 Road Upgrading of Dantay-Sagada Rd. KM384+700-

KM398+100 03/16/12 CAR 48.020 380 C 0.431 0.133 0.300 - - - 86.40 85.83% Satisfactory

BMK CONSTRUCTION/R.N.G.M. CONSTRUCTION (J.V.) 30458

Construction/Improvement of Access Roads Leading to Declared Tourism Destination, Sabang-Baler Road Leading

to Sabang Garden Malls and Garden Plaza8/8/2014 III 45.890 240 OG 0.342 0.240 0.150 0.012 0.056 0.033 83.30 -

BN BUILDERS CONSTRUCTION & SUPPLIES 28232 Rehabilitation of Multi-Purpose Building, Brgy. Poblacion 10/20/2014 XIII 1.961 90 C 0.416 0.153 0.300 - - - 86.90% 86.90%

SatisfactoryBNG Construction and General

Services 18503 Rd. Upgrading (Gravel to Concrete), Quezon-Capalayan-Espina-Navarro Rd., Arellano Dist. 09/07/09 XIII 9.231 253 O 0.378 0.225 0.150 0.030 0.054 0.033 87.00 -

BNL Construction 15725 Const. of Flood Control Structure (Slope Protection) along Nat'l Rd. (Almeria to Kawayan Rd. Sect.) 08/15/13 VIII 5.463 75 C 0.441 0.133 0.300 - - - 87.40 87.40%

Satisfactory

BNR Construction & Development Corporation 12903 Prev. Maint. (Int. Sect.), Arterial Rd., N. Bacalso Ave. (Cebu

South), K0007+000-K0008+390 08/24/13 VII 39.479 95 C 0.405 0.136 0.300 - - - 84.10 84.10% Satisfactory

BNR Construction & Development Corporation 12903

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. at Pajo-Basak-Marigondon Rd., Lapu-Lapu City, K0011+(-624)-

K0011+45708/12/13 VII 21.066 179 C 0.334 0.200 0.300 - - - 83.40 83.40%

Satisfactory

BNR Construction & Development Corporation 12903

Widening of Nat'l Rd. at Cebu North Hagnaya Wharf Rd., K0013+560-K0014+505 (Proposed for

Realignment/Modification to Impv't. of Nat'l Rd. at Cebu North Hagnaya Wharf Road, K0013+560-K0014+505

08/12/13 VII 25.800 300 O 0.356 0.232 0.150 0.030 0.055 0.050 87.30 -

BNR Construction & Development Corporation 12903 Const. of Drainage along Cebu North Hagnaya Wharf Road 03/24/12 VII 18.626 150 C 0.426 0.133 0.300 - - - 85.90 84.64%

SatisfactoryBNR CONSTRUCTION &

DEVELOPMENT CORPORATION/ZION CONSTRUCTION -JV

JV-13-452Upgrading of Access Road Leading to White Beach,

Section 1) Sta. 0+000 to Sta. 1+947.344; Section 2) Sta. 0+000 to Sta. 5+867.673

10/25/2014 VII 115.295 270 O 0.324 0.300 0.085 0.030 0.050 0.050 83.90% 83.90% Satisfactory

BNR CONSTRUCTION AND DEVELOPMENT CORPORATION 12963

Widening of National Road at Cebu Hagnaya Wharf Road, Consolacion, Cebu. K0013+560 to K0014+505 (Proposed

for Realignment/Modification to Imprv't of National Road at Cebu North Hagnaya Wharf Road, Consolacion, Cebu,

K0013+560 to K0014+505

8/8/2014 VII 27.330 330 C 0.408 0.146 0.300 85.40 86.54% Satisfactory

BNYU ENTERPRISE & CONSTRUCTION 27725 BERRRP-Cahayag (Tubigon) - Causwagan Sur (San Isidro)

Road 05/14/15 Bohol 17.801 307 C 0.500 0.200 0.300 - - - 100.00 100.00% Outstanding

BNYU Enterprises & Construction 27725 Talibon Area 07/13/13 NIA 3.867 120 O 0.370 0.300 0.150 0.020 0.060 0.050 95.00 -

BNYU ENTERPRISES AND CONSTRUCTION 27725 Road Upgrading (Gravel to Paved) Jct. (TNR), Cortes -

Balilihan - Catigbian - Macaas Road 8/13/2014 VII 18.002 170 C 0.399 0.179 0.300 87.80 91.22% Very Satisfactory

BNYU Enterprises and Construction 27725 PW-BHL-13-12 Emergency Repair & Rehabilitation of

calape-Pangangan Road 01/19/15 Bohol 10.242 165 O 0.380 0.299 0.150 0.030 0.060 0.033 95.20 -

BNYU Enterprises and Construction 27725 Rd. Upgrading (Gravel to Paved) Jct. (TNR) Cortes-

Balilihan-Catigbian-Macaas Rd., Km.46+045-Km.46+575 08/17/13 VII 18.966 245 O 0.380 0.260 0.150 0.030 0.065 0.050 93.50 -

BNYU Enterprises and Construction 27725 Talibon Small Reservoir Irrigation Project 9/29/08 10/3/08 NIA 4.990 210 O 0.328 0.173 0.100 0.030 0.047 0.200 87.80 -

BNYU Enterprises and Construction 27725 Upgrading of Jct. Dat-an, Carmen-Sierra Bullones-Pilar-

Alicia Road, K0089+320-K0090+257.92 08/09/12 VII 16.428 150 C 0.455 0.133 0.300 - - - 88.80 88.56% Satisfactory

BOADO ENGINEERING DESIGN AND CONSTRUCTION 25913 Construction of 1 Storey 3 Classroom School Building

Capas Integrated School 10/26/2014 I 1.781 90 C 0.414 0.188 0.300 - - - 90.20% 90.20% Very Satisfactory

Boado Engineering Design and Construction 25913 Const. of FMR, Sta. Maria 08/01/13 I 6.825 120 C 0.427 0.133 0.300 - - - 86.00 86.00%

Satisfactory

Bomel Construction 32878 Conc. of FMR, Brgy. Lusacan 08/03/13 IVA 2.340 30 C 0.323 0.200 0.300 - - - 82.30 82.30% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page40

Page 41: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Bomel Construction 32878Reblocking of MSR Old Route and MSR Daang Maharlika, Km.125+(-325)-Km.125+(-3), Km.121+896-Km.124+652 with

exception03/17/12 IVA 4.875 102 C 0.438 0.200 0.300 - - - 93.80 87.62%

Satisfactory

Bomel Construction 32878 Moran Communal Irrigation System 09/07/13 NIA 17.479 C 0.421 0.133 0.300 - - - 85.45 85.45% Satisfactory

Bonifacio M. Carlos Construction (Formerly: Bonifacio M. Carlos

Construction)3303 Conc. of Puerto Princesa South Road K0010+041-

K0010+560 07/31/12 IVB 13.000 134 C 0.413 0.200 0.300 - - - 91.30 89.68% Very Satisfactory

BONIFACIO M. CARLOS CONSTRUCTION CORP. 3303 Road Upgrading (Gravel to Paved) of PPSR Jct. Napsan-

Apurawan Road, K0028+731-K0029+237 11/24/2014 IV 7.321 92 C 0.444 0.133 0.300 - - - 87.70% 87.70% Satisfactory

Bonifacio M. Carlos Construction Corp. (Formerly: Bonifacio M.

Carlos Construction)3303

Road Upgrading (Gravel to Paved) of PPSR Jct. - Napsan - Apurawan Road - K0041+100 to K0042+138 and K0042+138

to K0042+5888/8/2014 IV-B 33.523 283 C 0.463 0.135 0.300 89.80 79.00%

Unsatisfactory

Bonifacio M. Carlos Construction Corp. (Formerly: Bonifacio M.

Carlos Construction)3303

Road Upgrading (Gravel to Paved) of PPSR Jct. - Napsan - Apurawan Road - K0027+967 to K0028+731 and K0028+731

to K0029+2378/8/2014 IV-B 20.431 113 OG 0.387 0.210 0.000 0.030 0.050 0.033 71.00 -

Bonifacio M. Carlos Trading Corp. (Formerly: Bonifacio M. Carlos

Construction)3303

Rd. Upgrading (Gravel to Paved) of PPSR Jct.-Napsan-Apurawan Rd., K0041+100-K0042+138 & K0042+138-

K0042+58808/15/13 IVB 33.940 201 O 0.355 0.091 0.150 0.030 0.042 0.050 71.80 -

Bonimar Construction Enterprises 23760 Reconst./Widening of Manila North Rd., K0262+497-K0264+236 11/24/12 I 31.436 240 C 0.397 0.200 0.300 - - - 89.70 84.60%

Satisfactory

Bonimar Construction Enterprises 23760 Reconst./Widening of Manila North Rd., K0262+497-K0264+236 08/08/12 I 30.098 240 O 0.249 0.300 0.150 0.030 0.050 0.033 81.20 -

BORDERLINE CONSTRUCTION AND SUPPLY 24433 Construction of Road, Brgy. Tacupan to Brgy. Ranzo,

Carmen, Cotabato Km. 1642+669 to Km. 1643+060 10/25/2014 XII 5.527 68 C 0.448 0.133 0.300 - - - 88.10% 88.10% Satisfactory

Borobudur Construction 21497Const. of Classrooms in Areas Experiencing Acute

Classroom Shortage Cluster I: Elem. & Sec. Sch. at Milaor-Gainza, Pamplona San Fernando & Minalabac

08/05/13 V 1.092 120 C 0.455 0.133 0.300 - - - 88.80 88.80% Satisfactory

BRE CONSTRUCTION 32605Const. of Slope Protection Works along Awang-Upi-Lebak -

Kalamansig Road (Awang Junction - DOS - Nuro) Km.1844+790 - Km.1875+148.20 with exception

8/12/2014 XII 9.646 230 C 0.417 0.200 0.300 91.70 85.94% Satisfactory

Bre Construction 32605Const. of Slope Protection Works along Awang-Upi-Lebak-

Kalamansig Rd. (Awang Jct.-DOS-Nuro) Km.1844+970-Km.1875+148.20 w/ exception

08/13/13 XII 9.397 220 O 0.335 0.240 0.150 0.020 0.043 0.033 82.10 -

BRG Construction 21931 Colocol Integrated CIS Rehabilitation & Extension Project 05/12/12 NIA 6.993 174 C 0.435 0.200 0.300 - - - 93.53 92.73% Very Satisfactory

BRILLANTES CONSTRUCTION 26447Const./Rehab. Of Flood Control Projects along Jucntion Sayre Highway Aglayan - Zamboanguita Road, K1520+(-

2233) - K1520+000 (with exception)8/5/2014 X 5.527 135 C 0.491 0.200 0.300 99.10 99.10%

Outstanding

Brillantes Construction 26447 Const. of Sch. Bldg. @ BNHS at Malaybalay City 08/10/12 X 1.020 135 C 0.463 0.133 0.300 - - - 89.60 86.30% Satisfactory

Brillantes Construction 26447 Const. of 3-CL Sch. Bldg. at New Tubigon ES 08/09/12 X 1.352 120 C 0.399 0.200 0.000 - - - 59.90 73.76% Poor

Brima Construction and Enterprises 8746 Rehab./Reconst./Upgrading along Linamon-Zamboanga

Road, Larapan Section, Sta.1535+817 - Sta.1540+771 06/07/10 X 10.248 105 O 0.225 0.240 0.150 0.030 0.055 0.050 75.00 -

Brostan Construction & Development 12360 Const. of Flood Control & Water Impounding Structures

Agos River Basin 08/08/13 IVA 10.726 160 C 0.325 0.200 0.300 - - - 82.50 82.50% Satisfactory

Brostan Construction & Development 12360 Const. of MPB (Phase I), Cagayan State University 11/14/08 II 9.640 300 O 0.316 0.240 0.100 0.030 0.037 0.100 82.30 -

Brostan Construction & Development 12360 Addalam River Irrigation Project 04/27/09 05/01/09 NIA 9.225 235 O 0.351 0.300 0.077 0.023 0.038 0.033 82.27 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page41

Page 42: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Brostan Construction & Development 12360

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. along Sta.Maria-Norzagaray Rd., a)K0035+259-

K0035+965.50 (w/ exception), b)K0037+611-K0037+775 (w/ exception), c)K0037+775-K0037+895 (w/ exception),

d)K0035+1449-K0037+611 (w/ exception), e)K0040+398-K0040+790 w/ exception), f)K0040+790-K0041+150 (w/

exception)

11/29/12 III 42.817 220 C 0.323 0.200 0.300 - - - 82.30 87.58% Satisfactory

Brostan Construction & Development 12360 Rehab./Reconst./Upgrading of Nat'l Arterial Rd., Manila

North Rd. 08/04/12 I 79.954 240 C 0.391 0.133 0.300 - - - 82.40 84.26% Satisfactory

Brostan Construction & Development 12360 Restoration/Upgrading of Abutment Protection of Ipil

Bridge, Km.355+574 08/12/12 II 5.890 180 C 0.384 0.200 0.300 - - - 88.40 89.06% Very Satisfactory

Brostan Construction & Development 12360

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. along Sta.Maria-Norzagaray Rd., a)K0035+259-

K0035+965.50 (w/ exception), b)K0037+611-K0037+775 (w/ exception), c)K0037+775-K0037+895 (w/ exception),

d)K0035+1449-K0037+611 (w/ exception), e)K0040+398-K0040+790 w/ exception), f)K0040+790-K0041+150 (w/

exception)

08/06/12 III 42.817 220 O 0.319 0.300 0.150 0.030 0.045 0.050 89.40 -

BROSTAN CONSTRUCTION AND DEVELOPMENT 12360 Help for Catubig Agricultural Advancement Project

HCAAPD-C-2 03/15/14 NIA 172.723 874 O 0.369 0.271 0.000 0.030 0.070 0.050 78.98 -

Brostan Construction and Development 12360 Road Opening/Const. of Aguinaldo-Magallanes-Nasugbu

Rd. (East-West), Bendita Sect. 08/17/11 IVA 24.100 90 O 0.333 0.300 0.150 0.030 0.050 0.033 89.60 -

Brostan Construction and Development 12360 Rehab./Reconst./Upgrading of Santiago-Tuguegarao Road

(Roxas Section) 02/23/10 II 19.290 228 O 0.339 0.300 0.150 0.030 0.050 0.050 91.90 -

BRYLLE TRADING & CONSTRUCTION SUPPLIES 32880 Construction/Rehabilitation of Drainage along Pangasinan-

Zambales Road K0365+800 to K0367+900 10/28/2014 I 8.967 152 C 0.386 0.200 0.300 - - - 88.60% 88.60% Satisfactory

BSP - 4B Joint Venture JV-11-305 Reconst. of Camachille Bridge & Approaches along Olangapo-Bugallon Rd., Km.148+979-Km.149+033.80 03/16/13 III 46.835 286 C 0.350 0.176 0.300 - - - 82.60 83.02%

Satisfactory

BSP & Company Inc. 19091

Rehab./Impv't. of Daang Maharlika Rd., Pagbilao-Atimonan Sect., under the Post Ondoy & Pepeng Short-Term

Infrastructure Rehab. Proj. (POPSTIRP), Roads & Bridges Component

03/19/13 BOM / IVA 172.471 384 C 0.434 0.133 0.300 - - - 86.70 90.09% Very Satisfactory

BUGANI CONSTRUCTION and ENTERPRISES, INC. 36435 Construction of Multi-Purpose Building (Phase II) 11/24/2014 CAR 1.849 88 O 0.377 0.240 0.150 0.030 0.047 0.050 89.40% 89.40%

Very SatisfactoryBuilders Multi-Purpose

Cooperative (BMPC) 31386 Const. of Macangao Agri. Vocational HS 08/19/11 XI 1.779 90 O 0.373 0.240 0.150 0.030 0.045 0.033 87.10 -

Builder's Multi-Purpose Cooperative (BMPC) 31386 Rehab. of Roads, Brgy. Kimolong 03/20/13 X 0.400 46 C 0.328 0.200 0.000 - - - 52.80 52.80%

Poor

Busilac Builders, Incorporated 7701Rehab./Reconst./Upgrading of Paved Nat'l Rd. Gen. from

PMS/HDM-4 Int. Sect., Ilocos Norte-Abra Rd., K0503+(-078)-K0504+850

08/14/13 I 11.372 90 C 0.469 0.133 0.300 - - - 90.20 90.20% Very Satisfactory

Busilac Builders, Incorporated 7701 Rehab./Reconst./Upgrading of Damaged National Road, Ilocos Norte-Apayao Road 09/09/09 I 24.758 206 O 0.295 0.300 0.150 0.030 0.050 0.033 85.80 -

BVG Contruction and Development Corp. Bamban Communal Irrigation System 08/15/15 NIA 33.927 210 O/E 0.255 0.000 0.093 0.008 0.005 0.050 40.97 -

C & F CONSTRUCTION & DEVELOPMENT CORPORATION 3509

Asphalt Overlay of N. Domingo St., K007+542 (Banahaw St.) - K007+792 (near Aurora Blvd.), K0006+372 -

K0007+217)11/28/2014 NCR 23.209 241 O 0.430 0.133 0.300 86.30% 86.30%

Satisfactory

C & F CONSTRUCTION & DEVELOPMENT CORPORATION 3509 Construction of 2-Storey, 6-Classroom School Building,

Meycauayan National High School 11/28/2014 III 6.269 180 C 0.499 0.133 0.300 - - - 93.20% 93.20% Very Satisfactory

C & F Construction & Development Corporation 3509 Impv't./Asphalt Overlay of Ermin Garcia St., K0011+(-240)-

K0011+000-K0012+677 08/05/13 NCR 19.831 150 O 0.347 0.206 0.150 0.030 0.050 0.050 83.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page42

Page 43: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

C & F Construction & Development Corporation 3509 Reblocking with Asphalt Overlay of Aurora Blvd. (East

Bound), EDSA-Marikina Bdry. Sta. 10+(-347)-Sta.13+105 11/29/12 NCR 30.827 191 C 0.454 0.200 0.300 - - - 95.40 92.52% Very Satisfactory

C & F Construction & Development Corporation 3509 Reblocking with Asphalt Overlay of Aurora Blvd. (East

Bound), EDSA-Marikina Bdry. Sta. 10+(-347)-Sta.13+105 08/10/12 NCR 30.827 180 O 0.380 0.300 0.135 0.023 0.035 0.033 90.60 -

C & F Construction & Development Corporation 3509 Rehab./Reconst. of Bocaue-San Jose Road, K0031+81-

K0034+0 (w/ exception) 08/08/12 III 23.411 180 C 0.427 0.200 0.300 - - - 92.70 89.76% Very Satisfactory

C & F Construction & Development Corporation 3509 Prev. Maint. along NCR/Bulacan Bdry.-Bigte-Ipo Dam Rd.

K0042+116-K0044+1000 (w/ exception) 03/21/13 III 28.388 45 C 0.457 0.133 0.300 - - - 89.00 89.00% Satisfactory

C & F Construction Development Corporation 3509 Const./Rehab. Of Sch. Bldg. Marilao Central Sch., Sandico

St. Brgy. Pob. 03/17/12 III 1.877 110 C 0.491 0.171 0.300 - - - 96.20 90.18% Very Satisfactory

C D U Construction 13915 Conc. of Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd., Cabatuan-Magtaon Bridge Sect., K0822+(366)-K0822+(029) 08/06/13 VIII 7.920 48 C 0.467 0.133 0.300 - - - 90.00 90.00%

Very Satisfactory

C D U Construction 13915Const. of Flood Control (Drainage Canal) along Palapag-

Mapanas-Gamay-Lapinig Rd., Mapno-Cabatuan Sect., K0805+300-K0817+800

08/06/13 VIII 9.141 180 O 0.332 0.300 0.096 0.030 0.060 0.050 86.80 -

C D U Construction 13915 Const. of Sch. Bldg., Calbayog City Night High Sch. 08/14/13 VIII 4.994 150 O 0.343 0.240 0.150 0.030 0.047 0.025 83.50 -

C D U Construction 13915 Const. of Sch. Bldg. (Two Storey) College of Law, University of Eastern Phil. (Main Campus) 08/09/13 VIII 5.675 180 O 0.392 0.240 0.150 0.030 0.052 0.050 91.40 -

C D U Construction 13915 Road Opening/Const. of Nijaga Sect. along Calbayog Diversion Rd. 06/12/10 VIII 19.295 150 O 0.353 0.238 0.150 0.030 0.037 0.033 84.10 -

C D U Construction 13915 Rehab./Reconst./Upgrading of Catarman-Calbayog Rd., 06/14/10 VIII 19.275 130 O 0.325 0.240 0.150 0.030 0.042 0.050 83.70 -

C D U Construction 13915 Conc. of Laoang-Lapinig-Arteche-San Policarpio Road Mapanas-Manaybanay Section, with exception 08/25/10 VIII 18.820 200 O 0.321 0.300 0.150 0.030 0.025 0.050 87.60 -

C D U Construction 13915 Conc. of Laoang-Calomotan Road 11/29/08 VIII 19.065 180 O 0.358 0.240 0.100 0.015 0.025 0.100 83.80 -C D U Construction 13915 Upgrading of Allen-Frederick National Road 09/14/09 VIII 8.652 120 O 0.337 0.240 0.150 0.030 0.050 0.050 85.70 -

C D U Construction 13915 Conc. of Laoang-Lapinig-Arteche (SONA), Laoang-Binaticlan Sect. 09/12/09 VIII 18.756 200 O 0.331 0.240 0.150 0.030 0.050 0.050 85.10 -

C D U Construction 13915 Upgrading of Allen-Cabacungan National Road 09/14/09 VIII 19.231 150 O 0.334 0.240 0.150 0.015 0.050 0.050 83.90 -

C D U Construction 13915 Upgrading of Pob.-Brgy. Cabacungan Rd., Km.699+630-Km.699+1103 08/11/12 VIII 9.138 120 C 0.404 0.142 0.300 - - - 84.60 85.38%

Satisfactory

C D U Construction 13915Repair/Restoration of Damaged Dale River Control,

Catarman (Bndry.)-Rawis Rd., San Roque-Pambujan Sect., Km.773+856-Km.773+930 w/ exception, Brgy. Dale

08/16/12 VIII 14.220 90 C 0.441 0.133 0.300 - - - 87.40 84.52% Satisfactory

C L Carandang Enterprises 29494 Rehab./Reconst. of Damaged Masbate Port National Road 05/25/09 V 7.715 150 O 0.317 0.300 0.150 0.023 0.040 0.033 86.30 -

C L Carandang Enterprises 29494 Rehab./Impvt. of DPWH Bldg., Masbate 1st DEO 05/25/09 V 1.926 80 O 0.331 0.240 0.150 0.030 0.040 0.033 82.40 -

C L Carandang Enterprises 29494 Const. of Drainage and Slope Protection, Masbate-Cataingan Rd. (K0001+700-K0015+554) w/ exception 03/12/13 V 9.332 132 O 0.304 0.300 0.150 0.030 0.025 0.033 84.20 -

C L Carandang Enterprises 29494 Road Upgrading of San Fernando-Talisay Rd. 08/24/10 V 11.001 190 O 0.313 0.300 0.150 0.020 0.025 0.033 84.10 -C L Carandang Enterprises / Lim General Contractor Corporation

(JV)JV-09-089 Conc. Of Jct. Paguiran-Brgy. Paguiran rd. 08/21/10 V 72.357 378 O 0.330 0.241 0.150 0.022 0.033 0.033 80.90 -

C L V Enterprises 18512 Const. of Multi-Purpose Building, Cawayan 05/27/09 X 0.939 119 O 0.300 0.300 0.150 0.020 0.025 0.033 82.80 -

C L V Enterprises 18512 Const. of Multi-Purpose Building, Bukidnon State University 09/02/09 X 3.372 150 O 0.388 0.240 0.150 0.030 0.047 0.033 88.80 -

C N E Construction 22148 Rehab. of Rd. Slip along Tacloban-Ormoc-Baybay-Maasin Road, along Baybay-Matalom Rd. 08/08/13 VIII 6.495 100 C 0.435 0.133 0.300 - - - 86.80 88.72%

Satisfactory

C N E Construction 22148Const. of 1 unit 2 storey 8-CL & 1 unit - 2 storey 6 CL Sch. Bldg., Tanauan Sch. of Craftsman & Home Industries (LIT

Tanauan Campus)08/19/13 VIII 16.594 240 O 0.400 0.237 0.150 0.020 0.019 0.050 87.60 -

C N E Construction 22148 Rehab. of Rd. Slip along Tacloban-Ormoc-Baybay-Maasin Rd. along Baybay-Matalom Rd. 03/15/13 VIII 6.495 100 O 0.400 0.240 0.150 0.030 0.047 0.033 90.00 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page43

Page 44: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

C N E Construction 22148 Const. of Maharlika Flood Control Structures along Ormoc-Baybay-Maasin Rd. 03/15/13 VIII 4.902 120 C 0.442 0.133 0.300 - - - 87.50 86.90%

Satisfactory

C. M. TAN CONSTRUCTION 28087 Construction/Improvement of Road along NRJ - Bayugan - Calaitan - Tandag Road, K1295+260 - K1296+615 8/6/2014 XIII 42.119 276 OG 0.400 0.254 0.150 0.007 0.023 0.050 88.40 -

C. T. Leoncio Construction & Trading 17371 Mauban Port Development Project 08/08/13 DOTC 4.615 120 C 0.447 0.200 0.300 - - - 94.70 94.70%

Very Satisfactory

C. T. LEONCIO CONSTRUCTION AND TRADING 17371 Kiamba Port Development Project 10/29/14 DOTC 4.965 135 C 0.448 0.200 0.300 - - - 94.79 94.79%

Very Satisfactory

C.A. BATALAC CONSTRUCTION & GEN. MDSE 28222

Const./Rehab. Of Drainage Canal / Protection Works Flood Control along Kidapawan - Ala Jct. Road at San Pablo

Section K1671+006 - K1671+4408/8/2014 XII 4.879 147 C 0.495 0.133 0.300 92.80 92.80%

Very Satisfactory

C.A. BETALAC CONSTRUCTION & GEN. MDSE. 28222

Construction/Rehabilitation of Drainage/Protection Works along Kidapawan-Ala Jct. Road at San Pablo Section,

K1671+006-K1671+44010/23/2014 XII 4.879 147 C 0.475 0.133 0.300 - - - 90.80% 90.80%

Very Satisfactory

C.A. Betalac Construction & Gen. Mdse. 28222 Completion of MPB at Brgy. New Isabela 08/17/13 XII 1.976 120 C 0.492 0.133 0.300 - - - 92.50 92.50%

Very Satisfactory

C.B Garay Philwide Builders 6004 Construction of 1 Unit 3-Storey, 15-Classroom School Building 01/18/10 NHA 18.115 150 O 0.3596 0.2756 0.00 0.0150 0.0255 0.0167 69.24 -

C.B Tampengco Construction & Supply 18505 Completion of School Bldg., Tampo E/S Main, Brgy. Tampo 09/03/09 NCR 1.904 60 O 0.328 0.225 0.150 0.030 0.041 0.033 80.70 -

C.B. TAMPENGCO CONSTRUCTION & SUPPLY 18505

Rehab./Reconstruction/Upgrading of Damaged Paved National Roads Based on Pavement Management

System/Highway Development & Management - 4 (HDM-4) (Intermittent Section) along C-4 Road (S02154LZ)

11/21/2014 NCR 9.697 121 C 0.410 0.133 0.300 - - - 84.30% 84.30% Satisfactory

C.B. TAMPENGCO CONSTRUCTION & SUPPLY 18505 Construction/Rehabilitation of Flood Control in Laguna

2nd DEO/1st LD along Tagapo Waterways 11/28/2014 IV 16.535 180 C 0.414 0.200 0.300 - - - 91.40% 91.40% Very Satisfactory

C.B. Tampengco Construction & Supply 18505 Const. of Three (3) Storey, Nine (9) Cl Sch. Bldg. Tinajeros

NHS(Phase II)-Acacia Annex 08/12/13 NCR 5.784 150 O 0.303 0.240 0.150 0.030 0.035 0.033 79.10 -

C.B. Tampengco Construction & Supply 18505 Const. of Three (3), Nine (9) Classroom Tinajeros NHS-

Acacia Annex 03/15/13 NCR 5.563 135 O 0.390 0.240 0.150 0.023 0.029 0.033 86.50 -

C.B. Tampengco Construction & Supply 18505 Rehab./Reconst./Upgrading of Damaged Paved Nat'l

Roads, Gov. W. Pascual Ave. 03/17/12 NCR 9.282 205 C 0.403 0.200 0.300 - - - 90.30 90.12% Very Satisfactory

C.B. Tampengco Construction & Supply 18505 Impvt. of Marikina-Infanta Rd., Sta. Cruz-Dela Paz Sect., 1st

Leg. District 11/21/12 IVA 17.460 180 C 0.424 0.197 0.300 - - - 92.10 89.88% Very Satisfactory

C.B. Tampengco Construction & Supply 18505 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds.

w/ Drainage Impvt. of 7th Ave. West 08/17/12 NCR 16.900 197 C 0.416 0.200 0.300 - - - 91.60 86.44% Satisfactory

C.B. Tampengco Construction & Supply 18505 Imprv't. of Marikina-Infante Rd., Sta. Cruz, Dela-Paz Sect.

1st Leg. District 07/31/12 IVA 17.460 180 O 0.359 0.240 0.150 0.030 0.055 0.050 88.40 -

C.C.M. CONSTRUCTION 11043Rehabilitation/Reconstruction of Loay Interior Road,

Section 1) K0134+000 to K0136+000; Section 2) K0145+000 to K0145+157; Section 3) K0145+181 to K0145+301

10/26/2014 VII 48.495 241 O 0.344 0.300 0.085 0.030 0.047 0.033 83.90% 83.90% Satisfactory

C.C.M. Construction 11043 Conc./Widening of Dauis-Panglao Island Center Rd. 08/17/13 VII 48.619 431 C 0.450 0.200 0.300 - - - 95.00 82.52% Satisfactory

C.C.M. Construction 11043 Conc./Widening of Dauis-Panglao Island Center Rd., Sta.3+800-Sta.6+635, Dauis-Panglao 03/12/13 VII 48.619 300 O 0.332 0.200 0.000 0.030 0.038 0.017 61.70 -

C.C.M. Construction 11043 Conc./Widening of Dauis-Panglao Island Center Rd., Sta.3+800-Sta.6+635, Dauis-Pangalo 08/07/12 VII 48.619 270 O 0.365 0.239 0.150 0.030 0.050 0.033 86.70 -

C.D.J. BUILDERS & CONSTRUCTION SUPPLIES 30347

Construction/Rehabilitation of Flood Control Projects in Isabela 4th DEO/4th Pangal Sur Flood Control Project, Sta.

0+000 - Sta. 0+390, Pangal Sur10/27/2014 II 19.290 164 C 0.350 0.200 0.300 - - - 85.00% 85.00%

Satisfactory

C.D.J. Builders & Construction Supplies 30347 Construction/Rehab. of Gucab Flood Control Project, Sta.

0+000 - Sta. 0+302 8/12/2014 II 19.300 201 OG 0.279 0.300 0.150 0.030 0.040 0.033 83.20 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page44

Page 45: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

C.D.J. Builders & Construction Supplies/Shanley Construction (JV) JV-13-232

Construction/ Rehabilitation of Flood Control Projects in Isabela 4th DEO/4th LD, Buenavista Flood Control Project,

Sta. 0+000 to Sta. 0+3088/12/2014 II 19.300 196 C 0.377 0.151 0.300 82.80 82.80%

Satisfactory

C.D.J. Builders & Construction Supplies/VB Manubay Construction

- Joint VentureJV-13-192

Constuction/Rehabilitation of Flood Control Projects, Mabini/Calao Flood Control Project, Sta. 0+000 to Sta.

0+3728/12/2014 II 19.300 201 C 0.371 0.154 0.300 82.50 82.50%

Satisfactory

C.DY BUILDERS AND GENERAL MERCHANDISE (Formerly: CD

CONSTRUCTION)17003 Completion of Hospital Facilities (Tagoloan Mini Hospital) 10/28/2014 X 4.468 60 O 0.358 0.240 0.150 0.010 0.022 0.033 81.30% 81.30%

Unsatisfactory

C.E. MERCADO CONSTRUCTION 36501 Construction of Multi Purpose Building at St. Dominic, Brgy. Talipapa, Quezon City 8/14/2014 NCR 4.739 90 C 0.455 0.133 0.300 88.80 88.80%

SatisfactoryC.F. Trinidad Construction and Supplies Corp. (Formerly: C.F.

Trinidad Construction)9199 Prev. Maint. (Asphalt Overlay) of Imelda Ave. 1.K0018+(-

232)-K0018+808; 2.K0018+(-010)-K0020+732 (Int. Sect.) 08/15/13 IVA 44.628 179 C 0.447 0.133 0.300 - - - 88.00 91.96% Very Satisfactory

C.F. Trinidad Construction and Supplies Corp. (Formerly: C.F.

Trinidad Construction)9199 Prev. Maint. (Asphalt Overlay) of Imelda Ave., 1. K0018+(-

232)-K0018+808; 2. K0018+(-010)-K0020+732 (Int. Sect.) 03/22/13 IVA 41.107 179 O 0.385 0.300 0.150 0.030 0.048 0.033 94.60 -

C.F. Trinidad Construction and Supplies Corp. (Formerly: C.F.

Trinidad Construction)9199 Widening of Taytay Diversion Rd. (6 Lanes) 11/22/12 IVA 43.305 300 C 0.372 0.200 0.300 - - - 87.20 86.78%

Satisfactory

C.F. Trinidad Construction and Supplies Corp. (Formerly: C.F.

Trinidad Construction)9199 Rehab./Reconst./Upgrading of Antipolo Circ. Rd. "A" 2nd

Leg. District 07/30/12 IVA 8.274 150 C 0.488 0.133 0.300 - - - 92.10 89.28% Very Satisfactory

C.F. Trinidad Construction and Supplies Corp. (Formerly: C.F.

Trinidad Construction)9199 Widening of Taytay Diversion Road (6-Lanes) 07/30/12 IVA 41.454 240 O 0.381 0.178 0.150 0.030 0.045 0.050 83.40 -

C.J.T. PASCUAL CONSTRUCTION 34285 Construction/Concreting of Nagattatan Road @ Nagattatan 10/23/2014 II 3.960 47 O 0.414 0.133 0.300 84.70% 84.70% Satisfactory

C.J.T. Pascual Construction 34285 Construction/Concreting of Nagattatan Road 8/7/2014 II 3.961 82 C 0.391 0.132 0.300 82.30 82.30% Satisfactory

C.L Carandang Enterprises 29494 Rehab./Reconst. of Masbate Circumferential Road 08/26/09 V 32.805 210 O 0.371 0.279 0.150 0.030 0.037 0.033 90.00 -

C.L Carandang Enterprises 29494 Rehab./Reconst. of Damaged Masbate Port National Road 08/26/09 V 7.715 180 O 0.320 0.300 0.150 0.030 0.047 0.033 88.00 -

C.L Carandang Enterprises 29494 Impvt. of Canvanez-Nasandig Brgy. Road 09/26/09 V 4.725 120 O 0.293 0.300 0.150 0.030 0.033 0.033 83.90 -

C.L. Carandang Enterprises 29494Const./Repair of Slope Protection/Embankment and

Draiange System Masbate-Cataingan-Placer Rd. (Km.27+600-Km.29+404.25)

03/12/13 V 8.960 119 O 0.322 0.294 0.000 0.020 0.010 0.017 66.30 -

C.M Dancel Construction & Supply 12640 Asphalt Overlay along Laoag-Sarrat-Piddig-Solsona Road 02/24/10 I 13.678 90 O 0.300 0.300 0.150 0.030 0.055 0.033 86.80 -

C.M Dancel Construction & Supply 12640 Rehab./Reconst./Upgrading of Damaged Paved National Road, Bonifacio Road 06/05/09 I 10.260 130 O 0.358 0.225 0.150 0.030 0.045 0.033 35.80 -

C.M. Pancho Construction Incorporated 183

Construction of Dalton Pass Nueva Vizcaya (New Alignment) San Jose-Aritao Road, Segment 5, Dalton Pass

Section Eastern Alternate Route8/15/2014 II 386.808 791 C 0.470 0.189 0.300 95.90 93.86%

Very Satisfactory

C.M. Pancho Construction Incorporated 183 Rehab. of Surigao-Davao Coastal Road, Jct. Bacuag-Claver

Section 11/23/08 XIII 661.069 540 O 0.338 0.300 0.070 0.030 0.070 0.100 90.80 -

C.M. Pancho Construction, Incorporated 183

Const. of Dalton Pass Nueva Vizcaya (New Alignment) San Jose-Aritao Rd., Segment 5, Dalton Pass Sect. Eastern

Alternate Route08/15/13 II 351.745 720 O 0.334 0.300 0.150 0.030 0.061 0.050 92.50 -

C.M. Tan Construction (Formerly: C.M. Tan Construction Supplies) 28087

Const. of Protection Works along NRJ- Bayugan-Esperanza Rd. crossing Luna (Sect. 2) 1276+566.2-

1276+648.411/28/12 XIII 18.188 165 O 0.331 0.300 0.150 0.020 0.055 0.050 90.60 -

C.R. Domingo Construction, Inc. (Formerly: C.R. Domingo Const.) 2992

Rd. Upgrading along Banaue-Mayoyao-Aguinaldo-A. Lista-Isabela Bdry. Rd. (Galanogon Sect.) Aguinaldo & Alfonso

Lista08/07/12 CAR 2.964 210 C 0.347 0.200 0.300 - - - 84.70 85.06%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page45

Page 46: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

C.R. Domingo Construction, Inc. (Formerly: C.R. Domingo Const.) 2992 Rd. Upgrading along Jct. Potia-Mt. Province Bdry. Rd.

Pinto Kiling (Caragasan Sect.), Alfonso Lista 08/08/12 CAR 13.033 180 C 0.327 0.200 0.300 - - - 82.70 85.04% Satisfactory

C.R. DOMINGO CONSTRUCTION, INC. (Formerly: C.R. Domingo

Construction)2992 Road Upgrading (Gravel to Paved) along Ubao - Taang

Road, K0399+540 - K0400+837 11/26/2014 CAR 43.806 257 O 0.358 0.265 0.150 0.030 0.056 0.050 90.90% 90.90% Very Satisfactory

C.R. DOMINGO CONSTRUCTION, INC. (Formerly: C.R. Domingo

Construction)2992

Road Upgrading (Gravel to Paved) along Banaue-Mayoyao-Alfonso Lista-Isabela Boundary Road, KO 422+243 - KO 422+558 and KO 425+558 and KO 425+483 - KO 426+092

11/26/2014 CAR 30.117 255 O 0.358 0.243 0.150 0.030 0.056 0.050 88.70% 88.70% Satisfactory

C.R. DOMINGO CONSTRUCTION, INC. (Formerly: C.R. Domingo

Construction)2992 Road Upgrading (Gravel to Paved) along Alfonso Lista -

Aurora Boundary Road, KO445+540 - KO447+130 11/26/2014 CAR 46.653 296 O 0.352 0.281 0.112 0.030 0.055 0.033 86.30% 86.30% Satisfactory

C.R. Domingo Construction, Inc. (Formerly: C.R. Domingo

Construction)2992 Const. of San Juan-San Jose Flood Control 03/19/13 CAR 13.475 148 C 0.413 0.133 0.300 - - - 84.60 85.68%

Satisfactory

C.R. Domingo Construction, Inc. (Formerly: CR Domingo Const.) 2992 Road Const. of Dolowog Road 08/07/13 CAR 0.481 80 C 0.420 0.200 0.300 - - - 92.00 92.00%

Very Satisfactory

C.R. Domingo Construction, Inc. (Formerly: CR Domingo Const.) 2992 Prev. Maint. along Nueva Vizcaya-Ifugao-Mt. Province

Bdry. Rd. (Asphalt Overlay) 08/05/13 CAR 17.982 99 C 0.451 0.133 0.300 - - - 88.40 88.40% Satisfactory

C.R. Domingo Construction, Inc. (Formerly: CR Domingo Const.) 2992 Rd. Upgrading (Gravel to Paved) along Ubao-Taang Rd.,

K0422+300-K0425+765 (w/ exceptions) 08/07/13 CAR 44.268 215 O 0.341 0.300 0.103 0.030 0.050 0.017 84.10 -

C.R. Domingo Construction, Inc. (Formerly: CR Domingo Const.) 2992 Rd. Upgrading (Gravel to Paved) along Alfonso Lista-

Aurora Bdry. Rd. K0442+124.5-K0445+540 08/07/13 CAR 38.538 230 O 0.317 0.300 0.103 0.030 0.050 0.033 83.30 -

C.S. Garcia Construction 1901Rehab./Re-const./Upgrading of Damaged Paved Nat'l

Roads (IS) along Marcos Highway, K0014+054-K0013+356 (Westbound) and K0013+391-K0014+054 (Eastbound)

03/14/12 NCR 12.333 72 C 0.405 0.200 0.300 - - - 90.50 92.00% Very Satisfactory

C.S. Garcia Construction 1901 Repair/Rehab./Impv't. along F. Blumentritt St., San Juan City, K007+(1147)-K007+234 w/ exception 03/22/13 NCR 9.558 30 C 0.449 0.133 0.300 - - - 88.20 88.20%

Satisfactory

C.S. Rayos Construction & General Services Inc. (Formerly: C.S. Rayos

Construction and General Services)

9790 Const./Rehab. of Drainage System & Outfall along Batangas-Tabangao-Lobo Rd., Gulod-Labac Sect. 08/01/13 IVA 12.860 166 C 0.409 0.133 0.300 - - - 84.20 84.56%

Satisfactory

C.S. Rayos Construction & General Services, Inc. (Formerly: C.S.

Rayos Const. and General Services)

9790 Const./Rehab. of Drainage System & Outfall along Batangas-Tabangao-Lobo Rd., Gulod Labac Sect. 03/12/13 IVA 13.349 166 O 0.350 0.240 0.150 0.030 0.045 0.033 84.80 -

C.T. LEONCIO CONSTRUCTION & TRADING 17371 Widening of Old Cagayan Valley Road Km. 45+388 to Km.

52+985 (Baliuag Section) 11/7/2014 III 33.978 195 C 0.410 0.133 0.300 - - - 84.30% 84.30% Satisfactory

C.T. LEONCIO CONSTRUCTION & TRADING/KATHA BUILDERS &

SUPPLIES (JV)JV-13-755

Network Development - Widening of National Roads-Secondary Roads: Widening of Meycauayan-Camalig-

Bahay Pari Road11/25/2014 III 91.784 270 C 0.374 0.240 0.150 - - - 87.20% 87.20%

Satisfactory

C.T. LEONCIO CONSTRUCTION & TRADING 17371 Gasan Port Development Project 08/05/15 DOTC 17.614 180 O 0.400 0.300 0.068 0.015 0.061 0.050 89.40 -

C.T. LEONCIO CONSTRUCTION & TRADING 17371

Concreting of Jct. MWCR (San Isidro)- Penal ColonyJCt. Yapang Road (Km. 302+000 to Km. 313+644.90 w/

exceptions)11/26/2014 IV 83.252 661 C 0.440 0.181 0.300 - - - 92.10% 92.10%

Very Satisfactory

C.T. Leoncio Construction & Trading 17371 Construction/Rehabilitation/Improvement of Clupa-

Calauag-Canaman Flood Control 8/8/2014 V 44.070 234 OG 0.327 0.300 0.126 0.020 0.047 0.033 85.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page46

Page 47: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

C.T. Leoncio Construction & Trading 17371

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Roads along Rolando Andaya Highway,

KO287+000 to KO288+9968/6/2014 V 38.800 174 OG 0.347 0.300 0.105 0.022 0.045 0.033 85.20 -

C.T. LEONCIO CONSTRUCTION & TRADING 17371

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved

Road Standard, Concreting of Cabatuan - New Lucena - Banga Bante Road, K028+667 - K030+208.8

8/16/2014 VI 29.101 166 C 0.317 0.200 0.300 81.70 82.66% Satisfactory

C.T. Leoncio Construction & Trading 17371 Widening of Old Cagayan Valley Rd., Km.45+388-

Km.52+985 (Baliuag Sect.) 08/13/13 III 33.978 165 O 0.335 0.240 0.150 0.023 0.045 0.033 82.60 -

C.T. Leoncio Construction & Trading 17371 Reconst. of Siniloan Bridge II along Paete-Pakil Pob. Rd. 08/09/13 IVA 26.331 230 C 0.438 0.200 0.000 - - - 63.80 74.72%

Poor

C.T. Leoncio Construction & Trading 17371 Rd. Upgrading (Gravel to Paved), Conc, of Cabatuan-New

Lucena-Banga Bante Rd., K0028+677-K0030+208.80 08/20/13 VI 26.461 135 O 0.377 0.240 0.120 0.023 0.040 0.033 83.30 -

C.T. Leoncio Construction & Trading 17371 Reconst. Of Siniloan Bridge II along Paete-Pakil Pob. Rd. 03/20/13 IVA 28.543 201 O 0.395 0.300 0.000 0.030 0.055 0.033 81.30 -

C.T. Leoncio Construction & Trading 17371 Reconst. of Siniloan Bridge II along Paete-Pakil Pob. Rd. 11/27/12 IVA 28.543 170 O 0.369 0.294 0.073 0.018 0.040 0.033 82.70 -

C.T. Leoncio Construction & Trading / Caana Construction

Corporation (JV)JV-12-454 Repair of Damage Expansion Joints of Nagtahan Fly-Over

using Thermajoint 03/20/13 NCR 10.025 45 C 0.464 0.133 0.300 - - - 89.70 89.70% Very Satisfactory

C.T. Leoncio Construction & Trading / Eric Van P. Sesbreno

Construction (JV)JV-12-323

Rd. Upgrading (Gravel to Paved) Intermittent Sects., Bambang-Kasibu-Quezon-Solano Rd., K0262+000-

K0264+050, Antutot Sect.03/22/13 II 42.486 179 O 0.377 0.240 0.150 0.030 0.051 0.033 88.10 -

C.T. Leoncio Construction & Trading/VCH Construction and

Trading - Joint VentureJV-13-226 Reconstruction of Igang Bridge I (Existing Permanent

Bridge) along PPN Road, K0219+718, Taytay, Palawan 8/6/2014 IV-B 18.071 220 OG 0.373 0.227 0.103 0.030 0.045 0.033 81.10 -

C.T. LEONCIO CONSTRUCTION & TRADING/VCH CONSTRUCTION AND 

TRADING‐ JVJV-13-226 Construction/Improvement of Access Road from Sandoval

Airport to Poblacion, K0212+300-K0214+855 11/21/2014 IV 45.966 239 O 0.339 0.240 0.150 0.030 0.048 0.050 85.70% 85.70% Satisfactory

C.T. LEONCIO CONSTRUCTION AND TRADING 17371 Construction/Maintenance of Flood Control and Drainage

along Marikina-Infanta Road 11/28/2014 IV 17.984 121 C 0.446 0.133 0.300 - - - 87.90% 87.90% Satisfactory

C.T. Leoncio Construction and Trading 17371 Sarangani Ports Cluster Development Project 04/23/14 DOTC 11.197 180 C 0.453 0.200 0.300 - - - 95.30 95.30%

Very Satisfactory

CAMCU Construction and Supplies 18507 Construction of Lubog CIP 08/31/13 NIA 3.792 135 C 0.455 0.160 0.300 - - - 91.48 91.48% Very Satisfactory

CAMCU Construction and Supply 18507 Bayag Sur CIP 11/13/13 NIA 1.830 148 O 0.395 0.300 0.027 0.020 0.058 0.050 85.00 -

Camia Construction 20506 Concreting along Kabugao-Pudtol-Luna Road, Nagsungbatan Section 06/01/09 CAR 14.117 277 O 0.400 0.300 0.150 0.030 0.045 0.033 95.80 -

Camia Construction 20506 Conc. along Kabugao-Pudtol-Luna Road, Swan Section 06/01/09 CAR 18.862 277 O 0.357 0.240 0.150 0.030 0.056 0.033 86.60 -

Camia Construction 20506 Rehab. of Kabugao-Pudtol-Luna Road, Lenning Section 05/30/09 CAR 13.870 366 O 0.294 0.300 0.150 0.030 0.035 0.033 84.20 -

Camia Construction 20506 Rehab. of Kabugao-Pudtol-Luna Road, Capitol Poblacion Section 05/30/09 CAR 18.562 391 O 0.288 0.300 0.150 0.030 0.040 0.033 84.10 -

Camia Construction 20506 Rehab. of Kabugao-Pudtol-Luna Road, Capitol-Poblacion Section 02/28/09 CAR 18.563 390 O 0.351 0.300 0.150 0.030 0.035 0.033 89.90 -

Camia Construction 20506 Upgrading of Kabugao-Pudtol-Luna Road (Lenneng Sect.) 09/04/09 CAR 13.870 402 O 0.331 0.240 0.150 0.024 0.056 0.033 83.40 -

Camia Construction 20506 Road Upgrading of Abbut-Conner- Kabugao Road (Gravel to Concrete), Manag-Guina-ang Section 02/20/10 CAR 9.358 360 O 0.381 0.234 0.150 0.030 0.040 0.033 86.80 -

Camia Construction 20506 Rehab. of Nat'l Rd. along Conner-Kabugao Road, Cut Section K0570+000-K0571+000 w/ exception, Matalag Sect. 11/28/12 CAR 24.110 255 O 0.372 0.300 0.000 0.030 0.051 0.033 78.60 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page47

Page 48: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Camia Construction 20506 Rehab. of Nat'l Rd. along Conner-Kabugao Rd., Cut Sect. K0570+000-K0571+000 w/ exception, Matalag Sect. 08/10/12 CAR 24.110 255 O 0.310 0.300 0.000 0.000 0.037 0.033 68.00 -

CAMIA CONSTRUCTION DEVELOPMENT CORPORATION 20506

Widening/Road Upgrading (Gravel to Concrete) along Kabugao, Apayao-Solsona-Ilocos Norte Road, Apayao

Side, K0607+378 to K0608+879, Apayao8/8/2014 CAR 46.213 239 OG 0.368 0.240 0.150 0.030 0.050 0.050 88.80 -

CARLYZ CONSTRUCTION 19776 Road Upgrading (Gravel to Concrete) of Brgy. Pob. West Road 11/24/2014 CAR 1.831 67 C 0.455 0.200 0.076 - - - 73.10% 73.10%

Poor

CARLYZ CONSTRUCTION 19776 Construction of Multi-Purpose Building (Public Market) 11/24/2014 CAR 2.321 120 O 0.353 0.240 0.150 0.030 0.058 0.050 88.10% 88.10% Satisfactory

Carlyz Construction 19776 Road Upgrading along Banaue-Mayoyao-Aguinaldo-A. Lista-Isabela Boundary Road (Kinakin-Dalican Sect.) 03/18/12 CAR 4.166 189 C 0.456 0.133 0.300 - - - 88.90 84.61%

Satisfactory

CARRASCAL INTEGRATED ENTERPRISES 4764 Road Slip Protection along Surigao - Davao Coastal Road,

K1218+380 to K1268+180 (Intermittent Sections) 10/26/2014 XIII 14.699 201 C 0.447 0.133 0.300 - - - 88.00% 88.00% Satisfactory

Carrascal Integrated Enterprises 4764 Rd. Upgrading (Gravel to Paved) Int. Sect. along Surigao-Davao Coastal Rd., (K1218+169.93-K1218+825) 08/14/13 XIII 9.332 86 C 0.407 0.131 0.300 - - - 83.80 83.80%

Satisfactory

Carrascal Integrated Enterprises 4764 Rehab./Reconst./Replacement/Retrofitting of Existing Permanent Bridges, Macapagal Bridge along SDCR 08/14/13 XIII 5.990 98 C 0.500 0.133 0.300 - - - 93.30 86.34%

Satisfactory

Carrascal Integrated Enterprises 4764 Rehab./Reconst./Replacement/Retrofitting of Existing Permanent Bridges, Macapagal Bridge along SDCR 03/16/13 XIII 5.991 88 O 0.329 0.225 0.150 0.030 0.050 0.033 81.70 -

Carrascal Integrated Enterprises 4764 Replacement of Bridge along Nat'l Rds. Catupgas Bridge II along Surigao-Davao Coastal Rd. 03/14/12 XIII 9.952 150 O 0.375 0.240 0.150 0.030 0.051 0.050 89.60 -

Carrascal Integrated Enterprises 4764 Replacement of Bridge along Nat'l Rds. Catupgas Bridge 1 along Surigao-Davao Coastal Rd. 11/23/12 XIII 18.146 330 C 0.435 0.162 0.300 - - - 89.70 90.90%

Very Satisfactory

Carrascal Integrated Enterprises 4764 Replacement of Bridge along Nat'l Rds. Catugpas Bridge 1 along Surigao-Davao Coastal Rd. 08/14/12 XIII 17.416 330 O 0.355 0.300 0.150 0.030 0.050 0.050 93.50 -

Carry-on Construction 8014 Const. of MPB at Barangay Tagalag 03/16/12 NCR 1.830 90 C 0.485 0.200 0.300 - - - 98.50 91.99% Very Satisfactory

Carry-on Construction 8014 Completion of MPB at Isla 03/16/12 NCR 2.565 90 C 0.437 0.200 0.300 - - - 93.70 90.13% Very Satisfactory

Cauayan United Enterprises & Construction Builders 8816

Preventiive Maintenance (Intermittent Section) alonf Gamu-Roxas Road at K0398+000 to K0399+609, Burgos, Isabela;

K0411+419 to K0412+0008/9/2014 II 28.062 143 C 0.461 0.132 0.300 89.30 89.30%

Very Satisfactory

Cauayan United Enterprises & Construction Builders 8816

Preventive Maintenance Based on Pavement System/Highway Development Management-4 (HDM-4)

MFO-1 along Cauayan Poblacion Road8/11/2014 II 8.528 66 C 0.445 0.133 0.300 87.80 87.80%

Satisfactory

CAUAYAN UNITED ENTERPRISES AND CONSTRUCTION BUILDERS 8816 Asphalt Overlay along Old CVR-Cabagan Road 10/26/2014 II 3.632 17 C 0.475 0.133 0.300 - - - 90.80% 90.80%

Very Satisfactory

CAUAYAN UNITED ENTERPRISES AND CONSTRUCTION BUILDERS 8816 Widening of Daang Maharlika (LZ) K0368+000 - K0373_000

(with excpetion), Cabaruan, Cauayan City, Isabela 10/25/2014 II 26.172 267 O 0.368 0.240 0.128 0.030 0.028 0.033 82.70% 82.70% Satisfactory

Cauayan United Enterprises and Construction Builders 8816 Prev. Maint. (Int. Sect.) along Santiago-Tuguegarao Rd. @

K0374+417-K0375+083, K0375+083-K0375+500 08/08/13 II 39.059 179 C 0.471 0.133 0.300 - - - 90.40 90.40% Very Satisfactory

Cauayan United Enterprises and Construction Builders 8816 Repair/Rehab./Impv't. along Naguilian-San Mariano Rd.

(Asphalt Overlay) K0388+600-K0397+737.92 08/08/13 II 5.000 40 C 0.462 0.133 0.300 - - - 89.50 89.50% Very Satisfactory

Cauayan United Enterprises and Construction Builders 8816

Prev. Maint. (Int. Sect.) along Gamu-Roxas Rd., 1)K0396+995-K0397+990; 2)K0403+000-K0400+000; 3)K0412+299-K0413+419; 4)K0413+613-K0413+686;

5)K0413+730-K0413+832, Gamu & Roxas

08/06/13 II 22.672 115 C 0.451 0.133 0.300 - - - 88.40 88.40% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page48

Page 49: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Cauayan United Enterprises and Construction Builders 8816 Conc. of FMR at Fugaru-Centro 2 08/06/13 II 9.749 66 C 0.436 0.133 0.300 - - - 86.90 86.90%

Satisfactory

Cauayan United Enterprises and Construction Builders 8816 Prev. Maint.along Daang Maharlika, K0370+840-K0373+178

(GAA) K0370+840-K0372+933.77, Tagaran 08/06/13 II 25.373 131 C 0.442 0.133 0.300 - - - 87.50 86.36% Satisfactory

Cauayan United Enterprises and Construction Builders 8816

Prev. Maint. along Daang Maharlika (LZ) K0361+820-K0363+899 (GAA) K0361+793-K0363+667.12 (POW)

Nungnungan II08/06/13 II 22.574 131 C 0.429 0.133 0.300 - - - 86.20 86.26%

Satisfactory

Cauayan United Enterprises and Construction Builders 8816 Asphalt Overlay along Daang Maharlika w/ Corrections

(Reblocking) K0395+659-K0396+1050.70, Baligatan 08/05/13 II 22.180 65 C 0.451 0.133 0.300 - - - 88.40 85.40% Satisfactory

Cauayan United Enterprises and Construction Builders 8816

Prev. Maint. along Daang Maharlika Rd. (Reblocking w/ Overlay) K0352+455-K0354+099.40, K0361+640-K0361+690,

Paddad, Alicia & Silawit08/10/12 II 18.211 130 C 0.423 0.200 0.300 - - - 92.30 92.42%

Very Satisfactory

Cauayan United Enterprises and Construction Builders 8816 Prev. Maint. along Cauayan-Cabatuan Rd. (Reblocking with

Overlay) K0380+(-103)-K0380+329 08/10/12 II 3.465 80 C 0.405 0.200 0.300 - - - 90.50 91.04% Very Satisfactory

Cauayan United Enterprises and Construction Builders 8816 Prev. Maint. along Santiago-Tuguegarao Road (50 mm

Overlay) K0361+000-K0362+287 08/10/12 II 6.779 90 C 0.392 0.200 0.300 - - - 89.20 90.46% Very Satisfactory

Cauayan United Enterprises and Construction Builders 8816

Prev. Maint. along Daang Maharlika (LZ) (Reblocking w/ Overlay w/ corrections 80 mm) K0367+100- K0370+104 w/

exception (Reblocking w/ 80 mm Overlay) K0370+104- K0370+294 (80 mm Overlay w/ minor correction)

08/10/12 II 23.638 140 C 0.387 0.200 0.300 - - - 88.70 90.26% Very Satisfactory

Cauayan United Entterprises and Construction Builders 8816

Prev. Maint. along Daang Maharlika (LZ) K0361+820-K0363+899 (GAA), K0361+793-K0363+667.12 (POW),

Nungnungan II03/19/13 II 22.574 131 O 0.300 0.300 0.150 0.030 0.050 0.033 86.30 -

Cauayan United Entterprises and Construction Builders 8816

Prev. Maint. along Daang Maharlika (LZ) K0370+840-K0373+178 (GAA), K0370+840-K0372+933.77 (POW),

Tagaran03/19/13 II 25.373 139 O 0.300 0.300 0.150 0.023 0.050 0.033 85.60 -

Cauayan United Entterprises and Construction Builders 8816 Asphalt Overlay along Daang Maharlika w/ Corrections

(Reblocking), K0395+659-K0396+1050.70, Baligatan 03/14/13 II 22.180 65 O 0.371 0.200 0.150 0.030 0.050 0.033 83.40 -

Cauayan United Entterprises and Construction Builders 8816

Prev. Maint. along Cauayan-Cabatuan Rd. (Asphalt Overlay) K0374+000-K0374+1000 w/ exception (GAA),

K0374+000-K0374+870.49 (POW)03/19/13 II 6.755 47 C 0.441 0.133 0.300 - - - 87.40 87.40%

Satisfactory

Cavacon Corporation (Formerly: Cagayan Valley Const. Corp.) 2622

Road Upgrading (Gravel to Paved), Baler-Casiguran Road (Dinadiawan-Casiguran Sect.) K0295+438-K0296+244 &

K0296+244-K0296+603 11/28/12 III 33.767 210 O 0.334 0.300 0.149 0.030 0.056 0.050 91.90 -

CAVACON CORPORATION (Formerly: Cagayan Valley Construction 

Corporation)2622

Rehabilitation of Barangay Road, Barangay San Antonio, Cabagan, Isabela, Sta. 0+000 - Sta. 996.30 (with exception

of 136.30 ln.m.)10/25/2014 II 4.652 103 C 0.415 0.133 0.300 - - - 84.80% 84.80%

Satisfactory

CAVACON CORPORATION (Formerly: Cagayan Valley Construction 

Corporation)2622

Construction of Roads Cabisera 22 to Paliueg Stretch 1: (a) Sta. 0+000 - Sta. 1+131. (b) Sta. 1+365 - Sta. 1+394.94

Stretch 2: Sta. 0+000 - Sta. 0+392.4 Stretch 3: Sta. 0+000 - Sta. 0 +304.06

10/24/2014 II 9.405 122 C 0.430 0.133 0.300 - - - 86.30% 86.30% Satisfactory

CAVACON CORPORATION (Formerly: Cagayan Valley Construction 

Corporation)2622

Construction of Flood Control Projects, Cavite 5th LD, Brgy. Mabuhay; Cabilang Baybay; Brgy. Milagrosa; Brgy. 8

Carmona; Maderan; and Brgy. Poblacion, G.M.A. with drainage outfall connecting to national road

11/5/2014 IV 9.016 175 O 0.350 0.300 0.120 0.030 0.054 0.050 90.40% 90.40% Very Satisfactory

Cavacon Corporation (Formerly: Cagayan Valley Construction

Corporation)2622

Network Development Off-Carriagewat Improvement (Paving of Shoulders) National Arterial Naguillian-San

Mariano Road K0386+546 to K0391+000 (with exception), K0396+000 to K0397+460 (with exception)

8/9/2014 II 31.676 179 OG 0.364 0.234 0.150 0.030 0.050 0.050 87.80 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page49

Page 50: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Cavacon Corporation (Formerly: Cagayan Valley Construction

Corporation)2622 Road Upgrading (Gravel to Paved) Nat'l. Arterial Rd.,

Dinadiawan-Madella Rd. Km.259+400 - Km.296+293 03/23/12 III 30.456 240 C 0.406 0.200 0.300 - - - 90.60 89.70% Very Satisfactory

Cavacon Corporation (Formerly:Cagayan Valley Construction Corporation)

2622 Road Upgrading (Gravel to Paved) San Luis-Ma. Aurora-Castañeda Rd. Km.252+000 to Km.251+784 to Km.252+008 08/16/11 III 13.468 120 O 0.299 0.300 0.108 0.030 0.055 0.033 82.50 -

CAVAT Capitol Merchandising and Construction 3112 Concreting of Provincial Road Basi East-West Solana Road

Section 8/7/2014 II 2.970 75 C 0.399 0.134 0.300 83.30 83.30% Satisfactory

Cavdeal-Cavite Ideal International Construction and Development

Corporation 5599

MMURTRIP Phase II, Const. of Metro Manila Urban Transport Integrated CP4, SLEX East & West Service

Roads and Pasong Tamo Ext.11/15/08 URPO 629.011 752 O 0.360 0.300 0.100 0.030 0.042 0.100 93.20 -

Cavdeal-Cavite Ideal International Construction and Development

Corporation 5599

Const. of El Nido-Bataraza Road, CP 3B-1, Segments 1-8, Abo-abo-Brooke's Point-Rio Tuba Section, (Sta.

128+026.93 to Sta. 247+923 w/ exception)06/01/09 PJHL 1,988.008 730 O 0.325 0.300 0.150 0.030 0.042 0.050 89.70 -

Cavdeal-Cavite Ideal International Construction and Development

Corporation 5599 Const. of El Nido-Bataraza Rd. Contract Package 3B-3,

Segment 1-8 Abo-abo - Brooke's Point - Rio Tuba Rd. Sect. 06/01/10 PJHL 1,988.008 730 O 0.334 0.300 0.150 0.030 0.065 0.050 92.90 -

CAVDEAL-Cavite Ideal International Construction and

Development Corporation (Formerly: Cavite Ideal Int'l. & Dev.

Corp.)

5599 Const./Impv't. of Ternate-Nasugbu Rd. Proj. (Km.94+112-Km.99+991) 03/26/13 BOC 808.952 1,609 O 0.384 0.258 0.150 0.030 0.070 0.050 94.20 -

CCI CONSTRUCTION 27004 Repair Rehabilitation of Corguer Facilities 10/10/13 DOST 8.359 85 C 0.415 0.200 0.300 - - - 91.50 91.50% Very Satisfactory

C.C.M. Construction 11043 BERRRP-Dimiao-Oac-Bilar Road 05/14/15 Bohol 18.272 314 C 0.492 0.200 0.300 - - - 99.20 99.20% Outstanding

CCM Construction 11043 BERRRP-Sikatuna-Sevilla via Cambuac Road 01/19/15 Bohol 23.327 465 O 0.358 0.261 0.150 0.024 0.061 0.050 90.40 -

CDC Construction & Supplies 28275Preventive Maintenance Based on PMS/HDM-4

(Intermittent Section) Alaminos-Bolinao Road K0328+000 to K0328+104

8/14/2014 I 9.620 65 C 0.433 0.133 0.300 86.60 86.60% Satisfactory

CDC Construction and Supplies 28275Const./Widening/Upgrading/Rehab. of Access Rd. to

Airport/Major Sea Ports & Declared Tourism Destinations Subic-Cawag-Balaybay Rd. (IS) Cawag

08/05/13 III 18.236 120 C 0.450 0.133 0.300 - - - 88.30 88.30% Satisfactory

CDC Construction and Supplies 28275 Repair/Rehab./Impvt. of Alaminos-Bolinao Rd., K0355+500-K0356+470 08/07/13 I 9.850 60 C 0.480 0.133 0.300 - - - 91.30 90.34%

Very Satisfactory

CDC Construction and Supplies 28275 Repair/Rehab./Impv't. of Alaminos-Bolinao Rd., K0355+500-K0356+470 03/15/13 I 9.850 60 O 0.361 0.291 0.150 0.015 0.030 0.050 89.70 -

CDU CONSTRUCTION 13915Rehabilitation /Reconstruction of Roadslip along Daang

Maharlika (DM) San Isidro-San Juanico Bridge, K0760+100-K0760+400

10/23/2014 VIII 14.065 180 C 0.475 0.133 0.300 - - - 90.80% 90.80% Very Satisfactory

CDU CONSTRUCTION 13915 Construction of School Building 2-Storey College of Law, Uneversity of Eastern Philippines (Main Campus) 8/9/2014 VIII 5.675 180 C 0.411 0.133 0.300 84.40 84.40%

Satisfactory

CDU CONSTRUCTION 13915Construction of Flood Control (Drainage Canal) along

Palapag - Mapanas - Gamay - Lapinig Road (Lapinig Mapno - Cabatuan Section) KO805+300 - KO817+800

8/12/2014 VIII 9.141 180 C 0.387 0.133 0.300 82.00 84.88% Satisfactory

CDU CONSTRUCTION 13915 Const. of School Building, Calbayog City Night High School 8/11/2014 VIII 4.994 210 C 0.499 0.133 0.300 93.20 86.41%

Satisfactory

CDU Construction 13915 Replacement of Lipata Bridge I along Pob.-Brgy. Cabacungan Road 03/20/12 VIII 8.809 120 O 0.400 0.240 0.150 0.015 0.035 0.033 87.30 -

CDU Construction 13915 Upgrading of Pob.-Brgy. Cabacungan Road, Km. 699+630-Km.699+1103 03/20/12 VIII 9.137 90 O 0.353 0.246 0.150 0.030 0.030 0.050 85.90 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page50

Page 51: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

CDU Construction 13915Repair/Restoration of Damaged Dale Rive Control,

Catarman (Bdry.)-Rawis Road, San Roque-Pambujan Sect., Km.773+856-Km.773+930, Brgy. Dale

03/23/12 VIII 14.219 90 O 0.333 0.225 0.150 0.030 0.055 0.033 82.60 -

CDU CONSTRUCTION 13915 Repair and Maintenance of Iba Bridge along Basey-Marabut-Pinamitinan Road Section 10/25/2014 VIII 4.506 150 O 0.399 0.240 0.026 0.030 0.041 0.033 76.90% 76.90%

Unsatisfactory

CE PADILLA 11278 Design and Renovation of Existing Cancer Center Facility 09/16/15 DOH 64.586 180 O 0.290 0.300 0.150 0.020 0.040 0.030 83.00 -

Cebu 7H Technochem Industries, Inc. 31578 Impv't./Conc. of Jct. Osmeña-Pilar Rd. (Mabini-Datu Sect.) 08/13/12 XIII 36.910 285 O 0.366 0.300 0.039 0.030 0.050 0.033 81.80 -

Cebu 7H Technochem Industries, Inc. 31578 Impv't./Conc. Of Jct. Cancohoy-Pilar Rd., Jamoyaon-Sto.

Niño-Macapagal Rd. Sect. 08/13/12 XIII 43.203 285 O 0.359 0.300 0.000 0.030 0.055 0.017 76.10 -

Cebu 7H Technochem Industries Inc. 31578 Asphalt Overlay of Tagbilaran East Rd., K0149+000-

K0149+990 08/19/13 VII 11.528 93 C 0.417 0.200 0.300 - - - 91.70 89.78% Very Satisfactory

Cebu 7H Technochem Industries Inc. / Uy Construction &

Development (JV)JV-11-316

Rd. Upgrading of Antequerra-San Isidro-Libertad (Tubigon) Rd., 1)K0026+(-714.00)-K0028+500.00; 2)K0032+301.00-

K0033+670.0008/15/13 VII 121.232 300 C 0.409 0.148 0.300 - - - 85.70 85.70%

Satisfactory

Cebu 7H Technochem Industries Inc. / Uy Construction and

Development (JV)JV-12-136

Impv't. of Tagbilaran North Rd. (Tagbilaran-Cortes-Tubigon, w/ Int. Sect.) Sec. 1:K0008+904-K0009+795; Sec. 2:K0038+818-K0041+012; Sec. 3:K0047+108-K0047+551;

Sec. 4:K0051+470-K0052+942

08/15/13 VII 70.221 270 O 0.364 0.292 0.150 0.030 0.040 0.033 90.90 -

CEBU 7H TECHNOCHEM INDUSTRIES INCORPORATED 31578

Asphalt Overlay, (Junction) TNR - Maribojoc - Antequera - Catagbacan (Loon) Road, a) K00016+985 - K00017+181 and

b) K00017+447 - K00018+65210/26/2014 VII 15.419 75 C 0.435 0.133 0.300 - - - 86.80% 86.80%

Satisfactory

CEBU 7H TECHNOCHEM INDUSTRIES INCORPORATED 31578 Asphalt Overlay of Tabilaran East Road(TER) 8/11/2014 VII 19.768 101 OG 0.340 0.240 0.150 0.022 0.051 0.050 85.30 -

Cebu 7H Technochem Industries, Inc. 31578 Tagbilaran Airport Development Project 08/11/15 DOTC 46.571 150 C 0.444 0.200 0.300 - - - 94.37 94.37% Very

SatisfactoryCebu 7H Technochem Industries,

Inc. 31578 Asphalt Overlay of Tagbilaran East Rd., K0149+000-K0149+990, San Pascual 03/13/13 VII 11.528 46 O 0.374 0.300 0.150 0.030 0.014 0.017 88.50 -

Cebu 7H Technochem Industries, Inc. 31578 Cluster A (Asphalt Overlay w/ Soil Stabilizer), Mariveles,

Catarman & Songculan, Dauis & Cabulihan 03/12/13 VII 8.976 150 C 0.471 0.000 0.300 - - - 77.10 82.50% Satisfactory

Cebu 7H Technochem Industries, Inc. 31578

Asphalt Overlay at Tagbilaran City-Corella-Sikatuna Rd., a)Km.002+450-Km.002+570, b)Km.002+570-Km.004+85720,

c)Km.007(+/-)181-Km.009+21508/07/12 VII 34.438 120 C 0.463 0.133 0.300 - - - 89.60 87.38%

Satisfactory

Cedan Construction 10172 Const. of MPB, Bangcol 11/22/12 III 1.420 83 C 0.413 0.200 0.300 - - - 91.30 89.97% Very Satisfactory

Cedan Construction 10172 Const. of MPB, Bangcol 08/16/12 III 1.420 83 O 0.374 0.284 0.150 0.030 0.023 0.033 89.40 -

Cedar Construction 24865 Rehab. of Regalado Ave., North (Mindanao Ave., Ext. to Regalado Ave., North Bridge) 08/02/13 NCR 9.552 214 C 0.395 0.133 0.300 - - - 82.80 82.80%

Satisfactory

Cedar Construction 24865 Repair/Rehab. of Regalado Ave., South, Brgy. Fairview 03/11/13 NCR 9.603 150 C 0.475 0.123 0.300 - - - 89.80 90.94% Very Satisfactory

Cedar Construction 24865Slope Protection (Repair & Maint.) along Sapang Maragul, San Juan Nepo, Betis, Guagua, Pampanga, 1.Sta.0+000-

Sta.0+252; 2.Sta.0+252-Sta.0+31003/19/12 III 4.385 90 C 0.438 0.133 0.300 - - - 87.10 86.14%

Satisfactory

Cedar Construction 24865 Repair/Rehab. of Slope Protection at Pamatawan River, Balaybalay 03/16/13 III 9.554 120 C 0.474 0.101 0.300 - - - 87.50 87.50%

SatisfactoryCeledio Construction Builders &

Supply 33923 Cayacay Small River Impounding Project 07/13/13 NIA 3.389 120 O 0.330 0.300 0.000 0.020 0.060 0.030 74.00 -

Celso C. Ferrer Contract 106438Repair/Reconst. Of Damaged Paved National Road along

Gapan-San Fernando-Olongapo Road, KO099+030.10 - KO110+300 with exceptions

9/26/2014 Special 3 32.253 150 C 0.321 0.200 0.300 82.10 82.10% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page51

Page 52: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Celso C. Ferrer Contractor 10643 Conc. of Bambang-Kasibu-Quezon-Solano Road (San Fernando Sect.) 11/27/08 II 47.758 120 O 0.366 0.240 0.100 0.030 0.033 0.067 83.60 -

Celso C. Ferrer-Contractor/ MIVICO Builders and Developers-JV

SL2-SN-001648

Package X-J: Construction of lateral "N" (Sta. 11+880-Sta. 13+440), sub-lat. "N-9" (Sta. 0+000-Sta. 1+020) and "N-9a" (Sta. 0+000-Sta. 0+920) including related structures and

supply, delivery and installation of steel gates

02/07/15 NIA 23.569 180 O 0.386 0.233 0.150 0.015 0.005 0.050 83.85 -

Central Mindanao Const. Multi-Purpose Cooperative 23697 Const. of MPB @ Pilot Provincial Science and Technology

H/S 11/07/08 XII 1.907 65 O 0.211 0.300 0.100 0.030 0.016 0.067 72.40 -

Central Mindanao Construction Multi-Purpose Cooperative 23697 Const. of Two (2) Storey, Four (4) Cl Sch. Bldg., at Antipas

NHS 08/09/13 XII 4.958 120 O 0.351 0.240 0.150 0.010 0.052 0.050 85.30 -

Central Mindanao Construction Multi-Purpose Cooperative 23697

Road Upgrading (Gravel to Concrete) Nat'l Secondary Rd. Km.1642+765-Km.1642+792, Km.1643+586-Km.1643+793

and Km.1644+772.50-Km.1645+131 (clustered) along Matalam-Lampayan-Antipas Rd.

08/17/11 XII 11.578 100 O 0.359 0.239 0.000 0.030 0.045 0.017 69.00 -

Central Mindanao Construction Multi-Purpose Cooperative 23697 Conc. of Paco-Roxas-Arakan Road, Pontevedra Section

Km. 1656+100-Km. 1656+750 09/05/09 XII 9.337 150 O 0.376 0.300 0.150 0.015 0.047 0.050 93.80 -

Central Mindanao Construction Multi-Purpose Cooperative 23697 Conc. of Paco-Roxas-Arakan Road, CFCST Section (KM.

1667+200-Km. 1667+963.65 09/05/09 XII 9.251 120 O 0.362 0.300 0.150 0.015 0.047 0.050 92.40 -

CENTRAL MINDANAO CONTRUCTION MULTI - PURPOSE

COOPERATIVE23697 Const. of Two (2) Storey Four (4) Classroom Schoo

Building at Antipas, NHS 8/9/2014 XII 5.015 195 C 0.488 0.154 0.161 80.30 83.80% Satisfactory

Cesar T. Carpio Construction 20833 Const./Rehab./Impvt. of Pambujan Circ. Road , Cababtoan-Cabarian-Canjumadal Road 08/31/08 VIII 9.295 180 O 0.288 0.225 0.100 0.030 0.040 0.100 78.30 -

Cesar T. Carpio Construction 20833 Repair/Rehab. of Catarman-Calbayog Road 08/26/08 VIII 9.594 150 O 0.364 0.240 0.100 0.030 0.032 0.100 86.60 -

CGGA Builders & Enterprises 23762 Const. of FMR 09/02/10 VIII 0.908 40 O 0.460 0.133 0.300 - - - 89.30 89.30% Very Satisfactory

CGR CAMILLE BUILDER, INC. (Formerly: CGR Camille Builder) 32259 Construction of Local Road at Pasonanca-Layuhan Road 10/21/2014 IX 4.668 90 O 0.379 0.239 0.083 0.030 0.025 0.017 77.30% 77.30%

Unsatisfactory

Cha Construction & Supply 28420 Const. of Concrete Rd., Zone 8, San Jose 08/06/13 V 3.880 45 C 0.442 0.133 0.300 - - - 87.50 87.50% Satisfactory

Cha Construction & Supply / E.A. Unabia Construction (JV) JV-10-188

Rd. Upgrading from Gravel to Concrete along Claveria-Calanasan-Kabugao Rd., K0624+(-301)-K0625+621, Sta.

Elena03/22/13 CAR 40.888 240 C 0.361 0.200 0.300 - - - 86.10 81.12%

Unsatisfactory

Charifer Builders, Inc. 33498 Development of Estancia Port 05/28/15 DOTC 8.196 90 C 0.418 0.200 0.300 - - - 91.84 91.84% Very Satisfactory

Chariot's Construction & Trading 27627 Repair/Rehab./Impvt. of Northwest Diversion Rd., Km. 63+537.50-Km. 69+807.50 w/ exceptions 11/19/12 III 5.000 118 O 0.268 0.300 0.150 0.030 0.047 0.050 84.50 -

Charlz Construction 8709 Const. of MPB at Opra NHS, Brgy. Kalunasan 03/21/13 VII 2.970 149 C 0.489 0.133 0.300 - - - 92.20 91.00% Very Satisfactory

CHARLZ CONSTRUCTION 8709Widening of National Roads,Improvement/Widening of

Daang Maharlika (Surigao - Agusan Section), Brgy. Luna, Surigao City

10/26/2014 XIII 41.684 179 O 0.335 0.240 0.150 0.020 0.051 0.050 84.60% 84.60% Satisfactory

Charlz Construction 8709Rd. Upgrading (Gravel to Paved) of Jct. S.H. Manolo

Fortich-Libona-Indahag Rd. (Gango Sect.) (K1492+845-K1494+000) Pob. Libona

08/07/13 X 25.514 120 C 0.479 0.200 0.300 - - - 97.90 82.12% Satisfactory

Charlz Construction 8709Rd. Upgrading (Gravel to Paved) of Jct. S.H.-Manolo

Fortich-Libona-Indahag Rd. (Gango Sect.) (K1492+845-K1494+000) Pob. Libona

03/21/13 X 25.514 106 O 0.310 0.251 0.035 0.030 0.040 0.050 71.60 -

Charlz Construction 8709Rehab./Impvt. of Butuan City-Misamis Oriental Road (Selective Conc. Paving along Balingasag-Binuangan

Sect.)08/24/08 X 38.527 379 O 0.316 0.300 0.100 0.015 0.041 0.100 87.20 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page52

Page 53: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Charlz Construction 8709 Const. of DPWH Bukidnon 3rd DEO Building (Phase III), Diklum 05/29/09 X 4.795 90 O 0.350 0.263 0.150 0.030 0.011 0.033 83.70 -

Charlz Construction 8709 Rehab./Reconst. (Asphalt to Concrete) of Jct. S.H. Manolo Fortich Libona-Indahag Rd., (Kiliog Section) 09/04/09 X 19.210 150 O 0.394 0.236 0.150 0.030 0.047 0.033 89.00 -

Charlz Construction 8709Road Upgrading (gravel to paved) @ Jct. Sayre Highway-

Impasug-ong-Patulangan By-Pass Rd., 1481+375-Km.1481+692 (w/ exception)

03/21/12 X 6.399 90 C 0.386 0.200 0.300 - - - 88.60 83.02% Satisfactory

Charlz Construction 8709 Cala-anan Resettlement Site Devt., Const. of Rds. (Conc.) & Drainages, Phase III, Brgy. Canitoan 11/25/12 X 55.782 150 C 0.421 0.133 0.300 - - - 85.40 86.60%

Satisfactory

Charlz Construction 8709 Cala-anan Resettlement Site Dev't., Const. of Rds. (Conc.) & Drainages, Phase III, Brgy. Canitoan 08/23/12 X 55.782 150 O 0.309 0.300 0.150 0.030 0.035 0.050 87.40 -

Charlz Construction 8709 Rehab./Reconst./Upgrading of Damaged Paved along Sayre Highway, Km.1470+531-Km.1473+1004 08/12/12 X 21.774 225 C 0.384 0.191 0.300 - - - 87.50 85.52%

Satisfactory

Charlz Construction 8706

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. along Butuan City-Cagayan de Oro-Iligan Rd., Agusan-Misamis Oriental K1263+000-K1264+000, K1265+000-

K1267+000

08/22/12 XIII 41.898 276 C 0.446 0.138 0.300 - - - 88.40 84.32% Satisfactory

CHEDMARYL CONSTRUCTION & SUPPLIES 27073 Const. of Lambunao NHS, Two (2) Storey, 6 Classroom

School Building 8/15/2014 VI 6.432 106 C 0.295 0.200 0.300 79.50 83.84% Satisfactory

Chedmaryl Construction & Supplies 27073 Const. of Lambunao NHS, Two (2) Storey 6 Classrooms

Bldg. 08/20/13 VI 6.432 90 O 0.370 0.226 0.150 0.030 0.048 0.033 85.70 -

CHIARA CONSTRUCTION 8736 Construction of 18.0 L.M Bridge 10/25/2014 I 5.107 134 C 0.414 0.158 0.300 - - - 87.20% 87.20% Satisfactory

Chiara Construction 8736 Const. of Two (2) Storey Building / Library at Tarlac State University, Lucinda Campus 11/13/08 III 14.416 270 O 0.388 0.180 0.100 0.030 0.022 0.100 82.00 -

China CAMC Engineeing Co., LTD. Const. of Agno River Integrated Irrigation Project (ARIIP) 08/15-20/11 NIA 93.846 900 O 0.370 0.290 0.150 0.030 0.070 0.050 95.97 -

China Harbour Engineering Company

SL1-SN-005059/FC-

07-005CP5, Cervantes-Mankayan-Abatan, Phase V 03/11/09 PJHL 682.076 812 O 0.365 0.300 0.150 0.030 0.070 0.050 96.50 -

China Harbour Engineering Company FC-98-264 CP5, Cervantes-Mankayan-Abatan, Phase V 11/14/08 PJHL 682.000 812 O 0.369 0.300 0.100 0.030 0.051 0.100 95.00 -

China Harbour Engineering Company FC-07-005

Contract Package 5, Cervantes-Mankayan-Abatan under Arterial Road Links Development Project, Phase V,

Sta.383+135 to Sta. 414+679.3808/27/09 PJHL 682.076 812 O 0.373 0.240 0.150 0.030 0.056 0.033 88.20 -

China Henan Shuili Yiju FC-10-003Landslide Risk Mitigation: Digos-Gen. Santos City Rd. & Davao-Calinan-Buda Rd., Mindanao Nat'l Rds. Impv't &

Mgt. Program Phase II (NRIMP)08/10/13 NRIM-PMO 535.161 731 O 0.390 0.300 0.077 0.030 0.047 0.050 89.40 -

China Henan Shuili Yiju FC-10-003 Landslide Risk Mitigation, Digos-Gen. Santos City Rd. & Davao-Calinan-Buda Rd. Sarangani and Davao City 03/16/13 NRIM-PMO 535.160 730 O 0.389 0.300 0.094 0.030 0.050 0.017 88.00 -

China International Water & Electric Corporation FC-09-008 Pinatubo Hazard Urgent Mitigation Proj. (PHUMP), Phase

III, CP-2, Lower Porac-Gumain River Diversion Channel 03/20/13 MPE-PMO 1,667.803 828 C 0.401 0.200 0.300 - - - 90.10 92.90% Very Satisfactory

China International Water & Electric Corporation FC-10-001

Impv't. of Digos-Cotabato Rd., Contract Package (CP)-RI 2.7 C: Pagalungan-Jct. Cotabato Sect., Mindanao Region,

under the Nat'l Rds. Impv't. & Mgt. Program, Phase II (NRIMP-II)

03/17/13 NRIM II - PMO 977.493 823 O 0.318 0.300 0.150 0.030 0.060 0.050 90.80 -

China International Water & Electric Corporation FC-10-001

Impvt. of Digos-Cotabato Rd., Contract Package (CP)-RI 2.7 C: Pagalungan-Jct. Cotabato Sect., Mindanao Region,

under NRIMP II08/14/12 NRIM-PMO 977.493 823 O 0.386 0.300 0.150 0.030 0.051 0.050 96.70 -

China Road & Bridge Corporation SL-2-SN-000631

Contract Package III, Calbayog-Gatanguit Road Sect., Arterial road links Dev't. Project, Phase VI 12/02/08 PJHL 1,397.424 1,020 O 0.360 0.300 0.100 0.030 0.070 0.100 96.00 -

China State (Phils.) Construction Eng'g. Corp.

SL1-SN-004865

CP No. C-5, Metro Manila Urban Transport Integration Project (MMURTRIP), NLEX Junction to North Fairview 11/24/08 URPO 606.345 720 O 0.340 0.300 0.050 0.030 0.056 0.067 84.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page53

Page 54: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

CHL Construction and Development Enterprises 15001 Impvt. of Marbel-Makar Rd. Pagalungan Sect. 08/23/12 XII 8.609 120 C 0.478 0.133 0.300 - - - 91.10 88.16%

Satisfactory

CHL Construction and Development Enterprises, Inc. 15001 Address Critical Bottlenecks, Traffic Decongestion,

Conc./Widening of Marbel-Makar Rd., Polomolok Sect. 08/23/13 XII 44.991 170 C 0.367 0.195 0.300 - - - 86.20 86.20% Satisfactory

CHL CONSTRUCTION AND DEV'T. ENT., INC. 15001

Concreting/Widening of Marbel-Makar Road, South Cotabato K1677+817 - K1680+320 (w/ exception), Tupi

Section8/16/2014 XII 45.768 165 C 0.446 0.133 0.300 87.90 87.90%

Satisfactory

Cholo Construction and Trading 32138 Drainage/Slope Protection along San Miguel-Concepcion Rd. 11/19/12 III 4.725 90 O 0.320 0.240 0.058 0.030 0.029 0.033 71.00 -

Chris-James Construction 11202 Upgrading (Gravel to Paved) of Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd., K0813+464-K0815+194 08/08/13 VIII 41.807 180 O 0.344 0.300 0.108 0.030 0.065 0.017 86.40 -

Chris-James Construction 11202Rd. Upgrading (Gravel to Paved) Conc. of Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd., Km.824+000-

Km.825+49408/06/13 VIII 31.280 237 C 0.418 0.133 0.300 - - - 85.10 83.42%

Satisfactory

Chris-James Construction 11202Road Upgrading (Gravel to Paved) Conc. of Pangpang-

Palapag-Mapanas-Gamay-Lapinig Rd., Km.824+000-Km.825+494.00

08/17/12 VIII 31.280 237 O 0.277 0.300 0.150 0.030 0.033 0.033 82.30 -

Chrisman Construction and Supplies 33274 Viga Pilot Channel Flood Control 07/30/13 V 4.825 64 C 0.456 0.133 0.300 - - - 88.90 88.90%

Satisfactory

CHRISTER CONSTRUCTION 16591 ROAD NETWORK CONSTRUCTION/ SITE DEV'T PHASE I 04/03/14 DOST 5.778 180 C 0.475 0.200 0.300 - - - 97.50 97.50% Outstanding

Christian Ian Construction Corporation 8191

Construciton/Widening/ Upgrading/Rehabilitation of Access Road to Declared Tourism Destinations, Bangrin

Mangrove Road, Sta. 0+000 to Sta. 4+9408/16/2014 I 65.743 285 C 0.412 0.200 0.300 91.20 91.20%

Very Satisfactory

Christian Ian Construction Corporation 8191

Const./Widening of/Upgrading/Rehab. of Access Rd. to Declared Tourism Destinations, Bangarin Mangrove Rd.,

Sta. 0+000-Sta. 4+49008/07/13 I 61.527 244 C 0.370 0.300 0.150 0.030 0.042 0.033 92.50 -

Christian Ian Construction Corporation 8191 Improvement/Rehab.of Daang Maharlika Road 09/05/09 III 41.225 180 O 0.342 0.300 0.150 0.030 0.050 0.033 90.50 -

Christian Ian Construction Corporation 8191 Replacement of Alasas Bridge, Brgy. San Isidro 08/14/12 III 10.973 150 C 0.455 0.200 0.300 - - - 95.50 93.34%

Very Satisfactory

Christian Ian Construction Corporation 8191

Rehab./Reconst. along Kennon Rd. (Int. Sect.) K0222+000-K0222+045, K0230+000-K0230+602, K0230+683.65-

K0231+121.20 (K0230+683.65-K0231+116.70 as per RBIA) K0231+154-K0231+761.20 (K0231+149.50-K0231+756.70 as

per RBIA) K0231+816-K0232+428.70 (K0231+811.50-K0232+400.10 as per RBIA) K0233+000-K0233+282.60, K0233+302.40-K0233+424.20 K0233+441.50-K0234+000

03/11/13 CAR 48.763 279 C 0.394 0.133 0.300 - - - 82.70 82.70% Satisfactory

CHU CONSTRUCTION 33747Rehabilitation/Reconstruction/Upgrading of Damaged

Paved National Secondary Roads of Kiling-Tanauan Tabon-Julita Road, K0932+(-638) - K0932+273

10/29/2014 VIII 13.921 140 C 0.404 0.133 0.300 - - - 83.70% 83.70% Satisfactory

CHU CONSTRUCTION 33747Replacement of Mabini Bridge 2 along Jct. Mabini -

Tubajon Road (Const. of Two Barrel RCBC), Tubajon, Dinagat Islands

10/27/2014 XIII 5.287 190 O 0.344 0.300 0.001 0.020 0.042 0.033 74.00% 74.00% Poor

CHU CONSTRUCTION 33747 Protection Works along Dinagat - Loreto Road, Wilson, San Jose, Dinagat Islands 10/27/2014 XIII 9.142 130 O 0.366 0.300 0.000 0.020 0.042 0.033 76.10% 76.10%

Unsatisfactory

CHU CONSTRUCTION COMPLETION OF MULTI-PURPOSE GYMNASIUM PH II 09/06/13 DOST 17.919 180 C 0.450 0.200 0.300 - - - 95.00 95.00% Very Satisfactory

Chu Construction 33747 Rd. Upgrading for Kiling-Tanauan-Tabontabon-Julita Road, K0934+128-K0935+(-429) 08/17/13 VIII 8.592 195 C 0.425 0.133 0.300 - - - 85.80 85.02%

Satisfactory

Chu Construction 33747Road Upgrading for Kiling-Tanauan-Tabontabon-Julita

Road, K0934+128-K0935+(-)429; K0935+(094)-K0935+388; K0936+(-)071-K0937+000

03/11/13 VIII 8.566 126 O 0.392 0.180 0.150 0.023 0.050 0.050 84.50 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page54

Page 55: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Chu Construction 33747 Prev. Maint. of Palo-Carigara-Ormoc Km.0947+000-Km.0947+600 08/21/12 VIII 5.458 120 C 0.451 0.133 0.300 - - - 88.40 84.62%

Satisfactory

Chu Construction 33747 Rehab./Reconst. Along Jct.-Taft-Oras-San-San Policarpio-Arteche Rd., K0908+385-K0908+211 08/19/13 VIII 11.690 114 O 0.330 0.300 0.000 0.030 0.060 0.033 75.30 -

Chu Construction / Jelm Construction (JV) JV-12-301

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. along Naga-Naga Anibong Rd., Km.0906+(-858)-K0906+(-405); K0906+103-K0906+1950 & K0906+039-K0906+439

08/22/13 VIII 30.164 258 O 0.356 0.240 0.150 0.030 0.060 0.050 88.60 -

Cielito A. Bay-ag Construction 19032 Concreting of Aritao-Quirino Road, Lupa Section 06/04/09 II 9.606 120 O 0.338 0.240 0.150 0.030 0.051 0.033 84.20 -

Ciriaco Corporation 6932 Contract Package II-A Lullutan Bridge 03/14/13 FABP-PMO 712.913 840 O 0.385 0.240 0.150 0.030 0.056 0.050 91.10 -

Ciriaco Corporation 6932 Const. of Delfin Albano Bridge along Tumauini-Delfin Albano Road (SA #2) 03/05/09 II 234.155 360 O 0.388 0.300 0.150 0.030 0.050 0.050 96.80 -

Ciriaco Corporation 6932 Const. of Delfin Albano Bridge along Tumauini-Delfin Albano Road (SA #1) 08/13/08 II 234.155 360 O 0.400 0.296 0.100 0.030 0.060 0.100 98.60 -

Ciriaco Corporation 6932 Contract Package II-A, Lullutan Bridge 08/07/12 PMO-PBPO 712.913 840 O 0.384 0.300 0.150 0.030 0.061 0.033 95.80 -

Citystar Construction 32774 Construction of Pasugui Flood Control (Pasugui Section Phase 2), Sablayan, Occidental Mindoro 8/14/2014 IV-B 9.380 264 C 0.365 0.200 0.300 86.50 84.22%

Satisfactory

Citystar Construction 32774 Const. of Pasugui Flood Control (Pasugui Sect. Phase 2) 07/30/13 IVB 8.380 204 O 0.310 0.300 0.124 0.030 0.030 0.033 82.70 -

CJA CONST. & SUPPLIES, CO. 34140Preventive Maintenance based on Preventive Management System/HDM-4 (Intermittent Section), Old Cagayan Valley

Road, Km. 43+204 - Km. 43+95611/24/2014 III 3.569 33 C 0.437 0.133 0.300 - - - 87.00% 87.00%

Satisfactory

CJA Construction and Supplies 34140 Const./Rehab. of Brgy. Perez Health Center 03/18/13 III 0.950 50 C 0.421 0.133 0.300 - - - 85.40 85.40% Satisfactory

Cleofe A. Aliviado Construction and Engineering Services 32676

Rehab./Reconst. of Damaged Paved Nat'l Rds., Bais-Kabankalan Rd., K0052+604-K0053+4 & K0055+0-K0056+4,

2nd District08/11/12 VII 12.189 215 C 0.418 0.200 0.300 - - - 91.80 83.64%

Satisfactory

CLIFFORD CONSTRUCTION CORPORATION 3724 Construction/Upgrading of River Control System Panitan

River Control, K0116+172 10/29/2014 VI 16.657 170 C 0.424 0.133 0.300 - - - 85.70% 85.70% Satisfactory

CLIFFORD CONSTRUCTION CORPORATION 3724 Construction/Upgrading of River Control System Panay

(Sta. Monica) River Control, K0124+050 10/29/2014 VI 9.800 179 C 0.411 0.133 0.300 - - - 84.40% 84.40% Satisfactory

CLIFFORD CONSTRUCTION CORPORATION 3724 Hamtic Port Development Project 01/29/15 DOTC 11.634 210 C 0.415 0.200 0.300 - - - - 93.30%

Very Satisfactory

Clifford Construction Corporation 3724 Hamtic Port Development Project 07/10/14 DOTC 11.634 210 O 0.374 0.300 0.150 0.030 0.041 0.050 94.52 -

Clifford Construction Corporation 3724Rehab./Reconst./Replacement/Retrofitting of Existing

Bridge along Nat'l Rds., Catipayan Bridge along Iloilo East Coast Capiz Bridge

08/18/13 VI 5.980 170 O 0.366 0.240 0.000 0.030 0.042 0.033 71.10 -

Clifford Construction Corporation 3724 Road Upgrading (Gravel to Concrete) Altavas-Jamindan Road 06/06/09 VI 3.849 150 O 0.362 0.246 0.150 0.023 0.045 0.033 85.90 -

Clifford Construction Corporation 3724 Road Upgrading / Concreting along Altavas-Jamindan Road 03/14/09 VI 21.841 210 O 0.330 0.294 0.150 0.030 0.055 0.033 89.20 -

Clifford Construction Corporation 3724 Road Upgrading/Conc. along Altavas-Jamindan Road 09/05/09 VI 22.278 349 O 0.336 0.287 0.110 0.023 0.040 0.017 81.30 -

Clifford Construction Corporation 3724 Rehab. of Tambak Seawall along Jaime Cardinal Sin Ave. (Phase II) Brgy. Tambak 03/25/12 VI 26.668 210 O 0.331 0.300 0.150 0.030 0.043 0.033 88.70 -

Clifford Construction Corporation 3724 Rehab. of Tambak Seawall along Jaime Cardinal Sin Ave. (Phase I), Brgy. Tambak 11/25/12 VI 25.626 270 C 0.457 0.133 0.300 - - - 89.00 85.34%

Satisfactory

Clifford Construction Corporation 3724 Rehab. of Tambak Seawall along Jaime Cardinal Sin Ave. (Phase I), Brgy. Tambak 08/17/12 VI 25.631 270 O 0.358 0.251 0.150 0.030 0.043 0.050 88.20 -

Clifford Construction Corporation 3724 Rehab. of Tambak Seawall along Jaime Cardinal Sin Ave. (Phase 2), Brgy. Tambak 08/17/12 VI 26.662 300 O 0.334 0.254 0.150 0.030 0.043 0.033 84.40 -

Clifford Construction Corporation 3724 Roxas PCG Station Building Development Project 08/13/13 DOTC 10.762 240 O 0.324 0.300 0.150 0.030 0.023 0.050 87.75 -

Clifford Construction Corportation 14332 Roxas PCG Station Building Project 03/18/14 DOTC 10.762 240 C 0.490 0.200 0.300 - - - 98.96 91.10% Outstanding

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page55

Page 56: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

CLTG BUILDERS 16852

Construction/ Rehabilitation of Drainage/ Protection of Works along National Roads & Bridges, Construction of Drainage System along Daang Maharlika, Davao City 2nd

LD c. Sasa Section

10/30/2014 XI 18.050 182 C 0.430 0.160 0.300 - - - 89.00% 89.00% Satisfactory

CLTG BUILDERS 16852 Construction of Calinan - Toril Road, Including ROW, Tagakpan Section Km. 1695+247.93 - Km. 1698+750 8/5/2014 XI 46.053 209 C 0.353 0.200 0.300 85.30 83.14%

Satisfactory

CLTG BUILDERS 16852 Widening of Digos – Makar Road (KO1576+240 to KO1577+(-010)), Padada Section, Padada 8/6/2014 XI 19.538 121 C 0.400 0.133 0.300 83.30 83.30%

Satisfactory

CLTG BUILDERS 16852

GAA Widening of Tagum-Panabo Circumferential Road, Davao del Norte 2nd LD Panabo City to Sto. Tomas Section

K1519+378 – K1520+851, Southern Davao Section DPWH CY 2014 (Widening of Tagum-Panabo Circumferential

Road, K1519+342 – K1520+851 Southern Davao Section, Panabo City)

8/8/2014 XI 29.216 191 C 0.331 0.200 0.300 83.10 83.10% Satisfactory

CLTG Builders 16852Rehab./Reconst./Upgrading along Digos-Makar Rd.,

Balutakay-Guihing Sect., Km.1568+718-Km.1568+1003.4; Km.1572+004.50-Km.1572+706.25

08/09/13 XI 19.425 70 C 0.444 0.133 0.300 - - - 87.70 87.70% Satisfactory

CLTG Builders 16852 Const. of Calinan-Toril Rd., incl. ROW, Tagakpan Sect., Km.1695+247.93-Km.1698+750 08/06/13 XI 46.053 209 O 0.316 0.300 0.102 0.030 0.036 0.033 81.70 -

CLTG Builders 16852 Rds. to Address Critical Bottlenecks Widening of Daang Maharlika (Agusan-Davao Rd.), Davao City Sect. 11/29/12 XI 19.429 243 C 0.480 0.133 0.300 - - - 91.30 85.96%

Satisfactory

CLTG Builders 16852 Widening of Davao-Cotabato Road, Toril District 08/16/12 XI 27.749 180 C 0.421 0.133 0.300 - - - 85.40 87.08% Satisfactory

CLTG Builders 16852 Rd. to Address Critical Bottlenecks Widening of Daang Maharlika (Agusan-Davao Rd.) Davao City Sect. 08/20/12 XI 19.429 165 O 0.335 0.231 0.140 0.030 0.055 0.033 82.40 -

CLTG Builders / Square Cube Construction (JV) JV-11-294 Widening of Tagum-Panabo Circ. Rd., 1st District, Pob.

Kapalong Sect. 08/01/13 XI 40.803 272 C 0.364 0.200 0.000 - - - 56.40 73.80% Poor

CLTG Builders / Square Cube Construction (JV) JV-11-293 Widening of Tagum-Panabo Circ. Rd., Pob. Kapalong Sect. 08/12/12 XI 38.317 263 O 0.361 0.225 0.150 0.030 0.055 0.033 85.40 -

CM Tan Construction (Formerly: CM Tan Const. Supplies) 28087 Impvt./Rehab. of Andanan River Control 08/19/12 XIII 17.340 210 C 0.333 0.200 0.300 - - - 83.30 86.60%

Satisfactory

CM TAN CONSTRUCTION (Formerly: CM Tan Construction

Supplies)28087 Construction/Improvement of Road along NRJ-Bayugan-

Calaitan-Tandag Road, K1295+260 - K1296+615 10/22/2014 XIII 42.119 276 O 0.355 0.220 0.150 0.023 0.037 0.050 83.50% 83.50% Satisfactory

CM Tan Construction (Formerly: CM Tan Construction Supplies) 28087 Const. of Protection Works along NRJ-Bayugan-Esperanza

Rd. crossing Luna, (Sect. 2) 1276+566.20-1276+648.40 03/20/13 XIII 18.188 225 O 0.339 0.300 0.150 0.030 0.030 0.030 87.90 -

CM Tan Construction (Formerly: CM Tan Construction Supplies) 28087

Rehab. of Crossing Luna Flood Control, NRJ-Bayugan-Esperanza Nat'l Rd. (Sect. 3) K1276+648-K1276+662.8

(Piling); K1276+400-K1276+720 (Deepening) Crossing Luna03/20/13 XIII 16.726 225 O 0.400 0.225 0.147 0.022 0.032 0.033 85.90 -

CMSEL Construction and Developer/I.F. Blanco's

Construction - Joint VentureJV-13-161 Construction of Camansihan River Control, Calapan City,

Oriental Mindoro 8/11/2014 IV-B 9.014 89 C 0.440 0.133 0.300 87.30 87.30% Satisfactory

CNE CONSTRUCTION 22148Rehabilitation of Road Slip along Biliran Circumferential

Road, Kawayan-Culaba Section, Km.1045+000 - Km. 1051+000 Intermittent Section

10/27/2014 VIII 9.158 84 C 0.391 0.200 0.300 - - - 89.10% 89.10% Very Satisfactory

Coastland Construction and Development Corp. 11487 Widening of Pres. Diosdado P. Macapagal Highway

(Caganganan Sect.) Km.1757+440-Km.1759+000 03/19/13 XI 23.855 130 O 0.330 0.219 0.150 0.030 0.045 0.050 82.40 -

Coastland Construction and Development Corp. 11487 Widening of Pres. Diosdado P. Macapagal Highway

(Manikling Sect.) Km.1742+889-Km.1743+586 03/19/13 XI 15.461 99 O 0.334 0.216 0.150 0.030 0.055 0.033 81.80 -

Coastland Construction and Development Corporation 11487

Widening of Pres. Diosdado P. Macapagal Highway (Pob. Lupon Sect.) a)Km.1751+046.67-Km.1752+797.67;

b)Km.1753+673.86-Km.1754+88008/15/13 XI 46.479 190 C 0.401 0.200 0.300 - - - 90.10 85.96%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page56

Page 57: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Coastland Construction and Development Corporation 11487 Widening of Pres. Diosdado P. Macapagal Highway

(Manikling Sect.) Km.1742+889-Km.1743+586 08/15/13 XI 15.461 99 C 0.441 0.133 0.300 - - - 87.40 84.04% Satisfactory

Coastland Construction and Development Corporation 11487 Widening of Pres. Diosdado P. Macapagal Highway

(Caganganan Sect.) Km.1757+440-Km.1759+000 08/15/13 XI 23.855 130 C 0.365 0.200 0.300 - - - 86.50 84.04% Satisfactory

Coastland Construction and Development Corporation 11487

Widening of Pres. Diosdado P. Macapagal Highway (Pob.-Lupon Sect.) a)Km.1751+046.67-Km.1752+797.67;

b)Km.1753+673.86-Km.1754+88003/19/13 XI 46.479 176 O 0.339 0.218 0.150 0.030 0.045 0.050 83.20 -

Coastland Construction and Development Corporation 11487 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd.

Jct. Manikling-Gov. Generoso Rd. 08/16/12 XI 20.771 180 C 0.416 0.133 0.300 - - - 84.90 88.38% Satisfactory

Coastland Construction and Development Corporation 11487 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd.

(IS) along Davao Oriental-Surigao del Sur Coastal Rd. 08/16/12 XI 40.106 150 C 0.408 0.133 0.300 - - - 84.10 85.00% Satisfactory

COFEJOK CONSTRUCTION AND SUPPLY CORP. 27493 Rehabilitation / Restoration of Fort Nuestra Señora del

Pilar Project 11/13/14 TIEZA 6.454 90 C 0.494 0.200 0.300 99.40 99.40% Outstanding

COFEJOK CONSTRUCTION AND SUPPLY CORPORATION

(Formerly: COFEJOK CONSTRUCTION AND SUPPLY)

27493Construction/Rehabilitation of Drainage/Slope Protection Works Flood Control along Kidapawan - Ala Jct. Road at

Kalawag I Section, Isulan, Sultan Kudarat10/23/2014 XII 4.801 147 C 0.451 0.133 0.300 - - - 88.40% 88.40%

Satisfactory

COFEJOK CONSTRUCTION AND SUPPLY CORPORATION

(Formerly: COFEJOK CONSTRUCTION AND SUPPLY)

27493 Local Infrastructure Program: Construction of Multi-Purpose Building 10/21/2014 XII 4.787 150 O 0.396 0.240 0.150 0.020 0.043 0.033 88.20% 88.20%

Satisfactory

COFEJOK CONSTRUCTION AND SUPPLY CORPORATION

(Formerly: COFEJOK CONSTRUCTION AND SUPPLY)

27493Road Upgrading (Gravel to Concrete) along Isulan Hwy. Jct. Dukay-Bagumbayan-Sen. Aquino-Kalamansig Road

(Km. 1859+000 - Km. 1859+900)10/27/2014 XII 19.521 83 O 0.384 0.237 0.000 0.030 0.045 0.033 72.90% 72.90%

Poor

COFEJOK CONSTRUCTION AND USPPLY CORPORATION

(Formerly: COFEJOK CONSTRUCTION AND SUPPLY)

Rehabilitation/Reconstruction of Critical Sections along National Roads, Road Slip along Isulan Hwy. Jct. - Sen.

Ninoy Aquino Road (K1808+523 - K1817+000 w/ exceptions)

10/27/2014 XII 34.755 336 O 0.370 0.240 0.150 0.030 0.050 0.033 87.30% 87.30% Satisfactory

COLBY CONSTRUCTION 33969 Construction of One Classroom School Building, Doña Imelda E/S 10/28/2014 II 1.092 45 C 0.377 0.200 0.300 - - - 87.70% 87.70%

Satisfactory

Colby Construction 33969 Construction of Footbridge 8/13/2014 II 3.960 105 C 0.470 0.063 0.300 83.30 83.30% Satisfactory

COLLERA'S CONSTRUCTION 13246Widening of Daang Maharlika (SO0024LT), KO915+411 -

KO916+911, KO919+754 - KO920+300.15 Salvacion - Cogon Section, Palo, Leyte & Calogcog - Solano Section

8/10/2014 VIII 34.120 210 OG 0.362 0.207 0.150 0.030 0.045 0.033 82.70 -

Collera's Construction 11246 Rehab. of Rd. Slip along Daang Maharlika, Abuyog & Mahaplag 08/09/13 VIII 7.223 100 C 0.490 0.133 0.300 - - - 92.30 92.30%

Very Satisfactory

Collera's Construction 11246Prev. Maint. along Ormoc-Baybay-Southern Leyte Bdry.

Rd., (K1087+000-K1088+000; K1089+000-K1092+000; K1092+000-K1093+000)

08/08/13 VIII 5.014 75 C 0.454 0.133 0.300 - - - 88.70 88.70% Satisfactory

Collera's Construction 11246 Rehab. of Rd. Slip along Daang Maharlika, Abuyog 03/15/13 VIII 7.223 100 O 0.334 0.240 0.150 0.030 0.035 0.033 82.20 -

Collera's Construction 13246 Rehab./Reconst./Upgrading of Damaged Paved Nat'l. Road Km.977+605-Km.983+000 (w/ exceptions) 03/27/12 VIII 8.314 130 C 0.262 0.133 0.300 - - - 69.50 84.20%

Satisfactory

Compact Builders, Inc 14492 Const. of 1 unit 3-Storey, 15-Classroom School Building 12/10/09 NHA 21.491 210 O 0.291 0.300 0.121 0.030 0.038 0.050 83.00 -

Compact Builders, Inc 14492 Construction of Livehood, Productivity & Training Center 02/09/10 NHA 4.992 120 O 0.334 0.300 0.150 0.030 0.059 0.923 92.30 -

Compact Builders, Incorporated 14492 Impv't./Asphalt Overlay of Kamuning Road K0011+588-K0012+122 03/19/13 NCR 5.754 39 C 0.447 0.133 0.300 - - - 88.00 88.00%

SatisfactoryCONCEPCION BASIC BUILDERS,

INCORPORATED 5255 Completion/Retrofitting of Tago-San Miguel Bridge along Jct. Gamut - San Miguel Road 10/30/2014 XIII 19.415 270 O 0.334 0.224 0.150 0.023 0.051 0.050 83.20% 83.20%

SatisfactoryConcepcion Basic Builders,

Incorporated 5255 Const. of Bislig Bridge (Completion) along Surigao-Davao Coastal Rd. 03/03/10 XIII 92.432 340 O 0.373 0.235 0.150 0.030 0.050 0.033 87.10 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page57

Page 58: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Concepcion Basic Builders, Incorporated 5255 Const. of Bislig Bridge along Surigao-Davao Coastal Road 11/27/08 XIII 81.615 365 O 0.286 0.300 0.100 0.030 0.059 0.100 87.50 -

Concepcion Basic Builders, Incorporated 5255 Const. of Bislig Bridge along Surigao-Davao Coastal Road 06/06/09 XIII 81.615 365 O 0.400 0.300 0.097 0.030 0.056 0.050 93.30 -

Concepcion Basic Builders, Incorporated 5255 Reconst./Completion of Tago-La Paz Bridge & Approaches 03/25/12 XIII 143.104 405 O 0.343 0.300 0.150 0.030 0.035 0.050 90.80 -

Concepcion Basic Builders, Incorporated 5255 Rehab. of Tago-San Miguel Bridge along NRJ-Bahbah-

Talacogon Rd. at Mapaga-Mabagoy Sect. 03/25/12 XIII 42.877 300 O 0.360 0.240 0.150 0.030 0.040 0.050 87.00 -

Concepcion Basic Builders, Incorporated 5255 Reconst./Completion of Tago La-Paz Bridge & Approaches 08/14/12 XIII 143.105 465 O 0.358 0.300 0.059 0.030 0.050 0.033 83.00 -

Concepcion Basic Builders, Incorporated 5255 Rehab. of Tago-San Miguel Bridge along Jct. Gamut-San

Miguel Rd. 08/17/12 XIII 42.877 330 O 0.400 0.300 0.002 0.030 0.060 0.017 80.90 -

CR DOMINGO CONSTRUCTION, INC. 2992 Const/Rehab of Drainage/Protection Works of San Jose-

San Marcos Flood Control, Alfonso, Lista, Ifugao 8/6/2014 CAR 7.398 140 C 0.356 0.133 0.300 78.90 78.90% Unsatisfactory

CR DOMINGO CONSTRUCTION, INC. 2992 Road Upgrading (Gravel to Paved) Along Ubao-Taang

Road, K0442+300 to K0445+765 8/6/2014 CAR 46.608 313 C 0.426 0.133 0.300 85.90 84.82% Satisfactory

CR DOMINGO CONSTRUCTION, INC. 2992 Road Upgrading (Gravel to Paved) Along Alfonso Lista-

Aurora Bdry Rd, K0442+124.5 to K0445+540 8/6/2014 CAR 38.538 260 C 0.448 0.133 0.300 88.10 85.22% Satisfactory

CR Domingo Construction, Inc. (Formerly: CR Domingo Const.) 2992 Const. of San Juan-San Jose Flood Control 11/25/12 CAR 13.475 148 O 0.388 0.238 0.150 0.022 0.033 0.033 86.40 -

CREST Construction 15240Preventive Maintenance Based on PMS (HDM-4)

(Intermittent Seciton) along, CAR Asphalt Overlay (50mm thk.)

8/7/2014 II 33.736 120 C 0.478 0.066 0.300 84.40 84.40% Satisfactory

Crest Construction 15240Prev. Maint. (Asphalt Overlay, 80mm Thick), Cagayan

Valley Rd., K0462+914-K0463+469, K0464+000-K0465+000, K0466+000-K0467+000

07/29/13 II 29.542 105 C 0.444 0.133 0.300 - - - 87.70 87.70% Satisfactory

Crest Construction 15240 Prev. Maint. (Asphalt Overlay 50mm Thick) Cagayan Valley Rd., K0470+857-K0474+000 07/29/13 II 23.988 95 C 0.430 0.133 0.300 - - - 86.30 86.30%

Satisfactory

Crest Construction 15240 Rehab. of Itawes Bridge Approach, K0519+725 (CAR) 11/19/12 II 7.726 166 O 0.380 0.240 0.150 0.030 0.059 0.050 90.90 -

Crizel Construction & Concrete Products 20835

Rd. Upgrading (Gravel to Conc.), Int. Sect., Dipolg-Punta-Dansullan-Sergio Osmeña, Zamboanga del Norte/Sur

Bdry., K1866+000-K1866+63508/20/13 IX 4.399 53 C 0.339 0.185 0.300 - - - 82.40 73.34%

Poor

Crizel Construction & Concrete Products 20835

Rd. Upgrading (Gravel to Conc.) Int. Sect., Dipolog-Punta-Dansullan-Sergio Osmeña, Zamboanga Norte/Sur Bdry.,

K1866+000-K1866+63503/22/13 IX 4.399 45 O 0.323 0.240 0.000 0.030 0.047 0.033 67.30 -

CSE Builders/ Eddmari Construction & trading - JV

Land Development and Construction of 1000 Housing Units (Channel Ridgeview 1) 09/05/15 NHA 289.700 405 O 0.319 0.247 0.000 0.030 0.042 0.033 67.14 -

CSJ CONSTRUCTION 34381 Rehab./Reconst./Upgrading of Damaged Paved National Roads along San Jose Old Road, K0725+400 - K0726+647 10/21/2014 VIII 1.079 64 C 0.413 0.133 0.300 - - - 84.60% 84.60%

Satisfactory

CSJ CONSTRUCTION 34381 Construction of Local Road, Opong-Irawahan Road, Sta. 0+000.00 - Sta. 0+550.00 11/20/2014 VIII 5.819 75 C 0.418 0.200 0.014 - - - 63.20% 63.20%

Poor

CTan Construction 18192 Const. of MPB @ Brgy. Obrero 03/15/13 V 1.480 90 C 0.432 0.133 0.300 - - - 86.50 86.50% Satisfactory

CTC BUIDER AND SUPPLIES INCORPORATED (Formerly: CTC

Builder)12088 Construction of Flood Control System along Bagacay

River 11/6/2014 V 14.097 120 C 0.413 0.133 0.300 - - - 84.60% 84.60% Satisfactory

CTC Builder & Supplies Incorporated (Formerly: CTC

Builder)12088 Const. of Macawayan River Flood Control Structures 08/14/13 V 13.958 131 C 0.455 0.175 0.300 - - - 93.00 88.02%

Satisfactory

CTC Builder and Supplies Inc./Sunwest Const. & Dev. Corp.

(JV)JV-06-070 Const. of Dancalan Bridge 02/25/09 V 57.031 720 O 0.352 0.240 0.150 0.030 0.061 0.033 86.60 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page58

Page 59: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

CTC Builders & Supplies Incorporated (Formerly: CTC

Builder)12088 Const. of Bacolod River Flood Control Structures, Brgy.

Bacolod 08/14/13 V 13.960 123 C 0.375 0.200 0.300 - - - 87.50 85.46% Satisfactory

CTC Builders & Supplies Incorporated (Formerly: CTC

Builder)12088 Impv't. of Bacon Public Market, Bacon District 03/16/13 V 28.016 540 C 0.379 0.200 0.300 - - - 87.90 89.51%

Very Satisfactory

CTC Builders & Supplies Incorporated (Formerly: CTC

Builder)12088 Const. of Macawayan River Flood Control Structures 03/15/13 V 13.958 131 O 0.294 0.300 0.150 0.015 0.055 0.033 84.70 -

CTC Builders & Supplies Incorporated (Formerly: CTC

Builder)12088 Const. of Bacolod River Flood Control Structures, Brgy.

Bacolod 03/15/13 V 13.960 123 O 0.344 0.222 0.150 0.030 0.045 0.050 84.10 -

CTC Builders & Supplies Incorporated (Formerly: CTC

Builder)12088 Replacement of Madarag Bridge along Daan Maharlika

(Daraga-Matnog Sect.) 03/16/13 V 38.140 330 C 0.412 0.200 0.000 - - - 61.20 77.88% Unsatisfactory

CTC Builders and Supplies Incorporated 12088 Construction of Flood Control System along Bagacay

River 8/12/2014 V 14.097 120 C 0.395 0.161 0.300 85.60 85.60% Satisfactory

CTC Builders and Supplies Incorporated (Formerly: CTC

Builder)12088 Road Widening along Daang Maharlika (K0574+180 -

K0579+000), Sorsogon City - Matnog Section 8/13/2014 V 47.382 240 C 0.396 0.151 0.300 84.70 84.70% Satisfactory

CTC Builders and Supplies Incorporated (Formerly: CTC

Builder)12088

Repair/Rehab. of Ariman-Casiguran Rd. (K0602+(-)051 - K0602+462) & Repair/Rehab. of Damaged Rd. along Ariman-

Casiguran (K0602+462-K0602+480)08/03/12 V 8.618 90 C 0.433 0.133 0.300 - - - 86.60 88.28%

Satisfactory

CTC Construction & Supplies 33039 Repair/Rehab. of Mapuyo Bridge, Brgy. Mapuyo 08/15/13 VIII 9.332 90 C 0.500 0.133 0.300 - - - 93.30 93.30% Very Satisfactory

CTC Construction & Supplies 33039 Repair & Maint. of Almeria Flood Control 08/14/13 VIII 1.940 90 C 0.469 0.133 0.300 - - - 90.20 90.20% Very Satisfactory

CTC Construction & Supplies 33039 Repair/Rehab. of Doroteo Bridge, Brgy. Talahid 03/12/13 VIII 4.550 80 C 0.469 0.138 0.300 - - - 90.70 90.70% Very Satisfactory

Culasi General Merchandising & Construction Services 22157 Construction of Canal Bench Flume 10/19/13 NIA 2.029 120 O 0.260 0.120 0.000 0.020 0.030 0.050 48.03 -

Culasi General Merchandising and Construction Services 22157 Const. of Two (2) CL Sch. Bldg., Sta. Barbara Nat'l

Comprehensive High Sch. 08/22/13 VI 0.969 60 C 0.483 0.133 0.300 - - - 91.60 91.60% Very Satisfactory

Culasi General Merchandising and Construction Services 22157 Const. of Two (2) CL Sch. Bldg, Buenavista Elem. Sch. 08/15/13 VI 1.486 60 O 0.360 0.240 0.000 0.030 0.027 0.033 69.00 -

Currimao Integrated Builders Corporation 8738 Manila North Road, K0468+609-K0469+967 (Reblocking and

Conc. of Shoulder), Batac Sect. 03/16/12 I 14.822 150 C 0.416 0.200 0.300 - - - 91.60 88.24% Satisfactory

C'ZARLES CONSTRUCTION & SUPPLY 23426

Rehabilitation/Reconst./Upgrading/Concreting along Jct. Old Escalante - Danao Port Road, K0102 + (-700) - K0102 +

(-076)10/21/2014 VI 10.469 153 C 0.408 0.133 0.300 - - - 84.10% 84.10%

Satisfactory

D & D Construction 33327 Const. of MPB Poblacion, La Paz 08/02/11 CAR 1.403 120 O 0.386 0.300 0.000 0.030 0.041 0.025 78.20 -D. C. E. Construction 29347 Const. of Ili Flood Control 03/21/13 CAR 12.905 225 O 0.328 0.288 0.006 0.018 0.023 0.000 66.30 -D. C. E. Construction 29347 Const. of Ili Flood Control 11/28/12 CAR 12.859 210 O 0.355 0.273 0.111 0.020 0.033 0.033 82.50 -

D. G. Sarmenta Construction 13024 Puerto Princesa Airport and Development Project 11/12/14 DOTC 21.496 150 C 0.487 0.200 0.300 - - - - 93.34% Very Satisfactory

D. G. Sarmenta Construction 13024 Puerto Princesa Airport Development Project 04/28/14 DOTC 21.496 150 O 0.368 0.300 0.136 0.030 0.027 0.050 91.03 -

D. S. PAMINTUAN CONSTRUCTION 4326 Improvement of Radial Gate & Portland Cement Concrete Pavement 05/23/15 NIA 19.563 90 C 0.3118 0.200 0.300 - - - - 81.18%

Unsatisfactory

D. S. PAMINTUAN CONSTRUCTION 4326 Canalization Works 05/23/15 NIA 8.098 180 O 0.365 0.200 0.000 0.030 0.070 0.050 71.51 -

D.C.E. Construction 29347 Const. of Ili Flood Control 08/10/13 CAR 12.905 255 C 0.464 0.200 0.300 - - - 96.40 83.20% Satisfactory

D.C.M Construction 5641Completion of the Const. of Agus II Bridge (Pumping

Bridge) & Approaches, Phase II Raya Madaya-Pumping Road

09/13/09 X 22.952 2,868 O 0.383 0.185 0.150 0.030 0.051 0.033 83.20 -

D.C.M. Construction 5641 Const. of Agus III (Pumping) Bridge & Approaches along Raya-Madaya Pumping Road 04/11/11 X 32.933 180 O 0.401 0.240 0.150 0.030 0.042 0.033 89.60 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page59

Page 60: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

D.C.R. Construction 5040 Widening of Cavite-Batangas Rd., Km.23+653-Km.25+306 08/14/13 IVA 31.628 271 C 0.460 0.133 0.000 - - - 59.30 78.56% Unsatisfactory

D.C.R. Construction 5040 Widening of Cavite-Batangas Rd., Km.23+653 - Km.25+306 11/23/12 IVA 31.628 271 O 0.338 0.300 0.150 0.030 0.056 0.033 90.70 -

D.C.R. Construction 5040 Widening of Cavite-Batangas Road, Km.23+653-Km.25+306 08/15/12 IVA 31.628 271 O 0.341 0.300 0.150 0.030 0.050 0.050 92.10 -

D.G. CHICO TRADING & CONSTRUCTION CORPORATION 8748 Proposed Rehabilitation of Road and Drainage System

along Galvez St. And Villanueva St. 11/20/2014 NCR 17.421 179 O 0.364 0.233 0.150 0.022 0.055 0.033 85.70% 85.70% Satisfactory

D.G. Chico Trading & Construction Corporation 8748 Proposed Const. of MPB, Jose Rizal Elem. Sch. 08/01/13 NCR 4.055 120 C 0.423 0.200 0.300 - - - 92.30 92.30%

Very Satisfactory

D.G. Chico Trading & Construction Corporation 8748

Rehab., Reconst./Upgrading of Damaged Paved Nat'l Roads (IS) along C-5 Service Rd. (Palar), District I,

Chainage 168- Chainage (-) 29603/13/12 NCR 6.549 90 C 0.378 0.180 0.300 - - - 85.80 85.62%

Satisfactory

D.G. SARMENTA CONSTRUCTION 13024 Widening of Roads Daang Maharlika Road 11/22/2014 III 33.050 150 C 0.472 0.133 0.300 - - - 90.50% 90.50% Very Satisfactory

D.G. Sarmenta Construction 13024 Repair/Rehab./Impvt. of Valdefuente-Fortaleza Rd., Km.120+310-Km.121+000 w/ exception 08/12/13 III 4.754 20 C 0.430 0.133 0.300 - - - 86.30 86.30%

Satisfactory

D.G. Sarmenta Construction 13024Rehab./Reconst./Upgrading of Damaged Paved Nat'l. Road

along Jct. Tablang-Gabaldon Rd., Km.148+000 w/ exception (half lane=863.05 Lm., whole lane=338.45Lm.)

03/21/12 III 12.612 118 C 0.443 0.133 0.300 - - - 87.60 88.56% Satisfactory

D.G.O. Construction 6788 Rehab./Reconst./Upgrading of Kennon Rd., K0226+604-K0227+122 07/29/13 CAR 5.598 90 C 0.434 0.133 0.300 - - - 86.70 86.70%

Satisfactory

D.G.O. Construction 6788 Repair/Rehab. along Baguio-Bauang Rd., K0281+800-K0285+400 w/ exceptions 07/29/13 CAR 9.167 170 C 0.482 0.133 0.300 - - - 91.50 89.46%

Very Satisfactory

D.G.O. Construction 6788 Repair/Rehab. along Baguio-Bauang Rd., K0281+800-K0285+400 (w/ exception) 03/12/13 CAR 9.167 170 O 0.381 0.240 0.150 0.030 0.030 0.050 88.10 -

D.J. VALERA CONSTRUCTION & SUPPLY

ARC-C 34003 IMPROVEMENT OF BITUKANG MANOK DAM #7 08/15/15 NIA 13.569 120 O 0.310 0.300 0.150 0.000 0.023 0.050 83.30 -

D.J.D. Construction 32217 Concrete Reblocking along Manila North Road (K0602+000-K0604+000 w/ exceptions) 03/14/12 II 9.563 240 C 0.337 0.200 0.300 - - - 83.70 84.78%

Satisfactory

D.K Jocson Construction / TSD Builders Const. and Supply JV JV-08-024 Conc. of Road along Bacolod North Road (Toboso Section) 03/09/09 VIII 18.174 281 O 0.333 0.297 0.150 0.030 0.050 0.033 89.30 -

D.K. Jocson Construction 6896 San Vicente Port Development Project 08/26/15 DOTC 17.559 180 C 0.483 0.200 0.300 - - - 98.34 85.04% Satisfactory

D.K. Jocson Construction 6896 San Vicente Port Development Project 05/27/15 DOTC 17.559 180 O 0.360 0.300 0.002 0.015 0.035 0.050 76.16 -

D.K. Jocson Construction 6896 Dipolog Feeder Port Development Project 06/10/15 DOTC 49.380 475 O 0.377 0.300 0.150 0.015 0.029 0.033 90.42 -

D.K. Jocson Construction 6896Rehabilitation/Reconstruction/Replacement/Retrofitting of

Permanent Bridge, Oas Diversion Bridge along Daang Maharlika Road

8/11/2014 V 8.964 210 OG 0.338 0.240 0.150 0.020 0.037 0.050 83.50 -

D.K. Jocson Construction 6896 Conc. of Nat'l Rd. along Bacolod South Rd. (K0207+900-K0208+356) 08/09/13 VI 34.447 295 C 0.446 0.133 0.300 - - - 87.90 87.18%

Satisfactory

D.K. Jocson Construction 6896 Conc. of Nat'l. Rd. along Bacolod South Rd., (K0207+900-K0208+356) 03/13/13 VI 34.447 190 O 0.384 0.300 0.092 0.018 0.040 0.033 86.70 -

D.K. Jocson Construction 6896 Conc. of Nat'l. Rd. Bacolod South Rd., K0193+004-K0193+300, Brgy. Pook 03/13/13 VI 13.521 162 C 0.381 0.144 0.300 - - - 82.50 82.80%

Satisfactory

D.K. Jocson Construction 6896 Rehab./Reconst./Strengthening of Banao Bridge along Daang Maharlika Rd., K0506+126.00-K0506+194.00 08/09/13 V 13.490 110 C 0.375 0.200 0.300 - - - 87.50 87.50%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page60

Page 61: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

D.K. Jocson Construction / TSD Builders Construction and Supply

(JV)JV-12-178 Rehab./Reconst. of Malogo Bridge along Bacolod North

Rd. 08/13/13 VI 13.625 121 C 0.403 0.133 0.300 - - - 83.60 83.30% Satisfactory

D.K. Jocson Construction / TSD Builders Construction and Supply

(JV)JV-12-178 Rehab./Reconst. of Malogo Bridge along Bacolod North

Rd. 03/15/13 VI 13.625 121 O 0.341 0.212 0.150 0.018 0.060 0.050 83.10 -

D.L. Aureo Construction 24894 Const. 1-unit 2 Storey 6 CL Sch. Bldg., Tanauan NHS (San Roque NHS) 08/19/13 VIII 7.015 120 C 0.493 0.133 0.300 - - - 92.60 92.60%

Very Satisfactory

D.L. Aureo Construction 24894 Drainage System at Tanghas-Lirang Creek along Picas San Jose DZR Airport Rd. 08/22/13 VIII 4.286 107 C 0.451 0.133 0.300 - - - 88.40 88.40%

Satisfactory

D.L. Aureo Construction 24894 Rehab./Reconst. at San Jose Manlurip-MacArthur Park Rd., Km.913+000-Km.913+711 08/22/12 VIII 8.947 90 C 0.486 0.133 0.300 - - - 91.90 88.00%

Satisfactory

D.L. Aureo Construction 24894 Candahug Revetment Wall, Candahug 03/22/13 VIII 1.965 120 C 0.500 0.133 0.300 - - - 93.30 93.30% Very Satisfactory

D.M House Const. Inc. 25810 Impvt./Rehab. of Roman Expressway, Bataan 1st Congressional District 05/28/10 III 53.666 90 O 0.386 0.240 0.150 0.030 0.043 0.033 88.20 -

D.M House Const. Inc. 25810 Improvement/Rehabilitation of Roman Expressway 05/21/09 III 71.955 150 O 0.378 0.300 0.150 0.030 0.037 0.050 94.50 -D.M.  MALIWANAG BUILDERS AND 

ENTERPRISES/ MARCHPHIL CONSTRUCTION (JV)                    

JV-13-383 Construction/ Rehabilitation of Lapute River Control 11/27/2014 IV 13.685 144 C 0.417 0.133 0.300 - - - 85.00% 85.00% Satisfactory

D.M. House Construction, Inc. 25810 Repair/Rehab./Impv't. of Roman Expressway (Phase II) 03/12/13 III 9.900 111 C 0.429 0.133 0.300 - - - 86.20 86.20% Satisfactory

D.M. HOUSE CONSTURCTION, INC. 25810 Rehab./Reconst./Upgrading of Damaged Paved National Road HDM-4 (Intermittent Section) G.S.U. Road 11/26/2014 III 23.079 120 O 0.228 0.300 0.150 0.023 0.032 0.033 76.60% 76.60%

Unsatisfactory

D.M. HOUSE CONSTURCTION, INC. 25810Rehabilitation/Reconstruction/Upgrading of Damaged

Paved National Road HDM-4 (Intermittent Sections) G.S.U. Road

11/26/2014 III 7.079 135 O 0.306 0.300 0.103 0.023 0.032 0.033 79.70% 79.70% Unsatisfactory

D.M. Maliwanag Builders and Enterprises/Marcphil Construction -

Joint VentureJV-13-383 Construction/Rehabilitation of Lapute River Control,

Mansalay, Oriental Mindoro 8/13/2014 IV-B 13.685 144 C 0.413 0.118 0.300 83.10 83.10% Satisfactory

D.R. ROBLES CONSTRUCTION 28559 IMPROVEMENT OF LATERAL G-2 (AMRIS) 08/15/15 NIA 9.211 120 O 0.309 0.300 0.150 0.015 0.031 0.033 83.84 -

D.R. ROBLES CONSTRUCTION 28559Rehabilitation/Improvement of Pasong Tamo Creek

(Himlayan Road to Congressional Avenue Extension) with exception

11/26/2014 NCR 17.388 210 C 0.388 0.133 0.300 - - - 82.10% 82.10% Satisfactory

D.R. ROBLES CONSTRUCTION 28559Paving of Shoulders Including Geometric Improvement of

Tanay-Sampaloc Road, K0058+116-K0061+000, w/ exception

11/7/2014 IV 28.443 197 C 0.426 0.200 0.300 - - - 92.60% 92.60% Very Satisfactory

D.R. Robles Construction 28559 Rehab./Reconst. Of Scout Alcaraz St., (K0006+417-K0007+646) 03/11/13 NCR 14.180 270 C 0.403 0.120 0.300 - - - 82.30 82.42%

Satisfactory

D.R. Robles Construction 28559 Widening of Angono Diversion Rd., Angono & Binangonan 11/22/12 IVA 28.896 210 C 0.336 0.200 0.300 - - - 83.60 87.95% Satisfactory

D.R. Robles Construction 28559 Widening of Angono Diversion Rd. Angono & Binangonan 07/31/12 IVA 28.896 210 O 0.390 0.240 0.150 0.030 0.055 0.050 91.50 -

D.R. Robles Construction 28559 Asphalting of Rd. at Narra St., Mutual Homes, Brgy. Putatan 03/11/13 NCR 3.042 30 C 0.475 0.133 0.300 - - - 90.80 90.80%

Very Satisfactory

D.R. Robles Construction 28559 Prev. Maint. of Manila East Rd. (K0048+000-K0050+002), Cardona to Baras 03/23/13 IVA 23.430 60 C 0.462 0.133 0.300 - - - 89.50 89.50%

Very Satisfactory

D.R. Robles Construction 28559 Prev. Maint. of Pililla Jct. Jalajala Rd. (K0066+000-K0066+530) 03/23/13 IVA 3.591 60 C 0.445 0.133 0.300 - - - 87.80 87.80%

Satisfactory

D.S. PAMINTUAN CONSTRUCTION 4326 Improvement of Lateral D (South Side) of AMRIS 08/15/15 NIA 8.530 60 Expired 0.275 0.000 0.000 0.010 0.000 0.050 33.49 -

D.S. Pamintuan Construction Package SP-1: Construction of slope protection at super diversion canal (Sta. 29+892)-Sta. 30+120) 02/07/15 NIA 8.393 170 C 0.350 0.197 0.300 - - - 84.65 84.65%

SatisfactoryD.T. ESTARON ENGINEERING &

CONST. 5082 Const. of 1-unit 2-Storey, 6-CL School Building at Maypangdan National High School 8/14/2014 VIII 6.738 275 C 0.491 0.133 0.300 92.40 91.77%

Very SatisfactoryD.T. Estaron Engineering and

Construction 5082 Completion of MPB in ESSU (Main Campus) 08/20/13 VIII 2.392 90 C 0.299 0.175 0.300 - - - 77.40 77.40% Unsatisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page61

Page 62: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

D.T. Estaron Engineering and Construction 5082 Const. of 1-Unit, 2-Storey, 6-Cl Sch. Bldg. at Maypangadan

NHS 08/20/13 VIII 6.301 250 O 0.391 0.258 0.150 0.030 0.053 0.033 91.50 -

D.V. Salud Construction 6564 Repair/Rehab./Impvt. of Pedestrian Overpass along Old Manila South Rd., Sta. Rosa-Dila Sect., K0039+900 08/10/13 IVA 9.752 120 O 0.339 0.071 0.000 0.022 0.023 0.017 47.20 -

Da Cadeliña Construction 29004 Dabubu River Irrigation Project 04/27/13 NIA 7.597 180 O 0.360 0.258 0.150 0.012 0.023 0.050 85.35 -

Dahl Construction 8931 Rehab.//Recons./Upgrading of Marikina-Infanta Rd., Brgy. San Jose 11/21/12 IVA 17.460 210 C 0.429 0.200 0.300 - - - 92.90 88.88%

Satisfactory

Dahl Construction 8931 Rehab./Reconst./Upgrading of Marikina-Infanta Rd., Brgy. San Jose 07/30/12 IVA 17.460 210 O 0.347 0.240 0.150 0.030 0.045 0.050 86.20 -

Dahl Construction 8931 Prev. Maint. of Cainta-Kayticling-Antipolo-Teresa-Morong Rd. (K0036+310-K0037+272; Int. Sect.) 03/23/13 IVA 9.774 60 C 0.457 0.133 0.300 - - - 89.00 89.00%

Satisfactory

DAKAY CONSTRUCTION & DEVELOPMENT CORP. 8838 San Jose Port Expansion Project 03/06/15 PPA 117.812 480 O 0.399 0.300 0.000 0.024 0.070 0.050 84.30 -

Dalanon Construction Refregiration Supply & Service 11205

Rd. Upgrading (Gravel to Paved) along Awang-Upi-Lebak-Kalamansig-Palimbang-Sarangani Rd. (Km.1963+471-Km.1977+121) realigned to Rd. Upgrading (Gravel to

Paved) along Awang-Upi-Lebak-Kalamansig-Palimbang-Sarangani Rd. (Km.2034+798-Km.2036+898)

03/13/13 XII 47.765 327 O 0.365 0.232 0.150 0.030 0.045 0.050 87.20 -

Dalanon Construction Refregiration Suppply & Service 11205

Road Upgrading (Gravel to Paved) along Awang-Upi-Lebak-Kalamansig-Palimbang-Sarangani Rd. (Km.1963+471-

Km.1977+121) Realign to Rd. Upgrading (Gravel to Paved) along Awang-Upi-Lebak-Kalamasig-Palimbang-Sarangani

Rd. (Km.2034+798-Km.2036+898)

08/18/13 XII 47.765 357 C 0.396 0.200 0.300 - - - 89.60 89.60% Very Satisfactory

Dalanon Construction Refregiration Suppply & Service 11205

Rd. Upgrading (Gravel to Paved) along Awang-Upi-Lebak-Kalamansig-Palimbang-Sarangani Rd. (Km.2010+661-

Km.2012+961 w/ exception)08/18/13 XII 45.366 196 O 0.340 0.300 0.138 0.024 0.051 0.033 88.60 -

Dalanon Construction Refrigeration Supply & Service 11205 Rehab./Reconst. of Dulawan-Marbel (Tacurong-New

Carmen Section) 06/08/10 XII 12.222 254 O 0.291 0.203 0.150 0.030 0.051 0.050 77.50 -

DAMICO BUILDERS & SUPPLIES 30355 Rehabilitation/Improvement of Flood Control Sturctures along Paniqui-Camiling-Wawa Road, Sawat-Bilad Section 11/20/2014 III 4.751 60 C 0.364 0.196 0.300 - - - 86.00% 86.00%

Satisfactory

DAMICO BUILDERS & SUPPLIES 30355

Rehabilitation/Reconstruction of Damaged Paved National Roads Including Drainage at Capas - San Jose - Mayantoc -

Malacampa Road (Capas Section), Road 1 - KO115+578 and Road 2 - KO115+578 to KO116+701 with exception

11/20/2014 III 10.142 85 C 0.395 0.133 0.300 - - - 82.80% 82.80% Satisfactory

DAMICO BUILDERS & SUPPLIES 30355

Rehab./Reconst. Of Capas - San Jose - Mayantoc - Malacampa Road (Capas Section) Road, Road 1:

KO115+563 to KO0115+578 and Road 2: KO115+578 to KO116+701 with exception

8/5/2014 III 10.142 85 C 0.453 0.133 0.300 88.60 88.60% Satisfactory

DAMICO BUILDERS & SUPPLIES 30355 Completion of Road and Construction of Wheel Guard at Maligaya, Sta. Ines East 8/6/2014 III 8.266 118 C 0.475 0.133 0.300 90.80 90.80%

Very Satisfactory

Damico Builders & Supplies 30355 Repair/Rehab./Impv't. of Damaged Paved Nat'l Rd. along Tibag-Burgos Rd., K0137+600-K0147+570, w/ exception 08/08/13 III 9.601 120 O 0.343 0.238 0.150 0.030 0.043 0.033 83.70 -

Damico Builders & Supplies 30355 Concreting of Brgy. Road from Brgy. San Agustin to Brgy. Bantog 09/02/09 III 1.687 87 O 0.365 0.240 0.150 0.030 0.047 0.033 86.50 -

Damico Builders & Supplies 30355 Conc. of Brgy. Road @ Nagmisaan 11/24/12 III 5.894 75 O 0.323 0.274 0.150 0.030 0.025 0.050 85.20 -

Danvic Construction 24439Rds. to Address Critical Bottlenecks, Nat'l Rd. Traffic Decongestion-Widening of ABS-CBN Quimpo Blvd.

Diversion Rd.08/19/13 XI 19.629 132 C 0.404 0.133 0.300 - - - 83.70 84.48%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page62

Page 63: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Danvic Construction 24439Rds. to Address Critical Bottlenecks, Nat'l Rd. Traffic Decongestion-Widening of ABS-CBN Quimpo Blvd.

Diversion Rd.03/22/13 XI 18.618 102 O 0.347 0.245 0.150 0.030 0.045 0.033 85.00 -

DANYSONS CONSTRUCTION 25452 Road Upgrading (Gravel to Paved) along Ilagan-Delfin Albano-Mallig Road @ KO438+779-KO439+882 10/25/2014 II 26.503 159 C 0.436 0.133 0.300 - - - 86.90% 86.90%

Satisfactory

Danysons Construction 25452 Road Upgrading (Gravel to Paved) along Ilagan-Delfin Albano-Malig Road, K0438+779 to K0439+882 8/9/2014 II 26.503 159 C 0.407 0.132 0.300 83.90 83.90%

Satisfactory

DANYSONS CONSTRUCTION 25452 Irrigation 04/27/15 NIA 19.816 162 O 0.353 0.300 0.115 0.030 0.070 0.017 88.47 -

Danysons Construction 25452 Rehab./Reconst./Upgrading (Int. Sect.) along Ilagan-Delfin Albano-Mallig Rd. K0448+484-K0449+390 08/08/13 II 3.923 75 C 0.286 0.200 0.300 - - - 78.60 78.60%

Unsatisfactory

Danysons Construction 25452 Conc. of Dummon-Turod FMR 08/08/13 II 4.600 85 C 0.345 0.133 0.300 - - - 77.80 85.06% Satisfactory

Danysons Construction 25452 Conc. of Dummon-Turod FMR 03/18/13 II 4.600 60 O 0.390 0.240 0.150 0.030 0.039 0.050 89.90 -

Darynn Construction & Supply 22322 Const. of MPB at Zone 3 03/16/13 XI 0.487 60 C 0.445 0.133 0.300 - - - 87.80 87.80% Satisfactory

DATREBIL CONSTRUCTION & SUPPLY 36908 Rehabilitation of Local Road along Brgy. Katipunan - Brgy.

Marcelina Road 10/22/2014 XIII 4.817 67 C 0.430 0.150 0.300 - - - 88.00% 88.00% Satisfactory

DAVAO CONCRETE PRODUCTS 12090Repair/Maintenance/Retrofitting of Maundo Bridge along

Pulang Lupa - Sta. Josefa Road (B01469MN( K1378+772.4 - K1378+749.5

10/23/2014 XIII 4.694 84 C 0.355 0.198 0.300 - - - 85.30% 85.30% Satisfactory

DAVAO CONCRETE PRODUCTS 12090 Widening of Tagum-Panabo Circumferencial Road, K1468+359 – K1469+051, Asuncion Section 8/8/2014 XI 20.713 140 C 0.390 0.133 0.300 82.30 82.30%

Satisfactory

Davao Concrete Products 12090 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds., SDCR K1439+000-K1439+470 (1439+150-K1439+647.70) 08/16/13 XIII 12.282 166 C 0.404 0.128 0.300 - - - 83.20 83.20%

Satisfactory

Davao Concrete Products 12090 Const. of Revetment, Saug River Flood Control, Cambanogoy (Tagum Panabo Circ. Rd.) 08/12/13 XI 18.589 243 C 0.465 0.133 0.300 - - - 89.80 89.08%

Very Satisfactory

Davao Concrete Products 12090 Embankment of Maniki Jumbo Bridge Approach "B" (Upstream R/S) Tagum Panabo Circ. Rd. 08/13/13 XI 1.985 135 C 0.400 0.133 0.300 - - - 83.30 80.84%

Unsatisfactory

Davao Concrete Products 12090 Embankment of Maniki Jumbo Bridge Approach "B" (Upstream R/S) Tagum Panabo Circ. Rd. 03/18/13 XI 1.985 135 O 0.299 0.240 0.150 0.030 0.040 0.033 79.20 -

Davao Concrete Products 12090 Impvt./Conc. of Babak-Samal-Kaputian, Island Garden 06/02/09 XI 33.719 90 O 0.366 0.300 0.150 0.030 0.037 0.050 93.30 -

Davao Concrete Products 12090 Impvt./Conc. of Babak-Samal-Katipunan Road, Katipunan Section 03/13/09 XI 34.712 286 O 0.327 0.274 0.150 0.022 0.060 0.050 88.30 -

Davao Concrete Products 12090 Const. of Revetment, Saug River Flood Control, Cambanogoy, (Tagum Panabo Circ. Rd.) 11/24/12 XI 18.589 161 O 0.386 0.240 0.150 0.030 0.030 0.050 88.60 -

Davao Concrete Products 12090 Const. of Revetment, Kapalong Flood Control (Left Side of Old Maniki Bridge), Maniki, Kapalong 11/24/12 XI 33.270 262 C 0.475 0.200 0.300 - - - 97.50 82.62%

Satisfactory

Davao Concrete Products 12090 Prev. Maint. (IS) Nat'l Secondary Tibanban-Lavigan Rd. 08/16/12 XI 9.123 100 C 0.396 0.133 0.300 - - - 82.90 83.86% Satisfactory

Davao Concrete Products 12090 Const. of Revetment Kapalong Flood Control (Left Side of Old Maniki Bridge), Maniki 08/12/12 XI 33.270 266 O 0.399 0.059 0.146 0.030 0.060 0.033 72.70 -

Davao Concrete Products 12090

Installation of Traffic Safety Devices @ Cotabato City Circ. Rd. (Western Sect.) (Km.1849+(-879)-Km.1855+565 w/ exception; Cotabato-Alla-Marbel Rd. (Km.1848+(-682)-

Km.1852+1011 w/ exception; & R. Rabago St.-De Mazenod Ave.-Quezon Ave. (Km.1852+(-248)-Km.1853+474)

03/15/13 XII 9.986 70 C 0.487 0.133 0.300 - - - 92.00 92.00% Very Satisfactory

DAVAO CONCRETE PRODUCTS/MN BAYALAS CONST.

(JV)

Construction of Flood Control Structure/Drainage along SDCR, Surigao del Sur 2nd LD, K1466+172 - K1467+814.70 8/9/2014 XIII 9.070 150 C 0.399 0.133 0.300 83.20 83.20%

Satisfactory

DAVAO CONCRETE PRODUCTS/MN BAYALAS CONST.

(JV)

Construction of Flood Control Structure/Drainage along SDCR, Surigao del Sur 2nd LD, K1464+491 - K1465+960 8/9/2014 XIII 11.129 251 OG 0.321 0.237 0.150 0.030 0.056 0.050 84.40 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page63

Page 64: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

DAVAO CONCRETE PRODUCTS/MN BAYALAS

CONSTRUCTION (JV)JV-13-327

Construction of Flood Control Structure/Drainage along SDCR, Surigao del Sur 2nd L.D., K1466+172 -

K1467+814.70 with exception10/24/2014 XIII 9.070 150 C 0.403 0.197 0.300 - - - 90.00% 90.00%

Very Satisfactory

Davao Engineers Engineers Contractors Cooperative (DECK) 30944 Const. of 3-Storey, 12 CL Partial Const. of Daniel

Aguinaldo NHS 03/29/12 XI 4.773 130 C 0.433 0.133 0.300 - - - 86.60 89.96% Very Satisfactory

DAVAO ROCK MIXER ENT./WEE ENG. CONSTRUCTION INC. (JV) JV-13-476 Replacement of Camanlangan Bridge, New Bataan

Nabunturan – Maragusan Road 8/9/2014 XI 27.646 195 OG 0.377 0.240 0.105 0.030 0.023 0.033 80.80 -

DAVAO ROCK MIXER ENTERPRISES 19250 Bislig City IDP-IC LCB-SDS-BCIDP-IC(LP-1)-14-2013 06/07/14 NIA 16.194 250 O 0.347 0.233 0.150 0.024 0.043 0.050 84.70 -

Davao Rock Mixer Enterprises 19250 Bukidnon Irrigation Management Office / Region 10 03/31/12 NIA 14.219 450 C 0.465 0.200 0.300 - - - 96.53 82.58% Satisfactory

DAVAO ROCK MIXER ENTERPRISES/ WEE ENG

CONSTRUCTION, INC. (JOINT VENTURE)

JV-13-476 Replacement of Camanlangan Bridge, New Bataan Nabunturan - Maragusan Road 10/26/2014 XI 29.105 239 C 0.454 0.139 0.300 - - - 89.30% 89.30%

Very Satisfactory

DAVAO UNITED BUILDERS COOPERATIVE 3310 Bislig City IDP-IC LCB-SDS-BCIDP-IC(LP-3)-16-2013 06/07/14 NIA 24.271 300 O 0.347 0.240 0.150 0.024 0.043 0.050 85.40 -

DAVHES TRADING AND CONSTRUCTION CORPORATION 9833 Improvement/Rehabilitation of Victor Medina Street

(Kabihasnan), Barangay San Dionisio 11/19/2014 NCR 6.053 75 C 0.484 0.137 0.300 - - - 92.10% 92.10% Very Satisfactory

Davhez Trading and Construction 9833 Const. of Sch. Bldg., Pilar Elem. Sch. at Pilar 08/15/13 NCR 2.890 75 C 0.370 0.189 0.300 - - - 85.90 85.90% Satisfactory

Davhez Trading and Construction 9833 Const. of Three (3) Storey, Nine (9) CL Sch. Bldg., Las Piñas Science High School 09/04/09 NCR 10.049 140 O 0.331 0.225 0.150 0.020 0.058 0.033 81.70 -

Davhez Trading and Construction 9833 Const. of MPB inc. other impv't. CAA (13.00 x 34.00) 03/11/13 NCR 4.793 120 C 0.449 0.121 0.300 - - - 87.00 87.00% Satisfactory

DBMR BUILDERS AND SUPPLY 22782Rehabilitation/Reconstruction/Replacement/Retrofitting of Langkilaan Bridge along Daang Maharlika (Agusan-Davao

Section) (B00931MN) K1376+840 - K1376+88110/23/2014 XIII 5.448 87 C 0.413 0.141 0.300 - - - 85.40% 85.40%

Satisfactory

DCE Construction 29347 Conc. along Calanasan-Claveria Road, Poblacion Section 02/19/10 CAR 14.875 538 O 0.353 0.240 0.150 0.030 0.035 0.033 84.10 -

DELLOSA DESIGN-BUILD SERVICES 11533

Widening of Jct. Digos-Buayan Airport Road, K1652+500 - K1653+375, Buayan Sect. K0+000 - K0+481, Buayan-Glan

Sect.10/29/2014 XII 46.062 300 O 0.367 0.236 0.150 0.030 0.045 0.033 86.10% 86.10%

Satisfactory

DELLOSA DESIGN-BUILD SERVICES 11533 Repair/Rehabilitation/Improvement along Digos-Makar for

Road 10/29/2014 XII 9.889 110 C 0.418 0.132 0.300 - - - 85.00% 85.00% Satisfactory

Dellosa Design-Build Services 11533 Impv't. of Jct. GSC Circ. Rd. Makar-Tupi-Marbel Rd. (Geometric Control) 08/23/13 XII 13.750 125 C 0.409 0.133 0.300 - - - 84.20 81.38%

Unsatisfactory

Dellosa Design-Build Services 11533 Impv't. of Jct. GSC Circ. Rd., Makar-Tupi-Marbel Rd. (Geometric Control) 03/23/13 XII 13.750 95 O 0.357 0.300 0.020 0.030 0.055 0.033 79.50 -

Dellosa Design-Build Services 11533 Road Conc. at Napal Rd., Brgy. Conel 03/23/13 XII 13.579 135 C 0.425 0.133 0.300 - - - 85.80 85.80% Satisfactory

DEOJ Construction 29050 Rehabilitation of Allacapan Bridge No, 2 along BMR 8/6/2014 II 5.850 180 C 0.461 0.133 0.300 89.40 89.40% Very Satisfactory

Diane Construction & Enterprises 34106 Road Rehabilitation 8/5/2014 IX 4.685 110 C 0.328 0.200 0.300 82.80 82.80% Satisfactory

Dicon Builders Corp. 33181 Const. of 2-Storey, 4-CL Sch. Bldg. at Northeast 1-A CES 08/17/13 X 4.417 150 C 0.484 0.133 0.300 - - - 91.70 91.70% Very Satisfactory

Dicon Builders Corp. 33181 Const./Conc. of Rds. Brgy. Tablon & Cugman 08/27/13 X 1.149 52 C 0.453 0.133 0.300 - - - 88.60 88.60% Satisfactory

Dicon Builders Corp. 33181 Const./Conc. of Rds., Brgy. Macasandig 03/18/13 X 3.762 57 C 0.432 0.200 0.300 - - - 93.20 93.20% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page64

Page 65: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

DICON BUILDERS, CORP. 33181Const./Rehab. Of Flood Control Mitigation Facilities along

Major River Basin Const. of Slope Protection along Manticao Approaches A & B (Downstream) (Phase I)

10/27/2014 X 8.260 105 O 0.275 0.289 0.150 0.015 0.056 0.050 83.50% 83.50% Satisfactory

Digos Tesston Construction & Supplies 8921

Rehab./Reconst. of Damaged Paved National at Lipata, Surigao Del Norte-Davao City Highway through Marlika,

Daang Maharlika Rd. (Agusan to Davao Rd.) Ilang-Tibungco Sect.

06/17/10 XI 19.290 113 O 0.361 0.240 0.150 0.030 0.047 0.050 87.80 -

DIGOS TESSTON CONSTRUCTION & SUPPLIES (Formerly: ACT

Construction)8921

Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects Road and Related Infrastructure Facilities for 2015 APEC Summit, Region XI-Local Roads, L. Ma. Guerrero Street, Junction

Fatima to Gaisano/ San Pedro Hospital

10/30/2014 XI 35.863 190 O 0.349 0.297 0.051 0.030 0.055 0.000 78.20% 78.20% Unsatisfactory

DIGOS TESSTON CONSTRUCTION & SUPPLIES (Formerly: ACT

Construction)8921

Rehab./Reconst./Replacement/Retrofitting of Waloe Bridge along Butuan City - Talacogon - Loreto - Veruela - Sta.

Josefa Road, K1377+(-527) - K1377+(-402)8/8/2014 XIII 24.435 185 OG 0.365 0.201 0.121 0.023 0.025 0.033 76.80 -

Digos Tesston Construction & Supplies (Formerly: Act

Construction)8021

Completion of Coronon Bridge I along Davao-Cotabato Rd., (Davao City-Jct. Digos Sect.), K1542+612.696-

K1543+291.11208/09/13 XI 14.670 104 C 0.322 0.200 0.300 - - - 82.20 82.38%

Satisfactory

Digos Tesston Construction & Supplies (Formerly: ACT

Construction)8021

Completion of Coronon Bridge I along Davao-Cotabato Rd., (Davao City Jct Digos Sect.) K1542+612.696-

K1543+291.11203/16/13 XI 14.229 74 O 0.342 0.235 0.150 0.030 0.035 0.033 82.50 -

Digos Tesston Construction & Supplies (Formerly: ACT

Construction)8921 Conc. Of Bansalan-Mt.Apo National Park Road, Managa-

Buenavista Section 08/27/10 XI 9.907 210 O 0.333 0.290 0.150 0.030 0.043 0.033 87.90 -

Digos Tesston Construction & Supplies (Formerly: ACT

Construction)8921 Conc. of Road at Brgy. Lizada, Toril District 03/20/12 XI 2.979 150 C 0.473 0.133 0.300 - - - 90.60 92.76%

Very Satisfactory

Digos Tesston Construction & Supplies (Formerly: ACT

Construction)8921

Rehab./Reconst./Upgrading of Damaged Paved Rds. at Davao-Cotabato Old Rd., Toril District Km.1526+(-)431-

Km.1526+(-)3203/20/12 XI 4.515 180 C 0.435 0.147 0.300 - - - 88.20 92.46%

Very Satisfactory

Digos Tesston Construction & Supplies (Formerly: Act

Construction)8921

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. (IS)/Impvt. of Don Julian Rodriguez Ave. leading to Davao

Crocodile Park, Km.1509+(-)328-Km.1511+796, IS11/28/12 XI 45.598 250 C 0.458 0.133 0.300 - - - 89.10 88.20%

Satisfactory

Digos Tesston Construction & Supplies (Formerly: Act

Construction)8921 Impvt. of Drainage at Davao-Cotabato Rd., Bangkal Sect.

(Sta.1517+000-Sta.1518+000) 08/20/12 XI 18.900 195 C 0.407 0.200 0.300 - - - 90.70 91.60% Very Satisfactory

Digos Tesston Construction & Supplies (Formerly: Act

Construction)8921 Loading & Unloading Bays, Davao-Cotabato Rd. (7

Stations) 08/20/12 XI 15.861 150 C 0.396 0.200 0.300 - - - 89.60 89.54% Very Satisfactory

Digos Tesston Construction & Supplies (Formerly: Act

Construction)8921

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. (IS)/ Impv't. of Don Julian Rodriguez Ave. Leading to

Davao Crocodile Park, Km.1509+(-328)-Km.1511+796, IS08/20/12 XI 45.598 220 O 0.354 0.237 0.150 0.030 0.055 0.050 87.60 -

DIGOS TESSTON CONSTRUCTION & SUPPLIES (Formerly:ACT

Construction)8921 Widening along Davao-Cotabato Road (Davao City-

Junction Digos Section) including ROW 8/7/2014 XI 35.077 153 C 0.391 0.133 0.300 82.40 82.40% Satisfactory

Digos Tesston Construction & Supplies / TSK Builders & Supplies

(JV)JV-12-365 Rd. Upgrading (Gravel to Paved) along Bansalan-Mt. Apo

Nat'l Park Rd., K1584+(-234)-K1585+008 03/16/13 XI 28.001 93 O 0.368 0.212 0.150 0.030 0.040 0.033 83.30 -

Digos Tesston Construction and Supply 8921 Miral SRIP 06/01/13 NIA 5.489 150 C 0.458 0.160 0.300 - - - 91.82 91.82%

Very Satisfactory

DIMAGUILA CONSTRUCTION AND SUPPLY INCORPORATED 14904 Asphalt Overlay of Santol Street, Chainage 0+000-

Chainage 0+776; Chainage 0+776-Chainage 0+848 11/28/2014 NCR 8.468 90 O 0.387 0.200 0.000 0.030 0.052 0.033 70.20% 70.20% Poor

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page65

Page 66: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Dimaguila Construction and Supply Incorporated 14904 Impv't./Conc. of Maginhawa St. (Sta.14+(-555)-Sta.14+(-338) 11/29/12 NCR 8.868 163 C 0.400 0.200 0.300 - - - 90.00 84.24%

SatisfactoryDimaguila Construction and Supply

Incorporated 14904 Impv't./Conc. of Maginhawa St. (Sta.14+(-555)-Sta.14+(-338) 08/19/12 NCR 8.868 163 O 0.350 0.300 0.056 0.030 0.035 0.033 80.40 -

Dinah Jane Construction Supply 33925 Const. of Storm Drainage & Canal along Carcar-Barili Rd., K0060+670-K0060+970, Brgy. Poblacion 03/17/13 VII 2.111 108 C 0.370 0.200 0.300 - - - 87.00 83.70%

Satisfactory

DIPOLOG TOP CONSTRUCITON AND DEVELOPMENT

CORPORATION6678

Rehab./Reconst./Replacement/Retrofitting of Existing Permanent Bridge, Timan Bridge along Sindangan-Liloy

Road10/24/2014 IX 15.084 155 O 0.270 0.212 0.100 0.030 0.025 0.033 67.00% 67.00%

Poor

Dipolog Top Construction and Development Corporation 6678 Const./Concrete Paving of Dipolog By Pass Rd. (Phase II)

Turno-Galas-Sinamon Rd. 08/22/13 IX 34.592 394 C 0.361 0.200 0.300 - - - 86.10 85.32% Satisfactory

Dipolog Top Construction and Development Corporation 6678 Const. of Flood Control, Bolicon 08/22/13 IX 29.844 255 O 0.329 0.300 0.000 0.020 0.042 0.033 72.40 -

Dipolog Top Construction and Development Corporation 6678 Const./Concrete Paving of Dipolog By Pass Road (Phase

II) Turno-Galas-Sinaman Rd. 03/23/13 IX 34.592 255 O 0.364 0.238 0.141 0.030 0.042 0.033 84.80 -

Dipolog Top Construction and Development Corporation 6678 Const. of Flood Control, Bolicon 03/23/13 IX 29.844 255 O 0.366 0.240 0.125 0.030 0.033 0.033 82.70 -

Dipolog Top Construction and Development Corporation 6678 Road Upgrading of Dipolog-Punta Dansullan-Sergio

Osmeña Road 03/18/09 IX 18.879 400 O 0.380 0.263 0.150 0.030 0.048 0.050 92.10 -

Dipolog Top Construction and Development Corporation 6678 Const. of River Bank Protection Works/River Control

Estaka Side 11/28/12 IX 8.568 253 C 0.467 0.178 0.264 - - - 90.90 88.32% Satisfactory

Dipolog Top Construction and Development Corporation 6678 Const. of River Bank Protection Work/River Control 08/24/12 IX 8.568 253 O 0.384 0.240 0.135 0.030 0.044 0.033 86.60 -

DJ Dayag Construction 35944 Const. of Lower Maton Flood Control 03/22/13 CAR 4.761 125 C 0.416 0.133 0.300 - - - 84.90 84.90% Satisfactory

DJCM CONSTRUCTION 27678 Construction of Hall of Justice, Luna, Apayao 8/10/2014 CAR 4.606 180 C 0.396 0.133 0.300 82.90 86.61% Satisfactory

DJCM Construction 27678

Road Upgrading (Gravel to Paved) based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved

Road Standard (HDM-4 Project Analysis) of Pinili-Banna (Espiritu) Road

8/8/2014 I 14.055 113 C 0.451 0.133 0.300 88.40 88.40% Satisfactory

DJCM Construction 27678 Repair/Rehab./Impv't. of Kabugao-Pudtol-Luna Rd., K0662+000 - K0065+350 w/ exception 08/13/13 CAR 9.872 121 C 0.461 0.133 0.300 - - - 89.40 89.40%

Very Satisfactory

DJCM Construction 27678 Repair/Rehab./Impv't. of Kabugao-Pudtol-Luna rd., K0678+000-K0681+000 w/ exception 08/13/13 CAR 9.900 150 C 0.434 0.133 0.300 - - - 86.70 86.70%

SatisfactoryDJCM Construction 27678 Const. of Hall of Justice 08/12/13 CAR 4.606 170 O 0.380 0.240 0.150 0.015 0.047 0.050 88.20 -

DJY Construction / E.K.C. Construction and Aggregates (JV) JV-12-089 Impv't. of Bengaw-ngaw Caves Road, Sta.0+000-Sta.2+500

(v.s.) Ambongdolan 07/31/13 CAR 18.984 190 C 0.422 0.133 0.300 - - - 85.50 87.60% Satisfactory

DJY Construction / E.K.C. Construction and Aggregates (JV) JV-12-089 Impv't. of Bengaw-ngaw Caves Rd., Sta. 0+000-Sta. 2+500

(v.s.), Ambongdolan 03/14/13 CAR 18.984 180 O 0.366 0.240 0.149 0.030 0.055 0.050 89.00 -

DL ENTERPRISES 18155Drainage/Slope Protection along Butuan City-Cagayan de Oro City - Iligan City Road - Km. 1424+514 - Km. 1424+845,

Brgy. Bugo10/25/2014 X 3.996 165 C 0.479 0.133 0.300 - - - 91.20% 91.20%

Very Satisfactory

DL ENTERPRISES 18155 Const. of Pedestrian Overpass (Bridge) 10/20/2014 X 3.993 150 O 0.322 0.300 0.150 0.010 0.042 0.050 87.40% 87.40% Satisfactory

DL Enterprises 18155 Const. of Iponan River Control (Upstream of Iponan Bridge I & II), Bulua Side 08/11/13 X 5.512 80 C 0.459 0.133 0.300 - - - 89.20 89.20% Very

Satisfactory

DL Enterprises 18155 Const. of Tangub City-Don Victoriano Road, Tangub City Section 03/17/09 X 22.914 723 O 0.331 0.300 0.150 0.030 0.045 0.050 90.60 -

DL Enterprises 18155 Road Upgrading (Gravel to Paved) Based on Gravel Rd. Strategies/HDM 4,Lumbia-Uguiaban By Pass Rd. (IS) 03/19/12 X 2.213 85 C 0.442 0.133 0.300 - - - 87.50 84.56%

Satisfactory

DL Enterprises 18155 Widening of CDO-Airport-Bukidnon Rd. Km.1440+020-Km.1452+000 Carmen-Lumbia Sect. 11/25/12 X 18.620 210 C 0.471 0.133 0.300 - - - 90.40 88.66%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page66

Page 67: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

DL Enterprises 18155 Widening of CDO-Airport-Bukidnon Rd. Km.1440+020-Km.1452+000, Carmen-Lumbia Sect. 08/23/12 X 18.620 210 O 0.297 0.300 0.150 0.030 0.048 0.050 87.50 -

DM Catignas Enterprises 27624 Construction of Check Structure & Canal System for Sta. Cruz RIS Extension 02/14/15 NIA 16.852 293 C 0.329 0.200 0.300 - - - 82.86 82.86%

Satisfactory

DMLC BUILDERS 36650 Rehabilitation/Improvement of Drainage System along 10th Avenue Extension 11/22/2014 NCR 4.565 120 C 0.438 0.133 0.300 - - - 87.10% 87.10%

SatisfactoryDomarax Construction and

Development 5502 Conc. of Roads, Brgy. Del Rosario 06/07/10 XIII 1.398 117 O 0.395 0.240 0.150 0.030 0.035 0.033 88.30 -

Domarax Construction and Development 5502 Conc. of Road Protection Tubod, Brgy. Poblacion 06/07/10 XIII 0.978 115 O 0.367 0.245 0.150 0.030 0.035 0.033 86.00 -

Domarax Construction and Development 5502 Road Upgrading (Gavel to Concrete) Surigao City-San

Juan Coastal Road 06/07/10 XIII 5.199 150 O 0.347 0.240 0.150 0.030 0.035 0.033 83.50 -

Double L Construction and Development Enterprises 9834 Rehab./ Reconst./ Upgrading Dumaguete North, Mainit-

Ajong Road Section 09/12/09 VII 38.320 280 O 0.387 0.300 0.150 0.030 0.042 0.050 95.90 -

Double L Construction and Development Enterprises 9834

Const./Impvt. of Dumaguete North Road (Intemittent Sections) a) Himampangon Section, Manjuyod: Km. 62.720-Km.63.233; b) Manjuyod Section: Km.52+971-Km. 54.000;

c) Tayasan Section: Km. 92.761

09/09/10 VII 63.690 330 O 0.323 0.300 0.000 0.030 0.061 0.050 76.40 -

Double L Construction and Development Enterprises 9834 Rehab. of Tugas Sect. Tanjay City, Dumaguete North Rd.,

Km.27+400-Km.28+400 08/13/12 VII 19.300 250 C 0.416 0.133 0.300 - - - 84.90 85.20% Satisfactory

DOUBLE MM BUILDERS 33758 Const. of DepED Standard Type School Building at Cauayan NHS 8/9/2014 VI 2.833 95 C 0.440 0.200 0.300 94.00 85.88%

Satisfactory

Double MM Builders 33758 Const. of DepEd Standard Type Sch. Bldg. @ Cauayan NHS 08/09/13 VI 2.283 95 O 0.357 0.212 0.132 0.030 0.043 0.050 82.40 -

DQT Builders Corporation 7950 Development of Quezon Port 09/03/15 DOTC 18.480 270 O 0.324 0.300 0.150 0.030 0.047 0.050 90.02 -

DQT Builders Corporation 7950 Widening of Daang Maharlika with exception, K0117+566 to K0121+896, Siriaya Section, Quezon 2nd LD 8/13/2014 IV-A 35.828 180 OG 0.384 0.300 0.150 0.030 0.032 0.033 92.90 -

DQT Builders Corporation 7950 Road Upgrading (Concrete Paving) Mulanay-San Francisco Road, K0288+000 to K0289+102 8/12/2014 IV-A 26.308 240 C 0.447 0.200 0.300 94.70 87.44%

Satisfactory

DQT Builders Corporation 7950 Construction of Lucban Overpass SLSU along Lucena-Tayabas-Lucban-Sampaloc-Mauban Port Road 8/14/2014 IV-A 9.800 300 C 0.352 0.200 0.300 85.20 83.40%

Satisfactory

DQT Builders Corporation (Formerly: DQT Builders) 7950

1. Assets Preservation of Nat'l Rds., Int. Sect.; A. Prev. Maint.; 1. Nat'l. Arterial (Prev. Maint.); 1. Daang Maharlika;

D. K0182+500-K0185+48108/05/13 IVA 36.599 175 C 0.443 0.133 0.300 - - - 87.60 85.68%

Satisfactory

DQT Builders Corporation (Formerly: DQT Builders) 7950 Rd. Upgrading (Concrete Paving) of Mulanay-San

Francisco Rd., K0287+115-K0288+000 08/07/13 IVA 20.000 180 O 0.303 0.284 0.150 0.030 0.030 0.033 83.00 -

DQT Builders Corporation (Formerly: DQT Builders) 7950 Rd. Upgrading (Concrete Paving) Mulanay-San Francisco

Rd., K0288+000-K0289+102 08/07/13 IVA 24.847 180 O 0.283 0.300 0.150 0.030 0.030 0.033 82.60 -

DQT Builders Corporation (Formerly: DQT Builders) 7950 Rehab./Reconst./Upgrading of MCR (Km.101+000-

Km.103+814 & Km.99+741-Km.100+072) (Gasan Sect.) 08/08/13 IVB 46.713 213 O 0.339 0.291 0.140 0.015 0.030 0.033 84.80 -

DQT Builders Corporation (Formerly: DQT Builders) 7950

1. Assets Preservation of Nat'l Rds., Intermittent Sect,; A. Prev. Maint.; 1. Nat'l. Arterial (Prev. Maint.); 1. Daang

Maharlika; D. K0182+500-K0185+48103/19/13 IVA 36.599 120 O 0.386 0.198 0.150 0.030 0.047 0.033 84.40 -

DQT Builders Corporation (Formerly: DQT Builders) 7950 Rehab./Reconst./Upgrading of MCR (Km.101+000-

Km.103+814 & Km.99+741-Km.100+072) (Gasan Sect.) 03/23/13 IVB 46.713 160 O 0.384 0.240 0.150 0.030 0.055 0.033 89.20 -

DQT Builders Corporation (Formerly: DQT Builders) 7950 Repair/Rehab. of Service Road, Sta. Cruz RIS 08/10/11 IVA 9.360 120 O 0.011 0.107 0.150 0.020 0.025 0.033 34.60 -

DQT Builders Corporation (Formerly: DQT Builders) 7950 Widening/Impvt. of Lucena Bdry. Tayabas-Lucabn Road

(Tayabas Sect.), Km.140+810-Km.144+000 w/ exception 03/17/12 IVA 17.023 170 C 0.405 0.197 0.300 - - - 90.20 86.06% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page67

Page 68: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

DQT Builders Corporation (Formerly: DQT Builders) 7950

Widening/Impvt. of MSR Diversion Rd. & MSR Old Route Tayabas, Quezon, Km.125+764-Km.126+000 (Diversion

Rd.), Km.124+646-Km.125+320 (Old Route)08/07/12 IVA 18.177 150 C 0.445 0.133 0.300 - - - 87.80 90.14%

Very Satisfactory

DQT Builders Corporation (Formerly: DQT Builders) 7950 Reconst. along Gumaca-Pitogo-Mulanay-San Narciso

(Catanauan Side), K0258+381-K0258+575 08/02/12 IVA 2.762 60 C 0.443 0.133 0.300 - - - 87.60 89.82% Very Satisfactory

DQT Builders Corporation (Formerly: DQT Builders) 7950 Conc. of Lucena-Tayabas-Lucban-Sampaloc-Mauban Rd.,

Sampaloc-Mauban Sect., Km.145+800-Km.148+279 08/07/12 IVA 42.556 270 C 0.481 0.133 0.300 - - - 91.40 85.94% Satisfactory

DQT Builders Corpration (Formerly: DQT Builders) 7950 Const. of Lucban Overpass SLSU along Lucena-Tayabas-

Lucban-Sampaloc-Mauban Port Rd. 08/08/13 IVA 8.932 150 O 0.357 0.212 0.150 0.030 0.023 0.050 82.20 -

DS Pamintuan Construction 31868 Rehab. Of Murcon Dam D/S Apron @ Division II Service Area 07/27/13 NIA 35.824 120 O 0.364 0.284 0.150 0.020 0.056 0.050 92.44 -

DSB Construction & Supply, Inc. 16126 Repair/Rehab./Improvement of Daan Maharlika National Road, San Rafael 8/13/2014 V 18.809 180 C 0.347 0.200 0.300 84.70 86.50%

Satisfactory

DSB Construction & Supply, Inc. 16126 Road Upgrading of San Fernando North Road (San Fernando Sect.) Km. 2+070-Km. 3+070 08/11/11 V 20.888 150 O 0.357 0.237 0.150 0.030 0.025 0.033 83.20 -

DSB Construction & Supply, Inc. 16126 Construction of Multi-Purpose Building 09/08/09 V 9.553 189 O 0.289 0.300 0.150 0.030 0.043 0.033 84.50 -

DSB Construction & Supply, Inc. 16126 San Vicente-San Carlos Road Linking Tabaco-Ligao to Legazpi-Tabaco-Tiwi Road 09/01/09 V 38.400 390 O 0.314 0.256 0.150 0.030 0.037 0.050 83.70 -

DSB Construction & Supply, Inc. 16126Repair of Bridge Approach/Abutment Protection and

Rechannelization of River Course, Taboc Bridge & along Juban Magallanes Road

02/16/10 V 4.770 83 O 0.321 0.240 0.150 0.015 0.035 0.033 79.40 -

DSB Construction & Supply, Inc. (Formerly: DSB Construction &

Supply)16126 Construction/Rehabilitation/Improvement of Basud River

Control 8/4/2014 V 18.139 207 C 0.357 0.200 0.300 85.70 84.50% Satisfactory

DSB Construction & Supply, Inc. (Formerly: DSB Construction &

Supply)16126

Repair of Collapse Pvmt. & Const. of Drainage System, Slope Protection & Concrete Guardrails along Sto.

Domingo Pob. Rd., K0541+000-K0545+150 w/ exceptions08/12/13 V 10.217 120 C 0.446 0.132 0.300 - - - 87.80 87.80%

Satisfactory

DSB Construction & Supply, Inc. (Formerly: DSB Construction &

Supply)16126

Cluster 1- Prev. Maint. (Asphalt Overlay) along Daang Maharlika Jct. Legazpi Sto. Domingo-Tabaco- Camarines

Sur Bdry. Rd.08/10/13 V 31.485 142 C 0.352 0.200 0.300 - - - 85.20 85.20%

Satisfactory

DSB Construction & Supply, Inc. (Formerly: DSB Construction &

Supply)16126 Const. of Sta. Misericordia Bridge No. 1 08/12/13 V 5.106 385 C 0.464 0.133 0.300 - - - 89.70 88.86%

Satisfactory

DSB Construction & Supply, Inc. (Formerly: DSB Construction &

Supply)16126

Package I, Repair/Rehab./Impvt. of Daan Maharlika Nat'l Rd., San Rafael, Castilla & Repair/Rehab./Impvt. of Daang

Maharlika Nati'l Rd., San Vicente08/14/13 V 23.554 180 O 0.353 0.276 0.150 0.030 0.035 0.033 87.70 -

DSB Construction & Supply, Inc. (Formerly: DSB Construction &

Supply)16126 Const./Rehab./Impv't. of Basud River Control, Brgy, Basud 08/12/13 V 18.139 200 O 0.368 0.300 0.051 0.030 0.055 0.033 83.70 -

DSB Construction & Supply, Inc. (Formerly: DSB Construction &

Supply)16126 Const. of Sta. Misericordia Bridge No. 1 03/18/13 V 5.106 344 O 0.370 0.240 0.134 0.024 0.060 0.050 87.80 -

DSB Construction & Supply, Inc. (Formerly: DSB Construction &

Supply)16126 Rehab. of Tabaco City Wharf Nat'l Rd. 03/18/13 V 37.893 190 C 0.400 0.133 0.300 - - - 83.30 85.46%

Satisfactory

DSB Construction & Supply, Inc. (Formerly: DSB Construction &

Supply)16126 Const. of Double Barrel Box Culvert Tramo Road 05/28/10 V 4.794 180 O 0.373 0.240 0.150 0.030 0.050 0.050 89.30 -

DSB Construction & Supply, Inc. (Formerly: DSB Construction &

Supply)16126 Rehab./Reconst. of Gahonon Road Brgy. Gahonon, (KO

342+442 - KO 342+618) 06/10/10 V 12.984 145 O 0.350 0.240 0.150 0.030 0.040 0.033 84.30 -

DSB Construction & Supply, Inc. (Formerly: DSB Construction &

Supply)16126 Const. of Sta. Misericordia Bridge No. 1 11/22/12 V 5.106 209 O 0.374 0.271 0.111 0.030 0.052 0.050 88.80 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page68

Page 69: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

DSB Construction & Supply, Inc. (Formerly: DSB Construction &

Supply)16126 Dredging of Bulawan River, Malilipot, Albay 08/01/12 V 17.025 116 C 0.367 - 0.500 - - - 86.70 86.94%

Satisfactory

DSB Construction & Supply, Inc. (Formerly: DSB Construction &

Supply)16126 Const. of San Fernando Bridge #1 & Approaches, San

Fernando 08/02/12 V 11.011 210 C 0.440 0.133 0.300 - - - 87.30 86.28% Satisfactory

DSB Construction & Supply, Inc. (Formerly: DSB Construction &

Supply)16126 Const. of San Francisco NHS 08/01/12 V 1.003 120 C 0.419 0.133 0.300 - - - 85.20 82.54%

Satisfactory

DSB Construction & Supply, Inc. (Formerly: DSB Construction &

Supply)16126 Road Upgrading (Gravel to Paved) of San Fernando North

Rd. 03/16/13 V 40.403 270 C 0.365 0.200 0.300 - - - 86.50 86.50% Satisfactory

DSB Construction & Supply, Inc. (Formerly: DSB Construction &

Supply)16126 Repair/Maint. of Dept. of Agriculture, Bureau of Post

Harvest Bodega & Guard House, Nat'l Highway 03/20/13 VII 0.734 60 C 0.399 0.133 0.300 - - - 83.20 83.20% Satisfactory

DSB CONSTRUCTION & SUPPLY, INC. (Formerly: DSB Construction

and Supply)16126

Repair/Rehab./Improvement (Additional Pavement Width) Along Daang Maharlika K0555+903 with exceptions and

K0557+000-K0557+800 with exceptions11/16/2014 V 10.863 135 O 0.354 0.237 0.150 0.030 0.035 0.033 83.90% 83.90%

Satisfactory

DSB Construction and Supply 16126 Conc. of Bical Road 08/12/08 V 14.163 120 O 0.318 0.240 0.070 0.030 0.028 0.067 75.30 -

DSB Construction and Supply, Inc. 16126 Completion of Multi-Purpose Building Phase VII 02/24/09 V 7.188 160 O 0.391 0.240 0.150 0.030 0.056 0.050 91.70 -

DSB Construction and Supply, Inc. 16126 Conc. of San Fernardo North Road 03/01/09 V 18.898 270 O 0.356 0.236 0.150 0.030 0.056 0.050 87.80 -

DSB Construction and Supply, Inc. (Formerly: DSB Construction &

Supply)16126 Const. of Sch. Bldg. at Balonbato E/S 03/20/12 NCR 3.740 120 C 0.429 0.200 0.300 - - - 92.90 88.07%

Satisfactory

DSB CONSTRUCTION AND SUPPLY, INC. (Formerly: DSB

Construction and Supply)16126

Road Widening along DM Jct. Legaspi-Sto. Domingo-Tabaco-Cam. Sur Bdry. Road, K0552+000-K0552+532,

Malilipot Section, K0562+000-K0563+000, Malinao Section w/ exception, K0566+850-K05678+400, Tiwi Section

11/16/2014 V 45.129 266 C 0.448 0.133 0.300 - - - 88.10% 88.10% Satisfactory

DSO ENTERPRISES 10733 Construction of Multi-Purpose Building 11/26/2014 IV 2.969 75 C 0.336 0.200 0.300 - - - 83.60% 83.60% Satisfactory

DSO Enterprises 10733 Prev. Maint. (MFO-1) Daang Maharlika Km. 0075+072.50-Km.0076+045 08/12/13 IVA 7.582 25 C 0.333 0.200 0.300 - - - 83.30 83.30%

Satisfactory

Dungan Constructors & Trading Corp. (Formerly: Dungan

Construction and Trading)19301 Rehab. & Impv't. of C-5 Rd. (K0017+600-K0018+600) (Int.

Sect.) 08/09/13 NCR 10.364 60 C 0.349 0.200 0.300 - - - 84.90 84.90% Satisfactory

Dungan Constructors and Trading Corp. 19301 Const./Rehab. of Drainage System & other Facilities &

Structures, Brgy. Tunasan 11/28/12 NCR 7.038 90 O 0.263 0.300 0.150 0.020 0.043 0.050 82.60 -

DUROS DEVELOPMENT CORP. 22729Rehabilitation/Reconstruction/Upgrading of Cebu North

Hagnaya Wharf Road, (K0079+660 to K0082+101) K0079+660 to K0081+710

10/22/2014 VII 38.815 179 C 0.321 0.200 0.300 - - - 82.10% 82.10% Satisfactory

DUROS DEVELOPMENT CORP. 7494Rehabilitation of Road from Brgy. Curva, Medellin to Brgy. Poblacion, Daan - Bantayan Leading to Maya Roro Port to

Malapascua Island, Sta. 111+952.67 to Sta. 117+50010/22/2014 VII 127.401 240 O 0.339 0.300 0.039 0.030 0.050 0.000 75.80% 75.80%

Unsatisfactory

Duros Development Corp. 22729Rd. Upgrading of Nat'l Rds. (Int. Sect.) along Sogod-

Tabuelan Rd: 1)K0110+490-K0111+(-422); 2)K0114+867-K0115+520; 3)K0110+414-K0110+466

08/10/13 VII 12.040 166 C 0.434 0.151 0.300 - - - 88.50 88.50% Satisfactory

Duros Development Corp. 22729 Const./Widening/Upgrading of Access Rd. to RORO, Daanbantayan Port 08/09/13 VII 27.645 179 C 0.441 0.133 0.300 - - - 87.40 87.40%

Satisfactory

Duros Development Corp. 22729 Guiwanon Revetment along Toledo-Tabuelan Rd., K0106+179 08/10/13 VII 1.476 63 C 0.416 0.200 0.300 - - - 91.60 85.84%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page69

Page 70: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Duros Development Corp. 22729 Rehab./Reconst.of Damaged Paved Nat'l Road along Antonio Y. De Pio Highway, K0109+000-K0110+379 03/25/12 VII 17.074 168 C 0.369 0.191 0.300 - - - 86.00 90.50%

Very Satisfactory

Duros Development Corp. 22729 Road Upgrading of Antonio De Pio Highway, Sta.137+720-Sta.140+212.41; Sta.133+931-Sta.135+300, San Remegio 03/24/12 VII 69.381 240 C 0.446 0.133 0.300 - - - 87.90 86.91%

Satisfactory

Duros Development Corp. 22729 Guiwanon Revetment along Toledo-Tabuelan Rd., K0106+179 11/27/12 VII 1.476 63 O 0.240 0.300 0.150 0.030 0.050 0.050 82.00 -

Duros Development Corp. 22729 Cluster X-Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. at Cebu North Hagnaya Wharf Rd. 08/21/12 VII 40.127 100 C 0.411 0.200 0.300 - - - 91.10 88.76%

Satisfactory

Duros Development Corp. 22729 Rehab./Reconst./Upgrading of Dumaguete North Rd., Bais City 08/16/12 VII 86.775 490 C 0.407 0.133 0.300 - - - 84.00 86.10%

Satisfactory

Duros Development Corp. 22729 Rehab. of Baha-baha-Ajong Sect. Widening & Conc. of Dumaguete North Rd., Km.8.382-Km.9.501 08/13/12 VII 19.277 240 C 0.429 0.133 0.300 - - - 86.20 85.78%

Satisfactory

Duros Development Corporation 22729 Concreting of Baloc-Isabela Rd. 09/14/09 VII 14.220 260 O 0.396 0.240 0.150 0.022 0.037 0.033 87.80 -

Duros Development Corporation 22729 Impvt./Conc. of Access Road to RORO Port at Maya-Daan Bantayan Road 09/01/09 VII 19.005 162 O 0.247 0.300 0.106 0.030 0.045 0.033 76.10 -

Dynamic Builders & Construction Co. (Phil) Inc. 24712 Rehab./Reconst./Upgrading along Bacolod City Bdry. Rd.

Km.2+555 - Km.5+092 w/ exceptions 06/07/10 VI 37.772 270 O 0.315 0.238 0.150 0.030 0.056 0.050 83.90 -

Dynamic Builders & Construction Co. (Phil) Inc. 24712 Rehab. of Bacolod South Road (Caradio-An Section) 05/28/09 VI 42.774 392 O 0.396 0.240 0.150 0.030 0.060 0.050 92.60 -

Dynamic Builders & Construction Co. (Phil) Inc. 24712 Rehab./Recons/Upgrading of Concreting of Bacolod North

road, Caduha-an Section 05/26/09 VI 18.331 140 O 0.355 0.300 0.130 0.030 0.045 0.050 91.00 -

Dynamic Builders & Construction Co. (Phil) Inc. 24712 Rehab./Reconst./Upgrading along Bacolod-San Carlos

Road, Km. 3+990-Km. 13+610 with exception 09/12/09 VI 20.800 235 O 0.320 0.300 0.150 0.030 0.055 0.050 90.50 -

DYNAMIC BUILDERS & CONSTRUCTION CO. (PHIL), INC. 24712

Impv't./Widening of Bacolod - Murcia - D.S. Benedicto - San Carlos City Road, (Murcia Section), Km.17+260 - Km.

029+860 with exception8/6/2014 VI 189.980 540 C 0.383 0.200 0.300 88.30 86.26%

Satisfactory

Dynamic Builders & Construction Co. (Phil.), Inc. 24712

Impv't of Bacolod-Murcia-D.S. Benedicto-San Carlos City Rd. & Slope Protection, Km. 42+400-Km. 52+760 (Rd.), Km.

71+933-Km. 75.855 (Coconet) D.S. Benedicto08/13/13 VI 94.398 360 C 0.457 0.133 0.300 - - - 89.00 86.42%

Satisfactory

Dynamic Builders & Construction Co. (Phil.), Inc. 24712

Impv't./Widening of Bacolod-Murcia-D.S. Benedicto-San Carlos City Rd., (Murcia Sect.), Km.17+260-Km.029+860 (w/

exceptions)08/13/13 VI 189.980 525 O 0.335 0.237 0.150 0.030 0.047 0.050 84.90 -

Dynamic Builders & Construction Co. (Phil.), Inc. 24712

Impv't./Widening of Bacolod-Murcia-D.S. Benedicto-San Carlos City Rd. (Murcia Sect.), Km.17+260-Km.29+860 (w

exceptions)03/15/13 VI 180.602 480 O 0.351 0.240 0.150 0.030 0.055 0.050 87.60 -

Dynamic Builders & Construction Co. (Phil.), Inc. 24712

Impv't. of Bacolod-Mucia-D.S. Benedicto-San Carlos City Rd. & Slope Protection, Km.42+400-Km.52+760 (Road),

Km.71+933-Km.75+855 (Coconet)03/15/13 VI 94.398 360 O 0.366 0.240 0.115 0.030 0.060 0.033 84.40 -

Dynamic Builders & Construction Co. (Phil.), Inc. 24712

Impv't./Widening of Bacolod-Murcia-D.S. Benedicto-San Carlos City Rd. (Murcia Sect.), Km.17+260-Km.0029+860 w/

exceptions11/27/12 VI 180.602 480 O 0.380 0.240 0.150 0.030 0.050 0.050 90.00 -

Dynamic Builders & Construction Co. (Phil.), Inc. 24712

Impv't. of Bacolod-Murcia-D.S. Benedicto-San Carlos City Rd. & Slope Protection Km.42+400-Km. 52+760 (Rd.), Km.71+933-Km.75+855 (Coconet), D.S. Benedicto-San

Carlos City Rd.

11/27/12 VI 94.398 360 O 0.325 0.240 0.150 0.030 0.055 0.050 85.00 -

E E I Corporation 333NAIA Expressway and its Related Roads Project, Phase I, Package IV-A, Sales St. Viaduct and Ramp Structure (MSE

Retaining Wall)03/12/09 URPO 368.005 270 O 0.364 0.300 0.000 0.030 0.065 0.050 80.90 -

E F C Enterprises 11795 Const. of Four (4) Storey, Sixteen (16) CL Sch. Bldg. at Muntinlupa NHS, Brgy. Pob. 08/14/13 NCR 28.943 240 O 0.305 0.240 0.150 0.030 0.041 0.033 79.90 -

E F C Enterprises 11795 Const. of Slope Protection, Zapote River Impvt. Proj., Phase III 11/28/12 NCR 12.295 331 O 0.287 0.298 0.150 0.030 0.045 0.050 86.00 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page70

Page 71: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

E F C Enterprises 11795 Riprapping of Creek Near (Phase II), Brgy. B.F. Homes 11/27/12 NCR 2.441 74 C 0.369 0.200 0.300 - - - 86.90 82.16% Satisfactory

E F C Enterprises 11795 Riprapping of Creek Near (Phase II), Brgy. B.F. Homes 08/02/12 NCR 2.421 74 O 0.297 0.240 0.150 0.030 0.040 0.033 79.00 -

E F C Enterprises 11795Cluster V: Reblocking w/ Asphalt Overlay of South Super

Highway East Service Rd., K0202+504-K0022+035 & K0023+129-K0023+566

03/11/13 NCR 24.932 75 C 0.447 0.133 0.300 - - - 88.00 88.00% Satisfactory

E F C Enterprises / B.M.K. Construction (J.V.) JV-08-321 Const./Widening of Katihan/NBP Bridge, South Luzon

Expressway Brgy. Pob. 03/11/13 NCR 55.859 356 C 0.494 0.123 0.300 - - - 91.70 92.30% Very Satisfactory

E F C Enterprises/B.M.K. Construction (JV) JV-08-321 Const./Widening of Katihan/NBP Bridge, SLEX, Brgy. Pob. 11/26/12 NCR 55.860 356 O 0.380 0.292 0.150 0.030 0.042 0.033 92.70 -

E M L Construction & Trading 10151

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. along Baliuag-Candaba Rd. Km.51+(-1570)-Km52+(-630) w/

exception, Km.52+(-630)-Km.54+000 w/ exception & Km.55+1080 to Km.55+1323

08/14/13 III 15.517 105 C 0.377 0.200 0.300 - - - 87.70 87.70% Satisfactory

E M L Construction & Trading 10151 Rehab./Const. of FMR @ Brgy. Dangcol 08/03/13 III 9.297 120 C 0.411 0.133 0.300 - - - 84.40 84.40% Satisfactory

E M L Construction & Trading 10151 Widening/Conc. of McArthur Highway MNR inc. Drainage and Traffic Mgt. @ K083+580-K0094+000 (w/ exceptions) 08/06/13 III 44.024 214 O 0.358 0.240 0.150 0.030 0.051 0.033 86.20 -

E M L Construction & Trading 10151 Const. and Repair of Drainage System along Old Manila North Rd. (OMNR) 08/07/13 III 22.501 180 O 0.354 0.240 0.150 0.030 0.051 0.033 85.80 -

E M L Construction & Trading 10151 Const. of Access Road to Pampanga 2nd DEO, San Antonio 03/29/12 III 9.457 90 C 0.463 0.133 0.300 - - - 89.60 87.98%

Satisfactory

E M L Construction & Trading 10151

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. along Gapan-San Fernando-Olongapo Rd., Km. 0069+000-

Km. 0070+000, Km. 0071+(-445-Km. 071+0000125+080-K0125+962

11/19/12 III 39.453 300 O 0.325 0.293 0.150 0.030 0.050 0.050 89.80 -

E M L Construction & Trading 10151 Widening of Lazatin Boulevard 07/20/12 III 27.654 258 C 0.429 0.200 0.300 - - - 92.90 82.10% Satisfactory

E M L Construction & Trading 10151 Repair/Rehab./Impv't. of Muzon-Tungkong Mangga Rd. 03/21/13 III 7.443 20 C 0.429 0.133 0.300 - - - 86.20 86.20% Satisfactory

E S DE GUZMAN CONSTRUCTION 17494Construction of Classroom in Areas Experiencing Acute Classroom Shortage, Cordon E/S, One (1) Storey, One (1)

Classroom, SB, Cordon10/30/2014 II 1.142 90 O 0.398 0.224 0.150 0.030 0.011 0.033 84.60% 84.60%

Satisfactory

E S De Guzman Construction 17494 Const. of Classroom, Bambang NHS 08/13/13 II 4.590 150 O 0.367 0.240 0.150 0.030 0.052 0.033 87.20 -

E S De Guzman Construction 17494 Construction of Multipurpose Bldg. 04/16/09 DOST 30.986 120 O 0.361 0.264 0.150 0.030 0.052 0.050 90.70 -

E U S Construction 21878Nat'l Rds. to other Strategic Tourist Destinations Pres.

Cory Aquino Blvd. (Bagasbas-Talisay Sect.), Brgy. Bagasbas

08/08/13 V 47.775 210 C 0.398 0.200 0.300 - - - 89.80 85.36% Satisfactory

E U S Construction 21878Nat'l. Rds. to other Strategic Tourist Destinations

President Cory Aquino Blvd. (Bagasbas-Talisay Sect.), Brgy. Bagasbas

03/27/13 V 47.775 210 O 0.319 0.236 0.150 0.024 0.045 0.050 82.40 -

E. A. Padilla Builders Casecnan Multipurpose Irrigation & Power Project II 02/07/15 NIA 329.256 C 0.419 0.150 0.300 - - - 86.90 86.90% Satisfactory

E. Caneda Construction 22168 Repair/Maint. of Phil. Postal Office Bldg., Region VII 03/20/13 VII 0.765 60 C 0.448 0.133 0.300 - - - 88.10 88.10% Satisfactory

E. Garcia Construction & E. Garcia Gravel & Sand 7243

Rehab./Reconst. Of Damaged Nat'l Road along Daang Maharlika, K0394+000-K0395+315 & K0395+1182-

K0396+63803/23/12 V 24.188 150 C 0.418 0.200 0.300 - - - 91.80 90.78%

Very Satisfactory

E. Garcia Construction & E. Garcia Gravel & Sand 7243

Preventive Maint. (IS Arterial) along Rolando R. Andaya Highways A)Km.282+000-Km.282+900 B)Km.285+000-

Km.285+83803/23/12 V 20.101 120 O 0.343 0.300 0.150 0.023 0.040 0.033 88.90 -

E. Garcia Construction & E. Garcia Gravel & Sand 7243 Rehab./Reconst./Strengthening of Santiago Bridge 08/09/12 V 5.811 140 C 0.444 0.133 0.300 - - - 87.70 88.18%

SatisfactoryE. Garcia Construction & E. Garcia

Gravel & Sand 7243 Conc. of Milaor-Minalabac-Pili Road Sect. Km.438+(-018)-Km. 443+300 w/ exception 08/14/12 V 41.784 240 C 0.474 0.133 0.300 - - - 90.70 86.68%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page71

Page 72: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

E. Garcia Construction and E. Garcia Gravel 7243 Naga Airport Development Project 03/07/09 PMS 43.333 150 O 0.373 0.300 0.150 0.020 0.063 0.050 95.60 -

E. Garcia Construction Corp. (Formerly E. Garcia Construction &

E. Garcia Gravel and Sand)7243 Construction of Flood Control, Camarines Sur 1st DEO,

Labmanan Flood Control 8/7/2014 V 22.785 165 OG 0.336 0.300 0.150 0.022 0.050 0.050 90.80 -

E. Garcia Construction Corp. (Formerly E. Garcia Construction &

E. Garcia Gravel and Sand)7243 Major Repair/Maintenance of Existing Permanent Bridge,

Hidong Bridge along Rolando Andaya Highway 8/6/2014 V 0.968 45 C 0.393 0.200 0.300 89.30 89.30% Very Satisfactory

E. Garcia Construction Corp. (Formerly E. Garcia Construction &

E. Garcia Gravel and Sand)7243 Channel Improvement/Revetment of Waras River, Iriga

Section 8/10/2014 V 18.187 200 OG 0.332 0.300 0.150 0.020 0.039 0.050 89.10 -

E. Garcia Construction Corp. (Formerly: E. Garcia Construction

& E. Garcia Gravel & Sand)7243 Repair/Maint. of San Fernando River Control Brgy.

Buenavista 03/21/13 V 2.143 180 C 0.454 0.133 0.300 - - - 88.70 89.84% Very Satisfactory

E. Garcia Construction Corporation 7243 Development of Sabang Port Project 05/28/14 DOTC 11.896 180 C 0.452 0.200 0.300 - - - - 94.10% Very Satisfactory

E. Garcia Construction Corporation 7243 Pio Duran Port Development Project 02/12/14 DOTC 4.240 120 C 0.396 0.200 0.300 - - - 89.56 89.56% Very Satisfactory

E. Garcia Construction Corporation 7243 Naga Airport Developmetn Project 02/13/14 DOTC 6.422 90 C 0.472 0.200 0.300 - - - 97.22 97.22% Outstanding

E. Garcia Construction Corporation 7243 Sabang Port Development Project 03/06/14 DOTC 11.896 180 O 0.344 0.300 0.150 0.020 0.070 0.050 93.40 -

E. Garcia Construction Corporation 7243 Camarines Sur LTFRB Building Construction Project 09/05/13 DOTC 16.796 240 O 0.381 0.300 0.150 0.030 0.062 0.033 95.60 -

E. Garcia Construction Corporation 7243 Camarines Sur LTFRB Building Construction Project 12/14/13 DOTC 16.796 240 C 0.445 0.200 0.300 - - - 94.50 95.30% Very Satisfactory

E. Garcia Construction, Corp. (Formerly: E. Garcia Construction

& E. Garcia Gravel & Sand)7243 Const. of Slope Protection & Safety Devices along Daang

Maharlika, Brgy. Sigamot 08/05/13 V 6.524 117 C 0.430 0.133 0.300 - - - 86.30 86.30% Satisfactory

E. Guadiz Construction 27172 Prev. Maint. along Manila North Rd. K0676+000-K0676+900 08/02/13 II 6.245 45 C 0.438 0.133 0.300 - - - 87.10 84.16% Satisfactory

E. Guadiz Construction 27172 Prev. Maint. along Manila North Rd., K0676+200-K0676+900 03/12/13 II 6.245 45 O 0.350 0.200 0.150 0.030 0.059 0.033 82.20 -

E. Lapus Enterprises 10813 Const./Impv't. of Bagac-Mariveles Rd., Mariveles Sect. 08/02/13 III 4.792 30 C 0.437 0.133 0.300 - - - 87.00 87.00% Satisfactory

E. Lapus Enterprises 10813 Const./Cons./Impvt. Of Bagac-Mariveles Rd. Km.182+348-Km.188+351 w/ exception (Mariveles Sect.) Brgy. Biaan 08/02/13 III 14.097 75 C 0.434 0.133 0.300 - - - 86.70 86.70%

Satisfactory

E. Lapus Enterprises 10813 Repair/Rehab./Impvt. of Bagac-Mariveles Rd., Mariveles Sect. 08/02/13 III 9.581 90 C 0.431 0.133 0.300 - - - 86.40 86.40%

Satisfactory

E. M. Cuerpo Inc. 30963 Construction of Eight (8) Five Storey Low Rise Buildings w/ Land Development and Survey Works 07/12/13 NHA 242.299 360 O 0.387 0.205 0.136 0.030 0.065 0.050 87.25 -

E. M. Cuerpo Incoporated 30963 Cagayan de Oro Airport Development Project 10/24/12 DOTC 21.315 120 O 0.368 0.300 0.150 0.030 0.035 0.050 93.30 -

E. M. Cuerpo, Inc. 30963 Construction of (8) Five storey Low Rise Buildings with Land Development and Survey Works, Tala Phase II 05/09/14 NHA 266.494 514 O 0.389 0.300 0.101 0.030 0.060 0.033 91.33 -

E. M. Cuerpo, Inc. 30963 Construction of (8) Five storey Low Rise Buildings with Land Development and Survey Works, Tala Phase II 10/31/13 NHA 266.494 514 O 0.379 0.283 0.110 0.030 0.065 0.050 91.70 -

E. M. Cuerpo, Inc. 30963 Cagayan de Oro Airport Development Project 06/27/13 DOTC 21.315 120 C 0.450 0.200 0.300 - - - 95.00 93.90% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page72

Page 73: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

E. P. MANANTAN CONSTRUCTION AND DEVELOPMENT

CORPORATION6457 Reconstruction of First District Engineering Office

Building 10/27/2014 XI 10.889 300 O 0.322 0.235 0.150 0.030 0.029 0.033 79.90% 79.90% Unsatisfactory

E. S. De Guzman Construction 17494 Colocol Integrated CIS Rehabilitation & Extension Project 05/12/12 NIA 10.932 227 C 0.445 0.200 0.300 - - - 94.50 92.09% Very Satisfactory

E. U. Jingco Construction 31486Emergency Repair of Damaged Rock Bulkhead along Old

RC Wharf & RoRo Ramp-1 caused by 7.2 Magnitude Earthquake

11/15/14 PPA 23.629 180 C 0.440 0.200 0.300 - - - - 96.53% Outstanding

E. U. Jingco Construction 31486Emergency Repair of Damaged Rock Bulkhead Along Old

R. C. Wharf & RoRo Ramp-1 Caused by 7.2 Magnitute Earthquake

08/15/14 PPA 23.629 180 O 0.396 0.300 0.150 0.030 0.056 0.050 98.20 -

E. U. JINGCO CONSTRUCTION 31486 Construction of Eco-Tourism Pavillon 12/02/14 TIEZA 7.395 300 O 0.386 0.300 0.150 0.015 0.018 0.050 91.90 -

E. U. Jingco Construction 31486 Repair of Damaged Retaining Wall & Concrete Pavement Bet. Pier I & II 03/25/11 PPA 6.928 90 O 0.364 0.225 0.150 0.030 0.035 0.033 83.70 -

E.A Ramirez Construction, Inc. 11631 Construction of 3-Storey School Building 09/08/09 NHA 19.080 204 O 0.364 0.271 0.053 0.030 0.056 0.050 82.40 -E.A Ramirez Construction, Inc. 11631 Construction of one (1) Unit Public Market 09/16/10 NHA 3.972 90 O 0.3906 0.2904 0.0092 0.0150 0.0250 0.0333 76.35 -

E.A Sancho Construction 5648 Impvt./Conc. Of Tabgon-Maysalay Road KO 502+400 - KO 504+476 06/04/10 V 14.142 150 O 0.301 0.293 0.150 0.030 0.035 0.033 84.20 -

E.A Sancho Construction 5648 Impv't./Conc. of Maysalay-Lamon Rd. 08/25/10 V 14.147 168 O 0.345 0.300 0.150 0.030 0.055 0.033 91.30 -

E.A. Sancho Construction Inc. (Formerly: E.A. Sancho

Construction)5648

Major Repair/Maintenance of Existing Permanent Bridge, Rehab./Reconstruction/Replacement/Retrofitting of

Tabuan Bridge along Pili-Tigaon-Albay Road8/8/2014 V 4.404 112 C 0.433 0.133 0.300 86.60 86.60%

Satisfactory

E.A. Sancho Construction Inc. (Formerly: E.A. Sancho

Construction)5648 Road Upgrading (Gravel to Paved) along Iriga City-San

Isidro-Hanawan Road 8/10/2014 V 35.831 178 C 0.351 0.200 0.300 85.10 85.40% Satisfactory

E.A. Sancho Construction Inc. (Formerly: E.A. Sancho

Construction)5648 CP-II(1-2) Rd. Upgrading (Gravel to Paved) along Iriga City-

San Isidro-Hanawan Rd. 08/01/13 V 11.654 178 O 0.345 0.243 0.150 0.030 0.055 0.033 85.60 -

E.A. Unabia Construction 29305 Conc. of Sta. Filomena FMR 08/12/13 CAR 9.319 180 C 0.400 0.133 0.300 - - - 83.30 84.08% Satisfactory

E.A. Unabia Construction 29305 Conc. of Sta. Filomena FMR 03/22/13 CAR 9.319 180 O 0.357 0.238 0.150 0.023 0.045 0.033 84.60 -

E.A. Unabia Construction 29305 Completion of MPB, Calanasan People's MPB, Pob. 08/12/12 CAR 4.091 180 C 0.357 0.200 0.300 - - - 85.70 85.49% Satisfactory

E.A. Unabia Construction 29305 Package 1 A) Const. of Grandstand (Phase 2) 03/22/13 CAR 4.946 295 C 0.432 0.133 0.300 - - - 86.50 86.50% Satisfactory

E.A. Unabia Construction / KDCM Construction / BHM Construction,

Joint VentureReplacement of Saleng Bridge along Kalinga-Abra Rd. 11/26/12 CAR 7.809 270 O 0.341 0.300 0.050 0.022 0.028 0.033 77.40 -

E.B.A Construction 6210 UP OU Centennial Center for Digital Learning 07/20/09 U.P. 12.948 60 O 0.361 0.261 0.150 0.020 0.020 0.050 86.20 -

E.B.J.R Construction 19780 Construction/Rehabilitation of Drainage Protection Works, Caglayan, Flood Control 8/8/2014 CAR 4.000 126 C 0.396 0.133 0.300 82.90 82.90%

Satisfactory

E.B.J.R Construction 19780

Maintenance of Natl Rd along Abbut-Conner Road, K0542+370 to K0562+000 w. Exception b. Conner-Kabugao Road, K0577+369 to K0602+792 c. Kabugao-Pudtol-Luna

Road, K0591+413 to K0603+000 w/ Exception and d. Abbut-Conner Road K0548+500 to K0550+500 w/Exception

8/8/2014 CAR 2.998 90 C 0.389 0.133 0.000 52.20 71.34% Poor

E.B.J.R. Construction 19780

Maint. of Nat'l Rd. (Item 200-Aggregate Base Course a)Abbut-Conner Rd., K0542+370-K0562+000 (w/

exceptions); b)Conner-Kabugao Rd., K0577+369- K0602+792; c) Kabugao-Pudtol-Luna Rd., K0591+413-

K0603+000 (w/ exceptions); d)Abbut-Conner Rd., K0548+500-K0550+500 w/ exception

08/10/13 CAR 2.998 90 O 0.333 0.300 0.111 0.030 0.050 0.017 84.10 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page73

Page 74: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

E.B.J.R. Construction 19780 Repair/Maint. of Caglayan River Control 03/21/13 CAR 0.977 60 C 0.404 0.133 0.300 - - - 83.70 83.46% Satisfactory

E.B.J.R. Construction 19780 Repair & Maint. of Flood Control Structures, Caglayao Flood Control, Caglayao 08/10/12 CAR 2.628 120 C 0.375 0.200 0.063 - - - 63.80 75.26%

UnsatisfactoryE.C De Luna Const. Corp.

(Formerly E.C. De Luna Const.) 11906 CP IV, Gatanguit-Calbiga Road Sect. Phase VI 12/03/08 PJHL 1,466.751 1,080 O 0.350 0.300 0.100 0.030 0.065 0.100 94.50 -

E.C De Luna Construction Corporation 11906 Marikina-Infanta Road Project, Km. 91+910-Km. 120+925

under SONA Projects in Luzon Beltway 03/05/10 PJHL 1,915.106 720 O 0.368 0.300 0.150 0.030 0.056 0.050 95.40 -

E.C De Luna Construction Corporation (Formerly: E.C De

Luna Const.)11906

Const. of El Nido-Bataraza Rd. CP-3B-1 Puerto Prinsesa-Aborlan Abo-abo Sect. Segments 1-7 Km.02+376 -

Km.128+026.93 w/ exception06/01/10 IVB 1,792.809 730 O 0.380 0.300 0.150 0.030 0.060 0.050 97.00 -

E.C. de Luna Construction Corporation (Formerly: E.C. De

Luna Construction)11906 Arterial Road Bypass Project Phase I, CP I: Plaridel

Bypass, Sta.32+970.33-Sta.39+625.00 03/26/12 PMO-PJHL 1,570.718 1,029 C 0.402 0.200 0.300 - - - 90.20 90.32% Very Satisfactory

E.C. TIMBANCAYA ENTERPRISES 15244 Construction of Multi-Purpose Building 11/24/2014 IV 5.679 117 C 0.497 0.133 0.300 - - - 93.00% 93.00% Very Satisfactory

E.C. Timbancaya Enterprises 15244 Repair/Maint. of Capitol-Canigaran Drainage Channel, Km.0+322-Km.1+091, Capitol-Canigaran Rd. 03/15/13 IVB 5.252 165 C 0.447 0.133 0.300 - - - 88.00 88.00%

Satisfactory

E.C.T. Construction 10060 Const./Concreting of Various Roads-Sanchez Mira, Cagayan 8/6/2014 II 3.884 67 C 0.347 0.194 0.300 84.10 84.10%

Satisfactory

E.E. MADAYAG CONSTRUCTION 25029 Rehabilitation of Multi-Purpose Building at Bacnotan Municipal Civic Center 10/25/2014 I 3.953 140 C 0.454 0.149 0.300 - - - 90.30% 90.30%

Very Satisfactory

E.E. Madayag Construction 25029 Const. of 6-Cl, 2-Storey at Catbangen Elementary School 8/4/2014 I 5.956 200 C 0.460 0.133 0.300 89.30 86.78% Satisfactory

E.E. Madayag Construction 25029 Construction of Local Roads, Brgy. Ambitacay 8/5/2014 I 1.861 37 C 0.340 0.200 0.300 84.00 84.00% Satisfactory

E.E. Madayag Construction 25029 Const. of 6-Cl, 2-Storey Bldg. at Catbangen Elem. Sch. 07/30/13 I 5.584 200 C 0.371 0.240 0.150 0.030 0.033 0.033 85.70 -

E.E. Madayag Construction 25029 Const. of Bungro-Susoc Integrated Sch. 03/11/13 I 1.213 170 C 0.381 0.200 0.300 - - - 88.10 88.10% Satisfactory

E.G Guillen Builders 14174 Conc. along Kabugao-Pudtol-Luna Road, Kapanikian Section 06/01/09 CAR 9.338 277 O 0.293 0.300 0.150 0.023 0.045 0.050 86.10 -

E.G. & I CONSTRUCTION CORPORATION 16225 Installation of Center Island/Median at A.C. Cortes Ave.,

Including Landscaping 10/21/2014 VII 28.446 186 O 0.382 0.265 0.150 0.015 0.033 0.033 87.80% 87.80% Satisfactory

E.G. CANABE CONSTRUCTION 27358 Rehabilitation of Damaged Paved Road along Leyte-Biliran Road (Biliran Bridge), Km.1006+(1096)-Km.1006+(-776) 10/27/2014 VIII 3.987 80 C 0.414 0.133 0.300 - - - 84.70% 84.70%

Satisfactory

E.G. Canabe Construction 27358

Maint., Rehab. & Impv't. of Nat'l Arterial & Sec. Rds. of Biliran Circ. Road (Slope Protection) Km.1037+000-

Km.1054+000 w/ exceptions along Almeria-Kawayan-Culaba Rd.

08/14/13 VIII 9.750 145 C 0.451 0.133 0.300 - - - 88.40 88.40% Satisfactory

E.GARCIA CONSTRUCTION CORPORATION (Formerly: E.

Garcia Construction & E. Garcia Gravel & Sand)

7243 Construction of Bombon Flood Control System Brgy. San Roque, Bombon, Camarines Sur 11/11/2014 V 17.581 170 C 0.470 0.134 0.300 - - - 90.40% 90.40%

Very Satisfactory

E.GARCIA CONSTRUCTION CORPORATION (Formerly: E.

Garcia Construction & E. Garcia Gravel & Sand)

7243 Channel Improvement/Revetment at Waras River, Iriga Section, Iriga City, Sta. 0+000 to Sta. 0+285 11/12/2014 V 18.187 200 C 0.469 0.165 0.300 - - - 93.40% 93.40%

Very Satisfactory

E.GARCIA CONSTRUCTION CORPORATION (Formerly: E.

Garcia Construction & E. Garcia Gravel & Sand)

7243 Road Upgrading (Gravel-Paved) Lagonoy - Presentacion Road 11/13/2014 V 25.095 138 C 0.403 0.133 0.300 - - - 83.60% 83.60%

Satisfactory

E.I. Templonuevo and Associates, Incorporated 1090 Road Upgrading (Gravel to Concrete) Caticlan-Malay-

Libertad Road 04/08/11 VI 9.640 120 O 0.360 0.237 0.150 0.030 0.037 0.033 84.70 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page74

Page 75: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

E.I. Templonuevo and Associates, Incorporated 1090

Const./Widening/Upgrading/Rehab. of Access Rds. to Airport RORO Ports & Declared Tourist Destinations,

Dumaguit Port08/17/12 VI 9.532 150 C 0.490 0.133 0.300 - - - 92.30 92.36%

Very Satisfactory

E.K.C Construction and Aggregates 14833 Impvt. of Baguio-Bontoc-Banaue Road, Conc. of Mt. Data-

Bontoc Road, Km. 367+228 - Km. 368+444 (one section), 03/08/09 CAR 13.750 657 O 0.300 0.300 0.000 0.030 0.045 0.033 70.80 -

E.K.C. CONSTRUCTION AND AGGREGATES 14833

Road Upgrading (Gravel to Concrete) based on Gravel Road Strategies, Traffic Benchmark for Upgrading to

Paved Road Standard (HDM-4 Project Analysis) (Intermittent Sections) along Acop-Kapangan-Kibungan-

Bakun Road, K0311+254 - K0312+000 & K0312+000 - K0312+670

11/21/2014 CAR 47.735 231 O 0.362 0.239 0.150 0.030 0.050 0.033 86.40% 86.40% Satisfactory

E.K.C. Construction and Aggregates / Lab General

Engineering (JV)JV-10-136 Rehab./Reconst. of Mt. Province-Ilocos Sur via Tue Road,

K0403+500-K0403+926.50; K0413+437-K0414+052 11/22/12 CAR 14.526 335 C 0.362 0.200 0.000 - - - 56.20 63.73% Poor

E.K.C. Construction and Aggregates / Lab General

Engineering (JV)JV-10-136 Rehab./Reconst. Of Mt. Province-Ilocos Sur via Tue Rd,.

K0403+500-K0403+926.50; K0413+437-K0414+052 08/04/12 CAR 14.526 395 O 0.317 0.300 0.000 0.000 0.023 0.033 67.30 -

E.K.C. Construction and Aggregates / Lab General

Engineering (JV)JV-10-136 Rehab. of Mt. Province-Ilocos Sur via Tue Road,

K0413+347-K0414+052; K0403+500-K0404+044 03/16/12 CAR 14.526 290 O 0.299 0.300 0.000 0.030 0.040 0.033 70.20 -

E.K.C. Construction and Agreggates 14833 Rehab./Reconst./Upgrading of Damaged Paved Nat'l. Rd.

(Halsema), K0262+000-K0266+000 (v.s.) 03/14/13 CAR 31.700 35 C 0.482 0.133 0.300 - - - 91.50 88.38% Satisfactory

E.L. ANOLIN CONSTRUCTION 35406Rehabilitation/Upgrading (Preventive Maintenance) of

Congressional Avenue, Q.C. (K011+(-205) to K013+(-065)) with exception

11/27/2014 NCR 7.569 150 O 0.351 0.240 0.150 0.030 0.040 0.033 84.40% 84.40% Satisfactory

E.L. Anolin Construction 35406 Repair & Maint. of Flood Control (Drainage Structure) along Rodriguez-San Jose Quezon City Rd. 08/03/12 IVA 1.961 75 C 0.459 0.133 0.300 - - - 89.20 89.80%

Very Satisfactory

E.L. TORRES CONSTRUCTION AND TRADING 31406 Rehab./Upgrading (Preventive Maintenance) of Quirino

Highway, (K020+000 to K023+897) 8/14/2014 NCR 9.486 180 C 0.484 0.133 0.300 91.70 91.70% Very Satisfactory

E.M. Angeles Enterprises 10150 Repair/Rehab./Impv't. of Int'l. Reciever Rd. (CAA Road) 03/11/13 NCR 14.842 60 C 0.452 0.133 0.300 - - - 88.50 88.50% Satisfactory

E.M. ARAGON ENTERPRISES 3314

Construction of Flood Control Projects, Cavite 3rd LD, Construction of Flood Control including Drainage Outfall in Imus River, Palico IV Section, with RROW acquisition; Flood Control and Water Impounding Structures in Imus

River, with RROW acquisition

11/5/2014 IV 12.266 180 C 0.404 0.133 0.300 - - - 83.70% 83.70% Satisfactory

E.M. Bayatan Construction 21332 Const. of Bridge, New 9 (along Arterial Rd.) Dumog Box Culvert along Aritao-Quirino Road 8/15/2014 II 9.767 150 OG 0.349 0.239 0.150 0.024 0.045 0.033 84.00 -

E.M. Bayatan Construction 21332 Const. of River Control Proj. along Magat River, Dadap Sect. 08/13/13 II 4.550 75 C 0.456 0.133 0.300 - - - 88.90 88.90%

Satisfactory

E.M. Bayatan Construction 21332 Cupas River Control, Sto. Domingo Sect. 08/13/13 II 16.166 105 C 0.446 0.133 0.300 - - - 87.90 88.14% Satisfactory

E.M. Bayatan Construction 21332 Cupas River Control, Sto. Domingo Sect. 03/20/13 II 14.700 90 O 0.400 0.225 0.150 0.030 0.045 0.033 88.30 -

E.M. Cuerpo, Inc. 30963 College of Engineering Building Expansion 04/10/15

PICE-Misamis Oriental-

CDO

108.334 360 C 0.500 0.200 0.300 - - - 100.00 87.50% Satisfactory

E.M. Cuerpo, Inc. 30963 College of Engineering Building Expansion 07/31/14

PICE-Misamis Oriental-

CDO

108.334 360 O 0.382 0.300 0.051 0.030 0.060 0.000 82.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page75

Page 76: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

E.M. Cuerpo, Inc. 30963 College of Engineering Building Expansion 04/29/14

PICE-Misamis Oriental-

CDO

108.334 O 0.400 0.300 0.061 0.020 0.050 0.000 83.10 -

E.M. CUERPO, Inc. 30963 Construction of Eight(8) Five storey Low Rise Buildings with Land Development and Survey Works, Tala, Phase II 05/09/14 NHA 266.494 514 O 0.389 0.300 0.101 0.030 0.060 0.033 91.33 -

E.M. CUERPO, Inc. 30963 Construction of Eight(8) Five storey Low Rise Buildings with Land Development and Survey Works, Tala, Phase II 10/31/13 NHA 266.494 514 O 0.379 0.283 0.110 0.030 0.065 0.050 91.70 -

E.M. Cuerpo, Inc. 30963 Rehab./Reconst. of Loay Interior Rd. 03/11/13 VII 41.104 270 C 0.255 0.200 0.300 - - - 75.50 82.34% Satisfactory

E.M. Cuerpo, Inc. 30963 Sta Teresa Port Development Project 05/03/12 DOTC 286.943 420 C 0.388 0.200 0.300 - - - 88.80 92.90% Very Satisfactory

E.M. Cuerpo, Inc. 30963 Sta Teresa Port Development Project 05/02/12 DOTC 96.295 360 C 0.400 0.200 0.300 - - - 90.00 92.80% Very Satisfactory

E.M.L Construction & Trading 10151 Rehabilitation of Angeles-Porac-Floridablanca-Dinalupihan Road 05/18/09 III 19.053 75 O 0.368 0.211 0.150 0.030 0.035 0.050 84.40 -

E.R. Dela Cruz Construction & Supply 32158 Const. of Maloma Dike (Upstream Sect.) Cabangan Side 08/03/13 III 17.738 135 C 0.418 0.133 0.300 - - - 85.10 85.10%

SatisfactoryE.R. Dela Cruz Construction &

Supply 32158 Raising of Grade Vega-Maculcol Dike 08/03/13 III 13.304 120 C 0.407 0.133 0.300 - - - 84.00 84.00% Satisfactory

E.R. Dela Cruz Construction & Supply 32158 Const. of Slope Protection/Flood Control, Maculcol Dike

(Downstream) San Felipe Side 08/03/13 III 17.737 120 C 0.406 0.133 0.300 - - - 83.90 83.90% Satisfactory

E.R. dela Cruz Construction & Supply 32158 Const. of MPB at Brgy. Alwa 03/15/13 III 4.358 120 C 0.439 0.133 0.300 - - - 87.20 87.20%

SatisfactoryE.R. dela Cruz Construction &

Supply 32158 Repair/Maint. of Flood Control Project, Vega-Maculcol Dike 03/15/13 III 4.656 120 C 0.436 0.133 0.300 - - - 86.90 86.90% Satisfactory

E.R. dela Cruz Construction & Supply 32158 Const. of MPB. at Brgy. Maloma 03/15/13 III 1.934 120 C 0.420 0.133 0.300 - - - 85.30 85.30%

SatisfactoryE.R. dela Cruz Construction &

Supply 32158 Prev. Maint. (Int. Sect.) Nat'l Arterial Rd., K0157+900-K0159+305, Olongapo-Bugallon Rd. 03/15/13 III 12.324 30 C 0.409 0.133 0.300 - - - 84.20 84.20%

SatisfactoryE.R. dela Cruz Construction &

Supply 32158 Road Conc./Impv't/.Rehab. of Rd. at Brgy San Juan 03/15/13 III 0.945 60 C 0.402 0.133 0.300 - - - 83.50 83.50% Satisfactory

E.R. dela Cruz Construction & Supply 32158 Const. of MPB @ Brgy. Amungan 03/15/13 III 4.538 120 C 0.400 0.133 0.300 - - - 83.30 83.30%

Satisfactory

E.R. RODRIGUEZ CONSTRUCTION 12596 Improvement of Earth dike along the Left Bank of Polo River, Sta. 0+000 to Sta. 1+471 11/22/2014 NCR 44.463 270 O 0.325 0.300 0.150 0.030 0.060 0.050 91.50% 91.50%

Very Satisfactory

E.R. Rodriguez Construction 12596 Construction of Flood Control and Drainage 8/15/2014 V 18.983 262 C 0.379 0.156 0.000 53.50 76.00% Unsatisfactory

E.R. Rodriguez Construction 12596Road Upgrading (Gravel to Paved) of Catanduanes Circ. Road, Km. 149+000-Km. 152+000, Inalmasinan-Hitoma

Sect.08/16/11 V 44.097 240 O 0.323 0.133 0.150 0.010 0.028 0.033 67.70 -

E.R. Rodriguez Construction 12596 Const. of Flood Control & Drainage 07/30/13 V 18.983 252 O 0.339 0.300 0.150 0.030 0.058 0.033 91.00 -

E.R. VENSON CONSTRUCTION/P K C S CONSTRUCTION &

HARDWARE (JV)JV-13-788

Network Development - Widening of National Roads - Arterial Roads Widening of Gapan-San Fernando-

Olongapo Road Bataan First District11/26/2014 III 22.079 150 O 0.383 0.221 0.150 0.030 0.037 0.033 85.40% 85.40%

Satisfactory

E.R. VENSON CONSTRUCTION/PASCAL

CONSTRUCTION (JV)JV-13-293 Improvement of Concrete Revetment of Colo River, Colo

Section 11/26/2014 III 17.112 155 C 0.429 0.133 0.300 - - - 86.20% 86.20% Satisfactory

E.R. VENZON CONSTRUCTION/PASCAL

CONSTRUCTION (J.V.)JV-13-293 Improvement of Concrete Revetment of Colo River, Colo

Section 8/12/2014 III 17.112 155 C 0.488 0.133 0.300 92.10 92.10% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page76

Page 77: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

E.S. Almuete Construction 5131 Const. of Classroom, Bonfal National High School 8/14/2014 II 6.657 265 C 0.488 0.200 0.000 68.80 75.66% Unsatisfactory

E.S. Almuete Construction 5131 Const. of Classroom, Bonfal NHS 08/13/13 II 6.084 180 O 0.385 0.240 0.066 0.033 0.029 0.033 78.60 -

E.S. Bihag Construction & Supply 35698 Conc. of Pinit-Oras Road 03/22/13 V 1.940 90 C 0.413 0.154 0.300 - - - 86.70 86.70% Satisfactory

E.S.L. BUILDERS AND PARTS SUPPLY 9014Widening (Paving of Shoulder)-Seal Widening of Calapan South Road K0025+550-K0026+492 Along Curva Section,

Naujan, Oriental Mindoro11/26/2014 IV 9.378 109 C 0.479 0.133 0.300 - - - 91.20% 91.20%

Very Satisfactory

E.S.R Construction and Supplies 10451 Gadakinsur CIP 10/6-10/08 MOPIO 10.740 270 O 0.360 0.160 0.100 0.020 0.040 0.200 88.00 -

E.S.R Construction and Supplies 10451 Gadakinsur Communal Irrigation Project, Package II 10/6-10/08 MOPIO 13.049 977 O 0.371 0.160 0.050 0.010 0.050 0.200 84.11 -

E.T.V.R Trading and Construction 14581 Rehab./Impvt. of DPWH Office Bldg., Regional Office 12/04/08 XI 19.250 300 O 0.389 0.300 0.100 0.030 0.058 0.100 97.70 -

E.T.V.R. Trading & Construction 14581Widening (Paving of Shoulder) - Seal Widening of Calapan South Road K0014+692.60 - K0015+175.30 along Managpi

Section8/11/2014 IV-B 9.964 86 OG 0.356 0.221 0.150 0.030 0.055 0.050 86.20 -

E.T.V.R. TRADING AND CONSTRUCTION 14581Widening (Paving of Shoulder)- Seal Widening of Calapan South Road K0014+692.60-K0015+175.30 along Managpi

Section11/26/2014 IV 10.048 113 C 0.481 0.133 0.300 - - - 91.40% 91.40%

Very Satisfactory

E.T.V.R. Trading and Construction 14581 Const. of Wawa Seawall along Calapan South Rd. 03/18/13 IVB 2.948 177 C 0.494 0.133 0.300 - - - 92.70 92.70% Very Satisfactory

E.T.V.R. Trading and Construction 14581 Repair/Rehab./Impv't. of Calapan North Road, K0033+600-K0033+743.50 w/ exception 03/18/13 IVB 9.390 90 C 0.442 0.141 0.300 - - - 88.30 88.30%

Satisfactory

EA-EC Construction 15737 Road Concreting of Corporal Street 8/10/2014 V 1.834 21 C 0.349 0.200 0.300 84.90 84.90% Satisfactory

EA-EC Construction 15737 Const. of Classroom S/B Catasan E/S 08/23/10 V 0.540 90 O 0.337 0.300 0.150 0.030 0.029 0.033 87.90 -

Eaglerock Construction & Development Corporation Construction of 3-Storey, 15 Classroom School Bldg. 02/22/13 NHA 22.123 224 C 0.494 0.193 0.300 - - - 98.73 85.98% Satisfactory

Eaglerock Construction & Development Corporation Construction of 3-Storey, 15 Classroom School Bldg. 09/07/12 NHA 22.123 180 O 0.364 0.178 0.150 0.020 0.050 0.050 81.23 -

Eaglerock Construction & Development Corpporation Construction of 3-Storey, 15 Classroom School Bldg. 07/05/12 NHA 22.123 180 O 0.318 0.225 0.150 0.020 0.035 0.050 79.80 -

Eaglerock Construction and Development Corp. 32286 Primetown III Yolanda Permanent Housing Project 05/29/15 NHA 99.246 220 O 0.332 0.257 0.150 0.030 0.060 0.050 87.89 -

Eaglerock Construction and Development Corporation 32286 Construction of Core Housing Units (701 Units) of

Kinamaligan Resettlement Project Phase I09/29/2014-10/03/2014 NHA 73.394 270 Delayed 0.312 0.300 0.150 0.010 0.050 0.050 87.24 -

East Asia Construction, Inc. 1904Prev. Maint., Iloilo-Antique Rd.; a)K0001+(-325)-K0001+977;

b)K0003+(-969)-K0003+(-627); c)K0006+100-K0006+782; d)Chainage 0942-Chainage 2012

08/23/13 VI 36.209 60 C 0.443 0.133 0.300 - - - 87.60 87.60% Satisfactory

East Asia Construction, Inc. 1904Rehab./Reconst./Upgrading of Damaged Paved Nat'l

Arterial Road (Conc' of Barotac Nuevo-Dumangas-Dacutan Wharf Road, Km.280+042.80-Km.281+482.00

03/21/12 VI 17.947 210 C 0.454 0.200 0.300 - - - 95.40 89.40% Very Satisfactory

EC Samonte Construction 31019

Road Upgrading (Gravel to Paved) based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road Standard Inteermittent Section (HDM-4 Project

Analysis) Intermittent Section Liloy-Siocon Road K1982+124 - K1983+130

8/8/2014 IX 27.742 201 C 0.343 0.182 0.000 52.50 68.04% Poor

EC Samonte Construction 31019 Rd. Upgrading (Gravel to Paved) Int. Sect., Liloy-Siocon Rd., K1982+124-K1983+130 08/12/13 IX 27.747 118 O 0.303 0.300 0.000 0.012 0.033 0.033 68.10 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page77

Page 78: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

EC Samonte Construction 31019 Rd. Upgrading (Gravel to Paved) Int. Sect., Liloy-Siocon Rd., K1982+124-K1983+130 03/16/13 IX 27.747 93 O 0.397 0.225 0.150 0.030 0.035 0.050 88.70 -

EC Samonte Construction 31019 Rd. Upgrading (Gravel to Paved) Int. Sect., Siocon-Sirawai-Sibucon Limpapa Rd., K2097+000-K2099+200 03/17/13 IX 27.908 93 O 0.365 0.232 0.150 0.030 0.040 0.033 85.00 -

EC Samonte Construction 31019 Concreting of Pathway Liloy Central School 06/01/09 IX 0.962 88 O 0.387 0.240 0.150 0.030 0.047 0.050 90.40 -EC Samonte Construction 31019 Const. of Liloy-Siocon Road, Dansalan-Lopoc 03/09/09 IX 28.654 311 O 0.369 0.281 0.150 0.030 0.035 0.050 91.50 -

EC STRUCTURAL COMPOSITES INC. 31961 Rehab./Reconst./Replacement/Retrofitting of Tripa de

Gallina Bridge (NB) along Gil Puyat Ave. 3/19/2015 NCR 8.726 90 O 0.400 0.225 0.150 0.030 0.025 0.033 86.30% 86.30% Satisfactory

ECANGELES CONSTRUCTION & CONST. SUPPLY 34420 Construction of Barangay Road, San Agustin 11/18/2014 III 4.731 74 C 0.467 0.133 0.300 - - - 90.00% 91.08%

Very SatisfactoryECAngeles Construction & Const.

Supply 34420 Repair/Maint. of DPWH Area & Maint. Warehouse, San Nicolas 03/16/13 III 0.972 60 C 0.482 0.130 0.300 - - - 91.20 91.20%

Very SatisfactoryECAngeles Construction &

Construction Supply 34420 Const. of 2-CL with CR, Cabitaugan E/S 03/16/13 III 1.357 75 C 0.419 0.133 0.300 - - - 85.20 85.20% Satisfactory

ECDA Construction 7013 Revetment along Angat River, Lumangbayan 03/18/13 III 5.205 52 C 0.387 0.200 0.300 - - - 88.70 85.34% Satisfactory

ED TING BUILDER & CONSTRUCTION SUPPLY 26199

Rehabilitation/Improvement of Road Slip along Butuan City - Malaybalay Road, K1261+700 - K1261+952 (Intermittent

Section), Mabuhay Section10/29/2014 XIII 0.923 48 C 0.387 0.179 0.300 - - - 86.60% 86.60%

Satisfactory

EDANNA CONSTRUCTION 25492

Road Upgrading (Gravel to Paved) based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Rd

Standard (HDM-4 Project Analysis) Intermittent Sect., Liloy-Lamao Port Road, K 1966+(-353) - K 1966+(-275) (FY 2014),

Z.N.

10/24/2014 IX 1.852 34 C 0.485 0.136 0.300 - - - 92.10% 92.10% Very Satisfactory

Edanna Construction 25492

Road Upgrading (Gravel to Paved) based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road Standard (HDM-4 Project Analysis) Intermittent

Section, Liloy-Lamao Port Road

8/9/2014 IX 1.852 24 C 0.411 0.200 0.300 91.10 91.10% Very Satisfactory

EDANNA CONSTRUCTION 25492 Emergebcy Repair of Damaged Container Yard-Back-Up Area caused by 7.2 Magnitude Earthquake 04/10/15 PPA 31.233 256 O 0.379 0.300 0.150 0.030 0.060 0.050 96.90 -

EDANNA CONSTRUCTION 25492 Emergebcy Repair of Damaged Container Yard-Back-Up Area caused by 7.2 Magnitude Earthquake 04/10/15 PPA 31.233 256 C 0.488 0.200 0.300 - - - - 97.60%

Outstanding

Edanna Construction 25492 Emergency Repair of Damaged Container Yard/ Back-Up Area caused by 7.2 Magnitude Earthquake 11/15/14 PPA 31.233 300 O 0.379 0.300 0.150 0.030 0.060 0.050 96.90 -

Eddie G. Guillen Builders 14174Repair/Rehab. Of Damaged Revetment & Seawall @ Brgy.

San Antonio & Maura under POPSTIRP, Flood Control Component

08/02/11 II / MFCP II- PMO 14.314 102 O 0.267 0.300 0.150 0.020 0.042 0.033 81.20 -

Eddie G. Guillen Builders 14174 Repair/Restoration of Damaged Seawall at Maura 11/24/12 II 13.559 180 C 0.480 0.200 0.000 - - - 68.00 76.70% Unsatisfactory

Eddie G. Guillen Builders 14174 Road Upgrading along Jct. Logac-Lasam-Gagabutan Road, (Peru Sect.) K0733+146-K0736+532.80 w/h exceptions 08/01/12 II 27.564 300 C 0.392 0.200 0.300 - - - 89.20 91.90%

Very Satisfactory

Eddmari Const. & Trading / Cholo Const. & Trading (JV) JV-07-091 Candaba-San Miguel Road 02/24/09 III 25.964 234 O 0.335 0.300 0.150 0.030 0.042 0.050 90.70 -

Eddmari Construction & Trading 20301 Construction of 4 Units Health/Day Care Center and 2 Units Police Center, NV 3, 4A,4B and 5A 06/04/10 NHA 8.989 90 O 0.40 0.30 0.15 0.026 0.051 0.05 97.70 -

Eddmari Construction & Trading 20301 Construction of 1-Unit Health/Day Care Center 06/04/10 NHA 1.998 90 O 0.40 0.30 0.150 0.024 0.049 0.05 97.30 -

Eddmari Construction & Trading 20301 Construction of 1-Unit Police Center 06/04/10 NHA 0.498 90 O 0.40 0.30 0.15 0.024 0.049 0.050 97.30 -

Eddmari Construction & Trading Const. of 1 Unit 3-Storey School Building 08/29/12 NHA 22.132 180 O 0.368 0.300 0.000 0.020 0.057 0.033 77.90 -

Eddmari Construction and Trading 20301 Tulaoc-Sto. Domingo Rd. (Prev. Maint.-Nep-Int. Sect.) Km.0061+545-Km.0061+830.9 07/29/13 III 2.665 15 C 0.437 0.133 0.300 - - - 87.00 87.00%

Satisfactory

Eddmari Construction and Trading 20301 Repair/Rehab. of Slope Protection along Sapangbalen @ P. Bulu 08/06/13 III 13.622 150 O 0.369 0.240 0.150 0.030 0.047 0.033 86.90 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page78

Page 79: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Eddmari Construction and Trading 20301 Candaba-San Miguel Road 02/24/09 III 45.764 193 O 0.379 0.299 0.150 0.030 0.037 0.050 94.50 -

Eden Construction 2010-0502 Construction of Concrete Lining @ Main Canal 07/27/13 NIA 2.876 60 C 0.444 0.160 0.300 - - - 90.44 90.44% Very Satisfactory

EDISON DEVELOPMENT CONSTRUCTION 2400

Construction/Rehabilitation of Drainage Slope Protection Along Jct. Dumalinao-Margosatubig K1702+000 -

K1705+180 (Intermittent Section)10/26/2014 IX 8.304 270 O 0.279 0.286 0.150 0.030 0.045 0.033 82.30% 82.30%

Satisfactory

Edmond Ray Construction & Supply 33167 Const. of Sch. Bldg., Canibungan Proper ES 08/16/13 X 1.144 84 C 0.449 0.133 0.300 - - - 88.20 88.20%

SatisfactoryEDMOND RAY CONSTRUCTION

AND SUPPLY 33167 Construction of School Building, Montol NHS, Ozamis City 8/14/2014 X 2.195 84 C 0.442 0.200 0.300 94.20 94.20% Very Satisfactory

Edmond Ray Construction and Supply 33167 Const. of Sch. Bldg., Montol NHS 08/16/13 X 2.195 137 O 0.376 0.300 0.056 0.030 0.050 0.033 84.50 -

Edrox Construction, Inc. 10926 Const. of MPB (Covered Court) Del Rosario 03/21/13 V 2.955 90 C 0.402 0.133 0.300 - - - 83.50 83.50% Satisfactory

Edward Lui Construction 8459 Impv't. of MPB, Brgy. Tinago 03/21/13 VII 0.495 75 C 0.460 0.133 0.300 - - - 89.30 89.30% Very Satisfactory

Edwarf Lui Construction 8459 Const. of MPB, Tejero Elem. Sch., Brgy. Tejero 03/19/12 VII 3.219 130 C 0.457 0.133 0.300 - - - 89.00 86.97% Satisfactory

EDWIN ERWIN SISON CONSTRUCTION 20162 Construction of Classroom at Bayombong Central School 10/29/2014 II 3.861 110 O 0.334 0.300 0.150 0.030 0.029 0.033 87.60% 87.60%

SatisfactoryEDWIN ERWIN SISON

CONSTRUCTION 20162 Construction of Multi-Purpose Building, Brgy. Poblacion 10/29/2014 II 1.980 64 C 0.436 0.133 0.300 - - - 86.90% 86.90% Satisfactory

EGB CONSTRUCTION 13722

Camarines Sur-Albay Diversion Road, San Fernando-Oas-Daraga Section of the Pan Philippine Highway (PPH) including Bridges, San Fernando-Minalabac Section

(Sta.426+716.20-Sta.430+030.80)

11/10/2014 V 47.476 404 C 0.426 0.133 0.300 - - - 85.90% 85.90% Satisfactory

EGB Construction 13722 Widening of Cagayan Valley Road (CVR), Caggy Section to Tuguegarao City Airport (with exception) 8/7/2014 II 34.751 180 C 0.354 0.294 0.150 0.018 0.051 0.033 90.00 90.00%

Very Satisfactory

EGB Construction 13722 Widening along Daang Maharlika K0396+000-K0397+214.36 w/ exception, Baligatan 08/05/13 II 9.518 113 C 0.404 0.200 0.300 - - - 90.40 90.40%

Very Satisfactory

EGB Construction 13722 Const. of Pamplona Flood Control Proj. 08/02/13 II 19.396 180 C 0.460 0.133 0.300 - - - 89.30 89.30% Very Satisfactory

EGB Construction 13722Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds.,

Cagayan-Apayao Rd. (Maddarulug-Solana Sect.n) K0488+024-K0488+922

07/29/13 II 15.716 195 C 0.448 0.133 0.300 - - - 88.10 88.10% Satisfactory

EGB Construction 13722 Rehab./Strengthening of Minanga Bridge, Minanga 08/05/13 II 9.133 123 C 0.414 0.200 0.300 - - - 91.40 86.54% Satisfactory

EGB Construction 13722 Rehab./Strengthening of Minanga Bridge, Minanga 03/13/13 II 9.133 123 O 0.353 0.194 0.150 0.030 0.056 0.050 83.30 -EGB Construction 13722 Conc. of Ilagan-Bigao-Palanan Rd. 05/29/10 II 14.475 110 O 0.380 0.240 0.150 0.030 0.056 0.033 88.90 -EGB Construction 13722 Const./Impvt. of Public Market 05/28/10 II 2.406 120 O 0.378 0.240 0.150 0.030 0.051 0.033 88.20 -

EGB Construction 13722 Repair of Flood Control Project, Baculud 11/20/12 II 20.370 257 C 0.404 0.200 0.300 - - - 90.40 90.76% Very Satisfactory

EGB Construction 13722 Repair/Restoration of Pangul Bridge (Ph-I), Cagayan-Apayao Rd., K0497+711 08/03/12 II 9.700 135 C 0.474 0.133 0.300 - - - 90.70 94.36%

Very Satisfactory

EGB Construction 13722Rehab./Reconst./Upgrading of Damaged Paved Nat'l

Roads, STR, (Jct. Kalinga-Tuguegarao Sect'), K0442+197-K0444+000

08/03/12 II 9.884 150 C 0.438 0.174 0.300 - - - 91.20 91.68% Very Satisfactory

EGB Construction 13722 Repair of Flood Control Project, Baculud 08/03/12 II 20.370 210 O 0.340 0.300 0.150 0.030 0.040 0.050 91.00 -

EGB CONSTRUCTION/MEGAY CONSTRUCTION AND SUPPLY (JV) JV-13-517

Construction of Flood Control Mitigation Structures and Drainage System along Cagayan River Basin, Cagayan

Valley 1st LD, Camalaniugan Section10/21/2014 II 28.084 150 C 0.351 0.200 0.300 - - - 85.10% 85.10%

Satisfactory

Eirish Builders & Supply Co. 33656 Road Upgrading (Gravel to Paved) Sibul-Biak-na-Bato Road, K0094+881 to K0095+206 9/27/2014 Special 3 4.415 60 C 0.347 0.191 0.300 83.80 83.80%

SatisfactoryEJR Builders and Construction

Supply 24255 Road Concreting at Poblacion 8/14/2014 I 4.090 60 C 0.415 0.133 0.300 84.80 84.80% Satisfactory

EJR Builders and Construction Supply 24255 Const. of Slope Protection & Cross Drainage along

Pangasinan-Zambales Rd., K0301+000-K0302+000 03/15/13 I 4.985 120 C 0.442 0.200 0.175 - - - 81.70 84.04% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page79

Page 80: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

El Dolliares Construction, Inc 33335 Cotabato City LTFRB Regional Office Project 04/02/14 DOTC 2.340 90 C 0.350 0.200 0.300 - - - 84.95 84.95% Satisfactory

El Kapitan Construction Service 33123 Const./Conc./Rehab./Completion of Sto. Tomas Multi-purpose Bldg. 08/24/09 III 0.475 35 O 0.356 0.240 0.150 0.030 0.051 0.050 87.70 -

Elkankonstrak Development Corporation (Formerly: Elkan

Konstrak & Aggreagates)26220 Construction/Maintenance of Flood Mitigation Structures

and Drainage System, Bacolod River Control 8/12/2014 V 18.953 140 C 0.400 0.150 0.300 85.00 85.00% Satisfactory

Elkankonstrak Development Corporation (Formerly; Elkan

Konstrak & Aggregates)26220

Rd. Upgrading (Gravel to Paved) Albay West Coast Rd. (Badian Sect. K0537+354-K0537+860.50, Catburawan Sect., K0538+650-K0538+850 & K0539+128- K0539+538, Maonon

Sect. K0544+128-K0544+328

03/20/13 V 8.466 177 C 0.332 0.200 0.249 - - - 78.10 84.76% Satisfactory

ELMUEL JAY TRADING AND CONSTRUCTION 17010 Preventive Maintenance (Asphalt Overlay) along Carmen

Junction- Manat Road, K0172+141 to K0173+298 10/30/2014 I 9.363 28 C 0.356 0.200 0.300 - - - 85.60% 85.60% Satisfactory

ELPA CONSTRUCTION 36613 Rehabilitation/Drainage Improvement along N. Ramirez St., (Cordillera St. to Sto. Tomas St., Intermittent Section) 8/16/2014 NCR 4.888 105 C 0.486 0.133 0.300 91.90 91.90%

Very Satisfactory

EML CONSTRUCTION & TRADING 10151 Preventive Maintenance of Angeles-Porac-Floridablanca-Dinalupihan Road (Intermittent Section) 11/18/2014 III 18.593 90 C 0.438 0.133 0.300 - - - 87.10% 87.10%

Satisfactory

EML CONSTRUCTION & TRADING 10151

Reconstruction of Damaged Paved National Roads Inlcuding Drainage based on PMS/HDM-4 (Intermittent Section) Bigaa-Plaridel via Bulacan and Malolos Road K0040+500 to K0041+500 & K0045+1006 to K0049+381

11/24/2014 III 28.422 300 O 0.323 0.300 0.142 0.030 0.037 0.033 86.50% 86.50% Satisfactory

EML CONSTRUCTION & TRADING 10151 Widening of Old Cagayan Valley Road (Baliuag Section) Km. 46+284 to Km. 52+985 11/7/2014 III 25.686 241 O 0.348 0.240 0.150 0.030 0.045 0.033 84.60% 84.60%

Satisfactory

EML CONSTRUCTION & TRADING 10151 Preventive Maintenance of San Antonio-Floridablanca Road (Intermittent Section) K0083+000 - K0083+740 8/11/2014 III 9.716 35 C 0.473 0.133 0.300 90.60 90.60%

Very Satisfactory

Enliven Construction and Enterprises 34230 Const. of Sch. Bldg. Standard Modified (7.0 x 9.0m) at

Leyte NHS 08/22/13 VIII 1.204 60 C 0.497 0.133 0.300 - - - 93.00 93.00% Very Satisfactory

Enliven Construction and Enterprises 34230 Const. of Sch. Bldg. Standard Modified (7.0 x 9.0m) at San

Jose Central Sch. 08/22/13 VIII 1.204 60 C 0.495 0.133 0.300 - - - 92.80 92.80% Very Satisfactory

ENRIQUE A. FLORES, JR. 2421 Widening of Ferguson Road 8/15/2014 CAR 5.116 60 C 0.475 0.133 0.300 90.80 90.80% Very Satisfactory

Enrique A. Flores, Jr. Contractor 2421 Restoration of Damaged Box Culvert & Slope Protection along Kennon Rd., K0241+780-K0241+830 08/17/13 CAR 7.522 130 C 0.490 0.133 0.300 - - - 92.30 92.30%

Very Satisfactory

EPL GENERAL CONSTRUCTION AND SUPPLY 15559 CONSTRUCTION OF TWO(2) STOREY REGIONAL OFFICE

BUILDING P-1, RO-V 04/17/15 NIA 24.779 300 O 0.344 0.300 0.091 0.065 0.020 0.050 86.89 -

EPN Builders & Developers 30341 Const. of MPB, Nagtipunan Central Sch. 08/12/13 II 2.700 75 C 0.489 0.133 0.300 - - - 92.20 92.20% Very Satisfactory

EPN Builders & Developers 30341 Colocol Integrated CIS Rehabilitation & Extension Project 05/12/12 NIA 9.411 227 C 0.418 0.200 0.300 - - - 91.76 90.59% Very Satisfactory

EPN Builders & Developers 30341 Colocol Integrated CIS Rehabilitation & Extension Project 11/07-12/11 NIA 9.525 180 O 0.378 0.244 0.133 0.024 0.070 0.050 89.82 -

EPN Builders & Developers 30341 Road Upgrading along Banaue-Mayoyao-Aguinaldo-A. Lista-Isabela Boundary Road, Anaba-Habbang Sect. 03/18/12 CAR 9.565 229 C 0.449 0.133 0.300 - - - 88.20 85.50%

Satisfactory

EPN Builders & Developers 30341 Const. of MPB at Doña Imelda 03/20/12 II 2.117 110 C 0.486 0.133 0.300 - - - 91.90 85.39% Satisfactory

EPN Builders & Developers 30341 Conc. of Yeban Sur-Yeban Norte FMR 03/18/13 II 4.621 60 C 0.427 0.133 0.300 - - - 86.00 86.00% Satisfactory

Equi-Parco Construction 14332 UMAYAM RIVER IRRIGATION PROJECT 09/12/15 NIA 25.695 541 O 0.324 0.240 0.150 0.015 0.060 0.050 83.93 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page80

Page 81: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Equi-Parco Construction UMAYAM RIVER IRRIGATION PROJECT 09/12/15 NIA 246.400 670 O 0.340 0.240 0.150 0.015 0.060 0.050 85.53 -

Equi-Parco Construction PIDP/Batutu River Irrigation System PIDP11-C-BRISN-1 05/17/14 NIA 76.047 469 O 0.347 0.271 0.150 0.030 0.055 0.050 90.26 -

Equi-Parco Construction PIDP/Batutu River Irrigation System PIDP11-C-BRISN-2 05/17/14 NIA 76.325 469 O 0.276 0.300 0.150 0.030 0.065 0.050 87.14 -

Equi-Parco Construction 14332 Conc. of Misamis Oriental-Bukidnon-Agusan Road 03/19/09 X 91.466 330 O 0.347 0.300 0.100 0.030 0.045 0.050 87.20 -Equi-Parco Construction 14332 Conc. of Misamis Oriental-Bukidnon-Agusan Road 06/10/09 X 91.466 330 O 0.271 0.300 0.150 0.030 0.043 0.050 84.40 -

Equi-Parco Construction 14332 Rehab./Reconst. of Butuan City-Cagayan De Oro City- Iligan Road 09/09/09 X 145.175 405 O 0.357 0.300 0.150 0.030 0.056 0.050 94.30 -

Equi-Parco Construction 14332 Rehab./Reconst. of Butuan City-Cagayan de Oro City-Iligan City (BCIR) Road 09/07/09 X 474.722 360 O 0.378 0.248 0.150 0.030 0.070 0.050 92.60 -

Equi-Parco Construction 14332 Conc. of Agusan del Norte-Surigao del Sur (Cabadbaran-Puting Bato Section) 03/03/09 XIII 95.698 540 O 0.335 0.300 0.150 0.030 0.056 0.050 92.10 -

Equi-Parco Construction 14332 Construction of Butuan City By-Pass Road, Bonbon-Kinamlutan Section 03/19/09 XIII 24.594 195 O 0.353 0.300 0.150 0.030 0.042 0.050 92.50 -

Equi-Parco Construction 14332 Rechanneling of Cabadbaran River, Putting Bato, Phase 1 03/03/09 XIII 19.280 180 O 0.334 0.000 0.200 0.050 0.067 0.250 90.10 -

Equi-Parco Construction 14332 Upgrading of Agusan-Bukidnon National Road 05/25/09 XIII 14.326 210 O 0.393 0.300 0.150 0.030 0.047 0.050 97.00 -

Equi-Parco Construction 14332 Rehab./Reconst. of Buenavista-Bunaguit Road Section 05/25/09 XIII 7.572 180 O 0.376 0.300 0.150 0.030 0.047 0.050 95.30 -

Equi-Parco Construction 14332 Concreting of Butuan City-Masao Port Rd., Jct. Doongan Bridge 09/16/09 XIII 14.213 195 O 0.378 0.240 0.150 0.030 0.060 0.050 90.80 -

Equi-Parco Construction 14332 Const./Conc. of SDCR(Lingig Boundary-Boston Sect.) along Bislig-Boston Sect. 09/11/09 XIII 325.527 585 O 0.383 0.225 0.150 0.030 0.065 0.050 90.30 -

Equi-Parco Construction 14332 Upgrading of Agusan-Bukidnon National Rd. 09/01/09 XIII 14.326 210 O 0.394 0.216 0.150 0.030 0.050 0.050 89.00 -

Equi-Parco Construction 14332 UMAYAM RIVER IRRIGATION PROJECT 09/12/15 NIA 14.652 315 C 0.424 0.120 0.300 - - - 84.43 84.43% Satisfactory

Equi-Parco Construction Company 14332 San Jose Airport Development Project 08/28/15 DOTC 88.404 398 C 0.482 0.200 0.300 - - - 98.20 97.99% Outstanding

EQUI-PARCO CONSTRUCTION COMPANY 3507 Wharf Extension Project 12/04/15 PPA 130.911 390 O 0.399 0.300 0.150 0.030 0.061 0.050 98.98 -

EQUI-PARCO CONSTRUCTION COMPANY 14332 Const. of Cagayan de Oro Road (By-Pass Road) including

RROW K1434+820-K1436+180 10/20/2014 X 137.944 446 C 0.393 0.133 0.300 - - - 82.60% 87.13% Satisfactory

EQUI-PARCO CONSTRUCTION COMPANY 14332 Const. of Misamis Oriental-Bukidnon By-Pass Road

PHIVIDEC-Alae Sect. 10/28/2014 X 38.540 240 C 0.389 0.194 0.000 - - - 58.30% 58.30% Poor

EQUI-PARCO CONSTRUCTION COMPANY 14332

Preventive Maintenance along Daang Maharlika Road (Agusan-Davao Section), Bayugan-Prosperidad Section,

K1245+450 - K1245+617, K1259+463 - K1259+527, K1272+000 - K1273+040, K1288+960 - K1290+849,

K1297+960 - K1298+960

10/22/2014 XIII 58.655 120 C 0.418 0.137 0.300 - - - 85.50% 85.50% Satisfactory

EQUI-PARCO CONSTRUCTION COMPANY 14332

Road Upgrading (Gravel to Concrete) of Buenavista-Bunaguit Road, K1261+822.33 - K1262+520.33, K1267+360 -

K1271+919, K1273+520 - K1274+000, K1276+486.27 - K1277+063

10/30/2014 XIII 120.376 270 O 0.372 0.251 0.150 0.022 0.047 0.050 89.20% 89.20% Very Satisfactory

EQUI-PARCO CONSTRUCTION COMPANY 14332 Construction of Butuan City Bypass Road (Lemon - NRJ -

Antongalon Section), K1237+894 - K1234+720 10/10/2014 XIII 123.506 270 O 0.310 0.300 0.150 0.022 0.047 0.050 87.90% 87.90% Satisfactory

EQUI-PARCO CONSTRUCTION COMPANY 14332

Rehabilitation/Reconstruction/Replacement/Retrofitting of Pandanon Bridge along Daang Maharlika (Surigao-Agusan

Road)10/20/2014 XIII 19.794 280 O 0.343 0.259 0.150 0.022 0.042 0.050 86.60% 86.60%

Satisfactory

EQUI-PARCO CONSTRUCTION COMPANY 14332 Const. of Cagayan de Oro Coastal Road (By-Pass Road)

including ROW, K1434+820 - K1436+180 8/4/2014 X 137.944 445 C 0.481 0.200 0.300 98.10 90.15% Very Satisfactory

EQUI-PARCO CONSTRUCTION COMPANY 14332 Construction of Revetment along Butuan City-Cagayan de

Oro City-Iligan City Road 8/11/2014 X 27.728 178 C 0.494 0.200 0.300 99.40 99.40% Outstanding

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page81

Page 82: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Equi-Parco Construction Company 14332 San Jose Airport Development Project 03/13/15 DOTC 88.404 398 O 0.397 0.300 0.150 0.030 0.045 0.050 97.17 -

Equi-Parco Construction Company 24715 Lipata Port Expansion & Improvement Project 02/10/15 PPA 75.531 438 C 0.485 0.200 0.300 - - - - 97.12% Outstanding

Equi-Parco Construction Company 14332 Caminawit Port Development Project 11/28/14 DOTC 73.313 270 C 0.485 0.200 0.300 - - - - 96.80% Outstanding

Equi-Parco Construction Company 14332 San Jose Airport Development Project 11/29/14 DOTC 88.404 360 O 0.400 0.300 0.150 0.030 0.055 0.050 98.50 -

Equi-Parco Construction Company 15953 Paving of Existing Back-up Area, Port of Masao 09/26/14 PPA 23.394 150 C 0.488 0.200 0.300 - - - 98.80 98.80% Outstanding

Equi-Parco Construction Company 24715 Lipata Port Expansion & Improvement Project 09/26/14 PPA 75.531 390 O 0.371 0.300 0.150 0.030 0.061 0.050 96.20 -

Equi-Parco Construction Company 14332 Repair/Rehab./Impvt. of Surigao-Davao Coastal Rd,. Mangagoy-Lingig Sect., Km.1468+831-Km.1469+344 08/17/13 XIII 9.900 105 C 0.470 0.133 0.300 - - - 90.30 90.30%

Very Satisfactory

Equi-Parco Construction Company 14332Repair/Rehab./Impv't. of Daang Maharlika (Surigao-Agusan

Rd.) along Pob. Sect., Km.1167+977-Km.1168+777 w/ exception

08/06/13 XIII 9.605 45 C 0.430 0.133 0.300 - - - 86.30 86.30% Satisfactory

Equi-Parco Construction Company 14332 Caminawit Port Development Project 03/12/14 DOTC 73.313 270 O 0.394 0.300 0.150 0.030 0.038 0.050 96.17 -

Equi-Parco Construction Company 14332 Impvt. of Drainage Facilities along Butuan City-Malaybalay Rd. Montilla Blvd. Sect. 08/23/13 XIII 16.739 220 O 0.392 0.240 0.150 0.030 0.040 0.050 90.20

Equi-Parco Construction Company 14332Widening of Butuan-Cagayan de Oro-Iligan-Agusan-

Misamis Oriental Rd., Agusan del Norte Dumalagan Bdry. Sect.

08/23/13 XIII 28.850 209 C 0.429 0.133 0.300 - - - 86.20 85.78% Satisfactory

Equi-Parco Construction Company 14332 Rehab./Reconst./Strengthening of Bridges along Nat'l Rds., Kibaluyot Bridge along BCIR 08/20/13 X 25.112 330 C 0.482 0.200 0.300 - - - 98.20 92.05%

Very Satisfactory

Equi-Parco Construction Company 14332Widening/Concr. of Butuan City-CDOC-Iligan City Rd. (Opol-Laguindingan Airport Sect.), Km.1466+282.80-

Km.1467+282.8008/19/13 X 83.789 360 C 0.398 0.200 0.300 - - - 89.80 89.47%

Very Satisfactory

Equi-Parco Construction Company 14332 Const. of Slope Protection at Iponan River (Downstream of Iponan Bridge I & II) Bulua Dise along BCIR, Phase I 08/11/13 X 15.412 183 C 0.444 0.133 0.300 - - - 87.70 86.35%

Satisfactory

Equi-Parco Construction Company 14332 Cagayan de Oro Basin 08/22/13 X 46.562 255 C 0.407 0.200 0.300 - - - 90.70 84.82% Satisfactory

Equi-Parco Construction Company 14332 Const. of Cagayan de Oro Coastal Rd. (By-Pass Rd.) inc. ROW, K1434+820-K01436+180.00 08/16/13 X 137.944 328 O 0.314 0.300 0.116 0.030 0.053 0.033 84.60 -

Equi-Parco Construction Company 14332Widening/Conc. of Butuan City-Cagayan de Oro City-Iligan

City Rd. (Opol-Laguindingan-Airport Sect.) Km.1466+282.80-Km.1467+282.80

03/12/13 X 83.789 330 O 0.350 0.300 0.150 0.020 0.045 0.033 89.80 -

Equi-Parco Construction Company 14332 Const. of Slope Protection along Butuan City-Cagayan de Oro City-Iligan City Rd., Agusan Sect. 03/18/13 X 10.722 150 C 0.363 0.200 0.300 - - - 86.30 87.38%

Satisfactory

Equi-Parco Construction Company 14332 Const. of Slope Protection along Butuan City-Cagayan de Oro City-Iligan City Rd., Alae-Bugo Sect. 03/18/13 X 12.889 150 C 0.378 0.200 0.300 - - - 87.80 86.36%

Satisfactory

Equi-Parco Construction Company 14332 Const. of Slope Protection at Iponan River (Downstream of Iponan Bridge I & II) Bulua Side, along BCIR, Phase I 03/11/13 X 15.412 183 O 0.314 0.270 0.150 0.030 0.042 0.050 85.60 -

Equi-Parco Construction Company 14332

Rehab./Replacement of Mandulog Bridges I Bridge ID: B00606MN along Highway Secondary Diversion Rd., Rd.

ID: R01497MN, Sect. ID: S00961MN, Km.1522+(-484) const. of 2 lanes 240m conc. bridge w/ 6 spans @ 40m per span

03/15/13 X 137.639 360 O 0.293 0.292 0.150 0.015 0.047 0.033 83.00 -

Equi-Parco Construction Company 14332 Cagayan de Oro River Basin 03/18/13 X 46.562 240 O 0.268 0.246 0.150 0.030 0.051 0.050 79.50 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page82

Page 83: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Equi-Parco Construction Company 14332 Drainage along Butuan City-Malaybalay (Montilla Blvd. & Diego Silang Sect.) 03/21/13 XIII 23.669 210 C 0.479 0.200 0.300 - - - 97.90 96.46%

Outstanding

Equi-Parco Construction Company 14332 Const. of Butuan City Bypass Rd. (Borbon-Bancasi Airport Sect. & NRJ Lemon-NRJ-Antongalon Sect.) 03/21/13 XIII 71.414 471 C 0.423 0.200 0.300 - - - 92.30 93.38%

Very Satisfactory

Equi-Parco Construction Company 14332 Widening/Conc. of Add'l Lane along Daang Maharlika (Agusan-Surgao Rd.), Ampayon Sect. 03/21/13 XIII 37.027 192 O 0.274 0.300 0.150 0.030 0.060 0.050 86.40 -

Equi-Parco Construction Company 14332Widening of Butuan-Cagayan de Oro-Iligan (Agusan-

Misamis Oriental Rd.), Agusan del Norte, Dumalagan to Bdry. Sect.

03/21/13 XIII 27.791 150 O 0.382 0.205 0.150 0.030 0.055 0.033 85.50 -

Equi-parco Construction Company 14332

Rehab./Reconst./Upgrading Damaged Paved Nat'l Rd., Butuan City-Cagayan De Oro City-Iligan Rd

a.)Km.1459+980-Km.1459+1002.35 & b.)Km.1460+0-Km.1460+1000

08/13/11 X 13.090 165 O 0.375 0.240 0.150 0.030 0.050 0.033 87.80 -

Equi-Parco Construction Company 14332 Repair/Impvt. (Asphalt Overlay) along Daang Maharlika (Agusan-Davao Sect.) 03/27/12 XIII 7.677 150 C 0.484 0.133 0.300 - - - 91.70 91.28%

Very Satisfactory

Equi-Parco Construction Company 14332 Rehab./Reconst./Upgrading of Damaged, Paved Rds. along Daang Maharlika (Agusan-Davao Road Sect.) 03/28/12 XIII 24.453 180 C 0.486 0.133 0.300 - - - 91.90 90.94%

Very Satisfactory

Equi-Parco Construction Company 14332 Reconst. Of Butuan-Cagayan de Oro-Iligan (Sta.1264+000-Sta. 1265+000 inclusive) Agusan-Misamis Oriental Road 03/19/12 XIII 7.947 90 C 0.432 0.133 0.300 - - - 86.50 85.12%

Satisfactory

Equi-Parco Construction Company 14332

Cluster 2011; Rehab./Reconst./Upgrading of Damaged Paved Nat'l. Roads Gen. from Pvt. Mgt. System/HDM-4 (IS)Butuan City-Cagayan de Oro City-Iligan City Road.

a)Km.1459+980-Km.1459+1002.35 b)Km.1460+0-Km.1460+1000

03/23/12 X 13.090 165 C 0.406 0.200 0.300 - - - 90.60 88.92% Satisfactory

Equi-Parco Construction Company 14332Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds.

(IS) Butuan City-Cagayan de Oro City-Iligan City Rd. a)Km.1446+0-Km.1446+980

03/23/12 X 12.728 164 C 0.452 0.133 0.300 - - - 88.50 86.22% Satisfactory

Equi-Parco Construction Company 14332 Butuan City-Cagayan de Oro City-Iligan City Road a)Km.1457+000-Km.1457+100, b)Km.1458+0-Km.1459+5 03/23/12 X 11.619 150 C 0.447 0.133 0.300 - - - 88.00 85.06%

Satisfactory

Equi-Parco Construction Company 14332

Cluster 2011: Assets Preservation of Nat'l Rds. Gen. from Pvt. Mgt. System/HDM-4, Preventive Maint. (IS) Butuan City-

Cagayan de Oro City-Iligan City Road a)Km.1466+474-Km.1468+4 & b)Km.1469+0-Km.1470+739

03/23/12 X 27.407 145 C 0.443 0.133 0.196 - - - 77.20 83.80% Satisfactory

Equi-Parco Construction Company 14332

Rehab./Replacement of Mandulog Bridge I, Bridge: ID: B00606MN, along Highway Secondary Diversion Rd., Rd.

ID: R01497MN Sect. ID: S00961 MN Location: K1522+(-484) Const. of Two (2) Lanes 240 m. Concrete Bridge with 6

Spaces @ 40 m. per Span

11/26/12 X 137.639 210 O 0.335 0.300 0.150 0.030 0.040 0.033 88.80 -

Equi-Parco Construction Company 14332Widening/Conc. of Butuan City-Cagayan de Oro-Iligan City

Rd. (Opol-Laguindingan Airport Sect.) Km.1466+282.80-Km.1467+282.80

11/23/12 X 83.789 330 O 0.366 0.246 0.150 0.030 0.045 0.050 88.70 -

Equi-Parco Construction Company 14332 Rehab./Reconst./Strengthening of Bridges along Nat'l Rds., Kibaluyot Bridge along BCIR 11/22/12 X 26.234 330 O 0.400 0.200 0.150 0.030 0.045 0.033 85.80 -

Equi-Parco Construction Company 14332 Cons. of Slope Protection at Iponan River (Downstream of Iponan Bridge I and II) Bulua side along BCIR, Phase I 11/24/12 X 15.412 153 O 0.300 0.300 0.150 0.030 0.040 0.033 85.30 -

Equi-Parco Construction Company 14332 Const. of Cagayan de Oro Coastal Rd. (By-Pass Rd.), inc. ROW 11/24/12 X 137.944 269 O 0.371 0.227 0.150 0.030 0.040 0.033 85.10 -

Equi-Parco Construction Company 14332 Cagayan de Oro River Basin 11/24/12 X 46.077 210 O 0.270 0.300 0.150 0.030 0.040 0.033 82.30 -

Equi-Parco Construction Company 14332Rehab. of Damaged Paved Nat'l Rd. along Daang Maharlika Rd. (Surigao-Agusan Sect.) a. Kicharao-Cabadbaran Sect.

b. Luna Bad-as Sect.11/20/12 XIII 111.377 120 C 0.476 0.200 0.300 - - - 97.60 94.36%

Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page83

Page 84: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Equi-Parco Construction Company 14332 Repair/Rehab./Strengthening of Bridges along Nat'l Rds., Kibaluyot Bridge along BCIR 08/14/12 X 26.234 330 O 0.343 0.300 0.150 0.030 0.045 0.033 90.10 -

Equi-Parco Construction Company 14332 Completion/Continuation of Cagayan de Oro City 3rd Bridge & Access Rd. 08/24/12 X 340.968 600 C 0.458 0.133 0.300 - - - 89.10 87.24%

Satisfactory

Equi-Parco Construction Company 14332Rehab./Reconst./Upgrading of Butuan City-Cagayan de Oro City-Iligan City Rd., a)Km.1490+664-Km.1492+324 &

b)Km.1496+398-Km.1499+63108/16/12 X 32.503 210 C 0.326 0.200 0.300 - - - 82.60 85.12%

Satisfactory

Equi-Parco Construction Company 14332 Flood Control along Butuan City-Malaybalay Rd., Brgy. Diego Silang Sect. 08/21/12 XIII 18.560 210 C 0.463 0.200 0.300 - - - 96.30 94.38%

Very Satisfactory

Equi-Parco Construction Company 14332Rehab. of Damaged Paved Nat'l Rd. along Daang Maharlika

Road (Surigao-Agusan Section) a.Kitcharao-Cabadbaran Sect.; b.Luna Bad-as Sect.

08/07/12 XIII 110.082 120 O 0.354 0.300 0.150 0.030 0.055 0.033 92.20 -

Equi-Parco Construction Company 14332 Asphalt Overlay of Daang Maharlika (Surigao-Agusan Sect.) Km.1172+107.20-Km.1174+000 08/07/12 XIII 19.728 89 C 0.426 0.200 0.300 - - - 92.60 90.26%

Very Satisfactory

Equi-Parco Construction Company 14332 Caminawit Port Development Project 11/13/13 DOTC 73.313 270 O 0.393 0.300 0.150 0.030 0.028 0.050 95.12 -

Equi-Parco Construction Construction / Gicar Construction

(JV)JV-08-062 Conc. of Dinagat Island Road Network, Dinagat-Loreto

Road (Basilisa-Albor Section) 06/02/10 XIII 161.113 447 O 0.283 0.300 0.150 0.030 0.055 0.033 85.10 -

EQUI-PARCO CONSTRUCTION CORPORATION 14332

Preventive Maintenance along Daang Maharlika Rd. (Agusan - Davao Sect.), K1245+450 - K1245+617, K1259+463 - K1259+527, K1272+000 - K1273+040, K1288+960 - K1290+849, K1297+960 - K1298+960

8/6/2014 XIII 58.655 120 OG 0.370 0.222 0.150 0.030 0.051 0.050 87.30 -

EQUI-PARCO CONSTRUCTION CORPORATION 14332

Road Upgrading (Gravel to Concrete) of NRJ Bayugan - Calaitan Road, K1286+720 - K1287+000, K1284+279 -

K1286+720, K1291+200 - K1291+5008/6/2014 XIII 66.890 240 OG 0.392 0.292 0.150 0.030 0.032 0.050 94.60 -

EQUI-PARCO CONSTRUCTION CORPORATION 14332 Improvement of Drainage Facilities along Butuan City -

Malaybalay Road (Montilla Boulevard Section) 8/15/2014 XIII 17.007 220 C 0.435 0.200 0.300 93.50 91.52% Very Satisfactory

EQUI-PARCO CONSTRUCTION CORPORATION 14332

Rehab./Reconstruction/Replacement/Retrofitting of Pandanon Bridge along Daang Maharlika (Surigao -

Agusan Road)8/5/2014 XIII 17.007 252 OG 0.354 0.249 0.150 0.030 0.046 0.050 87.90 -

Equi-Parco/Adfil Joint Venture JV-09-023 Conc./Impv't. of Tiniwisan-Maguinwall Rd. (Lemon-Pigdanlan Section) 02/23/10 XIII 335.031 51 O 0.370 0.240 0.150 0.030 0.050 0.050 89.00 -

ERCOBAL CONSTRUCTION CORP. 32812

Rehab./Reconst./Upgrading of Damaged Paved National Roads including Drainage Based on Pavement

Management System/Highway Development and Management 4 (HDM-4) along Nicanor Padilla St.

11/24/2014 NCR 7.161 201 O 0.361 0.300 0.150 0.008 0.041 0.017 87.70% 87.70% Satisfactory

Eric Van P. Sesbreno Construction 26243 Const. of Sta. Fe Flood Control along Nueva Vizcaya-Pangasinan Rd., K0216+980-K0217+300, Baracbac Sect. 09/26/13 II 9.506 120 C 0.402 0.122 0.300 - - - 82.40 82.40%

Satisfactory

Eric Van P. Sesbreño Construction 26243 Restoration of Cupas River Control, Calaocan-Macate Section 8/15/2014 II 15.565 120 C 0.424 0.133 0.300 85.70 85.70%

SatisfactoryEric Van P. Sesbreno Construction

/ C.T. Leoncio Construction and Trading (JV)

JV-11-340 Replacement/Const. of Burnay Bridge & Approaches inc. Const. of Detour Bridge 08/05/13 CAR 19.910 253 O 0.330 0.300 0.000 0.030 0.050 0.033 74.30 -

Eric Van P. Sesbreno Construction / C.T. Leoncio Construction and

Trading (JV)JV-11-340 Replacement/Const. of Burnay Bridge & Approaches inc.

Const. of Detour Bridge 03/17/13 CAR 19.911 253 O 0.364 0.300 0.000 0.030 0.061 0.033 78.80 -

Eric Van P. Sesbreno Construction / C.T. Leoncio Construction and

Trading (JV)JV-11-339

Rd. Upgrading (Gravel to Paved), Nueva Vizcaya-Pangasinan Rd., K0216+250-K0221+091.08 w/ exception,

Baracbac Sect.03/21/13 II 47.661 277 C 0.450 0.137 0.300 - - - 88.70 87.56%

Satisfactory

ES De Guzman Construction 17494 Const. of NVGCHS, 6CL,3-Storey Building, Bontal Annex 08/28/09 II 1.604 90 O 0.325 0.240 0.150 0.030 0.018 0.050 81.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page84

Page 85: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

ESD CRUZ CONSTRUCTION & SUPPLY 32368

Construction and Maintenance of Bridges along National Roads/Major Repair, Maintenance of Existing Permanent Bridges at Camparanga Bridge along Catarman-Laoang

Road

10/30/2014 VIII 1.419 34 C 0.458 0.133 0.300 - - - 89.10% 89.10% Very Satisfactory

ESD CRUZ CONSTRUCTION & SUPPLY 32368

Road Upgrading (Gravel to Paved) basd on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road Standard (HDM-4 Project Analysis), Intermittent

Sections, National Secondary, San Roque-Cababtoan Old Road, under Cluster Roads-2014-01 K0773+803 -

K0774+499, and K0775+506 - K0775+606

10/20/2014 VIII 14.038 95 C 0.349 0.200 0.300 - - - 84.90% 84.90% Satisfactory

ESD CRUZ CONSTRUCTION & SUPPLY 32368

Construction and Maintenance of Bridges along National Roads/Major Repair, Maintenance of Existing Permanent

Bridges at Cabacongognan Bridge along Catarman-Laoang Road

10/20/2014 VIII 1.417 34 C 0.465 0.133 0.300 - - - 89.80% 89.80% Very Satisfactory

ESER ENTERPRISES (Formerly: Eser Enterprises - Burot) 23902 Completion of Road at Sta. Ines Centro 8/6/2014 III 1.987 45 C 0.471 0.133 0.300 90.40 90.40%

Very Satisfactory

ESN CONSTRUCTION & TRADING 32720 Construction of One Storey One Classroom School Building, Mabolo ES 11/24/2014 III 1.078 60 C 0.500 0.133 0.300 - - - 93.30% 93.30%

Very Satisfactory

ESN Construction & Trading 32720 Const. of Two (2) Storey, Two (2) CL Sch. Bldg. Masagana H/S 03/19/13 III 2.284 90 C 0.324 0.200 0.300 - - - 82.40 82.40%

Satisfactory

ESR CONSTRUCTION AND SUPPLIES 10451

Asphalt Overlay/Re-blocking along Lanao-Pagadian-Zamboanga City Road, Intermittent Sections, Buug,

Zamboanga Sibugay a. K1742+(-594) - K1724+347 Boyugan Section, Buug; b. K1725+031 - K1725+941 Boyugan Section, Buug; c. K1726+246 - K1726+609 Basalem

Section, Buug

10/25/2014 IX 20.938 90 C 0.428 0.133 0.300 - - - 86.10% 86.10% Satisfactory

ESR CONSTRUCTION AND SUPPLIES 10451 Widening of Lanao-Pagadian-Zamboanga City Road

K1657+000 - K1658+600 10/26/2014 IX 28.658 120 C 0.340 0.200 0.300 - - - 84.00% 84.00% Satisfactory

ESR CONSTRUCTION AND SUPPLIES 10451 Restoration of Slope Protection at Agusan Canyon Bridge,

along S.H. - Manolo Fortich - Libona - Indahag Road 10/21/2014 X 14.040 149 O 0.342 0.259 0.150 0.010 0.042 0.033 83.60% 83.60% Satisfactory

ESR Construction and Supplies 10451Rehab./Reconst./Strengthening of Bridges along National Roads, Guintolan Brudge Crossing Sta Clara-Sandayong

Road, Km. 1782+0177 - Km. 1782+0478/8/2014 IX 21.915 510 C 0.442 0.200 0.300 94.20 89.01%

Very Satisfactory

ESR Construction and Supplies 10451 Construction/Rehabilitation of Tukuran Flood Control 8/13/2014 IX 14.896 170 OG 0.289 0.295 0.150 0.030 0.055 0.050 86.90 -

ESR Construction and Supplies 10451

Assets Preservatin of National Roads Generated from Pavement Management System/Highway Development and

Management - 4 (HDM-4) Rehab./Reconst./Upgrading of Damaged Paved National Roads, Intermittent Section,

Sindangan, Sindangan-Liloy Road K1988+000 K1991+020

7/25/2014 IX 29.285 189 C 0.366 0.200 0.300 86.60 86.60% Satisfactory

ESR Construction and Supplies 10451

Assets Preservation of National Roads Generated from Pavement Management System/Highway Development and

Management - 4(HDM-4) Rehab./Reconst./Upgrading of Damaged Paved National Roads, Intermittent Sections, Eastern Bobongan-Sominot-Midsalip-Dumingag Road

K1643+951 - K1614+000

7/25/2014 IX 47.861 180 C 0.363 0.200 0.300 86.30 86.30% Satisfactory

ESR Construction and Supplies 10451

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies Traffic Benchmark for Road Upgrading to Paved

Road Standard (HDM-4 Project Analysis Crossing Sta. Clara-Sandayong Road Km. 1800+920 - Km. 1802+000

8/7/2014 IX 25.703 170 C 0.296 0.200 0.300 79.60 86.26% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page85

Page 86: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

ESR Construction and Supplies 10451Improvement/Upgrading (Gravel to Concrete) of Rizal-

Dakak-Dapitan Coastal Loop Road and Access to Piñahon Island, Sta. 1825_500,00 - Sta. 1828+620.00

7/25/2014 IX 108.756 394 C 0.345 0.200 0.300 84.50 84.50% Satisfactory

ESR Construction and Supplies 10451

Asset Preservation of National Roads Generated (HDM-4) Rehab./Reconst./Upgrading of Damaged Paved National Roads, Intermittent Section, Liloy-Ipil Road K1991+020 -

K1992+397

7/25/2014 IX 23.050 179 C 0.331 0.200 0.300 83.10 83.10% Satisfactory

ESR Construction and Supplies 10451

Improvement/Upgrading (Gravel to Concrete) of Lanao-Pagadian City-Zamboanga City Road, Pob. Aurora-

Cabilinan Section Zamboanga del Sur, Sta. 1632+760 to Sta. 1636+880 w/ exception

7/25/2014 IX 84.035 258 C 0.330 0.200 0.300 83.00 83.00% Satisfactory

ESR Construction and Supplies 10451 Rd. Upgrading (Gravel to Paved) Crossing Sta. Clara-Sandayong Rd., Km.1800+920-Km.1802+000 08/09/13 IX 24.653 170 O 0.371 0.300 0.150 0.020 0.033 0.033 90.70 -

ESR Construction and Supplies 10451 Impv't./Concrete Paving of Shoulders, Dumalinao-Margosatubig Rd. 08/16/13 IX 135.589 402 C 0.382 0.200 0.278 - - - 86.00 89.72%

Very Satisfactory

ESR Construction and Supplies 10451

Rehab./Reconst./Strengthening of Bridges along Nat'l Rds. Guintoloan Bridge along Nat'l Rds' Guintoloan Bridge

Crossing Sta. Clara-Sandayong Rd., Km.1782+017-Km.1782+047

08/09/13 IX 21.915 510 O 0.357 0.268 0.150 0.024 0.033 0.033 86.50 -

ESR Construction and Supplies 10451 Rd pgrading (Gravel to Paved) Int. Sect., Sindangan-Siayan-Dumingag-Mahayag Rd., K1683+500-K1685+000 08/17/13 IX 35.886 259 O 0.323 0.300 0.150 0.018 0.037 0.033 86.10 -

ESR Construction and Supplies 10451 Reconst./Upgrading of Damaged Paved Nat'l Rds. Int. Sect., Liloy-Ipil Rd., K1991+020-K1992+397 08/12/13 IX 23.175 179 C 0.327 0.200 0.300 - - - 82.70 85.70%

Satisfactory

ESR Construction and Supplies 10451 Rd. Upgrading (Gravel to Paved) Int. Sect. Sindangan-Siayan-Dumingag-Mahayag Rd., K1678+150-K1679+817 08/17/13 IX 46.795 186 O 0.353 0.254 0.150 0.012 0.033 0.050 85.20 -

ESR Construction and Supplies 10451 Upgrading/Concrete Paving of Sindangan-Siayan-Dumingag-Mahayag Rd. 08/23/13 IX 127.987 349 C 0.283 0.200 0.300 - - - 78.30 84.42%

Satisfactory

ESR Construction and Supplies 10451Prev. Maint./Asphalt Overlay of Lanao-Pagadian-Zamboanga City Rd., (Basalem-Pob. Bulig Sect.),

Km.1726+308.65-Km.1729+17008/14/13 IX 28.261 80 C 0.400 0.133 0.300 - - - 83.30 84.38%

Satisfactory

ESR Construction and Supplies 10451Impv't./Upgrading (Gravel to Paved) of Rizal to Dipolog

Loop Rd. Guimputlan-Tag-ulo Sect. Sta.1852+377-Sta.1853+960 w/ exceptions

08/21/13 IX 62.890 330 C 0.295 0.200 0.300 - - - 79.50 83.22% Satisfactory

ESR Construction and Supplies 10451

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. Int. Sect. Sindangan-Liloy Rd. Km.1958+750-Km.1960+503 Re: Upgrading (Asphalt Paved to Concrete Paved) along

Liloy-Ipil Rd. Km.1988+000-Km.1991+020

08/12/13 IX 29.101 179 O 0.325 0.289 0.111 0.030 0.042 0.033 83.00 -

ESR Construction and Supplies 10451 Imprv't./Concrete Paving of Shoulders Dumalinao-Margosatubig Rd. 03/19/13 IX 135.589 402 O 0.342 0.300 0.150 0.030 0.050 0.050 92.20 -

ESR Construction and Supplies 10451Road Upgrading (Gravel to Conc.) Int. Sect., Jct. Aurora-Ozamis City Road, K1640+000-K1641+830, Pasingkalan,

Ramon Magsaysay03/21/13 IX 40.356 280 C 0.437 0.133 0.300 - - - 87.00 90.06%

Very Satisfactory

ESR Construction and Supplies 10451Widening/Concrete Paving of Jct. Polo-Dapitan Park Rd.,

Dapitan City, Sta.1825+100.00-Sta.1827+497.00 w/ exception

03/22/13 IX 25.870 257 C 0.442 0.133 0.300 - - - 87.50 88.40% Satisfactory

ESR Construction and Supplies 10451 Reconst./Upgrading of Damaged Paved Nat'l Rds. Int. Sect., Liloy-Ipil Rd., K1991+020-K1992+397 03/15/13 IX 23.050 109 O 0.367 0.240 0.150 0.030 0.040 0.050 87.70 -

ESR Construction and Supplies 10451 Upgrading (Asphalt to Concrete) of Liloy-Ipil Rd., Gatas Sect. along Dipolog City-Zamboanga City Rd. 03/15/13 IX 65.988 330 C 0.436 0.133 0.300 - - - 86.90 86.45%

Satisfactory

ESR Construction and Supplies 10451 Widening/Upgrading/Concrete Paving of Jct. Tiguma-Pagadian Airport Rd., Sta.1663+060-Sta.1664+300 03/21/13 IX 44.465 291 C 0.491 0.133 0.300 - - - 92.40 86.34%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page86

Page 87: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

ESR Construction and Supplies 10451 Rd. Upgrading (Gravel to Paved) Int. Sect., Sindangan-Siayan-Dumingag-Mahayag Rd., K1683+500-K1685+000 03/21/13 IX 34.586 110 O 0.358 0.225 0.150 0.030 0.043 0.050 85.60 -

ESR Construction and Supplies 10451Prev. Maint./Asphalt Overlay of Lanao-Pagadian-Zamboanga City Rd., (Basalem-Pob., Bulig Sect.),

Km.1726+308.65-Km.1729+17003/18/13 IX 28.261 80 O 0.400 0.200 0.150 0.030 0.038 0.033 85.10 -

ESR Construction and Supplies 10451Road Upgrading (Gravel to Conc.) Int. Sect., Lanao-

Pagadian-Zamboanga City Rd. K1644+450-K1646+600, Tintongan

03/21/13 IX 47.220 300 C 0.432 0.133 0.300 - - - 86.50 85.00% Satisfactory

ESR Construction and Supplies 10451 Rd. Upgrading (Gravel to Conc.) Int. Sect., Lanao-Pagadian-Zamboanga City Rd., K1632+949 - K1635+119, Cabilinan 03/21/13 IX 47.898 255 C 0.414 0.133 0.300 - - - 84.70 84.76%

Satisfactory

ESR Construction and Supplies 10451Rehab./Reconst./Strengthening of Bridges along Nat'l Rds.

Guintoloan Bridge Crossing Sta. Clara-Sandayong Rd., Km.1782+017-Km.1782+047

03/15/13 IX 21.915 360 O 0.373 0.240 0.123 0.030 0.047 0.033 84.60 -

ESR Construction and Supplies 10451 Rd. Upgrading (Gravel to Paved) Int. Sect. Sindangan-Siayan-Dumingag-Mahayag Rd., K1678+150-K1679+817 03/21/13 IX 46.795 126 O 0.367 0.225 0.150 0.030 0.038 0.033 84.30 -

ESR Construction and Supplies 10451 Dumingag-Siayan Road (Road Upgrading Gravel to Concrete) 03/06/10 IX 46.778 300 O 0.295 0.300 0.150 0.030 0.047 0.033 85.50 -

ESR Construction and Supplies 10451 Completion of Kagawasan, Dimataling-Pitogo Provincial Road Sta. 0+000 - Sta. 3+540 with exception 03/04/10 IX 27.575 263 O 0.300 0.281 0.150 0.030 0.042 0.050 85.30 -

ESR Construction and Supplies 10451 Dapitan-Dakak Rd. (Taguilon Sect.) Phase V 06/13/10 IX 55.050 300 O 0.392 0.256 0.150 0.030 0.040 0.033 90.10 -

ESR Construction and Supplies 10451 Dapitan-Dakak Rd. (Taguilon Sect.), Phase V, Dapitan City 08/25/10 IX 55.050 300 O 0.369 0.240 0.150 0.030 0.047 0.050 88.60 -

ESR Construction and Supplies 10451Road Upgrading (Gravel to Concrete) Dipolog-Punta-

Dansullan-SergionOsmeña, Zambo. Del Norte-Sur Bdry., Km.1876+000-Km.1877+000, De Venta Perla Section

06/08/09 IX 18.674 120 O 0.390 0.238 0.150 0.010 0.037 0.050 87.50 -

ESR Construction and Supplies 10451 Road Upgrading (Gravel to Concrete) , Jct. Blancia-Molave-Josefina Road 06/04/09 IX 46.470 300 O 0.342 0.240 0.150 0.030 0.051 0.050 86.30 -

ESR Construction and Supplies 10451 Conc./Widening of Jct. Dumalinao-Margosatubig Intermittent Section 09/09/09 IX 18.073 247 O 0.372 0.300 0.150 0.030 0.040 0.033 92.50 -

ESR Construction and Supplies 10451 Rehab./Impvt. of Dipolog-Punta-Dansullan-Sergio Osmeña Road (De Venta Perla-Poblacion Alto Section) 09/14/09 IX 28.120 210 O 0.360 0.300 0.150 0.030 0.045 0.033 91.80 -

ESR Construction and Supplies 10451Reblocking/Asphalt Overlaying of Junction Dumalinao-

Margosatubig Road, Margosatubig Section, Sta. 1714+920.00-Sta. 1719+739.10 with exception

09/10/09 IX 20.215 168 O 0.384 0.300 0.100 0.030 0.040 0.033 88.70 -

ESR Construction and Supplies 10451

Roads to Address Critical Bottleneck: Widening of Pagadian-Zamboanga City Road K1675+(-31)-K1678+52 Re-

Aligned to Widening of Pagadian-Zamboanga City Road K1675+980-K1676+692

03/26/12 IX 18.340 105 O 0.321 0.300 0.150 0.030 0.043 0.050 89.40 -

ESR Construction and Supplies 10451Asphalt Overlay/Repair and Rehab. of Lanao-Pagadian-

Zamboanga City Rd. (Monching Sect.) Km.1767+670-Km.1777+000 w/ exception

03/21/12 IX 4.824 100 C 0.323 0.200 0.300 - - - 82.30 88.70% Satisfactory

ESR Construction and Supplies 10451 Rehab./Impvt. of Dimataling-Tabina Prov'l Rd. Sta. 0+000-Sta.11+602.75 w/ exception 03/26/12 IX 101.168 765 C 0.409 0.133 0.300 - - - 84.20 84.82%

Satisfactory

ESR Construction and Supplies 10451Rd. Upgrading (Gravel to Paved) along Imelda-Bayog-

Kumalarang-Lapuyan-Margosatubig Rd. (Brgy. San Jose Sect.)

11/24/12 IX 47.977 285 C 0.432 0.133 0.300 - - - 86.50 89.05% Very Satisfactory

ESR Construction and Supplies 10451 Upgrading/Concrete Paving of Sindangan-Siayan-Dumingag-Mahayag Rd. 11/28/12 IX 127.987 349 O 0.304 0.292 0.150 0.030 0.059 0.050 88.50 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page87

Page 88: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

ESR Construction and Supplies 10451Rd. Upgrading (Gravel to Concrete) IS, Jct. Blancia-

Molave-Josefina Rd., K1693+000-K1685+000, Bag-ong, Ariosa

11/23/12 IX 43.815 240 C 0.335 0.200 0.300 - - - 83.50 86.14% Satisfactory

ESR Construction and Supplies 10451Impvt./Upgrading (Gravel to Paved) of Rizal to Dapitan City

Coastal Loop R., Guimputian-Tag-ulo Sect., Sta.1852+377.00-Sta.1853+960.00 w/ exceptions

11/30/12 IX 62.890 255 O 0.365 0.225 0.150 0.030 0.043 0.033 84.60 -

ESR Construction and Supplies 10451Rd. Upgrading (Gravel to Concrete) IS, Sindangan-Siayan-

Dumingag (Mahayag-Dumingag) Mahayag-Ditulan, K1677+496-K1679+000

11/23/12 IX 32.997 240 C 0.375 0.133 0.300 - - - 80.80 83.14% Satisfactory

ESR Construction and Supplies 10451 Widening/Upgrading/Concrete Paving of Jct. Tiguma-Pagadian Airport Rd., Sta.1663+060-Sta.1664+300 11/23/12 IX 44.465 216 O 0.234 0.300 0.150 0.030 0.059 0.050 82.30 -

ESR Construction and Supplies 10451Rd. Upgrading (Gravel to Paved) Along Imelda-Bayog-

Kumalarang-Lapuyan-Margosatubig Rd. (Brgy. San Jose Sect.)

08/28/12 IX 45.590 240 O 0.367 0.300 0.148 0.030 0.040 0.033 91.80 -

ESR Construction and Supplies 10451

Road to address Critical Bottleneck: (Widening of Pagadian-Zamboanga City R.) K1675+(-31)-K1678+52, re-

aligned to (Widening of Pagadian-Zamboanga City Rd. K1675+980-K1676+692

08/16/12 IX 17.696 135 C 0.432 0.133 0.300 - - - 86.50 88.24% Satisfactory

ESR Construction and Supplies 10451 Road Upgrading (Gravel to Concrete) IS, Jct. Blancia-Molave-Josefina Rd, K1693+000-K1685+000, Bagon Ariosa 08/18/12 IX 42.835 180 O 0.388 0.240 0.150 0.030 0.038 0.033 87.90 -

ESR Construction and Supplies 10451 Impvt./Upgrading (Gravel to Paved) of Rizal to Dapitan City Coastal Loop Rd., Guimputian-Tag-ulo Sect. 08/25/12 IX 62.890 225 O 0.394 0.226 0.150 0.022 0.043 0.033 86.80 -

ESR Construction and Supplies 10451Assets Preservation of Nat'l Rds,. Rehab./Reconst. Of Damage Paved Nat'l Rds. (IS), Liloy-Ipil Rd. K1983+000-

K1986+000 and K1989+847-K1990+21208/27/12 IX 17.696 88 C 0.433 0.133 0.300 - - - 86.60 86.48%

Satisfactory

ESR Construction and Supplies 10451 Rd. Upgrading (Gravel to Concrete) IS, Sindangan-Siayan-Dumingag (Mahayag-Dumingag) Mahayag-Ditulan 08/16/12 IX 32.148 180 1st 0.359 0.232 0.150 0.030 0.043 0.033 84.70 -

ESR Construction and Supplies 10451 Upgrading/Concrete Paving of Aurora-Ozamis Rd., Campo 1 & 2 03/21/13 IX 47.766 257 C 0.444 0.133 0.300 - - - 87.70 87.70%

Satisfactory

ETM Construction 16285 Const. of Rd. @ Sitio Daing, Duale 08/02/13 III 2.906 129 C 0.424 0.133 0.300 - - - 85.70 85.70% Satisfactory

Euluz Construction and Supply 32080 Prev. Maint. Pulilan Railroad Station Km.44+(-121)-Km.44+840 & Km.44+840-Km.44+970 08/14/13 III 2.686 23 C 0.478 0.133 0.000 - - - 61.10 61.10%

Poor

EUS CONSTRUCTION 21878

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Roads Including Drainage Based on

Pavement Management System/Highway Development, MGT-4 (HDM)-4 Intermittent Section Arterial Road Daang Maharlika K0303+000-K0305+865 Daang Maharlika (LZ)

K0303+000-K0305+865

11/8/2014 V 39.698 150 C 0.482 0.133 0.300 - - - 91.50% 91.50% Very Satisfactory

Everlast Construction 2364 Construction of Multi-Purpose Pavement @ Brgy. Pasonanca (Mayor Climaco Park) 8/6/2014 IX 9.175 571 C 0.485 0.133 0.300 91.80 88.26%

Satisfactory

Everlast Construction 2364 Const. of Multi-Purpose Pvmt. @ Brgy. Pasonanca (Mayor C. Climaco Park) 08/06/13 IX 9.175 570 O 0.355 0.300 0.110 0.020 0.037 0.033 85.50 -

Everlast Construction 2364 Const. of Multi-Purpose Pvmt. at Brgy. Pasonanca (Mayor C. Climaco Park) 03/11/13 IX 9.175 315 O 0.384 0.240 0.150 0.030 0.037 0.050 89.10 -

Everlast Construction 2364 Const. of Zamboanga City Schools Division Office 09/01/09 IX 14.182 305 O 0.370 0.300 0.150 0.030 0.035 0.033 91.80 -

Everlast Construction 2364 Rehab. of MPB, Zamboanga City Medical Center Bldg. I (Emergency Room) 03/20/12 IX 5.650 165 C 0.477 0.133 0.300 - - - 91.00 89.04%

Very Satisfactory

Everlast Construction 2364 Const. of MPB Western Mindanao State University 03/20/12 IX 8.442 180 C 0.449 0.133 0.300 - - - 88.20 87.64% Satisfactory

Everlast Construction 2364 Const. of Multi-Purpose Pavement at Brgy. Pasonanca (Mayor C. Climaco Park) 11/19/12 IX 9.175 315 O 0.339 0.224 0.150 0.023 0.045 0.050 83.10 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page88

Page 89: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Everlast Construction 2364 Const. of Multi-Purpose Pavement at Brgy. Pasonanca (Mayor C. Climaco Park) 08/14/12 IX 8.699 255 O 0.374 0.231 0.150 0.030 0.041 0.033 85.90 -

Excelssius Engr'ng. Services & C.T. Leoncio Construction &

Trading JV Construction of 3-Storey School Bldg. 07/10/12 NHA 22.132 180 O 0.395 0.269 0.143 0.030 0.056 0.050 94.30 -

Excelssius Engr'ng. Services & C.T. Leoncio Construction &

Trading JV Construction of 3-Storey School Bldg. 05/08/12 NHA 22.132 180 O 0.391 0.264 0.150 0.024 0.058 0.050 93.69 -

EXFE Construction and Trading Lomboy-Danak Lauangcupang SIP 08/15/15 NIA 15.801 176 C 0.450 0.082 0.300 - - - 83.25 83.25% Satisfactory

Ezjones Construction Inc. 34462 Const. of 2-Storey, 2-CL SB San Jose ES 08/10/13 VIII 2.428 180 O 0.380 0.300 0.095 0.030 0.058 0.000 86.30 -

Ezjones Construction Inc. 34462 Const. of 2-Storey, 2-CL SB San Isidro ES 08/10/13 VIII 2.299 170 O 0.372 0.300 0.059 0.030 0.064 0.025 85.00 -

F & J GENERAL CONSTRUCTION AND SUPPLY CORPORATION 31963

Preventive Maintenance Based on Pavement Management System/HDM-4 (Intermittent Sections), Surigao-Davao

Coastal Road K1462+143 - K1462+42310/24/2014 XIII 2.644 60 C 0.393 0.133 0.300 - - - 82.60% 82.60%

Satisfactory

F & J General Construction and Supply Corporation 31963

Repair/Rehab./Impvt. along Pandanon-Magallanes Rd., Cabadbaran City & Magallanes Km.1217+784-Km.1225+314

w/ exceptions, Brgy. Soriano-La Union & Caloc-an03/19/12 XIII 4.759 45 C 0.417 0.133 0.300 - - - 85.00 85.00%

Satisfactory

F. Casalme Construction & Supply 33657 Const. of 2-Storey, 2-Classroom @ Lemery E/S 07/30/13 IVA 2.237 120 C 0.476 0.133 0.300 - - - 90.90 90.90% Very Satisfactory

F. Gurrea Construction 6995 Iloilo City PCG Annex Building Development Project 07/23/13 DOTC 10.116 240 O 0.347 0.300 0.150 0.030 0.031 0.050 90.80 -

F. Gurrea Construction 6995 Barbaza Port Development Project 07/24/13 DOTC 10.999 150 O 0.333 0.300 0.150 0.030 0.038 0.050 90.10 -

F. Gurrea Construction Inc. 6995 Barbaza Port Development Project 10/16/13 DOTC 10.999 150 C 0.455 0.200 0.300 - - - 95.50 92.20% Very Satisfactory

F. GURREA CONSTRUCTION, INC 6995 Extension of RC Wharf, ICPC 11/24/15 PPA 271.600 570 O 0.360 0.294 0.150 0.030 0.070 0.050 95.44 -

F. GURREA CONSTRUCTION, INC. 6995 Iloilo City PCG District Building Project 02/19/14 DOTC 10.116 240 C 0.432 0.200 0.300 - - - 93.20 91.50% Very Satisfactory

F. Gurrea Construction, Inc. 6995 Maayon CIP Package 2 ( Canal Structures) 02/7-10/12 NIA 14.741 320 O 0.316 0.258 0.150 0.024 0.051 0.050 84.90 -F. Gurrea Construction, Inc. 6995 Const. of Maayon CIP (Package 1- Diversion Works) 04/13/13 NIA 60.137 540 O 0.374 0.243 0.116 0.024 0.056 0.033 84.60 -

F. GURREA CONSTRUCTION, INCORPORATED 6995 Widening of Iloilo East Coast-Estancia Wharf Road

K0179+040 - K0180+340 10/29/2014 VI 30.727 224 O 0.368 0.222 0.150 0.030 0.054 0.033 85.70% 85.70% Satisfactory

F. Gurrea Construction, Incorporated 6995 Reconst. of Embarcadero Bridge, Km. 0247+160.00 08/21/13 VI 46.445 270 C 0.460 0.133 0.300 - - - 89.30 89.30%

Very SatisfactoryF. Gurrea Construction,

Incorporated 6995 Completion of Anahawon 12/01/08 VI 9.423 180 O 0.381 0.223 0.000 0.022 0.043 0.067 73.60 -

F. Gurrea Construction, Incorporated 6995

Conc. of Oton-Mambog-Caboloan-Abilay-SanJose-San Miguel Road leading to Iloilo International Airport Km.

11+436.25-Km. 15+96.25 w/ exception05/25/09 VI 57.850 462 O 0.295 0.300 0.150 0.030 0.065 0.050 89.00 -

F. Gurrea Construction, Incorporated 6995

Conc. of Oton-Mambog-Caboloan-Abilay-San Jose-San Miguel Road leading to Iloilo International Airport Km.

11+436.25-Km.15+96.25 w/ exception09/10/09 VI 57.894 467 O 0.314 0.300 0.150 0.030 0.060 0.050 90.40 -

F. Gurrea Construction, Incorporated 6995 Conc. of Iloilo East West Road, San Rafael-Passi Section 09/06/10 VI 18.915 210 O 0.375 0.240 0.150 0.030 0.037 0.033 86.50 -

F. Gurrea Construction, Incorporated 6995 Completion of Valderama Bridge and Approaches 03/20/12 VI 54.403 180 C 0.441 0.133 0.300 - - - 87.40 89.44%

Very Satisfactory

F. Gurrea Construction, Incorporated 6995

Road Upgrading (Gravel to Paved) of Oton-Buray-Sta. Monica-San Antonio-San Miguel Road, K0018+076-

K0019+12003/19/12 VI 14.670 207 C 0.303 0.200 0.300 - - - 80.30 81.68%

Unsatisfactory

F. Jimenez Construction and Supply 34796 Replacement/Rehab./Strengthening of Overhead Bridge

along Daang Maharlika 08/06/13 IVA 4.555 90 C 0.500 0.133 0.300 - - - 93.30 93.30% Very Satisfactory

F.A Asprer Construction 21579 Dipolog Airport Development Project (Construction o Terminal Building) 11/10/10 DOTC 12.977 180 O 0.361 0.300 0.150 0.020 0.035 0.017 88.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page89

Page 90: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

F.A Sison Trading and Construction 27150 Rehab./Upgrading of Damaged National Roads (PMS/HDM-

4) Mindoro Oriental/Occidental East Coastal Road 08/27/10 IVB 7.522 200 O 0.361 0.055 0.150 0.030 0.055 0.033 68.40 -

F.A. Asprer Construction 21579 Conc. of Brgy. Road @ Laoang 11/23/12 III 7.242 75 O 0.305 0.300 0.150 0.030 0.030 0.033 84.80 -F.A. Sison Trading and

Construction 13725 Const./Completion of Rizal Elem. Sch., Tayuman St. 03/20/13 NCR 4.210 75 C 0.475 0.106 0.300 - - - 88.10 88.10% Satisfactory

F.A. Torres Construction/Three W Builders, Inc. Joint Venture JV-11-254 Replacement of Tepassy Bridge along Bulalacao-San Jose

Jct. Mapaya Rd., Brgy. Mapaya 11/25/12 IVB 9.498 240 C 0.486 0.200 0.113 - - - 79.90 83.02% Satisfactory

F.A. Torres Construction/Three W Builders, Inc. Joint Venture JV-11-254 Replacement of Tepassy Bridge along Bulalacao-San Jose

Jct. Mapaya Rd., Brgy. Mayapa 08/08/12 IVB 9.498 210 O 0.372 0.295 0.100 0.030 0.050 0.017 86.40 -

F.B. Bantales Engineering Construction 31045 Clustered Restoration Proj., Bokod & Tuba 03/13/13 CAR 7.338 105 O 0.140 0.210 0.150 0.030 0.035 0.033 59.80 -

F.F Cruz & Co., Inc. / Filipinas (Prefab. Bldg.) System, Inc. (JV) JV-08-138 Conc. of Mindoro Oriental East Coastal Road (Intermittent

Sections), Mansalay-Bdry. Mindoro Occidental Sect. 09/05/09 IVB 192.400 562 O 0.363 0.300 0.150 0.030 0.042 0.033 91.80 -

F.F. Diaz III Construction 34636 Replacement of Lagangeo Bridge No. 2 along Mt. Province-Cagayan via Tabuk-Enrile Rd. 03/16/13 CAR 5.181 190 C 0.447 0.200 0.000 - - - 64.70 71.60%

Poor

F.F. Rosales General Contractor 8814 Road Upgrading (Concrete Paving) of Mulanay-San Francisco Road, K0297+082 to K0298+082 8/12/2014 IV-A 23.489 240 C 0.425 0.200 0.300 92.50 86.32%

Satisfactory

F.F. Rosales General Contractor 8814Rd. Upgrading (Concrete Paving) of Mulanay-San

Francisco Road, K0297+082 - K0298+082, Brgy. Ilayang Yuni

08/06/13 IVA 22.043 180 O 0.316 0.253 0.150 0.030 0.040 0.033 82.20 -

F.F. Rosales General Contractor 8814 Asphalt Overlay of MSR-Daang Maharlika Road (K0102+000-K0105+774), Tiaong 03/14/12 IVA 26.248 98 C 0.414 0.200 0.300 - - - 91.40 88.34%

SatisfactoryF.H. Gopiteo Construction &

Supply 21336 Const. of Drainage Lined Canal at Carpenter Hill Sect. along Marbel-Makar Rd. 11/24/12 XII 15.061 268 C 0.492 0.200 0.000 - - - 69.20 80.54%

UnsatisfactoryF.H. Gopiteo Construction &

Supply 21336 Const. of Drainage Lined Canal at Carpenter Hill Sect. along Marbel-Makar Rd. 08/07/12 XII 15.061 268 O 0.392 0.240 0.150 0.030 0.047 0.050 90.90 -

F.H. Gopiteo Construction & Supply 21336 Const. of Drainage Lined Canal at Saravia Sect. along

Marbel-Makar Rd. 08/07/12 XII 14.324 261 C 0.466 0.133 0.300 - - - 89.90 87.14% Satisfactory

F.H. Gopiteo Construction & Supply 21336 Repair/Rehab,/Impv't. of Midsayap-Marbel Rd., Brgy.

Morales Sect., w/ exceptions 03/21/13 XII 9.496 240 C 0.390 0.200 0.042 - - - 63.20 63.20% Poor

F.L. REGUYAL CONSTRUCTION CORP(Formerly: F.L. Reguyal

Construction)3315 Construction of Protection Works along Daang Maharlika,

Carranglan Section, KO 188+507 to KO 188+640.50 11/21/2014 III 9.070 111 C 0.409 0.133 0.300 - - - 84.20% 84.20% Satisfactory

F.L. Reguyal Construction Corp. (Formerly: F.L. Reguyal

Construction)3315 Construction of Drainage Canal along Daang Maharlika

Road (San Jose City Section 9/25/2014 Special 3 18.139 150 C 0.359 0.200 0.300 85.90 85.90% Satisfactory

F.P. De Guzman Construction Inc. 10296Const. of Slope Protection for Marikina River along Brgy. Tumana, Eastbank Marikina City, 2nd District Sta. 6+120-

Sta.6+987.7008/06/13 NCR 43.822 214 C 0.467 0.133 0.300 - - - 90.00 90.00%

Very Satisfactory

F.P. De Guzman Construction Inc. 10296 Const. of MPB, Brgy. 91, Zone 8, Franco St. 07/29/13 NCR 3.796 194 C 0.384 0.200 0.300 - - - 88.40 88.40% Satisfactory

F.P. de Guzman Construction, Inc. 10296 Const./Rehab./Impvt. of MPB at Zone 25-40, District III, 03/15/12 NCR 1.876 119 C 0.455 0.190 0.250 - - - 89.50 85.79% Satisfactory

F.P. de Guzman Construction, Inc. 10296 Const. of Pedestrian Overpass Across Macros Highway Brgy. Mayamot 03/12/12 IVA 15.534 198 C 0.441 0.133 0.300 - - - 87.40 91.84%

Very SatisfactoryF.R Ignacio Construction

Incorporated 687 Pasay City LTO District Office Building Project 09/18/09 DOTC 11.937 255 O 0.384 0.300 0.150 0.030 0.039 0.050 95.30 -

Fairchild Builders & Developers, Inc. 10024 Rehab. along Tacloban-Baybay South Road along

Tacloban South Road 05/28/09 VIII 9.486 150 O 0.336 0.239 0.150 0.030 0.037 0.033 82.50 -

Fairchild Builders and Developers, Incorporated (Formerly: Fairchild

Marketing & Construction)10024 Rehab./Const./Conc. of FMR, Brgy. Comatin 08/19/12 VIII 18.999 160 C 0.414 0.200 0.300 - - - 91.40 85.22%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page90

Page 91: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Fairchild Builders and Developers, Incorporated / RJIR Enterprises

(JV)JV-11-187

Rd. Upgrading (Gravel to Paved) Based on Gravel Rd. along Merida-Lundag Puting Bato-Consolacion-Isabel Rd.,

Km.1108+(-040)-Km.1108+96008/13/12 VIII 19.685 190 C 0.403 0.200 0.300 - - - 90.30 83.76%

Satisfactory

FBS Engineering & Construction 34931 Colocol Integrated CIS Rehabilitation & Extension Project 05/12/12 NIA 3.097 217 C 0.433 0.200 0.300 - - - 93.31 89.51% Very Satisfactory

FDS Construction and Supply 26654 Supply Installation / Construction of the Interior Fit-out of DBP Virac Branch 03/13/12 DBP 6.814 150 C 0.479 0.000 0.300 - - - 77.85 82.02%

Satisfactory

FEAJ CONSTRUCTION AND GENERAL SERVICES 13609

Construction of Slope Protection CSR Junction Pola K0065+252-K0066+400 ( Intermittent Section (Both Sides)),

Maluaanluan, Pola, Oriental Mindoro11/26/2014 IV 9.031 121 C 0.439 0.133 0.300 - - - 87.20% 87.20%

Satisfactory

Feaj Construction and General Services 13609 Repair/Rehab./Impv't. of Puerto Galera Drainage, Calapan

North Rd. 08/02/13 IVB 9.893 160 C 0.405 0.178 0.300 - - - 88.30 86.20% Satisfactory

FEAJ Construction and General Services 13609 Repair/Rehab./Imprv't. of Puerto Galera Drainage, Calapan

North Rd. 03/18/13 IVB 9.893 160 O 0.350 0.240 0.150 0.030 0.045 0.033 84.80 -

FERDSTAR BUILDERS CONTRACTORS 4965

Construction of Two (2) Storey Four (4) Classrooms Building at Saguin Integrated H/S, San Fernando City,

Pampanga8/21/2014 III 4.656 120 C 0.473 0.160 0.300 93.30 93.30%

Very Satisfactory

Ferdstar Builders Contractors 4965 Repair/Maint. of Gumain Porac Diversion Channel 07/31/13 III 6.422 75 C 0.444 0.133 0.300 - - - 87.70 87.70% Satisfactory

Ferdstar Builders Contractors 4965 Drainage Impv't. along Mexico Km.71+000-Km.71+630 07/29/13 III 6.586 120 C 0.463 0.133 0.300 - - - 89.60 87.20% Satisfactory

Ferdstar Builders Contractors 4965Repair/Rehab./Const. of Drainage System along Gov't.

Center Rd. Network, Maharlika Highway & Pawing-Campetic Rd., Brgy. Candahug to Brgy. Pawing

08/22/13 VIII 37.215 300 O 0.400 0.240 0.150 0.012 0.045 0.050 89.70 -

Ferdstar Builders Contractors 4965 Rehab./Reconst. of Biliran Circ. Rd., Esperanza-Looc Rd. Sect., Km.1104+000-Km.1104+520 08/14/13 VIII 9.259 78 C 0.441 0.133 0.300 - - - 87.40 87.34%

Satisfactory

Ferdstar Builders Contractors 4965 Repair/Rehab./Impv't. of Dapdap Flood Control Structure along Palo-Carigara-Ormoc Rd., Brgy. Dapdap 03/22/13 VIII 4.825 120 C 0.454 0.133 0.300 - - - 88.70 87.44%

Satisfactory

Ferdstar Builders Contractors 4965 Rehab./Reconst. of Biliran Circ. Rd., Esperanza-Looc Rd. Sect., Km.1104+000-Km.1104+520 03/12/13 VIII 9.259 78 O 0.368 0.225 0.150 0.030 0.050 0.050 87.30 -

Ferdstar Builders Contractors 4965 Repair/Rehab. of Motiong Seawall Flood Control, Pob. Motiong 03/18/13 VIII 15.833 303 C 0.398 0.133 0.300 - - - 83.10 84.00%

Satisfactory

Ferdstar Builders Contractors 4965 Conc. of Barangay Road, Barangay Pag-asa (Phase I) 08/04/11 III 9.315 109 O 0.229 0.225 0.150 0.030 0.048 0.050 73.20 -

Ferdstar Builders Contractors 4965 Rehab./Impvt. of Daang Maharlika, Calbiga-Tacloban Rd. Sect. Km.897+200 - Km.901+200 w/ exceptions, Leyte Side 06/09/10 VIII 28.322 95 O 0.339 0.258 0.150 0.030 0.037 0.033 84.70 -

Ferdstar Builders Contractors 4965 Const. of Multi-Purpose Building at San Roque 08/25/09 III 5.254 93 O 0.384 0.240 0.150 0.030 0.051 0.033 88.80 -

Ferdstar Builders Contractors 4965Road Upgrading/Conc. of Capas-San Jose-Mayantoc-

Malacampa Rd. (Capas Section), K0116+701-K0118+874 w/ exception

08/06/12 III 26.781 120 O 0.305 0.300 0.150 0.030 0.030 0.050 86.50 -

Ferdstar Builders Contractors 4965 Repair of Calbiga Steel Bridge along Daang Maharlika-Calbiga-San Juanico Bridge Sect. 08/07/12 VIII 17.375 261 O 0.354 0.235 0.150 0.030 0.040 0.033 84.20 -

Ferdstar Builders Contractors 4965 Impvt./Rehab. of Old Nat'l Rd., Km.821+228-Km.822+424 (w/ exceptions) 08/07/12 VIII 10.445 201 C 0.337 0.200 0.300 - - - 83.70 83.94%

SatisfactoryFerrer Construction and

Engineering Services 16711 Proposed Exterior Repainting of PAZ Mendoza & Med. Lib. 03/20/09 U.P. 751.116 120 O 0.366 0.300 0.000 0.030 0.054 0.050 80.00 -

Ferreze Construction Supply & Manufacturing 26968 Const. of MPB (Renov./Rehab. of Psychiatric Ward)

Zamboanga City Medical Center 09/02/09 IX 5.220 126 O 0.327 0.300 0.150 0.030 0.053 0.050 91.00 -

FF Cruz & Co. Inc./Filipinas (Prefab. Bldg.) Systems, Inc. JV JV-08-139 Impvt./Const. of Roads and Bridges along Baler-Casiguran

Road (CP1) 09/09/09 III 1,703.61 450 O 0.378 0.300 0.150 0.030 0.050 0.050 95.80 -

FFJJ CONSTRUCTION 16712 Const. of Maluos Bridge II along Bukidnon - Davao city Road, Sinuda 10/23/2014 X 27.205 252 O 0.333 0.295 0.105 0.030 0.042 0.033 83.80% 83.80%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page91

Page 92: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

FFJJ CONSTRUCTION 16712

GAA - Widening of Agusan-Davao Road, K1458+680 - K1460+1258, Davao del Norte 1st LD DPWH CY-2014

(Widening of Agusan-Davao Road, K1458+680 - K1460+1087.48)

10/25/2014 XI 44.207 195 O 0.398 0.193 0.300 89.10% 89.10% Very Satisfactory

FFJJ CONSTRUCTION 15712Construction/Improvement of Access Road to Declared

Tourism Destination at Brgy. San Agustin, Km. 1607+480 - Km. 1609+592.793

10/22/2014 XI 46.280 208 O 0.291 0.218 0.104 0.022 0.040 0.017 69.20% 69.20% Poor

FFJJ CONSTRUCTION 16712Road Upgrading (gravel to paved) along Davao-Sarangani Coastal Road, (Malalag-Malita-JAS Road), km. 1678+776 to

km. 1679+860, Calian Section8/7/2014 XI 42.724 179 OG 0.023 0.300 0.000 0.030 0.019 0.000 37.20 -

FFJJ CONSTRUCTION 16712Widening/Rehabilitation/Strengthening of Permanent Bridges Generated from Bridge Management System

Luayan Bridge along Midsayap-Marbel Road8/5/2014 XII 4.854 180 C 0.457 0.169 0.300 92.60 92.60%

Very Satisfactory

FFJJ CONSTRUCTION 14268Widening of Cotabato-Marbel Road, K1712+398.30 - K1717+000 (w/ exception), Bishop's Palace-Paraiso

Section8/4/2014 XII 46.743 180 OG 0.322 0.240 0.150 0.030 0.057 0.050 84.90 -

FFJJ CONSTRUCTION 16712 Rehab./Reconst./Upgrading of Damaged Paved Road along NRJ Cuevas - Sta. Josefa Road, K1371+541 - K1373+000 8/8/2014 XIII 22.263 206 OG 0.303 0.290 0.131 0.030 0.051 0.033 83.80 -

FFJJ Construction 16712 Widening of Surigao-Davao Coastal Rd., Hijo Sect. 08/14/13 XI 20.314 180 C 0.396 0.133 0.300 - - - 82.90 82.90% Satisfactory

FFJJ Construction 16712 Const./Widening/Upgrading/Rehab. of Access Rd. to declare Tourism Destination, Brgy. Lacaron 08/10/13 XI 45.264 227 O 0.397 0.292 0.131 0.010 0.023 0.033 88.60 -

FFJJ Construction 16712 Const. of Bank Protection along Hijo River Apokon Sect. (Surigao-Davao Coastal Rd.) 08/12/13 XI 18.731 180 C 0.383 0.147 0.300 - - - 83.00 85.10%

Satisfactory

FFJJ Construction 16712 Repair/Rehab. of Protection Works, Pamana 08/07/13 XI 9.250 159 C 0.397 0.133 0.300 - - - 83.00 84.32% Satisfactory

FFJJ Construction 16712 Const. of Caraga River Protection, San Jose 08/17/13 XI 14.405 247 O 0.347 0.300 0.065 0.030 0.020 0.033 79.50 -

FFJJ Construction 16712Rd. Upgrading (gravel to paved) along Davao-Sarangani

Coastal Rd., (Malalag-Malita-JAS Rd.), Km.1678+776-Km.1679+860, Calian Sect.

08/07/13 XI 42.724 179 O 0.315 0.150 0.150 0.030 0.023 0.033 70.10 -

FFJJ Construction 16712Rds. to Address Critical Bottlenecks Nat'l Bridges,

Widening/Rehab./Strengthening of Permanent Bridges, Luayan Bridge along Midsayap-Marbel Rd.

08/05/13 XII 4.854 190 O 0.369 0.240 0.150 0.020 0.037 0.033 84.90 -

FFJJ Construction 16712Replacement of (Temporary to Permanent) NIA Bridge (15

LM FSB) along Kidapawan-Calunasan-M'lang Rd., CO21+958-CO22+438

08/09/13 XII 11.439 316 C 0.405 0.200 0.000 - - - 60.50 71.78% Poor

FFJJ Construction 16712 Widening of Tagum-Panabo Circ. Rd., 1st District Pob. Kapalong Sect., Km.1477+273-Km.1478+420 03/18/13 XI 18.563 133 O 0.337 0.235 0.150 0.030 0.050 0.033 83.50 -

FFJJ Construction 16712 Cons./Widening/Upgrading of Access Rd. to Declared Tourism Destination, Brgy. Lacaron 03/14/13 XI 45.264 179 O 0.360 0.000 0.150 0.000 0.030 0.050 59.00 -

FFJJ Construction 16712Replacement of (Temp. to Perm.) NIA Bridge (15LM FSB)

along Kidapawan-Calunasan-M'lang Rd. C021+958-C022+438

03/18/13 XII 11.439 316 O 0.329 0.300 0.000 0.030 0.040 0.033 73.20 -

FFJJ Construction 16712Roadslip/Protection along Surigao-Davao Coastal Rd.,

Lingig, Brgy. Mahayahay, Lingig Km.1478+500-Km.1478+545, (Km.1478+46-Km.1478+244.50)

03/17/13 XIII 23.390 245 O 0.321 0.225 0.150 0.030 0.050 0.050 82.60 -

FFJJ Construction 16712 Rehab./Conc. of FMR at Brgy. Poblacion to Brgy. Benolen 08/08/11 XII 9.503 75 O 0.284 0.200 0.000 0.020 0.035 0.033 57.20 -

FFJJ Construction 16712 Conc. of Cotabato City Circumferential Road 06/01/10 XII 27.563 150 O 0.320 0.201 0.150 0.030 0.042 0.033 77.60 -

FFJJ Construction 16712 Conc. of Davao del Sur-Sarangani Coastal Road, Kitayo-Balangonan Section 11/22/08 XI 28.900 300 O 0.274 0.241 0.100 0.022 0.035 0.067 73.90 -

FFJJ Construction 16712 Const. of Kinangan Bridge and Approaches 09/02/08 XI 18.593 332 O 0.304 0.240 0.070 0.015 0.035 0.100 76.40 -FFJJ Construction 16712 Const. of Pangian Bridge II and Approaches 11/23/08 XI 22.868 454 O 0.307 0.151 0.100 0.030 0.030 0.067 68.50 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page92

Page 93: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

FFJJ Construction 16712 Const. of Kiblis Bridge with Bridge and Approaches, Sarangani-Sultan Kudarat Coastal Road 09/02/08 XII 21.574 280 O 0.342 0.273 0.000 0.030 0.028 0.067 74.00 -

FFJJ Construction 16712 Concreting of Paco-Roxas-Arakan Valley Road, New Pontevedra Section 05/30/09 R-XII 15.095 206 O 0.327 0.300 0.000 0.024 0.045 0.033 72.90 -

FFJJ Construction 16712 Rehab./Recons/Upgrading of Digos-Makar Road, Baluyan-Tagansule Section, Km. 1587+500-Km. 1589+000 05/28/09 XI 19.289 210 O 0.320 0.225 0.150 0.030 0.046 0.050 82.10 -

FFJJ Construction 16712 Rehab/Conc. of Road Jct. Mana-Ticulon Lagumit Little Baguio Road 03/04/09 XI 19.293 262 O 0.279 0.252 0.110 0.030 0.048 0.033 75.20 -

FFJJ Construction 16712 Conc. of Paco-Roxas-Arakan Rd. (New Ponteverdra Section) 03/10/09 XII 15.095 150 O 0.378 0.300 0.000 0.030 0.060 0.033 80.10 -

FFJJ Construction 16712 Land Dev't. for the Const. of MPB (Cotabato Cultural Center / Grand Mosque) 03/19/12 XII 29.523 205 C 0.489 0.133 0.271 - - - 89.30 83.00%

Satisfactory

FFJJ Construction 16712 Const. of Bank Protection along Hijo River, Apokon Sect. Tagum City, (Surigao-Davao Coastal Rd.) 11/23/12 XI 18.341 150 O 0.360 0.240 0.150 0.030 0.035 0.050 86.50 -

FFJJ Construction 16712 Repair/Rehab. of Protection Works, Pamana 11/21/12 XI 9.250 159 O 0.385 0.240 0.134 0.030 0.030 0.033 85.20 -

FFJJ Construction 16712Rehab./Reconst./Upgrading of Damaged Paved Nat'l Arterial Rd. along Makilla-Ala Valley Rd. K1611+979-

K1614+45611/20/12 XII 37.131 345 O 0.384 0.248 0.150 0.030 0.045 0.033 89.00 -

FFJJ Construction 16712 Rehab./Reconst./Upgrading along Makilala-Ala Valley Rd., K1611+979-K1614+456 08/10/12 XII 33.756 270 O 0.352 0.249 0.150 0.030 0.051 0.033 86.50 -

FFJJ Construction 16712Replacement of (Temp. to Perm.) NIA Bridge (15 LM FSB)

along Kidapawan-Calunasan-M'lang Rd., C021+958-C022+438

08/11/12 XII 10.407 226 O 0.321 0.269 0.150 0.030 0.051 0.033 85.40 -

FFJJ Construction 16712 Replacement of (Temp. to Perm.) of Binay Bridge along Nowa-Doroluman-Greenfield Nat'l Rd., Magpet 08/10/12 XII 24.828 244 O 0.379 0.240 0.100 0.030 0.042 0.033 82.40 -

FFJJ Construction 16712Rd. Slip/Protection along Surigao-Davao Coastal Rd., Lingig Brgy. Mahayahay, Lingig, Km. 1478+500-Km.

1478+545 (Km. 1478+46-Km. 1478+244.50)11/25/12 XIII 23.392 210 O 0.320 0.225 0.150 0.022 0.060 0.050 82.70 -

FFJJ CONSTRUCTION/JMT CONSTRUCTION -Joint Venture JV-13-400

Road Upgrading (Gravel to Concrete) of Jct. Magsaysay - Cagdianao Road, Chainage 000 - Chainage 468.70,

K0005+520 - K0016+680 with Exception8/14/2014 XIII 81.790 235 OG 0.394 0.250 0.101 0.030 0.042 0.033 85.00 -

FGM BUILDERS RESOURCES & DEVELOPMENT CORPORATION 31807 Construction of 2-Storey, 2-Classroom @ V. Corcuera ES,

Package Z 8/15/2014 XI 2.215 255 C 0.466 0.133 0.300 89.90 90.74% Very Satisfactory

FGM Builders Resources & Development Corporation 31807 Const. of MPBs at Guihing Central E/S, Brgy. Guihing 08/09/13 XI 2.925 90 C 0.455 0.133 0.300 - - - 88.80 88.80%

SatisfactoryFGM Builders Resources & Development Corporation 31807 Const. of 2-Storey, 2-Cl @ V. Corcuera ES, Package Z 08/19/13 XI 2.215 240 O 0.358 0.285 0.150 0.030 0.038 0.050 91.10 -

FGM Builders Resources & Development Corporation 31807 Const. of Sch. Bldg. at Digos City Nat'l High Sch. 08/10/12 XI 1.350 90 C 0.457 0.104 0.300 - - - 86.10 86.66%

SatisfactoryFGM Builders Resources & Development Corporation 31807 Conc. of Brgy. Baliok, BAGAHAI Purok 6 FMR, Brgy. Baliok 03/22/13 XI 1.945 22 C 0.410 0.133 0.300 - - - 84.30 84.30%

SatisfactoryFGW Construction Corporation (Formerly: FGW Construction) 7436 Road Repair of Brgy. 4-Brgy.1 Pob. San Francisco, Sta.

0+000-Sta.0+605.35 03/27/12 XIII 3.543 150 C 0.390 0.133 0.300 - - - 82.30 82.36% Satisfactory

FH GOPITEO CONSTRUCTION & SUPPLY 21336 CONSTRUCTION OF DORMITORY BUILDING I PHASE I 03/06/14 DOST 17.632 243 C 0.470 0.200 0.150 - - - 82.00 82.00%

Satisfactory

FIAT CONSTRUCTION SERVICES 5463Road Upgrading (Gravel to Paved) of Tabango - Catmon - La Fortuna - Minlawaan - Gimorco Road Km. 1040+297 -

Km. 1042+3078/8/2014 VIII 44.040 223 C 0.375 0.133 0.300 80.80 80.80%

Unsatisfactory

FIAT CONSTRUCTION SERVICES 5463 Road Upgrading (Gravel to Paved) of San Isidro - Daja Road K1018+(-497)……... 8/8/2014 VIII 45.334 237 OG 0.290 0.238 0.150 0.022 0.045 0.033 77.80 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page93

Page 94: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Fiat Construction Services 5463Rd. Upgrading (Gravel to Paved) (Int. Sect.) inc. Drainage &

Rd. Facilities along Bacolod-Madalum Highway, Km.1567+000-Km.1567+1469, Km.1571+405-Km.1571+995

08/12/13 X 25.961 164 C 0.396 0.133 0.300 - - - 82.90 82.90% Satisfactory

Fiat Construction Services 5463Rd. Upgrading (Gravel to Paved) of Tabango-Catmon-La

Fortuna-Manlawaan-Gimarco Rd., Km.1040+297-Km.1042+307

08/12/13 VIII 44.040 223 O 0.362 0.240 0.105 0.018 0.042 0.017 78.40 -

Fiat Construction Services 5463 Rd. Upgrading (Gravel to Paved) of Tabango-La Fortuna-Manlawaan-Gimarco Rd. Km.1040+297-Km.1042+307 03/13/13 VIII 44.040 210 O 0.270 0.240 0.150 0.030 0.040 0.033 76.30 -

Fiat Construction Services 5463Conc. of Dinagat Island Resort Road Network (San Jose-

Basilisa Sect.) with One (1) Bridge and One (1) Box Culvert)

08/11/11 XIII 188.938 567 O 0.389 0.267 0.112 0.030 0.047 0.017 86.20 -

Fiat Construction Services 5463 Conc. of Dinagat-Loreto Road (San Jose-Basilisa Sect.) 08/11/11 XIII 190.877 549 O 0.372 0.297 0.073 0.030 0.054 0.017 84.30 -

Fiat Construction Services 5463 Conc. of Dinagat-Loreto Road (San Jose-Basilisa Sect) 04/07/11 XIII 190.877 450 O 0.374 0.247 0.138 0.030 0.055 0.050 89.40 -

Fiat Construction Services 5463 Conc. of Butuan City-Paining-Tandag Road 06/12/10 XIII 26.285 195 O 0.343 0.300 0.150 0.030 0.040 0.033 89.60 -

Fiat Construction Services 5463 Conc. of Dinagat-Loreto Road (San Jose Basilisa Section) 08/26/10 XIII 190.878 420 O 0.360 0.262 0.150 0.030 0.047 0.033 88.20 -

Fiat Construction Services 5463 Conc. of Dinagat Island Road Network (San Jose-Basilisa Section with One (1) Bridge and One (1) Box Culvert 08/26/10 XIII 188.939 525 O 0.380 0.287 0.064 0.030 0.047 0.017 82.50 -

Fiat Construction Services 5463 Conc. of Dinagat Island Rd. Network(San Jose-Basilisa Sect. with 1 Bridge and 1 Box Culvert) 09/05/09 XIII 188.939 465 O 0.382 0.253 0.150 0.030 0.047 0.033 89.50 -

FIAT Construction Services & B.M. Marketing (JV) 9852 Tacloban Airport Development Project 03/13/14 DOTC 176.112 360 O 0.341 0.300 0.150 0.030 0.056 0.050 92.70 -

Fiat Construction Services / 3K Rock Engineering (JV) JV-11-420 Rd. Upgrading (gravel to concrete) of Gurel-Bokod-

Kabayan-Buguias-Abatan Rd., K0312+500-K0330+000 (I.S.) 11/20/12 CAR 132.763 387 O 0.376 0.240 0.150 0.015 0.038 0.033 85.20 -

Fiat Construction Services / Jann-Norris Construction Supplies (JV) JV-12-403 Const. of Cupas River Control Caloocan-Macate Sect. 08/13/13 II 15.898 120 C 0.474 0.133 0.300 - - - 90.70 90.70%

Very Satisfactory

Fiat Construction Services / Kenneth Construction and General

Merchandise (JV)JV-12-271 Rehab./Reconst./Upgrading along Bacolod North R.d,

K0138+713-K0140+757 08/13/13 VI 33.122 193 C 0.447 0.133 0.300 - - - 88.00 88.00% Satisfactory

Fiat Construction Services / KVC Construction (JV) JV-11-012

Rd. Upgrading (Gravel to Concrete) along Gurel-Bokod-Kabayan-Buguias-Abatan Rd., K0303+600-K0312+600 (IS)

Abat-Bila Sect.11/29/12 CAR 113.005 330 C 0.444 0.200 0.300 - - - 94.40 89.60%

Very Satisfactory

Fiat Construction Services / KVC Construction (JV) JV-11-012

Rd. Upgrading (Gravel to Conc.) along Gurel-Bokod-Kabayan-Buguias-Abatan Rd., K0303+600-K0312+600 (IS)

Abat-Bila Sect.07/31/12 CAR 113.005 330 O 0.356 0.300 0.130 0.008 0.037 0.033 86.40 -

Fiat Construction Services / MG Samidan Construction (JV) JV-11-321 Rd. Upgrading (Gravel to Conc.) of Mt. Province-Ilocos Sur

via Kayan Rd., K0385+995-K0391+000, Bunga 08/02/13 CAR 83.201 327 C 0.423 0.133 0.300 - - - 85.60 86.53% Satisfactory

Fiat Construction Services / MG Samidan Construction (JV) JV-11-321 Rd. Upgrading (gravel to concrete) of Mt. Province-Ilocos

Sur via Kayan Rd. K0385+995-K0391+000 11/22/12 CAR 83.201 327 O 0.371 0.289 0.099 0.030 0.059 0.033 88.10 -

Fiat Construction Services / MG Samidan Construction (JV) JV-11-321 Rd. Upgrading (Gravel to Conc.) along Mt. Province-Ilocos

Sur Rd. via Kayan Rd., K0385+995-K0391+000, Burgos 08/03/12 CAR 83.201 270 O 0.326 0.300 0.122 0.030 0.051 0.033 86.20 -

FIAT CONSTRUCTION SERVICES/ MG SAMIDAN CONSTRUCTION

(JOINT VENTURE)JV-12-405 Road Upgrading (Gravel to Concrete) of Mountain Province

- Ilocos Sur via Tue Road, K0388+000 - K0393+380 (I.S.) 11/23/2014 CAR 119.749 426 C 0.410 0.181 0.300 - - - 89.10% 89.10% Very Satisfactory

FIAT CONSTRUCTION SERVICES/A.P.B. CONSTRUCTION

(JV)JV-13-542 Construcyion of Flood Control Structures, Bangbangar,

Bangued, Abra 8/11/2014 CAR 18.800 164 C 0.375 0.133 0.300 80.80 80.80% Unsatisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page94

Page 95: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Filipinas (Prefabricated Bldg.) Systems, Inc. 5562 Const. of Four (4) Storey with Roof Deck for DBM Building 11/26/08 Sp. Bldgs. 445.429 710 O 0.372 0.300 0.100 0.030 0.061 0.067 93.00 -

Firmabuilt Construction 30175

Rehabilitation/Reconstruction/Upgrading of Damaged National Road, (Intermittent Sections), Jct. MWCR (Bagong Silang) - Cabacao Diversion Road, K0424+(-399) to K0424+(-

029), Brgy. Cabagao

8/14/2014 IV-B 6.960 138 C 0.470 0.136 0.000 60.60 64.56% Poor

Firmabuilt Construction 30175Rehab./Reconst./Upgrading of Damaged Nat'l Rd., (Int.

Sect.) Jct. MWCR (Bagong Silang)-Cabacao, Diversion Rd., K0424+(-)399 to K0424+(-)029, Brgy. Cabagao

07/29/13 IVB 6.960 138 O 0.332 0.300 0.000 0.015 0.025 0.000 67.20 -

Firmabuilt Construction 30175 Const. of MPB (Phase 1) Occ. Mindoro State College 03/13/12 IVB 4.822 150 C 0.456 0.133 0.300 - - - 88.90 88.60% Satisfactory

Firmabuilt Construction 30175 Const. of MPB, Brgy. Poblacion Proper, Sablayan 03/13/12 IVB 2.890 120 C 0.474 0.133 0.300 - - - 90.70 85.80% Satisfactory

Firmabuilt Construction / Marcbilt Construction, Inc. Joint Venture JV-09-256 Road Upgrading at Abre de Ilog-San Jose Road (Marilao-

Bagong Silang Sect.), Brgy. New Dagupan 08/27/10 IVB 19.192 180 O 0.355 0.054 0.150 0.030 0.025 0.033 64.70 -

Firmabuilt Construction / Performance Builders &

Developers Corporation (JV)JV-12-257 Replacement/Reconst. of Mangat Bridge along Mindoro

West Coastal Rd., Brgy. San Pedro 07/30/13 IVB 6.736 220 O 0.355 0.300 0.046 0.030 0.037 0.033 80.10 -

FIRST NORTHWAY DEVELOPMENT & CONSTRUCTION CORPORATION 11645

Rehab./Reconst'n/ Upgrading of Damaged Paved National Roads Including Drainage Based on PMS-HDM-4

(Intermittent Section), Sta. Maria-Burgos Road K0373+000 to K0374+021

10/24/2014 I 7.663 121 C 0.423 0.146 0.300 - - - 86.90% 86.90% Satisfactory

FIRST NORTHWAY DEVELOPMENT & CONSTRUCTION CORPORATION 11645 Construction of Multi-Purpose Building, Barangay

Poblacion 10/24/2014 I 7.332 148 C 0.431 0.182 0.300 - - - 91.30% 91.30% Very Satisfactory

First Northway Development and Construction Corporation 11645

Rehab./Reconst./Upgrading of Damage Paved National Road Jct. Santiago - Banayo - Lidlidda - San Emilio -

Quirino Road a) K0369+129 - K0370+242, b) K0270+477 - K0370+587, c) K0370+745 - K0371+726

8/11/2014 I 38.115 283 C 0.448 0.133 0.300 88.10 85.94% Satisfactory

First Northway Development and Construction Corporation 11645

Rehab./Reconst./Upgrading of Damage Paved Nat'l Rd. Jct. Santiago Banayo-Lidlidda-San Emilio-Quirino Rd. a)K0369+129-K0370+242 b)K0270+477-K0370+587,

c)K0370+745-K0371+726

08/12/13 I 36.423 203 O 0.335 0.300 0.110 0.030 0.037 0.033 84.50 -

First Northway Development and Construction Corporation 11645 Completion of Candon-Salcedo Road 02/18/10 I 14.320 225 O 0.279 0.129 0.150 0.030 0.051 0.050 68.90 -

First Northway Development and Construction Corporation 11645 Repair/Rehab./Impv't. along Manila North Rd., Candon-

Santiago Sect., K0349+189-K0357+000 w/ exception 03/19/13 I 9.652 59 C 0.437 0.133 0.300 - - - 87.00 87.00% Satisfactory

FIVE MASSIVE INFRA & SUPPLY CORP. 36876 Road Concreting at Mahogany, Brgy. Sawata 10/24/2014 XI 4.851 84 C 0.384 0.137 0.300 - - - 82.10% 82.10%

SatisfactoryFIVE MASSIVE INFRA & SUPPLY

CORP. 36876 Construction of Multi-Purpose Building, City of Mati 10/27/2014 XI 1.483 60 C 0.415 0.139 0.300 - - - 85.40% 85.40% Satisfactory

FIVE MASSIVE INFRA & SUPPLY CORP. 36876 Construction of Road at Brgy. San Pedro, Cantilan,

Surigao del Sur 10/26/2014 XIII 0.951 60 C 0.458 0.133 0.300 - - - 89.10% 89.10% Very Satisfactory

FLORDES CONSTRUCITON & TRADING CORP.(Formerly: Flordes Construction & 

Trading)16916

Preventive Maintenance Based on Pavement Management System/Highway Development and Management-4 (HDM-4)

along Jones Bridge11/24/2014 NCR 13.936 192 O 0.393 0.262 0.071 0.030 0.058 0.033 84.70% 84.70%

Satisfactory

FLORDES CONSTRUCITON & TRADING CORP.(Formerly: Flordes Construction & 

Trading)16916 Construction of Slope Protection along NCR-Bulacan Bdry.-

Bigte-Ipo Dam Road, San Jose River 11/28/2014 III 46.206 170 C 0.486 0.133 0.300 - - - 91.90% 91.90% Very Satisfactory

FLORDES CONSTRUCTION & TRADING 16916 Proposed Raising of Grade with Drainage Improvement

along Mag Araullo St. Zone 61, District VI 8/15/2014 NCR 3.193 60 C 0.488 0.148 0.300 93.60 93.60% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page95

Page 96: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Flordes Construction & Trading 16916 Porposed Impv't. of Drainage System along P. Quirino Ave., near Nagtahan Link Rd. 08/31/13 NCR 4.491 147 C 0.458 0.133 0.300 - - - 89.10 89.10%

Very Satisfactory

Flordes Construction & Trading 16916 Repair/Rehab./Impv't. of Palumpong St., w/ exception 08/01/13 NCR 9.702 150 C 0.429 0.133 0.300 - - - 86.20 86.20% Satisfactory

Flordes Construction & Trading 16916 Reconst. of Rizal Ave., w/ Drainage Impv't. 07/29/13 NCR 13.019 180 C 0.412 0.133 0.300 - - - 84.50 84.50% Satisfactory

Flordes Construction & Trading 16916 Rd. Upgrading (Gravel to Paved) of Eastern Bulacan Rd. K0104+000-K0105+000 08/15/13 III 23.881 150 C 0.425 0.133 0.300 - - - 85.80 85.80%

Satisfactory

Flordes Construction & Trading 16916 Rd. Upgrading (Gravel to Paved) of Eastern Bulacan Rd. K098+000-K0100+000 08/15/13 III 45.888 210 C 0.422 0.133 0.300 - - - 85.50 86.34%

Satisfactory

Flordes Construction & Trading 16916 Const./Upgrading of Rd. Network w/ Drainage Impv't., Zone 25 & 26 03/20/13 NCR 9.697 189 C 0.458 0.079 0.300 - - - 83.70 85.62%

Satisfactory

Flordes Construction & Trading 16916 Rd. Upgrading (Gravel to Paved) of Eastern Bulacan Rd., K098+000-K0100+000, Doña Remedios 03/20/13 III 45.888 210 O 0.381 0.238 0.150 0.010 0.040 0.050 86.90 -

Flordes Construction & Trading 16916 Rehabilitation of NCR/Bulacan Boundary-Bigte Ipo Dam Road 06/01/09 III 42.902 150 O 0.334 0.240 0.150 0.030 0.040 0.050 84.40 -

Flordes Construction & Trading 16916 Const./Rehab./Replacement/ Completion and Repair of A. Regidor Elem. School 05/20/09 NCR 2.481 120 O 0.326 0.240 0.150 0.030 0.065 0.050 86.10 -

Flordes Construction & Trading 16916 Conc. of Roads with Drainage Impvt. Along Madrid and Jaboneros 03/15/12 NCR 6.425 90 C 0.488 0.200 0.300 - - - 98.80 93.70%

Very Satisfactory

Flordes Construction & Trading 16916 Proposed Const. of MPB, Blue Water , Brgy. 894 03/19/12 NCR 2.750 141 C 0.373 0.077 0.300 - - - 75.00 84.45% Satisfactory

Flordes Construction & Trading 16916Rehab./Reconst. Of Sta. Rita-Biak na Bato via Pulong Bayabas Rd.: a)Km.46+000-Km.76+704; b)Km.84+325-

Km.84+808; c)km.85+000-Km.85+57003/16/12 III 12.937 110 C 0.427 0.134 0.300 - - - 86.10 84.90%

Satisfactory

Flordes Construction & Trading 16916

Rehab./Reconst.of Sta. Rita-Biak na Bato via Pulong Bayabas Rd.: a)Km.74+081-Km.74+070; b)Km.74+070-

Km.75+548 w/ exception and c)Km.83+000-Km.4+150 w/ exception

03/16/12 III 18.418 150 C 0.396 0.135 0.300 - - - 83.10 83.52% Satisfactory

FLORIANE CONSTRUCTION AND SUPPLY 12261 Construction of Multi-Purpose Building at Village II, Brgy.

Libertad, Butuan City 10/29/2014 XIII 2.876 60 C 0.472 0.133 0.300 - - - 90.50% 90.50% Very Satisfactory

FLORIANE CONSTRUCTION AND SUPPLY 12261 Construction of Slope Protection along Butuan City-

Cagayan de Oro City-Iligan Road 8/11/2014 X 3.932 105 C 0.490 0.133 0.300 92.30 92.30% Very Satisfactory

FLT Enterprises 23039 Rehab. of Drainage System, Camp Delgado, Fort San Pedro 08/23/13 VI 3.395 60 C 0.460 0.133 0.300 - - - 89.30 89.30%

Very Satisfactory

FLT Enterprises 23039 REHAB OF VARIOUS NIS IN THE PROVINCE OF ILOILO, Package I - Santa Barbara RIS 04/05/14 NIA 4.130 120 O 0.336 0.245 0.150 0.030 0.038 0.050 84.90 -

FLT Enterprises 23039 Concreting of Various Canal Service RD Package 1 - Barotac Viejo RIS 08/31/13 NIA 4.869 120 O 0.280 0.240 0.000 0.025 0.056 0.050 65.10 -

FLT Enterprises 23039 Rehab. Of Various NIS in the Province of Iloilo, Package 1-Sta Barbara RIS 11/13/13 NIA 4.130 120 O 0.333 0.240 0.000 0.020 0.056 0.050 69.93 -

FLT Enterprises 23039 Rehab. Of Various NIS in the Province of Iloilo, Package 3-Aganan RIS 11/15/13 NIA 6.495 150 O 0.343 0.240 0.000 0.020 0.056 0.050 70.89 -

FLT Enterprises 23039 Proposed JRMP-2 Office 11/15/13 NIA 4.384 82 O 0.383 0.268 0.059 0.030 0.060 0.050 85.00 -

FOJAS BUILDERS ENTERPRISES 31869 Proposed Improvement of Roads and Drainage along M.Roxas St., (Suterto Delpan St.) 11/20/2014 NCR 6.540 120 C 0.450 0.133 0.300 - - - 88.30% 88.30%

Satisfactory

Forstone Construction Enterprises 31668 Repair of Lawa Flood Control, Lawa, Don Marcelino 08/09/12 XI 0.997 30 C 0.455 0.133 0.300 - - - 88.80 85.08% Satisfactory

FORTSTONE CONSTRUCTION ENTERPRISES 31668 Construction of 3 storey - 9 CL and 1-storey 2-CL School

Building, Fishing Village Comprehensive NHS 8/23/2014 XI 12.645 240 C 0.427 0.133 0.300 - - - 86.00% 86.00% Satisfactory

FORTSTONE CONSTRUCTION ENTERPRISES 31668

Construction of School Building a. 1-Storey 1-CL @ Migdolog ES; b. 1-Storey 2-CL @ John Martin Johnson HS,

Municipality of Don Marcelino, Davao Del Sur8/7/2014 XI 1.019 60 C 0.496 0.133 0.300 92.90 91.78%

Very Satisfactory

Fortstone Construction Enterprises 31668 Const. of Sch. Bldg. a. 1-storey 1-CL @ Migdolog ES; b. 1-storey 2-CL @ John Martin Johnson HS, Don Marcelino 08/17/13 XI 1.019 135 O 0.375 0.300 0.150 0.030 0.025 0.033 91.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page96

Page 97: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Fortstone Construction Enterprises 31668 Road Upgrading (gravel to paved0, Pangian-Pinalpalan-Demoloc Road Km.1618+768-Km.1619+028 03/21/12 XI 4.880 75 C 0.308 0.133 0.300 - - - 74.10 80.10%

Unsatisfactory

Fortstone Construction Enterprises 31668 Const. of 2 CL-School Bldg. Pongpong E/S 03/14/13 XI 1.194 60 C 0.408 0.133 0.300 - - - 84.10 84.10% Satisfactory

Foundation Specialists, Inc. 7437 Region I Contract Package (CP1)-CP1.1, Const. of Villamil Bridge & Approaches 08/14/12 PMO-Sp.

Bridges 89.221 458 O 0.400 0.300 0.101 0.030 0.065 0.033 92.90 -

FPJ Construction & Supply 28493 Improvement of Perimeter Fence 08/14/14 DOST 1.643 90 C 0.431 0.200 0.300 - - - 93.10 93.10% Very Satisfactory

FPJ Construction & Supply 28493 Repair/Rehab of ALA Building 08/14/14 DOST 1.988 90 C 0.492 0.200 0.300 - - - 99.20 99.20% Outstanding

FPJ Construction and Supply 28493Road Upgrading (Gravel to Paved) along Awang-Upi Lebak-

Kalamansig-Palimbang-Sarangani Rd. (Km.2002+815-Km.2002+975)

03/13/13 XII 4.452 37 C 0.404 0.133 0.300 - - - 83.70 83.70% Satisfactory

FRAMECON BUILDERS 22482 Local Infrastructure Program - Rehabilitation of Roads - P.Guevarra St. 11/24/2014 NCR 7.232 120 C 0.456 0.133 0.300 - - - 88.90% 88.90%

Satisfactory

FRAMECON BUILDERS 22482

Rehabilitation/Reconstruction of Damaged Paved National Roads Including Drainage based on Pavement

Management System/ HDM-4 (Intermittent Section) Plaridel - Pulilan Diversion Road, Km. 43+556 - Km. 44+036

11/24/2014 III 4.581 20 C 0.415 0.133 0.300 - - - 84.80% 84.80% Satisfactory

Framecon Builders 22482 Preventive Maintenance Gapan-San Fernando-Olongapo Road 9/26/2014 Special 3 13.190 55 C 0.435 0.136 0.300 87.10 87.10%

Satisfactory

FRAMECON BUILDERS 22482 Improvement of Lateral G-1, LTRIS 05/23/15 NIA 5.848 265 C 0.388 0.200 0.300 - - - - 88.81% Satisfactory

Framecon Builders 22482 Rehab. & Impv't. of Antonio Arnaiz Ave., (Int. Sect.) (Km 5+911-Km 6+411/Km7+458-Km8+021) 08/09/13 NCR 13.145 60 C 0.452 0.133 0.300 - - - 88.50 88.50%

Satisfactory

Framecon Builders 22482 Prev. Maint. along Pulilan-Calumpit Rd. Km.49+300-Km.50+232 08/14/13 III 5.223 44 C 0.439 0.133 0.300 - - - 87.20 87.20%

Satisfactory

Framecon Builders 22482 Const. of Two-Storey Four CL Sch. Bldg. at Northville 9 Elem. Sch. 08/14/13 III 4.592 150 O 0.342 0.240 0.150 0.020 0.047 0.033 83.20 -

Framecon Builders 22482Rehab., Reconst./Upgrading of Epifanio De Los Santos Avenue (EDSA), (Cluster D)(IS) (K0028+300-K0029+185 /

K0029+185-K0029+510)03/22/12 NCR 10.926 157 C 0.403 0.200 0.300 - - - 90.30 90.90%

Very Satisfactory

Framecon Builders 22482 Conc. of Road Brgy. Diversion of San Leonardo (1,162.75 L.M.) 03/20/12 III 9.553 160 O 0.337 0.200 0.240 - - - 77.70 87.06%

Satisfactory

Framecon Builders 22482 Rehab. of Roads along S. Pascual St., Brgy. San Agustin 03/15/13 NCR 4.844 37 C 0.422 0.133 0.300 - - - 85.50 85.50% Satisfactory

Framecon Builders 22482 Revetment along Angat River, Sipat 03/18/13 III 4.950 41 C 0.400 0.133 0.300 - - - 83.30 83.30% Satisfactory

Framecon Builders 22482 Rehab. of Talavera River, Installation of Spurdike (DOLOS) San Pascual Sect., San Pascual 11/26/12 III 9.649 140 C 0.325 0.200 0.300 - - - 82.50 82.26%

SatisfactoryFramecon Builders / Jerry R. Santiago Construction Joint

VentureJV-12-602 Const. of Digmala River Control Vega Sect., Sta. 0+000-

Sta.0+859.40 w/ exception (847.55 LM) 08/10/13 III 19.091 120 C 0.443 0.133 0.300 - - - 87.60 87.60% Satisfactory

FRD Construction 10227Rd. Upgrading of Bangkerohan-Galutan-Imelda-Mckinely

Rd., (Sta.747+300-Sta.749+500 & Sta.748+109.21-Sta.749+250)

03/21/13 VIII 72.744 310 C 0.406 0.134 0.300 - - - 84.00 82.92% Satisfactory

FRD Construction 10227Rehab./Reconst./Upgrading of Damaged Paved Nat'l

.Roads Canciledes-Manglos, Km.989+400-Km.998+245 w/ exceptions

03/29/12 VIII 48.241 350 C 0.428 0.133 0.300 - - - 86.10 84.81% Satisfactory

FRD Construction 10227 Rehab./Reconst./Upgrading of Wright-Taft Road (along Brgy. Binaloan-Brgy. San Pablo Road Sect.) w/ exception 03/30/12 VIII 57.889 300 C 0.418 0.133 0.300 - - - 85.10 84.32%

Satisfactory

FRD Construction 10227Rehab./Reconst.Upgrading of Damaged Paved Nat'l Rds., Brgy. Piliw-Brgy. Bacayawan, Km.983+500-Km.987+200 w/

exceptions08/20/12 VIII 48.152 380 C 0.357 0.133 0.300 - - - 79.00 73.51%

Poor

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page97

Page 98: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

FREDEN CONSTRUCTION 22665

Repair/Rehabilitation/Improvement (Additional Pavement Width with Drainage Improvement) of Digos-Makar Road,

K1652+(-167) to K1652+111 with exceptions, General Santos City

10/29/2014 XII 19.800 223 C 0.483 0.133 0.300 - - - 91.60% 91.60% Very Satisfactory

Freden Construction 22665

Reconst. of Critical Sect. along Nat'l. Rds. such as Slips Emergencies/Protection Works, Rd. Slip along Digos-

Makar Rd., Brgy. Batomelong Sect., K1634+431-K1634+453, Brgy. Batomelong

08/22/13 XII 9.350 165 C 0.484 0.133 0.300 - - - 91.70 91.70% Very Satisfactory

Full Blast Trading and Construction 29548 Const./Rehab. of Sch. Bldgs.: Maite E/S (One CL) 03/12/13 III 0.820 120 C 0.420 0.133 0.300 - - - 85.30 85.30%

SatisfactoryFull Blast Trading and

Construction 29548 Repair/Maint. of Sto. Domingo River Control (Sto. Domingo Sect.) 03/14/13 III 1.857 58 C 0.417 0.133 0.300 - - - 85.00 85.00%

SatisfactoryFuturistic Trading and

Construction 33597 Construction of Three (3) Storey Operating Room Complex, Phase 3 11/19/14 DOH 31.987 240 O 0.358 0.300 0.017 0.030 0.066 0.050 82.05 -

G. A. Flores Construction, Inc. 611 Marinduque Airport Development Project 05/29/14 DOTC 19.929 180 C 0.464 0.200 0.300 - - - - 95.70% Outstanding

G. C. BALLESTEROS Construction Balbalungao Small Reservoir Irrigation Project 05/23/15 NIA 1.024 153 O 0.384 0.300 0.030 0.023 0.051 0.050 83.78 -

G. F. ROVERO MERCHANDISING 27268 Construction of Pudiot Box Culvert along Aklan West Road, Brgy. Pudiot 10/10/2014 VI 7.056 211 C 0.421 0.133 0.300 - - - 85.40% 85.40%

Satisfactory

G. F. ROVERO MERCHANDISING 27268 Construction of Revetment Wall, Poblacion 10/10/2014 VI 4.725 160 O 0.352 0.202 0.150 0.030 0.055 0.050 83.90% 83.90% Satisfactory

G. V. Burton Builders & Supply 26804 Colocol Integrated CIS Rehabilitation & Extension Project 05/12/12 NIA 9.825 227 C 0.437 0.193 0.300 - - - 92.94 91.34% Very Satisfactory

G. V. Burton Builders & Supply 26804 Colocol Integrated CIS Rehabilitation & Extension Project 05/12/12 NIA 3.487 204 C 0.402 0.200 0.300 - - - 90.20 90.76% Very Satisfactory

G. V. Burton Builders & Supply 26804 Colocol Integrated CIS Rehabilitation & Extension Project 05/12/12 NIA 6.527 204 C 0.440 0.200 0.300 - - - 93.99 89.79% Very Satisfactory

G.A. Flores Construction, Inc 611 Marinduque Airport Development Project 04/02/14 DOTC 19.929 180 O 0.359 0.300 0.150 0.030 0.063 0.050 95.20 -

G.C.I Construction 11346 Road Upgrading (Gravel to Concrete) Gigmoto-Viga Rd., Phase II 08/17/10 V 74.100 285 O 0.334 0.300 0.150 0.022 0.042 0.050 89.80 -

G.C.I Construction 11346Upgrading (Gravel to Concrete) along Jct. CCR

Panganiban-Sabloyon Rd., Panganiban Sect. K0057+786 - K0060+755 w/ exception

08/17/10 V 48.170 269 O 0.337 0.300 0.150 0.022 0.035 0.050 89.40 -

G.C.I Construction 11346 Const. of San Vicente-Gutan-Lubak-Anguib Road,Phase V 02/25/09 II 20.259 330 O 0.267 0.300 0.150 0.030 0.035 0.050 83.20 -

G.C.I Construction 11346 Libmanan-Cabusao Embankment (Poblacion Revetment) 08/26/08 V 10.523 270 O 0.282 0.200 0.100 0.030 0.028 0.200 84.00 -

G.C.I Construction 11346 Road Upgrading of Libon-Bacolod-San Vicente-Marocmoc-Buga Road 05/28/09 V 19.230 134 O 0.326 0.240 0.150 0.030 0.040 0.050 83.60 -

G.C.I Construction 11346Rehab./Reconst. of Damaged National Road and Generated from Pavement Mgt. System (Highway Dev't & Mgt. HDM-4)

Jct. Bato-Baras Road03/04/09 V 19.180 301 O 0.361 0.300 0.150 0.030 0.061 0.050 95.20 -

G.C.I Construction 11346 Road Opening/Const. of Missing Links of Malinao-Buhi Road, (Buhi Side) 09/08/09 V 19.107 179 O 0.311 0.300 0.150 0.030 0.047 0.033 87.10 -

G.C.I Construction 11346 Quinali-Talisay River Flood Control Embankment & Channelization 02/26/10 V 38.400 417 O 0.360 0.300 0.105 0.030 0.050 0.033 87.80 -

G.C.I Construction 11346 Road Upgrading (Gravel to Concrete) Gigmoto-Viga Road, Phase II 02/25/10 V 74.100 270 O 0.349 0.245 0.150 0.030 0.050 0.050 87.40 -

G.C.I Construction 11346 Road Upgrading (Gravel to Concrete) Viga Panganiban-Bagamanoc Road 02/25/10 V 19.192 180 O 0.366 0.247 0.133 0.030 0.045 0.050 87.10 -

G.E.A Construction Corp. 10163 Road Upgrading at Abre de Ilog-San Jose Road (San Pedro-Mangat Section) Brgy. San Pedro 08/27/10 IVB 6.808 90 O 0.293 0.240 0.000 0.030 0.014 0.017 59.40 -

G.F Rovero Merchandising 27268 Impvt. of Access Road to Kalibo Airport 09/05/09 VI 8.032 244 O 0.378 0.300 0.150 0.030 0.025 0.033 91.60 -G.F. Falcis Construction and

Supply 26147 Const. of MPB at Bacauan-Mambatad Elem. Sch. 08/14/13 VI 3.799 150 C 0.476 0.133 0.300 - - - 90.90 85.30% Satisfactory

G.F. Falcis Construction and Supply 26147 Const. of MPB at Bacauan-Mambatad Elem. Sch. 03/17/13 VI 3.799 150 O 0.322 0.253 0.150 0.030 0.041 0.033 82.90 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page98

Page 99: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

G.F. Rovero Merchandising 27268 Construction of Aklan RIS (West) River Bank Protection 02/19/15 NIA 12.787 545 C 0.452 0.200 0.300 - - - 95.24 95.24% Very Satisfactory

G.F. Rovero Merchandising 27268 Widening of Aklan East Road (Kalibo Sect.) 08/17/13 VI 9.834 170 C 0.391 0.133 0.300 - - - 82.40 83.78% Satisfactory

G.F. Rovero Merchandising 27268 Widening of Aklan East Road (Kalibo Sect.) 03/19/13 VI 9.834 125 O 0.375 0.227 0.150 0.015 0.030 0.050 84.70 -

G.F. Rovero Merchandising 27268 Aklan River Irrigation System 11/15/13 NIA 9.069 C 0.417 0.200 0.300 - - - 91.67 88.27% Satisfactory

G.O. Marron General Contractor 6844 Construction of Multi-Purpose Building 8/4/2014 I 1.940 100 C 0.498 0.125 0.300 92.30 86.49% Satisfactory

G.O. Marron General Contractor 6844 Bacnotan Shallow Tube Wells 01/28/15 NIA 10.716 180 O 0.250 0.300 0.150 0.030 0.060 0.050 84.00 -

G.O. Marron General Contractor 6844 Const. of MPB 07/29/13 I 1.940 100 O 0.333 0.240 0.150 0.030 0.037 0.050 84.00 -

G.R. Bernales Construction & Supply 35849 Construction of Canal Structures of Rizal CIS 09/07/13 NIA 1.655 90 O 0.322 0.297 0.150 0.012 0.028 0.050 85.83 -

G.V Burton Builders 26804 Conc. of Aritao-Quirino Rd., Bitnong Sect. 06/07/10 II 9.646 180 O 0.345 0.300 0.150 0.024 0.042 0.033 89.40 -G.V. BURTON Builders &

Construction 26804 Colocol Integrated CIS Rehabilitation & Extension Project 10/24-29/11 NIA 3.286 120 O 0.364 0.285 0.150 0.030 0.033 0.050 91.14 -

G.V. BURTON Builders & Construction 26804 Colocol Integrated CIS Rehabilitation & Extension Project 11/07-12/11 NIA 11.240 180 O 0.378 0.240 0.141 0.024 0.070 0.050 90.27 -

G.V. Burton Construction 26804 Colocol Integrated CIS Rehabilitation & Extension Project 11/07-12/11 NIA 6.464 150 O 0.379 0.265 0.082 0.024 0.070 0.050 86.99 -

Gacutan Construction 10789 Construction of Dalakip-San Francisco Road 8/11/2014 II 7.425 79 C 0.364 0.190 0.300 85.40 85.40% Satisfactory

Gacutan Construction 10789 MARIIS Division 3 - Improvement Projects 07/27/12 NIA 9.251 120 O 0.400 0.300 0.103 0.030 0.016 0.050 89.90 -

GALENO CONSTRUCTION, INC. 3427 Construction of Standard One Storey School Building @ Magsaysay ES 10/25/2014 VI 1.010 88 O 0.368 0.242 0.150 0.015 0.042 0.033 85.00% 85.00%

Satisfactory

GALENO CONSTRUCTION, INC. 3427 Replacement of Alimango Bridge II along Bacolod Binalbagan, Negros Occidental 8/8/2014 VI 13.327 209 C 0.418 0.200 0.300 91.80 88.74%

Satisfactory

Galeno Construction, Inc. 3427 Replacement of Alimango Bridge II along Bacolod South Rd. 08/10/13 VI 13.327 209 O 0.346 0.240 0.150 0.030 0.051 0.050 86.70 -

Galeno Construction, Inc. 3427 Rehab./Reconst. along Guimbal-Tubungan Rd., Km 34+790-Km 35+290 08/14/13 VI 7.167 77 C 0.362 0.133 0.300 - - - 79.50 85.56%

Satisfactory

Galeno Construction, Inc. 3427 Rehab./Reconst. of Guimbal-Tubungan Rd., Km.34+790-Km.35+290 03/17/13 VI 7.167 77 O 0.364 0.252 0.150 0.030 0.050 0.050 89.60 -

Galeno Construction, Inc. 3427 Rehab./Reconst./Strengthening of Kabilukan Bridge along Dancalan-Candoni-Damutan Valley Rd., Brgy. Gatuslao 03/13/13 VI 13.621 276 C 0.397 0.197 0.300 - - - 89.40 85.68%

Satisfactory

GALLEGUEZ CONSTRUCTION 20942 Repair/Rehab of North Main Canal and Lat B at AMRIS (Baliuag Area) 08/15/15 NIA 39.314 180 C 0.416 0.121 0.300 - - - 83.62 83.62%

Satisfactory

Gane Tekno Builders 19528 Conc. of Brgy. Rd. (Agpo-Camagong Sect.) 08/02/13 V 0.934 20 C 0.397 0.200 0.300 - - - 89.70 89.70% Very Satisfactory

GAVER GENERAL MERCHANDISING 24186 Concreting of Farm to Market Road, Estancia, Kalibo,

Aklan 8/13/2014 VI 4.859 135 C 0.380 0.200 0.300 88.00 82.84% Satisfactory

Gaver General Merchandising 24186 Conc. of FMR, Estancia 08/17/13 VI 4.859 135 O 0.346 0.200 0.150 0.030 0.035 0.033 79.40 -

GC Ballesteros Construction 8598 Construction of New Canal with Lining @Buklod IA 07/27/13 NIA 4.746 75 O 0.350 0.240 0.150 0.025 0.056 0.050 87.07 -

GCI Construction and Development Corp. (Formerly: G.C.I.

Construction)11346

Rehab. of Sta. Margarita River Control along Taguntungan River Jct. Gattaran-Cumao-Capissayan-Sta. Margarita

Bolos Point Rd. (JGCCS-MBPR)07/30/13 II 13.567 169 O 0.397 0.240 0.150 0.030 0.043 0.033 89.30 -

GCI Construction and Development Corp. (Formerly: G.C.I.

Construction)11346

Const. of Tuguegarao City By-Pass inc. RROW, Sta.477+363.9-Sta.479+182.3 / Sta.484+248.833 (EQ):

Sta.483+232-Sta.484+541.5908/02/13 II 79.052 425 C 0.463 0.133 0.300 - - - 89.60 87.92%

Satisfactory

GCI Construction and Development Corp. (Formerly: G.C.I.

Construction)11346 Cagayan River Control Project, Brgy. Pata 08/05/12 II 75.084 306 O 0.348 0.300 0.150 0.030 0.045 0.050 92.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page99

Page 100: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

GCI Construction and Development Corp. (Formerly: G.C.I.

Construction)11346 Const. of Tuguegarao City By-Pass Rd., K0477+420-

EQ=K0479+182.3 (BK) / K0484+248.833 (AH) 08/05/12 II 74.479 285 O 0.370 0.300 0.080 0.030 0.055 0.033 86.80 -

GCI Construction and Development Corp. (Formerly: G.C.I.

Construction)11346 Rehab./Strengthening of Buntun Bridge, Cagayan-Apayao

Rd., Tuguegarao Sect., K0486+200 08/04/12 II 19.400 220 C 0.432 0.133 0.300 - - - 86.50 86.32% Satisfactory

GCI Construction and Development Corp. (Formerly: GCI Construction) 11346

Rehabilitation of Sta. Margarita River Control along Taguntungan River Jct. Gattaran-Cumao-Capissayan-Sta.

Margarita Bolos Point Roas (JGCCSMBPR)8/5/2014 II 14.282 169 C 0.399 0.133 0.300 83.20 86.86%

Satisfactory

GCI Construction and Development Corp. (Formerly: GCI Construction) 11346 Rehabilitaation/Improvement of Pili-Tigaon-Albay Bdry.

Road Pili-Ocampo Section 8/9/2014 V 73.350 293 C 0.403 0.200 0.300 90.30 87.60% Satisfactory

GCI Construction and Development Corp. (Formerly: GCI Construction) 11346 Construction/Rehabilitation/Improvement of Hibago Flood

Control 8/8/2014 V 44.075 179 OG 0.307 0.300 0.085 0.020 0.061 0.033 80.60 -

GCI. Construction & Development Corp. (Formerly: G.C.I.

Construction)11346 Camarines Sur-Albay Diversion Rd. (San Fernando-Oas

Sect. Of Pan Phil. Highway inc. Bridge) 03/21/13 V 91.706 420 C 0.475 0.133 0.300 - - - 90.80 90.62% Very Satisfactory

GCI. Construction & Development Corp. (Formerly: G.C.I.

Construction)11346 Rehab. of Daang Maharlika, K0446+724.36-K0455+013

(Intermittent Sect.) 03/24/13 V 46.899 177 C 0.384 0.197 0.300 - - - 88.10 88.22% Satisfactory

GCI. Construction & Development Corp. (Formerly: G.C.I.

Construction)11346 Asphalt Overlay along Daang Maharlika, K0452+000-

K0454+000 (Intermittent Sect.), Brgy. Anayan-Pawili 03/22/13 V 24.947 190 C 0.441 0.133 0.300 - - - 87.40 88.12% Satisfactory

GCI. Construction and Development Corp. 11346 Road Upgrading (Gravel to Conc.) along CCR, San Andres

Sect. K0169+277-K0173+300 08/16/11 V 48.170 264 O 0.342 0.300 0.145 0.012 0.033 0.017 84.90 -

GCI. CONSTRUCTION AND DEVELOPMENT CORP. (Formerly:

G.C.I. Construction)11346 Construction/Rehabilitation/Improvement of Hibago Flood

Control 11/11/2014 V 44.075 179 C 0.472 0.133 0.300 - - - 90.50% 84.56% Satisfactory

GCI. CONSTRUCTION AND DEVELOPMENT CORP. (Formerly:

G.C.I. Construction)11346 Preventive Maintenance (Intermittent Section Arterial)

along Rolando Andaya Highway 11/9/2014 V 38.805 119 C 0.479 0.133 0.300 - - - 91.20% 91.20% Very Satisfactory

GCI. Construction and Development Corp. (Formerly:

G.C.I. Construction)11346 Rehab./Reconst. of Damaged Nat'l Rd. (Int. Sect.-

Secondary), Sipocot-Cabusao Rd. K0400+800-K0401+385 08/03/13 V 11.619 119 C 0.398 0.198 0.300 - - - 89.60 89.60% Very Satisfactory

GCI. Construction and Development Corp. (Formerly:

G.C.I. Construction)11346 Prev. Maint.: Asphalt Overlay w/ Reblocking along Pili

Diversion Rd. (Int. Sect.) 08/06/13 V 9.228 54 C 0.362 0.200 0.300 - - - 86.20 86.20% Satisfactory

GCI. Construction and Development Corp. (Formerly:

G.C.I. Construction)11346

Camarines Sur/Albay Diversion Road (San Fernnado-Oas Sect. of the Pan Phil. Highway (PPH), Camarines Sur/Albay

inc. Bridges (Camarines Sur Sect.), Impv't./Upgrading of Salvacion Cristo Rey-Goyudan Rd. inc. Repair of Goyudan

Bridge Approaches & Slope Protection Works

08/07/13 V 47.199 220 C 0.395 0.155 0.300 - - - 85.00 85.00% Satisfactory

GCI. Construction and Development Corp. (Formerly:

G.C.I. Construction)11346 Conc. of Naga-Milaor Circ. & Rd. Right-of-Way Activities 08/05/13 V 47.043 240 C 0.436 0.133 0.300 - - - 86.90 88.28%

Satisfactory

GCI. Construction and Development Corp. (Formerly:

G.C.I. Construction)11346 Rehab./Impvt. of Pili-Tigaon-Albay-Bdry. Rd., Pili-Ocampo

Sect. 08/04/13 V 73.338 293 O 0.350 0.240 0.150 0.030 0.055 0.033 85.80 -

GCI. Construction and Development Corp. (Formerly:

G.C.I. Construction)11346 Rehab./Reconst. Of Damaged Nat'l Road along Sipocot-

Cabusao Road 03/23/12 V 24.470 150 C 0.410 0.200 0.300 - - - 91.00 89.56% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page100

Page 101: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

GCI. Construction and Development Corp. (Formerly:

G.C.I. Construction)11346 Rd. Upgrading (Gravel to Concrete) along CCR, San

Andres Sect., K0169+277-K0173+300 w/ exception 11/24/12 V 48.170 269 C 0.454 0.139 0.300 - - - 89.30 89.36% Very Satisfactory

GCI. Construction and Development Corp. (Formerly:

G.C.I. Construction)11346 Completion/Continuation of Unfinished Minali Bridge &

Approaches along Panganiban-Bagamanoc Rd. (Phase II) 11/24/12 V 34.549 329 C 0.460 0.133 0.300 - - - 89.30 86.54% Satisfactory

GCI. Construction and Development Corp. (Formerly:

G.C.I. Construction)11346 Conc. of Naga-Milaor Circ. & Road Right of Way Activities 08/14/12 V 47.043 180 O 0.374 0.240 0.150 0.030 0.065 0.033 89.20 -

GCI. Construction and Development Corp. (Formerly:

G.C.I. Construction)11346 Const./Upgrading of Seawall/Revetment/Dike 08/14/12 V 38.098 270 C 0.464 0.133 0.300 - - - 89.70 89.16%

Very Satisfactory

GCMG Construction 9743 Const./Impv't. of CCR Slope Protection Works Manuyog Sect. (Km.29+100-Km.30+035) 08/15/12 X 9.471 215 C 0.432 0.073 0.300 - - - 80.50 83.35%

SatisfactoryGEA Construction Corporation 10163 Laguindingan Airport Development Project 06/25/09 DOTC 22.360 180 O 0.400 0.300 0.150 0.020 0.039 0.050 95.90 -

Ged Construction 13614 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd., K0348+838-K0348+948, Alaminos-Bolinao Rd. 08/16/12 I 1.442 60 C 0.328 0.193 0.000 - - - 52.10 62.12%

Poor

GEED CONSTRUCTION 10823 Malimono Port Development Project 03/28/14 DOTC 4.717 60 C 0.417 0.200 0.300 - - - 91.70 91.70% Very Satisfactory

Geed Construction 10823Reconst. of Critiacal Sect. along Nat'l Rd. such as

Slips/Emergencies/Protection Works (Rd. Slip at Amag Hinayhayan Sect. along SDCR

03/24/12 XIII 17.779 200 C 0.480 0.133 0.300 - - - 91.30 87.10% Satisfactory

GEETY REALTY & DEVELOPMENT CORPORATION 30447

Const. of Flood Control/Drainage System along Carcar - Barili Road and Toledo - Barili - Santander Road,

K0060+591 - K0063+000, Brgy. Poblacion - Brgy. Sayaw10/28/2014 VII 26.659 217 C 0.341 0.200 0.300 - - - 84.10% 84.10%

Satisfactory

Geety Realty & Development Corporation 30447 Rd. Upgrading (Gravel to Paved) (Int. Sect.) Diversion Rd.,

Carcar Rotunda Heritage Area 08/05/13 VII 17.643 209 O 0.349 0.236 0.150 0.030 0.045 0.050 86.00 -

Geety Realty & Development Corporation 30447 Const. of Flood Control at Aloguinsan Bridge 08/07/13 VII 22.410 194 O 0.295 0.300 0.150 0.030 0.050 0.033 85.80 -

Geety Realty & Development Corporation 30447 Impv't. of Toledo-Pinamungajan-Aloguinsan-Mantalongon

Rd., K0082+500-K0083+084.97 (Selective Sects.) 03/17/13 VII 4.660 141 C 0.373 0.200 0.300 - - - 87.30 83.52% Satisfactory

Geety Realty & Development Orporation 30447

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved

National Road Standards (HDM-4 Project Analysis) (Intermittent Section) Diversion Road, Carcar Rotunda

Heritage Area

8/4/2014 VII 17.643 269 C 0.434 0.166 0.300 90.00 87.60% Satisfactory

Geety Realty & Development Orporation 30447-B

Road Upgrading (Gravel to Concrete) Based on Gravel Road Strategies, Traffic Benchmark (HDM-4 Project

Analysis), Tapal (Carcar) Zaragosa-Olango Road8/4/2014 VII 11.787 151 C 0.447 0.156 0.300 90.30 90.30%

Very Satisfactory

Geety Realty & Development Orporation 30447 Construction of Flood Control at Aloguinsan Bridge 8/6/2014 VII 22.410 165 C 0.414 0.200 0.300 91.40 88.04%

SatisfactoryGemma Construction Supply Inc.

(Formerly: Gemma Construction & Supply)

5044Rd. Upgrading (Gravel to Paved) along Demoloc-Little

Baguio-Alabel Rd,. Km.1649+800-Km.1650+920, Tayudan Sect.

03/14/13 XI 44.040 179 O 0.360 0.000 0.150 0.030 0.032 0.050 62.20 -

GEMMA CONSTRUCTION SUPPLY INC. (Formerly: Gemma Construction Supply)

5044

Assets Preservation of National Roads Preventive Maintenance Based on Pavement Management

System/Highway Development and Management-4 (HDM-4) along Dulawan-Marbel Road, K1751+00-K1752+003, K1755+723-K1756+563, Lambayong, Sulltan Kudarat

10/23/2014 XII 27.342 179 C 0.491 0.133 0.300 - - - 92.40% 92.40% Very Satisfactory

GEMMA CONSTRUCTION SUPPLY INC. (Formerly: Gemma Construction Supply)

5044

Assets Preservation of National Roads Preventive Maintenance Based on Pavement Management

System/Highway Development and Management-4 (HDM-4) along Kidapawan-Ala Jct. Road, K1672+027-K1673+321,

Tacurong City

10/23/2014 XII 44.732 179 C 0.485 0.133 0.300 - - - 91.80% 91.80% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page101

Page 102: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

GEMMA CONSTRUCTION SUPPLY INC. (Formerly: Gemma Construction Supply)

5044Rehabilitation/Reconstruction/Replacement/Retrofitting of Existing Permanent Bridges, Buayan Bridge along Buayan-

Glan Road, General Santos City10/29/2014 XII 38.786 204 C 0.464 0.133 0.300 - - - 89.70% 89.70%

Very Satisfactory

GEMMA CONSTRUCTION SUPPLY INC. (Formerly: Gemma Construction Supply)

5044 Completion of Permanent Bridge (Limulan Bridge) along Sen. Ninoy Aquino- Lebak - Kalamasig Road 8/14/2014 XII 8.328 92 C 0.470 0.133 0.300 90.30 90.30%

Very Satisfactory

GEMMA CONSTRUCTION SUPPLY INC. (Formerly: Gemma Construction Supply)

5044Construction of Revetment (River Bank Protection) along

Cotobato City Circumferencial Road (Down Stream & Upstream at Bubong Bridge Approach)

8/12/2014 XII 44.638 217 OG 0.398 0.240 0.150 0.022 0.040 0.050 90.00 -

Gemma Construction Supply Inc. (Formerly: Gemma Construction

Supply)5044

Asphalt Overlay of Cotabato-Lanao Rd. (Gang-Landasan-Parang Sect./Lamsan - Simuay Jct. Sect.) K1856+500-

K1858+859; K1862+750-K1863+14808/14/13 XII 44.735 100 C 0.417 0.200 0.300 - - - 91.70 91.70%

Very Satisfactory

Gemma Construction Supply Inc. (Formerly: Gemma Construction

Supply)5044

Rd. Upgrading (Gravel to Paved) along Demoloc-Little Baguio-Alabel Rd., Km.1649+800-Km.1650+920, Tayudan

Sect.08/07/13 XI 44.040 179 O 0.333 0.300 0.150 0.030 0.030 0.033 87.60 -

Gemma Construction Supply Inc. (Formerly: Gemma Construction

Supply)5044 Const. of Turn-Outs (Loading/Unloading Bay) along

Kidapawan-Ala Jct. Rd., Bo. 2 Km.1677+525-Km.1677+925 08/17/13 XII 5.822 95 C 0.443 0.176 0.300 - - - 91.90 90.10% Very Satisfactory

Gemma Construction Supply Inc. (Formerly: Gemma Construction

Supply)5044

Repair/Rehab./Impv't. along Kidapawan-Ala Jct. Road (EJC Montilla Sect.), Km.1677+525-Km.1677+785 (right side) &

Km.1677+665-Km.1677+925 (left side)08/17/13 XII 4.990 52 C 0.402 0.197 0.300 - - - 89.90 89.12%

Very Satisfactory

Gemma Construction Supply Inc. (Formerly: Gemma Construction

Supply)5044

Prev. Maint. (Int. Sect.); Nat'l. Arterial Rd., Marbel-Makar Rd., K1699+000-K1700+019, K1700+019-K1701+007,

K1703+1013-K1704+99408/06/13 XII 41.435 166 C 0.400 0.200 0.300 - - - 90.00 87.78%

Satisfactory

Gemma Construction Supply Inc. (Formerly: Gemma Construction

Supply)5044

Prev. Maint. (Int. Sect.): Nat'l. Secondary Rd.: Midsayap-Marbel Rd., K1785+997-K1786+992 & K1786+992-

K1789+02808/05/13 XII 27.897 115 C 0.360 0.196 0.300 - - - 85.60 85.12%

Satisfactory

Gemma Construction Supply Inc. (Formerly: Gemma Construction

Supply)5044

Rehab/Reconst/Upgrading of Damaged Paved Nat'l Rd. along Marbel-Makar Rd. K1710+530-K1710+290, K1709+260-K1708+300-K1707+410, K1707+420-K1706+520, K1706+500-

K1705+580

11/25/12 XII 36.899 268 C 0.492 0.200 0.122 - - - 81.40 85.90% Satisfactory

Gemma Construction Supply Inc. / Three W Builders, Inc. Joint

VentureJV-11-471

Rehab./Upgrading of Makilala-Allah Valley Junction Rd., Km 1634+324-Km 1635+225-Km 1634+444 ( with

exceptions)11/20/12 XII 73.256 290 O 0.372 0.300 0.022 0.030 0.060 0.050 83.40 -

Gemma Construction Supply, Inc. 5044 Const. of Isulan Highway Junction Dukay-Bagumbayan Sen. Ninoy Aquino Road (D' Lotilla Section) 03/03/10 XII 14.139 175 O 0.373 0.240 0.150 0.030 0.050 0.033 87.60 -

Gemma Construction Supply, Inc. (Formerly: Gemma Const. Supply) 5044 Reconst. of Bulok Bridge along Marbel-Makar Rd. 08/07/12 XII 15.519 224 C 0.497 0.133 0.300 - - - 93.00 89.28%

Very Satisfactory

Gemma Construction Supply, Inc. (Formerly: Gemma Construction

Supply)5044 Const. of Turn-Outs (Loading/Unloading Bay) along

Kidapawan-Ala Jct. Rd., Bo. 2, Km.1677+525-Km.1677+925 03/11/13 XII 5.822 95 O 0.341 0.290 0.150 0.030 0.045 0.033 88.90 -

Gemma Construction Supply, Inc. (Formerly: Gemma Construction

Supply)5044 Const. of Sebayor Bridge, Sta. Clara 03/14/13 XII 37.044 235 O 0.392 0.240 0.150 0.030 0.051 0.050 91.30 -

Gemma Construction Supply, Inc. (Formerly: Gemma Construction

Supply)5044

Rd. to Address Critical Bottlenecks Nat'l. Rd. Traffic Decongestion, Widening of Marbel-Cotabato Rd.,

K1724+200.6-K1727+100.603/20/13 XII 42.800 137 O 0.349 0.284 0.150 0.030 0.055 0.033 90.10 -

Gemma Construction Supply, Inc. (Formerly: Gemma Construction

Supply)5044

Repair/Rehab./Impv't. along Kidapawan-Ala Jct. Rd. (EJC Montilla Sect.), Km.1677+525-Km.1677+785 (Right Side)

and Km.1677+665-Km.1677+925 (Left Side)03/11/13 XII 4.912 32 O 0.323 0.300 0.150 0.030 0.050 0.033 88.60 -

Gemma Construction Supply, Inc. (Formerly: Gemma Construction

Supply)5044

Prev. Maint. (Intermittent Sect.); Nat'l Arterial Rd.; Marbel-Makar Rd., K1699+000-K17000+019, K1700+019-K1701+007,

K1703+1013-K1704+99403/20/13 XII 41.435 166 O 0.355 0.240 0.150 0.030 0.055 0.033 86.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page102

Page 103: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Gemma Construction Supply, Inc. (Formerly: Gemma Construction

Supply)5044 Prev. Maint. Marbel-Allah Valley-Cotabato Rd. (Km.1775+(-

736)-Km.1775+1002 & Km.1777+000-Km.1780+047) 03/12/13 XII 43.504 225 O 0.333 0.240 0.150 0.030 0.055 0.050 85.80 -

Gemma Construction Supply, Inc. (Formerly: Gemma Construction

Supply)5044

Prev. Maint. (Intermittent Sect.); Nat'l Secondary Rd.; Midsayap-Marbel Rd., K1785+997-K1786+992, K1786+992-

K1789+02803/20/13 XII 27.897 100 O 0.340 0.240 0.150 0.030 0.055 0.033 84.80 -

Gemma Construction Supply, Inc. / Three W Builder, Inc. (JV) JV-12-164

Rd. Upgrading (Gravel to Conc.) along Awang-Upi-Lebak-Kalamasig-Palimbang Rd. (Tambis-Sangay Sect.)

K01963+400-K01965+860 w/ exceptions, K01963+520-K01963+660

03/14/13 XII 121.170 390 O 0.399 0.299 0.150 0.030 0.037 0.033 94.80 -

Gemma ConstructionSupply 5044 Completion of MPB at Brgy. Kalanawi-I 06/02/09 R-XII 0.481 221 O 0.300 0.269 0.150 0.030 0.041 0.050 84.00 -

GENETIAN BUILDERS 18052 Construction of Flood Control Projects, Cavite 3rd LD, Construction of Flood Control in Imus River, Phase I 11/5/2014 IV 18.619 140 C 0.402 0.135 0.300 - - - 83.70% 83.70%

Satisfactory

GENETIAN BUILDERS 18052Construction/Rehabilitation of River/Flood Control

Structure at Sabang River, Siquijor Circumferential Road, K0006+908 (Upstream/Extension)

10/28/2014 VII 14.161 151 O 0.349 0.248 0.020 0.022 0.042 0.000 68.10% 68.10% Poor

GENETIAN BUILDERS 18052

Rehab/Reconst./Upgrading of Damaged National Road including draiange based on (PMS/HDM-4)(Intermittent Section) Jct. Aurora-Monte Alere-Jct. Labangan Road

K16533+461 - K1654+510

10/27/2014 IX 14.712 133 C 0.290 0.129 0.300 - - - 71.90% 71.90% Poor

GENETIAN BUILDERS 18052 Concreting of Road, Brgy. Bugo 10/25/2014 X 4.702 97 C 0.406 0.190 0.240 - - - 83.60% 83.60% Satisfactory

Genetian Builders 18052

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Roads, Intermittent Sections, Jct. Aurora-

Monte Alegre-Jct. Labangan Road K1650+923 - K1650+993; K1651+000 - K1652+790 - K1654+000

8/12/2014 IX 37.608 196 C 0.366 0.200 0.300 86.60 86.33% Satisfactory

GENETIAN BUILDERS 18052 Const.Concreting of Road Brgy. Lapasan, Cagayan de Oro City 8/4/2014 X 4.700 97 OG 0.382 0.300 0.150 0.030 0.050 0.050 96.20 -

Genetian Builders 18052Rehab./Reconst./Upgrading of Int. Sect., Jct. Aurora-Monte-

Jct. Labangan Rd., K1650+923-K1650+993; K1651+000- K1652+290 & K1652+790-K1654+000

08/17/13 IX 36.408 196 O 0.314 0.300 0.150 0.022 0.033 0.033 85.20 -

Genetian Builders 18052Const./Rehab./Impv't. of Lower Sibuguey Flood Protection along Lanao-Pagadian-ZC Rd. Balucanan-Salinding Sect.,

Phase II Km.2+240-Km.4+08008/08/13 IX 28.290 275 C 0.306 0.200 0.300 - - - 80.60 81.62%

Unsatisfactory

Genetian Builders 18052 Rehab./Const./Upgrading of Damaged Paved Nat'l Rds., Jimenez Old Route, Km.1724+1046-Km.1724+1287 08/14/13 X 2.715 75 C 0.043 0.133 0.000 - - - 17.60 39.56%

Poor

Genetian Builders 18052Rehab./Reconst./Upgrading of Int. Sect., Jct. Aurora-Monte-

Jct. Labangan Rd., K1650+923-K1650+993; K1651+000-K1652+290 & K1652+790-K1654+000

03/21/13 IX 36.408 106 O 0.380 0.240 0.150 0.030 0.038 0.033 87.10 -

Genetian Builders 18052Const./Rehab./Impv't. of Lower Sibuguey Flood Protection

along Lanao-Pagadian-Zamboanga City Rd., Balucanan-Salinding Sect., Phase II, Km.2+240-Km.4+480

03/15/13 IX 27.731 243 O 0.373 0.240 0.120 0.030 0.047 0.033 84.30 -

Genetian Builders 18052

Prev. Maint. along Jct. Dumalinao-Margosatubig Rd., Nat'l Secondary Rd. (Reblocking w/ Overlay 50mm) K1679+(-

833)-K1684+000 Realigned to K1678+(-111)-K1683+360 (Int. Sect.)

03/19/13 IX 20.990 51 C 0.376 0.200 0.000 - - - 57.60 61.20% Poor

Genetian Builders 18052 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Road along Dasmariñas-TMC Naic Road Km.44+478-Km.50+845 03/23/12 IVA 14.511 135 C 0.446 0.133 0.300 - - - 87.90 89.34%

Very Satisfactory

Genetian Builders 18052 Const. of Revetment Wall along Aklan River (Phase I) 11/25/12 VI 17.014 260 C 0.475 0.133 0.300 - - - 90.80 89.03% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page103

Page 104: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Genetian Builders 18052Const./Rehab./Impvt. of Lower Sibuguey Flood Protection along Lanao-Pagadian-Zamboanga City Rd., Balucanan-

Salinding Sect., Phase II, km.2+240-Km.4+48011/26/12 IX 27.731 170 O 0.351 0.300 0.030 0.030 0.059 0.033 80.30 -

Genetian Builders 18052 Const./Installation of New Drainage System along ICBR Rd., Velez-Burgos Sect. 11/24/12 X 15.478 270 C 0.445 0.133 0.300 - - - 87.80 85.46%

Satisfactory

Genetian Builders 18052 Const. of Revetment Wall along Aklan River (Phase I) 08/17/12 VI 17.014 275 O 0.358 0.240 0.150 0.030 0.035 0.050 86.30 -

Genetian Builders 18052 Widening/Concrete Paving of Ipil-Magdaup Wharf Rd. Pob. Ipil-Magdaup Sect., Km.2013+603-Km.1014+703 08/29/12 IX 30.625 210 C 0.436 0.200 0.300 - - - 93.60 91.74%

Very Satisfactory

Genetian Builders 18052Rehab./Impv't. of Nat'l Rd. along Lanao-Pagadian-Zamboanga City Rd. Gulinan Sect. w/ exception,

Km.1843+100-Km.1843+96408/30/12 IX 34.794 300 C 0.486 0.200 0.300 - - - 98.60 86.09%

Satisfactory

Genetian Builders 18052Const./Installation of New Drainage System along Iligan City-Cagayan de Oro City-Butuan City (ICBR Rd.), Velez-

Burgos Sect.08/06/12 X 15.484 265 O 0.331 0.300 0.150 0.020 0.035 0.050 88.60 -

Genetian Builders 18052 Rehab./Const./Upgrading of Jimenez Old Route, Km.1724+1046-Km.1724+1287 08/21/12 X 2.715 75 O 0.154 0.300 0.000 0.030 0.025 0.033 54.20 -

Geo Heart Construction and Trading 33316

Const./Rehab. Of Local Roads at Brgy. Amsic & Brgy. Mining Angeles City Sta. 0+000 - Sta. 0+304 (Amsic) & Sta.

0+000 - Sta. 0+304 (Mining), (Amsic) 304m (4m width) & (Mining) 304m (5m width), Angeles City

8/22/2014 III 4.229 40 C 0.467 0.133 0.300 90.00 90.00% Very Satisfactory

Geovan Marketing 10824 Const. of MPB, Barangay Cubay Sur 03/25/12 VI 1.918 90 C 0.458 0.200 0.300 - - - 95.80 90.10% Very Satisfactory

Gerra Construction 4326

Package X-G: Construction of Sub-laterals "N-6" (Sta. 4+500-Sta. 7+100) and "N-6E" (Sta. 0+000-Sta. 3+520) including related structures and supply, delivery and

installation of steel gates

02/07/15 NIA 22.922 180 O 0.324 0.287 0.150 0.015 0.023 0.050 85.01 -

Gerra Construction 29359 Dabubu River Irrigation Project 04/27/13 NIA 4.802 150 O 0.387 0.213 0.150 0.023 0.028 0.050 85.10 -

GES Construction 2011-1387 Calbiga Irrigation Project 11/22/14 NIA 8.865 150 C 0.457 0.200 0.300 - - - 95.71 95.71% Very Satisfactory

GES Construction 30299 Taripa CIS 10/6-10/08 PIO 1.012 90 O 0.359 0.238 0.100 0.015 0.029 0.100 84.14 -GES Construction 30299 Basey Irrigation Project 9/5-10/11 NIA 5.017 110 O 0.371 0.259 0.150 0.023 0.057 0.033 89.35 -

GG Mateo Construction 32168 Dibuluan River Irrigation Project 04/27/13 NIA 4.266 208 C 0.388 0.186 0.300 - - - 87.38 87.38% Satisfactory

Gicar Construction 12624 Rehab/Reconst./Upgrading of Damaged Paved Nat'l Road (IS) Surigao-Davao Coastal Road 11/23/12 XIII 42.659 300 C 0.419 0.194 0.300 - - - 91.30 89.38%

Very Satisfactory

GICAR CONSTRUCTION INC. (Formerly: Gicar Construction) 12624

Rehab./Reconst./Upgrading of Damaged Paved National Road including Drainage based on Pavement Management

System/Highway Development & Mangement-4 (HDM-4) (Intermittent Section), Sayre Highway, a. K1525+239 -

K1526+250 b. K1538+862 -K1539+695

8/5/2014 X 29.314 147 C 0.436 0.196 0.300 93.20 93.20% Very Satisfactory

GICAR CONSTRUCTION INC. (Formerly: Gicar Construction) 12624

Road Upgrading (Gravel to Paved) along Quezon - Mapawa - Capalayan - Espina - Navarro Rd. (Intermittent Sect.)

Km.1133+652 - Km.1134+5858/13/2014 XIII 23.548 210 C 0.410 0.098 0.300 80.80 84.04%

Satisfactory

Gicar Construction Inc. (Formerly: Gicar Construction) 12624 Flood Control Protection Works, Mainit Lakewall 08/08/13 XIII 16.849 150 C 0.397 0.133 0.300 - - - 83.00 83.00%

Satisfactory

Gicar Construction Inc. (Formerly: Gicar Construction) 12624

Rd. Upgrading (Gravel to Paved) along Quezon-Mapawa-Capalayan-Espina-Navarro Rd. (Int. Sect.) Km.1133+652-

Km.1134+58508/08/13 XIII 23.548 180 O 0.357 0.240 0.150 0.030 0.035 0.050 86.20 -

Gicar Construction Inc. (Formerly: Gicar Construction) 12624

Rd. Upgrading (Gravel to Paved) Gingoog-Claveria-Villanueva Rd. K01330+520-K01334+315, K01334+336-

K01337+096, K01337+311-K01338+50008/13/12 X 134.939 270 O 0.399 0.296 0.150 0.030 0.051 0.050 97.60 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page104

Page 105: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

GICAR CONSTRUCTION INC./SANTECH BUILDERS (J.V.) JV-12-391 Improvement/Upgrading (Gravel to Concrete) of NRJ

Lipata - Punta Bilar & Mabua Road, K1+620 - K4+295.75 8/13/2014 XIII 83.728 370 C 0.326 0.125 0.300 75.10 83.32% Satisfactory

GICAR CONSTRUCTION, INC. (Formerly: GICAR CONSTRUCTION) 12624 Widening of Bulua Bridge along Carmen-Patag-Bulua-Road 10/20/2014 X 22.316 195 O 0.307 0.235 0.125 0.015 0.037 0.033 75.20% 75.20%

UnsatisfactoryGICAR CONSTRUCTION, INC. (Formerly: 

GICAR CONSTRUCTION) 12624 Construction of Drainage System along Surigao City Wharf Road, Surigao City 10/26/2014 XIII 15.101 239 O 0.322 0.272 0.150 0.020 0.037 0.050 85.10% 85.10%

Satisfactory

GICAR CONSTRUCTION, INC. (Formerly: GICAR CONSTRUCTION) 12624

Construction/Improvement of Access Road Leading to Tourism Destinations, NRJ Lipata - Punta Bilar - Mabua Road, Leading to War Memorial Building and Pebbles

Beach Resort

10/28/2014 XIII 45.305 209 O 0.325 0.240 0.150 0.022 0.051 0.050 83.80% 83.80% Satisfactory

Gicar Construction, Inc. (Formerly: Gicar Construction) 12624

Rd. Upgrading (Gravel to Paved) Gingoog-Claveria-Villanueva Rd. K0133+520-K01334+315, K01334+336-

K01337+096, K01337+311-K01338+50008/22/13 X 134.939 380 C 0.364 0.191 0.300 - - - 85.50 84.63%

Satisfactory

Gicar Construction, Inc. (Formerly: Gicar Construction) 12624

Road Upgrading (Gravel to Paved), Gingoog-Claveria-Villanueva Rd., K01330+520-K01334+315, K01334+336-

K01337+096, K01337+311-K01338+50011/21/12 X 134.939 270 O 0.352 0.279 0.002 0.030 0.042 0.000 70.50 -

Gicar Construction, Inc. (Formerly: Gicar Construction) 12624 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd.,

(IS) Surigao-Davao Coastal Rd. 08/11/12 XIII 40.243 300 O 0.330 0.300 0.150 0.030 0.045 0.033 88.80 -

Gicar Construction, Inc. (Formerly: Gicar Construction) 12624 Rehab./Reconst. Damaged Paved Nat'l Rd., Km.1138+296-

Km.1141+000, Surigao-Agusan Rd. 08/08/12 XIII 36.818 410 C 0.406 0.133 0.300 - - - 83.90 85.13% Satisfactory

Gicar Construction, Inc. (Formerly: Gicar Construction) 12624 Conc. of NRJ Quezon-Mapawa-Capalayan-Espina-Navarro

Rd. 08/11/12 XIII 44.872 150 O 0.393 0.300 0.001 0.030 0.060 0.050 83.40 -

Gicar Construction, Inc. / Santech Builders (J.V.) JV-12-391 Impv't./Upgrading (Gravel to Concrete) of NRJ Lipata-

Punta Bilar & Mabua Rd., K1+620-K4+295.75 08/08/13 XIII 80.617 235 O 0.358 0.265 0.150 0.030 0.035 0.050 88.80 -

GIMP VENTURES 33025 Construction/Expansion of Barangay Health Station (BHS), Brgy. 6 10/24/2014 VI 0.965 72 O 0.366 0.240 0.150 0.030 0.056 0.033 87.50% 87.50%

Satisfactory

GIOVANNI CONSTRUCTION 12168Widening of National Road along Daang Maharlika (Agusan

- Davao Section) S00439MN K1307+493 - K1309+138.10 (Intermittent Section)

10/23/2014 XIII 36.670 256 O 0.302 0.288 0.150 0.023 0.047 0.050 86.00% 86.00% Satisfactory

GIOVANNI CONSTRUCTION 12168 Construction of Crossing Luna Flood Control 10/22/2014 XIII 15.679 249 C 0.440 0.133 0.300 - - - 87.30% 87.30% Satisfactory

GIOVANNI CONSTRUCTION 12168Widening of National Road along Daang Maharlika (Agusan - Davao Section) K1307+493 - K1309+138.100 (Intermittent

Section)8/8/2014 XIII 36.670 226 OG 0.345 0.216 0.150 0.020 0.035 0.050 81.60 -

GIOVANNI CONSTRUCTION 12168 Construction of Crossing Luna Flood Control 8/6/2014 XIII 36.670 189 OG 0.319 0.225 0.150 0.023 0.033 0.050 80.00 -

Giovanni Construction 12168Rd. Upgrading from Gravel to Concrete along Butuan City-

Talacogon, Loreto-Veruela-Sta. Josefa Rd. (K1332+897-K1333+869)

08/21/13 XIII 24.002 461 C 0.394 0.133 0.300 - - - 82.70 82.88% Satisfactory

Giovanni Construction 12168Rd. Upgrading from Gravel to Concrete along Butuan City-

Talacogon-Loreto-Veruela-Sta. Josefa Rd., K1332+897-K1333+869

03/20/13 XIII 24.002 449 O 0.317 0.300 0.150 0.030 0.041 0.050 88.80 -

Giovanni Construction 12168Rd. Upgrading from gravel to concrete along Butuan City-

Talacogon-Loreto-Veruela-Sta. Josefa Rd. K1332+897-K1333+869

11/28/12 XIII 24.002 354 O 0.381 0.300 0.001 0.030 0.060 0.000 77.20 -

Global V Builders Company 29763 Rehabilitation of Reception Area Building A, Annex 09/12/13 BSP 8.663 102 C 0.492 0.200 0.066 - - - 75.80 82.50% Satisfactory

Global V Builders Company 29763 Rehabilitation of Reception Area Building A, Annex 04/30/13 BSP 8.663 102 O 0.392 0.283 0.072 0.030 0.044 0.033 85.40 -

GLS Construction and General Merchandise 34233 Const. of Sch. Bldg., Mitazan IS 08/14/13 X 0.641 105 C 0.487 0.133 0.300 - - - 92.00 92.00%

Very SatisfactoryGLS Construction and General

Merchandise 34233 Const. of Sch. Bldg., Banisilon PS 08/14/13 X 0.628 105 C 0.487 0.133 0.300 - - - 92.00 92.00% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page105

Page 106: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

GLS Construction and General Merchandise 34233 Replacement of Bridges along Nat'l Rds. (Temporary to

Permanent) Bagacay Bridge along Bagacay Cadre Rd. 08/16/13 X 3.440 120 C 0.440 0.133 0.300 - - - 87.30 87.30% Satisfactory

GMP Builders 35448 Const./Impv't. of Brgy. Guintiguian FMR 03/14/13 VIII 1.449 37 C 0.475 0.141 0.300 - - - 91.60 91.60% Very Satisfactory

GOLD RICH CONSTRUCTION & TRADING (Formerly: Gold Rich

Construction)16489

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Roads including Drainage based on

Pavement Management System/Highway Development and Management-4 (HDM-4) (Intermittent Sections), Quirino

Highway (Baguio-Bauang Road), KO299+086-KO303+776 with exception

11/17/2014 CAR 42.047 190 O 0.323 0.277 0.150 0.030 0.055 0.033 86.80% 86.80% Satisfactory

GOLD RICH CONSTRUCTION & TRADING (Formerly: Gold Rich

Construction)16489

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Roads including Drainage based on

Pavement Management System/Highway Development and Management-4 (HDM-4) (Intermittent Sections), Rimando-

Ambiong Road, Chainage 0000 -Chainage 2402

11/17/2014 CAR 41.961 190 O 0.346 0.275 0.150 0.030 0.050 0.033 88.40% 88.40% Satisfactory

GOLD RICH CONSTRUCTION & TRADING (Formerly: Gold Rich

Construction)16489

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Roads including Drainage based on

Pavement Management System/Highway Development and Management-4 (HDM-4) (Intermittent Sections), Kennon

Road, KO244+360-KO0247+300 with exception

11/17/2014 CAR 41.951 215 O 0.348 0.258 0.150 0.030 0.050 0.050 88.60% 88.60% Satisfactory

Gold Rich Construction & Trading (Formerly: Gold Rich Construction) 16489

Opening/Impv't. of Baguio Circ. Rd. (Western Link), Sect. 1: Kennon Rd. Jct. to Montecillo, K0245+440-K0245+957,

Sect. 2: Ciudad Grande to Saint Louis University, K0245+1748-K0245+1910, Sect. 3: Bakakeng to Balacbac,

K0247+766-K0248+223.61, Sect. 4: Balacbac to Marcos Highway, (248+1875-248+2347) & Sect. 5: Happy Hallow

(246+1690-246+3860) Eastern Link

03/24/13 CAR 38.762 402 O 0.387 0.240 0.150 0.030 0.056 0.033 89.60 -

Gold Rich Construction & Trading (Formerly: Gold Rich Construction) 16489 Rehab./Reconst./Upgrading of Damaged Paved Nat'l

Roads, Loakan Rd. K0247+835-K0247+203.5 03/22/12 CAR 18.496 267 C 0.413 0.133 0.300 - - - 84.60 85.80% Satisfactory

Gold Rich Construction & Trading (Formerly: Gold Rich Construction) 16489 Rehab./Reconst./Upgrading of Damaged Paved Nat'l

Roads, Bokawkan Road, K00+000-K01+150 03/22/12 CAR 18.720 100 C 0.426 0.133 0.300 - - - 85.90 85.66% Satisfactory

Gold Rich Construction & Trading (Formerly: Gold Rich Construction) 16489 Conc. of M. Roxas-Leonard Wood Rd. 03/24/13 CAR 15.210 120 C 0.434 0.133 0.300 - - - 86.70 86.70%

Satisfactory

Gold Rich Construction & Trading (Formerly: Gold Rich Construction) 16489 Completion/Continuation of Perimeter Fence at Burnham

Park 03/23/13 CAR 4.830 60 C 0.394 0.136 0.300 - - - 83.00 83.00% Satisfactory

Golden Construction and Supply 35001 Conc. of FMR, Brgy. Bagumbayan 08/08/13 V 0.987 30 C 0.380 0.200 0.300 - - - 88.00 88.00% Satisfactory

Golden Ridge Enterprises & Engineering 29946 Sual Port Development Project 12/12/12 PPA 80.608 450 C 0.490 0.200 0.300 - - - 99.00 95.60%

Very Satisfactory Golden Ridge Enterprises and

Engineering Services 29946 Sual Port Development Project 08/28/12 PPA 80.608 390 O 0.393 0.300 0.112 0.030 0.065 0.033 93.33 -

Golden Roadrunner International Corporation 10177 Maint./Repair/Rehab. of Flood Control along Ayuyan-

Tinaytayan Rd., Dangula Sect. 08/19/13 VI 10.698 107 C 0.497 0.133 0.300 - - - 93.00 93.00% Very Satisfactory

Golden Tech Construction 14820 Addalam River Irrigation Project 04/27/09 05/01/09 NIA 9.792 370 O 0.325 0.240 0.150 0.023 0.038 0.050 82.57 -Goldenville Realty and

Development CorporationLand Development and Construction of Housing Units

(Villa Sofia) 5/3/2015 NHA 184.311 240 O 0.283 0.162 0.150 0.020 0.040 0.050 70.45 -

Goldrich Construction 16489 Masantol River Wharf (Phase 2) Improvement Project 7/1-4/08 PPA 16.879 120 O 0.362 0.240 0.100 0.015 0.035 0.067 81.84 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page106

Page 107: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Goldrich Construction 31884 Repair of retaining Wall, Mooring and Fendering System 10/25-27/11 PPA 17.960 240 O 0.374 0.254 0.093 0.030 0.047 0.050 84.75 -

GOLDRICH CONSTRUCTION & TRADING 16489

Asset Preservation (Prevent Maint-HDM-4) Along a) Kisad Rd, K0249+(-038)-K0249+222: b) Leonard Wood Rd, K0252+600-K0252+980; c) PMA Rd, Chainage 0000-Chainage 0110; d) Gov't Center Rd, Chainage 0000-Chainage 0102; e) Gov't Cener Rd, Chainage 0000-Chainage 0141; f) Gov't Center Rd, Chainage 0141-

Chainage 0185

8/15/2014 CAR 3.326 50 C 0.479 0.133 0.300 91.20 91.20% Very Satisfactory

Goldrich Construction & Trading (Formerly: Gold Rich Construction) 16489

Replacement/Rehab./Strengthening of Permanent Bridges along Nat'l Rds. Ferguson Bridge 2 along Ferguson Rd. & Rehab./Reconst./Conc. of its Approaches, K0306+1257-

K0305+1510

08/16/13 CAR 8.695 190 C 0.463 0.133 0.300 - - - 89.60 89.60% Very Satisfactory

Goldrich Construction & Trading (Formerly: Gold Rich Construction) 16489 Prev. Maint. (Int. Sect.) along Loakan Rd., K0245+1227-

K0245+1665 08/16/13 CAR 15.818 132 C 0.453 0.133 0.300 - - - 88.60 88.60% Satisfactory

Goldrich Construction & Trading (Formerly: Gold Rich Construction) 16489

Opening/Impv't. of Baguio Circ. Rd. (Western Link) Sect. 1:Kennon Rd. Jct.-Montecillo, K0245+440-K0245+957, Sect.

2:Ciudad Grande-St. Louis University, K0245+1748-K0245+1910, Sect. 3:Bukakeng-Balacbac, K0247+766-K0248+223.61, Sect. 4:Balacbac to Marcos Highway,

(248+1875-248+2347) & Sect. 5:Happy Hallow (246+1690-246+3860) Eastern Link

08/16/13 CAR 38.762 431 C 0.451 0.133 0.300 - - - 88.40 89.12% Very Satisfactory

GOLDROCK CONSTRUCTION & DEVELOPMENT CORP. 5389

Road Upgrading (Gravel to Concrete) of El Nido Junction - New Ibajay Road (Intermittent Section), Sta. 284+968 to

Sta. 295+337.50 ( w/ exceptions)11/21/2014 IV 103.231 346 O 0.379 0.240 0.150 0.030 0.043 0.050 89.20% 89.20%

Very Satisfactory

Goldrock Construction & Development Corp. 5389 Road Upgrading (Gravel to Paved) El Nido Junction, New

Ibajay Road, K0328+268 to K0328+810.50 8/6/2014 IV-B 10.964 411 C 0.460 0.134 0.300 89.40 87.12% Satisfactory

Goldrock Construction & Development Corp. 5389 Road Upgrading (Gravel to Paved) El Nido - Junction New

Ibajay Road, K0281+756 to K0284+810 8/7/2014 IV-B 44.930 411 C 0.447 0.133 0.300 88.00 88.30% Satisfactory

Goldrock Construction & Development Corp. 5389 Rd. Upgrading (Gravel to Paved) Jct. New Ibajay Rd.

K0281+756 to K0284+810 08/10/13 IVB 41.168 271 O 0.360 0.235 0.150 0.030 0.060 0.050 88.50 -

Goldrock Construction & Development Corp. 5389 Rehab./Upgrading (Conc.) of Taytay-El Nido Rd.

(Km.210+557-Km.215+406) 08/09/13 IVB 107.307 479 C 0.424 0.133 0.300 - - - 85.70 88.18% Satisfactory

Goldrock Construction & Development Corp. 5389

Const./Widening/Upgrading/Rehab. of Access Rd. Conc. of Taytay (Pancol)-El Nido Rd. (Km.215+900-Km.217+240;

Km.217+540-Km.220+881) w/ exception Taytay Sect.08/09/13 IVB 90.224 479 O 0.372 0.300 0.092 0.030 0.051 0.017 86.20 -

Goldrock Construction & Development Corp. 5389 Rd. Upgrading (gravel to paved) El Nido Jct., New Ibajay

Rd., K0328+268-K0328+810.50 08/10/13 IVB 10.465 271 O 0.341 0.234 0.150 0.030 0.051 0.050 85.60 -

Goldrock Construction & Development Corp. 5389

Const./Widening /Upgrading/Rehab. of Access Rd. Conc. of Taytay-El Nido Rd. (Km.254+910-Km.259+000 w/

exception)08/09/13 IVB 93.176 509 O 0.372 0.300 0.027 0.030 0.051 0.017 79.70 -

Goldrock Construction & Development Corp. 5389

Const./Widening/Upgrading/Rehab. of Access Rd., Conc. of Taytay (Pancol)-El Nido Rd. (Km.215+000-Km.217+240;

Km.217+540-Km.220+881 w/ exception), Taytay Sect.03/12/13 IVB 90.224 420 O 0.362 0.300 0.050 0.030 0.055 0.050 84.70 -

Goldrock Construction & Development Corp. 5389

Const./Widening/Upgrading/Rehab.on of Access Rd., Conc. of Taytay-El Nido Rd. (Km.254+910-Km.259+000 w/

exception)03/12/13 IVB 93.176 450 O 0.381 0.300 0.056 0.030 0.045 0.017 82.90 -

Goldrock Construction & Development Corp. 5389 Rehab./Upgrading (Conc.) of Taytay-El Nido Road

Km.210+557-Km.215+40 03/15/12 IVB 100.129 330 O 0.364 0.300 0.150 0.030 0.060 0.050 95.40 -

Goldrock Construction & Development Corp. 5389 Rehab./Upgrading (Conc.) of Taytay-El Nido Rd.

(Km.210+557-Km.215+406) 11/22/12 IVB 107.307 420 O 0.322 0.285 0.150 0.030 0.055 0.050 89.20 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page107

Page 108: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Goldrock Construction & Development Corp. 5389

Const./Widening/Upgrading/Rehab. of Access Rd., Conc. of Taytay (Pancol)-El Nido Rd. (Km.215+900-Km.217+240;

Km.217+540 -Km.220+881 w/ exceptions), Taytay Sect.11/23/12 IVB 82.402 381 O 0.363 0.286 0.119 0.030 0.055 0.033 88.60 -

Goldrock Construction & Development Corporation 5839

Const./Widening/Upgrading/Rehab. of Access Road Conc. of Taytay (Pancol)-El Nido Road (Km.215+900-Km.217+240;

Km.217+540-Km.220+881 w/ exception, Taytay Sect.08/03/12 IVB 82.402 330 O 0.367 0.300 0.150 0.030 0.045 0.033 92.50 -

Goldrock Construction & Development Corporation 5389 Rehab./Upgrading (Conc.) of Taytay-El Nido Rd.

Km.210+557-Km.215+406 08/03/12 IVB 100.129 349 O 0.296 0.300 0.150 0.030 0.040 0.033 84.90 -

Goldrock Construction & Development Corporation 5389 Const. of Barutuan Br. I Flood Control Structures along El

Nido Jct.-New Ibajay Rd., Km. 291+797 08/04/12 IVB 11.882 144 C 0.362 0.133 0.300 - - - 79.50 84.84% Satisfactory

GONZALO CONSTRUCTION 1826Upgrading/Improvement along Ambiong-Lubas Road (Benguet Section), K0253+560 to K0259+035 (v.s.), La

Trinidad, Benguet8/14/2014 CAR 49.000 360 C 0.414 0.133 0.300 84.70 86.50%

Satisfactory

GONZALO CONSTRUCTION 1826Rehab./Reconst./Upgrading of Daamaged Paved National

Roads (Intermittent Section) (Package XIV-2012), Kapangan, Benguet

8/13/2014 CAR 8.461 201 C 0.409 0.133 0.300 84.20 84.20% Satisfactory

Gonzalo Construction 1826 Upgrading/Impv't. along Ambiong-Lubas Rd., (Benguet Sect.) K0253+560-K0259+035 (v.s.) 07/29/13 CAR 45.596 209 O 0.379 0.300 0.080 0.030 0.055 0.033 87.70 -

Gonzalo Construction 1826 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. (Int. Sect.) (Package XIV-2012) 07/31/13 CAR 8.461 201 O 0.360 0.239 0.147 0.015 0.045 0.033 83.90 -

Gonzalo Construction 1826 Replacement of Bolo Bridge along Gurel-Bokod-Kabayan-Buguias-Abatan Rd., K0300+569 07/30/13 CAR 22.037 225 O 0.377 0.240 0.045 0.023 0.050 0.017 75.20 -

Gonzalo Construction 1826 Rehab./Reconst./Strengthening of Salacop Bridge 03/14/13 CAR 22.269 285 C 0.420 0.133 0.300 - - - 85.30 83.38% Satisfactory

Gonzalo Construction 1826 Rehabilitation/Reconstruction of Damanged Road along Abra-Kalinga Road 02/25/09 CAR 14.328 200 O 0.159 0.000 0.114 0.000 0.025 0.000 29.80 -

GONZALODO ENTERPRISE 30681 Const. of three (3) Storey, Nine (9) Classroom School Building at Basak Elementary School, Lapu - Lapu City 8/8/2014 VII 10.775 180 C 0.433 0.148 0.300 88.10 87.19%

Satisfactory

Gonzalodo Enterprises 30681Conc. of Rd. at Brgy. Opao, Mandaue City, Cebu (Proposed

for Modification to Asphalting of Rd. at Brgy. Opao, Mandaue City w/ Drainage Facilities)

08/12/13 VII 3.181 60 C 0.443 0.133 0.300 - - - 87.60 87.60% Satisfactory

Gonzalodo Enterprises 30681 Const. of Three (3) Storey, Nine (9) Cl Sch. Bldg. at Basak Elem. Sch. 08/12/13 VII 10.775 180 O 0.360 0.240 0.150 0.030 0.055 0.033 86.80 -

Gonzalodo Enterprises 30681Rehab./Reconst. Of Damaged Paved Nat'l Rds. at Pajo-

Basak-Marigondon Rd., Km.11+-(624)-Km.12+000, Km.12+000-Km.12+67

08/23/12 VII 12.944 99 C 0.423 0.133 0.300 - - - 85.60 82.24% Satisfactory

Gonzalodo Enterprises 30681 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. at Ferry Landing Rd, Chainage 0000-Chainage 0126 03/21/13 VII 2.070 30 C 0.452 0.133 0.300 - - - 88.50 88.50%

Satisfactory

Good Fortune International Incorporated 9246 Concreting of Lemery-San Rafael Road 09/08/09 VI 28.639 430 O 0.312 0.300 0.150 0.023 0.050 0.050 88.50 -

Good Fortune International, Inc. 9246 Aganan Sta. Barbara RIS (Rehabilitation of Aganan Sta. Barbara RIS Aganan Area Lateral D Bench Flume) 01/10-15/2011 NIA 3.586 120 O 0.3816 0.2400 0.0907 0.0300 0.0509 0.0500 84.32 -

Good Fortune International, Incorporated 9246

Rd. Upgrading (Gravel to Paved) of Nat'l Sec. Rd., Guimbal-Igbaras-Tubungan-Leon Rd., K0066+727-K0067+460

(K0066+727-K0067+591)08/22/13 VI 13.806 105 C 0.429 0.133 0.300 - - - 86.20 86.20%

Satisfactory

Good Fortune International, Incorporated 9246 Conc. of Lambunao-Inca Rd., Km.0057+031-Km.0057+814 08/23/12 VI 17.303 180 O 0.358 0.285 0.150 0.030 0.030 0.050 90.30 -

Good Fortune International, Incorporated 9246 Rehab./Impvt. of Mandurriao-San Miguel-Alimodian-Maasin-

Cabatuan Rd., K0012+200-K0014+728 w/ exception 08/24/12 VI 19.670 89 C 0.478 0.142 0.300 - - - 92.00 88.94% Satisfactory

Good Fortune International, Incorporated 9246 Prev. Maint. of Sara-San Dionisio Rd., K0203+962-

K0206+000, w/ exceptions 03/21/13 VI 13.416 45 C 0.416 0.127 0.300 - - - 84.30 84.30% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page108

Page 109: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Goodvibe Builders, Inc. 32686 Const. of Brgy. Rd. at La Paz 08/09/13 I 3.994 84 C 0.490 0.133 0.300 - - - 92.30 87.26% Satisfactory

Goodvibe Builders, Inc. 32686 Const. of Barangay Road at La Paz 03/13/13 I 3.994 84 O 0.306 0.300 0.150 0.015 0.035 0.033 83.90 -Goodvibe Builders, Inc. 32686 Widening of MNR, Urdaneta-Villasis Section 05/19/09 I 7.237 620 O 0.367 0.218 0.150 0.030 0.030 0.050 84.50 -

GOWIL BUILDERS 18733

Preventive Maintenance Based on Pavement Management System Highway Development Management-4 (HDM-4), National Secondary Road, Borromeo St., , C0000-C0645,

Cebu City

8/9/2014 VII 14.165 70 C 0.473 0.134 0.300 90.70 90.70% Very Satisfactory

Gowil Builders 18733Const. of Geometric Alignment of Roadway along Cebu-

Balamban Transcentral Highway, K0038+(-47)-K0039+950, Int. Sect. (w/ exception)

08/08/13 VII 42.110 275 O 0.378 0.274 0.150 0.030 0.055 0.050 93.70 -

Gowil Builders 18733 Const. of Storm Drainage & Canal along Toledo-Tabuelan-San Remegio Rd., K0062+000-K0068+700 (Int. Sect.) 08/07/13 VII 7.071 185 C 0.440 0.200 0.300 - - - 94.00 83.65%

Satisfactory

Gowil Builders 18733Const. of Geometric Alignment of Roadway along Cebu-

Balamban Transcentral H-way, K0038+(-47)-K0039+950, Int. Sect. (w/ exception)

03/17/13 VII 42.110 275 O 0.387 0.298 0.150 0.030 0.032 0.033 93.00 -

Gowil Builders 18733 Const. of Storm Drainage & Canal along Toledo-San Remegio Rd., K0062+00-K0062+78 (Int. Sect.) 03/17/13 VII 7.071 152 O 0.376 0.240 0.000 0.030 0.032 0.017 69.50 -

Gowil Builders 18733 Const. of Storm Drainage & Canal along Toledo-San Remegio Rd., K0062+00-K0068+78 (IS) 11/23/12 VII 7.071 137 O 0.391 0.240 0.111 0.030 0.035 0.033 84.00 -

Gr8t Builders and Supplies 33078 Repair/Rehab. of Bridge Approaches, Bank Revetment (Binatagan Rd. Sect.) 11/25/12 V 6.999 140 C 0.400 0.200 0.300 - - - 90.00 85.38%

Satisfactory

Gr8t Builders and Supplies 33078 Repair/Rehab. of Bridge Approaches, Bank Revetment (Binatagan Rd. Sect.) 08/07/12 V 6.725 120 O 0.341 0.240 0.150 0.030 0.029 0.033 82.30 -

Grace Const. Corp./Dipolog Top Const. Dev't. Corp (JV) JV-08-016 Dipolog Airport Development Project 09/02/09 DOTC 0.163 360 O 0.368 0.300 0.150 0.030 0.051 0.050 94.90 -

GRACE CONSTRUCTION CORPORATION 14-02197 Proposed Plaridel Port Improvement, Port of Plaridel 12/04/15 PPA 92.903 360 O 0.397 0.300 0.115 0.030 0.070 0.050 96.18 -

GRACE CONSTRUCTION CORPORATION 3771 Construction of Cagayan de Oro Coastal Road, (By-Pass

Road) including ROW, First District 8/16/2014 X 46.243 270 C 0.435 0.200 0.300 93.50 87.26% Satisfactory

Grace Construction Corporation 3771 Maint., Rehab. & Impv't. of Nat'l Rds. along Oroquieta City-Calamba Mt. Rd., K1753+275-K1754+610 w/ exceptions 08/14/13 X 9.356 45 C 0.401 0.133 0.300 - - - 83.40 83.40%

Satisfactory

Grace Construction Corporation 3771 Const. of Cagayan de Oro Coastal Rd., (By-Pass Rd.) inc. ROW First District 08/11/13 X 46.974 209 O 0.312 0.300 0.119 0.030 0.037 0.033 83.10 -

Grace Construction Corporation 3771 Const. of Upper Manakulil Bridge (Phase 1) along Cotabato City Circ. Rd. 08/13/13 XII 24.906 329 C 0.443 0.133 0.300 - - - 87.60 87.30%

Satisfactory

Grace Construction Corporation 3771 Reconst. of Kalaw Bridge 08/18/11 XI 94.331 632 O 0.400 0.300 0.055 0.030 0.050 0.033 86.80 -

Grace Construction Corporation 3771 Const. of One (1) RCDG Bridge (Piacan) & (1) Spillway (Sibuco) along Zamboanga West Coast Road 08/09/11 IX 128.835 887 O 0.345 0.240 0.150 0.030 0.045 0.033 84.30 -

Grace Construction Corporation 3771 Reconst. of Kalaw Bridge 04/10/11 XI 94.331 632 O 0.377 0.300 0.150 0.030 0.060 0.050 96.70 -

Grace Construction Corporation 3771 Const. of Lobog Parallel Bridge and Approaches (Phase IV) 06/02/10 X 52.566 441 O 0.379 0.300 0.150 0.030 0.047 0.033 93.90 -

Grace Construction Corporation 3771Const. of Upper Makar Bridge No.1 Phase IV (Completion

of Abutment "A" and Const. of 4 spans, 30 LM PSCG Superstructure) along Circumferential Rd.

03/10/10 XII 47.371 240 O 0.343 0.253 0.150 0.030 0.040 0.033 84.90 -

Grace Construction Corporation 3771 Const. of Limpapa Bridge & Approaches 08/19/08 IX 60.097 360 O 0.226 0.240 0.100 0.030 0.047 0.100 74.30 -

Grace Construction Corporation 3771 Impvt./Conc. Paving of Dapitan City-Dakak Road, Phase I 09/03/08 IX 48.038 340 O 0.360 0.270 0.100 0.030 0.042 0.100 90.20 -

Grace Construction Corporation 3771 Const. of Opao Bridge and Approaches, Brgy. Opao 06/09/09 IX 71.037 1,067 O 0.373 0.300 0.132 0.030 0.047 0.033 91.50 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page109

Page 110: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Grace Construction Corporation 3771 Impv't/Conc. Paving of Dapitan City-Dakak Road, Phase II 03/17/09 IX 47.488 702 O 0.337 0.277 0.150 0.030 0.035 0.050 87.90 -

Grace Construction Corporation 3771 Const. of Lobog Parallel Bridge and Approaches (Phase IV) 09/15/09 X 52.566 180 O 0.353 0.240 0.100 0.030 0.037 0.033 79.30 -

Grace Construction Corporation 3771 Upgrading/Concrete Paving Jct. Blancia-Molave-Josefina Rd., Mahayag-Josefina Sect. 03/28/12 IX 63.806 228 O 0.351 0.300 0.150 0.030 0.053 0.050 93.40 -

Grace Construction Corporation 3771 Asphalt Overlay along Lanao-Pagadian-Zamboanga City Road, Km.1801+663-Km.1803+680 03/21/12 IX 19.033 119 C 0.401 0.133 0.300 - - - 83.40 83.10%

Satisfactory

Grace Construction Corporation 3771 Upgrading/Concrete Paving Jct. Blancia-Molave-Josefina Rd., Mahayag-Josefina Sect. 08/19/12 IX 63.806 385 C 0.429 0.133 0.300 - - - 86.20 90.52%

Very Satisfactory

Grace Construction Corporation 3771 Rehab./Reconst. Of Ozamiz-Pagadian Rd. Pangabuan-Labuyo Rd., Km.1678+000-Km.1680+270 08/19/12 X 29.246 115 C 0.310 0.133 0.300 - - - 74.30 85.16%

Satisfactory

Grace Construction Corporation 3771 Conc. of Iligan Circ. Rd. (Phase I) 08/18/12 X 329.805 1,382 C 0.389 0.200 0.300 - - - 88.90 84.54% Satisfactory

Grace Construction Corporation 3771 Const. of Upper Manakulil/Bridge (Phase I) along Cotabato City Circ. Rd. 08/16/12 XII 23.906 289 O 0.395 0.240 0.105 0.030 0.051 0.050 87.10 -

GRACE CONSTRUCTION CORPORATION/M.

MONTESCALAROS ENTERPRISES, INC. JOINT VENTURE

JV-13-043 Reconst. of Cabula Bridge/Nicdao Steel Utility Bridge, Sitio Maasin, Brgy. Nicdao 10/25/2014 X 197.231 491 O 0.348 0.292 0.150 0.030 0.051 0.050 92.10% 92.10%

Very Satisfactory

GRANBY TRADING & CONSTRUCTION 27554 Construction of Cogon Eco-Tourism Park (Phase 1) 05/08/14 TIEZA 7.991 180 O 0.303 0.267 0.000 0.030 0.026 0.050 67.52 -

GRANBY TRADING & CONSTRUCTION 27554 Construction of Cogon Eco-Tourism Park (Phase 1) 06/10/14 TIEZA 7.991 180 O 0.398 0.300 0.150 0.030 0.035 0.050 96.47 -

GRANBY TRADING & CONSTRUCTION 27554 Construction of Cogon Eco-Tourism Park (Phase 1) 07/18/14 TIEZA 7.991 180 C 0.494 0.200 0.300 99.40 88.40% Satisfactory

GRAND BUILDERS 6845Road Impv't from Highway leading to Pagayawan Falls 1) K1557+843-K1559+666.22 2) K0002+060-K0002+654.21; 3)

K001+880-K002+148.43610/29/2014 X 50.753 210 O 0.275 0.296 0.083 0.007 0.033 0.033 72.70% 72.70%

Poor

Grand Builders 6845

Rehab./Const.Upgrading of Damaged Paved Nat'l Rds. (Int. Sect.) BCIR, Sugbongcogon-Binuangan-Ampenican-

Lagonglong Sect., Misamis Oriental, K01364+299-K01365+000, K01368+798-K01370+000, K01372+000-

K01373+000, K01379+798-K01380+000

08/21/13 X 51.907 225 C 0.374 0.200 0.000 - - - 57.40 70.96% Poor

Grand Builders 6845 Const. of Iligan Circ. Road 03/16/13 X 22.302 360 C 0.304 0.200 0.300 - - - 80.40 84.21% Satisfactory

Grand Builders 6845

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. (IS) BCIR, Sugbongcogon-Binuangan-Ampenican-Lagonglong Sect., Misamis Oriental, K01364+299-

K01365+000, K01368+798-K01370+000, K01372+000-K1373+000, K01379+567-K01380+000

11/21/12 X 51.907 225 O 0.373 0.300 0.000 0.030 0.047 0.050 80.00 -

GRECO CONSTRUCTION AND SUPPLY 21884

Construction/Rehabilitation of Flood Control Structures along Sarangani - Davao del Sur Coastal Road, Malapatan,

Sarangani Province10/29/2014 XII 4.746 100 C 0.421 0.133 0.300 - - - 85.40% 85.40%

Satisfactory

Greco Construction and Supply 21884Replacement/Rehab./Strengthening of Permanent Bridges

Gen. from Bridge Mgt. System (BMS) of Tambilil Bridge along Sarangani-Sultan Kudarat Coastal Rd.

08/19/13 XII 4.520 100 C 0.429 0.200 0.300 - - - 92.90 89.84% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page110

Page 111: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Greco Construction and Supply 21884Replacement/Rehab./Strengthening of Permanent Bridge

Gen. from Bridge Mgt. System (BMS), Tambilil Bridge along Sarangani-Sultan Kudarat Coastal Rd.

03/22/13 XII 4.520 100 O 0.358 0.240 0.150 0.030 0.050 0.050 87.80 -

Green Horizon Landscapers & Developers, Inc. 18802 Impvt. (Conc. of Access Road @ Juction Pola Road Km

73+000 (leading to Pola Port) 09/03/09 IVB 35.603 240 O 0.337 0.288 0.150 0.030 0.051 0.050 90.60 -

Green Horizon Landscapers & Developers, Inc. 18802 Completion of Calapan South Road, Tabtabong-Banti

Section 09/05/09 IVB 38.059 238 O 0.359 0.240 0.150 0.030 0.042 0.050 87.10 -

Green Zone Construction & Supply 35102 Rehab/Reconst. Of Daang Maharlika (K0624+979 - K0625+062) with exception 8/12/2014 V 1.195 37 C 0.419 0.136 0.300 85.50 85.50%

Satisfactory

GREENWALL CONSTRUCTION 14457Construction/Completion of Three (3) Storey, Nine (9)

Classrooms School Buiding (Phase 2) at Bayanan Elementary School

11/17/2014 NCR 10.839 180 O 0.309 0.300 0.150 0.030 0.058 0.050 89.70% 89.70% Very Satisfactory

Grelips Construction & Development 34236 Const. of MPB, Oas Polytechnic High Sch. 11/25/12 V 2.355 150 C 0.491 0.133 0.300 - - - 92.40 84.91%

Satisfactory

Grelips Construction & Development 34236

Repair/Maint. of San Fernando East Concrete Dike Sta.0+848.90-Sta.1+438.90 along San Fernando North Rd.

Baybay Dagat03/14/13 V 1.990 90 C 0.410 0.133 0.300 - - - 84.30 84.30%

Satisfactory

Grelips Construction & Development 32236 Const. of MPB, Oas, Polytechnic High Sch. 08/08/12 V 2.355 150 O 0.400 0.240 0.082 0.030 0.032 0.033 81.70 -

GRELIPS CONSTRUCTION AND DEVELOPMENT 34236 Legaspi City LTFRB Regional Office Project 04/27/15 DOTC 6.199 210 C 0.484 0.200 0.300 - - - 98.38 92.58% Very

SatisfactoryGRELIPS CONSTRUCTION AND

DEVELOPMENT 34236 Legaspi City LTFRB Regional Office Building Project 09/03/14 DOTC 6.199 210 O 0.369 0.300 0.150 0.015 0.050 0.017 90.10 -

Greyrock Construction 9296 Zamboanga City-Labuan Road (Labuan Proper Sect.) 03/20/12 IX 18.990 260 C 0.430 0.133 0.300 - - - 86.30 86.84% Satisfactory

Gulf Canary Construction and Development, Inc. 12522 Z3R Rehabilitation Project - Mariki 08/07/15 NHA 137.834 459 O 0.371 0.275 0.150 0.023 0.038 0.050 90.63 -

Gulf-Canary Construction and Development Inc. 12522 Z3R Rehabilitation Project-Mariki 03/13/15 NHA 137.721 300 O 0.386 0.273 0.150 0.030 0.027 0.050 91.51 -

GVDPM CONSTRUCTION / E.A. UNABIA CONSTRUCTION /

TECKCON CONSTRUCTION / KALINGA BUILDERS (J.V.)

JV-13-562 Const./Rehab./ of Drainage Protection Works at Bulanao Flood Control, Tabuk City, Kalinga 8/7/2014 CAR 37.853 134 OG 0.373 0.240 0.150 0.024 0.050 0.050 88.70 -

GVDPM Construction Corp. (Formerly: ZM Construction) 9052 Rehab. of Existing Dike Paite-Maculcol, San Felipe Side 08/03/13 III 17.726 120 C 0.416 0.133 0.300 - - - 84.90 84.90%

SatisfactoryGVDPM Construction Corp. (Formerly: ZM Construction) 9052 Const. of Slope Protection/Flood Control, Maloma Dike

(Upstream Sect.) 08/03/13 III 35.298 120 C 0.388 0.133 0.300 - - - 82.10 82.10% Satisfactory

GVDPM Construction Corp. (Formerly: ZM Construction) 9052 Const. of Slope Protection/Flood Control, Kiling (North

Side) 03/15/13 III 13.292 120 O 0.371 0.190 0.150 0.030 0.050 0.033 82.40 -

GVDPM Construction Corp. (Formerly: ZM Construction) 9052 Rehab./Reconst./Upgrading of Gapan-Olongapo Rd. 03/22/13 III 57.492 323 O 0.297 0.235 0.150 0.030 0.045 0.033 79.00 -

GVDPM Construction Corp. (Formerly: ZM Construction) 9052 Const. of Various S/B: Const. of 1 CL at Libaba E/S 03/15/13 III 0.547 90 C 0.458 0.133 0.300 - - - 89.10 89.10%

Very SatisfactoryGVDPM Construction Corp. (Formerly: ZM Construction) 9052 Prev. Maint. (Int. Sect.) Nat'l Arterial Rd., Olongapo-

Bugallon Rd., K0167+760 - K0167+450 03/15/13 III 13.770 35 C 0.455 0.133 0.300 - - - 88.80 88.80% Satisfactory

H C M Construction Corporation 19382 Const./Widening of Pres. C.P. Garcia Ave. (C-5) Ext., SLEX to Coastal Sect., Sta. 0+354.106-Sta. 0+660 08/17/13 NCR 100.458 341 C 0.453 0.133 0.300 - - - 88.60 88.44%

Satisfactory

H L J CONSTRUCTION & ENTERPRISES 18080

Road Upgrading (gravel to paved) along Davao-Sarangani Coastal Road, (Malalag-Malita-JAS), km. 1689+648.732 to

km. 1691+217.302 Lanipao Section, Don Marcelino8/7/2014 XI 37.204 179 OG 0.277 0.300 0.011 0.030 0.019 0.000 63.70 -

H.G. Lopez 17691 Construction of Drainage Structure along Manila North Road, San Fernando City Section 10/25/2014 I 9.653 176 C 0.416 0.145 0.300 - - - 86.10% 86.10%

Satisfactory

H.G. Lopez Construction 17691 Construciton of 9-Cl, 3-Storey Building at La Union National High School 8/4/2014 I 10.842 295 C 0.463 0.133 0.300 89.60 88.48%

Satisfactory

H.G. Lopez Construction 17691 Prev. Maint. along San Fernando Port Rd., K0267+000-K0268+717 07/29/13 I 12.534 54 C 0.475 0.133 0.300 - - - 90.80 90.08%

Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page111

Page 112: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

H.G. Lopez Construction 17691 Const. of 9-Cl, 3-Storey Bldg. at La Union NHS 07/30/13 I 10.418 270 O 0.368 0.240 0.150 0.030 0.042 0.050 88.00 -

H.G. Lopez Construction 17691 Prev. Maint. along San Fernando Port Rd., K0267+000-K0268+717 03/11/13 I 12.534 54 O 0.373 0.300 0.150 0.008 0.015 0.050 89.60 -

H.L.J Construction & Enterprises 18080 Rehab./Recons./Upgrading of Dumaguete North Rd., Polo-Tugas Rd. Sect. 09/12/09 VII 23.022 210 O 0.372 0.240 0.150 0.030 0.037 0.033 86.20 -

H.L.J Construction & Enterprises 18080 Impvt. of Roads leading to the Twin Springs Project, Brgy. Bunga to Brgy. Baslay Road 11/25/08 VII 9.311 145 O 0.323 0.236 0.100 0.030 0.027 0.067 78.30 -

H.L.J Construction & Enterprises 18080 Conc. of Dancalan-Candoni-Damutan Valley Road, Caningay Section, Brgy. Caningay 05/30/09 VI 16.235 280 O 0.380 0.268 0.150 0.023 0.045 0.033 89.90 -

H.L.J Construction & Enterprises 18080 Conc. of Dancalan-Candoni-Damutan Valley Road, Tabu Section, Brgy. Tabu 05/30/09 VI 18.335 280 O 0.366 0.251 0.150 0.023 0.050 0.033 87.30 -

H.L.J Construction & Enterprises 18080 Conc. of Boracay Road (Lapus-Lapus, Fairways Sect.) 03/15/09 VI 19.686 289 O 0.312 0.296 0.150 0.018 0.050 0.033 85.90 -

H.L.J Construction & Enterprises 18080 Reconst. of Bacolod South Kabankalan Road 03/03/09 VI 16.997 180 O 0.261 0.292 0.150 0.030 0.055 0.033 82.10 -

H.L.J. CONSTRUCTION & ENTERPRISES 18080 Rehabilitation/Reconstruction/Replacement/Retrofitting of

Existing Permanent Bridges Mambuloc Bridge 1 10/27/2014 VI 5.646 120 C 0.485 0.081 0.300 - - - 86.60% 86.60% Satisfactory

H.L.J. CONSTRUCTION & ENTERPRISES 18080 Construction/Improvement of Mabinay Leading to Crystal

Cave 10/27/2014 VII 45.568 239 O 0.329 0.226 0.150 0.024 0.061 0.050 84.00% 84.00% Satisfactory

H.L.J. Construction & Enterprises 18080 Repair/Rehab./Impv't. of Binalbagan-Isabela Rd. K0073+800-K0073+1023 08/10/13 VI 4.792 28 C 0.494 0.133 0.300 - - - 92.70 92.70%

Very Satisfactory

H.L.J. Construction & Enterprises 18080 Repair/Rehab./Impv't. of Hinigaran-Isabela Rd. K0067+459-K0068+513 w/ exception 08/10/13 VI 9.537 49 C 0.488 0.133 0.300 - - - 92.10 92.10%

Very Satisfactory

H.L.J. Construction & Enterprises 18080 Const. of DepEd Standard Type Sch. Bldg. @ Bulwangan NHS 08/09/13 VI 2.842 90 O 0.388 0.240 0.150 0.030 0.032 0.033 87.30 -

H.L.J. Construction & Enterprises 18080 Const./Widening/Upgrading/Rehab. of Access Rd. to Declared Tourism Destinations, Brgy. Punta-Taytay 08/06/13 VI 45.541 180 O 0.369 0.200 0.150 0.030 0.037 0.050 83.60 -

H.L.J. Construction & Enterprises 18080 Reconst. of Martilo Bridge 08/22/13 VII 11.731 192 O 0.347 0.300 0.137 0.023 0.045 0.017 86.90 -

H.L.J. Construction & Enterprises 18080 Reconst. of Habag Bridge 08/22/13 VII 11.354 222 O 0.388 0.300 0.084 0.023 0.045 0.017 85.70 -

H.L.J. Construction & Enterprises 18080 Upgrading (Gravel to Concrete) Conc. of Hanay-Hanay Rd. leading to Twin Lake 08/21/13 VII 14.472 115 O 0.326 0.300 0.000 0.030 0.055 0.050 76.10 -

H.L.J. Construction & Enterprises 18080Rd. Upgrading (Gravel to Paved) along Davao-Sarangani Coastal Rd., (Malalag-Malita-JAS), km. 1689+648.732-km.

1691+217.302, Lanipao Sect., Don Marcelino08/08/13 XI 37.204 179 O 0.314 0.298 0.138 0.030 0.023 0.033 83.60 -

H.L.J. Construction & Enterprises 18080Road Upgrading (Gravel to Paved) Davao-Sarangani

Coastal Rd., Malalag-Malita-JAS Rd., Biton Sect., Km.1669+180.5-Km.1670+080

08/11/11 XI 37.417 180 O 0.391 0.290 0.150 0.008 0.054 0.050 94.30 -

H.L.J. Construction & Enterprises 18080Road Upgrading (Gravel to Paved) Davao-Sarangani Coastal Road, Malalag-Malita-JAS Rd., Calian Sect.

Km.1675+520 - Km.1677+683.96008/11/11 XI 41.448 180 O 0.344 0.300 0.150 0.008 0.050 0.050 90.20 -

H.L.J. Construction & Enterprises 18080Road Upgrading (Gravel to Paved) Jct. Bancal-

Leon_Antique Bdry. Rd. K0031+412-K0031+948 & K0033+798-K0034+180

03/23/12 VI 17.864 120 C 0.443 0.200 0.300 - - - 94.30 86.02% Satisfactory

H.L.J. Construction & Enterprises 18080Rehab./Reconst./Upgrading of Damaged Paved Nat'l Arterial Road, Conc. of Lublub-Bolilao-Salad Road,

Km.278+711-Km.279+69203/21/12 VI 10.654 120 C 0.409 0.200 0.300 - - - 90.90 85.92%

Satisfactory

H.L.J. Construction & Enterprises 18080 Conc.g of Bacolod-South Road, Sangke Sect., Brgy. Sangke 03/29/12 VI 28.170 280 C 0.356 0.200 0.300 - - - 85.60 84.10%

Satisfactory

H.L.J. Construction & Enterprises 18080 Rehab./Reconst./Strengthening of Talagpun-ay Bridge along Candoni-Sipalay R., Brgy. Canindangan 11/29/12 VI 5.112 200 C 0.452 0.133 0.300 - - - 88.50 81.90%

Unsatisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page112

Page 113: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

H.L.J. Construction & Enterprises 18080 Rehab./Reconst./Strengthening of Talagpun-ay Bridge along Candoni-Sipalay Rd., Brgy. Camindangan 08/11/12 VI 5.238 200 O 0.400 0.300 0.000 0.030 0.045 0.000 77.50 -

H.L.J. Construction & Enterprises 18080Rehab. of Polo Sect., Tanjay-Dumaguete North Rd, Tanjay

City existing Pavement (w/ exceptions), Km.26+378-Km.27+294

08/11/12 VII 19.249 240 C 0.404 0.133 0.300 - - - 83.70 86.46% Satisfactory

H.L.J. Construction & Enterprises 18080 Rehab./Reconst. Of Damaged Paved Nat'l. Rd., Dumaguete North Rd., K0019+119-K0019+999, 2nd District 08/11/12 VII 12.991 215 C 0.422 0.133 0.300 - - - 85.50 85.92%

Satisfactory

H2 LANDMARK BUILDERS, INC. (Formerly: Landmark Builders) 7400 Road Upgrading (Gravel to Concrete) of Mati - Maragusan

Road 8/7/2014 XI 70.009 237 OG 0.405 0.225 0.150 0.030 0.047 0.050 90.70 -

H2 Landmark Builders, Inc. (Formerly: Landmark Builders) 7400

Rd. Upgrading (Gravel to Paved) along Mati-Maragusan Rd., Bactinan, Km.1518+641-Km.1520+025.50 w/ exception,

Bactinan Sect.08/16/13 XI 42.041 204 C 0.447 0.166 0.300 - - - 91.30 91.30%

Very Satisfactory

H2 Landmark Builders, Inc. (Formerly: Landmark Builders) 7400

Road Upgrading (Gravel to Paved) along Mati-Maragusan Rd. a)Km.1518+200-Km.1518+552; b)Km.1531+209-

Km.1532+850, Bactinan-Buso-Caguisokan Sect.08/16/13 XI 33.116 149 C 0.344 0.200 0.300 - - - 84.40 84.70%

Satisfactory

H2 Landmark Builders, Inc. (Formerly: Landmark Builders) 7400

Rd. Upgrading (Gravel to Paved) along Mati-Maragusan Rd. a)Km.1518+200-Km.1518+552; b)Km.1531+209-Km.1532+850, Bacatinan-Buso-Caguisokan Sect.

03/20/13 XI 33.116 149 O 0.292 0.277 0.150 0.030 0.050 0.050 84.90 -

H2 Landmark Builders, Inc. (Formerly: Landmark Builders) 7400 Road Upgrading (Gravel to Paved) Mati-Maragusan Rd. 08/16/12 XI 34.301 150 C 0.467 0.133 0.300 - - - 90.00 87.96%

SatisfactoryH2 Landmark Builders, Inc.

(Formerly: Landmark Builders) 7400 Rd. Upgrading (Gravel to Paved) Mati-Maragusan Rd. 08/16/12 XI 14.895 80 C 0.449 0.133 0.300 - - - 88.20 86.58% Satisfactory

Haidee Construction & Development Corp. 10365 Proposed Replacement/Const. of Leoncia Bridge along

Clark Circ. @ Angeles City 08/03/12 III 32.009 180 C 0.418 0.164 0.300 - - - 88.20 89.28% Very Satisfactory

HAIDEE CONSTRUCTION & DEVELOPMENT CORP./B.P. CRUZ

BUILDERS & TRADING (JV)JV-13-323

Widening/Improvement of Manila North Road, including Drainage System, K0083+580 to K0094+000 (w/ exception),

Angeles-Mabalacat Section11/19/2014 III 41.069 246 O 0.350 0.240 0.150 0.030 0.046 0.033 84.90% 84.90%

Satisfactory

Haidee Construction & Development Corp./Supreme ABF

Construction & Construction Supply Company, Inc. (JV)

JV-11-527 Impvt./Widening of McArthur Highway (MNR) Angeles-Mabalacat Sect. 11/23/12 III 93.698 331 O 0.388 0.240 0.150 0.030 0.060 0.050 91.80 -

Haidee Construction and Development Corp. 10365 Const. of Tagumbao Bridge & Approaches along Gerona-

Sta. Ignacia Rd. 08/08/13 III 226.266 480 O 0.387 0.240 0.150 0.030 0.051 0.050 90.80 -

HAIDEE CONSTRUCTION AND DEVELOPMENT CORPORATION

Long-Term Permanent Works at Pasig-Potrero Bridge of SCTEX 02/04/15 BCDA 71.620 360 O 0.392 0.300 0.150 0.030 0.027 0.050 94.87 -

HAIDEE CONSTRUCTION AND DEVELOPMENT CORPORATION

Long-Term Permanent Works at Pasig-Potrero Bridge of SCTEX 04/29/15 BCDA 71.620 360 O 0.392 0.294 0.137 0.030 0.049 0.017 91.83 -

HAIDEE CONSTRUCTION AND DEVELOPMENT CORPORATION 4846 Construction of BCDA Remaining Infrastructure Works

inside Bonifacio Global City, package 2 12/15/14 BCDA 115.618 420 O 0.389 0.300 0.071 0.030 0.043 0.050 88.36 -

HAKKATAN KONSTRUK & GENERAL MERCHANDISE 31610 Const. of DepEd Standard Type School Building at Tabu

NHS Ilog, Negros Occidental 8/9/2014 VI 3.331 85 C 0.435 0.200 0.300 93.50 84.82% Satisfactory

Hakkatan Konstruk & General Merchandise 31610 Const. of DepEd Standard Type Sch. Bldg. @ Tabu NHS 08/09/13 VI 3.331 95 O 0.326 0.240 0.150 0.030 0.032 0.033 81.10 -

Hakkatan Konstruk & General Merchandise 31610 Const./Impvt. of DPWH Office Bldg., 3rd Negros Occidental

District Engineering & Sitio Mojon, Brgy. I 06/05/10 VI 4.308 220 O 0.356 0.266 0.150 0.022 0.041 0.033 86.80 -

Hakkatan Konstruk & General Merchandise 31610 Const./Impvt. of DPWH Bldg., 3rd Negros Occidental DEO

at Sitio Mojon, Brgy. 1 08/24/10 VI 4.474 220 O 0.369 0.240 0.150 0.030 0.035 0.033 85.70 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page113

Page 114: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Halrey Construction Inc. 2267 Rd. Upgrading (Gravel to Paved) of Eastern Bulacan Rd., K0080+200-K0094+809, Doña Remedios 03/20/13 III 19.706 150 O 0.369 0.240 0.150 0.020 0.040 0.050 86.90 -

Halrey Construction Inc./ Three W Builders Inc. - JV Guadalupe Heights 1 10/09/15 NHA 289.884 240 O 0.280 0.280 0.150 0.030 0.038 0.050 82.80 -

HALREY CONSTRUCTION, INC. 2267 Widening of San Marcelino - San Antonio Road, K0153+000 - K0154+550 11/27/2014 III 30.399 150 C 0.425 0.133 0.300 - - - 85.80% 85.80%

Satisfactory

Halrey Construction, Inc. 2267 Construction/Rehabilitation of Marilao-San Jose Road, San Jose Del Monte City 9/27/2014 Special 3 18.573 120 C 0.405 0.133 0.300 83.80 83.80%

Satisfactory

Halrey Construction, Inc. 2267 Rd. Upgrading (Gravel to Paved) of Eastern Bulacan Rd., K0080+200-K0094+809 Doña Remedios 08/15/13 III 19.706 150 C 0.410 0.133 0.300 - - - 84.30 85.86%

Satisfactory

Halrey Construction, Inc. 2267 Impvt./Concrete Blocking along Epifanio delos Santos Ave. 03/31/11 NCR 4.623 60 O 0.397 0.200 0.150 0.030 0.045 0.033 85.50 -

Halrey Construction, Inc. 2267

Restoration/Rehab./Reconst. Of Daang Maharlika Rd. [a)Km.053+(-277)-Km.053+000 b)Km.068+000-Km.069+000; Km.069+000-Km.069+357; & Km.069+357-Km.069+857] w/

exceptions

03/16/12 III 18.782 150 C 0.439 0.187 0.300 - - - 92.60 90.38% Very Satisfactory

Halrey Construction, Inc. 2267 Rehab./Reconst. Of Muzon-Tungkong Mangga Road, Km.041+(-586)-Km.045+036 w/ exception 03/17/12 III 32.297 196 C 0.355 0.135 0.300 - - - 79.00 86.98%

SatisfactoryHanjin Heavy Industries & Const.

Co. Ltd. FC-03-010 CP No.1 Const. of Jaro Floodway & Imprv't. of Tigum & Aganan Rivers 03/03/10 MFCP1 1,979.449 1,920 O 0.335 0.265 0.150 0.030 0.056 0.050 88.60 -

Hanjin Heavy Industries & Const. Co. Ltd.

SL1-SN-004892

Help for Catubig Agricultural Advancement Project (HCAAP) 11/9-12/09 NIA 0.994 1,253 O 0.393 0.288 - 0.024 0.037 0.037 77.90 -

Hanjin Heavy Industries & Const. Co. Ltd. 4892 Help for Catubig Agricultural Advancement Project -

Irrigation & Drainage Component (HCAAP-IDC) 09/27/10 NIA 749.759 1,381 O 0.398 0.300 - 0.030 0.061 0.050 83.90 -

Hanjin Heavy Industries & Construction Co., Ltd. (Korea) FC-11-008 Const. of Bacolod-Silay Airport Access Road (BSAAR)

Proj. 11/27/12 KEDCF 400.988 420 O 0.389 0.293 0.117 0.030 0.060 0.017 90.60 -

Hanjin Heavy Industries & Construction, Co. Ltd. (Korean) FC-11-008 Const. of Bacolod-Silay Airport Access Rd. (BSAAR) Proj. 08/12/13 KEDCF-

PMO 415.893 572 O 0.392 0.200 0.134 0.030 0.044 0.033 83.30 -

Hanjin Heavy Industries & Construction, Co. Ltd. (Korean) FC-11-008 Const. of Bacolod-Silay Airport Access Rd. (BSAAR) Proj. 03/16/13 KEDCF-

PMO 426.704 537 O 0.367 0.300 0.150 0.030 0.051 0.033 93.10 -

Hanjin heavy Industries & Construction, Co., Ltd. FC-08-005

Central Mindanao Rd. Proj., Contract Package 2, Const./Impv't of North Upi-Maguindanao/Sultan Kudarat

Bdry.08/11/11 PMO-

RRNDP 948.000 870 O 0.362 0.300 0.150 0.030 0.045 0.033 92.00 -

Hanjin Heavy Industries and Construction Co., Ltd. FC-08-005

Central Mindanao Road Project, Contract Package 2, Const./Improvement of North Upi-Maguindanao/Sultan

Kudarat Boundary03/30/11 RRNDP 892.399 782 O 0.363 0.240 0.150 0.030 0.047 0.033 86.30 -

HB Construction 32855 Asphalt Overlay w/ correction along Retiro Street, District IV 07/29/13 NCR 3.755 30 C 0.443 0.133 0.300 - - - 87.60 87.60%

Satisfactory

HCM Construction Corporation 19382 Const./Widening of Pres. Garcia Ave. (C-5) Ext., SLEX to Coastal Sect. 11/24/12 NCR 100.467 326 O 0.383 0.300 0.086 0.030 0.051 0.000 85.00 -

Hebei Road and Bridge Group Co., Ltd. FC-10-006

Impvt. of Malalag-Malita-Jose Abad Santos Rd., CP-RI-2.6: Malita Don Marcelino Sect., Mindanao under the Nat'l Rds.

Impvt. & Mgt. Program, Phase 2 (NRIMP-2)11/21/12 NRIMP 588.815 731 O 0.360 0.281 0.150 0.030 0.051 0.050 92.20 -

Hebei Road and Bridge Group Co., Ltd. FC-10-006 Impv't. of Malalag-Malita-Jose Abad Santos Rd., CP-RI-2.6:

Malita-Don Marcelino Sect., Mindanao under NRIMP-2 08/09/12 NRIM-PMO 549.575 731 O 0.325 0.265 0.150 0.030 0.061 0.050 88.10 -

Henry S. Oaminal Const. & General Merchandise 10578 Completion of Dormitory bldg. Phase I 11/26/08 DOST 5.829 150 O 0.320 0.300 0.128 0.017 0.043 0.023 74.80 -

Henry S. Oaminal Const. & General Merchandise 10578 Conc. of Jct. (LIR) Carmen-Sagbayan-Bacane Road 08/29/08 VII 22.646 250 O 0.293 0.222 0.000 0.020 0.032 0.100 66.70 -

Henry S. Oaminal Construction & General Merchandise 10578

Rehab/Reconst./Upgrading of Damaged Paved Nat'l Rd. along Daang Maharlika Rd. (Surigao-Agusan Sect.)

Km.1193+000-Km.1201+00003/22/12 XIII 58.915 315 O 0.303 0.300 0.150 0.030 0.040 0.050 87.30 -

Henry S. Oaminal Construction and Geneneral Merchandise 10578 Rehab./Reconst./Upgrading of Bacolod Circ. Rd., Sta.3+019-

Sta.9+424 w/ exception 03/11/13 VI 97.511 553 O 0.307 0.300 0.100 0.024 0.055 0.050 83.60 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page114

Page 115: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Henry S. Oaminal Construction and General Merchandise 10578

Rehab/Reconst./Upgrading of Damaged Paved Nat'l Rd. along Daang Maharlika Rd. (Surigao-Agusan Sect.)

Km.1193+000-Km.1201+00011/22/12 XIII 58.915 315 O 0.348 0.297 0.108 0.030 0.050 0.000 83.30 -

Henry S. Oaminal Construction and General Merchandise 10578 Rehab./Reconst./Upgrading of Bacolod South Circ. Rd.,

Sta.3+019-Sta.9+424 w/ exception 11/20/12 VI 97.511 495 O 0.366 0.274 0.078 0.023 0.055 0.033 82.90 -

Henry S. Oaminal Construction and General Merchandise 10578

Rd. Upgrading (Gravel to Paved) along Jct. S.H. Aglayan-Alanib-Ticalaan Rd. (Tankulan-Kalapat Sect.) K1509+640-

K1511+85111/20/12 X 24.732 240 C 0.403 0.200 0.300 - - - 90.30 84.96%

Satisfactory

Henry S. Oaminal Construction and General Merchandise 10578 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd.

(IS): Sayre Highway, Maluko-Damay Sect., Maluko 11/20/12 X 59.428 225 O 0.334 0.300 0.077 0.030 0.050 0.017 80.80 -

Henry S. Oaminal Construction and General Merchandise 10578 Rehab./Reconst./Upgrading of Bacolod South Circ. Rd.,

Sta.3+019-Sta.9+424 (w/ exception) 08/13/12 VI 97.560 465 O 0.364 0.244 0.150 0.030 0.059 0.050 89.70 -

Henry S. Oaminal Construction and General Merchandise 10578

Rd. Upgrading (Gravel to Paved) along Jct. S.H. Aglayan-Alanib-Ticalaan Rd. (Tankulan-Kalapat Section) K1509+640-

K1511+85108/11/12 X 24.732 225 O 0.352 0.234 0.125 0.030 0.040 0.033 81.40 -

Henry S. Oaminal Construction and General Merchandise 10578

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. along Daang Maharlika Rd. (Surigao-Agusan Sect.)

Km.1193+000Km.1201+00008/07/12 XIII 58.915 315 O 0.341 0.300 0.051 0.030 0.060 0.050 83.20 -

HERBANA BUILDERS AND SUPPLY 32523 Development of Kawayan Resort 08/12/15 DOTC 4.999 120 C 0.467 0.200 0.300 - - - 96.66 96.66%

Very SatisfactoryHERBANA BUILDERS AND

SUPPLY 32523 Lipa LTO Regional Office Building Project 05/29/15 DOTC 34.027 360 O 0.382 0.300 0.150 0.030 0.047 0.050 95.90 -

Herbana Builders and Supply 32523 Construction of LTO Building 03/26/15 DOTC 34.027 360 O 0.386 0.268 0.150 0.030 0.047 0.050 93.06 -

HERBANA BUILDERS AND SUPPLY 32523 Borongan Airport Development Project 08/27/14 DOTC 13.313 165 O 0.394 0.300 0.150 0.020 0.050 0.050 96.40 -

HERBANA BUILDERS AND SUPPLY 32523 Borongan Airport Development Project 11/06/14 DOTC 13.313 165 C 0.469 0.200 0.300 - - - - 96.90%

OutstandingHERBANA CONSTRUCTION AND

SUPPLY 32523 Malabsay Falls Eco-Tourism Park Development 6/4/15 TIEZA 24.700 180 O 0.322 0.234 0.120 0.020 0.058 0.033 78.70 -

Herbert Malmis General Merchandise & Contractor, Inc. 4593 Concrete Paving of Maribojoc-Antequera-Catagbacan

(Loon) Road, Sta.21+915.57-Sta.22+600 w/ exception 03/26/12 VII 11.114 210 C 0.448 0.133 0.300 - - - 88.10 90.92% Very Satisfactory

Herefold Builders & Construction Supply 20789 Repair/Rehab. of MPB (Municipal Bldg.) 11/20/12 IVA 11.576 252 C 0.427 0.200 0.300 - - - 92.70 87.75%

SatisfactoryHerefold Builders & Construction

Supply 20789 Repair/Rehab. of MPB (Municipal Bldg.) 08/09/12 IVA 11.576 240 O 0.290 0.300 0.150 0.030 0.050 0.033 85.30 -

HEXAMINDZ CORPORATION 31666Improvement/Upgrading (Gravel to Concrete) of Highway Jct. Santiago – Macopa – Pantad Leading to Pusan Point,

Caraga, Davao Oriental8/13/2014 XI 67.980 209 OG 0.262 0.300 0.115 0.030 0.039 0.050 79.60 -

Hexamindz Corporation (Formerly: Kilusang Magkaibigan M.P.

Cooperative (KMMPC))31666

Rehab./Reconst./Upgrading of Damaged Paved National Roads including Drainage based on PMS/HDM-4

(intermittent Section) Sindangan - Liloy Road a. K1941+000 - K1941+1000, b. K1955+771 - K1956+004, c. K1958+000 -

K1959+002

8/9/2014 IX 33.487 193 OG 0.353 0.300 0.121 0.030 0.045 0.017 86.60 -

HEXAMINDZ CORPORATION (Formerly: Kilusang Magkaibigan

M.P. Cooperative KMMPC)31666

Rehab./Reconst./Upgrading of Damaged Paved National Roads including drainage based on PMS/HDM-4

(Intermittent Sect.), Sindangan-Liloy Road a.) K1941+000 - K1941+1000, b.) K1955+771 - K1956+004, c.) K1958+000 -

K1956+004

10/24/2014 IX 33.487 237 O 0.191 0.221 0.105 0.030 0.045 0.033 62.50% 62.50% Poor

HEXAMINDZ CORPORATION (Formerly: Kilusang Magkaibigan

M.P. Cooperative KMMPC)31666 Widening of Road along Daang Maharlika (Agusan-Davao)

Road, Poblacion Section 10/26/2014 XI 16.891 110 C 0.339 0.197 0.300 - - - 83.60% 83.60% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page115

Page 116: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

HEXAMINDZ CORPORATION (Formerly: Kilusang Magkaibigan

M.P. Cooperative KMMPC)31666 Cluster IV - Construction of San Isidro E/S 10/29/2014 XI 4.552 60 C 0.467 0.133 0.300 - - - 90.00% 90.00%

Very Satisfactory

HEXAMINDZ CORPORATION (Formerly: Kilusang Magkaibigan

M.P. Cooperative, KMMPC)31666 Asphalt Overlay with Concrete Blocking of Balete Drive,

K0010+(-740) - K0010+420 8/16/2014 NCR 10.891 135 C 0.494 0.133 0.300 92.70 92.70% Very Satisfactory

HG III Construction & Development Corporation Puerto Princesa Port Expansion Project 12/06/12 PPA O 0.395 0.289 0.150 0.030 0.061 0.050 97.50 -

HG III Construction and Development Corporation 8431 Land Development and Construction of Housing Units

(Viejo People's Village) 10/03/15 NHA 289.175 360 O 0.344 0.265 0.150 0.020 0.061 0.050 88.92 -

HG III Construction and Development Corporation 8431 New Bohol (Panglao) Airport Development Project 05/20/15 DOTC 69.364 270 C 0.468 0.200 0.300 - - - 96.80 93.70% Very

Satisfactory

HGG Builders & Supply 17824 Completion of Administration Building 11/12/14 DOST 9.519 150 C 0.479 0.200 0.300 - - - 97.90 98.11% Outstanding

HGG BUILDERS AND SUPPLY 17824 Construction of Drainage System/Protection Works along Maharlika, Cam. Sur 2nd LD, K0397+(-060)-K0397+700 11/10/2014 V 16.448 158 C 0.439 0.133 0.300 - - - 87.20% 87.20%

Satisfactory

HGG BUILDERS AND SUPPLY 17824Preventive Maintenance (Intermittent Section Arterial)

along Rolando Andaya Highway a. K0305+042 to K035+1002

11/9/2014 V 14.793 151 C 0.453 0.133 0.300 - - - 88.60% 88.60% Satisfactory

HGG Builders and Supply 17824 Construction of Water Sanitation Facilities at Pamukid Elem. School 8/7/2014 V 0.303 60 C 0.470 0.133 0.300 90.30 90.30%

Very Satisfactory

HGG Builders and Supply 17824 Construction of Line Canal with Slope Protection along Rolando Andaya Highway, Zone 2, Brgy. Lower Sta. Cruz 8/6/2014 V 1.458 119 C 0.400 0.200 0.300 90.00 87.78%

Satisfactory

HGG Builders and Supply 17824Cluster: Prev. Maint. (Int. Sect. Arterial) along Rolando R. Andaya Highway 1) K0291+000-K0293+647 2) K02293+647-

K0295+54208/03/13 V 17.794 120 C 0.439 0.133 0.300 - - - 87.20 87.20%

Satisfactory

HGG Builders and Supply 17824Cluster: Rehab./Reconst. of Damaged Nat'l Rd. (Int. Sect.-Arterial), Andaya Highway, 1)K0300+500-K0 300+750 2) K0

302+00008/03/13 V 5.542 120 C 0.372 0.200 0.300 - - - 87.20 87.20%

Satisfactory

HGG Builders and Supply 17824 Const. of Line Canal w/ Slope Protection along Rolando R. Andaya Highway Zone 2, Brgy. Lower Sta. Cruz 08/03/13 V 1.458 119 O 0.375 0.240 0.150 0.030 0.035 0.033 86.30 -

HGG Builders and Supply 17824 Reblocking &Asphalt Overlay of Danao-Pasacao Rd., Km.420+300-Km.428+233 (with exception) 08/14/12 V 32.343 201 C 0.455 0.133 0.300 - - - 88.80 88.98%

Satisfactory

HGG Builders and Supply / Partido Construction and Supply (JV) JV-12-243 Rehab./Reconst./Strengthening of Bridge along Nat'l Rds.,

Aslong Bridge 08/05/13 V 11.839 150 C 0.440 0.157 0.300 - - - 89.70 89.70% Very Satisfactory

HGIII Construction 3368 Rehabilitation/Upgrading of West Breakwater 01/28/15 PPA 129.331 420 C 0.464 0.200 0.300 - - - - 97.33% Outstanding

HG-III Construction & Development Corporation 8431 New Bohol (Pangalao) Airport Construction and

Sustainable Environment Protection Project 11/13/14 DOTC 65.748 240 C 0.390 0.300 0.150 0.020 0.014 0.050 92.40 -

HG-III Construction & Development Corporation 8431 Rehabilitation/Upgrading of West Breakwater 06/27/14 PPA 129.331 420 O 0.398 0.300 0.150 0.030 0.051 0.050 97.93 -

HG-III Construction & Development Corporation 3368 Placer Port Development Project 09/11/13 DOTC 22.713 210 C 0.457 0.200 0.300 - - - 95.70 95.70%

Very Satisfactory HG-III Construction and

Development Corporation Puerto Princesa Port Expansion Project 06/21/13 PPA 290.489 540 C 0.496 0.200 0.300 - - - 99.60 95.39% Very Satisfactory

HG-III Construction and Development Corporation Puerto Princesa Port Expansion Project 06/29/12 PPA 290.489 540 O 0.305 0.300 0.150 0.030 0.060 0.033 87.74 -

HGW = 3 Engineering & Construction 34574 Perimeter Fence & Gates PSHS CARC 12/17/14 DOST 9.442 231 C 0.489 0.200 0.262 - - - 95.09 95.09

Very Satisfactory

High Strength Dev. Corporation 31976 Construction of Bantog-Balbaloto, FMR 05/22/09 III 1.879 79 O 0.294 0.300 0.150 0.020 0.030 0.050 84.40 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page116

Page 117: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

HIGH STRENGTH DEVELOPMENT CORPORATION 31976

Preventive Maintenance along Tarlac - Sta. Rosa Road a.) K0136+(-045) - K0136+715 (Modified to : K0146+(-440.50) -

K0147+627.50)8/7/2014 III 8.356 30 C 0.335 0.198 0.300 83.30 83.30%

Satisfactory

Hi-Tone Construction & Development Coporation 23385 San Andres Port Development Project 06/09/14 DOTC 48.274 240 O 0.328 0.300 0.150 0.030 0.035 0.050 89.33 -

Hi-Tone Construction & Development Corporation 23385 San Andres Port Development Project 09/25/14 DOTC 48.274 315 C 0.459 0.200 0.300 - - - 95.92 91.97%

Very SatisfactoryHi-Tone Construction &

Development Corporation 8784 Construction of RC Wharf 10/23/14 PPA 79.105 433 C 0.449 0.200 0.300 - - - - 92.24% Very Satisfactory

Hi-Tone Construction & Development Corporation 8784 Construction of RC Wharf 06/20/14 PPA 79.105 433 O 0.397 0.300 0.058 0.030 0.070 0.050 90.47 -

Hi-Tone Construction & Development Corporation

(Formerly: Lo-Tone Const. Supply)23385 Corollary Works at Tagaytay Resettlement Project 10/26-29/09 NHA 19.985 120 O 0.390 0.300 0.128 0.030 0.056 0.033 93.70 -

Hi-Tone Construction and Development (Formerly: Lo-Tone

Constructio & Supply)23385

Camarines Sur-Albay Diversion Road (San Fernando-Oas-Daraga Section of the Pan Philippine Highway (PPH)

including Bridges, Albay Side, Road Opening/Upgrading of Caguiba-Bongabong-Taladong (Jct. National Road)-Comon-

Inarado-Gapo-Dinoronan-Tabon-Tabon Section

8/16/2014 V 85.676 313 OG 0.328 0.300 0.115 0.022 0.042 0.033 84.00 -

Hi-Tone Construction and Development Corporation 23385 Road Upgrading (Gravel to Paved) Catanduanes Circ.

Road, K0130+845-K0133+100, Mabini-San Jose Sect. 08/16/11 V 44.102 240 O 0.374 0.061 0.150 0.030 0.042 0.033 69.00 -

Hi-Tone Construction and Development Corporation 23385

Emergency Repair of Dilapidated 150n Panels R.C. Deck (3.5m x 3.725m) in scttered Locations Between Berths 1-4,

Port of Davao, Sasa11/23/13 PPA 22.960 210 C 0.500 0.200 0.300 - - - 100.00 100.00%

Outstanding

Hi-Tone Construction and Development Corporation

(Formerly: Lo-Tone Construction & Supply)

23385 Rehab. of Flood Control System along Basud River 08/12/13 V 14.089 105 C 0.458 0.133 0.300 - - - 89.10 89.10% Very Satisfactory

Hi-Tone Construction and Development Corporation

(Formerly: Lo-Tone Construction & Supply)

23385 Rehab. of Flood Control System along Igang-Baclayon River 08/12/13 V 14.232 143 C 0.379 0.200 0.300 - - - 87.90 87.90%

Satisfactory

Hi-Tone Construction and Development Corporation

(Formerly: Lo-Tone Construction & Supply)

23385 Rehab. of Flood Control System along Panarayon River, Brgy Panarayon 08/12/13 V 15.207 110 C 0.370 0.200 0.300 - - - 87.00 87.00%

Satisfactory

Hi-Tone Construction and Development Corporation

(Formerly: Lo-Tone Construction & Supply)

23385 Prev. Maint. (Int. Sect.) Asphalt Overlay, Guinobatan Pob. Rd., K0511+(-978)-K0511+740 08/09/13 V 10.720 146 C 0.355 0.200 0.300 - - - 85.50 85.50%

Satisfactory

Hi-Tone Construction and Development Corporation

(Formerly: Lo-Tone Construction & Supply)

23385

Reconst. of Critical Sect. along Nat'l Rd., Road Slip along Catanduanes Circ. Rd. (Km.0014+960-Km.015+080.06, Km.

017+710, Km.020+350, Km.020+400, Km.033+200, Km.033+600)

07/30/13 V 13.807 182 C 0.355 0.200 0.300 - - - 85.50 85.50% Satisfactory

Hi-Tone Construction and Development Corporation

(Formerly: Lo-Tone Construction & Supply)

23385 Rehab./Repair of Flood Control System Yawa River, Bogtong Sect., Bogtong 08/10/13 V 9.682 90 C 0.462 0.133 0.300 - - - 89.50 86.14%

Satisfactory

HI-TONE CONSTRUCTION AND DEVELOPMENT CORPORATION

(Formerly: Lo-Tone Construction & Supply)

23385 Construction/Improvement of Yawa River Control Bogtong-Rawis Section 11/15/2014 V 45.739 214 C 0.428 0.133 0.300 - - - 86.10% 86.10%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page117

Page 118: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

HI-TONE CONSTRUCTION AND DEVELOPMENT CORPORATION

(Formerly: Lo-Tone Construction & Supply)

23385 Rehabilitation of Flood Control System along Lower Mabinit River 11/15/2014 V 15.980 147 C 0.416 0.133 0.300 - - - 84.90% 84.90%

Satisfactory

Hi-Tone Construction and Development Corporation

(Formerly: Lo-Tone Construction & Supply)

23385 Rehab./Impv't. of Bariw-Alimsog Rd. (Bariw Sect.) & Buhatan-Alimsog Rd. (Alimsog Sect.) 03/18/13 V 1.420 140 C 0.396 0.200 0.300 - - - 89.60 87.02%

Satisfactory

Hi-Tone Construction and Development Corporation

(Formerly: Lo-Tone Construction & Supply)

23385 Rehab./Repair of Flood Control System Yawa River, Bogtong Sect., Bogtong 03/16/13 V 9.682 90 O 0.332 0.227 0.150 0.030 0.050 0.050 83.90 -

Hi-Tone Construction and Development Corporation/

Lanuzo's Construction & Supply (JV)

JV-12-452Cluster 12:Rehab/Impv't. of Mapulang Daga-Cagbulacao Rd. & Const. of Sula Bridge Approach 'B" Brgy. Sula &

Mapulang Daga, Bacacay08/12/13 V 14.386 110 C 0.376 0.200 0.300 - - - 87.60 87.60%

Satisfactory

Hi-Tri Development Corporation 1758Const. of Flood Control/Drainage Structures along Bogo-Curva-Medellin-Daanbantayan Rd., Paypay & Bitoon Sect.,

Daanbantayan & San Remegio08/10/13 VII 8.645 120 C 0.375 0.200 0.300 - - - 87.50 85.94%

Satisfactory

Hi-Tri Development Corporation 1758 Rehab./Reconst./Upgrading Int. Sect. along Biliran-Cagayan de Oro-Iligan Rd. (BCIR) Sugbongcogon Sect. 08/21/13 X 100.248 420 C 0.361 0.133 0.300 - - - 79.40 83.62%

Satisfactory

Hi-Tri Development Corporation 1758Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. (In. Sect.): Butuan City-Cagayan de Oro City-Iligan City

Rd., Tagbocboc-Balingoan-Esperanza Sect.08/21/13 X 79.201 300 C 0.392 0.133 0.300 - - - 82.50 83.32%

Satisfactory

Hi-Tri Development Corporation 1758 Const./Road Opening of Zamboanga West Coast Rd., Sirawai-Sibuco Rd., Sitio Sibongon-Bato Tindog Sect. 08/24/10 IX 373.450 600 O 0.355 0.283 0.150 0.023 0.042 0.033 88.60 -

Hi-Tri Development Corporation 1758 Rehab./Reconst./Upgrading of MCR (Asphalt Overlay) 03/20/12 IVB 24.689 58 C 0.496 0.133 0.300 - - - 92.90 88.04% Satisfactory

Hi-Tri Development Corporation 1758

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Roads Generated From HDM-4 (IS) along Butuan-Cagayan de Oro-

Iligan Road (BCIR), Sugbongcon Sect., K1363+000-K1376+704.25 w/ exception

03/29/12 X 100.248 360 O 0.363 0.240 0.150 0.030 0.060 0.050 89.30 -

Hi-Tri Development Corporation 1758Const. of Flood Control/Drainage Structures along Bogo-Curva-Medellin-Daanbantayan Rd., Paypay & Bitoon Sect.,

Daanbantayan & San Remegio11/27/12 VII 8.645 120 O 0.334 0.240 0.150 0.030 0.045 0.050 84.90 -

Hi-Tri Development Corporation 1758Upgrading/Concrete Paving of Dipolog-Punta-Dansullan-Sergio Osmeña Zamboanga del Norte/Zamboanga del Sur

Bdry.11/29/12 IX 80.902 290 O 0.338 0.240 0.150 0.030 0.054 0.033 84.50 -

Hi-Tri Development Corporation 1758Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd.

(IS) along Biliran-Cagayan de Oro-Iligan Road (BCIR), Sugbongcogon Sect.

11/21/12 X 100.248 420 O 0.364 0.239 0.150 0.030 0.055 0.033 87.10 -

Hi-Tri Development Corporation 1758Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd.

(IS): Butuan City-Cagayan de Oro City-Iligan City R., Tagbocboc-Balingoan-Esperanza Sect.

11/21/12 X 79.201 300 O 0.321 0.238 0.150 0.030 0.050 0.033 82.20 -

Hi-Tri Development Corporation 1758 Rehab./Retrofitting of CarayCaray Bridge, Biliran-Naval (Abutment Protection) 08/07/12 VIII 12.652 150 C 0.377 0.133 0.300 - - - 81.00 85.80%

Satisfactory

Hi-Tri Development Corporation 1758Upgrading/Concrete Paving of Dipolog-Punta-Dansullan

Sergio Osmeña Zamboanga del Norte / Zamboanga del Sur Bdry.

08/23/12 IX 80.802 290 O 0.367 0.300 0.150 0.030 0.032 0.033 91.20 -

Hi-Tri Development Corporation 1758Rehab./Reconst./Upgrading along Butuan-Cagayan de Oro-

Iligan Rd. (BCIR), Sugbongcogon Sect., K1363+000 - K1376+704.25 with exception

08/13/12 X 100.248 390 O 0.255 0.300 0.150 0.030 0.050 0.050 83.50 -

HLJ CONSTRUCTION & ENTERPRISES 18080 Const./Widening//Upgrading/Rehab. Of Access Road to

Declared Tourism Destination Brgy. Punta Taytay 8/11/2014 VI 48.105 180 C 0.395 0.200 0.300 89.50 85.96% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page118

Page 119: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

HLJ CONSTRUCTION & ENTERPRISES 18080 Const. of DepEd Standard Type School Building at

Bulwagan NHS, Hinoba-an, Negros Occidental 8/9/2014 VI 2.842 85 C 0.413 0.200 0.300 91.30 88.50% Satisfactory

HLJ Construction & Enterprises 18080 Completion of Dormitory Building 12/17/14 DOST 17.188 345 C 0.454 0.200 0.270 - - - 92.40 92.40% Very Satisfactory

HLJ Construction & Enterprises 18080 Tabuc Norte PCIP 10/19/13 NIA 10.085 180 O 0.324 0.162 0.000 0.018 0.025 0.000 52.89 -

HLJ CONSTRUCTION AND ENTERPRISES 18080 Reconstruction of Martilo Bridge 8/15/2014 VII 12.297 222 C 0.479 0.147 0.300 92.60 89.18%

Very SatisfactoryHLJ CONSTRUCTION AND

ENTERPRISES 18080 Reconstruction of Habag Bridge 8/15/2014 VII 12.050 258 C 0.490 0.143 0.300 93.30 88.74% Satisfactory

HNR Construction and Supply 22085 Roxas Airport Development Project 09/24/14 DOTC 23.270 120 C 0.434 0.200 0.300 - - - 93.36 93.36 Very Satisfactory

Homefixmix Builders Center 29997 Repair/Maint. (Existing Drainage/Flume) of Concrete Flume along MNR, K0269+000-K0270+700 w/ exception 07/29/13 I 3.764 120 O 0.389 0.240 0.150 0.030 0.037 0.033 87.90 -

Homeflix Builders Center 29997Repair/Maintenance (Existing Drainage/Flume) of Concrete Flume along Manila North Road K0269+000 - K0270+700 w/

exception8/4/2014 I 3.901 125 C 0.417 0.133 0.300 85.00 86.74%

Satisfactory

Homera Construction 33102 Conc. of Roads, Hillcrest St., Brgy. Immaculate Concepcion 08/05/13 NCR 2.455 88 C 0.405 0.133 0.300 - - - 83.80 83.80%

Satisfactory

Homeworld Construction Corp. (Formerly: Homeworld

Engineering)14725

Prev. Maint. (Int. Sect.) along Binalbagan-Isabela Rd. a)K0064+000-K0064+511, b)K0064+866-K0064+1250, c)K0067+034-K0067+200, d)K0068+342-K0068+426,

e)K0072+000-K0072+695

08/10/13 VI 17.850 115 C 0.471 0.133 0.300 - - - 90.40 85.90% Satisfactory

Homeworld Construction Corporation 14725

Prev. Maint. (Int. Sect.) along Binalbagan-Isabela Rd., a)K0064+000-K0064+511, b)K0064+866-K0064+1250, c)K0067+034-K0067+200, d)K0068+342-K0068+426,

e)K0072+000-K0072+695

03/12/13 VI 16.230 92 O 0.338 0.297 0.109 0.022 0.030 0.033 82.90 -

Homeworld Construction Corporation (Formerly:

Homeworld Engineering)14725 Prev. Maint. of Nat'l Arterial Rd. along Bacolod North Rd.

K0003+017-K0003+260 & K0000+460 to K0001+000 08/07/13 VI 16.401 40 C 0.493 0.133 0.300 - - - 92.60 92.60% Very Satisfactory

Homeworld Engineering 14725 Rehab./Reconst. of Damaged Paved Nat'l Roads Generated from PMS/HDM-4, Sum-ag-Abuanan Road 03/05/09 VI 31.087 471 O 0.266 0.281 0.150 0.030 0.060 0.050 83.70 -

HONEYVILE CONSTRUCTION 32160 Individual Project Road Concreting, San Isidro-San Vicente 11/12/2014 V 9.186 90 C 0.450 0.140 0.300 - - - 89.00% 89.00% Satisfactory

HONEYVILLE CONSTRUCTION 32160 Drainage Improvement along Trabajo Street (J.P.Rizal going to Pasig River), District I 11/19/2014 NCR 10.006 150 O 0.363 0.225 0.150 0.030 0.040 0.033 84.10% 84.10%

Satisfactory

HONEYVILLE CONSTRUCTION 32160 CONSTRUCTION OF OCINI CIS & HUYON-HUYON CIP 04/17/15 NIA 18.823 180 C 0.411 0.200 0.210 - - - - 82.07% Satisfactory

Honeyville Construction 32160 Impvt./Const. of Gravity Wall along Taytay River at Int. Sect. from Sta.0+520-Sta.6+040 08/17/13 IROWR-

PMO 44.846 175 C 0.344 0.200 0.300 - - - 84.40 84.40% Satisfactory

Honeyville Construction 32160 Impvt. of San Rafael-Mampirao-San Jose Road, (Pugay-Mampirao Section) 05/30/09 V 18.817 215 O 0.335 0.300 0.150 0.030 0.040 0.050 90.50 -

Honeyville Construction 32160 Impvt. of Goa-Digdigon-San Isidro Road, San Isidro Section 09/09/09 V 18.788 195 O 0.313 0.278 0.150 0.030 0.047 0.050 86.80 -

Honeyville Construction 32160 Rd. Upgrading (Gravel to Paved) Nabua-Balatan Rd., K490+629-K490+847 11/27/12 V 4.750 195 C 0.404 0.133 0.300 - - - 83.70 87.24%

Satisfactory

Honeyville Construction 32160 Const. of Reinforced Concrete Wall/Flood Control, Sto. Domingo 11/28/12 V 8.731 180 C 0.373 0.200 0.300 - - - 87.30 87.12%

Satisfactory

Honeyville Construction 32160 Rd. Upgrading (Gravel to Paved), Nabua-Balatan Rd. (K0490+629-K0490+847) 08/10/12 V 4.750 135 O 0.389 0.240 0.150 0.030 0.054 0.033 89.60 -

Honeyville Construction 32160Conc. of Tomagodtod-Sibobo Rd., Km.458+(-533)-

Km.458+222, Km.460+343 - Km.460+587 & Km.460+737-Km.461+477

08/13/12 V 34.919 180 C 0.461 0.133 0.300 - - - 89.40 87.24% Satisfactory

Honeyville Construction 32160 Const. of Reinforced Concrete Wall/Flood Control, Sto. Domingo 08/13/12 V 8.731 180 O 0.367 0.240 0.150 0.030 0.050 0.033 87.00 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page119

Page 120: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Honeyville Construction 32160Conc. of Lagonoy-Presentacion Rd. (Kinahulugan-Omalo-

Cabotonan Sect.), Km. 507+100-Km. 510+300 w/ exceptions, Lagonoy-Presentacion

08/11/12 V 42.736 225 C 0.440 0.133 0.300 - - - 87.30 85.44% Satisfactory

Honeyville Construction 32160 Naga City Flood Control: Repair/Maint. of Naga River Revetment, Sta. 0+000-Sta. 0+047, Brgy. Dinaga 08/06/13 V 1.960 75 C 0.453 0.133 0.300 - - - 88.60 88.60%

Satisfactory

Honeyville Construction 32160 Const./Repair/Impv't. of Drainage System along Tigaon-Goa-San Jose-Lagonoy Rd. 08/02/13 V 9.244 150 C 0.444 0.133 0.300 - - - 87.70 87.70%

Satisfactory

HONY TRADING AND CONSTRUCTION 26898

Construction of Slope Protection with Gabions as Foundation along Buli Creek (Villa Alegre), Pinagbuhatan,

Pasig City, Sta. 0+000 to Sta. 0+562.5711/29/2014 NCR 9.346 180 C 0.431 0.133 0.300 - - - 86.40% 86.40%

Satisfactory

HONY TRADING AND CONSTRUCTION 26898 Slope Protection/Bank Improvement of Merville Creek

Phase II, Barangay Sun Valley 11/19/2014 NCR 8.662 180 C 0.439 0.133 0.300 - - - 87.20% 87.20% Satisfactory

Horamabi Builders 24129 Widening of Saguing Bridge along Gapan-San Fernando-Olongapo Rd. 07/31/13 III 6.800 120 C 0.424 0.133 0.300 - - - 85.70 85.70%

Satisfactory

Horamabi Builders 24129 Const. of Two (2) CL Units, Three (3) CL Sch. Bldg. @ Payangan E/S 04/01/11 III 4.473 150 O 0.369 0.300 0.150 0.030 0.029 0.033 91.10 -

Horamabi Builders 24129 Improvement/Rehabilitation of Roman Expressway 05/21/09 III 39.329 90 O 0.348 0.300 0.150 0.030 0.037 0.050 91.50 -

Horamabi Builders 24129 Conc. of Tabon Road (FMR) 11/21/12 III 4.771 120 C 0.422 0.200 0.300 - - - 92.20 88.66% Satisfactory

Horamabi Builders 24129 Conc. of Tabon Road (FMR) 08/10/12 III 4.771 120 O 0.325 0.300 0.150 0.030 0.025 0.033 86.30 -

Horamabi Builders 24129 Conc. of Capitangan Road 03/13/13 III 4.826 119 C 0.384 0.200 0.300 - - - 88.40 88.40% Satisfactory

Houserock Builders & Trading 18822 Drainage Impv't. along Jose Abad Santos Ave. (Yuseco to Tayuman), Dist II 07/29/13 NCR 4.765 120 C 0.453 0.133 0.300 - - - 88.60 88.60%

Satisfactory

Houserock Builders & Trading 18822 Raising of Grade with Drainage Impv't. of F. Cayco St. 07/29/13 NCR 4.277 120 C 0.440 0.133 0.300 - - - 87.30 87.30% Satisfactory

HPL Construction 22289 Widening/Improvement of Dugo-San Vicente Road (Mission-Sta. Ana Section) 8/4/2012 II 46.240 194 C 0.338 0.200 0.285 82.30 82.64%

Satisfactory

HPL Construction 22289 Widening/Improvement of DVSR (Mission-Sta. Ana Section) 8/5/2012 II 44.694 194 C 0.281 0.200 0.210 69.10 76.34%

Unsatisfactory

HPL Construction 22289 Replacement of Naddungan Bridge No.2 along Magapit-Capissayan Road, Gattaran Section 8/5/2014 II 20.018 285 C 0.412 0.200 0.026 63.80 72.74%

Poor

HPL Construction 22289 Widening/Improvement of Dugo-San Vicente Road 8/4/2014 II 34.544 194 C 0.300 0.195 0.210 70.50 69.30% Poor

HPL Construction 22289Road Upgrading (Gravel to Paved) Junciton Magapit-

Capissayn Road, Sta 557+932 to Sta. 561+616 (K0558+000 to K0561) with exception

8/6/2014 II 45.889 194 C 0.388 0.200 0.000 58.80 66.90% Poor

HPL GENERAL CONSTRUCTION 22289Construction of Flood Control Mitigation Structures and Drainage System along Cagayan River Basin, Cagayan

Vallet 1st LD10/21/2014 II 28.842 150 O 0.305 0.300 0.100 0.030 0.028 0.033 79.60% 79.60%

Unsatisfactory

HPL General Construction 22289 Widening/Impv't. of Port Irene Access Rd. 07/31/13 II 15.348 151 C 0.414 0.133 0.300 - - - 84.70 84.70% Satisfactory

HPL General Construction 22289 Const. of Chico River Flood Control Proj. along Cagayan-Apayao Rd. 08/02/13 II 18.794 240 C 0.450 0.133 0.262 - - - 84.50 85.10%

Satisfactory

HPL General Construction 22289 Replacement of Naddungan Bridge No.2 along Magapit-Capissayan Rd., Gattaran Sect. 07/30/13 II 20.018 292 O 0.332 0.300 0.000 0.030 0.054 0.033 74.90 -

HPL General Construction 22289Rd. Upgrading (Gravel to Paved) Jct. Magapit-Capissayan Rd., Sta.557+932-Sta.561+616 (K0558+000-K0561+880) w/

exception07/31/13 II 43.874 179 O 0.369 0.236 0.000 0.030 0.055 0.033 72.30 -

HPL General Construction 22289 Widening/Impv't. of Dugo-San Vicente Rd. (Mission-Sta. Ana Sect.) 07/31/13 II 46.241 179 O 0.323 0.300 0.000 0.030 0.038 0.017 70.80 -

HPL General Construction 22289 Widening/Impv't. of DSVR (Mission-Sta. Ana Sect.) 07/31/13 II 44.694 179 O 0.359 0.239 0.000 0.030 0.047 0.033 70.80 -

HPL General Construction 22289Rd. Upgrading (Gravel to Paved) Sta.564+520-Sta.568+435 (K0565+059-K0569+226) Jct. Magapit-Capissayan Rd. w/

exception07/31/13 II 33.674 179 O 0.349 0.240 0.000 0.030 0.049 0.033 70.10 -

HPL General Construction 22289 Widening/Impv't. of Dugo-San Vicente Rd. 07/31/13 II 33.045 179 O 0.356 0.237 0.000 0.030 0.045 0.017 68.50 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page120

Page 121: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

HPL General Construction 22289Rd. Upgrading (Gravel to Paved), K0582+085-K0584+200, Jct. Gattaran-Cumao-Capissayan-Sta. Margarita, Bolos

Point Rd.07/30/13 II 30.035 179 O 0.331 0.240 0.000 0.030 0.054 0.017 67.20 -

HPL General Construction 22289 Repair/Rehab. of Baculud Bridge & Approaches along CVR 07/30/13 II 48.327 210 C 0.457 0.091 0.000 - - - 54.80 66.54% Poor

HPL General Construction 22289 Widening/Impvt. of DSVR (Mission-Sta. Ana Sect.) 03/11/13 II 46.241 179 O 0.391 0.300 0.047 0.030 0.047 0.050 86.50 -

HPL General Construction 22289 Const. of Chico River Flood Control Project along Cagayan-Apayao Rd. 03/12/13 II 18.794 240 O 0.267 0.300 0.150 0.030 0.051 0.033 83.10 -

HPL General Construction 22289 Widening/Impv't. of DSVR (Mission-Sta. Ana Sect.) 03/11/13 II 44.694 179 O 0.388 0.300 0.011 0.030 0.056 0.033 81.80 -

HPL General Construction 22289 Repair/Rehab. of Baculud Bridge & Approaches along CVR 03/11/13 II 48.327 225 O 0.387 0.300 0.000 0.030 0.050 0.000 76.70 -

HPL General Construction 22289 Replacement of Naddungan Bridge #2 along Magapit-Capissayan Rd., Gattaran Sect. 03/12/13 II 20.018 285 O 0.357 0.240 0.000 0.030 0.056 0.050 73.30 -

HPL General Construction 22289 Widening/Impvt. of DSVR (Mission-Sta. Ana Sect.) 11/23/12 II 46.241 179 O 0.352 0.300 0.150 0.030 0.048 0.033 91.30 -HPL General Construction 22289 Widening/Impvt. of DSVR (Mission-Sta. Ana Sect.) 11/23/12 II 44.694 179 O 0.348 0.300 0.150 0.030 0.048 0.033 90.90 -

HPL General Construction 22289 Const. of Chico River Flood Control Project along Cagayan Apayao Rd. 11/25/12 II 18.794 240 O 0.378 0.240 0.150 0.030 0.048 0.033 87.90 -

HPL General Construction 22289 Replacement of Naddungan Bridge #2 along Magapit-Capissayan Rd., Gattaran Sect. 11/24/12 II 20.018 255 O 0.387 0.281 0.100 0.030 0.048 0.033 87.90 -

HPL General Construction 22289 Repair/Rehab. of Baculud Bridge & Approaches along CVR 11/23/12 II 48.327 210 O 0.382 0.300 0.000 0.030 0.048 0.033 79.30 -

HPL General Construction 22289 Prev. Maint. at K0538+117-K0541+000 along Cagayan Valley Rd. 11/24/12 II 27.456 60 C 0.465 0.200 0.000 - - - 66.50 64.46%

Poor

HPL General Construction 22289 Repair/Rehab. of Baculud Bridge & Approaches along CVR 07/30/12 II 48.327 210 O 0.350 0.235 0.000 0.023 0.030 0.033 67.10 -

HPL General Construction 22289 Prev. Maint. at K0538+117-K0541+000 along Cagayan Valley Rd. 07/30/12 II 27.456 60 O 0.356 0.200 0.000 0.023 0.035 0.017 63.10 -

HRB Construction 10528 Land Development of Magarao Resettlement Project 11/9-12/09 NHA 5.277 110 O 0.454 0.200 0.300 - - - 95.40 -

Humming Bird Construction & Supply 33810 Const. of Three (3) Units-One (1) Storey Three (3) Cl Bldg.

(Type 1) at Dr. VFGMNHS-Daga Ext. High Sch. 08/12/13 VI 5.464 120 C 0.477 0.133 0.300 - - - 91.00 91.00% Very Satisfactory

Hunan Road & Bridge Corporation FC-11-004CP-RI 2.1: Impv't. of Magapit-Sta. Ana Rd., Magapit-

Mission Jct. Sect., Cagayan, Luzon, under the Nat'l Rds. Impv't & Mgt. Program, Phase II (NRIMP 2)

03/17/13 NRIM-PMO 383.327 22 months O 0.390 0.240 0.150 0.030 0.061 0.033 90.40 -

Hunan Road & Bridge Corporation FC-08-016NRIMP-2, CP-R12.9: Marcos Highway (Evangelista St. to

Masinag Sect.) Pasig City, Marikina City, Cainta and Antipolo City

8/13-14/11 NRIM-PMO 969.223 630 O 0.359 0.300 0.150 0.030 0.070 0.050 95.90 -

HVC SAGITTARIUS COMMERCIAL AND CONSTRUCTION 12954 Const./Completion in Area Expiriencing Acute Classroom

Shortage, Lugan Central Elementary School 8/6/2014 XII 9.439 200 C 0.405 0.133 0.300 83.80 83.80% Satisfactory

HVC Sagittarius Commercial and Construction 12954 Sarangani-Davao del Sur Coastal Road, Punsad-Pangyan

Section 06/11/09 R-XII 9.390 180 O 0.327 0.265 0.150 0.024 0.040 0.033 83.90 -

I & E CONSTRUCTION 10410 Road Upgrading (Gravel to Paved) Bagac - Mariveles Road K0183+788 - K0185+624 8/13/2014 III 47.466 198 C 0.455 0.133 0.300 88.80 88.80%

Satisfactory

I & E CONSTRUCTION 10410Widening /Impv't along Maharlika Highway Km. 935+634 -

Km. 945+500 (with exception) and Km. 951+800 - Km. 958+804 (with exception)

8/9/2014 VIII 23.300 134 C 0.432 0.159 0.300 89.10 89.10% Very Satisfactory

I & E Construction 10410 Removal of Landslides and Restoration of Collapsed Stone Masonry, Tagaytay-Taal Lake Rd. (Intermittent Sect.) 06/03/10 IVA 14.460 115 O 0.400 0.300 0.150 0.030 0.030 0.033 94.30 -

I & E Construction 10410 Widening of Sta. Rosa-Ulat-Tagaytay Rd., K0047+561-K0049+161 (w/ exception) 08/10/12 IVA 28.080 225 O 0.380 0.240 0.150 0.030 0.055 0.050 90.50 -

I & E Construction 10410 Asphalt Overlay of Manila South Rd., K0029+250-K0032+000 (IS) 08/10/12 IVA 46.477 226 O 0.363 0.208 0.150 0.030 0.045 0.050 84.60 -

I & E Construction 10410 Completion of Gandara Bridge along Gandara Diversion Rd. inc. Approaches 08/09/12 VIII 45.569 210 C 0.417 0.133 0.300 - - - 85.00 82.84%

Satisfactory

I&E Construction 10410 Rd. Upgrading (Gravel to Paved) Bagac-Mariveles Rd. K0183+788-K0185+624 08/02/13 III 45.112 175 O 0.377 0.240 0.150 0.023 0.045 0.033 86.80 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page121

Page 122: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

I&E Construction 10410Widening/Impv't. along Maharlika Highway, Km.935+634-

Km.945+500 (w/ exceptions) & Km.951+800.00-Km.958+804.00 (w/ exceptions)

08/19/13 VIII 23.300 120 O 0.386 0.240 0.150 0.010 0.047 0.050 88.30 -

I&E Construction 10410 Widening of Sta. Rosa-Ulat, Tagaytay Road, K0047+561-K0049+161 (w/ exceptions) 11/29/12 IVA 28.080 235 C 0.400 0.173 0.300 - - - 87.30 89.22%

Very Satisfactory

I&E Construction 10410 Asphalt Overlay of Manila South Rd. K0029+250 to K0032+000 (IS) 11/29/12 IVA 46.477 240 C 0.408 0.200 0.300 - - - 90.80 87.08%

Satisfactory

I&E CONSTRUCTION CORPORATION (Formerly: I&E Construction) 10410

Network Development-Widening of National Roads, National Arterial Roads, Widening of Dasmariñas-Trece

Martires City-Naic Road (Governor's Drive), Naic Section, leading to Ternate-Nasugbu Road

11/7/2014 IV 39.455 286 O 0.334 0.300 0.126 0.030 0.047 0.033 87.00% 87.00% Satisfactory

I. A. Bosque Construction Corporation 12597 Preventive Maintenance National Arterial Daang Maharlika,

K0205+319 to K0207+319, K0207+319 to K208+000 8/11/2014 IV-A 37.413 245 C 0.435 0.200 0.300 93.50 85.58% Satisfactory

I.A. Bosque Construction Corp. 12597 Conc.g of Unisan-Jct.-Panaon Rd. (Balanacan Sect.), K0197+045-K0198+545 08/06/13 IVA 32.984 180 C 0.350 0.200 0.300 - - - 85.00 86.32%

Satisfactory

I.A. Bosque Construction Corp. 12597 Prev. Maint. (MFO-1) (Int. Sect.), Nat'l Arterial Rd. (Prev.

Maint.); 1. Daang Maharlika (LZ) E. K0205+319-K0207+319; K0207+319-K0208+000

08/06/13 IVA 35.424 144 O 0.349 0.296 0.000 0.030 0.025 0.017 71.70 -

I.A. Bosque Construction Corp. 12597

Assets Preservation of Nat'l Rds. Intermittent Sect.; A. Prev. Maint.; 1. National Arterial (Prev. Maint.); 1. Daang Maharlika (LZ) E. K0205+319-K0207+319; F. K0207+319 -

K0208+000

03/18/13 IVA 35.424 144 O 0.384 0.251 0.131 0.030 0.060 0.033 88.90 -

I.A. Bosque Construction Corp. 12597 Conc. of Unisan Jct.-Panaon Rd. (Balanacan Sect.) K0197+045-K0198+545 03/17/13 IVA 32.984 180 O 0.345 0.242 0.150 0.030 0.055 0.050 87.20 -

I.A. Bosque Construction Corp./W.J. Construction (JV) JV-12-633 Construction of Concrete Canal Lining of DUMACAA RIS 09/07/13 NIA 26.942 180 O 0.357 0.242 0.150 0.030 0.042 0.050 87.12 -

I.A. Bosque Construction Corporation Mauban Port Improvement Project 04/11-15/11 PPA 32.798 403 O 34.750 30.000 5.266 3.000 7.000 1.667 81.68 -

I.A. Bosque Construction Corporation

Const of Mauban Port Improvement Project (Ports & Harbor) 02/15-18/11 PPA 32.797 403 O 0.387 0.291 0.087 0.030 0.064 0.017 87.62 -

I.D.A. JR. BUILDERS & CONSTRUCTION SUPPLY 32022

Const. of Drainage Canal along Calubian San Isidro - Tabango - Villaba - Palompon Road Km.1027+900 -

K1026+4008/8/2014 VIII 3.551 100 C 0.400 0.133 0.300 83.30 83.30%

Satisfactory

I.D.R. CONSTRUCTION 33559 Proposed Improvement of Road & Drainage along J. Posadas St., Zone 100 and Vicinity 11/20/2014 NCR 13.097 140 O 0.336 0.300 0.000 0.008 0.025 0.017 68.60% 68.60%

Poor

I.D.R. Construction 33559 Repair/Rehab/Impv't of Mendez Rd., Brgy. Baesa 08/02/13 NCR 3.840 60 C 0.419 0.133 0.300 - - - 85.20 85.20% Satisfactory

I.D.R. Construction 33559 Repair/Rehab./Impv't. of Congressional Avenue, Q.C. (K0012+300-K0014+142, East Bound) w/ exceptions 03/12/13 NCR 9.899 60 C 0.428 0.133 0.300 - - - 86.10 86.10%

Satisfactory

I.F. Blanco's Construction 25350 Rehab./Restoration of Flood Control Seawall, Recudo, Wawa, Pinamalayan 03/16/12 IVB 5.627 120 C 0.372 0.133 0.300 - - - 80.50 83.08%

Satisfactory

IA Ferrer Construction & Supply 34709 Const. of Flood Control San Roque, Lagonoy 08/02/13 V 0.938 90 C 0.462 0.133 0.300 - - - 89.50 89.50% Very Satisfactory

Ian Jason Construction and Supply 26408 Const. of 2-CL Abongan NHS Extension, Brgy. Alacalian 03/15/12 IVB 1.019 94 C 0.474 0.133 0.300 - - - 90.70 85.10% Satisfactory

IBC Intenational Builders Corporation 8576 New Iloilo Airport Development Project (Construction of

Secondary Access Road) 08/05/10 DOTC 121.222 210 O 0.355 0.300 0.107 0.030 0.070 0.050 91.20 -

IBC INTERNATIONAL BUILDERS CORPORATION 8576 Kalibo Airport Development Project 06/16/15 DOTC 56.800 180 C 0.443 0.200 0.300 - - - 94.30 94.30% Very

SatisfactoryIBC INTERNATIONAL BUILDERS

CORPORATION Dumangas Port Expansion Project 11/25/15 PPA 110.800 445 O 0.397 0.295 0.130 0.030 0.070 0.033 95.48 -

IBC International Builders Corporation 8576 Roxas Airport Development Project 09/24/14 DOTC 128.128 270 O 0.340 0.300 0.150 0.030 0.070 0.050 93.95 -

IBC INTERNATIONAL BUILDERS CORPORATION 8576 Roxas Airport Development Project 11/20/14 DOTC 128.128 270 C 0.452 0.200 0.300 - - - - 94.90%

Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page122

Page 123: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

IBC INTERNATIONAL BUILDERS CORPORATION 8576 Siargao Airport Development Project 10/16/14 DOTC 23.566 354 O 0.377 0.300 0.150 0.020 0.039 0.050 93.60 -

IBC International Builders Corporation 8576 Iloilo City Parola Ferry Terminal Development Project 03/20/14 DOTC 123.880 300 C 0.386 0.200 0.300 - - - 88.61 91.26%

SatisfactoryIBC International Builders

Corporation 8576 Widening of Dungon Bridge IV, Iloilo-Jaro Diversion Road 03/02/09 VI 14.389 436 O 0.303 0.240 0.150 0.030 0.055 0.033 81.10 -

IBC International Builders Corporation 8576 Iloilo City Parola Ferry Terminal 12/11/13 DOTC 123.880 300 O 0.360 0.300 0.150 0.030 0.040 0.050 93.04 -

IBC International Builders Corporation 8576 Proposed Improvement of container yard 08/25/12 PPA 32.010 310 O 0.390 0.226 0.150 0.030 0.065 0.050 91.10 -

IBC International Builders Corporation 8576 Improvement of Container Yard 11/15/12 PPA 32.010 310 C 0.482 0.200 0.300 - - - 98.20 93.95%

Very Satisfactory IBC International Builders

Corporation (Formerly: IBC Iloilo Builders Corp.)

8576 Prev. Maint. of Sara-Concepcion Rd., K0209+266-K0215+816 w/ exceptions 08/21/13 VI 20.300 91 C 0.482 0.133 0.300 - - - 91.50 87.84%

Satisfactory

IBC International Builders Corporation (Formerly: IBC Iloilo

Builders Corp.)8576 Conc. of Buruanga-Libertad Rd. (Jct. Nabas-

Buruanga/Libertan Rd. Sect.) inc. 3 bridges 08/16/13 VI 136.800 600 O 0.369 0.240 0.124 0.030 0.037 0.033 83.30 -

IBC International Builders Corporation (Formerly: IBC Iloilo

Builders Corp.)8576

Preventive Maint. of Various Road Sect. along Bacolod North Road (Asphalt Overlay w/ Reblocking) a) K0013+841-

K0014+208; b) K0012+526 K0013+841 (Cluster VIII)03/28/12 VI 17.620 80 C 0.471 0.196 0.300 - - - 96.70 89.14%

Very Satisfactory

IBC International Builders Corporation (Formerly: IBC Iloilo

Builders Corp.)8576 Completion of Baltazar Aquino Bridge, Phase II along Leon-

Baucari Road 03/20/12 VI 101.349 420 C 0.430 0.200 0.300 - - - 93.00 88.86% Satisfactory

IBC International Builders Corporation (Formerly: IBC Iloilo

Builders Corp.)8576

Restoration (80 mm. Asphalt Concrete) of Damaged Paved Iloilo-Antique Nat'l Road. (Clustered 2) K0024+000-

K0024+100 & K0028+000-K0028+330 (550), Tigbuan & Guimbal

03/19/12 VI 11.587 100 C 0.454 0.200 0.300 - - - 95.40 88.38% Satisfactory

IBC International Builders Corporation (Formerly: IBC Iloilo

Builders Corp.)8576

Restoration (80 mm. Asphalt Concrete) of Damaged Paved Iloilo-Antique Nat'l Rd. (Clustered 1) K009+(-937)-

K009+100303/20/12 VI 16.938 100 C 0.430 0.133 0.300 - - - 86.30 84.14%

Satisfactory

IBC INTERNATIONAL BUILDERS CORPORATION (Formerly: IBC

Iloilo Builders Corporation)8576

Road Upgrading (Gravel to Paved) along Miag-ao-Cadre Road, Miag-ao, K0039+(-222) - K0039+(-199); K0039+351 -

K0040+00010/20/2014 VI 13.901 217 C 0.419 0.133 0.300 - - - 85.20% 85.20%

Satisfactory

IBC INTERNATIONAL BUILDERS CORPORATION (Formerly: IBC

Iloilo Builders Corporation)8576

Rehabilitation/Reconstruction of Oton-Pakiad-Mandurriao Road, K009+000-K009+278 (Section 1); K0010+898-

K0010+963 (Section 2); K0011+036-K0011+386 (Section 3)10/20/2014 VI 13.620 136 O 0.340 0.236 0.150 0.030 0.055 0.033 84.40% 84.40%

Satisfactory

IBC INTERNATIONAL BUILDERS CORPORATION (Formerly: IBC

Iloilo Builders Corporation)8576 Rehabilitation/Reconstruction/Upgrading of Guimbal-

Igbaras-Tubungan-Leon Road (with exception) 10/20/2014 VI 113.300 315 O 0.370 0.300 0.103 0.030 0.040 0.033 87.60% 87.60% Satisfactory

IBC INTERNATIONAL BUILDERS CORPORATION (Formerly: IBC

Iloilo Builders Corporation)8576 Preventive Maintenance of National Secondary Road,

Lacson Street, Bacolod City K0001+(-151) to K0001+508 10/27/2014 VI 13.864 69 C 0.467 0.133 0.300 - - - 90.00% 90.00% Very Satisfactory

IBC INTERNATIONAL BUILDERS CORPORATION (Formerly: IBC

Iloilo Builders Corporation)8576

Rehabilitation/Reconstruction/Retrofitting of Existing Permanent Bago Bridge along Bacolod South By Pass

Road, K0022+352 - K0022+62210/22/2014 VI 37.121 180 O 0.391 0.225 0.150 0.030 0.055 0.050 90.10% 90.10%

Very Satisfactory

IBC INTERNATIONAL BUILDERS CORPORATION (Formerly: IBC

Iloilo Builders Corporation)8576

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Road (Intermittent Section) along Bacolod

South Road, K0066+961 - K0068+11710/23/2014 VI 20.542 192 O 0.358 0.248 0.150 0.030 0.050 0.050 88.60% 88.60%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page123

Page 124: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

IBC INTERNATIONAL BUILDERS CORPORATION (Formerly: IBC

Iloilo Builders Corporation)8576

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Road, Iloilo-Capiz Road (New Route), a) K0015+600 - K0017+000 and b) K0017+710 - K0018+043

10/28/2014 VI 25.800 171 C 0.437 0.133 0.300 - - - 87.00% 87.00% Satisfactory

IBC International Builders Corporation (Formerly: IBC Iloilo

Builders Corporation)8576 Replacement of Bridges along Nat'l Rds. Tangalan Bridge,

along Aklan West Coast Rd. (Kalibo-Nabas) 03/19/13 VI 36.300 330 C 0.437 0.170 0.300 - - - 90.70 88.09% Satisfactory

IBC International Builders Corporation (Formerly: IBC Iloilo

Builders Corporation)8576

Prev. Maint. (Int. Sect.) Jct. Bagonawa-La Carlota-Isabela Rd., Haguimit-La Granja Sect., K0051+713-K0054+204 w/

exception03/14/13 VI 17.000 65 O 0.355 0.240 0.150 0.030 0.030 0.050 85.50 -

IBC International Builders Corporation (Formerly: IBC Iloilo

Builders Corporation)8576 Prev. Maint. of Sara-Concepcion Rd., K0209+266-

K0215+816, w/ exceptions 03/21/13 VI 20.300 91 O 0.339 0.240 0.150 0.030 0.045 0.050 85.40 -

IBC International Builders Corporation (Formerly: IBC Iloilo

Builders Corporation)8576 Const. of Floodway Bridge along Metro Iloilo Radial Rd., R-

4 By-Pass over Jaro Floodway 03/22/13 VI 45.870 385 O 0.381 0.298 0.082 0.030 0.035 0.000 82.60 -

IBC International Builders Corporation (Formerly: IBC Iloilo

Builders Corporation)8576 Road Upgrading/Conc. of Tiolas-Sinugbuhan Rd. 02/23/10 VI 18.228 210 O 0.320 0.300 0.150 0.030 0.047 0.050 89.70 -

IBC International Builders Corporation (Formerly: IBC Iloilo

Builders Corporation)8576 Rehab. (Asphalt Overlay) of Bacolod South Road (Tiling

Sect.) at Brgy. Tiling 06/05/10 VI 15.827 117 O 0.364 0.240 0.150 0.022 0.037 0.033 84.60 -

IBC International Builders Corporation (Formerly: IBC Iloilo

Builders Corporation)8576 Replacement of Bridges along Nat'l Rds., Tangalan Bridge,

along Aklan West Coast Rd. (Kalibo-Nabas) 11/25/12 VI 36.300 330 O 0.384 0.240 0.102 0.030 0.045 0.033 83.40 -

IBC International Builders Corporation (Formerly: IBC Iloilo

Builders Corporation)8576 Const. of Floodway Bridge along Metro Iloilo Radial Rd., R-

4 by Pass Over Floodway 11/20/12 VI 43.306 337 O 0.368 0.300 0.067 0.030 0.050 0.017 83.20 -

IBC International Builders Corporation (Formerly: IBC Iloilo

Builders Corporation)8576 Conc. of Buruanga-Libertad Rd. (Jct. Nabas-

Buruanga/Libertad Rd. Sect.) inc. 3 Bridges 11/23/12 VI 136.800 480 O 0.282 0.300 0.146 0.030 0.050 0.017 82.50 -

IBC International Builders Corporation (Formerly: IBC Iloilo

Builders Corporation)8576 Repair/Rehab./Impv't. of Guimbal-Tubungan Rd., K29+(-

230)-K29+280; K38+513-K38+663 (L/S) w/ exception 03/17/13 VI 9.380 92 C 0.441 0.187 0.202 - - - 83.00 83.00% Satisfactory

IBC International Builders Corporation (Formerly: IBC Iloilo

Builders)8576 Impv't./Rehab. of Aklan West Rd. (Kalibo-Caticlan) Phase

II, Numancia, Aklan Rd. Sect., Sta. 272+200-Sta. 272+860 08/17/13 VI 17.023 149 C 0.428 0.133 0.300 - - - 86.10 86.10% Satisfactory

IBC International Builders Corporation (Formerly: IBC Iloilo

Builders)8576

Prev. Maint. (Int. Sect.) Jct. Bagonawa-La Carlota-Isabela Rd., Haguimit-La Granja Sect., K0051+713-K0054+204 w/

exception08/11/13 VI 17.000 65 C 0.465 0.133 0.300 - - - 89.80 87.22%

Satisfactory

IBC International Builders Corporation (Formerly: IBC Iloilo

Builders)8576 Const. of Jaro Floodway Bridge along Metro Iloilo Radial

Rd., R-4 By Pass, Over Jaro Floodway 08/23/13 VI 45.870 415 C 0.468 0.133 0.300 - - - 90.10 85.78% Satisfactory

IBC INTERNATIONAL BUILDERS CORPORATION/CCM Construction

(JV)

Emergency Repair of Dam. Access Road Network and Back-Up Area Caused by 7.2 Magnitude Earthquake,

Tagbilaran City08/15/14 PPA 27.603 210 O 0.376 0.300 0.150 0.024 0.051 0.050 95.13 -

Icalina Builders and Construction Supply 26889 Const. of 3-CL (2-Storey Type) SB, Mancanhon E/S 05/25/09 X 3.081 140 O 0.295 0.300 0.080 0.030 0.013 0.033 75.10 -

Icalina Builders and Construction Supply 26889 Const. of 3 CL 2 Storey Sch. Bldg., Macanhan E/S 03/02/09 X 3.167 120 O 0.305 0.180 0.150 0.030 0.020 0.033 71.80 -

IKM Builders & Construction Supply 30252 Repair/Rehab. Of Box Culvert & Pangao Creek along

Batangas-Quezon Road 03/20/12 IVA 4.988 120 O 0.344 0.283 0.150 0.000 0.032 0.027 83.60 -

ILBI CONSTRUCTION SUPPLY & SERVICES 32021 Construction of MPB st Sapu Padidu-Malapatan-Sarangani

Province 10/29/2014 XII 2.338 80 C 0.494 0.134 0.300 - - - 92.80% 92.80% Very Satisfactory

IM Construction 20074 Prev. Maint. (MFO-1) of Pagsanjan-Lucban Rd., K0096+230-K0097+558 08/09/13 IVA 13.439 60 C 0.479 0.133 0.300 - - - 91.20 91.20%

Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page124

Page 125: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

IM CONSTRUCTION CORPORATION 20074

Rehab./Reconstruction/Upgrading of Damaged Paved National Roads Based on Pavement Management

System/Highway Development & Management - 4 (HDM-4) (Intermittent Section) along Adante Street

11/21/2014 NCR 11.742 121 C 0.425 0.133 0.300 - - - 85.80% 85.80% Satisfactory

IM CONSTRUCTION CORPORATION 20074 Asphalt Overlay of BIR Road, K0012+346 - K0012+506,

K0012+257 - K0012+(-287) 8/15/2014 NCR 17.020 120 C 0.479 0.133 0.300 91.20 91.20% Very Satisfactory

IM Construction Corporation 20074 Completion of MPB (Package A) R. Medina Compound, Brgy. San Dionisio 09/03/09 NCR 0.997 60 O 0.305 0.203 0.150 0.030 0.023 0.025 73.60 -

IM Construction Corporation 20074 Widening/Rehab. of Sta. Maria By Pass Road inc. Drainage Canal 11/30/12 III 57.115 210 C 0.392 0.200 0.300 - - - 89.20 88.42%

Satisfactory

IM Construction Corporation 20074 Widening/Rehab. of Sta. Maria By Pass Road inc. Drainage Canal 08/03/12 III 55.819 180 O 0.289 0.300 0.150 0.030 0.060 0.050 87.90 -

IM Construction Corporation 20074 Repair/Rehab./Impv't. of McArthur Highway 03/18/13 NCR 9.405 90 C 0.395 0.135 0.300 - - - 83.00 83.00% Satisfactory

IM Construction Corporation / A.J. Lava Builders (JV) JV-11-301 Widening of Tanay-Sampaloc Rd., K0057+(-685)-

K0071+510.93 (IS) 11/19/12 IVA 47.974 180 C 0.381 0.200 0.300 - - - 88.10 87.74% Satisfactory

IM Construction Corporation / A.J. Lava Builders (JV) JV-11-301 Widening of Tanay-Sampaloc Rd., K0057+(-685)-

K0071+510.93, (IS) 08/02/12 IVA 47.974 150 O 0.362 0.240 0.143 0.030 0.050 0.050 87.50 -

Infra Builders & Sellers Phils. 9391 Conc. of Basud-Tagaytay-Baligang-Taladong-Comon-Inarado-Peñafrancia Road, Comon-Inarado Road Section 05/27/09 V 19.100 240 O 0.319 0.300 0.150 0.023 0.035 0.033 86.00 -

Infra Builders & Sellers Phils. 9394 Emergency Repair/ Replacement of Damaged RC Pier Deck 05/24/13 PPA 39.614 180 O 0.371 0.300 0.112 0.000 0.040 0.050 87.30 -

Infra Builders & Sellers Phils. 9391 Emergency Repair/ Replacement of Damaged RC Pier Deck 09/27/13 PPA 39.614 240 C 0.483 0.200 0.300 - - - 98.30 91.68% Very Satisfactory

Infra Builders and Sellers Phils/Azulrem Constn. &

Engineering ServicesJV-14-189 Repair of Damaged Port Facilities 03/19/15 PPA 17.450 120 C 0.485 0.155 0.300 - - - - 94.01%

Very Satisfactory

Interior-Philoworks Construction (JV) JV-06-026 Const./Impvt. of Libon-Marocmoc-Pantao Road 05/28/09 RRNDP 22.890 566 O 0.363 0.300 0.137 0.030 0.045 0.050 92.50 -

Interior-Philoworks Construction (JV) JV-06-026 Contract Package III, Libon-Marocmoc, Pantao Road 03/07/09 RRNDP 212.890 566 O 0.374 0.300 0.137 0.030 0.056 0.050 94.70 -

International Builders Corporation (IBC) 5876 Construction of Berthing Facilities 05/30/14 PPA 108.800 450 O 0.398 0.300 0.150 0.030 0.070 0.050 99.80 -

International Builders Corporation (IBC) 5876 Construction of Berthing Facilities 05/30/14 PPA 108.800 450 C 0.482 0.200 0.300 - - - - 99.17%

OutstandingInternational Builders Corporation

(IBC) 8576 Construction of Berthing Facilities 06/28/13 PPA 108.800 450 O 0.398 0.300 0.150 0.030 0.070 0.050 99.80 -

International Builders Corporation/CCM Construction

SL 1-SN-008251

Emergency Repair of Damaged Access Road Network and Back-Up Area caused by 7.2 Magnitude Earthquake 11/15/14 PPA 27.603 210 C 0.476 0.200 0.300 - - - - 96.11%

Outstanding

Isabela EBC Builders & Construction 26089 Rehab./Reconst./Upgrading of Daang Maharlika K0315+337-

K0316+000, K0319+574.15-K0319+957.95 03/19/12 II 8.858 120 C 0.302 0.200 0.300 - - - 80.20 83.08% Satisfactory

Isabela EBC Builders & Construction 26089

Rehab./Reconst./Upgrading of Santiago-Tuguegarao Road K0337+000-K0337+900, K0337+900-K0338+000, K0338+000-

K0339+000, K0340+00-K0341+00003/19/12 II 17.701 150 C 0.400 0.133 0.300 - - - 83.30 82.28%

Satisfactory

Isaga Builders 8652 Completion of MPB, Conner Legislative MPB 08/10/13 CAR 1.945 105 C 0.415 0.200 0.300 - - - 91.50 91.50% Very Satisfactory

Isaga Builders 8652 Proposed Rehab./Impvt. along Calanasan-Claveria Road, Magnas Section 02/27/09 CAR 9.272 416 O 0.282 0.287 0.150 0.030 0.043 0.033 82.50 -

Isaga Builders 8652 Rehab. / Impvt. along of Calanasan-Claveria Road, Magnas Section 09/05/09 CAR 9.120 438 O 0.368 0.240 0.150 0.030 0.056 0.033 87.70 -

Isaga Builders 8652 Pavement Mgt. System Highway Dev't. & Mgt./HDM-4 (IS) along Abbut Conner Road 03/20/12 CAR 4.485 179 C 0.434 0.133 0.300 - - - 86.70 87.48%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page125

Page 126: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

ISH Construction 30407 Const. of Multi-Purpose Covered Court, Function Hall and Day Care Center 07/24/09 NHA 14.742 120 O 0.379 0.259 0.150 0.030 0.070 0.050 93.80 -

ISH Construction Construction of Three (3) Storey 15-Classroom School Bldg. 03/24-11/24/11 NHA 24.066 195 O, delayed 0.441 0.200 0.300 - - - 94.10 84.35% Satisfactory

ISH Construction Inc. 30407 Construction of Three-Storey School Building (12 Classrooms) 07/10/08 SLB 17.201 150 O 0.400 0.246 0.100 0.020 0.053 0.100 91.80 -

ISH Construction, Inc. 30407 San Isidro Resettlement Project 03/2-4/2010 NHA 13.266 150 O 0.3787 0.3000 0.1058 0.03 0.05 0.05 91.45 -

ITP Construction 9392 Sta. Josefa Pump Irrigation Project 08/30/14 NIA 17.282 346 C 0.376 0.196 0.300 - - - - 87.20% Satisfactory

ITP Construction (Formerly: Construction) 9392

Rehab./Reconst./Upgrading of Butuan City-Cagayan de Oro City-Iligan City Rd., K1348+001.5-K1352+227.4 w/

exception08/13/12 X 44.945 270 O 0.244 0.300 0.000 0.030 0.050 0.033 65.70 -

ITP Construction Inc. 9392 Const. of 3-Storey 15-Classroom School Building 07/30/09 NHA 18.111 150 O 0.400 0.299 0.150 0.030 0.058 0.050 98.70 -

ITP Construction Inc. Construction of Nine (9) Five (5) Storey Residential Bldg. w/ Land Development 06/27/13 NHA 404.463 270 O 0.362 0.276 0.087 0.030 0.038 0.033 82.57 -

ITP Construction Inc. (Formerly: ITP Construction) 9392

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. (IS) Butuan City-Cagayan de Oro City-Iligan City Rd.

K1348+001.5-K1352+227.40 (w/ exception)11/22/12 X 44.945 301 C 0.442 0.200 0.300 - - - 94.20 82.71%

Satisfactory

ITP CONSTRUCTION, INC. 9392 Boracay Drainage Immediate Improvement Program (Phase 1) 2/6/15 TIEZA 91.900 665 C 0.481 0.200 0.300 98.10 89.22%

Very Satisfactory

ITP CONSTRUCTION, Inc. 9392 Land Development of Butuan City, New Villages, Phase 2 12/12/14 NHA 36.571 359 C 0.439 0.197 0.300 - - - 93.55 88.53% Satisfactory

ITP CONSTRUCTION, Inc. 9392 Construction of Five-Storey Resedential Buildings with Land Development (Bldg. No. 27, 29 and 30 only) 09/18/14 NHA 437.940 270 O 0.397 0.275 0.150 0.030 0.035 0.050 93.70 -

ITP CONSTRUCTION, Inc. 9392 Land Development of Butuan City New Villages, Phase 2 10/25/13 NHA 36.571 345 O 0.298 0.300 0.150 0.030 0.041 0.033 85.18

ITP CONSTRUCTION, Inc. Construction of Nine (9) Five-Storey Residential Buildings w/ Land Development 09/19/13 NHA 404.463 270 O 0.397 0.282 0.054 0.030 0.035 0.033 83.10

ITP CONSTRUCTION, INC. 9392 Boracay Drainage Immediate Improvement Program (Phase 1) 03/11/14 TIEZA 83.499 500 O 0.341 0.300 0.070 0.030 0.059 0.033 83.30

ITP CONSTRUCTION, Inc. 9392 Land Development of Butuan City New Villages, Phase 2 10/25/13 NHA 36.571 345 O 0.298 0.300 0.150 0.030 0.041 0.033 85.18 -

ITP Construction, Inc. Construction of (9) Five-Storey Resedential Buildings w/ Land Development 09/19/13 NHA 404.463 270

On-going (6 bldgs);

Suspended (3 bldgs)

0.397 0.282 0.054 0.030 0.035 0.033 83.10 -

ITP Construction, Inc. 9392 Construction of One (1) unit Three-Storey School Building 09/24/08 NHA 17.202 150 O 0.395 0.286 0.030 0.020 0.053 0.033 81.62 -

ITP Construction, Inc. / R.C. Tagala Construction (JV) JV-11-133

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd., Puerto Princesa South Rd. (Caramay-Aplian-Calasaguen

Sect.) K0164+024-K0168+587.25 w/ exceptions08/14/13 IVB 98.613 387 C 0.392 0.200 0.300 - - - 89.20 86.80%

Satisfactory

ITP Construction, Inc. / R.C. Tagala Construction (JV) JV-11-333

Rehab./Reconst./Upgrading of Puerto Princesa South Rd., (Caramay-Aplian-Calasaguen Sect.) (K0164+024-

K0168+587.25 w/ exceptions)03/15/13 IVB 93.914 346 O 0.359 0.276 0.125 0.030 0.055 0.033 87.80 -

Ivahrick Contractors 13688 Prev. Maint. (Int. Sect.) of South Superhighway West Service Rd. (K0012+864-K0013+285) 08/01/13 NCR 4.046 30 C 0.324 0.200 0.300 - - - 82.40 82.40%

SatisfactoryIvy Michelle Trading &

Construction 24093 Improvement of Puerto Princesa South Road K0090+180 ‐ K0091+210, Narra, Palawan 8/5/2014 IV-B 4.781 82 C 0.406 0.133 0.300 83.90 83.90%

Satisfactory

Ivy Michelle Trading & Construction 24093

Rd. Upgrading (Gravel to Concrete) of Puerto Princesa South Rd. Sta. 147+568-Sta.149+800-Sta.150+350-

Sta.150+850, Sta.151+035-Sta.151+635.50 & Sta.151+672-Sta.158+368

08/13/13 IVB 84.474 153 O 0.351 0.240 0.150 0.030 0.047 0.050 86.80 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page126

Page 127: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Ivy Michelle Trading & Construction 24093 Rd. Upgrading (Gravel to Conc.) Conc. of Puerto Princesa

South Rd. (Ipaputo-Labog Sect.) K0139+736-K0142+897.50 03/14/13 IVB 75.556 316 C 0.443 0.133 0.300 - - - 87.60 85.98% Satisfactory

Ivy Michelle Trading & Construction 24093 Rd. Upgrading of Puerto Princesa South Rd. 1. K0119+816-

K0120+472 2. K0124+396-K0124+515 03/15/13 IVB 13.292 75 O 0.363 0.237 0.150 0.030 0.045 0.033 85.80 -

Ivy Michelle Trading & Construction 24093 Conc. of PPSR Jct. Napsan-Apurawan Rd. 06/04/10 IVB 38.131 220 O 0.349 0.225 0.120 0.030 0.051 0.033 80.80 -

J & A PIMENTEL CONSTRUCTION 7953Rehabilitation/Retrofitting of Existing Permanent Bridges,

Canag-as Bridge along Jct. Gamut-San Miguel Road, Surigao del Sur 1st L.K12D.

10/25/2014 XIII 5.847 138 C 0.379 0.176 0.300 - - - 85.50% 85.50% Satisfactory

J & A PIMENTEL CONSTRUCTION 7953 Widening along Surigao-Davao Coastal Road, Tandag City, Surigao del Sur 1st LD (K1300+928 - K1301+729) 10/25/2014 XIII 11.219 88 C 0.327 0.200 0.300 - - - 82.70% 82.70%

Satisfactory

J & A PIMENTEL CONSTRUCTION 7953Widening along SCDR, Tandag City Surigao del Sur 1st LD,

K1295+204-K1297+261, Tandag Bridge, Brgy. Dagocdoc, Jct. Tandag Airport Rd. & K1295+286.70-K1296+218.20

8/12/2014 XIII 42.985 192 OG 0.322 0.207 0.150 0.022 0.028 0.050 77.90 -

J & A PIMENTEL CONSTRUCTION 7953Widening along Surigao-Davao Coastal Road, Tandag City, Surigao del Sur 1st LD, K1300+928 - K1301+729, Jct. Tago-

Tandag City8/12/2014 XIII 11.219 88 C 0.377 0.133 0.300 81.00 81.00%

Unsatisfactory

J & A Pimentel Construction 7953 Replacement of Bridge along Nat'l Rds. Badjang Bridge along Surigao-Davao Coastal Rd. 03/16/13 XIII 18.706 268 C 0.440 0.122 0.300 - - - 86.20 89.50%

Very SatisfactoryJ & A Pimentel Construction 7953 Impvt./Conc. of Telaje Road 06/09/10 XIII 6.470 120 O 0.381 0.240 0.150 0.030 0.040 0.033 87.40 -

J & A Pimentel Construction 7953 Construction of Tandag Shoreline Protection Project (Phase II) 03/12/09 XIII 13.851 150 O 0.375 0.240 0.150 0.030 0.035 0.050 88.00 -

J. A. CONSTRUCTION 35189 Villareal Port Development Project 10/27/14 DOTC 1.928 60 C 0.400 0.200 0.300 - - - 90.00 90.00% Very Satisfactory

J. B.S. Construction, Inc. 679 Rehabilitation and Development of Estero De Sampaloc 08/01/14 PRRC 20.639 368 C 0.467 0.200 0.300 - - - - 95.92% Very Satisfactory

J. C Baac Construction Corporation 25974 Impvt./Widening/Conc. of Bontoc-Tabuk-Tuguegarao Road,

Phase II, Suyo-Tangadan Section 03/04/09 CAR 47.214 360 O 0.385 0.296 0.150 0.030 0.032 0.033 92.60 -

J. C Baac Construction Corporation 25974 Impv't/Rehab Larion Alto-Cabbo-Baliuag Road (going to

Callao Alternate Route) 02/27/09 II 19.143 230 O 0.328 0.300 0.116 0.030 0.550 0.033 135.70 -

J. C Baac Construction Corporation 25974 Impvt./Rehab. of Balbalan-Pinukpuk Road 11/18/08 CAR 26.052 260 O 0.323 0.234 0.100 0.020 0.030 0.067 77.40 -

J. C. Piñon Construction, Inc. 20905 Construction of RC Wharf, RoRo Ramp, and Back-Up Area, Balanacan Port 04/29/15 PPA 76.672 360 O 0.400 0.300 0.085 0.030 0.070 0.050 93.54 -

J. CORDON CONSTRUCTION & SUPPLY 32982

Construction and Maintenance of Bridge along National Roads, Nabitasan Bridge along Iloilo City - Dumangas

Coastal Road10/28/2014 VI 2.639 150 C 0.446 0.093 0.300 - - - 83.90% 83.90%

Satisfactory

J. Cordon Construction & Supply 32982 Concrete Paving of Liningwan Rd. Sect. 08/05/13 VI 4.087 60 C 0.393 0.200 0.300 - - - 89.30 89.30% Very Satisfactory

J. Cordon Construction & Supply 32982 Repair of School Bldg. at Leon National High School 03/05/10 VI 1.440 90 O 0.296 0.300 0.150 0.015 0.027 0.033 82.10 -

J. CUSTORIO CONSTRUCTION 16237 Construction of Bridge, Palanas Cara RCBC along Calbayog - Catarman 10/22/2014 VIII 5.930 211 C 0.469 0.133 0.300 - - - 90.20% 90.20%

Very Satisfactory

J. Custorio Construction 16237 Const. of 2-CL SB, San Agustin PS 08/10/13 VIII 2.584 150 C 0.493 0.109 0.300 - - - 90.20 90.20% Very Satisfactory

J. Custorio Construction 16237 Const. of Catarman Bridge along Catarman-Laoang Road 05/26/09 VIII 9.419 150 O 0.360 0.240 0.150 0.030 0.050 0.033 86.30 -

J. Custorio Construction 16237 Rehab./Reconst./Upgrading of Damaged Paved National Roads, along Catarman-Calbayog Road 05/26/09 VIII 9.425 120 O 0.331 0.233 0.150 0.030 0.050 0.033 82.70 -

J. Custorio Construction 16237 Impvt./Rehab. of Dagansa-Libjo Road 03/07/09 VIII 4.797 60 O 0.314 0.300 0.050 0.020 0.037 0.050 77.10 -

J. Custorio Construction 16237 Const. of Catarman Bridge along Catarman-Laoang Road 09/14/09 VIII 9.419 172 O 0.345 0.240 0.150 0.030 0.045 0.033 84.30 -

J. D. LEGASPI CONSTRUCTION 9608 Jolo Port Development Project 09/11/14 DOTC 86.428 587 C 0.461 0.200 0.300 - - - - 96.00% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page127

Page 128: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

J. D. Legaspi Construction 9608 Jolo Port Development Project 09/11/14 DOTC 86.428 587 O 0.390 0.300 0.150 0.030 0.040 0.050 96.00 -

J. D. LEGASPI CONSTRUCTION 9608 Help for Catubig Agricultural Advancement Project HCAAPD-C-1 03/15/14 NIA 231.889 935 O 0.364 0.277 0.000 0.300 0.070 0.050 79.02 -

J. E. MANALO and Co., Inc. 422 Construction of RC Wharf and Two RoRo Ramps with Breasting Dolphins 08/08/14 PPA 228.253 559 C 0.599 0.200 0.200 - - - - 98.65%

Outstanding

J. M. LUCIANO CONSTRUCTION, INC. (Formerly: J. M. Luciano

Const.)2083

NRJ-Dumagnon-Enchanted River-Baculin Road Leading to Enchanted River, Talisay, Hinatuan, Surigao del Sur, Sta.

0+000 to Sta. 1+280, Sta. 3+760 to Sta. 4+6008/10/2014 XIII 41.965 152 OG 0.337 0.225 0.150 0.030 0.047 0.050 83.90 -

J. M. LUCIANO CONSTRUCTION, INC. (Formerly: J. M. Luciano

Const.)2083

Widening/Upgrading of Poblacion RTR - San Antonio - Tagnote Road with Bridge, K0+000 - K1+680, RTR, Agusan

del Norte8/5/2014 XIII 57.321 270 OG 0.341 0.225 0.150 0.030 0.033 0.050 82.90 -

J.A. Achacoso Enterprises & General Services 33229

Rehab./Reconst. Of Damaged Paved Nat'l. Road along Ormoc-Albuera Diversion Rd., Km.10129+(930)-Km.1012+(-

524)03/24/12 VIII 4.921 90 O 0.328 0.232 0.150 0.030 0.035 0.050 82.50 -

J.B. BASALLO CONSTRUCTION AND SUPPLIES 17391 Construction of Hospital Annex Building, Rosario District

Hospital 10/26/2014 I 11.268 150 O 0.372 0.241 0.150 0.030 0.051 0.050 89.40% 89.40% Very Satisfactory

J.B.S. Construction, Inc. 679 Rehabilitation and Development of Estero De Sampaloc 02/28/14 PRRC 20.639 368 O 0.382 0.300 0.150 0.030 0.042 0.050 95.40 -

J.C Baac Construction Corporation 25974 Impvt./Rehab. Larion Alto-Cabbo-Baliuag Road (Going to Callao alternate Route) 05/18/09 II 19.134 281 O 0.371 0.247 0.150 0.030 0.047 0.033 87.80 -

J.C. BAAC CONSTRUCTION CORPORATION 25974 Road Upgrading (Gravel to Paved) of Bulanao-Paracelis

Road, Cudal Section 11/27/2014 CAR 36.792 231 O 0.329 0.282 0.100 0.030 0.055 0.050 84.60% 84.60% Satisfactory

J.C. Baac Construction Corporation 25974 Replacement of Gaday Bridge along Kalinga-Abra Rd. 11/26/12 CAR 11.751 285 O 0.324 0.300 0.041 0.022 0.028 0.033 74.80 -

J.C. Baac Construction Corporation 25974 Rd. Upgrading of Mt. Province-Calanan-Pinukpuk Abbut

Rd. (Calanan-Tulyao Sect.), K0498+34 -K0499+674 08/08/12 CAR 26.369 236 C 0.343 0.200 0.300 - - - 84.30 85.68% Satisfactory

J.C. Ferrer Construction 11657 Construction of One (1), 2-Storey, 6-Classroom, Bugallon IS 8/14/2014 I 6.408 139 C 0.463 0.169 0.300 93.20 88.72%

SatisfactoryJ.C. Ferrer Construction 11657 Const. of One (1) Unit, 2-Storey, 6-Cl, Bugallon IS 08/06/13 I 6.408 139 O 0.384 0.229 0.150 0.030 0.042 0.033 86.80 -

J.C. Piñon Constructionn 20905 Construction of Marshalling Yard and Paving of Exixting Back-Up Area 04/19/13 PPA 32.950 300 O 0.392 0.300 0.150 0.030 0.070 0.050 99.17 -

J.D Legaspi Construction 9608 Construction of Solano-Quezon Road 03/12/09 II 62.893 540 O 0.365 0.300 0.150 0.030 0.055 0.050 95.00 -

J.D Legaspi Construction 9608 Impvt./Conc. of Surigao Sur-Davao Oriental Coastal Road, (Manay-Boston) Baganga Section PhaseII, C P No. 7 09/06/09 XI 191.035 597 O 0.380 0.300 0.150 0.030 0.042 0.033 93.50 -

J.D Legazpi Construction 9608 Construction of Solano-Quezon Road 06/02/09 II 62.893 540 O 0.373 0.300 0.150 0.030 0.051 0.050 95.40 -

J.D. Legaspi Construction 9608

Preventive Maintenance (MFO-1) Asphalt Overlay with Corrections along Naic Junction-Caylabne Road, Naic

Section, K0049+786 to K0049+272, K0049+272 to K0051+076, 7th Legislative District

8/5/2014 IV-A 40.350 105 C 0.430 0.200 0.300 93.00 93.00% Very Satisfactory

J.D. Legaspi Construction 9608 Repair/Restoration of Seawall along Roxas Blvd. 03/14/13 NCR 81.171 180 C 0.422 0.155 0.300 - - - 87.70 87.85% Satisfactory

J.D. Legaspi Construction 9608 Const. of Abaton-Maidland II Bridge & Approaches 03/19/13 IVB 129.171 420 O 0.378 0.300 0.075 0.030 0.054 0.050 88.70 -

J.D. Legaspi Construction 9608Rehab./Reconst./Upgrading of Damaged Pav't. of Nat'l Rd.

(MFO-2) (IS) Rizal Bdry-Famy-Quezon Rd.,-K0080+831-K0081+988

08/06/12 IVA 20.741 195 O 0.337 0.300 0.000 0.030 0.050 0.017 73.40 -

J.D. Legaspi Construction 9608 Const. of Abaton-Maidland II Bridge & Approaches 08/07/12 IVB 117.430 360 O 0.328 0.300 0.114 0.030 0.035 0.033 84.00 -

J.D. MADRID CONSTRUCTION 30365 Proposed Philippine Air Force Fence Relocation and Guard House 09/08/15 BCDA 3.599 135 C 0.476 0.200 0.300 - - - 97.60 97.60%

OutstandingJ.E Arradaza Construction and

Suppy 33256 Const. /Repair/Impvt. of MPB at Brgy. Pardo 09/02/10 VII 1.155 65 O 0.376 0.268 0.119 0.015 0.023 0.033 83.40 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page128

Page 129: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

J.E Manalo and Company, Inc. 422 New Port of San Jose 05/04-06/11 PPA 148.337 514 O 0.365 0.292 0.150 0.030 0.070 0.050 95.70 -

J.E Manalo and Company, Inc. 422 New Port of San Jose 10/04-06/11 PPA 148.337 514 O 0.499 0.200 0.300 - - - 99.89 97.24% Outstanding

J.E Manalo and Company, Inc. 422 Const. of Proposed New Port of San Jose (Ports & Harbor) 02/8-10/11 PPA 148.336 514 O 0.353 0.300 0.150 0.030 0.070 0.050 95.24 -

J.E. Manalo & Co., Inc. 422 Construction of RC Wharf and Two (2) RoRo Ramps w/ Breasting Dolphins 02/28/14 PPA 228.253 559 O 0.392 0.299 0.150 0.030 0.057 0.050 97.80 -

J.E. Tico Construction, Inc. (Formerly: Jet Construction

Supply)7063 Upgrading (Gravel to Paved) of Tapaz-Jamindan-Altavaz

Rd., Km. 115+031-Km. 115+670 w/ exception 08/19/13 VI 10.698 121 C 0.451 0.133 0.300 - - - 88.40 88.40% Satisfactory

J.E. Tico Construction, Inc. (Formerly: Jet Construction

Supply)7063 Const. of Estancia NHS 08/21/13 VI 26.812 180 O 0.333 0.240 0.150 0.030 0.038 0.050 84.10 -

J.E. Tico Construction, Inc. (Formerly: Jet Construction

Supply)7063

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. (Int. Sect.)(Nat'l Arterial Rd.) Guimaras Circ. Rd. K002+040-

K0010+23308/05/13 VI 38.631 187 C 0.340 0.200 0.300 - - - 84.00 83.64%

Satisfactory

J.E. Tico Construction, Inc. (Formerly: Jet Construction

Supply)7063

Rehab./Reconst./Upgrading of Damaged Paved Nat'l. Rds. (Int. Sect.) (Nat'l. Arterial Rd.) Guimaras Circ. Rd.,

K0002+040-K0010+223, Jordan & Buenavista03/16/13 VI 37.259 160 O 0.377 0.200 0.150 0.022 0.035 0.050 83.40 -

J.G. Garcia Construction 21054 Const./Impvt./Rehab. of FMR, Brgy. Babasit 08/05/13 I 1.965 60 C 0.474 0.133 0.300 - - - 90.70 85.96% Satisfactory

J.G. Garcia Construction 21054 Const./Impv't./Rehab. of FMR, Brgy. Babasit 03/16/13 I 1.965 60 O 0.381 0.189 0.150 0.030 0.045 0.033 82.80 -

J.G. Oranza Construction 33370 Const. of Lined Canal (Baluan Sect.) along Jct. Digos-Makar-Buayan Rd., Brgy. Baluan 03/23/13 XII 7.302 135 C 0.401 0.133 0.300 - - - 83.40 86.28%

Satisfactory

J.H Pajara Construction Corp. 1890 CP 6, Restoration of Patapat Viaduct under the Arterial Road Links Dev. Project, Phase V 11/15/08 PJHL 187.597 395 O 0.379 0.300 0.100 0.030 0.070 0.100 97.90 -

J.H Pajara Construction Corp. 1890 Const. of Calaba Bridge & Approaches (Phase I) 02/24/09 Sp. Bridges 177.680 1,002 O 0.396 0.289 0.000 0.030 0.055 0.033 80.30 -

J.I. Etac Construction & Supply 32722 Rehab./Conc. of Calbayog-Catarman Rd. via Lope de Vega K0789+220-K0806+100 08/14/13 VIII 5.039 95 C 0.337 0.200 0.300 - - - 83.70 83.70%

Satisfactory

J.M. Luciano Construction, Inc. 2083 Road Upgrading (Gravel to Concrete) Surigao-Davao Coastal Rd. (IS), Km. 1268+404-Km.1269+200.50 03/24/12 XIII 21.733 210 O 0.390 0.296 0.150 0.030 0.042 0.033 94.10 -

J.M. Luciano Construction, Inc. 2083 Road Upgrading (Gravel to Concrete) Surigao-Davao Coastal Rd. (IS), Km. 1268+404-Km.1269+200.50 11/23/12 XIII 23.083 270 C 0.433 0.182 0.300 - - - 91.50 90.45%

Very Satisfactory

J.M. Luciano Construction, Inc. 2083 Rehab./Reconst./Strengthening of Bridge @ Cabadbaran Bridge 11/23/12 XIII 19.121 330 C 0.468 0.137 0.300 - - - 90.50 87.98%

Satisfactory

J.M. LUCIANO CONSTRUCTION, INC. (Formerly: J.M. Luciano Construction) 2083 Widening/Upgrading of Poblacion RTR - San Antonio -

Tagnote Road with Bridge, K0+000 - K1+680 10/30/2014 XIII 57.321 330 O 0.322 0.279 0.150 0.030 0.056 0.050 88.70% 88.70% Satisfactory

J.M. LUCIANO CONSTRUCTION, INC. (Formerly: J.M. Luciano Construction) 2083

Rehabilitation/Reconstruction of Road Slip Protection along Surigao-Davao Coastal Road, K1480+153 -

K1480+207, (Intermittent Sections)10/24/2014 XIII 5.789 60 C 0.448 0.133 0.300 - - - 88.10% 88.10%

Satisfactory

J.M. Luciano Construction, Inc. (Formerly: J.M. Luciano

Construction)2083 Rd. Upgrading (Gravel to Conc.) of Jct. Lingig-Trento Rd.,

Pagmam-an to Boundary Cuevas Sect. with Bridge 03/07/13 XIII 113.786 375 O 0.283 0.300 0.150 0.030 0.045 0.033 84.10 -

J.M. Luciano Construction, Inc. (Formerly: J.M. Luciano

Construction)2083 Const./Impv't. along Surigao-Davao Coastal Rd. (SDCR)

Cortes-Lanuza Sect. 03/15/13 XIII 96.500 330 C 0.322 0.200 0.300 - - - 82.20 87.99% Satisfactory

J.M. Luciano Construction, Inc. (Formerly: J.M. Luciano

Construction)2083 Rehab./Reconst./Strengthening of Bridge @ Cabanahan

Bridge 08/14/12 XIII 18.024 300 O 0.283 0.300 0.150 0.030 0.050 0.050 86.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page129

Page 130: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

J.M. Luciano Construction, Inc. (Formerly: J.M. Luciano

Construction)2083 Road Upgrading (Gravel to Concrete) Surigao-Davao

Coastal Rd. (IS), Km.1268+404-Km.1269+200.50 08/14/12 XIII 21.734 210 O 0.320 0.254 0.150 0.030 0.050 0.050 85.40 -

J.M. Luciano Construction, Inc. (Formerly: Luciano Construction) 2083 Road Upgrading (Gravel to Concrete) of Jct. Lingig-Trento

Rd., Pagmam-an to Boundary Cuevas Sect. w/ Bridge 08/18/13 XIII 113.785 359 C 0.458 0.142 0.300 - - - 90.00 86.46% Satisfactory

J.M. MALIGAYA CONSTRUCTION & CONSTRUCTION SUPPLY 15018 Construction of Flood Control along Crisanto M. Delos

Reyes ave., 11/7/2014 IV 11.624 180 C 0.454 0.133 0.300 - - - 88.70% 88.70% Satisfactory

J.M. Maligaya Construction & Construction Supply 15018

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. (MFO-2) along Noveleta-Naic-Tagaytay Road, K0053+372-

K0054+19503/20/12 IVA 9.339 226 C 0.471 0.133 0.300 - - - 90.40 88.72%

Satisfactory

J.N. Dela Torre Construction 24978 Repair/Maint. of Barbacan Bridge River Control, Dumarao 03/11/13 IVB 1.617 81 C 0.439 0.133 0.300 - - - 87.20 87.20% Satisfactory

J.P. Aquino & Bros. (Engineers, Developers, Architects, Builders) 13231 Conc. of FMR @ Brgy. Tibagan 11/24/12 III 7.527 93 O 0.317 0.283 0.150 0.030 0.035 0.033 84.80 -

J.P. AQUINO CONSTRUCTION 7 ENTERPRISES (Formerly: J.P.

Aquino Bros. (Engineers, Developers, Architects, Builders)

13231 Concreting of Road at Carabaon - Calao Road 8/6/2014 III 8.223 130 C 0.425 0.133 0.300 85.80 85.80% Satisfactory

J.Q.G. CONSTRUCTION 10530 Construction of Roads, Amacalan - Bularit 8/7/2014 III 5.120 45 C 0.437 0.133 0.300 87.00 87.00% Satisfactory

J.Q.G. Construction 10530Const. of Reinforced Concrete Slope Protection along

Concepcion-La Paz Rd. (Concepcion Sect.), K0123+200-K0124+831.50 w/ exception

08/07/13 III 7.418 120 C 0.423 0.133 0.300 - - - 85.60 85.60% Satisfactory

J.Q.G. Construction 10530 Preventive Maint. along Paniqui-Pob. Road, K0144+0-K0145+717 03/15/12 III 5.110 102 C 0.460 0.200 0.300 - - - 96.00 85.26%

Satisfactory

J.S General Contractor 15258 Concreting of Tanza-Trece Martirez City-Indang Road 06/03/09 IV-A 9.630 120 O 0.368 0.240 0.150 0.030 0.025 0.050 86.30 -

J.S. General Contractor 15258Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. (MFO-2) along Maragondon-Magallanes-Amuyong Rd.,

K0059+(-060)-K0060+24608/13/13 IVA 16.917 136 C 0.339 0.200 0.300 - - - 83.90 83.90%

Satisfactory

J.S. General Contractor 15258 Reconst. of Convento Bridge along Naic Jct. Caylabne Rd. 08/13/13 IVA 14.332 179 C 0.479 0.133 0.300 - - - 91.20 91.14% Very Satisfactory

J.S. General Contractor 15258 Reconst. of Convento Bridge along Naic Jct.-Caylabne Rd. 11/26/12 IVA 13.824 179 O 0.353 0.300 0.150 0.030 0.045 0.033 91.10 -

J.T. GAMOLO CONSTRUCTION 15759

Road Upgrading (Gravel to Concrete) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to

Paved Road Standard (HDM-4) Project Analysis) (Intermittent Sections) along Kibawe-Kadingilan-

Kalilangan Road 1) K1592+000 - K1592+715; 2) K1593+172 - K1594+035

10/22/2014 X 45.824 214 C 0.375 0.191 0.300 - - - 86.60% 86.60% Satisfactory

J.T. GAMOLO CONSTRUCTION 15759 Rehab./Reconst./Upgrading of Damaged Paved along Maramag - Maradugao Road, K1591+200 - K1592+780 8/8/2014 X 24.135 149 C 0.460 0.187 0.300 94.70 94.70%

Very Satisfactory

J.T. GAMOLO CONSTRUCTION 15759 Construction of Classroom Aglayan Elementary School, Lalawan Annex 8/15/2014 X 4.185 210 C 0.498 0.200 0.300 99.80 89.16%

Very Satisfactory

J.T. GAMOLO CONSTRUCTION 15759

Road Upgrading (Gravel to Paved) of Junction Sayre Highway Aglayan - Zamboanguita Road, Capinonan & Iba

Sections, a. K1538+1010 - K1540+100 b. K1547+134 - K1547+500, Cabanglasan

8/5/2014 X 39.086 180 OG 0.383 0.296 0.110 0.030 0.041 0.033 89.30 -

J.T. GAMOLO CONSTRUCTION 15759 Cluster II - Construction of 2-Storey 4-CL of Old Nongnongan NHS 8/7/2014 X 4.420 214 C 0.435 0.200 0.300 93.50 91.33%

Very Satisfactory

J.T. GAMOLO CONSTRUCTION 15759 Cluster II - Construction of 2-Storey 4-CL of New Nongnongan NHS ( San Nicolas Annex) San Nicolas 8/7/2014 X 4.803 214 C 0.468 0.200 0.300 96.80 89.45%

Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page130

Page 131: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

J.T. GAMOLO CONSTRUCTION 15759 Construction of Slope Protection (Upstream of Musuan Bridge) along Sayre Highway 8/7/2014 X 4.940 60 C 0.492 0.200 0.300 99.20 90.20%

Very Satisfactory

J.T. GAMOLO CONSTRUCTION 15759

Rehab./Reconst./Upgrading of Damaged Paved National Roads including Drainage based on Pavement

Management System/Highway Development and Management-4 (HDM-4) (Intermittent Section)

8/6/2014 X 31.119 143 OG 0.374 0.300 0.107 0.030 0.050 0.050 91.10 -

J.T. Gamolo Construction 15759 Cluster II - Const. of 2-Storey 4-CL of Old Nongnongan NHS Old Nongnongan 08/08/13 X 4.420 214 O 0.371 0.279 0.150 0.030 0.041 0.033 90.40 -

J.T. Gamolo Construction 15759 Cluster II - Const. of 2-Storey 4-CL of New Nongnongan NHS (San Nicolas Annex) San Nicolas 08/08/13 X 4.803 214 O 0.369 0.240 0.150 0.030 0.041 0.033 86.30 -

J.T. Gamolo Construction 15759

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. Int. Sect. Sayre Highway Impalutao and Patpat Sect.,

K1485+230-K1486+000; K1496+000-K1496+290; K1496+700-K1497+000 w/ exception, Impasugong & Malaybalay City

08/10/13 X 24.019 135 C 0.379 0.200 0.300 - - - 87.90 85.26% Satisfactory

J.T. Gamolo Construction 15759 Const. of Classroom at Aglayan ES 08/09/13 X 4.185 210 O 0.324 0.240 0.150 0.030 0.052 0.050 84.60 -

J.T. Gamolo Construction 15759 Const. of Slope Protection (Upstream of Musuan Bridge) along Sayre Highway, Musuan 08/08/13 X 4.940 60 O 0.320 0.240 0.150 0.030 0.052 0.050 84.20 -

J.T. Gamolo Construction 15759Road Upgrading (Gravel to Paved) Int. Sec. inc. Drainage & Rd. Facilities along Don Carlos-Kadilingan Rd. a)K158+(-

107)-K158+329; b)K1587+(-323)-K1587+(-128)08/08/13 X 14.376 142 C 0.375 0.183 0.300 - - - 85.80 83.94%

Satisfactory

J.T. Gamolo Construction 15759 Rehab./Reconst./Upgrading (Asphalt to concrete) of S.H. Alae-Kisolon Rd., K1474+000-K1474+500, Kisolon 08/06/13 X 8.534 113 C 0.390 0.133 0.300 - - - 82.30 83.08%

Satisfactory

J.T. Gamolo Construction 15759 Rehab./Reconst./Upgrading of Int. Sect., Jct. SH Impalambong-Old Casisang Rd. K1507+(-829)-K1507+153 08/09/13 X 13.658 124 C 0.332 0.200 0.300 - - - 83.20 82.78%

Satisfactory

J.T. Gamolo Construction 15759 Rehab./Reconst./Upgrading (Asphalt to Concrete) of S.H.-Alae-Kisolon Rd., K1474+000-K1474+500, Kisolon 03/21/13 X 8.534 113 O 0.332 0.236 0.150 0.030 0.055 0.033 83.60 -

J.T. Gamolo Construction 15759

Rehab./Reconst./Upgrading of Intermittent Sect., Sayre Highway Impalutao and Patpat Sect., K1485+230-

K1486+000; K1496+000-K1496+290; K1496+700-K1497+000 w/ exception, Impasugong & Malaybalay City

03/19/13 X 24.019 135 O 0.320 0.257 0.150 0.030 0.045 0.033 83.50 -

J.T. Gamolo Construction 15759Upgrading of Rd. (Gravel to Paved), Traffic (Int. Sect.) inc.

Drainage Facilities along Don Carlos-Kadingilan Rd., a)K1581+(-107)-K1581+329; b K1587+(-323)-K1587+(-128)

03/20/13 X 14.376 70 O 0.280 0.284 0.150 0.030 0.050 0.033 82.70 -

J.T. Gamolo Construction 15759 Rehab./Reconst./Upgrading of Intermittent Sect. Jct. SH Impalambong-Old Casisang Rd. K1507+(-829)-K1507+153 03/19/13 X 13.658 94 O 0.304 0.241 0.150 0.030 0.050 0.050 82.50 -

J.T. Gamolo Construction 15759 Const. of MPB, Lumbo 08/10/12 X 18.790 210 C 0.441 0.200 0.300 - - - 94.10 89.06% Very Satisfactory

J.T. Gamolo Construction 15759 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. IS, Maramag-Marudugao Rd., K1576+229.50-K1576+850 08/09/12 X 6.890 118 C 0.427 0.200 0.148 - - - 77.50 79.18%

Unsatisfactory

J.T. GAMOLO CONSTRUCTION/MAFIL BUILDERS, INC. (J.V.)

15759Construction of Drainage System along Sayre Highway,

Bukidnon 2nd LD, K1475+256 TO K1496+765 (with exception), Impasugong and Dalwangan

8/6/2014 X 13.661 195 OG 0.383 0.300 0.115 0.008 0.023 0.033 86.20 -

J.T. GAMOLO CONSTRUCTION/RRN

CONSTRUCTION (JOINT VENTURE)

JV-13-166Construction of Drainage System along Sayre Highway, Bukidnon 2nd LD, Cabangahan Section, K1520+000 TO

K1522+000 (with exception)8/5/2014 X 13.790 195 C 0.462 0.200 0.300 96.20 96.20%

Outstanding

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page131

Page 132: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

J.V Lagon Construction Corporation 11561 Rehab./Reconst./Upgrading of Damaged Paved National

Road along Marbel-Makar Road 06/06/09 R-XII 14.317 224 O 0.318 0.254 0.150 0.012 0.055 0.017 80.60 -

J.V Lagon Construction Corporation 11561 Rehab./Reconst. of Damaged Roads Dulawan-Marbel

(Tacuromg-New Carmen Section) 06/02/09 R-XII 19.022 435 O 0.380 0.300 0.000 0.030 0.060 0.017 78.70 -

J.W.D. Construction 22291 Construction of MARIIS Main Canal, and Lateral under the PIDP 07/27/12 NIA 5.476 120 O 0.371 0.226 0.100 0.030 0.070 0.050 84.65 -

JA ACHACOSO ENTERPRISES & GEN. SERVICES 33229

Rehab./Reconst. Of Critical Section along National Highway, Road Slip along Kananga - Tungonan Hot Spring

Road, KO996+526 - KO996+6498/7/2014 VIII 2.559 90 C 0.456 0.133 0.300 88.90 88.90%

Satisfactory

Jaben General Contracting & Eng'g Services 34934 Repair/Rehab. & Const. of FMRs in the Designated Key

Production Areas, Happy Hallow 03/24/13 CAR 6.403 75 C 0.427 0.200 0.300 - - - 92.70 92.70% Very Satisfactory

JACINTO GERONA CONSTRUCTION 8165 Construction of TIEZA Building 09/25/14 TIEZA 29.701 330 C 0.462 0.155 0.300 91.70 91.70% Very

Satisfactory

Jagon Builders 24748 Const. of MPB Northville 1-B, Punturin 03/29/11 NCR 2.567 90 O 0.296 0.240 0.150 0.030 0.045 0.050 81.10 -

Jagon Builders 24748 Rehab./Impv't. of Brgy. Roads, Wenceslao 03/13/12 I 2.619 90 C 0.258 0.133 0.300 - - - 69.10 77.32% Unsatisfactory

JAGONBUILD CONNSTRUCTION CORPORATION 24748 Rehab./Reconst./ of Damaged Paved National Road

including Drainage, Chanage 0436 to 0872 8/8/2014 NCR 18.730 150 OG 0.386 0.240 0.150 0.015 0.047 0.050 89.40 -

JAGONBUILD CONNSTRUCTION CORPORATION (Formerly: Jargon

Builders)24748

Rehab./Reconst./Upgrading of Damaged Paved National Roads including Drainage Based on Pavement

Management -4 (HDM-4) along Reina, Binondo, Manila8/15/2014 NCR 5.040 75 C 0.461 0.133 0.300 89.40 89.40%

Very Satisfactory

Jagonbuild Construction Corp. 24748 Const. of Flood Control Wall along Meycauayan River in Brgy. Pangkera 03/18/13 NCR 7.051 120 O 0.298 0.300 0.150 0.023 0.018 0.033 82.20 -

Jagonbuild Construction Corp. ( Formerly: Jagon Builders) 24748 Const. of Flood Control Wall along Meycauyan River, Brgy.

Pangkera 08/13/13 NCR 7.051 120 C 0.444 0.133 0.300 - - - 87.70 84.40% Satisfactory

JAGONBUILD CONSTRUCTION CORP. (Formerly: Jagon Bulders) 24748 Preventive Maintenance along Bigaa-Plaridel via Bulacan

and Malolos Road (km. 31+(-032) to km. 32+000 11/7/2014 III 11.460 80 C 0.466 0.133 0.300 - - - 89.90% 89.90% Very Satisfactory

JAGONBUILD CONSTRUCTION CORP., (Formerly: jagon Builders) 24748

Rehab./Reconstruction of Damaged Paved National Roads based on Pavement Management System/Highway

Development & Management-4 (HDM-4) (Intermittent Section) along C-4 Road (S02153LZ)

11/21/2014 NCR 6.685 151 C 0.417 0.133 0.300 - - - 85.00% 85.00% Satisfactory

JAIME B. CHING ENTERPRISES 4256Rehabilitation/Upgrading/Widening/Concreting along

Bacolod North Road, K0025+500 - K0026+537; K0026+644 - K0027+671 with exception

10/21/2014 VI 26.674 163 C 0.428 0.133 0.300 - - - 86.10% 86.10% Satisfactory

Jaime B. Ching Enterprises 4256 Completion of Sto. Angel Central-Poblacion V Bridge, Sta. Cruz, Laguna 8/14/2014 IV-A 32.996 239 C 0.484 0.133 0.300 91.70 91.70%

Very Satisfactory

JAIME B. CHING ENTERPRISES 4256

Rehab./Reconst./Upgrading of Damaged Paved National Roads (Intermittent Sections) National Arterial Road BSR (kabankalan - Hinoba-an Section) Brgy. Masaling & Brgy.

Caliling KO123+550 - KO125+539

8/9/2014 VI 36.412 224 C 0.392 0.200 0.300 89.20 86.71% Satisfactory

JAIME B. CHING ENTERPRISES 4256Rehab./Reconst./Upgrading of Paved National Road (intermittent Section) along Bacolod South Road (a) K0065+635 - K0067+003 (b) K0072+000 - K0072+020

8/8/2014 VI 21.032 201 C 0.349 0.200 0.300 84.90 84.21% Satisfactory

JAIME B. CHING ENTERPRISES 4256

Rehab./Reconst./Upgrading of Damaged Paved National Road Dumaguete North Road (DNR), K0097+042.20 to

K0097+385.14, K0097+801.64 to K0097+980, K0098+038.14 to K0099+680.40 …………….

8/14/2014 VII 41.119 200 C 0.419 0.147 0.300 86.60 86.60% Satisfactory

Jaime B. Ching Enterprises 4256 Const. of Bridge, Brgy. Sta. Angel Central-Pob., V Bridge 08/09/13 IVA 4.925 219 C 0.475 0.133 0.300 - - - 90.80 90.80% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page132

Page 133: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Jaime B. Ching Enterprises 4256

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds., (Int. Sect.) Nat'l Arterial Rd., Bacolod South Rd.

(Kabankalan-Hinoba-an Sect.) Brgy. Masaling & Brgy. Caliling Sect., K0123+550-K0125+539

08/09/13 VI 36.412 209 O 0.342 0.240 0.150 0.030 0.042 0.033 83.70 -

Jaime B. Ching Enterprises 4256Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd.

(Int. Sect.) along Bacolod South Rd., a)K0065+635-K0067+003, b)K0072+000-K0072+020

08/10/13 VI 21.032 201 O 0.332 0.240 0.139 0.030 0.035 0.050 82.60 -

Jaime B. Ching Enterprises 4256

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd., Dumaguete North Rd. (DNR) K0097+042.20-K0097+385.14, K0097+801.64-K0097+980.14, K0098+038.14-K0099+680.40, K0110+076.4-K0110+225.90, K0110+239.40-K0110+475.84

08/22/13 VII 41.119 200 O 0.315 0.300 0.093 0.030 0.055 0.033 82.60 -

Jaime B. Ching Enterprises 4256Rd. Upgrading (Gravel to Paved) Int. Sect. at Mabina -

Ayongon Rd. (MAR) Sec.1:K0126+764-K0128+385; Sec.2;K0131+862-K0132+282

08/22/13 VII 44.888 205 O 0.333 0.300 0.054 0.030 0.050 0.033 80.00 -

Jaime B. Ching Enterprises 4256

Rehab./Reconst./Upgrading of Damaged Paved Nat'l. Rds., (Int. Sect.) Nat'l. Arterial Rd., Bacolod South Rd.

(Kabankalan-Hinoba-an Sect.), Brgy. Masaling & Brgy. Caliling Sect. K0123+500-K0125+539

03/13/13 VI 34.589 179 O 0.345 0.256 0.150 0.030 0.050 0.033 86.40 -

Jaime B. Ching Enterprises 4256Rehab./Reconst./Upgrading of Damaged Paved Nat'l. Rd.

(Int. Sect.) along Bacolod South Rd., a)K0065+635-K0067+003, b)K0072+000-K0072+020

03/12/13 VI 21.032 171 O 0.384 0.248 0.131 0.018 0.035 0.033 84.90 -

Jaime B. Ching Enterprises 4256Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd., Nat'l Secondary Rd. a) Paete-Famy-Pob. Rd., K0104+400-

K0104+70008/11/11 IVA 4.065 115 O 0.361 0.300 0.150 0.030 0.045 0.050 93.60 -

Jaime B. Ching Enterprises 4256 Reconst. of Jct. Bagonawa-La Castellana-Isabela Rd., Sta.64+877.90 - Sta.65+703.60 w/ exception 06/03/10 VI 9.453 96 O 0.372 0.240 0.150 0.022 0.047 0.033 86.40 -

Jaime B. Ching Enterprises 4256 Rehab. of Bacolod South Road (Pilar-Marina Section) 05/28/09 VI 9.484 116 O 0.373 0.240 0.150 0.015 0.045 0.033 85.60 -

Jaime B. Ching Enterprises 4256

Completion of Santisima Cruz Bridge (Santisimo/Sto. Angel Bridge w/ Approaches Drainage Slope Protection &

Other Road Network inc. RROW Acquisition & other related activities

03/17/12 IVA 70.199 360 O 0.395 0.278 0.150 0.030 0.045 0.050 94.80 -

Jaime B. Ching Enterprises 4256 Replacement of Calapnagan Bridge along Vallehermoso-Canla-on City La Castellana Rd. 11/28/12 VI 25.472 204 C 0.445 0.170 0.300 - - - 91.50 83.10%

Satisfactory

Jaime B. Ching Enterprises 4256 Replacement of Calapnagan Bridge along Vallehermoso-Canlaon City-La Castellana Rd. 08/10/12 VI 25.472 215 O 0.309 0.300 0.079 0.030 0.040 0.017 77.50 -

Jaime B. Ching Enterprises 4256 Land Development of Bon-Bon Village, Phase II 07/06/12 NHA 12.275 180 C 0.389 0.300 0.300 - - - 98.87 95.75% Very Satisfactory

Jakboa Builders (JB) 31563 Renovation of Comfort Rooms at the Sports Science and Wellness Center 11/24/11 UP 2.067 60 O 0.400 0.300 0.000 0.030 0.031 0.017 77.80 -

JAM - C BUILDERS 32870

Road Upgrading along Capas - San Jose - Mayantoc - Malacampa Road, a. K0144+193 - K0144+555 b. K0146+515 -

K0146+524, Mayantoc, Tarlac, Modified to Rehab./Reconst./Upgrading of Damaged Paved National

Roads 1. Capas - San Jose - Mayantoc - Malacampa Road, a. K0147+881 - K0149+122.50 with exception, Mayantoc

Tarlac

8/7/2014 III 7.521 120 C 0.447 0.133 0.300 88.00 88.00% Satisfactory

JAMARI CONSTRUCTION (Formerly: FRAE CNSTRUCTION) 21580 Widening of Carmen-Patag-Bulua Road Section K1441+500-

K1443+739.84 (both sides) 10/20/2014 X 24.825 227 O 0.361 0.253 0.145 0.022 0.028 0.033 84.20% 84.20% Satisfactory

JAMEETRIX CONSTRUCTION 19176 Concreting of Roads for Package B, Brgy. Centro 10/30/2014 XI 1.980 130 C 0.416 0.123 0.300 - - - 83.90% 83.90% Satisfactory

Jann-Norris Construction & Supplies 31814 Colocol Integrated CIS Rehabilitation & Extension Project 05/12/12 NIA 8.730 204 C 0.386 0.200 0.300 - - - 88.60 89.88%

Very Satisfactory Jann-Norris Construction and

Supplies 35880 Const. of Bakir Flood Control along Nueva Vizcaya-Ifugao Road 8/14/2014 II 6.944 75 C 0.385 0.143 0.300 82.80 85.56%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page133

Page 134: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Jann-Norris Construction and Supplies 35880 Const. of Bakir Flood Control along Nueva Vizcaya-Ifugao

Rd. 08/13/13 II 6.944 75 O 0.362 0.300 0.094 0.030 0.055 0.033 87.40 -

JANN-NORRIS CONSTRUCTION AND SUPPLIES/MABUHAY

CONGLOMERATE ASPHALT INC. (JV)

35880

Asset Preservation of National Roads. Preventive Maintenance, based on PMS/HDM-4, Intermittent Section,

Aritao-Quirino Road, K0244+378 - K0246+000 and K0247+227 - K0247+545

10/30/2014 II 15.831 90 C 0.437 0.133 0.300 - - - 87.00% 87.00% Satisfactory

Japuz-Jansol Enterprises 22869 Construction of Teruvian Dam & Canal System 04/13-18/09 NIA 4.178 90 O 0.352 0.180 0.150 0.030 0.064 0.050 82.55 -

Japuz-Jansol Enterprises 22869 Completion of Brgy. Maac and Cabuan W WS 08/15/12 X 7.377 90 C 0.498 0.200 0.300 - - - 99.80 94.52% Very Satisfactory

JARGON CONSTRUCTION & SUPPLY 23474

Road Upgrading (Gravel to paved) Based on Gravel Road Strategies Traffic Benchmark for Upgrading to Paved Road Standard (HDM-4) Project Analysis (Intermittent Section)

along Maitum - Lake Sebu Road, K1777+(-127) - K1779+540

8/14/2014 XII 47.974 216 C 0.447 0.186 0.300 93.30 93.30% Very Satisfactory

Jargon Construction & Supply 23474

Repair/Restoration of Damaged Rd. Slope along Jct. Dumalinao-Margosatubig Rd. (SO1170MN), Guipos Sect.,

Km.1689+130-Km.1689+257 R/S & Km.1689+408.78-Km.1689+478.80 L/S

08/16/13 IX 4.767 113 C 0.383 0.155 0.300 - - - 83.80 83.80% Satisfactory

Jargon Construction & Supply 23474 Const. of MPB at Phil. Science High Sch., Paraiso 08/06/13 XII 4.933 190 C 0.430 0.133 0.300 - - - 86.30 85.82% Satisfactory

Jargon Construction & Supply 23474 Rd. Upgrading (Gravel to Paved), Intermittent Sect., along Maitum-Lake Seibu Rd., Km.1777+(-127)-Km.1779+540 03/22/13 XII 45.583 175 O 0.383 0.280 0.150 0.030 0.033 0.033 90.90 -

Jargon Construction & Supply 23474 Const. of MPB, Phil. Science School, Paraiso 03/20/13 XII 4.933 190 O 0.352 0.240 0.150 0.030 0.050 0.033 85.50 -

Jargon Construction & Supply 23474 Replacement of Temp. to Perm. Bridges, Luyong Bridge along Maitum-Lake Sebu Rd. 03/21/13 XII 8.206 140 O 0.368 0.240 0.150 0.030 0.033 0.033 85.40 -

Jargon Construction & Supply 23474Rd. Upgrading (Gravel to Paved) along Awang-Upi Lebak-Kalamansig-Palimbang-Sarangani Rd. (NEP-Km.1958+389-

Km.1960+000) realigned to (Km.2032+015-Km.2033+600)03/13/13 XII 34.764 278 O 0.348 0.228 0.150 0.030 0.045 0.050 85.10 -

Jargon Construction & Supply 23474 Road Upgrading of Isulan Hwy. Jct. Dukay-Bagumbayan-Sen. Ninoy Aquino Road (Tayugo Section) 03/03/10 XII 13.257 155 O 0.374 0.243 0.150 0.030 0.050 0.033 88.00 -

Jargon Construction & Supply 23474 Road Upgrading of Isulan Hwy. Jct. Dukay-Bagumbayan-Sen. Ninoy Aquino Road (Sitio Katipunan Section) 03/03/10 XII 10.456 128 O 0.320 0.240 0.150 0.030 0.050 0.033 82.30 -

Jargon Construction & Supply 23474 Sarangani-Davao del Sur Coastal Road (Gumasa Section) 06/15/10 XII 9.606 150 O 0.274 0.300 0.150 0.030 0.047 0.033 83.40 -

Jargon Construction & Supply 23474 Widening/Conc. of Sarangani-Sultan Kudarat Coastal Road, Malalag Sect. 03/29/12 XII 17.298 225 C 0.424 0.200 0.300 - - - 92.40 88.40%

Satisfactory

Jargon Construction & Supply 23474 Maitum-Lake Sebu Road (Km.1766+776.50 - Km.1767+730.20) with exception 03/29/12 XII 11.818 185 C 0.455 0.200 0.300 - - - 95.50 86.50%

Satisfactory

Jargon Construction & Supply 23474 Road Upgrading along Sarangani-Davao del Sur Coastal Rd., Km 1722+626-Km 1724+100 11/27/12 XII 27.831 240 C 0.483 0.200 0.125 - - - 80.80 86.90%

Satisfactory

Jargon Construction & Supply 23474 Road Upgrading (Gravel to Conc.) along Sarangani-Davao del Sur Coastal Rd., Km.1722+626-Km.1724+000 08/21/12 XII 26.906 210 O 0.389 0.240 0.150 0.030 0.051 0.033 89.30 -

Jaro Builders & Construction Supply 25560 Construction of Minas River Control, Baco, Oriental

Mindoro 8/11/2014 IV-B 9.012 78 C 0.414 0.133 0.300 84.70 84.70% Satisfactory

Jaro Builders & Construction Supply 25560 Rd. Upgrading (Gravel to Paved) CSR Jct. Minas Rd.,

K0050+(-610)-K0050+228 08/01/13 IVB 9.450 90 C 0.367 0.200 0.300 - - - 86.70 87.84% Satisfactory

Jaro Builders & Construction Supply 25560 Rd. Upgrading (Gravel to Paved) CSR Jct. Minas Rd.,

K0050+(-)610-K0050+228 03/19/13 IVB 9.450 90 O 0.366 0.240 0.150 0.030 0.050 0.050 88.60 -

JASA Builders 31330 Widening of Urdaneta Jct.-Dagupan Road (calasiao Section) Km.205+522 to Km. 206+161 with exception 8/12/2014 I 17.829 180 C 0.399 0.133 0.300 83.20 87.46%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page134

Page 135: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Jasa Builders 31330 Widening of Urdaneta Jct.-Dagupan Rd. (Calasiao Sect.) Km. 205+522-Km. 206+161 w/ exception 08/02/13 I 16.211 201 O 0.347 0.300 0.150 0.030 0.047 0.050 92.40 -

Jasa Builders 31330 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. along Pangasinan-Zambales Rd., K0333+500-K0335+000 08/08/13 I 17.674 126 C 0.489 0.133 0.300 - - - 92.20 86.38%

Satisfactory

Jasa Builders 31330 Widening of Urdaneta Jct.-Dagupan Rd. (Calasiao Sect.) Km.205+522-Km.206+161 w/ exception 03/14/13 I 16.211 180 O 0.355 0.300 0.150 0.024 0.020 0.033 88.20 -

Jasa Builders 31330 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. along Pangasinan-Zambales Rd., K0333+500-K0335+000 03/15/13 I 17.674 96 O 0.289 0.300 0.150 0.018 0.035 0.033 82.50 -

Jasa Builders 31330 Prev. Maint. of Binmaley-Lingayen Rd. via Quibaol, K0364+061-K0366+567 03/16/13 I 14.419 30 C 0.486 0.133 0.300 - - - 91.90 91.90%

Very Satisfactory

JASA BUILDER'S 31330

Rehab./Reconst'n./ Upgrading of Damaged Paved National Roads Including Drainage based on PMS/HDM-

4(Intermittent Section); Pang-Zamb. Road K0302+000 to K0303+000/K0302+580- K0303+420(New Station);Pang.-

Zamb. Road K0307+000 to K0308+000; Pang.-Zamb. Road K0309+000 to K0309+844; Pang. Zamb. Road K0313+331 to

K0313+421

10/27/2014 I 43.427 165 C 0.437 0.134 0.300 - - - 87.10% 87.10% Satisfactory

Jasa Builders 31330 Const. of Palagao Flood Control Proj. along Jct. Ipil-Quirino Bdry. Rd., Sta.000+072-Sta.000+406, Palagao 03/15/13 II 16.975 160 C 0.417 0.133 0.300 - - - 85.00 85.12%

Satisfactory

Jasa Builders / EJR Builders and Construction Supply Joint Venture JV-12-034 Impvt./Const. of Brgy. Bario to Brgy. Malimpin Rd., Bario

ARC 10/25/13 I 23.065 210 C 0.439 0.133 0.300 - - - 87.20 87.20% Satisfactory

Jasa Builders / V.B. Manubay Construction (Joint Venture) JV-12-055 Const. of Flood Control Structures Pangal Sur Flood

Control, Sta.000+000-Sta.000+528, Pangal Sur 03/15/13 II 19.109 160 C 0.417 0.200 0.300 - - - 91.70 90.50% Very Satisfactory

Jasa Builders / V.B. Manubay Construction (Joint Venture) JV-12-056 Conc. of Jct. Ipil-Quirino Bdry. Rd. K0369+807-K0370+864,

K0374+276-K0375+080 (w/ exceptions) 03/15/13 II 17.179 180 C 0.436 0.133 0.300 - - - 86.90 88.82% Satisfactory

Jasmig Construction Supply 26069Const./Rehab. Of Flood Control System along Palico-

Balatan-Batangas City Road (Intermittent) Tuy & Balayan Sect. Tuy & Balayan

8/6/2014 IV-A 7.050 279 C 0.475 0.200 0.300 97.50 90.69% Very Satisfactory

Jasmig Construction Supply 26069 Widening of Tagaytay-Nasugbu Rd., K0091+303-K0092+750 w/ exceptions 07/31/13 IVA 23.520 225 C 0.340 0.200 0.300 - - - 84.00 84.00%

Satisfactory

Jasmig Construction Supply 26069 Prev. Maint. (MFO-I) Int. Sect. of Secondary Rd., Batanagas-Lobo Rd. from K0117+258-K0105+(-459)-K0105+000 08/16/13 IVA 5.082 60 C 0.467 0.200 0.300 - - - 96.70 91.06%

Very Satisfactory

Jasmig Construction Supply 26069Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. (MFO-2) (Int. Sect.) Sec. Rd. along Batangas-Quezon Rd.,

K0134+(-651)-K0134+00007/31/13 IVA 11.699 90 C 0.279 0.200 0.300 - - - 77.90 85.88%

Satisfactory

Jasmig Construction Supply 26069 Const./Rehab. Of Flood Control System along Palico-Balayan-Batangas City Rd. (Int.) Tuy & Balayan Sect. 07/31/13 IVA 7.050 279 O 0.347 0.256 0.135 0.030 0.040 0.033 84.10 -

Jasmig Construction Supply 26069 Rehab./Reconst./Upgrading of (Int. Sect.) Secondary Rd. along Batangas-Quezon Rd., K0134+(-651)-K0134+000 03/12/13 IVA 11.699 90 O 0.387 0.240 0.150 0.030 0.055 0.050 91.20 -

Jasmig Construction Supply 26069Const./Rehab. of Flood Control System along Palico-

Balayan-Batangas City Road (Intermittent) Tuy & Balayan Sect.

03/13/13 IVA 7.050 171 O 0.382 0.240 0.150 0.030 0.047 0.033 88.20 -

Jasmig Construction Supply 26069Prev. Maint. (MFO-1) Intermittent Sect. Secondary Rd. at

Batangas-Lobo Rd. from K0117+258-K0105+(-459)-K0105+000

03/12/13 IVA 5.082 60 O 0.348 0.240 0.150 0.030 0.055 0.050 87.30 -

Jasmig Construction Supply 26069 Nat'l Arterial Rd. along Batangas-Tabangao-Lobo Road K0134+790-K0134+900, De La Paz Proper 03/22/12 IVA 2.401 130 C 0.414 0.200 0.300 - - - 91.40 92.42%

Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page135

Page 136: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Jasmig Construction Supply 26069Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds.

along Batangas Lobo Rd. (K0105+0-K0105+560) Kumintang Ibaba

03/22/12 IVA 9.408 125 C 0.404 0.200 0.300 - - - 90.40 90.22% Very Satisfactory

Jasmig Construction Supply 26029Rehab./Reconst./Upgrading of Damaged Nat'l Road (MFO-

2) along Noveleta-Naic-Tagaytay Road, K0059+550-K0060+2

03/20/12 IVA 7.234 230 C 0.465 0.133 0.300 - - - 89.80 87.34% Satisfactory

Jasmin Construction 9561 Rehab./Reconst. Of Damaged Paved Nat'l. Rds., Baras-Gigmoto Rd. 08/17/10 V 12.085 205 O 0.328 0.286 0.100 0.020 0.030 0.050 81.40 -

Jaykris Enterprises 30906Repair/Rehab./Impv't. of Slipped Sect., along Lanao-

Pagadian-Zamboanga City Rd., Basalem Sect., Sta.1724+940-Sta.1725+025, Basalem, Buug

03/18/13 IX 9.653 128 C 0.481 0.133 0.300 - - - 91.40 88.10% Satisfactory

JB & Sons Trading and Construction 30133 Const. of Tigaplan Flood Control along Puerto Princesa

South Rd. 03/14/13 IVB 4.524 120 C 0.401 0.143 0.300 - - - 84.40 87.12% Satisfactory

JB Rock Construction Supply 34911 Repair/Rehab./Replacement/Completion & Repair of 2-CL (7m x 18m) Tagbilaran City Central Sch. 03/26/12 VII 0.911 88 C 0.423 0.133 0.300 - - - 85.60 91.48%

Very Satisfactory

J-Bros Construction 27587 Construction of 3-Storey 15-Classroom School Building 03/19/09 NHA 17.203 150 O 0.337 0.300 0.000 0.030 0.043 0.000 71.00 -

J-Bros Construction 27587 Construction of 1 Unit 3-Storey School Building 09/26/09 NHA 18.513 210 O 0.453 0.118 0.300 - - - 87.10 75.83% Unsatisfactory

J-Bros Construction 27587 Strengthening/Retrofitting of the Primier Guest House, Gate 4, Malacañang Compound 11/24/12 NCR 42.478 180 C 0.432 0.200 0.300 - - - 93.20 96.07%

Outstanding

JC Pinon Construction 2011-0959Repair of Damaged RC Curb & Curtain Wall and

Replacement of Dilapidated Mooring & Fendering System along Berth Nos. 1,3,4&5

12/07/12 PPA 31.093 180 O 0.392 0.300 0.150 0.030 0.070 0.050 99.20 -

JC Pinon Construction Inc. 20905 Construction of Marshalling Yard and Paving of Existing Back-Up Area 11/25/13 PPA 33.608 353 C 0.480 0.200 0.300 - - - 98.00 98.70%

Outstanding

JC Pinon Construction, Inc. Repair of Damaged RC curb & curtain wall and

replacement of dilapidated mooring and fendering system along berths 2, 3, 4, & 5

06/21/13 PPA 31.093 180 C 0.500 0.200 0.300 - - - 100.00 99.50% Outstanding

JC Pinon Construction, Incorporation 20905 Repair of Damaged RC Deck/Slab and Replacement of

Delapidated Mooring and Fendering System 05/29/15 PPA 32.025 300 C 0.457 0.200 0.300 - - - - 95.67% Very Satisfactory

JC Solidarity Construction 33487 Dibuluan River Irrigation Project 04/27/13 NIA 4.564 208 C 0.365 0.184 0.300 - - - 84.90 84.94% Satisfactory

JCO Construction and Supply 32576 Const. of 2 Cl Modified Sch. Bldg., Nabua West Elem. Sch. 07/31/13 V 0.951 64 C 0.488 0.110 0.300 - - - 89.80 89.80% Very Satisfactory

JDC Builders Branch 32048 Repair of Pagsangaan Flood Control Structure along Palompon-Isabel-Merida-Ormoc Road Section 03/10/09 VIII 6.690 402 O 0.274 0.245 0.150 0.020 0.021 0.050 76.00 -

Jecel Constructiion Supply 21956 Construction of Multi-Purpose Building @ Poblacion Padada 05/29/09 XI 0.951 75 O 0.351 0.300 0.150 0.030 0.038 0.033 90.20 -

Jeff Construction 25599 Paombong Port Development Project 08/20/14 DOTC 8.854 210 O 0.369 0.300 0.150 0.030 0.016 0.050 91.43 -

Jeff Enterprises 25599 Panganiban Port Development Project 07/27/15 DOTC 8.615 150 O 0.382 0.300 0.000 0.030 0.031 0.050 79.26 -

Jeff Enterprises 25599 Paombong Port Development Project 05/14/15 DOTC 8.854 180 C 0.437 0.200 0.300 - - - 93.71 92.11% Very Satisfactory

Jegma Construction and Development Corporation 14775 Impvt./Conc. of Bogo-Curva-Medellin-Daan Bantayan Road

Sta. 106+800-Sta. 112+911.80 09/03/09 VII 100.494 330 O 0.328 0.300 0.150 0.030 0.056 0.050 91.40 -

Jegma Construction & Dev't. Corporation 14775 Conc. of Liloy, Zamboanga del Norte-Ipil Zamboanga,

Sibugay 11/21/08 IX 14.314 135 O 0.358 0.240 0.070 0.030 0.030 0.033 76.10 -

Jegma Construction and Development Corporation 14775

Rehab./Reconst. of Damaged Paved Nat'l Rds. along Cebu North Hagnaya Wharf Rd. (Int. Sect.) K0050+000-

K0050+44808/13/13 VII 7.635 54 C 0.468 0.133 0.300 - - - 90.10 84.64%

Satisfactory

JEGMA CONSTRUCTION AND DEVELOPMENT CORPORATION 14775 Construction of Drainage System along Cebu North

Hagnaya Wharf Road, Sogod Section 10/21/2014 VII 18.612 240 O 0.372 0.300 0.138 0.030 0.045 0.033 91.80% 91.80% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page136

Page 137: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Jegma Construction and Development Corporation 14775

Rd. Upgrading of Nat'l Rds. (Int. Sect.) at Toledo-Tabuelan-San Remigio Rd.: 1)K0105+138-K0105+338; 2)K0105+500-

K0107+000; 3)K0105+338-K0105+408; 4)K0105+408-K0105+418; 5)K0105+120-K0105+138

08/10/13 VII 10.164 121 C 0.381 0.200 0.300 - - - 88.10 88.10% Satisfactory

Jegma Construction and Development Corporation 14775

Rehab./Reconst. Of Damaged Paved Nat'l. Rds. along Cebu North Hagnaya Wharf Rd. (Intermittent Sect.) K0050+000-

K0050+44803/19/13 VII 7.635 54 O 0.365 0.200 0.150 0.030 0.032 0.033 81.00 -

Jegma Construction and Development Corporation 14775 Impvt./Conc. of Bogo-Curva-Medellin-Daan Bantayan-Maya

Rd. 06/15/10 VII 60.795 300 O 0.306 0.237 0.150 0.030 0.060 0.050 83.30 -

Jegma Construction and Development Corporation 14775 Improvement of Multi-Purpose Building 03/03/09 VII 0.949 50 O 0.319 0.173 0.150 0.020 0.019 0.033 71.40 -

Jegma Construction and Development Corporation 14775

Impvt./Conc. of Bogo-Curva-Medellin-Daan Bantayan-Maya Road, Sta.115+600-Sta.116+048; Sta.120+026.10-

Sta.121+613.5; Sta.123+904-124+440 Sta.125+984.50-Sta. 126+000

03/24/12 VII 48.089 240 C 0.402 0.133 0.300 - - - 83.50 85.66% Satisfactory

Jegma Construction and Development Corporation 14775

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds., Cebu North Hagnaya Wharf Rd. (K0078+(-954)-K0079+000)

K0077+046-K0079+260 (Ilihan Sect.)08/21/12 VII 40.180 180 C 0.406 0.190 0.300 - - - 89.60 87.92%

Satisfactory

Jegma Construction and Development Corporation 14775 Rehab./Reconst. of North Hagnaya Wharf Rd. 08/06/12 VII 55.224 270 C 0.425 0.133 0.300 - - - 85.80 83.70%

Satisfactory

Jejor's Construction Corp 5143 Land Development of NHA-CDO Bayanihan Village, Ph 1 02/02/14 NHA 26.059 180 S 0.395 0.300 0.000 0.030 0.065 0.033 82.25 -

Jejor's Construction Corp. 5143 Land Development of NHA-CDO Bayanihan Village, Ph 1 08/14/14 NHA 26.000 254 C 0.500 0.200 0.300 - - - - 100.00% Outstanding

Jejor's Construction Corp. 5143 Land Dvelopment of NHA-CDO Bayanihan Village, Ph 1 02/07/14 NHA 26.059 180S

as of 12/06/2013

0.395 0.300 0.000 0.030 0.065 0.033 82.25 -

Jejors Construction Corporation 5143 Rehabilitation/Upgrading of RC Pier, Port of Baligoan 02/10/15 PPA 23.233 240 C 0.478 0.200 0.300 - - - - 94.42% Very Satisfactory

Jejors Construction Corporation 5143 Paving of Back-Up Area and Construction of RORO Ramp 02/10/15 PPA 53.954 331 C 0.469 0.200 0.300 - - - - 95.12% Very Satisfactory

JEJOR'S CONSTRUCTION CORPORATION 5143 Repair/Rehab./Impv't. of DPWH Building (Phase I) DPWH

Regional Office Compound, R-X 10/27/2014 X 37.102 180 C 0.406 0.133 0.300 - - - 83.90% 83.90% Satisfactory

Jejor's Construction Corporation 2011-1436 Re-waterproofing of Roofdeck & Parapets Walls, Application of Water Repellant and Related Repair Works 10/29/14 BSP 3.545 68 C 0.459 0.200 0.300 - - - 95.90 95.88%

Very Satisfactory

Jejor's Construction Corporation 5148 Construction of Roof Garden on Covered Walk going to Gate 6 04/15/14 BSP 1.995 60 C 0.459 0.200 0.300 - - - - 95.90%

Very Satisfactory

Jejor's Construction Corporation 1436 Waterproofing of Roof Deck & Parapets, Application of Water Repellant and Related Repair Works 03/05/14 BPS 3.478 60 C 0.500 0.147 0.300 - - - 94.70 94.70%

Very Satisfactory

Jejor's Construction Corporation 5143 Paving of Back-Up Area and Construction of RORO Ramp 08/30/14 PPA 53.954 270 O 0.393 0.300 0.097 0.030 0.070 0.050 93.95 -

Jejor's Construction Corporation 5143 Balbagon Port Development Project 01/29/14 DOTC 9.203 90 C 0.397 0.200 0.300 - - - 89.67 89.67% Very Satisfactory

Jejor's Construction Corporation 5143Rehab./Reconst./Upgrading (Asphalt to Concrete) of Jct. S.H.-Manolo Fortich-Libona-Indahag Rd. (Agusan Canyon

Sect.) K1458+649-K1460+63508/06/13 X 29.261 133 C 0.425 0.133 0.300 - - - 85.80 86.58%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page137

Page 138: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Jejor's Construction Corporation 5143

Const. of Slope Protection along Linamon-Zamboanga Road (Bulod River), Km.1586+596.90, Const. of 154.20m

Flood Control using Pre-Cast Concrete Sheet Piles & Class A Grouted Riprap

08/17/13 X 12.806 255 C 0.451 0.200 0.300 - - - 95.10 82.11% Satisfactory

Jejor's Construction Corporation 5143Rehab./Reconst./Upgrading (Asphalt to Concrete) of Jct. S.H.-Manolo Fortich-Libona-Indahag Rd. (Agusan Canyon

Sect.) K1458+649-K1460+63503/21/13 X 29.261 119 O 0.328 0.280 0.150 0.030 0.050 0.033 87.10 -

Jejor's Construction Corporation 5143 Rd. Upgrading (Gravel to Paved) (Int. Sect.) Cagayan de Oro City-Dominorog-Camp Kibaritan Rd. 03/22/13 X 50.364 259 O 0.271 0.300 0.096 0.020 0.025 0.033 74.50 -

Jejor's Construction Corporation 5143

Const. of Slope Protection along Linamon-Zamboanga Rd. (Bulod River) Km.1586+956.90 Const. of 154.20m Flood Control using Pre-Cast Concrete Sheet Piles & Class A

Grouted Riprap

03/15/13 X 12.806 225 O 0.221 0.300 0.000 0.010 0.051 0.050 63.20 -

Jejor's Construction Corporation 5143 Rehab./Reconst. (Asphalt to Concrete) of Jct. S.H. Manolo Fortich Libona-Indahag Rd., (Gango Section) 09/04/09 X 19.217 180 O 0.388 0.254 0.150 0.030 0.047 0.033 90.20 -

Jejor's Construction Corporation 5143 Const./Installation of New Drainage System along ICBR Rd., Osmeña-Corrales Sect. 03/30/12 X 15.418 165 O 0.356 0.300 0.055 0.030 0.045 0.017 80.30 -

Jejor's Construction Corporation 5143

Const. of Slope Protection along Linamon-Zamboanga Rd. (Bulod River), Location: K1586+956.90, Const. of 150.20

meters Flood Control using Pre-Cast Concrete Sheet Piles & Class A Grouted Riprap

11/26/12 X 12.806 210 O 0.349 0.225 0.150 0.030 0.050 0.033 83.70 -

Jejor's Construction Corporation 5143 Rd. Upgrading (Gravel to Paved) (IS): Cagayan de Oro City-Dominorog-Camp Kibaritan Rd. 11/19/12 X 50.364 150 O 0.358 0.300 0.069 0.030 0.045 0.033 83.50 -

Jejor's Construction Corporation 5143 Const./Installation of New Drainage System along ICBR Rd., Osmeña-Corrales Sect. 08/06/12 X 15.393 210 C 0.444 0.200 0.300 - - - 94.40 85.94%

Satisfactory

Jejor's Construction Corporation 5143 Const./Installation of New Drainage System along ICBR Rd., Bitan-ag-Osmeña Sect. 08/07/12 X 14.489 261 C 0.432 0.200 0.300 - - - 93.20 85.82%

Satisfactory

Jelm Construction / Chu Construction (JV) JV-12-198 Conc. of Bagahupi-Babatngon-Sta. Cruz-Barugo-Carigara

Rd., Brgy. Bacong, K0925+029.08-K0926+009.08 08/20/13 VIII 19.599 173 C 0.445 0.133 0.300 - - - 87.80 86.48% Satisfactory

Jelm Construction / Chu Construction (JV) JV-12-198 Conc. of Bagahupi-Sta. Cruz-Barugo-Carigara Rd.,

Sta.K0925+029.08-K0926+009.08, Brgy. Bacong 03/22/13 VIII 18.600 120 O 0.361 0.227 0.150 0.030 0.055 0.033 85.60 -

Jemak Construction & Supply 32056 Asphalt Overlay of Quezon-Batangas Rd., K0100+460-K0100+1000 08/03/13 IVA 3.848 28 C 0.470 0.133 0.300 - - - 90.30 90.30% Very

Satisfactory

Jemak Construction & Supply 32056 Conc. of FMR, Brgy. Mangilag Norte 08/03/13 IVA 2.348 36 C 0.331 0.200 0.300 - - - 83.10 83.10% Satisfactory

Jemak Construction & Supply 32056 Impvt. of Jct. Lucena-Diversion Rd., Lucena-Tayabas-Mauban Port Rd. 03/16/13 IVA 26.691 248 C 0.456 0.133 0.300 - - - 88.90 89.14%

Very Satisfactory

Jemak Construction & Supply 32056 Conc. of Manila South Rd.-Jct. Lopez-Catanauan Rd. 03/18/13 IVA 86.608 323 O 0.377 0.240 0.130 0.030 0.056 0.033 86.60 -

Jemak Construction & Supply 32056 Completion of Bantilan Bridge II Approaches along Quezon Eco-Tourism Road incl. Acquisition of RROW 03/14/12 IVA 22.792 270 O 0.395 0.296 0.150 0.020 0.038 0.050 94.90 -

Jemak Construction & Supply 32056 Impvt. of Jct. Lucena Diversion Rd., Lucena-Tayabas-Mauban Port Rd. 11/28/12 IVA 26.691 250 O 0.375 0.255 0.150 0.030 0.033 0.050 89.30 -

Jemak Construction & Supply 32056 Completion of Bantilan Bridge II Approaches along Eco-Tourism inc. acquisition of RROW 07/31/12 IVA 22.792 270 C 0.429 0.133 0.300 - - - 86.20 91.42%

Very Satisfactory

Jensab Construction & Design 30654 Prev. Maint. of Cebu North Hagnaya Wharf Rd. (Old Route) Int. Sect. K0034+110- K0034+684 03/19/13 VII 8.039 40 C 0.432 0.200 0.300 - - - 93.20 93.20%

Very Satisfactory

Jepa Construction and Supplies 30375 Const. of Rd., Brgy. A. Ricardo 03/14/13 III 0.929 30 C 0.397 0.133 0.300 - - - 83.00 83.00% Satisfactory

Jerry R, Santiago Construction 18453 Widening of National Roads, Daang Maharlika Road, KO119+767 - KO123+119 with exception 9/25/2014 Special 3 33.389 132 C 0.383 0.138 0.300 82.10 82.10%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page138

Page 139: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Jerry R. Santiago Construction 18453

Prev. Maint. (w/ correction Rehab./Reconst./ Upgrading of Damaged Paved Nat'l Rds. & Paving of Shoulder along

Daang Maharlika Rd., Km.104+242-Km.107+110 (2,875.00 LM)

08/12/13 III 25.291 120 C 0.446 0.133 0.300 - - - 87.90 87.90% Satisfactory

Jet Construction Supply 7063 Road Upgrading (Gravel to Paved) Mandurriao-Jaro Rd. 05/31/10 VI 4.405 150 O 0.329 0.000 0.150 0.015 0.019 0.017 53.00 -

Jet Construction Supply 7063 Conc. of Sibalom-Pis-anan Road 09/02/10 VI 33.164 150 O 0.357 0.240 0.000 0.030 0.042 0.033 70.20 -Jetver Trading & Construction 25501 Const. of Multi-Purpose Building, Brgy. Alfonso XIII 03/03/10 IVB 0.676 60 O 0.311 0.300 0.150 0.023 0.037 0.050 87.10 -

JFJ CONSTRUCTION & SUPPLY, INC. 32107 Alibuag Spring Development Project 04/10/14 TIEZA 4.993 300 O 0.342 0.289 0.051 0.015 0.000 0.000 69.70 -

JFJ CONSTRUCTION & SUPPLY, INC. 32107 Alibuag Spring Development Project 06/17/14 TIEZA 4.992 300 C 0.402 0.193 0.000 59.50 66.60% Poor

JFJ Construction and Supply, Inc. 32107 Sipalay Port Development Project 07/09/14 DOTC 1.740 60 C 0.448 0.200 0.300 - - - 94.78 94.78% Very Satisfactory

JGC Construction & Enterprises 34305Rehabilitation/Reconstruction/Upgrading of Damaged

Paved National Road aling Ipil-Liloy-Sindangan Road Km. 1998+208 - Km. 1998+622 Namnama Road Section

8/7/2014 IX 7.064 185 C 0.385 0.200 0.300 88.50 86.76% Satisfactory

JGC Construction & Enterprises 30305Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd.

along Ipil-Liloy Sindangan Rd., Km.1998+208-Km.1998+622, Namnama Rd. Sect.

08/08/13 IX 7.064 185 O 0.348 0.241 0.150 0.020 0.047 0.050 85.60 -

JH Pameron Construction & Enterprises 18792 Proposed Drainage/Protection at Cocob Sect. along

Gutalac-Baliguian Rd., Km.2012+850-Km.2015+900 08/13/13 IX 3.595 200 C 0.404 0.184 0.300 - - - 88.80 87.30% Satisfactory

JH Pameron Construction & Enterprises 18792 Proposed Drainage/Protection at Simukoy Bridge &

Approaches, Km.1946+834 along Sindangan-Liloy Rd. 03/16/13 IX 2.326 54 C 0.491 0.133 0.300 - - - 92.40 92.76% Very Satisfactory

JH Pameron Construction & Enterprises 18792 Proposed Drainage/Protection at Cocob Sect. along

Gutalac-Baliguian Rd., Km.2012+850-Km.2015+900 03/16/13 IX 3.596 195 O 0.373 0.240 0.150 0.030 0.033 0.050 87.60 -

JH Pameron Construction & Enterprises 18792 Const. of Two (2) Storey Four (4) CL Sch. Bldg. At Tukuran

CNHS (San Carlos NHS) 03/27/12 IX 3.966 90 C 0.433 0.133 0.300 - - - 86.60 86.32% Satisfactory

JH Pameron Construction & Enterprises 18792 Proposed Drainage/Protection at Cocob Sect. along

Gutalac-Baliguian Rd. Km.2012+850-Km.2015+900 11/28/12 IX 3.597 157 O 0.323 0.243 0.150 0.030 0.054 0.050 85.00 -

Jhall Marketing & Services 15760 Repair/Rehab. of Culasi Rd. 03/21/13 VI 0.999 45 C 0.438 0.133 0.300 - - - 87.10 87.10% Satisfactory

Jhall Marketing & Services 15760 Rehabilitation of Various NIS 07/21/12 NIA 6.331 150 O 0.395 0.300 0.044 0.008 0.025 0.050 82.13 -

JHJ Construction 3781Const./Widening/Upgrading/Rehab. of Access Rds.

Declared Tourism Destination, Upgrading (Asphalt to Concrete) Guimaras Circ. Rd., K0091+649-K0092+866

08/05/13 VI 9.700 65 C 0.489 0.133 0.300 - - - 92.20 92.20% Very Satisfactory

JHJ Construction 3781 Const. of MPB at Kirayan NHS 08/14/13 VI 3.319 130 O 0.361 0.230 0.000 0.030 0.027 0.033 68.10 -

JHJ Construction 3781Road Upgrading (Gravel to Paved) Based on Gravel Road

Strategies, Secondary Road Conc. of Lublub-Calao-Rosario-Cansilayan Road

03/21/12 VI 9.321 135 C 0.468 0.200 0.300 - - - 96.80 89.48% Very Satisfactory

JHJ Construction 3781 Road Upgrading (Gravel to Paved) Passi-San Rafael-Lemery-Sara Rd. K077+608-K078+378 03/23/12 VI 18.360 225 C 0.416 0.200 0.300 - - - 91.60 87.34%

Satisfactory

JHJ Construction 3781 Conc./Reblocking of Ilolilo-Capiz (Old Route) Rd., K0056+341-K0064+192.50 08/23/12 VI 13.226 210 O 0.377 0.289 0.104 0.030 0.030 0.033 86.30 -

JHJ Construction 3781 Construction of Sta. Rita - CIP 08/31/13 NIA 4.065 155 C 0.397 0.200 0.300 - - - 89.67 89.67% Very Satisfactory

JIJOMER Construction 33867 Construction of Magat River Flood Protection Dike 04/17/15 NIA 9.841 120 C 0.500 0.160 0.300 - - - - 96.00% Very Satisfactory

JIMBERNS BUILDERS & CONSTRUCTION SUPPLY 36875 Construction of Multi-Purpose Building 10/22/2014 XIII 1.911 60 O 0.289 0.300 0.150 0.020 0.032 0.050 84.10% 84.10%

SatisfactoryJIMWEN CONSTRUCTION & GENERAL MERCHANDISE 330 UMAYAM RIVER IRRIGATION PROJECT 09/12/15 NIA 13.095 347 C 0.400 0.133 0.300 - - - 83.28 83.28%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page139

Page 140: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

JIMWEN CONSTRUCTION & GENERAL MERCHANDISE 53066

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Roads Including Drainage Based on

Pavement Management System (Highway Development and Management-4 (HDM-4)(Intermittent Section) National

Secondary Road along Jct. Dumalinao-Margosatubig Road, K1718+1005.30 - K1718+1240

10/26/2014 IX 4.879 99 C 0.350 0.194 0.300 - - - 84.40% 84.40% Satisfactory

JIMWEN CONSTRUCTION & GENERAL MERCHANDISE Sta. Josefa Pump Irrigation Project 08/30/14 NIA 14.885 441 C 0.371 0.193 0.300 - - - - 86.40%

SatisfactoryJimwen Construction & General

Merchandise 33066 Const./Conc. of Roads, Brgy. Bugo 03/18/13 X 3.089 57 C 0.384 0.200 0.300 - - - 88.40 88.40% Satisfactory

JIRK CONSTRUCTION 29918 Construction of TESDA Multi-Purpose Building, San Isidro, Luna, Apayao 8/10/2014 CAR 3.981 150 C 0.428 0.133 0.300 86.10 85.75%

Satisfactory

JIRK CONSTRUCTION 29918 Construction of San Juan PS, Sta. Marcela, Apayao 8/10/2014 CAR 2.553 120 C 0.474 0.133 0.300 90.70 86.78% Satisfactory

Jirk Construction 29918 Const. of TESDA MPB, San Isidro 08/12/13 CAR 3.909 120 O 0.370 0.240 0.150 0.015 0.047 0.033 85.50 -Jirk Construction 29918 Const. of San Juan PS 08/12/13 CAR 2.553 120 O 0.366 0.240 0.150 0.015 0.047 0.033 85.10 -

Jirk Construction 29918 Asphalt Overlay/Repair/Rehab. of Cagayan Valley Road (CVR), Cagayan @ K0541+000-K0542+000 w/ exceptions 07/30/12 II 9.897 120 C 0.410 0.200 0.000 - - - 61.00 63.70%

Poor

Jits Construction Corp. 13232 Construction of 3-Storey 15-Classroom School Building 07/31/09 NHA 18.108 150 O 0.340 0.171 0.150 0.020 0.051 0.050 78.20 -

JJ & J CONSTRUCTION AND GENERAL SUPPLY 30231 Repair/Rehabilitation of Mactan Airport Road, Lapu-Lapu

Section, K0018+634 - K0019+936, Lapu-Lapu City 10/21/2014 VII 16.204 60 C 0.443 0.147 0.300 - - - 89.00% 89.00% Satisfactory

JJ & J Construction and General Supply 30234 Conc./Rehab. of Barangay Rd. at Brgy. Basak 08/13/13 VII 11.174 110 C 0.356 0.200 0.300 - - - 85.60 85.60%

Satisfactory

JJA CONSTRUCTION AND SUPPLY 22676

Package I. a. Maintenance of National Road along Abbut-Conner-Kabugao Road, K0559+120 - K0568+100

(Intermittent Sections) b. Maintenance of National Roads along Conner-Kabugao Road, K0567+127 - K0567+270

(Intermittent Section)

11/28/2014 CAR 3.193 90 C 0.461 0.133 0.300 - - - 89.40% 89.40% Very Satisfactory

JJA CONSTRUCTION AND SUPPLY 35459 "Cluster A" Expansion of Health Station a) Talagutong; b) West Lamidan; c) Lawa 10/23/2014 XI 1.940 60 C 0.374 0.168 0.300 - - - 84.20% 84.20%

Satisfactory

JJJARNS Construction 35952 Concreting of Lucban Farm-to-Market Road 8/6/2014 II 4.819 77 C 0.448 0.135 0.261 84.40 84.40% Satisfactory

JJJARNS Construction 35952 Conc. of Lucban FMR 08/02/13 II 4.819 90 O 0.350 0.225 0.150 0.030 0.045 0.033 83.30 -

JJM Commercial Inc. 32752

Rehab./Impv't. of Drainage Structure along Manila North Rd. (Clustered) 1)K0269+170-K0270+000 w/ exception,

L=102.00m, 2) K0272+350-K0273+650 w/ exception, L=97.00m 3) K0275 w/ exception L=170.00m

07/29/13 I 2.346 114 C 0.489 0.133 0.300 - - - 92.20 92.20% Very Satisfactory

JLA Construction and Supplies 24503 Const. of FMR at Brgy. Matina Biao 08/06/13 XI 1.468 40 C 0.398 0.133 0.300 - - - 83.10 83.10% Satisfactory

JLA Construction and Supplies 24503 Repair/Maint. of Tres de Mayo Revetment 03/16/13 XI 1.993 56 C 0.393 0.133 0.300 - - - 82.60 87.16% Satisfactory

JLA Construction and Supplies 24503 Package 10 - Const. FMR at 1) Brgy. Dacudao & Brgy. Talomo River, Calinan District 03/11/13 XI 1.949 40 O 0.327 0.234 0.150 0.030 0.054 0.050 84.50 -

JLA Construction and Supplies 24503 Const. of FMR at Brgy. Matina Biao, Tugbok District 03/12/13 XI 1.948 120 C 0.371 0.200 0.300 - - - 87.10 87.10% Satisfactory

JLA Construction and Supplies 24503 Conc. of Roads at Colorado-Kitaha Rd., Brgy. Colorado 03/16/13 XI 1.956 40 C 0.419 0.133 0.300 - - - 85.20 85.20% Satisfactory

JLP Construction & Supply 26983 Academic Building 3 05/14-15/09 DOST 8.294 120 O 0.383 0.295 0.150 0.030 0.062 0.050 97.00 -

JLP CONSTRUCTION AND SUPPLY (Formerly JLP Construction) 26983 Expansion, Batac Main Health Center I 10/22/204 I 3.463 171 C 0.470 0.177 0.300 - - - 94.70% 94.70%

Very Satisfactory

J-Marbel Construction and Supply 24268 Construction of Auditorium 03/19/09 DOST 13.961 169 O 0.350 0.293 0.062 0.030 0.053 0.033 82.05 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page140

Page 141: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

J-MARBELLA CONSTRUCTION 204268 PSHS BRC SITE DEV'T PROJ. PHASE 2 04/10/13 DOST 15.206 205 C 0.488 0.200 0.300 - - - 98.80 98.80% Outstanding

J-MARBELLA CONSTRUCTION 204268 PSHS BRC SITE DEV'T PROJ. PHASE 2-A 04/10/13 DOST 7.350 135 C 0.481 0.200 0.300 - - - 98.10 98.10% Outstanding

JMBM CONSTRUCTION 32955 Construction of 1-Storey 2-Classroom Building at Bungro-Sucoc Integrated School 10/25/2014 I 1.818 90 C 0.466 0.182 0.300 - - - 94.80% 94.80%

Very Satisfactory

JM-Cofer Construction and Supply 36143 Construction of Drainage System along Baao-Iriga City-Nabua Road, Baao Section 8/10/2014 V 1.897 186 OG 0.332 0.300 0.110 0.020 0.033 0.033 82.80 -

JMT CONSTRUCTION 14186 Reconstruction of SCDR (Placer - Bacuag Road Section), K1152+903.30 to K01160+940, along SCDR, Placer 6/13/2014 XIII 55.942 276 C 0.332 0.200 0.300 - - - 83.20% 83.20%

Satisfactory

JMT CONSTRUCTION 14186 Construction of One-Storey, One Classroom School Building, C.V. Diez Memorial Central Elementary School 10/28/2014 XIII 1.075 66 C 0.427 0.133 0.300 - - - 86.00% 86.00%

Satisfactory

JMT CONSTRUCTION 14186Rehab./Reconst./Improvement of Damaged Paved National Roads including Drainage based on PMS/HDM-4, National

Arterial Road, Km. 1149+000 to Km. 1151+00010/26/2014 XIII 30.689 253 O 0.338 0.238 0.147 0.022 0.051 0.050 84.60% 84.60%

Satisfactory

JMT CONSTRUCTION 14186 Road Upgrading (Gravel to Paved) Jct. Gamut-San Miguel-Bayugan Road (K1319+746 - K1320+718) 10/25/2014 XIII 25.205 205 C 0.384 0.200 0.262 - - - 84.60% 84.60%

Satisfactory

JMT CONSTRUCTION 14186 Road Upgrading (Gravel to Paved) Jct. Gamut - San Miguel - Bayugan Road, K1319+746.00 - K1320+718 8/6/2014 XIII 25.511 125 OG 0.358 0.230 0.000 0.015 0.028 0.050 68.10 -

JMT CONSTRUCTION 14186

Const./Improvement of Access Roads Leading to Declared Tourism Destinations, Calderon Village Sittio Tagbasingan Rd. Leading to Mamanwa Cultural Village and Eco Park &

Surigao City's Highest Peak Mts.

8/13/2014 XIII 9.140 90 C 0.367 0.200 0.300 86.70 86.70% Satisfactory

JMT CONSTRUCTION 14186 Concreting of Jct. Mabini - Tubajon Road, Km. 085+(-1362) to Km. 085+(-875), Km. 085+000 to Km. 086+375 8/14/2014 XIII 41.765 235 OG 0.392 0.265 0.059 0.030 0.047 0.033 82.60 -

JMT Construction 14186 Repair of Concrete Pavement at Area J and Portion of 6th Street 03/14/14 PPA 27.707 165 O 0.395 0.240 0.150 0.030 0.047 0.050 91.20 -

JMT Construction 14186 Repair of Concrete Pavement at Area J and Portion of 6th Street 08/30/14 PPA 27.707 165 C 0.458 0.200 0.300 - - - - 93.05%

Very Satisfactory

JMT Construction 14186 Repair of Concrete Pavement at Area J and Portion of 6th Street 03/14/14 PPA 27.707 165 O 0.395 0.240 0.150 0.030 0.047 0.050 91.20 -

JMT Construction 14186 Rehab./Reconst./Strengthening of Hinatigan Bridge along Surigao-Davao Coastal Rd., Brgy. Hinatigan 08/08/13 XIII 20.721 442 C 0.491 0.133 0.300 - - - 92.40 86.94%

Satisfactory

JMT Construction 14186 Reconst. of SDCR (Placer-Bacuag Rd. Sect.) along SDCR, K1152+903.30-K1160+940 08/08/13 XIII 50.940 237 O 0.361 0.233 0.150 0.030 0.035 0.050 85.90 -

JMT Construction 14186

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Arterial Rd., Daang Maharlika (Surigao-Agusan Sect.)

a)Km.1123+(-847)-Km.1123+000; b)Km.113+000-Km.1131+092, Brgy Luna & Brgy. Quezon

03/14/13 XIII 36.061 363 C 0.326 0.200 0.300 - - - 82.60 84.40% Satisfactory

JMT Construction 14186 Rehab./Reconst./Strengthening of Hinatigan Bridge along Surigao-Davao Coastal Rd., Brgy. Hinatigan 03/14/13 XIII 15.662 442 O 0.362 0.225 0.150 0.020 0.026 0.050 83.30 -

JMT Construction 14186 Replacement of Cabongbongan Bridge 2 along Jct. Magsaysay-Cagdianao Rd. 03/13/13 XIII 6.272 212 O 0.333 0.171 0.000 0.015 0.010 0.000 52.90 -

JMT Construction 14186 Rd. Upgrading ( Gravel to Concrete) Surigao-San Juan Coastal Rd. 09/06/09 XIII 9.485 210 O 0.368 0.200 0.150 0.030 0.055 0.033 83.60 -

JMT Construction 14186 Rehab./Repair of Daywan Bridge (Surigao-Davao Coastal Road), Brgy. Daywan 11/21/12 XIII 14.225 335 C 0.500 0.133 0.300 - - - 93.30 88.05%

Satisfactory

JMT Construction 14186 Replacement of Cabongbongan Bridge 2 along Jct. Magsaysay-Cagdianao Rd. 11/22/12 XIII 6.272 212 O 0.364 0.300 0.000 0.030 0.050 0.017 76.10 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page141

Page 142: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

JMT Construction 14186 Replacement of Cabongbongan Bridge 2 along Jct. Magsaysay-Cagdianao Rd. 08/10/12 XIII 5.869 150 O 0.341 0.300 0.122 0.030 0.055 0.033 88.10 -

JMT Construction 14186Asphalt Overlay w/ Pavement Markings & Reblocking

Surigao-Agusan Rd. Sect. (Impv't. along Daang Maharlika, Surigao-Agusan Sect., Km.1127+200-Km.1128+138)

08/08/12 XIII 5.851 165 C 0.471 0.133 0.300 - - - 90.40 87.16% Satisfactory

JMT Construction 14186 Rehab./Repair of Daywan Bridge (Surigao-Davao Coastal Rd.), Brgy. Daywan 08/08/12 XIII 13.159 300 O 0.328 0.247 0.150 0.030 0.055 0.033 84.30 -

JMT Construction 10029 Repair of Reinforced Concrete Deck at Berth 6 & 7 05/31/13 PPA 24.850 240 C 0.495 0.200 0.300 - - - 99.50 96.58% Outstanding

JMT Construction 14186 Repair of Reinforced Concrete Deck at Berth 6 & 7 02/14/13 PPA 24.850 240 O 0.366 0.300 0.150 0.030 0.050 0.050 94.60 -

J'NER CEPADA CONSTRUCTION 30212Road Upgrading (Gravel to Paved) of Jct. Himay-angan-

Silago - Abuyog Bdry. Road Km.1122+546.10 - Km.1122+919.70, Km.1124+705.50 - Km.1125+085.50

8/5/2014 VIII 11.910 180 OG 0.355 0.300 0.150 0.008 0.050 0.033 89.60 -

J'ner Cepada Construction 30212 Canturing Flood Control @ Bdry. So. Leyte-Maasin-Macrohon-Sogod Jct. Daang Maharlika 03/16/13 VIII 6.654 150 C 0.445 0.118 0.300 - - - 86.30 84.26%

Satisfactory

J'ner Cepada Construction 30212 Maintenance/Rehab./Impvt. of National Arterial Secondary Rd., Macrohon-P.Burgos Rd., Km.1154+000 - Km.1170+000 06/07/10 VIII 9.543 180 O 0.372 0.300 0.060 0.030 0.037 0.033 83.20 -

J'ner Cepada Construction 30212 Impvt. (Concreting) of Access Road to Maasin Port 05/27/09 VIII 1.833 120 O 0.400 0.240 0.150 0.030 0.047 0.050 91.70 -

JO Builders 34470 Clark Airport Development Project 01/15/15 DOTC 19.853 195 C 0.468 0.200 0.300 - - - - 94.29% Very Satisfactory

JO BUILDERS 34470 Clark Airport Development Project 08/14/14 DOTC 19.853 195 O 0.369 0.300 0.150 0.030 0.050 0.033 93.20 -

JOAN CONSTRUCTION 13840 Construction of Multi-Purpose Building (CSWD Office) at Brgy. Tandang Sora, Butuan City 10/29/2014 XIII 1.998 75 C 0.463 0.133 0.300 - - - 89.60% 89.60%

Very Satisfactory

JOBEL ENTERPRISES 19799Widening of Sta. Cruz Poblacion Road including Drainage/Outfall, K0085+220 to K0090+480 (with

exception), Laguna 4th LD 11/26/2014 IV 17.316 211 C 0.344 0.200 0.300 - - - 84.40% 84.40%

Satisfactory

Jobel Enterprises 19799 Construction/Improvement of Drainage System along Pagsanjan-Lucban Road, Pagsanjan-Laguna 4th LD 8/14/2014 IV-A 2.820 75 C 0.437 0.200 0.300 93.70 93.70%

Very Satisfactory

Jobel Enterprises 19799 Widening of Daang Maharlika, K0083+036.35-K0085+304.43 (Intermittent Sect.) 03/15/13 IVA 22.586 224 C 0.450 0.133 0.300 - - - 88.30 82.06%

Satisfactory

Jobel Enterprises 19799 Widening of Daang Maharlika, K0083+036.35-K0085+304.43 (IS) 11/29/12 IVA 22.596 224 O 0.297 0.300 0.000 0.030 0.050 0.033 71.00 -

Jobel Enterprises 19799 Widening of Daang Maharlika K0083+036.35-K0085+304.43 (IS) 08/08/12 IVA 22.596 200 O 0.285 0.300 0.150 0.030 0.050 0.033 84.80 -

John Arne Construction 24621 Talibon SRIS Extension 07/13/13 NIA 4.024 140 O 0.380 0.240 0.000 0.020 0.060 0.030 73.00 -

John Arne Construction 24621 Const. of Rd., Sitio Maluya, Cupang 03/14/13 III 0.930 30 C 0.408 0.133 0.300 - - - 84.10 84.10% Satisfactory

JOHN DEE B. BUSTAMANTE CONSTRUCTION 30458

Construction & Maintenance of Bridges along National Roads Rehab./Reconst./ Replacement/Retrofitting of

Existing Permanent Bridges along Nueva Ecija - Aurora Road

8/8/2014 III 3.937 90 C 0.444 0.133 0.300 87.70 87.70% Satisfactory

JOHN DEE B. BUSTAMANTE CONSTRUCTION 30458

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved

Road Standards (HDM-4 Project Analysis), National Arterial Road, Nueva Ecija - Aurora Road

8/8/2014 III 5.960 154 C 0.433 0.133 0.300 86.60 86.60% Satisfactory

John Dee B. Bustamante Construction 30458 Conc. of Road, Salay-Mucdol Road with Box Culvert 08/10/13 III 2.761 107 C 0.428 0.133 0.300 - - - 86.10 86.10%

Satisfactory

Jomarcann General Construction 30599 Conc. of North Drive-Leonard Wood Road 03/24/13 CAR 7.729 120 C 0.482 0.133 0.300 - - - 91.50 91.50% Very Satisfactory

Jomarcann General Construction 30599 Rehab./Impv't. of Marcos Highway Flood Control (Imelda-Balsigan Brgy.) 03/11/13 CAR 8.310 100 C 0.459 0.133 0.300 - - - 89.20 89.20%

Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page142

Page 143: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

JOMZKI CONSTRUCTION AND SUPPLY 32703 Rehabilitation & Reconstruction of MPC Structure (Covered Court) Brgy. Taludtod 11/8/2014 IV 3.500 105 C 0.323 0.200 0.300 - - - 82.30% 82.30%

Satisfactory

J-One Builders 32509Repair/Rehab./Impv't. along Banisilan-Guiling-Alamada-Libungan Rd., Km.1699+639-Km.1700+098 w/ exception

(0.310 Km.) (both side), Pob/ Libungan08/12/13 XII 9.583 157 C 0.451 0.133 0.300 - - - 88.40 88.40%

Satisfactory

J-One Builders 32509 Reconst. of Approaches & Bank Protection, Olandang Bridge IV (57.60 lin.m.), Olandang 03/16/13 XII 10.623 175 C 0.467 0.133 0.300 - - - 90.00 87.78%

Satisfactory

J-One Builders 32509 Conc. of FMR in Villarica 11/22/12 XII 9.179 140 C 0.433 0.200 0.300 - - - 93.30 90.54% Very Satisfactory

J-One Builders 32509 Conc. of FMR in Villarica 08/14/12 XII 9.179 140 O 0.370 0.240 0.150 0.030 0.047 0.050 88.70 -

Joni Construction 26023 Const. of 1 unit - 2 storey 8CL Sch. Bldg., Alangalang NHS 08/19/13 VIII 9.853 120 C 0.497 0.133 0.300 - - - 93.00 93.00% Very Satisfactory

JONIK TRADING & CONSTRUCION 20612 Construction of 1-Storey 1-Classroom School Bldg., Pangascasan Integrated School 10/27/2014 I 1.073 60 C 0.489 0.166 0.300 - - - 95.50% 95.50%

Very Satisfactory

Jonik Trading & Construction 20612 Construction/Rehabilitation of Caranglaan River Bank Slope Protection along Pangasinan-Zambales Road 8/14/2014 I 3.800 85 C 0.403 0.133 0.300 83.60 83.60%

Satisfactory

Jonik Trading & Construction 20612 Conc. of Rd. at Germinal Rd. 08/07/13 I 1.000 22 C 0.423 0.133 0.300 - - - 85.60 85.60% Satisfactory

Jorviv's Construction 8527 Rd. Upgrading (Gravel to Paved) of CDO City - Dominorog-Camp Kibaritan Rd. (Dominorog Sect.), Dominorog 08/11/12 X 32.256 342 C 0.406 0.200 0.300 - - - 90.60 89.88%

Very Satisfactory

Jorviv's Construction 8527 Road Upgrading (Gravel to Concrete) Barandias-Dominorog Rd. (Nabaliwa Sect.) 08/11/12 X 9.490 179 C 0.322 0.200 0.300 - - - 82.20 72.96%

Poor

JOSELLE CONSTRUCTION 16243 Construction of Multi-Purpose Building at Brgy. Lingayao, Las Nieves, Agusan del Norte 10/29/2014 XIII 1.983 45 C 0.383 0.200 0.300 - - - 88.30% 88.30%

SatisfactoryJOTCRESM ENGINEERING &

ENTERPRISES 32417 CONSTRUCTION OF DORMITORY I 01/28/14 DOST 10.951 277 C 0.441 0.200 0.300 - - - - 87.80% Satisfactory

JOVIC CONSTRUCTION & SUPPLY 35703 Const of Various Flood Control Nayon Flood Control (Upstream of Bannit Briodge) 8/5/2014 CAR 0.586 113 C 0.400 0.133 0.300 83.30 83.30%

Satisfactory

JP CHAN CONSTRUCTION 23789 Talisayan Seaside Blvd. Baywalk 1/8/15 TIEZA 2.500 90 C 0.471 0.200 0.300 97.10 97.10% Outstanding

JQD Construction and General Services 18852 Const. of Tigbao E/S, 2-CL 08/05/13 VIII 1.142 90 C 0.389 0.133 0.300 - - - 82.20 85.14%

SatisfactoryJQD Construction and General

Services 18852 Const. of Tigbao E/S, 2-CL 03/16/13 VIII 1.142 90 O 0.381 0.225 0.150 0.030 0.035 0.050 87.10 -

Jrald Construction and Trading 33079 Conc. of Brgy. Rd., Babo Sacan 07/31/13 III 1.919 35 C 0.446 0.133 0.300 - - - 87.90 87.90% Satisfactory

Jrald Construction and Trading 33079 Repair/Maint. of Santol Creek at Fortuna Section 03/11/13 III 3.501 75 C 0.406 0.133 0.300 - - - 83.90 83.90% Satisfactory

JRD CONSTRUCTION AND SUPPLY 37318 Road Upgrading (Gravel to Concrete) of Barangay Duit -

Baggo - Nungawa Road 11/24/2014 CAR 1.813 77 C 0.439 0.133 0.300 - - - 87.20% 87.20% Satisfactory

JRD‐D2 ENTERPRISES 18291 Construction of Two (2) Storey, Eight (8) Classroom School Building at Sampaloc National High School 11/27/2014 IV 9.053 180 C 0.470 0.133 0.300 - - - 90.30% 90.30%

Very Satisfactory

JRRB Construction 17247 Dibuluan River Irrigation Project 04/27/13 NIA 4.684 208 C 0.368 0.186 0.300 - - - 85.44 85.44% Satisfactory

JRY Construction 10943 Emergency Repair of Damaged Access Road Causeway Caused by 7.2 Magnitude Earthquake on October 15, 2013 08/07/15 PPA 35.353 360 C 0.500 0.200 0.300 - - - 100.00 96.22%

Outstanding

JRY Construction 10943 Emergency Repair of Damaged Access Road Causeway caused by 7.2 Magnitude Earthquake 11/15/14 PPA 35.247 360 O 0.369 0.288 0.150 0.024 0.056 0.050 93.70 -

JRY Construction 10943 Repair of RoRo Ramp, Pavement, Gate and Port Lighting System 05/04/12 PPA 20.558 360 C 0.479 0.200 0.300 - - - 97.90 98.05%

Outstanding

JRY Construction 10943 Construction of Passenger Terminal Building and Back-Up Area 05/09/13 PPA 69.999 360 O 0.393 0.267 0.117 0.030 0.070 0.050 92.70 -

JRY Construction Corporation 10943 Construction of PTB & Back-Up Area 08/15/14 PPA 73.929 360 C 0.494 0.200 0.300 - - - - 94.70% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page143

Page 144: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

JSP Construction 12517 Reconst./Reblocking along Gumaca-Pitogo-Mulanay-San Narciso Rd., K0258+133-K0259+381 08/01/12 IVA 3.769 120 C 0.416 0.133 0.300 - - - 84.90 89.82%

Very SatisfactoryJTA Builders 1801 Const. of 2-CL 7.0m x 1.0 m Dulong E/S 09/09/09 X 1.033 60 O 0.379 0.191 0.150 0.030 0.043 0.033 82.60 -

JTA Builders 18401Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds.

along Arterial Rd. a) K0069+900-K0073+042 & b)K0075+400-K0077+205

11/28/12 VI 45.859 229 C 0.418 0.133 0.300 - - - 85.10 84.80% Satisfactory

JTA Builders 18401Cluster II-Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. along Lanoza Nat'l Arterial Rd.; a) K0069+900-

K0073+042 & b) K0075+400-K0077+20608/10/12 VI 45.859 229 O 0.359 0.295 0.102 0.030 0.060 0.000 84.60 -

JTA BUILDERS/G.M. PAJARILLAGA CONSTRUCTION &

SUPPLY (JV)JV-13-357 Widening of Nueva Vizcaya-Ifugao Road, K0284+250 -

K0284+920 10/29/2014 II 19.500 190 C 0.405 0.134 0.300 - - - 83.90% 83.90% Satisfactory

JTC Construction Co., Inc. 32479 Asphalt Overlay of Calamba-Sta. Cruz-Famy Jct. Rd., K0080+862-K0081+452 08/09/13 IVA 7.472 30 C 0.439 0.133 0.300 - - - 87.20 87.20%

Satisfactory

JTC Cruz Construction Co. Inc. 32479 Preventive Maintenance (MFO-1) Liliw-Majayjay Road, K0103+368 to K0105+405 8/15/2014 IV-A 15.087 53 C 0.411 0.200 0.300 91.10 91.10%

Very SatisfactoryJTC CRUZ CONSTRUCTION CO.,

INC. 32479 Preventive Maintenance (Intermittent Section), 7th Avenue East 11/22/2014 NCR 9.712 90 C 0.433 0.133 0.300 - - - 86.60% 86.60%

Satisfactory

JTC CRUZ CONSTRUCTION CO., INC. 32479Cluster I for the Preventive Maintenance (MFO-1) of

Calamba-Sta. Cruz-Famy Jct. Road, A. K0109+-078 to K0109+000; B. K0109+450 to K0109+989

11/26/2014 IV 9.246 33 C 0.316 0.200 0.300 - - - 81.60% 81.60% Unsatisfactory

JTC Cruz Construction Co., Inc. 32479 Const. of MPB in Panghulo NHS, Brgy. Panghulo 03/15/13 NCR 4.455 60 C 0.443 0.133 0.250 - - - 82.60 82.60% Satisfactory

Jucons Construction & Supply 32051 Rehab./Reconst. along Jct. Taft-Oras-San Policarpio-Arteche Rd., K0960+000-K0960+1040 08/19/13 VIII 5.176 58 C 0.442 0.200 0.300 - - - 94.20 94.20%

Very Satisfactory

Jucons Construction & Supply 32051 Const. of 1-Unit, 1-Storey, 2-CL Rm. 7.0m x 18.0m Sch. Bldg. w/ two seater-CR attached & septic vault at ANSCHI 08/19/13 VIII 1.626 127 C 0.472 0.133 0.300 - - - 90.50 90.50%

Very Satisfactory

Jucons Construction & Supply 32051 Repair/Rehab. of Flood Control Abutment Structures, Maharlika Highway, Km.936+685 03/11/13 VIII 7.710 180 C 0.404 0.162 0.300 - - - 86.60 86.60%

Satisfactory

JUF CONSTRUCTION 17987 Rehabilitation/Reconstruction of Roadslip along Dimakiling J.P. St. 10/23/2014 VIII 18.048 180 C 0.462 0.133 0.300 - - - 89.50% 89.50%

Very Satisfactory

JUF CONSTRUCTION 17987 Rehab./Impv't. of Flood Control along Calbayog - Catarman Road (Phase II) 8/11/2014 VIII 7.783 150 C 0.443 0.200 0.300 94.30 85.66%

Satisfactory

JUF Construction 17987 Rehab./Impv't. of Flood Control along Catarman-Calbayog Rd., Brgy. Oquendo 08/13/13 VIII 7.785 89 O 0.386 0.300 0.000 0.030 0.050 0.033 79.90 -

JUF Construction 17987 Rehab./Repair of Jibatang Bridge along Daang Maharlika (SM) (San Isidro-San Juanico Bridge), Brgy. Lonoy 03/19/13 VIII 27.644 240 C 0.431 0.114 0.300 - - - 84.50 83.75%

Satisfactory

JULDAN BUILDERS 22810 Construction of 3 Classroom at Daang Sarile Integrated School 11/7/2014 III 1.867 75 C 0.430 0.133 0.300 - - - 86.30% 86.30%

Satisfactory

Junjing Construction 32636 Const. of Sch. Bldg., Ozamiz City Sch. of Arts and Trades 08/16/13 X 4.842 137 O 0.399 0.203 0.055 0.030 0.059 0.033 77.90 -

JUNJING CONSTRUCTION & GENERAL MERCHANDISE 32636 Construction of School Building, Ozamis City School of

Arts and Trades 8/14/2014 X 4.842 84 C 0.442 0.200 0.145 78.70 78.14% Unsatisfactory

JUNTAN CONSTRUCTION AND SUPPLIES 26024 Construction of Roads-Municipality of San Luis 12/6/2014 IV 3.994 90 C 0.448 0.133 0.300 - - - 88.10% 88.10% Satisfactory

JUPA CONSTRUCTION 23577

Rehabilitation/Reconstruction of Critical Section along National Roads such as Slips/Emergency/Protection

Works, Secondary Roads, Road Slip along Rawis-Catubig-Las Navas Road under Cluster Roadslip - 2014-01

1.)K0803+000-k0804+000 (with exceptions), Catubig-Las Navas Section

10/20/2014 VIII 19.406 170 C 0.443 0.133 0.300 - - - 87.60% 87.60% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page144

Page 145: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

JUPA CONSTRUCTION 23577

Road Widening of National Road along Catarman (Boundary) Rawis Road Section KO771+000 - KO773+000 with exception Preventive Maintenance along Catarman -

Laoang Road - San Roque Pambujan Section, KO773+000 - KO774+000 with exception

8/12/2014 VIII 6.279 150 C 0.390 0.133 0.300 82.30 82.30% Satisfactory

Jupa Construction 23577 Conc. of Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd., Magtaon-Mapanas Sect., K0823+(-172)-K0823+730 08/06/13 VIII 18.826 176 C 0.438 0.124 0.300 - - - 86.20 86.20%

Satisfactory

Jupa Construction 23577 Rd. Widening of Nat'l Rd. along Catarman (Boundary) Rawis Rd. Sect., K0771+000-K0773+000 w/ exception 08/06/13 VIII 6.279 150 O 0.366 0.240 0.150 0.030 0.055 0.033 87.40 -

Jupa Construction 23577Conc. of Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd.,

Nipa-Maragano Sect., Km.809+000-Km.810+000 w/ exception

08/17/12 VIII 12.252 105 C 0.452 0.133 0.300 - - - 88.50 84.00% Satisfactory

JV Lagon Construction Corporation 11561 Sarangani-Davao Del Sur Coastal Road, Sapu Masla-

Kapatan Section Malapatan-Glan 09/16/09 XII 7.010 90 O 0.350 0.000 0.000 0.010 0.015 0.000 37.50 -

JV Lagon Construction Corporation 11561 Rehab./Reconst. of Damaged Roads Dulawan Marbel

(Tacurong-New Carmen Section) 03/13/09 XII 19.022 435 O 0.365 0.300 0.099 0.030 0.035 0.050 87.90 -

JV Loreto Const. & Development Corp. / Viguz Const. Corp. (JV) JV-09-091 Rehab./Reconst. of Daang Maharlika, Dulag-McArthur Rd.

Sect. 06/10/10 VIII 47.000 192 O 0.373 0.250 0.150 0.030 0.047 0.050 90.00 -

JV Loreto Construction & Development Corp. 13120 Rehab./Reconst. Along Daang Maharlika, K0995+000-

K0997+000 w/ exceptions 03/27/12 VIII 11.937 160 O 0.312 0.232 0.150 0.030 0.030 0.050 80.40 -

JWD Construction 22291 Construction of RMMC-RM5 Pumping Station 04/17/15 NIA 16.518 353 C 0.445 0.160 0.300 - - - - 90.51% Very Satisfactory

JYM Construction & Supply 34595 Ibong Sapa Flood Control 07/30/13 V 4.845 64 C 0.409 0.200 0.300 - - - 90.90 87.24% Satisfactory

JYM Construction & Supply 34595 Ibong Sapa Flood Control 03/17/13 V 4.845 60 O 0.342 0.300 0.100 0.030 0.043 0.033 84.80 -

Kajima Corporation FC-04-023 Const. of Segment 3B-2, Subway (Tunnel) Section at Cebu City, MCDP III, Cebu South Coastal Road 06/06/09 MCDP 1,367.069 1,247 O 0.357 0.300 0.150 0.030 0.070 0.050 95.70 -

Kajima Corporation FC-04-023 Const. of Cebu South Coastal Rd., Project Segment 3B-2 (Tunnel Sect.) 06/19/10 MCDP 1,625.321 1,367 O 0.299 0.300 0.000 0.030 0.070 0.050 74.90 -

Kamagong Builders and Developers Corporation 1720

Const./Rehab of Drainage Protection Works along National Roads and Bridges/Secondary Roads/Const?Rehab of

Drainage System along Kawit-Noveleta Diversion Road, Cavite 1st LD

8/5/2014 IV-A 46.550 200 OG 0.362 0.240 0.150 0.015 0.038 0.033 83.80 -

Kane Construction, Inc. 2888 Restoration of Rd./Damaged Drainage Facilities along Gov. Pack Rd. (POPSTIRP Proj.) 03/24/13 CAR 9.673 409 C 0.464 0.200 0.000 - - - 66.40 70.36%

Poor

Kane Construction, Inc. 2888 Restoration of Collapsed Retaining Wall along Kennon R.d, Km.244+00 -Km.244+186 (POPSTIRP Proj.) 03/24/13 CAR 5.880 409 C 0.465 0.200 0.000 - - - 66.50 67.22%

Poor

Kane Construction, Inc. 2888Restoration of Overhang Revetment Wall & Collapsed

Retaining Wall along Kennon Rd., Km.241+000-Km.241+093.5 w/ exception

03/24/13 CAR 5.811 409 C 0.320 0.200 0.000 - - - 52.00 61.66% Poor

Karpa Builders and Trading 33003 Const. of MPB, Phase II, BPSU (Main Campus) 03/14/13 III 2.904 80 C 0.477 0.133 0.300 - - - 91.00 91.00% Very Satisfactory

Kasanga Construction and Supplies (Formerly: Kasanga

Construction)17024 Repair/Maint. of San Isidro Drainage System 03/18/13 IVB 1.500 73 C 0.467 0.133 0.300 - - - 90.00 90.00%

Very Satisfactory

Kasanga Construction and Supplies (Formerly: Kasanga

Construction)17024 Const. of San Antonio Drainage System along Calapan

South Rd. 03/19/13 IVB 2.637 150 C 0.463 0.133 0.300 - - - 89.60 89.60% Very Satisfactory

Kasanga Construction and Supplies (Formerly: Kasanga

Construction)17024 Repair/Maint. of Salong Drainage System 03/19/13 IVB 1.426 49 C 0.455 0.133 0.300 - - - 88.80 88.80%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page145

Page 146: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Kasangga Construction and Supplies (Formerly: Kasangga

Construction)17024 Repair/Maint. of Minas River Control CSR Jct. Minas

Km.38+750-Km.38+770.80 (Macatoc Side) 08/06/12 IVB 1.630 65 C 0.400 0.200 0.300 - - - 90.00 82.02% Satisfactory

KCS Construction & Supply 19641 Conc. of Alianza Road 06/08/10 V 4.719 90 O 0.304 0.300 0.150 0.030 0.035 0.033 85.20 -

KCS Construction & Supply 19641 Impvt. of Lagonoy-Presentacion Road, Km. 499+491-Km.528+00 with exceptions 09/09/09 V 14.142 231 O 0.346 0.240 0.150 0.030 0.042 0.050 85.80 -

KCS Construction & Supply 19641 Const. of Hospital Bldg., Bicol Medical Center 08/13/12 V 2.598 147 C 0.479 0.133 0.300 - - - 91.20 87.14% Satisfactory

Kejamarenik Construction & Construction Supplies 33742 Construction of Multi-Purpose Building at Brgy. 7,

Mamburao 8/14/2014 IV-B 9.688 210 C 0.429 0.200 0.014 64.30 75.22% Unsatisfactory

Kejamarenik Construction & Construction Supplies 33742 Const. of MPB at Brgy. 7 07/29/13 IVB 9.699 210 O 0.349 0.300 0.049 0.030 0.038 0.033 79.90 -

KENBE CONSTRUCTION & SUPPLY 34290 Rehab./Reconstruction/Upgrading/Concreting of Jct. New

Sagay - Old Sagay Road, K0088+000 - K0088+320 10/21/2014 VI 5.968 78 C 0.398 0.133 0.300 - - - 83.10% 83.10% Satisfactory

Kenbe Construction & Supply 34290 Const./Rehab. of Drainage System Bliss Site 08/17/12 VI 0.879 95 C 0.445 0.133 0.300 - - - 87.80 85.64% Satisfactory

Kenwood Construction Enterprises 22186 Const. of 1-Storey 2-CL Sch. Bldg. at Jose Maram Paningbatan Sr. E/S 08/03/13 I 1.167 90 C 0.482 0.133 0.300 - - - 91.50 91.50%

Very Satisfactory

Kenwood Construction Enterprises 22186

Const. of Lateral Drainage along Urdaneta Jct.-Dagupan Rd., Km.200+727-Km.201+110, Sta. Barbara Sect. w/

exception & Km.205+82 -Km.206+161, Calasiao Sect. w/ exception

03/14/13 I 8.031 120 C 0.484 0.133 0.300 - - - 91.70 92.54% Very Satisfactory

Kenwood Construction Enterprises 22186 Impvt./Rehab. of DPWH-Sub DEO 05/31/09 I 2.892 180 O 0.357 0.264 0.150 0.030 0.045 0.033 87.90 -

Kenwood Construction Enterprises 22186 Widening/Concreting of McArthur Highway (MNR) including Traffic Management 05/19/09 I 10.060 138 O 0.350 0.201 0.000 0.030 0.050 0.033 66.40 -

Kenwood Construction Enterprises 22186 Widening of Camiling-Wawa-Bayambang-Malasiqui-Sta. Barbara Rd., Km. 179+480-Km. 180+500 (Bayambang Sect.) 11/28/12 I 15.070 265 C 0.452 0.200 0.300 - - - 95.20 93.70%

Very Satisfactory

Kevin Yoshi Builders (Formerly: Con Builders) 32216 Const. of Flood Control/Drainage along Digos-Makar Rd.

(Apopong Sect.), Brgy. Apopong 08/23/13 XII 6.705 128 C 0.452 0.133 0.300 - - - 88.50 88.50% Satisfactory

KGD BUILDERS 21960 Repair/Imprv't. of Flood Control and Drainage Structurein Brgy. Tinagacan 8/16/2014 XII 7.656 120 C 0.467 0.135 0.300 90.20 87.20%

Satisfactory

KGD Builders 21960 Repair & Impv't. of Flood Control & Drainage Structure in Brgy. Tinagacan 08/22/13 XII 7.656 120 O 0.376 0.240 0.150 0.020 0.033 0.033 85.20 -

Khan Kon Chi Construction 33442Emergency Repair of Damaged Open Storage/Back-up

Area Caused by 7.2 Magnitude Earthquake on October 15, 2013

04/10/15 PPA 19.700 194 C 0.452 0.200 0.300 - - - - 95.20% Very Satisfactory

Kilusang Magkaibigan M.P. Cooperative (KMMPC) 31666 Widening of Surigao-Davao Coastal Rd., Maco Sect. 08/14/13 XI 13.767 122 C 0.416 0.200 0.300 - - - 91.60 91.60%

Very SatisfactoryKilusang Magkaibigan M.P.

Cooperative (KMMPC) 31666 Rehab./Reconst./Upgrading of Sumulong Highway 08/15/13 IVA 22.522 223 O 0.333 0.240 0.000 0.030 0.040 0.000 64.30 -

Kilusang Magkaibigan M.P. Cooperative (KMMPC) 31666 Rehab./Reconst./Upgrading of Sumulong Highway 03/22/13 IVA 22.522 179 O 0.354 0.300 0.000 0.030 0.050 0.017 75.10 -

Kilusang Magkaibigan Multi-Purpose Cooperative (KMMPC) 31666 Rd. Upgrading of Cateel-Compostela Rd. (Davao Oriental

Side) Km.1559+607-Km.1561+680 (w/ exception) 08/17/12 XI 28.108 180 O 0.372 0.240 0.128 0.030 0.047 0.033 85.00 -

Kilusang Magkaibigan Multi-Purpose Cooperative (KMMPC) 31666 Rd. Upgrading of Compostela-Cateel Rd. (Davao Oriental

Side) Km.1560+000-Km.1561+000 08/17/12 XI 18.116 161 C 0.396 0.134 0.300 - - - 83.00 83.84% Satisfactory

Kilusang Magkaibigan Multi-Purpose Cooperative (KMMPC) 31666 Const. of Siburon Sewall 08/05/12 XIII 2.751 120 C 0.442 0.159 0.300 - - - 90.10 87.76%

Satisfactory

Kim Harold Trading, Manufacturing & Construction 28019 Repair/Maint. of Puerto Princesa-Malvar Rd., Drainage

Canal Km.02+189-Km.02+434 Malvar Rd. 08/15/13 IVB 2.766 150 C 0.480 0.200 0.000 - - - 68.00 67.64% Poor

Kim Harold Trading, Manufacturing & Construction 28019 Repair/Maint. of Puerto Princesa-Malvar Rd., Drainage

Canal, Km.02+189-Km.02+434, Malvar Rd. 03/16/13 IVB 2.766 120 O 0.321 0.240 0.000 0.030 0.050 0.033 67.40 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page146

Page 147: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Kim Harold Trading, Manufacturing & Construction 28019 Const. of Barutuan Bridge III, Flood Control Structures

along El Nido-Jct. New Ibajay Rd., Km. 296+504 08/04/12 IVB 8.380 133 O 0.338 0.133 0.300 - - - 77.10 81.72% Unsatisfactory

Kim Harold Trading, Manufacturing & Construction 28019 Repair/Maint. of DPWH Building El Nido Resthouse (Maint

Sect.), Villa Libertad 03/12/13 IVB 0.388 48 C 0.469 0.167 0.300 - - - 93.60 93.60% Very Satisfactory

Kim-Harold Trading, Manufacturing & Construction 28019

Construction of Drainage/Slope Protection Works along Puerto Princesa North Road with Road Widening Roxas -

Taytay Road Section, K0174+810 - K0174+960; K0161+680 - K0161+730 (Intermittent)

8/6/2014 IV-B 11.103 121 OG 0.370 0.229 0.148 0.022 0.052 0.017 83.80 -

KIM‐HAROLD TRADING, MANUFACTURING & CONSTRUCTION  28019

Construction Drainage/Slope Protection Works along Puerto Princesa North Road with Road Widening Roxas -

Taytay Road Section, K174+810-K174+960;K0161+680-K0161+730 (Intermittent)

11/21/2014 IV 11.512 191 C 0.416 0.133 0.300 - - - 84.90% 84.24% Satisfactory

KING'S BUILDERS & DEVELOPMENT CORP. 29199 Construction of Bucayao River Control 11/26/2014 IV 18.116 140 C 0.420 0.200 0.300 - - - 92.00% 92.00%

Very SatisfactoryKING'S BUILDERS & DEVELOPMENT 

CORP. 29199 Construction of Longos-River Control along NCR 11/28/2014 IV 5.863 79 C 0.494 0.133 0.300 - - - 92.70% 92.70% Very Satisfactory

King's Builders & Development Corp. 29199 Conc. of Brgy. San Aquilino-Roma FMR 08/08/12 IVB 4.752 71 C 0.352 0.143 0.300 - - - 79.50 83.88%

Satisfactory

King's Builders & Development Corp./Alberto Uy Construction &

Development JVJV-11-150 Impvt./Conc. of Calapan South Rd. Salcedo Sect. 08/08/12 IVB 22.979 161 C 0.399 0.133 0.300 - - - 83.20 82.60%

Satisfactory

King's Builders & Development Corporation 29199 Construction/Rehabilitation of Villa Pag-asa River Control,

Bansud, Oriental Mindoro 8/12/2014 IV-B 9.240 104 C 0.419 0.133 0.300 85.20 85.20% Satisfactory

King's Builders & Development Corporation 29199

Widening (Paving of Shoulder) - Seal Widening of Calapan South Road K0008+537.50 - K0008+860 along Bayanan I

E/S Section8/11/2014 IV-B 3.675 79 C 0.405 0.133 0.300 83.80 83.80%

Satisfactory

King's Builders & Development Corporation 29199

Repair/Rehabilitation/Improvement of Calapan South Road, Masipit Section (Left Side) Km. 5+415 - Km. 7+250 with

exceptions8/11/2014 IV-B 9.900 140 C 0.415 0.133 0.300 84.80 84.80%

Satisfactory

King's Builders and Development Corporation 29199 Bansud Port Development Project 08/13/14 DOTC 3.816 90 C 0.430 0.200 0.300 - - - 92.95 92.95%

Very Satisfactory

Kirskat Venture 13361 Prev. Maint. (Int. Sect.) Nat'l Arterial Rd. (Iloilo East Coast-Capiz Rd., Brgy. Sta. Fe, K0.169+279-K0.170+323 08/18/13 VI 19.980 140 C 0.451 0.133 0.300 - - - 88.40 88.40%

Satisfactory

Kirskat Venture 32042Conc. Of Iloilo East Coast-Capiz Road, President Roxas-Pilar-Balasan Road Sect. (Sta.154+421.20-Sta.163+660 w/

exception)03/26/12 VI 61.792 230 C 0.372 0.200 0.300 - - - 87.20 87.14%

Satisfactory

Kirskat Venture 32042 Road Upgrading (Gravel to Paved) San Rafael-Dumarao Rd., Km.075+018-K074+473.93 03/22/12 VI 11.988 150 C 0.381 0.200 0.300 - - - 88.10 85.22%

SatisfactoryKirskat Venture 32042 Maayon CIP 02/07/12 NIA 24.335 463 O 0.351 0.246 0.150 0.024 0.051 0.050 87.20 -

KJC Construction & Supply 33401 Const. of Rehabilitation of Aganan River Irrigation System (Irrigation & Flood Control) 06/04/10 NIA 4.469 120 O 0.347 0.300 0.150 0.020 0.032 0.050 89.89 -

KJC Construction and Suppy 6995 CONSTRUCTION OF JOROG PIP 04/05/14 NIA 1.809 662 O 0.367 0.258 0.150 0.024 0.047 0.033 87.90 -

KLDS Trading & Construction 28091 Prev. Maint. (MFO-1) (Int. Sect.), Asphalt Overlay along Crisanto M. Delos Reyes Ave., K0054+(-306)-K0054+267 08/13/13 IVA 6.120 50 C 0.467 0.133 0.300 - - - 90.00 90.00%

Very Satisfactory

KMD Builders and Construction Supply 33791 Repair/Maintenance along Cordon-Aurora Bdry. Road,

K0330+000 to K0335+000 8/13/2014 II 2.028 50 C 0.463 0.133 0.300 89.60 89.60% Very Satisfactory

KRB CONSTRUCTION 34197 Expansion, Banna (Espiritu) RHU 10/22/2014 I 2.473 130 C 0.471 0.167 0.300 - - - 93.80% 93.80% Very Satisfactory

Kuataco Construction Building and General Contractor 11224 Rehab./Reconst. of Damaged Paved Nat'l Rd. Abra-Ilocos

Sur Rd., Km.398+000-Km.405+000 (I.S.) 08/14/12 CAR 22.323 298 C 0.338 0.151 0.300 - - - 78.90 83.64% Satisfactory

Kuatako Construction Building and General Contractor 11224 Rd. Upgrading (Gravel to Paved) Abra-Cervantes Rd.,

K0449+415-K0456+346, Pob. Sallapadan 08/14/13 CAR 41.273 179 O 0.329 0.300 0.000 0.030 0.050 0.033 74.20 -

KUMI CONSTRUCTION 94969 Improvement/Riprapping along Duyan-Duyan Creek (Mirriam College of Lagarian Creek) 8/15/2014 NCR 4.652 90 C 0.478 0.133 0.300 91.10 91.10%

Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page147

Page 148: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Kumi Construction 34969 Impvt./Riprapping along Duyan-Duyan Creek (Mirriam College-Lagarian Creek) 08/09/13 NCR 4.652 90 C 0.457 0.200 0.300 - - - 95.70 83.64%

Satisfactory

Kumi Construction 34969 Impv't./Riprapping along Duyan-Duyan Creek (Mirriam College-Lagarian Creek) 03/19/13 NCR 4.652 90 O 0.240 0.300 0.150 0.023 0.018 0.025 75.60 -

KUNTEL CONSTRUCTION 10234

Rehab./Reconst./Upgrading of Damaged National Roads (Intermittent Sections) Bacolod South Road (kabankalan -

Hinoba-an Section) A: Ko166+944 - KO167+932 & B: KO169+000 - KO0170+012 Brgy. Maricalum

8/9/2014 VI 36.631 253 C 0.425 0.200 0.300 92.50 85.42% Satisfactory

Kuntel Construction 10234

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. (Int. Sect.), Bacolod South Rd. (Kabankalan-Hinoba-an

Sect.) A.K0166+944-K0167+932 & B.K0169+000-K0170+012, Brgy. Maricalum

08/09/13 VI 35.320 179 O 0.346 0.240 0.118 0.030 0.040 0.033 80.70 -

KV Construction & Supply 17509 Const./Widening/Upgrading/Rehab. of Access Rds. to Major Airport, Daet-Airport Rd. 03/23/13 V 46.060 180 O 0.292 0.290 0.150 0.024 0.035 0.033 82.40 -

KV Construction and Supply 17509 Widening of Access Road Leading Daet-Airport Road Camarines Norte 2nd Legislative District 8/5/2014 V 46.357 210 OG 0.310 0.294 0.150 0.020 0.033 0.050 85.70 -

KV Construction and Supply 17509 Constr./Widening/Upgrading/Rehab. of Access Rd. to Daet Airport 08/16/12 V 27.622 270 C 0.426 0.133 0.300 - - - 85.90 87.34%

Satisfactory

KV Construction and Supply 17509 Road Upgrading (Gravel to Concrete) Km.313+501-Km.314+869 & Km.314+992-Km.314+1360 08/16/12 V 44.617 330 C 0.420 0.133 0.300 - - - 85.30 85.90%

Satisfactory

KVC CONSTRUCTION 28959

Rehab./Reconst./Upgrading of Damaged Paved National Roads including Draiange based on Pavement

Management System/ Highway Development and Management-4 (HDM-4) (Intermittent Sections) on National

Secondary and National Arterial Roads (Package XVII-2013)

11/20/2014 CAR 11.610 222 O 0.377 0.243 0.000 0.030 0.050 0.050 75.00% 75.00% Poor

KVC CONSTRUCTION 28959 Road Upgrading of Dantay - Sagada Road, KO390+520 - KO390+840 11/22/2014 CAR 7.737 168 O 0.369 0.240 0.010 0.030 0.050 0.033 73.20% 73.20%

Poor

KVC Construction 28959 Rehab. of Moatong Bridge, K0301+743 07/30/13 CAR 7.866 150 C 0.467 0.133 0.000 - - - 60.00 74.64% Poor

KVC Construction 28959Road Upgrading/Rehab./Reconst. (Asphalt to Concrete)

Acop-Kapangan-Kibuagan-Bakun Road, K0269+390-K0271+000 v.s.

08/16/11 CAR 15.100 98 O 0.400 0.241 0.056 0.030 0.037 0.017 78.10 -

KVC Construction 28959 Rehab. of Moatong Bridge, K0301+743 03/13/13 CAR 7.866 120 O 0.291 0.300 0.150 0.023 0.047 0.033 84.40 -

KVC CONSTRUCTION / 3K ROCK ENGINEERING (JV) JV-13-342

Road Upgrading (Gravel to Concrete) of Asin - Nangalisan San Pascual Road, K0270+594-K0272+220 (i.s.) and

K0275+5311-K0275+7178 (i.s.)11/28/2014 CAR 97.500 274 O 0.370 0.238 0.139 0.030 0.055 0.050 88.20% 88.20%

Satisfactory

KVC Construction / Aguinsod General Construction (JV) JV-11-218 Rd. Upgrading (Gravel to Conc.) Gurel-Bokod-Kabayan-

Buguias-Abatan Rd. (K0314+000-K0315+500) 07/31/12 CAR 21.871 210 O 0.321 0.300 0.150 0.008 0.028 0.033 84.00 -

KVC Construction / Agunsod General Construction (JV) JV-11-218 Rd. Upgrading (Gravel to Concrete) Gurel-Bokod-Kabayan-

Buguias-Abatan Rd. (K0314+000-K0315+500) 11/20/12 CAR 23.086 210 C 0.416 0.197 0.300 - - - 91.30 86.92% Satisfactory

KVC Construction / R.S. Sepian Construction and Trucking (JV) JV-12-072 Const. of Amburayan Flood Control (Naguey Sect.) 03/14/13 CAR 8.431 120 C 0.461 0.133 0.300 - - - 89.40 89.40%

Very Satisfactory

KVCC Construction 27179 Const./Rehab./Impvt. of DPWH Biliran DEO 08/26/10 VIII 2.882 120 O 0.361 0.240 0.150 0.030 0.042 0.033 85.60 -

Kyro Builders 19567 NIA- Participatory Irrigation Development Project 09/30/15 NIA 70.128 800 O 0.359 0.300 0.004 0.024 0.060 0.050 79.70 -

Kyro Builders UMAYAM RIVER IRRIGATION PROJECT 09/12/15 NIA 173.037 848 O 0.290 0.240 0.140 0.015 0.060 0.050 79.48 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page148

Page 149: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

KYRO BUILDERS

Package X-B: Construction of Sub-laterals "N-5D" (Sta. 7+800 - Sta. 12+855), "N-5C" (Sta. 0+000-5+765), and "N-5D" (Sta. 0+000-2+815) including related structures and

supply, delivery and installation of steel gates

02/07/15 NIA 102.818 180 O 0.316 0.283 0.150 0.030 0.023 0.050 85.22 -

Kyro Builders 19567 Rehab./Reconst./Upgrading of Damaged Paved National road, Pias-Currimao-Balacad Road, Currimao-Paoay 08/20/10 I 18.977 180 O 0.374 0.240 0.150 0.030 0.048 0.033 87.50 -

Kyro Builders 19567 Conc. of Talugtug-Muñoz Rd. Sta.2+061 to Sta.4+982.20 03/19/12 III 16.965 120 C 0.443 0.133 0.300 - - - 87.60 90.48% Very Satisfactory

Kyro Builders 19567

Impvt./Widening of Bacolod-Murcia-Don Salvador-Benedicto San Carlos Rd., Don Salvador Benedicto-San

Carlos City Sect. Sta.37+025-Sta.37+540; Sta.45+000-Sta.48+060 w/ exception, Sta.83+916.60-Sta.85+796.60

11/27/12 VI 76.871 417 C 0.423 0.133 0.247 - - - 80.30 84.86% Satisfactory

Kyro Builders / Rachel Faye Const. (JV) JV-10-039 Rehab. Of Various Slope Protection along Baguio Bontoc

Rd., (Halsema Highway) Km.265+000-Km.315+000 (I.S.) 08/16/11 CAR 28.948 240 O 0.310 0.300 0.122 0.030 0.047 0.033 84.20 -

L M D Construction 9410 Construction of Multi-Purpose Building at Dumalinao Pilot School 06/20/09 IX 4.595 180 O 0.380 0.240 0.150 0.020 0.042 0.050 88.20 -

L. C Ting Construction 23666 Rehab. of Gamut Steel Bridge along Surigao-Davao Coastal Road (Alternate Road) 06/09/10 XIII 9.617 60 O 0.352 0.300 0.109 0.030 0.040 0.033 86.40 -

L. C Ting Construction 23666 Rehab. of Paypay Twin Bridge 06/01/10 XIII 19.266 270 O 0.400 0.180 0.150 0.030 0.045 0.033 83.80 -

L. C Ting Construction 23666Rehab./Reconst. of Damaged Paved National Road

(Asphalt Overlay) Daang Maharlika Road (Surigao-Agusan Road)

06/07/10 XIII 14.077 90 O 0.355 0.240 0.150 0.023 0.035 0.033 83.60 -

L. C. TING CONSTRUCTION 23666Construction of Flood Control Structure/Drainage along SDCR, Surigao del Sur 2nd LD, Wakat-Tagbina, Barobo,

K1411+520 - K1412+0008/9/2014 XIII 11.129 158 OG 0.320 0.225 0.119 0.023 0.042 0.050 77.90 -

L. C. TING CONSTRUCTION 23666Road Slip Protection along Surigao-Davao Coastal Road, Lingig, Brgy. Mahayhay, Lingig, Surigao del Sur 2nd LD,

K1477+553.10 - K1477+606.108/10/2014 XIII 19.826 190 C 0.390 0.124 0.300 81.40 85.18%

Satisfactory

L. C. TING CONSTRUCTION 23666 Rehabilitation/Retrofitting of Existing Permanent Bridges, Bihawan Bridge along SDCR, Surigao del Sur 1st LD 8/11/2014 XIII 14.456 185 OG 0.334 0.200 0.150 0.030 0.037 0.050 80.10 -

L. C. TING CONSTRUCTION 23666Rehab./Reconst./Upgrading of Damaged Paved Road along

NRJ San Francisco - Bahi - Barobo Rd., Km. 1313+445 - Km. 1351+600

8/8/2014 XIII 23.305 171 OG 0.328 0.230 0.000 0.023 0.037 0.033 65.10 -

L. C. TING CONSTRUCTION 23666 Rehabilitation/Retrofitting of Lucena Bridge along NRJ - Bahbah - Talacogon Road 8/6/2014 XIII 15.321 217 OG 0.398 0.195 0.028 0.023 0.030 0.017 69.10 -

L. G. Lasacar Construction 11960 Lawigan Port Development Project 11/06/13 DOTC 9.235 90 C 0.416 0.200 0.300 - - - 91.60 91.60% Very Satisfactory

L. N. R. Construction 14148 Construction/Rehabilitation of Sabang Fishport 02/05/15 DOTC 39.370 300 O 0.344 0.300 0.150 0.030 0.050 0.032 90.55 -

L. N. R. Construction 14148 Repair of Port Facilities for Damages caused by the Typhoon Yolanda 02/04/15 PPA 25.658 240 C 0.497 0.200 0.300 - - - - 98.86%

Outstanding

L. N. R. CONSTRUCTION 14148 New Construction of Vinsons Port 10/16/14 DOTC 40.978 240 C 0.479 0.200 0.300 - - - - 93.92% Very Satisfactory

L. N. R. CONSTRUCTION 14148 Repair of Port Facilities for damages caused by typhoon Yolanda 08/22/14 PPA 23.339 180 O 0.397 0.300 0.150 0.030 0.058 0.050 98.49 -

L. N. R. CONSTRUCTION 14148 Pilar Port Development Project 07/24/14 DOTC 12.182 120 C 0.461 0.200 0.300 - - - 96.10 96.50% Outstanding

L. N. R. CONSTRUCTION 14148 Sabang Port Development Project 09/05/14 DOTC 39.370 300 O 0.372 0.300 0.150 0.015 0.050 0.050 93.70 -

L. N. R. Construction 14148 New Construction of Vinzons Port 06/25/14 DOTC 40.978 240 O 0.356 0.300 0.150 0.030 0.043 0.033 91.27 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page149

Page 150: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

L. N. R. CONSTRUCTION 14148 Corcuera Port Development Harbor 02/26/14 DOTC 24.050 180 C 0.451 0.200 0.300 - - - 95.10 95.10% Very Satisfactory

L. N. R. CONSTRUCTION 14148 Kaputian Multi-Purpose Port Development Project 03/26/14 DOTC 2.943 90 C 0.437 0.200 0.300 - - - 93.70 93.70% Very Satisfactory

L. R. Tiqui Builders, Inc. 13810 Balagtas Port Development Project 10/31/13 DOTC 2.940 90 C 0.404 0.200 0.300 - - - 90.40 90.40% Very Satisfactory

L.A Arizola Construction & Supply 31060 Conc. of Kidapawan Magnet-Pangaon-an Road inc. Marbel Bridge and Approaches 03/09/09 XII 9.485 90 O 0.328 0.240 0.150 0.030 0.035 0.033 81.60 -

L.A Digao Construction 15371 Const./Impvt./Renovation of Public Market 08/29/10 XIII 3.775 120 O 0.356 0.240 0.150 0.030 0.035 0.033 84.40 -L.A. Arizola Construction and

Supply 31060 Const. of Seawall, Sitio Sta. Cruz & San Antonio (Agdao Beach) Brgy. L. Garcia 11/29/12 XI 1.210 90 C 0.481 0.135 0.300 - - - 91.60 84.10%

SatisfactoryL.A. Arizola Construction and

Supply 31060 Const. of Sewall, Sitio Sta. Cruz & San Antonio (Agdao Beach) Brgy. L. Garcia 08/21/12 XI 1.210 90 O 0.294 0.209 0.150 0.030 0.058 0.050 79.10 -

L.A. Clamor Construction 26413 Conc. of Quezon Eco-Tourism Rd. inc. RROW, Talaan Sect. 11/29/12 IVA 13.909 205 C 0.430 0.139 0.300 - - - 86.90 86.66% Satisfactory

L.A. Clamor Construction 26413 Conc. of Quezon Eco-Tourism Road inc. RROW, Talaan Sect. 07/31/12 IVA 13.909 210 O 0.364 0.238 0.150 0.030 0.050 0.033 86.50 -

L.A. Clamor Construction 26413 Construction of Diversion Works & Canal Structures of Ilosong CIP 09/07/13 NIA 6.621 150 O 0.343 0.249 0.150 0.018 0.040 0.050 84.97 -

L.A. PROFUGO CONST. & SUPPLY 33609

Construction and Maintenance of Bridges along National Roads-Major Repair/Maintenance of Existing Permanent

Bridges, Arterial Road Quezon (First District) 1. Amao Br. Along Daang Maharlika (LZ)

11/26/2014 IV 1.852 30 C 0.464 0.133 0.300 - - - 89.70% 89.70% Very Satisfactory

L.B. LEONCIO TRADING & CONSTRUCTION 31587 CP-02-14 Road Upgrading ( Gravel to Paved) of Irawan-

Tagburos Road 11/24/2014 IV 12.170 139 C 0.416 0.133 0.300 - - - 84.90% 77.82% Unsatisfactory

L.B. Leoncio Trading & Construction 31587

Road Upgrading (Gravel to Paved) of Irawan - Tagburos Road, K0012+1046 - K0013+485 and K0016+754.80 -

K0016+8018/8/2014 IV-B 11.244 109 OG 0.373 0.219 0.046 0.030 0.030 0.033 73.10 -

L.B. Leoncio Trading & Construction 31587 Construction of 2 Storey 6 CL, San Jose National High

School 8/8/2014 IV-B 6.367 260 C 0.470 0.133 0.300 90.30 87.43% Satisfactory

L.B. Leoncio Trading & Construction 31587 Const. of 2 Storey 6 CL San Jose NHS 08/16/13 IVB 6.286 260 O 0.381 0.228 0.150 0.020 0.033 0.050 86.20 -

L.C Construction 7024 Improvement of Access Road, Pagadian City Airport (Lumbia Sect.) 06/05/09 IX 15.346 195 O 0.375 0.238 0.150 0.020 0.042 0.050 87.50 -

L.C Construction 7024 Rehab. of Cagayan de Oro Port Road 03/03/09 X 0.490 14 O 0.275 0.240 0.042 0.020 0.027 0.050 65.40 -L.C Ting Construction 23666 Conc. of Butuan City-Pianing-Tandag Rd. 09/14/09 XIII 19.195 255 O 0.282 0.281 0.150 0.030 0.060 0.033 83.60 -

L.C Ting Construction / Davao L.A. Parts & Hardware Corporation

Joint VentureJV-07-102 Impvt./Conc. of Surigao Sur-Davao Oriental Coastal Road

(Manay-Boston) Manay Section 11/25/08 XI 47.225 166 O 0.272 0.298 0.100 0.030 0.055 0.067 82.20 -

L.C. Construction 7024

Rd. Upgrading (Gravel to Concrete) Jct. Tubod-Lakewood Rd., K1710+2000-K1710+3000 realigned to Rd. Upgrading

to Paved Rd. Standard, Jct. Tubod-Lakewood Rd., K1710+990-K1711+735

11/21/12 IX 21.923 182 O 0.364 0.225 0.000 0.030 0.043 0.033 69.50 -

L.C. Construction 7024

Road Upgrading (Gravel to Concrete), Jct. Tubod-Lakewwod Rd., K1710+2000-K1710+3000 Re-aligned to Rd.

Upgrading to Paved Rd., Jct. Tubod-Lakewood Rd., K1710+990-K1711+735

08/16/12 IX 21.923 182 O 0.392 0.240 0.122 0.030 0.038 0.033 85.50 -

L.C. Talon Construction 19644 Const./Rehab. of Community Center 08/09/12 II 4.682 210 C 0.473 0.200 0.300 - - - 97.30 82.81% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page150

Page 151: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

L.C. TING CONSTRUCTION 23666RehabilItation/Reconstruction of Road Slip along Butuan-Cagayan de Oro-Iligan Road (Agusan-Misamis Oriental),

K1266+000 - K1266+044, K1266+110 - K1266+125)10/21/2014 XIII 13.597 194 C 0.356 0.197 0.300 - - - 85.30% 85.30%

Satisfactory

L.C. TING CONSTRUCTION 23666 Replacement of Sabangahan Bridge along Misamis, Oriental - Bukidnon - Agusan Road 8/9/2014 X 12.970 214 OG 0.397 0.300 0.025 0.023 0.041 0.000 78.60 -

L.C. Ting Construction 23666 Rehab./Strengthening of Sumo-Sumo Bridge along Surigao-Davao Coastal Rd. 08/15/13 XIII 13.801 154 C 0.413 0.133 0.300 - - - 84.60 84.60%

Satisfactory

L.C. Ting Construction 23666 Road Slip/Protection along Surigao-Davao Coastal Rd., Mahayahay, K1477+533.10-K1477+606.10 08/16/13 XIII 19.826 190 O 0.372 0.240 0.150 0.030 0.035 0.050 87.70 -

L.C. Ting Construction 23666 Replacement of Bridge along Nat'l Rds. Catugpas III along Surigao-Davao Coastal Rd. 03/16/13 XIII 11.186 139 O 0.383 0.232 0.150 0.030 0.025 0.033 85.30 -

L.C. Ting Construction 23666 Reconst. of Critical Sect. along Nat'l Rds. Payasan-Los Arcos Rd. (Rd. Slip) Km.1389+820-Km.1389+920 03/21/13 XIII 14.312 180 C 0.471 0.133 0.100 - - - 70.40 78.56%

Unsatisfactory

L.C. Ting Construction 23666Widening/Conc. of Add'l Lane both directions along Butuan City-Cagayan de Oro-Iligan Road, Bancasi-

Dumalagan Sect.03/31/12 XIII 21.790 239 C 0.391 0.200 0.300 - - - 89.10 87.36%

Satisfactory

L.C. Ting Construction 23666Reconst. of Critical Sect. along Nat'l Rd. such as

Slips/Emergencies/Protection Works (Rd. Slip at San Agustin Salvacion Sect. along SDCR)

03/25/12 XIII 17.992 210 C 0.484 0.133 0.300 - - - 91.70 87.08% Satisfactory

L.C. Ting Construction 23666 Reconst. of Critical Road Slip Sect. along NRJ-Bahbah-Talacogon Rd. at Mapaga-Mabagoy Sect. 03/28/12 XIII 18.899 285 C 0.393 0.190 0.300 - - - 88.30 87.04%

Satisfactory

L.C. Ting Construction 23666 Reconst. of Critical Road Slip along Daang Maharlika (Agusan-Davao Rd.), Sianib Sect. 03/28/12 XIII 23.686 284 C 0.449 0.133 0.300 - - - 88.20 86.76%

Satisfactory

L.C. Ting Construction 23666 Reconst. of Critical Road Slip Sect. along Daang Maharlika (Agusan-Davao Rd.) Afga Sect. 03/28/12 XIII 18.897 285 C 0.480 0.133 0.300 - - - 91.30 86.44%

Satisfactory

L.C. Ting Construction 23666 Widening/Conc. of Add'l lane along SDCR (Tandag City Sect.) 03/24/12 XIII 44.910 250 C 0.356 0.200 0.300 - - - 85.60 83.98%

Satisfactory

L.C. Ting Construction 23666 Reconst. of Critical Sect. along Nat'l Rds. Payasan-Los Arcos Rd. (Road Slip) Km. 1393+575-Km. 1393+670 11/24/12 XIII 10.589 174 C 0.485 0.133 0.300 - - - 91.80 90.66%

Very Satisfactory

L.C. Ting Construction 23666Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd.

along Daang Maharlika (Agusan-Davao Sect.) km. 1246+481-km. 1254+093.00, Afga-Bayugan

11/29/12 XIII 41.718 195 C 0.438 0.200 0.300 - - - 93.80 90.20% Very Satisfactory

L.C. Ting Construction 23666Rehab./Reconst./Strengthening of Guinoyoran Bridge

along Daang Maharlika (Surigao-Agusan Rd.) Km.1197+534.50

11/19/12 XIII 15.985 255 C 0.308 0.200 0.300 - - - 80.80 83.62% Satisfactory

L.C. Ting Construction 23666 Reconst. of Critical Sect. along Nat'l Rds. Payasan-Los Arcos Rd. (Road Slip) Km.1393+575-Km.1393+670 08/15/12 XIII 10.589 150 O 0.384 0.254 0.148 0.030 0.050 0.033 89.90 -

L.C. Ting Construction 23666Rehab./Reconst./Strengthening of Guinoyoran Bridge

along Daang Maharlika (Surigao-Agusan Rd.) Km.1197+534.50, San Isidro

08/07/12 XIII 15.985 255 O 0.387 0.240 0.150 0.030 0.040 0.033 88.00 -

L.C. Ting Construction 23666Rehab./Reconst./Upgrading of Damage Paved Nat'l Rd.

along Daang Maharlika (Agusan-Davao Sect.) Km.1246+481.50-Km.1254+093.00, Afga-Bayugan

08/19/12 XIII 39.828 195 O 0.345 0.270 0.150 0.030 0.050 0.033 87.80 -

L.C. Ting Construction 23666 Rd. Upgrading (Gravel to Concrete) Jct. Gamut-San Miguel Bayugan Rd. 08/15/12 XIII 28.918 377 C 0.432 0.145 0.300 - - - 87.70 86.80%

Satisfactory

L.C. Ting Construction 23666 Reconst. of Critical Rd. Slip Sect. along NRJ-Bahbah-Talacogon Rd. at San Rafael Sect. 08/19/12 XIII 24.730 365 C 0.355 0.200 0.300 - - - 85.50 84.90%

Satisfactory

L.C. Ting Construction 23666 Impvt. of Daang Maharlika Rd. (Agusan-Surigao Sect.), Km.1238+000-Km.1239+010 03/21/13 XIII 10.718 71 C 0.344 0.200 0.300 - - - 84.40 84.40%

Satisfactory

L.C. TING CONSTRUCTION/ROAD EDGE TRADING & DEVELOPMENT

SERVICES (J.V.)

SL1-SN-008082

Construction of Revetment along Butuan City-Cagayan de Oro City-Iligan City Road 8/11/2014 X 34.759 239 OG 0.384 0.263 0.150 0.030 0.035 0.033 89.50 -

L.G Lasacar Construction 11960 Const./Rehab. of Protection Works / Seawall, Looc Catarman 09/05/09 X 9.358 270 O 0.318 0.226 0.150 0.020 0.047 0.033 79.40 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page151

Page 152: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

L.G Lasacar Construction 11960 Const./Impvt. of Mambajao-Catarman-Cross County Road (Phase 4) Mambajao-Catarman Section 09/05/09 X 9.483 225 O 0.296 0.236 0.000 0.030 0.037 0.017 61.60 -

L.G Lasacar Construction 11960 Impvt./Rehab. of Camiguin Circumferential Road Tangub Section 09/06/09 X 19.004 352 O 0.368 0.012 0.150 0.020 0.037 0.017 60.40 -

L.G. Lasacar Construction 11960 Const./Impv't. of CCR Slope Protection Works Alangilan (Km.30+400-Km.30+900) 08/15/12 X 8.657 185 C 0.431 0.167 0.235 - - - 83.30 85.52%

Satisfactory

L.M.G. Construction 5719 Repair/Rehab./Impv't. of Nueva Ecija-Aurora Rd., K0214+918-K0216+329 w/ exceptions 08/10/13 III 9.900 46 O 0.362 0.200 0.000 0.030 0.050 0.033 67.50 -

L.M.G. Construction 5719 Rehab./Impv't. of Drainage System along Libingan ng mga Bayani Rd. 08/15/12 NCR 5.721 90 C 0.395 0.200 0.300 - - - 89.50 82.18%

Satisfactory

L.M.G. Construction 5719 Repair/Maint. of Cataning River Control 03/14/13 III 1.860 56 C 0.416 0.133 0.300 - - - 84.90 84.90% Satisfactory

L.M.G. Construction / Z F Construction Joint Venture JV-12-343

Asset Preservation of Nat'l Rd. Gen. from Pvmt. Mgt. System/Highway Dev. & Mgt. System (HDM-4), Nueva Ecija-

Aurora Rd., a)K0212+265-K0214+000; b)K0220+000-K0221+000; c)K0229+000-K0230+698

08/10/13 III 13.927 150 O 0.366 0.200 0.150 0.030 0.050 0.033 82.90 -

L.N. SALVADOR CONSTRUCTION 16661 Construction of Protection Works Calapan North Road K0042+000-K0043+000 (Intermittent Section) 11/28/2014 IV 19.534 166 C 0.496 0.133 0.300 - - - 92.90% 92.90%

Very Satisfactory

L.N. Salvador Construction 16661 Construction of Protection Works Calapan North Road, K0042+000 - K0043+000 (Intermittent Section) 8/11/2014 IV-B 18.030 154 OG 0.367 0.196 0.150 0.030 0.050 0.050 84.30 -

L.N. Salvador Construction 16661 Const. of Pob. Drainage System along Nat'l. Rd. (CNR) 03/18/13 IVB 8.370 141 C 0.463 0.133 0.300 - - - 89.60 89.60% Very Satisfactory

L.N.R Construction 14148 Development of Pilar Port Project 04/24/14 DOTC 12.182 120 O 0.400 0.300 0.150 0.030 0.038 0.050 96.81 -

L.N.R. CONSTRUCTION 14148 Sabang Port Development Project 09/24/15 DOTC 43.293 360 C 0.477 0.200 0.300 - - - 97.70 95.30% Very Satisfactory

L.P. Engineering Services 9823 Rehabilitation of Murcon Dam - Electro Mechanical Works 07/27/13 NIA 35.658 120 O 0.400 0.300 0.150 0.012 0.023 0.050 93.53 -

L.P.O. Enterprises 20730 Widening of Sta. Cruz Pob. Rd. inc. Drainage 08/09/13 IVA 10.836 91 C 0.398 0.133 0.300 - - - 83.10 83.10% Satisfactory

L.R Tiqui Builders, Inc. 13810 Const. of Palilihan Bridge and Approaches (Phase IV) 02/18/10 III 24.992 150 O 0.368 0.300 0.150 0.030 0.042 0.050 94.00 -

L.R Tiqui Builders, Inc. 13810 Rehab./Reconst./Upgrading of Damaged Paved National Road at Pulilan-Calumpit Rd. 03/02/10 III 47.735 120 O 0.353 0.300 0.150 0.030 0.051 0.033 91.70 -

L.R Tiqui Builders, Inc. 13810 Rehab./Reconst./Upgrading of Damaged Paved National Road at Bigaa-Plaridel via Bulacan & Malolos Rd. 06/09/10 III 28.694 110 O 0.389 0.300 0.150 0.015 0.032 0.033 91.90 -

L.R Tiqui Builders, Inc. 13810 Rehab./Reconst./Upgrading of Damaged Paved National Roads at Gen.Alejo Santos Highway 06/10/10 III 40.605 275 O 0.357 0.240 0.150 0.018 0.043 0.033 84.10 -

L.R Tiqui Builders, Inc. 13810 Asphalt overlay of Daang Maharlika 03/13/09 II 39.996 80 O 0.388 0.225 0.150 0.030 0.059 0.050 90.20 -

L.R Tiqui Builders, Inc. 13810 Traffic Management along Manila North Road from Meycauayan, Bulacan-Mabalacat, Pampanga (Package II) 06/02/09 III 138.317 269 O 0.315 0.300 0.150 0.030 0.060 0.050 90.50 -

L.R Tiqui Builders, Inc. 13810 Impvt./Rehab. of Norzagaray-Bigte Road, Bulacan 3rd Congressional District 06/03/09 III 57.822 180 O 0.249 0.300 0.150 0.030 0.055 0.050 83.40 -

L.R Tiqui Builders, Inc. 13810Impvt./Widening of McArthur Highway (MNR)-Phase V,

Meycauayan (Bulacan) to Mabalacat (Pampanga)-Bocaue-Balgatas-Guiguinto Sect.)-CP II

09/05/09 III 88.724 180 O 0.371 0.300 0.150 0.030 0.056 0.033 94.00 -

L.R Tiqui Builders, Inc. 13810 Impvt./Widening/Concreting of Manila North Road (MNR)-Phase V (Malolos-Calumpit Section)-CP I 09/05/09 III 110.823 240 O 0.361 0.300 0.150 0.030 0.056 0.033 93.00 -

L.R Tiqui Builders, Inc. 13810 Impvt./Rehab. of General Alejo Santos Highway inc. Niugan Bridge No. 3 09/09/09 III 62.146 230 O 0.358 0.300 0.150 0.030 0.056 0.033 92.70 -

L.R Tiqui Builders, Inc. 13810 Impvt./Rehab. of Norzagaray-Bigte Road 09/09/09 III 57.900 200 O 0.345 0.300 0.150 0.030 0.056 0.033 91.40 -L.R Tiqui Builders, Inc. 13810 Rehab. of Bocaue-San Jose Road 09/07/09 III 1.905 73 O 0.379 0.240 0.150 0.030 0.042 0.033 87.40 -

L.R Tiqui Builders, Inc. 13810 Const. of Palilihan Bridge # 1 including approaches and Road Right-of-Way along Roman Expressway 02/27/09 III 90.181 240 O 0.351 0.300 0.150 0.030 0.056 0.050 93.70 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page152

Page 153: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

L.R Tiqui Builders, Inc. 13810 Impvt. (Widening/Conc.) of Mc Arthur Highway (MNR) Meycauayan to Mabalacat, Pampanga (Phase IV) Package II 03/06/09 III 70.394 180 O 0.366 0.300 0.150 0.030 0.047 0.050 94.30 -

L.R Tiqui Builders, Inc. 13810 NCR/Bulacan Bdry.-Bigte-Ipo Dam Road inc. Replacement of Kay Tialo Bridge 03/10/09 III 47.641 210 O 0.366 0.300 0.150 0.030 0.038 0.050 93.40 -

L.R Tiqui Builders, Inc. 13810 Impvt. (Widening/Conc.) of Mc Arthur Highway (MNR) Meycauayan to Mabalacat, Pampanga (Phase IV) Package 1 11/21/08 III 188.051 270 O 0.376 0.300 0.100 0.030 0.060 0.100 96.60 -

L.R Tiqui Builders, Inc. 13810 Impvt/Widening of Aguinaldo Highway and other related road Phase II 11/11/08 IV-A 60.022 360 O 0.274 0.300 0.100 0.030 0.028 0.100 83.20 -

L.R Tiqui Builders, Inc. 13810 Traffic Management along Manila North Road, MNR from Meycauayan, (Package 2) 03/09/09 TEAM 138.317 239 O 0.371 0.300 0.150 0.030 0.060 0.050 96.10 -

L.R. De Guzman Construction 10263 Const. of Road @ Brgy. Alangan 04/02/11 III 3.205 88 O 0.280 0.293 0.150 0.011 0.015 0.017 76.60 -

L.R. TIQUI BUILDERS, INC. 13810 Construction of Single Barrel Box Culvert along Sto. Rosario Street 11/29/2014 NCR 14.450 180 C 0.412 0.187 0.300 - - - 89.90% 89.90%

Very Satisfactory

L.R. TIQUI BUILDERS, INC. 13810

Rehabilitation/Reconstruction/Upgrading of Damaged Paved Naitonal Roads (Intermittent Seciton) Gen. Alejo

Santos Highway Km. 45+000 to Km. 55+671 to Km. 56+102 & Km. 56+102 to Km. 56+948

11/7/2014 III 21.570 161 C 0.478 0.131 0.300 - - - 90.90% 90.90% Very Satisfactory

L.R. TIQUI BUILDERS, INC. 13810 Dredging/Deepening with Channel Improvement along Angat River 11/7/2014 III 13.823 255 C 0.418 0.133 0.300 - - - 85.10% 85.10%

Satisfactory

L.R. TIQUI BUILDERS, INC. 13810Widening of Daang Maharlika Road Km. 39+000 to Km. 41+1001 (Plaridel Section); Km. 45+033 to Km. 48+000

(Baliuag Section)11/7/2014 III 31.487 230 C 0.370 0.200 0.300 - - - 87.00% 87.00%

Satisfactory

L.R. Tiqui Builders, Inc. 13810Const. of Slope Protection for Marikina River along Brgy. Tumana, Eastbank Marikina City, 2nd District Sta. 6+120-

Sta.6+621.1008/06/13 NCR 43.770 214 C 0.452 0.133 0.300 - - - 88.50 88.44%

Satisfactory

L.R. Tiqui Builders, Inc. 13810 Widening of Daang Maharlika (Doña Remedios Trinidad Sect.) Km.45+452-Km.52+722 w/ exceptions 08/13/13 III 36.062 240 O 0.375 0.240 0.150 0.030 0.055 0.033 88.30 -

L.R. Tiqui Builders, Inc. 13810

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. (Int. Sect.) Gen. Alejo Santos Highway Km.45+000-Km.55+671, Km.55+671-Km.56+102 & Km.56+102-

Km.56+948

08/14/13 III 21.570 161 O 0.373 0.240 0.133 0.020 0.050 0.050 86.60 -

L.R. Tiqui Builders, Inc. 13810 Const. of Tartaro Bridge 08/15/13 III 24.892 210 C 0.449 0.133 0.300 - - - 88.20 85.32% Satisfactory

L.R. Tiqui Builders, Inc. 13810 Dredging/Deepening w/ Channel Impv't. along Angat River 08/14/13 III 13.893 135 O 0.353 0.265 0.134 0.023 0.045 0.033 85.30 -

L.R. Tiqui Builders, Inc. 13810 Const. of Slope Protection for Marikina River along Brgy. Tumana, Eastbank, 2nd District Sta.6+120 Sta.6+621.10 03/22/13 NCR 43.770 214 O 0.398 0.233 0.150 0.030 0.040 0.033 88.40 -

L.R. Tiqui Builders, Inc. 13810 Rehab./Reconst./Raising of Damaged Paved Nat'l Rd. along M.H. Del Pilar St. 03/18/13 NCR 28.428 339 C 0.411 0.200 0.300 - - - 91.10 85.52%

Satisfactory

L.R. Tiqui Builders, Inc. 13810Widening of McArthur Highway (Manila North Rd.) inc. Rehab./Impv't. of existing Pvmnt. Loading & Unloading

Bays & ROW03/18/13 III 47.515 344 C 0.359 0.133 0.300 - - - 79.20 87.78%

Satisfactory

L.R. Tiqui Builders, Inc. 13810 Const. of Tartaro Bridge 03/18/13 III 24.862 180 O 0.37 0.185 0.150 0.024 0.055 0.050 83.40 -

L.R. Tiqui Builders, Inc. 13810 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Roads Daang Maharlika (IS) Km.46+130-Km.49+560 w/ exception 03/14/12 III 44.802 170 C 0.467 0.196 0.300 - - - 96.30 93.60%

Very Satisfactory

L.R. Tiqui Builders, Inc. 13810

Restoration/Rehab./Reconst. Of Sta. Maria-Norzagaray Rd.: a)Km.34+131-Km.34+920 w/ exception; b)Km.35+695-

Km.35+1128; c)Km.35+1128-Km.35+1460.41 w/ exception; d)Km.38+052.56-Km.39.000; e)Km.39+010.92-Km.40+119

03/17/12 III 42.769 195 C 0.392 0.200 0.300 - - - 89.20 87.22% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page153

Page 154: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

L.R. Tiqui Builders, Inc. 13810 Pinatubo Hazard Urgent Mitigation Proj. (PHUMP), Phase III, Loan Agreement No. PH-P241, Flood Mitigation Works 03/13/12 MPE-PMO 196.285 642 C 0.429 0.133 0.300 - - - 86.20 85.09%

Satisfactory

L.R. Tiqui Builders, Inc. 13810Rehab./Restoration of Roads & Bridges along Various

Raod Sect. in Bulacan & Tarlac under POPSTIRP Roads and Bridges Component, Norzagaray Bigte Rd.

03/16/12 III/BOM 13.156 280 C 0.350 0.200 0.300 - - - 85.00 83.80% Satisfactory

L.R. Tiqui Builders, Inc. 13810 Rehab./Reconst. of NCR/Bulacan Bdry. - Bigte-Ipo Dam Rd. Km.37+61 -Km.42+116 (w/ exception) 03/14/12 III 14.840 100 C 0.341 0.200 0.300 - - - 84.10 82.96%

Satisfactory

L.R. Tiqui Builders, Inc. 13810 Widening of McArthur Highway (MNR) inc. Rehab./Impvt.of Existing Pvmt. Loading & Unloading Bays & ROW 11/30/12 III 103.925 270 C 0.441 0.200 0.300 - - - 94.10 93.44%

Very Satisfactory

L.R. Tiqui Builders, Inc. 13810 Widening/Const./Rehab. along C-5 Rd., Km.11+168-Km.14+533 w/ exceptions, Southbound 08/15/12 NCR 48.385 232 C 0.450 0.200 0.300 - - - 95.00 96.50%

Outstanding

L.R. Tiqui Builders, Inc. 13810 Widening of McArthur Highway (MNR) inc. Rehab./Impvt.of Existing Pvmt. Loading & Unloading Bays & ROW 08/03/12 III 100.349 360 O 0.362 0.300 0.150 0.030 0.055 0.033 93.00 -

L.S.D. Construction & Supplies 8980 Rd. Upgrading along Capas-San Jose-Mayantoc-Malacampa Rd., K0145+283-K0147+-476, Mayantoc 08/08/13 III 35.686 182 O 0.382 0.254 0.150 0.030 0.059 0.050 92.50 -

L.S.D. Construction & Supplies 8980 Const. of Drainage System along Baguio-Bua-Itogon Rd., K0254+(-655)-K0268+055 (V.S.) 07/29/13 CAR 18.556 150 O 0.357 0.240 0.150 0.015 0.045 0.050 85.70 -

L.S.D. Construction & Supplies 8980Rd. Upgrading (Gravel to Conc.) along Gurel-Bokod-

Kabayan-Buguias-Abatan Rd., K0322+491-K0338+760 (IS) Kabayan Sect.

07/30/13 CAR 95.365 455 C 0.435 0.133 0.300 - - - 86.80 84.19% Satisfactory

L.S.D. Construction & Supplies 8980

Const. of Typical Cross Drainage Structure (Dome/Cathedral Type) of various sect. along MNR w/n the

district 1)Pob. Villasis Sect.; 2)Bacag Villasis Sect.; 3)Nancayasan, Urdaneta Sect.; 4)Anonas, Urdaneta Sect.;

5)Sumabot, Binalonan Sect.; 6)Pob. Binalonan Sect.; 7)Alipangpang, Pozorrubio Sect.; 8)Pob. Sision Sect.;

9)Paldit Sision Sect.; 10)Pob. Sision Sect.

08/09/13 I 30.303 247 O 0.378 0.300 0.111 0.030 0.037 0.033 88.90 -

L.S.D. Construction & Supplies 8980

Road Upgrading (Gravel to Paved), along Awang-Upi Lebak-Kalamansig-Palimbang-Sarangani Rd.

(Km.1963+471-Km.1977+121) realigned to Rd. Upgrading (Gravel to Paved) along Awang-Upi-Lebak-Kalamansig-Palimbang-Sarangani Rd. (Km.2012+961-Km.2014+656)

03/13/13 XII 35.903 235 O 0.357 0.240 0.000 0.030 0.044 0.033 70.40 -

L.S.D. Construction and Supplies 8980Rd. Upgrading (gravel to concrete) along Gurel-Bokod-

Kabayan-Buguis-Abatan Rd., K0322+491-K0338+760 (IS), Kabayan Sect.

11/21/12 CAR 95.365 455 O 0.364 0.300 0.150 0.030 0.047 0.050 94.10 -

La Torre Builders & Construction 2010-0514 Calbiga Irrigation Project 11/22/14 NIA 8.857 185 C 0.456 0.200 0.297 - - - 95.25 95.25% Very Satisfactory

LABB Constrction 13524PW-BHL-13-14 BOHOL EMERGENCY ROAD REPAIR AND REHABILITATION OF JCT.(LIR)-QUINOGUITAN-SEVILLA-

HANOPOL ROAD05/15/15 Bohol 13.298 325 C 0.488 0.200 0.300 - - - 98.84 98.84%

Outstanding

LABB CONSTRUCTION 13524

Upgrading of Junction (LIR) - Buenavista, Carmen - Danao -Getafe Road, Sec 1: K0086+400 - K0086+982.72, Sec 2:

K0087+091 - K0087+530.468, Sec 3: K0087+819 - K0087+183.97, Sec 4: K0090+576 - K0091+540

10/26/2014 VII 88.868 360 C 0.354 0.200 0.300 - - - 85.40% 85.40% Satisfactory

LABB CONSTRUCTION 13524 Major Repair/Maintenance of Existing Permanent Bridges, Clarin Bridge along Tagbilaran East Road 8/12/2014 VII 3.024 140 C 0.424 0.200 0.300 92.40 92.40%

Very Satisfactory

LABB CONSTRUCTION 13524Access Road to Declared Tourism Destination (road

Upgrading) Gravel to Paved of Jct. (TNR), Maribojoc - Antequera - Catagbacan (Loon) Road

8/13/2014 VII 22.740 255 C 0.450 0.141 0.300 89.10 91.98% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page154

Page 155: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

LABB Construction 13524 PW-BHL-13-05 Emergency Repair & Rehabilitation of Hinawanan (LOAY)-Concepcion-Jct.(Loboc-Sikatuna) Road 01/20/15 Bohol 16.436 255 O 0.390 0.297 0.117 0.020 0.061 0.050 93.50 -

LABB Construction 13524 New Bohol (Panglao) Airport Development Project 11/13/14 DOTC 17.973 150 C 0.400 0.200 0.300 - - - 90.00 90.00% Very Satisfactory

Labb Construction 13524 Const./Impv't. of Concepcion, Danao-Buenavista, Carmen Rd., K0071+820-K0073+170 08/16/13 VII 62.582 277 C 0.433 - 0.500 - - - 93.30 93.30%

Very Satisfactory

Labb Construction 13524Access Rd. to declared Tourism Destination (Rd.

Upgrading-Gravel to Paved) @ Jct. (TNR) Maribojoc-Antequera-Catagbacan (Loon) Rd., Km.23+057-Km.23+993

08/17/13 VII 21.596 210 O 0.387 0.257 0.150 0.030 0.065 0.050 93.90 -

Labb Construction 13524 Const. of Bridges along Concepcion-Danao-Buenavista Carmen Road 11/19/08 VII 9.564 350 O 0.343 0.238 0.100 0.030 0.037 0.100 84.80 -

Labb Construction 13524 Concreting of La Union, Candijay-Mabini Road (Sta. 166+670-Sta. 166+846) 06/05/09 VII 2.636 125 O 0.359 0.300 0.131 0.030 0.042 0.033 89.50 -

Labb Construction 13524 Const. of Bridge along Concepcion, Danao-Buenavista Carmen Road 06/06/09 VII 13.914 504 O 0.344 0.263 0.150 0.030 0.047 0.050 88.40 -

Labb Construction / Herbert Malmis General Merchandise &

Contractor, Inc. (JV)JV-11-093 Conc./Widening of Rd. Balilihan-Hanopol-Batuan Rd.,

Hanopol 03/12/13 VII 40.547 255 C 0.301 0.200 0.300 - - - 80.10 83.46% Satisfactory

LADY OF ASSUMPTION ENTERPRISES 25360

Rehabilitation/Reconstruction of Critical Sections along National Road Roadslip Along Tacloban-Baybay South

Road K0990+500 - K0990+600, Mailhi Section10/28/2014 VIII 17.370 179 C 0.493 0.133 0.300 - - - 92.60% 92.60%

Very Satisfactory

LADY OF ASSUMPTION ENTERPRISES 25360

Const. of Padre Burgos Flood Control along Bdry. Southern Leyte - Maain - Macrohon - Sogod - Daang

Maharlika K1160+000 K1160+4008/5/2014 VIII 13.250 175 OG 0.272 0.300 0.150 0.030 0.045 0.033 83.00 -

Lady of Assumption Enterprises 25360 Rd. Leading to Danao Camp Tree Park 08/05/13 VIII 33.334 188 C 0.460 0.133 0.300 - - - 89.30 87.02% Satisfactory

Lady of Assumption Enterprises 25360 Road Leading to Danao Camp Tree Park 03/16/13 VIII 33.334 128 O 0.305 0.260 0.150 0.030 0.060 0.050 85.50 -

Lady of Assumption Enterprises 25360Rehab./Reconst. Of Damaged Paved Nat'l Road along

Bdry. So. Leyte-Maasin-Macrohon-Sogod-Daang Maharlika, Km.1198+500-Km.1198+900

03/28/12 VIII 6.269 240 C 0.481 0.133 0.300 - - - 91.40 93.74% Very Satisfactory

Lady of Assumption Enterprises 25360 Prev. Maint. Daang Maharlika Road Km.1012+000-Km.1014+500 08/20/12 VIII 10.094 167 C 0.410 0.133 0.300 - - - 84.30 83.88%

Satisfactory

Lady of Assumption Enterprises 25360 Rehab./Reconst. along Ormoc-Baybay Southern Leyte Bdry. Rd. Km.1090+200-Km.1113+068, w/ exceptions 08/17/12 VIII 18.816 175 C 0.392 0.133 0.300 - - - 82.50 83.58%

Satisfactory

LAKEWOOD CONSTRUCTION COMPANY 5294 Rehabilitation of Multi-Purpose Building at Sitio

Tigbungabong, San Pedro, Tungawan 10/23/2014 IX 3.976 130 C 0.498 0.133 0.300 - - - 93.10% 93.10% Very Satisfactory

Lanao Builder and Enterprises 15982

Road Upgrading (Gravel to Paved) Int. Sect. inc. Drainage & Rd. Facilities Tubod-Ganassi Rd., K1600+535-K1601+125; K1601+08- K1601+874; K1603+(-104 -

K1601+874.93; K1603+(042.50)-K1603+758.97

08/17/13 X 42.128 195 C 0.392 0.133 0.300 - - - 82.50 82.50% Satisfactory

Lanao Builder and Enterprises 15982 Rehab./Reconst./Upgrading along Dobleston-Butadon Rd., Km.2004+098-Km.2006+336 08/12/13 X 37.678 213 O 0.289 0.238 0.150 0.010 0.045 0.033 76.50 -

Lanao Builder and Enterprises 15982 Rehab./Reconst./Upgrading along Dobleston-Butadon Rd., Kapatagan, Lanao del Norte, Km.2004+098-Km.2006+336 03/14/13 X 35.723 167 O 0.343 0.246 0.150 0.010 0.040 0.033 82.20 -

Lanao Builder and Enterprises 15982 Rehab./Reconst./Upgrading of Linamon-Zamboanga Road 06/03/10 X 30.126 179 O 0.385 0.240 0.150 0.023 0.045 0.033 87.60 -

Lanao Builder and Enterprises 15982 Rehab. of Linamon-Zamboanga Roads, Kauswagan Section 08/30/08 X 9.053 120 O 0.333 0.240 0.100 0.030 0.032 0.100 83.50 -

Lanao Builder and Enterprises 15982 Rehab. of Sapad Public Market (Phase I) @ Poblacion Sapad 03/25/12 X 1.782 120 C 0.458 0.133 0.300 - - - 89.10 88.33%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page155

Page 156: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

LANAO BUILDERS & ENTERPRISES 15982

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic benchmark for Upgrading to Paved

Road STD (HDM-4 Project Analysis) (Intermittent Section) Lanao del Norte Interior Circumferential Road (LDNICR)

Lala-Salvador-Tubod Road, Pantao Ragat Section K1548+250 - K1551+768

10/29/2014 X 77.232 223 O 0.331 0.300 0.000 0.010 0.033 0.033 70.70% 70.70% Poor

LANAO BUILDERS & ENTERPRISES 15982 Const. of Multi-Purpose Building at MSU-IIT MPC, Lambaguhon, Brgy. San Roque 10/29/2014 X 7.095 120 C 0.456 0.139 0.300 - - - 89.50% 89.50%

Very Satisfactory

LANAO BUILDERS & ENTERPRISES 15982 Repair/Rehab. Lanao Avenue, Tubod, Iligan City 10/29/2014 X 4.330 80 O 0.312 0.284 0.150 0.010 0.032 0.050 83.80% 83.80% Satisfactory

Lanao Builders and Enterprises 15982 Completion of ACA Bldg., I Phase (Construction) 11/26/08 DOST 11.364 270 O 0.339 0.289 0.093 0.030 0.060 0.050 86.12 -

Lanao Builders and Enterprises 15982 Completion of ACA Building I (Phase 3) 11/26/08 DOST 11.364 270 O 0.339 0.289 0.093 0.030 0.060 0.050 86.12 -

LC TING CONSTRUCTION/ROAD EDGE TRADING & DEVELOPMENT

SERVICES JOINT VENUREJV-13-228 Const. of Angalay Bridge including approaches along CDO-

Airport-Bukidnon Road, Lumbia-Uguiban By-Pass Road 10/20/2014 X 16.078 220 O 0.345 0.300 0.000 0.015 0.047 0.033 74.00% 74.00% Poor

LDV Construction 35864 Design and Built and Detailed Engineer Drawings and Construction of Internal Medicine Building 11/05/14 DOH 49.950 365 O 0.388 0.300 0.150 0.030 0.065 0.050 98.21 -

Le Reve Builders 27312Rehabilitation/Reconstruction of Damaged Paved National

Road, Sta. Rita - Camias, Old Road K0073+326 - K0073+1027

9/27/2014 Special 3 8.749 105 C 0.403 0.134 0.300 83.70 83.70% Satisfactory

LE REVE BUILDERS 27312 Repair and Rehabiliation of Hanging Bridge 12/05/14 TIEZA 1.079 60 C 0.498 0.025 0.300 82.30 82.30% Satisfactory

Le Reve Builders 27312 Repair/Rehab./Impv't. of Daang Maharlika Rd. (San Miguel Sect.) Km.76+388.73-Km.76+899.73 w/ exceptions 03/20/13 III 9.702 90 C 0.485 0.133 0.300 - - - 91.80 91.80%

Very Satisfactory

Le Reve Builders 27312 Rehab./Reconst./Const. of Drainage Canal along Daang Maharlika Rd. (Maguinao/Cruz na Daan Sect.) 03/20/13 III 1.968 90 C 0.411 0.133 0.300 - - - 84.40 84.40%

Satisfactory

Lea & Sons Trading & Construction 34959 Repair/Maint.of DPWH Bldg. Office Quarter (PJHL Bldg.) 03/12/13 IVB 0.516 45 O 0.344 0.240 0.034 0.030 0.041 0.050 73.90 -

Lea & Sons Trading & Construction 34959 Repair/Maint. of Puerto Princesa South Rd. Revetment (Phase II), Km.024+420, PPSR 03/16/13 IVB 1.755 55 C 0.375 0.200 0.300 - - - 87.50 87.50%

SatisfactoryLea & Sons Trading and

Construction 34959 Repair/Maint. of DPWH Bldg. Office Quarter (PJHL Bldg.) 08/10/13 IVB 0.550 76 C 0.438 0.156 0.300 - - - 89.40 78.55% Unsatisfactory

Leadway Construction & Development Corp. (LCDC) 4378

Impvt./Widening/Conc. of MNR-Phase V-Meycauayan, Bulacan to Mabalacat, Pampanga-Completion of Tulaoc

Bridge and Sto. Domingo Bridge and Approaches (CP VI)08/28/09 III 31.028 171 O 0.361 0.300 0.150 0.030 0.050 0.050 94.10 -

Leadway Construction & Development Corp. (LCDC) 4378 Const. of BASA Airbase Access Road (Floridablanca)

leading to SCTEX Interchange 08/25/09 III 93.566 240 O 0.369 0.300 0.150 0.030 0.051 0.033 93.30 -

Leadway Construction & Development Corp. (LCDC) 4378

CP 29 Repair of Checkgates along Bebe Anak Pampanga Delta and Sapang iBa under the Post Ondoy and Pepeng Short -Term Infrastructure Rehab. Project (POPSTIRP)

03/14/12 BOM / III 24.328 90 O 0.310 0.300 0.150 0.030 0.045 0.050 88.50 -

Leamor Construction and Supply 34928 Const. of MPBs at Brgy. Barayong 08/09/13 XI 1.216 90 C 0.497 0.133 0.300 - - - 93.00 93.00% Very Satisfactory

Leamor Construction and Supply 34928 Const. of Bridge at Dahlia Street, Poblacion I 08/09/13 XI 1.944 60 C 0.442 0.133 0.300 - - - 87.50 87.50% Satisfactory

Leamor Construction and Supply 34928 Const. of Bridge at Dahlia St., Poblacion I 03/16/13 XI 1.944 60 O 0.372 0.239 0.150 0.030 0.030 0.050 87.10 -

Lechi Construction 24196 Construction of Flood Control (Seawall) 06/06/09 VIII 2.833 120 O 0.356 0.240 0.150 0.022 0.037 0.033 83.80 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page156

Page 157: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Leda Construction Incorporated 12229 Jct. (LIR) Buenavista-Carmen-Danao-Getafe Rd. 09/09/09 VII 12.184 450 O 0.344 0.240 0.150 0.030 0.037 0.033 83.40 -

LEDA CONSTRUCTION INCORPORATED (Formerly: Leda

Construction)12229

Widening of Biliran Circumferential Road to Include Payment of RROW Damages (Virginia-Culaba Proper

Section) Km.1067+000 - Km. 1068+30010/27/2014 VIII 24.806 241 O 0.338 0.300 0.098 0.030 0.045 0.033 84.40% 84.40%

Satisfactory

LEDA CONSTRUCTION INCORPORATED (Formerly: LEDA

Construction)12229 Const./Imrv't. of Conception - Danao - Buenavista -

Carmen Road, K0071+820 to K0073+806.89 8/13/2014 VII 64.263 364 C 0.479 0.178 0.300 95.70 90.90% Very Satisfactory

Leda Construction Incorporated (Formerly: Leda Construction) 12229

Conc./Impv't. of Sagbayan-Danao Rd., a)Sta.78+910.20-Sta.80+016.50; b)Sta.94.+720-Sta.95+306.25;

c)Sta.95+477.85-Sta.95+509.90; d)Sta.95+565.70-Sta.96+141.10

08/15/13 VII 48.744 288 C 0.447 0.133 0.300 - - - 88.00 88.00% Satisfactory

Leda Construction Incorporated (Formerly: Leda Construction) 12229

Rehab./Reconst. of Damaged Paved Nat'l Rd. along Biliran Circ. Rd., Km.1100+000-Km.1102+000 w/ exceptions

(Bunga-Magbangon Rd. Sect.)08/14/13 VIII 36.293 178 C 0.462 0.133 0.300 - - - 89.50 89.50%

Very Satisfactory

Leda Construction Incorporated (Formerly: Leda Construction) 12229 Rehab./Impv't. of Sawa Bridge and Approaches along West

Samar Coastal Rd. 08/16/13 VIII 29.937 360 C 0.431 0.133 0.300 - - - 86.40 86.40% Satisfactory

Leda Construction Incorporated (Formerly: Leda Construction) 12229 Const./Impv't. of Concepcion-Danao-Buenavista, Carmen

Rd., K0071+820-K0073+806.93 08/16/13 VII 62.464 270 O 0.337 0.264 0.150 0.030 0.046 0.050 87.70 -

Leda Construction Incorporated (Formerly: Leda Construction) 12229

Rd. Upgrading of Jaro-Dagami-Burauen-La Paz Rd., Km.0955+000-Km.0955+527; Km.0955+611-Km.0955+970; Km.0952+589-Km.0952+855; Km.0952+000-Km.0952+091

08/17/13 VIII 12.141 205 C 0.454 0.133 0.300 - - - 88.70 89.36% Very Satisfactory

Leda Construction Incorporated (Formerly: Leda Construction) 12229 Rehab./Strengthening/ Reconst. of Makapiko Bridge along

Balilihan-Hanopol-Batuan Rd., Batuan Sect. 03/14/13 VII 34.152 488 O 0.390 0.275 0.150 0.030 0.055 0.033 93.30 -

Leda Construction Incorporated (Formerly: Leda Construction) 12229 Reconst. of Makapiko Bridge along Balilihan-Hanopol-

Batuan Rd., Batuan Sect. 03/14/13 VII 13.313 252 C 0.472 0.133 0.300 - - - 90.50 88.76% Satisfactory

Leda Construction Incorporated (Formerly: Leda Construction) 12229

Repair of Concrete Pavement & Const. of Box Culverts & Rd. Slope Protection along Jagna-Sierra Bullones Rd.,

Km.70.00-Km.94.200 w/ exception03/14/13 VII 13.875 261 O 0.368 0.240 0.150 0.030 0.045 0.033 86.60 -

Leda Construction Incorporated (Formerly: Leda Construction) 12229

Rd. Upgrading of Jaro-Dagami-La Paz Rd., Km.0955+000-Km.0955+527; Km.0955+611-Km.0955+970; Km.9052+589-

Km.0952+855; Km.0952+000-Km.0952+09103/11/13 VIII 12.141 145 O 0.383 0.240 0.150 0.030 0.045 0.050 89.80 -

Leda Construction Incorporated (Formerly: Leda Construction) 12229 Rehab./Strengthening of San Joaquin Bridge along Daang

Maharlika, San Joaquin 03/22/13 VIII 31.640 180 O 0.400 0.225 0.150 0.030 0.029 0.033 86.70 -

Leda Construction Incorporated (Formerly: Leda Construction) 12229 Concrete Paving of Biliran Circ. Rd. Salvacion-Bool Rd.

Sect., Km.1061+870-Km.1064+197 w/ exception 03/12/13 VIII 48.021 310 C 0.406 0.137 0.300 - - - 84.30 85.92% Satisfactory

Leda Construction Incorporated (Formerly: Leda Construction) 12229 Rd. Upgrading of Kiling-Tanauan-Tabontabon-Julita Rd.,

K0932+477.5-K0934+175.40 03/11/13 VIII 34.690 200 C 0.370 0.180 0.300 - - - 85.00 83.44% Satisfactory

Leda Construction Incorporated (Formerly: Leda Construction) 12229 Reconst. of Calbiga Bridge along Daang Maharlika Rd. 03/18/13 VIII 47.269 350 O 0.331 0.240 0.150 0.030 0.040 0.033 82.40 -

Leda Construction Incorporated (Formerly: Leda Construction) 12229 Const. of Concepcion, Danao-Buenavista, Carmen Rd.,

Danao & Dagohoy, Bohol inc. Bridges 08/18/11 VII 34.350 270 O 0.400 0.300 0.150 0.030 0.030 0.033 94.30 -

Leda Construction Incorporated (Formerly: Leda Construction) 12229 Rehab./Reconst. of Palo-Carigara-Ormoc Rd., Palo-

Carigara-Ormoc Rd. Sect. 05/31/10 VIII 11.194 120 O 0.400 0.300 0.069 0.030 0.037 0.033 86.90 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page157

Page 158: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Leda Construction Incorporation (Formerly: Leda Construction) 12229 Const. of Concepcion, Danao-Buenavista, Carmen Rd.,

Danao & Dagohoy, Bohol inc. Bridges 08/10/12 VII 38.410 356 C 0.428 0.133 0.300 - - - 86.10 89.58% Very Satisfactory

Leda Construction Incorporation (Formerly: Leda Construction) 12229 Rehab./Strengthening/Reconst. of Makapiko Bridge along

Bililihan-Hanopol-Batuan Rd., Batuan Sect. 08/09/12 VII 33.578 391 O 0.366 0.240 0.150 0.030 0.045 0.033 86.40 -

LEGACY CONSTRUCTION 22465

Construction of Slope Protection and Drainage System along Mandurriao-San Miguel-Alimodian-Maasin-Cabatuan

Road, K0012+380-K0012+774.4 and K0013+091.5-K0014+781

10/28/2014 VI 9.203 140 C 0.409 0.133 0.300 - - - 84.20% 84.20% Satisfactory

LEGACY CONSTRUCTION 22465Construction/Rehabilitation of Flood Mitigation Facilities

along Major River Basin and Principal Rivers: Silway-Apopong-Sinawal River Basins (Polomolok)

10/29/2014 XII 9.571 145 O 0.345 0.199 0.150 0.030 0.055 0.050 82.90% 82.90% Satisfactory

LEGACY CONSTRUCTION 22465Completion of Access Road to Mandurriao Bridge Mandurriao, Iloilo City Sta. 5+200 - Sta. 5+900 with

exception8/4/2014 VI 15.994 174 C 0.395 0.200 0.300 89.50 89.50%

Very Satisfactory

LEGACY CONSTRUCTION 22465

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies Traffic Benchmark for Upgrading to Paved Road

Standards (HDM-4) Project Analysis, Concreting of January - Badiangan - Tina Road K0040+151.50 -

K0041+400 (K0040+151.50 - K0041+376)

8/15/2014 VI 17.920 195 C 0.410 0.200 0.300 91.00 85.42% Satisfactory

Legacy Construction 22465Rd. Upgrading (Gravel to Paved), Conc. of Janiuay-

Badiangan-Tina Rd., K0040+151.50-K0041+400 (K0040+151.50-K0041+376)

08/20/13 VI 17.920 201 O 0.364 0.203 0.150 0.030 0.037 0.033 81.70 -

Legacy Construction 22465 Rehab./Recons./Upgrading of Dumaguete North Rd. (Calo Rd. Sec.) 09/12/09 VII 26.856 200 O 0.386 0.240 0.150 0.030 0.037 0.033 87.60 -

Legacy Construction 22465Reconst./Upgrading/Conc. of Bacolod North Road;

a)K0075+903-K0075+953; b) K0078+000-K0078+378 (Cluster IV)

03/28/12 VI 9.262 125 C 0.466 0.133 0.300 - - - 89.90 86.42% Satisfactory

Legacy Construction 22165 Rehab./Upgrading (Conc.) of Boracay Circ. Rd. Sta.2+350-Sta.2+800, Bolabog-Tulubhan Sect., Boracay Island 11/23/12 VI 13.822 120 O 0.400 0.240 0.121 0.030 0.050 0.033 87.40 -

Legazpi Premium Development Corp. / C. T. Leoncio Construction

and Trading (JV)Construction of Passenger Terminal Building 07/06/12 PPA 29.252 270 O 0.391 0.300 0.150 0.030 0.038 0.050 95.90 -

LEGAZPI PREMIUM DEVELOPMENT CORPORATION 20701 Replacement/Construction of Ibingan Bridge (BO4179LZ)

along Bacon-Sawanga-Prieto Diaz Road (SO3736LZ) 11/6/2014 V 17.053 202 C 0.474 0.133 0.300 - - - 90.70% 90.70% Very Satisfactory

Legazpi Premium Development Corporation 20701

Cluster 16: Repair/Rehab./Impvt. of Legazpi-Punta de Jesus Rd. (S05860LZ) a)Repair/Rehab.Impvt. of Legazpi-

Punta De Jesus Rd. ((Taysan Sect.) K0530+597-K0532+300 w/ exceptions; b)Repair/Rehab.Impvt. of Legazpi-Punta De Jesus Rd. (Taysan-Homapon Sect.) K0535+200-K0536+00

w/ exception

08/11/13 V 19.446 56 C 0.392 0.196 0.300 - - - 88.80 88.86% Satisfactory

Legazpi Premium Development Corporation 20701 Rehab./Reconst. Of Damaged Paved Nat'l Rds. (Int.Sect.)

Bacon-Sawanga-Prieto Diaz Rd. 08/13/13 V 70.792 290 C 0.323 0.200 0.300 - - - 82.30 88.06% Satisfactory

Legazpi Premium Development Corporation 20701

Replacement (Temp. to Perm.) of Bridges along Nat'l Rds., Haya Bridge Jct. CCR-Panganiban-Sabloyon Rd.

(K0074+830.05-K0074+851.05)07/30/13 V 11.928 154 O 0.341 0.300 0.112 0.030 0.035 0.033 85.10 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page158

Page 159: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Legazpi Premium Development Corporation 20701

Cluster 16: Repair/Rehab./Impvt. of Legazpi-Punta de Jesus Rd. (S0586LZ) a) Repair/Rehab./Impvt. of Legazpi-Punta de Jesus Rd. (Taysan Sect.) K0530+597-K0532+300 w/ exceptions; b) Repair/Rehab./Impvt. of Legazpi-Punta

de Jesus Rd. (Taysan-Homapon Sect.) K0535+200 -K0536+000 w/ exception

03/16/13 V 9.724 56 O 0.337 0.300 0.150 0.030 0.039 0.033 88.90 -

Legazpi Premium Development Corporation 20701 Road Upgrading (Gravel to Paved) Catanduanes Circ.

Road, K0141+400-K0143+634, Milaviga Sect. 08/16/11 V 45.555 240 O 0.375 0.070 0.150 0.030 0.028 0.050 70.30 -

Legazpi Premium Development Corporation 20701 Opening/ Impvt. of Sitio Tina-Sitio Nauasan Rd. (Phase I) 02/27/10 VI 40.515 310 O 0.382 0.300 0.129 0.020 0.028 0.017 87.60 -

Legazpi Premium Development Corporation 20701 Const. of the Extension of Tabaco City Public Market 02/22/10 V 11.568 159 O 0.380 0.240 0.150 0.030 0.040 0.050 89.00 -

Legazpi Premium Development Corporation 20701 Rehab./Reconst. Of Damaged Paved Nat'l Rds. (IS) Bacon-

Sawanga-Prieto Diaz Rd. 11/21/12 V 68.440 240 O 0.351 0.300 0.150 0.030 0.055 0.033 91.90 -

Legazpi Premium Development Corporation 2701 Package I (Conc. of Roads) 08/04/12 V 13.107 120 C 0.403 0.133 0.300 - - - 83.60 83.66%

SatisfactoryLegazpi Premium Development

Corporation 20701 Rehab./Repair of Nat'l. Rd. Calumpang Rd., Sta.3+206.40-Sta.327+95 (w/ exception) 03/12/13 V 16.629 75 C 0.367 0.200 0.300 - - - 86.70 86.70%

Satisfactory

Legazpi Premium Development Corporation / CTC Builder and

Supplies Incorporated JVJV-10-153 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds.

of Ariman-Jct. Bulusan Lake Rd. 08/03/12 V 60.969 239 C 0.460 0.133 0.300 - - - 89.30 87.92% Satisfactory

Legazpi Premium Development Corporation/ C.T. Leonico

Construction and Trading (JV) Construction of Passenger Terminal Building 11/09/12 PPA 29.689 285 C 0.450 0.150 0.300 - - - 90.00 94.13%

Very Satisfactory

LEHCI CONSTRUCTION 24196

Off-carriageway Improvement Paving of Shoulders (Seal Widening) Palo-Carigara-Ormoc Road (K0948+250-

K0951+450, Brgy. San Vicente-Brgy. Abango, Tunga-Barugo

10/29/2014 VIII 25.256 190 C 0.319 0.240 0.013 - - - 68.50% 68.50% Poor

LEHCI CONSTRUCTION 24196Road Upgrading (Gravel to Paved) Bagahupi-Babatngon -

Sta. Cruz Barugo, Carigara Road Leyte, KO934+049 - KO935+267.60 ; KO930+639 - KO931+420

8/9/2014 VIII 39.330 221 C 0.448 0.133 0.300 88.10 88.10% Satisfactory

Lehci Construction 24196Rd. Upgrading of (Gravel to Paved) Bagahupi-Babatngon-Sta. Cruz-Barugo-Carigara Rd., K0934+049-K0935+267.60;

K0930+639-K0931+42008/17/13 VIII 39.330 221 O 0.385 0.178 0.150 0.023 0.035 0.050 82.10 -

Lehci Construction 24196 Road Upgrading (Gravel to Concrete) Tigbao-Sta. Fe- San Miguel Road, K909+(172)-K909+378 03/19/12 VIII 8.821 137 C 0.477 0.133 0.234 - - - 84.40 86.44%

SatisfactoryLeza Construction and Supply 25565 Const. of Drainage Canal System at Tuliao 11/26/08 I 4.822 120 O 0.267 0.200 0.100 0.020 0.028 0.133 74.80 -

LGC Trucking and Construction 14464Const./Rehab. of Rd. Slip along Daang Maharlika (Agusan-Davao Rd.) Salvacion Sect., K1297+572.50-K1297+613.30;

K1298+218.30-K1298+272.3003/20/13 XIII 11.345 270 C 0.372 0.200 0.300 - - - 87.20 87.56%

Satisfactory

LGC Trucking and Construction 14464 Const. of MPB (SURSECO-1 Gym), Brgy. San Fernando 03/04/10 XIII 1.903 165 O 0.387 0.240 0.150 0.030 0.047 0.033 88.70 -

LGC Trucking and Construction 14464 Const. of Flood Control Structures/Shoreline Protection, Guava Jct., Brgy. Poblacion 03/04/10 XIII 0.954 165 O 0.360 0.240 0.150 0.030 0.047 0.050 87.70 -

LIBRIUS CONSTRUCTION & SUPPLY (Formerly: Librius Construction Supply) 23580 Rehabilitation & Reconstruction of MPC Structure

(Covered Court) Brgy. Halalang 10/27/2014 IV 4.704 90 C 0.463 0.133 0.300 - - - 89.60% 89.60% Very Satisfactory

Librius Construction & Supply Corporation 23580 Construction of Two Storey Six Classroom RGR Type SB

at Jacobo Zobel Memorial ES, Brgy. Poblacion 8/6/2014 IV-A 13.711 180 C 0.487 0.200 0.300 98.70 89.32% Very Satisfactory

Librius Construction & Supply Corporation (Formerly: Librius

Construction & Supply)23580

Replacement/Rehab./Strengthening of Permanent Bridges Gen. from Bridge Mgt. System (BMS) Angasin Bridge

along Tanauan-Talisay-Tagaytay Rd.08/02/13 IVA 4.168 60 C 0.402 0.156 0.300 - - - 85.80 85.80%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page159

Page 160: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Librius Construction & Supply Corporation (Formerly: Librius

Construction & Supply)23580 Const. of Two (2) Storey, (6) Cl. RGR Type Sch. Bldg.,

Jacobo Zobel Memorial Elem. Sch. Brgy. Pob. 07/31/13 IVA 13.711 180 O 0.335 0.264 0.150 0.030 0.041 0.033 85.30 -

Lim General Contractor 8482 Conc. of Tablas Circ. Road, San Agustin-Calatrava Road (Can-Omiang-Cabulotan Section) 08/27/09 IVB 19.298 180 O 0.333 0.300 0.150 0.030 0.047 0.033 89.30 -

Lim General Contractor Corporation (Formerly; Lim

General Contractor)8482 Replacement/Temp. to Perm. of Mores Bridge along SFNR 03/14/13 V 5.819 178 C 0.400 0.200 0.266 - - - 86.60 86.60%

Satisfactory

Linear Construction Corp. Const. of 1 Unit 3-Storey School Building 08/24/12 NHA 22.144 180 O 0.394 0.300 0.089 0.030 0.055 0.050 91.80 -

Linear Construction Corp. 3575 Const. of 1 Init 3-Storey School Building 05/10/12 NHA 22.144 180 O 0.360 0.300 0.150 0.024 0.055 0.050 93.90 -

Linear Construction Corporation 3575 Construction of 1 unit 3-Storey, 15-Classroom School Building 04/12/10 NHA 21.655 249 O 0.398 0.300 0.000 0.030 0.070 0.050 84.80 -

Linear Construction Corporation 3575 Construction of Two-Storey Multi-Purpose Center 06/16/10 NHA 4.989 90 O 0.40 0.300 0.075 0.030 0.070 0.050 92.50 -

Linear Construction Corporation 3575 Construction of 1 unit 3-Storey, 15-Classroom School Bldg. 06/16/10 NHA 22.107 150 O 0.396 0.30 0.00 0.03 0.07 0.05 84.60 -

LISA CONSTRUCTION 24134 Rehab./Reconst./Replacement/Retrofitting of Existing Permanent Bridges, Ft. Magsaysay Br. 11/27/2014 III 9.435 75 C 0.498 0.133 0.300 - - - 93.10% 93.10%

Very Satisfactory

LISA Construction 24134 Preventive Maintenance, Sumacab-San Josef-Bonifacion Road 9/25/2014 Special 3 5.940 37 C 0.477 0.133 0.300 91.00 91.00%

Very Satisfactory

LISA Construction 24134 Balbalungao Small Reservoir Irrigation Project 05/23/15 NIA 1.482 153 C 0.3871 0.160 0.300 - - - - 84.75% Satisfactory

Lisa Construction 24134 Cabanatuan City-Carmen Road 06/02/09 III 28.570 120 O 0.391 0.206 0.150 0.020 0.030 0.050 84.70 -

Lisa Construction 24134

Rehab./Reconst./Upgrading of Damaged Paved Nat'l. Rd. along Gapan-Ft. Magsaysay, Km.116+000 -

Km.116+1010.90 w/ exception L=230.73 l.m.; Km.117+795 - Km.120+107.50 w/ exception L=1,387.83 l.m. (1,618.56 l.m.)

03/21/12 III 22.907 150 C 0.383 0.133 0.300 - - - 81.60 86.10% Satisfactory

Lisa Construction 12584 CHB Canal Lining and Road Resurfacing 07/27/13 NIA 7.758 75 C 0.414 0.200 0.300 - - - 91.35 91.35% Very Satisfactory

LJPM BUILDERS & CONSTRUCTION SUPPLY 29981 Construction of Road Brgy. Himarco, Palompon 8/7/2014 VIII 2.413 37 C 0.405 0.133 0.300 83.80 83.80%

SatisfactoryLJPM Builders & Construction

Supply 29981 Rehab./Strengthening of Nailong Bridge 1 along Daang Maharlika, Pres. Roxas 03/16/13 VIII 3.730 83 O 0.285 0.280 0.150 0.030 0.035 0.033 81.30 -

LJPM Builders & Construction Supply 29981 Rehab./Impvt. of National Road along Amaga-Liloan Road

Section 11/21/08 VIII 3.735 180 O 0.380 0.240 0.100 0.020 0.037 0.100 87.70 -

LJPM BUILDERS & CONSTRUCTION SUPPLY 29981 Construction of Drainage Structure along Tanauan-Dagami

Road, K0931+900, Brgy. Balilit Section 10/29/2014 VIII 6.575 220 C 0.420 0.133 0.300 - - - 85.30% 85.30% Satisfactory

LL Construction 34244 Rehabilitation of Multi-Purpose Bldg. at Petit Barracks, Zone 4 8/5/2014 IX 4.132 126 OG 0.369 0.202 0.150 0.030 0.041 0.050 84.20 -

Llaban Construction & Trucking / Philtil Construction Joint Venture JV-11-275

Rehab./Reconst./Upgrading of Damaged Paved along Bukidnon-Cotabato Rd., Tambad Sect. Km 1607+010-Km

1607+880 (0.97km)11/22/12 XII 21.671 235 C 0.433 0.200 0.300 - - - 93.30 91.80%

Very Satisfactory

LLABAN CONSTRUCTION AND SUPPLY (Formerly: Llaban Construciton and Trucking)

29504

Rehab./Reconst./Replacement/Retrofitting of existing permanent Buluan Bridge II along Davao - Cotabato Road (Jct. Digos - Cotabato Section) Pigcawayan Cotabato, Km.

1711+164 - Km. 1711+182

10/25/2014 XII 33.451 252 O 0.355 0.225 0.150 0.022 0.045 0.033 83.00% 83.00% Satisfactory

LLABAN CONSTRUCTION AND SUPPLY (Formerly: Llaban Construction & Trucking

29504Road Upgrading (Gravel to Concrete) along Dualing - New

Panay Midsayap Road, Upper Bulanan Section, Km.1714+505 to K1715+009.66

8/11/2014 XII 10.959 65 C 0.407 0.200 0.300 90.70 90.70% Very Satisfactory

LLABAN CONSTRUCTION AND SUPPLY (Formerly: Llaban Construction & Trucking

29504Rehab./Reconst./Replacement /Retrofitting of Existing

Permanent Buluan Bridge II along Davao - Cotabato Road (Jct. Digos - Cotabato Section)

8/11/2014 XII 30.572 252 OG 0.388 0.250 0.150 0.030 0.030 0.050 89.80 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page160

Page 161: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

LLABAN CONSTRUCTION AND TRUCKING 29504 MALITUBOG IRRIGATION PROJECT MIP-LMC-004 Package

V 06/06/14 NIA 37.808 503 C 0.344 0.200 0.300 - - - 84.39 84.39% Satisfactory

Llaban Construction and Trucking 29504Rehab./Reconst./Upgrading along Matalam-M'lang-Bagontapay Jct. Rd. Km.1652+000-Km.1653+855-

Km.1655+000 (Clustered)03/18/13 XII 32.352 309 C 0.414 0.133 0.300 - - - 84.70 86.92%

Satisfactory

Llaban Construction and Trucking 29504 Road Upgrading (Gravel to Conc.) along Kidapawan-Ilomavis Tourist Rd., K1630+000-K1631+820 03/18/13 XII 39.860 320 C 0.401 0.133 0.300 - - - 83.40 86.70%

Satisfactory

Llaban Construction and Trucking / Philtil Construction (JV) JV-11-275

Rehab./Reconst./Upgrading of Damaged Paved along Bukidnon-Cotabato Rd. Tambad Sect., Km.1607+010-

Km.1607+880 (0.97 Km.)08/15/12 XII 19.953 210 O 0.391 0.240 0.150 0.030 0.047 0.050 90.80 -

LLM CONCRETE PRODUCTS 14235Concrete Revetment on Steel Sheet Piles along Talomo River, Peñano Section, Calinan Districct, Third District,

Davao City10/20/2014 XI 18.815 190 O 0.354 0.255 0.110 0.022 0.055 0.033 82.90% 82.90%

Satisfactory

LLM CONCRETE PRODUCTS 14235 Construction of Roads in Kibao, Matanao 10/24/2014 XI 1.851 60 C 0.467 0.135 0.300 - - - 90.20% 90.20% Very Satisfactory

LLM CONCRETE PRODUCTS 14235 Construction of Concrete Revetment on Steel Sheet Piles at Kalye Apike Protecting Calinan - Baguio - Cadalian Road 8/4/2014 XI 11.721 120 C 0.462 0.133 0.300 89.50 89.50%

Very Satisfactory

LLM Concrete Products 14235 Const. of Drainage along Lapu-Lapu St. 03/15/13 XI 8.870 150 C 0.456 0.133 0.300 - - - 88.90 85.84% Satisfactory

LLM CONCRETE PRODUCTS/PJ SAN PEDRO CONSTRUCTION AND

SUPPLY (JOINT VENTURE)JV-13-836 Concrete Revetment on Steel Sheet Piles along Lipadas

River, Llizada-Marapangi Section, Toril District, Davao City 10/20/2014 XI 27.708 217 O 0.377 0.207 0.150 0.015 0.055 0.033 83.70% 83.70% Satisfactory

LM CONSTRUCTION AND GENERAL MARKETING 33727 Local Infrastructure Program-Construction of Local Road

at Brgy. San Vicente I 10/24/2014 XIII 7.048 92 C 0.393 0.200 0.235 - - - 82.80% 82.80% Satisfactory

LMD Construction 9410

Road Upgeading of (Gravel to Paved) Based on Gravel Road Strategies, Traffice Benchmark FOR Upgrading to

Paved Road Standard (HDM-4 Project Analysis) Intermittent Section, Jct. Aurora-Ozamis City Road,

K1644+000 - K1645+910

8/12/2014 IX 44.369 206 C 0.417 0.200 0.300 91.70 87.62% Satisfactory

LMD Construction 9410

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading Paved Road Standard (HDM-4 Project Analysis), Intermittent Sections,

Eastern-Bobongan-Sominot-Midsalip-Dumingag Road K1649+549 - K1651+049

8/12/2014 IX 35.932 165 C 0.398 0.200 0.300 89.80 83.71% Satisfactory

LMD Construction 9410

Road Upgrading of (Gravel to Paved) based on Gravel Road Strategies, Traffic Benchmark for Upgrading to

Paved Road Standard (HDM-4 Project Analysis) intermittent Section, ZJct. Blancia-Molave-osefina Road,

K1684+500 - K1685+607

8/12/2014 IX 34.846 195 C 0.347 0.200 0.300 84.70 82.72% Satisfactory

LMD Construction 9410 Rd. Upgrading (Gravel to Paved) Int. Sect., Jct. Aurora-Ozamis City Rd., K1644+000-K1645+910 08/17/13 IX 44.369 206 O 0.326 0.296 0.150 0.012 0.033 0.033 85.00 -

LMD Construction 9410 Rd. Upgrading (Gravel to Paved), Int. Sect., Jct. Blancia-Molave-Josefina Rd., K1684+500-K1685+607 08/17/13 IX 34.846 255 O 0.302 0.254 0.150 0.030 0.028 0.033 79.70 -

LMD Construction 9410Road Upgrading (Gravel to Paved), Int. Sect., Eastern

Bobongan-Sominot Midsalip-Dumingag Rd., K1649+549-K1651+049

08/17/13 IX 34.732 165 O 0.360 0.278 0.000 0.024 0.033 0.033 72.80 -

LMD Construction 9410Rd. Upgrading (Gravel to Paved) Imelda-Bayog-

Kumalarang-Lapuyan-Margosatubig Rd., La Victoria Sect., K1755+075.00-K1756+000.00 w/ equation

08/14/13 IX 24.635 174 O 0.253 0.300 0.073 0.030 0.028 0.033 71.70 -

LMD Construction 9410 Rd. Upgrading (Gravel to Paved) Eastern Bobongan-Sominot Midsalip-Dumingag Rd., K1649+549-K1651+049 03/20/13 IX 34.732 105 O 0.379 0.225 0.150 0.030 0.048 0.033 86.50 -

LMD Construction 9410 Rd. Upgrading (Gravel to Paved) Int. Sect., Jct. Aurora-Ozamis City Rd., K1644+000-K1645+910 03/21/13 IX 44.369 116 O 0.367 0.225 0.150 0.030 0.043 0.033 84.80 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page161

Page 162: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

LMD Construction 9410 Rd. Upgrading (Gravel to Paved) Int. Sect., Jct. Blancia-Molave-Josefina Rd, K1684+500-K1685+607 03/21/13 IX 33.795 105 O 0.350 0.225 0.150 0.030 0.043 0.033 83.10 -

LMD Construction 9410Rd. Upgrading (Gravel to Paved) Imelda-Bayog-

Kumalarang-Lapuyan-Margosatubig Rd. La Victoria Sect., K1755+075.00-K1756+000.00 w/ equations

03/18/13 IX 24.635 145 O 0.333 0.225 0.150 0.030 0.043 0.050 83.10 -

LMD Construction 9410 Road Upgrading (Gravel to Paved) Jct. Aurora-Ozamiz City Road 03/27/12 IX 31.679 255 C 0.427 0.133 0.300 - - - 86.00 88.40%

Satisfactory

LMD Construction 9410Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds., Lanao-Pagadian-Zamboanga City Road, Km.1658+389.80-

Km.1661+780.8003/27/12 IX 26.002 167 C 0.421 0.133 0.300 - - - 85.40 83.90%

Satisfactory

LMG CONSTRUCTION - Construction/Completion of Southville 3, Multi-purpose Building, Barangay Poblacion 11/17/2014 NCR 7.739 120 O 0.339 0.240 0.150 0.030 0.060 0.050 86.90% 86.90%

Satisfactory

LMG Construction 5719 Improvement of Lateral A, SDA 05/23/15 NIA 17.949 210 S 0.380 0.300 0.000 0.015 0.037 0.033 76.52 -

LMG Construction 5719 Improvement of Lateral A-Extra, SDA, Talavera & Sto. Domingo 05/23/15 NIA 17.949 210 S 0.380 0.300 0.000 0.015 0.047 0.033 77.46 -

LMG Construction

Package X-L: Construction of lateral "N" (Sta. 13+440-Sta. 14+500) and sub-lat. "N-10" (Sta. 0+000-Sta. 1+500)

including related structures and supply, delivery and installation of steel gates

02/07/15 NIA 17.141 180 O 0.323 0.292 0.150 0.030 0.014 0.050 85.89 -

LMG CONSTRUCTION/PETER G. CHUA BUILDERS JOINT VENTURE JV-13-832 Rehabilitation/Drainage Improvement and Concreting

along Mo. Ignacio St. 11/27/2014 NCR 17.972 198 O 0.352 0.292 0.150 0.030 0.050 0.033 90.70% 90.70% Very Satisfactory

Long Island Builders & Construction 31730 Repair/Maint. of Rd. Slip along Pagadian City-Zamboanga

City Rd., K1722+276-K1722+430 Kamarin Sect. 08/16/13 IX 3.320 121 C 0.354 0.200 0.300 - - - 85.40 83.78% Satisfactory

Long Island Builders & Construction 31730

Repair/Restoration of Damage Rd. Slope along Jct. Dumalinao-Margosatubig Rd. (Tikwas Sect.) Int. Sect.,

K1683+240-K1684+00003/19/13 IX 3.517 93 C 0.426 0.133 0.300 - - - 85.90 87.82%

Satisfactory

Long Island Builders & Construction 31730 Repair & Maint. of Balongating River Control

(Downstream/Left Bank Slope) Balongating, Guipos 03/19/13 IX 1.397 116 C 0.477 0.200 0.000 - - - 67.70 70.64% Poor

Long Island Builders & Construction 31730 Repair/Maint. of Slip Shoulder along Pagadian City-

Zamboanga City Rd., K1722+276-K1733+430, Kamarin Sect. 11/21/12 IX 3.320 54 O 0.400 0.228 0.089 0.030 0.047 0.033 82.70 -

Long Island Builders & Construction / NFH Construction &

Supply (JV)JV-11-269

Rd. Upgrading (Gravel to Concrete) , Sindangan-Lakewood Nat'l Secondary Rd., (Lakewood Sect.) K1716+(-)234-

K1716+82011/21/12 IX 35.494 240 O 0.321 0.228 0.000 0.023 0.048 0.033 65.30 -

Long Island Builders & Construction / NFH Construction &

Supply (JV)JV-11-269

Rd. Upgrading (Gravel to Concrete), Sindangan-Lakewood Nat'l Secondary Rd. (Lakewood Sect.) K1716+(-234)-

K1716+82008/16/12 IX 35.494 240 O 0.361 0.240 0.150 0.030 0.027 0.033 84.10 -

Longwide Builders 20196 Repair/Rehab. of Damaged Pavement of Quezon Airport Road 06/09/10 XIII 7.287 129 O 0.329 0.287 0.150 0.030 0.040 0.033 86.90 -

Lorenzo Construction & Development Corp. 4284 Impvt./Rehab. of Gapan-San Fernando-Olongapo Road 09/05/09 III 42.155 180 O 0.224 0.300 0.150 0.030 0.050 0.033 78.70 -

Lorenzo Construction and Development Corporation 4284

Package X-A: Construction of Super Diversion Canal (Sta. 41+560-Sta. 42+920); Lateral "N" and sub-laterals including related structures and supply, delivery and installation of

steel gates

02/07/15 NIA 352.781 240 O 0.359 0.280 0.150 0.030 0.014 0.050 88.27 -

Lorenzo Construction and Development Corporation 4284 Impvt./Rehab. of Gapan-San Fernando-Olongapo Road 06/03/09 III 42.155 180 O 0.317 0.300 0.150 0.030 0.030 0.050 87.70 -

Lotiff Construction 21962 Rehab. of Mainit Sect., Tanjay, Dumaguete North Rd., Km.34+000 - Km.35+000 04/05/11 VII 19.270 247 O 0.325 0.257 0.150 0.023 0.055 0.050 86.00 -

Lotrim Construction 12273 Construction of DOST Caraga S & T Center 06/18/09 DOST 14.233 345 O 0.367 0.208 0.130 0.030 0.060 0.030 82.50 -

Lotrim Construction Incorporated (Formerly: Lotrim Construction) 12273 Reblocking of NRJ Barobo-Agusan del Sur Bdry. Rd.

Km.1412+000-Km.1416+383 (IS) 08/16/12 XIII 17.944 195 C 0.348 0.200 0.300 - - - 84.80 86.00% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page162

Page 163: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

LOTRIM CONSTRUCTION, INCORPORATED (Formerly: Lotrim

Construction)12273 Widening of Calinan-Baguio-Cadalian Road, Baguio

District km. 1688+302 to km. 1689+465 8/5/2014 XI 15.223 209 C 0.408 0.133 0.300 84.10 85.06% Satisfactory

LOTRIM CONSTRUCTION, INCORPORATED (Formerly: Lotrim

Construction)12273 Improvement of JNR Mabuhay-Mabunga-Union-JNR

Poblacion Road, MMURNEC ARC 8/6/2014 XI 27.664 245 C 0.318 0.190 0.300 80.80 82.66% Satisfactory

Lotrim Construction, Incorporated (Formerly: Lotrim Construction) 12273 Widening of Calinan-Baguio-Cadalian Rd., Baguio District

Km.1688+302-Km.1689+465 08/06/13 XI 15.223 209 O 0.322 0.300 0.149 0.030 0.023 0.033 85.70 -

Lotrim Construction, Incorporated (Formerly: Lotrim Construction) 12273 Impv't. of JNR Mabuhay-Mabunga-Union-JNR Pob. Rd.

MMURNEC ARC 08/09/13 XI 27.664 214 O 0.279 0.300 0.150 0.030 0.030 0.050 83.90 -

LOURBEL CONSTRUCTION & SUPPLY 31370 Improvement and Beautification of Kalayaan Park 01/29/14 TIEZA 9.757 180 C 0.408 0.171 0.300 87.90 87.90% Satisfactory

Lourbel Construction & Supply Improvement and Beautification of Kalayaan Park 01/29/14 TIEZA 9.757 180 C 0.408 0.171 0.300 - - - 87.90 87.90% Satisfactory

Lourel Design & Construction Development of Tibolo Eco-Cultural Village 04/03/14 TIEZA 10.077 210 C 0.440 0.161 0.300 - - - 90.10 90.10% Very Satisfactory

Lourel Design & Construction 17099Asphalt Overlay/Reblocking of Midsayap-Marbel Road, Km.

Sta. 1779+000-Km. Sta. 1786+000, Dumadalig-New Iloilo Section

03/05/10 XII 9.649 110 O 0.306 0.300 0.150 0.023 0.050 0.033 86.20 -

Lourel Design & Construction 17099 Asphalt Overlay/Reblocking of Marbel-Makar Rd., Km. Sta. 1701+000-Km. Sta. 1707+000, Sarawa - Bo. 6 Section 03/05/10 XII 9.644 110 O 0.314 0.286 0.150 0.023 0.050 0.033 85.60 -

LOUREL DESIGN AND CONSTRUCTION 17099 Development of Tibolo Eco-Cultural Village 04/03/14 TIEZA 10.077 210 C 0.440 0.161 0.300 90.10 90.10% Very

SatisfactoryLOUREL DESIGN AND

CONSTRUCTION 17099 Lake Lahit Sebu Development 04/08/14 TIEZA 12.487 210 C 0.453 0.191 0.300 94.40 94.40% Very Satisfactory

LOUREL DESIGN AND CONSTRUCTION 17099 Nasugbu Mini Convention and Visitors Center (Phase 1) 04/16/14 TIEZA 14.983 240 C 0.482 0.200 0.300 98.20 98.20%

Outstanding

LOUREL DESIGN AND CONSTRUCTION 17099 Bulusan Lake Development Project Installation of

Underground Primary Lines 12/16/14 TIEZA 10.891 105 C 0.450 0.200 0.300 95.00 95.00% Very Satisfactory

LOUREL DEVELOPMENT CORP. 17099 Alburquerque Sanitary Landfill (Phase 3) 3/17/15 TIEZA 55.800 210 O 0.383 0.294 0.000 0.030 0.045 0.033 78.50 -

LOUREL DEVELOPMENT CORPORATION 17099 Rehabilitation of Corregidor Lighthouse 10/30/14 TIEZA 24.979 60 C 0.486 0.198 0.300 98.15 98.15%

Outstanding

LSD CONSTRUCTION & SUPPLIES 8980 Construction of Drainage System along Baguio-Bua-Itogon Road, K0254+(-655) To K0268+055 (v.s.), Itogon, Benguet 8/14/2014 CAR 18.556 180 C 0.452 0.133 0.300 88.50 86.82%

Satisfactory

LSD Construction and Supplies 8980Rd. Upgrading (Gravel to Concrete) along Gurel-Bokod-

Kabayan-Buguias-Abatan Rd., K0322+491-K0338+760 (IS) Kabayan Sect.

07/31/12 CAR 95.365 359 O 0.313 0.300 0.026 0.008 0.028 0.033 70.80 -

LSD Construction and Supplies / C.M Dancel Construction and

Supply Joint Venture JV-08-315 Rehab./Reconst./Upgrading of Laoag-Sarrat-Piddig-

Solsona Road 02/24/10 I 134.537 330 O 0.258 0.273 0.055 0.030 0.051 0.033 70.00 -

LTB Builders and Construction 18752 Renovation of DBP General Santos Branch Building 01/26/12 DBP 3.938 120 C 0.476 0.133 0.300 - - - 90.95 85.20% Very Satisfactory

LTM Builders 35247 Rd. Upgrading (Gravel to Paved) of Mabatang Vicinal Rd. 07/31/13 III 3.262 90 C 0.455 0.133 0.300 - - - 88.80 88.80% Satisfactory

LTM Builders 35247 Impv't./Rehab. of Lying-in Health Clinic 03/13/13 III 0.975 60 C 0.472 0.133 0.300 - - - 90.50 90.50% Very Satisfactory

LTS BUILDERS AND CONSTRUCTION SUPPLY 33473 Construction of Elementary/Secondary School Buildings 8/11/2014 VII 5.871 160 C 0.451 0.157 0.300 90.80 83.87%

SatisfactoryLTS Builders and Construction

Supply 33473 Const. of San Miguel Technical Vocational Sch. 08/19/13 VII 4.550 160 O 0.397 0.300 0.002 0.030 0.047 0.033 80.90 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page163

Page 164: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

LTS Builders and Construction Supply 33473 Const. of 2 CL School Building with toilet (7mx18m)

Policarpio Dano H/S 09/05/09 VII 1.132 90 O 0.400 0.240 0.150 0.030 0.037 0.033 89.00 -

Lucban Builders & Construction Supply Incorporated 31336 Const. of DPWH Building @ DPWH Quezon 1st DEO, Brgy.

Abang 05/29/09 IV-A 4.148 150 O 0.360 0.240 0.150 0.030 0.023 0.033 83.60 -

LUCK WELL CONSTRUCTION 17510 MATNOG PORT EXPANSION PROJECT 05/23/14 PPA 192.699 711 C 0.440 0.178 0.300 - - - - 88.39% Satisfactory

LUCK-WELL CONSTRUCTION 17510 PORT OF GLAN IMPROVEMENT PROJECT 10/09/15 PPA 72.264 330 O 0.391 0.268 0.150 0.030 0.065 0.050 95.39 -

LUCK-WELL CONSTRUCTION 17510Repair of concrete pavement and gaps of PSC sheet piles and concrete blocks along Ro-Ro ramp at Port of Lamao,

Limay, Bataan06/26/15 PPA 11.373 130 C 0.463 0.173 0.300 - - - 93.60 93.60% Very

Satisfactory

Luckwell Construction 17510 Construction of Back-Up Area and Widening of Causeway 04/10/15 PPA 51.947 519 C 0.444 0.200 0.300 - - - - 95.68% Very Satisfactory

Luck-Well Construction 17510 Construction of Back-Up Area and Widening of Causeway 05/28/14 PPA 51.570 300 O 0.393 0.300 0.150 0.018 0.065 0.050 97.60 -

Luck-Well Construction 17510 Paving of the Newly Constructed Back-up Area Project 04/20-23/10 PPA 47.305 300 O 0.3657 0.3000 0.1256 0.024 0.0600 0.0500 92.53 -

Luck-Well Construction 17510 Repair of Old Wharf, Port of Danao 09/12/12 PPA 11.985 200 O 0.357 0.300 0.150 0.030 0.047 0.017 90.10 -

Luck-Well Construction 17510 Matnog Port Expansion Project 03/08/13 PPA 185.815 450 O 0.387 0.250 0.000 0.030 0.056 0.050 77.30 -

Luck-Well Construction 17510 Matnog Port Expansion Project 05/24/13 PPA 185.815 450 O 0.398 0.300 0.059 0.030 0.070 0.050 90.70 -

LUCKY STAR CONSTRUCTION AND TRADING 2011-0461 Construction of PSHSCLC ALA Building II, Phase I 09/11/14 DOST 28.086 240 C 0.488 0.200 0.300 - - - 98.80 96.14%

Outstanding

LUCKY STAR CONSTRUCTION AND TRADING 2011-0461 Cons. Of PSHSCLC ALA Building II, Phase I-Lot 2 09/11/14 DOST 8.516 120 C 0.445 0.200 0.300 - - - 94.50 94.60%

Very Satisfactory

LUCKY STAR CONSTRUCTION AND TRADING 2011-0461 Competion of PSHS CLC Building I Phase II 12/18/14 DOST 10.238 230 C 0.482 0.200 0.300 - - - 98.20 97.01%

Outstanding

Lug Konstract 33783 Const./Impv't. of Carigara Revetment 03/12/13 VIII 5.430 180 O 0.343 0.240 0.150 0.030 0.060 0.050 87.30 -

Lumel Glenn Construction Construction/Rehabilitation of Sinugdan River Control, Mansalay, Oriental Mindoro 8/13/2014 IV-B 9.096 112 C 0.420 0.133 0.300 85.30 85.30%

Satisfactory

Lumel Glenn Construction 26817 Repair/Maint. of Bansud River Control, Phase II 03/20/13 IVB 4.523 105 C 0.400 0.133 0.300 - - - 83.30 83.30% Satisfactory

LVRO Construction & Supply 18116 Repair/Rehab. Along Dinagat-Loreto Road 11/19/08 XIII 9.649 160 O 0.307 0.168 0.100 0.023 0.038 0.100 73.60 -

LVRO Construction & Supply 18116 Rehab./Reconstruction of Damaged Paved along Dinagat-Loreto Road 03/04/09 XIII 7.086 225 O 0.368 0.240 0.150 0.030 0.035 0.050 87.30 -

LVRO Construction & Supply 18116 Repair/Rehab. along Dinagat-Loreto Road 03/04/09 XIII 9.649 190 O 0.372 0.282 0.082 0.030 0.035 0.033 83.40 -LVRO Construction & Supply 18116 Const. of Aguntayan-Hilong-Hilong FMR 05/26/09 XIII 8.473 175 O 0.390 0.274 0.150 0.030 0.047 0.033 92.40 -

LVRO Construction & Supply 18116 Const./Rehab. of Agutayan-Hilong-hilong Rd.(Phase II) 09/01/09 XIII 4.720 90 O 0.388 0.215 0.150 0.030 0.060 0.033 87.60 -

LVRO Construction and Supply 18116 Impvt./Upgrading (Gravel to Concrete)- NRJ Tagcatong-Vinapor Rd. 08/06/13 XIII 27.927 200 O 0.300 0.204 0.145 0.030 0.025 0.033 73.70 -

LVRO Construction and Supply 18116 Impv't./Upgrading (Gravel to Concrete) - NRJ Tagcatong-Vinapor Rd. 03/12/13 XIII 27.927 170 O 0.347 0.295 0.150 0.020 0.025 0.033 87.00 -

LVRO Construction and Supply 18116 Conc. of Jct. Magsaysay-Cagdianao Rd. 03/13/13 XIII 34.685 335 O 0.306 0.240 0.000 0.030 0.045 0.033 65.40 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page164

Page 165: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

LVRO Construction and Supply 18116 Replacement of Maatas Bridge I along Jct. Magsaysay-Cagdianao Rd. 03/13/13 XIII 6.296 195 C 0.396 0.200 0.000 - - - 59.60 68.27%

Poor

LVRO Construction and Supply 18116 Rehab./Reconst. along Daang Maharlika (Agusan-Davao Sect.) 08/21/11 XIII 8.748 190 O 0.373 0.231 0.150 0.030 0.032 0.033 84.90 -

LVRO Construction and Supply 18116 Const. of San Jose MPB Phase VI 03/21/12 XIII 8.633 180 C 0.458 0.133 0.300 - - - 89.10 87.63% Satisfactory

LVRO Construction and Supply 18116 Conc. of Agusan-Bukidnon Road, Sta. 1206+621-Sta. 1261+429 03/19/12 XIII 13.145 150 C 0.444 0.133 0.300 - - - 87.70 86.32%

Satisfactory

LVRO Construction and Supply 18116 Rehab./Reconst. along Daang Maharlika (Agusan-Davao Sect.) 03/27/12 XIII 8.749 190 C 0.451 0.133 0.300 - - - 88.40 86.30%

Satisfactory

LVRO Construction and Supply 18116Rehab./Reconst. Of Surigao Wharf Road and Asphalt

Overlay along Surigao Wharf a.Sta. 1126+000-Sta.1126+520, b.Sta. 1125+404-Sta. 1125+436.87

03/23/12 XIII 7.100 210 C 0.444 0.133 0.300 - - - 87.70 86.02% Satisfactory

LVRO Construction and Supply 18116 Const. & Conc. of Purok 1 Road, Brgy. Pob. 03/21/12 XIII 4.275 148 C 0.426 0.133 0.300 - - - 85.90 86.02% Satisfactory

LVRO Construction and Supply 18116 Conc. of Jct. Magsaysay-Cagdianao Rd. 11/22/12 XIII 34.685 305 O 0.37 0.237 0.080 0.030 0.050 0.033 80.00 -

LVRO Construction and Supply 18116 Conc. of Jct. Magsaysay-Cagdianao Road 08/10/12 XIII 31.813 270 O 0.343 0.240 0.150 0.030 0.050 0.050 86.30 -

LVRO Construction and Supply 18116 Repair of Sto. Niño Revetment along Dinagat-Loreto Rd. 08/09/12 XIII 1.492 85 C 0.429 0.133 0.300 - - - 86.20 86.14% Satisfactory

LVRO Construction and Supply 18116Rehab./Reconst. of Damaged Nat'l Rd. & Asphalt Overlay

along Daang Maharlika (Surigao-Agusan Sect.), Km.1144+838-Km.1147+182 (w/ exception)

08/08/12 XIII 22.584 300 C 0.425 0.135 0.124 - - - 68.40 77.46% Unsatisfactory

LVRO CONSTRUCTION AND SUPPLY 18116 Impvt./Upgrading (Gravel to Paved) of NRJ - Tagcatong -

Vinapor Rd. 8/6/2014 XIII 22.927 200 C 0.247 0.200 0.300 74.70 78.09% Unsatisfactory

LYD CONSTRUCTION 37342 Construction and Rehabilitation of Multi-Purpose Building 8/9/2014 X 1.980 91 OG 0.371 0.300 0.150 0.030 0.053 0.050 95.40 -

M A M Construction & Trading (Formerly: M A M Construction) 19915 Conc. of Brgy. Rd., Ayala St., Dila-Dila 03/11/13 III 0.963 30 C 0.401 0.133 0.300 - - - 83.40 83.40%

Satisfactory

M M Construction 12012Rehab./Reconst./Upgrading of Damaged Paved National

Rd. along Daang Maharlika Solano-Diadi Sect. w/ exception

06/10/10 II 9.645 80 O 0.360 0.300 0.150 0.030 0.042 0.033 91.50 -

M M Construction 12012Rehab./Reconst./Upgrading of Damaged Paved National

Rd. along Daang Maharlika Villaros-Rosario Sect. w/ exception

06/10/10 II 14.470 90 O 0.358 0.276 0.150 0.030 0.042 0.033 88.90 -

M M Construction 12012 Rehab./Reconst. of Damaged National Roads, Daang Maharlika, Poblacion Villaflores Section 03/11/09 II 14.468 200 O 0.355 0.300 0.150 0.030 0.050 0.033 91.80 -

M M Construction 12012 Rehab./Reconst. of Damaged National Roads, Daang Maharlika, Poblacion Villaflores Section 11/28/08 II 14.468 200 O 0.374 0.240 0.100 0.030 0.047 0.067 85.80 -

M M Construction 12012 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. (IS) Daang Maharlika, K0248+000-K0248+998 08/15/12 II 19.981 105 C 0.352 0.200 0.300 - - - 85.20 85.74%

SatisfactoryM M Construction Corporation (Formerly: MM Construction) 12012 Const. of Sta. Fe River Control Proj., Revetment Nos. 1, 2 &

3 (Indiana Elem. Sch.) 08/13/13 II 19.399 135 C 0.406 0.133 0.300 - - - 83.90 83.90% Satisfactory

M M Construction Corporation (Formerly: MM Construction) 12012 Widening of Daang Maharlika, K0270+755.40-K0271+736.40 08/13/13 II 14.700 120 C 0.413 0.133 0.300 - - - 84.60 85.20%

Satisfactory

M N Revelo Construction 24789 Reconst. of Lanao-Pagadian-2Z Road, Lumbog Sect. Km. 1743+900 02/26/10 IX 4.035 123 O 0.275 0.285 0.150 0.020 0.047 0.050 82.70 -

M. B. Eclar Trading and Construction 32118 Const. of 3-Storey, 9-CL and 2-Storey, 4-CL School

Building, Naguilian National High School 8/5/2014 I 14.599 210 C 0.383 0.175 0.300 85.80 85.66% Satisfactory

M. B. Eclar Trading and Construction 32118 Road Upgrading (Gravel to Paved) Based on Gravel Road

Strategies Traffic Benchmark, Agoo Beach Road 8/5/2014 I 9.907 121 C 0.398 0.133 0.300 83.10 83.10% Satisfactory

M. Montesclaros Enterprises Inc. (Formerly: Monteclaros

Enterprises)6506 Road Upgrading (Gravel to Paved) along Jct. SH Bangcud-

Mailag Road (By-Pass Road) 06/15/10 X 16.923 150 O 0.348 0.240 0.150 0.030 0.055 0.033 85.60 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page165

Page 166: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

M. Montesclaros Enterprises Inc. (Formerly: Monteclaros

Enterprises)6506 Road Upgrading (Gravel to Paved) of Jct. S.H. Aglayan-

Alanib-Ticalaan Road 06/13/10 X 28.843 150 O 0.345 0.240 0.150 0.030 0.055 0.033 85.30 -

M. Montesclaros Enterprises Inc. (Formerly: Monteclaros

Enterprises)6506 Rehab. of Damaged Paved National Roads along Jct.

Impalambong-Cadre Barracks Road 06/15/10 X 6.982 60 O 0.330 0.240 0.150 0.023 0.055 0.050 84.80 -

M. Montesclaros Enterprises Inc. (Formerly: Monteclaros

Enterprises)6506 Rehab./Reconst./Upgrading of Don Carlos-Kadingilan

Road, Don Carlos-Lalapoy Sect. 06/14/10 X 25.926 120 O 0.335 0.240 0.150 0.030 0.055 0.033 84.30 -

M. Montesclaros Enterprises Inc. (Formerly: Monteclaros

Enterprises)6505

Road Upgrading/Gravel to Asphalt along Kibawe-Kadilingan Road (Sta. 1582+874-Sta. 1582+942.45 w/ exception) selective Sections, Kibawe-Kadilingan-

Kalilangan

05/28/09 X 28.335 120 O 0.367 0.300 0.150 0.030 0.050 0.050 94.70 -

M. Montesclaros Enterprises Inc. (Formerly: Monteclaros

Enterprises)6506

Rehab./Reconst./Upgrading of Damaged Paved National Roads along Maramag-Maradugo Road, Sta. 1558+538-

Sta.1576+850 selected sections 05/29/09 X 6.731 120 O 0.310 0.245 0.150 0.030 0.054 0.050 83.90 -

M. Montesclaros Enterprises Inc. (Formerly: Monteclaros

Enterprises)6506 Const. of 135 L.M. Steel Bridge (Bridge Approaches) 05/28/09 X 22.665 240 O 0.306 0.260 0.150 0.030 0.040 0.050 83.60 -

M. Montesclaros Enterprises Inc. (Formerly: Monteclaros

Enterprises)6506 Const. of 135 lm Steel Bridge (Bridge Approaches 03/03/09 X 22.665 271 O 0.360 0.240 0.150 0.030 0.045 0.050 87.50 -

M. Montesclaros Enterprises Inc. (Formerly: Monteclaros

Enterprises)6506 Const. of 135 l.m. Steel Bridge (Bridge Approaches) 09/04/09 X 22.665 240 O 0.288 0.300 0.150 0.030 0.051 0.050 86.90 -

M. MONTESCLAROS ENTERPRISES, INC. 6506

Rehabilitation/Reconst./ Widening of Daang Maharlika (Surigao - Agusan Section), a.) K1235+000 - K1235+972; b.)

K1236+000 - K1237+000; c.) K1237+000 - K1237+380, (Intermittent Section)

8/15/2014 XIII 25.534 175 OG 0.388 0.200 0.150 0.030 0.070 0.050 88.80 -

M. MONTESCLAROS ENTERPRISES, INC. 6506

Rehabilitation/Reconst./Improvement of Butuan City - Cagayan de Oro - Iligan (Agusan - Misamis Or.) a.)

K1234+091 - K1235+0618/15/2014 XIII 16.899 123 C 0.500 0.133 0.300 93.30 93.30%

Very Satisfactory

M. MONTESCLAROS ENTERPRISES, INC. (Formerly: M.

Monteclaros Enterprises)6506

Rehabilitation/Repair of Road Slip along Butuan City - Pianing - Tandang, K1234+900 to K1235+300 (Intermittent

Section)10/29/2014 XIII 12.896 154 C 0.339 0.200 0.300 - - - 83.90% 83.90%

Satisfactory

M. MONTESCLAROS ENTERPRISES, INC. (Formerly: M.

Montesclaros Enterprises)6506

Road Upgrading (Gravel to Concrete) Based on Gravel Road Strategies Traffic Benchmark for Upgrading to Paved

Road Standard (HDM-4 Project Analysis) (Intermittent Sections) along Jct. Dologon-Kisanday-Guinoyoran Road; a) K1547+855-K1549+343.564 b) K1549+603.48 - K1549+740

10/23/2014 X 47.311 174 C 0.428 0.200 0.300 - - - 92.80% 92.80% Very Satisfactory

M. MONTESCLAROS ENTERPRISES, INC. (Formerly: M.

Montesclaros Enterprises)6506 Const. of Valencia by-Pass Road Including RROW

K1527+910-K1530+780, K1527+800-K1528+000 10/24/2014 X 86.214 330 O 0.308 0.300 0.150 0.030 0.056 0.050 89.40% 89.40% Very Satisfactory

M. Montesclaros Enterprises, Inc. (Formerly: M. Montesclaros

Enterprises)6506 Rehab./Reconst./Upgrading @ Sayre Highway Rd.,

Impalutao Sect., K1483+(-233)-K1485+230.50 03/19/13 X 43.609 255 C 0.296 0.200 0.300 - - - 79.60 85.54% Satisfactory

M. Montesclaros Enterprises, Inc. (Formerly: M. Montesclaros

Enterprises)6506

Preservation of Nat'l. Rds., BCIR a)K1447+000-K1448+000 b)K1448+297-K1451+383 c)K1452+000-K1452+681 d)K1455+000-K1455+390 e)K1456+671-K1457+000

f)K1465+214-K1466+000

03/12/13 X 90.824 204 C 0.403 0.142 0.300 - - - 84.50 84.98% Satisfactory

M. Montesclaros Enterprises, Inc. (Formerly: M. Montesclaros

Enterprises)6506

Prev. Maint. Sayre Highway, Pob. Malaybalay & Casisang Sect., a)K1505+(-287)-K1505+818 b)K1508+224-K1508+504

w/ exceptions03/19/13 X 21.931 92 O 0.355 0.200 0.150 0.030 0.045 0.050 83.00 -

M. Montesclaros Enterprises, Inc. (Formerly: M. Montesclaros

Enterprises)6506 Prev. Maint. along Maramag-Maradugao Rd., (Adtuyon

Sect.) K1577+(-042)-K1578+944 03/20/13 X 24.920 139 O 0.346 0.207 0.150 0.030 0.045 0.050 82.80 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page166

Page 167: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

M. Montesclaros Enterprises, Inc. (Formerly: M. Montesclaros

Enterprises)6506

Rehab./Reconst./Upgrading of Intermittent Sect., Sayre Highway, Allalum Bridge Sect. Chainage 000+Chainage

02554, K1476+(-775)-K1476+(-369) w/ exceptions03/19/13 X 3.764 29 C 0.450 0.133 0.300 - - - 88.30 88.30%

Satisfactory

M. Montesclaros Enterprises, Inc. (Formerly: M. Montesclaros

Enterprises)6506 Assets Preservation of Nat'l. Rds. (Intermittent Sect.)

along Don Carlos-Kadingilan Rd., K1569+145-K1569+1205 03/20/13 X 15.285 40 C 0.408 0.124 0.300 - - - 83.20 83.20% Satisfactory

M. Montesclaros Enterprises, Inc. (Formerly: Montesclaros

Enterprises)6506

Prev. Maint.e of Sayre Highway, Pob. Malaybalay & Casisang Sect., a)K1505+(-287)-K1505+818; b)K1508+224-

K1508+504 (w/ exception)08/09/13 X 21.931 92 C 0.424 0.200 0.300 - - - 92.40 86.76%

Satisfactory

M. Montesclaros Enterprises, Inc. (Formerly: Montesclaros

Enterprises)6506 Prev. Maint. along Maramag-Maragdao Rd. (Adtuyon Sect.)

K1577+(-042)-K1578+944 08/06/13 X 24.920 139 C 0.451 0.133 0.300 - - - 88.40 85.04% Satisfactory

M. Montesclaros Enterprises, Inc. (Formerly: Montesclaros

Enterprises)6506

Road Upgrading (Gravel to Paved) (Int. Sect.) inc. Drainage & Rd. Facilities of Jct. S.H. Bangcud-Mailag Road (By-Pass Rd.) a)K1525+595-K1525+677; b)K1526+(-048)-K1526+747;

c)K1528+231-K1530+(-385), Bangcud

08/09/13 X 36.329 189 O 0.306 0.236 0.150 0.030 0.050 0.050 82.20 82.20% Satisfactory

M. Montesclaros Enterprises, Inc. (Formerly: Montesclaros

Enterprises)6506

Road Upgrading (Gravel to Paved) (Int. Sect.) inc. Drainage & Rd. Facilities along Dologon-Kisanday-Guinorayan Rd.

c)K1546+(-035)-K0547+000; d)K1547+000-K1547+69308/08/13 X 41.336 198 O 0.310 0.215 0.150 0.030 0.045 0.033 78.30 -

M. Montesclaros Enterprises, Inc. (Formerly: Montesclaros

Enterprises)6506 Road Upgrading (Gravel to Paved) Jct. Dologon-Busco-

Quezon Road, K1552+639 - K1553+056 03/20/12 X 8.126 90 C 0.416 0.200 0.300 - - - 91.60 88.84% Satisfactory

M. P. Villegas Construction 16683 Const. of PSHS Dormitory Building I Phase I 09/11/14 DOST 8.195 120 C 0.310 0.200 0.000 - - - 51.00 82.00% Satisfactory

M. S. CRUZ BUILDERS AND TRADING 33697 Construction of Visitors Information Center and Rest Area 6/16/15 TIEZA 2.500 90 C 0.436 0.178 0.225 83.80 83.80%

Satisfactory

M. S. CRUZ BUILDERS AND TRADING 33697 Rehabilitation of Old Train Terminal 03/13/14 TIEZA 4.974 150 C 0.441 0.165 0.300 90.70 90.70% Very

Satisfactory

M. S. CRUZ BUILDERS AND TRADING 33697 Visitor's Information Center and Rest Area 07/09/14 TIEZA 2.499 90 C 0.477 0.196 0.300 97.30 97.30%

OutstandingM. S. CRUZ BUILDERS AND

TRADING 33697 Visitor's Information Center and Rest Area 07/09/14 TIEZA 2.499 90 C 0.473 0.196 0.300 96.90 96.90% Outstanding

M. S. CRUZ BUILDERS AND TRADING 33697 Construction of Cottages 09/12/14 TIEZA 9.990 345 C 0.400 0.176 0.300 87.65 87.65% Satisfactory

M.A.C. Torres Enterprise Re-piping of sewr & Water Lines of CR 02/18/11 UP 1.534 45 O 0.400 0.300 0.000 0.030 0.057 0.050 83.70 -

M.B Ang Const. & Supply 25001 Conc. of Caibiran-Cabucgayan National Circ. Road (Uson-Gamay Section) 11/18/08 VIII 3.725 160 O 0.337 0.240 0.100 0.030 0.042 0.100 84.90 -

M.B. ECLAR TRADING AND CONSTRUCTION 32118

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies Traffic Benchmark, Agoo Beach Road,

KO241+632 to KO242+15510/26/2014 I 9.907 121 C 0.370 0.177 0.300 - - - 84.70% 84.70%

Satisfactory

M.C.B Zamora Construction & Supplies 32006 Const. of MPB at Barangay Matungao 02/15/10 IVB 0.891 90 O 0.302 0.300 0.150 0.030 0.023 0.033 83.80 -

M.C.B Zamora Construction & Supplies 32006 Const. of MPB at Brgy. Zone II 05/28/10 IVB 0.897 90 O 0.388 0.298 0.000 0.030 0.041 0.017 77.40 -

M.C.B. ZAMORA CONSTRUCTION & SUPPLIES 32006

Construction/Completion of Two (2) Storey Four (4) Classroom at Francisco G. Nepomuceno Memorial High

School, Angeles City8/22/2014 III 4.484 150 C 0.494 0.133 0.300 92.70 92.70%

Very Satisfactory

M.C.B. Zamora Construction & Supplies 32006 Const. of Slope Protection along Porac River, Brgy. Jalung 07/31/13 III 5.580 104 C 0.423 0.133 0.300 - - - 85.60 85.60%

SatisfactoryM.C.B. Zamora Construction &

Supplies 32006 Const. of Slope Protection/Flood Control, Bucao Dike (Downstream Sect.) 08/03/13 III 8.866 70 C 0.403 0.133 0.300 - - - 83.60 83.60%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page167

Page 168: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

M.C.B. Zamora Construction & Supplies 32006 Rehab./Impvt. of Angeles-Porak-Floridablanca-Dinalupihan

Rd., Calantas Sect. 03/19/12 III 9.427 75 C 0.442 0.133 0.300 - - - 87.50 90.56% Very Satisfactory

M.DEL ROSARIO CONSTRUCTION AND TRADING 30615 Rehabilitation of Road, Joyous Heights 11/28/2014 IV 4.628 90 C 0.470 0.133 0.300 - - - 90.30% 90.30%

Very SatisfactoryM.G Salazar Const. Corp. 4072 Construction of Girls Dormitory Bldg. 05/28/09 DOST 30.572 285 O 0.352 0.260 0.150 0.030 0.048 0.050 89.00 -M.G Salazar Const. Corp. 4072 Site Development Project 05/28/09 DOST 0.972 101 O 0.360 0.251 0.100 0.024 0.058 0.033 82.60 -

M.G Salazar Const. Corp. 4072 Rehab/Reconst./Upgrading of Daang Maharlika Road (Baliuag & Plaridel Section) 05/29/09 III 42.945 228 O 0.325 0.240 0.150 0.030 0.040 0.050 83.50 -

M.G Salazar Const. Corp. 4072 Rehab./Reconst./Upgrading at Daang Maharlika Road (Baliuag & Plaridel Section) 09/04/09 III 42.945 228 O 0.325 0.240 0.150 0.030 0.046 0.033 82.40 -

M.G. Francisco Construction 29831 Const. of Two (2) strorey, Two (2) CL Sch. Bldg. at Meneses Duque H.S. 03/18/13 III 2.213 90 C 0.424 0.133 0.300 - - - 85.70 85.70%

Satisfactory

M.G. LUALHATI CONSTRUCTION 35373Widening/Replacement/ Rehabilitation/ Strengthening of

Permanent Bridge At Tabuyoc Bridge Along MNR, (Phase I & II)

10/30/2014 I 43.217 192 O 0.369 0.300 0.150 0.024 0.055 0.050 94.80% 94.80% Very Satisfactory

M.G. SALAZAR CONS. CORP. (Formerly: M.G. Salazar

Construction)4072 Construction of River Wall along Tullahan River, Phase IX 11/22/2014 NCR 39.850 240 O 0.273 0.300 0.150 0.030 0.045 0.033 83.10% 83.10%

Satisfactory

M.G. Salazar Construction Corporation 4072 Const. of Coastal Dike 08/12/13 NCR 45.296 219 O 0.341 0.240 0.150 0.030 0.050 0.050 86.10 -

M.G. Samidan Construction 33234Road Upgrading (Gravel to Concrete) of National Roads

along Gurel-Bokod-Kabayan-Buguias-Abatan Rd. K0355+000-K0356+100 (I.S.)

03/14/12 CAR 17.245 194 O 0.374 0.240 0.150 0.030 0.045 0.050 88.90 -

M.H Southern Construction 5841 Sarangani Davao del Sur Coastal Road, Cross Section 06/11/09 R-XII 7.457 150 O 0.297 0.249 0.150 0.024 0.045 0.050 81.50 -

M.H Southern Construction 5841 Conc. of Road and Reblocking, Marbel-makar Road, Matin-ao Silway 8, (Km. 1662+800 - Km. 1663+740) 06/08/09 R-XII 14.167 195 O 0.301 0.300 0.000 0.030 0.055 0.033 71.90 -

M.H Southern Construction 5841 Conc. of Road & Reblocking, Marbel-Makar Road, Matinao Silway 8 03/20/09 XII 14.169 180 O 0.346 0.300 0.150 0.030 0.040 0.050 91.60 -

M.H. Southern Construction 5841

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. (South Cotabato 2nd District), Marbel-Makar Rd.,

K1701+896-K1703+(-58), K1702+966-K1703+2 Modified to: K1702+307-K1702+966, K1702+966-K1703+066

03/21/13 XII 14.394 225 C 0.435 0.200 0.000 - - - 63.50 70.46% Poor

M.J. APIN BUILDERS 12179 VARIOUS CONSTRACTION OF HOSPITAL FACILITIES 09/04/15 DOH 13.177 270 O 0.488 0.200 0.300 - - - 98.80 98.80% Outstanding

M.J. Apin Builders 12179 Construction of One-Storey, Three-Classroom School Building, Buyo Impact Elementary School 8/9/2014 V 1.602 150 C 0.434 0.133 0.300 86.70 86.56%

Satisfactory

M.J. Apin Builders 12179 Const. of 1 Storey 3-Cl. Sch. Buildings, Buyo Impact Elem. Sch. 08/02/13 V 1.602 120 O 0.365 0.240 0.150 0.030 0.047 0.033 86.50 -

M.MONTESCLAROS ENTERPRISES, INC. (Formerly:

M.Montesclaros Enterprises6506

Rehab./Reconst./Upgrading of Damaged Paved National Roads including Drainage based on Pavement Management System/Highway Development &

Management-4 (HDM-4) (Intermittent Sections), Don Carlos-Kadingilan Road, Bukidnon 3rd LD, K1568+152.00 -

K1569+145.00; K1569+975 - K1572+333; K1574+000 - K1574+202; K1574+202 - K1575+058; K1582+978 - K1583+420; with exceptions, Net Length=3.206km.

8/8/2014 X 91.142 255 OG 0.367 0.291 0.150 0.024 0.070 0.050 95.20 -

M.MONTESCLAROS ENTERPRISES, INC. (Formerly:

M.Montesclaros Enterprises6506

Road Upgrading (Gravel to paved) Based on Gravel Road Strategies Traffic Benchmark for Upgrading to Paved Road Standard (HDM-4) Project Analysis (Intermittent Section) including Drainage and Road Facilities of Junction S.H. Bangcud-Mailag Road (By-Pass Road) a. km1525+595 to K1526+677 b. K1526+(-048) - K1526+747 c. K1528+231 -

K1530+(-385)

8/5/2014 X 36.329 219 C 0.462 0.200 0.300 96.20 87.80% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page168

Page 169: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

M.MONTESCLAROS ENTERPRISES, INC. (Formerly:

M.Montesclaros Enterprises6506

Widening of Sayre Highway Bukidnon 2nd LD Kalasungay & Casisang Sections, K1502+(-250) - K1503+000, K1509+(-

400) - K1509+8008/6/2014 X 36.863 179 C 0.462 0.200 0.300 96.20 96.20%

Outstanding

M.MONTESCLAROS ENTERPRISES, INC. (Formerly:

M.Montesclaros Enterprises6506

Road Upgrading (gravel to paved) based on Gravel Road Strategies, Traffic Benchmark, for Upgrading to Paved Road Standard (HDM-4 Project Analysis) (Intermittent Section) including Drainage and Road Facilities Along Dologon-Kisanday-Guinoyoran Road c)K1546+(-035) -

K1547+000, d)K1547+000 - K1547+693

8/7/2014 X 43.918 220 C 0.466 0.187 0.300 95.30 85.10% Satisfactory

M.R Vargas Construction 8215 M'lang Airport Development Project 03/13/09 DOTC 13.458 180 O 0.360 0.293 0.150 0.023 0.050 0.033 90.90 -M.R.C Bechaida Construction &

Supply 32821 Conc. of Masagongsong Bridge Approaches 11/18/08 VIII 1.867 140 O 0.370 0.232 0.100 0.015 0.037 0.100 85.40 -

M.S Ramos Construction 31684 Const./Impvt. of P. Antonio St. (Covered Walkway/Sidewalk/Curb & Gutter, Brgy. Ugong 09/10/09 NCR 5.254 90 O 0.398 0.225 0.150 0.020 0.035 0.050 87.80 -

M.S. CRUZ BUILDERS & TRADING 33697 Widening along Tacloban-Baybay South Road, Chainage 0+000 - Chainage 0+111 10/30/2014 VIII 4.551 67 O 0.288 0.240 0.100 0.030 0.040 0.033 73.10% 73.10%

Poor

M.S. Cruz Builders & Trading 33697 Const. of Local Road at Brgy. Navaling, Magalang, Pampanga 8/23/2014 III 3.739 50 OG 0.372 0.238 0.150 0.030 0.055 0.050 89.50 -

M.S. Ramos Construction 31684Preventive Maintenance along Norzagaray-Bigte Road a)

K0072+572 - K0072+915 b) K0073+000 - K0073+738 c) K0072+960 - K0072+1160

9/27/2014 Special 3 10.923 30 C 0.483 0.131 0.300 91.40 91.40% Very Satisfactory

M.S. Ramos Construction 31684 Const. of MPB, Lolomboy 03/15/12 III 2.256 88 C 0.496 0.154 0.300 - - - 95.00 92.90% Very Satisfactory

M.S. Ramos Construction 31684 Conc. of Road, Barangay Pulong Gubat 03/15/12 III 3.670 59 C 0.330 0.200 0.300 - - - 83.00 85.94% Satisfactory

M.S. Ramos Construction 31684Prev. Maint. along Meycauayan-Camalig-Bahay Pari Rd., a)K0023+312-K0024+600 (w/ exceptions), b)K0025+700-

K0027+000 (w/ exceptions)08/08/12 III 22.256 75 C 0.446 0.200 0.300 - - - 94.60 93.40%

Very Satisfactory

M.S. Ramos Construction / Le Reve Builders Joint Venture JV-12-320

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. San Miguel-Sibul Rd. a)K0082+537-K0083+236; b)K0078+(-400)- K0078+000; c)K0083+236-K0083+366; d)K0078+(-476)-

K0078+(-400); e)K0086+000-K0086+231; f)K0086+908-K0087+621

08/15/13 III 27.591 180 C 0.445 0.133 0.300 - - - 87.80 87.80% Satisfactory

M.V. Caldo Engineering Construction and Supplies 16938 Prev. Maint. (Int. Sect.) Beata St.-K0008+035-K0008+360,

5th District 08/01/13 NCR 1.677 54 C 0.415 0.133 0.300 - - - 84.80 84.80% Satisfactory

M.V. Caldo Engineering Construction and Supplies 16938 Reconst. of C. Palanca St., w/ Drainage Impv't. 07/29/13 NCR 3.837 90 C 0.444 0.133 0.300 - - - 87.70 86.44%

SatisfactoryM.V. Caldo Engineering

Construction and Supplies 16938 Reconst. of C. Palanca St. w/ Drainage Impv't. 03/20/13 NCR 3.837 90 O 0.354 0.239 0.150 0.030 0.050 0.033 85.60 -

M.V. Caldo Engineering Construction and Supplies 16938 Prev. Maint. (Int. Sect.) of Zamora St. Chainage 00-

Chainage 0230, 5th District 03/13/13 NCR 1.826 30 C 0.477 0.133 0.300 - - - 91.00 91.00% Very Satisfactory

M.V. Sabalburo Construction and Supply 32561 Repair/Rehab./Impvt. along MNR Km. 331+000-Km.

333+000 w/ exceptions 08/12/13 I 9.849 104 C 0.497 0.133 0.300 - - - 93.00 93.00% Very Satisfactory

M.V. Sabalburo Construction and Supply 32561 Repair/Rehab./Impv't. Along Sta. Lucia-Salcedo Rd., Km.

343+000-Km. 346+000 w/ exception 08/12/13 I 4.851 80 C 0.408 0.133 0.300 - - - 84.10 84.10% Satisfactory

M.V. Sabalburo Construction and Supply 32561 Rehab. of Drainage Canal along MNR, Km. 405+500-Km.

406+715 08/13/13 I 9.690 128 C 0.470 0.133 0.300 - - - 90.30 92.88% Very Satisfactory

M.V. Sabalburo Construction and Supply 32561 Rehab. of Drainage Canal along MNR, Km.405+500-

Km.406+715 03/20/13 I 9.690 100 O 0.388 0.300 0.150 0.030 0.045 0.033 94.60 -

M3A Construction 32123 Rd. Opening of San Jose East-San Jose West Rd. 08/06/13 V 1.940 90 C 0.426 0.200 0.167 - - - 79.30 79.30% Unsatisfactory

Mabrak Construction 33340 Conc. of Nueva Vizcaya-Ifugao-Mt. Province Road 05/26/09 CAR 3.782 40 O 0.400 0.300 0.000 0.030 0.029 0.033 79.20 -

Mabuhay Conglomerate, Inc. 28118 Asphalt Overlay along Daang Maharlika, Km.434+(-037)-Km.434+773 (IS), Brgy. Mabolo 08/13/12 V 8.633 60 C 0.446 0.133 0.300 - - - 87.90 88.68%

SatisfactoryMAC Builders 7249 Hindang Port Development Project 12/05/12 DOTC 14.432 105 O 0.370 0.300 0.150 0.030 0.062 0.050 96.20 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page169

Page 170: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

MAC Builders 7249 Proposed Pier Extension and Passenger Terminal Building 03/01/13 PPA 38.509 309 C 0.500 0.200 0.000 - - - 70.00 83.14% Satisfactory

MAC Builders 7249 Hindang Port Development Project 03/20/13 DOTC 14.432 105 C 0.465 0.200 0.300 - - - 96.50 96.30% Outstanding

MAC Builders 7249 Construction of Back-up Area and RoRo Ramp on Fill 05/17/13 PPA 89.836 420 O 0.389 0.300 0.150 0.030 0.064 0.050 98.35 -

MAC Builders 7249 Ormoc Airport Development Project 08/12/15 DOTC 95.418 420 O 0.388 0.300 0.039 0.020 0.050 0.033 83.01 -

MAC BUILDERS 7249 Ormoc Airport Development Project 04/15/15 DOTC 54.839 135 C 0.441 0.200 0.300 - - - 94.10 92.00% Very Satisfactory

MAC BUILDERS 7249 Asphalt Overlay along Daang Maharlika (SM) (San Isidro - San Juanico Bridge), K0701+050 - K0701+216 10/23/2014 VIII 10.549 64 C 0.443 0.133 0.300 - - - 87.60% 87.60%

Satisfactory

MAC BUILDERS 7249Rehabilitation/Reconstruction/Replacement/Retrofitting of Existing Bridges Maypatag Bridge along Ormoc-Baybay-

Southern Leyte Boundary Road10/28/2014 VIII 12.540 162 C 0.492 0.133 0.300 - - - 92.50% 92.50%

Very Satisfactory

MAC BUILDERS 7249Road Upgrading (gravel to Paved) Merida - Lundag -

Putting Bato - Consolacion - Isabel Road K1121+162 - K1122+255

8/7/2014 VIII 30.615 234 C 0.419 0.133 0.000 55.20 75.84% Unsatisfactory

MAC BUILDERS 7249Rehab./Reconst. Of Damaged Paved National Road including drainag along Calubian Jct. - San Isidro -

Tabango - Villaba - Palompon Road Km………8/8/2014 VIII 25.548 179 OG 0.372 0.240 0.150 0.030 0.045 0.033 87.00 -

MAC Builders 7249 Ormoc Airport Development Project Construction of New Terminal 02/17/15 DOTC 95.418 360 O 0.369 0.300 0.150 0.020 0.025 0.033 89.78 -

MAC Builders 7249 Ormoc Airport Development Project Asphalt Overlay of Runway 02/17/15 DOTC 54.839 120 O 0.361 0.300 0.150 0.020 0.026 0.050 90.73 -

MAC BUILDERS 7249 Construction of Back-Up Area and Roro Ramp on Fill 04/29/15 PPA 92.985 660 C 0.500 0.200 0.300 - - - 99.98 99.00% Outstanding

Mac Builders 7249 Rd. Upgrading (Gravel to Pave) Merida-Lundag-Puting Bato-Consolacion-Isabel Rd., K1121+162-K1122+255 08/10/13 VIII 30.615 234 O 0.382 0.240 0.150 0.018 0.056 0.050 89.60 -

Mac Builders 7249 Prev. Maint. of Jaro-Dagami-Burauen-La Paz Rd., Km.0964+500-Km.0969+000 08/17/13 VIII 30.857 174 C 0.477 0.133 0.300 - - - 91.00 85.78%

Satisfactory

Mac Builders 7249 Rehab. & Impv't. of Naval-Caibiran, Cross Country Rd. (Major Rd. Slip), Km.1035+000-Km.1044+000 w/ exceptions 08/15/13 VIII 8.921 208 C 0.478 0.133 0.300 - - - 91.10 85.82%

Satisfactory

Mac Builders 7249 Rehab./Impv't. of Flood Control Proj., Dungca-an River Flood Control Works 03/15/13 VIII 17.856 170 O 0.380 0.240 0.150 0.030 0.050 0.050 90.00 -

Mac Builders 7249Upgrading/Concrete Paving of Gaps along Calbayog

Diversion Rd. (inc. RROW), Sta.5+062-Sta.5+725.89 and Sta.7+178.86-Sta.11+009.48, Calbayog City & Sta. Margarita

03/19/13 VIII 96.305 345 O 0.321 0.238 0.150 0.030 0.060 0.050 84.90 -

Mac Builders 7249 Rehab./Repair of Kinawan Bridge along Daang Maharlika (SM) (San Isidro-San Juanico Bridge) Kinawan 03/19/13 VIII 27.286 210 C 0.442 0.133 0.300 - - - 87.50 84.56%

Satisfactory

Mac Builders 7249 Road Leading to Leyte Golf and Country Club, Macabug-Mabini Rd. 03/15/13 VIII 25.125 174 O 0.331 0.240 0.150 0.030 0.040 0.050 84.10 -

Mac Builders 7249 Rehab. & Impv't. of Naval-Caibiran, Cross Country Rd. (Major Rd. Slip), Km.1035+000-Km.1044+000 w/ exceptions 03/12/13 VIII 8.921 150 O 0.320 0.240 0.150 0.030 0.050 0.033 82.30 -

Mac Builders 7249 Prev. Maint. of Jaro-Dagami-Burauen-La Paz Rd., Km.0964+500-Km.0969+000 03/11/13 VIII 30.857 144 O 0.314 0.239 0.150 0.030 0.040 0.050 82.30 -

Mac Builders 7249 Road Upgrading (Gravel to Paved) of Belen-Consuegra Rd., Km.981+940 - Km.981+910 06/04/10 VIII 18.540 240 O 0.334 0.300 0.150 0.030 0.037 0.033 88.40 -

Mac Builders 7249 Concrete Paving of Critical Portion along Caibiran-Cabucgayan Rd. (Pawikan-Bunga Sect.) 06/02/10 VIII 19.180 300 O 0.343 0.280 0.150 0.030 0.042 0.033 87.80 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page170

Page 171: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Mac Builders 7249 Replacement of Old Ticud Bridge connecting Iloilo City-Dumangas Coastal Road 09/08/10 V I 47.804 140 O 0.360 0.240 0.150 0.030 0.037 0.033 85.00 -

Mac Builders 7249 Conc. of Calubian Jct., San Isidro-Tabango-Villaba-Palompon Road 06/02/09 VIII 55.351 330 O 0.364 0.240 0.150 0.030 0.035 0.050 86.90 -

Mac Builders 7249 Conc. of Calubian Jct. San Isidro-Tabango-Villaba-Palompon Road Tabango-San Isidro 09/05/09 VIII 55.351 330 O 0.357 0.245 0.150 0.030 0.040 0.050 87.20 -

Mac Builders 7249 Rehab. (Conc.) of Cabungaan-Tabunok-Consuegra Road 09/05/09 VIII 14.052 180 O 0.340 0.245 0.150 0.030 0.040 0.050 85.50 -

Mac Builders 7249Rehab. of Damaged Paved National Roads along Daang

Maharlika Abuyog Mahaplag Road Section (Balinsasayao-Hilusig Road Section)

09/02/10 VIII 47.049 240 O 0.364 0.240 0.150 0.030 0.042 0.033 85.90 -

Mac Builders 7149 Rehab./Strengthening/Reconst. Of Can-Avid Bridge Jct. Taft-Oras-San Policarpio-Arteche Road 03/29/12 VIII 46.374 251 O 0.400 0.300 0.090 0.023 0.040 0.033 88.60 -

Mac Builders 7249 Rehab./Const. of Drainage Lined Canal along Calbayog-Allen Road Sect., K0690+500-K0732+600 03/25/12 VIII 45.983 180 O 0.355 0.225 0.150 0.030 0.030 0.033 82.30 -

Mac Builders 7249 Rehab./Strengthening/Reconst. of Dolores Bridge Jct. Taft-Oras-San Policarpio-Arteche Rd. 03/29/12 VIII 18.568 159 O 0.327 0.300 0.092 0.030 0.040 0.033 82.20 -

Mac Builders 7249 Rehab./Strenthening/Reconst. Of Quinapondan Bridge Jct. Buenavista-Lawaan-Marabut, 03/29/12 VIII 16.701 140 O 0.360 0.300 0.070 0.020 0.030 0.033 81.30 -

Mac Builders 7249Road Upgrading (Gravel to Concrete) of Calubian Jct.-San

Isidro-Tabango-Villaba-Palompon Road, Km.1009+500-Km.1011+248.55

03/22/12 VIII 32.852 320 C 0.356 0.133 0.300 - - - 78.90 84.30% Satisfactory

Mac Builders 7249Road Upgrading (Gravel to Concrete) of Calubian Jct.-San

Isidro-Tabango-Villaba-Palompon Road, Km.1006+374-Km.1005+967

03/22/12 VIII 7.842 222 C 0.401 0.133 0.300 - - - 83.40 82.80% Satisfactory

Mac Builders 7249 Rehab./Reconst. Of Damaged Paved Nat'l .Road, Palompon-Isabel-Merida-Ormoc Rd. Km.1114+000-Km.1116+000 03/24/12 VIII 25.163 210 C 0.288 0.133 0.300 - - - 72.10 82.36%

Satisfactory

Mac Builders 7249Road Upgrading (Gravel to Concrete) of Calubian Jct.-San

Isidro -Tabango-Villaba-Palompon Road, Km.1019+962-Km.1020+997

03/22/12 VIII 18.412 270 C 0.294 0.133 0.300 - - - 72.70 82.12% Satisfactory

Mac Builders 7249 Rehab. of Daang Maharlika (Km.1037+971-Km.1047+107 (w/ exceptions) 03/30/12 VIII 43.951 260 O 0.348 0.203 0.150 0.030 0.035 0.050 81.60 -

Mac Builders 7249 Rehab./Reconst. Of Damaged Paved Nat'l Road, Palo-Carigara-Ormoc Road, Km.1003+000-Km.1005+000 03/24/12 VIII 26.547 197 O 0.269 0.240 0.150 0.030 0.050 0.033 77.20 -

Mac Builders 7249Cluster No. RB13: Rehab./Restoration of Rds. & Bridges along various Rd. Sect. in Palawan, POPSTIRP, Roads &

Bridges Component07/30/12 IVB / BOM 57.023 331 C 0.342 0.200 0.300 - - - 84.20 88.28%

Satisfactory

Mac Builders 7249 Repair/Replacement of San Policarpio Bridge 08/19/12 VIII 21.275 265 O 0.373 0.300 0.147 0.030 0.035 0.033 91.80 -

Mac Builders 7249 Rehab./Strengthening/Reconst. of Can-avid Bridge Jct. Taft-Oras-San Policarpio-Arteche Rd. 08/19/12 VIII 46.374 360 O 0.322 0.300 0.140 0.030 0.038 0.033 86.30 -

Mac Builders 7249Rd. Upgrading (Gravel to Paved) based on Gravel Rd.

Strategies, Pangpang-Palapag-Mapanas-Gamay, Anito-Bag-ot Sect., K0835+531-K0838+000, w/ exceptions

08/17/12 VIII 127.381 360 O 0.338 0.300 0.128 0.030 0.033 0.033 86.20 -

Mac Builders 7249 Completion of Macabut Bridge along Borongan-Guiuan Rd., Km.1008+426 08/20/12 VIII 4.460 70 C 0.430 0.133 0.300 - - - 86.30 83.90%

Satisfactory

Mac Builders 7249 Rehab./Strengthening/Reconst. Of Dolores Bridge, Jct. Taft-Oras-San Policarpio-Arteche Rd. 08/20/12 VIII 18.568 235 O 0.354 0.300 0.072 0.030 0.038 0.033 82.70 -

MAC Builders 7249 Proposed Pier Extension & Passenger Terminal Building 10/09/12 PPA 38.591 309 O 0.328 0.300 0.150 0.030 0.061 0.050 91.90 -

MAC Builders / Ubas Construction (JV) JV-05-021 Impvt. of Allen-Malaga Section along Maharlika Highway,

Ferry Terminal-Allen 08/30/08 VIII 46.652 260 O 0.354 0.240 0.000 0.022 0.054 0.067 73.70 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page171

Page 172: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Madyaw Construction & Dev. Corporation 29598

Road Upgrading from Gravel to Paved along Butuan City-Talacogon-Loreto-Veruela-Sta. Josefa Rd, (K1345+625-

K1349+326)08/21/13 XIII 44.760 209 O 0.355 0.222 0.150 0.030 0.035 0.033 82.50 -

Madyaw Construction & Dev. Corporation 29598 Conc. of Butuan City-Talacogon-Veruela-Sta. Josefa Rd.,

Km.1357+837-Km.1358+424 03/19/13 XIII 35.076 301 O 0.322 0.300 0.000 0.030 0.030 0.033 71.50 -

Madyaw Construction & Dev. Corporation 29598 Conc. of Butuan City-Talacogon-Loreto-Veruela-Sta.

Josefa Rd., Km.1354+(-874)-Km.1354+916 03/19/13 XIII 39.775 336 O 0.258 0.300 0.000 0.030 0.044 0.033 66.50 -

Madyaw Construction & Dev. Corporation 29598 Conc. of Manapa Provincial Rd. 02/23/10 XIII 28.879 300 O 0.379 0.239 0.150 0.030 0.045 0.033 87.60 -

Madyaw Construction & Dev. Corporation 29598 Completion of San Luis Footbridge, Old Poblacion 12/01/08 XIII 5.722 210 O 0.324 0.300 0.100 0.030 0.032 0.100 88.60 -

Madyaw Construction & Dev. Corporation 29598 Conc.of Talacogon-La Paz Road Section along Butuan City-

Talacogon-La Paz-Loreto Veruela-Sta. Josefa Road 06/09/09 XIII 19.247 416 O 0.350 0.300 0.150 0.030 0.051 0.050 93.10 -

Madyaw Construction & Dev. Corporation 29598 Const./Impvt. of Water Supply System (Hydrolic Ram

Pump), Brgy. M.J. Santos 06/11/09 XIII 1.856 133 O 0.339 0.300 0.150 0.030 0.048 0.050 91.70 -

Madyaw Construction & Dev. Corporation 29598 Conc. of NRJ Cuevas-Sampaguita Rd., Road Upgrading

(Gravel to Concrete), San Jose 03/27/12 XIII 6.970 170 C 0.420 0.200 0.300 - - - 92.00 89.60% Very Satisfactory

Madyaw Construction & Dev. Corporation 29598 Concrete/Reblocking of NRJ Cuevas-Sta. Josefa Road 03/27/12 XIII 2.529 135 C 0.420 0.133 0.300 - - - 85.30 85.60%

Satisfactory

Madyaw Construction & Dev. Corporation 29598 Widening of Butuan-Cagayan de Oro-Iligan Rd. (Agusan-

Misamis Oriental Sect.) Dumalagan to Bdry. Sect. 08/23/12 XIII 20.618 135 C 0.439 0.133 0.300 - - - 87.20 87.80% Satisfactory

Madyaw Construction & Dev. Corporation 29598 Conc. of Butuan City-Talacogon-Loreto-Veruela-Sta.

Josefa Rd., Km.1357+837-Km.1359+424 08/18/12 XIII 33.474 220 O 0.388 0.240 0.108 0.030 0.050 0.033 84.90 -

Madyaw Construction & Dev. Corporation 29598 Conc. of Butuan City-Talavera-Loreto-Veruela-Sta. Josefa

Rd., Km.1354+(-874)-Km.1354+916 08/18/12 XIII 38.292 260 O 0.365 0.240 0.115 0.030 0.055 0.033 83.80 -

MAER SUMMIT KONSTRUCTS, CO. 25262 PIDP/Lupon Irrigation System 05/17/14 NIA 32.720 490 O 0.344 0.261 0.150 0.008 0.055 0.050 86.65 -

MAER SUMMIT KONSTRUKT CO. (Formerly: Summit Konstrukt) 25262

Construction/ Improvement of Access Road leading to Declared Tourism Destination, Fatimal-Parola-Cape San

Agustin Road leading to Cape San Agustin Island10/27/2014 XI 47.040 224 O 0.363 0.300 0.000 0.030 0.060 0.017 77.00% 77.00%

Unsatisfactory

MAER SUMMIT KONSTRUKT CO. (Formerly: Summit Konstrukt) 25262 Replacement/ Completion of Quarry Bridge along Mati -

Maragusan Road 10/27/2014 XI 23.520 227 O 0.392 0.300 0.006 0.030 0.060 0.017 80.50% 80.50% Unsatisfactory

MAER SUMMIT KONSTRUKT CO. (Formerly: Summit Konstrukt) 25262 Construction/Impv't. of Access Road Leading to Declared

Tourism Destinations Fatima - Parola - Cape San Agustin 8/11/2014 XI 47.040 209 OG 0.363 0.286 0.117 0.030 0.047 0.033 87.60

MAER SUMMIT KONSTRUKT CO. (Formerly: Summit Konstrukt) 25262 Road Upgrading (Gravel to Paved) Tibanban-Lavigan Road

(Brgy. Tagabebe - Brgy. Pundaguitan Section) 8/15/2014 XI 47.780 266 C 0.372 0.200 0.300 87.20 86.24% Satisfactory

MAER SUMMIT KONSTRUKT CO. (Formerly: Summit Konstrukt) 25262 Replacement of Camogna Bridge & Approaches along

Tibanban – Lavigan Road. 8/11/2014 XI 21.782 225 C 0.471 0.200 0.300 97.10 83.96% Satisfactory

Maer Summit Konstrukt Co. (Formerly: Summit Konstrukt) 25262 Road Upgrading (Gravel to Paved) Tibanban-Lavigan Rd.

(Brgy. Tagabebe - Brgy. Pundaguitan Sect.) 08/14/13 XI 47.787 203 O 0.385 0.300 0.079 0.030 0.045 0.017 85.60

Maer Summit Konstrukt Co. (Formerly: Summit Konstrukt) 25262 Rd. Upgrading (Gravel to Paved) Tibanban-Lavigan Rd.,

Km.1803+281-Km.1804+840 Nangan Sect. 08/14/13 XI 42.924 199 C 0.404 0.200 0.300 - - - 90.40 84.82% Satisfactory

Maer Summit Konstrukt Co. (Formerly: Summit Konstrukt) 25262

Road Upgrading (Gravel to Paved) Tibanban-Lavigan Rd.; a)Km. 1795+399.2-Km. 1796+171; b)Km. 1797+142-

Km1798+52508/15/13 XI 38.594 190 C 0.418 0.133 0.300 - - - 85.10 83.54%

Satisfactory

Maer Summit Konstrukt Co. (Formerly: Summit Konstrukt) 25262 Replacement of Camogna Bridge & Approaches along

Tibanban-Lavigan Rd. 08/15/13 XI 21.782 224 O 0.303 0.300 0.058 0.030 0.028 0.033 75.20

Maer Summit Konstrukt Co. (Formerly: Summit Konstrukt) 25262

Road Upgrading (Gravel to Paved) along Tibanban-Lavigan Rd. Sect., a)Km.1795+399.20-Km.1796+171; b)Km.1797+142-

Km.1798+52503/19/13 XI 38.594 167 O 0.330 0.235 0.150 0.030 0.030 0.050 82.50 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page172

Page 173: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Maer Summit Konstrukt Co. (Formerly: Summit Konstrukt) 25262 Rd. Upgrading (Gravel to Paved) along Tibanban-Lavigan

Rd. Sect., a)Km.1803+281-Km.1804+840, Nangan Sect. 03/19/13 XI 42.924 169 O 0.326 0.225 0.150 0.030 0.030 0.050 81.10 -

Maer Summit Konstrukt Co. (Formerly: Summit Konstrukt) 25262 Road Upgrading of Tibangan-Lavigan Rd., Nangan Sect. 06/08/10 XI 9.639 100 O 0.385 0.240 0.150 0.030 0.045 0.033 88.30 -

Maer Summit Konstrukt Co. (Formerly: Summit Konstrukt) 25262 Road Upgrading of Tibanban-Lavigan Rd., Luzon-Tiblawan

Sect. 06/08/10 XI 19.283 120 O 0.349 0.240 0.150 0.030 0.045 0.033 84.70 -

Maer Summit Konstrukt Co. (Formerly: Summit Konstrukt) 25262 Road Upgrading of Tibanban-Lavigan Rd., Tagabebe-

Pundaguitan Sect. 06/08/10 XI 19.279 120 O 0.332 0.240 0.150 0.030 0.045 0.050 84.70 -

Maer Summit Konstrukt Co. (Formerly: Summit Konstrukt) 25262 Construction of Multi-Purpose Building 06/05/09 XI 4.723 230 O 0.387 0.266 0.150 0.030 0.043 0.033 90.90 -

Maer Summit Konstrukt Co. (Formerly: Summit Konstrukt) 25262 Road Upgrading (Gravel to Paved) along Tibanban-Lavigan

Road 03/27/12 XI 40.189 210 C 0.446 0.200 0.300 - - - 94.60 94.00% V. Satisfactory

Maer Summit Konstrukt Co. (Formerly: Summit Konstrukt) 25262 Rehab./Reconst. Of Damaged Paved Nat'l Rd., Daang

Maharlika (MN) Km.1480+000-Km.1482+000 03/25/12 XI 14.581 127 C 0.413 0.197 0.300 - - - 91.00 89.20% V. Satisfactory

Maer Summit Konstrukt Co. (Formerly: Summit Konstrukt) 25262 Impvt./Widening of Agusan-Davao (Daang Maharlika) Pob.

Carmen & Panabo-Lasang Sect. 03/25/12 XI 29.584 195 C 0.325 0.200 0.300 - - - 82.50 88.15% Satisfactory

Maer Summit Konstrukt Co. (Formerly: Summit Konstrukt) 25262 Widening of Agusan-Davao Rd. (Daang Maharlika) Pob.

Carmen & Pob. Panabo-Lasang Sect. 03/26/12 XI 17.005 120 C 0.347 0.200 0.300 - - - 84.70 86.50% Satisfactory

Maer Summit Konstrukt Co. (Formerly: Summit Konstrukt) 25262

Const./Impvt. of Panabo Flyover (Preparation Works/Activities on the Flyover Site for the

Const./Implementation of the Panabo Flyover)11/23/12 XI 9.800 259 C 0.446 0.133 0.300 - - - 87.90 86.40%

Satisfactory

Maer Summit Konstrukt Co. (Formerly: Summit Konstrukt) 25262 Rd. Upgrading (Gravel to Paved) Tibanban-Lavigan Rd. 11/26/12 XI 43.349 241 C 0.453 0.133 0.300 - - - 88.60 84.88%

Satisfactory

Maer Summit Konstrukt Co. (Formerly: Summit Konstrukt) 25262

Const./Impvt. of Panabo Flyover (Preparation Works/Activities on the Flyover Site for the

Const./Implementation of the Panabo Flyover)08/12/12 XI 9.800 97 O 0.326 0.243 0.150 0.030 0.055 0.050 85.40 -

Maer Summit Konstrukt Co. (Formerly: Summit Konstrukt) 25262 Widening of Daang Maharlika (Agusan-Davao Rd.) Sto.

Niño-Salvacion Sect. 08/12/12 XI 21.006 120 C 0.369 0.133 0.300 - - - 80.20 84.10% Satisfactory

Maer Summit Konstrukt Co. (Formerly: Summit Konstrukt) 25262 Widening of Daang Maharlika (Agusan-Davao Rd. Panabo-

Lasang Sect. 08/12/12 XI 26.518 150 C 0.341 0.133 0.300 - - - 77.40 83.92% Satisfactory

Maer Summit Konstrukt Co. (Formerly: Summit Konstrukt) 25262 Rd. Upgrading (Gravel to Paved) Tibanban-Lavigan Rd. 08/16/12 XI 43.349 211 O 0.398 0.300 0.002 0.030 0.061 0.033 82.40 -

MAFIL BUILDERS, INC. 35845 Const. of Multi-Purpose Building for Evacuation Center, Brgy. Mandaing Cabanglasan, Bukidnon 10/24/2014 X 1.885 105 C 0.440 0.146 0.300 - - - 88.60% 88.6%

Satisfactory

MAFIL BUILDERS, INC. 35845 MajorRepair/Maintenance of Existing Permanent Bridge along Kibawe-Kadingilan Road 8/7/2014 X 4.745 60 C 0.281 0.113 0.300 69.40 69.40%

Poor

Mafil Enterprises 27226 Road Upgrading (Gravel to Paved) Jct. Dologon-Panadtalan Road 06/15/10 X 4.713 75 O 0.353 0.240 0.150 0.023 0.050 0.033 84.90 -

Maghayup Construction 21641 Malinao Service Area 07/13/13 NIA 4.592 120 O 0.270 0.300 0.150 0.020 0.070 0.030 84.00 -

Maghuyop Construction 21641 Const./Renovation/Completion/ Expansion of MPB 03/29/11 VII 0.481 150 O 0.356 0.268 0.150 0.030 0.064 0.050 91.80 -

Makapa Builders 30029 Construction of Back-up Area, RC Platform & RoRo Ramp 03/08/13 PPA 64.309 360 O 0.397 0.240 0.150 0.030 0.065 0.050 93.20 -

MAKAPA Construction 30029 Construction of Back-up Area, RC Platform and RoRo Ramp 07/19/13 PPA 64.309 360 O 0.394 0.300 0.150 0.030 0.060 0.033 96.70 -

MAKAPA CORP./ORIENT STAR CONST., INC.-J.V 9037 Bulalacao Port Expansion Project 11/06/15 PPA 108.606 420 O 0.400 0.300 0.046 0.030 0.070 0.033 87.90 -

Makapa Corporation 30029 Oas Flood Control, Busac Section 8/16/2014 V 7.789 200 C 0.341 0.200 0.300 84.10 84.10% Satisfactory

MAKAPA Corporation 30029 Construction of Back-Up Area, RC Platform and RoRo Ramp 02/27/14 PPA 65.426 419 C 0.438 0.200 0.300 - - - 93.80 94.29%

Very Satisfactory

Makapa Corporation 30029Road Upgrading (Gravel to Paved) (Intermittent Sect.), Albay West Coast Road, K0549+600-K0553+305.30 w/

exceptions03/19/13 V 52.625 240 C 0.363 0.200 0.300 - - - 86.30 88.46%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page173

Page 174: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Makapa Corporation 30029 Const./Upgrading of Malidong-Buenavista Rd. going to Tourist Destination (Butanding) 03/19/13 V 27.652 210 C 0.358 0.200 0.300 - - - 85.80 86.76%

Satisfactory

Makapa Corporation 30029Rehab./Reconst./Strengthening of Maonon Bridge along

Albay West Coast Rd., Brgy. Maonon, Ligao City K0546+658- 0564+694, Brgy. Maonon

03/19/13 V 17.319 330 C 0.383 0.171 0.300 - - - 85.40 86.33% Satisfactory

Makapa Corporation 30029Road Upgrading (Gravel to Paved) Albay West Coast Road,

K0516+584-K0516+939 & K0520+215-K0520+660, Pantao-Rawis

03/18/12 V 16.399 150 C 0.433 0.200 0.300 - - - 93.30 91.50% V. Satisfactory

Makapa Corporation 30029 Guinobatan Flood Control (Maninila, Maipon & Travesia) 08/08/12 V 28.615 210 C 0.433 0.185 0.300 - - - 91.80 91.74% V. Satisfactory

Makapa Corporation 30029 Rehab./Impvt. of Yawa River Control Boulder Dike on Steel Sheet Pile Foundation 07/31/12 V 17.194 180 C 0.473 0.072 0.300 - - - 84.50 86.54%

Satisfactory

Mak-Jay Construction 19057 Repair/Rehab./Impv't. of Acop-Kapangan-Kibungan-Bakun Rd. K0263+000-K0265+800 07/31/13 CAR 9.848 157 C 0.398 0.133 0.243 - - - 77.40 *77.40%

UnsatisfactoryMALTA CONSTRUCTION &

SUPPLY 29173 Construction of Multi Purpose Building at Brgy. Sierra 8/5/2014 III 2.654 60 C 0.417 0.133 0.300 85.00 85.00% Satisfactory

MAMSAR CONST. AND INDUSTRIAL CORP. (Formerly:

Mamsar Enterprises Agro-Industrial Corp.)

15885Preventive Maintenance Based on PMS/HDM-4

(Intermittent Section), Surigao - Davao Coastal Road, Km. 1147+(-910) - Km. 1148+000

8/13/2014 XIII 16.131 76 C 0.414 0.137 0.300 85.10 85.10% Satisfactory

MAMSAR CONST. AND INDUSTRIAL CORP. (Formerly:

Mamsar Enterprises Agro-Industrial Corp.)

6845Road Upgrading (Gravel to Paved) along Butuan City -

Talacogon - Loreto - Veruela - Sta. Josefa Road, K1389+(-407) - K1389+514 & K1389+514 - K1389+574 with Exception

8/8/2014 XIII 19.042 177 OG 0.350 0.205 0.150 0.030 0.042 0.050 82.70

MAMSAR CONSTRUCTION & INDUSTRIAL CORPORATION

(Formerly: Mamsar Enterprises Agro-Industrial Corporation)

15885

Const. & Maintenance of Bridges along National Roads: Rehab./Reconst./ Replacement/Retrofitting of Existing Permanent Bridges, (Bauyan Bridge along Malabang -

Dobleston - Tukuran Road, Lanao del Norte)

8/13/2014 X 46.484 207 OG 0.400 0.300 0.150 0.018 0.047 0.050 96.50

MAMSAR CONSTRUCTION AND INDUSTRIAL CORPORATION 15885 Replacement of Del Mores Bridge along Mabini - Tubajon

Road, Tubajon, Dinagat Islands 10/27/2014 XIII 18.222 220 O 0.337 0.300 0.000 0.020 0.056 0.033 74.60% 74.6% Poor

Mamsar Construction and Industrial Corporation 15885 Const. of Shore Protection including RC Pier /Wharf and

Reclamation Area, DPWH, RES 03/09/10 XI 106.212 400 O 0.328 0.300 0.150 0.030 0.045 0.033 88.60 -

Mamsar Construction and Industrial Corporation 15885

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd., Nat'l Arterial Rd., Daang Maharlika, Km.1135+928-

Km.1137+000 w/ exception11/21/12 XIII 19.481 263 C 0.418 0.200 0.300 - - - 91.80 88.62%

Satisfactory

Mamsar Construction and Industrial Corporation 15885 Roadslip Protection along Surigao-Agusan Rd. Sect. Brgy.

San Pablo 08/08/12 XIII 4.383 180 C 0.461 0.137 0.300 - - - 89.80 88.72% Satisfactory

Mamsar Construction and Industrial Corporation (Formerly:

Mamsar Enterprises Agro-Industrial Corporation)

15885

Const. of Iligan City Circ. Rd. (Phase II) incl. Protection Works Iligan City Circ. Road (C-3), K0+202-K0+640 (Sect. I-

Scion), K0+300-K01+600 (Sect. 2 Ubaldo Sect. w/ exception)

08/17/13 X 42.240 179 O 0.313 0.240 0.150 0.030 0.047 0.050 83.00

Mamsar Construction and Industrial Corporation (Formerly:

Mamsar Enterprises Agro-Industrial Corporation)

15885

Const. of Slope Protection along Linamon-Zamboanga Rd., Maigo, Lanao del Norte, Km.1562+577.85, Const. of

124.80m, Flood Control using Pre Cast Concrete Sheet Piles & Class A Grouted Riprap

03/15/13 X 11.905 210 C 0.415 0.144 0.300 - - - 85.90 86.08% Satisfactory

Mamsar Construction and Industrial Corporation (Formerly:

Mamsar Enterprises Agro-Industrial Corporation)

15885 Const. of Balo-i Bridge 03/13/13 X 28.545 488 C 0.434 0.163 0.300 - - - 89.70 85.47% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page174

Page 175: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Mamsar Construction and Industrial Corporation (Formerly:

Mamsar Enterprises Agro-Industrial Corporation)

15885 New Const./Completion/Continuation of Unfinished/On-going Bridge at Baloi across Agus Bridge River 03/13/13 X 19.002 348 C 0.388 0.189 0.300 - - - 87.70 83.38%

Satisfactory

Mamsar Construction and Industrial Corporation (Formerly:

Mamsar Enterprises Agro-Industrial Corporation)

15885 Reconst. of Nat'l Arterial Rds. (Intermittent Sect.), Surigao-Davao Coastal Rd., Brgy. Pananay-an 03/14/13 XIII 6.741 45 O 0.292 0.300 0.150 0.030 0.045 0.033 85.00 -

Mamsar Construction and Industrial Corporation (Formerly:

Mamsar Enterprises Agro-Industrial Corporation)

15885Rehab./Reconst./Upgrading along Misamis Oriental-Ma.Cristina Bdry. Road Iligan City Central Section,

Sta.1525+619.7 - Sta.1526+083.207/07/10 X 13.899 148 O 0.388 0.240 0.150 0.030 0.055 0.050 91.30 -

Mamsar Construction and Industrial Corporation (Formerly:

Mamsar Enterprises Agro-Industrial Corporation)

15885 Const. of Balo-i Bridge 11/27/12 X 74.275 612 C 0.500 0.133 0.300 - - - 93.30 88.17% Satisfactory

Mamsar Construction and Industrial Corpration (Formerly:

Mamsar Enterprises Agro-Industrial Corporation)

15885 Reconst. of Nat'l Arterial Rd. (Int. Sect.), Surigao-Davao Coastal Rd., Brgy. Pananay-an 08/08/13 XIII 6.741 45 C 0.390 0.133 0.300 - - - 82.30 83.92%

Satisfactory

Manuel A. Dela Torre, Jr. Builders 31024 Repair & Maint. of Slope Protection along Buga Creek 03/20/13 III 1.960 80 C 0.433 0.133 0.300 - - - 86.60 84.56% Satisfactory

Marbel Dynamic Builders 6150 Const. of Reinforced Concrete Box Culvert Rd.-CLS Rd., Brgy. Cabuling 08/06/13 XII 4.290 120 C 0.434 0.133 0.300 - - - 86.70 90.30% V.

Satisfactory

Marbel Dynamic Builders 6150 Const. of Reinforced Concrete Box Culvert-CLS Rd., Brgy. Cabuling 03/20/13 XII 4.290 120 O 0.359 0.300 0.150 0.030 0.055 0.033 92.70 -

Marbel Dynamic Builders 6150 Completion of MPB at Brgy. Pob., Malapatan 08/21/12 XII 0.995 100 C 0.500 0.133 0.300 - - - 93.30 89.87% V. Satisfactory

Marcbilt Construction, Inc. 21844Widening of Cavite-Batangas Road, Silang Seciton

Including Drainage System, K0041+000 to K0041+730, 5th Legislative District

8/5/2014 IV-A 22.373 171 OG 0.386 0.300 0.000 0.030 0.059 0.033 80.80

Marcbilt Construction, Inc. 21844 Prev. Maint. (MFO-1) Asphalt Overlay w/ Corrections along Silang Bypass Rd., K0042+000-K0042+929 08/13/13 IVA 23.359 90 C 0.462 0.133 0.300 - - - 89.50 *89.50% V.

Satisfactory

Marcbilt Construction, Inc. 21844 Asphalt Overlay of Lucena-Tayabas-Mauban Port Rd., K0128+(-972)-K0128+000 08/03/13 IVA 6.492 140 C 0.467 0.133 0.300 - - - 90.00 89.88% V.

Satisfactory

Marcbilt Construction, Inc. 21844 Const. of Manila-Cavite Coastal Rd. (Service Rd.) 03/21/13 NCR 36.789 328 C 0.451 0.107 0.300 - - - 85.80 86.22% Satisfactory

Marcbilt Construction, Inc. 21844 Asphalt Overlay of Lucena-Tayabas-Mauban Port Rd., K0128+(-)972-K0128+000 03/16/13 IVA 6.492 140 O 0.340 0.300 0.150 0.030 0.045 0.033 89.80 -

Marcbilt Construction, Inc. 21844 Const. (Opening/Widening/Conc.) of CALA-Daang Hari Rd. Bdry. (Pasong Buwaya 2 Sect. 05/31/10 IVA 37.952 215 O 0.349 0.300 0.150 0.030 0.045 0.033 90.70 -

Marcbilt Construction, Inc. 21844Road Upgrading (gravel to paved), MWCR, Sablayan-Sta.

Cruz (Buenavista-Sto. Nino Section) KO 322+594- KO 323+465.65 to KO 323+622-KO 324+472

08/31/09 IVB 19.300 140 O 0.351 0.292 0.150 0.030 0.042 0.033 89.80 -

Marcbilt Construction, Inc. 21844 Road Upgrading (gravel to paved), MWCR, (San Francisco Section) KO 332+300- KO 334+755 08/30/09 IVB 28.659 165 O 0.337 0.300 0.150 0.030 0.042 0.033 89.20 -

Marcbilt Construction, Inc. 21844 Road Upgrading (Gravel to Paved) MWCR, (San Francisco Section) 05/29/09 IV-B 28.659 150 O 0.303 0.300 0.150 0.030 0.035 0.050 86.80 -

Marcbilt Construction, Inc. 21844 Road Upgrading (Gravel to Paved) MWCR, Sablayan-Sta. Cruz (Buenavista-Sto. Nino Section) 05/29/09 IV-B 19.112 140 O 0.305 0.290 0.150 0.030 0.025 0.050 85.00 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page175

Page 176: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Marcbilt Construction, Inc. 21844 Rehab./Reconst. (Conc.) of Dasmariñas-Carmona Road 11/12/08 IV-A 28.920 180 O 0.341 0.202 0.100 0.030 0.037 0.100 81.00 -

Marcbilt Construction, Inc. 21844Rehab./Reconst./Upgrading of Damaged Paved Nat'l Road

(MFO-2) along Indang-Alfonso via Luksuhin Road, K00259+947-K0060+923

03/20/12 IVA 14.084 184 C 0.481 0.133 0.300 - - - 91.40 89.78% V. Satisfactory

MARCBILT CONSTRUCTION, INC./MIRASOL M. MEDINA 

CONSTRUCTION & TRADING (JV)‐ Widening of Convento Bridge along Naic Junction-

Caylabne Road 11/7/2014 IV 21.681 255 O 0.359 0.300 0.150 0.030 0.035 0.033 90.70% 90.7% Very Satisfactory

MARCBILT CONSTRUCTION, INC./SAN MARCELINO BUILDER, INC. (JV) JV-13-281

Road Upgrading ( Gravel to Paved) based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road Standard (HDM- 4 Project Analysis Intermittent

Secion) Secondary Road, JCT. MWCR (Baging Silang)-Cabacao Diversion Road, K0425+690-K0427+059

11/25/2014 IV 41.998 239 C 0.282 0.286 0.080 - - - 76.60% 76.6% Unsatisfactory

Marcbilt Construction, Inc./San Marcelino Builders, Inc. Joint

Venture21844

Preventive Maintenance (Asphalt Overlay) along Lucena-Tayabas-Lucena-Sampaloc-Mauban Port Road, K0140+042

to K0141+565 and k0143+475 to K0144+4558/14/2014 IV-A 36.518 69 C 0.449 0.200 0.300 94.90 94.90%

Very Satisfactory

Marcbilt Construction, Inc./San Marcelino Builders, Inc. Joint

VentureJV-13-281

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road Standards (HDM-4 Project Analysis), Secondary

Road, Jct. MWCR (Bagong Silang) - Cabacao Diversion Road, K0425+633.7 - K0427+746

8/14/2014 IV-B 38.757 209 OG 0.369 0.237 0.150 0.030 0.045 0.033 86.40

Marcons Builder 8044 Const. of MPB, Caba NHS, Pob. Norte 08/01/13 I 4.914 238 C 0.474 0.133 0.300 - - - 90.70 88.74% Satisfactory

Marcons Builder 8044 Const. of Mpb, Caba NHS, Pob. Norte 03/12/13 I 4.699 238 O 0.395 0.300 0.150 0.010 0.032 0.033 92.00 -

Marcons Builder 8044Const. (Road Opening) of Missing Links of National Road, Sallapadan-Tubo, Abra-Cervantes, Ilocos Sur, Abra Side,

Km.467+100 - Km.484+00003/30/11 CAR 65.204 470 O 0.317 0.272 0.150 0.020 0.027 0.033 81.90 -

Marcons Builder 8044 Const. of DPWH Regional Office Building, Phase V 03/13/09 CAR 24.058 360 O 0.361 0.276 0.150 0.030 0.056 0.033 90.60 -Marcons Builder 8044 Const. of DPWH Regional Office Building (Phase V) 08/29/08 CAR 24.059 360 O 0.376 0.300 0.100 0.030 0.047 0.100 95.30 -

Marcons Builder 8044 Completion/Continuation of Perimeter Fence @ Burnham Park 08/16/12 CAR 19.271 120 C 0.451 0.170 0.300 - - - 92.10 74.74%

PoorMarcons Builder 8044 Const. of MPB, Caba Nat'l High Sch., Pob. Norte 11/25/12 I 4.699 238 O 0.317 0.300 0.150 0.020 0.018 0.033 83.80 -

Marcons Builders 8044Const. (Road Opening) of Missing Links of Nat'l Rd.

Sallapadan-Tubo, Abra-Cervantes, Ilocos Sur, Abra Side Km.467+100-Km.484+000

08/03/11 CAR 65.204 470 O 0.292 0.238 0.150 0.023 0.033 0.033 76.90 -

Marcris Enterprises 32820 Const./Impv't./Rehab. of FMR, Brgy. Cabanbanan 03/16/13 I 1.473 60 C 0.374 0.133 0.300 - - - 80.70 *80.70% Unsatisfactory

MARCUS CONSTRUCTION 12601Flood Control Structure at USM (Phase 2) along Kabacan River, USM, Kabacan, Cotabato Km. 1649+105.41 - Km.

1649+16010/25/2014 XII 11.759 178 C 0.473 0.133 0.300 - - - 90.60% 90.6%

Very Satisfactory

MARCUS CONSTRUCTION 12601

Widening of Road along Davao - Cotabato - Road Katidtuan - Osias Section, Kabacan, Cotabato, Km. 1644+(-

232) - Km. 1644+463.36 and Km. 1644+495.20 - Km. 1646+280 both sides

10/25/2014 XII 47.241 178 C 0.472 0.133 0.300 - - - 90.50% 90.5% Very Satisfactory

MARCUS CONSTRUCTION 12601 Widening of Road Davao-Cotabato Road, Katidtuan - Osias Section, Cotabato Road 8/11/2014 XII 47.241 178 OG 0.329 0.297 0.150 0.030 0.050 0.050 90.60

Marcus Construction 12601 Rehab./Impvt. of Bukidnon-Cotabato National Road (Tambad Sect.), Brgy. Tambad 09/03/09 XII 57.136 289 O 0.368 0.300 0.150 0.030 0.033 0.033 91.40 -

Marcus Construction 12601 Const. of Slope Protection Works along Dualing-New Panay-Midsayap Road (Arizona Section) 09/04/09 XII 9.407 206 O 0.400 0.240 0.150 0.010 0.042 0.033 87.50 -

Marcus Construction 12601Rehab./Replacement of Grebona Bridge along Banisilan-

Guiling-Alamada-Libungan Road (Completion of Grebona-Libungan, Cotabato, Km.1697+207)

03/22/12 XII 10.527 180 C 0.473 0.133 0.300 - - - 90.60 88.26% Satisfactory

Marcus Construction 12601 Completion of Ugalingan Flood Control along Bukidnon-Cotabato Rd., Ugalingan 03/18/13 XII 11.500 157 C 0.410 0.133 0.300 - - - 84.30 *84.30%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page176

Page 177: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

MAR-DEB Construction & Development 6718

Preventive Maintenance (Intermittent Section) along Santiago-Tuguegarao Road, K0410+123 to K0410+577;

K0416+246 to K0417+2428/9/2014 II 20.380 133 C 0.464 0.131 0.300 89.50 89.50%

Very Satisfactory

MAR-DEB Construction & Development 6715 Repair/Improvement of Cagayan Rver Control, Dabburab 8/11/2014 II 28.849 230 C 0.298 0.200 0.300 79.80 83.10%

SatisfactoryMar-Deb Construction &

Development 6715 Repair/Impv't. of Cagayan River Control, Dabburab 08/07/13 II 28.850 200 O 0.355 0.240 0.150 0.030 0.045 0.033 85.30

Mar-deb Construction & Development 6715 Con. of Jct. Ipil-Quirino Bdry. Rd. San Agustin, Isabela,

K0371+780-K0374+276 (w/ exceptions) Dappig-Laoag 03/15/13 II 17.179 180 C 0.449 0.133 0.300 - - - 88.20 90.36% V. Satisfactory

Mar-deb Construction & Development 6715 Const. of Riverbank Protection Works, San Isidro & Sto.

Domingo 03/19/13 II 11.626 240 C 0.329 0.200 0.300 - - - 82.90 87.76% Satisfactory

Mar-deb Construction & Development 6715 Repair/Rehab. of Macalaoat Bridge along Santiago-

Tuguegarao Rd. 03/19/13 II 17.576 225 C 0.437 0.133 0.300 - - - 87.00 87.48% Satisfactory

Mar-Deb Construction & Development 6715 Rehab./Reconst./Upgrading of Damaged Paved National

Rd. KO 369+(-297) - KO 370+000 w/ exception 06/02/10 II 9.816 120 O 0.379 0.247 0.150 0.030 0.051 0.050 90.70 -

Mar-Deb Construction & Development 6715 Completion of Turod-Banquero Concrete Overflow Bridge

PhaseIII 08/14/08 II 9.879 300 O 0.351 0.260 0.000 0.030 0.037 0.100 77.80 -

Mar-deb Construction & Development 6715 Ilot Bridge along Daang Maharlika 11/27/12 II 13.301 195 C 0.457 0.133 0.300 - - - 89.00 87.74%

SatisfactoryMar-deb Construction &

Development 6715 Const. of Sch. Bldg. (Phase II), Cagayan NHS (Main) 11/20/12 II 1.151 120 C 0.408 0.142 0.300 - - - 85.00 83.32% Satisfactory

Mar-deb Construction & Development 6715

Prev. Maint. (IS) along Daang Maharlika: a)K0391+050-K0392+900; b)K0389+990-K0391+(-149); & c) K0388+330-

K0388+81008/09/12 II 35.056 180 C 0.396 0.200 0.300 - - - 89.60 89.06% V.

Satisfactory

Mar-deb Construction & Development 6715 Ilot Bridge along Daang Maharlika 08/11/12 II 12.456 195 O 0.354 0.240 0.150 0.030 0.045 0.050 86.90 -

MAR-DEB CONSTRUCTION DEVELOPMENT 6715

Preventive Maintenance Based on Pavement System/Highway Development Management-4 (HDM-4) MFO-1 along Santiago-Tuguegarao Road, KO360+000 -

KO360+758

10/25/2014 II 5.310 60 C 0.447 0.133 0.300 - - - 88.00% 88% Satisfactory

Margarita Construction 20201 Replacement/Rehab./Strengthening of Viente Reales Bridge 08/13/13 NCR 4.914 150 C 0.399 0.133 0.300 - - - 83.20 *83.20%

SatisfactoryMargarita Construction 20201 Rehab. of Sta. Maria-By Pass Road 09/07/09 III 4.757 100 O 0.357 0.240 0.150 0.030 0.042 0.033 85.20 -

Margarita Construction 20201 Repair/Rehab./Impvt. of G. Lazaro St., (Phase II) Chainage 335.00-Chainage 531.00 w/ exceptions 03/18/13 NCR 4.702 90 C 0.443 0.135 0.300 - - - 87.80 *87.80%

Satisfactory

Marie-Kris Construction & Trading 32418 Conc./Drainage Impv't. of Rds., Alleys & Pathwalks, Maaralin St., Brgy Central 08/05/13 NCR 5.123 105 C 0.420 0.133 0.300 - - - 85.30 *85.30%

Satisfactory

MARK ANTHONY CONSTRUCTION & SUPPLY 34057 Construction of Magdug Flood Control 10/27/2014 XI 3.995 50 C 0.428 0.133 0.300 - - - 86.10% 86.1%

Satisfactory

MARK ANTHONY CONSTRUCTION & SUPPLY 34057

Construction of Pundaguitan Flood Control Governor Generoso davao Oriental Protecting Tibanban-Lavigan

Road8/11/2014 XI 2.995 50 C 0.429 0.133 0.300 86.20 86.20%

Satisfactory

Mark Anthony Construction & Supply 34057 Rehab./Impv't. of Rd., Purok Roads 03/19/13 XI 4.995 37 O 0.336 0.240 0.150 0.030 0.048 0.050 85.40 -

Mark Anthony Construction & Supply 34057 Const. of Sanghay Brgy. Bridge 03/19/13 XI 2.999 90 C 0.285 0.190 0.300 - - - 77.50 81.88%

Unsatisfactory

MARKBILT CONSTRUCTION 12522 Sta. Josefa Pump Irrigation Project 08/30/14 NIA 204.785 1,097 O/Expired 0.360 0.271 0.000 0.008 0.023 0.050 71.19 -

Markbilt Construction 12522 Const. of Small Reservoir Irrigation Project - Masidem Dam (Dam) 05/2-7/11 NIA 192.198 1,098 O 0.384 0.272 0.150 0.030 0.025 0.050 91.05 -

Marknest Construction and Trading (Formerly: Marknest Const.) 16818 Road Upgrading of Mt. Arayat Park Road 05/19/09 III 11.429 90 O 0.356 0.300 0.150 0.020 0.033 0.050 90.90 -

Marquin Construction 13332 Const. of 2-CL SB on top of the existing SB at Compostela NHS 09/14/09 VII 2.234 120 O 0.383 0.240 0.150 0.030 0.035 0.025 86.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page177

Page 178: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Marquin Construction 13332 Construction of 2-CL SB at Mohon NHS 09/14/09 VII 1.212 120 O 0.332 0.240 0.150 0.030 0.035 0.025 81.20 -

MARRA BUILDERS 8784 TACLOBAN PORT IMPROVEMENT/ REHABILITATION PROJECT PHASE 2 06/26/15 PPA 235.500 480 C 0.495 0.200 0.300 - - - 99.52 99.53%

Outstanding

MARRA BUILDERS 8784 Tacloban Port Improvement/ Rehabilitation Project Ph-2 08/22/14 PPA 235.500 480 O 0.395 0.300 0.150 0.030 0.070 0.050 99.50 -

MARRA BUILDERS 8784 CONSTRUCTION OF BACK-UP AREA 04/04/14 PPA 195.531 540 C 0.478 0.200 0.300 - - - 97.78 98.93% Outstanding

Marra Builders 8784 Construction of Back-up Area 02/08/13 PPA 181.414 540 O 0.396 0.300 0.150 0.030 0.070 0.050 99.60 -

Marra Builders, Inc. 8784 Tacloban Port Improvement/ Rehabilitation Project 12/5-8/11 PPA 375.906 720 O 0.399 0.300 0.150 0.030 0.070 0.050 99.85 -

Marra Builders, Inc. 8784 Construction of Back-up Area 06/28/13 PPA 181.414 540 C 0.398 0.300 0.150 0.030 0.070 0.050 99.80 -

Marra Builders, Inc. 8784 Tacloban Port Improvement / Rehabilitation 05/31/12 PPA 375.906 720 O 0.394 0.300 0.150 0.030 0.070 0.050 99.42 -

Marra Builders, Inc. 8784 Tacloban Port Improvement / Rehabilitation Project 10/11/12 PPA 375.906 720 C 0.482 0.200 0.300 - - - 98.21 98.71% Outstanding

Mar-Vel Construction & Supply 23722Construction of Bridges RCBC (Reinforced Concrete Box

Culvert), Barangay San Ignacio, San Pablo City along Daang Maharlika (LZ)

8/15/2014 IV-A 12.276 206 OG 0.391 0.300 0.150 0.022 0.040 0.033 93.60

MAR‐VEL CONSTRUCTION & SUPPLY (Formerly: Mar‐Vel Construction) 23722 Widening of Permanent Bridge, Masapang Bridge 2, along

Calamba-Sta. Cruz-Famy Jct. Road 11/27/2014 IV 8.280 208 C 0.444 0.200 0.300 - - - 94.40% 94.4% Very Satisfactory

Mar-vel Construction & Supply (Formerly: Mar-vel Construction) 23722 Const. of Two Storey - Four CL School Bldg. at Cavite

National High School 06/01/10 IVA 4.801 169 O 0.395 0.300 0.052 0.030 0.029 0.050 85.60 -

Mar-Vel Construction & Supply/ C.T. Leoncio Construction &

Trading (JV)JV-13-503

Widening of Sta. Rosa - Ulat - Tagaytay Road, K0045+500 to K0047+850 (with Exception) including RROW

acquisition8/9/2014 IV-A 45.325 240 OG 0.356 0.300 0.150 0.020 0.052 0.033 91.10

MASBATE-ILOILO CONSTRUCTION 26579 Const. of Managopaya CIP 04/05/14 NIA 2.600 90 C 0.466 0.164 0.000 - - - 63.00 63.00% Poor

MASBATE-ILOILO CONSTRUCTION & TRADING CORP. 26579

Replacement/Rehab./Strengthening of Permanent Bridge Management System (BMS) Construction of Siwalo Bridge

along Mandurriao - San Miguel - Alimodian - Maasin - Cabatuan Road Brgy. Siwalo, K0030+001.60 -

K0030+013.60

8/15/2014 VI 5.253 181 C 0.355 0.200 0.300 85.50 84.6% Satisfactory

Masbate-Iloilo Construction & Trading Corp. 26579

Replacement/Rehab./Strengthening of Permanent Bridge Mgt. System (BMS), Const. of Siwalo Bridge along

Mandurriao-San Miguel-Alimodian-Maasin-Cabatuan Rd., Brgy. Siwalo, K030+001.6-K0030+013.6

08/20/13 VI 4.957 170 O 0.347 0.238 0.150 0.030 0.042 0.033 84.00

Masbate-Iloilo Construction & Trading Corp. 26579 Repair/Maint. of Jalaur River Control, Sta.0+000-

Sta.0+015.50 (15.50 L.M.) 03/23/13 VI 1.858 110 C 0.333 0.200 0.300 - - - 83.30 *83.30% Satisfactory

MASULOT CONSTRUCTION 10716Road Upgrading (Gravel to Paved) along Demoloc-Little

Baguio-Alabel Road, km. 1636+043.582 to km. 1637+113.30 Abbes-San Roque Section

8/7/2014 XI 30.966 179 OG 0.009 0.300 0.000 0.030 0.020 0.000 35.90

Masulot Construction 10716Rd. Upgrading (Gravel to Paved) along Demoloc-Little Baguio-Alabel Rd., Km.1636+043.582-Km.1637+113.30

Abbes-San Roque Sect.08/08/13 XI 30.966 179 O 0.073 0.300 0.150 0.030 0.030 0.033 61.60

Masulot Construction 10716Rd. Upgrading (Gravel to Paved) along Demoloc-Little Baguio-Alabel Rd,. Km.1636+043.582-Km.1637+113.30

Abbes-San Roque Sect.03/14/13 XI 30.966 179 O 0.242 0.236 0.150 0.030 0.032 0.050 74.00 -

Masulot Construction 10716Prev. Maint. (Int. Sect.) along Davao-Sarangani Coastal Rd., Km.1584+067-Km.1585+000 (w/ exception) Digos-Makar Rd., Km.1584+067-Km.1585+000 (w/ exception)

03/13/13 XI 10.666 28 O 0.306 0.200 0.000 0.010 0.032 0.000 54.80 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page178

Page 179: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Masulot Construction 10716Const. of Sabang Bridge along Arakan-Analopon-Napaliko-Katipunan Road (Steel Truss Component to be supplied by

others)09/05/09 XII 9.217 150 O 0.336 0.300 0.000 0.010 0.028 0.033 70.70 -

Masulot Construction 10716 Const. of Kidapawan-Magpet-Pangao-An Road, Mateo-Gubatan Sect.) 09/05/09 XII 30.527 250 O 0.307 0.290 0.000 0.010 0.033 0.033 67.30 -

Masulot Construction 10716 Const. of Kidapawan-Magpet-Pangao-an Road, Mateo-Gubatan Section 06/01/09 R-XII 30.528 250 O 0.292 0.300 0.000 0.024 0.050 0.033 69.90 -

Masulot Construction 10716 Const. of Sabang Bridge along Arakan-Anapolon-Napaliko-Katipunan Road 05/30/09 R-XII 9.218 150 O 0.308 0.300 0.000 0.018 0.035 0.033 69.40 -

Masulot Construction 10716Const. (Opening) of Missing Links at Tubalan-Pangian-Pinalpalan-Alabel Road, Malita-Jose Abad Santos Road,

Tubalan Section05/28/09 XI 19.089 115 O 0.400 0.300 0.150 0.022 0.028 0.033 93.30 -

Masulot Construction 10716 Road Upgrading of Mati-Maragusan Road (Buso-Taguibo Section) 06/05/09 XI 15.429 100 O 0.315 0.300 0.150 0.030 0.037 0.033 86.50 -

Masulot Construction 10716 Road Upgrading of Mati-Maragusan Road (Don Martin Marundan-Menzi Section) 06/05/09 XI 19.289 120 O 0.313 0.300 0.150 0.030 0.037 0.033 86.30 -

Masulot Construction 10716 Rehab./Recons./Upgrading of Digos-Makar Road, Kiblagon-Tagansule Section, Km. 1584+000-Km. 1584+750 05/28/09 XI 9.649 180 O 0.363 0.237 0.150 0.030 0.037 0.033 85.00 -

Masulot Construction 10716 Road Upgrading (Gravel to Paved) Demoloc-Little Baguio-Alabel Road, Km.1637+113.30-Km.1638+180 03/21/12 XI 23.548 120 O 0.400 0.263 0.150 0.020 0.028 0.033 89.40 -

Masulot Construction 10716Rehab./Reconst. of Damaged Paved of Nat'l Road along

Cotabato City Circ.Road (Western Sect.), K1867+000-K1867+1880 / K1859+641.45-K1860+641.45

03/19/12 XII 27.818 260 O 0.315 0.240 0.150 0.030 0.059 0.050 84.40 -

MASULOT CONSTRUCTION/RAQI BUILDER CONSTRUCTION &

SUPPLY (J.V.)10716

Road Upgrading (Gravel to Concrete) at Isulan Hwy Jct. Dukay-Bagumbayan-Sen. Ninoy Aquino-Kalamansig Road

(Km. 1852+917 - 10/27/2014 XII 38.966 133 O 0.357 0.242 0.025 0.030 0.050 0.050 75.40% 75.4%

Unsatisfactory

Maverick & Wee Eng Joint Venture JV-07-105 CP 8: Impvt./Conc. of Surigao Sur-Davao Oriental Coastal Road (Manay-Boston) Baganga-Cateel Section 11/25/08 XI 191.290 597 O 0.381 0.240 0.100 0.030 0.060 0.100 91.10 -

Maverick & Wee Eng Joint VentureSL1-SN-

005102/JV-07-105

Impvt./Conc. of Surigao Sur-Davao Oriental Coastal Road (Manay Boston) Banganga-Cateel Section 06/09/09 XI 191.222 597 O 0.368 0.255 0.150 0.030 0.060 0.050 91.30 -

Maverick Builders Inc. / Wee Eng Construction, Inc. Joint Venture JV-11-425 Const. of Flood Control at Padada River Guihing 11/23/12 XI 62.511 228 C 0.400 0.200 0.300 - - - 90.00 88.62%

Satisfactory

Maverick Builders Incorporated 14460 Rehab./Impvt. of Manay-Mati Section along Surigao Sur-Davao Oriental Coastal Road, Badas-Baso Section 06/05/09 XI 48.132 161 O 0.381 0.300 0.150 0.030 0.051 0.033 94.50 -

Maverick Builders Incorporated 14460 Rehab./Impvt. of Manay-Mati Section along Surigao Sur-Davao Oriental Coastal Road, (Dawan-Tagamot Section) 06/05/09 XI 71.995 210 O 0.380 0.300 0.150 0.030 0.047 0.033 94.00 -

Maverick Builders Incorporated 14466 Rehab./Recons./Upgrading of Damaged Paved National Roads, for Package 1-A: a) Matina-Harana Section 06/11/09 XI 19.284 210 O 0.360 0.300 0.150 0.030 0.051 0.033 92.40 -

Maverick Builders Incorporated 31666 Concreting of Compostela-Cateel Road 06/08/09 XI 67.990 590 O 0.341 0.236 0.150 0.030 0.042 0.050 84.90 -

MAVERICK BUILDERS INCORPORATED (Formerly:

Maverick Builders)14466 Const. of Sta. Fe Bridge along Surigao del Sur Bdry. -

Davao Oriental Coastal Road 10/29/2014 XI 17.504 192 C 0.412 0.131 0.300 - - - 84.30% 84.3% Satisfactory

MAVERICK BUILDERS INCORPORATED (Formerly:

Maverick Builders)14466 Cluster I - Repair/Maint. of (Inst. of Fender Piles) at Bridges

along Surigao del Sur Bdry. - Davao Oriental 10/29/2014 XI 14.290 151 C 0.482 0.133 0.300 - - - 91.50% 91.5% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page179

Page 180: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

MAVERICK BUILDERS INCORPORATED (Formerly:

Maverick Builders)14466

Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Road Including Drainage along Digos-

Makar Road (KO 1576+001 - KO 1577+705)10/23/2014 XI 31.338 136 C 0.443 0.133 0.300 - - - 87.60% 87.6%

Satisfactory

MAVERICK BUILDERS INCORPORATED (Formerly:

Maverick Builders)14466

Improvement/Upgrading Const./Impv’t. of Access Road leading to Declared Tourism Destination Jct. Menzi-

Dahican-Lawigan Section Road, with leading to Cinco Masao Beach Resort (Dahican Lawigan Section)

8/11/2014 XI 38.149 220 OG 0.300 0.300 0.137 0.030 0.043 0.050 86.00

Maverick Builders Incorporated (Formerly: Maverick Builders) 14466

Widening of Digos-Makar Rd. (Balutakay-Jct. Hagonoy Sect.) K1569+000-K1569+882 realigned to Widening of Digos-Makar Rd. (Balutakay-Junction Hagonoy Sect.)

K1569+000-K1569+807

08/09/13 XI 18.992 93 C 0.414 0.133 0.300 - - - 84.70 *84.70% Satisfactory

Maverick Builders Incorporated (Formerly: Maverick Builders) 14466 Widening of Pres. Diosdado P. Macapagal Highway 08/18/13 XI 89.304 515 C 0.394 0.200 0.300 - - - 89.40 86.34%

Satisfactory

Maverick Builders Incorporated (Formerly: Maverick Builders) 14466 Impv't./Upgrading (Gravel to Concrete) along Jct. Menzi-

Dahican-Lawigan Rd. (Dahican-Lawigan Sect.) 08/18/13 XI 93.624 297 C 0.357 0.200 0.300 - - - 85.70 83.12% Satisfactory

Maverick Builders Incorporated (Formerly: Maverick Builders) 14466 Impv't./Upgrading (Gravel to Concrete) along Jct. Menzi-

Dahican-Lawigan Rd., Dahican-Lawigan Sect. 03/19/13 XI 93.624 237 O 0.325 0.236 0.150 0.030 0.040 0.033 81.40 -

Maverick Builders Incorporated (Formerly: Maverick Builders) 14466 Asphalt Overlay/Repair & Rehab. of Tibanban-Lavigan

Road, Km.1775+000 - Km.1775+740 w/ exception 08/19/11 XI 1.643 40 O 0.380 0.200 0.150 0.030 0.059 0.050 86.90 -

Maverick Builders Incorporated (Formerly: Maverick Builders) 14466 Widening of Digos-Makar Rd. (Km. 1568+(- 447)-Km.

1568+553; Km. 1577+(-)010-Km. 1578+035 11/22/12 XI 45.181 181 C 0.463 0.133 0.300 - - - 89.60 88.88% Satisfactory

Maverick Builders Incorporated (Formerly: Maverick Builders) 14466 Widening of Digos-Makar Rd. (Km.1568+(-447)-

Km.1568+553; Km.1577+(-010)-Km.1578+035 08/11/12 XI 45.307 165 O 0.369 0.225 0.150 0.030 0.060 0.050 88.40 -

Maverick Builders Incorporated (Formerly: Maverick Builders) 14466

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. along Digos-Makar Rd., Sect. 1: Sta.1569+000-

Sta.1571+070; Sect. 2: Sta.1573+000-Sta.1576+000; Sect. 3: Sta.1571+070-Sta.1571+474.249

08/11/12 XI 74.107 300 C 0.351 0.200 0.300 - - - 85.10 85.82% Satisfactory

Maverick Builders Incorporated (Formerly: Maverick Builders) 14466 Asphalt Overlay/Repair & Rehab. of Jct. Manikling, Brgy.

Pob. 08/15/12 XI 8.240 120 C 0.414 0.133 0.300 - - - 84.70 84.82% Satisfactory

Maverick Builders Incorporated (Formerly: Maverick Builders) 14466 Widening of Pres. Diosdado Macapagal Highway 08/10/12 XI 89.304 214 O 0.338 0.298 0.084 0.030 0.060 0.033 84.30 -

Maverick Builders Incorporated / Wee Eng Construction, Inc. (JV) JV-11-425 Const. of Flood Control at Padada River (Downstream)

Guihing 03/17/13 XI 32.599 212 C 0.374 0.200 0.300 - - - 87.40 88.48% Satisfactory

Maverick Builders Incorporated/Wee Eng Construction Inc., (JV)

JV-11-425 Const. of Flood Control at Padala River, Guihing 08/10/12 XI 62.511 212 O 0.382 0.282 0.090 0.030 0.060 0.033 87.70 -

Maverick Builders, Incorporated 14466 Concreting of Compostela-Cateel Road 09/12/09 XI 69.384 590 O 0.265 0.300 0.150 0.030 0.047 0.033 82.50 -

Maverick Builders, Incorporated (Formerly: Maverick Builders) 14466 Conc. of Compostela-Cateel Road 03/09/09 XI 67.990 590 O 0.266 0.300 0.150 0.030 0.032 0.050 82.80 -

Maverick Builders, Incorporated (Formerly: Maverick Builders) 14466 Rehab./Impv't. of Manay-Mati Sect. along Surigao Sur-

Davao Oriental Coastal Road, Badas-Baso Section 03/11/09 XI 48.132 161 O 0.388 0.300 0.150 0.030 0.059 0.050 97.70 -

MAXNELL ENTERPRISES 7170 Completion of Engineering Building at University of Antique (Main Campus), Sibalom, Antique 8/13/2014 VI 4.984 90 OG 0.355 0.300 0.000 0.030 0.023 0.000 70.80

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page180

Page 181: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Maxnell Enterprises 7170 Completion of Eng'g Bldg. at University of Antique, (Main Campus) 08/15/13 VI 4.984 60 O 0.295 0.240 0.150 0.030 0.027 0.033 77.50

Mayhaligue Construction 29586 Colocol Integrated CIS Rehabilitation & Extension Project 05/12/12 NIA 2.383 206 C 0.408 0.200 0.300 - - - 90.82 91.01% V. Satisfactory

MAYHALIGUE Construction 29586 Colocol Integrated CIS Rehabilitation & Extension Project 10/24-29/11 NIA 3.477 120 O 0.367 0.284 0.150 0.030 0.033 0.050 91.42 -

MB Eclar Trading & Construction 32118Const. of Shore Protection/Flood Control in La Union 2nd

District Rock Bulkhead & Slope Protection, Brgy. San Nicolas West

07/31/13 I 16.878 180 C 0.400 0.133 0.300 - - - 83.30 88.28% Satisfactory

MB Eclar Trading & Construction 32118 Const. of 3-Storey, 9-Cl and 2-Storey, 4-Cl Sch. Bldg., Naguilian NHS 08/01/13 I 14.599 210 O 0.370 0.240 0.150 0.030 0.033 0.033 85.60

MB Eclar Trading & Construction 32118Const. of Shore Protection/Flood Control in La Union 2nd

Dist. Rock Bulkhead & Slope Protection, Brgy. San Nicolas West

03/12/13 I 16.879 180 O 0.393 0.300 0.150 0.010 0.030 0.033 91.60 -

MB Eclar Trading & Construction 32118 Const. of Rock Groins, Brgy. Alaska 03/12/13 I 22.546 163 O 0.365 0.300 0.150 0.015 0.014 0.033 87.70 -

MB Eclar Trading & Construction 32118 Repair/Rehab. of Principe River Control 03/12/13 I 17.405 280 C 0.330 0.200 0.300 - - - 83.00 85.46% Satisfactory

MB Eclar Trading & Construction 32118 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds., K0229+736-K0231+865 MNR 11/25/12 I 42.304 210 C 0.423 0.200 0.300 - - - 92.30 90.14%

V. Satisfactory

MB Eclar Trading & Construction 32118 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds., K0229+736-K0231+865 MNR 08/09/12 I 42.304 210 O 0.344 0.300 0.150 0.020 0.040 0.033 88.70 -

MBB Construction 11363 Santa Flood Control along Manila North Road 8/12/2014 I 17.106 392 C 0.361 0.200 0.300 86.10 84.57% Satisfactory

MBB Construction 11363 Rehab./Reconst./ Upgrading of Quirino-Panda Road a) K0407+(-480) to K0407+845, b) K0408+776 to K0409+235 8/6/2014 I 31.337 206 C 0.489 0.200 0.030 71.90 82.04%

Satisfactory

MBB Construction 11363 Rehab./Reconst./Upgrading of Quirino-Pandan Rd. a)K0407+(-480)- K0407+845, b)K0408+776-K0409+225 08/13/13 I 31.337 176 O 0.380 0.300 0.098 0.030 0.047 0.033 88.80

MBB Construction 11363 Santa Flood Control along MNR 08/12/13 I 17.106 383 O 0.394 0.300 0.003 0.030 0.051 0.033 81.10MBB Construction 11363 Santa Flood Control along MNR 03/19/13 I 17.106 363 O 0.324 0.300 0.150 0.015 0.038 0.033 86.00 -

MBB Construction 11363 Rehab./Reconst.Upgrading of Vigan-San Vicente Rd., K0408+(-1652)-K0408+201 03/20/13 I 27.653 166 O 0.367 0.225 0.150 0.030 0.038 0.033 84.30 -

MBB Construction 11363 Rehab./Reconst./Upgrading of Damaged Paved National Road along MNR 05/27/10 I 19.103 157 O 0.390 0.225 0.057 0.030 0.047 0.017 76.60 -

MBB Construction 11363 Const. of Ilocos Sur 2nd DEO Bldg. 08/13/08 I 14.140 365 O 0.261 0.240 0.100 0.030 0.037 0.100 76.80 -MBB Construction 11363 Const. of Ilocos Sur 2nd DEO Bldg. 11/12/08 I 14.140 365 O 0.251 0.115 0.030 0.022 0.025 0.067 51.00 -MBB Construction 11363 MNR, Candon-Santiago Section 11/12/08 I 18.920 200 O 0.338 0.034 0.100 0.022 0.022 0.067 58.30 -

MBD General Construction 9991 Const. of Ozamiz City Coastal By-Pass Rd. 08/16/13 X 51.314 270 C 0.495 0.133 0.000 - - - 62.80 75.07% Unsatisfactory

MBD General Construction 9991 Rehab. of Cebu North Hagnaya Wharf Rd., K0004+288-K0007+321 03/21/13 VII 36.636 240 C 0.481 0.133 0.300 - - - 91.40 88.94%

SatisfactoryMBD General Construction 9991 Conc. of Calamba-Baliangao Road 11/29/08 X 16.180 180 O 0.312 0.000 0.050 0.023 0.035 0.100 52.00 -MBD General Construction 9991 Conc. of Oroquieta-Calamba Mt. Road 11/29/08 X 7.146 120 O 0.258 0.085 0.100 0.023 0.025 0.100 59.10 -MBD General Construction 9991 Concreting of Oroquieta-Calamba Mt. Road 06/08/09 X 7.146 120 O 0.292 0.300 0.000 0.010 0.011 0.000 61.30 -MBD General Construction 9991 Concreting of Calamba-Baliangao Road 06/08/09 X 16.180 180 O 0.256 0.200 0.000 0.010 0.011 0.000 47.70 -MBD General Construction 9991 Conc. of Oroquieta-Calamba Mt. Road 03/18/09 X 7.146 219 O 0.313 0.240 0.000 0.030 0.045 0.000 62.80 -

MBD General Construction 9991Rehab./Upgrading od Jimenez Port Road and Concr. of Shoulders inc. Const. of Drainage Canal along Jimenez

Old Route09/15/09 X 13.349 150 O 0.392 0.252 0.150 0.020 0.051 0.033 89.80 -

MBD General Construction 9991 Conc. of Oroquieta-Calamba Mt. Road 09/15/09 X 7.146 120 O 0.253 0.244 0.000 0.030 0.028 0.033 58.80 -MBD General Construction 9991 Const. of Ozamis City Coastal By-Pass Road 03/26/12 X 51.314 240 O 0.362 0.185 0.150 0.030 0.047 0.050 82.40 -MBD General Construction 9991 Const. of Ozamiz City Coastal By-Pass Rd. 08/19/12 X 51.314 270 O 0.384 0.223 0.124 0.030 0.047 0.033 84.10 -

MBD/LABB Joint Venture JV-08-259Conc. of JCT TER, Jagna-Sierra Bullones Rd. Km. 76.526-

Km.77.681;Km77.9163-Km.78.94995&Km.79.19182-Km.81.500

09/04/09 VII 88.829 270 O 0.351 0.255 0.150 0.030 0.042 0.033 86.10 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page181

Page 182: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

MCB CONSTRUCTION & SUPPLY 12128 Repair/Rehabilitation/ Improvement along Calasiao Old Road, Km.206+800-Km. 207+100 with Exception 10/29/2014 I 4.804 65 C 0.439 0.133 0.300 - - - 87.20% 87.2%

SatisfactoryMCB CONSTRUCTION &

SUPPLY/WJP CONSTRUCTION & SUPPLY -JV

JV-13-615 Widening of Pangasinan- Nueva Ecija Road , K0179+000 to K0184+000 with Exceptions 10/30/2014 I 23.013 100 C 0.408 0.199 0.300 - - - 90.70% 90.7%

Very Satisfactory

MCB Construction and Supply 12128Rehab./Reconst./Upgrading of San Nicolas-San Quintin

Rd., San Nicolas-San Quintin, Km.200+000-Km.212+000 w/ exceptions

08/10/12 I 17.410 132 C 0.396 0.200 0.300 - - - 89.60 87.02% Satisfactory

MDEC Corporation Renovation of Service Wing Building 02/17/11 UP 8.989 180 O 0.303 0.300 0.150 0.015 0.000 0.050 81.80 -

Medardo Construction & Supply 33341 Const. of Mariwara Elem. Sch., Sitio Mariwara, Brgy. Princess Urduja 03/12/12 IVB 2.305 120 C 0.402 0.200 0.300 - - - 90.20 84.95%

Satisfactory

Medardo Construction & Supply 33341 Const. of Palawan State University (Brooke's Point Public Library) Pangobilian 03/12/12 IVB 1.199 90 C 0.460 0.200 0.300 - - - 96.00 84.73%

Satisfactory

MEGA M BUILDERS 20515Rehabilitation/Reconstruction/Upgrading Damage Paved

National Road MSR Passing Poblacion K0082+500-K0083+000 (Intermittent Section)

11/27/2014 IV 14.487 30 C 0.434 0.200 0.300 - - - 93.40% 93.4% Very Satisfactory

Mega M Builders 20515 Repair/Rehab./Impv't. of Daang Maharlika (SO1681LZ), K0089+500-K0091+518, w/ exceptions 08/12/13 IVA 9.880 15 C 0.478 0.133 0.300 - - - 91.10 *91.10% V.

Satisfactory

Mega M Builders 20515 Repair/Rehab. of FMR at Brgy. San Isidro 07/29/13 IVA 0.964 120 C 0.353 0.200 0.300 - - - 85.30 *85.30% Satisfactory

Mega M Builders 20515 Rehab. of Tiaong-Diversion Rd. inc. Slope Protection 03/16/13 IVA 28.612 290 C 0.430 0.133 0.300 - - - 86.30 87.38% Satisfactory

Mega Plus Construction 28322Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. (Int. Sect.), Secondary Rd., Civic Center Rd. 1, Chainage

0000-Chainage 015603/21/13 VII 3.457 28 C 0.456 0.133 0.300 - - - 88.90 *88.90%

Satisfactory

MEGABUCKS CONSTRUCTION & DEVELOPMENT CORP. 37554 NIA MARIIS DRD INFRA 2014-003 04/17/15 NIA 4.948 60 C 0.452 0.200 0.300 - - - - *95.24%

V. Satisfactory

Megaconstruct Group Inc. 33871 Const. of Bansud Drainage System 07/31/13 IVB 4.655 150 C 0.449 0.141 0.300 - - - 89.00 *89.00% Satisfactory

Megawide Construction Corporation

Construction of Ten (10) Five storey LRB with Land Development 04/23/15 NHA 620.310 687 C 0.467 0.122 0.269 - - - 85.72 86.06%

SatisfactoryMegawide Construction

CorporationConstruction of Ten (10) Five storey Medium Rise

Buildings with Land Development 05/09/14 NHA 610.294 623 O 0.372 0.231 0.142 0.030 0.061 0.050 88.58 -

Megawide Construction Corporation

Construction of Ten(10) Five storey Medium Rise Buildings with Land Development 10/31/13 NHA 592.930 540 O 0.347 0.273 0.094 0.030 0.061 0.033 83.82

Megawide Construction Corporation

Construction of Ten (10) Five storey Medium Rise Buildings with Land Development 10/31/13 NHA 592.930 540

On-going; Partial

Suspension on Bldgs.

A, B, C & D

0.347 0.273 0.094 0.030 0.061 0.033 83.79 -

MEGAY CONSTRUCTION 34354 Shoring at Dungeon in Fort Santiago 2/10/15 TIEZA 3.300 105 O 0.284 0.300 0.017 0.030 0.070 0.050 75.12MEGAY CONSTRUCTION 34354 Completion of Camiguin Tourism Center Pavillon 6/23/15 TIEZA 6.700 120 O 0.363 0.281 0.150 0.030 0.025 0.050 89.90

MEGAY CONSTRUCTION 34354 Sibul Spring Resort Development 02/12/14 TIEZA 4.996 150 C 0.432 0.189 0.300 92.13 92.13% Very Satisfactory

Megay Construction Sibul Spring Development 02/12/14 TIEZA 4.838 150 C 0.432 0.189 0.300 - - - 92.13 *92.13% V. Satisfactory

MEGAY CONSTRUCTION / ILC SUMMIT CONSTRUCTION, INC,

(JV) 34354 Establishment of First Easter Mass-Archaeological

Historical Recreation Park 4/8/15 TIEZA 10.300 150 O 0.285 0.225 0 0.015 0.056 0.050 63.07

MEGAY CONSTRUCTION / ILC SUMMIT CONSTRUCTION, INC,

(JV) 34354 Establishment of First Easter Mass-Archaeological

Historical Recreation Park 6/10/15 TIEZA 10.300 195 O 0.357 0.274 0.053 0.015 0.047 0.033 77.90

Megay Construction and Supply 34354 Conc. of Roads, Bagay 07/29/13 II 0.499 60 C 0.431 0.133 0.300 - - - 86.40 *86.40% Satisfactory

Megay Construction and Supply 34354 Conc. of Road, Atulayan Norte 07/29/13 II 0.499 60 C 0.429 0.133 0.300 - - - 86.20 *86.20% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page182

Page 183: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Megay Construction and Supply 34354 Const./Repair/Rehab. of MPB (BPPSC) Bulacan Police Provincial Office 03/18/13 III 0.950 30 C 0.410 0.133 0.300 - - - 84.30 *84.30%

SatisfactoryMegila Construction Dev't and

Supply 19262 Const. of 1-Storey, 4-Cl Sch. Bldg. Mabini NHS, Catalunan Grande NHS Annex 08/19/13 XI 2.008 150 C 0.480 0.133 0.300 - - - 91.30 *91.30% V.

Satisfactory

Mel Jean Construction Corporation (Formerly: Mel Jean Enterprises) 16344 Widening of Manila-Batangas Rd., inc. Drainage Structure,

Bugtong-Maraouy Sect., Km.72+300-Km.73+330 (Int. Sect.) 03/11/13 IVA 18.158 150 O 0.348 0.240 0.150 0.023 0.040 0.033 83.40 -

Mel-Jean Construction Corporation (Formerly: Mel Jean Enterprises) 16344 Rehab./Reconst./Upgrading of Damaged Roads along

Manila-Batangas Rd., Maraouy-Inosluban Sect. 06/07/10 IVA 7.419 90 O 0.355 0.225 0.150 0.015 0.050 0.050 84.50 -

Mel-Jean Construction Corporation (Formerly: Mel Jean Enterprises) 16344 Widening of Manila-Batangas Road at Inosluban Sect. (4

lanes w/ exception @ left side) 03/10/12 IVA 28.892 210 C 0.451 0.176 0.300 - - - 92.70 87.06% Satisfactory

Mel-jean Construction Corporation (Formerly: Mel Jean Enterprises) 16344 Widening of Manila-Batangas Rd., Inosluban Sect. (4 lanes) 11/09/12 IVA 28.575 210 C 0.428 0.133 0.300 - - - 86.10 89.94%

V. Satisfactory

Mel-jean Construction Corporation (Formerly: Mel Jean Enterprises) 16344 Widening of Manila-Batangas Road, Inosluban Sect. (4

lanes) 08/10/12 IVA 28.576 210 O 0.365 0.300 0.150 0.030 0.047 0.033 92.50 -

Mel-Jean Construction Corporation (Formerly: Mel-Jean Enterprises) 16344

Widening of Manila-Batangas Road inc. Drainage Structure Bugtong-Maraouy Sect., Km.72+300 - Km.73+330 (Int.

Sect.)07/29/13 IVA 19.098 180 C 0.437 0.133 0.300 - - - 87.00 84.84%

Satisfactory

MELROBE BUILDERS & CONSTRUCTION SUPPLIES 29752 Construction of Access Road from National Highway to

Banaybanay Port, Banaybanay, Davao Oriental 8/11/2014 XI 5.818 110 C 0.361 0.200 0.300 86.10 86.10% Satisfactory

Melrobe Builders & Construction Supplies 29752 Const. of Multi-Purpose Building Covered Court) Brgy.

Cabadiangan 06/10/09 XI 2.362 90 O 0.371 0.300 0.150 0.030 0.047 0.033 93.10 -

Menjer Construction 22815 Construction of Perimeter Fence 11/26/08 DOST 8.853 180 O 0.349 0.242 0.150 0.018 0.025 0.033 81.70 -Menjer Construction 22815 Construction of Perimeter Fence 11/26/08 DOST 8.853 180 O 0.349 0.242 0.150 0.018 0.025 0.033 74.10 -

Menjer Construction 22815 Repair/Rehab. of Rd. Slip along Dobleston-Butadon Nat'l R. (Secondary Rd.) 11/28/12 X 3.451 36 O 0.374 0.222 0.150 0.030 0.023 0.033 83.20 -

MEP Construction 18759 Renovation of DOF Cottage 03/11/13 CAR 6.500 150 C 0.478 0.133 0.300 - - - 91.10 *91.10% V. Satisfactory

MEP Construction 18759 Rehab./Impv't. of Camp 7 Flood Control 03/23/13 CAR 5.783 100 C 0.328 0.200 0.300 - - - 82.80 *82.80% Satisfactory

Mesagon Eng'g Builders 13749 Propose Multi-Purpose Bldg. (Completion of the Innovation & Packaging Devt. Center) 03/31/11 DOST 3.850 195 O 0.339 0.300 0.150 0.030 0.051 0.050 92.00 -

META CONSTRUCTION 28882 Construction of 1 Sty 3-Classroom, San Miguel Integrated School 10/27/2014 II 2.000 100 C 0.484 0.135 0.300 - - - 91.90% 91.9%

Very Satisfactory

Meta Construction 28882Widening along Santiago - Tuguegarao Road Isabela 4th

LD, K0338+137 - K0339+000, K0340+600 - K0340+750, K0341+100 - K0341+926

8/12/2014 II 12.961 180 OG 0.356 0.232 0.150 0.018 0.035 0.033 82.40

Meta Construction 28882 Opening/Rehab. of FTMR Pangal Sur 03/15/13 II 9.046 120 O 0.363 0.226 0.150 0.030 0.033 0.028 83.00 -Meta Construction 28882 Construction of Multi-Purpose Building 03/05/09 II 0.458 80 O 0.240 0.300 0.150 0.023 0.028 0.033 77.40 -

Metalite Builders Development Inc. 31004 Const./Conc. of Rds. Brgy. Macadandig & Gusa 08/22/13 X 2.233 82 C 0.393 0.133 0.300 - - - 82.60 *82.60% Satisfactory

METRICS CONSTRUCTION & TRADING - Construction/Rehabilitation of 15th Avenue (P. Tuazon -

Bonny Serrano) 11/27/2014 NCR 8.814 177 C 0.421 0.133 0.300 - - - 85.40% 85.4% Satisfactory

Metrics Construction and Trading 18223 Const. of Three (3) Storey, Six (6) Cl Sch. Bldg., Pura Kalaw E/S 08/05/13 NCR 6.407 120 C 0.435 0.133 0.300 - - - 86.80 *86.80%

Satisfactory

Metropolis Construction, Inc. 3586 Const. of Teacher Education and Law Center Bldg., Rizal Technological University (Phase III), Brgy. Malamig 03/13/12 NCR 19.270 180 C 0.322 0.200 0.300 - - - 82.20 89.69%

V. Satisfactory

MF Construction 22192 Const.of DPWH Siquijor District Engineering Office Building inc. Quarters 09/07/09 VII 2.892 189 O 0.373 0.240 0.150 0.030 0.037 0.033 86.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page183

Page 184: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

MG Samidan Construction 33234Rd. Upgrading (Gravel to Conc.) of Nat'l Rds. along Gurrel-

Bokod-Kabayan-Buguias-Abatan Rd., K0355+000-K0356+100 (I.S.)

08/02/12 CAR 17.387 210 C 0.430 0.133 0.300 - - - 86.30 87.86% Satisfactory

MG Samidan Construction 33234 Impv't. of Pitpitan-Tamog-o Rd., in Bauko Arc 03/16/13 CAR 17.466 173 C 0.465 0.200 0.000 - - - 66.50 *66.50% Poor

MG Samidan Construction / CSD Engineering and Construction

Joint VentureJV-11-697 Rd. Upgrading (gravel to paved) of Rizal Nat'l. Rd.,

K0522+327-K0528+928 03/21/13 CAR 9.410 90 C 0.468 0.133 0.300 - - - 90.10 *90.10% V. Satisfactory

MG SAMIDAN CONSTRUCTION / TADIAN GENERAL CONSTRUCTION

JV-13-286

Road Upgrading (Gravel to Paved) of Mt. Province-Ilocos Sur via Tue Road, Section 1: K0388+900 - K0389+500,

K0393+500 - K0393+856; Section 2: K0398+000 - K0398+578, K0399+728 - K0399+811; Section 3: K0412+165 -

K0412+942, K0413+327 - K0413+354, K0413+368 - K0413+400

11/23/2014 CAR 56.128 270 O 0.337 0.280 0.150 0.030 0.055 0.050 90.20% 90.2% Very Satisfactory

MGBJ RISING CONSTRUCITON & DEVELOPER 18656

Preventive Maintenance (Asphalt Overlay) along Sarangani - Davao del Sur Coastal Road, K1654+(-291) - K1654+324,

Alabel, Sarangani Province10/29/2014 XII 8.788 60 C 0.474 0.133 0.300 - - - 90.70% 90.7%

Very Satisfactory

MGBJ Rising Construction & Land Developer 18656

Prev. Maint. Nat'l Arterial (Prev. Maint.), South Cotabato Sub-DEO, Digos-Makar Rd., Chainage 0000-Chainage 0175

(S00230MN) Int. Sect.08/23/13 XII 2.170 21 C 0.468 0.133 0.300 - - - 90.10 *90.10%

V. Satisfactory

MGBJ Rising Construction & Land Developer 18656 Rehab./Impv't. of Filipino-American Friendship Ave. 08/23/13 XII 14.086 50 C 0.429 0.133 0.300 - - - 86.20 *86.20%

Satisfactory

MGDJ Construction 29352Widening/Rehab. of Bridge from Two (2) Lanes to Four (4)

Lanes along Batangas-Quezon Rd., Bawi Bridge, Padre Garcia

07/29/13 IVA 3.526 106 C 0.415 0.133 0.300 - - - 84.80 85.58% Satisfactory

MGDJ Construction 29352 Widening/Rehab. of Bridge Two (2) lanes to Four (4) Lanes along Batangas-Quezon Rd., Bawi Bridge 03/11/13 IVA 3.399 90 O 0.358 0.240 0.150 0.030 0.050 0.033 86.10 -

MGT Builders & Supply 33872 Road Upgrading of Cumadcad-San Isidro Pob. Rd. 08/04/12 V 6.144 90 C 0.431 0.133 0.300 - - - 86.40 85.26% Satisfactory

MGT Builder's & Supply 33872 Repair/Reconst./Upgrading of Damaged Paved National Secondary Road along Jct. Donsol-Banuang Gurang Road 8/13/2014 V 3.924 50 C 0.421 0.133 0.300 85.43 85.43%

Satisfactory

Micah Construction and Supply 26625 Rd. Upgrading (Gravel to Paved), Intermittent Sect., Nat'l Secondary, Davao-Cotabato Old Rd. 03/21/13 XI 5.377 42 C 0.407 0.133 0.300 - - - 84.00 *84.00%

Satisfactory

MICRO ASIA BUILDERS CORP. 26286 Construction of Information Center with Restroom 6/18/15 TIEZA 2.600 150 O 0.377 0.300 0.120 0.030 0.056 0.050 93.32

MICRO-ASIA BUILDERS CORP 26286 Const. of DepEd Standard Type School Building at Tayum ES Cauayan, Negros Occidental 8/9/2014 VI 2.302 85 C 0.441 0.200 0.300 94.10 85.98%

Satisfactory

Micro-asia Builders Corp. 26286 Const. of DepEd Standard Type Sch. Bldg. @ Tuyom ES 08/09/13 VI 2.302 85 O 0.334 0.240 0.150 0.030 0.038 0.033 82.50

MICRO-ASIA BUILDERS CORPORATION

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Road, Bacolod Circumferential Road (S),

K0010+424 - K0011+52110/27/2014 VI 11.473 120 C 0.417 0.133 0.300 - - - 85.00% 85%

Satisfactory

MIGHTY CONSTRUCTION & SUPPLY 34278

Construction of Classroom in Areas Experiencing Acute Classroom Shortage, Lupa E/S, One (1) Classroom, SB,

Lupa10/30/2014 II 1.130 90 O 0.367 0.300 0.150 0.030 0.018 0.033 89.80% 89.8%

Very Satisfactory

MIGO CONSTRUCTION 34663 Construction of Two Units, One-Storey, One Classroom School Building at Sabang Elementary School 10/28/2014 XIII 2.128 60 O 0.357 0.240 0.150 0.020 0.043 0.050 86.00% 86%

Satisfactory

MIKKIL CONSTRUCTION 37020 Const. of Classroom (BEFF Batch 1) 1 Storey 1 CL Tula ES, 1 storey 2 CL Molocboloc PS 10/27/2014 X 3.070 75 C 0.358 0.161 0.000 - - - 51.90% 51.9%

Poor

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page184

Page 185: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

MIN CONSTRUCTION 14656

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Roads Including Drainage based on Pavement Management Analysis-4 (HDM-4 Project

Analysis) Intermittent Section along Ipil-Liloy-Sindangan Road (Poblacion Muslim and Taway Section) K2004+497 to

K2004+800; K2010+360 to K2011+420; and K2012+000 to K2012+790 with exception

10/23/2014 IX 33.841 225 C 0.423 0.133 0.300 - - - 85.60% 85.6% Satisfactory

Min Construction 14656

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Road including Drainage based on Pavement Management System/Highway Devt. &

Management-4 (HDM-4 Project Analysis) Intermittent Section along Ipil-Liloy-Sindangan Road (Poblacion

Muslim and Taway Section (K2004+497 to K2004+800; K2010+360 to K2011+420; and K2012+000 to K2012+790

with exception

8/8/2014 IX 31.195 195 OG 0.312 0.300 0.147 0.030 0.035 0.033 85.70

Min Construction 14656 Road Upgrading (Gravel to Concrete) at Sindangan-Siayan-Dumingag-Mahayag Road (Denoyan-Pob.-Siayan Section) 04/13/11 IX 33.841 385 O 0.328 0.300 0.150 0.030 0.038 0.050 89.60 -

Min Construction 14656 Proposed Conc. of Liloy-Siocon Road (Kipit-Gutalac Section) 08/28/08 IX 19.125 168 O 0.317 0.240 0.100 0.030 0.047 0.100 83.40 -

Min Construction 14656 Proposed Conc. of Liloy-Siocon Road (Kipit-Gutalac Section) 11/25/08 IX 19.125 213 O 0.327 0.239 0.100 0.030 0.025 0.067 78.80 -

Min Construction 14656 Conc. of Jct. Imelda-Alicia Rd. (Lutiman-Lambuyugan Sect.) 11/24/12 IX 42.706 295 C 0.412 0.133 0.300 - - - 84.50 84.50%

Satisfactory

Min Construction 14656Rd. Upgrading (Gravel to Paved) Sindangan-Siayan-

Dumingag-Mahayag Rd. (Suguilon Sect.), Km.1933+000-Km.1934+841 Modified to Km.1949+613-Km.1951+425

11/28/12 IX 39.430 180 O 0.286 0.300 0.150 0.030 0.043 0.033 84.20 -

Min Construction 14656Rd. Upgrading (Gravel to Paved), Sindangan-Siayan-

Dumingag-Mahayag Rd. (Suguilon Sect.) Km.1933+000-Km.1934+841 Modified to Km.1949+613-Km.1951+425

08/25/12 IX 39.430 150 O 0.330 0.300 0.150 0.030 0.032 0.033 87.50 -

Min Construction 14656 Conc. of Jct. Imelda-Alicia Rd. (Lutimon-Lambuyugon Sect.) 08/28/12 IX 42.706 261 O 0.357 0.232 0.142 0.030 0.035 0.033 82.90 -

Mindanao Construction Services & Land Development Corporation 34147 Conc. of Rd. at Teachers Village, Brgy. Calinan Pob.

Calinan District 03/11/13 XI 1.344 30 C 0.415 0.133 0.300 - - - 84.80 *84.80% Satisfactory

MINDANAO CONSTRUCTION SERVICES AND LAND DEVELOPMENT CORP.

34147 Conctruction of Road-Lika to Cemetery under Local Infrastructure 8/9/2014 XII 4.578 77 C 0.473 0.133 0.300 90.60 90.60%

Very Satisfactory

Mindanao Rock 23479 Ozamis Airport Development Project 07/16/15 DOTC 67.141 330 C 0.412 0.200 0.300 - - - 91.24 *92.29% V. Satisfactory

MINDANAO ROCK 23479 Ozamis Airport Development Project 04/28/15 DOTC 67.141 270 O 0.366 0.300 0.150 0.030 0.044 0.050 94.00 -

Mindanao Rock 23479

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. (Int. Sect.) Ozamiz-Oroquieta Rd., K01707+205-

K01708+201, K1709+389-K1712+685, K01713+318-K01715+391, & K01715+968-K01716+820

08/16/13 X 87.400 180 C 0.420 0.133 0.300 - - - 85.30 *85.30% Satisfactory

Mindanao Rock 23479 Prev. Maint., Bagacay-Cadre Rd., K1698+265-K1698+685 08/16/13 X 4.592 37 C 0.419 0.133 0.300 - - - 85.20 *85.20% Satisfactory

Mindanao Rock 23479 Const. of Ozamis City Coastal By-Pass Road 06/09/09 X 42.951 240 O 0.309 0.258 0.150 0.020 0.043 0.050 83.00 -Mindanao Rock 23479 Const. of Ozamis City Coastal By Pass Road 09/16/09 X 42.950 240 O 0.308 0.257 0.150 0.030 0.051 0.033 82.90 -

MINDANAO ROCK 23479 Ozamis Airport Development Project 12/10/14 DOTC 67.141 270 O 0.356 0.300 0.150 0.020 0.044 0.050 92.00 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page185

Page 186: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Mindanao Rock / GLS Construction and General Merchandise JV-12-510 Widening/Impv't. of Ozamiz-Oroquieta Rd. (Clarin-

Sinacaban) Km.1705+979-Km.1721+184, w / exceptions 08/16/13 X 25.944 140 O 0.320 0.200 0.072 0.030 0.025 0.033 68.00

MIVICO Builders and Developers 20551 Rehab./Reconst./Upgrading of Damaged Paved National Road, Sumacab-San Josef-Bonifacio Road 9/26/2014 Special 3 12.675 90 C 0.323 0.200 0.300 82.30 82.30%

Satisfactory

Mivico Builders and Developers 20551

Prev. Maint. (Int. Sect.) along Sta. Rosa-Tarlac Rd., Km.110+000-Km.110+687.99 (L=687.99 LM); Km.110+687.99-

Km.111+1002.41 w/ exception (L=771.42 LM); Km.111+1002.41- Km.112+201.38 (L=201.97 LM) (16661.38

LM)

08/09/13 III 20.780 108 C 0.437 0.133 0.300 - - - 87.00 *87.00% Satisfactory

Mivico Builders and Developers 20551 Prev. Maint. along Mt. Province-Nueva Vizcaya Road (Int. Sect.), K0383+070-K0364+000 & K0384+153-K0384+471 07/30/13 CAR 9.986 72 C 0.412 0.133 0.300 - - - 84.50 *84.50%

Satisfactory

Mivico Builders and Developers 20551 Upgrading of Nueva Ecija-Pangasinan Rd. 06/07/10 III 24.003 90 O 0.369 0.198 0.150 0.030 0.048 0.033 82.80 -

Mivico Builders and Developers 20551 Rehab. of Digdig River, Installation of Spurdike (DOLOS) Putlan Sect., Putlan 11/26/12 III 9.648 155 C 0.367 0.200 0.300 - - - 86.70 82.38%

Satisfactory

MJ Barcelona Construction and Supply 34723 Construction of San Rafael Communal Irrigation Project

Contract Reference No. NIA R6-ARISP-RAFAEL-CW14-14 02/19/15 NIA 10.783 150 O 0.382 0.263 0.150 0.030 0.064 0.050 93.78 -

MJ Barcelona Construction and Supply 71781 Rehab. Of Jalaur-Saugue RIS (Suague Area) Bench Flume,

Lat B3 NIAR6-NIS Extn. 13-JSRIS-CW32-13 11/15/13 NIA 4.666 90 O 0.355 0.126 0.000 0.010 0.028 0.033 55.20 -

MM Construction Corporation (Formerly: MM Construction) 12012 Widening of Daang Maharlika, K0270+755.40-K0271+736.40 03/20/13 II 14.086 90 O 0.347 0.240 0.150 0.030 0.056 0.033 85.60 -

MN Bayalas Construction 34251 Const. of 1-Storey, 2-CL at Kahayagan NHS 08/17/13 XIII 1.305 135 C 0.381 0.200 0.300 - - - 88.10 85.70% Satisfactory

MN Bayalas Construction 34251 Drainage along NRJ Barobo-Agusan del Sur Bdry. 03/17/13 XIII 4.550 165 C 0.449 0.200 0.300 - - - 94.90 89.20% V. Satisfactory

MN Bayalas Construction 34251 Const. of 1 Storey-2 CL at Kahayagan NHS, Tagbina, SDS Kahayagan 03/17/13 XIII 1.305 135 O 0.395 0.225 0.150 0.015 0.023 0.033 84.10 -

MN Macato Builders 33448 Impv't. of Manlawaan Bridge II Approaches & Other Bridges along Nat'l Rds & Grouted Riprap, Districtwide 08/12/13 VIII 3.784 150 C 0.368 0.200 0.300 - - - 86.80 79.54%

Unsatisfactory

MN Macato Builders 33448 Impv't. of Manlawaan Bridge II Approaches & Other Bridges along Nat'l. Rds. & Grouted Riprap, Districtwide 03/13/13 VIII 3.784 150 O 0.269 0.225 0.150 0.030 0.040 0.033 74.70 -

Molte Aries Construction & Industries 3684 Road Upgrading of San Fernando-Bagulin Road 09/02/09 I 14.114 400 O 0.353 0.300 0.150 0.030 0.060 0.033 92.60 -

Molte Aries Construction & Industries 3684 Road Upgrading of San Fernando-Bagulin Road 05/28/09 I 14.114 400 O 0.300 0.260 0.150 0.030 0.035 0.033 80.80 -

MOM Enterprises

Package X-M: Construction of lateral "N" (Sta. 14+500-Sta. 16+960) and sub-lat. "N-11" (Sta. 0+000-Sta. 1+380)

including related structures and supply, delivery and installation of steel gates

02/07/15 NIA 25.621 180 O 0.331 0.300 0.115 0.030 0.019 0.050 84.49 -

Monolithic Const. & Concrete Products Inc. / Cofejok Const. &

Supply Corp. (JV)JV-11-741

Rd. Upgrading (Gravel to Paved) along Awang-Upi-Lebak-Kalamansig-Palimbang-Sarangani Rd. (Km.1963+471-

Km.1977+121) Realign to Rd Upgrading (Gravel to Paved) along Awang-Upi-Lebak-Kalamasig-Palimbang-Sarangani

Rd. (Km.2021+151-Km.2023+241 w/ exception)

08/18/13 XII 45.861 344 C 0.415 0.200 0.300 - - - 91.50 *91.50% V. Satisfactory

Monolithic Const. & Concrete Products Inc. / Palmares General

Merchandise (JV)JV-11-740

Rd. Upgrading (Gravel to Paved) along Awang-Upi-Lebak-Kalamansig-Palimbang-Sarangani Rd. (Km.1963+471-

Km.1977+121) Realign to Rd. Upgrading (Gravel to Paved) along Awang-Upi-Lebak-Kalamasig-Palimbang-Sarangani

Rd. (Km.2017+229-Km.2019+229 w/ exception)

08/18/13 XII 43.835 345 C 0.410 0.200 0.300 - - - 91.00 *91.00% V. Satisfactory

Monolithic Construction & Concrete Product, Inc. 5733 Rehab./Conc. of Marinduque Circumferential Road

(Intermittent Section) 08/25/09 IVB 82.951 360 O 0.370 0.282 0.150 0.030 0.051 0.033 91.60 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page186

Page 187: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Monolithic Construction & Concrete Product, Inc. 5733 Const. of Water Impounding at Poblacion 08/08/12 IVA 30.070 300 O 0.340 0.240 0.150 0.030 0.050 0.033 84.30 -

MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC. 5733 Construction of Slope Protection along NCR-Bulacan Bdry.-

Bigte-Ipo Dam Road, Ilog Bayad Bridge 11/28/2014 III 46.534 170 C 0.466 0.133 0.300 - - - 89.90% 89.9% Very Satisfactory

MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC. 5733

Rehab./Reconst./Upgrading of Damaged Paved National Roads Mdo. Or./Occ. ECR Milagrosa Section (K0186+182-

K0187+000 and K0201+52711/27/2014 IV 18.239 189 C 0.463 0.133 0.300 - - - 89.60% 89.6%

Very Satisfactory

MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC. 5733 Road leading to Mahangub-Lubilan & Talabaan Falls,

Upgrading (Gravel to Concrete) 10/27/2014 X 45.434 239 O 0.267 0.294 0.030 0.023 0.037 0.033 68.40% 68.4% Poor

MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC. 5733 Rehabilitation and Protection of Tuganay River 10/23/2014 XI 39.529 132 O 0.400 0.300 0.150 0.030 0.030 0.025 93.50% 93.5%

Very Satisfactory

MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC. 5733 Concrete Revetment on Steel Sheet Piles along Talomo

River, Kalye Apike Section, Calinan District, Davao City 10/20/2014 XI 28.341 201 O 0.389 0.243 0.110 0.015 0.055 0.033 84.50% 84.5% Satisfactory

Monolithic Construction & Concrete Products, Inc. 5733 Replacement/Rehabilitation of Tiguisan Munti Bridge along

Calapan South Road 8/12/2014 IV-B 4.273 207 C 0.406 0.133 0.300 83.90 83.18% Satisfactory

Monolithic Construction & Concrete Products, Inc. 5733 Construction of Kasay Flood Control along Dr. Damian

Reyes Road (Boac Side) 8/16/2014 IV-B 15.307 210 C 0.436 0.133 0.300 86.90 87.38% Satisfactory

Monolithic Construction & Concrete Products, Inc. 5733

Reconstruction of Road Slip along Mogpog - Balanacan Road (Mogpog - Balanacan Section) Km. 11+000 - Km.

16+937, with Exception41867 IV-B 15.924 236 C 0.451 0.132 0.300 88.30 86.68%

Satisfactory

MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC. 5733 Improvement of Drainage Structure at Sapang Creek along

Butuan City-Cagayan de Oro City Road Phase II 8/16/2014 X 40.871 299 C 0.479 0.200 0.300 97.90 84.46% Satisfactory

MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC. 5733 Rehabilitation/Improvement/Widening of Mamay Road forn

Jct. Diversion to Daang Maharlika 8/15/2014 XI 44.680 181 OG 0.313 0.225 0.150 0.030 0.050 0.050 81.80

Monolithic Construction & Concrete Products, Inc. 5733 Quipot Irrigation Project 02/14/15 NIA 117.463 360 C 0.375 0.200 0.300 - - - 87.50 *87.50%

SatisfactoryMonolithic Construction &

Concrete Products, Inc. 5733 Replacement of Bridges along Nat'l Rds. crossing Malabog Bridge along Fatima-Malabog 08/20/13 XI 21.360 328 C 0.401 0.200 0.300 - - - 90.10 *90.10% V.

SatisfactoryMonolithic Construction &

Concrete Products, Inc. 5733 Const. of Water Impounding at Poblacion 08/08/13 IVA 30.070 389 C 0.296 0.200 0.300 - - - 79.60 82.42% Satisfactory

Monolithic Construction & Concrete Products, Inc. 5733

Const./Widening/Upgrading/Rehab. of Jct. Island Garden City of Samal Circ. Road, Babak-Tambo Island Garden City

of Samal08/20/13 XI 41.594 222 O 0.279 0.300 0.150 0.030 0.045 0.033 83.70

Monolithic Construction & Concrete Products, Inc. 5733 Const. of Kasay Flood Control along Dr. Damian Reyes Rd.

(Boac Side) 08/07/13 IVB 14.105 196 O 0.320 0.300 0.150 0.015 0.042 0.050 87.70

Monolithic Construction & Concrete Products, Inc. 5733 Replacement/Rehab. of Tiguisan Munti Bridge along

Calapan South Rd. 07/31/13 IVB 4.273 207 O 0.349 0.240 0.150 0.020 0.035 0.050 84.40

Monolithic Construction & Concrete Products, Inc. 5733

Reconst. of Rd. Slip along Mogpog-Balanacan Rd. (Mogpog-Balanacan Sect.) Km.11+000-Km.16+937 w/

exceptions08/07/13 IVB 15.915 236 O 0.328 0.241 0.150 0.030 0.032 0.050 83.10

Monolithic Construction & Concrete Products, Inc. 5733 Impv't. of Drainage Structure at Sapang Creek along

Butuan City-Cagayan de Oro City Rd. Phase II, Brgy. Bulua 08/11/13 X 40.871 239 O 0.368 0.240 0.044 0.030 0.040 0.033 75.50

Monolithic Construction & Concrete Products, Inc. 5733

Rehab./Reconst./Upgrading of Damaged Paved Nat'l. Rds. along Nueva Vizcaya-Ifugao-Mt. Province Rd., K0290+600-K0305+000 (IS), K0291+(-390)-K0305+000 (IS) as per RBIA

03/17/13 CAR 48.126 205 C 0.470 0.200 0.300 - - - 97.00 93.76% V. Satisfactory

Monolithic Construction & Concrete Products, Inc. 5733

Reconst. of Rd. Slip along Mogpog-Balanacan Rd. (Mogpog-Balanacan Sect.) Km.11+000-Km.16+937.00 w/

exception03/23/13 IVB 15.915 215 O 0.388 0.235 0.150 0.030 0.045 0.033 88.10 -

Monolithic Construction & Concrete Products, Inc. 5733 Const./Widening/Upgrading/Rehab. of Jct. Island Garden

City of Samal Circ. Rd., Babak-Tambo 03/17/13 XI 41.594 179 O 0.358 0.245 0.150 0.030 0.030 0.050 86.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page187

Page 188: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Monolithic Construction & Concrete Products, Inc. 5733

Rehab./Reconst./Upgrading of Damaged Paved Nat'l. Roads (Intermittent Sect.) for Package 11 (Buhangin-

Lapanday Road, Km.1505+(-)462 - Km.1506+000)08/25/11 XI 5.130 160 O 0.372 0.240 0.150 0.030 0.050 0.050 89.20 -

Monolithic Construction & Concrete Products, Inc. 5733 Rehab./Conc. of Marinduque Circumferential Road

(Intermittent Section) 05/19/09 IV-B 82.951 360 O 0.353 0.300 0.150 0.030 0.033 0.050 91.60 -

Monolithic Construction & Concrete Products, Inc. 5733 Rehab./Conc. of Marinduque Circ. Rd. (Intermittent

Section) 03/11/09 IV-B 82.951 360 O 0.296 0.272 0.150 0.030 0.025 0.050 82.30 -

Monolithic Construction & Concrete Products, Inc. 5733 Impv't/Conc.Paving of Jct. Baliguian to Siocon Road, Jct.

Baliguian-Nonoyan-Sta. Maria Section 03/07/09 IX 48.006 380 O 0.386 0.263 0.099 0.030 0.037 0.033 84.80 -

Monolithic Construction & Concrete Products, Inc. 5733 Rehabilitation of Odiongan Bridge along Cateel-

Compostela Section 06/08/09 XI 52.910 240 O 0.370 0.237 0.150 0.030 0.042 0.050 87.90 -

Monolithic Construction & Concrete Products, Inc. 5733 Rehab. of Odiongan Bridge along Cateel-Compostela Sect. 09/11/09 XI 52.910 240 O 0.376 0.240 0.150 0.030 0.038 0.033 86.70 -

Monolithic Construction & Concrete Products, Inc. 5733 Rehab./Reconst./Upgrading of MCR (Tigwi-Dampulan-

Lipata-Yook Sect.), 03/21/12 IVB 24.877 142 C 0.446 0.133 0.300 - - - 87.90 91.86% V. Satisfactory

Monolithic Construction & Concrete Products, Inc. 5733

Rehab./Reconst./Upgrading of Dr. Damian Reyes Memorial Road Boac Side, (Km.12+031-Km.12+564.30, Km.14+000-

Km.14+997.70)03/20/12 IVB 23.205 127 C 0.447 0.133 0.300 - - - 88.00 91.66%

V. Satisfactory

Monolithic Construction & Concrete Products, Inc. 5733

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. (IS) for Package II Buhangin-Lapanday Road, Km.1505+(-

)462-Km.1506+00003/29/12 XI 5.130 160 C 0.420 0.200 0.300 - - - 92.00 90.32%

V. Satisfactory

Monolithic Construction & Concrete Products, Inc. 5733 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds.

(IS) along R. Castillo Street, Km. 1505+950-Km. 1506+645 11/29/12 XI 39.436 271 C 0.442 0.133 0.300 - - - 87.50 88.90% Satisfactory

Monolithic Construction & Concrete Products, Inc. 5733

Const./Installation of New Drainage along Iligan City-Cagayan de Oro City-Butuan (ICBR Rd.), Corrales-Velez

Sect.08/06/12 X 14.996 210 C 0.486 0.200 0.300 - - - 98.60 88.28%

Satisfactory

Monolithic Construction & Concrete Products, Inc. 5733 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds.

(IS) along R. Castillo St., Km.1505+950-Km.1506+645 08/21/12 XI 39.436 250 O 0.372 0.239 0.150 0.030 0.060 0.050 90.10 -

Monolithic Construction & Concrete Products, Inc. 5733 Widening/Const. of Digos Bridge II along Digos Diversion

Rd. 08/10/12 XI 22.018 348 C 0.445 0.131 0.300 - - - 87.60 87.78% Satisfactory

Monolithic Construction & Concrete Products, Inc. 5733 Widening/Const. of Miral Bridge along Davao-Cotabato Rd. 08/10/12 XI 11.755 292 C 0.470 0.104 0.300 - - - 87.40 87.34%

Satisfactory

MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC. 5733

Road Upgrading (Gravel to Concrete) along Surallah - Lake Sebu - Maitum Road, K01759+568 to K01765+260.50 (with Exceptions), South Cotabato; K01763+065 - K01763+085 (shadol I Bridge); K01763+701.40 - K01763+722 (Shadol II

Bridge); K01764+138.20 - K01764+145.10 (RCBC)

10/22/2014 XII 169.063 540 C 0.450 0.133 0.300 - - - 88.30% 88.3% Satisfactory

MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC. / COLBY CONSTRUCTION (JV)

JV-13-646

Road Upgrading (Gravel to Paved) of banaue-Mayoyao-A. Lista-Isabela Bdry. Road, Based on Gravel Road

Strategies, Traffic Benchmark for Upgrading to Paved Road Standard (HDM-4 Project Analysis) Intermittent

Sections, Section1: K0398+835 - K0399+118.91; Section2: K0401+641 - K0401+713.316; Section3: K0406+491 - K0406+572; Section4: K0406+648 - K0406+674.89;

Section5: K0413+698 - K0413+787.74; Section6: K0416+130 - K0417+618.49; Section7: K0419+606 - K0421+048.35

11/26/2014 CAR 102.959 301 O 0.339 0.272 0.150 0.030 0.060 0.050 90.10% 90.1% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page188

Page 189: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC. / COLBY CONSTRUCTION (JV)

JV-13-560

Road Upgrading (Gravel to Paved) of Ubao-Taang, Based on Gravel Road Stategies, Traffic Benchmark for

Upgrading to Paved Road Standard (HDM-4 Project Analysis) (Intermittent Sections), K0401+083-K0401+481, K401+481-K0401-571,K0401+571-K0402+499,K0402+635-

K0402+690-K0402+775,K0402+775-K0404+267,K0404+267-K0404+387,K0404+387-K0404+513, K0404+513-

K0404+609,K0404+609-K0404+656,K0404+656-K0404+736, K0404+736-K0404+888, & K0404+888-K0404+940

11/26/2014 CAR 100.700 257 O 0.386 0.280 0.088 0.030 0.060 0.050 89.40% 89.4% Very Satisfactory

Monolithic Construction and Concrete Products, Inc. 5733 Talibon Small Reservoir Irrigation Project 9/29/08 10/3/08 NIA 49.099 390 O 0.367 0.175 0.100 0.030 0.042 0.200 91.40 -

Monolithic Construction and Concrete Products, Inc. / Jagon

Builders (JV)JV-09-283

Widening/Conc. Of Commonwealth Ave. Incl. RROW, Sta.5+400 - Sta.6+000 incl. Footbridge in front of COA

Bldg.09/03/10 NCR 40.826 108 O 0.254 0.300 0.150 0.030 0.045 0.033 81.20 -

Monolithic Construction and Concrete Products, Inc./Jagon

Builders (JV)JV-09-283

Widening/Conc. of Commonwealth Ave. inc. RROW Sta.5+400-Sta.6+000 inc. Footbridge infront of COA

Building04/08/11 NCR 40.826 153 O 0.333 0.259 0.000 0.030 0.050 0.033 70.50 -

Monolithic Construction and Concrete Products, Inc./King's

Builders & Development Corp. (JV)JV-11-489

Rd. Upgrading (Gravel to Concrete) Calapan South Rd. (Km.183+124.50-Km.185+019.76; Km.186+733-Km.189+060;

Km.190+439.57-Km.191+478)11/27/12 IVB 111.476 390 O 0.365 0.269 0.150 0.030 0.051 0.050 91.50 -

Montaño Construction & Development Corp. 2010-1185 Dapitan Resettlement Project 11/12/13 NHA 22.695 215 C 0.494 0.200 0.300 99.40

Montaño Construction & Development Corp. 2010-1185 Dapitan Resettlement Project 11/12/13 NHA 22.695 215 C 0.494 0.200 0.300 - - - - 99.40%

OutstandingMontaño Construction &

Development Corp. 19473 Const. of De Venta Perla Bridge & Approaches (Phase II) 06/12/10 IX 27.869 293 O 0.353 0.240 0.000 0.030 0.035 0.050 70.80 -

Montaño Construction & Development Corp. 2010-1185 Dapitan City Resettlement Project 01/23/13 NHA 22.695 215 O 0.398 0.300 0.150 0.030 0.056 0.050 98.43 -

Montaño Construction & Development Corp. 19473 Maasin Airport Development Project 03/21/13 DOTC 29.295 150 O 0.400 0.300 0.150 0.030 0.056 0.025 96.10 -

MONTAÑO CONSTRUCTION & DEVELOPMENT CORPORATION 19473

Construction of Polanco PSCG Bridge and Approaches (PHASE I) Along Dipolog-Polanco-Piñan-Jct. Oroquieta

Road10/28/2014 IX 14.950 245 C 0.443 0.143 0.300 - - - 88.60% 88.6%

Satisfactory

Montaño Construction & Development Corporation 19473 Restoration of Sanito Bridge Sta. 1800+731 to Sta.

1800+764.40 8/8/2014 IX 32.899 554 C 0.457 0.200 0.300 95.70 88.38% Satisfactory

MONTAÑO Construction & Development Corporation 19473 Maasin Airport Development Project 06/24/14 DOTC 57.589 360 O 0.340 0.300 0.150 0.010 0.045 0.050 89.44 -

Montaño Construction & Development Corporation 19473 Restoration of Sanito Bridge

Sta.1800+731.60Sta.1800+764.40 08/09/13 IX 32.178 554 O 0.262 0.300 0.150 0.030 0.033 0.050 82.50

Montaño Construction & Development Corporation 19473 Const. of Salug-Daku Bridge & Approaches along

Sindangan-Siayan-Dumingag-Mahayag Rd. 08/17/13 IX 27.645 270 O 0.306 0.300 0.000 0.022 0.042 0.033 70.30

Montaño Construction & Development Corporation 19473 Replacement of Licabang (Dipolog) Bridge Phase I, Jct.

Mahayag-Dumingag-Siyam Rd. 03/21/13 IX 28.082 240 C 0.465 0.133 0.300 - - - 89.80 87.28% Satisfactory

Montaño Construction & Development Corporation 19473 Const. of Salug-Daku Bridge &Approaches along

Sindangan-Siayan-Dumingag-Mahayag Rd. 03/21/13 IX 27.645 270 O 0.361 0.240 0.150 0.030 0.033 0.033 84.70 -

Montaño Construction & Development Corporation 19473 Restoration of Sanito Bridge Sta.1800+731.60-

Sta.1800+764.40 03/14/13 IX 32.178 404 O 0.364 0.240 0.120 0.030 0.047 0.033 83.40 -

Montaño Construction & Development Corporation 19473

Rd. Upgrading (Gravel to Concrete) IS, Dipolog-Punta-Dansullan-S. Osmeña-Zamboanga Norte/Sur Bdry. from

K1885+000-K1885+292; K1885+57 -K1887+000 Modified to K1884+891-K1885+321; K1885+546-K1885+771; K1887+494-

K1887+999

11/29/12 IX 24.527 240 C 0.398 0.200 0.300 - - - 89.80 89.74% V. Satisfactory

Montaño Construction & Development Corporation 19473 Widening of Jct. Polo-Dapitan Park R. 11/29/12 IX 26.697 255 C 0.373 0.200 0.300 - - - 87.30 87.48%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page189

Page 190: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Montaño Construction & Development Corporation 19473 Const. of Salug-Daku Bridge & Approaches along

Sindangan-Siayan-Dumingag-Mahayag Rd. 11/23/12 IX 27.645 210 O 0.367 0.225 0.150 0.030 0.045 0.050 86.70 -

Montaño Construction & Development Corporation 19473 Restoration of Sanito Bridge, Sta.1800+713.60-

Sta.1800+764.40 11/26/12 IX 31.039 374 O 0.379 0.225 0.120 0.030 0.059 0.033 84.60 -

Montaño Construction & Development Corporation 19473

Rd. Upgrading (Gravel to Concrete) IS, Dipolog-Punta-Dansullan-S. Osmeña-Zamboanga Norte/Sur Bdry. from

K1885+000-K1855+292, K1885+573-K1887+000 Modified to K1884+891-K1885+321, K1885+546 - K1885+771,

K1887+494-K1887+999

08/22/12 IX 24.528 256 O 0.396 0.240 0.150 0.030 0.043 0.033 89.20 -

Montaño Construction & Development Corporation 19473 Widening of Jct. Polo-Dapitan Park Rd. 08/22/12 IX 26.697 240 O 0.354 0.240 0.135 0.030 0.043 0.033 83.50 -

Montaño Construction & Development Corporation 19473 Const. of Salug-Daku Bridge & Approaches along

Sindangan-Siayan-Dumingag-Mahayag Rd. 08/18/12 IX 27.645 210 O 0.365 0.218 0.150 0.030 0.038 0.033 83.40 -

Montano Construction & Development Corporation 19473 Maasin Airport Development Project 09/26/13 DOTC 29.295 150 C 0.495 0.200 0.300 - - - 99.47 97.44%

Outstanding Montano Construction &

Development Corporation 19473 Maasin Airport Development Project 10/30/13 DOTC 12.926 120 O 0.378 0.300 0.150 0.020 0.042 0.050 93.96 -

Montaño Construction & Development Corporation /

Montphil Construction Corp. (JV)JV-11-281

Road Upgrading (Gravel to Concrete) IS, Dipolog-Punta-Dansullan-S. Osmeña-Zamboanga Norte/Sur Bdry. from

K1871+000-K1872+167, K1874+361-K1875+000 Modified to K1889+942-K1891+282

08/22/12 IX 28.235 286 O 0.383 0.240 0.150 0.030 0.043 0.033 87.90 -

Montaño Construction & Development Corporation /

Montphil Construction Corporation (JV)

JV-11-281

Rd. Upgrading (Gravel to Concrete) IS, Dipolog-Punta-Dansullan-S. Osmeña-Zamboanga Norte/Sur Bdry. From

K1871+000-K1872+167, K1874+361-K1875+000 Modified to K1889+1942-K1891+282

11/29/12 IX 28.235 270 C 0.452 0.200 0.300 - - - 95.20 90.82% V. Satisfactory

Montaño Construction & Development Corporation / Westmin Enterprises and

Construction Services (JV)

JV-12-346

Rd. Upgrading (Gravel to Conc.), Int. Sect., along Dipolog-Punta-Dansullan-Sergio Osmeña, ZDN/SIJR. From K1880+4915-K1880+5146; K1880+537 -K1885+120; K1888+096-K1889+000 to K1888+(-133)-K1889+373

08/20/13 IX 30.393 158 O 0.314 0.296 0.000 0.030 0.042 0.033 71.50

Montaño Construction & Development Corporation / Westmin Enterprises and

Construction Services (JV)

JV-12-346

Rd. Upgrading (Gravel to Conc.) Int. Sect., along Dipolog-Punta-Dansullan-Sergio Osmeña, ZDN/SIJR. from K1880+4915-K1880+5146; K1880+5371-K1885+120; K1888+096-K1889+000 to K1888+(-133)-K1889+373

03/22/13 IX 30.393 129 O 0.361 0.237 0.150 0.030 0.037 0.033 84.80 -

MONTAÑO CONSTRUCTION & DEVELOPMENT

CORPORATION/RUDHIL CONSTRUCTION ENTERPRISES,

INC. (JV)

JV-13-746Widening of Taway Bridge along Ipil-Liloy-Sindangan Road

Section Bridge Station: Km. 2012+391.08 - Km. 2012+417.13

10/23/2014 IX 26.454 315 O 0.355 0.240 0.129 0.030 0.040 0.033 82.70% 82.7% Satisfactory

Montaño Construction & Development Corporation/Westmin

Enterprises and Construction Services (JV)

JV-13-272

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road Standard (HDM-4 Project Analysis) (Intermittent

sections) Ilaya-Isis-Polanco Road K1814+(-892) to K1814+(-683) - K181+(206) to K1814+046

8/14/2014 IX 66.486 176 OG 0.330 0.300 0.150 0.030 0.040 0.050 90.00

Montaño Construction & Development Corporation/Westmin

Enterprises and Construction Services (JV)

JV-12-346

Road Upgrading (Gravel to Paved) Based on Gravel/Strategies, Traffice Benchmark for Uograding to

Paved Road Standard(HDM-4 Project Analysis) Intermittnet sections along Dipolog-Punta Dansullan-Sergio Osmeña,

ZDN/Sur Boundary From K1880+4195 - K1880+5146; K1880+5371 - K1885+120; K1888+096 - K1889+000 -

K1889+373

8/1/4/14 IX 30.393 188 C 0.450 0.150 0.300 90.00 82.89% Satisfactory

MONTANO CONSTRUCTION & DEV'T. CORPORATION 19473 Maasin Airport Development Project 03/12/14 DOTC 12.926 120 C 0.436 0.200 0.300 - - - 93.64 93.84%

Very Satisfactory

MONTANO CONSTRUCTION AND DEVELOPMENT CORPORATION 19473 Dipolog Airport Development Project 08/27/15 DOTC 52.516 588 O 0.399 0.300 0.150 0.020 0.050 0.050 96.90 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page190

Page 191: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

MONTANO CONSTRUCTION AND DEVELOPMENT CORPORATION 19473 Maasin Airport Development Project 04/14/15 DOTC 57.589 426 O 0.400 0.300 0.000 0.030 0.061 0.050 84.10 -

MONTANO CONSTRUCTION AND DEVELOPMENT CORPORATION 19473 Dipolog Airport Development Project 06/11/15 DOTC 52.516 420 O 0.386 0.300 0.150 0.020 0.032 0.050 93.87 -

Monte Construction & Supply 19474 Conc. of Bambang-Kasibu-Quezon-Solano Rd., Bumolos Camp Sect. 06/07/10 II 9.645 180 O 0.371 0.240 0.150 0.030 0.042 0.033 86.60 -

Monte Construction & Supply 19474 Colocol Integrated CIS Rehabilitation & Extension Project 05/12/12 NIA 7.648 204 C 0.418 0.200 0.300 - - - 91.82 90.26% V. Satisfactory

Montphil Construction Corporation 24285 Completion of MPB (Gym) 06/12/10 IX 1.905 110 O 0.397 0.240 0.150 0.030 0.029 0.050 89.60 -

Morning Steel Construction 30698Repair/Impv't. of Baler-Casiguran Rd. K0224+000-

K0248+700 (Int. Sect.) modified to K0244+000-K0248+700 (Int. Sect.)

08/10/13 III 8.955 102 C 0.432 0.133 0.300 - - - 86.50 *86.50% Satisfactory

Morning Steel Construction 30698 Const./Repair/Rehab. of Quezon St. (12M Right-of-Way extension w/ Drainage Impvt.) 06/05/10 III 9.402 150 O 0.365 0.239 0.150 0.030 0.054 0.033 87.10 -

Morning Steel Construction 30698 Rehab./Improvement of Debucao-Diome FTMR 09/08/09 III 4.717 150 O 0.359 0.228 0.150 0.030 0.050 0.033 85.00 -

Morning Steel Construction 30698 Maint./Repair & Rehab. of Infra Facility/Flood Control & Drainage System, Suklayin Flood Control 11/27/12 III 2.768 124 O 0.327 0.240 0.150 0.030 0.047 0.050 84.40 -

Morning Steel Construction 30698 Maint./Repair & Rehab. of Infra Facility/Flood Control & Drainage System, Buhangin Flood Control, Brgy. Buhangin 11/27/12 III 2.772 123 O 0.310 0.240 0.150 0.030 0.047 0.050 82.70 -

Mountaineers Engineering & Const. Services 6154 Restoration of Roadslip/Rd. Cut along Tublay (K0264+200-

K0268+900) 11/21/12 CAR 2.909 155 O 0.307 0.300 0.150 0.020 0.033 0.033 84.30 -

Mountaineers Engineering & Construction Services 6154 Const. of 2-Storey, 4-CL Benguet NHS-Beckel Annex 05/20/09 CAR 4.429 277 O 0.371 0.229 0.150 0.030 0.035 0.050 86.50 -

Mountaineers Engineering & Construction Services 6154 Rehab./Reconst. Of Bontoc-Cadre Road 08/04/12 CAR 19.236 225 C 0.426 0.200 0.300 - - - 92.60 82.16%

SatisfactoryMountainers Engineering &

Construction Services 6154 Restoration of Roadslip/Rd. Cut along Tublay, Benguet (K0264+200-K0268+900) 03/14/13 CAR 2.909 155 C 0.426 0.133 0.300 - - - 85.90 84.94%

Satisfactory

MPJR Builders Co. 20446 Prev. Maint. (Int. Sect.), Arterial Rd., N. Bacalso Ave. (Osmeña Blvd. Sect.), Chainage 0000-Chainage 0840 08/24/13 VII 15.741 65 C 0.399 0.136 0.300 - - - 83.50 *83.50%

Satisfactory

MPJR Builders Co. 20446

Rehab., Reconst./Upgrading of Epifanio De Los Santos Avenue (EDSA), (Cluster B) (IS) (K0027+415-K0027+602 /

K0028+034-K0028+700 / K0028+700-K0029+800 / K0027+602-K0028+034)

03/22/12 NCR 18.454 171 C 0.366 0.200 0.300 - - - 86.60 91.82% V. Satisfactory

MQR Construction and Supplies 33664 Major Repair/Maintenance of Existing Permanent Bridge, Cabangan Bridge along Daang Maharlika 8/11/2014 V 0.851 60 C 0.325 0.200 0.300 82.50 82.50%

Satisfactory

MRB Construction and Supply 17701 Const. of Rehabilitation of Rock Causeway at Port of Dingalan, Aurora Province (Ports & Harbor) 02/21-25/11 PPA 16.279 180 O 0.364 0.299 0.010 0.030 0.065 0.033 80.15 -

MRB Construction and Supply 17701 Repair of Damaged Facilities (Conc. Pavement, Fence, Drainage and Lighting System) 03/1-4/11 PPA 12.883 136 O 0.397 0.300 0.150 0.030 0.070 0.050 99.65 -

MRB Construction Corp. 17701 Construction of RoRo Ramp at El Codo Canal, Pasig River 12/12/13 PPA 19.666 180 O 0.400 0.300 0.006 0.030 0.065 0.033 83.49 -

MRB Construction Corporation 17701 Construction of Back-Up Area and Ext. of Pier 05/23/14 PPA 98.109 360 O 0.356 0.300 0.150 0.024 0.051 0.050 93.10 -MRB II CONSTRUCTION

CORPORATION (Formerly: MRB Construction and Supply)

17701 Asphalt Overlay with Concrete Blocking of Kamuning Road, Quezon City, K0011+(-245) - K0011+328 8/15/2014 NCR 11.976 165 C 0.493 0.133 0.300 92.60 92.60%

Very Satisfactory

MRB11 Construction Corporation 17701 Construction of Back-Up Area and Extension of Pier 05/22/15 PPA 98.109 409 C 0.473 0.200 0.269 - - - 94.20 93.50% V. Satisfactory

MRB11 Construction Corporation (Formerly: MRB Construction and

Supply)17701 Conc. & Impvt. of Rd., Magsaysay Ave., University of the

Philippines, Phase I 11/29/12 NCR 9.475 162 C 0.370 0.200 0.300 - - - 87.00 82.62% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page191

Page 192: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

MRB11 Construction Corporation (Formerly: MRB Construction and

Supply)17701 Conc. & Impv't. of Road, Magsaysay Ave., University of the

Philippines, Quezon City, Phase I 08/13/12 NCR 9.476 135 O 0.249 0.300 0.150 0.030 0.035 0.033 79.70 -

MRRM TRADING & CONSTRUCTION 19657 Construction/Rehabilitation/Raising of Grade of Alabang-

Muntinlupa Road, S03264LZ, K0030+535-K0031+024 11/17/2014 NCR 15.932 174 O 0.348 0.300 0.050 0.030 0.039 0.000 76.70% 76.7% Unsatisfactory

MRRM Trading & Construction 19657Construciton of Two-Storey, Four-Classroom School

Building with Comfort Room, Dr. Rodolfo V. Pamor MHS (Sagnay Western Annex High School)

8/9/2014 V 4.435 150 C 0.388 0.200 0.300 88.80 86.49% Satisfactory

MRRM Trading & Construction 19657 Const. of 2-Storey 4- Cl. Sch. Bldg. w/ CR, Dr. Rodolfo V. Pamor MHS (Sagnay Western Annex HS) 08/02/13 V 4.435 120 O 0.334 0.256 0.150 0.030 0.052 0.033 85.50

MRRM Trading and Construction Const. of 3-Storey 15 School Building 08/23/12 NHA 22.103 180 O 0.349 0.284 0.150 0.020 0.045 0.050 89.76 -

MRRM Trading and Construction Const. of 3-Storey 15 School Building 10/10/12 NHA 22.103 180 O 0.300 0.231 0.145 0.030 0.042 0.030 77.83 -

MS Cruz Builders & Trading 33697 Conc. of Brgy. Road, Babo Pangulo 07/31/13 III 0.961 20 C 0.452 0.133 0.300 - - - 88.50 *88.50% Satisfactory

MSB VITUG CONSTRUCTION 33019 Rehabilitation and Development of Estero De San Miguel 07/08/14 PRRC 52.373 270 O 0.356 0.243 0.150 0.010 0.031 0.050 84.06 -

MSB VITUG CONSTRUCTION 33019 Rehabilitation and Development of Estero de Concordia 03/25/14 PRRC 9.733 180 O 0.363 0.300 0.051 0.024 0.035 0.050 82.30 -

MSB VITUG CONSTRUCTION 33019 Rehabilitation and Development of Estero de Concordia 05/06/14 PRRC 9.733 180 C 0.431 0.200 0.196 - - - - 82.46% Satisfactory

MSB VITUG CONSTRUCTION 33019 Rehabilitation and Development of Estero De Aviles 03/28/14 PRRC 6.838 150 C 0.426 0.200 0.177 - - - - 74.96% Poor

MSDLR Construction Construction of Passenger Terminal Building 12/09/13 PPA 24.840 300 C 0.486 0.200 0.300 - - - 98.60 96.98% Outstanding

MSDLR Construction 32266 Construction of Passenger Terminal Building 06/07/13 PPA 24.840 300 C 0.379 0.300 0.150 0.030 0.060 0.050 96.90 -

MSE Construction & Trading Corp. 133127 Asphalt Overlay w/ correction along Quezon Blvd. 07/29/13 NCR 3.051 58 C 0.431 0.133 0.300 - - - 86.40 *86.40% Satisfactory

Mulana Construction 30708 Construction of School Building Cawag P/S 09/10/09 VII 0.580 165 O 0.400 0.155 0.150 0.030 0.037 0.033 80.50 -Multi-System Construction &

Development Corp.Repair of Conc. Pavement/Paving Blocks & Gaps of Conc.

Piles & Blocks 06/26/15 PPA 18.923 172 C 0.453 0.106 0.300 - - - 85.86 *85.86% Satisfactory

Multi-System Construction & Development Corporation 26920 Various Repair at Port of Casiguran, Aurora Province 04/10/15 PPA 23.392 130 O 0.400 0.300 0.150 0.030 0.063 0.050 99.26 -

Multi-System Construction and Development Corporation 26920 Repair of Sidewalk/Curb and Gutter at 25th St., A.C.

Delgado 12/12/13 PPA 11.076 106 O 0.388 0.300 0.118 0.030 0.070 0.050 95.60 -

Multi-System Construction and Devt. Corp 26920 Repair of Sidewalk/Curb and Gutter at 25th St., A.C.

Delgado 04/25/14 PPA 11.076 121 C 0.485 0.200 0.267 - - - 95.17 95.43% V. Satisfactory

MUST ENTERPRISES 13336

Road Upgrading (Gravel to Concrete) along Kapinpilan - Lumpog Road, Sambolawan, Midsayap, Cotabato Km.1706+430 - Km. 1707+420 (104 Embankment),

Km.1706+430 - Km. 1707+415 (311 PCCP)

8/11/2014 XII 24.801 139 C 0.442 0.189 0.300 93.10 93.10% Very Satisfactory

Must Enterprises 13336Road Upgrading (Gravel to Concrete) Nat'l Secondary Rd., Km.1684+(-257) - Km.1684+779 along Paco-Roxas-Arakan

Valley08/18/11 XII 19.704 200 O 0.380 0.300 0.039 0.030 0.050 0.033 83.20 -

Must Enterprises 13336 Const. of MPB at Don E. Sero E/S 06/01/10 XII 1.920 79 O 0.329 0.240 0.150 0.030 0.035 0.033 81.70 -Must Enterprises 13336 Const./Conc. of Cotabato Airport at Awang 05/26/09 R-XII 19.058 138 O 0.342 0.300 0.150 0.030 0.055 0.033 91.00 -

Must Enterprises / Rden Construction & Supply (JV) JV-12-235

Rd. Upgrading (Gravel to Concrete) along Kapinpilan-Lumupog Rd., Km.1704+(-294)-Km.1706+430.20 Kapinpilan

Sect.08/12/13 XII 43.234 203 O 0.338 0.300 0.150 0.030 0.058 0.033 90.90

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page192

Page 193: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

MUST ENTERPRISES/RDEN CONSTRUCTION AND SUPPLY

JOINT VENTUREJV-12-235

Road Upgrading (Gravel to Concrete) along Kapinpilan - Lumpog Road, Midsayap, Cotabato Km.1704+(-294) - Km.

1706+270.208/11/2014 XII 43.234 203 C 0.424 0.200 0.300 92.40 91.50%

Very Satisfactory

MWJ CONSTRUCTION - Road Opening/Upgrading of Burauen-Albuera Road including Bridges, Leyte-Burauen Side, Leyte 2nd District 10/29/2014 VIII 45.109 179 O 0.393 0.276 0.150 0.015 0.040 0.033 90.70% 90.7%

Very Satisfactory

MWJ Construction 14882 Const./Rehab./Conc. of Rd., San Rafael-San Agustin-Magsaysay Jct. Calipayan-Del Pilar Rd. 08/17/13 VIII 14.261 120 C 0.496 0.133 0.300 - - - 92.90 *92.90%

V. Satisfactory

MWJ Construction 14882 Rd. Upgrading of Burauen-Mahagnao Rd., Km.0981+926.00-Km.0983+000 08/17/13 VIII 34.489 160 C 0.466 0.133 0.225 - - - 82.40 *82.40%

Satisfactory

MWJ Construction 14882Repair/Impv't. of Flood Control Structures: A. Burauen-La Paz Rd., Km.981+108, Burauen-La Paz Rd. Sect., Tabon-

Tabon03/11/13 VIII 2.371 150 C 0.372 0.180 0.300 - - - 85.20 84.60%

Satisfactory

MYMS CONSTRUCTION AND SUPPLY 36258 Rehabilitation of Multi-Purpose Building, Tubay 10/20/2014 XIII 1.972 90 O 0.343 0.240 0.150 0.020 0.027 0.050 83.00% 83%

Satisfactory

N & N Construction Corporation 30716Repain/Construction/ Rehabilitation and Improvement

(Road Slip) along Nasugbu-Ternate Road, Batangas, First Legislative District, K0121+700 to K0121+767.50

8/6/2014 IV-A 8.402 210 C 0.402 0.200 0.300 90.20 90.20% Very Satisfactory

N & N Construction Corporation 30716 Package I - Repair/Maintenance 1. Sto. Niño River Control, Sto. Niño 08/09/11 III 1.956 100 O 0.340 0.180 0.000 0.022 0.035 0.033 61.00 -

N. B. SALBO CONSTRUCTION 6091 COMPLETION OF ACADEMIC BUILDING I PHASE II 04/03/14 DOST 5.635 120 C 0.473 0.200 0.180 - - - - 82.99% Satisfactory

N. Congson Construction & Supply 25695Replacement/Rehab./Strengthening of Permanent Bridges

Gen. from Bridge Mgt. System (BMS), Calabanit Bridge along Sarangani-Davao del Sur Coastal Rd.

08/20/13 XII 3.600 127 C 0.472 0.133 0.300 - - - 90.50 *90.50% V. Satisfactory

N. Congson Construction & Supply 25695Upgrading (Gravel to Concrete) Jct. Nat'l Highway

(Sarangani-Davao del Sur Coastal Rd. to Gumasa White Beach Rd.), Gumasa

08/20/13 XII 17.772 150 C 0.411 0.197 0.300 - - - 90.80 88.70% Satisfactory

N. Congson Construction & Supply 25695Upgrading (Gravel to Concrete) Jct. Nat'l Highway

(Sarangani-Davao del Sur Coastal Rd. to Gumasa White Beach Rd.), Gumasa

03/22/13 XII 17.772 137 O 0.367 0.234 0.150 0.030 0.042 0.050 87.30 -

N. Congson Construction & Supply 25695 Rehab./Impv't. of Small Margus River Flood Control Structure along Sarangani-Davao del Sur Coastal Rd. 03/22/13 XII 7.544 178 C 0.417 0.133 0.300 - - - 85.00 85.30%

Satisfactory

N. Q Villapando Construction 13338 Butuan Airport Development Project 04/20/15 DOTC 27.014 240 C 0.478 0.200 0.300 - - - 97.81 93.53% V.Satisfactory

N. Q. Villapando Construction 13338 Surigao Airport Development Project 09/17/15 DOTC 22.327 390 C 0.470 0.200 0.300 - - - 97.03 *97.05% Outstanding

N. Q. VILLAPANDO CONSTRUCTION 13338 Surigao Airport Development Project 09/16/14 DOTC 21.519 300 O 0.382 0.300 0.150 0.030 0.058 0.050 97.06 -

N. Q. VILLAPANDO CONSTRUCTION 13338 Butuan Airport Development Project 09/18/14 DOTC 27.014 240 O 0.387 0.240 0.150 0.030 0.060 0.050 91.71 -

N.B Avila Construction 30983 Road Upgrading (Gravel to Paved) of Jct. MWCR San Jose Airport - Jct. Bubog Rd., Brgy. Bubog 05/25/10 IVB 5.394 90 O 0.390 0.238 0.150 0.030 0.060 0.033 90.10 -

N.B Avila Construction 30983 Rechanneling of Busuanga River, Pitogo 05/25/10 IVB 0.574 60 O 0.400 - 0.200 0.025 0.079 0.167 87.10 -

N.B Garcia Construction/ F.A. Torres Construction (JV) JV-08-288 Road Upgrading (gravel to paved), MWCR, Rizal-Calintaan

(San Pedro-Mangat Section) KO 256+028- KO 256+733 08/31/09 IVB 9.646 164 O 0.345 0.298 0.150 0.030 0.037 0.033 89.30 -

N.B Garcia Construction/ F.A. Torres Construction (JV) JV-08-288 Road Upgrading (Gravel to Paved) MWCR, Rizal-Calintaan

(San Pedro-Mangat Section) 05/29/09 IV-B 9.565 90 O 0.281 0.300 0.150 0.030 0.033 0.050 84.40 -

N.B Salbo Construction 6091Rehab./Reconst./Upgrading along Misamis Oriental-Ma.Cristina Bdry. Road, Dalipuga Centenial-Tag-ibo Section, Sta.1514+000 - Sta.1514+781 w/ exceptions

06/07/10 X 13.912 120 O 0.366 0.240 0.150 0.030 0.055 0.050 89.10 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page193

Page 194: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

N.B Salbo Construction 6091 Road Upgrading (Gravel to Paved) of Gingoog-Claveria-Villanueva Road Km.1362+580.794 - Km.1363+764.294 06/10/10 X 19.297 105 O 0.374 0.235 0.150 0.023 0.050 0.033 86.50 -

N.B Salbo Construction 6091 Rehab. / Reconst. of Damaged Road Sections along Linamon-Zamboanga Road (Taguitic Section) 11/28/08 X 19.212 455 O 0.251 0.300 0.100 0.024 0.045 0.100 82.00 -

N.B Salbo Construction 6091 Road Upgrading (Gravel to Concrete) based on GTRSTB, Gingoog-Claveria-Villanueva Road 03/11/09 X 19.293 165 O 0.347 0.233 0.150 0.030 0.050 0.033 84.30 -

N.B. AVILA CONSTRUCTION 13751Construction/Rehabilitation of Flood Control Projects in

Isabela 4th DEO/4th LD - Magabito Flood Control, K0000+000 - K0000+126

10/27/2014 II 7.954 114 C 0.400 0.160 0.300 - - - 86.00% 86% Satisfactory

N.B. AVILA CONSTRUCTION 13751 Construction of Flood Control along Tagaytay-Manila via Silang Road 11/6/2014 IV 10.486 180 C 0.445 0.133 0.300 - - - 87.80% 87.8%

Satisfactory

N.B. Avila Construction 13751Rehabilitation of Diversion Works of Tres Cruzes River

Irrigation System 02/14/15 NIA 9.616 150 C 0.433 0.160 0.300 - - - 89.33 *89.33% V. Satisfactory

N.B. Avila Construction 13751Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds.

(MFO-2) along Tagaytay-Cavite via Mendez Rd., K0062+280-K0062+900

08/13/12 IVA 8.969 94 C 0.438 0.200 0.300 - - - 93.80 94.22% V. Satisfactory

N.B. SALBO CONSTRUCTION 6091 COMPLETION OF DORMITORY BLDG II PHASE II 12/13/12 DOST 20.564 C 0.472 0.200 0.210 - - - - 91.65% V. Satisfactory

N.B. Salbo Construction 6091Rd. Upgrading (Gravel to Paved) (Int. Sect.) inc. Drainage &

Rd. Facilities along LDNICR (Balo-i) to Pantao Ragat Rd., Km.1547+(-663)-Km.1548+000; Km.1548+000-Km.1548+250

08/13/13 X 40.357 152 C 0.414 0.133 0.300 - - - 84.70 83.26% Satisfactory

N.B. Salbo Construction 6091Road Upgrading (Gravel to Paved) (Int. Sect.) inc. Drainage & Rd. Facilities along LDNICR (Balo-I) to Pantao Ragat Rd., Km.1547+(-663)-Km.1548+000; Km.1548+000-Km.1548+250

03/13/13 X 38.894 132 O 0.305 0.300 0.150 0.000 0.035 0.033 82.30 -

N.B. Salbo Construction 6091Road Upgrading (Gravel to Paved) (Int. Sect.) Secondary; Balo-I-Pantao Rd., Km.1553+(-100)-Km.1553+700, Pantao

Ragat03/13/13 X 18.910 80 C 0.399 0.144 0.300 - - - 84.30 *84.30%

Satisfactory

N.B. Salbo Construction 6091 `Completion of Dormitory Bldg II Phase II 08/25/11 DOST 20.564 O 0.395 0.300 0.150 0.033 0.023 0.030 93.13 -

N.C. AGUILAR CONST. & SUPPLY INC. 36949 Upgrading /Box Culvert along Villanueva Creek, Schillings

Lane (Villanueva Village), Barangay San Dionisio 11/18/2014 NCR 6.416 237 O 0.251 0.240 0.100 0.030 0.055 0.033 70.90% 70.9% Poor

N.D.M. Sanchez Builders & Development Corporation 35410 Widening of Daang Maharlika inc. Drainage System, Sto.

Tomas Sect., Sto. Tomas Sect., K062+570-K063+509.50 08/01/13 IVA 36.602 210 O 0.334 0.243 0.150 0.030 0.040 0.033 83.00

N.D.M. SANCHEZ BUILDERS & DEVELOPMENT CORPORATION/IKM BUILDERS & CONSTRUCTION SUPPLY 

JOINT VENTURE

JV-13-237 Widening of Manila-Batangas, Aguila Section K0093+960-K0095+465.30 (Both Side) 12/5/2014 IV 36.667 210 C 0.483 0.133 0.300 - - - 91.60% 91.6%

Very Satisfactory

N.K Enterprise 29292 Rehab./Imprv't. of Various Brgy. Rds. At Villafont & Imparayan 02/25/10 VI 18.922 210 O 0.338 0.263 0.150 0.020 0.030 0.033 83.40 -

N.K. ENTERPRISE 29292 Replacement/Const. of Ipil Bridge Km. 160+947.97, Ipil , Barbaza, Antique 8/13/2014 VI 16.379 245 C 0.370 0.200 0.000 57.00 77.82%

Unsatisfactory

N.K. Enterprise 29292 Replacement/Const. of Ipil Bridge, Km. 160+947.97, Brgy. Ipil 08/15/13 VI 16.381 210 O 0.362 0.300 0.150 0.030 0.042 0.033 91.70 -

N.K. Enterprise 29292 Const. of Drainage & Slope Protection Works along Bacolod South Rd., K0099+100-K0103+900 w/ exc. 08/08/13 VI 9.603 188 C 0.430 0.133 0.300 - - - 86.30 86.48%

Satisfactory

N.K. Enterprise 29292 Const. of Drainage & Slope Protection Works along Bacolod South Rd., K099+100-K0103+900, w/ exception 03/13/13 VI 9.603 170 O 0.322 0.295 0.132 0.024 0.060 0.033 86.60 -

N.M.E. Construction 22984 Proposed Repair/Rehab. of Rds. & Alleys and its Vicinities, Brgy. 790, Sta. Ana & Onyx St., San Andres Bukid 03/13/13 NCR 1.952 120 C 0.491 0.067 0.300 - - - 85.80 *85.80%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page194

Page 195: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

N.S Gambito Construction Services 31640 Concreting of Aritao-Quirino Road, Bitnong Section 06/04/09 II 9.650 104 O 0.328 0.240 0.150 0.030 0.051 0.050 84.90 -

N.V. BALBUENA CONSTRUCTION 12055Construction of Two (2) Storey Four (4) Classrooms,

Mariveles National High School - Cabcaben Annex (Batangas II)

8/13/2014 III 4.707 120 C 0.444 0.133 0.300 87.70 87.70% Satisfactory

N.V. Balbuena Construction 12055 Repair/Maint of Tenejero River Control (Maite Sect.) 03/14/13 III 1.860 56 C 0.440 0.133 0.300 - - - 87.30 *87.30% Satisfactory

Naga E.S. Construction and Supply 6593 Const. of MPB Brgy. Pacol 08/13/12 V 4.762 180 C 0.496 0.133 0.300 - - - 92.90 88.07% Satisfactory

Nascon Builders 14786 Const. of Multi-Purpose Building, Brgy. CP Garcia 06/02/09 X 1.060 75 O 0.374 0.276 0.110 0.030 0.019 0.033 84.20 -

NBL CONSTRUCTION 16722

Preventive Maintenance of National Arterial Road based on PMS/HDM-4 (Intermittent Sections) along Palico-Balayan-Batangas Road at: 1. K0097+535-K0098+002; 2.K0098+736-K0099+066; 3. K0103+230; 4.K0113+000-K0113+800 and 5.

K0128+000-K0128+230

11/8/2014 IV 7.190 90 C 0.487 0.127 0.300 - - - 91.40% 91.4% Very Satisfactory

NBL Construction 30396 Repair/Rehab./Impv't of Manila-Batangas Rd., K0066+560-K0067+600 w/ exceptions Malvar Sect. 08/01/13 IVA 9.841 40 C 0.468 0.133 0.300 - - - 90.10 *90.10% V.

Satisfactory

NBL Construction 30396 Prev. Maint. (MFO-1) (Int. Sect.), Tanauan-Talisay-Tagaytay Rd., K0074+949-K0076+083 08/02/13 IVA 8.966 45 C 0.455 0.133 0.300 - - - 88.80 *88.80%

Satisfactory

NBL Construction 30396Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds.

(MFO-2), Nat'l Secondary Rd., Banay-banay-Mojon Cuenca Rd., Cuenca & Alitagtag

03/21/12 IVA 38.388 180 C 0.400 0.200 0.300 - - - 90.00 89.58% V. Satisfactory

NBL Construction 30396 Rehab./Reconst./Upgrading of Bauan-Mabini Road K0171+344-K0172+288 03/22/12 IVA 10.606 150 C 0.409 0.133 0.300 - - - 84.20 87.50%

Satisfactory

NBL Construction 30396 Repair/Rehab./Impv't. of Tanauan-Talisay-Tagaytay Rd. K0079+196-K0080+200, (Int. Sect.) 03/14/13 IVA 9.695 60 C 0.438 0.133 0.300 - - - 87.10 *87.10%

Satisfactory

NBL Construction 30396 Const./Completion of MPB (Philippine Nat'l. Red Cross Bldg.) 03/12/13 IVA 4.999 164 C 0.430 0.133 0.300 - - - 86.30 *86.30%

Satisfactory

NBL Construction / Vicmar Construction, Inc. Joint Venture JV-09-090 Conc./Widening/Impvt. of Bauan-Mabini Circumferential

Rd. 06/04/10 IVA 57.895 90 O 0.365 0.240 0.150 0.023 0.048 0.050 87.60 -

NDM Equipment Rental and Construction

Land Development of Tacloban North Resettlement Project Phase 2 with Road Concreting of Phase I 02/28/15 NHA 40.818 200 O 0.377 0.242 0.150 0.024 0.054 0.050 89.65 -

NDM Sanchez Builders and Development Corporation 35410

Widening of Daang Maharlika including Drainage System, Sto. Tomas Section, K0062+570 to K0063+509.50, Sto.

Tomas, Batangas8/9/2014 IV-A 37.579 240 C 0.434 0.200 0.300 93.40 87.16%

Satisfactory

Nes-san Builders 25142 Repair/Rehab./Impvt. of Angeles-Porac Rd., Angeles City Km.0084+000-Km.0084+700 w/ exception 08/06/13 III 9.504 15 C 0.462 0.133 0.300 - - - 89.50 *89.50% V.

Satisfactory

Nes-san Builders 25142 Repair/Rehab./Impv't. of San Fernando-Lubao Rd., San Pablo-San Antonio K0079+000-K0081+000 (w/ exception) 07/31/13 III 9.380 60 C 0.425 0.133 0.300 - - - 85.80 *85.80%

Satisfactory

New Arcond Builders Incorporated (Formerly: Arcond Builders) 9614

Concrete Widening/Conc. Blocking w/ Drainage & Sidewalk Impv't. along Araneta Ave. K0009+646+(-033)

Northbound08/05/13 NCR 31.295 249 O 0.303 0.224 0.105 0.030 0.045 0.033 74.00

NEW ARCOND BUILDERS INCORPORATED / ALPIZ

CONSTRUCTION AND DEVELOPMENT CORP. JOINT

VENTURE

JV-13-445 Improvement of Roosvelt Avenue (K0007+940 to K0010+811) 8/14/2014 NCR 17.370 180 C 0.474 0.133 0.300 90.70 90.70%

Very Satisfactory

NEW BIG FOUR J CONSTRUCTION INC. (Formerly: Four J Costruction) 15104 Construction/Rehabilitation of Flood Control in Laguna 1st

DEO/4th LD, Lumban River 11/26/2014 IV 45.570 235 O 0.337 0.300 0.000 0.030 0.023 0.033 72.30% 72.3% Poor

NEW BIG FOUR J CONSTRUCTION INC. (Formerly: Four J Costruction) 15104

Cluster II for the Preventive Maintenance (MFO-1) of Paete-Famy Poblacion Road, A. K0103+-1472 to K0103+-977; B. K0110+-088 to K0111+490; C. K0112+000 to K0112+810

11/26/2014 IV 26.896 60 C 0.355 0.200 0.300 - - - 85.50% 85.5% Satisfactory

New Big Four J Construction, Inc. 15104 Rehab./Reconst./Upgrading of Marikina-Victoria Valley-Antipolo Road 05/18/09 IV-A 19.209 180 O 0.389 0.240 0.150 0.020 0.030 0.050 87.90 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page195

Page 196: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

NEW BIG FOUR J CONSTRUCTION, INC. (Formerly: Four J Construction)/11 

DIAMOND EAGLE CONSTRUCTION (JV)‐

Construction/Rehabilitation of Flood Control in Laguna 2nd DEO/1st LD along Manila South Road at Brgy Tagapo,

K000+000-K00+381, Sta. Rosa City, Laguna11/28/2014 IV 9.202 165 C 0.386 0.200 0.300 - - - 88.60% 88.6%

Satisfactory

New C. C. Barcelona Construction Corporation 14489 Infrastructure Development of Veterans Regional Hospital 10/24/14 DOH 99.785 480 O 0.363 0.264 0.150 0.030 0.065 0.050 92.20 -

New Kanlaon Construction Inc. 896 Dicasalarin Point Lighthouse Development Project 01/17/13 DOTC 28.875 180 C 0.433 0.300 0.200 - - - 93.30 93.30% V. Satisfactory

New Kanlaon Construction inc./ JE Manalo & CO., Inc. (JV) 896

Southern Philippines Irrigation Sector Project SPISP(Construction of Binalawan Concrete Buttress Dam

& Appurtenant Facilities)06/12/10 NIA 167.797 378 O 0.382 0.211 0.00 0.030 0.033 0.017 67.30 -

New Kanlaon Construction Inc/ J E Manalo & Co., Inc (JV) 896 Southern Philippines Irrigation Sector Project (SPISP) 06/07-12/10 NIA 167.797 378 O 0.382 0.211 - 0.030 0.033 0.017 67.30 -

New Kanlaon Construction, Inc. 896 Concreting of Barotac Nuevo-Dumangas-Dacutan Wharf Road 06/11/09 VI 17.611 99 O 0.357 0.240 0.150 0.015 0.040 0.050 85.20 -

New Mindoreños Lumber, Hardware and General

Merchandise31745 Road Upgrading (gravel to paved) MWCR, Sablayan-Sta.

Cruz (Pag-asa-Amnay Section) KO 352+647-KO 354+004.5 08/30/09 IVB 19.158 179 O 0.365 0.296 0.150 0.030 0.042 0.033 91.60 -

New Mindoreños Lumber, Hardware and General

Merchandise31745

Road Upgrading (gravel to paved) MWCR, Sablayan-Sta. Cruz (San Vicente-Cabacungan Section) KO 329+363-KO

330+92108/30/09 IVB 19.175 182 O 0.350 0.300 0.150 0.030 0.042 0.033 90.50 -

New Mindoreños Lumber, Hardware and General

Merchandise31745

Road Upgrading (gravel to paved) MWCR, Sta. Cruz-Mamburao (Casoy-Balansay Section) KO 399+495-KO

400+87209/01/09 IVB 19.292 185 O 0.348 0.300 0.150 0.030 0.042 0.033 90.30 -

New Mindoreños Lumber, Hardware and General

Merchandise31745

Road Upgrading (gravel to paved) MWCR, Sta. Cruz-Mamburao (Pagbahan-Talabaan Section) KO 389+704-KO

391+15708/30/09 IVB 14.471 191 O 0.368 0.300 0.101 0.022 0.042 0.033 86.60 -

New Mindorenos Lumber, Hardware and General

Merchandise 31745 Road Upgrading (Gravel to Paved) MWCR, Sablayan-Sta.

Cruz (San Vicente-Cabacungan Section) 05/29/09 IV-B 19.176 140 O 0.351 0.300 0.150 0.030 0.037 0.033 90.10 -

New Mindorenos Lumber, Hardware and General

Merchandise 31745 Road Upgrading (Gravel to Paved) MWCR, Sablayan-Sta.

Cruz (Pag-asa Amnay Section) 05/29/09 IV-B 19.158 140 O 0.354 0.300 0.115 0.030 0.035 0.033 86.70 -

New Mindorenos Lumber, Hardware and General

Merchandise 31745 Road Upgrading (Gravel to Paved) MWCR, Sta. Cruz-

Mamburao (Casoy-Balansay Section) 05/30/09 IV-B 19.188 140 O 0.308 0.300 0.070 0.030 0.030 0.033 77.10 -

New Mindoreños Lumber, Hardware and General

Merchandise (Formerly: Mercedita Benasas General Merchandise)

31745 Replacement/Reconst. of Orobugan Bridge 1 along Crossing MWCR (Pola) - Casague-Jct. Alacaak Rd. 07/29/13 IVB 7.454 201 C 0.428 0.165 0.300 - - - 89.30 86.24%

Satisfactory

New Mindoreños Lumber, Hardware and General

Merchandise (Formerly: Mercedita Benasas General Merchandise)

31745 Replacement/Reconst. of Siburan Bridge along Jct. MWCR (San Isidro)-Penal Colony-Jct. Yapang Rd. 07/30/13 IVB 9.443 219 C 0.396 0.196 0.300 - - - 89.20 85.96%

Satisfactory

New Mindoreños Lumber, Hardware and General

Merchandise (Formerly: Mercedita Benasas General Merchandise)

31745Replacement/Reconst. of San Isidro Bridge 2 along Jct. MWCR (San Isidro)-Penal Colony-Jct. Yapang Rd., Brgy.

Malisbong07/30/13 IVB 7.475 215 C 0.376 0.200 0.160 - - - 73.60 79.84%

Unsatisfactory

New Mindoreños Lumber, Hardware and General

Merchandise (Formerly: Mercedita Benasas General Merchandise)

31745 Road Upgrading of Abra de Ilog-San Jose Rd.(Casoy Mimping Sect.) Brgy. Balansay 05/24/10 IVB 6.753 90 O 0.322 0.238 0.130 0.030 0.050 0.033 80.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page196

Page 197: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

New Mindoreños Lumber, Hardware and General

Merchandise (Formerly: Mercedita Benasas General Merchandise)

31745 Const. of Casague MPB 11/21/08 IV-B 0.864 45 O 0.329 0.240 0.100 0.030 0.027 0.100 82.60 -

New Mindoreños Lumber, Hardware and General

Merchandise (Formerly: Mercedita Benasas General Merchandise)

31745 Const. of Payompon Flood Control 03/12/12 IVB 3.810 60 C 0.402 0.133 0.300 - - - 83.50 86.44% Satisfactory

New Mindoreños Lumber, Hardware and General

Merchandise (Formerly: Mercedita Benasas General Merchandise)

31745 Replacement of Orobungan Bridge 3 along Crossing MWCR (Pola)-Casague-Jct. Alacaak Rd., Brgy. Kurtinganan 11/25/12 IVB 14.815 210 C 0.461 0.133 0.300 - - - 89.40 87.30%

Satisfactory

New Mindoreños Lumber, Hardware and General

Merchandise (Formerly: Mercedita Benasas General Merchandise)

31745Replacement/Reconst. of Orobugan Bridge 1 along

Crossing MWCR (Pola)-Casague-Jct. Alacaak Rd., Brgy. Kurtinganan

11/25/12 IVB 7.454 201 O 0.337 0.220 0.150 0.030 0.055 0.050 84.20 -

New Mindoreños Lumber, Hardware and General

Merchandise (Formerly: Mercedita Benasas General Merchandise)

31745Replacement/Reconst. of San Isidro Bridge 2 along Jct. MWCR (San Isidro)-Penal Colony-Jct. Yapang Rd., Brgy.

Malisbong11/25/12 IVB 7.476 185 O 0.327 0.240 0.150 0.023 0.050 0.050 84.00 -

New Mindoreños Lumber, Hardware and General

Merchandise (Formerly: Mercedita Benasas General Merchandise)

31745 Replacement/Reconst. of Siburan Bridge along Jct. MWCR-(San Isidro)-Penal Colony-Jct. Yapang Rd. 11/25/12 IVB 9.443 2,019 O 0.325 0.240 0.150 0.023 0.050 0.050 83.80 -

New Mindoreños Lumber, Hardware and General

Merchandise (Formerly: Mercedita Benasas General Merchandise)

31745 Replacement of Orubugan Br. 3 along MWCR (Pola) Casague-Jct. Alacaak Rd., Brgy. Kurtinganan 08/10/12 IVB 14.815 210 O 0.351 0.250 0.128 0.030 0.050 0.050 85.90 -

NEW RICH GENERAL CONTRACTOR SERVICES & TRADING COMPANY, INC.

27629Construction of Slope Protection (Drainage) along Bacolod

South Road, (Camansi Section, Phase II), K0021+770 - K0022+065 (Camansi Section)

10/22/2014 VI 5.742 80 C 0.446 0.133 0.300 - - - 87.90% 87.9% Satisfactory

New Rich General Contractor Services & Trading Company, Inc. 27629 Construction of Canal Structures of Kay Mangga CIS

Extension 02/14/15 NIA 1.163 120 C 0.333 0.200 0.300 - - - 83.30 *83.30% Satisfactory

New TBP Construction & Development Corp. 29155 Const. of Cross Drainage Structures along MNR 11/25/08 I 4.417 120 O 0.344 0.120 0.100 0.020 0.042 0.133 75.90 -

New TBP Construction & Development Corporation 29155 Construction of Cross Drainage Structures along MNR 08/25/09 I 4.417 337 O 0.358 0.265 0.150 0.030 0.045 0.033 88.10 -

NEW VIC CONSTRUCTION CORPORATION 13779 Construction of ER/Trauma Building Phase I 11/06/14 DOH 102.260 365 O 0.397 0.226 0.150 0.030 0.070 0.050 92.24 -

Newadis Construction 23806Road Upgrading (gravel to paved), MWCR, Calintaan-Sablayan (Bulangcog-Iriron Section) KO 276+468- KO

277+14108/31/09 IVB 9.650 192 O 0.344 0.294 0.150 0.030 0.037 0.033 88.80 -

Newadis Construction 23806 Const. of MPB Paluan NHS 05/24/10 IVB 1.440 100 O 0.356 0.240 0.150 0.030 0.029 0.033 83.80 -

Newadis Construction 23806 Road Upgrading (Gravel to Paved) MWCR, Calintaan-Sablayan (Bulangcog-Iriron Section) 05/30/09 IV-B 9.573 90 O 0.314 0.300 0.150 0.030 0.042 0.050 88.60 -

Newadis Construction 23806 Const. of MPB, Occ. Mindoro NHS, Brgy. 9 03/12/12 IVB 1.828 90 O 0.300 0.200 0.150 0.030 0.018 0.050 74.80 -

Newadis Construction 23806 Const. of MPB, Occidental Mindoro Nat'l High Sch. Brgy. 9 08/11/12 IVB 1.827 90 C 0.443 0.133 0.300 - - - 87.60 78.64% Unsatisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page197

Page 198: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Newbig Four J Construction Inc. (Formerly: Four J Construction) 15104 Completion of MPB at Philippine Drug Enforcement

Agency (PDEA) Compound 04/07/11 NCR 9.543 201 O 0.392 0.300 0.150 0.030 0.041 0.033 94.60 -

Newbig Four J Construction Inc. (Formerly: Four J Construction) 15104 Const. of Municipal Hall 06/01/10 IVA 33.705 210 O 0.388 0.300 0.150 0.030 0.052 0.033 95.30 -

Newbig Four J Construction Inc. (Formerly: Four J Construction) 15104 Const./Rehab. of Drainage System at Dr. A. Santos Ave. 11/27/12 NCR 14.227 195 C 0.493 0.200 0.300 - - - 99.30 90.06%

V. Satisfactory

Newbig Four J Construction Inc. (Formerly: Four J Construction) 15104 Impvt./Widening of Gen. Emilio Aguinaldo Highway-Manila-

Cavite Rd., IS inc. RROW, Km.17+512-Km.20+271 11/23/12 IVA 43.649 381 O 0.345 0.300 0.150 0.030 0.044 0.033 90.20 -

Newbig Four J Construction Inc. (Formerly: Four J Construction) 15104 Asphalt Overlay of Mcdonald Jct.-Alido Bridge (Chainage

0000-Chainage 0375) inc. Drainage System (0+000-0+408) 11/23/12 IVA 5.259 364 O 0.344 0.300 0.150 0.023 0.051 0.033 90.10 -

Newbig Four J Construction Inc. (Formerly: Four J Construction) 15104 Overlay 80mm Thick Sta. Rosa-Ulat-Tagaytay Road

K0039+100-K0044+000 (IS) 11/29/12 IVA 47.294 219 C 0.377 0.200 0.300 - - - 87.70 86.26% Satisfactory

Newbig Four J Construction Inc. (Formerly: Four J Construction) 15104 Widening of Molino-Bacoor Rd., K0014+800-K0016+986 11/24/12 IVA 77.597 375 O 0.311 0.276 0.150 0.030 0.040 0.033 84.00 -

Newbig Four J Construction Inc. (Formerly: Four J Construction) 15104 Const./Rehab. of Drainage System at Dr. A. Santos Ave. 08/02/12 NCR 14.109 180 O 0.329 0.240 0.150 0.030 0.040 0.050 83.90 -

Newbig Four J Construction Inc. (Formerly: Four J Construction) 15104 Overlay 80mm thick Sta. Rosa-Ulat-Tagaytay Road

K0039+100-K0044+000 (IS) 08/11/12 IVA 47.294 95 O 0.340 0.240 0.150 0.030 0.043 0.050 85.30 -

NewBig Four J Construction, Inc. 15104 Const. of Municipal Hospital Building 03/01/10 IVA 33.705 210 O 0.337 0.300 0.150 0.030 0.050 0.033 90.00 -

Newbig Four J Construction, Inc. (Formerly: Four J Construction) 15104 Asphalt Overlay of Manila South Rd., Prev. Maint. (MFO-1),

Int. Sect. 09/20/13 IVA 100.771 150 C 0.415 0.200 0.300 - - - 91.50 *91.50% V. Satisfactory

Newbig Four J Construction, Inc. (Formerly: Four J Construction) 15104 Asphalt Overlay of Mcdonald Jct.-Alido Bridge (Chainage

0000-Chainage 0375) inc. Drainage System (0+000-0+048) 08/14/13 IVA 5.262 363 C 0.317 0.200 0.300 - - - 81.70 86.74% Satisfactory

Newbig Four J Construction, Inc. (Formerly: Four J Construction) 15104 Impv't./Widening of Gen. Emilio Aguinaldo Highway-Manila-

Cavite Road, Int. Sect. inc. RROW, Km.17+512-Km.20+271 08/14/13 IVA 47.395 381 C 0.344 0.200 0.300 - - - 84.40 84.88% Satisfactory

Newbig Four J Construction, Inc. (Formerly: Four J Construction) 15104 Widening of Molino-Bacoor Rd., K0014+800-K0016+986 08/15/13 IVA 78.417 375 C 0.406 0.133 0.300 - - - 83.90 83.96%

Satisfactory

Newbig Four J Construction, Inc. (Formerly: Four J Construction) 15104 Widening of Daang Maharlika, K0054+570-K0055+117 (w/

exception) 03/21/13 IVA 47.471 324 C 0.424 0.135 0.300 - - - 85.90 85.06% Satisfactory

Newbig Four J Construction, Inc. (Formerly: Four J Construction) 15104 Widening/Rehab. Of Nat'l Road along Zapote-Salawag-

Salitran Rd., 2nd LD, Km.17+509- Km.18+015 (IS) 03/22/12 IVA 6.474 94 C 0.481 0.133 0.300 - - - 91.40 89.48% V. Satisfactory

Newbig Four J Construction, Inc. (Formerly: Four J Construction) 15104 Const. of MPB, Seaside Drive, Brgy. Tambo 03/21/13 NCR 3.450 100 C 0.460 0.123 0.300 - - - 88.30 *88.30%

Satisfactory

Newington Builders, INC. 17542 Widening of Lipa-Rosario Road, Lipa City Section, Lipa City, Batangas, Km. 81+500 to Km. 82+700 (with exception) 8/8/2014 IV-A 19.144 180 C 0.467 0.200 0.300 96.70 89.56%

Very Satisfactory

Newington Builders, Inc. (Formerly: E. Gardiola

Construction)17542 Repair/Rehab. & Impv't of Rd. Maharlika Highway,

K0081+400-K0083+000 (Int. Sect.) 08/12/13 IVA 24.626 30 C 0.435 0.133 0.300 - - - 86.80 *86.80% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page198

Page 199: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Newington Builders, Inc. (Formerly: E. Gardiola

Construction)17542 Const. of Lobo-Malabrigo-Laiya-San Juan Rd., Biga Sect. 08/03/13 IVA 43.649 278 C 0.467 0.188 0.300 - - - 95.50 95.08% V.

Satisfactory

Newington Builders, Inc. (Formerly: E. Gardiola

Construction)17542 Widening of Lipa-Rosario Rd., Lipa City Sect., (Km.81+500-

Km.82+700 w/ exception) 07/29/13 IVA 19.144 210 O 0.348 0.293 0.086 0.030 0.035 0.033 82.50

Newington Builders, Inc. (Formerly: E. Gardiola

Construction)17542 Widening of Lipa-Rosario Rd., Lipa City Sect., Km.81+500-

Km.82+700 (w/ exception) 03/11/13 IVA 18.313 150 O 0.371 0.240 0.150 0.030 0.047 0.033 87.10 -

Newington Builders, Inc. (Formerly: E. Gardiola

Construction)17542 Const. of Lobo-Malabrigo-Laiya-San Juan Road, Biga Sect. 11/29/12 IVA 43.650 248 O 0.393 0.300 0.150 0.030 0.042 0.033 94.80 -

NFH Construction & Supply Conctruction/Rehabilitation/Improvement of Ocampo Flood Control 8/8/2014 V 17.769 191 OG 0.342 0.300 0.046 0.020 0.047 0.033 78.80

NFH Construction & Supply 16055 Const. of Basag Bridge (Ligao-Sabloyon Road) 03/02/09 V 23.780 487 O 0.335 0.239 0.150 0.030 0.061 0.050 86.50 -NFH Construction & Supply 16055 Const. of Daguit 2 Bridge 03/13/09 V 19.650 714 O 0.341 0.240 0.000 0.030 0.056 0.050 71.70 -NFH Construction & Supply 16055 Const. of Daguit 2 Bridge 08/28/08 V 19.650 330 O 0.342 0.300 0.070 0.030 0.028 0.067 83.70 -NFH Construction & Supply

(Formerly: NFH Gravel & Sand) 16055 Mataoroc Bridge along Milaor-Minalabac-Pili Rd. Sect. 03/21/13 V 15.570 320 C 0.392 0.192 0.300 - - - 88.40 88.76% Satisfactory

NFH Construction & Supply (Formerly: NFH Gravel & Sand) 16055 Rehab. of Daang Maharlika, K0443+(-420)-K0446+724.36

Intermittent Sect. 03/22/13 V 23.449 139 C 0.394 0.186 0.300 - - - 88.00 86.92% Satisfactory

NFH CONSTRUCTION & SUPPLY (Formerly: NFH Gravel and Sand) 16055 Rehabilitation/Reconstruction/Upgrading of Damaged

Paved National Roads along Rolando Andaya Highway 11/9/2014 V 26.595 122 C 0.415 0.133 0.300 - - - 84.80% 84.8% Satisfactory

NFH Construction & Supply (Formerly: NFH Gravel and Sand) 16055 Prev. Maint.: Asphalt Overlay along Panganiban Rd. (Int.

Sect.) Sta. 0+975-Sta. 1+602 08/06/13 V 12.493 42 C 0.446 0.133 0.300 - - - 87.90 *87.90% Satisfactory

NFH Construction & Supply (Formerly: NFH Gravel and Sand) 16055 Prev. Maint./Asphalt Overlay along Daang Maharlika,

K0522+839-K0524+004 08/10/13 V 15.400 60 C 0.389 0.135 0.300 - - - 82.40 *82.40% Satisfactory

NFH Construction & Supply (Formerly: NFH Gravel and Sand) 16055 Widening/Impv't. of Rds. Cabrera-Kayticling-Antipolo Rd.,

Km.29+100-Km.30+400 (w/ exception) (Four Lanes) 03/22/13 IVA 38.618 328 C 0.436 0.133 0.300 - - - 86.90 88.10% Satisfactory

NFH Construction & Supply (Formerly: NFH Gravel and Sand) 16055 Rehab./Reconst. of Damaged National Road, Lakandula

Drive 05/27/09 V 32.610 120 O 0.343 0.240 0.150 0.023 0.035 0.050 84.10 -

NFH Construction & Supply (Formerly: NFH Gravel and Sand) 16055 Const. of Flood Control Project along Rangas River

(Upstream of Rangas River) 08/03/12 V 41.670 180 C 0.455 0.133 0.300 - - - 88.80 88.26% Satisfactory

NGP CONSTRUCTION 11369 Initao-Libertad Landscape and Seascape Development 2/26/15 TIEZA 8.000 240 C 0.325 0.184 0.300 80.90 87.3 Satisfactory

NGP Construction 11369 Repainting of Building Facades and Various Re-waterproofing Works 03/06/14 BPS 7.247 69 C 0.479 0.200 0.300 - - - 97.90 *97.90%

Outstanding

NGP CONSTRUCTION 11369 Initao-Libertad Protected Landscape & Seascape Dev't. Project 06/19/14 TIEZA 7.265 150 S 0.337 0.263 0.150 0.030 0.070 0.050 90.02

NGP Construction 11369 Replacement of Damaged Roofing and Wall Cladding Systems at BSP Roxas Branch Office 10/20/14 BSP 5.068 137 C 0.461 0.200 0.300 - - - 96.10 95.82%

V. Satisfactory

NGP Construction 11369 Replacement of Damaged Roofing and Wall Cladding Systems at BSP Tacloban Branch Office 10/23/14 BSP 5.202 137 C 0.435 0.200 0.300 - - - 93.50 95.79%

V. Satisfactory

NIRVANA CONSTRUCTION AND SUPPLIES 18691

Rehabilitation/Reconstruction/Replacement of Existing Permanent Bridges, Molok Bridge along Makar-Marbel

Road, Brgy. Labangal8/16/2014 XII 7.770 68 C 0.488 0.133 0.300 92.10 92.10%

Very Satisfactory

Nirvana Construction and Supplies 18691 Kidapawan City Resettlement Project/ LGU PABAHAY 03/29/15 NHA 23.926 345 C 0.433 0.200 0.300 - - - 93.33 89.09% V. Satisfactory

Nirvana Construction and Supplies 18691 Kidapawan City Resettlement Project/ LGU PABAHAY 01/09/15 NHA 23.930 345 O 0.340 0.300 0.150 0.030 0.033 0.050 90.31 -

NIRVANA Construction and Supplies 18691 Kidapawan City Resettlement Project/ LGU Pabahay 06/13/14 NHA 23.930 345 O 0.327 0.300 0.086 0.030 0.042 0.033 81.79 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page199

Page 200: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Nirvana Construction and Supplies 18691 Sarangani-Davao del Sur Coastal Road (Burias Section) 06/16/10 XII 9.394 150 O 0.316 0.237 0.150 0.030 0.047 0.050 83.00 -

NORIELLE CONSTRUCTION 31300 Construction of Junction National Highway Sta. Rita Road 10/25/2014 VIII 4.618 45 C 0.408 0.133 0.300 - - - 84.10% 84.1% Satisfactory

Norm Construction 13754 Const. of MPB at DENR 06/07/10 VII 1.446 169 O 0.262 0.296 0.138 0.030 0.041 0.033 80.00 -

NORSAM BUIDERS & CONSTRUCTION SUPPLY 21184

Construction and Maintenace of Bridge along National Road,

Rehabilitation/Reconstruction/Replacement/Retrofitting of Existing Permanent Bridges, Pambuian Bridge along

Catarman-Laoang Road

10/20/2014 VIII 3.790 82 C 0.491 0.132 0.000 - - - 62.30% 62.3% Poor

NORSAM BUILDERS & CONSTRUCTION SUPPLY 21184 Concreting/Upgrading of Gaps along Lapinig Arteche Road

Lapinig - Imelda Section KO853+114.50 - KO854+210 8/12/2014 VIII 25.556 232 C 0.410 0.133 0.300 84.30 84.30% Satisfactory

Norsam Builders & Construction Supply 21184 Conc./Upgrading of Gaps along Lapinig-Arteche Rd.,

Lapinig-Imelda Sect., K0853+114.50-K0854+210 08/06/13 VIII 25.566 262 O 0.339 0.239 0.150 0.030 0.060 0.033 85.10

Norsam Builders & Construction Supply 21184 Rehab./Upgrading of Catarman Diversion Rd. II 06/14/10 VIII 7.518 100 O 0.363 0.240 0.150 0.030 0.037 0.033 85.30 -

Norsam Builders & Construction Supply 21184 Macagtas IS 7/6-10/09 NIA 4.559 240 O 0.363 0.240 0.150 0.030 0.063 0.050 89.61 -

Norsam Builders & Construction Supply 2184 San Miguel CIS 7/6-10/09 NIA 4.005 150 O 0.365 0.240 0.150 0.030 0.063 0.050 89.77 -

Norsam Builders & Construction Supply 21184 Rehab./Reconst. Of Damaged Paved Nat'l Road along Allen-

Catarman, K0702+000-K0702+100 03/20/12 VIII 11.533 150 C 0.474 0.133 0.300 - - - 90.70 84.58% Satisfactory

NORSAM BUILDERS & CONSTRUCTION SUPPLY/ESD

CRUZ CONSTRUCTION & SUPPLY ( JV)

JV-13-280Construction/Rehabilitation of Slope Protection, Bantayan River Control along Catarman-Laoang Road, K0767+878 -

K0767+96010/20/2014 VIII 13.074 120 C 0.457 0.133 0.300 - - - 89.00% 89%

Satisfactory

NORSAM CONSTRUCTION 21184 Help for Catubig Agricultural Advancement Project HCAAP-LMC-C-4 03/15/14 NIA 9.889 403 C 0.440 0.104 0.300 - - - 84.40 84.40%

Satisfactory

Northern / DMJ Construction (JV) JV-08-115 Construction of Baler-Casiguan Road CP3 03/06/09 III 505.307 450 O 0.394 0.300 0.150 0.030 0.033 0.033 94.00 -

Northern / Z M Construction (JV) JV-08-275 Const. (Road Opening) of Lubao By-Pass Road of San Fernando-Olongapo Road inc. RROW 05/19/09 III 135.396 180 O 0.318 0.272 0.150 0.030 0.051 0.050 87.10 -

Northern / ZM Construction (JV) JV-07-148Tarlac-Nueva Ecija-Dingalan Port Road, Sta. Rosa-Jct. Fort

Magsaysay Road (Phase 2) & Gabaldon-Dingalan Road (Phase 3)

03/04/09 III 238.983 300 O 0.367 0.300 0.150 0.030 0.032 0.050 92.90 -

NORTHERN BUILDERS 8789 Completion of Moncada-Paniqui Road 11/20/2014 III 18.614 160 C 0.362 0.170 0.300 - - - 83.20% 83.2% Satisfactory

NORTHERN BUILDERS 8789

Rehabilitation/Reconstruction of Damaged Paved National Roads including Drainage at Capas - San Jose - Mayantoc -

Malacampa Road, KO118+874 to KO120+498 with exception

11/20/2014 III 19.410 80 C 0.444 0.133 0.300 - - - 87.70% 87.7% Satisfactory

Northern Builders 8789 Construction/Rehabilitation of Drainage System of Blumentritt Interceptor Catchment Area, Manila 4th 8/15/2014 NCR 42.646 300 C 0.497 0.133 0.300 93.00 93.00%

Very Satisfactory

Northern Builders 8789

Preventive Maintenance Based on Pavement Management System/Highway Development & Management (HDM-4)

Intermittent Section National Arterial Roads, Daang Maharlika, Alicia & Cauayan

8/10/2014 II 87.879 130 OG 0.374 0.300 0.112 0.030 0.045 0.033 89.40

Northern Builders 8789 Widening/Improvement of Nambang-Kasibu-Solano Road including Drainage (Bambang-Kasibu Section) 8/14/2014 II 42.376 216 C 0.452 0.133 0.300 88.50 88.05%

Satisfactory

NORTHERN BUILDERS 8789Rehab./Reconst. Of Damaged Paved National Roads including Drainage at Capas - San Jose Mayantoc -

Malacampa Road, K0118+874 to K0120+498 with exception8/5/2014 III 19.410 8789 C 0.419 0.133 0.300 85.20 85.20%

Satisfactory

NORTHERN BUILDERS 8789Const./Rehab./ of various Projects in Tarlac 1st LD (Const./Rehab. Of Anao - Ramos Road with Bridge

Component, Anao Section, Anao, Tarlac)8/6/2014 III 46.544 265 OG 0.391 0.231 0.150 0.024 0.060 0.033 88.90

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page200

Page 201: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Northern Builders 8780 Prev. Maint. (Int. Sect.) of Visayas Ave., (K0013+233-K0014+441) 08/02/13 NCR 15.713 90 C 0.407 0.133 0.300 - - - 84.00 *84.00%

Satisfactory

Northern Builders 8789 Prev. Maint. along Old Manila North Rd. 08/07/13 III 21.301 90 C 0.473 0.133 0.300 - - - 90.60 *90.60% V. Satisfactory

Northern Builders 8789Pinatubo Hazard Urgent Mitigation Proj., Phase III, CP No.5-Raising of Rds. & Const. of Side Drainage (Sta. 77+500-Sta.

77+760) & Sta. 77+490-Sta.78+66007/31/13 MPE-PMO 44.964 211 C 0.453 0.133 0.300 - - - 88.60 *88.60%

Satisfactory

Northern Builders 8789 Repair/Rehab./Impv't. of Pinagpanaan-Rizal-Pantabangan Rd., K0139+547-K0141+565.70 08/13/13 III 9.396 35 C 0.428 0.133 0.300 - - - 86.10 *86.10%

Satisfactory

Northern Builders 8789 Conc. of Baras-Baras-Mapalad Road 08/07/13 III 21.341 187 C 0.437 0.133 0.300 - - - 87.00 86.64% Satisfactory

Northern Builders 8789 Widening/Impv't. of Bambang-Kasibu-Solano Rd. inc. Drainage (Bambang-Kasibu Sect.) 08/14/13 II 41.677 209 O 0.353 0.240 0.150 0.030 0.055 0.033 86.10

Northern Builders 8789 Widening/Conc. of R-10, (Bangkulasi Bridge inc. Approaches crossing Bangkulasi River) 03/23/13 NCR 88.986 480 C 0.455 0.135 0.300 - - - 89.00 92.36%

V. Satisfactory

Northern Builders 8789 Widening/Impv't. of Bambang-Kasibu Rd. inc. Drainage (Bambang-Kasibu Sect.) 03/20/13 II 41.677 180 O 0.390 0.240 0.150 0.030 0.051 0.033 89.40 -

Northern Builders 8789

Road Upgrading (Gravel to Paved) Aritao-Quirino Road, a)K0272+358.6-K0272+580.696; b)0273+188.85-K0274+(-

445.5); c)K0274+247.52-K0276+(-491.08); d)K0276+126.31-K0278+817.04

03/20/13 II 98.680 269 O 0.383 0.246 0.150 0.030 0.047 0.033 88.90 -

Northern Builders 8789Widening/Conc. of Manila North Road (MNR), Tarlac

province Phase VI (Package II), Tarlac 2nd Congressional District, Tarlac City & Gerona Sect.

06/03/10 III 123.010 210 O 0.384 0.268 0.150 0.030 0.048 0.033 91.30 -

Northern Builders 8789Urgent Rehab. Works due to the Passage of Typhoon

"Pepeng" in the Province of Pangasinan under the Agno River Control Project

06/11/10 AFCS 5.790 45 O 0.353 0.240 0.150 0.030 0.047 0.050 87.00 -

Northern Builders 8789Widening/Conc. of Bontoc-Banaue Road, Talubin-Samoki Section Bontoc, Km. 376+911-Km.385+000 (intermittent

Section) 08/30/09 CAR 120.619 450 O 0.365 0.240 0.087 0.030 0.056 0.017 79.50 -

Northern Builders 8789 Concrete Paving/Impvt. of Jct. National Road, Bitnong-Belance, Nueva Vizcaya Boundary Road 06/01/09 II 125.420 540 O 0.347 0.300 0.150 0.030 0.051 0.050 92.80 -

Northern Builders 8789 Concrete Paving/Impv't of Jct. National Road, Bitnong-Belance, Nueva Vizcaya Bdry. Road 03/10/09 II 125.412 540 O 0.354 0.300 0.150 0.030 0.045 0.050 92.90 -

Northern Builders 8789 Const. of Tarlac-Nueva Ecija-Dingalan Port Road (Jct. Fort Magsaysay-Laur Section) Contract Package 3 05/30/09 III 299.894 360 O 0.337 0.300 0.150 0.030 0.042 0.050 90.90 -

Northern Builders 8789 Const. of Tarlac-Nueva Ecija-Dingalan Port Road (Jct. Fort Magsaysay-Laur Section) CP 3 09/07/09 III 299.894 360 O 0.379 0.300 0.150 0.030 0.050 0.033 94.20 -

Northern Builders 8789 Construction of Togbongon River Control 03/10/09 XIII 9.585 149 O 0.300 0.300 0.150 0.030 0.033 0.050 86.30 -

Northern Builders 8789 Conc. of Aritao-Quirino Road K0260+595-K0262+736 03/23/12 II 44.814 270 C 0.431 0.200 0.300 - - - 93.10 93.70% V. Satisfactory

Northern Builders 8789 Widening/Conc. of R-10 (Bangkulasi Bridge inc. approaches crossing Bangkulasi River) 11/24/12 NCR 89.051 480 O 0.352 0.299 0.150 0.030 0.065 0.050 94.60

Northern Builders 8789 Rehab. of Drainage System along Bayan-Bayanan Ave. & vicinity Sta.0+000-Sta. 0+979 11/21/12 NCR 37.675 253 C 0.402 0.133 0.300 - - - 83.50 83.32%

Satisfactory

Northern Builders 8789 Asphalt Overlay of City of San Fernando-GSO Rd., Const. of Pedestrian Overpass & Installation of 3 Traffic Lights 11/21/12 III 62.518 240 O 0.350 0.300 0.150 0.030 0.031 0.050 91.10 -

Northern Builders 8789 Conc. of Rd. @ Quezon to New Salem Rd. 11/24/12 III 7.891 97 O 0.352 0.282 0.150 0.030 0.050 0.033 89.70 -

Northern Builders 8789 Reconst. of New Ibajay Bridge, Km.329+005 11/23/12 IVB 12.820 325 C 0.481 0.133 0.300 - - - 91.40 89.81% V. Satisfactory

Northern Builders 8789 Rehab. of Drainage System along Bayan-Bayanan Ave. & vicinity Sta.0+000-Sta. 0+979 08/15/12 NCR 37.675 253 O 0.262 0.300 0.150 0.030 0.040 0.050 83.20 -

Northern Builders 8789 Const. of Sch. Bldg. at Eduardo Cojuangco Nat'l. Voc. High Sch. 08/09/12 III 10.668 148 C 0.423 0.200 0.300 - - - 92.30 92.86% V.

Satisfactory

Northern Builders 8789 Impvt./Widening/Conc. of MNR 2nd District (Tarlac City-Gerona Sect.) 08/10/12 III 324.386 240 C 0.343 0.200 0.300 - - - 84.30 90.78% V.

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page201

Page 202: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Northern Builders 8789 Rehab of Tarlac River Control at San Jose De Urquico 08/09/12 III 14.319 120 C 0.383 0.200 0.300 - - - 88.30 89.74% V. Satisfactory

Northern Builders 8789 Impvt./Widening/Conc. of MNR, (Paniqui-Moncada Sect..) 08/14/12 III 161.244 210 C 0.341 0.200 0.300 - - - 84.10 88.72% Satisfactory

Northern Builders 8789 Asphalt Overlay of City of San Fernando-GSO Rd., Const. of Pedestrian Overpass & Installation of 3 Traffic Lights 08/16/12 III 62.518 240 O 0.340 0.215 0.150 0.030 0.047 0.050 83.20 -

Northern Builders 8789 Reconst. of New Ibajay Bridge 08/04/12 IVB 12.819 325 O 0.332 0.263 0.149 0.030 0.035 0.050 85.90 -

Northern Builders 8789Rd. Upgrading (Gravel to Concrete) Intermittent Sect., Aritao-Quirino Rd., K0267+018-K0272+269; K0263+559-

K0266+398; K0263+(-278)-K0263+(-141) w/ exception03/20/13 II 135.002 396 C 0.453 0.133 0.300 - - - 88.60 *88.60%

Satisfactory

Northern Builders / Ferdstar Builders Contractors (JV) JV-07-118 Rehab/Reconst. of Tulaoc-Sto. Domingo Road, Mexico

Section 02/24/09 III 96.425 300 O 0.337 0.281 0.150 0.030 0.047 0.050 89.50 -

Northern Builders / New Big Four J Construction (JV) JV-08-207 Impvt./Conc. & Widening of Panglao Island Central Spur

Rd. 06/03/10 VII 111.090 300 O 0.258 0.300 0.000 0.030 0.060 0.050 69.80 -

Northern Builders / R.A. Pahati Gravel & Sand (JV) JV-08-008 Rehab/Impvt./Widening of Tarlac-Nueva Ecija-Dingalan

Port Road, Phase I, Fort Magsaysay-Laur Road Section 03/04/09 III 223.075 300 O 0.388 0.300 0.150 0.022 0.032 0.050 94.20 -

Northern Builders/Ferdstar Builders Contractor Joint Venture JV-07-143 Completion/Continuation of Unfinished On-going Bridge:

Anao Bridge along San Jose Malino-Anao Road 05/18/09 III 18.988 60 O 0.307 0.300 0.150 0.030 0.042 0.050 87.90 -

Northern Builders/Ferdstar Builders Contractor Joint Venture JV-07-118 Rehab./Reconst. of Tulaoc Sto. Domingo Road, Mexico

Sect. 05/18/09 III 96.425 300 O 0.298 0.300 0.150 0.030 0.037 0.050 86.50 -

Northern Builders/New Big Four J Const. Inc. (Joint Venture) JV-08-207

Imprv't/Conc./widening of Panglao center Spur Rd. Sta. 3+120-to Sta.3=500; Sta.3+700-Sta.5+200;Sta.5+540-

Sta.6+20009/03/09 VII 110.999 300 O 0.383 0.240 0.150 0.030 0.037 0.050 89.00 -

Northern Builders/New Big Four J Const. Inc. (Joint Venture) JV-08-207

Imprv't./Conc. of Jct.(TER),Jagna-Sierra Bullones Rd. Km.86.283-Km86.800;Km.87.020-Km.87.380;Km87.540-

Km.89.64550;Km.94.380-Km.95.68009/04/09 VII 87.718 270 O 0.329 0.240 0.150 0.030 0.037 0.050 83.60 -

Northern Builders/New Big Four J Construction Inc. Joint Venture JV-08-207

Impvt./Conc./Widening of Panglao Center Spur Road, Sta. 3+120-Sta.3+500, Sta. 3+700-Sta. 5+200, Sta. 5+540-Sta.

6+20006/10/09 VII 110.999 300 O 0.358 0.300 0.150 0.030 0.047 0.050 93.50 -

Northern/DMJ Construction Joint Venture JV-08-115 Construction of Baler-Casiguran Road (Contract Package

3) 05/28/09 III 505.307 450 O 0.337 0.300 0.150 0.030 0.037 0.033 88.70 -

Northern/ZM Construction Joint Venture JV-08-275 Const. of (Road Opening) of Lubao-By Pass Road of San

Fernando-Olongapo Road inc. RROW 08/25/09 III 135.396 180 O 0.336 0.300 0.150 0.030 0.051 0.033 90.00 -

NOVANNE VENTURES CONSTRUCTION CORPORATION (Formerly: NOVANNE VENTURES

CONSTRUCTION)

22107Const. of Slope Protection along Bacolod South Road Km.

0182+618 (Bacuyangan Bridge Approaches), Brgy. Talacagay

8/8/2014 VI 2.831 60 C 0.383 0.200 0.300 88.30 83.56% Satisfactory

Novanne Ventures Construction Corporation (Formerly: Novanne

Ventures Construction)22107

Const. of Slope Protection along Bacolod South Rd. Km.0182+618 (Bacuyangan Bridge Approaches), Brgy.

Talacagay08/09/13 VI 2.831 60 O 0.342 0.225 0.136 0.030 0.038 0.033 80.40

NTL BUILDERS & DEVELOPER 33450 Construction of Two Classroom School Building, Gamis E/S 10/28/2014 II 1.970 75 C 0.438 0.133 0.300 - - - 87.10% 87.1%

Satisfactory

NTL Builders & Developer 33450 Completion of AcademicBLDG 2-III 09/10/14 DOST 12.106 303 C 0.470 0.200 0.300 - - - 97.00 97.14% Outstanding

NTL BUILDERS & DEVELOPER 33450 COMPLETION OF SCOPE PROTECTION / RIP RAP PHASE 4 09/12/13 DOST 9.534 120 C 0.472 0.200 0.300 - - - 97.20 *97.20%

Outstanding

NTL BUILDERS & DEVELOPER 33450 COMPLETION OF DORMITORY BOYS III, COMP. ACA BULDANT II-IV 09/12/13 DOST 10.211 150 C 0.441 0.200 0.300 - - - 94.10 *94.10%

V. Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page202

Page 203: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

NTL Builders & Developers 33450 Dibuluan River Irrigation Project 04/27/13 NIA 4.699 208 C 0.384 0.184 0.300 - - - 86.80 86.86% Satisfactory

NTL Builders and Developer 33450 Construction of Multi Purpose Building, Capitol Complex 8/13/2014 II 9.163 165 C 0.392 0.191 0.300 88.30 88.37% Satisfactory

NTL Builders and Developer 33450 Const. of MPB, Capitol Complex 08/11/13 II 8.783 150 O 0.384 0.240 0.150 0.030 0.047 0.033 88.40

NTL Builders and Developer 33450 Rehab./Reconst./Upgrading of Jct. Ipil-Quirino Bdry. Rd., K0371+122-K0371+908 03/19/12 II 3.632 117 C 0.414 0.133 0.300 - - - 84.70 88.18%

SatisfactoryNukaza Trading and Construction

Services 32067 Const./Rehab./Completion of Flood Control Project at Brgy. Cupang 02/18/10 NCR 2.381 101 O 0.342 0.240 0.150 0.030 0.029 0.033 82.40 -

NURBEN ENGINEERING AND BUILDING CONTRACTOR 32432 Development of Tourist Spots in Misamis Oriental 6/30/15 TIEZA 2.950 120 O 0.351 0.277 0.150 0.015 0.014 0.050 85.69

NY Construction 30388Emergency Repair of Damaged Open Storage/Back-up Area, RoRo Ramps, Retaining Wall and Rock Bulkhead

Caused by 7.2 Magnitude Earthquake on October 15, 201304/10/15 PPA 26.154 250 O 0.351 0.282 0.150 0.024 0.064 0.050 92.11 -

NY Construction and Supply 30388 Repair of Damaged Slope Protection Structure 09/30/15 PPA 12.519 270 C 0.342 0.200 0.300 - - - 84.20 *84.20% Satisfactory

NY Construction and Supply 30388 Construction and Supply for the Catbalogan Port Rehabilitation Project 04/20-23/10 PPA 35.835 150 O 0.3960 0.3000 0.1500 0.0300 0.0700 0.0500 99.60 -

NY Construction and Supply 30388 Concrete Paving of Reclaimed Area (open storage area) 05/09/13 PPA 19.002 315 O 0.400 0.300 0.150 0.030 0.065 0.050 99.48 -

O. G. SANTOS CONSTRUCTION 2050

Rehab/Reconst/Upgrading of Damaged National Road Including Drainage based on (PMS/HDM-4)(Intermittent

Section) Lanao-Pagadian-Zamboanga City Road K1655+000 - K1657+000

10/27/2014 IX 25.675 165 C 0.340 0.200 0.300 - - - 84.00% 84% Satisfactory

O. G. SANTOS CONSTRUCTION 2050Rehabilitation/Reconstruction/Upgrading of Damaged

Paved National Road Digos-Makar Road: Km. 1586+600 - Km. 1588+472

10/22/2014 XI 31.385 180 O 0.026 0.202 0.104 0.018 0.035 0.017 40.20% 40.2% Poor

O. G. Santos Construction NHA-Pantukan Resettlement Project 05/16/14 NHA 29.904 365 C 0.494 0.200 0.300 - - - - 99.41% Outstanding

O. G. SANTOS CONSTRUCTION 2050 Construction of River Protection 10/28/2014 XI 4.606 88 C 0.400 0.150 0.300 - - - 85.00% 85% Satisfactory

O. G. SANTOS CONSTRUCTION AND GP & H CONSTRUCTION &

SUPPLY (JOINT VENTURE)- Road Upgrading of Cateel-Compostela Road (Davao

Oriental Side) Cateel 10/29/2014 XI 43.257 135 C 0.218 0.197 0.300 - - - 71.50% 71.5% Poor

O.G. SANTOS CONSTRUCTION 2050

GAA Widening of Tagum-Panabo Circumferencial Road, Davao del Norte 2nd LD Panabo City to St. Tomas Section

K1496+714 – K1497+666, Menzi Section (Widening of Tagum-Panabo Circumferencial Road, K1496+714 –

K1497+685 Menzi Section, Sto. Tomas

8/9/2014 XI 18.295 102 C 0.342 0.200 0.300 84.20 84.20% Satisfactory

O.G. SANTOS CONSTRUCTION 2050 Construction of Mahan-Ub River Protection along Surigao-Davao, Manay, Davao Oriental 8/16/2014 XI 6.824 153 C 0.339 0.200 0.300 83.90 83.6%

Satisfactory

O.G. Santos Construction NHA-Pantukan Resettlement Project 05/16/14 NHA 29.904 365 C 0.494 0.200 0.300 99.41

O.G. Santos Construction 2050 Const. of 7m x 9m (modified) Crispin E. Rojas NHS (Lambajon) Annex of Baganga NHS (5 CL) 08/17/13 XI 2.944 142 C 0.487 0.133 0.300 - - - 92.00 *92.00% V.

Satisfactory

O.G. Santos Construction 2050 Constof 5-CL - 7m x 9m, San Luis NHS 08/17/13 XI 2.944 142 C 0.454 0.133 0.300 - - - 88.70 *88.70% Satisfactory

O.G. Santos Construction 2050Road Upgrading (Gravel to Paved) Int. Sect., Fatima-

Malabog Rd.: a)Km.1503+400-Km.1503+961 b)Km.1506+541-Km.1507+470.98

08/20/13 XI 34.731 140 O 0.377 0.271 0.150 0.030 0.035 0.050 91.30

O.G. Santos Construction 2050 Const. of two (2) Storey Sixteen (16) Cl & one (1) Storey Eight (8) Cl Sch. Bldg. @ New Corella NHS 08/12/13 XI 28.497 225 O 0.363 0.225 0.150 0.030 0.030 0.050 84.80

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page203

Page 204: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

O.G. Santos Construction 2050 Const. of Mahan-ub River Protection along Surigao-Davao Coastal Rd., Brgy. Central 08/17/13 XI 6.824 153 O 0.296 0.300 0.150 0.030 0.025 0.033 83.40

O.G. Santos Construction 2050Road Upgrading (Gravel to Conc.) Int. Sect., Lanao-

Pagadian-Zamboanga City Rd., K1638+500-K1640+000, Lantungan

03/20/13 IX 32.527 240 C 0.445 0.174 0.300 - - - 91.90 83.44% Satisfactory

O.G. Santos Construction 2050 Rd. Slip along Malalag-Malita-JAS-Glan Rd., Malalag 03/13/13 XI 29.091 212 O 0.320 0.186 0.150 0.030 0.030 0.033 74.90 -

O.G. Santos Construction 2050 Const. of Buhangin Flood Control, Malalag-Malita JAS, Brgy. Buhangin 03/15/13 XI 4.994 98 O 0.200 0.148 0.150 0.010 0.030 0.050 58.80 -

O.G. Santos Construction 2050(Rd. Slip) Surigao-Davao Coastal Rd., Bislig-Lingig Rd. Sect., Mangagoy & Lingig, Km.1467+680-Km.1467+780,

(Km.1467+430-Km.1467+765)03/17/13 XIII 25.968 285 O 0.342 0.300 0.042 0.030 0.028 0.017 75.90 -

O.G. Santos Construction 2050Road Upgrading (Gravel to Paved) Demoloc-Little Baguio-

Alabel Rd., Bolila-Sanghay, Malita Km.1646+620-Km.1647+680

03/21/12 XI 33.238 140 O 0.399 0.275 0.150 0.020 0.037 0.050 93.10 -

O.G. Santos Construction 2050Road Upgrading (Gravel to Paved) Highway Jct. Mana-

Ticulon-Lagumit-Little Baguio Rd. Km.1647+400-Km.1648+200

03/21/12 XI 15.765 180 C 0.228 0.200 0.300 - - - 72.80 78.74% Unsatisfactory

O.G. Santos Construction 2050 Const. of 1-Strorey, 2 Classroom (7x9), Binugao NHS 03/12/13 XI 1.470 60 C 0.437 0.133 0.300 - - - 87.00 *87.00% Satisfactory

O.G. Santos Construction 2050 Conc. of Rd. at Brgy. Baganihan, Marilog District 03/11/13 XI 1.483 15 C 0.427 0.133 0.300 - - - 86.00 *86.00% Satisfactory

O.G. Santos Construction 2050 Upgrading of Sitio Pangi FMR, Brgy. Mandug, Buhangin District 03/22/13 XI 1.956 22 C 0.273 0.133 0.300 - - - 70.60 *70.60%

Poor

O.G. Santos Construction NHA - Pantukan Resettlement Project 06/14/13 NHA 29.926 365 O 0.398 0.300 0.141 0.030 0.065 0.050 98.45 -

O.G. Santos Construction / Mindanao Construction Services &

Land Development Corporation (JV)

JV-12-581 Widening of Cotabato-Davao Nat'l Rd., Km.1640+769-Km.1641+700 (Notre Dame Sect.) Davao-Cotabato Rd. 08/09/13 XII 18.611 158 C 0.387 0.200 0.300 - - - 88.70 *88.70%

Satisfactory

O.L. De Leon Construction 16194 Upgrading (Gravel to Concrete) of Bagong Silang-Capalonga Rd., K0321+000-K0321+458 08/18/11 V 9.229 230 O 0.301 0.283 0.150 0.020 0.042 0.050 84.60 -

O.L. De Leon Construction 16194 Const. of Drainage System at Pob. 1, 2 & 3 04/03/11 V 5.725 150 O 0.356 0.225 0.150 0.030 0.035 0.033 82.90 -

O.L. De Leon Construction 16194 Road Upgrading (Gravel to Concrete), Km. 320+573-Km. 321+000 08/16/12 V 43.834 270 C 0.447 0.133 0.300 - - - 88.00 88.12%

Satisfactory

O.L. De Leon Construction 16194Prev. Maint. of Daang Maharlika, Km.361+000-Km.361+980

& Km.367+990 Realigned to Km.341+929-Km.342+617, Km.343+319-Km.344+091

08/16/12 V 21.351 180 C 0.439 0.133 0.300 - - - 87.20 87.92% Satisfactory

O.R Sarmiento Construction 1411 Repair/Impvt./Asphalt Paving of Bugko-Nenita-San Jose Rd., Km.760+000 - Km.779+000 (Mondragon-Silvino Rd.) 06/16/10 VIII 192.823 385 O 0.387 0.300 0.150 0.030 0.042 0.050 95.90 -

O.R Sarmiento Construction 1411 Talibon Small Reservoir Irrigation Project 9/29/08 10/3/08 NIA 11.574 343 O 0.350 0.157 0.100 0.030 0.047 0.200 88.40 -

O.R Sarmiento Construction 1411 Conc. of Junction (TER), Jagna-Sierra-Bullones Road 08/29/08 VII 81.102 300 O 0.337 0.223 0.000 0.030 0.059 0.100 74.90 -

O.R. Sarmiento Construction 1411 Rd. Upgrading (Gravel to Concrete) along Balbalan-Pinukpuk Rd., Km.505+000-Km.523+399 (I.S.) 03/20/13 CAR 165.980 480 O 0.319 0.240 0.150 0.030 0.051 0.050 84.00 -

O.R. Sarmiento Construction 1411 Road Upgrading of Jct. Taft-Oras-San Policarpio-Arteche Road 03/29/12 VIII 61.048 230 O 0.373 0.300 0.026 0.030 0.055 0.033 81.70 -

O.R. Sarmiento Construction / Plerm Construction & Development

Corp. JVJV-11-277 Reconst. of Longos Bridge, Calapan North Rd. 08/07/12 IVB 104.412 386 O 0.340 0.300 0.082 0.030 0.040 0.033 82.50 -

O.R. Sarmiento Construction / Plerm Construction & Development

Corporation (JV)JV-11-031 CP 2.1 Const. of Tangcul Bridge & Approaches & CP 2.2

Const. of Sicalaco Bridge & Approaches 08/15/13 PMO-SBP 67.616 375 C 0.459 0.200 0.300 - - - 95.90 96.50% Outstanding

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page204

Page 205: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

O.R. Sarmiento Construction / Plerm Construction & Development

Corporation (JV)JV-11-277 Reconst. of Longos Bridge, Calapan North Rd. 03/18/13 IVB 103.455 416 O 0.387 0.240 0.150 0.030 0.051 0.033 89.10 -

O.R. Sarmiento Construction / Plerm Construction & Development

Corporation (JV)JV-11-487 Replacement of Baroc Bridge to Const. of Pre-Stressed

Bridge at Calapan Rd. 03/21/13 IVB 46.732 380 C 0.471 0.133 0.300 - - - 90.40 90.37% V. Satisfactory

O.R. Sarmiento Construction / Plerm Construction & Development

Corporation (JV)JV-11-031 CP 2.1, Const. of Tangcul Bridge & Approaches and CP

2.2, Const. of Sicalao Bridge & Approaches 08/01/12 PMO-SBP 67.616 375 O 0.374 0.300 0.150 0.030 0.065 0.050 96.90 -

O.R. Sarmiento Construction / Plerm Construction and

Development Corporation (JV)JV-11-277 Reconst. of Longos Bridge, Calapan North Rd. 11/26/13 IVB 103.454 615 C 0.467 0.134 0.300 - - - 90.10 87.52%

Satisfactory

Ocean Construction Services 32220 Const. of 27.75m x 27.20m Public Market Bldg. 03/20/13 II 3.800 136 C 0.498 0.133 0.300 - - - 93.10 88.24% Satisfactory

OCM Steel Corporation 32421 Rehabilitation of 2nd Floor Building A, SPC 12/05/12 BSP 37.750 180 C 0.301 0.238 0.150 0.030 0.070 0.050 83.90 -

OCTAGON CONCRETE SOLUTION 34475 MANGUINO-O PORT IMPROVEMENT PROJECT 06/25/15 PPA 39.905 300 O 0.400 0.300 0.150 0.030 0.050 0.050 98.00 -

OCTAGON CONCRETE SOLUTIONS 34475

Asphalt Overlay along Biliran Circumferential Road, Bagongbong-Almeria Road Section, Km. 1033+000 - Km.

1034+00010/27/2014 VIII 10.226 94 C 0.452 0.201 0.000 - - - 65.30% 65.3%

Poor

OCTAGON CONCRETE SOLUTIONS 34475

Road Upgrading (gravel to Paved) Merida - Lundag - Putting Bato - Consolacion - Isabel Road A. K1109+059 -

K1110+000 B. 1110+057 - K1111+(-389)8/7/2014 VIII 34.745 260 C 0.382 0.189 0.300 87.10 88.72%

Satisfactory

Octagon Concrete Solutions 34475 Repair of R.C. Deck at Conventional Pier & Mooring and Fendering System 03/21/14 PPA 21.871 75 O 0.400 0.300 0.000 0.020 0.064 0.033 81.70 -

Octagon Concrete Solutions 34475Rd. Upgrading (Gravel to Pave) Merida-Lundag-Puting Bato-Consolacion-Isabel Rd., a.K1109+059-K1110+000,

b.K1110+057-K1111+(-389)08/10/13 VIII 34.745 260 O 0.393 0.240 0.150 0.015 0.050 0.050 89.80

Octagon Concrete Solutions 34475Rehab./Reconst. of Damaged Paved Nat'l Rd. (Intermittent

Sect.), Ormoc-Baybay Southern Leyte Bdry. Rd., A.K1032+000-K1033+000 B.K1026+000-K1027+000

03/14/13 VIII 13.815 150 O 0.390 0.290 0.150 0.023 0.040 0.033 92.60 -

Octagon Concrete Solutions 34475 Prev. Maint. of Palo-Carigara-Ormoc Rd., K0939+(-935)-K0940+000 03/11/13 VIII 13.963 95 O 0.360 0.240 0.150 0.023 0.040 0.050 86.30 -

Octagon Concrete Solutions 34475 Rd. Upgrading (Gravel to Paved) of Sambulawan Jct.-Calaguise-Calubian Rd., Km.995+407-Km.997+417 03/13/13 VIII 41.353 281 C 0.390 0.153 0.300 - - - 84.30 84.78%

Satisfactory

Octagon Concrete Solutions 34475 Concrete Paving of Biliran Circ. Rd., Asug-Talibong Rd. Section, Km.1091+826-Km.1095+153 w/ exceptions 03/12/13 VIII 47.954 300 C 0.273 0.186 0.300 - - - 75.90 82.08%

Satisfactory

Octagon Concrete Solutions 34475 Rd. Upgrading (Gravel to Paved) of Sambulawan Jct.-Calaguise-Calubian Rd., Km.1000+230-Km.1001+390 03/13/13 VIII 26.941 221 C 0.334 0.154 0.300 - - - 78.80 82.04%

Satisfactory

Octagon Concrete Solutions 34475Road Upgrading (Gravel to Paved) of Tabango-Catmon-La

Fortuna-Manlawaan-Gimarco Rd., Km.1031+907-Km.1033+242

03/22/12 VIII 28.847 210 O 0.322 0.230 0.150 0.030 0.035 0.050 81.70 -

Octagon Concrete Solutions 34475Road Upgrading (Gravel to Paved) Based on Gravel Road,

Libungao-Matag-ob-Palompon Road, Km.1010+409-Km.1012+404

03/24/12 VIII 34.799 220 O 0.289 0.243 0.105 0.030 0.045 0.017 72.90 -

Octagon Concrete Solutions 34475Rd. Upgrading (Gravel to Paved) Calubian Jct.-San Isidro-

Tabango-Villaba-Palompon Rd., Km.1011+248.55-Km.1013+133; Km.1019+882-Km.1019+962

11/21/12 VIII 43.469 281 C 0.451 0.200 0.268 - - - 91.90 87.28% Satisfactory

Octagon Concrete Solutions 34475 Rd. Upgrading (Gravel to Paved) of Belen-Consuegra Rd., K0981+810-K0983+631 11/21/12 VIII 37.407 270 C 0.437 0.133 0.300 - - - 87.00 87.24%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page205

Page 206: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Octagon Concrete Solutions 34475 Road Upgrading (Gravel to Paved) along Ormoc-Lake Imelda Rd., Km.1013+534-Km.1015+559 11/22/12 VIII 42.930 220 C 0.383 0.200 0.300 - - - 88.30 85.96%

Satisfactory

Octagon Concrete Solutions 34475Rd. Upgrading (Gravel to Paved) of Tabango-Catmon-La

Fortuna-Manlawaan-Gimarco Rd., Km.1031+907-Km.1033+242

11/21/12 VIII 28.847 221 C 0.445 0.133 0.300 - - - 87.80 85.94% Satisfactory

Octagon Concrete Solutions 34475 Repair/Rehab./Impvt. of Carigara-Barugo Rd. (S00069LT), K0944+835-K0945+349 w/ exceptions 11/25/12 VIII 9.895 90 O 0.359 0.240 0.150 0.030 0.043 0.033 85.50 -

Octagon Concrete Solutions 34475 Rd. Upgrading (Gravel to Pave) along Libungao-Matag-ob-Palompon Rd., Km.1010+409-Km.1012+404 11/22/12 VIII 34.799 219 C 0.407 0.200 0.300 - - - 90.70 80.02%

Unsatisfactory

Octagon Concrete Solutions 34475Rd. Upgrading (Gravel to Paved) of Tabango-Catmon-La

Fortuna-Manlawan-Gimarco Rd., Km.1031+907-Km.1033+242

08/09/12 VIII 28.847 221 O 0.354 0.300 0.131 0.030 0.045 0.017 87.70 -

Octagon Concrete Solutions 34475 Road Upgrading (Gravel to Paved) of Belen-Consuegra Rd. Km.0981+810-Km.0983+631 08/09/12 VIII 37.407 265 O 0.316 0.300 0.150 0.030 0.045 0.033 87.40 -

Octagon Concrete Solutions 34475Road Upgrading (Gravel to Paved) Based on Gravel Rd. along Libungao-Matag-ob-Palompon Rd., Km.1005+567-

Km.1006+56708/13/12 VIII 19.750 220 O 0.309 0.300 0.150 0.030 0.045 0.033 86.70 -

Octagon Concrete Solutions 34475 Rd Upgrading (gravel to paved) based on Gravel Rd. Along Ormoc-Lake Imelda Rd., Km.1013+534-Km.1015+559 08/11/12 VIII 42.930 220 O 0.289 0.297 0.150 0.030 0.045 0.033 84.40 -

Octagon Concrete Solutions 34475Rehab./Reconst. of Palo-Carigara-Ormoc Rd. (K0957+368-

K0957+769; K0961+440-K0961+916; K0967+460-K0969+300) Palo-Carigara-Ormoc Rd.

08/21/12 VIII 27.127 180 C 0.402 0.200 0.300 - - - 90.20 84.38% Satisfactory

Octagon Concrete Solutions 34475Rd. Upgrading (Gravel to Paved) of Calubian Jct.-San

Isidro-Tabango-Villaba - Palompon Rd., Km.1011+248.55-Km.1013+133; Km.1019+882-Km.1019+962

08/09/12 VIII 43.469 281 O 0.298 0.286 0.150 0.030 0.045 0.033 84.20 -

Octagon Concrete Solutions 34475 Prev. Maint. (Int. Sect.) Palompon-Isabel-Maerida-Ormoc Rd., Km.1130+000-Km.1131+000 03/14/13 VIII 6.357 60 C 0.416 0.200 0.300 - - - 91.60 *91.60%

V. Satisfactory

O'hara Construction & Aggregates 33173 Proposed One Storey Two Class room 7x7 (modified) Mamuyod E/S 08/26/09 CAR 1.025 82 O 0.344 0.240 0.118 0.030 0.043 0.033 80.80 -

O'hara Construction & Aggregates 33173 Rehab./Reconst. Along Pico-Lamtang Road KM254+907-KM254+988 03/22/12 CAR 6.795 209 C 0.394 0.133 0.300 - - - 82.70 84.20%

SatisfactoryOIC Construction & Supply

(Formerly: OIC Construction) 23727 Rehab./Reconst. of Talisay-Laurel-Agoncillo Rd., Laurel-Agoncillo Sect. 06/10/10 IVA 21.225 120 O 0.384 0.225 0.150 0.023 0.054 0.033 86.90 -

OLIN DEVELOPMENT ENGINEERING & CONSTRUCTION 26271 Construction of Multi-Purpose Building at Brgy. Poblacion 10/21/2014 XIII 1.975 60 C 0.410 0.176 0.300 - - - 88.60% 88.6%

Satisfactory

OMENGAN CONSTRUCTION AND DEVELOPMENT CORPORATION 5119 Road Upgrading (Gravel to Concrete) of Conner - Kabugao

Road KO585+834 - KO588+691 & KO590+340 - KO594+774 11/28/2014 CAR 193.548 448 O 0.328 0.280 0.150 0.030 0.060 0.050 89.80% 89.8% Very Satisfactory

OMENGAN CONSTRUCTION AND DEVELOPMENT CORPORATION 5119

Road Upgrading (Gravel to Paved) of Mt. Province Bdry.-Calanan-Pinukpuk-Abbut Road (Pinukpuk) K0523+850 -

K0527+214, KO527+615 - K0529+041, KO529+474 - KO530-268, KO532+019-KO534+852

11/27/2014 CAR 127.895 285 O 0.354 0.279 0.150 0.030 0.060 0.050 92.30% 92.3% Very Satisfactory

OMENGAN CONSTRUCTION and DEVELOPMENT CORPORATION 5119

Road Upgrading (Gravel to Concrete) along Conner-Kabugao, Apayao-Solsona-Ilocos Norte Road, Apayao

Side, K0606+(-370) to K0607+376, Apayao8/8/2014 CAR 42.116 241 C 0.405 0.133 0.300 83.80 89.62%

Very Satisfactory

OMENGAN CONSTRUCTION and DEVELOPMENT CORPORATION 5119

Road Upgading (Gravel to Concrete) along Claveria - Calanasan - Kalagao Road, K0649+629 to K0651+469 (I.S.),

Apayao8/9/2014 CAR 46.909 179 OG 0.374 0.240 0.150 0.024 0.040 0.033 86.10

Omengan Construction and Development Corporation 5119

Rd. Upgrading (Gravel to Conc.) along Kabugao, Apayao-Solsona-Ilocos Norte Rd., Apayao Side, K0606+(-370)-

K0607+37608/10/13 CAR 42.116 230 O 0.360 0.300 0.150 0.030 0.050 0.033 92.30

Omengan Construction and Development Corporation 5119

Road Upgrading (Gravel to Concrete) along Kabugao, Apayao-Solsona-Ilocos Norte Rd., Apayao Side, K0606+(-

370)-K0607+37603/21/13 CAR 42.116 170 O 0.398 0.297 0.150 0.024 0.045 0.033 94.70 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page206

Page 207: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Omengan Construction and Development Corporation 5119 Conc. along Kabugao-Pudtol-Luna Road, Mataguisi

Section 06/01/09 CAR 18.868 277 O 0.322 0.300 0.150 0.030 0.050 0.033 88.50 -

Omengan Construction and Development Corporation 5119 Improvement/Widening/Concreting of Bontoc-Tabuk-

Tuguegarao Road, Phase III, Dao Bridge-Cobaet Bridge 03/03/09 CAR 47.241 300 O 0.362 0.288 0.150 0.030 0.045 0.033 90.80 -

Omengan Construction and Development Corporation 5119

Impvt./Widening/Conc. Of Bontoc-Tabuk-Tuguegarao Road, Phase VI, Mamaga Bridge-Basao Bridge, Km.

420+970-Km.429+94003/04/09 CAR 83.149 365 O 0.376 0.300 0.150 0.030 0.045 0.033 93.40 -

Omengan Construction and Development Corporation 5119 Conc. along Kabugao-Pudtol-Luna Road, Matuguise

Section 09/05/09 CAR 18.868 277 O 0.365 0.240 0.150 0.030 0.056 0.033 87.40 -

Omengan Construction and Development Corporation 5119

Widening / Conc. of Mt. Data-Bontoc Road Sabangan Bridge, Poblacion to Malitep Bridge Section Balili Section,

Km. 374+233-Km 380+22708/28/09 CAR 91.443 430 O 0.361 0.240 0.053 0.023 0.042 0.017 73.60 -

Omengan Construction and Development Corporation 5119

Impvt./Widening/Conc. of Bontoc-Tabuk-Tuguegarao Road, Phase VI, Mamaga Bridge-Basao Bridge, Km. 420+970-

Km.429+94011/20/08 CAR 83.149 365 O 0.331 0.240 0.100 0.030 0.045 0.067 81.30 -

Omengan Construction and Development Corporation 5119 Rehab. of Nat'l Rd. along Conner-Kabugao Rd., Landslide,

K0570+200-K0571+800 w/ exception, Matalag Sect. 11/27/12 CAR 24.219 342 O 0.354 0.300 0.068 0.020 0.042 0.033 81.70 -

Omengan Construction and Development Corporation 5119 Rd. Upgrading (Gravel to Conc.) along Kabugao-Pudtol-

Luna-Cagayan Bdry. Rd., K0657+427-K0661+000 08/11/12 CAR 46.989 252 C 0.387 0.145 0.300 - - - 83.20 88.18% Satisfactory

Omengan Construction and Development Corporation 5119 Rehab./Reconst./Upgrading of Paved Nat'l Rds. along

Baguio-Bontoc Rd., K0317+415-K0318+500, Sinipsip 08/02/12 CAR 20.272 252 O 0.291 0.240 0.133 0.010 0.051 0.033 75.80 -

Omengan Construction and Development Corporation 5119 Rehab. of Nat'l Rd. along Conner-Kabugao Rd., Landslide,

K0570+200-K0571+800 w/ exception, Matalag Sect. 08/10/12 CAR 24.219 300 O 0.310 0.300 0.046 0.015 0.045 0.033 74.90 -

Omengan Construction and Development Corporation 5119

Rd. Upgrading (Gravel to Concrete) of Mt. Province-Ilocos Sur Rd. K0388+000-K0412+425 (I.S.) Tadian-Bauko-

Sabangan08/04/12 CAR 137.509 425 O 0.302 0.300 0.022 0.030 0.047 0.033 73.40 -

Omengan Construction and Development Corporation 5119 Const. of Bulanao Drainage along Kalinga-Cagayan-Enrile

Rd., K0499+407-K499+880 03/20/13 CAR 13.514 147 C 0.392 0.200 0.300 - - - 89.20 *89.20% V. Satisfactory

Omnicon Builders 22816 Const. of MPB at Patindig Araw 08/14/13 IVA 0.679 135 C 0.475 0.133 0.300 - - - 90.80 86.46% Satisfactory

Omnicon Builders 22816 Const. of Two (2) Classroom S/B Bubog NHS 03/13/12 IVB 0.918 90 C 0.469 0.133 0.300 - - - 90.20 85.72% Satisfactory

Omnicon Builders 22816 Const. of MPB at Patindig Araw 11/23/12 IVA 0.679 135 C 0.318 0.300 0.150 0.022 0.023 0.033 84.60 -OQC Construction 22690 Addalam River Irrigation Project 04/27/09 05/01/09 NIA 2.827 178 O 0.358 0.240 0.150 0.023 0.038 0.033 84.23 -

Orani Builders and Supply 5349 Repair/Maint. of Pagalanggang River Control 03/12/13 III 1.417 60 C 0.429 0.133 0.300 - - - 86.20 *86.20% Satisfactory

ORANI BUILDERS SUPPLY 5349 Replacement/Rehab.Strengthening of Limay Bridge along Jct. Layac - Balanga - Mariveles Port Road 8/13/2014 III 24.256 148 C 0.499 0.133 0.300 93.20 93.20%

Very Satisfactory

ORANI BUILDERS SUPPLY 5349 Improvement ofConcrete Revetment of Colo River, Magsaysay Section 8/12/2014 III 12.825 158 C 0.401 0.191 0.300 89.20 89.20%

Very Satisfactory

Orani Builders Supply 5349 Replacement/Rehab./Strengthening of Pangulisan Bridge along Jct. Layac-Balanga-Mariveles Port Rd. 08/03/13 III 3.447 48 C 0.433 0.133 0.300 - - - 86.60 *86.60%

Satisfactory

Orani Builders Supply 5349 Replacement/Rehab./Strengthening of Limay Bridge along Jct. Layac-Balanga-Mariveles Port Rd. 08/03/13 III 24.030 148 O 0.400 0.240 0.150 0.030 0.050 0.033 90.30

Orani Builders Supply 5349Rehab./Reconst./Upgrading of Jct. Layac-Balanga-

Mariveles Port Rd. (Mariveles Zigzag Rd.) K0158+398-K0160+120

08/02/13 III 46.523 148 O 0.379 0.240 0.150 0.030 0.045 0.033 87.70

Orani Builders Supply 5349 Asphalt Overlay of Tabacan-Poblacion Road 05/20/09 III 16.268 120 O 0.400 0.200 0.150 0.023 0.025 0.050 84.80 -Orani Builders Supply 5349 Widening of Gapan-San Fernando-Olongapo Road 05/20/09 III 28.516 120 O 0.350 0.209 0.150 0.030 0.040 0.050 82.90 -Orani Builders Supply 5349 Concreting of Mabatang-Vicinal Road 05/20/09 III 7.643 120 O 0.314 0.233 0.150 0.030 0.037 0.050 81.40 -

Orani Builders Supply 5349 Replacement of Castañeda Bridge along TLLR, (Km.37+340-Km.37+466) Lubang Island 03/24/12 IVB 7.386 150 O 0.388 0.240 0.150 0.022 0.018 0.050 86.80 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page207

Page 208: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Orani Builders Supply 5349 Replacement & Const. of Palasingsingan Bridge, Km.24+900-Km.25+057.50, Lubang Island 03/24/12 IVB 9.821 240 O 0.389 0.240 0.150 0.020 0.029 0.033 86.10 -

Orient Star Const./Lumel Glenn Const. (JV) JV-09-001 Completion of Mindoro Oriental/Occidental East Coastal

Road, Nasucob-Campasaan Sect. 09/04/09 IVB 14.281 200 O 0.336 0.300 0.150 0.022 0.020 0.033 86.10 -

Orient Star Construction / BCT Trading & Construction, JV JV-09-067 Const. of Bulalacao Port Development Project -Phase 2

(Ports & Harbor) 02/7-10/11 PPA 70.838 403 O 0.386 0.300 0.137 0.030 0.065 0.033 95.10 -

Orient Star Construction Inc. (Formerly: Orient Star

Construction)7183 Construction of Alcate River Control, Victoria, Oriental

Mindoro 8/11/2014 IV-B 9.015 102 C 0.420 0.133 0.300 85.30 85.30% Satisfactory

Orient Star Construction Inc./Lumel Glenn Construction - Joint Venture

Construction of Bongabong Flood Control (Minscat Section), Brgy. Labasan, Bongabong, Oriental Mindoro 8/13/2014 IV-B 9.104 135 C 0.400 0.133 0.300 83.30 83.30%

Satisfactory

Orient Star Construction Inc./Lumel Glenn Construction Joint Venture JV-11-086 Const. of Bongabong River Control (San Jose-Kaligtasan) 08/09/12 IVB 15.055 186 C 0.420 0.133 0.300 - - - 85.30 83.26%

Satisfactory

Orient Star Construction, Inc. / Lumel Glenn Construction (JV) JV-12-203 Const. of Bongabong Flood Control (Minscat Sect.) Brgy.

Labasan 07/31/13 IVB 9.104 135 C 0.450 0.143 0.300 - - - 89.30 87.62% Satisfactory

Orient Star Construction, Inc. / Lumel Glenn Construction (JV) JV-12-203 Const. of Bongabong Flood Control (Minscat Sect.), Brgy.

Labasan 03/20/13 IVB 9.104 135 O 0.365 0.242 0.150 0.030 0.045 0.033 86.50 -

Oriental Sales Center and Contractor 33630 Repair/Rehab./Impv't. along Villasis-Malasiqui-San Carlos

Road, Km.188+426-Km.189+174 w/ exception 03/14/13 I 9.256 30 C 0.431 0.200 0.300 - - - 93.10 *93.10% V. Satisfactory

Orientech Construction & Development Corporation 8874 Construction of Multi-Purpose Bldg.(Phase II) 09/04/09 XIII 14.470 210 O 0.386 0.240 0.150 0.030 0.043 0.033 88.20 -

Orpega Construction 34337 Rehab./Asphalt Overlay of Kings St. & Manager St., Brgy. Sangandaan, District 2 03/12/13 NCR 4.750 60 C 0.450 0.117 0.300 - - - 86.70 *86.70%

SatisfactoryOscar R. Sarmiento Construction,

Inc. (Formerly: O.R. Sarmiento Construction)

1411Conc. of Panglao Island Circ. Rd. (Songculan Sect.) Sec.1)K0004+002.98-K0005+774; Sec.2)K0006+637-

K00012+00008/15/13 VII 140.475 405 O 0.288 0.300 0.150 0.030 0.060 0.050 87.80

Oting Construction and Supply 32681 Conc.g/Rehab. of Brgy. Tarong-Brgy. Cabilao Rd., K000+000-K000+170 08/21/13 VI 1.494 60 C 0.407 0.133 0.300 - - - 84.00 *84.00%

SatisfactoryP. C. Panopio Construction and

Trading 32824 Upgrading/Conc. of FMR at Sta. Rita 07/29/13 III 1.866 30 C 0.396 0.133 0.300 - - - 82.90 86.26% Satisfactory

P. L Sebastian Construction 1076 Rehab./Reconst./Upgrading of Tagum-Panabo Circumferential Road 09/07/09 XI 96.181 200 O 0.389 0.241 0.150 0.030 0.051 0.050 91.10 -

P. L. SEBASTIAN COSTRUCTION 35840 Road Upgrading (Gravel to Paved) along Compostela - Cateel Road, Bango Section 10/26/2014 XI 46.993 250 C 0.366 0.189 0.300 - - - 85.50% 85.5%

Satisfactory

P.B Obial Construction 16784 Conc. along Liloy, ZN-Ipil, ZS (Phase IV) Sta. 2000+260 - Sta. 2001+010 02/25/10 IX 14.335 130 O 0.306 0.287 0.150 0.020 0.028 0.033 82.40 -

P.B Obial Construction 16784 Const. of MPB at Palomoc, Titay 06/06/10 IX 3.344 100 O 0.346 0.240 0.150 0.030 0.029 0.050 84.50 -

P.B Obial Construction 16784 Rehab./Const. of Dipolog-Sindangan-Liloy Road Magsaysay Section 06/01/09 IX 3.292 90 O 0.394 0.240 0.085 0.030 0.047 0.033 82.90 -

P.B. OBIAL CONSTRUCTION 16784 Construction/Rehabilitation of Flood Control Project in Naghalin Bridge/River Brgy. Naghalin 10/21/2014 VII 13.433 140 O 0.328 0.240 0.150 0.030 0.045 0.033 82.60% 82.6%

Satisfactory

P.B. Obial Construction 16784

Rehab./Reconst.n/Upgrading of Damaged Paved Nat'l Rds. at Mactan Circ. Rd.; a)K0031+000-K0031+221; b)K0031+655-

K0032+000; c)K0032+155-K0033+983 (Proposed for Realignment/Modification to Asphalt Overlay of Nat'l Rd. at Mactan Circ. Rd., a)K0031+000-K0031+221; b)K0031+655-

K0032+000; c)K0032+155-K0033+983

08/13/13 VII 38.448 130 C 0.425 0.200 0.300 - - - 92.50 *92.50% V. Satisfactory

P.E.R.R.C Construction and Development Corpporation Const. of 1 Unit 3-Storey School Building 10/19/12 NHA 22.123 180 O 0.331 0.263 0.049 0.030 0.050 0.033 75.60 -

P.E.R.R.C. CONSTRUCTION & DEVELOPMENT CORP. 23869

Widening of Naic Diversion including Major Junction with Indang and Governor's Drive leading to Ternate-Nasugbu

Road11/6/2014 IV 30.555 231 O 0.318 0.299 0.150 0.023 0.040 0.017 84.70% 84.7%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page208

Page 209: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

P.E.R.R.C. Construction and Development Corporation Const. of 1 Unit 3-Storey School Building 04/23/13 NHA 22.123 180 C 0.439 0.200 0.300 - - - 93.90 81.09%

Unsatisfactory

P.J Cruz Construction and Trading (Formerly: P.J. Cruz Const.) 14223 Completion of School Bldg. at Rosa Susano-Novaliches

E/S 09/14/09 NCR 11.463 152 O 0.343 0.227 0.150 0.020 0.047 0.033 82.00 -

P.J San Pedro Construction and Supply 14994 Rehab./Reconst. of Damaged Paved National Roads at

Davao-Cotabato Old Rd. 06/16/10 XI 12.257 113 O 0.377 0.240 0.150 0.030 0.047 0.033 87.70 -

P.J San Pedro Construction and Supply 14994 Completion of Multi Purpose Gymnasium 07/08/09 DOST 10.426 226 O 0.383 0.300 0.050 0.030 0.047 0.067 87.70 -

P.J San Pedro Construction and Supply 14996 Construction of Multi-Purpose Building, Brgy. Bato 03/02/09 XI 2.265 180 O 0.334 0.300 0.150 0.030 0.038 0.033 88.50 -

P.J. Cruz Construction and Trading (Formerly: P.J. Cruz Construction) 14223 Completion/Rehab. of MPB at Elias Aldana 08/15/13 NCR 0.968 45 C 0.420 0.133 0.300 - - - 85.30 *85.30%

Satisfactory

P.J. San Pedro Construction and Supply 14994 Impv't. of Drainage along Davao City Diversion Rd.,

Countryside Village 03/23/13 XI 8.995 210 C 0.434 0.133 0.300 - - - 86.70 87.90% Satisfactory

P.J. San Pedro Construction and Supply 14994 Road Upgrading along Bayabas-Eden Road, Toril District 03/29/11 XI 8.504 180 O 0.314 0.300 0.150 0.030 0.033 0.050 87.70 -

P.L Sebastian Construction 1076 Impvt./Widening of Agusan-Davao Rd. (Daang Maharlika) Poblacion Carmen and Poblacion Panabo Sect. 06/02/10 XI 30.240 180 O 0.366 0.240 0.150 0.030 0.051 0.033 87.00 -

P.L Sebastian Construction 1076 Baobo River Irrigation Project 10/21-24/08 NIA 224.599 631 O 0.368 0.162 0.070 0.030 0.042 0.200 87.17 -

P.L Sebastian Construction 1076 CP9: Impvt./Conc. of Surigao del Sur-Davao Oriental Coastal Road, (Manay-Boston) Cateel-Boston Section) 11/25/08 XI 197.331 615 O 0.393 0.271 0.100 0.030 0.065 0.100 95.90 -

P.L Sebastian Construction 1076 Impvt./Conc. of Kapalong-Talaingod-Valencia, Bukidnon Road, Brgy. Tiburcia -Brgy. Sto. Nino Section 06/03/09 XI 226.942 600 O 0.373 0.300 0.150 0.030 0.047 0.050 95.00 -

P.L Sebastian Construction 1076 Impvt./Conc. of Surigao Sur-Davao Oriental Coastal Road (Manay Boston) Cateel-Boston Section 06/09/09 XI 197.331 615 O 0.378 0.279 0.150 0.030 0.060 0.050 94.70 -

P.L Sebastian Construction 1076 Rehab./Recons/Upgrading of Carmen-Dapecol Compound Road 06/01/09 XI 67.346 180 O 0.356 0.278 0.150 0.030 0.047 0.050 91.10 -

P.L Sebastian Construction 1076 Rehab./Recons/Upgrading of Tagum-Panabo Circumferential Road 06/01/09 XI 96.181 200 O 0.400 0.197 0.120 0.030 0.042 0.033 82.20 -

P.L Sebastian Construction 1076 Impv't/Conc. of Kapalong-Talaingod-Valencia Bukidnon Road, Brgy. Tiburcia to Brgy. Sto. Nino Sect. 03/14/09 XI 226.943 600 O 0.375 0.300 0.150 0.030 0.060 0.050 96.50 -

P.L Sebastian Construction 1076 CP-9: Imprvt./ Concreting of Surigao-Davao Oriental Coastal Road, (Manay-Boston) Cateel-Boston Section 09/11/09 XI 197.331 615 O 0.374 0.300 0.150 0.030 0.054 0.050 95.80 -

P.L Sebastian Construction 1076 Rehab./Reconst./Upgrading of Carmen-Dapecol Compound Road 09/07/09 XI 67.347 180 O 0.347 0.300 0.150 0.030 0.047 0.050 92.40 -

P.L. SEBASTIAN CONSTRUCTION 35840 Replacement of Tiblawan Bridge and approaches along Tibanban-Lavigan Road 8/14/2014 XI 61.263 375 C 0.482 0.200 0.300 98.20 82.48%

Satisfactory

P.L. Sebastian Construction 35840 Dummun River Irrigation System, Cagayan - Batanes IMO, Region 2 PIDP2-C-DRISN-1 04/26/14 NIA 67.006 911 C 0.432 0.200 0.300 - - - 93.20 *93.21%

V. Satisfactory

P.L. Sebastian Construction 35840 Replacement of Tiblawan Bridge & Approaches along Tibanban-Lavigan Rd. 08/15/13 XI 61.263 210 O 0.333 0.225 0.066 0.030 0.033 0.033 72.00

P.L. Sebastian Construction 1076Preventive Maint. of Daang Maharlika (MN) a.)Km.1478+(-

)13-Km.1479+095 b.)Km.1480+(-)342-Km.1480+002 c.)Km.1482+905-Km.1482+1015

03/26/12 XI 13.433 90 C 0.422 0.200 0.300 - - - 92.20 90.10% V. Satisfactory

P.L. Sebastian Construction 35840 Prev. Maint. along Tagum-Panabo Circ. Rd. Km.1505+243-Km.1505+772 03/18/13 XI 10.268 47 C 0.396 0.133 0.300 - - - 82.90 *82.90%

Satisfactory

P.L. Sebastian Construction / R.D. Interior Junior Construction / Wee

Eng Construction Inc. (JV)JV-10-040 Impvt. of Digos-Cotabato Rd., Contract Package-R1 - 2.7B,

Kidapawan-Pagalungan Sect. under NRIMP II 08/13/12 NRIM-PMO 379.100 639 O 0.390 0.245 0.150 0.030 0.056 0.050 92.10 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page209

Page 210: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

P.L. Sebastian Construction/ R.D. Interior Junior Construction / Wee

Eng Construction Inc. (JV)JV-10-040

Impv't. of Digos-Cotabato Rd., Contract Package-R1-2.7B, Kidapawan-Pagalungan Sect. under the Nat'l Rds. Impv't. &

Mgt. Program Phase II (NRIMP II)03/17/13 XII 379.100 639 O 0.317 0.300 0.100 0.030 0.055 0.033 83.50 -

P.S. SEPIAN CONSTRUCTION AND TRUCKING 20519

Upgrading of Balili-Suyo-Sagada Road leading to Sagada Cave, Rice Terraces and Water Falls, Bontoc, Mountain

Province8/12/2014 CAR 92.188 237 OG 0.373 0.240 0.150 0.024 0.050 0.050 88.70

P.T. DIAMOND MERCHANDISE & CONSTRUCTION 15451 Rehabilitation of Local Roads, Barangay Poblacion,

Bangued, Abra 8/11/2014 CAR 9.772 38 C 0.445 0.133 0.300 87.80 87.80% Satisfactory

P.T. DIAMOND MERCHANDISE AND CONSTRUCTION 15451 Rehabilitation of Revetment/Protection Works along

Parsua River 10/23/2014 I 7.129 71 C 0.438 0.133 0.300 - - - 87.10% 87.1% Satisfactory

P.T. DIAMOND MERCHANDISE AND CONSTRUCTION 15451 Rehabilitation of Road Along Manila North Road (MNR) 10/23/2015 I 9.265 121 C 0.441 0.200 0.300 - - - 94.10% 94.1%

Very SatisfactoryP.T. DIAMOND MERCHANDISE

AND CONSTRUCTION 15451 Rehabilitation of Roads along Manila North Road Km. 423+500 to Km. 429+700 w/ Exception 10/23/2014 I 9.184 150 C 0.453 0.168 0.300 - - - 92.10% 92.1%

Very SatisfactoryPABLO S. LABASBAS

CONSTRUCTION 6302 Concreting of Jct. Bolod-Bolod - Albor Road, Libjo, Dinagat Island 10/27/2014 XIII 23.700 225 O 0.272 0.239 0.000 0.024 0.042 0.033 61.00% 61%

PoorPABLO S. LABASBAS

CONSTRUCTION 6302 Repair/Rehab./Imprv't. of Malayog Flood Control 8/13/2014 VIII 17.817 150 C 0.480 0.133 0.300 91.30 90.46% Very Satisfactory

PABLO S. LABASBAS CONSTRUCTION 6302

Raising of Grade & Drainage (Flooded Section) Jct. Buenavista - Lawaan - Marabut Road KO997+448.80 -

KO998+2928/14/2014 VIII 21.361 138 C 0.341 0.200 0.300 84.10 73.78%

Poor

PABLO S. LABASBAS CONSTRUCTION

Help for Catubig Agricultural Advancement Project HCAAP-LCB-C3-2012 03/15/14 NIA 17.663 577 O 0.386 0.261 0.052 0.030 0.070 0.050 84.87 -

Pablo S. Labasbas Construction 6302 Const. of 1 unit-2 Storey 8 CL Sch. Bldg. & 1 unit-1 Storey 3 CL Sch. Bldg,. Carigara School of Fisheries 08/17/13 VIII 11.222 200 O 0.347 0.240 0.150 0.023 0.045 0.050 85.50

Pablo S. Labasbas Construction 6302 Repair/Rehab./Impv't. of Malayog Flood Control, Brgy. Malayog 08/13/13 VIII 17.817 150 O 0.391 0.240 0.150 0.030 0.055 0.033 89.90

Pablo S. Labasbas Construction 6302 Const. of Retaining Wall and Line Ditch Canal along Calbayog-Allen Rd., K0699+200-K0713+000 w/ exceptions 08/13/13 VIII 19.300 150 O 0.335 0.240 0.150 0.030 0.055 0.033 84.30

Pablo S. Labasbas Construction 6302 Raising of Grade & Drainage (Flooded Sect.) Jct. Buenavista-Lawaan-Marabut Rd., K0997+448.80-K0998+292 08/19/13 VIII 21.361 148 O 0.272 0.300 0.000 0.030 0.050 0.017 66.90

Pablo S. Labasbas Construction 6302 Const. of Gandara-Matuguinao Road 03/10/09 VIII 24.121 240 O 0.351 0.240 0.150 0.030 0.047 0.033 85.10 -

Pablo S. Labasbas Construction 6302 Const. of MPB, Brgy. Capoocan 03/25/12 VIII 1.900 120 C 0.473 0.133 0.300 - - - 90.60 85.35% Satisfactory

Pablo S. Labasbas Construction 6302 Const. of Sch. Bldg. Brgy. Hamorawon 03/26/12 VIII 4.583 120 C 0.429 0.133 0.300 - - - 86.20 84.24% Satisfactory

Pablo S. Labasbas Construction 6302Repair of Damaged Rd. Sect. along Looc-Odionagan-San

Andres Rd., Km.3+334.30-Km.17+500 (IS) / (Km.3+400-Km.17+500 (IS)

11/29/12 IVB 10.102 150 O 0.353 0.240 0.150 0.023 0.040 0.033 83.90 -

Pablo S. Labasbas Construction 6302 Rehab./Reconst. of Damaged Paved Nat'l Rd. along Daang Maharlika, K0703+225-K0704+440 w/ exceptions 08/08/12 VIII 17.890 60 C 0.425 0.133 0.300 - - - 85.80 83.28%

Satisfactory

Pacer Construction & Development Corporation 4839 Repair/Rehab. of Flood Control Structures at Abucay

Creek 08/22/13 VIII 1.991 60 C 0.457 0.133 0.300 - - - 89.00 *89.00% Satisfactory

Pacific Concrete Products Inc. 17150 Prev. Maint. along Meycauayan Service Rd., K0000+000-K0000+577 w/ exception 03/21/13 III 5.773 15 C 0.431 0.133 0.300 - - - 86.40 *86.40%

Satisfactory

Pacific Star Erectors 14224 Completion of Payanan MPB, San Gregorio 08/12/13 CAR 2.885 90 C 0.485 0.133 0.300 - - - 91.80 *91.80% V. Satisfactory

Pacific Star Erectors 14224 Const. of Bunot Bridge along Apayao (Calanasan)-Ilocos Norte Rd. 03/22/13 CAR 10.398 165 O 0.363 0.300 0.090 0.022 0.025 0.033 83.30 -

Pacific Star Erectors 14224 Const. of Apayao State College MPB (Phase IV) 05/30/09 CAR 4.717 180 O 0.343 0.292 0.150 0.030 0.029 0.033 87.70 -

Pacific Star Erectors 14224 Construction of Apayao State College Multi-Purpose Building 02/28/09 CAR 2.324 150 O 0.391 0.300 0.150 0.030 0.045 0.033 94.90 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page210

Page 211: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Pacific Star Erectors 14224 Construction of Pudtol MPB (Gymnasium) Phase IV 02/27/09 CAR 6.613 210 O 0.327 0.300 0.150 0.022 0.041 0.033 87.30 -

Pacific Star Erectors 14224 Const. of San Gregorio MPB, Luna (Const. of Grandstand, Phase I) 03/22/13 CAR 4.767 210 C 0.464 0.133 0.300 - - - 89.70 *89.70%

V. Satisfactory

Pacific Star Erectors 14224 Const. of TESDA Bldg. (Phase 3) 08/12/12 CAR 2.742 180 C 0.373 0.200 0.300 - - - 87.30 86.18% Satisfactory

Pacific Star Erectors / ASC Construction & Concrete Products

(JV)JV-10-128 Rd. Upgrading along Conner-Kabugao Rd., K0566+411-

K0567+594.50 08/10/12 CAR 18.650 275 C 0.392 0.200 0.000 - - - 59.20 73.42% Poor

Pacific Stars Erectors 14224 Const. of DPWH Regional Office Building (Phase VII) Region II 04/03/11 II 10.605 300 O 0.386 0.300 0.150 0.023 0.037 0.033 92.90 -

Pacific Stars Erectors 14224 Construction of Pudtol MPB (Gymnasium) 09/04/09 CAR 6.613 266 O 0.396 0.240 0.150 0.030 0.056 0.033 90.50 -

Pacific Stars Erectors 14225 Construction of Apayao State College MPB (Phase IV) 09/04/09 CAR 4.712 199 O 0.393 0.240 0.150 0.030 0.056 0.033 90.20 -

PADER CONSTRUCTION AND SUPPLY 20213

Road Upgrading (Gravel to Concrete) along Bukidnon - Cotabato Road,Tambad, Carmen, Cotabato (Km. 1608+572 -

Km. 1608+634.41)8/11/2014 XII 1.512 49 C 0.457 0.149 0.300 90.60 90.60%

Very Satisfactory

Pader Construction and Supply 20213 Construction of 2 CL SB at Eliseo E/S 03/04/09 XII 1.047 70 O 0.353 0.300 0.150 0.030 0.035 0.033 90.10 -

PALMARES GENERAL MERCHANDISE 24657 Repair/Rehab. Of Banga River Flood Control and Drainage

along Cotabato - Marbel Road, Kibid - Dumaguil Section 8/5/2014 XII 7.850 120 C 0.418 0.200 0.300 91.80 85.98% Satisfactory

Palmares General Merchandise 24657 Conc. Of Malvar St.-Roxas Ave., Brgy. Pob. 08/05/13 XII 9.504 115 C 0.396 0.200 0.300 - - - 89.60 *89.60% V. Satisfactory

Palmares General Merchandise 24657 Repair/Rehab. of Banga River Flood Control & Drainage along Cotabato-Marbel Rd., Kibid-Dumaguil Sect. 08/06/13 XII 7.850 120 O 0.240 0.300 0.150 0.030 0.051 0.050 82.10

Palmares General Merchandise 24657 Conc./Widening of Midsayap-Marbel Rd,. Maibu Sect., Km1783+482-Km1784+515 11/25/12 XII 11.600 215 C 0.448 0.133 0.300 - - - 88.10 88.58%

Satisfactory

Palmares General Merchandise 24657

Conc./Widening of Midsayap-Marbel Rd. (Maibu Sect.), Km.1783+482-Km.1784+515, Tantangan, (savings of

Rehab./Reconst./Upgrading of damaged paved Nat'l Rd., (2nd District) along Marbel-Makar Rd., K1710+530-

K1710+290, K1709+260-K1708+300, K1708+310-K1707+410, K1707+420-K1706+520, K1706+500-K1705+580;

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd., (2nd District) along Marbel Makar Rd., K1700+571-

K1702+562)

08/07/12 XII 11.600 200 O 0.374 0.238 0.150 0.030 0.047 0.050 88.90 -

Palmea Construction & Development 8200 Construction of Lateral "A" at Sta. 5+299.75 - Sta 5+510.80

of Laris 02/27-03/03/12 NIA 3.904 60 O 0.374 0.287 0.106 0.030 0.038 0.050 88.52 -

Panay East Coast Construction & Supply 26469 Impvt. of Drainage System, Brgy. Poblacion (along Plaza) 03/05/10 VI 0.481 60 O 0.347 0.300 0.044 0.010 0.023 0.033 75.70 -

Panay East Coast Construction & Supply 26469 Jalaur-Suage River Irrigation System 01/10-15/11 NIA 3.307 224 O 0.3890 0.2407 0.0792 0.0300 0.0573 0.0500 84.62 -

Panay East Coast Construction and Supply 26469 Const. of FMR, Brgy. Balantang Sitio Bintud 08/23/13 VI 3.872 60 C 0.472 0.133 0.300 - - - 90.50 *90.50%

V. Satisfactory

Panay East Coast Construction and Supply 26469

Rd. Upgrading (Gravel to Paved) of Nat'l Secondary Rd., Guimbal-Igbaras-Tubungan-Leon Rd., K0067+591-

K0067+992.6 Brgy. Tina-an Sur Sect.08/22/13 VI 6.129 90 C 0.463 0.133 0.300 - - - 89.60 91.94%

V. Satisfactory

Panay East Coast Construction and Supply 26469

Road Upgrading (Gravel to Paved) of Nat'l. Secondary Rd., Guimbal-Igbaras-Tubungan-Leon Rd., K0067+591-

K0067+992.6, Brgy. Tina-an Sur Sect.03/22/13 VI 6.129 90 O 0.360 0.300 0.150 0.030 0.045 0.050 93.50 -

Panay East Coast Construction and Supply 26469 Rehab. of Damaged Paved along Capiz-Aklan Rd.,

Km.332+000-Km.332+342, Pob., Sepian Sect. 08/19/11 VI 5.371 100 O 0.334 0.215 0.150 0.030 0.050 0.033 81.20 -

Panay East Coast Construction and Supply 26469 Rehab. of Damaged Paved along Capiz-Aklan Rd.,

Km.332+000-Km.332+342, Pob. Sapian Sect. 08/21/12 VI 5.371 100 C 0.408 0.200 0.300 - - - 90.80 85.04% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page211

Page 212: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Pangasinan New Wilson Lumber & Construction 8313

Widening of Camiling-Wawa-Bayambang-Malasiqui-Sta. Barbara Road (Malasiqui Section) Km. 193+490 to Km.

194+1208/12/2014 I 20.165 193 C 0.418 0.133 0.300 85.10 84.77%

Satisfactory

Pangasinan New Wilson Lumber & Construction 8313

Widening of Camiling-Wawa-Bayambang-Malasiqui-Sta. Barbara Road (Bayambang Section) Km. 180+440 to Km.

181+247.85, Pangasinan (Phase II)8/12/2014 I 21.713 200 C 0.380 0.200 0.300 88.00 83.74%

Satisfactory

Pangasinan New Wilson Lumber & Construction 8313

Widening of Camiling-Wawa-Bayambang-Malasiqui-Sta. Barbara Rd. (Bayambang Sect.) Km.180+500-Km. 181+120,

(Phase II)08/03/13 I 21.713 200 O 0.343 0.300 0.044 0.030 0.042 0.050 80.90

Pangasinan New Wilson Lumber & Construction 8313 Widening of Camiling-Wawa-Bayambang-Malasiqui-Sta.

Barbara Rd. (Malasiqui Sect.) Km.193+490-Km.194+120 03/14/13 I 20.166 170 O 0.397 0.300 0.025 0.015 0.029 0.033 79.90 -

Pangasinan New Wilson Lumber & Construction 8313 Widening of Camiling-Wawa-Bayambang-Malasiqui-Sta.

Barbara Rd. (Malasiqui Sect.) Km. 193+490-Km. 194+120 08/02/13 I 20.166 200 O 0.332 0.300 0.150 0.030 0.047 0.033 89.20

Pangasinan New Wilson Lumber & Construction / Pas Construction &

Supplies (JV)JV-12-463 Repair/Rehab./Impv't. of Lingayen-Binmaley Rd. K0363+(-

762)-K0364+061 w/ exception 08/06/13 I 9.404 76 C 0.471 0.133 0.300 - - - 90.40 89.68% V. Satisfactory

Pangasinan New Wilson Lumber / Pas Construction & Supplies (JV) JV-12-463 Repair/Rehab./Impv't. of Lingayen-Binmaley Rd., K0363+(-

762)-K0364+061 w/ exception 03/16/13 I 9.405 76 O 0.339 0.300 0.150 0.030 0.040 0.033 89.20 -

Partido Construction & Supply 20631 Impvt. of Junction Digdigon (GOA)-Tinambac Road, (Balaynan-Tierra Nevada Sect.) 05/31/09 V 21.358 150 O 0.303 0.300 0.150 0.030 0.055 0.050 88.80 -

Partido Construction & Supply 20631 Conc. of Bagong Silang Capalonga Road, Katabangan Sect. 06/04/09 V 6.021 180 O 0.366 0.240 0.150 0.030 0.050 0.050 88.60 -

Partido Construction & Supply 20631 Conc.of Goa-Tinambac Road, Payatan-Tupi-Tierra Nevaion 03/10/09 V 4.704 165 O 0.388 0.240 0.150 0.030 0.056 0.050 91.40 -

Partido Construction & Supply 20631 Impvt. of Jct. Digdigon (GOA)-Tinambac Road, (Balaynan-Tierra Nevada Section) 09/09/09 V 21.358 175 O 0.318 0.300 0.150 0.030 0.051 0.050 89.90 -

PARTIDO CONSTRUCTION AND SUPPLY 20631

Road Upgrading (Gravel to Paved) of Digdigon (Goa)-Tinambac Road, Goa, Camarines Sur K0496+072 -

K0496+34311/13/2014 V 7.124 105 C 0.451 0.155 0.300 - - - 90.60% 90.6%

Very Satisfactory

Partido Construction and Supply 20631 Road Upgrading (Gravel to Paved) of Jct. Digdigon (Goa) - Tinambac Road, K0496+072 - K0496+388 with exceptions 8/9/2014 V 7.124 105 C 0.401 0.164 0.300 86.50 86.50%

Satisfactory

Partido Construction and Supply 20631 Conc. of Goa-Digdigon-San Isidro Rd. 08/02/13 V 19.552 147 C 0.438 0.135 0.300 - - - 87.30 *87.30% Satisfactory

Partido Construction and Supply 20631 Conc. of Goa-Digdigon-San Isidro Rd., Km. 489+000-Km. 490+250 08/10/12 V 22.824 195 C 0.472 0.133 0.300 - - - 90.50 88.70%

Satisfactory

PAS CONSTRUCTION & SUPPLIES 32890 Preventive Maintenance along Pangasinan- Zambales Road K0353+860 to K0354+500 10/28/2014 I 6.673 10 C 0.468 0.136 0.300 - - - 90.40% 90.4%

Very Satisfactory

PASCAL CONSTRUCTION 34168 Rehabilitation and/or Improvement of Tourism Activity Center 05/14/14 TIEZA 2.497 120 C 0.480 0.200 0.300 98.00 98.00%

Outstanding

Pascal Construction 34168 Const./Impvt. of MPB 03/20/12 III 2.786 117 C 0.483 0.133 0.300 - - - 91.60 85.23% Satisfactory

Pascal Construction 34168Repair/Reconst./Upgrading of Damaged Paved Nat'l Rd.,

Jct.-Layac-Balanga-Mariveles Port Road (K0107+393-K0107+764)

08/09/12 III 5.314 105 C 0.378 0.200 0.300 - - - 87.80 88.10% Satisfactory

Pascal Construction 34168 Repair/Maint. of San Pedro River Control 03/12/13 III 1.869 75 C 0.445 0.133 0.300 - - - 87.80 *87.80% Satisfactory

PATRICK CONSTRUCTION 27780Rehabilitation of Bridge Approach along Dugo-San Vicente

Road (DSVR), Palagao Bridge No. 2, KO591+1097, Simpatuyo

10/20/2014 II 1.386 52 C 0.404 0.200 0.150 - - - 75.40% 75.4% Unsatisfactory

Patrick Construction 27780 Rehab./Impvt./Const. of DPWH-CFDEO Building, Minanga 03/12/12 II 3.619 150 C 0.423 0.188 0.300 - - - 91.10 *86.90% Satisfactory

PATRILA BUILDERS, INC. 26628 Widening of Iloilo East Coast-Estancia Wharf Road K0178+(-817) - K0179+040 10/29/2014 VI 42.699 323 O 0.366 0.210 0.150 0.030 0.054 0.050 86.00% 86%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page212

Page 213: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Patrila Builders, Inc. 26628 Rehabilitation of San Miguel-Sebaste, Sibunag/Region VI 06/10/11 Guimaras 25.649 30 weeks O 0.400 0.300 0.150 0.030 0.070 0.050 100.00 -

Patrila Builders, Inc. 26628 Rehabilitation of San Miguel-Sebaste, Sibunag/Region VI 08/15/11 Guimaras 28.022 34 weeks O 0.399 0.300 0.150 0.024 0.070 0.050 99.30 -

Patrila Builders, Inc. 26628 Rehabilitation of San Miguel-Sebaste, Sibunag/Region VI 02/08/12 Guimaras 29.622 44 weeks C 0.487 0.197 0.300 - - - 98.37 99.14% Outstanding

Patrila Builders, Inc. 26628 Upgrading/Concreting of Ajuy-Concepcion Road 06/09/09 VI 9.233 240 O 0.373 0.300 0.150 0.030 0.050 0.050 95.30 -Patrila Builders, Inc. 26628 Upgrading/Conc. of Ajuy-Concepcion Road 03/17/09 VI 8.394 180 O 0.362 0.300 0.150 0.030 0.055 0.050 94.70 -Patrila Builders, Inc. 26658 Upgrading/Conc. of Ajuy-Concepcion Road 09/08/09 VI 9.233 240 O 0.322 0.286 0.000 0.030 0.050 0.050 73.80 -

Patrila Builders, Inc. 26628

Rehab./Reconst./Upgrading of Damage Paved Nat'l Arterial Rd.; a)Conc. of Iloilo East-Coast Rd., Km.251+545.50-Km.251+644.50 b)Conc. of Iloilo East-Coast Capiz Rd.,

Km.251+644.50-Km.251+995.50

08/23/12 VI 6.278 185 C 0.368 0.200 0.300 - - - 86.80 84.40% Satisfactory

Patrila Builders, Inc. 26628 Rehabilitation of San Miguel-Sebaste Road 08/15/11 PPA 25.649 30 O 0.399 0.300 0.150 0.024 0.070 0.050 99.30 -

Patrilla Builders Inc. 26628 Construction of Gaban CIP 04/05/14 NIA 3.339 120 C 0.427 0.191 0.300 - - - 91.80 *91.80% V. Satisfactory

PAULA MAE BUHONG CONSTRUCTION 26128

Road Upgrading (Gravel to Paved) Along Banaue-Hungduan-Benguet Bdry Road, K0368+000 to K0370+300,

Hungduan, Ifugao8/5/2014 CAR 48.461 328 C 0.418 0.133 0.300 85.10 87.08%

Satisfactory

Paula Mae Buhong Construction 26128 Rd. Upgrading (Gravel to Conc.) of Banaue-Hungduan-Benguet Bdry. Rd., K0368+000-K0370+300 08/04/13 CAR 44.934 296 O 0.371 0.240 0.150 0.023 0.050 0.050 88.40

Paula Mae Buhong Construction 26128 Widening/Concreting of Banaue-Hungduan-Tinoc-Benguet Bdry. Rd., Hwang Section 02/25/10 CAR 4.739 349 O 0.356 0.240 0.150 0.030 0.030 0.033 83.90 -

PBO Construction 18403Impvt./Widening/Conc. of Bontoc-Tabuk-Tuguegarao Road, Phase IV, Km. 461+000-Km. 467+000, Lubuagan-Cagaluan

Section03/04/09 CAR 47.185 300 O 0.255 0.285 0.150 0.030 0.041 0.050 81.10 -

PBO Construction 18403 Widening/Concreting of Mayoyao-Aguinaldo Road, Km. 399+000 - Km. 419+000 (w/ exception) 03/06/09 CAR 68.468 420 O 0.296 0.136 0.150 0.022 0.032 0.017 65.30 -

PBO Construction 18403 Widening/Concreting of Mayoyao-Aguinaldo Road, Km. 399+000 - Km. 419+000 (w/ exception) 02/24/10 CAR 68.441 473 O 0.348 0.240 0.144 0.030 0.045 0.033 84.00 -

PBO Construction 18403Impvt./Widening/Conc. of Bontoc-Tabuk-Tuguegarao Road, Phase IV, Km. 461+000-Km. 467+000, Lubuagan-Cagaluan

Section11/19/08 CAR 47.185 300 O 0.305 0.240 0.100 0.030 0.040 0.100 81.50 -

PBO Construction 18403 Rd. Upgrading (Gravel to Concrete) along Kalinga-Abra Rd. K0470+000-K0472+100, Ableg-Balenciagao Sur, Pasil Sect. 11/26/12 CAR 48.989 263 O 0.374 0.240 0.117 0.023 0.050 0.033 83.70 -

PBO Construction 18403 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. (IS) along Abbut-Conner Rd., K0572+203-K0573+980 11/28/12 CAR 17.030 179 C 0.398 0.200 0.000 - - - 59.80 69.16%

Poor

PBO Construction 18403 Rehab./Reconst. Of Damaged Paved Nat'l Rds. (IS) along Abbut-Conner Rd., K0572+203-K0573+980 08/10/12 CAR 17.030 179 O 0.299 0.300 0.085 0.000 0.037 0.033 75.40 -

Pearl Construction and Supply 34806 Conc. of Road, Brgy. Esperanza 08/06/13 XII 2.290 120 C 0.468 0.200 0.150 - - - 81.80 85.88% Satisfactory

Pearl Construction and Supply 34806 Conc. of Road, Brgy. Esperenza 03/20/13 XII 2.290 120 O 0.360 0.279 0.134 0.030 0.050 0.033 88.60 -

Pearl Construction and Supply 34806 Const. of MPB, Marbel 5 Elem. School, Bo.5 03/28/12 XII 2.702 105 C 0.458 0.133 0.300 - - - 89.10 86.65% Satisfactory

Pentagon Industrial Development & Construction Company,

Incorporated12796

Impvt./Widening of McArthur Highway (MNR)-Phase V, Meycauayan (Bulacan) to Mabalacat (Pampanga)-

(Meycauayan-Marilao Section)-CP III09/09/09 III 47.235 150 O 0.376 0.300 0.150 0.030 0.042 0.033 93.10 -

Persan Construction Inc. 2852Const./Conc. of Sect. Of the Third Bulacan Circum. Rd.

Network Daang Maharlika-DRT Via San Ildefonso Rd. (San Ildefonso Sect.)

03/04/10 III 47.642 210 O 0.367 0.300 0.150 0.030 0.047 0.050 94.40 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page213

Page 214: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Persan Construction Inc. 2852Const./Conc. Of Sects. Of the Third Bulacan Circum. Rd. Network CVR-San Miguel-DRT-Angat Gen. Alejo Santos

Highway (Akle to DRT Sect.)03/04/10 III 47.642 210 O 0.338 0.296 0.150 0.030 0.042 0.050 90.60 -

Persan Construction Inc. 2852 Conc. and Const. of Slope Protection of Pintong Bukawe FMR 02/18/10 IVA 19.230 120 O 0.333 0.300 0.150 0.030 0.050 0.033 89.60 -

Persan Construction Inc. (Formerly: Persan Construction) 2852 Prev. Maint. (Int. Sect.) along R-10 08/12/13 NCR 7.919 121 C 0.399 0.133 0.300 - - - 83.20 *83.20%

Satisfactory

Persan Construction, Inc. 2852 Impvt./Rehab. of Daang Maharlika Road, Bulacan 3rd Congressional District 06/04/09 III 77.094 150 O 0.364 0.300 0.150 0.030 0.050 0.050 94.40 -

Persan Construction, Inc. 2852 Rehabilitation of Sibul-Biak Na Bato Road 06/01/09 III 14.299 110 O 0.372 0.239 0.150 0.030 0.051 0.050 89.20 -Persan Construction, Inc. 2852 Improvement of Pintong-Bukawe Road 08/24/09 IVA 19.232 180 O 0.341 0.285 0.150 0.030 0.043 0.050 89.90 -

Persan Construction, Inc. 2852 Widening of Carmona Bridge (Phase I) inc. approaches 03/03/10 IVA 60.454 529 O 0.393 0.300 0.150 0.030 0.050 0.033 95.60 -

Persan Construction, Inc. 2852 Rehab. of FMR, Brgy. Pintong Bukawe 03/14/09 IV-A 18.711 150 O 0.375 0.276 0.150 0.030 0.033 0.050 91.40 -

Persan Construction, Inc. 2852 Impvt. And Rehab. of Daang Maharlika Road, San Rafael-San Ildefonso Section 11/21/08 III 95.473 120 O 0.370 0.300 0.100 0.018 0.037 0.100 92.50 -

Persan Construction, Inc. 2852 Impvt./Rehab. of Daang Maharlika Road 09/08/09 III 77.099 150 O 0.362 0.300 0.150 0.030 0.051 0.033 92.60 -

Persan Construction, Inc. (Formerly: Persan Construction) 2852 Repair/Rehab./Impv't. of Sta. Maria-Norzagaray Rd.

(Norzagaray Sect.), K0043+300-K0044+958 w/ exceptions 08/15/13 III 9.643 30 C 0.423 0.133 0.300 - - - 85.60 *85.60% Satisfactory

Persan Construction, Inc. (Formerly: Persan Construction) 2852

Assets Preservation of Nat'l Rds., Prev. Maint. (MFO-1) (Int. Sect.), Arterial Rd. Asphalt Overlay of Dasmariñas-

Carmona Rd., K00358+120-K0035+71008/14/13 IVA 6.925 120 C 0.394 0.200 0.300 - - - 89.40 *89.40% V.

Satisfactory

Persan Construction, Inc. (Formerly: Persan Construction) 2852 Repair/Rehab./Reconst./Upgrading of Gen. Luna St. 06/28/10 NCR 15.360 145 O 0.385 0.300 0.150 0.030 0.055 0.050 97.00 -

Persan Construction, Inc. / Ulticon Builders, Inc. (JV) JV-07-108 Impv't/Conc. of Kapalong-Talaingod Bdry. Valencia

Bukidnon Road, Sitio Napisulan to Highway Bdry. 03/14/09 XI 738.154 780 O 0.399 0.300 0.150 0.022 0.055 0.050 97.60 -

Persan Construction, Incorporated / HG III Construction and

Development Corporation (JV)JV-08-038 Implementation of Civil Works for Const. of CP 2,

Pantabangan-Canili Road Sect. 04/11/11 PJHL 579.000 499 O 0.339 0.300 0.150 0.030 0.042 0.050 91.10 -

Persan Construction/Ulticon Builders, Inc. (JV) JV-07-108

Impvt./Conc. of Kapalong-Talaingod-Valencia, Bukidnon Road (Sitio Napisulan to Highway Boundary, Valencia

Section) 06/03/09 XI 738.153 780 O 0.394 0.300 0.150 0.030 0.042 0.050 96.60 -

Petrina Construction & General Merchandise (Formerly: Petrina

Grocers Marketing)29695 Const. of Classroom at Bangcud NHS 08/10/13 X 6.509 180 O 0.360 0.205 0.150 0.030 0.029 0.033 80.70

PETRINA CONSTRUCTION & GENERAL MERCHANDISING (Formerly: Petrina Grocers

Marketing)

29695 Construction of Classroom at Bangcud National High School 8/5/2014 X 6.509 210 C 0.494 0.168 0.000 66.20 76.35%

Unsatisfactory

PGM Construction & Plumbing Services 9997 Supply of Labor and Materials for Proposed Arch Gateway 11/23/11 UP 0.737 60 O 0.372 0.300 0.150 0.000 0.028 0.050 90.00 -

PGM Construction & Plumbing Services Renovation of Ten Laboratory 02/17/11 UP 14.019 150 O 0.305 0.300 0.150 0.030 0.051 0.050 88.60 -

PGO CONSTRUCTION 15153Road Upgrading (Gravel to Paved) / Concreting of Stop Aguinaldo - Bug-Ang Road, K0111+543 - K0112+153 and

K0112+648 - K0113+59510/22/2014 VI 42.400 207 C 0.439 0.133 0.300 - - - 87.20% 87.2%

Satisfactory

PGO Construction 15153 Rehab./Reblocking of Deteriorated Conc. Pavement along Bacolod North Road 03/10/09 VI 9.231 220 O 0.331 0.300 0.150 0.030 0.060 0.033 90.40 -

PGO Construction 15153 Rehab./Reblocking of Deteriorated Conc. Pavement along Bacolod North Road 11/24/08 VI 9.231 220 O 0.343 0.225 0.100 0.022 0.048 0.067 80.50 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page214

Page 215: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

PGO Construction 15153Road Upgrading/Conc. Of Jct. Nat'l Road, Sagay-Bato-Dian-

Ay-Marcelo-Balea Jct. Nat'l Rd., K0109+117-K0110+160(Bug-ang Sect)

03/27/12 VI 17.788 210 C 0.322 0.200 0.300 - - - 82.20 85.86% Satisfactory

PGO Construction 15153Road Upgrading/Conc. Of Jct. Nat. Road, Sagay-Bato-Dian-

Ay-Marcelo-Balea Jct. Nat'l Rd., K0116+460-K0117+339 (Marcelo Sect)

03/27/12 VI 17.388 202 C 0.354 0.200 0.300 - - - 85.40 84.68% Satisfactory

PHEAMES COMMUNITY CONSTRUCTION CORPORATION 31773 Widening of Daang Maharlika (with exception), Quezon LD,

MSR Diversion Road Section 11/28/2014 IV 21.560 300 O 0.372 0.241 0.150 0.030 0.045 0.033 87.10% 87.1% Satisfactory

Philippine Chemsteel Industries, Inc. 16965 Repair/Rehab./Impv't. of Famy-Real-Infanta Rd., K0130+383-

K0132+000, w/ exception 08/08/13 IVA 9.848 24 C 0.474 0.133 0.300 - - - 90.70 *90.70% V. Satisfactory

PHILSOUTH BUILDERS 21962Upgrading (Gravel to Concrete) Concreting of Dumaguete -

Valencia Road Leading to Casaroro Falls & Japanese Shrine

8/14/2014 VII 9.626 110 C 0.391 0.188 0.300 87.90 87.90% Satisfactory

PHILSOUTH BUILDERS 21962 Northern Mindanao PCG Search and Rescue Project 02/05/15 DOTC 72.130 390 O 0.395 0.300 0.104 0.030 0.055 0.050 93.45 -

Philsouth Builders 21962 Rehab. of Mainit Sect., Tanjay, Dumaguete North Rd., Km.34+000-Km.35+000 08/13/12 VII 19.270 240 C 0.388 0.133 0.300 - - - 82.10 85.16%

Satisfactory

PHILSOUTH BUILDERS 21962 Northern Mindanao PCG Search and Rescue Base Project 07/08/15 DOTC 72.130 464 O 0.374 0.300 0.103 0.030 0.063 0.050 92.00 -

PHILSOUTH BUILDERS (Formerly: Lotiff Construction) 21962

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Roads (Concrete Pavement) Dumaguete

City - Valencia - Bacong Road, K0008+(-495) to K0009+00010/28/2014 VII 21.043 142 C 0.363 0.200 0.258 - - - 82.10% 82.1%

Satisfactory

PHILSOUTH BUILDERS (Formerly: Lotiff Construction) 21962

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Roads Including Drainage Based on

Pavement Management System/Highway Development and Management-4 (HDM-4) (I.S.) Dumaguete City - Valencia -

Bacong Road, 2nd District

10/27/2014 VII 33.841 268 O 0.314 0.300 0.100 0.030 0.055 0.000 79.90% 79.9% Unsatisfactory

Philsouth Builders (Formerly: Lotiff Construction) 21962

Prev. Maint. of Jct. Murcia-Cansilayan-Damsite-Abuanan-Bago City Rd. (Asphalt Overlay), a)K0022+000-K0022+423;

b)K0023+(-67)-K0025+302 (Cluster X)08/13/13 VI 18.405 80 C 0.440 0.133 0.300 - - - 87.30 *87.30%

Satisfactory

Philsouth Builders (Formerly: Lotiff Construction) 21962 Rd. Upgrading (Gravel to Paved), Metro Dumaguete

Diversion Rd. 08/21/13 VII 45.570 179 O 0.375 0.238 0.150 0.030 0.050 0.033 87.60

Philtil Construction 21607 Rehab./Impv't. of Rds. in North Cotabato, Upper Baguer, Km.1709+460-Km.1711+580, Cabpangi 03/16/13 XII 2.833 110 C 0.432 0.133 0.300 - - - 86.50 *86.50%

Satisfactory

Philworks Construction and Supply 32103

Rehab./Reconst./Upgrading of Damaged Paved National Roads including Drainage Based on HDM-4 (Intermittent

Section), Rolando A. Andaya Highway, K0295+542-K0303+000, with exceptions

8/6/2014 V 91.805 180 OG 0.335 0.300 0.056 0.030 0.050 0.050 82.10

Philworks Construction and Supply 32103Repair and Improvement of Slope Protection & Drainage

System along Rolando Andaya Highway, A) KO 330+180 to KO330+245, B) KO327+750 to KO327+776

8/6/2014 V 5.715 154 C 0.364 0.200 0.300 86.40 85.20% Satisfactory

Philworks Construction and Supply 32103Rehab/Reconst. Of Damaged Paved National Road along Daang Maharlika Hghway, K0397+354 - K0433+964, with

exceptions8/7/2014 V 122.677 249 C 0.379 0.200 0.300 87.90 87.00%

Satisfactory

Philworks Construction and Supply 32103 Repair/Rehab. /Impv't. of Daang Maharlika, Bato Sect., K0477+000-K0479+088 w/exception 08/01/13 V 9.646 90 C 0.390 0.192 0.300 - - - 88.20 *88.20%

Satisfactory

Philworks Construction and Supply 32103 Const. of Water Impounding Proj., Belen 08/06/13 V 10.532 240 C 0.443 0.137 0.300 - - - 88.00 *88.00% Satisfactory

Philworks Construction and Supply 32103 Rehab./Restoration/Impv't. of Damaged Sect. along Libon-Marocmoc-Pantao Rd. (Mararag Sect.) 08/09/13 V 19.402 240 C 0.470 0.133 0.300 - - - 90.30 88.98%

Satisfactory

Philworks Construction and Supply 32103 Restoration/Impv't. of Damaged Sect. along Libon-Marocmoc-Pantao Rd. 08/09/13 V 19.402 240 C 0.416 0.133 0.300 - - - 84.90 86.76%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page215

Page 216: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Philworks Construction and Supply 32103 Rehab./Reconst. of Damaged Paved Nat'l Rd. along Daang Maharlika Highway, K0397+354-K0433+964 w/exceptions 08/07/13 V 122.677 249 O 0.269 0.300 0.150 0.030 0.065 0.050 86.40

Philworks Construction and Supply 32103 Const. of Martirez Bridge & Approaches 08/07/13 V 72.409 541 C 0.435 0.133 0.300 - - - 86.80 85.27% Satisfactory

Philworks Construction and Supply 32103Repair and Impv't. of Slope Protection & Drainage System along Rolando Andaya Highway, a) K0330+180-K0330+245;

b) K0327+750-K0327+776, Brgy. Bulawan08/03/13 V 7.810 120 O 0.315 0.251 0.150 0.030 0.065 0.033 84.40

Philworks Construction and Supply 32103 Rehab. of Damaged Paved Nat'l. Rd. along Daang Maharlika 03/22/13 V 163.033 376 C 0.377 0.200 0.300 - - - 87.70 88.84%

Satisfactory

Philworks Construction and Supply 32103 Const. of Martinez Bridge & Approaches 03/20/13 V 72.409 541 O 0.354 0.300 0.054 0.030 0.050 0.033 82.10 -

Philworks Construction and Supply 32103 Const./Completion of San Vicente-Gutan-Lubac-Nangaramuan-Pozo Robo Rd. 08/17/10 II 109.800 365 O 0.330 0.275 0.150 0.015 0.030 0.033 83.30 -

Philworks Construction and Supply 32103 Rehab./Restoration/Impvt. of Damaged Sect. along Libon-Marocmoc-Pantao Rd. (Mararag Sect.) 11/26/12 V 19.402 210 O 0.366 0.250 0.150 0.030 0.052 0.033 88.10 -

Philworks Construction and Supply 32103 Restoration/Impvt. of Damaged Sect. along Libon-Marocmoc-Pantao Rd. 11/26/12 V 19.402 210 O 0.375 0.240 0.150 0.030 0.052 0.033 88.00 -

Philworks Construction and Supply / MWJ Construction (JV) JV-09-087 Road Opening/Const. of Burauen Rd. including Bridges

(Sta.987+169 - Sta.990+269.40 05/31/10 VIII 94.970 300 O 0.386 0.240 0.150 0.030 0.047 0.033 88.60 -

Phintecstar Constructionn, Inc. Land Development and Construction of 409 Housing Units (Villa Diana) 06/12/15 NHA 116.999 295 O 0.371 0.258 0.150 0.030 0.051 0.050 91.08 -

PHRANARET CONSTRUCTION 16878

Road Upgrading (Gravel to Paved) of Banaue-Mayoyao-A. Lista-Isabela Bdry. Road K0343+652 - K0343+748, K0344+143 - K0344+171, K0347+880 - K0348+135, K0349+000 - K0349+190, K0349+375 - K0349+384, K0351+829 - K0351+891 & K0352+122 - K0352+503

11/26/2014 CAR 32.406 266 O 0.350 0.240 0.150 0.030 0.055 0.050 87.50% 87.5% Satisfactory

PHRANARET CONSTRUCTION 16878Road Upgrading (Gravel to Paved) along Banaue -

Hungdun - Benguet Bdry. Road, K0348+380 - K0353+205, with exception

8/10/2014 CAR 42.686 321 C 0.441 0.133 0.300 87.40 84.58% Satisfactory

Phranaret Construction 16878 Repair/Rehab./Impv't. along Nueva Vizcaya-Ifugao-Mt. Province Bdry. Rd., K0298+855-K0305+000, Lamut 08/05/13 CAR 9.459 119 C 0.451 0.133 0.300 - - - 88.40 *88.40%

Satisfactory

Phranaret Construction 16878 Rd. Upgrading (Gravel to Conc.) along Banaue-Hungduan-Benguet, K0348+380-K0353+205 08/06/13 CAR 40.013 232 O 0.347 0.300 0.067 0.030 0.050 0.033 82.70

Phranaret Construction 16878 Road Upgrading along Banaue-Hungduan-Tinoc-Benguet Bdry. Rd. (Hiwang-Bokiawan Sect.) 03/18/12 CAR 14.226 314 C 0.441 0.133 0.300 - - - 87.40 85.72%

Satisfactory

Phranaret Construction 16878Restoration of Roadslip, Slope Protection & Drainage Structures along Banaue-Habbang Rd., Km.354+000-

Km.388+000(IS), Banaue & Mayoyao08/07/12 CAR 3.145 240 C 0.375 0.200 0.300 - - - 87.50 85.46%

Satisfactory

Phranaret Construction 16878 Rd. Upgrading along Tabuk-Banaue via Tanudan-Barlig Rd. 08/07/12 CAR 45.938 310 C 0.373 0.200 0.300 - - - 87.30 82.08% Satisfactory

Phranaret Construction 16878 Repair & Rehab. of Nueva Vizcaya-Ifugao-Mt. Province Bdry. Rd., K0335+(-358)-K0345+000 (w/ exceptions) 03/18/13 CAR 9.892 145 C 0.445 0.133 0.300 - - - 87.80 *87.80%

Satisfactory

Phranaret Construction 16878Prev. Maint./Rehab./Impv't. along Nva. Vizcaya-Ifugao-Mt.

Province Bdry. Rd. (Add'l. Pvmt. width, Reblocking & Restoration of Roadslip) K0324+000-K0334+667

03/17/13 CAR 9.900 180 C 0.395 0.133 0.300 - - - 82.80 *82.80% Satisfactory

PHRANARET Construction 16878 Colocol Integrated CIS Rehabilitation & Extension Project 05/12/12 NIA 6.643 197 C 0.434 0.200 0.300 - - - 93.42 91.99% V. Satisfactory

Pibs Trading and Construction 14734Rehab./Reconst./Upgrading of Camague-Ceanuri-Tominobo Section-Sta.1527+950 - Sta.1529+342 w/

exception06/09/10 X 9.257 105 O 0.349 0.240 0.150 0.030 0.045 0.050 86.40 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page216

Page 217: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Pibs Trading and Construction 14734 Rehab./Impvt. of DPWH Bldg. Lanao del Norte 1st District Engineering Office and Employees Quarter 06/05/09 X 3.733 180 O 0.376 0.273 0.150 0.030 0.005 0.033 86.70 -

PING-ANN'S CONSTRUCTION AND TRADING 34188 Development of Camp Manuel T. Yan Eco-Tourism and

Tribal Park 3/7/15 TIEZA 10.000 120 O 0.311 0.234 0.150 0.030 0.058 0.050 83.37

Pins Construction 13630 Concrerting of Brgy. Road along Upper Dumalinao to Brgy. Kalingayan Road, Dumalinao (Phase IV) 8/13/2014 IX 6.450 155 C 0.284 0.200 0.300 78.40 80.80%

Unsatisfactory

Pins Construction 13630Conc. of Brgy. Rd. along Upper Dumalinao to

Brgy.Kalingayan Rd., Brgy. Upper Dumalinao & Brgy. Kalingayan, Dumalinao (Phase IV)

08/16/13 IX 6.450 155 O 0.305 0.278 0.150 0.030 0.028 0.033 82.40

Pins Construction 13630 Conc. of R.T. LIM Street & M. Roxas Ave. 11/21/12 IX 9.305 118 O 0.315 0.225 0.000 0.023 0.043 0.033 63.90 -

Pins Construction 13630 Repair/Rehab./Impvt. of Lakewood-Bayog-Sindangan Nat'l Secondary Rd., K1717++340-K1717+860, Pob. Lakewood 08/16/12 IX 9.490 135 O 0.318 0.219 0.150 0.030 0.038 0.033 78.80 -

Pirra Construction Enterprises 10545 Const. of ACA Bldg. I & Dormitory Bldg. 04/16/09 DOST 24.290 180 O 0.356 0.271 0.150 0.030 0.044 0.050 90.10 -

PJ CONSTRUCTION AND SUPPLY 32305 UMAYAM RIVER IRRIGATION PROJECT 09/12/15 NIA 15.219 242 O 0.367 0.240 0.000 0.015 0.060 0.050 73.21 -

PJ San Pedro Const. And Supply 14994 Completion of Multi-Purpose Gymnasium 07/08/08 DOST 10.426 226 O 0.383 0.300 0.050 0.030 0.047 0.067 87.70 -

PJ San Pedro Construction andSupply 14994 Tiling Works and Exterior & Interior Painting of Central

Administration Building 07/08/09 U.P. 5.768 195 O 0.366 0.165 0.100 0.030 0.044 0.100 80.50 -

PLD CONSTRUCTION 1859 Repair/Imprv't of Mandaue City, Causeway Ouano Avenue) Chainage 2001 to Chainage 2727, Mandaue City, Cebu 8/8/2014 VII 44.282 210 OG 0.371 0.200 0.150 0.030 0.056 0.050 85.70

PLD CONSTRUCTION 1859Preventive Maintenance Based on Pavement Management

System Highway Development Management-4 (HDM-4), National Secondary Road, J. Luna Avenue, C0000

8/9/2014 VII 18.780 50 C 0.450 0.133 0.300 88.30 88.30% Satisfactory

PLD Construction 1859Asset Preservation of Nat'l Rd., (Int. Sect.) Prev. Maint., Overton-Buru-un Bdry. Rd., Km.1532+(-831)-Km.1532+(-

420)-Km.1532+124.5008/17/13 X 23.342 60 C 0.408 0.133 0.300 - - - 84.10 82.60%

Satisfactory

PLD Construction 1859 Prev. Maint. (Int. Sect.) Overton-Buru-un Bdry. Rd., K1532+(-831)-K1532+(-420); K1532+(-420)- K1532+124.50 03/15/13 X 23.342 60 O 0.379 0.187 0.150 0.010 0.040 0.050 81.60 -

PLD Construction 1859 Opening/Conc. of Cebu-Toledo Wharf Road, Linao-Talisay-Minglanilla 08/20/08 VII 18.693 160 O 0.281 0.217 0.100 0.023 0.022 0.100 74.30 -

PLD Construction 1859 Const. of Main Building, Cebu State College of Science & Tecnology (CSCST) Bitoon Campus 03/13/09 VII 19.084 160 O 0.366 0.300 0.150 0.030 0.057 0.050 95.30 -

PLD Construction 1859 Const./Widening/Upgrading of Access Roads to Roro Port 03/24/12 VII 18.527 180 O 0.379 0.216 0.150 0.030 0.037 0.050 86.20 -

PLD Construction 1559 Const./Widening/Upgrading of Access Rds. to Roro Port 08/21/12 VII 18.527 180 C 0.444 0.133 0.300 - - - 87.70 86.80% Satisfactory

Plerm Construction & Development Corporation 33288

Construction and Maintenance of Bridges along National Roads - Replacement of Papandayan Bridge along Calapan

South Road8/12/2014 IV-B 10.948 200 OG 0.367 0.236 0.150 0.030 0.040 0.033 85.60

PM Pacia Construction 1913 Completion of Sch. Bldg. at Baclaran Elem. Sch. Central 08/08/13 NCR 3.447 120 C 0.391 0.133 0.300 - - - 82.40 83.80% Satisfactory

PM Pacia Construction 1913 Completion of Sch. Bldg. at Baclaran Elem. Sch. Central 03/21/13 NCR 3.366 120 O 0.391 0.211 0.150 0.030 0.029 0.033 84.40 -

Polymer-Vic Const. 6157 Asphalt Overlay of Bataan Technological Park Inc. Road 05/20/09 III 19.030 90 O 0.396 0.200 0.150 0.030 0.025 0.050 85.10 -

Polymer-Vic Construction 6157 Replacement/Rehab./Strengthening of Bantan Bridge along Jct. Layac-Balanga-Mariveles Port Rd. 08/02/13 III 4.906 70 C 0.450 0.133 0.300 - - - 88.30 *88.30%

Satisfactory

Polymer-vic Construction 6157 Restoration of Bataan Technological Park, Inc. Road (BTPI), Km.178+013.50-Km.180+550.50 03/21/12 III 24.951 73 C 0.069 0.133 0.300 - - - 50.20 71.68%

Poor

Pon Construction and Trading 33667 Impvt. of Pentor-Balsik River Control (Daang Bago Section) 02/18/10 III 4.728 120 O 0.367 0.220 0.150 0.020 0.038 0.050 84.50 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page217

Page 218: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Postema Construction & Development 15283

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Road along Noveleta-Rosario Diversion Road 6th LD K.27+489-

Km.30+500 (IS)03/22/12 IVA 13.306 128 C 0.461 0.133 0.300 - - - 89.40 88.56%

Satisfactory

PRAGMATIC DEVELOPMENT & CONSTRUCTION CORPORATION 4846 Construction/Rehabilitation of Flood Control Project in

Catmon Daan Bridge/River Brgy. Catmon Daan 10/21/2014 VII 9.832 154 O 0.275 0.300 0.150 0.030 0.045 0.033 83.30% 83.30% Satisfactory

PRAGMATIC DEVELOPMENT & CONSTRUCTION CORPORATION 4846

Preventive Maintenance based on Pavement Management System/Highway Development and Management-4 (HDM-

4), National Secondary Road, Salinas Drive, Chainage 0012 - Chainage 0569

10/20/2014 VII 16.376 150 C 0.445 0.147 0.300 - - - 89.20 89.20% Very Satisfactory

Pragmatic Development & Construction Corporation 4846 Repair/Rehab. of Cebu North Hagnaya Wharf Rd., Mandaue

Sect., Chainage 0751-Chainage 1032 03/20/13 VII 4.107 17 C 0.457 0.200 0.300 - - - 95.70 *95.70% V. Satisfactory

PRAGMATIC DEVELOPMENT AND CONSTRUCTION CORP.

Construction of the BCDA Remaining Works Inside Bonifacio Global, Package 2 09/24/15 BCDA 115.105 365 C 0.432 0.191 0.300 - - - 92.29 84.77%

Satisfactory

PRAGMATIC DEVELOPMENT AND CONSTRUCTION CORPORATION 4846 Construction of BCDA Remaining Infrastructure Works

inside Bonifacio Global City, package 2 02/24/15 BCDA 115.618 420 O 0.380 0.230 0.032 0.030 0.043 0.033 74.80 -

PRC Construction 16631 Colocol Integrated CIS Rehabilitation & Extension Project 05/12/12 NIA 14.310 254 C 0.393 0.200 0.300 - - - 89.31 89.79% V. Satisfactory

Precious Construction 32995 Desilting/Channel Improvement/Revetment at Waras River, Sta. Elena Section 8/10/2014 V 17.899 231 OG 0.320 0.300 0.150 0.024 0.028 0.050 87.20

Precious Construction 32995 Const. of Water Impounding at Anoling 08/08/13 IVA 28.180 365 C 0.345 0.200 0.300 - - - 84.50 85.28% Satisfactory

Precious Construction 32995 Improvement of Farm-to-Market Road, Quinfermin-Bugbuga-San Jose Road 02/26/09 I 9.630 133 O 0.315 0.300 0.150 0.020 0.025 0.050 86.00 -

Precious Construction 32995 Const. of Flood Control System along Palico-Balayan-Batangas Road, Brgy. Tuyon-Tuyon & Brgy. Luntal 03/23/12 IVA 17.149 90 O 0.303 0.300 0.150 0.030 0.048 0.033 86.40 -

Precious Construction 32095 Const. of Water Impounding at Anoling 08/08/12 IVA 26.814 300 O 0.351 0.240 0.150 0.022 0.045 0.050 85.80 -

PREMIUM MEGASTRUCTURES 36079 Road Upgrading (Gravel to Paved) of Cabungaan - Tabunok - Consuegra Road K1014+(-403)……... 8/8/2014 VIII 97.667 305 OG 0.376 0.240 0.150 0.022 0.045 0.033 86.60

Premium Megastructures Inc. 36079 Const. of Flood Control Structures Burauen-Mahagnao Rd., Km.798+365.50-Km.982+000 (Left Side) 08/17/13 VIII 4.752 90 C 0.500 0.133 0.300 - - - 93.30 *93.30%

V. Satisfactory

Premium Megastructures Inc. 36079 Const. of Dungca-an Flood Control Structure 08/08/13 VIII 4.650 90 C 0.484 0.133 0.300 - - - 91.70 *91.70% V. Satisfactory

Premium Megastructures Inc. 36079 Rehab./Resurfacing of Cabungaan-Tabunok-Consuegra Rd., K1017+797-K1019+862.30 w/ exceptions 08/12/13 VIII 4.758 90 O 0.387 0.225 0.150 0.012 0.050 0.050 87.40

PREMIUM MEGASTRUCTURES, INC. 36079 Construction/Rehabilitation of Flood Control Projects,

Baybay City Flood Control Structures 10/28/2014 VIII 12.964 160 C 0.433 0.133 0.300 - - - 86.60% 86.6% Satisfactory

Prime Mate Builders 32687 Const. of 2-Storey, 4-CL Balili E/S (Phase I) 05/20/09 CAR 4.163 268 O 0.348 0.275 0.150 0.030 0.029 0.050 88.20 -

PRIME PAVE CONSTRUCTION AND ASPHALT CORPORATION 36597

Preventive Maintenance Based on Pavement Management System/Highway Development and Management-4

(Intermittent Section) of Gapan-San Fernando-Olongapo Road, Km.0069+(-554) - Km.0069+(-437)

11/17/2014 III 1.576 12 C 0.472 0.133 0.300 - - - 90.50% 90.5% Very Satisfactory

Prismodial Const. Corp/Izumo Contractors Inc. (JV)

28345/27742

Contruction of Eight (8) Five Storey Residential Buildings with Land Development and Survey Works 06/24/14 NHA 253.300 360 O 0.329 0.246 0.150 0.030 0.051 0.050 85.60 -

PRISMODIAL CONSTRUCTION 28345 Construction/ Improvement of Tourism Facilities at Grand Apo Reef Nature Park 03/21/14 TIEZA 9.988 240 S 0.310 0.212 0.000 0.000 0.070 0.000 59.20

Prismodial Construction Corp. 28345 Construction of 3-Storey, 15-Classroom School Building pkg.1B 12/08/09 NHA 18.111 150 O 0.308 0.300 0.000 0.030 0.045 0.000 68.30 68.30%

Poor

Prismodial Construction Corp. 28345 Construction of 3-Storey, 15-Classroom School Building 09/03/09 NHA 18.107 150 O 0.360 0.276 0.000 0.030 0.055 0.000 63.60 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page218

Page 219: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

PRISMODIAL CONSTRUCTION CORPORATION 28345 Dipolog Airport Development Project 02/11/15 DOTC 49.420 479 C 0.462 0.200 0.165 - - - - 88.70%

SatisfactoryPrismodial Construction

Corporation 28345 Dipolog Airport Development Project 10/09/13 DOTC 46.483 300 O 0.349 0.300 0.150 0.020 0.044 0.050 91.30 -

Prismodial Construction Corporation 28345 Timberland Village 11/15/12 NHA 33.168 300 O 0.319 0.199 0.150 0.023 0.045 0.050 78.57 -

Prismodial Construction/ RCDG Construction Corporation (JV) JV-09-082 Rehab. of Manlipac-Mayaposi Section 09/01/10 VII 57.850 240 O 0.338 0.300 0.150 0.030 0.042 0.033 89.30 -

Proline Construction 33548 Dabubu River Irrigation Project 04/27/13 NIA 3.917 150 O 0.374 0.213 0.150 0.023 0.028 0.050 83.80 -

PTK GROUP , INC./IPM CONSTRUCTION & DEVELOPMENT CORPORATION‐JOINT 

VENTUREJV-13-656

Road Upgrading (Gravel to Paved) Aramaywan-Berong-Puerto Princesa Road, K0179+516 to K0181+905.50,

Quezon, Palawan2/23/2015 IV 37.532 224 C 0.419 0.200 0.300 - - - 91.90% 83.08%

Satisfactory

PTK Group Inc./IPM Construction & Development Corporation - Joint

VentureJV-13-656 Upgrading of Access Road from National Highway to

Panacan Port, Narra, Palawan 8/4/2014 IV-B 19.427 136 C 0.416 0.139 0.300 85.50 85.50% Satisfactory

PTK Group Inc./IPM Construction & Development Corporation - Joint

VentureJV-13-656 Road Upgrading (Gravel to Paved) Aramaywan - Berong -

Puerto Princesa Road) K0179+516 - K0181+905.50 8/5/2014 IV-B 35.044 179 OG 0.364 0.233 0.080 0.022 0.040 0.033 77.20

PULSAR CONSTRUCTION 24422 Road Upgrading (Gravel to Paved) along Cadcadir-Kabugao Road, KO602+420 to KO603+160 10/22/2014 II 14.943 180 C 0.456 0.168 0.300 - - - 92.40% 92.4%

Very Satisfactory

PULSAR CONSTRUCTION 24422 Preventive Maintenance along Manila North Road, KO590+(-955) to KO593+560 10/22/2014 II 38.352 165 C 0.455 0.133 0.300 - - - 88.80% 88.8%

Satisfactory

PULSAR CONSTRUCTION 24422

Network Development-Widening of National Roads-Arterial Roads: Widening of Cagayan-Apayao Road with

exceptions, Cagayan-Apayao Road with exceptions, Tuguegarao Cathedral to Buntun Bridge Section,

KO482+776 - KO486+276

10/22/2014 II 30.630 224 O 0.273 0.300 0.149 0.030 0.051 0.050 85.30% 85.3% Satisfactory

PULSAR CONSTRUCTION 24422 Restoration of Claveria Bridge Protection Work, KO611+680 along Manila North Road 10/23/2014 II 17.794 240 C 0.333 0.200 0.300 - - - 83.30% 83.3%

Satisfactory

Pulsar Construction 24422 Rehabilitation of Tucalan Bridge 8/6/2014 II 10.725 180 C 0.460 0.133 0.300 89.30 89.30% Very Satisfactory

Pulsar Construction 24422

Network Development-Widening of National Roads-Arterial Roads: Widening of Cagaan-Apayao Road with exceptions,

Cagayan-Apayao Road with exceptions, Tuguegarao Cathedral to Buntun Bridge Section, K0482+776 to

K0486+276

8/8/2014 II 30.630 224 OG 0.353 0.238 0.150 0.033 0.040 0.033 84.70

Pulsar Construction 24422 Const. of Gagabutan Bridge No.2 inc. PCCP along Cagayan-Apayao Rd. 08/03/13 II 23.938 240 C 0.416 0.133 0.300 - - - 84.90 *84.90%

Satisfactory

Pulsar Construction 24422 Const. of Gagabutan Bridge No.4 inc. PCCP along CAR 08/03/13 II 30.444 300 C 0.448 0.133 0.300 - - - 88.10 90.50% V. Satisfactory

Pulsar Construction 24422 Const. of Gagabutan Bridge No.1 inc. PCCP along CAR 08/03/13 II 12.620 180 C 0.442 0.133 0.300 - - - 87.50 86.60% Satisfactory

Pulsar Construction 24422 Const. of Gagabutan Bridge No. 4 inc PCCP 03/12/13 II 30.444 270 O 0.385 0.240 0.150 0.030 0.061 0.050 91.60 -Pulsar Construction 24422 Const. of Gagabutan Bridge No. 1 inc. PCCP 03/12/13 II 12.620 210 O 0.377 0.300 0.000 0.030 0.061 0.033 80.10 -

Pulsar Construction 24422 Cagayan River Flood Control Project (Enrile Section) 02/21/10 II 22.193 210 O 0.350 0.300 0.150 0.030 0.057 0.050 93.70 -

Pulsar Construction 24422 Construction of River Control Project 02/15/10 II 4.822 75 O 0.338 0.300 0.150 0.030 0.056 0.050 92.40 -

Pulsar Construction 24422 Repair/Rehab. of Revetment Flood Control at Enrile Sect. along Cagayan River 05/28/10 II 14.998 180 O 0.366 0.300 0.150 0.030 0.061 0.033 94.00 -

Pulsar Construction 24422 Cagayan River Flood Control 05/28/10 II 22.193 210 O 0.373 0.240 0.150 0.030 0.061 0.050 90.40 -Pulsar Construction 24422 Upgrading of Abbut-Conner-Kabugao Road 05/30/09 CAR 13.990 330 O 0.388 0.242 0.110 0.030 0.040 0.050 86.00 -Pulsar Construction 24422 Upgrading of Abbut-Corner-Kabungao Road 02/28/09 CAR 13.991 428 O 0.400 0.300 0.150 0.030 0.037 0.033 95.00 -Pulsar Construction 24422 Upgrading of Abbut-Conner-Kabugao Road 09/05/09 CAR 13.991 428 O 0.382 0.240 0.046 0.030 0.056 0.017 77.10 -

Pulsar Construction 24422 Road Upgrading (Gravel to Concrete) of Abbut-Conner-Kabugao Road, Mayogyog Section 02/21/10 CAR 17.997 377 O 0.357 0.240 0.150 0.030 0.050 0.033 86.00 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page219

Page 220: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Pulsar Construction 24422Rehab./Reconst./Upgrading of Damaged Paved National

Roads Cagayan-Apayao Road, Sampaguita-Solano Section,

05/18/09 II 19.289 120 O 0.379 0.240 0.150 0.030 0.056 0.050 90.50 -

Pulsar Construction 24422 Concrete Paving along JLLGR, San Pedro Section 02/23/09 II 19.291 240 O 0.328 0.300 0.150 0.023 0.040 0.050 89.10 -Pulsar Construction 24422 Addalam River Irrigation Project 04/27/09 05/01/09 NIA 7.952 227 O 0.330 0.259 0.150 0.023 0.038 0.033 83.30 -Pulsar Construction 24422 Const. of Sanchez Mira Flood Control Project 03/14/12 II 16.561 195 O 0.325 0.240 0.150 0.030 0.045 0.050 84.00 -

Pulsar Construction 24422Rd. Upgrading (Gravel to Concrete) along Conner-Kabugao

Rd., K0567+765.50-K0568+393.36 w/ exemption; K0568+393.36-K0569+208.36

11/28/12 CAR 17.537 175 O 0.326 0.300 0.000 0.020 0.042 0.033 72.10 -

Pulsar Construction 24422 Const. of Gagabutan Bridge No. 4 inc PCCP along CAR 11/25/12 II 30.444 270 O 0.381 0.256 0.150 0.030 0.059 0.050 92.60 -

Pulsar Construction 24422 Const. of Gagabutan Bridge No. 1 inc. PCCP along CAR 11/25/12 II 12.089 180 O 0.387 0.243 0.150 0.030 0.059 0.050 91.90 -

Pulsar Construction 24422 Road Upgrading (Gravel to Paved) IS, K0365+688-K0388+542 w/ exception 08/14/12 II 38.831 300 C 0.418 0.200 0.300 - - - 91.80 89.88%

V. SatisfactoryPulsar Construction / Deoj

Construction (JV) JV-11-684 Const. of Illuru Bridge No.3 inc. PCCP along Cagayan-Apayao Rd. 08/03/13 II 19.879 270 C 0.474 0.133 0.300 - - - 90.70 90.28% V.

SatisfactoryPulsar Construction / Deoj

Construction (JV) JV-11-684 Const. of Illuru No.3 inc. PCCP 03/12/13 II 19.879 270 O 0.377 0.300 0.000 0.030 0.061 0.033 80.10 -

Pulsar Construction / Deoj Construction Joint Venture JV-11-684 Const. of Illuru Bridge No. 3 inc PCCP 11/25/12 II 19.042 210 O 0.392 0.242 0.150 0.030 0.059 0.033 90.60 -

PUREGOLD CONSTRUCTION & DEVELOPMENT CORP. 34258 Construction of Flood Control at Sibulan River, Sta. Cruz,

Davao del Sur 8/6/2014 XI 4.774 75 C 0.431 0.133 0.300 86.40 86.40% Satisfactory

Puregold Construction & Development Corp. 34258 Const. of Classroom/Sch. Bldg. in Digos City NHS, Rizal

Ave. 08/17/13 XI 1.921 60 C 0.487 0.133 0.300 - - - 92.00 *92.00% V. Satisfactory

Puregold Construction & Development Corp. 34258 Const. of MPB at Dawis E/S 03/15/13 XI 1.464 60 C 0.476 0.133 0.300 - - - 90.90 *90.90%

V. SatisfactoryPuregold Construction &

Development Corp. 34258 Conc. of Rds. at Brgy. Luna - Balintawak St. 03/16/13 XI 2.411 27 C 0.426 0.133 0.300 - - - 85.90 *85.90% Satisfactory

PUREGOLD CONSTRUCTION AND DEVELOPMENT CORP. 34258 Construction of Multi-Purpose Building at Zone IV 10/24/2014 XI 1.844 60 C 0.442 0.133 0.300 - - - 87.50% 87.5%

Satisfactory

PYRAMID CONSOLIDATED BUILDERS & GEN. MERCHANDISE 15599 Const. of 1 Storey - 2 CL School Building, Sil-ipon E/S 10/21/2014 X 1.861 120 O 0.305 0.278 0.150 0.010 0.038 0.050 83.10% 83.1%

Satisfactory

Pyramid Consolidated Builders & Gen. Merchandise 15599 Reconst./Upgrading (Asphalt to Concrete) of Sayre

Highway (San Vicente-Kisolon Sect.) 08/06/13 X 5.911 44 C 0.443 0.133 0.300 - - - 87.60 *87.60% Satisfactory

Pyramid Consolidated Builders & Gen. Merchandise 15599

Rehab./Upgrading (Asphalt to Concrete) along S.H. Alae-Kisolon Rd., Maluko-Kisolon Rd. Sect., K1472+355.95-

K1472+895.95, Manolo Fortich08/06/13 X 10.909 127 C 0.406 0.133 0.300 - - - 83.90 85.04%

Satisfactory

Pyramid Consolidated Builders & Gen. Merchandise 15599 Const. of 2-Cl Modified Standard School Buildin Mahayag

NHS 03/12/09 IX 0.949 90 O 0.349 0.247 0.150 0.030 0.030 0.050 85.60 -

Pyramid Consolidated Builders & Gen. Merchandise 15599 Const. of Seawall, San Alonzo, Balingoan 03/03/10 X 0.447 119 O 0.329 0.240 0.150 0.030 0.047 0.050 84.60 -

Pyramid Consolidated Builders & General Merchandise 15599

Rehab./Upgrading (Asphalt to Concrete) along S.H. Alae-Kisolon Road, Maluka-Kisolon Rd. Sect., K1462+300-

K1472+895.95, Manolo Fortich-Sumilao03/21/13 X 10.909 127 O 0.283 0.300 0.150 0.030 0.045 0.050 85.80 -

Q.C.D. CONSTRUCTION & SUPPLY 37537Construction of Classroom in Areas Experiencing Acute Classroom Shortage, Macalong E/S, One (1) Classroom

School Building10/30/2014 II 1.120 90 C 0.478 0.133 0.300 - - - 91.10% 91.1%

Very Satisfactory

Q.C.D. CONSTRUCTION & SUPPLY 37537 Construction of Classroom, Bonfal West ES 10/29/2014 II 1.068 58 C 0.448 0.133 0.300 - - - 88.10% 88.1% Satisfactory

Qingjian Group Co., Ltd. Philippine Branch FC-10-005

Impv't. of Digos-Cotabato Rd., CP-RI-2.7A: Digos-Kidapawan Sect. under the Nat'l Rds. Impv't. & Mgt.

Program-Phase II (NRIMP-2)08/22/13 NRIM-PMO 623.610 731 O 0.378 0.300 0.132 0.030 0.051 0.033 92.40

Qingjian Group Co., Ltd. Philippine Branch FC-11-011

CP-R1-2.4: Impv't. of Bacolod-Kabankalan Rd., Bacolod-Bago Sect., under Nat'l Rds. Impv't. Mgt. Program, Phase II

(NRIMP-2), Bacolod-Bago City Sect.08/07/13 NRIM-PMO 340.600 540 O 0.394 0.300 0.051 0.030 0.051 0.050 87.60

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page220

Page 221: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

QM BUILDERS 30743 Road Upgrading (Concreting) of Tapal - (Carcar) Zaragosa -Olango - Aloguinsan Road, K0081+600 to K0083+020 10/23/2014 VII 39.547 166 C 0.391 0.138 0.300 - - - 82.90% 82.9%

Satisfactory

QM Builders 30743-B Widening of Cebu-Toledo Wharf Road Km.20+560 to Km. 21+120, Talisay City Section 8/4/2014 VII 45.768 224 OG 0.397 0.281 0.150 0.018 0.037 0.033 91.60

QM Builders 30743 Repair/Rehab. of Toledo-Pinamungajan-Aloguinsan Rd., K0054+407-K0055+825 (w/ exception) 08/07/13 VII 18.981 56 C 0.427 0.200 0.300 - - - 92.70 *92.70% V.

Satisfactory

QM Builders 30743

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. at Cebu-Toledo Wharf Rd., Talisay City Sect., K0022+000-

K0022+115, K0024+053-K0024+105, K0024+518-K0024+1060, K0025+470-K0025+672

08/05/13 VII 12.680 121 C 0.442 0.151 0.300 - - - 89.30 *89.30% V. Satisfactory

QM Builders 30743Rd. Upgrading (Gravel to Paved) along Dalaguete-

Mantalongon-Badian Rd., K0091+580-K0092+019 (Phase 1) & K0091+580-K0091+145 (Phase 2 & 3)

08/08/13 VII 59.050 351 O 0.396 0.288 0.150 0.030 0.056 0.033 95.30

QM Builders 30743 Rd. Upgrading (Conc.) of Toledo-Pinamungajan-Aloguinsan-Mantalongon Rd., K0081+160-K0083+094 08/07/13 VII 10.787 103 C 0.439 0.178 0.300 - - - 91.70 90.86% V.

Satisfactory

QM Builders 30743 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds., Cebu-Toledo Wharf Rd., Km.11+216-Km.12+000 08/06/13 VII 16.266 210 C 0.436 0.155 0.300 - - - 89.10 87.30%

Satisfactory

QM Builders 30743 Rd. Upgrading (Conc.) of Toledo-Pinamungajan-Aloguinsan-Mantalongon Rd. K0081+160-K0083+094 03/15/13 VII 10.787 74 O 0.335 0.300 0.150 0.030 0.055 0.033 90.30 -

QM Builders 30743 Rehab. of Cebu-Toledo Wharf Road 03/15/13 VII 52.337 238 O 0.378 0.000 0.200 0.050 0.073 0.125 82.60 -

QM Builders 30743 Road Rehab./Reconst./Upgrading along Sibonga-Dumanjug Road, Balagytiki Section 05/29/09 VII 14.037 75 O 0.392 0.300 0.150 0.030 0.050 0.050 97.20 -

QM Builders 30743Const. of Roadway Realignment /Widening of Cebu-

Balamban-Transcentral Road Km. 37+910-Km. 37+960, Sitio Kurus-Kurus

05/26/09 VII 9.524 120 O 0.400 - 0.200 0.050 0.071 0.250 97.10 -

QM Builders 30743 Road Upgrading (Gravel to Paved) along Sibonga-Dumanjug Road 05/29/09 VII 18.718 75 O 0.377 0.300 0.150 0.030 0.050 0.050 95.70 -

QM Builders 30743 Imprv't.(Conc.) of Access Rd., Bais Port Access Rd. 09/12/09 VII 19.168 200 O 0.252 0.300 0.150 0.030 0.047 0.050 82.90 -

QM Builders 30743 Road Widening of Toledo-Pinamungajan-Mantalongon Rd. Km.77+320 - Km.78+400, Aloguinsan Sect. 06/12/10 VII 16.338 120 O 0.400 0.300 0.150 0.030 0.037 0.033 95.00 -

QM Builders 30743 Road Widening of Toledo-Pinamungajan-Mantalongon Rd. Km.86+987.10 - Km.87+721.24 06/12/10 VII 13.554 120 O 0.348 0.297 0.150 0.030 0.035 0.033 89.30 -

QM Builders 30743 Rehab./Reconstruction of Cebu-Toledo Wharf Road 03/16/09 VII 21.217 150 O 0.372 0.300 0.000 0.022 0.027 0.050 77.10 -

QM Builders 30743 Repair/Rehab. of Brgy. Upper Tunghaan to Sitio Maria Respondo FMR 09/10/09 VII 14.410 120 O 0.341 0.240 0.150 0.030 0.040 0.050 85.10 -

QM Builders 30743 Widening/Rehab. of Cebu-Toledo Wharf Road 03/20/12 VII 37.959 180 C 0.492 0.193 0.300 - - - 98.50 95.44% V. Satisfactory

QM Builders 30743Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies/HDM-4 along Argao-Ronda Road, Km.81+797-

Km.82+61703/23/12 VII 18.174 239 C 0.470 0.133 0.300 - - - 90.30 90.42%

V. Satisfactory

QM Builders 30743 Road Upgrading/Conc. along Tapal (Carcar) Zaragosa-Olango-Aloguinsan Road, K0080-(340)-K0080+619 03/22/12 VII 5.645 116 C 0.426 0.133 0.300 - - - 85.90 87.88%

Satisfactory

QM Builders 30743 Rehab. of Cebu-Toledo Wharf Rd. 11/19/12 VII 52.337 210 O 0.398 0.291 0.150 0.030 0.035 0.033 93.70 -

QM Builders 30743 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd., Cebu-Toledo Wharf Rd., Km.11+216-Km.12+000 11/19/12 VII 16.266 210 O 0.371 0.247 0.150 0.020 0.040 0.033 86.10 -

QM Builders 30743Rehab./Reconst. of Damaged Paved Nat'l Rd.: Dumaguete

South Rd. K0072+283.70-K0073+724 (K0072+417-K0073+468) & K0092+228-K0092+385-K0092+785)

08/14/12 VII 24.210 320 C 0.440 0.133 0.300 - - - 87.30 88.02% Satisfactory

QM Builders 30743 Road Upgrading/Conc. along Toledo-Pinamungajan-Alonguinsan-Mantalongon Rd., K0078+72-K0078+912 08/20/12 VII 17.742 110 C 0.434 0.133 0.300 - - - 86.70 87.36%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page221

Page 222: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

QM Builders / Ven Ray Construction (JV) JV-11-488 Rehab. of Toledo-Pinamungahan-Mantalongon Rd. 03/15/13 VII 62.992 270 C 0.444 0.200 0.300 - - - 94.40 88.79%

Satisfactory

Quezon Victory General Contractor 6631 Road Upgrading (Gravel to Paved) MSR Jct.-Lopez-Hondagua Port Road 05/31/10 IVA 21.515 90 O 0.384 0.225 0.150 0.030 0.050 0.050 88.90 -

Quezon Victory General Contractor 6631 Rehab./Reconst. of Tiaong-San Antonio Road 05/25/09 IV-A 9.590 139 O 0.384 0.240 0.150 0.030 0.025 0.050 87.90 -

Quezon Victory General Contractor 6631 Concreting of Gumaca-Pitogo-Mulanay-San Narciso Road 05/26/09 IV-A 14.473 146 O 0.393 0.240 0.150 0.020 0.025 0.050 87.80 -

Quezon Victory General Contractor 6631 Const./Conc. of Candelaria-By-Pass Road inc. RROW at Brgy. Mangilag Sur 05/25/09 IV-A 17.658 99 O 0.358 0.240 0.150 0.030 0.025 0.050 85.30 -

QUEZON VICTORY LUMBER AND GENERAL CONTRACTOR (Formerly: Quezon Victory General Contractor)

6631Road Upgrading along MSR Jct. lopez-Cabanatuan Road,

K0237+005-K0257+835, K0238+009-K0238+899, Net Length=1.63kms., 230mm thick

11/29/2014 IV 37.271 280 C 0.444 0.133 0.300 - - - 87.70% 87.7% Satisfactory

Quezon Victory Lumber and General Contractor (Formerly:

Quezon Victory General Contractor)

6631 Rehab./Impvt. of MSR Diversion Rd., Km.125+(-241)-Km.125+680 w/ exception 08/08/11 IVA 16.928 170 O 0.309 0.300 0.150 0.030 0.040 0.050 87.90 -

Quirante Construction 32827Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. (Int. Sect.), Secondary Rd,. Civic Center Rd. 1, Chainage

0000-Chainage 010703/21/13 VII 1.992 12 C 0.467 0.133 0.300 - - - 90.00 *90.00%

V. Satisfactory

R C S Construction 12458 Repair/Rehab. of One (1) Classroom School Building @ M.P. Cuaderno Sr., ES, Brgy. Sibacan 08/28/09 III 0.490 53 O 0.384 0.240 0.150 0.020 0.037 0.033 86.40 -

R C S Construction 12458 Const. of MPB (Phase II), Brgy. Banawang 03/14/13 III 1.741 56 C 0.438 0.133 0.300 - - - 87.10 *87.10% Satisfactory

R N V Construction 12570 Repair/Maint. of Damaged Slope Protection alongh Pato-o East-West Rd., Km.7+390-Km.7+444 08/06/13 IVB 3.941 90 C 0.452 0.135 0.300 - - - 88.70 *88.70%

Satisfactory

R N V Construction 12570 Const. of Bachawan River Control along Tablas Circ. Rd. 08/05/13 IVB 1.616 85 C 0.373 0.200 0.300 - - - 87.30 86.58% Satisfactory

R N V Construction 12570 Const. of Line Canal along Tablas Circ. Rd., K039+550-K040+250 08/05/13 IVB 3.080 65 C 0.000 0.200 0.300 - - - 50.00 72.32%

Poor

R N V Construction 12570 Const./Imprv't of Brgy. Poblacion Line Canal-San Andres 02/22/10 IVB 1.466 100 O 0.274 0.300 0.150 0.030 0.048 0.033 83.50 -

R N V Construction 12570 Rehab./Impvt. of Romblon DEO 11/24/08 IV-B 4.693 146 O 0.355 0.240 0.100 0.030 0.032 0.100 85.70 -R N V Construction 12570 Const. of Line Canal, Km.39+550-K0040+250 11/29/12 IVB 3.080 60 O 0.364 0.240 0.150 0.023 0.045 0.050 87.20 -

R N V Construction 12570 Const. of Bachawan River Control along Tablas Circ. Rd. 11/29/12 IVB 1.616 80 O 0.346 0.240 0.150 0.030 0.045 0.050 86.10 -

R N V Construction/Dadoy Freight Service Construction and Supply

Joint VentureJV-11-268 Reblocking of Tablas Circ. Rd., K0057+429-K0068+240 w/

exceptions (IS) 11/29/12 IVB 23.638 180 C 0.396 0.200 0.300 - - - 89.60 90.50% V. Satisfactory

R N V Construction/Dadoy Freight Service Construction and Supply

Joint VentureJV-11-268 Reblocking of Tablas Circumferential Rd., Tablas Island 08/17/12 IVB 23.638 150 O 0.343 0.300 0.150 0.030 0.055 0.033 91.10 -

R R C CONSTRUCTION 24369Construction of Flood Control at Brgy. Bulihin with Drainage Outfall Connecting to National Road 5th

Legislative District11/6/2014 IV 22.484 171 C 0.438 0.133 0.300 - - - 87.10% 87.1%

Satisfactory

R R C Construction 24369Repair/Rehab along Santiago-Tuguegarao Road,

K0419+259.21 to K0421+000, K0425+695.50 to K0426+200 & K0426+200

8/8/2014 II 36.364 289 C 0.407 0.131 0.300 83.80 87.40% Satisfactory

R R C Construction 24369 Const./Rehab. of Mallig Flood Control Proj. (Rangayan Sect.) 08/08/13 II 8.798 180 C 0.470 0.133 0.300 - - - 90.30 *90.30% V.

Satisfactory

R R C Construction 24369Repair/Rehab. Along Santiago-Tuguegarao Rd.,

K0419+259.21-K0421+000, K0425+695.50-K0426+200 & K0426+200-K0427+000

08/05/13 II 34.673 209 O 0.357 0.300 0.150 0.030 0.055 0.033 92.50

R R C Construction 24369Const. of Babanuang Bridge along Santiago-Tuguegarao Rd. (inclusive of Approaches & Detour Bridge) @ Brgy.

Babanuang03/18/13 II 10.906 240 O 0.399 0.225 0.150 0.030 0.039 0.033 87.60 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page222

Page 223: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

R R C Construction 24369Repair/Rehab. of Santiago-Tuguegarao Rd., K0419+259.21-

K0421+000, K0425+695.50-K0426+200 & K0426+200-K0427+000

03/13/13 II 34.673 179 O 0.371 0.240 0.150 0.030 0.047 0.033 87.10 -

R R C Construction 24369

Repair/Maint. of Nat'l Rds. along Naguilian-San Mariano Rd. @ a)K0391+540-K0396+878 (Int. Sect.) Benito Soliven,

Isabela & b)K0398+120-K0403+518 (Int. Sect.) San Mariano,Benito Soliven & San Mariano

03/18/13 II 10.672 240 C 0.432 0.133 0.300 - - - 86.50 85.78% Satisfactory

R R C Construction 24369 Rehab./Strengthening of Paza Bridge, Manaring 03/13/13 II 4.726 89 O 0.337 0.126 0.150 0.030 0.040 0.033 71.60 -

R R C Construction 24369 Road Upgrading (Gravel to Paved) along Santiago-Tuguegarao Rd. (Old Route of STR), Aurora Sect. 03/17/12 II 8.689 180 C 0.404 0.133 0.300 - - - 83.70 88.38%

Satisfactory

R R C Construction 24369 Ilagan-Delfin, Albano-Mallig, Tumauini-Delfin Alabang Sect. 03/16/12 II 33.050 234 C 0.329 0.200 0.300 - - - 82.90 82.84% Satisfactory

R R C Construction 24369Restoration of Road Slip and Slope Protection along Naguilian-San Mariano Rd, Km.412+300-Km.412+720

(POPSTIRP)08/09/12 II/BOM 9.510 180 C 0.392 0.190 0.300 - - - 88.20 85.68%

Satisfactory

R R C Construction 24369 Conc. of Ilagan-Delfin Albano-Mallig Road 08/06/12 II 19.049 255 C 0.411 0.191 0.300 - - - 90.20 85.52% Satisfactory

R TWO S BUILDERS AND ENTERPRISE 36883 Construction of 1 Storey 2 CL 7.00mx18.00m School

Building at Don Faustino N. Dy E/S 10/25/2014 II 1.902 92 C 0.483 0.132 0.300 - - - 91.50% 91.5% Very Satisfactory

R Two S Builders and Enterprises 36883 Construction of Brgy. Road at Santo Niño 8/11/2014 II 3.396 82 OG 0.306 0.290 0.150 0.030 0.035 0.033 84.40

R V Laborte Builders Castanas Centro Communal Irrigation System 09/07/13 NIA 2.702 O 0.350 0.244 0.150 0.020 0.023 0.050 83.67 -

R. Allosa Construction & Trucking Service (Formerly: R. Allosa

Construction)12964

Rd. Upgrading (Gravel to Paved) of Calubian Jct. San Isidro-Tabango-Villaba-Palompon Rd., Km.1034+479-

Km.1034+708; & Km.1035+184-Km.1035+62403/13/13 VIII 13.286 210 O 0.328 0.237 0.150 0.030 0.045 0.033 82.30 -

R. C. Tagala Construction 11597 Rehab. of Tabla-Sta. Cruz Section, Tanjay, Dumaguete North Rd., Km.35.183-Km.36.183 08/08/11 VII 19.200 250 O 0.344 0.300 0.150 0.030 0.025 0.033 88.20 -

R. D Interior Jr. Const./Brostan Const. Dev't (JV) JV-08-002 Pagadian Airport Development Project 03/23/09 DOTC 174.361 360 O 0.377 0.300 0.150 0.030 0.056 0.050 96.30 -

R. D Policarpio Co., Inc. 4414 Tacloban Airport Development Project 10/08/09 DOTC 0.126 180 O 0.365 0.300 0.040 0.030 0.042 0.050 82.70 -

R. D. Interior Junior Construction 6483 Pinamalayan Airport Development Project 03/25/15 DOTC 62.125 266 C 0.480 0.200 0.300 - - - - 90.78% V. Satisfactory

R. D. Interior Junior Construction 6483 Pinamalayan Airport Development Project 12/04/14 DOTC 62.125 180 O 0.397 0.200 0.019 0.030 0.064 0.050 75.98 -

R. DE MESA CONSTRUCTION 18770 Const./ Concreting of Roads, Brgy. Camaman-an 10/25/2014 X 4.700 127 C 0.451 0.133 0.300 - - - 88.40% 88.4% Satisfactory

R. G. Dela Cruz Construction 35498 Improvement / Restoration of Embankment of Irrigation Facilities 08/03/12 NIA 3.834 75 C 0.400 0.160 0.300 - - - 86.00 86.00% Satisfactory

R. M. Vitug Construction 9227 San Fernando LTO Regional Office Building Project 05/15/14 DOTC 45.279 450 C 0.469 0.200 0.300 - - - - 97.40% Outstanding

R. M. Vitug Construction 9227 San Fernando LTO Regional Office Building Project 11/20/13 DOTC 24.864 300 O 0.366 0.300 0.150 0.030 0.070 0.050 96.60 -

R. R. ENCABO CONSTRUCTION, INC.

Infrastructure Development of the Jose B. Lingad Memorial Regional Hospital 02/18/15 DOH 224.815 540 O 0.362 0.295 0.150 0.030 0.065 0.050 95.20 -

R. R. ENCABO CONSTRUCTION, INC.

Infrastructure Development of the Jose B. Lingad Memorial Regional Hospital 10/15/14 DOH 224.815 540 O 0.382 0.254 0.150 0.030 0.050 0.050 91.60 -

R. R. ENCABO CONSTRUCTORS, INC. 14716 LTFRB Central Office Building and NCR LTFRB Regional

Office Building Project 01/06/15 DOTC 61.269 540 O 0.393 0.300 0.150 0.015 0.056 0.017 93.10 -

R. R. ENCABO CONSTRUCTORS, INC. Design and Build of MRH 11/21/14 DOH 149.784 520 O 0.388 0.250 0.141 0.030 0.056 0.016 88.10 -

R. R. Encabo Contractors, Inc./Espina-Perez-Espina and

Associates14-02373 Design-Built for Infra Proj. for CVMC Hospital

Modernization 10/24/14 DOH 281.638 540 O 0.392 0.278 0.150 0.030 0.064 0.033 94.70 -

R. R. RICAFORT CONSTRUCTION & SUPPLIES 14402 PIDP/Camiling River Irrigation System 05/31/14 NIA 13.882 160 O 0.379 0.240 0.134 0.015 0.042 0.033 84.34 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page223

Page 224: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

R. R. Ricafort Construction and Supplies 14402 PIDP/ Camiling River Irrigation System 03/31/15 NIA 13.882 558 C 0.381 0.200 0.300 - - - 88.11 85.85%

SatisfactoryR. SEMILLA CONSTRUCTION AND

MARKETING 9263 Construction of Nasipit River Protection 10/28/2014 XI 4.729 88 C 0.357 0.200 0.300 - - - 85.70% 85.7% Satisfactory

R. SEMILLA CONSTRUCTION AND MARKETING 9263 Construction of Nasipit River Protection, Tarragona, Davao

Oriental 8/13/2014 XI 4.729 88 C 0.409 0.133 0.300 84.20 84.20% Satisfactory

R. V. Construction 6110 Ports Horizontal Structures 10/07/13 DOTC 2.761 45 C 0.416 0.200 0.300 - - - 91.61 *91.61% V. Satisfactory

R.A Del Rosario Construction 4636 Const. of MPB, Brgy. San Agustin III 11/10/08 IV-A 4.778 90 O 0.322 0.231 0.100 0.015 0.029 0.100 79.70 -

R.A Del Rosario Construction 4636 Rehab./Reconst. (Concreting) of Indang-Alfonso via Luksuhin Rd. 11/13/08 IV-A 39.525 210 O 0.325 0.300 0.100 0.020 0.028 0.100 87.30 -

R.A. CONSTRUCTION & GENERAL MERCHANDISE 33060 Const. of DepEd Standard Type School Building on Gil

Montilla NHS, Main Sipalay City, Negros Occidental 8/9/2014 VI 3.338 85 C 0.420 0.200 0.300 92.00 86.05% Satisfactory

R.A. Construction & General Merchandise 33060 Const. of DepEd Standard Type Sch. Bldg. @ Gil Montilla

NHS Main, Sipalay City 08/09/13 VI 3.338 90 O 0.339 0.240 0.150 0.030 0.043 0.033 83.50

R.A. Construction & General Merchandise 33060 Rd. Upgrading of Isabela-Libas Negros Occidental Bdry.

Rd., a) K0086+250-K0087+000 08/10/13 VI 18.023 157 O 0.380 0.202 0.000 0.030 0.037 0.033 68.20

R.A. Construction & General Merchandise 33060 Rd. Upgrading of Isabela-Libas-Negros Occidental Bdry.

Rd., a)K0086+250-K0087+000 03/12/13 VI 18.023 157 O 0.322 0.300 0.150 0.015 0.030 0.050 86.70 -

R.A. Del Rosario Construction 4636 Concrete Reblocking of Salawag-Paliparan Rd., K0028+(-70)-K0036+056.50 (IS) 11/24/12 IVA 21.785 260 C 0.365 0.200 0.300 - - - 86.50 86.80%

Satisfactory

R.A. Del Rosario Construction 4636 Concrete Reblocking of Salawag-Paliparan Rd. K0028+(-070)-K0036+056.50 (IS) 08/15/12 IVA 21.785 260 O 0.355 0.235 0.150 0.030 0.050 0.050 87.00 -

R.A. Ignacio Construction 29977 Repair/Rehab./Impv't. of Cavite-Batangas Rd., K0046+672-K0047+250 w/ exception 08/13/13 IVA 9.388 40 C 0.472 0.133 0.300 - - - 90.50 *90.50% V.

Satisfactory

R.A. LACANLALE CONSTRUCTION 32661 Abatan River Eco-Tourism Development Project 04/29/14 TIEZA 4.290 160 S 0.360 0.289 0.150 0.015 0.018 0.050 88.20

R.A. Lacanlale Construction Abatan River Eco-Tourism Development Project 04/30/14 TIEZA 4.290 160 O 0.360 0.289 0.150 0.015 0.018 0.050 88.20 -

R.A. Moya Construction Corporation 10097 Const. of 3-Storey MPB, C.P. Garcia Ave., Brgy. U.P.

Campus, District 4 03/19/13 NCR 9.483 210 O 0.364 0.300 0.150 0.022 0.041 0.033 91.00 -

R.A. PAHATI CONST. & SUPPLY, INC. 35843

Rehabilitation/ Reconstruction/Upgrading of Damaged Paved National along San Juan-San Gabriel Road,

K0282+000 to K0282+98010/25/2014 I 15.283 150 C 0.350 0.200 0.300 - - - 85.00% 85%

Satisfactory

R.A. PAHATI CONST. & SUPPLY, INC. 35843Construction of Retaining Wall (Slope Protection) at

Nangka River (San Mateo Side), Barangay Sto. Niño, Sta. 3+150 to Sta. 3+650, San Mateo, Rizal

11/27/2014 IV 3.064 180 C 0.449 0.200 0.300 - - - 94.90% 94.54% Very Satisfactory

R.A. Pahati Const. & Supply, Inc. 35843 Rehab. & Impv't. of Sagbat Pililia Diversion Rd. (K0053+000-K0059+029) w/ exception 08/16/13 IVA 9.528 46 C 0.477 0.133 0.300 - - - 91.00 *91.00%

V. Satisfactory

R.A. Pahati Const. & Supply, Inc. 35843 CP-XXX(1-2) Rehab./Restoration along Nabua-Balatan Road K0489+690-K0 489+730 & K0484+600-K0484+640 08/01/13 V 2.730 120 C 0.453 0.133 0.300 - - - 88.60 *88.60%

Satisfactory

R.A. Pahati Const. & Supply, Inc. 35843 Widening/Impv't. of Sumulong Highway 08/15/13 IVA 17.140 210 C 0.437 0.133 0.300 - - - 87.00 87.12% Satisfactory

R.A. Pahati Const. & Supply, Inc. 35843 Widening/Impv't. of Sumulong Highway 03/22/13 IVA 17.140 180 O 0.346 0.240 0.150 0.030 0.056 0.050 87.20 -

R.A. Pahati Construction and Supply Inc. 35843 Rehabilitation and Development of Estero De Valencia 03/04/14 PRRC 23.255 433 C 0.411 0.200 0.300 - - - 91.10 89.80%

Very SatisfactoryR.A. Pahati Construction and

Supply Inc. 35843 Rehabilitation and Development of Estero De Valencia 01/24/14 PRRC 23.255 433 O 0.362 0.300 0.101 0.020 0.057 0.050 89.00 -

R.A. Pahati Construction and Supply, INC. 35843

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Roads along San Juan-San Gabriel Road @

K0282+000 - K0282+9808/4/2014 I 15.283 150 OG 0.313 0.291 0.150 0.022 0.031 0.050 85.70

R.A. Pahati Construction and Supply, INC. 35843 Widening of National Roads, Daang Maharlika Road,

KO85+000 - KO85+500 and KO089+094 - KO090+557.86 9/26/2014 Special 3 25.457 120 C 0.332 0.200 0.300 83.20 83.20% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page224

Page 225: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

R.A. Pahati Construction and Supply, INC. 35843

Construction of Retaining Wall (Slope Protection) at Nangka River (San Mateo Side), Brgy. Sto. Niño, Sta. 3+150

to Sta. 3+650, San Mateo Rizal8/4/2014 IV-A 43.276 180 OG 0.383 0.300 0.150 0.030 0.047 0.033 94.30

R.A. Pahati Gravel and Sand 22495 Rehab./Restoration of Roads & Bridges POPSTIRP RB/5, Mindoro West Coats, Kambingan Sect., Km. 346+350 08/10/11 IVB / BOM 8.827 180 O 0.352 0.240 0.150 0.030 0.045 0.033 85.00 -

R.A. Pahati Gravel and Sand 22495 Repair/Restoration of Albay West Coast Road, Dumalangan Sect. 03/18/12 V 6.596 135 C 0.434 0.200 0.300 - - - 93.40 86.80%

Satisfactory

R.A. Pahati Gravel and Sand 22495Rehab./Restoration of Road & Bridges along Various Road

Sect. in Aurora under POPSTIRP, Roads and Bridges Component, Cluster No. RB17

03/23/12 BOM / III 52.799 360 O 0.351 0.300 0.150 0.030 0.035 0.033 89.90 -

R.A. Pahati Gravel and Sand 22495 Rehab./Restoration of Roads & Bridges POPSTIRP RB-15, Mindoro Weast Coast, Kambingan Sect., Km.346+350 08/10/12 IVB 8.287 381 C 0.417 0.200 0.300 - - - 91.70 87.68%

Satisfactory

R.A. Pahati Gravel and Sand 22495Rehab./Restoration of Roads & Bridges POPSTIRP RB/5,

Mindoro West Coast, Barokan Sahing Sect., Km. 306+400-Km.306+900 w/ exception

08/10/12 IVB / BOM 5.709 180 C 0.328 0.200 0.300 - - - 82.80 85.08% Satisfactory

R.A.M Builders 10549 Rehab./Reconst. of MSR-Diversion Road 05/26/09 IV-A 27.964 114 O 0.352 0.240 0.150 0.030 0.025 0.050 84.70 -

R.A.M Builders 10549Const. (Road Opening) of Quezon Eco-Tourism Road

(LUCBATCR) inc. RROW, Phase II, Brgy. Bignay II, Maggalang Kiling

05/25/09 IV-A 17.689 114 O 0.343 0.240 0.150 0.030 0.025 0.050 83.80 -

R.A.M Builders 10549Const. of Quezon Eco-Tourism Road (LUC-BAT CR) incl.

RROW: Phase I, Guisguis-Talaan Sect., Conc. Of Guisguis Section

11/18/08 IV-A 17.780 206 O 0.337 0.300 0.100 0.030 0.037 0.100 90.40 -

R.A.M. BUILDERS 10549Construction of Lucena-Diversion Talao-Talao Port Road,

including RROW, Concreting of Silangang Mayao Road Section including Slope Protection

11/28/2014 IV 43.990 299 O 0.383 0.246 0.150 0.030 0.040 0.033 88.20% 88.2% Satisfactory

R.A.M. BUILDERS 10549

Asset Preservation of National Roads-Preventive Maintenance based on Pavement Management System-4

(HDM-4), (Intermittent Sections), National Arterial Roads 3. Gumaca-Pitogo-Mulanay-San Narciso Rd., K0202+200-

K0206+537

11/28/2014 IV 18.207 120 O 0.365 0.203 0.150 0.030 0.045 0.033 82.60% 82.6% Satisfactory

R.A.M. Builders 10549 Const. of Slope Protection incl. RROW along Quezon Eco-Tourism Rd. (LUC-BATCR) at Bantilan-Guis-Guis Sect. 03/16/13 IVA 29.775 294 C 0.434 0.133 0.300 - - - 86.70 87.18%

Satisfactory

R.A.M. Builders / BC Villaseñor Construction (JV) JV-11-206 Road Upgrading (Gravel to Concrete) Nat'l Secondary Rd.,

MSR JCT. Lopez-Buenavista Road, K0221+636-K0222+138 03/15/12 IVA 5.197 120 O 0.372 0.240 0.150 0.030 0.041 0.050 88.30 -

R.A.M. Builders/L.S. Abelar Construction JV JV-08-229 Impvt. of Quirino-Andaya Highway, Quezon Side, Brgy.

Silang II-Sto. Niño-San Diego 05/28/09 IV-A 33.765 90 O 0.333 0.240 0.150 0.030 0.035 0.050 83.80 -

R.B. CANDARE CONSTRUCTION 8819 LMC-2013-ANDANAN-WAWA-RIS 06/07/14 NIA 11.950 150 O 0.370 0.190 0.150 0.018 0.051 0.017 79.60 -

R.C Tagala Construction 11597Road Upgrading (gravel to paved) Conc. of MOOECR

(Calawag-Caguray Br. And Talaba Section) KO 219+141- KO 221+141 to KO 224+456 - KO 224+740

09/01/09 IVB 19.300 176 O 0.341 0.300 0.129 0.030 0.051 0.033 88.40 -

R.C Tagala Construction 11597 Road Upgrading (gravel to paved) Conc. of MOOECR KO 210+760 - KO 212+248 08/30/09 IVB 33.688 219 O 0.341 0.300 0.129 0.030 0.051 0.033 88.40 -

R.C Tagala Construction 11597Road Upgrading (gravel to paved) MWCR, Sta. Cruz-

Mamburao (Mulawin-San Vicente Section) KO 383+519-KO 385+002.5

08/31/09 IVB 19.260 186 O 0.357 0.298 0.150 0.022 0.023 0.033 88.30 -

R.C Tagala Construction 11597 Const./Completion of Macagua Bridge along Brookes Point-Rio Tuba Road 09/09/09 IVB 17.950 180 O 0.355 0.283 0.150 0.030 0.028 0.033 87.90 -

R.C Tagala Construction 11597 Rehab./Reconst./Upgrading of Dumaguete North Rd., Tapon Norte-Tandayag Rd. Sect. 09/12/09 VII 28.787 200 O 0.377 0.240 0.150 0.030 0.037 0.033 86.70 -

R.C Tagala Construction 11597 Rehab./Reconst./Upgrading of Dumaguete North Rd.,CAB-Sta. Cruz Sec. 09/12/09 VII 28.796 200 O 0.350 0.240 0.150 0.030 0.037 0.033 84.00 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page225

Page 226: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

R.C Tagala Construction 11597 Road Upgrading (Gravel to Paved) MWCR, Sta. Cruz-Mamburao (Mulawin-San Vicente Section) 05/30/09 IV-B 19.205 140 O 0.331 0.239 0.123 0.030 0.030 0.050 80.30 -

R.C Tagala Construction 11597 Const./Completion of Macagua Bridge aling Brooke's Point-Rio Tuba Road 06/02/09 IV-B 17.950 180 O 0.337 0.222 0.150 0.023 0.020 0.050 80.20 -

R.C Tagala Construction 11597 Repair/Rehab. of Dumaguete North Road, Km. 15.090-Km. 17.0775 05/26/09 VII 20.194 105 O 0.361 0.240 0.000 0.030 0.051 0.033 71.50 -

R.C. Tagala Const./ITP Const. Inc. (JV) JV-11-333

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd., Puerto Princesa South Rd. (Caramay-Aplian-Calasageun

Sect.) (K0164+024-K0168+587.25 w/ exceptions)11/20/12 IVB 93.914 347 O 0.357 0.272 0.106 0.030 0.056 0.033 85.40 -

R.C. Tagala Const./ITP Const. Inc. (JV) JV-11-333

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. Puerto Princesa South Rd. (Caramay-Apilan-Calasaguen

Sect.) K0+165+024-K0168+587.25 w/ exceptions)08/01/12 IVB 92.156 330 O 0.392 0.284 0.056 0.030 0.045 0.017 82.40 -

R.C. Tagala Construction 11597 Rehabilitation/Strengthening of Babuyan Bridge PPNR 8/8/2014 IV-B 12.016 255 C 0.397 0.133 0.300 83.00 84.74% Satisfactory

R.C. TAGALA CONSTRUCTION 11597 Upgrading (Gravel to Concrete) Concreting of Luka Road Leading to Tanjay Boardwalk. Tanjay City, Negros Oriental 8/14/2014 VII 14.464 175 C 0.426 0.148 0.300 87.40 86.74%

Satisfactory

R.C. Tagala Construction 11597 Rehab./Strengthening of Babuyan Bridge PPNR 08/15/13 IVB 11.720 225 O 0.376 0.248 0.127 0.030 0.045 0.033 85.90

R.C. Tagala Construction 11597 Upgrading (Gravel to Concrete) Conc. of Luka Rd. leading to Tanjay Boardwalk 08/21/13 VII 13.717 175 O 0.288 0.300 0.150 0.030 0.045 0.050 86.30

R.C. Tagala Construction 11597 Rehab. of Tabla-Sta. Cruz Sect., Tanjay, Dumaguete North Rd., Km.183-Km.36.183 08/13/12 VII 19.200 240 C 0.417 0.133 0.300 - - - 85.00 88.15%

Satisfactory

R.C. Tagala Construction / Bemkar Construction Joint Venture JV-11-337

Rehab./Reconst./Strengthening of Bridges along Nat'l Rds., Guisican Bridge along Daang Maharlika, Brgy.

Guisican10/12/13 V 25.049 419 C 0.483 0.133 0.300 - - - 91.60 91.60% V.

Satisfactory

R.C. Tagala Construction / Bemkar Construction Joint Venture JV-11-336

Rehab./Reconst./Strengthening of Bridges along Nat'l Rds., Anameam Bridge along Daang Maharlika, Brgy.

Anameam10/12/13 V 20.300 420 C 0.481 0.133 0.300 - - - 91.40 *91.40% V.

Satisfactory

R.D Interior Junior Construction 6483 Upgrading/Improvement of Magapit-Mission Road 09/09/09 II 96.491 330 O 0.360 0.300 0.150 0.030 0.042 0.050 93.20 -

R.D Interior Junior Construction 6483 Road Upgrading (Gravel to Paved) of Lala-Salvador-Tubod Road 06/03/10 X 19.138 121 O 0.363 0.240 0.150 0.030 0.045 0.033 86.10 -

R.D Interior Junior Construction 6483 Upgrading/Improvement of Magapit-Mission Road, Lal-lo and Sta. Teresita 05/19/09 II 96.491 330 O 0.385 0.240 0.150 0.030 0.056 0.050 91.10 -

R.D Interior Junior Construction 6483 Improvement of Access Road, Bagabag Airport 06/01/09 II 35.416 74 O 0.375 0.240 0.150 0.030 0.056 0.050 90.10 -

R.D Interior Junior Construction 6483 Conc. of SDCR, Marihatag-Hinatuan-Bislig Section, (Tagbina-Hinatuan Subsection) 11/27/08 XIII 282.908 345 O 0.331 0.300 0.100 0.030 0.050 0.100 91.10 -

R.D Interior Junior Construction 6483 Impvt./Conc. of Bislig-Manay Road (Boston-Bislig Sect. with Monkag & San Vicente Bridge) 11/27/08 XIII 289.168 570 O 0.342 0.300 0.100 0.030 0.055 0.100 92.70 -

R.D Interior Junior Construction 6483 Impvt./Conc. of Bislig-Manay Road (Boston-Bislig Section with Monkag & San Vicente Bridge) 06/06/09 XIII 289.168 570 O 0.374 0.300 0.106 0.030 0.056 0.050 91.60 -

R.D Interior Junior Construction 6483 Concreting of Surigao-Davao Coastal Road, Marihatag-Hinatuan Bislig Section (Tagbina-Hinatuan Subsection) 06/06/09 XIII 232.908 345 O 0.381 0.300 0.055 0.030 0.061 0.050 87.70 -

R.D Interior Junior Construction 6483 Impvt./Conc. of Bislig-Manay Road (Boston-Bislig Sect. with Monkag & San Vicente Bridge) 03/14/09 XIII 289.168 570 O 0.370 0.300 0.106 0.030 0.061 0.033 90.00 -

R.D Interior Junior Construction 6483 Conc. of Surigao-Davao Coastal Rd./ Hinatuan-Bislig-Lingig Subsection, w/ 2 Bridges & 1 RCBC 09/10/09 XIII 259.760 420 O 0.388 0.300 0.083 0.030 0.060 0.033 89.40 -

R.D Interior Junior Construction 6483 Conc. of Surigao-Davao Coastal Rd., Marihatag-Hinatuan-Bislig Sect.,(Tagbina-Hinatuan Subsection) 09/18/09 XIII 232.908 375 O 0.371 0.300 0.027 0.030 0.060 0.033 82.10 -

R.D Policarpio Inc. 4414Impvt./Widening of McArthur Highway (Manila North Road) Phase V Meycauayan Bulacan) to Mabalacat (Pampanga),

(City of San Fernando Section Contract Package II) 08/28/09 III 48.066 160 O 0.354 0.300 0.150 0.030 0.050 0.050 93.40 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page226

Page 227: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

R.D Policarpio Inc. 4414Impv./Widening/Conc. of MNR-Phase V-Meycuayan,

Bulacan to Mabalacat, Pampanga-Replacement of Del Pilar Bridge and Approaches

08/28/09 III 68.686 210 O 0.362 0.240 0.150 0.030 0.050 0.050 88.20 -

R.D Policarpio Inc. 4414Impvt. (Widening/Conc. of McArthur Highway (MNR)

Meycauayan (Bulacan) to Mabalacat (Pampanga) Ph-IV Package VII, Replacement of Tinajero Bridge & App.

11/11/08 III 45.805 180 O 0.373 0.240 0.100 0.030 0.061 0.100 90.40 -

R.D Policarpio Inc. 4414 CP 6: Impvt./Conc. of Surigao Sur-Davao Oriental Coastal Road (Manay-Boston) Baganga Section Phase I 11/25/08 XI 157.077 492 O 0.339 0.240 0.100 0.030 0.055 0.100 86.40 -

R.D Policarpio Inc. 4414 Impvt./Conc. of Surigao Sur-Davao Oriental Coastal Road (Manay-Boston) Baganga Section, Phase I 06/09/09 XI 157.077 492 O 0.371 0.254 0.150 0.030 0.056 0.033 89.40 -

R.D Policarpio Inc. 4414 Impvt./Conc. of Surigao Sur-Davao Oriental Coastal Road, (Manay-Boston) Baganga Section Phase I, CP No. 6 09/11/09 XI 157.076 522 O 0.365 0.300 0.150 0.030 0.056 0.033 93.40 -

R.D Sadsad Const. & Trading 19240 Const. of Multi-Purpose Building at Calulut 08/24/09 III 5.239 98 O 0.393 0.240 0.150 0.030 0.051 0.050 91.40 -

R.D Sadsad Const. & Trading 19240 Repair/Rehab., Gapan-San Fernando-Olongapo (GSO) 08/18/08 III 9.653 90 O 0.348 0.200 0.100 0.030 0.058 0.100 83.60 -

R.D. INTERIOR JUNIOR CONSTRUCTION 6483

Preventive Maintenance Based on Pavement System/Highway Development and Management-4 (HDM-4)

(Intermittent Section), Cordon Aurora Boundary Road (Isabela Boundary Jct. Dumabato), KO322+(-360) - KO322+000; KO322+200 - KO323+000; KO341+100 - KO342+000; KO343+680 - KO345+040; KO345+481 - KO346+000; KO346+511 - KO348+326; KO349+038 -

KO349+948; KO350+000 - KO531+1013

10/25/2014 II 68.071 150 C 0.466 0.133 0.300 - - - 89.90% 89.9% Very Satisfactory

R.D. INTERIOR JUNIOR CONSTRUCTION 6483 Const. of Pantar Bridge along Iligan City-Marawi City Road 10/29/2014 X 84.602 390 O 0.390 0.248 0.120 0.030 0.061 0.033 88.20% 88.2%

Satisfactory

R.D. INTERIOR JUNIOR CONSTRUCTION 6483

Repair/ Reconst./ Replacement/ Retrofitting of Existing Permanent Bridge, Pantar Bridge along Iligan City-Marawi

City National Road10/29/2014 X 24.394 225 O 0.391 0.232 0.150 0.030 0.042 0.033 87.80% 87.8%

Satisfactory

R.D. INTERIOR JUNIOR CONSTRUCTION 6483 Strengthening of Pantar Bridge along Iligan-Marawi City

Road 10/29/2014 X 14.156 204 O 0.395 0.240 0.115 0.030 0.042 0.033 85.50% 85.5% Satisfactory

R.D. Interior Junior Construction 6483 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. Tuguegarao Sect. 07/29/13 II 13.576 135 C 0.478 0.133 0.300 - - - 91.10 *91.10% V.

Satisfactory

R.D. Interior Junior Construction 6483Prev. Maint. along Santiago-Baluarte-Quirino Bdry. Rd.,

K0331+063-K0332+066, K0332+066-K0333+097, K0333+097-K0334+281

08/09/13 II 19.441 80 C 0.467 0.133 0.300 - - - 90.00 *90.00% V. Satisfactory

R.D. Interior Junior Construction 6483 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd., Lakambini-Sto. Domingo Sect., Cagayan-Apayao Rd. 08/04/13 II 25.694 210 C 0.445 0.133 0.300 - - - 87.80 *87.80%

Satisfactory

R.D. Interior Junior Construction 6483Rehab./Extension of San Pedro Bridge Approach "B" along

NRJ Villa Sur-San Pedro - Cabuuan-Ysmael-Disimungal Rd., K0367+614.50-K0367+410

08/12/13 II 12.330 255 C 0.441 0.133 0.300 - - - 87.40 *87.40% Satisfactory

R.D. Interior Junior Construction 6483 Washed Out Flood Control Proj. (Restoration), San Vicente 03/17/13 II 44.676 360 C 0.374 0.133 0.300 - - - 80.70 88.56% Satisfactory

R.D. Interior Junior Construction 6483 Const. of Naguiling Bridge along The Chico River 08/06/11 II 132.907 360 O 0.396 0.285 0.150 0.030 0.061 0.050 97.20 -

R.D. Interior Junior Construction 6483 Preventive Maint. of Nat'l Rd. (Asphalt Overlay=80mm Thk) Cagayan Valley Rd. K0499+041-K0493+463 w/ exception 08/04/11 II 18.391 90 O 0.356 0.300 0.150 0.030 0.061 0.050 94.70 -

R.D. Interior Junior Construction 6483 Rehab./Replacement of Lucban Bridge along Manila North Road 08/03/11 II 69.268 240 O 0.374 0.281 0.045 0.030 0.061 0.033 82.40 -

R.D. Interior Junior Construction 6483 Const. of Maguiling Bridge along the Chico River 03/15/12 II 132.907 360 O 0.388 0.300 0.076 0.030 0.060 0.050 90.40 -

R.D. Interior Junior Construction 6483 Rehab./Replacement of Lucban Bridge along Manila North Road 03/15/12 II 76.195 385 O 0.381 0.286 0.093 0.030 0.050 0.033 87.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page227

Page 228: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

R.D. Interior Junior Construction 6483 Const. of Slope Protection along Malabang-Dobleston-Tukuran Nat'l Road, Pitikul Sect. 03/21/12 X 37.867 324 C 0.428 0.133 0.300 - - - 86.10 87.78%

Satisfactory

R.D. Interior Junior Construction 6483 Drainage Bislig Surigao del Sur @ Km.1463+448-Km.1467+488 (Km.1463+448-Km.1467+375.5 IS) 11/25/12 XIII 27.548 247 C 0.414 0.200 0.300 - - - 91.40 89.18%

V. Satisfactory

R.D. Interior Junior Construction 6483Drainage Bislig Surigao del Sur @ Km.1463+448-Km.1467+488 (Km.1463+448-Km.1467+375.5 w/

intermittent)08/16/12 XIII 27.548 262 O 0.303 0.300 0.150 0.030 0.060 0.050 89.30 -

R.D. MANDANAS CONSTRUCTION 32114Construction/Rehabilitation of Flood Control in Laguna

2nd DEO/1st LD along Manila South Road at Salang Bago Bridge, Sta. Rosa City

11/28/2014 IV 13.599 210 C 0.367 0.200 0.300 - - - 86.70% 86.7% Satisfactory

R.D. Policarpio & Company, Inc. 4414Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds.

(Int. Sect.) Roman Expressway, Km.137+246.10-Km.152+120

03/23/13 III 39.768 376 O 0.380 0.300 0.116 0.030 0.060 0.033 91.90 -

R.D. SADSAD CONSTRUCTION AND TRADING 19240 Construction/Rehabilitation of Flood Control in Laguna

2nd DEO/1st LD along Macabling River 11/28/2014 IV 16.449 195 C 0.459 0.200 0.300 - - - 95.90% 95.9% Very Satisfactory

R.D. Sadsad Construction and Trading 19240 Repair/Rehab./Impv't. of Olongapo-Bugallon Rd. (Asphalt)

Overlay K0151+0-K0152+0 w/ exception 03/16/13 III 9.694 18 C 0.431 0.133 0.300 - - - 86.40 *86.40% Satisfactory

R.D. Sadsad Construction and Trading 19240 Prev. Maint. of Tanay Sampaloc Road (K0057+(-470)-

K0058+000) Intermittent Sect. 03/23/13 IVA 8.371 60 C 0.472 0.133 0.300 - - - 90.50 *90.50% V. Satisfactory

R.E. ORLINA CONSTRUCTION CORPORATION 17176 Rehabilitation/Drainage Improvement and Concrete

Reblocking along C.P. Garcia Avenue 11/27/2014 NCR 15.599 271 O 0.328 0.240 0.150 0.030 0.030 0.033 81.10% 81.1% Unsatisfactory

R.F. Varquez Construction 24307 Replacement of Mabini Bridge along Dinagat-Loreto Rd. 08/09/12 XIII 5.265 165 O 0.342 0.279 0.106 0.030 0.055 0.033 84.50 -

R.F. Varquez Construction 24307 Replacement of Allan Bridge along Dinagat-Loreto Rd. 08/09/12 XIII 5.267 165 O 0.340 0.240 0.150 0.023 0.035 0.033 82.10 -

R.F. VARQUEZ CONSTRUCTION 24302 Road Upgrading (Gravel to Paved) Jct. Gamut - San Miguel - Bayugan Road (K1321+415.88 to K1321+770.68) 10/25/2014 XIII 12.114 159 C 0.417 0.154 0.300 - - - 87.10% 87.1%

Satisfactory

R.F. VARQUEZ CONSTRUCTION 24302 Road Upgrading (Gravel to Paved) Jct. Gamut - San Miguel - Bayugan Road, K1321+415.88 - K1321+770.68 8/11/2014 XIII 12.114 159 OG 0.381 0.225 0.150 0.022 0.033 0.050 86.10

R.G Erillo Construction Incorporated (Formerly: R.G. Erillo

Construction & Supply)932

Rehab./Reconst./Upgrading of Bacolod Circumferential Road Km. 11+552 (South) to Km. 4+567 (North) w/

exceptions09/12/09 VI 14.466 250 O 0.298 0.300 0.150 0.030 0.040 0.050 86.80 -

R.G. Dela Cruz Construction 35498 Construction of Road, Brgy. Poblacion Sur 9/24/2014 Special 3 4.986 98 C 0.336 0.192 0.300 82.80 82.80% Satisfactory

R.G. Dela Cruz Construction 27624 Concrete Pavement 07/27/13 NIA 3.546 75 C 0.417 0.200 0.300 - - - 91.67 *91.67% V. Satisfactory

R.G. DIAZ BUILDERS & TRADING 23814Widening/Improvement of Camp Dau Road including

Drainage System along Camp Dau Road, K0088+(-212) to K0088+(-142)

11/19/2014 III 2.625 83 C 0.448 0.133 0.300 - - - 88.10% 88.1% Satisfactory

R.G. DIAZ BUILDERS & TRADING 23814 Construction/Completion of One (1) Storey Three (3) CL San Pedro Elem. School @ Brgy. San Pedro 2 11/19/2014 III 1.853 75 C 0.454 0.133 0.300 - - - 88.70% 88.7%

Satisfactory

R.G. Florentino Construction & Trading-San Andres, Romblon

Branch (Formerly: R.G. Florentino Construction)

18301 Const. of Parpagoha River Control along Tablas Circ. Rd. 11/29/12 IVB 4.574 90 O 0.350 0.240 0.150 0.030 0.050 0.050 87.00 -

R.G. Florentino Construction & Trading-Sand Andres Romblon

Branch (Formerly: R.G. Florentino Construction)

18301 Const. of Parpagoha River Control along Tablas Circ. Rd. 08/05/13 IVB 4.574 90 C 0.336 0.200 0.300 - - - 83.60 85.64% Satisfactory

R.G. Macaspac Construction and Engineering Consultant 23402 Rehab./Impv't. of Rds. in Panghulo, Brgy. Panghulo 03/15/13 NCR 1.927 150 C 0.446 0.133 0.300 - - - 87.90 83.46%

Satisfactory

R.J Ibarra Construction 23538 Construction of DPWH-Zambales 2nd District Engineering Office Building 05/23/09 III 18.901 180 O 0.368 0.239 0.150 0.030 0.029 0.050 86.60 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page228

Page 229: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

R.J Ibarra Construction 23538 Partial Completion of Gordon Heights National High School 09/01/09 III 1.958 90 O 0.320 0.240 0.150 0.030 0.048 0.033 82.10 -

R.J Ibarra Construction 23538 Const. of 2 CL Sch. Bldg. Secondary 11/12/08 III 2.062 90 O 0.260 0.266 0.100 0.030 0.023 0.100 77.90 -

R.J. IBARRA CONSTRUCTION 23538 Construction of Drainage Structure along San Marcelino - San Antonio Road, K0155+104 - K0156+512 11/27/2014 III 19.246 150 C 0.365 0.133 0.300 - - - 79.80% 79.8%

Unsatisfactory

R.J. Ibarra Construction 23538Emergency Works on Collapsed Slope Protection & Cross-Drainage Structure along Olongapo-Bugallon Rd., Mangan

Vaca08/05/13 III 4.647 60 C 0.414 0.133 0.300 - - - 84.70 *84.70%

Satisfactory

R.J. Ibarra Construction 23538 Impv't. of Pamatawan River, Brgy. Del Pilar Side 08/05/13 III 26.924 210 C 0.446 0.133 0.300 - - - 87.90 83.82% Satisfactory

R.J. Ibarra Construction 23538 Impv't. of Sacatihan River, Brgy. Sacatihan 08/05/13 III 11.853 120 C 0.408 0.133 0.300 - - - 84.10 82.30% Satisfactory

R.J. Ibarra Construction 23538 Impv't. of Sacatihan River, Brgy. Sacatihan 03/16/13 III 11.853 120 O 0.373 0.180 0.150 0.030 0.045 0.033 81.10 -

R.J. Ibarra Construction 23538 Impv't. of Pamatawan River, Brgy. Del Pilar Side, Phase II 03/15/13 III 26.924 210 O 0.339 0.200 0.150 0.030 0.042 0.050 81.10 -

R.J. Ibarra Construction 23338Rehab./Reconst./Upgrading of Damaged Paved Nat'l Road along Olongapo-Bugallon Road, Km.130+000-Km.130+020

& Km.130+677-Km.131+58703/23/12 III 10.187 120 C 0.386 0.138 0.300 - - - 82.40 82.46%

Satisfactory

R.J. Ibarra Construction 23338 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. along Olongapo-Bugallon Rd. 08/14/12 III 12.500 137 C 0.342 0.191 0.300 - - - 83.30 87.80%

Satisfactory

R.J. Ibarra Construction 23538 Prev. Maint. (Magsaysay Drive) Chainage 0000-Chainage 0611 03/16/13 III 8.027 15 C 0.472 0.133 0.300 - - - 90.50 *90.50%

V. Satisfactory

R.K.X. ODIAMAR CONSTRUCTION 16107Rehab./Reconst./Upgrading of Damaged Paved National Roads including Drainage along Daang Maharlika Road, Package 5: K0459+005-K0459+802, Baao, Camarines Sur

11/12/2014 V 1.286 165 C 0.487 0.133 0.300 - - - 92.00% 92% Very Satisfactory

R.K.X. Odiamar Construction 16107 Conc. of Shoulder along Daang Maharlika & Baao-Iriga City-Nabua Rd., K0472+300-K0472+546 & K0471+000-K0471+131 07/31/13 V 2.867 35 C 0.347 0.200 0.300 - - - 84.70 *84.70%

Satisfactory

R.K.X. Odiamar Construction 16107 Restoration of Slip/Embankment along Maguiring-Sibobo-Cagsao Road, Km.460+571 03/21/12 V 2.388 150 O 0.347 0.225 0.150 0.030 0.043 0.033 82.80 -

R.K.X. Odiamar Construction 16107 Const. of Villa Paz Bridge I Flood Control Structures along El Nido-Jct. New Ibajay Road, Km. 321+835 08/04/12 IVB 7.909 133 C 0.299 0.200 0.300 - - - 79.90 83.14%

Satisfactory

R.M Padillo Builders 31206 Const./Repair/Rehab of MPB (San Isidro Parish MPC), Poblacion 03/05/09 VIII 0.710 90 O 0.336 0.272 0.150 0.015 0.025 0.050 84.80 -

R.M Vitug Construction 9227 Upgrading of Lubao Diversion Road 05/18/09 III 28.663 100 O 0.315 0.240 0.150 0.030 0.040 0.050 82.50 -

R.M. Adalim Construction 20458 Construction of Canal Structures and Drainage System of Agos RIS 09/07/13 NIA 9.530 120 C 0.456 0.133 0.300 - - - 88.92 *88.92%

Satisfactory

R.M. Mondares Construction 23173 Supply & Installation of 6-person 3 stops-Elevator 08/18/14

PICE-Misamis Oriental-

CDO

3.872 240 O 0.397 0.300 0.080 0.030 0.070 0.050 92.70 -

R.M. Mondares Construction 23173 Supply & Installation of 6-person 3 stops-Elevator

PICE-Misamis Oriental-

CDO

3.872 240 C 0.500 0.200 0.000 - - - 70.00 85.89% Satisfactory

R.M. Vitug Construction 9227 Const./Rehab. of Flood Control Structure of Camachile River (Desilting and Slope Protection) Nagbunga 08/05/13 III 8.838 90 C 0.397 0.133 0.300 - - - 83.00 *83.00%

Satisfactory

R.M. VITUG CONSTRUCTION 9227 San Fernando LTO Regional Office Building Project 02/06/14 DOTC 45.279 450 O 0.387 0.300 0.150 0.030 0.070 0.050 98.74 -

R.M. Vitug Construction 9227 Impv't. of Camachile River, Brgy. Nagbunga 08/05/13 III 16.223 120 C 0.390 0.133 0.300 - - - 82.30 86.68% Satisfactory

R.M. Vitug Construction 9227 Impv't. of Camachile River, Brgy. Nagbunga 03/16/13 III 15.420 120 O 0.376 0.240 0.150 0.030 0.050 0.050 89.60 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page229

Page 230: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

R.M. Vitug Construction 9227Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds.

along Gapan-San Fernando-Olongapo Rd., K0125+080-K0125+962

11/21/12 III 18.472 167 C 0.433 0.133 0.300 - - - 86.60 90.86% V. Satisfactory

R.O Builders & Dev. Corp. 22393Rehab./Reconst./Upgrading of Damaged Paved National

Rd. along Daang Maharlika Namamparan-Diadi Poblacion Sect.

06/10/10 II 19.280 105 O 0.334 0.300 0.150 0.030 0.047 0.033 89.40 -

R.O Builders & Dev. Corp. 22393 Rehab./Reconst./Upgrading of Damaged Paved National Road along Maharlika (Nagsabaran-Balete Section) 06/01/09 II 18.904 90 O 0.358 0.300 0.150 0.030 0.051 0.033 92.20 -

R.O Builders & Dev. Corp. 22393 Conc. of Aritao-Dupax-Kasibu-Quirino Road, Mangayang Section 03/11/09 II 16.182 150 O 0.345 0.300 0.150 0.030 0.050 0.050 92.50 -

R.O Builders & Dev. Corp. 22393 Conc. of Aritao-Dupax-Kasibu-Quirino Road, Mangayang Section 11/28/08 II 16.182 150 O 0.351 0.279 0.100 0.020 0.033 0.067 85.00 -

R.O. Builders & Dev. Corp. 22393 Replacement of Inatub Bridge along Bambang-Kasibu-Quezon-Solano Rd. 08/13/13 II 5.409 91 C 0.452 0.133 0.300 - - - 88.50 *88.50%

Satisfactory

R.O. Builders & Dev. Corp. 22393Replacement of Temporary to Permanent Bridges Gen. from Bridge Mgt. System (BMS), Imugan Bridge along

Nueva Vizcaya-Pangasinan Rd.08/14/13 II 7.028 192 C 0.409 0.133 0.300 - - - 84.20 *84.20%

Satisfactory

R.R Encabo Constructors and Traders 14716 Alaminos Airport Dev't Project (Construction of Runway

Strip - Phase I) 4/1/2011 DOTC 96.342 210 O 0.363 0.300 0.150 0.030 0.062 0.017 92.20 -

R.R Seismundo Construction & Supply 10961 Conc. of Compostela Cateel Road-Osmeña Sect., Sitio

Nursery Sec. & Spur II-Pansansalan Sec. 03/16/09 XI 46.270 330 O 0.283 0.288 0.150 0.030 0.038 0.033 82.20 -

R.R. Encabo Constructor's Inc. Rehabilitation and Development of Estero de San Sebastian (Sta. 0+000 to Sta. 0+316) 02/27/14 PRRC 6.849 150 O 0.400 0.300 0.150 0.030 0.032 0.050 96.20 -

R.R. Encabo Constructors Incorporated / R.C. Tagala

Construction (Joint Venture)JV-12-366 Rehab./Reconst./Strengthening of Bridges along

Catanduanes Circ. Rd., Kanparel Bridge, (Km.0056+470) 07/30/13 V 31.520 211 O 0.342 0.272 0.131 0.030 0.040 0.033 84.80

R.R. Encabo Constructors Incorporated/R.C. Tagala

Construction (JV)JV-12-366 Rehabilitation/Reconstruciton/Strengthening of Bridges

along Catanduanes Circumferential Road, Kanparel Bridge 8/14/2014 V 32.126 241 C 0.365 0.200 0.000 56.50 73.48% Poor

R.R. Ricafort Const. and Supplies (Formerly: R.R. Ricafort

Construction)14402 Conc. of Polangui-Gebulwangan-Quezon-Trangue-Mabini

Rd. (Sta.762+140-Sta.765+420) w/ exceptions 03/21/13 VIII 72.749 370 C 0.435 0.136 0.300 - - - 87.10 88.78% Satisfactory

R.R. RICAFORT CONSTRUCTION AND SUPPLIES (Formerly: R.R.

Ricafort Construction)14402 Preventive Maintenance along La Paz - Victoria Road

(Lapaz Section), KO138+863 to KO139+000 8/5/2014 III 1.352 15 C 0.457 0.133 0.300 89.00 89.00% Satisfactory

R.R. RICAFORT CONSTRUCTION AND SUPPLIES (Formerly: R.R.

Ricafort Construction)14402 Completion/Concreting of Brgy. Bacsay - Maasin Road 8/6/2014 III 6.796 60 C 0.482 0.126 0.300 90.80 90.80%

Very Satisfactory

R.R. Ricafort Construction and Supplies (Formerly: R.R. Ricafort

Construction)14402

Const. of Reinforced Concrete Slope Protection along Concepcion-Capas Rd. (Concepcion Sect.), K0112+187-

K0112+524 w/ exception08/07/13 III 4.108 90 C 0.426 0.133 0.300 - - - 85.90 *85.90%

Satisfactory

R.R. Ricafort Construction and Supplies (Formerly: R.R. Ricafort

Construction)14402

Conc. of Rd. Cluster VIII at: a)Sinait-Sta. Maria Rd., Tarlac City; b)Brgy. Rd. Mangolago, Victoria; c)Maluid-San

Andres Rd. Victoria08/07/13 III 27.116 192 C 0.349 0.200 0.300 - - - 84.90 *84.90%

Satisfactory

R.R. Ricafort Construction and Supplies (Formerly: R.R. Ricafort

Construction)14402 Mogpog River Control along Marinduque Circ. Rd. (Banto-

Mogpog Sect.) 08/07/13 IVB 12.701 200 C 0.386 0.200 0.300 - - - 88.60 85.18% Satisfactory

R.R. Ricafort Construction and Supplies (Formerly: R.R. Ricafort

Construction)14402 Mogpog River Control along Marinduque Circ. Rd. (Banto-

Mogpog Sect.) 03/23/13 IVB 12.701 190 O 0.344 0.232 0.150 0.030 0.040 0.033 82.90 -

R.R. Ricafort Construction and Supplies (Formerly: R.R. Ricafort

Construction)14402 Const. of MPB, Brgy. Burgos 11/14/08 III 3.004 90 O 0.302 0.240 0.100 0.000 0.018 0.100 76.00 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page230

Page 231: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

R.R. Ricafort Construction and Supplies (Formerly: R.R. Ricafort

Construction)14402 Const. of Public Market 03/15/12 III 14.283 272 C 0.492 0.133 0.300 - - - 92.50 89.35%

V. Satisfactory

R.R. Ricafort Construction and Supplies (Formerly: R.R. Ricafort

Construction)14402 Conc. of Brgy. Road @ Brgy. San Agustin-Bantog Rd. 11/24/12 III 7.904 80 O 0.315 0.288 0.150 0.030 0.035 0.033 85.10 -

R.R. Ricafort Construction and Supplies (Formerly: R.R. Ricafort

Construction)14402 Const. of 2 Storey, 8-CL Sch. Bldg. w/ Common CR at

Eduardo Cojuangco Nat'l Vocational HS 08/09/12 III 6.904 120 C 0.392 0.200 0.300 - - - 89.20 87.16% Satisfactory

R.R. RICAFORT CONSTRUCTION AND SUPPLIES(Formerly: R.R.

Ricafort Construction)14402

Preventive Maintenance along Victoria-Pura Road KO151+000 to KO152+000 Modified to Preventive

Maintenance along Victoria-Pura Road KO151+000 to KO152+000 w/ exceptions

11/20/2014 III 8.475 30 C 0.492 0.133 0.300 - - - 92.50% 92.5% Very Satisfactory

R.R. RICAFORT CONSTRUCTION AND SUPPLIES(Formerly: R.R.

Ricafort Construction)14402 Construction of Road at Brgy. Patling, Sta. 0+000 to Sta.

0+477 11/20/2014 III 3.611 23 C 0.492 0.133 0.300 - - - 92.50% 92.5% Very Satisfactory

R.R. Seismundo Construction and Supply 10961 Impv't./Widening of Tagum-Panabo Circ Rd., Mankilam

Sect. 08/13/12 XI 17.611 167 C 0.443 0.136 0.300 - - - 87.90 88.56% Satisfactory

R.S Reyna Construction 9648 Repair of Brgy. Roads, Brgy. Balocawehay-Katipunan-Ulhay-Tambis 05/28/09 VIII 1.915 25 O 0.320 0.200 0.150 0.030 0.047 0.033 78.00 -

R.S. SEPIAN CONSTRUCTION AND TRUCKING 20519 Upgrading (Gravel to Paved) Balili-Suyo-Sagada Road

Leading to Sagada Caves, Rice Terraces and Water Falls 11/21/2014 CAR 92.188 297 O 0.312 0.281 0.150 0.030 0.055 0.050 87.80% 87.8% Satisfactory

R.S. SEPIAN CONSTRUCTION AND TRUCKING 20519

Road Upgrading (Gravel to Concrete) based on Gravel Road Strategies, Traffic Benchmark for Upgrading to

Paved Road Standard (HDM-4 Project Analysis) (Intermittent Sections) along Acop-Kapangan-Kibungan-

Bakun Road, K0334+690 - K0335+000, K0335+000 - K0335+124, K0335+205 - K0336+000

11/21/2014 CAR 44.535 209 O 0.334 0.240 0.150 0.030 0.055 0.050 85.90% 85.9% Satisfactory

R.S. SEPIAN CONSTRUCTION AND TRUCKING 20519 Construction / Improvement of Poblacion - Chumang -

Liwo Road Leading to O'phaw - Mechancha Waterfalls 11/25/2014 CAR 57.900 300 O 0.362 0.238 0.150 0.030 0.055 0.050 88.50% 88.5% Satisfactory

R.S. Sepian Construction and Trucking 20519 Rd. Upgrading (Gravel to Concrete), Abra-Ilocos Norte Rd.,

K0436+000-K0436+700 03/23/13 CAR 14.954 220 C 0.250 0.133 0.300 - - - 68.30 64.34% Poor

R.S. Sepian Construction and Trucking 20519 Repair/Restoration along Baguio-Bua-Itogon Rd.

K0260+480-K0260+530 11/20/12 CAR 17.825 210 C 0.455 0.200 0.300 - - - 95.50 82.12% Satisfactory

R.S. Sepian Construction and Trucking 20519 Rd. Opening/Const. of Missing Links of Nat'l Rd., Abra-

Ilocos Norte Rd., Km.424+000-Km.452+100 (I.S.) 08/14/12 CAR 46.543 683 C 0.376 0.175 0.300 - - - 85.10 83.18% Satisfactory

R.S. Sepian Construction and Trucking 20519 Repair/Restoration along Baguio-Bua-Itogon Rd.

K0260+480-K0260+530 07/30/12 CAR 17.825 180 O 0.324 0.217 0.115 0.010 0.033 0.033 73.20 -

R.T Morabe Construction 11377 Concreting of Laoang-Lapinig-Arteche Road Km. 965+515.00-Km.966+645.00 06/08/09 VIII 19.138 150 O 0.331 0.235 0.150 0.030 0.045 0.050 84.10 -

R.T Morabe Construction 13377 Const. of La Paz-Javier-Bito Rd., La Paz-Javier-Bito Rd. Sect. 05/31/10 VIII 14.167 120 O 0.377 0.300 0.104 0.030 0.042 0.017 87.00 -

R.T Morabe Construction 11377 Concreting of Tabango-Catmon- (La Fortuna) Manlawaan-Gimarco Road 06/02/09 VIII 9.353 336 O 0.343 0.300 0.150 0.030 0.037 0.050 91.00 -

R.T Morabe Construction 11377 Concreting of Tabango-Catmon (La Fortuna) Manlawaan-Gimarco Road Km 1039+540-Km 1040+000 03/12/09 VIII 9.353 180 O 0.341 0.026 0.150 0.030 0.037 0.033 61.70 -

R.T Morabe Construction 13377 Const. of La Paz-Javier-Bito Road, La Paz-Javier-Bito Rd. Section 08/24/10 VIII 14.167 120 O 0.473 0.133 0.300 - - - 90.60 88.44%

Satisfactory

R.T. Builders 33773 Drainage System at Abucay Daang Maharlika, Brgy. Abucay 08/22/13 VIII 4.009 107 C 0.459 0.133 0.300 - - - 89.20 86.20%

SatisfactoryR.T. Builders 33773 Rehab./Reconst. along Rizal Avenida Ext. Road 03/19/12 VIII 4.119 60 O 0.379 0.225 0.150 0.015 0.027 0.050 84.60 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page231

Page 232: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

R.T. Builders 33773 Rehab./Reconst. Along Rizal Ave. Extension Rd., Km.905+(-1067)-Km.905+(-907) 08/22/12 VIII 4.119 60 C 0.464 0.133 0.300 - - - 89.70 86.64%

Satisfactory

R.T. DIWA CONSTRUCTION 14263 Concreting of Provincial Road Brgy. Casingsingan-San Juan Section, Amulung West 10/23/2014 II 2.970 75 C 0.342 0.200 0.300 - - - 84.20% 84.2%

Satisfactory

R.T. MORABE CONSTRUCTION 11377 Rehab./Reconst. Along Jct Taft-Oras, San Policarpio-Arteche, KO 890+400-KO895+177 8/14/2014 VIII 22.547 155 C 0.458 0.200 0.000 65.80 65.80%

Poor

R.T. Morabe Construction 11377Repair/Rehab./Conc. of Jct. Taft-Oras-San Policarpio-

Arteche Nat'l Rd., Km.954.540-Km.956+020, Brgy. Carapdapan

08/19/13 VIII 28.950 357 C 0.447 0.186 0.300 - - - 93.30 87.42% Satisfactory

R.T. Morabe Construction 11377 Rehab./Reconst. along Taft-Oras-San-San Policarpio-Arteche Rd., K0890+400-K0895+177 08/19/13 VIII 22.547 155 O 0.361 0.300 0.000 0.030 0.055 0.017 76.30

R.T. Morabe Construction 11377 Repair/Rehab./Conc. Of Jct. Taft-Oras-San Policarpio-Arteche Nat'l Rd., Km.954+540-Km.956+020 08/19/12 VIII 28.950 327 O 0.294 0.300 0.150 0.030 0.028 0.033 83.50 -

R.T. Morabe Construction / J.A. Achacoso Enterprises & General

Services (JV)JV-11-292 Rehab./Reconst. Of Damaged Paved Natl Rd. along Palo-

Carigara Ormoc Rd., Km.992+000-Km.992+990 08/13/12 VIII 14.321 162 C 0.388 0.200 0.300 - - - 88.80 83.22% Satisfactory

R.T.Y CONSRUCTION 10341Construction/Rehabilitation of Drainage System along

Lucena Bdry.-tayabas-Lucban-Sampaloc Road, Camatian Flood Control

12/1/2014 IV 4.872 62 C 0.478 0.133 0.300 - - - 91.10% 91.1% Very Satisfactory

R.T.Y CONSRUCTION 10341Rehabilitation/Reconstruction/Upgrading of Mauban-

Tignoan Road, Mauban Section, K0159+901.5-K0160+440 and K0162+000-K0162+793.5

12/1/2014 IV 18.275 135 C 0.466 0.133 0.300 - - - 89.90% 89.9% Very Satisfactory

R.T.Y CONSRUCTION 10341Road Upgrading along Catanuan-Buenavista Road,

K0254+116-K0255+355, K0255+868-K0255+958, K0255+958, K0255+958-K0256+008, Net Length=1.59kms., 280mm thick

11/29/2014 IV 35.476 220 C 0.446 0.133 0.300 - - - 87.90% 87.9% Satisfactory

R.T.Y Construction 10341 Road Upgrading of Dr. Damian Reyes Memorial Road (Torrijos Side) 08/25/09 IVB 47.275 210 O 0.344 0.250 0.150 0.030 0.051 0.050 87.50 -

R.T.Y Construction 10341 Rehab./Reconst. of San Juan-Candelaria Jct.-Candelaria-Bolboc Road, inc. Bantilan Bridge 05/25/09 IV-A 19.195 114 O 0.394 0.240 0.150 0.030 0.025 0.050 88.90 -

R.T.Y Construction 10341 Construction of TESDA Training Center 05/18/09 IV-B 14.395 213 O 0.343 0.289 0.150 0.030 0.012 0.050 87.40 -

R.T.Y Construction 10341 Rehab./Conc. of Dr. Damian Reyes Road (Torrijos Side) 05/18/09 IV-B 48.247 254 O 0.351 0.259 0.150 0.030 0.023 0.050 86.30 -

R.T.Y Construction 10341 Construction of TESDA Training Center 03/11/09 IV-B 14.395 180 O 0.390 0.204 0.150 0.030 0.018 0.050 84.20 -

R.T.Y Construction 10341 Rehab./Conc. of Dr. Damian Reyes Road (Torrijos Side) 03/11/09 IV-B 48.245 240 O 0.362 0.179 0.150 0.030 0.025 0.050 79.60 -

R.T.Y. Construction 10341 Road Upgrading (Concrete Paving) along Talaba - Summit -Panaon Road, K0195+533 to K0197+045, Quezon Third 8/12/2014 IV-A 36.033 310 C 0.351 0.200 0.300 85.10 83.30%

Satisfactory

R.T.Y. Construction 10341Preventive Maintenance Daang Maharlika, K0163+291 to

K164+100; K0164+100 to K0164+1050; K0164+1050 to K0166+171

8/11/2014 IV-A 42.482 221 C 0.436 0.200 0.300 93.60 82.98% Satisfactory

R.T.Y. Construction 10341Repair/Improvement of Sabang Bridge Approaches along Tigwi ‐ 

Dampulan ‐ Lipata ‐ Yook ‐ Buenavista Road (K0096+612.5 ‐ K0096+700)

8/16/2014 IV-B 4.921 85 C 0.412 0.133 0.300 84.50 84.50% Satisfactory

R.T.Y. Construction 10341 Rehab./Reconst./Upgrading of Lucena-Tayabas-Mauban Port Rd. Jct. Km.128+282-Km.132+070 w/ exception 08/03/13 IVA 42.817 245 C 0.301 0.200 0.300 - - - 80.10 84.54%

Satisfactory

R.T.Y. Construction 10341 Rd. Upgrading (Concrete Paving) along Talaba-Summit-Panaon Rd., K0195+533-K0197+045 08/06/13 IVA 34.582 165 O 0.328 0.245 0.150 0.030 0.035 0.033 82.10

R.T.Y. Construction 10341

Assets Preservation of Nat'l Roads Gen. from Pvmt. Mgt. System/Highway Dev't. Mgt.-4 (HDM-4) Int. Sect.; A. Prev. Maint.; 1. Nat'l Arterial (Prev. Maint.); 1. Daang Maharlika;

a.K0163+291 - K0164+100; b.K0164+100-K0164+1050; c.K0164+1050-K0166+171

08/05/13 IVA 40.482 171 O 0.395 0.225 0.000 0.030 0.028 0.017 69.50

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page232

Page 233: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

R.T.Y. Construction 10341

Assets Preservation of Nat'l Rds. Int. Sect.; A. Prev. Maint.; 1. Nat'l Arterial (Prev. Maint.); 1. Daang Maharlika;

A.K0163+291-K0164+100; B.K0164+100-K0164+1050; C.K0164+1050-K0166+171

03/19/13 IVA 40.482 171 O 0.39 0.240 0.074 0.030 0.056 0.033 82.30 -

R.T.Y. Construction 10341Rehab./Reconst./Upgrading of MCR (Tawiran-Taytay-

Bonliw Sect.) Km.36+87 -Km.33+000 / Km.42+331-Km.42+518 / Km.48+936-Km.497+224.80, Sta. Cruz-Torrijos

03/23/13 IVB 23.634 205 C 0.427 0.133 0.300 - - - 86.00 86.96% Satisfactory

R.T.Y. Construction 10341 Road Upgrading (Gravel to Concrete) Abuyon-Buenavista Road K0250+000-K0250+(-768) 03/12/12 IVA 15.346 193 C 0.451 0.189 0.300 - - - 94.00 87.70%

Satisfactory

R.T.Y. Construction 10341 Road Upgrading (Gravel to Concrete) Lopez-Buenavista Road K0238+(510)-K0238+(922) 03/12/12 IVA 28.840 174 C 0.423 0.200 0.300 - - - 92.30 87.44%

Satisfactory

R.T.Y. Construction 10341 Rehab./Reconst. Of Lucena-Tayabas-Lucban Road inc. Ibia Bridge 03/17/12 IVA 24.105 235 C 0.421 0.189 0.300 - - - 91.00 87.16%

Satisfactory

R.T.Y. Construction 10341 Const. of Banahaw MPB 03/20/12 IVB 4.794 180 C 0.440 0.133 0.300 - - - 87.30 90.52% V. Satisfactory

R.T.Y. Construction 10341 Rehab./Reconst./Upgrading of MCR (Reblocking of Sta. Cruz Sect.) 03/20/12 IVB 25.276 170 C 0.458 0.133 0.300 - - - 89.10 88.26%

Satisfactory

R.T.Y. Construction 10341 Rehab./Reconst./Upgrading of MCR (Km.54+000-Km.58+201.50 w/ exceptions) 03/21/12 IVB 18.977 127 C 0.389 0.133 0.300 - - - 82.20 85.68%

Satisfactory

R.T.Y. Construction 10341 Road Upgrading (Gravel to Concrete) of Lopez-Buenavista Rd., KM.238+922-Km.240+380 08/02/12 IVA 27.506 210 C 0.462 0.133 0.300 - - - 89.50 91.54% V.

Satisfactory

R.T.Y. Construction 10341 Road Upgrading (Gravel to Concrete) of Catanauan-Buenavista Rd., Km. 0251+616-Km.252+486 08/02/12 IVA 17.590 180 C 0.430 0.133 0.300 - - - 86.30 90.98% V.

Satisfactory

R.T.Y. Construction 10341 Const./Conc. of Quezon Eco-Tourism Rd. (LUC-BATCR) inc. RROW Manggalang Sect. 07/31/12 IVA 45.582 240 C 0.456 0.133 0.300 - - - 88.90 89.02%

V. Satisfactory

R.T.Y. Construction 10341 Widening of Manila South New Diversion Rd., Km.154+700, Brgy. Silangan Malicboy 08/03/12 IVA 35.918 120 C 0.453 0.133 0.300 - - - 88.60 87.58%

Satisfactory

R.T.Y. Construction 10341 Rehab./Reconst./Upgrading of Lucena-Tayabas-Mauban Port Rd. Jct. Km.128+282-Km.132+070 w/ exception 07/30/12 IVA 39.824 230 O 0.346 0.239 0.150 0.030 0.060 0.050 87.50 -

R.T.Y. Construction 10341 Const. of Masin Bridge & Approaches along Candelaria By-Pass Rd. inc. RROW 07/31/12 IVA 43.174 285 C 0.438 0.133 0.300 - - - 87.10 86.74%

Satisfactory

R.T.Y. Construction 10341 Rehab./Impv't. of Dolores Sect. 08/13/12 IVB 15.232 180 C 0.431 0.181 0.300 - - - 91.20 88.32% Satisfactory

R.T.Y. Construction 10341 Repair/Rehab./Impv't. of Dr. Damian Reyes Memorial Rd. (Boac Side) Km.20+000-Km.20+810 w/ exception 03/23/13 IVB 9.610 90 C 0.370 0.200 0.300 - - - 87.00 *87.00%

Satisfactory

R.T.Y. Construction 10341 Repair/Rehab./Impv't. of MCR (S0001M0) (Butansapa-Lamesa Sect.) 03/23/13 IVB 9.899 90 C 0.425 0.133 0.300 - - - 85.80 *85.80%

SatisfactoryR.U Aquino Construction and

Development Corporation / RCDG Construction Corporation Joint

Venture

JV-08-130 Widening/Concreting of Mt. Data-Bontoc Road, Malitep Bridge, Balili to Amsolong Bridge Alab Section 05/23/09 CAR 114.942 450 O 0.380 0.240 0.150 0.030 0.060 0.033 89.30 -

R.U Aquino Construction and Development Corporation / RCDG

Construction Corporation Joint Venture

JV-08-131 Widening/Conc. of Mount Data-Bontoc Road Amsolong Alab Poblacion Sectiopn. Km. 385+350-Km. 391+457 08/28/09 CAR 99.305 450 O 0.369 0.240 0.087 0.023 0.047 0.017 78.30 -

R.U Aquino Construction and Development Corporation / RCDG

Construction Corporation Joint Venture

JV-08-157Conc. of Bontoc-Tabuk-Tuguegarao Road (Package BLT-16), Tinglayan Boundary Section I Tocucan to Betwagan

Sect., Km. 401+300-Km. 406+200 with exception08/29/09 CAR 128.685 425 O 0.351 0.240 0.004 0.023 0.056 0.017 69.10 -

R.V Construction 6110 Const. of MPB @ Brgy. Obrero 03/10/09 VIII 1.929 120 O 0.400 0.263 0.150 0.030 0.033 0.050 92.60 -

R.V Laborte Builders 20459 Const./Conc. of Candelaria-By-Pass Road, Brgy. Malabanban Sur, incl. RROW 02/17/10 IVA 17.680 240 O 0.355 0.300 0.150 0.030 0.042 0.050 92.70 -

R.V Laborte Builders 20459 Const./Conc. of Candelaria-By-Pass Road, Brgy. Masin Sur, incl. RROW 02/17/10 IVA 17.676 180 O 0.353 0.300 0.150 0.020 0.042 0.033 89.80 -

R.V Laborte Builders 20459 Completio of Olongtao MPB 11/11/08 IV-A 3.370 90 O 0.325 0.300 0.100 0.020 0.023 0.100 86.80 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page233

Page 234: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

R.V Rieta Trading & Gen. Construction 28671 Const. of 2 Storey MPB 08/26/08 IV-A 0.575 120 O 0.295 0.263 0.100 0.030 0.018 0.100 80.60 -

R.V. CONSTRUCTION 6110 Paving of Shoulders (Seal Widening) along Sta. Margarita Old Route 10/23/2014 VIII 9.558 160 C 0.384 0.173 0.300 - - - 85.70% 85.7%

Satisfactory

R.V. Laborte Builders 20459 Quipot Irrigation Project 02/14/15 NIA 31.282 356 C 0.350 0.200 0.300 - - - 85.00 *85.00% Satisfactory

R.V. Laborte Builders 20459 Completion of Bangao Bridge along Mulanay-San Fernando Rd. 08/07/13 IVA 15.230 118 C 0.321 0.200 0.300 - - - 82.10 *82.10%

Satisfactory

R.V. Laborte Builders 20459 Const. of Lucena Diversion Rd. Talao-Talao Port Rd. inc.RROW, Mayao Crossing Sect. 08/03/13 IVA 40.807 160 O 0.282 0.300 0.150 0.030 0.028 0.033 82.30

R.V. Laborte Builders 20459 Rehab./Reconst./Strengthening of Maligaya Bridge along Daang Maharlika (LZ) 03/19/13 IVA 47.574 360 C 0.450 0.133 0.300 - - - 88.30 90.88%

V. Satisfactory

R.V. Laborte Builders 20459 Rehab./Widening of Lucena Diversion Rd. inc. Const. of Lined Canal 03/16/13 IVA 44.346 258 C 0.452 0.133 0.300 - - - 88.50 87.00%

Satisfactory

R.V. Laborte Builders 20459 Completion of Canda Bridge along Eco-Tourism Rd. and Approaches inc. RROW, Sta.5+266-Sta.6+899 03/14/12 IVA 29.841 220 C 0.452 0.200 0.300 - - - 95.20 90.82%

V. Satisfactory

R.V. Rieta Trading & Gen. Construction 28671 Repair/Rehab./Impv't. of Cavite-Batangas Rd., Silang Sect.,

K0052+535-K0053+763 w/ exceptions 08/13/13 IVA 9.385 40 C 0.459 0.133 0.300 - - - 89.20 *89.20% V. Satisfactory

R.Z. RONCAL CONST. AND TRADING/GVDPM CONST. CORP.

(JV)JV-13-559 West Circumferencial Road (Friendship Highway) leading

to DMIA (Angeles City Section) Angeles City, Pampanga 8/23/2014 III 101.677 360 OG 0.388 0.240 0.102 0.024 0.056 0.016 82.60

R.Z. Roncal Construction and Trading 22219 Rehab./Reconst./Replacement/Retrofitting of Existing

Permanent Bridge, Maharlika Road 9/26/2014 Special 3 44.093 160 C 0.450 0.133 0.300 88.30 88.30% Satisfactory

R.Z. Roncal Construction and Trading 22219

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd.s along Nueva Ecija-Aurora Rd., Cabanatuan City & Palayan City Km.122+215-Km.122+423 w/ exception (159.18 LM);

Km.125+106-Km.125+149.23; Km.125+149.23-Km.128+820 w/ exception (2,224.27 LM); Km.129+007-Km.130+000 w/

exception (711.46 LM)

08/10/13 III 21.560 140 C 0.439 0.133 0.300 - - - 87.20 *87.20% Satisfactory

R.Z. Roncal Construction and Trading / GVDPM Construction

Corp. Joint VentureJV-12-331

Prev. Maint. (Int. Sect.) along Nueva Ecija-Aurora Rd., Cabanatuan City Km.117+(-)799 - Km.119+175 w/ exception

L=2,925.17 LM08/09/13 III 39.926 80 C 0.403 0.133 0.300 - - - 83.60 *83.60%

Satisfactory

R.Z. Tigas Construction and Trading 34198 Repair/Rehab./Impv't. & Const. of Drainage Canal & Flood

Control, Tabacan, Pob. Rd., Rizal 03/13/13 III 1.447 120 C 0.426 0.133 0.300 - - - 85.90 *85.90% Satisfactory

RA Construction & General Merchandise 33060 Rehabilitation of Hacienda Mimi-Ilian Communal Irrigation

System 02/17/15 NIA 4.719 150 O 0.345 0.241 0.150 0.030 0.023 0.050 83.90 -

Rabbit Construction & Development Corporation 8545 Prev. Maint. Zamboanga City-Labuan-Limpapa Rd.,

Km.1950+940-Km.1981+000 08/05/13 IX 8.057 136 C 0.380 0.200 0.300 - - - 88.00 *88.00% Satisfactory

Rabbit Construction & Development Corporation 8545 Concreting of Zamboanga City-Labuan-Limpapa Road

(Upper Labuan Section) 05/25/09 IX 18.874 185 O 0.343 0.240 0.150 0.030 0.056 0.050 86.90 -

Rabbit Construction & Development Corporation 8545 Reconst. of Zamboanga City-Labuan-Limpapa Road 03/03/09 IX 46.600 365 O 0.346 0.243 0.150 0.030 0.060 0.050 87.90 -

Rabbit Construction & Development Corporation 8545 Conc. of Zamboanga City-Labuan-Limpapa Road (Upper

Labuan Section) 09/01/09 IX 18.874 185 O 0.366 0.300 0.150 0.030 0.060 0.033 93.90 -

Rabbit Construction & Development Corporation 8545 Reconst. of Zamboanga City-Labuan-Limpapa Road 11/18/08 IX 46.600 365 O 0.320 0.300 0.100 0.030 0.045 0.100 89.50 -

Rabbit Construction & Development Corporation 8545 Road Upgrading (Gravel to Concrete) at San Ramon Penal

Colony 03/20/12 IX 27.810 240 O 0.350 0.282 0.150 0.030 0.038 0.050 90.00 -

Rabbit Construction & Development Corporation 8545 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. @

Zamboanga City-Labuan-Limpapa Rd. 03/19/12 IX 37.109 270 O 0.340 0.300 0.150 0.030 0.038 0.033 89.10 -

Rabbit Construction & Development Corporation 8545 Rd. Upgrading (Gravel to Concrete) at San Ramon Penal

Colony 08/13/12 IX 27.810 240 C 0.462 0.133 0.300 - - - 89.50 89.80% V. Satisfactory

Rabbit Construction & Development Corporation 8545 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. @

Zamboanga City-Labuan-Limpapa Rd. 08/13/12 IX 37.109 270 C 0.462 0.133 0.300 - - - 89.50 89.26% V. Satisfactory

Rachki Enterprises 17689 Construction of 2 Storey 4 Classroom School Building at Miranda Elementary School 8/9/2014 IV-A 4.719 120 C 0.484 0.200 0.300 98.40 88.11%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page234

Page 235: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Rachki Enterprises (Formerly: Geto Construction) 17689 Const. of Two (2) Storey, Four (4) Cl. Sch. Bldg. at Miranda

Elem. Sch. 08/02/13 IVA 4.719 150 O 0.333 0.268 0.150 0.030 0.023 0.033 83.70

Rachki Enterprises (Formerly: Geto Construction) 17689 Improvement of FMR in Sto. Niño, Pagrai, Brgy. Mayamot 05/18/09 IV-A 4.804 169 O 0.383 0.240 0.150 0.020 0.025 0.033 85.10 -

Radiance Traders & Builders 32891 Const. of Alcala-Cabituculan East FTMR 09/08/09 III 0.936 118 O 0.300 0.300 0.150 0.030 0.050 0.033 86.30 -

Radiance Traders & Builders 32891 Rehab. Of San Luis-Ma. Aurora-Castañeda Rd., San Luis-Ma. Aurora-Castañeda 11/27/12 III 10.459 150 O 0.234 0.300 0.150 0.030 0.058 0.050 82.20 -

Radiance Traders & Builders 32891 Const./Completion of MPB, Provincial Govt. of Aurora Coop Devt. Center So. Setan (Aurora Trading Center) 07/31/12 III 0.553 45 C 0.431 0.133 0.300 - - - 86.40 90.18%

V. Satisfactory

RAF GENERAL CONSTRUCTION 6699Preventive Maintenance of National Road, Abra - Kalinga

Road, K046+369 - K0427+730, Poblacion and Laang, Lagangilang, Abra

8/11/2014 CAR 19.070 76 C 0.444 0.133 0.300 87.70 87.70% Satisfactory

Raf General Construction 6699 Replacement of Bontoc-Cadre Bridge along Bontoc-Cadre Rd. 08/03/13 CAR 8.598 177 C 0.472 0.133 0.000 - - - 60.50 65.30%

Poor

Raf General Construction 6699 Replacement of Bontoc-Cadre Bridge along Bontoc-Cadre Rd. 11/23/12 CAR 8.271 120 O 0.299 0.300 0.000 0.020 0.033 0.033 68.50 -

RAF GENERAL CONSTRUCTION / JABEN GENERAL CONTRACTING

& ENG'G. SERVICES (JV)JV-13-263

Road Upgrading of Mt. Province-Cagayan via Tabuk-Enrile Road, KO396+812 - KO396+889, KO397+655 - KO397+704,

KO397+806 - KO397+818, KO398+571 - KO397+576, KO398+693 - KO398+744, KO 399+136 - KO399+225, KO410+646 - KO410+736, KO411+324 - KO411+430

11/22/2014 CAR 14.724 265 O 0.362 0.265 0.000 0.030 0.055 0.033 74.50% 74.5% Poor

Rain Construction Corporation (Formerly: Rain Construction) 15959 Rehab. & Impv't. of Kalayaan Ave. (Int. Sect.) K0005+819-

K0005+2948 (S033681LZS03367LZ) 08/09/13 NCR 17.524 75 C 0.404 0.133 0.300 - - - 83.70 *83.70% Satisfactory

Rain Construction Corporation (Formerly: Rain Construction) 15959

Asphalt Overlay of Muntinlupa-Insular Prison Rd. (K0029+287-K0029+417),(K0029+858-K0030+864),

(K0032+191-K0032+671 )08/14/13 NCR 11.075 40 C 0.392 0.133 0.300 - - - 82.50 *82.50%

Satisfactory

Ramarplus Incorporated (Formerly: Ramar Enterprises) 8092 Repair/Rehab. of Kinale River Flood Control 08/09/13 V 9.153 120 C 0.375 0.200 0.300 - - - 87.50 *87.50%

SatisfactoryRamarplus Incorporated (Formerly:

Ramar Enterprises) 8092 Construction of Dike at Left Quintal River 8/16/2014 V 46.065 248 OG 0.337 0.300 0.150 0.020 0.030 0.050 88.70

RAMISES CONSTRUCTION 17351Rehabilitation/Reconstruction/Replacement/Retrofitting of Doongan Bridge along Butuan City - Masao Port Road Jct.

Doongan Bridge10/29/2014 XIII 4.458 78 C 0.483 0.133 0.300 - - - 91.60% 91.6%

Very Satisfactory

Ramona Construction & Enterprises 14661 Const. of Sch. Bldg., Ozamis City NHS (Malaubang Annex) 08/16/13 X 2.258 84 C 0.458 0.133 0.300 - - - 89.10 *89.10% V.

Satisfactory

Ramona Construction & Enterprises 14661 Road Upgrading (Gravel to Paved) Int. Sect. Jct. Blancia-

Molave-Josefina Rd., Km.1682+460-K1683+000 03/21/13 IX 18.042 100 O 0.367 0.225 0.150 0.030 0.032 0.050 85.40 -

Ramsa Construction 25580 Repair/Rehab./Impvt. of MNR Km. 426+800-Km. 429+058 w/ exceptions 07/13/13 I 4.937 90 C 0.452 0.133 0.300 - - - 88.50 86.94%

Satisfactory

Ramsa Construction 25580 Repair/Rehab./Impv't. of MNR, Km.426+800-Km.429+058 w/ exceptions 03/20/13 I 4.938 90 O 0.396 0.225 0.150 0.015 0.040 0.033 85.90 -

Ramsa Construction 25580 Impvt. of DPWH Ilocos Sur 1st DEO Building 05/29/10 I 4.756 250 O 0.364 0.240 0.150 0.022 0.029 0.033 83.80 -

Rania Construction & Supplies 34064 Construction of Lateral "A" at Sta. 5+510.80 Sta 5+729.24 of Laris (Class A Rectangular Canal Lining) 02/27-03/03/12 NIA 3.604 60 O 0.334 0.300 0.150 0.030 0.047 0.050 91.10 -

RANIA Construction and Supplies Soriano Communal Irrigation System 01/27/15 NIA 9.507 120 O 0.250 0.300 0.150 0.030 0.060 0.050 84.00 -

RANIA Construction and Supplies Soriano Communal Irrigation System 01/27/15 NIA 9.650 120 O 0.260 0.300 0.150 0.030 0.060 0.050 85.00 -

Rapid Foremost Const. Co. 32618 Replacement/Rehab./Strengthening of Permanent Bridges: 2. Binahaan Bridge along Daang Maharlika 03/18/13 IVA 4.585 79 O 0.338 0.240 0.150 0.030 0.042 0.033 83.30 -

Rapid Foremost Const., Co. 32618Replacement/Rehab./Strengthening of Permanent Bridges Gen. from Bridge Mgt. System (BMS) 2. Binahaan Bridge

along Daang Maharlika08/05/13 IVA 4.585 170 C 0.456 0.133 0.300 - - - 88.90 85.54%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page235

Page 236: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

RAQI BUILDERS CONSTRUCTION & SUPPLY 27032

Construction/ Rehabilitation of Drainage/Protection Works along National Roads and Bridges, Flood Control along

Isulan Highway Junction Dukay-Bagumbayan Section-Sen. Ninoy Aquino Road

10/27/2014 XII 2.273 150 C 0.478 0.133 0.300 - - - 91.10% 91.1% Very Satisfactory

RAQI BUILDERS CONSTRUCTION AND SUPPLY 27082 Construction of Water Sanitation Facilities, Koronadal

NCHS 8/5/2014 XII 3.984 155 C 0.494 0.133 0.300 92.70 92.70% Very Satisfactory

RB Soriano Construction 22635 Thermal Moisture Protection (Re-roofing & Waterproofing) 08/26/10 U.P Manila 2.011 90 O 0.35 0.24 0.15 0.03 0.05 0.05 87.00 -

RC Tagala Construction 11597 Alcantara Port Development Project 10/22/14 DOTC 4.482 120 C 0.415 0.200 0.300 - - - 91.49 *91.49% V. Satisfactory

RC Tagala Construction 11597 Culasi Port Development Project 09/25/14 DOTC 21.002 210 O 0.333 0.300 0.135 0.020 0.035 0.017 83.91 -

RCDG CONSTRUCTION CORPORATION 5063 Road Rehabilitation (Asphalt Overlay with Pavement

Markings) at Barangay Sta. Catalina 10/21/2014 IX 3.887 103 C 0.448 0.127 0.300 - - - 87.50% 87.5% Satisfactory

RCDG Construction Corporation 5063 Road Rehabilitation 8/5/2014 IX 3.887 103 C 0.471 0.200 0.300 97.10 97.10% Outstanding

RCDG Construction Corporation / Badsbro Construction and General

Merchandise (Joint Venture)JV-12-029

Const./Impv't. of Lower Sibuguey Flood Protection along Lanao-Pagadian-Zamboanga City Rd., Kimus-Balucanan

Sect., Phase I, Km.0+000-Km.2+24003/15/13 IX 36.813 260 O 0.381 0.240 0.150 0.030 0.033 0.050 88.40 -

RCDG Construction Corporation / Badsbro Construction and General

Merchandise (JV)JV-12-029

Const./Imprv't. of Lower Sibuguey Flood Protection along Lanao-Pagadian-Zamboanga City Rd., Kimus-Balucanan

Sect., Phase I, Km.0+000-Km.2+24008/08/13 IX 37.564 275 C 0.312 0.200 0.300 - - - 81.20 85.61%

Satisfactory

RCDG Construction Corporation / Badsbro Construction and General

Merchandise (JV)JV-12-029

Const./Impvt. of Lower Sibuguey Flood Protection along Lanao-Pagadian-Zamboanga City Rd., Kimus-Balucanan

Sect., Phase 1, Km.0+000-Km.2+24011/26/12 IX 36.813 230 O 0.349 0.254 0.150 0.030 0.054 0.050 88.70 -

RCDS Construction & Supply, Inc. 32331 Restoration of Quionale "B" Control (Awang Sect.) 03/18/13 V 6.686 183 C 0.411 0.133 0.300 - - - 84.40 *84.40% Satisfactory

RCDS Construction & Supply, Inc. (Formerly: RCDS Construction and

Supply)32331 Preventive Maintenance along Danao-Pasacao Road 8/7/2014 V 9.381 50 C 0.432 0.133 0.300 86.50 86.50%

Satisfactory

RCDS Construction & Supply, Inc. (Formerly: RCDS Construction and

Supply)32331

Widening of DM Jct.-Legazpi-Sto. Domingo-Tabaco-Tiwi-Cam Sur Bdry. Road, Tabaco Section, K0553+660 -

K0554+6008/4/2014 V 20.695 189 OG 0.352 0.300 0.043 0.022 0.051 0.033 80.10

R'Cel Gen. Contractor & Gen. Merchandise 13385

Replacement/Rehab./Strengthening of Permanent Bridges Gen. from Bridge Mgt. System (BMS), Iringan Bridge along

Daang Maharlika08/05/13 IVA 5.412 120 C 0.479 0.133 0.300 - - - 91.20 *91.20% V.

Satisfactory

R'Cel Gen. Contractor & Gen. Merchandise 13385

Replacement/Rehab./Strengthening of Permanent Bridges Gen. from Bridge Mgt. System (BMS) 3. Gumihan Bridge

along Quirino Highway08/06/13 IVA 14.380 220 O 0.260 0.292 0.150 0.030 0.040 0.033 80.50

R'Cel Gen. Contractor & Gen. Merchandise 13385 Replacement/Rehab./Strengthening of Permanent Bridges;

3. Gumihan Bridge along Quirino H-way 03/19/13 IVA 14.380 80 O 0.278 0.245 0.146 0.030 0.065 0.033 79.70 -

R'Cel Gen. Contractor & Gen. Merchandise 13385 Widening of Bridges along Nat'l. Rds., Liliw Bridge along

San Pablo-Nagcarian-Liliw Rd., Km.100+420 03/15/13 IVA 12.652 215 C 0.445 0.133 0.000 - - - 57.80 75.44% Unsatisfactory

R'Cel Gen. Contractor & Gen. Merchandise 13385 Widening of Bridges along Nat'l. Rds., Oples Bridge along

San Pablo-Rizal-Nagcarlan-Liliw Rd., Km.99+620 03/15/13 IVA 12.641 215 C 0.448 0.133 0.000 - - - 58.10 74.90% Poor

R'Cel Gen. Contractor & Gen. Merchandise 13385 Widening of Daang Maharlika K0085+304.43-K0091+518

(Intermittent Sect.) 03/15/13 IVA 45.230 274 C 0.426 0.133 0.000 - - - 55.90 70.21% Poor

R'Cel Gen. Contractor & Gen. Merchandise 13385 Rehab./Reconst./Strengthening of Bridges along Nat'l.

Rd.s Inalakan Bridge along Daang Maharlika (L2) 03/19/13 IVA 7.642 180 C 0.475 0.133 0.300 - - - 90.80 87.02% Satisfactory

R'cel Gen. Contractor & Gen. Merchandise 13385 Widening of Bridges along Nat'l Rds., Liliw Bridge along

San Pablo-Rizal-Nagcarlan-Liliw Rd., Km.100+420 11/28/12 IVA 12.652 215 O 0.319 0.285 0.150 0.030 0.055 0.033 87.20 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page236

Page 237: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

R'cel Gen. Contractor & Gen. Merchandise 13385 Widening of Bridges along Nat'l Rds., Oples Bridge along

San Pablo-Rizal-Nagcarlan-Liliw Rd., Km.99+620 11/28/12 IVA 12.641 215 O 0.314 0.284 0.150 0.030 0.050 0.033 86.10 -

R'cel Gen. Contractor & Gen. Merchandise 13385 Widening of Daang Maharlika, K0085+304.43-K0091+518

(IS) 11/29/12 IVA 45.230 274 O 0.331 0.300 0.000 0.030 0.050 0.033 74.40 -

R'cel Gen. Contractor & Gen. Merchandise 13385 Widening of Daang Maharlika Highway K0085+304.43-

K0091+518 (IS) 08/08/12 IVA 45.230 250 O 0.332 0.300 0.111 0.030 0.045 0.033 85.10 -

R'CEL GEN.CONTRACTOR & GEN. MERCHANDISE 13385 Paving of Shoulders (Seal Widening) along Calamba-Sta.

Cruz-Famy Jct. Road, Lumban Section 11/26/2014 IV 5.297 70 C 0.459 0.200 0.300 - - - 95.90% 95.9% Very Satisfactory

RCPS Construction & General Trading 17792 Improvement of Minante Checkgate, Supply Canal

Protection 07/27/12 NIA 1.766 60 O 0.385 0.227 0.100 0.030 0.070 0.050 86.25 -

RDEN CONSTRUCTION & SUPPLY 33707Concreting of Roads, Poblacion to Buluan, Pob. 1 - Front

of Brgy. Hall and Concreting of Manuangan - Malu - oa Road, Pigcawayan, Cotabato

10/25/2014 XII 5.640 42 C 0.475 0.133 0.300 - - - 90.80% 90.8% Very Satisfactory

RDen Construction & Supply 33707Const. of FMR, Lower Baguer, Impv't. of FMR, Libungan,

Cotabato, K1705+176-K1706+340 end of Proj. K1705+176.50-K1706.50 (PCCP) (1.1635kms.)

08/13/13 XII 7.374 57 C 0.395 0.200 0.300 - - - 89.50 87.10% Satisfactory

RDen Construction & Supply 33707Const. of FMR, Lower Baguer, Impv't. of FMR, K1705+176-

K1706+340 end of proj. K1705+176.50-K1706.50 (PCCP) (1,163.5 kms.)

03/16/13 XII 7.374 57 O 0.340 0.235 0.150 0.030 0.050 0.050 85.50 -

RDen Construction & Supply / ACJ Construction Resources (JV) JV-11-291 Conc. of Rd. along Banisilan-Guiling-Alamada-Libungan

Rd., Tuasi-Barangiran Sect., Barangiran 03/16/13 XII 40.065 260 C 0.391 0.133 0.300 - - - 82.40 85.58% Satisfactory

Rden Construction & Supply / ACJ Construction Resources (JV) JV-11-295 Conc. of Rd. along Dualing-Baliki-Silik Rd., Dualing-Baliki

Sect. Km.1668+529-Km.1690+556 08/14/12 XII 44.728 319 O 0.353 0.259 0.150 0.030 0.051 0.050 89.30 -

Rden Construction & Supply / ACJ Construction Resources Joint

VentureJV-11-295 Conc. of Rd. along Dualing-Baliki-Silik Rd., Dualing Baliki

Sect. Km. 1668+529-Km 1690+556, Aleosan 11/22/12 XII 44.728 319 C 0.447 0.133 0.300 - - - 88.00 88.78% Satisfactory

RDEN CONSTRUCTION AND SUPPLY 33707 MALITUBOG IRRIGATION PROJECT MIP-LMC-004 Package

IV 06/06/13 NIA 35.599 455 C 0.358 0.199 0.300 - - - 85.65 *85.65% Satisfactory

RDG Construction and Supply 19388 Rehabilitation and Minor Improvement Works of Km.15 Kipalili-New Loon Road 06/10/15 Davao Del

Norte 12.862 155 C 0.454 0.087 0.300 - - - 84.11 84.16% Satisfactory

RDG Construction and Supply 19388 RMI of Km.15 Kipalili-New Loon road 05/06/15 Davao Del Norte 12.909 155 CD O 0.364 0.283 0.136 0.030 0.044 0.033 89.00 -

RDG Construction and Supply 19388 RMI of Km.15 Kipalili-New Loon road 04/21/15 Davao Del Norte 12.909 155 O 0.369 0.221 0.085 0.030 0.040 0.050 79.52 -

RDG Construction and Supply 19488 Sirawan (CARFA) SIP 06/01/13 NIA 13.131 120 O 0.389 0.240 0.150 0.030 0.051 0.050 91.04 -

Readycon Trading & Construction Corporation 15452

Asphalt Overlay of Batangas-Quezon Rd. a)San Ignacio, Rosario Sect. (K0126+249-K0127+000) b)Ibaan Sect.

(K0127+963-K0131+163)03/11/13 IVA 23.883 75 O 0.385 0.300 0.150 0.030 0.050 0.033 94.80 -

Redcar Trading & Construction 27368 Reconst./Upgrading of Muntinlupa Insular Prison Rd., (Int. Chainage 000+Chainage 0114) 08/14/13 NCR 1.288 25 C 0.407 0.133 0.300 - - - 84.00 *84.00%

SatisfactoryRegg's Builders / Mar-deb

Construction & Development (Joint Venture)

JV-12-035 Repair/Restoration of Rang-ay Flood Control, Sta.000+000-Sta.000+220 03/15/13 II 15.520 165 C 0.436 0.149 0.300 - - - 88.50 87.36%

Satisfactory

Regional Infrastructure Development Corp. / Ronwood

Construction & Supply (JV)JV-12-355 Repair/Rehab. & Const. of FMR, Anakan-Minmbunga-

Tinabalan-Mimbalagan Rd. 08/20/13 X 39.391 208 C 0.322 0.200 0.300 - - - 82.20 *82.20% Satisfactory

Regional Infrastructure Development Corporation 26373 Conc. of Tagbongabong Prov. Rd. Phase II, Tagbongabong

Remedios T. Romualdez (RTR) 08/05/13 XIII 9.451 103 C 0.435 0.126 0.300 - - - 86.10 *86.10% Satisfactory

Regional Infrastructure Development Corporation 26373 Rehab./Gravelling of NRJ Karaos-Lapag-Sumogbong Rd. 03/07/10 XIII 2.354 105 O 0.384 0.228 0.150 0.030 0.042 0.033 86.70 -

Regional Infrastructure Development Corporation 26373 Const. of Earth Canal at Talacogon-La Paz Road, along

Circumferential Road 03/17/09 XIII 3.733 120 O 0.333 - 0.200 0.050 0.040 0.250 87.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page237

Page 238: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Regional Infrastructure Development Corporation 26373 Concreting of Sta. Josefa Bdry.-Veruela Sect. along

National Secondary Rd. 09/14/09 XIII 4.764 145 O 0.376 0.225 0.139 0.030 0.065 0.033 86.80 -

Regional Infrastructure Development Corporation 26373 Conc. of NRJ-Calaitan-Tandag Rd. (Calaitan Sect.) 09/14/09 XIII 9.621 195 O 0.346 0.248 0.150 0.030 0.055 0.033 86.20 -

RELY CONSTRUCTION 10433Upgrading of Road Surfaces along Asuncion - San Isidro - Laak - Veruel Road, Sagayen Section, Km. 1481+380 - Km.

1483+500 with exception10/24/2014 XI 21.339 135 O 0.366 0.162 0.300 82.80% 82.8%

Satisfactory

Rely Construction & Supply 10433 Conc. of Juction Lingig-Trento Road 11/27/08 XIII 28.878 230 O 0.342 0.212 0.100 0.030 0.043 0.100 82.70 -

Rely Construction & Supply 10433 Impv't/Widening of Agusan-Davao Road, Daang Maharlika, Pob. Carmen and Pob. Panabo 03/13/09 XI 38.575 270 O 0.337 0.252 0.150 0.030 0.043 0.050 86.20 -

Rely Construction & Supply 10433 Conc. of Juction Lingig-Trento Road 03/14/09 XIII 28.878 230 O 0.329 0.300 0.150 0.030 0.037 0.050 89.60 -

RELY CONSTRUCTION AND SUPPLY 10433

Road Upgrading (Gravel to Paved) based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road Standard (HDM-4 Project Analysis) Intermittent

Section, Improvement/Widening of Daang Maharlika Road K1501+561 - K1501+400

8/15/2014 XI 33.622 155 OG 0.463 0.200 0.150 0.030 0.035 0.033 91.10

Rely Construction and Supply 10433 Impv't./Widening of Agusan-Davao Rd. (Daang Maharlika), Pob. Nabunturan-Mawab Sect. 08/14/13 XI 17.100 157 C 0.374 0.152 0.300 - - - 82.60 83.44%

Satisfactory

Rely Construction and Supply 10433 Rd. Upgrading along Asuncion-San Isidro-Laak-Veruela Rd. 03/17/13 XI 81.658 283 C 0.339 0.133 0.300 - - - 77.20 83.80%

Satisfactory

Rely Construction and Supply 10433 Rd. Upgrading along Asuncion-San Isidro-Laak Veruela Rd. 03/17/13 XI 91.565 344 O 0.147 0.240 0.150 0.030 0.050 0.033 65.00 -

Rely Construction and Supply 10433 Const./Widening of Libasan Bridge along Nabunturan-Mainit Park Rd. 08/17/11 XI 15.473 280 O 0.362 0.274 0.150 0.030 0.060 0.050 92.60 -

Rely Construction and Supply 10433 Compostela-Cateel Rd. Dispatching-Mahilaya Sect. 06/06/10 XI 18.042 180 O 0.373 0.225 0.150 0.030 0.045 0.033 85.60 -

Rely Construction and Supply 10433Rehab./Reconst./Upgrading of Damaged Paved National

Rd. Sect., Lipata (Surigao Del Norte) Davao City Highway through Daang Maharlika Rd. (Agusan to Davao Rd.)

06/02/10 XI 47.219 180 O 0.332 0.240 0.150 0.030 0.050 0.050 85.20 -

Rely Construction and Supply 10433 Impvt./Const. of Baganga-New Bataan Road Section, Baganga-Tigabauan-Binondo Section 09/12/09 XI 27.199 280 O 0.311 0.300 0.150 0.030 0.038 0.033 86.20 -

Rely Construction and Supply 10433Impvt./Rehab. Of Nat'l Secondary Road along San Isidro-

Laak-Veruela Road Km. 1477+920-Km.141484+540 w/ exception

03/26/12 XI 13.297 150 C 0.401 0.200 0.300 - - - 90.10 90.76% V. Satisfactory

Rely Construction and Supply 10433 Impvt./Rehab. Of Nat'l Secondary Rd., along San Isidro-Laak-Veruela Km.1484+540-Km.1491+050 w/ exception 03/26/12 XI 13.294 150 C 0.418 0.189 0.300 - - - 90.70 89.50%

V. Satisfactory

Rely Construction and Supply 10433 Impvt./Rehab. of Nat'l Secondary Rd. along San Isidro-Laak-Veruela Road Km.1471+705-Km.1477+920 w/ exception 03/26/12 XI 17.724 150 C 0.410 0.133 0.300 - - - 84.30 88.20%

Satisfactory

Rely Construction and Supply 10433 Rd. Upgrading along Asuncion-San Isidro-Laak-Veruela Rd. 11/24/12 XI 88.290 269 O 0.373 0.240 0.150 0.030 0.051 0.033 87.70 -

Rely Construction and Supply 10433 Impvt./Widening of Agusan-Davao Rd. (Daang Maharlika) Pob. Nabunturan-Mawa Sect. 11/27/12 XI 17.100 157 O 0.364 0.230 0.150 0.030 0.033 0.033 84.00 -

Rely Construction and Supply 10433 Road Upgrading at Cateel-Compostela Rd. (Davao Oriental Side) Km.1580+000-Km.1581+580 08/17/12 XI 38.241 203 O 0.297 0.240 0.150 0.030 0.056 0.050 82.30 -

Rely Construction and Supply 10433 Rehab./Impv't. along Daang Maharlika Rd. (w/ exception) 03/22/13 XI 9.510 63 C 0.330 0.200 0.300 - - - 83.00 *83.30% Satisfactory

Remigio General Construction 2298 MNR K0475+000-K0476+000 (Reblocking), K0473+219-K0477+305.50 (Conc. of Shoulder) 01/24/13 I 8.229 90 C 0.395 0.133 0.300 - - - 82.80 *82.80%

SatisfactoryRemigio General Construction / Werr Corp. (International) (JV) JV-11-345 Rehab. of Dakkel a Dannum Bridge along MNR 03/22/13 I 12.955 222 C 0.358 0.133 0.300 - - - 79.10 79.82%

UnsatisfactoryRemix Construction & Trading

Corp. 19378 Const. of MPB, Brgy. Old Capitol Site District 4 03/19/13 NCR 5.566 120 C 0.456 0.188 0.300 - - - 94.40 *94.40% V. Satisfactory

REMNANT BUILDERS 31889 CONST & COMP. OF PSHS CARC ACA BLDG I 09/11/13 DOST 28.857 270 C 0.438 0.200 0.154 - - - 79.20 *79.2% Unsatisfactory

Rend Enterprises & General Contractor 32382 Const. of MPB at Rd. 7, Brgy. Project 6 03/12/13 NCR 3.860 180 C 0.453 0.121 0.300 - - - 87.40 *87.40%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page238

Page 239: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Renol Engineering Services & Construction 33949 Desilting and Excavation Works of drainage Canal @

Libuganon RIS 06/01/13 NIA 20.059 100 C 0.420 0.500 - - - - 92.00 *92.00% V. Satisfactory

Revere Construction & Supply 17426

Widening of Daang Maharlika incl. Bridge & Drainage System, Sto. Tomas Sect., K0063+980-K0066+480,

K066+907-K0067+307 & K0671+980-K0069+398 (IS) (4 lanes)

08/09/12 IVA 46.550 180 O 0.348 0.238 0.150 0.030 0.054 0.033 85.30 -

Revere Construction and Supply 17426 Asphalt Overlay of Manila-Batangas Rd., Lipa City Sect. (K0079+091-K0080+249 w/ exception) 07/29/13 IVA 17.854 95 C 0.447 0.133 0.300 - - - 88.00 90.70% V.

Satisfactory

Revere Construction and Supply 17426 Asphalt Overlay of Rosario-San Juan Rd., Pinagsibaan-Puting Kahoy Sect., (K0106+174-K0107+184) 07/29/13 IVA 6.490 100 C 0.406 0.200 0.300 - - - 90.60 90.48% V.

Satisfactory

Revere Construction and Supply 17426Replacement/Rehab./Strengthening of Permanent Bridges Gen. from Bridge Mgt. System (BMS) Bignay Bridge along

Tanauan-Talisay-Tagaytay Rd.08/02/13 IVA 7.940 75 C 0.421 0.133 0.300 - - - 85.40 89.54% V.

Satisfactory

Revere Construction and Supply 17426 Asphalt Overlay of Manila-Batangas Rd., Lipa City Sect. (K0079+091-K0080+249 w/ exemption) 03/11/13 IVA 17.349 60 O 0.371 0.300 0.150 0.023 0.048 0.033 92.50 -

Revere Construction and Supply 17426 Replacement/Rehab./Strengthening of Permanent Bridges, Bignay Bridge along Talisay-Laurel-Agoncillo Rd. 03/14/13 IVA 7.940 75 O 0.400 0.300 0.150 0.015 0.025 0.033 92.30 -

Revere Construction and Supply 17426 Widening of Daang Maharlika Rd. K0070+(-)611-K0073+760.00, Net Length = 4,371.00 L.M. 03/15/13 IVA 150.858 240 C 0.470 0.133 0.300 - - - 90.30 91.32%

V. Satisfactory

Revere Construction and Supply 17426 Asphalt Overlay of Rosario-San Juan Rd., Pinagsibaan-Puting Kahoy Sect. (K0106+174-K0107+184) 03/11/13 IVA 6.335 90 O 0.350 0.300 0.150 0.023 0.048 0.033 90.40 -

Revere Construction and Supply 17426 Impvt. of Drainage and other Related Structures of Manila-Batangas City Road, Sto. Tomas-Malvar Sect. 06/10/10 IVA 11.574 90 O 0.374 0.225 0.150 0.015 0.050 0.033 84.70 -

Revere Construction and Supply 17426 Widening of Manila-Batangas Rd., Brgy. Maraouy, Lipa City Sect. (Phase I) 06/07/10 IVA 24.625 120 O 0.345 0.225 0.150 0.023 0.045 0.050 83.80 -

Revere Construction and Supply 17426 Rehab./Reconst./Upgrading of Damaged National Roads at San Juan-Laiya Road 05/28/09 IV-A 48.238 180 O 0.373 0.240 0.150 0.030 0.030 0.050 87.30 -

Revere Construction and Supply 17426 Rehab./Reconst./Upgrading of Damaged of Talisay-Laurel-Agoncillo Road (Laurel-Agoncillo Section) 05/22/09 IV-A 48.242 120 O 0.366 0.240 0.150 0.030 0.030 0.050 86.60 -

Revere Construction and Supply 17426 Widening of Batangas-Quezon Road at Rosario Section (2 lanes) 03/20/12 IVA 28.743 210 C 0.456 0.164 0.300 - - - 92.00 87.92%

Satisfactory

Revere Construction and Supply 17426Rehab./Reconst./Upgrading of Damaged Paved Nat'l Secondary Rd., Lake Taal-Tagaytay Rd. K0065+203-

K0069+443 = 1.89 km. (w/ exception)03/21/12 IVA 24.668 180 C 0.328 0.200 0.300 - - - 82.80 85.86%

Satisfactory

Revere Construction and Supply 17426

Widening of Daang Maharlika inc. Bridge & Drainage System, Sto. Tomas Sect., K0063+980-K0066+480,

K066+907-K0067+307 & K0671+980-K0069+398 (IS) (4 lanes)

11/21/12 IVA 48.265 240 C 0.351 0.200 0.300 - - - 85.10 85.22% Satisfactory

Revere Construction and Supply 17426 Asphalt Overlay of Lipa-Rosario Rd., Lipa City Sect. (K0081+(-705)-K0081+295) 03/11/13 IVA 6.864 45 C 0.453 0.133 0.300 - - - 88.60 *88.60%

Satisfactory

REY ROSE CONSTRUCTION & SUPPLY 22934

Rehabilitation/Reconstruction of Critical Section, Road Slip along Agusan-Bukidnon Road, K1259+898 -

K1259+94010/21/2014 XIII 2.924 88 C 0.422 0.163 0.300 - - - 88.50% 88.5%

Satisfactory

REY ROSE CONSTRUCTION & SUPPLY/ROIM BUILDERS &

CONSTRUCTION SUPPLY (JV)JV-13-262 Rehabilitation/Reconstruction/Upgrading of Damaged

Paved National Roads along NRJ-Bahbah-Talacogon Road 10/22/2014 XIII 40.035 297 O 0.339 0.234 0.150 0.030 0.042 0.050 84.50% 84.5% Satisfactory

REY ROSE CONSTRUCTION & SUPPLY/ROIM BUILDERS &

CONSTRUCTION SUPPLY -Joint Venture

SL1-SN-00811

Rehab./Reconst./Upgrading of Damaged Paved National Roads along NRJ - Bahbah - Talacogon Road, K1294+(-499) - K1295+000; K1301+000 - K1302+000; K1306+000 -

K1306+280

8/6/2014 XIII 40.035 233 OG 0.369 0.226 0.150 0.030 0.033 0.050 85.80

REYDAN BUILDERS 13059 Construction of Box Culvert and Slope Protection along Surallah - Lake Sebu - Maitum Road, K1745+300 10/21/2014 XII 4.871 117 C 0.356 0.133 0.300 - - - 78.90% 78.9%

Unsatisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page239

Page 240: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

REYDAN BUILDERS 13059 Widening of Makar - Kiamba Road, K1667+243 - K1668+236, General Santos City 8/16/2014 XII 19.288 117 C 0.453 0.192 0.300 94.50 94.50%

Very Satisfactory

REYDAN BUILDERS 13059 Const. of San Felipe Bridge Bank Protection along Midsayap - Marbel Road, KO1789+249, San Felipe Section 8/5/2014 XII 4.971 135 C 0.437 0.200 0.300 93.70 93.70%

Very Satisfactory

REYDAN BUILDERS 13059 Concreting/Widening of Marbel - Makar Road, South Cotabato, K1675+661.8 - K1677+761, Polomok Section 8/16/2014 XII 18.553 116 C 0.474 0.133 0.300 90.70 90.70%

Very Satisfactory

REYDAN BUILDERS 13059 Road to Address Critical Bottlenecks National Road Traffic Decongestion, Widening of Marbel-Midsayap Road 8/5/2014 XII 32.700 204 C 0.409 0.200 0.300 90.90 90.51%

Very Satisfactory

Reydan Builders 13059 Rds. to Address Critical Bottlenecks Nat'l Rd. Traffic Decongestion, Widening of Marbel-Midsayap Rd. 08/06/13 XII 32.700 150 O 0.367 0.236 0.150 0.015 0.056 0.033 85.70

Reydan Builders 13059 Rds. To address Critical Bottlenecks Nat'l. Rd. Traffic Decongestion, Widening of Marbel-Midsayap Rd. 03/20/12 XII 31.700 105 O 0.353 0.300 0.150 0.030 0.065 0.050 94.80 -

Reydan Builders 13059 Replacement of Box Culvert at New Cuyapo along Marbel-Midsayap Road 03/28/12 XII 3.890 161 C 0.494 0.133 0.300 - - - 92.70 94.02%

V. Satisfactory

Reydan Builders 13059 Retrofitting of Tamontaka Bridge along Cotabato-Alla-Marbel Road 03/19/12 XII 18.244 275 C 0.439 0.200 0.300 - - - 93.90 86.94%

Satisfactory

Reydan Builders 13059

Strengthening/Reconst./Replacement (Temp. to Perm.) of Bridge along Nat'l Rds. Bolok Bridge along Marbel-Makar

Rd., K1710+722.10 re-aligned to: Const. of Box Culvert along Marbel-Makar Rd. @ Jct. No. 6 w/ Lined Canal @

outlet to Marbel River, K1706+150.

11/24/12 XII 11.446 268 C 0.451 0.133 0.300 - - - 88.40 89.12% V. Satisfactory

Reydan Builders 13059

Strengthening/Reconst./Replacement (Temp. to Perm.) of Bridge along Nat'l Rds.: Bolok Bridge along Marbel-Makar

Rd., K1710+722.10 realigned to Const. of Box Culvert along Marbel-Makar Rd. at JCt. No.6 w/ line canal at outlet to

Mabel River, K1706+150

08/07/12 XII 10.682 210 O 0.378 0.240 0.150 0.030 0.047 0.050 89.50 -

RFN Construction & Development Corp. 8722 Const. of Livelihood, Production & Training Center 02/18/10 NHA 4.992 90 O 0.3966 0.2550 0.150 0.030 0.050 0.050 93.16 -

RFN Construction & Development Corp. 8722 Construction of One (1) unit Three-Storey School Building 09/18/09 NHA 18.108 150 O 0.375 0.300 0.150 0.030 0.058 0.050 96.33 -

RFN Construction & Development Corporation 2272 Construction of One (1) Unit 3-Storey, 15 Classroom

School Bldg. 05/07/13 NHA 17.527 250 C 0.470 0.200 0.300 - - - 97.03 88.73% Satisfactory

RFN Construction & Development Corporation 2272 Construction of One (1) Unit 3-Storey, 15 Classroom

School Bldg. 01/31/13 NHA 22.122 180 O 0.385 0.300 0.059 0.030 0.054 0.017 84.54 -

RFN Construction Dev't Corp./Versontal Builders JV Sr. San Roque Resettlement Project, Phase 1 09/21/12 NHA 33.785 345 O 0.388 0.254 0.083 0.030 0.030 0.050 83.44 -

RFN Construction Dev't. Corp./Versontal Builders JV Sr. San Roque Resettlement Project, Phase 1 11/23/12 NHA 33.785 345 O 0.325 0.300 0.150 0.030 0.053 0.050 90.77 -

RG & K Construction and General Merchandise 33021

Const. of Slope Protection along Butuan City-Cagayan de Oro City-Iligan City, Downstream of Iponan Bridge I and II,

Misamis Oriental Side, Barra08/19/13 X 17.118 240 O 0.366 0.208 0.150 0.020 0.041 0.050 83.50

RG & K Construction and General Merchandise 33021 Const. of Misamis Oriental-Bukidnon By-Pass Rd.

PHIVDEC-Alae Sect. 08/19/13 X 45.294 179 O 0.329 0.240 0.150 0.030 0.040 0.033 82.20

RG & K Construction and General Merchandise 33021

Const. of Slope Protection along Butuan City-Cagayan de Oro City-Iligan City, Downstream of Iponan Bridge I and II,

Misamis Oriental Side03/13/13 X 17.118 240 O 0.352 0.240 0.150 0.030 0.050 0.050 87.20 -

RG & K Construction and General Merchandise 33021 Assets Preservation of Nat'l Rds., Butuan City-Cagayan de

Oro City-Iligan City Rd. (Km.1488+000-Km.1489+000) 08/16/12 X 10.611 120 C 0.421 0.200 0.300 - - - 92.10 86.22% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page240

Page 241: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

RGP Builders 20680 Const. of Rds. from Marine Hatchery Proj. to Nat'l. Highway, Brgy. Punta 08/06/13 IVA 23.275 161 C 0.252 0.200 0.300 - - - 75.20 82.52%

Satisfactory

RGP Builders 20680 Const. of Rd. from Marine Hatchery Proj. to Nat'l. Highway, Brgy. Punta 03/17/13 IVA 23.275 157 O 0.358 0.251 0.150 0.030 0.035 0.050 87.40 -

Rhodamay Construction Supply 25989 Repair/Rehab./Impv't. of Puerto Princesa South Rd., K0217+000-K0221+000 (w/ exception) 03/19/13 IVB 4.998 120 C 0.082 0.200 0.000 - - - 28.20 *28.20%

Poor

Rhodwill Parts and Hardware 18871 Widening of Pres. Diosdado P. Macapagal Highway (Maputi Sect.) Km.1766+980-Km.1767+633.40 w/ exception 08/16/13 XI 10.290 69 C 0.441 0.133 0.300 - - - 87.40 86.44%

Satisfactory

Rhodwill Parts and Hardware 18871 Widening of Pres. Diosdado P. Macapagal Highway (Maputi Sect.) Km.1766+980-Km.1767+633.40 w/ exception 03/19/13 XI 10.291 69 O 0.343 0.240 0.150 0.030 0.045 0.050 85.80 -

Rhodwill Parts and Hardware 18871 San Jose River Control 03/03/10 XI 4.714 120 O 0.400 0.240 0.150 0.023 0.049 0.050 91.20 -

RHYES BUILDERS & SUPPLY 22115 Repair/Reconst. Of Roadslip along Catarman-Calbayog Road K0770+911 - K0771+150, Nabaloog, Catarman 10/21/2014 VIII 8.661 120 O 0.367 0.239 0.150 0.023 0.045 0.033 85.70% 85.7%

Satisfactory

RHYES BUILDERS & SUPPLY 22115 Concreting of Bangkerohan-Gulutan-Imelda-Hinatad-McKinley-Cabangahan Road 10/21/2014 VIII 9.117 71 O 0.341 0.240 0.150 0.030 0.040 0.050 85.10% 85.1%

Satisfactory

Rhyes Builders & Supply 22115 Conc. of Bangkerohan-Galutan-Imelda-Hinatad-Mckinley Rd. 03/21/13 VIII 46.462 180 C 0.391 0.133 0.300 - - - 82.40 82.22%

Satisfactory

Rhyes Builders & Supply 22115 Conc. of Bangkerohan-Galutan-Imelda-Hinatad-Mckinley Rd. 08/13/12 VIII 46.462 180 O 0.324 0.239 0.150 0.030 0.033 0.033 80.90 -

Rhyes Builders & Supply / ESD Cruz Construction & Supply (JV) JV-11-066

Conc. of Pangpang-Palapag-Mapanas-Gamay-lapinig Rd, Cabatuan-Magtaun Sect., Km.820+000.00-Km.824+000.00

w/ exception08/17/12 VIII 33.889 305 O 0.335 0.240 0.150 0.030 0.033 0.033 82.10 -

Rhyes Builders & Supply / Norsam Builders & Construction Supply

(JV)JV-11-271 Upgrading of Colab-og-Lungib-Buenasuerte-Pasabuena-

Maxvilla Rd. 08/10/13 VIII 46.345 270 C 0.369 0.188 0.300 - - - 85.70 85.52% Satisfactory

Rhyes Builders & Supply / Norsam Builders & Construction Supply

(JV)JV-11-271 Upgrading of Colab-og-Lungib-Buenasuerte-Pasabuena-

Maxvilla Rd. 08/11/12 VIII 46.345 180 O 0.289 0.300 0.150 0.030 0.035 0.050 85.40 -

Rhyes Builders / ESD Cruz Construction (JV) JV-11-066

Conc. of Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd., Cabatuan-Magtaon Sect., Km.820+000-Km.824+000 w/

exception08/06/13 VIII 33.889 407 C 0.391 0.182 0.300 - - - 87.30 84.18%

Satisfactory

RHYES Builders and Supply Help for Catubig Agricultural Advancement Project HCAAP-LMC-C-2 03/15/14 NIA 9.260 540 C 0.473 0.071 0.300 - - - 84.44 84.44%

Satisfactory

RICHFIELD BUILDERS 24525 Construction of Two (2) Storey Six (6) Classrooms Bais City Pilot School, Bais City 8/14/2014 VII 6.677 163 C 0.465 0.155 0.300 92.00 88.15%

Satisfactory

Richfield Builders 24525 Const. of 2 Storey 6-CL SB at Bais City Pilot Sch. 08/21/13 VII 6.555 153 O 0.393 0.220 0.142 0.030 0.047 0.033 86.50

Richfield Builders 24525 Rehab./Reconst. of Damaged Paved Nat'l Rd., Dumaguete North Rd., K0044+78-K0044+328 08/09/11 VII 3.843 91 O 0.339 0.300 0.085 0.030 0.040 0.033 82.70 -

Richmar Construction 18797Rehab./Reconst. of Damaged Paved Nat'l Rd. (IS) Matacon-

Libon-Polangui Jct. Rd., San Agustin, K486+(-648)-K486+052

11/26/12 V 9.269 165 C 0.452 0.133 0.300 - - - 88.50 86.10% Satisfactory

Richmar Construction 18797Rehab./Reconst. of Damaged Paved Nat'l Rd. (IS) Matacon-

Libon-Polangui Jct. Rd., San Agustin, K0486+(-648)-K0486+052

08/07/12 V 9.269 165 O 0.362 0.237 0.129 0.030 0.054 0.033 84.50 -

Richmark Construction 14227 Calbiga Irrigation Project 11/22/14 NIA 8.777 290 C 0.457 0.200 0.300 - - - 95.71 *95.71 V. Satisfactory

Richmark Construction 14227 Calbiga Irrigation Project 11/22/14 NIA 9.920 180 C 0.457 0.200 0.300 - - - 95.65 *95.65% V. Satisfactory

Richphil Builders, Inc. / Armando U. Khong Hun General Contractor,

Inc. (Joint Venture)JV-11-042

Rehab./Widening of Rd.s & Impv't. of Drainage System along Manila East Rd. (Rosario-Cainta Rd.) Km.15+654-

Km.17+13103/16/13 NCR 43.261 395 C 0.418 0.200 0.254 - - - 87.20 82.55%

Satisfactory

Rikda Construction & Dev't Corp. 32758 Completion of Academic Building I 10/16/14 DOST 4.104 119 C 0.437 0.200 0.300 - - - 93.70 95.68% V. Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page241

Page 242: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

RIKKI CONSTRUCTION 33492 Replacement/Rehabilitation/Strengthening of Kapayawan Bridge along Mt. Province-Ilocos Sur via Tue Road 8/12/2014 CAR 4.476 140 C 0.449 0.133 0.300 88.20 83.40%

Satisfactory

Rim Construction 15938 Rehab./Impvt. of Mountain Province-Ilocos Sur Road via Tue 03/09/09 CAR 19.012 369 O 0.351 0.300 0.150 0.030 0.050 0.050 93.10 -

Rim Construction 15938 Rehab./Impvt. of Mountain Province-Ilocos Sur Road via Tue 08/28/09 CAR 19.011 460 O 0.367 0.240 0.061 0.015 0.042 0.017 74.20 -

Ris Construction 34126 Rehab./Reconst. Of the Upper Chico River Flood Control, Dawaan-Akiki Drainage Sect. 08/02/13 CAR 4.457 113 C 0.452 0.133 0.300 - - - 88.50 *88.50%

Satisfactory

RIS Construction 34126 Const. of Bayudan Flood Control (Bauko - Sabangan Sect.) along Mt. Province-Ilocos Sur Rd. via Tue 03/16/13 CAR 4.998 70 C 0.278 0.200 0.300 - - - 77.80 *77.80%

Unsatisfactory

RISING SUN BUILDERS PHILS., INC. 30703 Improvement & Beautification of Bulusukan River 1/23/15 TIEZA 8.600 180 O 0.351 0.300 0.150 0.030 0.058 0.033 92.26

RISING SUN BUILDERS PHILS., INC. 30703 Improvement & Beautification of Bulusukan River 5/19/15 TIEZA 8.600 210 O 0.350 0.233 0.150 0.030 0.070 0.050 88.28

RISING SUN BUILDERS PHILS., INC. 30703 Hundred Islands Development 05/21/14 TIEZA 9.990 150 O 0.301 0.300 0.150 0.015 0.023 0.050 83.91

RISING SUN BUILDERS PHILS., INC. 30703 Hundred Islands Development 08/15/14 TIEZA 9.987 150 C 0.466 0.198 0.300 96.40 88.90% Satisfactory

RISM DESIGNERS AND GENERAL MERCHANDISE & ENGINEERING

SERVICES32830 Const. of DepED Standard Type School Building at Carol-

an ES Kabankalan City 8/8/2014 VI 2.429 85 C 0.448 0.200 0.300 94.80 85.84% Satisfactory

Rism Designer's and General Merchandise & Engineering

Services32830 Const. of DepEd Standard Type Sch. Bldg. @ Carol-an ES 08/08/13 VI 2.429 85 O 0.369 0.200 0.150 0.030 0.038 0.033 82.00

Ritche-Nathalie Builders and General Merchandise 27501 Erosion Protection/Rehab. of Tudela River Brgy. Taguima 08/16/13 X 4.999 130 C 0.482 0.133 0.300 - - - 91.50 *91.50%

V. SatisfactoryRitche-Nathalie Builders and

General Merchandise 27501 Completion of Opol Building 06/09/09 X 0.952 180 O 0.400 0.225 0.150 0.010 0.011 0.033 82.90 -

RITVIT Construction & Development Corp.

Renov. Of Acct., Budget, HRD, Legal, UPMDFI, Provident Offices & Social Hall (Building) 02/17/11 UP 14.019 150 O 0.342 0.300 0.150 0.020 0.057 0.050 91.90 -

RITVIT Construction & Development Corp.

Proposed Renovation of Accounting, Budget, HRD, Legal, UPMDFI, Provident Offices & Social Hall 11/24/11 UP 14.829 150 O 0.339 0.300 0.150 0.030 0.070 0.050 93.90 -

Ritvit Construction & Development Corporation 9426 Renovation of Budget, Accounting, HRDO, Legal, UPMDFI

Provident Offices & Social Hall 08/26/10 U.P Manila 14.091 150 O 0.40 0.30 0.08 0.03 0.07 0.05 91.00 -

RIVBROS Construction Factors and Development Calitlitan Communal Irrigation System 01/26/15 NIA 26.984 240 O 0.250 0.300 0.150 0.030 0.060 0.050 84.00 -

RJIR ENTERPRISES 34843Widening of Road along Palo-Carigara-Ormoc Road

Chainage 0+131 Leyte along Palo-Carigara-Ormoc Road, K1010+512 - K1010+562

8/7/2014 VIII 4.330 120 C 0.403 0.133 0.300 83.60 83.60% Satisfactory

RKKI Construction 33492 Replacement/Rehab./Strengthening of Kapayawan Bridge along Mt. Province-Ilocos Sur via Tue Rd. 08/02/13 CAR 4.171 140 O 0.367 0.240 0.099 0.015 0.048 0.033 80.20

RKKI Construction 33492 Replacement of Losong Bridge along Mt. Province-Ilocos Sur via Kayan Rd. 03/16/13 CAR 8.456 150 C 0.444 0.200 0.000 - - - 64.40 68.42%

Poor

RLK Construction & Builders 32194 Construction of Lateral "A" at Sta. 4+876 - Sta 5+299.75 of Laris 02/27-03/03/12 NIA 6.856 90 O 0.376 0.240 0.150 0.030 0.053 0.050 89.88 -

RMS Builder and Supply 19490 Prev. Maint. RT Lim Blvd. (Dual) Chainage 0063-Chainage 0823 08/05/13 IX 4.621 121 O 0.363 0.294 0.000 0.030 0.047 0.033 76.70

RMS Builders and Supply 19490 Rehabilitation of Local Road at Sta. Maria - Gov. Ramos Intersection 8/5/2014 IX 6.991 102 OG 0.350 0.300 0.105 0.030 0.041 0.033 85.90

RMS Builders and Supply 19490 Preventive Maintenance of R.T. Lim Boulevard (Dual Chainage 0063 - Chainage 0823 8/5/2014 IX 4.520 166 C 0.425 0.139 0.300 86.40 80.58%

UnsatisfactoryRND Construction 7035 Agno River Integrated Irrigation Project 7/13-18/09 NIA 3.806 90 O 0.345 0.300 0.150 0.015 0.038 0.033 88.11 -

RNN Construction Corporation (Formely: RNN Construction) 24880 Rehab./Reconst./Upgrading of Damaged Paved Roads (IS)

(K0028+572.50-K0028+996.50) at PPTA Road 03/12/12 NCR 3.566 103 C 0.438 0.124 0.300 - - - 86.20 91.30% V. Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page242

Page 243: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

RNS Construction Engineering 34046 Repair/Rehab./Const. of FMR at Brgy. Poblacion-Brgy. Dalican to Brgy. Benolen & Brgy. Bagoinged 03/15/13 XII 9.681 89 C 0.404 0.133 0.300 - - - 83.70 *83.70%

Satisfactory

ROAD EDGE TRADING & DEVELOPMENT SERVICES 33140

Preventive Maintenance Based on PMS/HDM-4 (Intermittent Section), along Surigao City - San Juan

Coastal Road8/13/2014 XIII 15.350 71 C 0.371 0.133 0.300 80.40 80.40%

Unsatisfactory

ROAD EDGE TRADING & DEVELOPMENT SERVICES 33140 Repair/Rehab./Improvement along Surigao - Agusan Road,

Sta. 1150+375 - Sta. 1146+800 with Exceptions, Timamana 8/13/2014 XIII 4.743 78 C 0.296 0.136 0.300 73.20 81.18% Unsatisfactory

ROAD EDGE TRADING & DEVELOPMENT SERVICES 33140 Protection Works along Dinagat - Loreto Road (Paragua

Section) 8/14/2014 XIII 9.183 100 OG 0.202 0.240 0.001 0.030 0.023 0.033 52.90

Road Edge Trading & Development Services 33140 Installation/Application/Const. of Rd. Safety Devices along

Maharlika Rd., Km.104+195-Km.123+345 w/ exceptions 08/09/13 III 4.814 30 C 0.412 0.133 0.300 - - - 84.50 *84.50% Satisfactory

Road Edge Trading & Development Services 33140 Repair/Rehab./Impv't. along Surigao-Agusan Rd,.

Sta.1150+37 -Sta.1146+800 w/ exceptions 08/07/13 XIII 4.743 78 O 0.362 0.223 0.150 0.030 0.050 0.050 86.50

Road Edge Trading & Development Services 33140 Impvt./Rehab. along Sta. Monica-Burgos-San Isidro Rd.,

Sta. 48+135-Km.68+469.60 w/ exceptions 08/13/12 XIII 19.284 240 C 0.452 0.168 0.300 - - - 92.00 87.80% Satisfactory

Road Edge Trading & Development Services 33140 Const. of Slope Protection along Bacolod South Rd. 03/12/13 VI 18.806 120 C 0.331 0.200 0.300 - - - 83.10 *83.10%

Satisfactory

ROAD EDGE TRADING AND DEVELOPMENT SERVICES 33140 Major Repair/Maintenance of Existing Permanent Bridges,

Lagonglong Bridge Along BCIR 8/11/2014 X 4.576 180 OG 0.388 0.265 0.150 0.023 0.048 0.033 90.70

ROAD EDGE TRADING AND DEVELOPMENT SERVICES 33140 Construction of Drainage Canal along Butuan City-

Cagayan de Oro City-Iligan City Road 8/11/2014 X 13.809 210 OG 0.400 0.300 0.150 0.008 0.029 0.033 92.00

Roadmax Construction Corporation 26804 Construction of PCCP as Solar Dryer 07/27/13 NIA 6.537 75 C 0.406 0.200 0.300 - - - 90.55 *90.55%

V. Satisfactory

ROADTECH CONSTRUCTION 17580 Preventive Maintenance along Lingayen-Labrador Diversion Road K0364+690- K0366+000 10/28/2014 I 13.584 16 C 0.361 0.200 0.300 - - - 86.10% 86.1%

SatisfactoryRoadtech Construction 17580 Replacement of Udiao Bridge 03/13/13 I 32.104 210 O 0.374 0.285 0.000 0.023 0.040 0.017 73.90 -

Roadtech Construction 17580Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds.

along Urdaneta Jct.-Dagupan Rd. Km.203+459-Km.206+777 w/ exception

08/16/11 I 15.589 190 O 0.383 0.300 0.150 0.030 0.045 0.050 95.80 -

Roadtech Construction 17580Rehab./Reconst./Upgrading of Damaged Paved National Roads along Urdaneta Jct.-Dagupan Road, Km.203+459 -

Km. 206+777 w/ exception04/07/11 I 15.589 150 O 0.390 0.240 0.150 0.018 0.037 0.033 86.80 -

Roadtech Construction 17580Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds.

along Urdaneta Jct-Dagupan Road, Km 203+459-Km. 206+777 w/ exception

03/19/12 I 15.589 190 C 0.363 0.200 0.300 - - - 86.30 89.30% V. Satisfactory

ROBETH GEN. MDSE. AND SUPPLY (Formerly: Robeth Gen. Merchandise & Supplies - Isulan

Branch)

23175 Road Upgrading along Isulan Jct. Ninoy Aquino Road K1777+1474 - K1781+594 8/8/2014 XII 34.932 207 C 0.418 0.133 0.300 85.10 86.20%

Satisfactory

ROBETH GEN. MDSE. CONST & SUPPLY (Formerly: Robeth Gen.

Mdse. & Suppllies - Isulan Branch)23175

Construction of Road-Jose Abad Santos St. Purok 5, Poblacion Tulunan, Under Local Infrastructure Program, Poblacion Tulunan, Cotabato, Km. 0+000 to Km. 0+328

with 15.9 meters Exemption

10/24/2014 XII 4.001 49 C 0.410 0.133 0.300 - - - 84.30% 84.3% Satisfactory

ROBETH GEN. MDSE. CONST & SUPPLY (Formerly: Robeth Gen.

Mdse. & Suppllies - Isulan Branch)23175

Road Upgrading (Gravel to Concrete) along Isulan Hwy. Jct. Dukay-Bagumbayan-Sen. Aquino-Kalamansig Road

(Km. 1859+046 - Km. 1850+218), Buenaflores10/27/2014 XII 26.805 127 C 0.398 0.127 0.300 - - - 82.50% 82.5%

Satisfactory

Robeth Gen. Mdse. Const. & Supply (Formerly: Robeth Gen. Mdse & Supplies-Isulan Branch)

23175Strengthening/Reconst./Replacement of Pamintuan Bridge (24 L.M. Flatslab) along Makilala-Ala Valley Rd. C006+152-

C006+224 (24 LM Flatslab)08/11/12 XII 10.336 226 O 0.381 0.278 0.150 0.030 0.051 0.050 94.00 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page243

Page 244: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Robeth Gen. Mdse. Const. & Supply (Formerly: Robeth Gen.

Mdse. & Supplies - Isulan Branch)23175

Rd. Upgrading (Gravel to Paved) along Awang-Upi-Lebak-Kalamansig-Palimbang-Sarangani Road (Km.1963+471-

Km.1977+121) Realign to Rd. Upgrading (Gravel to Paved) along Awang-Upi-Lebak - Kalamasig-Palimbang-Sarangani Rd. (Km.1954+708-Km.1957+000 w/ exception), Kalamansig-

Palimbang

08/15/13 XII 33.430 309 C 0.410 0.200 0.300 - - - 91.00 89.02% V. Satisfactory

Robeth Gen. Mdse. Const. & Supply (Formerly: Robeth Gen.

Mdse. & Supplies - Isulan Branch)23175

Rd. Upgrading (Gravel to Paved) Int. Sect. along Isulan Jct. Ninoy Rd., Km.1777+474-Km.1778+125, Km.1779+077-

Km.1778+806, Km.1780+175, Km.1780+965-Km.1781+58908/17/13 XII 34.932 215 O 0.308 0.300 0.150 0.030 0.048 0.033 86.90

Robeth Gen. Mdse. Const. & Supply (Formerly: Robeth Gen.

Mdse. & Supplies-Isulan Branch)23175

Rd. Upgrading (Gravel to Paved) along Awang-Upi-Lebak-Kalamansig-Palimbang-Sarangani Rd. (Km.1963+471-

Km.1977+121) realigned to Rd Upgrading (Gravel to Paved) along Awang-Upi-Lebak-Kalamansig-Palimbang-Sarangani

Rd. (Km.1954+708-Km.1957+000 w/ exception)

03/14/13 XII 33.430 309 O 0.337 0.255 0.150 0.030 0.055 0.050 87.70 -

Robeth Gen. Mdse. Const. & Supply (Formerly: Robeth Gen.

Mdse. & Supplies-Isulan Branch)23175

Strengthening/Reconst./Replacement of Pamintuan Bridge (24 Lm Flatslab) along Makilala-Ala Valley Rd. C006+152-

C006+224 (24 lm Flatslab)11/20/12 XII 11.361 236 C 0.456 0.133 0.300 - - - 88.90 91.96%

V. Satisfactory

Robeth Gen. Mdse., Const. & Supplies-Isulan Branch 23175 Road Upgarding, Gamasil Section 11/26/08 XII 14.048 225 O 0.161 0.300 0.100 0.030 0.043 0.100 73.40 -

Robeth Gen. Mdse., Const. & Supplies-Isulan Branch 23175 Road Upgrading, Gamasil Section 03/13/09 XII 14.048 225 O 0.390 0.300 0.150 0.030 0.060 0.050 98.00 -

ROBIG Builders and Development Corporation 35327 Safety Signages Works along SCTEX 03/12/15 BCDA 12.379 60 C 0.456 0.200 0.300 - - - 95.61 *95.61%

V. Satisfactory

ROCKWORLD INDUSTRIES 7852Off Carriage-way Improvement Paving of Shoulders (Seal

Widening) Dulag - Julita - Buraen Road KO944+000 - KO944+214, Brgy. San Vicente - Brgy. Del Pilar

8/9/2014 VIII 22.502 150 OG 0.370 0.228 0.150 0.030 0.045 0.033 85.60

Rockworld Industries 7582Rehab./Reconst. of Damaged Paved Nat'l. Rd. along Dulag-

Julita-Burauen Rd., K0941+000-K0945+600; K0947+000-K0948+300

03/11/13 VIII 18.268 135 O 0.353 0.225 0.150 0.023 0.050 0.050 85.10 -

Rockworld Industries 7582 Const. of Burauen-Mahagnao Rd. 05/31/10 VIII 10.713 120 O 0.371 0.300 0.104 0.030 0.042 0.033 88.00 -

Rockworld Industries 7582 Rehab./Reconst. of Daang Maharlika, K0950+000-K0951+012, K0958+000-K0958+804 08/21/12 VIII 18.930 150 C 0.399 0.133 0.300 - - - 83.20 84.82%

Satisfactory

Rocky 5 G Builders 32506 Const. of MPB, La Trinidad Vegetable Trading Post, Trading Post 03/12/12 CAR 0.918 72 C 0.455 0.133 0.300 - - - 88.80 88.66%

Satisfactory

Rocky 5G Builders 32506 Repair/Restoration of Slip along Baguio-Bontoc Rd., K0265+000-K0341+000 (V.S.) 08/02/12 CAR 6.168 200 C 0.357 0.200 0.300 - - - 85.70 77.30%

UnsatisfactoryRoda Construction and General

Supply 19674 Conc. of Ariman-Bulusan Lake Road 05/26/10 V 19.200 82 O 0.352 0.237 0.150 0.030 0.035 0.033 83.70 -

Roda Construction and General Supply 19674 Rehab./Impvt. of Sitio Wawa-Brgy. Lajong Road 08/26/09 V 1.920 60 O 0.314 0.269 0.150 0.030 0.047 0.050 86.00 -

Roda Construction and General Supply 19674 Rehab./Reconst. of Damaged Paved Nat'l Rd., (Int. Sect.)

Bacon District 08/13/13 V 11.084 105 C 0.402 0.200 0.300 - - - 90.20 *90.20% V. Satisfactory

ROIM BUILDERS & CONSTRUCTION SUPPLY 20226

Road Upgrading (Gravel to Paved) along Butuan City-Talacogon-Loreto-Veruela-Sta. Josefa Road (K1331+180 -

K1332+490.10)10/22/2014 XIII 27.937 257 C 0.407 0.132 0.300 - - - 83.90% 83.9%

Satisfactory

ROIM BUILDERS & CONSTRUCTION SUPPLY 20226

Road Upgrading (Gravel to Paved) along Butuan City - Talacogon - Loreto - Veruela - Sta. Josefa Road,

K1325+992 - K1328+4278/6/2014 XIII 49.000 287 C 0.341 0.200 0.300 84.10 82.96%

Satisfactory

Roim Builders & Construction Supply 20226

Const./Rehab. of Rd. Slip along NRJ-Bahbah-Talacogon Rd. (Sta.1305+350.00-Sta.1310.40 L/S (Slip 3);

Sta.1305+803.60-Sta.1305+870.20 R/S (Slip 4) Prosperidad & Talacogon

08/21/13 XIII 14.146 350 C 0.411 0.133 0.300 - - - 84.40 85.38% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page244

Page 245: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Roim Builders & Construction Supply 20226

Road Upgrading from Gravel to Paved along Butuan City-Talacogon-Loreto-Veruela-Sta. Josefa Rd. K1325+992-

K1328+42708/21/13 XIII 45.086 209 O 0.267 0.300 0.150 0.015 0.040 0.050 82.20

Roim Builders & Construction Supply 20226

Const./Rehab. of Slip along NRJ-Bahbah-Talacogon Rd. (Sta. 1305+350.00-Sta. 1310.40 L/S (Slip 3); Sta.1305+803.60-

Sta.1305+870.20 R/S (Slip 4)03/20/13 XIII 14.146 350 O 0.325 0.300 0.150 0.030 0.032 0.033 87.00 -

Roim Builders & Construction Supply 20226

Const./Rehab. of Rd. Slip along NRJ Bahbah-Talacogon Rd., Sta. K1305+350-Sta. K1310.40L/S (Slip 3); Sta.

1305+803.60-Sta. 1305+870.2 R/S (Slip 4) 11/28/12 XIII 14.146 300 O 0.252 0.278 0.150 0.030 0.065 0.050 82.50 -

Roim Builders & Construction Supply 20226 Repair of Lucena Bridge Approaches, Slope/Bank

Protection 08/19/12 XIII 16.594 250 C 0.400 0.200 0.300 - - - 90.00 94.02% V. Satisfactory

Roim Builders & Construction Supply 20226

Const./Rehab. of Rd. Slip along NRJ-Bahbah-Talacogon Rd. (Sta. 1305+350.00-Sta. 1310.40 L/S (Slip 3); Sta.1305+803.60-Sta.1305+870.20 R/S (Slip 4)

08/18/12 XIII 14.146 270 O 0.311 0.300 0.150 0.030 0.045 0.050 88.60 -

ROJUNED CONSTRUCTION 13483Road Upgrading (Gravel to Concrete) Along Alfonso Lista-Aurora Bdry Road, K0440+(-158) - K00441+347 (K0442+100)

Intermittent Section8/6/2014 CAR 1.246 60 C 0.430 0.133 0.300 86.30 86.30%

Satisfactory

Rola Construction 6813 Concreting of Pugay-Bongliw-Yade-Tambangan Road 8/9/2014 V 2.779 60 C 0.329 0.200 0.300 82.90 84.82% Satisfactory

ROLA CONSTRUCTION 6813 Capiz National High School, Roxas City (capital), Capiz (b) Const. of Two (2) Storey, 4 Classrooms School Building 8/14/2014 VI 4.675 245 C 0.402 0.200 0.300 90.20 85.93%

Satisfactory

Rola Construction 6813 Conc. of Pugay-Bongliw-Yade-Tambangan Rd. 08/02/13 V 2.779 60 O 0.363 0.240 0.150 0.030 0.045 0.033 86.10

Rola Construction 6813 Capiz NHS, Roxas City (Capital), Capiz, (b) Const. of 2-Storey, 4 Cl Sch. Bldg. 08/18/13 VI 4.493 210 O 0.317 0.240 0.150 0.030 0.054 0.050 84.10

Rola Construction 6813 Road Upgrading, Roxas City Boundary, Panitan-Bailan Rd. 03/01/10 VI 19.099 238 O 0.332 0.300 0.150 0.010 0.028 0.033 85.30 -

Rola Construction 6813 Const. of Two (2) Storey, 8-Classroom Sch. Bldg. Nonito Paz Arroyo Memorial NHS @ Sagread Familia 11/27/12 V 9.555 180 C 0.483 0.133 0.300 - - - 91.60 88.59%

Satisfactory

Rola Construction 6813 Indv. Project-Const. of Two Storey 8-Cl Sch. Bldg. Nonito Paz Arroyo Memorial Nat'l High Sch., Sagrada Familia 08/09/12 V 9.555 180 O 0.370 0.240 0.150 0.030 0.050 0.033 87.30 -

ROLA CONSTRUCTION 6813 Cluster : Concreting of Local Roads at Lupi, Del Gallego and Sipocot, Camarines Sur 11/9/2014 V 1.878 90 C 0.453 0.133 0.300 - - - 88.60% 88.6%

Satisfactory

ROLAND CONSTRUCTION 19201 Road Upgrading (Gravel to Paved) Jct. Gamut-San Miguel-Bayugan Road (K1318+565 - K1318+756.85) 10/25/2014 XIII 4.123 56 C 0.415 0.175 0.300 - - - 89.00% 89%

Satisfactory

ROLCO CONSTRUCTION & DEVELOPMENT CORPORATION (Formerly: Rolco Construction &

General Merchandise)

29686 Local Infrastructure Program - Construction of Road Brgy. Nagotgot 11/15/2014 V 4.781 52 C 0.462 0.200 0.069 - - - 73.10% 73.1%

Poor

ROLCO CONSTRUCTION & DEVELOPMENT CORPORATION (Formerly: Rolco Construction &

General Merchandise)

29686Contract Package No. 01 (Installation of Road Safety

Devices and Pavement Markings) g. Goa-Digdigon-San Isidro Road (Pinaglabanan Section)

11/13/2014 V 0.750 45 C 0.469 0.133 0.300 - - - 90.20% 90.2% Very Satisfactory

Rolco Construction & General Merchandise 29686 Rehab. of Flood Control System along Bulawan River, San

Roque Sect. 08/11/13 V 18.228 180 C 0.456 0.133 0.300 - - - 88.90 *88.90% Satisfactory

Roma Construction and Development Corporation 6514 Completion of Agbalo Bridge along Iloilo East Coast Capiz

Road 03/26/12 VI 85.106 360 O 0.400 0.181 0.150 0.030 0.035 0.050 84.60 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page245

Page 246: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

RONWOOD CONST. & SUPPLY/REGIONAL INFRASTRUCTURE

DEVELOPMENT CORPORATION (JV)

JV-13-384Improvement/Upgrading (Gravel to Concrete) of NRJ

Blanca - Bunawan Eco Park Road Leading to Bunawan Eco Park, K1344+300 - K1347+036

8/8/2014 XIII 72.476 225 OG 0.381 0.242 0.150 0.030 0.047 0.050 90.00

RONWOOD CONSTRUCTION & SUPPLY 25311

Widening of Butuan - Cagayan de Oro - Iligan Road (Agusan - Misamis Oriental Section) Nasipit Section, Sta.

1259+480 - Sta. 1261+2538/4/2014 XIII 34.547 221 C 0.391 0.143 0.300 83.40 84.60%

Satisfactory

Ronwood Construction & Supply 25311Widening of Butuan-Cagayan de Oro-Iligan Rd. (Agusan-

Misamis Oriental Sect.) Nasipit Sect., Sta.1259+480-Sta.1261+253

03/12/13 XIII 34.547 157 O 0.358 0.233 0.150 0.030 0.050 0.033 85.40 -

Ronwood Construction & Supply 25311 Jct. Cancohoy-Pilar Road, (Caridad-Pilar Section) 08/12/11 XIII 21.116 260 O 0.361 0.225 0.150 0.023 0.032 0.033 82.40 -

Ronwood Construction & Supply 25311 Jct. Del Carmen-San Benito-Burgos Rd., Del Carmen-San Benito Rd. Section 02/26/10 XIII 17.126 261 O 0.371 0.240 0.104 0.030 0.047 0.033 82.50 -

Ronwood Construction & Supply 25311 Completion of the Channel of Osmeña-Dapa Flood Control 06/05/10 XIII 9.645 180 O 0.304 0.300 0.150 0.030 0.040 0.033 85.70 -

Ronwood Construction & Supply 25311 Completion of the Channel of Osmeña-Dapa Flood Control 08/28/10 XIII 9.645 240 O 0.345 0.266 0.150 0.008 0.045 0.050 86.40 -

Ronwood Construction & Supply 25311 Const. of Catangan-Cabitoonan-Libertad Road & Bridges 11/21/08 XIII 9.644 180 O 0.284 0.213 0.100 0.030 0.032 0.100 75.90 -

Ronwood Construction & Supply 25311 Impvt./ (Conc.) of Access Road Jct. BCIR to Balingoan Port Road 06/01/09 X 2.603 120 O 0.333 0.240 0.133 0.020 0.065 0.033 82.40 -

Ronwood Construction & Supply 25311 Cancohoy-San Isidro-Pilar Road, San Isidro-Pilar Section 05/29/09 XIII 6.752 150 O 0.390 0.201 0.150 0.030 0.051 0.050 87.20 -

Ronwood Construction & Supply 25311 Conc. of SAFRAGEMC Subdivision Road, San Isidro 06/08/09 XIII 2.825 150 O 0.427 0.133 0.300 - - - 86.00 84.98% Satisfactory

Ronwood Construction & Supply 25311 Del Carmen-Sta. Monica-San Isidro Rd., Sta Monica-San Isidro Sect. 09/03/09 XIII 7.715 150 O 0.364 0.289 0.150 0.030 0.060 0.033 92.60 -

Ronwood Construction & Supply 25311 Jct. del Carmen-San Benito-Burgos Rd., Del Carmen-San Benito Rd. Sect. 09/03/09 XIII 17.126 240 O 0.355 0.263 0.150 0.030 0.060 0.033 89.10 -

Ronwood Construction & Supply 25311 Jct. Osmeña-Pilar Rd. 09/03/09 XIII 13.239 210 O 0.326 0.225 0.150 0.030 0.060 0.033 82.40 -

Ronwood Construction & Supply 25311 Concreting of SAFRAGEMC Subdivision Road 03/17/09 XIII 2.825 150 O 0.324 0.252 0.150 0.030 0.037 0.050 84.30 -

Ronwood Construction & Supply 25311 Const. of Catangan-Cabitoonan-Libertad Road & Bridges 03/07/09 XIII 9.644 194 O 0.353 0.237 0.150 0.030 0.032 0.050 85.20 -

Ronwood Construction & Supply 25311Reconst. Of Damaged Paved Nat'l Rds., Butuan-Cagayan

de Oro-Iligan (Agusan-Misamis Oriental), Sta.1261+966.70-Sta.1263+000

08/19/12 XIII 20.688 210 C 0.349 0.200 0.300 - - - 84.90 87.24% Satisfactory

Ronwood Construction & Supply 25311 Jct. Del Carmen-Sta. Monica-San Isidro Road (Sta.24+680 - Sta.26+340) 08/13/12 XIII 24.401 240 C 0.363 0.146 0.300 - - - 80.90 82.70%

Satisfactory

Ronwood Construction & Supply 25311 Jct. Concohoy-Pilar Rd. (Sta.20+673-Sta.21+991.5) 08/13/12 XIII 16.618 210 C 0.353 0.146 0.300 - - - 79.90 82.18% Satisfactory

Ronwood Construction & Supply 25311 Impvt./Conc. of Jct. Del Carmen-Sta. Monica (Km.0076+297.20-Km.0028+080) 08/13/12 XIII 29.498 180 O 0.283 0.240 0.150 0.030 0.050 0.050 80.30 -

Ronwood Construction & Supply 25311 Jct. Del Carmen-Sta. Monica-San Isidro Rd., San Benito-Sta. Monica-Burgos Sect. 08/13/12 XIII 21.040 272 C 0.386 0.145 0.000 - - - 53.10 67.98%

Poor

Ronwood Construction & Supply 25311Widening of Butuan-Cagayan de Oro-Iligan Rd. (Agusan-

Misamis Oriental Sect.) Nasipit Sect., Sta.1259+480-Sta.1261+253

08/06/13 XIII 34.547 251 O 0.363 0.234 0.150 0.030 0.027 0.050 85.40

Ronwood Construction & Supply / Regional Infrastructure

Development Corporation (J.V.)JV-12-129

Const. of Jct. Osmeña-Pilar Rd. (San Roque-Pilar Sect.), K18+000-K19+000 & K20+500-K22+620, Pilar, Siargao

Island08/09/13 XIII 79.634 225 O 0.372 0.230 0.150 0.023 0.045 0.050 87.00

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page246

Page 247: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

RONWOOD CONSTRUCTION & SUPPLY/REGIONAL INFRASTRUCTURE

DEVELOPMENT CORPORATION (JV)

JV-13-384Improvement/Upgrading (Gravel to Concrete) of NRJ

Blanca-Bunawan Eco Park Road leading to Bunawan Eco Park, K1344+300 - K1347+036

10/23/2014 XIII 72.476 225 O 0.310 0.300 0.150 0.023 0.042 0.050 87.50% 87.5% Satisfactory

ROPRIM CONSTRUCTION 8546 Construction of Multi-Purpose Building at Oton Central School 8/4/2014 VI 3.799 327 C 0.443 0.200 0.300 94.30 87.16%

Satisfactory

Roprim Construction 8516 Const. of MPB at Trapiche Elem. Sch. 08/14/13 VI 3.799 150 C 0.451 0.133 0.300 - - - 88.40 90.71% V. Satisfactory

Roprim Construction 8516 Const. of MPB at Oton Central Sch. 08/14/13 VI 3.799 327 O 0.361 0.240 0.150 0.030 0.027 0.033 84.10 Roprim Construction 8516 Const. of MPB at Trapiche Elem. School 03/17/13 VI 3.799 150 O 0.365 0.270 0.150 0.030 0.052 0.050 91.70 -Roprim Construction 8546 Conc. of Pototan-Dingle-Tabugon Rd. 02/24/10 VI 43.380 240 O 0.334 0.284 0.150 0.030 0.033 0.050 88.10 -

Roprim Construction 8546 Rehab. of Capiz-Aklan Rd. Km.324+000 - Km.328+905.50 w/ exception 06/14/10 VI 27.802 250 O 0.325 0.240 0.150 0.030 0.042 0.050 83.70 -

Roprim Construction 8546 Reblocking of Pototan-Mina Janiuay Road 03/18/09 VI 9.545 232 O 0.348 0.300 0.150 0.030 0.060 0.050 93.80 -Roprim Construction 8546 Reblocking of Pototan-Mina Janiuay Road 12/04/08 VI 9.546 120 O 0.293 0.225 0.100 0.015 0.032 0.100 76.50 -

Roprim Construction / Jet Construction Supply (JV) JV-11-266 Replacement/Const. of Linaban Bridge, (Km. 83+017.60) 08/15/13 VI 23.959 410 O 0.356 0.300 0.024 0.030 0.033 0.033 77.60

ROSAND BUILDERS 15781 Imprv't./Asphalt Overlay of Hemady St. Quezon City, K0008+534 - K0009+618 8/15/2014 NCR 8.242 45 C 0.489 0.133 0.300 92.20 92.20%

Very Satisfactory

Rosand Builders 15781 Impv't./Asphalt Overlay of Hemady St., (K0008+53 -K0009+618) 03/19/13 NCR 7.670 38 O 0.378 0.300 0.000 0.023 0.025 0.033 75.90 -

Rosand Builders 15781 Rehab./Reconst. of Damaged Paved National Roads at Davao City Diversion Rd. Ma-a-Shrine Rd. Sect. 06/16/10 XI 14.474 90 O 0.384 0.237 0.150 0.030 0.047 0.033 88.10 -

Rosand Builders 15781 Construction of 3-Storey, 15 Classroom School Buildings 01/20/10 NHA 21.615 150 O 0.391 0.300 0.006 0.030 0.055 0.050 83.20 -

Rosand Builders 15781 Construction of Two-Storey Multi-Purpose Center 02/25/10 NHA 3.492 90 O 0.388 0.300 0.150 0.030 0.070 0.050 98.80 -

Rosand Builders 15781 Construction of 3-Storey, 15 Classroom School Building 04/14/10 NHA 21.605 350 O 0.397 0.300 0.150 0.030 0.050 0.050 99.70 -

Rostel Construction & Supply 26934 Rd. Upgrading (Gravel to Paved) of Buenavista-Bunaguit Rd., Sta.1272+000-Sta.1273+500 08/06/13 XIII 38.017 169 O 0.341 0.252 0.021 0.030 0.035 0.017 69.60

Rostel Construction & Supply 26934 Road Upgrading (Gravel to Paved) of Buenavista-Bunaguit Road, Sta.1272+000 - Sta.1273+500 03/12/13 XIII 38.017 131 O 0.313 0.300 0.150 0.030 0.023 0.033 84.90 -

Rostel Construction & Supply 26934 Upgrading of Buenavista-Bunaguit Road (Malpoc-Rizal Section) 05/31/10 XIII 10.663 135 O 0.374 0.249 0.150 0.023 0.035 0.033 86.40 -

Rostel Construction & Supply 26934 Upgrading of Buenavista-Bunaguit Road (Malpoc-Rizal Section) 08/23/10 XIII 10.563 180 O 0.344 0.245 0.150 0.030 0.045 0.033 84.70 -

ROSTEL CONSTRUCTION AND SUPPLY 26934 Impvt./Upgrading (Gravel to Paved) of Buenavista -

Bunaguit Road, Sta. 1272+000 - Sta. 1273+500 8/5/2014 XIII 38.017 206 C 0.387 0.133 0.300 82.00 79.15% Unsatisfactory

ROVILLA CONSTRUCTION 19514Rehabilitation/Reconstruction/Upgrading of Damaged Road along Antonio Y de Pio Highway: 1) K0112+135 - K0112+326, Tabuelan and 2) K0139+979 - K0140+213

10/22/2014 VII 10.434 151 C 0.350 0.200 0.300 - - - 85.00% 85% Satisfactory

Rovilla Construction 19514Const. of 2 Storey - 4 CL Sch. Bldg. at Santa Fe NHS, Santa

Fe; & Const. of 2 Storey - 4 CL Sch. Bldg. at Lambusan NHS, San Remegio

08/10/13 VII 9.392 140 C 0.475 0.133 0.300 - - - 90.80 *90.80% V. Satisfactory

Rovilla Construction 19514Rd. Upgrading of Nat'l Rds. (Int. Sect.) at Bogo-Curva-

Medellin-Daanbantayan-Maya Rd: 1)K0132+335-K0132+586; & 2)K0134+387-K0134+880

08/10/13 VII 12.320 121 C 0.406 0.200 0.300 - - - 90.60 *90.60% V. Satisfactory

Rovilla Construction 19514 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. at Antonio I De Pio Highway, K0134+240-K0135+000 08/21/12 VII 15.698 95 C 0.409 0.148 0.300 - - - 85.70 87.14%

Satisfactory

ROWIE'S CONSTRUCTION 23595

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies Traffic Benchmark for Upgrading to Paved Road Standard (HDM-4 Project Analysis)(Intermittent Sections)

Surigao - Davao Coastal Road, K1480+155 - K1480+191

10/24/2014 XIII 1.176 64 C 0.407 0.200 0.253 - - - 86.00% 86% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page247

Page 248: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Rowie's Construction 23595 Conc. of Farm-To-Market Road 03/15/13 XIII 1.902 49 O 0.376 0.271 0.150 0.030 0.020 0.030 87.70 -

Rowie's Construction 23595 Rehab./Improvement of DPWH Surigao del Sur 1st DEO Bldg. 06/03/09 XIII 1.923 90 O 0.357 0.300 0.150 0.030 0.030 0.050 91.70 -

ROYAL CROWN MONARCH CONST & SUPPLIES CORP. / REND

SL2-SN-001516 PIDP/Angat-Maasim River Irrigation System 05/31/14 NIA 34.577 305 O 0.332 0.263 0.127 0.023 0.047 0.050 84.03 -

Royal Crown Monarch Const. & Supplies Corp./REND

SL2-SN-001516 PIDP/Angat-Maasim River Irrigation System 03/31/15 NIA 34.579 427 C 0.422 0.200 0.300 - - - 92.18 87.28%

SatisfactoryRoyal Crown Monarch

Construction & Supplies Corporation

9036 Concreting of Capas-Botolan Road, Km. 122+528-Km. 124+628, Capas Section 05/20/09 III 28.686 150 O 0.375 0.214 0.150 0.020 0.030 0.050 83.90 -

Royal Crown Monarch Construction & Supplies

Corporation9036 Const. of Multi-Purpose Building at Tarlac College of

Agriculture 09/02/09 III 9.355 150 O 0.358 0.300 0.150 0.030 0.056 0.050 94.40 -

Royal Crown Monarch Construction & Supplies

Corporation (Formerly: R.C. Miranda Construction & Supplies)

9036

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. Cluster III along: 1. Capas-San Jose-Mayantoc-Malacampa

Rd. (2nd District) K0129+322-K0130+250 w/ exception, K0130+250-K0131+250 w/ exception, K0131+250-

K0132+000 w/ exception, K0133+000 - K0134+000 w/ exception; 2. Rehab. of Capas-San Jose-Mayantoc-

Malacampa Rd. (2nd District) K0128+250-K0134+600 w/ exception, K0132+000-K0133+000

08/08/13 III 43.200 134 C 0.443 0.134 0.300 - - - 87.70 *87.70% Satisfactory

Royal Crown Monarch Construction & Supplies

Corporation (Formerly: R.C. Miranda Construction & Supplies)

9036 Prev. Maint. of NE-Pangasinan Rd., K0151+503-K0154+000; K0155+262-K0155+637; K0155+637-K0156+075 08/13/13 III 26.657 60 C 0.393 0.133 0.300 - - - 82.60 84.28%

Satisfactory

Royal Crown Monarch Construction & Supplies

Corporation (Formerly: R.C. Miranda Construction & Supplies)

9036 Prev. Maint. of Tarlac-Sta. Rosa Rd. 11/24/12 III 54.013 265 O 0.367 0.262 0.150 0.030 0.061 0.050 92.00 -

Royal Crown Monarch Construction & Supplies

Corporation (Formerly: R.C. Miranda Construction & Supplies)

9036Repair/Rehab./Maint. of Parua River Flood Control at

Barangays Balutu, Calius Gueco and Panalicsican, Sta. 0+000-Sta. 0+262

08/06/12 III 19.056 120 C 0.402 0.200 0.300 - - - 90.20 92.60% V. Satisfactory

Royal Crown Monarch Construction & Supplies

Corporation (Formerly: R.C. Miranda Construction & Supplies)

9036 Prev. Maint. of Tarlac-Sta. Rosa Rd. 08/08/12 III 54.013 180 O 0.315 0.300 0.150 0.030 0.039 0.050 88.40 -

Royal Crown Monarch Construction & Supplies

Corporation (Formerly: R.C. Miranda Construction & Supplies)

9036

Rehab./Reconst/Upgrading of Int. Sect., Nat'l Secondary Rd. along San Nicolas-Natividad-San Quintin-Umingan-

Guimba Rd., Km.216+000-Km.218+127 w/ exception; Km.221+960-Km.223+278; Km.227+000-Km.227+760;

Km.230+160-Km.231+683.40

03/13/13 I 67.805 300 C 0.413 0.200 0.300 - - - 91.30 *91.30% V. Satisfactory

ROYAL CROWN MONARCH CONSTRUCTION & SUPPLIES

CORPORATION (Formerly: R.C. Miranda Construction Supplies)

9036 Construction of Susuba Bridge along Manila North Road, KO104+712.60 to KO104+737.40 8/5/2014 III 21.319 210 OG 0.400 0.258 0.150 0.023 0.051 0.050 93.20

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page248

Page 249: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

ROYAL CROWN MONARCH CONSTRUCTION & SUPPLIES

CORPORATION (Formerly: R.C. Miranda Construction Supplies)

9036 Rehab./Impv't. of Flood Control Structures in Tarlac 1st LD along Camiling River, Sawat - Bilad Section 8/7/2014 III 21.321 118 C 0.480 0.133 0.300 91.30 91.30%

Very Satisfactory

Royal Crown Monarch Construction & Supplies

Corporation (Formerly: RC Miranda Construction & Supplies)

9036

Road Upgrading (Gravel to Concrete) based on Gravel Road Strategies, Traffic Benchmark for Upgrading to

Paved Road Standard (HDM-4 Project Analysis) (Intermittent Section) Secondary Road: NJR Villa Sur-San

Pedro-Cabua-an-Ysmael Disimungal

8/13/2014 II 45.986 240 C 0.334 0.266 0.150 0.030 0.055 0.050 88.50 88.50% Satisfactory

Royal Sea Bees Construction 30099 Implementation of Various Projects under Package 15 11/17/08 CAR 0.933 120 O 0.241 0.214 0.100 0.030 0.030 0.067 68.20 -

RPParayno Construction 32682Reconst./Replacement of One(1) Unit Std. Single Barrel

RCBC along San Nicolas-Natividad-San Quintin-Umingan-Guimba Rd., Umingan Sect.

03/13/13 I 1.070 198 C 0.473 0.133 0.300 - - - 90.60 *90.60% V. Satisfactory

RR & B FINEST CONSTRUCTION & DEVELOPMENT CORP 14849 Repair of R. C. Platform and Roro Ramp 05/29/15 PPA 22.757 150 C 0.490 0.200 0.300 - - - - *98.95%

Outstanding

RR & B Finest Construction & Development Corp. 14849 Repair of RC Pier Approach 11/8-11/11 PPA 40.170 360 O 0.337 0.300 0.150 0.030 0.064 0.050 93.10 -

RR and B Finest Construction and Development 14849 Repair of R.C. Pier Approach 05/31/12 PPA 41.416 360 C 0.500 0.200 0.300 - - - 100.00 95.86%

V. Satisfactory RR Encabo Construction

Inc./Brostan Construction and Development

Construction of Four(4) Five Storey Low Rise Building and Land Development 08/11/15 NHA 151.207 300 O 0.374 0.265 0.000 0.030 0.051 0.000 71.94 -

RR Ricafort Construction & Supply 14402 Construction of Lateral "A" at Sta. 3+262 Sta 4+256 of Laris 02/27-03/03/12 NIA 17.949 150 O 0.353 0.265 0.150 0.030 0.047 0.050 89.46 -

RRC CONSTRUCTION 24369 Construction of Drainage along Daang Maharlika KO426+800 - KO429+100 with exception 10/24/2014 II 9.709 234 C 0.339 0.200 0.300 - - - 83.90% 83.9%

Satisfactory

RRL Builders 23454 Iloilo City LTFRB Regional Office Development Project 03/19/14 DOTC 4.979 150 C 0.487 0.200 0.300 - - - 98.72 93.85% Outstanding

RRL Builders 23454 Iloilo City LTFRB Regional Office Development Project 07/25/13 DOTC 4.979 150 O 0.354 0.300 0.150 0.015 0.049 0.050 91.80 -

RRL Builders Corp. / WTG Construction & Dev't Corp. (JV) JV-12-091 Construction of Back-up Area with RoRo Ramp on Fill &

Upgrading of Existing Back-up Area 04/12/13 PPA 62.380 360 O 0.394 0.267 0.150 0.030 0.051 0.050 94.20 -

RRL Builders Corp./WTG Construction & Development Corp.

(JV)JV-12-091 Construction of Back-Up Area w/ RoRo Ramp on Fill and

Upgrading of Existing Back-Up Area 02/21/14 PPA 62.380 421 C 0.479 0.200 0.300 - - - 97.90 95.66% Very Satisfactory

RRL Builders Corporation 23454 Iloilo City PCG District Station Development Project 02/14/13 DOTC 10.544 180 O 0.393 0.300 0.150 0.020 0.039 0.033 93.50 -

RRL BUILDERS INCORPORATED 23454 Iloilo City PCG Station Building Project 02/20/14 DOTC 10.544 180 C 0.420 0.200 0.300 - - - 92.00 93.10% Very Satisfactory

RRMD Construction and Supply (Formerly: RRMD Construction) 23615

Rehab./Reconst./Upgrading along Misamis Oriental-Ma. Cristina Bdry. Road Mandulog-Tambo-IIT Section,

Sta.1520+962 - Sta.1524+09406/07/10 X 13.935 120 O 0.378 0.240 0.150 0.030 0.055 0.050 90.30 -

RRMD Construction and Supply (Formerly: RRMD Construction) 23615

Rehab./Reconst./Upgrading along Overton Buru-un Road at Buru-un - Poblacion Section, Sta.1535+067 -

Sta.1535+803.50 w/ exception06/10/10 X 9.284 105 O 0.373 0.240 0.150 0.030 0.055 0.050 89.80 -

RRN Construction 20228 Repair & Rehab. of Rd. from Mamala Bridge to Jct .Nat'l Highway 08/10/12 X 8.753 105 C 0.401 0.200 0.100 - - - 70.10 77.72%

Unsatisfactory

RRN Construction Corporation (Formerly: RNN Construction) 24880 Rehab./Reconst./Upgrading of Damaged Paved Roads (IS)

(K0028+572.50-K0028+996.50) at PPTA Road 08/17/11 NCR 3.566 98 O 0.367 0.300 0.150 0.030 0.050 0.050 94.70 -

RT Builders 33773 Drainage System at Abucay, Daang Maharlika, Barangay Abucay 11/29/12 VIII 4.009 107 O 0.354 0.240 0.150 0.030 0.035 0.033 84.20 -

RT Morabe Construction 11377 BIP No. 11-2011 Construction of Open canal and Canal Structures 09/06/11 NIA 7.071 105 O 0.359 0.258 0.150 0.023 0.057 0.050 89.74 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page249

Page 250: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Ruby-Jade Construction 19202 Rehab. of Lobbot Street 06/06/10 III 4.688 120 O 0.394 0.241 0.150 0.030 0.032 0.033 88.00 -Ruby-Jade Construction 19202 Construction of Brgy. Lobbot Road 03/03/09 III 4.703 150 O 0.329 0.300 0.124 0.023 0.018 0.033 82.70 -

Ruby-Jade Construction 19202 Asphalting of Rd. at Durian St., Mutual Homes, Brgy. Putatan 03/11/13 NCR 2.908 30 C 0.475 0.133 0.300 - - - 90.80 *90.80%

V. SatisfactoryRubylim Construction & Supplies,

Inc. 11685 Impvt. of San Fernando South Road, San Fernando Section 02/17/10 V 11.340 240 O 0.346 0.232 0.150 0.030 0.040 0.033 83.10 -

Rubylim Construction & Supplies, Inc. (Formerly: Ruby Lim Construction & Supplies)

11685Const. of/Repair of Scoured Shoulder/Embankment/Lined

Canal & Riprap along San Fernando North Rd., Km.21+400-Km.28+070 with exception

03/14/13 V 9.506 150 O 0.304 0.220 0.042 0.018 0.010 0.017 61.10 -

Rubylim Construction & Supplies, Inc. (Formerly: Ruby Lim Construction & Supplies)

11685 Rehab./Reconst./Upgrading of P. Florentino St. 03/20/13 NCR 14.406 223 C 0.468 0.097 0.000 - - - 56.50 69.16% Poor

Rubylim Construction & Supplies, Inc. (Formerly: Ruby Lim Construction & Supplies)

11685 Road Upgrading of San Fernando South Rd. (Pinamoghaan Sect.) 08/24/10 V 19.100 170 O 0.292 0.300 0.150 0.020 0.035 0.033 83.00 -

Rudhil Construction & Enterprises Inc. (Formerly: Rudhil Const.) 22901

Rd. Upgrading (Gravel to Paved) Imelda-Bayog Kumalarang-Lapuyan-Margosatubig Rd., Minsulao Sect.,

Km.1762+730-Km.1764+00008/14/13 IX 32.914 225 O 0.310 0.248 0.124 0.030 0.028 0.033 77.30

Rudhil Construction & Enterprises Inc. (Formerly: Rudhil Const.) 22901

Const. of Slope Protection along Dipolog-Punta-Dansullan-Sergio Osmeña Rd., Km.1875+490-Km.1875+560 (due to

Rd. Slip)08/20/13 IX 8.324 90 O 0.319 0.300 0.000 0.020 0.033 0.033 70.50

RUDHIL CONSTRUCTION & ENTERPRISES, INC. 22901

Road Upgrading (Gravel to Paved) based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Rd

Standard (HDM-4 Project Analysis) Intermittent Sect., ZNAC Acccess Road, K1989+(-773) - K1989+(-260)(FY

2014), Z.N.

10/24/2014 IX 12.560 169 C 0.428 0.123 0.300 - - - 85.10% 85.1% Satisfactory

RUDHIL CONSTRUCTION & ENTERPRISES, INC. 22901

Const./Improvement of Access Roads Leading to Declared Tourism Destinations Juction Manukan Town Site Leading

to Libutan Cave10/30/2014 IX 27.929 195 O 0.256 0.297 0.130 0.030 0.045 0.017 77.50% 77.5%

Unsatisfactory

RUDHIL CONSTRUCTION & ENTERPRISES, INC. 22901 Construction of Multi-Purpose Building at Brgy. Candiis,

Malangas 10/25/2014 IX 5.911 158 O 0.296 0.198 0.134 0.030 0.041 0.033 73.20% 73.2% Poor

Rudhil Construction & Enterprises, Inc. (Formerly: Rudhil

Construction)22901

Road Upgrading of (Gravel to Paved) based on Gravel Road Strategies, Traffic Benchmark for Upgrading to

Paved Road Standard (HDM-4 Project Analysis) intermittent Section, ZNAC Access Road K1989+(-773) -

K1989+(-260)(FY 2014)

8/9/2014 IX 12.207 181 OG 0.334 0.300 0.150 0.030 0.050 0.033 89.70

Rudhil Construction & Enterprises, Inc. (Formerly: Rudhil

Construction)22901

Rehab./Reconst./Upgrading of Damaged National Road including Drainage based on (PMS/HDM-4)(Intermittent

Section) Pagadian City-Zamboanga City Road K1662+500 - K1663+500

8/13/2014 IX 13.989 100 C 0.337 0.200 0.300 83.70 83.70% Satisfactory

Rudhil Construction & Enterprises, Inc. (Formerly: Rudhil

Construction)222901 Rehabilitation of Road (Rotunda) along Pagadian-

Zamboanga City Road Sta. 1801+252.90 8/7/2014 IX 11.831 195 OG 0.295 0.300 0.140 0.030 0.051 0.017 83.30

Rudhil Construction & Enterprises, Inc. (Formerly: Rudhil

Construction)22901

Road Upgrading of (Gravel to Paved) Imelda-Bayog-Kumalarag-Lapuyan-Margosatubig Road, Minsulao

Section, K1762+730 to K1764+0008/9/2014 IX 32.912 270 C 0.326 0.200 0.300 82.60 79.42%

Unsatisfactory

Rudhil Construction & Enterprises, Inc. (Formerly: Rudhil

Construction)22901 Rd. Upgrading (Gravel to Conc.) Int. Sect. along Piñan-

Mutia Rd., K1816+192-K1818+(-083) 03/22/13 IX 38.898 144 O 0.360 0.225 0.150 0.030 0.037 0.033 83.50 -

Rusmen Builders & Development Corporation 10674 Rehab./Reconst./Upgrading of Damaged National Road at

Batangas-Lobo Road 05/22/09 IV-A 48.240 180 O 0.384 0.240 0.150 0.030 0.040 0.050 89.40 -

Rusmen Builders & Development Corporation 10674 Rehab./Reconst./Upgrading of Damaged National Roads of

Banay-banay-Cuenca-Mojon Road 05/20/09 IV-A 42.456 120 O 0.392 0.240 0.150 0.030 0.030 0.050 89.20 -

Rusmen Builders & Development Corporation (Formerly: Rusmen

Builders)10674 Prev. Maint. (MFO-1) (Intermittent Sect.) Banay-Banay-

Mojon-Cuenca Rd., K0090+849-K0091+370 03/14/13 IVA 5.790 30 O 0.371 0.240 0.150 0.030 0.055 0.050 89.60 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page250

Page 251: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Rusmen Builders & Development Corporation (Formerly: Rusmen

Builders)10674 Widening of Manila-Batangas-Quezon Rd., Ibaan Sect. (4

lanes) 11/21/12 IVA 28.575 240 C 0.425 0.133 0.300 - - - 85.80 86.67% Satisfactory

Rusmen Builders & Development Corporation (Formerly: Rusmen

Builders)10674 Impvt./Rehab. along Palico-Balayan-Batangas City Road,

K0135+211-K0135+789.00 w/ exception 11/20/12 IVA 9.459 150 C 0.410 0.133 0.300 - - - 84.30 86.10% Satisfactory

Rusmen Builders & Development Corporation (Formerly: Rusmen

Builders)10674 Prev. Maint. (MFO-1) (IS) Daang Maharlika (LZ), K0063+300

K0065+000 08/08/12 IVA 23.348 60 C 0.469 0.133 0.300 - - - 90.20 90.32% V. Satisfactory

Rusmen Builders & Development Corporation (Formerly: Rusmen

Builders)10674 Impvt./Rehab. along Palico-Balayan-Batangas City Rd.,

K0135+211-K0135+789.00 w/ exception 08/09/12 IVA 9.460 120 O 0.375 0.240 0.150 0.030 0.045 0.033 87.30 -

Rusmen Builders & Development Corporation (Formerly: Rusmen

Builders)10674 Widening of Manila-Batangas-Quezon Road, Ibaan Sect. (4

lanes) 08/10/12 IVA 28.575 210 O 0.353 0.240 0.150 0.030 0.047 0.033 85.30 -

Rusmen Builders & Development Corpration (Formerly: Rusmen

Builders)10674 Prev. Maint. (MFO-1) (Int. Sect.) Banay-Banay-Mojon-

Cuenca Rd., K0090+849-K0091+370 08/02/13 IVA 5.790 30 C 0.429 0.139 0.300 - - - 86.80 88.48% Satisfactory

S & CU CONSTRUCTION 13128 Panay Ports Cluster Development Project 11/18/14 DOTC 16.374 180 C 0.397 0.200 0.300 - - - 89.70 *89.70% V. Satisfactory

S & CU CONSTRUCTION 13128 Pontevedra Ports Cluster Development Project 11/19/14 DOTC 12.361 150 C 0.417 0.200 0.300 - - - 91.70 *91.70% V. Satisfactory

S & CU Construction 13128 Pilar Port Cluster Project 05/08/14 DOTC 4.690 90 C 0.408 0.200 0.300 - - - 90.84 *90.84% V. Satisfactory

S and CU CONSTRUCTION 13128 Rehab./Reconst. Of Damaged National Roads, Antequera - San Isidro - Libertad (Tubigon Road) 8/11/2014 VII 16.793 202 C 0.403 0.194 0.300 89.70 88.14%

Satisfactory

S and CU Construction 13128 Rehab./Reconst. of Damaged Nat'l Rds., Antequera-San Isidro-Libertad (Tubigon) Rd., K0031+000-K0032+000 08/19/13 VII 16.793 212 O 0.352 0.251 0.150 0.030 0.055 0.033 87.10

S and CU Construction 13128 Repair of Rd. Slip Cortes-Balilihan-Catigbian-Macaas Rd., Km.43+800-Km.44+134 03/12/13 VII 16.979 225 C 0.467 0.046 0.300 - - - 81.30 86.64%

Satisfactory

S and CU Construction 13128 Const. of School Building, San Jose National High School 09/10/09 VII 1.042 175 O 0.400 0.257 0.150 0.030 0.042 0.033 91.20 -

S and CU Construction 13128 Conc. of Jct. (LIR) Buenavista, Carmen-Danao-Getafe Rd. 03/27/12 VII 13.290 275 C 0.457 0.133 0.300 - - - 89.00 87.50% Satisfactory

S.S.R. Construction 11469 Potable Water System, San Alejandro 11/27/12 III 4.875 180 C 0.421 0.133 0.300 - - - 85.40 87.56% Satisfactory

S.S.R. Construction 11469 Potable Water System, San Alejandro 08/03/12 III 4.875 180 O 0.354 0.300 0.150 0.030 0.023 0.033 89.00 -S.T Hidalgo Construction 22498 Construction of Flood Control, Brgy. Linao 05/28/09 VIII 4.745 90 O 0.310 0.240 0.150 0.022 0.030 0.033 78.50 -S.T Hidalgo Construction 22498 Construction of Flood Control 03/04/09 VIII 4.745 90 O 0.312 0.300 0.150 0.020 0.019 0.033 83.40 -

S.T. Hidalgo Construction 22498 Drainage System at Mahayahay Creek, Brgy. Fatima along Picas, San Jose DZR Airport Rd. 08/22/13 VIII 4.295 107 C 0.401 0.200 0.300 - - - 90.10 *90.10% V.

Satisfactory

Sadlan Construction 33550 Rehab. of Aggoyo River Flood Control, Bontoc Sect. & Samoki, Talubin 08/04/12 CAR 4.495 95 C 0.389 0.200 0.300 - - - 88.90 88.18%

Satisfactory

Safeway Construction 5842 Const./Impv't./Rehab. Of FMR, Brgy. Baritao 08/05/13 I 1.963 60 C 0.479 0.133 0.300 - - - 91.20 86.76% Satisfactory

Safeway Construction & Supply 5842 Const./Impv't./Rehab. of FMR, Brgy. Baritao 03/16/13 I 1.963 60 O 0.357 0.223 0.150 0.030 0.045 0.033 83.80 -

SAGA ENGINEERING 35019 Const./ Concreting of Roads, Brgy. Agusan 10/25/2014 X 4.383 97 C 0.412 0.133 0.300 - - - 84.50% 90.72% Very Satisfactory

SAGA ENGINEERING 35019 Const./Conc. Of Road Brgy. Agusan, Cagayan de Oro City 8/4//14 X 4.383 97 OG 0.389 0.300 0.150 0.030 0.050 0.033 95.20

Saga Engineering 35019 Const./Conc. of Roads, Brgy. Tablon 03/18/13 X 1.969 62 C 0.372 0.200 0.300 - - - 87.20 *87.20% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page251

Page 252: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Saint Bernard Construction 28368

Road Upgrading (Gravel to Paved) of Goa-Digdigon Isidro Road (Tagongtong Section) Original Sta.: K0488+477.37 -

K0489+000.00 with exception, Revised Sta.: K0488+477.32 - K0489+060.00 with exception

8/9/2014 V 10.602 119 C 0.380 0.153 0.300 83.30 83.30% Satisfactory

SAL Construction Help for Catubig Agricultural Advancement Project HCAAP-LMC-C-3 03/15/14 NIA 5.382 405 C 0.464 0.085 0.300 - - - 84.96 84.96%

Satisfactory

SAL Construction 34646 BIP No. 11-2011 Construction of Open canal and Canal Structures 09/06/11 NIA 6.977 105 O 0.360 0.260 0.150 0.023 0.057 0.050 90.00 -

Sammi Construction Company Ltd. FC-05-008 CP IV, Const./Impvt of Looc-Odiongan-San Andres Road Rural Road Network Development Project 05/21/09 RRNDP 646.871 890 O 0.347 0.300 0.074 0.030 0.037 0.050 83.80 -

Sammi Construction Company Ltd. FC-05-008 CP IV, Const./Impvt. of Looc-Odiongan-San Andres Road 08/30/09 RRNDP 698.808 980 O 0.348 0.240 0.149 0.030 0.051 0.033 85.10 -

Sammi Construction Company Ltd. FC-05-008 Contract Package IV, Const./Impvt. of Looc-Odiongan-San Andres Road, Km 101+965.00 - Km. 143+560.68 02/22/10 RRNDP 646.871 750 O 0.359 0.300 0.150 0.030 0.061 0.050 95.00 -

Sammi Construction Company Ltd. FC-05008 CP IV, Const./Impvt. of Looc-Odiongan-San Andres Road 08/29/08 IV-B 649.871 750 O 0.400 0.300 0.050 0.030 0.070 0.067 91.70 -

Sammi Construction Company Ltd. FC-05-008 CP IV, Const./Impvt. of Looc-Odiongan-San Andres Road 11/25/08 IV-B 649.871 750 O 0.365 0.300 0.030 0.030 0.070 0.067 86.20 -

SAMURAI CONSTRUCTION 32214 Construction of Multi-Purpose Building 11/24/2014 IV 1.874 120 C 0.481 0.133 0.300 - - - 91.40% 91.4% Very Satisfactory

Samurai Construction 32214 Const. of MPB,Palawan State University 03/15/13 IVB 2.789 90 O 0.342 0.300 0.030 0.030 0.035 0.017 75.40 -SAN NARCISO BUILDERS

CORPORATION 24527 CONSTRUCTION OF DRAINAGE SYSTEM 02/27/14 DOST 9.049 217 C 0.439 0.200 0.300 - - - 93.90 *93.9% V.Satisfactory

San Narciso Builders Corporation (Formerly: San Narciso Builders) 24527

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. at M. Logarta Rd., Mandaue City, Chainage 0048-Chainage

028203/21/13 VII 3.188 30 C 0.420 0.133 0.300 - - - 85.30 *85.30%

Satisfactory

SANDSTORM CONSTRUCTION 23411 Construction of Alangilan Multi-Purpose Building 12/6/2014 IV 2.495 120 C 0.485 0.133 0.300 - - - 91.80% 91.8% Very Satisfactory

Sanlahi Group of Builders Inc. 11874 Conc. of Calapan North Road (Calapan-Puerto Galera Section) 09/03/09 IVB 48.162 370 O 0.332 0.292 0.150 0.030 0.047 0.033 88.40 -

Sanlahi Group of Builders Inc. 11874 Rehabilitation/Reconstruction of Calapan South Road Section 05/25/09 IV-B 12.544 90 O 0.338 0.286 0.150 0.030 0.055 0.050 90.90 -

Sanlahi Group of Builders Inc. 11874 Conc. of Calapan North Road (Calapan-Puerto Galera Section) 05/24/09 IV-B 48.152 295 O 0.327 0.297 0.150 0.030 0.045 0.033 88.20 -

Sanlahi Group of Builders Inc. 11874 Conc. of Calapan North Road (Calapan-puerto Galera Sec.) 02/25/09 IV-B 48.152 270 O 0.251 0.223 0.150 0.030 0.042 0.050 74.60 -

Sanlahi Group of Builders, Inc./811 Trading & Construction Joint

VentureJV-09-253 Road Upgrading (Gravel to Paved) of Jct. MWCR Labangan-

Murtha-Jct., Iriron Road 08/27/10 IVB 38.600 250 O 0.349 0.046 0.150 0.030 0.030 0.033 63.80 -

Sanrho Builders, Inc./3RB Construction & Supply (JV) JV-13-366 Widening/Improvement of Ligao-Tabaco Road, K0526+000

to K0527+1012 8/4/2014 V 36.424 179 OG 0.354 0.221 0.150 0.022 0.061 0.050 85.80

SANRHO Construction and Supplies 24213 Land Development of Salvation Ressettlement Project 06/21/13 NHA 10.488 150 O 0.392 0.300 0.150 0.020 0.060 0.050 97.16 -

SANRHO Construction and Supplies 24213 Land Development of Salvacion Resettlement Project 06/22/12 NHA 10.488 150 O 0.366 0.300 0.150 0.030 0.050 0.050 94.62 -

Sanrho Construction and Supplies 24213 Deepening of Tagas River (Cobo-Basud Sect.) 08/01/12 V 17.234 135 C 0.330 - 0.500 - - - 83.00 85.58% Satisfactory

Sanrho Construction and Supplies / Ajan Jeada, Inc. (JV) JV-10-188 Const. of MPB (Multi Storey Cityhall Annex Phase I) 08/01/12 V 38.050 300 C 0.450 0.133 0.300 - - - 88.30 90.19%

V. SatisfactorySantech Builders 16797 Impvt. of Kinabutan River Control 11/24/08 XIII 4.765 90 O 0.357 0.200 0.050 0.015 0.035 0.200 85.70 -Santech Builders 16797 Impvt. of Kinabutan River Control 03/09/09 XIII 4.765 331 O 0.347 0.300 0.111 0.030 0.037 0.033 85.80 -

Santech Builders 16797 Conc. of Lake Mainit Circ. Rd. Tagbuyawan-Mansayao Rd. Sect. 09/06/09 XIII 9.143 238 O 0.348 0.233 0.150 0.030 0.055 0.033 84.90 -

Santech Builders 16797 Roadslip along Daang Maharlika Road (Surigao-Ipil-Lipata Road Sect.), Brgy. Lipata 11/21/12 XIII 8.658 195 C 0.421 0.200 0.000 - - - 62.10 74.88%

Poor

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page252

Page 253: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

SARANGANI ROCKMIXER 6549 Widening of Digos-Makar Road, South Cotabato K1631+(-068) to K1632+471, Batomelong Section 8/16/2014 XII 41.682 180 C 0.452 0.189 0.300 94.10 94.10%

Very Satisfactory

Sarangani Rockmixer 6549 Prev. Maint. Nat'l Arterial (Prev. Maint.), Makar-Kiamba Rd., K1660+467-K1662+000 (Int. Sect.), Brgy. Tambler 08/23/13 XII 23.343 70 C 0.429 0.133 0.300 - - - 86.20 *86.20%

Satisfactory

Sarangani Rockmixer 6549 Conc./Widening of Digos-Makar Rd., Km.1624+750-Km.1626+250, Malandag Sect. 08/22/13 XII 33.630 174 C 0.413 0.133 0.300 - - - 84.60 85.68%

Satisfactory

Sarangani Rockmixer 6549 Const. of Lined Canal (Buayan Sect.) along Jct. Digos-Makar-Buayan Rd., Brgy. Buayan 03/23/13 XII 7.762 12 C 0.397 0.157 0.300 - - - 85.40 87.74%

Satisfactory

Sarangani Rockmixer 6549 Conc./Widening of Digos-Makar Rd., Km.1624+750-Km.1626+250 Malandag Sect. 03/21/13 XII 33.630 170 O 0.367 0.229 0.150 0.030 0.055 0.033 86.40 -

Sarangani Rockmixer 6549 Sarangani-Davao del Sur Coastal Road (Malapatan-Glan Section) 06/15/10 XII 14.856 120 O 0.318 0.240 0.150 0.030 0.047 0.050 83.50 -

Sarangani Rockmixer 6549 General Santos City Circ. Rd., Conc. of Sinawal-Apopong Sect., Sta.5+442-Sta.6+942, Brgy. Sinawal-Apopong 08/22/12 XII 18.493 165 C 0.465 0.133 0.300 - - - 89.80 90.28%

V. Satisfactory

Sarca Estate Development Corporation 20520 Rehab./Reconst./Upgrading of MCR (Tigwi-Dampulan-

Lipata-Yook Sect.) Km.87+000-Km.93+245 w/ exception 08/14/12 IVB 46.467 291 C 0.443 0.200 0.300 - - - 94.30 82.30% Satisfactory

Sarca Estate Development Corporation / Bomel Construction

Joint VentureJV-12-470 Widening of Lucena-Tayabas-Lucban Rd., K0143+593.50-

K0145+797, K0137+345-K0137+876 08/08/13 IVA 41.812 120 O 0.337 0.300 0.150 0.030 0.023 0.050 89.00

Sarca Estate Development Corporation / Quezon Victory

Lumber and General Contractor (JV)

JV-10-112 Rehab./Reconst. Of Famy-Real-Infanta-Dinahican Port Road 03/16/12 IVA 33.048 98 C 0.427 0.149 0.300 - - - 87.60 84.48%

Satisfactory

SARCA Estate Development Corporation/Bomel Construciton

(JV)JV-12-470

Widening of Lucena-Tayabas-Lucban Road, Tayabas City, K0143+593.50 to K0145+797 (SectionI) and K0137+345 to

K0137+876 (Section)8/14/2014 IV-A 45.029 240 C 0.325 0.200 0.300 82.50 86.40%

Satisfactory

SAREX BUILDERS 23734

Rehab./Reconst. of Damaged Paved National Roads including Drainage along Sarangani - Davao del Sur

Coastal Road, K1688+850 - K1689+890, Glan, Sarangani Province

10/29/2014 XII 17.889 135 O 0.241 0.240 0.000 0.023 0.061 0.033 59.80% 59.8% Poor

Sarex Builders 23734Replacement/Rehab./Strengthening of Permanent Bridges Gen. from Bridge Mgt. System (BMS), Glan Bridge along

Sarangani-Davao del Sur Coastal Rd.08/20/13 XII 6.930 147 C 0.441 0.133 0.300 - - - 87.40 *87.40%

Satisfactory

Sarex Builders 23734 Rd. Upgrading (Gravel to Paved) Int. Sect. along Sarangani-Davao del Sur Coastal Rd., Km.1713+562-Km.1713+957 08/20/13 XII 8.571 122 C 0.432 0.133 0.300 - - - 86.50 *86.50%

Satisfactory

Sarex Builders 23734 Rehab./Impv't. of Pangyan River Flood Control Structure along Sarangani-Davao del Sur Coastal Rd. 03/22/13 XII 6.613 165 C 0.475 0.133 0.300 - - - 90.80 89.00%

Satisfactory

Sarex Builders 23734 Rehab./Impvt. of DPWH Sarangani DEO Building 06/16/10 XII 4.695 150 O 0.350 0.240 0.074 0.030 0.045 0.033 77.20 -

Sarex Builders 23734 Const. of River Flood Control Structures in Sarangani, Calabanit River 11/27/12 XII 14.693 180 C 0.451 0.200 0.300 - - - 95.10 91.74%

V. Satisfactory

Sarex Builders 23734 Const. of River Flood Control Structures in Sarangani, Calabanit River 08/21/12 XII 14.693 180 O 0.324 0.294 0.150 0.030 0.047 0.050 89.50 -

Sarex Builders / Greco Construction & Supply (JV) JV-12-288 Rd. Upgrading (Gravel to Paved) Int. Sect. along Demoloc-

Little Baguio-Alabel Rd., K1669+725-K1670+520 08/21/13 XII 20.738 155 C 0.433 0.133 0.300 - - - 86.60 87.38% Satisfactory

Sarex Builders / Greco Construction and Supply (JV) JV-12-288

Road Upgrading (Gravel to Paved), Intermittent Sect., along Demoloc-Little Baguio-Alabel Road, K1669+725-

K1670+52003/21/13 XII 20.738 131 O 0.361 0.246 0.150 0.030 0.042 0.050 87.90 -

Sargasso Construction and Development Corp. 6587

Raising/Strengthening of Riverwalls along Malabon River, Catmon Creek & Longos Creek, KAMANAVA, Area Flood

Control & Drainage System Impv't. Proj.03/16/13 KAMANAVA-

PMO 148.853 300 O 0.383 0.225 0.150 0.030 0.048 0.033 86.90 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page253

Page 254: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Sargasso Construction and Development Corp. 6587 Rehab./Reconst./Upgrading of Dr. Damian Reyes Memorial

Road (Torrijos Side), Km.48+300-Km.57+789 w/ exception 08/14/12 IVB 40.970 297 C 0.325 0.200 0.300 - - - 82.50 82.80% Satisfactory

SATRAP Construction Company Inc. 2526

Const./Widening/Upgrading/Rehab. Of Access Road to Airport, Major Seaports and Declared Tourism

Destinations, Widening of Manila North Road, K0406+300, - K0406+000 and K0406+500 - K0408+880, Bantay-San

Idelfonso Section

8/7/2014 I 53.605 258 C 0.433 0.049 0.300 78.20 84.20% Satisfactory

SATRAP Construction Company Inc. 2526 Constructionof Quirino-Panda Bridge along Quirino-Panda

Road 8/6/2014 I 20.746 222 OG 0.350 0.204 0.111 0.030 0.045 0.033 77.30

SATRAP CONSTRUCTION COMPANY, INC. 2526 Asphalt Overlay of Vigan Airport Road, K0408+000 to

K0408+408+692 10/23/2014 I 5.755 22 C 0.399 0.200 0.300 - - - 89.90% 89.9% Very Satisfactory

SATRAP CONSTRUCTION COMPANY, INC. 2526 Asphalt Overlay of Vigan-Caoayan Road, K0408+ (-

012) to K0408+1997 10/23/2014 I 19.630 95 C 0.406 0.152 0.300 - - - 85.80% 85.8% Satisfactory

Satrap Construction Company, Inc. 2526

Const./Widening/Upgrading/Rehab. of Access Rd. to Airport, Major Seaports & Declared Tourism Destination, Widening of Manila North Rd., K0406+300-K0406+000 &

K0408+500-K0408+880, Bantay-San Ildefonso Sect.

08/13/13 I 56.762 210 O 0.336 0.300 0.136 0.030 0.047 0.033 88.20

Satrap Construction Company, Inc. 2526 Replacement of Pantay Daya Bridge along Vigan-Sta.Catalina Rd. 03/20/13 I 18.395 296 C 0.478 0.133 0.300 - - - 91.10 87.89%

Satisfactory

Satrap Construction Company, Inc. 2526 Replacement of Quirino Bridge 03/15/12 I 20.434 550 C 0.401 0.133 0.300 - - - 83.40 84.04% Satisfactory

SBB CONSTRUCTION & SUPPLY 31238 Widening of Davao-Bukidnon Road, (Lomondao Section), Km. 1659+997 - Km. 1661+091 10/20/2014 XI 16.901 162 C 0.422 0.139 0.300 - - - 86.10% 86.1%

Satisfactory

SBB CONSTRUCTION & SUPPLY 31238 Construction and Maintenance of Bridges along National Roads a) Libby Bridge along Davao – Cotabato Old Road 8/16/2014 XI 3.952 70 C 0.369 0.200 0.300 86.90 86.90%

Satisfactory

SBB Construction & Supply 31238 Road Upgrading (Gravel to Paved) of Inawayan-Baracatan Road Km.1539+110-Km.1539+285 08/05/13 XI 3.558 58 C 0.383 0.200 0.300 - - - 88.30 84.22%

Satisfactory

SBB Construction & Supply 31238 Rd. Upgrading (Gravel to Paved) of Inawayan-Baracatan Rd., Km.1539+110-Km.1539+285 03/12/13 XI 3.634 30 O 0.324 0.216 0.150 0.030 0.045 0.050 81.50 -

SBB Construction & Supply 31238 Road Upgrading at Davao Regional Medical Training Center 06/16/10 XI 4.023 88 O 0.388 0.240 0.150 0.030 0.042 0.033 88.30 -

SBB Construction & Supply 31238 Conc. of Road at Brgy. Lizada 03/12/13 XI 1.971 17 C 0.420 0.133 0.300 - - - 85.30 *85.30% Satisfactory

SBB Construction & Supply 31238 Conc. of Sitio Saka FMR, Brgy. Bago Gallera, Talomo District 03/22/13 XI 1.935 22 C 0.394 0.133 0.300 - - - 82.70 *82.70%

Satisfactory

SBF CONSTRUCTION & DEVELOPMENT CORPORATION 11470 Construction of 2-Storey 4-CL & 2-Storey 6-CL School

Building in Oton National High School 8/5/2014 VI 11.363 180 C 0.450 0.200 0.300 95.00 76.03% Unsatisfactory

SBF Construction & Development Corporation 11470 Const. of 2-Storey 4-CL & 2-Storey 6-CL Sch. Bldg. in Oton

NHS 08/14/13 VI 11.246 180 O 0.317 0.202 0.065 0.030 0.032 0.033 67.90

Scion Construction 33680 Construction of Multi Purpose Building, Kinalaglagan 8/9/2014 IV-A 4.427 150 C 0.414 0.200 0.300 91.40 84.89% Satisfactory

Scion Construction 33680 Const. of MPB, Kinalaglagan Mataas na Kahoy 08/01/13 IVA 4.427 150 O 0.341 0.244 0.150 0.030 0.023 0.033 82.10

SCP Construction 8797 Sta. Josefa Pump Irrigation Project 08/30/14 NIA 16.013 364 C 0.376 0.196 0.300 - - - - 87.19% Satisfactory

SCP Construction 8797 Balingasag River Irrigation Project 09/26-27/11 NIA 199.249 465 O 0.339 0.245 0.109 0.024 0.056 0.033 80.62 -

SCP Construction 8797 Rehab./Reconst. of Damaged Paved National Roads along Butuan City-Cagayan de Oro City-Iligan City Road 11/24/08 X 18.867 210 O 0.365 0.240 0.100 0.030 0.035 0.067 83.70 -

SCP Construction 8797 Conc. of SDCR, (Tagasaka-Bislig Subsection) along Hinatuan-Bislig-Boston Section 11/28/08 XIII 158.872 375 O 0.278 0.184 0.100 0.030 0.030 0.100 72.20 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page254

Page 255: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

SCP Construction 8797 Rehab./Reconst. of Damaged Paved National Roads along Butuan City-Cagayan de Oro City-Iligan City Road 03/09/09 X 18.867 234 O 0.327 0.240 0.055 0.030 0.045 0.033 73.00 -

SCP Construction 8797 Conc. of Surigao-Davao Coastal Road (Tagsaka-Bislig Subsection) along Hinatuan-Bislig-Section 06/06/09 XIII 156.872 405 O 0.379 0.300 0.150 0.030 0.061 0.050 97.00 -

SCP Construction 8797 Conc. of Surigao-Davao Coastal Rd.(Tagsaka-Bislig Subsection) along Hinatuan-Bislig-Boston Sect. 09/10/09 XIII 156.872 433 O 0.378 0.238 0.130 0.030 0.060 0.033 86.90 -

SCP Construction 8797 Const. of Jct. Sayre Highway-Aglayan-Alanib-Ticalaan Road, Ticalaan-Paganan Sect. 11/20/12 X 95.328 375 O 0.245 0.208 0.000 0.020 0.012 0.000 48.50 -

SCP Construction 8797 Rd. Upgrading (Gravel to Paved) of Gingoog-Claveria-Villanueva Rd. 11/21/12 X 24.513 531 O 0.191 0.204 0.000 0.020 0.012 0.000 42.70 -

SCP Construction 8797 Const. of Jct. Sayre Highway-Aglayan-Alanib-Ticalaan Rd., Ticalaan-Paganan Sect. 08/11/12 X 95.330 375 O 0.071 0.180 0.000 0.020 0.008 0.017 29.60 -

SCP Construction 8797 Rd. Upgrading (Gravel to Paved) of Gingoog-Claveria-Villanueva Rd. 08/07/12 X 24.513 531 O 0.038 0.180 0.000 0.020 0.000 0.017 25.50 -

SCP Construction Balingasag River Irrigation Project 03/27/12 NIA 199.249 585 O 0.334 0.256 0.150 0.030 0.056 0.033 85.96 -

SCP Construction 8797 Conc. of Surigao-davao Coastal Rd. (Tagasaka-Bislig Subsection) along Hinatuan-Bislig-Boston Section) 03/06/10 XIII 156.872 555 O 0.231 0.300 0.071 0.030 0.047 0.050 72.90 -

Settlers Builder 21643 Replacement/Const. of Bongsod Bridge, Km. 105+650.50, Brgy. Bongsod 08/15/13 VI 11.889 178 O 0.354 0.300 0.004 0.030 0.033 0.033 75.40

Settlers Builder 21643 Const. of 2-CL Bldg. at Apgahan Elem. School 02/25/10 VI 0.888 80 O 0.352 0.300 0.150 0.000 0.022 0.033 85.70 -Settlers Builder 21643 Replacement/Const. of Guinbanga-an Bridge 11/22/12 VI 16.186 290 O 0.308 0.275 0.128 0.030 0.055 0.033 82.90 -

Settlers Builder 21643 Conc. Of Hamtic-Bia-an-Egaña-Sibalom Rd., Km.97+097-Km.98+524 (w/ exception) 08/15/12 VI 15.229 180 C 0.447 0.200 0.300 - - - 94.70 82.28%

Satisfactory

Seven Digit Construction & Supplies 25471 Puerto Princesa North Road (PPNR) Junction Taytay

Poblacion Road (Const. of Drainage and Sidewalk) 06/03/09 IV-B 10.443 233 O 0.321 0.300 0.100 0.030 0.035 0.033 81.90 -

Seven Digit Construction & Supplies 25471 Const. of MPB, Brgy. San Isidro 03/15/12 IVB 0.949 82 C 0.476 0.200 0.300 - - - 97.60 91.51%

V. SatisfactorySeven Digit Construction &

Supplies 25471 Const. of Sibaltan Bridge I Flood Control Structures along El Nido-Jct. New Ibajay Road, Km.314+171 03/16/12 IVB 8.162 137 O 0.366 0.288 0.150 0.010 0.030 0.033 87.70 -

Seven Digit Construction & Supplies 25471 Const. of Sibaltan Bridge I Flood Control Structures along

El Nido-Jct., New Ibajay Rd., Km.314+171 08/04/12 IVB 8.162 137 O 0.286 0.133 0.300 - - - 71.90 81.38% Unsatisfactory

Seven Digit Construction & Supplies 25471 Repair/Maint. of Mayturong River Control Abangan 03/12/13 IVB 1.407 66 C 0.424 0.200 0.300 - - - 92.40 *92.40%

V. Satisfactory

SEVEN DIGIT CONSTRUCTION & SUPPLIES                  25471

Construction of Drainage/Slope Protection Works along Puerto Princesa North Road (Intermittent) Langogan-

Roxas Road Section11/20/2014 IV 18.130 136 C 0.441 0.133 0.300 - - - 87.40% 87.4%

Satisfactory

SEVEN DIGIT CONSTRUCTION & SUPPLIES                  25471

Construction of Drainage/Slope Protection Works along Puerto Princesa Princesa North Road (Intermittent) Roxas-

Taytay Road Section11/20/2014 IV 17.875 181 C 0.391 0.133 0.300 - - - 82.40% 82.4%

Satisfactory

Shak Construction and Supply 28289Const. of Shore Protection/Seawalls along Guimaras Circ. Rd., Brgy. Canhawan-Cabalagnan, (K0077+100-K0077+280)

w/ exception08/05/13 VI 4.455 112 C 0.444 0.133 0.300 - - - 87.70 *87.70%

Satisfactory

Shak Construction and Supply 28289 Const. of Sch. Bldg. at CapSU Burias Extension 08/19/13 VI 4.850 90 C 0.438 0.133 0.300 - - - 87.10 *87.10% Satisfactory

Shak Construction and Supply 28289 Repair/Rehab. of Road Poblacion 04/05/11 VI 4.986 90 O 0.350 0.237 0.150 0.030 0.037 0.033 83.70 -

Shak Construction and Supply 28289 Preventive Maint. of Balasan-Carles Rd. 03/22/12 VI 9.582 90 C 0.415 0.200 0.300 - - - 91.50 86.52% Satisfactory

Shak Construction and Supply 28289 Construction of ITO SUR SWIP 08/31/13 NIA 5.191 127 C 0.339 0.240 0.150 0.025 0.056 0.050 86.03 -

SHEAR CONSTRUCTION AND SUPPLY 34027 Construction of Brgy. Road, Brgy. Cotmo and Brgy.

Tagpocol to Pinamasagan 11/10/2014 V 7.304 120 C 0.423 0.133 0.300 - - - 85.60% 85.6% Satisfactory

Sheen-Sheen Construction 29015 Rehab. of CCR, Maac-Kalipagas Section 03/07/09 X 9.536 197 O 0.360 0.240 0.150 0.030 0.040 0.033 85.30 -

Sheen-Sheen Construction 20915 Impvt./Const. of Road leading to St. Peter's Village (Vicente Reyes) Sitio Lamok, Benoni 09/05/09 X 1.733 110 O 0.383 0.300 0.000 0.030 0.051 0.017 78.10 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page255

Page 256: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Silk & Steel Construction 25314 Const. of MPB at Brgy.Alang-Alang 09/06/10 VIII 4.785 244 O 0.368 0.240 0.150 0.030 0.018 0.033 83.90 -

Silver Dragon Const. & Lumber & Glass Supply 30835 Rehab./Reconst. Of Bago-Ma-ao-La Carlota Road,

Sta.4+898.50 - Sta.5+405.50 w/ exception (Burcoz Sect.) 03/30/12 VI 8.685 60 C 0.424 0.200 0.300 - - - 92.40 86.94% Satisfactory

Silver Dragon Construction & Lumber & Glass Supply 30835

Impv't./Widening of Bacolod-Murcia-D.S. Benedicto-San Carlos City Rd., K0053+860-K0086+000 (K0052+735-

K0056+583), Don Salvador Benedicto08/13/13 VI 47.454 240 C 0.396 0.133 0.300 - - - 82.90 *82.90%

Satisfactory

Silver Dragon Construction & Lumber & Glass Supply 30835

Rehab./Restoration/Upgrading of Damaged Paved Nat'l Rds., along Bacolod North Nat'l Rd., K0146+549 -

K0157+500 (w/ exceptions)10/31/13 VI 78.159 260 C 0.452 0.133 0.300 - - - 88.50 *88.50%

Satisfactory

Silver Dragon Construction & Lumber & Glass Supply 30835 Const./Conc. of Bago-Ma-ao Pacol FMR, Sta. 0+873-

01+680; Sta. 0+203-0+336 08/11/13 VI 12.570 70 C 0.423 0.133 0.300 - - - 85.60 *85.60% Satisfactory

Silver Dragon Construction & Lumber & Glass Supply 30835 Conc. of Brgy. Cabug, FMR, Brgy. Cabug 08/06/13 VI 8.060 60 C 0.402 0.133 0.300 - - - 83.50 *83.50%

SatisfactorySilver Dragon Construction &

Lumber & Glass Supply 30835 Repair/Rehab. of Orong Revetment Wall, Sta. 0+000-Sta. 0+072, Brgy. Orong 08/08/13 VI 2.982 102 C 0.414 0.133 0.300 - - - 84.70 86.08%

Satisfactory

Silver Dragon Construction & Lumber & Glass Supply 30835

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. (Int. Sect.) Bacolod South Nat'l Arterial Rd. (By-Pass Rd.),

K0020+029.50-K0020+685.5008/11/13 VI 12.295 106 C 0.395 0.133 0.300 - - - 82.80 85.92%

Satisfactory

Silver Dragon Construction & Lumber & Glass Supply 30835

Const. of Flood Control Structure along Bago River Across Bacolod South Nat'l Arterial Rd., Sta. 0+136.12-Sta. 0+360,

Bantayan Sect.08/11/13 VI 15.492 133 O 0.300 0.300 0.150 0.023 0.035 0.050 85.80

Silver Dragon Construction & Lumber & Glass Supply 30835 Repair/Rehab./Impv't. of Iloilo-Capiz Rd. (New Route),

Roxas Ave., Km.114+800-Km.115+535 w/ exception 08/18/13 VI 9.132 75 O 0.339 0.240 0.150 0.030 0.050 0.033 84.20

Silver Dragon Construction & Lumber & Glass Supply 30835 Road Upgrading (Gravel to Paved) (Int. Sect.) Bago-

Mambucal Nat'l Sec. Rd., K0058+688.00-K0059+616 08/11/13 VI 21.198 244 O 0.330 0.237 0.150 0.030 0.042 0.050 83.90

SILVER DRAGON CONSTRUCTION & LUMBER & GLASS SUPPLY 30835 Widening of Arterial Road in Bacolod South Road,

K0006+969 - K0008+462 with exception 10/27/2014 VI 35.431 150 C 0.449 0.133 0.300 - - - 88.20% 88.2% Satisfactory

SILVER DRAGON CONSTRUCTION & LUMBER & GLASS SUPPLY 30835

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Road (Intermittent Section), Bacolod South

Road, Section I (Valladolid Section): K0028+840 - K0031+620, Section II (San Enrique Section): K0034+503 -

K0035+490

10/27/2014 VI 70.095 275 C 0.435 0.133 0.300 - - - 86.80% 86.8% Satisfactory

SILVER DRAGON CONSTRUCTION & LUMBER & GLASS SUPPLY 30835

Assets Preservation of National Roads Generated from Pavement Management System/Highway Development and

Management - 4 (HDM-4), Rehabilitation/Reconstruction/Upgrading of Damaged

Paved National Road, (Intermittent Sections), K0025+(-165) - K0026+422, Bago-Mambucal Road

10/22/2014 VI 23.540 125 C 0.461 0.133 0.300 - - - 89.40% 89.4% Very Satisfactory

SILVER DRAGON CONSTRUCTION & LUMBER & GLASS SUPPLY 30835

Repair/Rehab./Impv't. of Iloilo-Capiz Road (New Route) Roxas Ave., Roxas City, Km. 14+800 - Km. 115+535 with

exception8/14/2014 VI 9.991 125 C 0.349 0.200 0.300 84.90 84.48%

Satisfactory

SILVER DRAGON CONSTRUCTION & LUMBER & GLASS SUPPLY 30835

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies Traffic Benchmark for Upgrading to Paved Road

Standard (HDM-4) Project Analysis (Intemittent Section) Bago-Mambucal National Secondary Road K0058+688 -

K0059+616

8/7/2014 VI 21.198 250 C 0.400 0.200 0.300 90.00 86.64% Satisfactory

SILVER DRAGON CONSTRUCTION & LUMBER & GLASS SUPPLY 30835

Const. of Flood Control Structure along Bago River across Bacolod South National Arterial Road, Sta. 0+136.12 - Sta.

0+360 Bantayan Section8/7/2014 VI 15.492 133 C 0.377 0.200 0.300 87.70 86.56%

Satisfactory

Silver Dragon Construction & Lumber & Glass Supply 30835

Rehab./Reconst./Upgrading of Damaged Paved Nat'l. Rd. (Int. Sect.) Bacolod South Nat'l. Arterial Rd. (By-Pass

Road) K0020+029.50-K0020+685.5003/14/13 VI 12.295 75 O 0.322 0.300 0.150 0.018 0.040 0.050 88.00 -

Silver Dragon Construction & Lumber & Glass Supply 30835 Repair/Rehab. of Orong Revetment Wall, Sta.0+000-

Sta.0+072, Brgy. Orong 03/13/13 VI 2.982 102 O 0.375 0.300 0.088 0.024 0.050 0.033 87.00 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page256

Page 257: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Silver Dragon Construction & Lumber & Glass Supply 30835 Rehab./Reblocking of Bacolod Circumferential Rd. from

Brgy. Pahanocoy to Brgy. Banago Sect. w/ exception 06/07/10 VI 38.198 275 O 0.326 0.240 0.150 0.030 0.051 0.033 83.00 -

Sixteen Enterprises - Calapan Branch 18187

Rehabilitation/Reconstruction/Upgrading of Damaged Paved Road, Pinamalayan Airport Road, Gloria Section

(K0077+130 - K0079+006 w/ Exception)8/12/2014 IV-B 18.546 144 OG 0.366 0.236 0.150 0.030 0.045 0.033 86.00

Sixteen Enterprises - Calapan Branch 18187 Widening (Paving of Shoulder) - Seal Widening of Calapan

South Road K005+415 - K007+187 (Intermittent Section) 8/11/2014 IV-B 16.541 121 C 0.415 0.133 0.300 84.80 84.80% Satisfactory

Sixteen Enterprises - Calapan Branch 18187 Replacement/Rehabilitation/Strengthening of Babangonan

Bridge, CSR Junction Minas, K0036+370 8/11/2014 IV-B 12.850 201 C 0.439 0.132 0.300 87.10 85.96% Satisfactory

Sixteen Enterprises - Calapan Branch 18187 Const. of Bongabong Flood Control (Aplaya Sect.) 07/31/13 IVB 18.189 174 C 0.439 0.147 0.300 - - - 88.60 86.92%

SatisfactorySixteen Enterprises - Calapan

Branch 18187 Const. of Bongabong Seawall (Aplaya Sect.) 07/31/13 IVB 18.004 144 C 0.417 0.143 0.300 - - - 86.00 86.42% Satisfactory

Sixteen Enterprises - Calapan Branch 18187 Const. of Bansud River Control 07/31/13 IVB 9.098 150 C 0.380 0.200 0.300 - - - 88.00 85.30%

SatisfactorySixteen Enterprises - Calapan

Branch 18187 Replacement/Rehab./Strengthening of Babangonan Bridge, CSR Jct. Minas, K0036+370 08/01/13 IVB 12.851 180 O 0.352 0.238 0.150 0.020 0.042 0.050 85.20

Sixteen Enterprises - Calapan Branch 18187 Completion of Calapan South Road, Tuklong-San Roque

Section 09/05/09 IVB 38.110 238 O 0.378 0.240 0.150 0.030 0.051 0.050 89.90 -

Sixteen Enterprises - Calapan Branch 18187 Rehab. (Reconst. of PCCP) CSR Jct. Minas Rd. (K0035+(-

654)-K0036+000) 03/17/12 IVB 29.095 216 C 0.442 0.133 0.300 - - - 87.50 88.58% Satisfactory

Sixteen Enterprises / Lumel Glenn Construction (JV) JV-12-086 Impv't./Conc. of Calapan South Rd., Maligaya-Narra Sect.

(K0075+849-K0079+233) (w/ exception) 07/31/13 IVB 43.028 228 C 0.429 0.140 0.300 - - - 86.90 87.05% Satisfactory

Sixteen Enterprises / Lumel Glenn Construction (JV) JV-11-086 Impv't./Conc. of Calapan South Rd., Maligaya-Narra Sect.,

(K0075+849-K0079+233 w/ exception) 03/20/13 IVB 41.343 198 O 0.362 0.240 0.150 0.030 0.045 0.033 86.00 -

Sixteen Enterprises / Lumel Glenn Construction Joint Venture JV-11-086 Impvt./Conc. of Calapan South Rd., Maligaya-Narra Sect.

(K0075+849-K00791+233 w/ exception) 11/27/12 IVB 41.343 183 O 0.367 0.236 0.150 0.030 0.050 0.050 88.30 -

Sixteen Enterprises / Thunderheads Const. (JV) JV-08-302 Completion of Calapan South Road, Nasucob Section 09/05/09 IVB 19.060 224 O 0.359 0.245 0.150 0.030 0.051 0.050 88.50 -

Sixteen Enterprises / Thunderheads Construction Corp.

Joint VentureJV-11-097 Const. of Orconuma Upstream Flood Control, Bongabong

(Upstream of Abutment "B") 08/09/12 IVB 18.040 201 C 0.407 0.133 0.300 - - - 84.00 83.70% Satisfactory

Sixteen Enterprises/Alberto Uy Construction & Development Joint

VentureJV-10-176 Impvt./Conc. of Calapan South Road Nabuslot Sect. 08/07/12 IVB 19.205 158 C 0.449 0.200 0.224 - - - 87.30 84.18%

Satisfactory

SIXTEEN ENTERPRISES‐CALAPAN BRANCH 18187 Concreting of Calapan South Road, K0161+000-K0161+901 11/27/2014 IV 14.337 189 C 0.449 0.133 0.300 - - - 88.20% 88.2%

Satisfactory

SIXTEEN ENTERPRISES‐CALAPAN BRANCH 18187 Construction of Bubuli River Control 11/28/2014 IV 9.193 78 C 0.493 0.133 0.300 - - - 92.60% 92.6%

Very SatisfactorySIXTEEN ENTERPRISES‐CALAPAN 

BRANCH 18187 Concreting & Rehabilitation of Local Road-Manganngan I 11/28/2014 IV 9.278 60 C 0.426 0.133 0.300 - - - 85.90% 85.9% Satisfactory

Sixteen Enterprises-Calapan Branch 18187 Const. of Sumagui River Control along Calapan South Rd.,

Brgy. Sumagui 03/20/13 IVB 14.770 198 C 0.362 0.200 0.300 - - - 86.20 87.76% Satisfactory

Sixteen Enterprises-Calapan Branch 18187 Const. of Bongabong Seawall (Aplaya Sect.) 03/20/13 IVB 18.004 144 O 0.368 0.241 0.150 0.030 0.045 0.033 86.70 -

Sixteen Enterprises-Calapan Branch 18187 Const. of Bongabong Flood Control (Aplaya Sect.) 03/20/13 IVB 18.189 144 O 0.347 0.243 0.150 0.030 0.055 0.033 85.80 -

Sixteen Enterprises-Calapan Branch 18187 Const. of Bansud River Control 03/20/13 IVB 9.098 150 O 0.272 0.300 0.150 0.030 0.050 0.033 83.50 -

Sixteen Enterprises-Calapan Branch 18187 Road Upgrading (Gravel to Concrete) CSR Jct. Minas Rd.

K0048+135-K0049+701 11/27/12 IVB 25.044 190 C 0.440 0.191 0.300 - - - 93.10 86.02% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page257

Page 258: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Sixteen Enterprises-Calapan Branch 18187 Conc. of Mindoro Or./Occ. East Coastal Rd., San Miguel

Sect. 08/08/12 IVB 41.348 252 C 0.412 0.133 0.300 - - - 84.50 85.10% Satisfactory

Sixteen Enterprises-Calapan Branch 18187 Road Upgrading (Gravel to Concrete) CSR Jct. Minas Road

K0048+135-K0049+701 08/06/12 IVB 25.044 180 O 0.238 0.300 0.150 0.030 0.031 0.050 79.90 -

SIXTEEN ENTERPRISES‐CALAPAN BRANCH/L.N. SALVADOR CONSTRUCTION (JV)                   

JV-13-410 Rehab./Reconst./Upgrading of Damaged Paved National Roads at Calapan South Road Mansalay and Bulalacao 11/27/2014 IV 36.615 240 C 0.468 0.133 0.300 - - - 90.10% 90.1%

Very Satisfactory

SJ Bonifacio Builders 32226

Prev. Maint. along Jct. Dumalinao-Margosatubig Nat'l Sec. Rd., ZDS (Asphalt Overlay, 50mm) K1719+000-K1719+794 Realigned to K1714+823-K1715+305, Lumbog, Vicencio

Sagun

08/16/13 IX 4.679 44 C 0.313 0.200 0.300 - - - 81.30 82.62% Satisfactory

SJ Bonifacio Builders 32226

Prev. Maint. along Jct. Dumalinao-Margosatubig Nat'l. Secondary Rd., ZDS (Asphalt Overlay, 50mm) K1714+000-K1719+794 Realigned to K1714+823-K1715+305, Lumbog-

Margosatubig

03/19/13 IX 4.679 44 O 0.375 0.200 0.150 0.030 0.030 0.050 83.50 -

SJ Bonifacio Builders 32226Prev. Maint. along Pagadian City-Zamboanga City Nat'l

Arterial Rd. (Reblocking w/ overlay, 0.50mm) K1677+840-K1678+081

03/19/13 IX 2.859 58 C 0.471 0.200 0.000 - - - 67.10 64.88% Poor

SJ Bonifacio Builders 32226Prev. Maint. along Pagadian City-Zamboanga City Nat'l

Arterial Rd. (Reblocking w/ Overlay, 0.500mm) K1677+840-K1678+081

08/16/12 IX 2.859 58 O 0.336 0.200 0.000 0.030 0.035 0.033 63.40 -

Slver Dragon Construction & Lumber & Glass Supply 30835 Rd. Upgrading (Gravel to Paved) (Int. Sect.), Bago-

Mambucal Nat'l. Secondary Rd., K0058+688-K0059+616 03/14/13 VI 19.585 112 O 0.289 0.300 0.150 0.015 0.045 0.050 84.90 -

SMT CONSTRUCTION 36331 Construction of Multi-Purpose Building @ Matusalem 10/25/2014 II 2.877 90 C 0.443 0.133 0.300 - - - 87.60% 87.6% Satisfactory

SMT Construction 36331 Construction of Multi-Purpose Building at San Felipe 8/8/2014 II 2.970 79 OG 0.293 0.276 0.150 0.030 0.047 0.050 84.60

So Construction 17714 Repair/Rehab./Impv't. of Nat'l Rd., Baler-Cemento Rd., K0231+500-K0238+000 w/ exceptions 08/10/13 III 10.000 152 O 0.354 0.240 0.150 0.030 0.050 0.033 85.70

So Construction 17714 Repair/Rehab./Impvt. of Baler-Casiguran Rd., Km. 236+600-Km. 243+000 w/ exceptions 11/28/12 III 9.450 165 C 0.346 0.200 0.300 - - - 84.60 85.50%

Satisfactory

So Construction 17714 Reconst. of Dinadiawan Bridge Approach "B", Baler-Casiguran Rd, Km. 286+828 07/31/12 III 3.395 100 C 0.412 0.200 0.300 - - - 91.20 91.56% V.

Satisfactory

So Construction 17714 Repair/Rehab./Impvt. of Baler-Casiguran Rd., Km. 236+600-Km. 243+000 w/ exceptions 07/31/12 III 9.450 165 O 0.378 0.300 0.075 0.030 0.045 0.033 86.10 -

SOCOR CONSTRUCTION CORPORATION 8020

Preventive Maintenance Based on Pavement Management System/Highway Development and Management-4 (HDM-4)

National Secondary Road, Governor Cuenco Ave.: a.)K0005+(-768) - K0005+000 and b.)K0005+000 -

K0005+392

10/20/2014 VII 28.993 140 C 0.440 0.138 0.300 - - - 87.80% 87.8% Satisfactory

SOCOR CONSTRUCTION CORPORATION 8020

Preventive Maintenance of Catarman - Laoang Road KO746+535 - KO747+100, KO756+572 - KO756+1002; KO759+000 - Ko759+539; KO759+728 - KO764+520

8/13/2014 VIII 38.704 410 C 0.424 0.200 0.300 92.40 82.14% Satisfactory

Socor Construction Corporation 8020Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. (Int. Sect.), Secondary Rd., Cebu Circ. Rd. (Katipunan St.),

Chainage 0000-Chainage 0995 08/24/13 VII 27.983 75 C 0.395 0.137 0.300 - - - 83.20 *83.20%

Satisfactory

Socor Construction Corporation 8020 Impv't. of Catarman Diversion Rd. K0742+(-360)-K0743+025 & K0743+025-K0743+085 08/10/13 VIII 15.123 61 C 0.396 0.200 0.300 - - - 89.60 88.82%

Satisfactory

Socor Construction Corporation 8020Prev. Maint. of Catarman-Laoang Rd., K0746+535-K0747+100, K0756+572- K0756+1002; K0759+000-

K0759+539; K0759+728-K0764+53008/10/13 VIII 38.704 200 O 0.330 0.300 0.000 0.030 0.060 0.033 75.30

Socor Construction Corporation 8020 Rehab. of A. Cortes Ave. 03/16/13 VII 22.001 180 C 0.465 0.200 0.300 - - - 96.50 90.44% V. Satisfactory

Socor Construction Corporation 8020 Road Upgrading (Gravel to Paved), Jct. Sayre Hwy.-Manolo Fortich-Libona-Indahag Rd. San Miguel (Miranda) Sect. 11/20/12 X 35.742 270 C 0.480 0.133 0.300 - - - 91.30 89.74%

V. Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page258

Page 259: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Socor Construction Corporation 8020Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. along Natalio Bacalso Ave. (Cebu South Rd.) K0082+200-

K0084+20008/17/12 VII 32.014 119 C 0.465 0.133 0.300 - - - 89.80 88.78%

Satisfactory

Socor Construction Corporation 8020 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. along Santander-Barili-Toledo Rd., K0162+217-K0162+687 03/18/13 VII 8.840 60 C 0.450 0.200 0.300 - - - 95.00 *95.00%

V. Satisfactory

Socor Construction Corporation 8020 (Asphalt Overlay) along Butuan-Cagayan de Oro-Iligan Rd. (Agusan-Misamis Oriental), Km.1267+000-Km.1267+516.52 03/12/13 XIII 6.488 25 C 0.385 0.200 0.300 - - - 88.50 *88.50%

Satisfactory

Socor Construction Corporation 8020 Cagayan de Oro Airport Development Project 06/27/13 DOTC 7.413 30 C 0.450 0.200 0.300 - - - 95.00 *95.00% V. Satisfactory

Socor Construction Corpration 8020 Impv't. of Catarman Diversion Rd. 1, K0742+(-360)-K0743+025 & K0743+025-K0743+085 03/20/13 VIII 15.123 61 O 0.308 0.300 0.150 0.030 0.045 0.050 88.30 -

Solfio P. Jacinto ConstructionPackage X-C: Construction of lateral "N" (Sta. 6+640-Sta. 9+600) including related structures and supply, delivery

and installation of steel gates02/07/15 NIA 32.396 180 O 0.315 0.282 0.150 0.030 0.014 0.050 84.10 -

Solid M Construction 33991 Calbiga Irrigation Project 11/22/14 NIA 26.963 240 C 0.454 0.200 0.300 - - - 95.39 *95.39% V. Satisfactory

SOLID M Construction Help for Catubig Agricultural Advancement Project HCAAP-LCB-C1-2012 03/15/14 NIA 17.747 300 C 0.481 0.064 0.300 - - - 84.43 84.43%

Satisfactory

Solid Rock Construction 8958 Const. of Don Mariano Marcos Ave. Ext. Proj. under Metro Manila Urban Transport Integration Proj. (MMURTIP) 08/16/13 URPO -

PMO 69.995 542 C 0.346 0.133 0.300 - - - 77.90 87.68% Satisfactory

Solid Rock Construction 8958Const. of Don Mariano Marcos Ave., Ext. Project under

Metro-Manila Urban Transport Integration Project (MMURTIP)

04/02/11 URPO 65.898 285 O 0.357 0.300 0.145 0.030 0.060 0.050 94.20 -

Solid Rock Construction 8958 Conc. of Congressional Ave. Ext. (Phase II) 09/14/09 NCR 28.754 210 O 0.341 0.244 0.150 0.023 0.050 0.050 85.80 -

Solid Rock Corporation 8958 Impvt./Widening of C.P. Garcia Ave., (Sta.13+93 -Sta.14+685) 03/19/13 NCR 16.653 303 C 0.433 0.133 0.300 - - - 86.60 82.64%

Satisfactory

Soy Eng Construction 15533 Const. of MPB (Gym) Phase 8 at Jose Rizal Memorial State University 03/28/12 IX 4.342 90 C 0.394 0.200 0.300 - - - 89.40 91.15%

V. Satisfactory

Soy Eng Construction 15533 Repair/Maint. of River Control Structures at Polanco River Control & Sianib River Control 03/28/12 IX 1.303 100 C 0.405 0.200 0.300 - - - 90.50 84.98%

SatisfactorySoy Eng Construction / L.C.

Construction (JV) JV-12-233 Rd. Upgrading (Gravel to Conc.) Int. Sect. along Piñan-Mutia Rd., K1824+(-458)-K1825+232 03/22/13 IX 9.498 61 O 0.333 0.287 0.150 0.030 0.040 0.033 87.30 -

Soy Eng Construction / L.C. Construction(JV) JV-12-233 Rd. Upgrading (Gravel to Conc.) Int. Sect. along Piñan-

Mutia Rd., K1824+(-458)-K1825+232 08/20/13 IX 9.498 121 O 0.280 0.287 0.000 0.030 0.042 0.033 67.20

SPECO BUILDERS INC. (Formerly: VRF Construction) 15301 Road Upgrading (Gravel to Paved) along Nueva Ecija -

Aurora Road 8/8/2014 III 103.357 360 OG 0.380 0.240 0.150 0.012 0.052 0.050 88.40

SPECO BUILDERS, INC. 15301Rehabilitation/Reconstruction of Damaged Paved National

Roads including Drainage of Nueva Ecija - Pangasinan Road

11/27/2014 III 16.435 90 C 0.451 0.133 0.300 - - - 88.40% 88.4% Satisfactory

Speco Builders, Inc. 15301 Construction of Drainage Canal along Bongabon - Rizal - Aurora Road (Rizal Section) KO 153+464 to KO 153+1372 9/25/2014 Special 3 18.141 150 C 0.415 0.133 0.300 84.80 84.80%

Satisfactory

Speco Builders, Inc. 15301 Preventive Maintenance of Nueva Ecija - Pangasinan Road 9/24/2014 Special 3 30.755 90 OG 0.387 0.200 0.150 0.030 0.035 0.033 83.50

SPJ CONSTRUCTION 12584 Improvement of Lateral G-3, LTRIS 05/23/15 NIA 6.127 210 C 0.397 0.200 0.300 - - - - *89.74% V. Satisfactory

SPJ CONSTRUCTION 12584 Canal Structure and Steel Gates 05/23/15 NIA 1.817 120 O 0.375 0.200 0.000 0.030 0.070 0.050 72.48 -

Spring Star Construction & Supply 20240 Const. of MPB Annex 34, Brgy. Don Bosco 08/09/13 NCR 3.871 90 C 0.470 0.133 0.300 - - - 90.30 *90.30% V. Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page259

Page 260: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Spring Star Construction & Supply 20240 Const. of Calzada Tipas Bridge 02/24/10 NCR 14.399 308 O 0.313 0.208 0.150 0.022 0.037 0.033 76.30 -

SPRING STAR CONSTRUCTION AND SUPPLY 20240 Upgrading of Box Culvert along villanueva Creek

Tributaries, UPS 5, Camella, Barangay San Isidro 11/18/2014 NCR 6.059 240 C 0.435 0.133 0.300 - - - 86.80% 86.8% Satisfactory

Square Cube Const. (Formerly: Square Cube Trading Division & Const Division-Mandaue Branch)

25120 Jct. Osmeña-Pilar Road (Osmeña-Maasin-Mabini Section) 08/12/11 XIII 22.824 270 O 0.361 0.225 0.130 0.023 0.043 0.050 83.20 -

Square Cube Const. (Formerly: Square Cube Trading Division &

Const. Division-Mandaue Branch)25120 Ubay Flood Control 03/13/13 VII 3.667 157 O 0.347 0.240 0.150 0.030 0.035 0.033 83.50 -

SQUARE CUBE CONSTRUCTION 25120 Construction of Two (2) Storey Six (6) Classroom School Building at Maslog National High School 8/8/2014 VII 6.457 159 C 0.465 0.158 0.300 92.30 87.82%

SatisfactorySquare Cube Construction 25120 New Bohol (Panglao) Airport Development Project 05/22/14 DOTC 49.358 240 O 0.377 0.300 0.150 0.030 0.032 0.050 93.89 -

Square Cube Construction 25120Const./Completion of On-going Bridges (inc. approaches)

at Lower Pakigne Bridge along Natalio Bacalso Ave., Phase 8

08/18/12 VII 37.440 270 O 0.327 0.240 0.150 0.030 0.055 0.050 85.20 -

Square Cube Construction 25120 Const. of San Roque Bridge, San Roque 11/24/12 VIII 15.821 190 C 0.393 0.148 0.300 - - - 84.10 84.64% Satisfactory

Square Cube Construction 25120 Rehab./Reconst. Of Damaged Paved Nat'l Rd. (Km.1135+071-Km.1135+817) Tomas Oppus St. 08/20/12 VIII 4.010 167 C 0.421 0.133 0.300 - - - 85.40 86.78%

Satisfactory

Square Cube Construction 25120 Bayongan Capayas IS Improvement Project 07/13/13 NIA 4.909 140 C 0.334 0.200 0.300 - - - 83.40 *83.40% satisfactory

Square Cube Construction 25120 Const. of San Roque Bridge 08/20/12 VIII 15.821 190 O 0.363 0.217 0.150 0.030 0.040 0.050 85.00 -

Square Cube Construction (Formerly: Square Cube Trading

Division & Construction Division-Mandaue Branch)

25120Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. at Canduman-Cebu North Rd. a)K0012+586-K0013+194;

b)K0012+(-1250)-K0012+(-1141)08/12/13 VII 12.509 75 C 0.342 0.200 0.300 - - - 84.20 *84.20%

Satisfactory

Square Cube Construction (Formerly: Square Cube Trading

Division & Construction Division-Mandaue Branch)

25120 Const. of Flood Control at Barili Bridge 08/07/13 VII 16.296 203 O 0.373 0.241 0.150 0.030 0.050 0.033 87.70

Square Cube Construction (Formerly: Square Cube Trading

Division & Construction Division-Mandaue Branch)

25120Const./Completion of On-going Bridges (inc. approaches) at Lower Pakigne Bridge along Natalio Bacalso Ave. Phase

808/05/13 VII 34.444 300 C 0.398 0.187 0.300 - - - 88.50 86.52%

Satisfactory

Square Cube Construction (Formerly: Square Cube Trading

Division & Construction Division-Mandaue Branch)

25120 Const. of 2 Storey 6CL SB at Maslog NHS 08/14/13 VII 6.457 159 O 0.359 0.240 0.150 0.030 0.047 0.033 85.90

Square Cube Construction (Formerly: Square Cube Trading

Division & Construction Division-Mandaue Branch)

25120 Ubay Flood Control 08/19/13 VII 3.667 157 C 0.428 0.133 0.300 - - - 86.10 84.54% Satisfactory

Square Cube Construction (Formerly: Square Cube Trading

Division & Construction Division-Mandaue Branch)

25120 Strengthening of Agas-Agas Bridge along Daang Maharlika 08/06/13 VIII 17.317 156 C 0.469 0.133 0.300 - - - 90.20 87.08% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page260

Page 261: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Square Cube Construction (Formerly: Square Cube Trading

Division & Construction Division-Mandaue Branch)

25120 Const. of Maasin Flood Control along Tomas Opus Street (Nat'l Rd.) 08/07/13 VIII 39.502 270 O 0.371 0.240 0.150 0.006 0.047 0.050 86.40

Square Cube Construction (Formerly: Square Cube Trading

Division & Construction Division-Mandaue Branch)

25120 Const. of Baybay Diversion Road, Sta. 0+000-Sta. 5+346.67, w/ exceptions 08/05/13 VIII 90.663 310 O 0.376 0.198 0.150 0.018 0.051 0.050 84.30

Square Cube Construction (Formerly: Square Cube Trading

Division & Construction Division-Mandaue Branch)

25120 Repair/Rehab. Of Slope/Seawall Protection, Pob. Motiong 08/16/13 VIII 15.146 90 C 0.391 0.200 0.300 - - - 89.10 85.26% Satisfactory

Square Cube Construction (Formerly: Square Cube Trading &

Construction Division-Mandaue Branch)

25120 Const. of Maasin Seawall 06/07/10 VIII 19.102 300 O 0.343 0.300 0.150 0.030 0.037 0.050 91.00 -

Square Cube Construction (Formerly: Square Cube Trading &

Construction Division-Mandaue Branch)

25120 Road Upgrading (Gravel to Paved ) at Davao-Cotabato Old Road National Roads Davao-Cotabato at Libby Sect. 06/16/10 XI 19.300 113 O 0.363 0.240 0.150 0.030 0.047 0.050 88.00 -

Square Cube Construction (Formerly: Square Cube Trading &

Construction Division-Mandaue Branch)

25120 Dapa-Del Carmen Road 02/26/10 XIII 16.570 266 O 0.383 0.240 0.114 0.030 0.047 0.033 84.70 -

Square Cube Construction (Formerly: Square Cube Trading &

Construction Division-Mandaue Branch)

25120 Jct. Cancohoy-Del Carmen Rd. 02/26/10 XIII 16.735 266 O 0.361 0.240 0.109 0.030 0.047 0.033 82.00 -

Square Cube Construction (Formerly: Square Cube Trading &

Construction Division-Mandaue Branch)

25120 Const. of One (1) Unit 1 CL Standard/Modified Sch. Bldg. at Kagay E/S 09/05/09 VII 0.626 110 O 0.366 0.240 0.150 0.030 0.035 0.050 87.10 -

Square Cube Construction (Formerly: Square Cube Trading &

Construction Division-Mandaue Branch)

25120 Const. of One (1) Unit 2-CL Standard / Modified School Building at Kagay E/S 09/05/09 VII 0.626 110 O 0.348 0.240 0.150 0.030 0.035 0.050 85.30 -

Square Cube Construction (Formerly: Square Cube Trading &

Construction Division-Mandaue Branch)

25120 Const. of One (1) Unit-2CL Standard / Modified School Building at Nangka E/S 09/04/09 VII 1.254 109 O 0.303 0.214 0.150 0.030 0.023 0.050 77.00 -

Square Cube Construction (Formerly: Square Cube Trading &

Construction Division-Mandaue Branch)

25120 Road Upgrading, Junction Himay-angan-Silago-Abuyog Road 09/04/10 VIII 36.700 300 O 0.340 0.236 0.148 0.030 0.047 0.033 83.40 -

Square Cube Construction (Formerly: Square Cube Trading &

Construction Division-Mandaue Branch)

25120 Road Upgrading (Gravel to Paved) of Kananga-Tungonan Hot Spring Road 08/31/10 VIII 18.225 254 O 0.366 0.239 0.150 0.030 0.042 0.033 86.00 -

Square Cube Construction (Formerly: Square Cube Trading &

Construction Division-Mandaue Branch)

25120 Construction/Improvement of San Ricardo-Bil-atan Road 05/26/09 VIII 19.087 200 O 0.335 0.251 0.150 0.030 0.047 0.050 86.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page261

Page 262: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Square Cube Construction (Formerly: Square Cube Trading &

Construction Division-Mandaue Branch)

25120 Road Upgrading (Gravel to Paved) Ormoc-Lake Imelda Road 05/30/09 VIII 18.230 225 O 0.297 0.257 0.150 0.030 0.037 0.050 82.10 -

Square Cube Construction (Formerly: Square Cube Trading &

Construction Division-Mandaue Branch)

25120 Road Upgrading (Gravel to Paved) Kananga-Tungonan Hot Spring Road, Brgy. Rizal Road Section, 05/30/09 VIII 12.755 180 O 0.241 0.300 0.150 0.030 0.042 0.050 81.30 -

Square Cube Construction (Formerly: Square Cube Trading &

Construction Division-Mandaue Branch)

25120 Rehab./Reconst./Upgrading of Damaged Paved National Road, Ormoc-Baybay, Southern Leyte Boundary Road 09/06/09 VIII 15.501 249 O 0.357 0.300 0.150 0.015 0.035 0.050 90.70 -

Square Cube Construction (Formerly: Square Cube Trading

Division & Const. Division-Mandaue Branch)

25120

Preventive Maint. along Bdry. So. Leyte-Maasin-Macrohon-Sogod-Daang Maharlika, Km.1139+021-Km.1139+570 &

Preventive Maint. along Tomas Oppus St., Km.1135+081-Km.1135+071.9

08/17/11 VIII 6.200 150 O 0.370 0.300 0.150 0.030 0.030 0.033 91.30 -

Square Cube Construction (Formerly: Square Cube Trading

Division & Const. Division-Mandaue Branch)

25120 Jct. Osmeña-Pilar Rd (Sta.4+571.70-Sta.5+771.7) 08/13/12 XIII 16.258 210 C 0.444 0.133 0.300 - - - 87.70 85.90% Satisfactory

SQUARE CUBE CONSTRUCTION (Formerly: Square Cube Trading Division 

& Construction Division ‐ Mandaue Branch)

25120 Construction of Carcar Road (Improvement of Drainage System), Phase V 10/24/2014 VII 41.408 237 O 0.260 0.300 0.150 0.022 0.042 0.050 82.40% 82.4%

Satisfactory

SQUARE CUBE CONSTRUCTION (Formerly: Square Cube Trading Division 

& Construction Division ‐ Mandaue Branch)

25120 Construction/Rehabilitation of Flood Mitigation Facilities along Principal Rivers, Hijo River 10/24/2014 XI 11.267 99 O 0.232 0.261 0.150 0.020 0.040 0.033 73.60% 73.6%

Poor

SQUARE CUBE CONSTRUCTION (Formerly: Square Cube Trading Division 

& Construction Division ‐ Mandaue Branch)

25120

GAA - San Agustin - New Balanban Road, leading to Tagum Botanical Park and Bird Park, Tagum City, Davao del Norte (Road Upgrading (Gravel to Concrete) of San Agustin-ew Balanban Road leading to Tagum Botanical

Park and Bird Park)

10/24/2014 XI 46.282 209 O 0.208 0.208 0.046 0.024 0.030 0.017 53.30% 53.3% Poor

SQUARE CUBE CONSTRUCTION (Formerly: Square Cube Trading

Division & Construction Division - Mandaue Branch)

25120 Construction of Flood Control at Barili Bridge 8/6/2014 VII 16.296 150 C 0.425 0.133 0.300 85.80 86.94% Satisfactory

Square Cube Construction (Formerly: Square Cube Trading Division & Construction Division

Mandaue Branch)

25120 Const./Replacement of Olivo Bridge 03/24/12 VII 18.774 200 O 0.359 0.240 0.150 0.030 0.042 0.033 85.40 -

Square Cube Construction (Formerly: Square Cube Trading Division & Construction Division

Mandaue Branch)

25120Rehab./Reconst. of Damaged Paved Nat'l Rds. along Cebu North Hagnaya Wharf Road (IS) Sect. 1 (K0044+0-K0046+0), Sect. 2 (K0047+900-K0048+0), Sect. 3 (K0052+58-K0054+0)

03/30/12 VII 29.694 195 C 0.344 0.200 0.300 - - - 84.40 83.68% Satisfactory

SQUARE CUBE CONSTRUCTION (Formerly: Square Cube Trading

Division & Construction Division) - Mandaue Branch

25120 Construction of Baybay Diversion Road, Sta.0+000 - Sta.5+346.67 with exception 8/6/2014 VIII 82.533 370 C 0.401 0.133 0.300 83.40 83.40%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page262

Page 263: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

SQUARE CUBE CONSTRUCTION (Formerly: Square Cube Trading

Division & Construction Division) - Mandaue Branch

25120 Const. of Maasin Flood Control along Tomas Oppus Street (National Road) 8/5/2014 VIII 39.502 300 C 0.429 0.184 0.300 91.30 86.02%

Satisfactory

SQUARE CUBE CONSTRUCTION (Formerly: Square Cube Trading Division 

& Construction Division‐Mandaue Branch)

25120 Completion of Flood Protection Works along Daang Maharlika 10/25/2014 VIII 21.468 150 O 0.371 0.240 0.150 0.023 0.029 0.050 86.30% 86.3%

Satisfactory

Square Cube Construction (Formerly: Square Cube Trading

Division & Construction Division-Mandaue Branch)

25120 Rehab./Widening of Existing Pvmt. along Pagadian City-Zamboanga City Rd. w/ exceptions K1675+(-031) 08/16/13 IX 37.801 255 O 0.325 0.288 0.150 0.018 0.033 0.033 84.70 -

Square Cube Construction (Formerly: Square Cube Trading

Division & Construction Division-Mandaue Branch)

25120 Strengthening of Agas-Agas Bridge along Daang Maharlika 03/16/13 VIII 17.086 126 O 0.280 0.300 0.150 0.030 0.040 0.050 85.00 -

Square Cube Construction (Formerly: Square Cube Trading

Division & Construction Division-Mandaue Branch)

25120 Repair/Rehab. of Slope/Seawall Protection, Pob. Motiong 03/18/13 VIII 15.631 210 O 0.367 0.225 0.150 0.023 0.029 0.033 82.70 -

Square Cube Construction (Formerly: Square Cube Trading

Division & Construction Division-Mandaue Branch)

25120 Const. of Maasin Flood Control along Tomas Oppus Street (Nat'l. Rd.) 03/16/13 VIII 37.525 193 O 0.320 0.225 0.150 0.030 0.050 0.050 82.50 -

Square Cube Construction (Formerly: Square Cube Trading

Division & Construction Division-Mandaue Branch)

25120 Road Upgrading (Gravel to Paved) Jct. Himay-angan-Silago-Abuyog Bdry. Rd., Km.1129+700-Km.1130+740 03/28/12 VIII 12.721 330 C 0.358 0.133 0.300 - - - 79.10 84.02%

Satisfactory

SQUARE CUBE CONSTRUCTION (Formerly: Square Cube Trading

Division and Construction Division -Mandaue Branch)

25120 Asphalt Overlay of E. Rodriguez Sr. Avenue, K0009+(-526) (J. Jimenez St.) to K0010+609 (Aurora Blvd.) 8/15/2014 NCR 14.423 40 C 0.452 0.133 0.300 88.50 88.50%

Satisfactory

Square Cube Construction (Formerly: Squared Cube Trading Division & Construction Division-

Mandaue Branch)

25120 Rehab./Widening of Existing Pavement along Pagadian City Road with exceptions K1675+(-031) - K1677+432.27 8/13/2014 IX 39.402 400 C 0.288 0.200 0.300 78.80 85.34%

Satisfactory

SQUARE CUBE CONSTRUCTION//QM BUILDERS

(JV)JV-13-291 Construction of Drainage Systemalong Cebu North

Hagnaya Wharf Road 8/8/2014 VII 17.479 210 OG 0.356 0.270 0.150 0.030 0.051 0.050 90.70

ST. BERNARDINE CONSTRUCTION & ENTERPRISES (Formerly: St.

Bernardine Construction)18474

Proposed Construction/Rehabilitation and Additional Manholes along Taft Ave. (SB) from Quirino Ave. To

Remedios St.11/20/2014 NCR 6.074 120 C 0.479 0.133 0.300 - - - 91.20% 91.2%

Very Satisfactory

ST. BERNARDINE CONSTRUCTION & ENTERPRISES (Formerly: St.

Bernardine Construction)18474 Construction/Improvement of Drainage System along

Tigaon-Goa-San Jose-Lagonoy Road 11/13/2014 V 7.287 106 C 0.485 0.133 0.300 - - - 91.80% 91.8% Very Satisfactory

St. Bernardine Construction & Enterprises (Formerly: St. Bernardine Construction)

18474 Const. of Two (2)-Classroom, One-Storey School Building at Sagrada Elementary School 8/6/2014 V 1.141 160 C 0.357 0.200 0.300 85.70 89.55%

Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page263

Page 264: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

St. Bernardine Construction & Enterprises (Formerly: St. Bernardine Construction)

18474 Construction/Rehabilitation of Canaman Flood Control, San Vicente-Del Rosario Creek 8/8/2014 V 13.264 174 OG 0.366 0.300 0.000 0.020 0.051 0.033 77.00

St. Bernardine Construction & Enterprises (Formerly: St. Bernardine Construction)

18474 Const. of Two (2) Cl One-Storey Sch. Bldg., Sagrada Elem. Sch. 08/03/13 V 1.141 150 O 0.344 0.300 0.150 0.030 0.055 0.033 91.20

St. Ramund Construction, Inc. 19242 Road Upgrading/Conc. Of Jct.-D.S. Benedicto-Spur 16-Calatrava Road, K0055+394-K0056+115 03/27/12 VI 14.255 170 C 0.410 0.183 0.300 - - - 89.30 86.06%

SatisfactoryST. RAYMUND CONSTRUCTION,

INC. 19242 Upgrading/Concreting (From Asphalt to Concrete) along Bacolod North Road, K0026+050 - K0026+537 10/21/2014 VI 8.119 116 C 0.441 0.133 0.300 - - - 87.40% 87.4%

Satisfactory

St. Raymund Construction, Inc. 19242 Conc. of Bacolod South Road, Pook Section Brgy. Pook 04/01/11 VI 9.388 150 O 0.373 0.240 0.150 0.030 0.033 0.033 85.90 -

St. Raymund Construction, Inc. 19242 Const. of Flood Control / River Bank Protection at Canmoros-Nabuswang River Brgy. Canmoros 06/03/10 VI 9.335 190 O 0.280 0.300 0.150 0.030 0.047 0.033 84.00 -

ST.GERRARD CONSTRUCTION 31762 Rehabilitation of Drainage System M.H. Del Pilar Street, Brgy. Maysilo 11/21/2014 NCR 12.516 150 O 0.351 0.258 0.150 0.030 0.030 0.050 86.90% 86.9%

SatisfactorySta Cruz Construction and General

Services 32289 Repair of Damaged Rock Causeway 03/19/15 PPA 22.373 C 0.408 0.200 0.300 - - - - *90.77% V. Satisfactory

Sta. Cruz Construction 9301 Construction/Rehabilitation/Improvement of Flood Control at San Isidro 8/8/2014 V 4.495 125 C 0.343 0.200 0.300 84.30 84.30%

SatisfactorySta. Cruz Construction and General

Services 32289 Construction of Diversion Works, Gabion Protection Works and Canal System for Manolo CIS 02/14/15 NIA 9.347 150 C 0.413 0.128 0.300 - - - 84.12 *84.12%

SatisfactorySta. Cruz Construction and General

Services 32289 Repair & Maint. Of Service Road and Perimeter Lighting System at Phase II 02/01/13 PPA 24.771 148 O 0.399 0.300 0.150 0.030 0.055 0.050 98.40 -

Sta. Cruz Construction and General Services 32289 Repair & Maint. Of Service Road and Perimeter Lighting

System at Phase II 04/25/13 PPA 26.735 175 C 0.480 0.200 0.300 - - - 98.04 98.26% Outstanding

STAR WILLIAM CONSTRUCTION 35938 Desilting of Nangka River 8/7/2014 NCR 3.546 60 C 0.404 0.000 0.500 90.40 90.40% Very Satisfactory

STAY CONSTRUCTION 23323

Road Upgrading (Gravel to Paved) along Acop-Kapangan-Kibungan-Bakun Road, K0326+935 - K 0328+000 (Kibungan

to Sinipsip Section), K0328+(-085) - K0328+653 (To Poblacion, Bakun Section)

11/21/2014 CAR 64.899 240 O 0.348 0.240 0.150 0.030 0.055 0.050 87.30% 87.3% Satisfactory

Stay Construction 23323 Repair & Rehab. along Kennon Road 05/19/09 CAR 6.454 200 O 0.304 0.291 0.150 0.010 0.032 0.033 82.00 -Stay Construction 23323 Concreting of Acop-Kapangan-Kibungan Road 05/21/09 CAR 19.168 180 O 0.297 0.300 0.065 0.010 0.025 0.033 73.00 -Stay Construction 23323 Concreting along Baguio-Bua-Itogon Road 08/26/09 CAR 12.720 200 O 0.384 0.240 0.150 0.030 0.051 0.033 88.80 -

Stay Construction 23323 Conc. of Acop-Kapangan-Kibungan Road Km. 263+000- Km. 266+700 (v.s.) 08/26/09 CAR 19.168 229 O 0.356 0.240 0.150 0.015 0.042 0.033 83.60 -

Stay Construction 23323 Rehab. of Benguet National Road 08/25/09 CAR 4.718 200 O 0.379 0.194 0.067 0.015 0.042 0.017 71.40 -Stay Construction/Vymeah

Construction (JV) JV-08-036 Const. of Tabuk-Tanudan-Banaue Road, Banaue Section 05/25/09 CAR 19.126 284 O 0.361 0.145 0.100 0.015 0.040 0.033 69.40 -

Steel City Fabricators Corporation 27035 Const./Rehab./Replacement, Completion/Repair Kalasungay E/S 09/02/09 X 6.486 75 O 0.318 0.037 0.150 0.030 0.047 0.033 61.50 -

Steelite Construction Corporation 33846 Impvt. of Kambal Road, Barangay Guitnang Bayan 1 & 11 03/14/12 IVA 4.820 150 C 0.485 0.133 0.300 - - - 91.80 87.06% Satisfactory

Stellar Builders 35031 Construction of Vista Alegre CIP 08/31/13 NIA 2.626 120 O 0.381 0.240 0.150 0.015 0.023 0.050 85.93 -

STEVEN CONSTRUCTION & SUPPLY 21987 Construction of Flood Control System, Bolo-Pawa River 11/6/2014 V 14.100 140 C 0.477 0.123 0.300 - - - 90.00% 90% Very Satisfactory

STEVEN CONSTRUCTION & SUPPLY 21987Rehabilitation/Reconstruction of Critical Sections along

National Roads, Road Slip along Sta. Fe-Pastrana-Dagami Road, Km.0939+560, Brgy. San Benito

10/29/2014 VIII 9.001 115 C 0.420 0.133 0.300 - - - 85.30% 85.3% Satisfactory

Steven Construction & Supply 21987 Rd. Upgrading (Gravel to Paved) Banquerohan-Bariis-Sogoy-Sorsogon Bdry. Rd. 08/11/13 V 9.485 111 C 0.384 0.152 0.300 - - - 83.60 *83.60%

Satisfactory

Steven Construction & Supply 21987 Cluster II Const. of Nine (9) Units One Storey, One (1) CL, Modified Type Sch. Bldg. (7 x 9), Brgy. Tinabanan PS 08/16/13 VIII 0.646 180 C 0.403 0.122 0.300 - - - 82.50 *82.50%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page264

Page 265: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Steven Construction & Supply 21987 Rehab. of All Weather FMR at Brgy. Carrideo-Brgy. Manapao 08/03/12 V 4.483 120 C 0.444 0.133 0.300 - - - 87.70 88.36%

Satisfactory

Steven Construction & Supply 21987 Conc. of Brgy. Paco-Brgy. Nato FMR 08/03/12 V 2.113 120 C 0.451 0.133 0.300 - - - 88.40 88.04% Satisfactory

STO. CRISTO CONSTRUCTION AND TRADING(Formerly: Sto.

Cristo Construction)26096 Construction/Improvement of Bagac - Mariveles Road,

Mariveles Section 11/27/2014 III 9.357 90 C 0.411 0.127 0.300 - - - 83.80% 83.8% Satisfactory

Sto. Nino Construction 4867 Concreting of Jct. Tubod-Lakewood Road, Sta. 1701+818.70-Km. 1710+320 (with exceptions) 06/02/09 IX 68.948 508 O 0.378 0.240 0.150 0.030 0.047 0.050 89.50 -

Sto. Nino Construction 4867 Concreting of Lanao-Pagadian-Zamboanga City Road, Pagadian-Dumalinao (Intermittent Section) 06/05/09 IX 27.850 413 O 0.359 0.240 0.150 0.030 0.047 0.050 87.60 -

Sto. Nino Construction 4867 Road Upgrading (Gravel to Concrete) Dipolog-Punta-Dansullan-Sergio Osmeña 06/10/09 IX 15.259 210 O 0.367 0.240 0.150 0.030 0.037 0.050 87.40 -

Sto. Nino Construction 4867 Construction of River Control, Salug Diut River 05/05/09 IX 9.310 420 O 0.374 0.240 0.150 0.010 0.042 0.050 86.60 -

Sto. Nino Construction 4867 Construction of Flood Control Projects along Dipolo River 06/05/09 IX 9.285 180 O 0.356 0.240 0.150 0.010 0.042 0.050 84.80 -

Sto. Nino Construction 4867 Impvt./Concrete Paving of Ilmelda-Alicia Road, Naga-naga Section, Sta. 1767+380-Sta. 1767+764 05/30/09 IX 10.491 160 O 0.326 0.240 0.150 0.030 0.042 0.050 83.80 -

Sto. Nino Construction 4867 Conc. of Jct. Blancia-Molave-Josefina Road (Molave-Mahayag Section) 03/12/09 IX 18.550 348 O 0.372 0.244 0.150 0.030 0.035 0.050 88.10 -

Sto. Nino Construction 4867 Const. of River Control @ Salug Diut River 03/12/09 IX 9.310 340 O 0.382 0.240 0.150 0.030 0.035 0.050 88.70 -

Sto. Nino Construction 4867 Rehab./Reconst./Upgrading of Pagadian City Wharf Road 09/11/09 IX 13.938 203 O 0.345 0.300 0.150 0.023 0.035 0.033 88.60 -

Sto. Nino Construction 4867 Road Upgrading (Gravel to Concrete) Dipolog-Punta-Dansullan-Sergio Osmeña 09/17/09 IX 15.259 210 O 0.329 0.300 0.150 0.030 0.040 0.033 88.20 -

Sto. Nino Construction 4867 Conc. of Jct. Blancia-Molave-Josefina Road (Molave-Mahayag Section) 08/29/08 IX 18.550 150 O 0.237 0.223 0.100 0.030 0.042 0.100 73.20 -

Sto. Nino Construction 4867 Conc. of Jct. Blancia-Molave-Josefina Road (Molave-Mahayag Section) 11/29/08 IX 18.550 150 O 0.340 0.220 0.100 0.030 0.030 0.100 82.00 -

Sto. Nino Construction 4867 Const. of River Control @ Salug River 08/29/08 IX 9.310 150 O 0.272 0.120 0.100 0.030 0.035 0.200 75.70 -

Sto. Nino Construction 4867 Impvt./Conc. Paving of Imelda-Alicia Road, (Phase III), Guintolan Section 08/22/08 IX 33.916 320 O 0.295 0.235 0.100 0.030 0.042 0.100 80.20 -

Sto. Nino Construction 4867 Rehab. of Oroquieta City-Calamba Mt. Road 11/29/08 X 15.675 150 O 0.373 0.260 0.000 0.023 0.038 0.067 76.10 -

STONELINE CONSTRUCTION 33707 MALITUBOG IRRIGATION PROJECT MIP-LMC-005 Package II 06/06/14 NIA 25.918 330 C 0.392 0.200 0.300 - - - 89.24 *89.24%

V. Satisfactory

Stoneline Construction (Formerly: Abubakar Engineering Exponent) 13132 Rehab./Impv't. of Rd. at SK Pendatun Ave. 03/15/13 XII 1.460 50 C 0.462 0.133 0.300 - - - 89.50 *89.50%

V. Satisfactory

STRONGLANE CONSTRUCTION & TRADING 32333 Repair of Cagnipa Flood Control Structure 8/11/2014 VIII 2.996 75 C 0.441 0.133 0.178 75.20 83.36%

SatisfactorySTRONGLANE CONSTRUCTION &

TRADING 32333 Repair of Minlawaan Flood Control Structure 8/13/2014 VIII 2.992 75 C 0.378 0.200 0.173 75.10 83.32% Satisfactory

Stronglane Construction & Trading 32333 Repair of Cagnipa Flood Control Structure, Brgy. Canipa 08/13/13 VIII 2.996 75 O 0.380 0.235 0.150 0.030 0.060 0.033 88.80

Stronglane Construction & Trading 32333 Repair of Minlawaan Flood Control Structure, Brgy. San Policarpio 08/13/13 VIII 2.992 75 O 0.360 0.245 0.150 0.030 0.055 0.033 87.30

Stronglane Construction and Trading 32333 Bonotbonot Small River Impounding Project 07/13/13 NIA 4.526 120 O 0.340 0.300 0.000 0.020 0.060 0.030 75.00 -

STRUCKTURA TEKNIKA SERVICES, CO. 16648 Construction of Three (3) Storey , Six (6) Classroom

School Building at San Juan National High School 8/7/2014 NCR 8.243 270 C 0.410 0.133 0.300 84.30 85.21% Satisfactory

Struktura Teknika Services Co./Three W Builders, Inc. JV Construction of Six (6) 5-Storey Residential Buildings 08/05/14 NHA 197.730 360 O 0.369 0.271 0.150 0.023 0.023 0.050 88.63 -

STRUKTURA TEKNIKA SERVICES COMPANY 16646 Rehabilitation of Drainage System along Northbay

Boulevard 11/21/2014 NCR 10.168 155 O 0.360 0.300 0.090 0.015 0.035 0.033 83.30% 83.3% Satisfactory

Struktura Teknika Services Company 16646 Const./Repair/Rehab. of MPB at EP Quarter, Phil. Air Force

San Fernando Air Base 07/29/13 IVA 10.000 180 C 0.492 0.133 0.300 - - - 92.50 *92.50% V. Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page265

Page 266: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Struktura Teknika Services Company 16646 Const. of Three (3) Storey, Six (6) Cl Sch. Bldg. at San

Juan NHS 08/06/13 NCR 8.243 270 O 0.362 0.240 0.150 0.030 0.041 0.033 85.60

Struktura Teknika Services Company 16646 Rehab. of Rds. along Union St., Brgy San Jose (Pob) 08/12/13 NCR 6.205 138 C 0.455 0.133 0.300 - - - 88.80 85.38%

SatisfactoryStruktura Teknika Services

Company 16646 Rehab. of Rd.s along Union St., Brgy. San Jose (Pob.) 03/15/13 NCR 6.206 121 O 0.387 0.209 0.150 0.022 0.030 0.033 83.10 -

Struktura Teknika Services Company 16646 Const. of MPB, Northbay Boulevard South 03/17/12 NCR 4.820 118 C 0.372 0.200 0.300 - - - 87.20 89.93%

V. SatisfactoryStruktura Teknika Services

Company 16646 Const./Completion of Two (2) Storey, Ten (10) Classroom @ Bagumbayan E/S 03/15/13 NCR 4.116 120 C 0.434 0.097 0.300 - - - 83.10 *83.10%

Satisfactory

STX ENTERPRISES 21547

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road Standard (HDM-4 Project Analysis Intermittent

Section) Secondary Road, Crossing MWCR (Labangan)- Murtha- Jct. Iriron Road

11/27/2014 IV 42.505 299 O 0.371 0.287 0.112 0.030 0.032 0.033 86.50% 86.5% Satisfactory

STX ENTERPRISES 21547

Road Upgrading (Gravel to Paved) Based on Gravel Riad Strategies, Traffic benchmark for Upgrading to Paved Road Standard (HDM-4 Project Analysis Intermittent)

Secondary, Crossing MWCR (Pola)- Casague Jct. Alacak Road, K0378+900-K0379+891.45, K0380+090-K0381+500

11/25/2014 IV 38.191 299 O 0.349 0.286 0.150 0.020 0.038 0.033 87.60% 87.6% Satisfactory

STX Enterprises 21547

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road Standards (HDM-4 Project Analysis), Secondary

Road, Jct. MWCR (Pola) - Casague Jct. Alacaak Road, Sta. 378+900 - 379+891.45, Sta. 0380+090 - 381+500

8/14/2014 IV-B 35.939 209 OG 0.368 0.236 0.140 0.030 0.035 0.033 84.20

STX Enterprises 24547 Prev. Maint. (Int. Sec.) CSR Jct. Pola, K0069+000-K0071+000, K0072+000-K0072+895 08/01/13 IVB 18.044 120 C 0.427 0.133 0.300 - - - 86.00 83.90%

Satisfactory

STX Enterprises 21547 Prev. Maint. (Int. Sect.) CSR Jct. Pola, K0069+000-K0071+000, K0072+000-K0072+895 03/19/13 IVB 18.044 120 O 0.355 0.207 0.150 0.030 0.050 0.033 82.50 -

STX Enterprises 21547 Repair/Maintenance of Macator River Control 03/19/13 IVB 1.427 50 C 0.452 0.133 0.300 - - - 88.50 *88.50% Satisfactory

STX Enterprises 21547 Repair/Maint. of Alcate River Control 03/19/13 IVB 1.059 30 C 0.443 0.133 0.300 - - - 87.60 *87.60% Satisfactory

STX Enterprises / Northern Builders (JV) JV-08-234 Conc. of Calapan South Road 09/02/09 IVB 162.022 270 O 0.318 0.300 0.150 0.030 0.051 0.033 88.20 -

STX Enterprises / Northern Builders (JV) JV-08-234 Concreting of Calapan South Road 02/15/10 IVB 162.920 270 O 0.327 0.300 0.150 0.030 0.054 0.033 89.40 -

Subcon Corporation 25079 Const. of Classroom Bldg. at Sta.Rita H/S 05/30/10 III 2.340 90 O 0.367 0.214 0.150 0.030 0.021 0.033 81.50 -

Subiccon Construction 25079 2014 Heavy Maintenance Works Along SCTEX-Asphalt Resurfacing 08/14/14 BCDA 68.470 120 O 0.349 0.300 0.150 0.030 0.048 0.050 92.70 -

Subiccon Construction 25079 2014 Heavy Maintenace Works Along SCTEX - Asphalt Resurfacing 11/07/14 BCDA 68.470 120 O 0.349 0.300 0.150 0.030 0.048 0.050 92.70 -

Subiccon Construction 25079 2014 Heavy Maintenace Works Along SCTEX - Asphalt Resurfacing 11/07/14 BCDA 68.470 120 C 0.461 0.200 0.300 - - - - 94.08%

V. Satisfactory

Subiccon Corporation (Formerly: Subcon Construction) 25079 Prev. Maint. along Jct. Layac Balanga-Mariveles Port Rd.,

K0123+1352-K0124+400 (w/ exception) 03/14/13 III 18.696 68 C 0.444 0.133 0.300 - - - 87.70 *87.70% Satisfactory

SUMAG BUILDERS CONSTRUCTION 32894 Replacement/Rehabilitation/Strengthening of Dawaic

Bridge along Mt. Province-Ilocos Sur via Tue Road 8/12/2014 CAR 4.337 143 C 0.427 0.133 0.153 71.30 79.88% Unsatisfactory

Sumag Builders Construction 32894 Rehab. of Chico River Flood Control, Caluttit-Pakkil Sect. 08/04/12 CAR 4.886 109 C 0.405 0.200 0.300 - - - 90.50 87.62% Satisfactory

Sumag Builders Construction 32894 Upgrading of Mt. Province-Ilocos Sur via Tue Rd., Tadian & Bauko 03/16/13 CAR 4.729 193 C 0.400 0.133 0.300 - - - 83.30 *83.30%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page266

Page 267: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Sumag Builders Corporation 32894 Replacement/Rehab./Strengthening of Dawaic Bridge along Mt. Province-Ilocos Sur via Tue Rd. 08/02/13 CAR 4.337 143 O 0.356 0.240 0.150 0.015 0.045 0.050 85.60

Sumitomo Construction Co. Ltd. FC-04-010 CP V, Agas-Agas Bridge Project 03/07/09 PJHL 995.037 990 O 0.367 0.298 0.150 0.030 0.070 0.050 96.50 -

Sumitomo Construction Co. Ltd. FC-04-010 CP V, Agas-Agas Bridge Project 08/30/08 PJHL 869.429 780 O 0.386 0.300 0.100 0.030 0.070 0.100 98.60 -

Sunstone Construction 11122 Conc. of Road along Dualing-New Panay-Midsayap Road, Sta. Cruz Sect. 03/22/12 XII 7.959 142 C 0.433 0.200 0.300 - - - 93.30 86.28%

Satisfactory

Sunstone Construction 11122 Conc. of Rd. along New Panay-Midsayap Rd., Sta. Cruz-Katalicanan Sect. (Km 1690+866.35-km 1693+047.35) 11/22/12 XII 46.290 319 C 0.484 0.133 0.300 - - - 91.70 90.02%

V. Satisfactory

Sunstone Construction 11122 Impvt. of Banisilan-Guiling-Alamada-Libungan Rd., Rangayen, Sitio Tiuasi-Barangiran Sect., Rangayen 08/15/12 XII 19.903 210 C 0.470 0.133 0.300 - - - 90.30 90.42%

V. Satisfactory

Sunstone Construction 11122 Conc. of Rd. along New-Panay-Midsayap Rd., Sta. Cruz Katalicanan Sect. (Km.1690+866.35-Km.1693+047.35) 08/14/12 XII 46.443 319 O 0.359 0.253 0.150 0.030 0.047 0.050 88.90 -

SUNSTONE CONSTRUCTION AND SUPPLY 11122 MALITUBOG IRRIGATION PROJECT STAGE II MIP-LMC-

004 PACKAGE VI 06/06/14 NIA 37.721 503 C 0.365 0.192 0.300 - - - 85.76 *85.76% Satisfactory

Sunwest Construction & Development Corporation 15906 Gaba Port Development Project 07/29/15 DOTC 18.652 180 O 0.343 0.300 0.150 0.020 0.035 0.050 89.75 -

SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION 15906 Bicol (New Legaspi) Int'l Airport Development Project 08/20/15 DOTC 778.551 854 O 0.363 0.300 0.150 0.030 0.070 0.050 96.30 -

Sunwest Construction & Development Corporation 15906 RC Wharf Extension and Construction of Back-up Area 09/29/15 PPA 95.492 420 O 0.399 0.300 0.150 0.030 0.059 0.050 98.80 -

Sunwest Construction & Development Corporation 15906 New Bicol International Airport & Development Project 02/04/14 DOTC 708.000 540 O 0.351 0.300 0.150 0.030 0.062 0.050 94.31 -

Sunwest Construction & Development Corporation 15906 New Bicol International Airport Development Project 04/23/14 DOTC 708.000 540 O 0.355 0.300 0.150 0.030 0.042 0.050 92.66 -

Sunwest Construction & Dev't Corporation 15906 Bicol (New Legaspi) Int'l Airport Development Project 07/24/14 DOTC 289.240 330 C 0.460 0.200 0.300 - - - - 95.20%

V. SatisfactorySunwest Construction & Dev't

Corporation 15906 Bicol (New Legaspi) Int'l Airport Development Project 07/24/13 DOTC 289.188 330 C 0.433 0.200 0.300 - - - 93.30 94.30% V. Satisfactory

Sunwest Construction & Dev't Corporation 15906 Bulan Airport Development Project 07/25/13 DOTC 5.803 180 C 0.440 0.200 0.300 - - - 94.00 93.70% V.

Satisfactory Sunwest Construction & Dev't

Corporation 15906 Dapdap Port Development Project 09/03/13 DOTC 13.971 135 C 0.425 0.200 0.300 - - - 92.50 *92.50% V. Satisfactory

Sunwest Construction & Dev't Corporation 15906 Construction of R. C. Wharf 08/16/13 PPA 83.351 334 C 0.500 0.200 0.000 - - - 70.00 82.49% Satisfactory

Sunwest Construction and Development Corporation

(Formerly: Sunwest Construction & Supply)

15906 Construction of Puro Rock Causeway 05/28/10 V 48.088 270 O 0.381 0.240 0.150 0.030 0.050 0.050 90.10 -

Sunwest Construction and Development Corporation

(Formerly: Sunwest Construction & Supply)

15906Bulan Airport Development Project (Apron Expansion, Runway Extension, Continuation of Concrete Paving of

Runway and Construction of Terminal Building)07/15/10 DOTC 57.802 180 O 0.378 0.300 0.150 0.030 0.047 0.050 95.50 -

Sunwest Construction and Development Corporation

(Formerly: Sunwest Construction & Supply)

15906 Bicol (New Legaspi) Int'l Airport Development Project (Construction of Airstrip) 07/16/10 DOTC 289.240 330 O 0.347 0.300 0.150 0.030 0.070 0.050 94.70 -

Sunwest Construction and Development Corporation

(Formerly: Sunwest Construction & Supply)

15906 Bicol (New Legaspi) Int'l Airport Development Project (Continuation of Construction of Airstrip) 07/16/10 DOTC 289.188 330 O 0.351 0.300 0.150 0.030 0.070 0.050 95.10 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page267

Page 268: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Sunwest Construction and Development Corporation

(Formerly: Sunwest Construction & Supply)

15906 Pio Duran Port Development Project 03/9-12/10 PPA 60.399 300 O 0.389 0.300 0.150 0.030 0.056 0.050 97.50 -

Sunwest Construction and Development Corporation

(Formerly: Sunwest Construction & Supply)

15906 Asphalt Overlay Topas-Palsong Road 02/27/10 V 47.767 190 O 0.359 0.240 0.150 0.030 0.045 0.050 87.40 -

Sunwest Construction and Development Corporation

(Formerly: Sunwest Construction & Supply)

15906 Asphalt Overlay of Balaogan-Casugad Road 02/27/10 V 4.767 149 O 0.354 0.239 0.150 0.030 0.045 0.050 86.80 -

Sunwest Construction and Development Corporation

(Formerly: Sunwest Construction & Supply)

15906 Asphalt Overlay of Palsong-Balaogan Road 02/27/10 V 47.768 148 O 0.337 0.238 0.150 0.030 0.045 0.050 85.00 -

Sunwest Construction and Development Corporation 15906 Legazpi Urban Draiange Improvement Project

(Const./Impvt. Of Dike at Macabalo River) 8/16/2014 V 141.021 501 C 0.350 0.200 0.300 85.00 86.14% Satisfactory

Sunwest Construction and Development Corporation 15906 Reconst./Rehab. of Damaged Paved Nat'l. Rd. (Intermittent

Sect.) Daang Maharlika 03/20/13 V 111.849 270 C 0.344 0.200 0.300 - - - 84.40 86.14% Satisfactory

Sunwest Construction and Development Corporation 15906 Upgrading of Balud-Milagros-Aroroy Road (San Pablo

Sect.) 08/09/11 V 99.999 390 O 0.383 0.237 0.150 0.030 0.056 0.050 90.60 -

Sunwest Construction and Development Corporation 15906 Upgrading of Balud-Tawad-Milagros-Aroroy Road (Paraiso

Section) 08/09/11 V 96.193 390 O 0.374 0.238 0.150 0.030 0.061 0.033 88.60 -

Sunwest Construction and Development Corporation 15906

Const./Rd. Opening of Camarines Sur/Albay Diversion Rd. San Fernando-Oas Sect. of Pan Phil. Highway Camarines

Sur Sect., Bula-Nabua-Bato Sect.11/27/12 V 514.200 730 C 0.467 0.133 0.300 89.04%

V. Satisfactory

Sunwest Construction and Development Corporation 15906 Proposed Passenger Terminal Building 07/20/12 PPA 55.195 427 O 0.393 0.282 0.076 0.030 0.070 0.050 90.06 -

Sunwest Construction and Development Corporation 15906 Construction of R.C. Wharf 02/15/13 PPA 83.082 299 O 0.400 0.300 0.000 0.030 0.060 0.050 84.00 -

Sunwest Construction and Development Corporation 15906 Passenger Terminal Building 02/15/13 PPA 55.873 427 C 0.474 0.200 - - - - 67.40 85.39% Satisfactory

Sunwest Construction and Development Corporation 15906 Construction of R.C. Wharf 11/30/12 PPA 83.083 240 O 0.394 0.300 0.150 0.030 0.053 0.050 97.65 -

Sunwest Construction and Development Corporation 15906 Construction of Passenger Terminal Building 11/30/12 PPA 55.195 360 O 0.399 0.296 0.150 0.030 0.056 0.030 96.15 -

SUNWEST CONSTRUCTION AND DEVELOPMENT CORPORATION (Formerly: Sunwest Construction

and Supply)

15906 Completion of Sula Bridge Including Approach 11/7/2014 V 37.559 186 C 0.468 0.133 0.300 - - - 90.10% 90.1% Very Satisfactory

Sunwest Construction and Development Corporation

(Formerly: Sunwest Construction and Supply)

15906 Legazpi Urban Drainage Impv't. Proj. (Const./Impv. Of Dike @ Macabalo River) 08/14/13 V 141.207 334 O 0.374 0.285 0.092 0.030 0.055 0.033 86.90

Sunwest Construction and Development Corporation

(Formerly: Sunwest Construction and Supply)

15906 Upgrading of Balud-Tawad-Milagros-Aroroy Road (Paraiso Section), 2nd District 04/13/11 V 96.193 390 O 0.326 0.300 0.120 0.030 0.056 0.050 88.20 -

Sunwest Construction and Development Corporation

(Formerly: Sunwest Construction and Supply)

15906 Const. of San Isidro Bridge 03/30/11 V 48.031 397 O 0.325 0.300 0.109 0.030 0.065 0.033 86.20 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page268

Page 269: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Sunwest Construction and Development Corporation/Hi-tone

Construction and Development Corporation (JV)

JV-13-200 Rehab./Reconst./Replacement/Retrofitting of Existing Pemanent Bridge; Bascaran Bridge along Daang Maharlika 8/15/2014 V 28.348 227 OG 0.333 0.271 0.150 0.020 0.047 0.050 87.10

Superpower Construction 17149Repair and Maintenance of Flood Control Structures,

Catanauan-Mulanay Rd. (Catanauan Side), K0260+422-K0260+499 & K0260+512-K0260+707 (LS)

03/12/12 IVA 2.250 75 C 0.438 0.200 0.300 - - - 93.80 87.86% Satisfactory

SUPREME ABF CONSTRUCTION & CONSTRUCTION COMPANY

INC./GENETIAN BUILDERS (JV)JV-13-623 Construction of Bridges, Lower Landing Bridge along

Mahayag-Dumingag-Siayan Road, Zamboanga del Sur 10/27/2014 IX 23.324 190 O 0.400 0.240 0.150 0.030 0.030 0.017 86.70% 86.7% Satisfactory

Supreme ABF Construction & Construction Supply Company 25226

Rd. Upgrading (Gravel to Concrete) along Dualing-New Panay-Midsayap Rd., New Leon Sect., Cotabato

a)Km.1701+(421)-Km.1702+527.50; b)Km.1704+292-Km.1704+540, New Leon Sect.

08/12/13 XII 43.485 170 O 0.324 0.300 0.150 0.030 0.060 0.033 89.70

SUPREME ABF CONSTRUCTION & CONSTRUCTION SUPPLY

COMPANY INC.25226

Road Upgrading (Gravel to Concrete) along Dualing - New Panay - Midsayap Road, New Leon Section Cotabato A)

Km.1701+(-421) - Km.1702+527.50 B) Km.1704+290 - Km.1704+540

8/11/2014 XII 43.485 170 C 0.474 0.133 0.300 90.70 90.10% Very Satisfactory

SUPREME ABF CONSTRUCTION & CONSTRUCTION SUPPLY

COMPANY, INC.25226 Construction of Standard One-Storey (3 CL) School

Building at San Jose Elementary School 10/24/2014 VI 2.710 74 C 0.487 0.133 0.300 - - - 92.00% 92% Very Satisfactory

SUPREME ABF CONSTRUCTION & CONSTRUCTION SUPPLY

COMPANY, INC.25226

Road Widening along Aklan West Road (Junction Nabas-Kalibo/Numancia Boundary Road Section), K0265+280 -

K0268+33010/30/2014 VI 30.571 299 O 0.355 0.206 0.150 0.030 0.055 0.050 84.60% 84.6%

Satisfactory

SUPREME ABF CONSTRUCTION & CONSTRUCTION SUPPLY

COMPANY, INC.25226 Construction of River Control (Revetment Wall) along

Aklan River Brgy. Biga-a 10/30/2014 VI 43.187 274 C 0.447 0.133 0.300 - - - 88.00% 88% Satisfactory

SUPREME ABF CONSTRUCTION & CONSTRUCTION SUPPLY

COMPANY, INC.25226

Upgrading of Baclayon - Corella Road Leading the Philippine Tarsier and Wildlife Sanctuary, K0253+930 to

K0259+10010/26/2014 VII 114.743 300 O 0.342 0.300 0.102 0.030 0.035 0.033 84.20% 84.2%

Satisfactory

SUPREME ABF CONSTRUCTION & CONSTRUCTION SUPPLY

COMPANY, INC.25226 Road Upgrading (Gravel to Paved) of Dolongon-Basey

Road Chainage 1391-Chainage 2816 10/25/2014 VIII 26.825 180 O 0.342 0.240 0.000 0.023 0.045 0.033 68.30% 68.3% Poor

SUPREME ABF CONSTRUCTION & CONSTRUCTION SUPPLY

COMPANY, INC.25226 Completion of on going bridges (including approaches)

Jaro, Iloilo City 8/4/2014 VI 14.865 210 C 0.417 0.200 0.300 91.70 89.42% Very Satisfactory

SUPREME ABF CONSTRUCTION & CONSTRUCTION SUPPLY

COMPANY, INC.25226 Road Upgrading of Isabela - Libas Negros Occidental Bdry.

Road K0081+000 - K0083+000 8/7/2014 VI 33.414 203 C 0.395 0.200 0.300 89.50 82.12% Satisfactory

Supreme ABF Construction & Construction Supply Company, Inc. 25226 Conc. of Pacita-La Paz Drive Rd. 11/22/12 VI 17.097 150 C 0.355 0.200 0.300 - - - 85.50 90.00% V.

Satisfactory

Supreme ABF Construction & Construction Supply Company, Inc. 25226 Conc. of Pacita-La Paz Drive Road Hamtic, Antique 08/15/12 VI 17.113 150 O 0.350 0.300 0.150 0.030 0.050 0.050 93.00 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page269

Page 270: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

SUPREME ABF CONSTRUCTION & CONSTRUCTION SUPPLY COMPANY, INC. / REDSON

CONSTRUCTION AND SUPPLIES JOINT VENTURE

JV-13-273 Construction of Flood Control Structure and Drainage System at Silay City 10/21/2014 VI 47.931 304 O 0.368 0.245 0.150 0.023 0.047 0.050 88.30% 88.3%

Satisfactory

Supreme ABF Construction and Construction Supply 25226 Const. of Revetment Wall along Aklan River, Taba-ao 08/17/13 VI 16.254 180 C 0.381 0.200 0.300 - - - 88.10 *88.10%

Satisfactory

Supreme ABF Construction and Construction Supply 25226

Const./Impv't. of Rd. (Thermoplastic Pvmt. & Pedestrian Crossing Markings), Bacolod-San Carlos Rd., K0005+1083-

K0013+580 w/ exceptions08/07/13 VI 9.118 35 C 0.333 0.200 0.300 - - - 83.30 *83.30%

Satisfactory

Supreme ABF Construction and Construction Supply 25226 Completion of On-going Bridges (inc. Approaches) of

Dungon Bridge along Mandurriao-Jaro Rd. 08/23/13 VI 14.865 210 O 0.389 0.240 0.150 0.030 0.037 0.033 87.90

Supreme ABF Construction and Construction Supply 25226 Rd. Upgrading of Isabela-Libas Negros Occidental Bdry.

Rd., K0081+000-K0083+000 08/10/13 VI 33.414 203 O 0.300 0.208 0.095 0.030 0.035 0.050 71.80

Supreme ABF Construction and Construction Supply 25226 Rd. Upgrading of Isabel-Libas Negros Occidental Bdry.

Rd., K0081+000-K0083+000 03/12/13 VI 33.414 203 O 0.307 0.249 0.150 0.015 0.055 0.050 82.60 -

T SQUARE BUILDERS 14268 Widening of Digos Makar Road (KO1569+807 to KO1570+550), Hagonoy Section, Hagonoy 8/7/2014 XI 18.939 121 C 0.419 0.133 0.300 85.20 85.20%

Satisfactory

T. M Abad Construction 9302 Const. of Livelihood, Production and Training center 05/04/11 NHA 4.976 90 O 0.379 0.300 0.150 0.030 0.057 0.050 96.60 -

T. M Abad Construction 9302 Const. of Livelihood, Production and Training center 01/13/12 NHA 4.976 90 C 0.500 0.200 0.300 - - - 100.00 97.50% Outstanding

T. M. Abad Construction 9302 Pandan Port Development Project 05/17/14 DOTC 4.789 75 C 0.446 0.200 0.300 - - - 94.60 *94.60% V. Satisfactory

T. M. Abad Construction 2272 Construction of Multi-Purpose Covered Court (Building) 04/01/11 NHA 5.412 90 O 0.378 0.284 0.000 0.020 0.032 0.000 71.40 -

T. Solomon Construction 10046 Const. of 2-Storey, 6-Cl RGR Type Sch. Bldg., Sta. Anastacia-San Rafael NHS, Brgy. San Rafael 08/01/13 IVA 13.643 210 O 0.333 0.300 0.150 0.030 0.018 0.033 86.40

T. Solomon Construction & Development Corporation 10046

Construction of 2 Storey 6 Classroom RGR Type School Bldg, Sta. Anastacia-San Rafael NHS, Brgy. San Rafael,

Sto. Romas, Batangas8/9/2014 IV-A 13.643 180 C 0.486 0.200 0.300 98.60 90.06%

Very Satisfactory

T. Square Builders 14268Assess Critical Bottlenecks, Traffic Decongestion,

Widening of Digos-Makar Rd., South Cotabato Sub-DEO, K1642+071-K1644+470

08/22/13 XII 46.576 170 C 0.410 0.195 0.300 - - - 90.50 *90.50% V. Satisfactory

T. Square Builders 14268Rehab./Impv't. of Rd. Slip along Sarangani-Davao del Sur Coastal Rd., Nacolyael-Small Margus Sect., Km.1729+244-

Km.1729+59408/20/13 XII 19.711 207 C 0.393 0.200 0.300 - - - 89.30 88.22%

Satisfactory

T. Square Builders 14268 Const. of Lined Canal/Flood Control along Marbel-Makar Rd., Apopong Sect., Brgy. Apopong 08/23/13 XII 17.323 213 O 0.338 0.240 0.150 0.022 0.047 0.033 83.00

T. Square Builders 14268 Conc. of Roads at La Fortuna Roads 05/29/09 XI 4.718 60 O 0.367 0.300 0.150 0.030 0.033 0.050 93.00 -

T. Square Builders 14268 Bagong Taas Bridge along Sarangani-Davao del Sur Coastal Rd. 08/21/12 XII 8.697 175 C 0.447 0.133 0.300 - - - 88.00 88.12%

SatisfactoryT.E.L.O De Guzman Construction

and Supply 37151 Road Concreting of Bagoladio - Itangon 8/10/2014 V 4.666 64 C 0.373 0.200 0.300 87.30 87.30% Satisfactory

T.J. Velasco Construction & Supply 10560Impv't. of Major Intersections along Manila North Rd.,

Binalonan-Asingan-Sta. Maria Rd., K0190+(-247)-K0190+003, Binalonan Sect.

08/09/13 I 6.717 110 C 0.488 0.133 0.300 - - - 92.10 91.20% V. Satisfactory

T.J. Velasco Construction & Supply 10560Impv't. of Major Intersections along Manila North Rd.,

Binalonan-Asingan-Sta. Maria Rd., K0190+(-247)-K0190+003, Binalonan Sect.

03/13/13 I 6.717 80 O 0.355 0.300 0.150 0.023 0.045 0.033 90.60 -

T.M. ABAD CONTRUCTION 9302 Pulilan-Plaridel River Port Development Project 06/29/15 DOTC 5.124 90 C 0.434 0.200 0.300 - - - 93.40 *93.40% V.Satisfactory

T.N.J Buhong Construction 19687 Widening/Conc. of Poblacion-Banaue-Brgy. Bangaan, Awaan-Banagan Section 03/06/09 CAR 23.084 270 O 0.369 0.295 0.150 0.022 0.037 0.033 90.60 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page270

Page 271: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

T.N.J Buhong Construction 19687Widening/Conc. of Pob. Bnaue-Brgy. Bangaan, Banaue

(Intermittent Sections from Awaan-Bangaan Sections) KM. 342+00-KM 354+045 (IS)

08/31/09 CAR 23.084 457 O 0.335 0.240 0.150 0.030 0.056 0.033 84.40 -

T.N.J Buhong Construction 19687 Widening/Conc. of Poblacion-Banaue-Brgy. Bangaan, Awaan-Banagan Section 11/16/08 CAR 23.123 270 O 0.268 0.126 0.070 0.008 0.030 0.033 53.50 -

T.N.J. Buhong Construction 19687 Rd. Upgrading along Banaue-Hungduan-Benguet Bdry. Rd., K0364+365-K0367+980 (w/ exceptions) 08/04/13 CAR 40.770 344 C 0.454 0.133 0.300 - - - 88.70 88.94%

Satisfactory

T.N.J. Buhong Construction 19687 Rd. Upgrading along Banaue-Hungduan-Benguet, K0348+380-K0353+549 08/04/13 CAR 19.336 194 C 0.421 0.133 0.300 - - - 85.40 82.04%

Satisfactory

T.N.J. Buhong Construction 19687 Road Upgrading along Banaue-Mayoyao Road-Ibayong Sect. (K0342+790-K0343+344) 03/18/12 CAR 7.724 192 C 0.447 0.133 0.300 - - - 88.00 85.18%

Satisfactory

T.N.J. Buhong Construction 19687 Rd. Upgrading along Banaue-Hungduan-Benguet Bdry. Rd., K0364+365-K0367+980 (w/ exceptions) 08/05/12 CAR 40.770 239 C 0.336 0.300 0.150 0.030 0.042 0.033 89.10 -

T.N.J. Buhong Construction 19687 Rd. Upgrading along Banaue-Hungduan-Benguet Bdry. Rd., K0384+000-K0385+549 08/05/12 CAR 19.336 150 O 0.321 0.300 0.100 0.030 0.047 0.000 79.80 -

T.Square Builders 14268Rehab./Impv't. of Rd. Slip along Sarangani-Davao del Sur Coastal Rd., Nacolyaei-Small Margus Sect., Km.1729+244-

Km.1729+59403/22/13 XII 19.711 207 O 0.363 0.237 0.150 0.030 0.045 0.050 87.50 -

T.Square Builders 14268Road Upgrading (Gravel to Paved), Intermittent Sect.,

along Sarangani-Davao del Sur Rd., Km.1735+273-Km.1736+870

03/22/13 XII 40.192 182 O 0.355 0.234 0.150 0.030 0.050 0.033 85.20 -

TABADA CONSTRUCTION & SUPPLIES 35997 Construction of Road at Brgy. Pinana-an, Las Nieves,

Agusan del Norte 10/29/2014 XIII 3.497 37 C 0.394 0.139 0.300 - - - 83.30% 83.3% Satisfactory

Tabada Construction & Supplies 35997 Conc. of Road Pob. II, Babag 3 Brgy. Rd. 08/06/13 XIII 6.606 48 C 0.402 0.133 0.300 - - - 83.50 *83.50% Satisfactory

Tacloban Ras Construction Corporation 17184

Repair/Rehab. of National Road along Jct. Taft-Arteche Road (Reblocking), Km. 891+802-Km. 921+000 w/

exception06/08/09 VIII 7.645 95 O 0.224 0.240 0.150 0.030 0.045 0.033 72.20 -

Tacloban Ras Construction Corporation 17184 Asphalt Overlay along Borongan-San Julian Road 06/09/09 VIII 9.553 138 O 0.371 0.240 0.000 0.030 0.035 0.000 67.60 -

Tacloban Ras Construction Corporation 17184 Concreting of Sambulawan-Jct. Calaguise-Calubian Road 06/02/09 VIII 18.734 240 O 0.400 0.232 0.150 0.022 0.037 0.050 89.10 -

Tacloban Ras Construction Corporation 17184 Conc. of Tabing-Kawayan-Sta. Rosa-Lawis-Tabango Road 09/05/09 VIII 18.737 240 O 0.367 0.245 0.150 0.018 0.040 0.033 85.30 -

TADIAN GENERAL CONSTRUCTION 35339

Const/Rehab of Drainage along Baguio-Bontoc Rd, Mt. Province-Ilocos Sur via Kayan Road (Tadian-Losong

Section), Tadian (Drainage/Slope Protection); Const/Rehab of Drainage along Mt.Province Sur via Tue Road, Tadian

8/12/2014 CAR 4.000 71 C 0.475 0.133 0.300 90.80 90.80% Very Satisfactory

Tadian General Construction 35339Installation of Curb & Gutter, Widening Blocks & Safety Devices along Mt. Province-Ilocos Sur via Kayan Rd.,

K0396+445-K0399+00008/02/13 CAR 3.558 140 C 0.467 0.133 0.300 - - - 90.00 *90.00% V.

Satisfactory

TANGO ROMEO GENERAL CONSTRUCTION 18926

Contract Package 6: Const/Imprvt of Access Road Leading to Airportsa, Seaports and Declared Tourism Destination, Road around Burnham Park, Baguio City: A) Lake Drive 1;

B) Juan Luna Drive and C) Lake Drive 2

8/15/2014 CAR 14.226 70 C 0.493 0.133 0.300 92.60 92.60% Very Satisfactory

Tanon Construction & Supplies 32844 Rehab./Reconst./Replacement/Retroffiting of Tinahaban Bridge 1 along Bacolod North Rd. E.B. Magalona 08/12/13 VI 3.654 37 C 0.423 0.139 0.300 - - - 86.20 *86.20%

Satisfactory

Tantuco Construction & Trading Corporation (Formerly: Tantuco Lumber & Construction Supply)

7255 Const. of Eco-Tourism Rd. (LUC-BATCR) Phase III inc. RROW, Ilayang Talim-Isabang Sect. 08/03/13 IVA 41.815 160 O 0.266 0.298 0.150 0.030 0.042 0.050 83.60

Tantuco Construction & Trading Corporation (Formerly: Tantuco Lumber & Construction Supply)

7255 Road Opening of Quezon Eco-Tourism Rd. (LUC-BATCR) inc. RROW at Salinas Sect. 03/16/13 IVA 38.635 281 C 0.420 0.133 0.300 - - - 85.30 85.90%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page271

Page 272: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Tantuco Construction Trading Corporation 7255

Quezon Eco-Tourism Road (Lucena City-Batangas Coastal Road) Phase III, Concreting of Eco-Tourism Coastal Road

(Section III), Talaan-Bocohan Section, K0142+343.50 to K0144+803

8/13/2014 IV-A 43.129 250 OG 0.337 0.300 0.150 0.015 0.051 0.050 90.30

Tapnio and Tan Construction & Development Corporation 10798 Const. of Three (3) Sch. Bldgs., Nine (9) Cl at Sampaguita

ES 08/13/13 NCR 12.545 210 O 0.282 0.240 0.150 0.030 0.058 0.050 81.00

Tapnio and Tan Construction & Development Corporation 10798 Const. of 4 storey 12 Cl. at Toro Hills, E/S 08/02/13 NCR 22.612 180 O 0.298 0.240 0.150 0.030 0.041 0.033 79.20

TAPNIO AND TANCONSTRUCTION & DEVELOPMENT CORPORATION 10798 Construction of 4 Storey Eight (8) Classroom Building at

Masambong H/S, Quezon City 8/14/2014 NCR 15.437 180 C 0.467 0.133 0.300 90.00 90.00% Very Satisfactory

Tarifa Construction & Supplies 33239 Construction of Multi-Purpose Building at Brgy. Palacpalac 02/27/09 III 2.361 75 O 0.205 0.239 0.150 0.030 0.035 0.050 70.90 -

Teckcon Construction 33214 Restoration of Mt. Province Bdry.-Calanan-Pinukpuk-Abbut Road K0424+900-K0483+040 03/20/12 CAR 10.467 120 O 0.358 0.230 0.150 0.030 0.035 0.033 83.60 -

Teddie Construction Development Inc. 6313 Land Development of Zamboanga City Townsite 01/10/14 NHA 23.710 240 O 0.381 0.300 0.144 0.023 0.055 0.033 93.56

Teddie Construction Development Inc. 6313 Land Development of Zambaonga City Townsite 01/10/14 NHA 23.711 240 O 0.381 0.300 0.144 0.023 0.055 0.033 93.56 -

Teddie Construction Development Inc. 6313 Const. of Flood Control along Davao-Cotabato Road at a)

Sambas Section and b) Power Section 02/25/10 XI 4.723 90 O 0.354 0.239 0.150 0.030 0.045 0.050 86.80 -

Teddie Construction Development Inc. 6313 Improvement/Rehabilitation of Gov. Camins road 05/26/09 IX 26.653 196 O 0.381 0.180 0.000 0.010 0.047 0.000 61.80 -

Teddie Construction Development Inc. 6313 Improvement/Rehabilitation of Gov. Camins Road 09/02/09 IX 26.653 227 O 0.383 0.300 0.000 0.030 0.055 0.033 80.10 -

Teddie Construction Development Inc. 6313 Const. (New Opening) of Zamboanga West Coast Road,

Sirawai-Sibuco Road, Bitugan-Tapanayan-Talabiga Section 08/19/08 IX 32.446 340 O 0.160 0.043 0.000 0.030 0.042 0.100 37.50 -

Teddie Construction Development Inc. 6313 Conc. of Montevista-Compostela-Mati Road, Liboton-

Saddle Section 06/04/09 XI 50.960 300 O 0.400 0.300 0.150 0.020 0.033 0.033 93.60 -

Teddie Construction Development Inc. 6313 Conc. of Montevista-Compostela-Mati Road, Liboton-

Maddle Section 09/09/09 XI 50.960 300 O 0.397 0.286 0.150 0.024 0.047 0.050 95.40 -

Teddie Construction Development Inc./Wee Eng Const., Inc. (J.V.) JV-07-116 Zamboanga Airport Development Project 04/30/09 DOTC 105.729 300 O 0.398 0.300 0.150 0.020 0.054 0.033 95.50 -

TEDDIE CONSTRUCTION DEVELOPMENT, INC. 6313

Widening of Zamboanga City-Libuan-Limpapa Road, K1950+093 to K1957+540 (w/ exception)(as per list)

modified to: K1950+080 to K1956+64010/21/2014 IX 42.270 240 O 0.366 0.236 0.150 0.030 0.045 0.033 86.00% 86%

Satisfactory

Teddie Construction Development, Inc. 6313 Asphalt Overlay/Repair & Rehab. of Basilan Circ. Rd.

(Isabela-Lamitan Section) K1+248-K2+000 w/ exception 03/13/13 IX 9.714 58 C 0.429 0.120 0.300 - - - 84.90 83.34% Satisfactory

Teddie Construction Development, Inc. 6316 Zamboanga Airport Development Project 02/07/13 DOTC 86.623 210 C 0.458 0.200 0.300 - - - 95.80 95.80%

V. Satisfactory Teddie Construction Development,

Inc./Wee Eng Construction, Inc. (JV)

JV-07-116 Zamboanga Airport Development Project 8/6-7/09 DOTC 0.105 300 O 0.387 0.300 0.150 0.020 0.044 0.050 95.10 -

THE STEADFAST BUILDERS 8176Construction of Local Roads - Sampaguita St. Brgy.

Pembo, Cadena de Amor St. Brgy. Pembo, Maya St. & its Approaches, Brgy. Rizal, District II

11/19/2014 NCR 5.123 150 O 0.382 0.219 0.150 0.023 0.045 0.033 85.15% 85.15% Satisfactory

The Steadfast Builders 8176 Prev. Maint. of Dapitan St., Q.C. (K0005+568.80-K0008+174.30) Int. Sect. 08/02/13 NCR 6.989 90 C 0.394 0.200 0.300 - - - 89.40 *89.40% V.

Satisfactory

The Steadfast Builders 8176 Road & Drainage Impv't. along P. Sanchez St. 07/29/13 NCR 6.365 147 C 0.425 0.133 0.300 - - - 85.80 *85.80% Satisfactory

The Steadfast Builders 8176 Rehab./Reconst./Upgading of Felix Ave. (Formerly Imelda Ave.) 05/18/09 IV-A 38.426 180 O 0.389 0.240 0.150 0.030 0.025 0.050 88.40 -

The Steadfast Builders 8176 Impv't./Widening of Cainta-Kaytickling-Antipolo-Teresa Road (2 Lanes) 03/13/12 IVA 18.236 315 C 0.461 0.079 0.300 - - - 84.00 90.90%

V. Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page272

Page 273: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

The Tuscan Structures & Supplies 18257 Concrete Paving of Biliran Circumferential Road, Look-Habuhab Section 06/04/09 VIII 19.160 200 O 0.356 0.240 0.150 0.030 0.037 0.033 84.60 -

The Tuscan Structures & Supplies 18257 Concrete Paving of Biliran Circumferential Road, Guindapunan-Pinamihagan Section 06/04/09 VIII 19.155 200 O 0.311 0.240 0.150 0.030 0.037 0.033 80.10 -

The Tuscan Structures & Supplies 18257 Concrete Paving of Biliran Circ. Road, (Guindapunan-Pinamihagan Sect.) 09/03/09 VIII 19.155 200 O 0.344 0.240 0.150 0.030 0.050 0.033 84.70 -

The Tuscan Structures & Supplies 18257 Concrete Paving of Biliran Circ. Road, (Look-Habuhab Sect.) 09/03/09 VIII 19.160 200 O 0.337 0.240 0.150 0.030 0.050 0.033 84.00 -

The Tuscan Structures & Supplies 18257 Concrete Paving of Biliran Circ. Road, (Bilwang-Mapuyo Section) 09/03/09 VIII 19.142 200 O 0.348 0.256 0.150 0.006 0.045 0.033 83.80 -

The Tuscan Structures & Supplies 18257 Concrete Paving of Biliran Circ. Road, Tomalistis-Cabibihan Sect. 03/22/12 VIII 8.959 257 C 0.404 0.133 0.299 - - - 83.60 84.05%

Satisfactory

THE TUSCAN STRUCTURES AND SUPPLIES 18257

Construction of Drainage Sydtem along Naval-Caibiran CCR to Include Payment of RROW Damages, Km.

1026+800-Km.1028+000 with exceptions10/27/2014 VIII 11.138 228 C 0.422 0.133 0.300 - - - 85.50% 85.5%

Satisfactory

The Tuscan Structures and Supplies 18257

Concrete Paving of Biliran Circ. Rd., Km.1089+100-Km.1096+640 w/ exceptions (San Agustin-Pawikan Rd.

Sect.)03/12/13 VIII 43.665 180 O 0.311 0.232 0.150 0.030 0.050 0.033 80.60 -

The Tuscan Structures and Supplies 18257 Concrete Paving of Biliran Circ/ Rd., Madao-Tucdao Rd.

Sect., Km.1055+064-Km.1061+100 w/ exceptions 11/20/12 VIII 48.084 280 C 0.453 0.133 0.300 - - - 88.60 85.54% Satisfactory

The Tuscan Structures and Supplies 18257 Concrete Paving of Biliran Circ.Road Madao-Tucdao Rd.

Sect. Km.1055+064-Km.1061+100 w/ exceptions 08/07/12 VIII 48.084 250 O 0.331 0.300 0.150 0.030 0.040 0.033 88.40 -

The Tuscan Stuctures & Supplies 18257 Conc. Paving of Biliran Circ. Road (Masagaosao-Bulalacao Section) 08/26/10 VIII 24.915 340 O 0.356 0.236 0.150 0.030 0.047 0.033 85.20 -

THREE W BUILDERS / SOPHIA CONSTRUCTION AND SUPPLY

JOINT VENTUREJV-12-258

Road Upgrading (Gravel to Concrete) along Awang - Upi - Lebak - Kalamansig - Palimbang - Sarangani Road,

Km.2036+815 to Km.2038+414 with exception8/14/2014 XII 34.681 123 C 0.441 0.189 0.300 93.00 93.00%

Very Satisfactory

THREE W BUILDERS / SOPHIA CONSTRUCTION AND SUPPLY

JOINT VENTUREJV-12-258

Road Upgrading (Gravel to Concrete) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road Standard (HDM-4 Project Analysis) along

Awang-Upi-Lebak - Kalamansig - Palimbang - Sarangani Road, Km.2041+691 - Km. 2043+919 with exception

8/14/2014 XII 46.021 196 C 0.440 0.200 0.300 94.00 90.28% Very Satisfactory

Three W Builders Inc. 10722 Const. of Pamasilan I Bridge 08/18/11 IVA 38.572 197 O 0.348 0.183 0.150 0.030 0.040 0.050 80.10 -

Three W Builders Inc. / Sophia Construction and Supply (JV) JV-12-258

Rd. Upgrading (Gravel to Concrete) along Awang-Upi-Lebak-Kalamansig-Palimbang-Sarangani Rd., Km.2041+691-

Km.2043+919 w/ exception08/18/13 XII 46.021 181 O 0.384 0.236 0.150 0.024 0.051 0.033 87.80

THREE W BUILDERS INC./REPOLMAN CONSTRUCTION

(JV)JV-13-368

Preventive Maintenance (Asphalt Overlay of San Marcelino - Nagbayto Road) K0151+(-1012) - K0152+185 (K0151+(-

1012) - K0151+853.75)11/27/2024 III 27.366 75 C 0.448 0.133 0.300 - - - 88.10% 88.1%

Satisfactory

Three W Builders, Inc Construction of Twenty (20) Two-storey Residential Buildings 10/17/13 NHA 222.953 330 O 0.343 0.203 0.150 0.030 0.047 0.050 82.30

Three W Builders, Inc 10722 Impvt. of Quirino-Andaya Highway, Quezon Side, Brgy. San Luis II-Bagong Silang I 05/28/09 IV-A 38.590 90 O 0.348 0.240 0.150 0.020 0.025 0.050 83.30 -

Three W Builders, Inc 10722 Rehab./Reconst. Selective Conc. Paving & Asphalt, along Ozamis-Pagadian Road 06/09/09 X 38.659 240 O 0.292 0.300 0.000 0.030 0.043 0.033 69.80 -

Three W Builders, Inc 10722 Rehab./Reconst. (Selective Concrete Paving & Asphalt) along Ozamis-Pagadian Road 03/17/09 X 38.659 240 O 0.330 0.300 0.150 0.030 0.045 0.050 90.50 -

THREE W BUILDERS, INC. 10722Rehabilitation/Upgrading (Preventive Maintenance) Regaldo Avenue South Quezon City (K0023+(-959) -

K00223+(481)) with exception11/26/2014 NCR 17.370 120 C 0.461 0.133 0.300 - - - 89.40% 89.4%

Very Satisfactory

THREE W BUILDERS, INC. 10722Construction/Maintenance of Flood Control and Drainage System / Slope Protection Works along Antipolo-Teresa

Road11/28/2014 IV 17.943 140 C 0.478 0.133 0.300 - - - 91.10% 91.1%

Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page273

Page 274: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

THREE W BUILDERS, INC. 10722 Upgrading ( Gravel to Concrete Access Road Leading to Jatico Resort, Brgy. Bayanga 10/20/2014 X 36.384 280 O 0.329 0.300 0.121 0.015 0.037 0.033 83.50% 83.5%

Satisfactory

THREE W BUILDERS, INC. 10722 Road Slip along Malalag-Malita-JAS Road, Bagsak Section Sta. 1621+920 - Sta. 1622+020 10/22/2014 XI 14.403 102 O 0.150 0.242 0.150 0.008 0.035 0.017 60.20% 60.2%

Poor

THREE W BUILDERS, INC. 35843Construction/Rehabilitation of Drainage Protection Works along National Roads a.) Bugo Section (Bantiles Creek) b.)

Agusan River Section8/4/2014 X 9.811 230 OG 0.397 0.288 0.150 0.018 0.040 0.030 92.30

THREE W BUILDERS, INC. 10722

Cluster A-Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading

to Paved Road Standard (HDM-4 Project Analysis) (Intermittent Section) including Drainage and Road

Facilities, Lumbia - Uguiaban By-Pass Road

8/15/2014 X 40.976 240 C 0.434 0.192 0.300 92.60 86.54% Satisfactory

Three W Builders, Inc. 10722 Installation/Application/Const. of Rd. Safety Devices at Old Manila South Rd., Calamba Sect. (Sta. 50+120) 08/10/13 IVA 9.702 263 C 0.483 0.133 0.300 - - - 91.60 *91.60% V.

Satisfactory

Three W Builders, Inc. 10722 Repair/Rehab./Impv't. of Mayapa-Canlubang Rd., K0050+(-750)-K0050+000 (w/ exceptions) 08/10/13 IVA 9.704 30 C 0.463 0.133 0.300 - - - 89.60 *89.60% V.

Satisfactory

Three W Builders, Inc. Construction of (20) Two-Storey Resedential Buildings 11/17/13 NHA 222.953 330 O 0.343 0.203 0.150 0.030 0.047 0.050 82.30 -

Three W Builders, Inc. 10722

Road Upgrading (Gravel to Paved) (Int. Sect.) inc. Drainage & Rd. Facilities Lumbia-Uquiaban By Pass Rd.

a)Km.1461+861-Km.1462+093; b)Km.1462+2950-Km.1463+760

08/11/13 X 38.892 224 O 0.351 0.300 0.132 0.007 0.050 0.050 89.00

Three W Builders, Inc. 10722

Rd. Upgrading (Gravel to Paved) (Int. Sect.) inc. Drainage & Rd. Facilities, Lumbia-Uquiaban By Pass Rd., a)Km.1461+861-Km.1462+093; b)Km.1462+295-

Km.1463+760

03/11/13 X 38.892 179 O 0.300 0.225 0.150 0.010 0.042 0.033 76.00 -

Three W Builders, Inc. 10722 Const. of Lucban Diversion Road, Phase II 08/09/11 IVA 57.866 618 O 0.373 0.225 0.150 0.030 0.042 0.033 85.30 -

Three W Builders, Inc. 10722Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds.

along Abra-Ilocos Sur, K0386+813-K0405+520 w/ exception (K0387+(-387)-K0405+407 (I.S.) as per RBIA)

11/30/12 CAR 101.286 270 O 0.334 0.300 0.069 0.030 0.059 0.033 82.50 -

Three W Builders, Inc. 10722

Road Upgrading (gravel to concrete) of Abra-Cervantes Rd., K0444+600-K0446+050 & K0446+660-K0449+360 w/

exceptions, (K0444+600-K0446+025 & K0446+710-K0449+415 as per RBIA)

11/30/12 CAR 55.892 294 O 0.335 0.240 0.150 0.030 0.023 0.033 81.10 -

Three W Builders, Inc. / Almakar Builders and Metal Works Joint

VentureJV-12-266 Prev. Maint. (MFO-1), Asphalt Overlay along Crisanto M.

Delos Reyes Ave., K0060+143 K0062+143 08/13/13 IVA 19.954 60 C 0.472 0.133 0.300 - - - 90.50 *90.50% V. Satisfactory

Three-In-One Construction & Trading 14695 Proposed Repair/Maintenance of Dept. of Labor &

Employment Bldg., Intramuros 11/19/12 NCR 9.221 291 O 0.400 0.000 0.000 0.020 0.038 0.033 49.10 -

Thunder Construction 17247 Repair/Maint. of Bucay Flood Control; Repair/Maint. of Sinalang Flood Control (Package), Bucay & Bangued 08/14/13 CAR 2.224 36 C 0.472 0.133 0.300 - - - 90.50 *90.50% V.

Satisfactory

Thunder Construction 17247 Rd. Upgrading (Gravel to Conc.) FMR leading to Borokibok Spring Resort 08/15/13 CAR 18.437 120 C 0.429 0.133 0.300 - - - 86.20 *86.20%

Satisfactory

Thunder Construction 17247 Road Upgrading , Abra-Cervantes Road, Km. 430+450 - Km. 445+450 02/25/09 CAR 14.268 208 O 0.126 0.224 0.120 0.030 0.022 0.017 53.90 -

Thunderheads Construction Corporation 22420 Construction of Bansud River Control 8/14/2014 IV-B 9.194 104 C 0.401 0.133 0.300 83.40 83.40%

Satisfactory

Tiger Valley Builders 33063 Repair/Restoration of Santiago-Tuguegarao Rd. Maddarulug Sect. 05/28/10 II 2.412 130 O 0.369 0.240 0.150 0.024 0.042 0.033 85.80 -

TKS Builders and Supplies 23415 Rehab./Reconst. of Davao-Agusan Rd., Redemptorist-Davao Light Sect. 08/20/12 XI 4.177 135 C 0.396 0.200 0.300 - - - 89.60 93.32%

V. Satisfactory

TNJ BUILDERS 34268 Construction of Buluan Multi Purpose Building 11/28/2014 CAR 3.500 227 O 0.375 0.240 0.150 0.030 0.041 0.033 86.90% 86.9% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page274

Page 275: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Tobias Construction and Developer 13064 Desilting and Excavation Works of drainage Canal @ Libuganon RIS 06/01/13 NIA 7.969 100 C 0.411 0.500 - - - - 91.10 *91.10%

V. Satisfactory

Tokwing / ZM Construction (JV) JV-08-274 Const./Replacement of Bucao Bridge and Approaches along Iba-South Road over Bucao River 09/03/09 III 144.750 250 O 0.381 0.300 0.150 0.030 0.047 0.033 94.10 -

TOKWING CONSTRUCTION Construction of Eighteen (18) Three Storey Residential Buildings 07/13/13 NHA 169.570 375 O 0.364 0.185 0.150 0.024 0.054 0.050 82.70

Tokwing Construction Construction of Eighteen (18) Three Storey Residential Buildings 07/13/13 NHA 169.739 375 O 0.364 0.185 0.150 0.024 0.054 0.050 82.70 -

Tokwing Construction 9650 Const. (Road Opening) of Missing Link of National Road, Abra-Ilocos Norte Side, Km. 433+000 - Km. 452+620 02/16/10 CAR 47.656 494 O 0.349 0.262 0.150 0.020 0.033 0.033 84.70 -

Tokwing Construction 9650 Const. (Road Opening) of Missing Link of National Roads, Abra-Ilocos Norte, Abra Side, Km.433+000 - Km.452+620 05/25/10 CAR 47.656 494 O 0.303 0.000 0.150 0.022 0.035 0.033 54.30 -

Tokwing Construction 9650 Const. of Calaba Bridge and Approaches (Phase 2), Brgy. Calaba 09/07/09 PMO 157.810 630 O 0.352 0.240 0.150 0.030 0.056 0.033 86.10 -

Tokwing Construction 9650 Construction of Calaba Bridge and Approaches (Phase II) 02/24/09 Sp. Bridges 143.959 510 O 0.355 0.235 0.150 0.022 0.040 0.033 83.50 -

Tokwing Construction 9650 Const. of Mindanao Ave. Extension (Segment C) 11/28/08 NCR 161.879 360 O 0.375 0.180 0.100 0.030 0.042 0.067 79.40 -

Tokwing Construction 9650 Road Upgrading (Gravel to Paved), Baler-Casiguran Rd., Km. 276+800-Km. 285+000 11/26/12 III 144.896 240 O 0.324 0.280 0.150 0.030 0.040 0.033 85.70 -

Tokwing Construction / Northern Builders (JV) JV-09-017

Pinatubo Hazard Urgent Mitigation Proj. (PHUMP), Phase III, CP-3B: City of San Fernando Flood Control Works, Part

B-Outlet Channels & Bridges from Sta.0+000-Sta.0+840 (San Fernando River): 0+000-2+021.14 (Matulid Creek);

Sta.0+000-2+161.07(PAU Creek); Sta.0+400-Sta.1+494.02 (Dalaquitan Creek); Sta.0+083.84-Sta.3+500.86 (Mapalad Creek); and Sta.0+000-Sta.1+056.79, San Felipe (Cut-Off

Channel)

08/01/11 MPE-PMO 490.933 540 O 0.387 0.300 0.079 0.030 0.058 0.050 90.40 -

Tokwing Construction / Northern Builders (JV) JV-09-017

Pinatubo Hazard Urgent Mitigation Project (PHUMP), Phase III, CP-3B: City of San Fernando Flood Control Works, Part B- Outlet Channels and Bridges from Sta.

0+000-Sta. 0+840 (San Fernando River); Sta.0+000- Sta. 2+021.14 (Matulid Creek); Sta 0+000- Sta. 2+161.07 (PAU Creek); Sta. 0+400-Sta 1+494.02 (Dalaquitan Creek); Sta 0+083.84- Sta 3+500.86 (Mapalad Creek); & Sta 0+00- Sta

1+056.79 San Felipe (Cut-Off Channel)

03/12/12 MPE-PMO 490.933 540 O 0.340 0.289 0.104 0.030 0.050 0.033 84.60 -

Tokwing Construction / Northern Builders (JV) JV-09-017

Pinatubo Hazard Urgent Mitigation Project (PHUMP), Phase III, CP-3B: City of San Fernando Flood Control Works, Part B-Outlet Channels and Bridges from Sta. 0+000-Sta. 0+840 (San Fernando River); Sta. 0+000-

2+021.14 (Matulid Creek); Sta. 0+000-2+161.07 (Pau Creek); Sta.0+400-Sta. 1+494.02 (Dalaquitan Creek); Sta.0+083.84-Sta. 3+50086 (Mapalad Creek; and Sta. 0+000-Sta. 1+056.79

San Felipe (Cut-Off Channel)

07/30/12 PMO-MPE 490.933 602 O 0.355 0.259 0.130 0.030 0.065 0.050 88.90 -

Tokwing Construction Corp. (Formerly: Tokwing Construction) 9650

Rd. Upgrading (Gravel to Conc.) along Kalinga-Abra Rd., K0476+000-K0479+697 w/ exception, (K0476+000-

K0479+539 (w/ exception) as per RBIA & K0480+300-K0482+640, (K0480+342-K0482+081 as per RBIA) Balenciagao Norte, Pasil & Balbalan Proper Sect.

08/08/13 CAR 124.174 448 O 0.333 0.300 0.150 0.030 0.050 0.033 89.60

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page275

Page 276: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Tokwing Construction Corp. (Formerly: Tokwing Construction) 9650

Rd. Upgrading (Gravel to Conc.) along Kalinga-Abra Rd., K0476+000-K0479+697 w/ exception, (K0476+000-

K0479+539 (w/ exception) as per RBIA) & K0480+300-0482+640, (K0480+342-K0482+081 as per RBIA)

Balenciagao Norte, Pasil & Balbalan Proper Sect.

03/19/13 CAR 124.174 388 O 0.365 0.300 0.150 0.030 0.045 0.033 92.30 -

Tokwing Construction Corp. (Formerly: Tokwing Construction) 9650

Rd. Upgrading (gravel to concrete) along Kalinga-Abra Rd., K0476+000-K0479+697 w/ exception, (K0476+000-

K0479+539 (with exception) as per RBIA) & K0480+300-K0482+640, (K0480+342-K0482+081 as per RBIA) Balenciagao Norte, Pasil & Balbalan Proper Sect.

11/28/12 CAR 124.174 388 O 0.280 0.183 0.113 0.007 0.032 0.033 64.80 -

TOKWING CONSTRUCTION CORP.(Formerly TOKWING

Construction)9650

Road Upgrading (Gravel to Concrete) of Kalinga-Abra Road, K0476+00 to K0473+697 with Exception, (K0476+000 to K0479+539 (with exception) as per RBIA) & K0480+300

to K0482+640 (K0480+342 to K0482+081 as per RBIA) Balenciago Norte, Pasil & Balbalan Proper Section

8/8/2014 CAR 124.173 535 C 0.358 0.133 0.300 79.10 79.10% Unsatisfactory

TOKWING CONSTRUCTION, CORP. (Formerly: Tokwing Construction) 9650 Restoration of Santol Creek, Slope Protection 11/18/2014 III 8.473 90 C 0.439 0.133 0.300 - - - 87.20% 87.2%

Satisfactory

Tokwing/ZM Construction (JV) JV-08-274 Const./Replacement of Bucao Bridge and Approaches along Iba South Road over Bucao River 05/27/09 III 144.750 250 O 0.384 0.253 0.150 0.030 0.051 0.050 91.80 -

Tokwing/ZM Construction (JV) JV-08-075 Const. of Tarlac-Nueva-Ecija-Aurora-Dingalan Port Road (Jct. Fort Magsaysay-Laur Section) Contract Package 2 05/30/09 III 298.974 360 O 0.364 0.300 0.150 0.030 0.040 0.050 93.40 -

Tokwing/ZM Construction (JV) JV-08-075 Const. of Tarlac-Nueva Ecija-Aurora-Dingalan Port Road (Jct. Fort Magsaysay-Laur Section) Contract Package 2 09/07/09 III 298.974 360 O 0.388 0.300 0.150 0.030 0.040 0.050 95.80 -

Toledo Const. Corp./ Advanced Foundation Const. System Corp.

(JV)JV-02-063 NAIA Expressway & its Related Road Proj. Phase I,

Package 3, Skyway Ramps 2 & 3 08/28/08 URPO 721.651 1,543 O 0.330 0.300 0.000 0.030 0.047 0.100 80.70 -

TONGKA CONSTRUCTION 4064 Preventive Maintenance of Angeles - Porac Floridablanca - Dinalupihan Road, K0091+633 - K0092+000 8/11/2014 III 4.826 25 C 0.456 0.133 0.300 88.90 88.90%

Satisfactory

TONKA CONSTRUCTION 4064 Construction of Roads, San Juan Bano-Gatiawin to Aquino Byway 11/17/2014 III 9.488 133 O 0.380 0.240 0.150 0.030 0.047 0.033 88.00% 88%

SatisfactoryTop Most Development &

Marketing Corporation 13361 Completion of Pociento Bridge, Brgy. Canipayan 02/25/10 VI 4.767 120 O 0.320 0.300 0.150 0.020 0.032 0.050 87.20 -

Top Most Development & Marketing Corporation 13361 Road Upgradingof Oton-Mambog-Cabolo-An-Abilay-San

Jose Road 06/10/09 VI 9.461 150 O 0.355 0.300 0.150 0.030 0.060 0.050 94.50 -

Top Most Development & Marketing Corporation 13361 Road Upgrading of Oton-Mambog-Cabolo-An-Abilay-San

Jose Road 09/10/09 VI 9.461 180 O 0.358 0.300 0.150 0.030 0.050 0.050 93.80 -

Top Most Development and Marketing Corp. 13361 Const. of Drainage System, Arnaldo Blvd., Km. 116+400-

Km. 118+100 08/18/13 VI 9.034 115 C 0.351 0.200 0.300 - - - 85.10 *85.10% Satisfactory

Top Most Development and Marketing Corp. 13361 Const. of Passi Bridge 03/19/12 VI 5.071 120 C 0.485 0.200 0.300 - - - 98.50 91.78%

V. Satisfactory

Top Most Development and Marketing Corp. 13361

Restoration (80 mm. Asphalt Concrete) of Oton-Pakiad-Mandurriao Rd. at K009+(-779)-K009+(-239), Reblocking

PCC at K0010+402-K0010+77203/20/12 VI 9.118 207 C 0.397 0.200 0.300 - - - 89.70 85.56%

Satisfactory

Top Most Development and Marketing Corp. 13361 Upgrading/Conc. of Iloilo-Antique Rd., Crossing Dapuyan

to Ginot-an Sect. to Miag-ao 03/19/12 VI 9.512 180 C 0.095 0.200 0.300 - - - 59.50 76.06% Unsatisfactory

Topmost Development and Marketing Corp. 13361 Conc. of Lambunao-Inca Road, Km. 49+257 - Km. 59

+793.70 with exception 09/05/10 VI 7.091 150 O 0.375 0.240 0.150 0.030 0.051 0.033 87.90 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page276

Page 277: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Toptech Trading & Construction Co. Inc. (Formerly: Top Tech Trading and Construction)

25522Rehab./Reconst./Upgrading of Damaged Paved Nat'l. Rds. (MFO-2), (Int. Sect.) Banay-banay-Mojon-Rd., K0090+229-

K0090+84908/02/13 IVA 7.737 45 C 0.395 0.139 0.300 - - - 83.40 *83.40%

Satisfactory

TOPTECH TRADING & CONSTRUCTION CO., INC. 25522

Widening of Manila-Batangas Diversion Road including Drainage System, K0061+015 to K0061+745, Sto. Tomas

Section, Batangas 3rd LD12/2/2014 IV 39.018 390 O 0.345 0.300 0.150 0.012 0.035 0.017 85.90% 85.9%

Satisfactory

Toptech Trading & Construction Co., Inc. (Formerly: Top Tech

Trading and Construction)25522

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. (MFO-2), (Intermittent Sect.) Manila-Batangas Rd.

K0068+000-K0068+40003/14/13 IVA 7.510 45 C 0.462 0.133 0.300 - - - 89.50 *89.50%

V. Satisfactory

Toptech Trading & Construction Co., Inc. (Formerly: Top Tech

Trading and Construction)25522 Repair/Rehab./Imprv't. of Tanauan-Talisay-Tagaytay Rd.,

K0073+873-K0074+573 03/14/13 IVA 9.692 60 C 0.444 0.133 0.300 - - - 87.70 *87.70% Satisfactory

Toptech Trading & Construction Co., Inc. (Formerly: Top Tech

Trading and Construction)25522 Prev. Maint. (MFO-1) (Intermittent Sect.) Lipa-Balete Rd.,

K0084+000-K0084+463 03/14/13 IVA 4.694 20 C 0.428 0.133 0.300 - - - 86.10 *86.10% Satisfactory

Toptech Trading & Construction Co., Inc. (Formerly: Top Tech

Trading and Construction)25522 Prev. Maint. (MFO-1) (Intermittent Sect.) Lipa-Balete Rd.,

K0087+000-K0087+751 03/14/13 IVA 7.403 45 C 0.410 0.133 0.300 - - - 84.30 *84.30% Satisfactory

Toreja's Construction Supply Corporation 15453

Prevent Maint of Natl Scdry Rd Based on PMS/HDM-4 (Inter Sect) along Diokno Hway at 1: K0077+000 to

K00077+100, 2: K0078+834 to K0078+994 and 3: K0082+689 to K0083+500

8/6/2014 IV-A 26.177 179 C 0.447 0.200 0.300 94.70 94.70% Very Satisfactory

Toreja's Construction Supply Corporation 15453

Preventive Maintenance Based on Pavement Management System/Highway Development & Management-4 (HDM-4)

(Intermittent Section), Sdry. Rd. along Batangas Port Diversion Rd., K0102+194 to K0102+824

8/7/2014 IV-A 19.554 75 C 0.325 0.200 0.300 82.50 82.50% Satisfactory

Toreja's Construction Supply Corporation 15453 Widening along Palico-Balayan-Batangas Rd., Mahayhay

Jct. 07/30/13 IVA 9.667 141 C 0.464 0.133 0.300 - - - 89.70 90.06% V. Satisfactory

Toreja's Construction Supply Corporation 15453 Widening along Palico-Balayan-Batangas Rd., Mahayhay

Jct. 03/13/13 IVA 9.667 120 O 0.378 0.240 0.150 0.030 0.055 0.050 90.30 -

Toreja's Construction Supply Corporation 15453

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. along Batangas-Tabangao-Lobo Road, (K0109+403-

K0110+035), Brgy. San Isidro03/22/12 IVA 10.252 138 C 0.433 0.133 0.300 - - - 86.60 90.92%

V. Satisfactory

TOREJA'S CONSTRUCTION SUPPLY CORPORATION  15453

Rehabilitation/Reconstruction/Upgrading Damaged Paved National Road Including Drainage Based on Pavement

Management System/Highway Development Management-4 (HDM-4) San Pablo-Rizal-Nagcarlan-Liliw

11/27/2014 IV 43.305 209 O 0.380 0.300 0.150 0.030 0.061 0.033 95.40% 95.4% Very Satisfactory

TOREJA'S CONSTRUCTION SUPPLY CORPORATION  15453

Rehabilitation/Reconstruction/Upgrading Damaged Paved National Road Including Drainage Based on Pavement

Management System/Highway Development Management-4 (HDM-4) Calauan-Nagcarlan Road, K0088+600-K0090+153

(Intermittent Section)

11/27/2014 IV 26.894 200 O 0.363 0.300 0.150 0.030 0.064 0.033 94.00% 94% Very Satisfactory

TOREJA'S CONSTRUCTION SUPPLY CORPORATION  15453

A) Rehab/Reconst/Upgrading of Damaged Paved Natl Rd incl Drainage Based on Pavt Mgnt System/H-way Devt &

Mgnt-4 (HDM-4) (IS), Banay-Banay-Mojon-Cuenca Rd K0092+197-K0092+369 b) Rehab/Reconst/Upgrading of

Damaged Paved Natl Rd incl Drainage Based on Pavt Mgnt System/H-way Devt & Mgnt-4 (HDM-4) (IS), Banay-Banay-

Mojon-Cuenca Rd K0093+964-K0094+277

12/2/2014 IV 8.302 90 C 0.492 0.133 0.300 - - - 92.50% 92.5% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page277

Page 278: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

TOREJA'S CONSTRUCTION SUPPLY CORPORATION  15453

Preventive Maintenance Based on Pavement Management System/Highway Dev't & Mgnt-4(HDM-4) (Intermittent Section) Arterial Road Along Palico-Batangas road,

K0145+000 to K0145+800

12/6/2014 IV 12.286 50 C 0.481 0.136 0.300 - - - 91.70% 91.7% Very Satisfactory

Toyo Construction Co. LTD / Tobishima Corporation (JV) FC-06-034 CP IV, Urgent Bridges Const. Project for Rural Devt.,

Quinoguitan Bridge 03/31/11 UBCPRD 61.123 24 Months O 0.393 0.240 0.000 0.030 0.042 0.033 73.80 -

Toyo Construction Co. LTD / Tobishima Corporation (JV) FC-06-034 CP IV, Urgent Bridges Const. Project for Rural Devt.,

Moawa Bridge 03/31/11 UBCPRD 46.073 24 Months O 0.372 0.240 0.000 0.030 0.042 0.033 71.70 -

Toyo Construction Co. Ltd. FC-09-006 Const. of Pinatubo Hazard Urgent Mitigation Project,

Phase III, CP-4 Excavation & Dredging of Major Rivers from Sta. 5+850-Sta. 22+820

08/15/12 MPE-PMO 923.149 944 O 0.373 0.300 0.149 0.030 0.065 0.033 95.00 -

Toyo Construction Co., Ltd. FC-09-006Const. of Pinatubo Hazard Urgent Mitigation Project

(PHUMP), Phase III, CP-4 (Excavation and Dredging of Major Rivers from Sta.5+850 to Sta.22+820)

08/01/11 MPE-PMO 868.134 780 O 0.397 0.297 0.150 0.030 0.047 0.050 97.10 -

Toyo Construction Co., Ltd. FC-09-006 Pinatubo Hazard Urgent Mitigation Project-Phase III, CP No.4 (Dredging and Channel Excavation of Major River) 03/31/11 MPE 922.421 780 O 0.400 0.300 0.150 0.030 0.051 0.025 95.60 -

Toyo Construction Co., Ltd. - The Project for Flood Disaster Mitigation in Camiguin Island 04/02/11 MFCP II Y 780.000 550 O 0.361 0.300 0.150 0.030 0.070 0.050 96.10 -

Toyo Construction Co., Ltd. FC-09-006Const.. of Pinatubo Hazard Urgent Mitigation Project

(PHUMP), Phase III, CP-4 (Excavation and Dredging of Major Rivers from Sta.5+850-Sta.22+820)

03/13/12 MPE-PMO 868.134 847 O 0.400 0.300 0.150 0.030 0.051 0.050 98.10 -

Toyo-Nippon-Miyaji (JV) SL2-SN-000843

Const. of CP-1 UBCPRD (Construction of Pantal Bridge), Brgy. Kabayan Central 05/21/09 UBCPRD 26.777 28 mos. O 0.391 0.300 0.150 0.030 0.050 0.033 95.40 -

Toyo-Nippon-Miyaji (JV) SL2-SN-000843

Const. of CP-1 UBCPRD (Construction of Ellet Bridge), Brgy. Eddet, Kabayan Central 05/21/09 UBCPRD 26.777 273 O 0.371 0.300 0.150 0.030 0.060 0.033 94.40 -

Toyo-Tobishima (JV) FC-06-034 Const. of Tagbalidbid 2 Bridge Cagwait 03/03/10 UBCPRD 20.450 300 O 0.354 0.300 0.150 0.030 0.055 0.050 93.90 -

Toyo-Tobishima (JV) FC-06-034 Const. of Package III, Urgent Bridges Const. Projects for Rural Devt. (Bacao Bridge) 11/28/08 UBCPRD 23.103 10 mos. O 0.320 0.300 0.100 0.030 0.037 0.100 88.70 -

TR CONSTRUCTION 11697 Construction of Flood Control System, Ariman River 11/6/2014 V 9.346 120 C 0.403 0.133 0.300 - - - 83.60% 83.6% Satisfactory

Tracsom Builders Incorporated (Formerly: Tracsom Builders) 5935 Construction of 4-Storey, 16 Classroom School Building @

Sta. Lucia H/S 03/06/09 NCR 23.864 210 O 0.348 0.285 0.000 0.030 0.047 0.033 74.30 -

Tracsom Builders, Incorporated 5935 Const. of 4-Storeys, 36-Classroom Sch. Bldg. at San Andres Bonifacio Integrated Sch., Brgy. Addition Hills 03/22/13 NCR 39.879 360 C 0.460 0.079 0.300 - - - 83.90 85.86%

Satisfactory

Trans-Aurora Construction 11388 Road Upgrading (Gravel to Paved) Baler-Cemento via Dicaloyungan 06/05/10 III 20.639 160 O 0.378 0.234 0.150 0.030 0.055 0.033 88.00 -

Tribu Design & Construction 12756 Const. of Conner Central NHS Talifugu Annex 08/10/13 CAR 5.379 120 O 0.368 0.300 0.000 0.015 0.041 0.017 74.10

TRIBU DESIGN AND CONSTRUCTION 12756 Road Upgrading (Gravel to Paved) of Malalao National

Road, (Agbannawag - Malalao - Bulu Section) 11/27/2014 CAR 27.539 223 O 0.357 0.268 0.120 0.030 0.055 0.033 86.30% 86.3% Satisfactory

Tribu Design and Construction 12756 Const. of Sta Fe River Flood Control along Daang Maharlika, Calitlitan Section K0226+000 8/15/2014 II 7.519 120 C 0.372 0.186 0.300 85.80 85.80%

Satisfactory

Tribu Design and Construction 12756 Replacement of Camalugan Bridge along Balbalan-Pinukpuk Rd. 03/20/13 CAR 12.336 150 O 0.331 0.240 0.150 0.023 0.040 0.033 81.70 -

Tribu Design and Construction 12756Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd.

along Kalinga-Cagayan Rd. (Calanan-Enrile Sect.) K0520+000-K0522+000

08/09/12 CAR 15.429 129 C 0.392 0.200 0.300 - - - 89.20 88.84% Satisfactory

Tribu Design and Construction / Jann Norris Construction and

Supplies (Joint Venture)JV-12-319

Road Upgrading (Gravel to Paved) along Bambang-Kasibu-Solano Rd. 1)K0320+(-513)-K0320+(-384), 2)K0320+(-384)-

K0320+726, Runruno03/20/13 II 26.530 148 O 0.350 0.242 0.150 0.030 0.042 0.033 84.70 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page278

Page 279: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

TRIBU DESIGN AND CONSTRUCTION/JANN-NORRIS CONSTRUCTION AND SUPPLIES

(JV)

JV-13-599

Road Upgrading (Gravel to Paved) based on Gravel Road Strategies, Traffic Benchmark fo Upgrading to Paved Road

Standard (HDM-4 Project Analysis) Intermittent Section, Bambang-Kasibu-Solano Road, K0274+155 - K0274+762,

Macalong Section. K0277+519 - K0279+144, Watwat Section

10/30/2014 II 45.667 179 C 0.416 0.133 0.300 - - - 84.90% 84.9% Satisfactory

Triches Construction and Trading 33876 Asphalt Overlay of South Super Highways West Service Rd. (SO3298LZ) D=80MM, K0020+571-K0020+707 03/11/13 NCR 1.482 0 C 0.455 0.133 0.300 - - - 88.80 *88.80%

Satisfactory

Tri-Dom Trading & Construction 10843 Concreting of Barangay Road, San Isidro Village 02/24/10 V 1.149 120 O 0.364 0.240 0.150 0.030 0.035 0.050 86.90 -

Tri-Dom Trading and Construction 10843 Virac Port Projects 09/25/13 DOTC 4.897 120 C 0.483 0.133 0.300 - - - 91.66 *91.66% V. Satisfactory

Tri-dom Trading and Cosntruction 10843 Road Upgrading (Gravel to Paved) Baras-Gigmoto-Viga Road (K0031+500-K0031+900) Puraran-Benticayan Sect. 08/17/11 V 9.334 90 O 0.386 0.094 0.116 0.030 0.056 0.033 71.50 -

TRILEX BUILDERS and CONSTRUCTION SUPPLY

Rehabilitation and Development of Paco Market Wet Section 09/24/14 PRRC 18.889 75 C 0.401 0.200 0.300 - - - - 91.00%

V. SatisfactoryTRILEX BUILDERS and

CONSTRUCTION SUPPLYBioremediation Project in Estero de Valencia: Enclosed

Wetland for Drainages (PR-BT-02) 10/17/14 PRRC 4.682 120 C 0.361 0.200 0.300 - - - 86.10 *86.10% Satisfactory

TRILEX BUILDERS and CONSTRUCTION SUPPLY

Rehabilitation and Development of Paco Market Wet Section 04/08/14 PRRC 18.889 75 O 0.362 0.300 0.150 0.020 0.035 0.050 91.70 -

TRILEX Builders and Construction Supply

Poblacion Linear Park and Makati/Mandaluyong Bridge Link-Up 03/06/14 PRRC 0.674 45 C 0.485 0.200 0.300 - - - 95.80 *95.8% Very

SatisfactoryTrilex Builders Construction and

Supply 26590 Const. of MPB at the Albert E/S (Phase I) 08/14/08 NCR 1.919 90 O 0.231 0.300 0.100 0.030 0.047 0.100 80.80 -

Trimluv Builders and Supply 33467 Rehab./Impv't. of Bacolod North Rd. at K0038+883-K0039+363 (Km. 76+620 w/ exception) 08/12/13 VI 8.927 84 C 0.443 0.133 0.300 - - - 87.60 *87.60%

Satisfactory

Trimluv Builders and Supply 33467Reconst./Upgrading/ Conc. of Bacolod North Road; a) K0041+280-K0041+357; b) K0041+425-K0041+835; c)

K0041+835-K0041+843 (Cluster V)03/28/12 VI 11.645 225 C 0.413 0.200 0.300 - - - 91.30 88.60%

Satisfactory

Trinity Construction and Development 27755 Const. of 1 unit 2 CL S/B at Salingkubong PS 03/06/10 VII 0.852 100 O 0.392 0.217 0.150 0.030 0.045 0.050 88.40 -

TRIPARCO DEVELOPMENT CORPORATION 23327 Rehabilitation/Reconstruction/Upgrading of Nasipit Port

Road, Chainage 000-Chainage 0096 10/21/2014 XIII 0.898 37 C 0.423 0.133 0.300 - - - 85.60% 85.6% Satisfactory

TRIPARCO DEVELOPMENT CORPORATION 23327

Rehab./Reconst./Improvement of Butuan City - Cagayan de Oro - Iligan (Agusan - Misamis Or.), K1247+400 -

K1248+6408/15/2014 XIII 9.326 80 C 0.477 0.133 0.300 91.00 91.00%

Very Satisfactory

Triparco Development Corporation 23327 Repair/Rehab./Impvt. of Surigao-Davao Coastal Rd., Mangagoy-Lingig Sect., Km.1469+344-Km.1469+985 08/17/13 XIII 9.900 105 C 0.456 0.133 0.300 - - - 88.90 *88.90%

Satisfatory

Triparco Development Corporation 23327 Repair/Rehab./Impvt. of Daang Maharlika (Surigao-Agusan Rd.) along Pob. Sect., K1167+177-K1167+997 w/ exception 08/08/13 XIII 9.602 45 C 0.434 0.133 0.300 - - - 86.70 *86.70%

Satisfactory

Triparco Development Corporation 23327 Repair/Rehab./Impv't. of GCVR, Gingoog City Sect., Km.1317+146-Km.1317+937 w/ exception 08/20/13 X 9.402 38 C 0.428 0.200 0.300 - - - 92.80 92.80% V.

Satisfactory

Triparco Development Corporation 23327 Repair/Rehab./Impv't. of GCVR, Gingoog City Sect., Km.1316+354-Km.1317+146 w/ exception 08/20/13 X 9.415 38 C 0.402 0.200 0.300 - - - 90.20 *90.20%

V. Satisfactory

Triparco Development Corporation 23327Repair/Rehab./Impv't. of Daang Maharlika (Agusan-Davao

Rd)., Pasta-Rosario Sect., Km.1319+781.50-Km.1320+549.50

03/19/13 XIII 9.407 76 C 0.341 0.200 0.300 - - - 84.10 *84.10% Satisfactory

Triple 8 Construction & Supply 10684Prev. Maint. (Asphalt Overlay) of Cainta-Kaytikling-Antipolo-Teresa Road, 1. K0018+(035)-K0018+655;

K0020+000-K0021+300 (Int. Sect.)08/15/13 IVA 7.162 179 C 0.458 0.133 0.300 - - - 89.10 *89.10% V.

Satisfactory

Triple 8 Construction & Supply 10684 Widening of Cavite-Batangas Rd., Km.25+306-Km.26+960 08/14/13 IVA 31.912 369 C 0.347 0.200 0.300 - - - 84.70 83.74% Satisfactory

Triple 8 Construction & Supply 10684 Completion of Retaining Wall along R-10, Smokey Mountain 03/20/13 NCR 4.324 100 C 0.485 0.068 0.300 - - - 85.30 83.80%

SatisfactoryTriple 8 Construction & Supply 10684 Flood Control Angat River Paltao 06/10/10 III 4.772 105 O 0.389 0.240 0.150 0.015 0.053 0.033 88.00 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page279

Page 280: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Triple 8 Construction & Supply 10684Contract Package I, Const. of Slope Protection along

Daang Maharlika, Calbiga-Tacloban Rd. Sect., Km.849+475 -Km.866+904 w/ exceptions

06/17/10 VIII 37.711 95 O 0.358 0.300 0.150 0.030 0.042 0.033 91.30 -

Triple 8 Construction & Supply 10684Rehab./Reconst. of Meycauayan-Camalig Rd.

a)Km.020+000-Km.020+798; b)km.020+000-Km.020+596 (w/ exception); c)Km.027+000 - Km.028+000 (w/ exception)

03/17/12 III 15.718 120 C 0.343 0.200 0.300 - - - 84.30 83.88% Satisfactory

Triple 8 Construction & Supply 10684 Widening of Cavite-Batangas Rd., Km.25+306-Km.26+960 11/23/12 IVA 31.912 369 O 0.312 0.300 0.115 0.030 0.041 0.033 83.10 -

Triple 8 Construction & Supply 10684

Widening of Manila-Cavite Rd. (Kawit-Noveleta Diversion Rd. / CEZ Diversion Rd.) inc. RROW Acquisition

(Emergency Bays as holding areas for trucks & 40-footer vans for their maint. & repair)

11/23/12 IVA 31.520 180 O 0.310 0.260 0.150 0.030 0.045 0.033 82.80 -

Triple 8 Construction & Supply 10684 Revetment along Pampanga River, Sta. Lucia 03/18/13 III 4.795 35 C 0.450 0.133 0.300 - - - 88.30 *88.30% Satisfactory

Trisan Construction and Development 35083

Replacement (Temp. to Perm.) of San Vicente Bridge #2 (B00311LZ) along Libon-San Vicente-Buga Rd.,

K0493+556.3-K0493+564.3, San Vicente11/25/12 V 5.527 180 C 0.461 0.133 0.300 - - - 89.40 85.86%

Satisfactory

Trisan Construction and Development 35083

Replacement (Temporary to Permanent) of San Vicente Bridge #2 (B0011LZ) along Libon-San Vicente-Buga Rd.,

Brgy. San Vicente, K0493+556.3-K0493+564.308/08/12 V 5.527 180 O 0.339 0.240 0.150 0.030 0.043 0.033 83.50 -

Triumph Builders & Steel Inc. 2272 Const. of MPB at Mauban South Elem. School 02/26/09 IV-A 2.701 60 O 0.343 0.300 0.150 0.030 0.037 0.050 91.00 -

Triumph Builders & Steel Inc. 2272 Construction of 3-Storey, 15 Classroom School Bldg. 4/19/2010 NHA 21.886 150 O 0.3657 0.3000 0.1500 0.0150 0.0470 0.0500 92.77 -

Triumph Builders & Steel Inc. 2272 Construction of 3-Storey 15-Classroom School Building 06/18/09 NHA 18.113 150 O 0.381 0.252 0.150 0.024 0.047 0.050 90.36 -

Triumph Builders and Steel, Inc. Const. of 1 Unit 3-Storey School Building, Package 1 08/24/12 NHA 22.118 180 O 0.378 0.279 0.080 0.030 0.053 0.050 87.00 -

Triumph Builders and Steel, Inc. Const. of 1 Unit 3-Storey School Building, Package 1 05/10/12 NHA 22.118 180 O 0.367 0.260 0.150 0.030 0.053 0.050 91.00 -

TRM Construction and Development Corp. 30731 Construction of Livelihood, Production & Training Center 3/12/2010 NHA 4.990 90 O 0.359 0.287 0.113 0.024 0.035 0.033 85.10 -

TRM Construction and Development Corp. 30731 Construction of 3-Storey School Building 09/23/08 NHA 17.200 150 O 0.283 0.300 0.000 0.030 0.032 0.100 74.51 -

TRYST BUILDERS ENTERPRISES 31164 Completion of Multi-Purpose Building 11/19/2014 CAR 9.019 150 O 0.310 0.272 0.150 0.030 0.047 0.033 84.20% 84.2% Satisfactory

TRYST BUILDERS ENTERPRISES 31164 Construction of Maton Flood Control, Calanasan, Apayao 8/10/2014 CAR 3.812 150 OG 0.273 0.240 0.150 0.020 0.041 0.050 77.40

TSD BUILDERS CONSTRUCTION AND SUPPLY 22129

Const./Widening/Upgrading/Rehab. of Access Road to declared tourism destinationalong Bacolod City Boundary

Road8/11/2014 VI 23.350 269 C 0.416 0.200 0.300 91.60 84.82%

Satisfactory

TSD Builders Construction and Supply 22129

Const./Widening/Upgrading/Rehab. of Access Rd. to Declared Tourism Destination along Bacolod City Bdry.

Rd.08/06/13 VI 23.350 218 O 0.397 0.240 0.063 0.023 0.047 0.033 80.30

T-SQUARE BUILDERS 14268Road Upgrading (Gravel to Concrete) along Paco--Roxas-

Arakan Valley Junction Davao-Bukidnon Road, K1689+788 -K1691+403.80

8/16/2014 XII 80.181 320 C 0.420 0.186 0.300 90.60 90.60% Very Satisfactory

T-SQUARE BUILDERS 14268 Widening of Digos-Makar Road, South Cotabato K1640+251 to K1642+337, Katangawan Section 8/16/2014 XII 46.953 180 C 0.412 0.191 0.300 90.30 90.30%

Very Satisfactory

T-Square Builders 14268 Const. of Additional 2 Lanes along Davao-Cotabato Road (Poblacion Bansalan Sect.) 04/02/11 XI 9.638 150 O 0.385 0.300 0.150 0.030 0.035 0.050 95.00 -

T-Square Builders 14268 Impvt./Conc. of Road at Bansalan-Mt. Apo National Park Road 03/06/09 XI 28.919 270 O 0.274 0.273 0.150 0.030 0.054 0.033 81.40 -

T-Square Builders 14268 Impvt./Conc. of Road at Bansalan-Mt. Apo National Park Road 11/19/08 XI 28.919 270 O 0.214 0.279 0.100 0.030 0.040 0.100 76.30 -

T-Square Builders 14268 Conc. of Road & Reblocking, Marbel-Makar Road, Palian Section 03/20/09 XII 15.102 180 O 0.363 0.240 0.150 0.030 0.035 0.050 86.80 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page280

Page 281: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

T-Square Builders 14268 Const. of Drainage Structure along Marbel-Makar Rd. 11/24/12 XII 12.500 328 C 0.482 0.133 0.300 - - - 91.50 86.82% Satisfactory

TUCHAR CONSTRUCTION 13644 Rehabilitation of Drainage System along O. De Guzman Street & Vicinity Brgy. IVC 11/29/2014 NCR 13.949 180 C 0.469 0.133 0.300 - - - 90.20% 90.2%

Very SatisfactoryTURQUOISE CONSTRUCTION & TRADING(Formerly: Turquoise

Construction)21801 Construction of Slope Protection along Burakan Creek 11/17/2014 III 6.673 118 O 0.293 0.240 0.150 0.030 0.037 0.033 78.30% 78.3%

Unsatisfactory

TWIN DRAGON CONSTRUCTION CONSTRUCTION OF PROV. SCIENCE & TECHNOLOGY BUILDING 02/19/13 DOST 4.656 120 C 0.481 0.200 0.300 - - - 98.10 *98.1

Outstanding

TWINA BUILDERS AND SUPPLY 23897Construction of One (1) Storey, Three (3) Classroom

School Building, Moria E/S, Banlag, Monkayo, Comval Province

8/9/2014 XI 2.197 45 C 0.490 0.133 0.300 92.30 92.30% Very Satisfactory

Twina Builders & Supply 23897 Rehabilitation/Repair of Boy's Residence Hall 08/14/14 DOST 2.226 90 C 0.487 0.200 0.183 - - - 87.03 *87.03% Satisfactory

TWINA BUILDERS AND SUPPLY 23897 Completion of the DPWH-Standard Two (2) Storey Building of Agusan del Sur 2nd District Engineering Office 10/23/2014 XIII 9.506 180 O 0.325 0.284 0.150 0.020 0.022 0.050 85.10% 85.1%

Satisfactory

TWINA BUILDERS AND SUPPLY 23897 Local Infrastructure Program-Construction of Local Road at San Roque 10/24/2014 XIII 4.980 133 C 0.416 0.145 0.278 - - - 83.90% 83.9%

Satisfactory

Ubas Construction 18875 Const./Impvt./Rehab. of La Perla-Cabulaloan-Yabyaban Road 03/03/09 VIII 14.160 467 O 0.251 0.225 0.070 0.030 0.037 0.050 66.30 -

Ubas Construction 18875 Const./Impvt./Rehab. of La Perla-Cabulaloan-Yabyaban Road 08/31/08 VIII 14.160 270 O 0.344 0.225 0.050 0.030 0.032 0.067 74.80 -

UKC Builders, Inc. 10759 Bayanihan sa Iligan Village, Brgy. Sta. Elena 03/15/13 X 66.500 240 C 0.429 0.133 0.300 - - - 86.20 89.44% V. Satisfactory

UKC Builders, Inc. 10759 Cebu North Coastal Road, Phase I 09/03/08 VII 43.189 228 O 0.380 0.225 0.070 0.030 0.037 0.100 84.20 -UKC Builders, Inc./ Equi-parco

Construction. Co., Inc - JV J.V. -09-097 Cagayan de Oro Improvement Project (Ports & Harbor) 09/05-09/11 PPA 187.898 540 O 0.467 0.200 0.300 - - - 96.74 -

UKC Builders, Inc./ Equi-parco Construction. Co., Inc - JV J. V.-09-097 Const. of Cagayan de Oro Improvement Project (Ports &

Harbor) 02/2-5/11 PPA 187.898 540 O 0.355 0.298 0.150 0.030 0.070 0.050 95.36 -

UKC BUILDERS, INCORPORATED 10759 WHARF EXTENSION, PORT OF CAGAYAN DE ORO 07/24/15 PPA 59.254 300 O 0.370 0.300 0.150 0.020 0.065 0.050 95.50 -

Ulticon Builders Inc. 17267 Rehabilitation/Improvement of National Road along Daang Maharlika 02/27/10 XI 144.738 270 O 0.368 0.300 0.150 0.030 0.055 0.050 95.30 -

Ulticon Builders Inc. 17267 Const./Impvt. of Davao Del Sur-Sarangani Coastal Road, Meybio-Glan Bdry. Section 02/24/10 XI 96.289 280 O 0.338 0.300 0.150 0.030 0.056 0.050 92.40 -

Ulticon Builders Inc. 17267 Conc. of San Ildefonso-Hulid Sect. along Cateel-Compostela Rd. 03/03/10 XI 62.856 300 O 0.309 0.240 0.150 0.030 0.055 0.050 83.40 -

Ulticon Builders Inc. 17267 Repair/Rehab./Impvt. of Daang Maharlika Rd. 06/04/10 XI 88.226 180 O 0.374 0.284 0.102 0.030 0.051 0.033 87.40

Ulticon Builders Inc. 17267 Conc. of San Alfonso-Hulid Sect. along Cateel-Compostela Rd. 06/06/10 XI 62.856 330 O 0.326 0.234 0.150 0.030 0.056 0.050 84.60 -

Ulticon Builders Inc. 17267 Rehab./Reconst. of Sayre Highway (Kisolon-Lumbo Section) 09/04/09 X 189.228 300 O 0.286 0.290 0.150 0.030 0.051 0.033 84.00 -

Ulticon Builders Inc. 17267 Impvt./Conc. of Surigao Sur-Davao Oriental Coastal Road (Manay Boston) Boston Section 06/09/09 XI 286.479 600 O 0.367 0.300 0.150 0.030 0.065 0.050 96.20 -

Ulticon Builders Inc. 17267 Rehab./Reconst./Upgrading of Digos Diversion Road 05/30/09 XI 46.834 220 O 0.365 0.300 0.150 0.030 0.042 0.050 93.70 -

Ulticon Builders Inc. 17267 CP-10: Imprvt./ Conc. of Surigao-Davao Oriental Coastal Road, (Manay-Boston) Boston Section 09/11/09 XI 286.477 600 O 0.373 0.300 0.150 0.030 0.054 0.033 94.00 -

Ulticon Builders Inc. 17267 Rehab./Reconst./Upgrading of Damaged Paved National Road along Daang Maharlika 09/07/09 XI 192.020 540 O 0.373 0.240 0.150 0.030 0.059 0.050 90.20 -

Ulticon Builders Inc. 17267 Rehab./Upgrading of Digos Diversion Road 09/05/09 XI 46.834 220 O 0.374 0.240 0.150 0.030 0.054 0.050 89.80 -

Ulticon Builders Inc. 17267 CP 10: Impv't./Conc. of Surogao Sur-Davao Oriental Coastal Road (Manay-Boston) Boston Section 11/26/08 XI 286.479 600 O 0.345 0.284 0.100 0.030 0.060 0.100 91.90 -

ULTICON BUILDERS INCORPORATED 17267 Road Upgrading (Gravel to Concrete) of Bansalan Mt. Apo

National Park Road 8/8/2014 XI 70.833 231 OG 0.381 0.284 0.150 0.030 0.047 0.050 94.20

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page281

Page 282: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

ULTICON BUILDERS INCORPORATED 17267 Road Upgrading (Gravel to Concrete) of Bansalan Mt. Apo

National Park Road 8/7/2014 XI 56.518 365 C 0.453 0.168 0.300 92.10 90.84% Very Satisfactory

ULTICON BUILDERS, INC. 17267Improvement/Upgrading (Gravel to Concrete) of Island Garden City of Samal (IGACOS) Circumferential Road

(East Side) (Babak-Penaplata10/29/2014 XI 47.528 190 C 0.394 0.134 0.300 - - - 82.80% 82.8%

Satisfactory

Ulticon Builders, Inc. 17267 Repair/Rehab./Impv't. of Road along Sayre Highway, Laguitas, Km.1513+252 - Km.1514+914 (Phase II) 08/09/13 X 9.496 137 C 0.468 0.133 0.300 - - - 90.10 *90.10% V.

Satisfactory

Ulticon Builders, Inc. 17267 Repair/Rehab./Impv't. of Rd. along Sayre Highway, Laguitas, Km.1513+252-Km.1514+914 08/09/13 X 4.494 137 C 0.423 0.133 0.300 - - - 85.60 85.60%

Satisfactory

Ulticon Builders, Inc. 17267 Rd. Upgrading (Gravel to Concrete) of Bansalan Mt. Apo Nat'l Park Rd., Bansalan 08/06/13 XI 56.518 237 O 0.373 0.286 0.150 0.030 0.028 0.033 90.00

Ulticon Builders, Inc. 17267Assets Preservation of Nat'l Rds. Int. Sect. Sayre Highway,

a) K1555+270-K1556+000; b) K1559+000-K1560+000; c)K1560+330-K1561+000

08/08/13 X 22.857 75 C 0.401 0.133 0.300 - - - 83.40 85.14% Satisfactory

Ulticon Builders, Inc. 17267 Widening of Sayre Highway, Lumbo-Musuan Sect., K1540+249-K1540+344 08/20/13 X 21.668 183 C 0.388 0.133 0.300 - - - 82.10 83.12%

Satisfactory

Ulticon Builders, Inc. 17267

Assets Preservation of Nat'l. Rds. Gen. from Pvmt. Mgt. System Highway Dev't. & Mgt.-4 (HDM-4) (Int. Sect.) along

Sayre Highway a)K1555+270-K1556+000; b)K1559+000-K1560+000; c)K1560+330-K1561+000

03/20/13 X 22.857 75 O 0.330 0.300 0.150 0.010 0.040 0.033 86.30 -

Ulticon Builders, Inc. 17267 Widening of Sayre Highway, Lumbo-Musuan Sect., K1540+249-K1540+344 03/20/13 X 20.504 153 O 0.361 0.249 0.150 0.010 0.035 0.033 83.80 -

Ulticon Builders, Inc. 17267 Impv't./Conc. of Island Garden City of Samal (IGACOS) 03/17/13 XI 89.506 403 O 0.298 0.298 0.150 0.030 0.050 0.033 85.90 -

Ulticon Builders, Inc. 17267 Widening of Davao-Cotabato Rd. 03/15/13 XI 121.663 415 O 0.302 0.300 0.100 0.030 0.056 0.050 83.80 -Ulticon Builders, Inc. 17267 Widening of Davao-Cotabato Rd. 11/23/12 XI 121.663 351 O 0.360 0.300 0.061 0.030 0.051 0.033 83.50 -Ulticon Builders, Inc. 17267 Impvt./Conc. of Island Garden City of Samal 11/28/12 XI 86.288 307 O 0.383 0.292 0.061 0.030 0.056 0.000 82.20 -Ulticon Builders, Inc. 17267 Impvt./Conc. of Island Garden City of Samal 08/22/12 XI 86.288 214 O 0.359 0.231 0.150 0.030 0.051 0.033 85.40 -Ulticon Builders, Inc. 17267 Widening of Davao-Cotabato Rd. 08/11/12 XI 121.663 244 O 0.383 0.300 0.006 0.030 0.060 0.050 82.90 -

Ulticon Builders, Inc. 17267 Rehab./Impv't./Conc. of Surigao Sur-Davao Oriental Coastal Rd. (Manay-Boston Sect.) 08/17/12 XI 361.280 522 C 0.417 0.200 0.036 - - - 65.30 76.82%

Unsatisfactory

Unitec Builder Inc. 4803 Proposed Widening of Sinunuc Bridge and Approaches, Phase II 02/22/10 IX 11.878 545 O 0.383 0.300 0.150 0.030 0.047 0.050 96.00 -

Unitec Builder Inc. 4803 Rehab. of Daang Maharlika Highway, Sect. 8, Allen-Malaga Rd. Sect., Km.687+366.55 - Km.690+866.55 w/ exceptions 06/16/10 VIII 96.441 200 O 0.357 0.300 0.150 0.030 0.042 0.033 91.20 -

Unitec Builder Inc. 4803 Rehab. of Daang Maharlika Highway, Sect 7, Allen-Malaga Rd. Sect., Km.683+866.55 - Km.687+366.55 w/ exceptions 06/16/10 VIII 96.435 200 O 0.354 0.300 0.150 0.030 0.042 0.033 90.90 -

Unitec Builder Inc. 4803 Rehab./Const./Upgrading of Damaged Paved National Rd. along Catarman-Laoang Rd. 06/14/10 VIII 47.963 150 O 0.350 0.240 0.150 0.030 0.042 0.050 86.20 -

Unitec Builder Inc. 4803 Improvement/Rehabilitation of R.T. Lim Boulevard 05/26/09 IX 18.661 270 O 0.343 0.240 0.150 0.010 0.042 0.050 83.50 -Unitec Builder Inc. 4803 Improvement/Rehabilitation of R.T. Lim Boulevard 09/02/09 IX 18.661 300 O 0.311 0.300 0.150 0.023 0.045 0.033 86.20 -

Unitec Builder Inc. 4803 Rehab./Impvt. of Balite-Seven Hills-Happy Valley Section 03/07/09 VIII 19.176 180 O 0.294 0.205 0.150 0.030 0.047 0.050 77.60 -

Unitec Builder Inc. 4803 Concreting of San Jose-Mandugang National Road 09/14/09 VIII 19.277 180 O 0.337 0.240 0.150 0.030 0.050 0.033 84.00 -

Unitec Builder Inc. 4803 Widening of Sinunuc Bridge & Approaches, Phase I, along Zamboanga City-Labuan Road 11/18/08 IX 21.668 436 O 0.354 0.289 0.100 0.030 0.045 0.100 91.80 -

Unitec Builder Inc. 4803 Proposed Widening of Sinunuc Bridge & Approaches, Phase I, along Zamboanga City-Labuan Road 08/21/08 IX 21.672 436 O 0.311 0.240 0.000 0.030 0.042 0.067 69.00 -

Unitec Builder, Inc. 4803 Rehabilitation of Bridges at Ayala Bridge #2 along Zamboanga City-Labuan-Limpapa Road 8/5/2014 IX 30.963 505 C 0.453 0.133 0.300 88.60 85.89%

Satisfactory

Unitec Builder, Inc. 4803

Rd. Upgrading (Gravel to Paved) Int. Sect., Zamboanga West Coast Rd., Limpapa-Sibuco Sect.) K1979+(-685)-

K1980+000- K1981+980 Re: K1979+(-685)-K1981+980 w/ exceptions

08/05/13 IX 46.026 201 O 0.343 0.238 0.150 0.030 0.037 0.033 83.10

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page282

Page 283: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Unitec Builder, Inc. 4803 Rehab./Reconst./Strengthening of Bridges at Ayala Bridge #2 along Zamboanga City-Labuan-Limpapa Rd. 08/05/13 IX 30.963 375 O 0.374 0.300 0.000 0.030 0.047 0.033 78.40

Unitec Builder, Inc. 4803Impv't./Downgrading of Zamboanga City/Zamboanga del

Norte Bdry. to Sibuco, Limapa-Malayal Sect., Sta.1978+640-Sta.1979+680 w/ exception

08/05/13 IX 64.362 285 C 0.452 0.014 0.000 - - - 46.60 66.64% Poor

Unitec Builder, Inc. 4803 Rd. Upgrading (Gravel to Paved) Int. Sect., Siocon-Sirawai Rd., K2080+000-K2081+300 03/17/13 IX 37.750 105 O 0.329 0.234 0.150 0.030 0.045 0.033 82.10 -

Unitec Builder, Inc. 4803 Rehab./Reconst./Strengthening of Bridges at Ayala Bridge #2 along Zamboanga City-Labuan-Limpapa Rd. 03/12/13 IX 30.776 325 O 0.391 0.300 0.022 0.030 0.042 0.033 81.80 -

Unitec Builder, Inc. 4803Impv't./Downgrading of Zamboanga del Norte, Brgy. to

Sibuco, Limpapa-Malayal Sect., Sta.1978+640-Sta.1979+680 w/ equation

03/12/13 IX 64.317 225 O 0.367 0.300 0.000 0.030 0.042 0.033 77.20 -

Unitec Builder, Inc. 4803 Rehab./Upgrading of RT Lim Boulevard, (Km.1940+314-Km.1940+2034) Baliwasan Seaside Sect. 03/20/12 IX 17.404 210 C 0.404 0.133 0.300 - - - 83.70 83.70%

Satisfactory

Unitec Builder, Inc. 4803Road Upgrading (Gravel to Paved) based on Gravel Road

Strategies/HDM-4 (IS), Siocon-Sirawai Road (Km.2076+193-Km.2077+913)

03/22/12 IX 38.058 158 C 0.341 0.133 0.300 - - - 77.40 82.50% Satisfactory

Unitec Builder, Inc. 4803Impvt./Downgrading of Zamboanga City/Zamboanga del

Norte Bdry. to Sibuco, Limpapa-Malayal Sect., Sta.1978+640-Sta.1979+680 w/ equation

11/19/12 IX 64.317 225 O 0.332 0.211 0.150 0.030 0.055 0.050 82.80 -

Unitec Builder, Inc. 4803 Rehab./Reconst./ Strengthening of Bridges at Ayala Bridge #2 along Zamboanga City-Labuan-Limpapa Rd. 11/19/12 IX 30.776 295 O 0.360 0.300 0.050 0.030 0.053 0.033 82.60 -

Unitec Builder, Inc. 4803 Rehab./Reconst./Strengthening of Bridges at Ayala Bridge #2 along Zamboanga City-Labuan-Limpapa Rd. 08/13/12 IX 30.776 295 O 0.400 0.300 0.147 0.023 0.032 0.033 93.50 -

Unitec Builder, Inc. 4803 Rd. Upgrading (Gravel to Paved) of Zamboanga City-Labuan-Limpapa Rd. 08/13/12 IX 18.655 251 C 0.409 0.133 0.300 - - - 84.20 85.58%

SatisfactoryUnitec Builder, Inc. / EZJones

Const., Inc. (JV) JV-11-363 Const./Repair/Rehab./Impv't. of San Isidro-Lope De Vega Rd. 08/15/12 VIII 142.362 244 O 0.367 0.300 0.150 0.030 0.040 0.033 92.00 -

Unitec Builder, Inc. / EZJones Const., Inc. (JV) JV-11-121 Rd. Upgrading of San Isidro-Lope De Vega Rd. (Sta.0+000-

Sta.3+650 w/ exception) 08/15/12 VIII 94.084 350 O 0.357 0.300 0.150 0.030 0.040 0.033 91.00 -

Unitec Builder, Inc. / EZJones Const., Inc. (JV) JV-11-363 Concrete Paving of San Isidro-Lope De Vega Rd.,

Sta.1+860-Sta.8+250 with exceptions 08/15/12 VIII 137.989 300 O 0.348 0.237 0.150 0.030 0.040 0.033 83.80 -

Unitec Builder, Inc. / EZJones Construction, Inc. (JV) JV-11-230 Conc. of Trujillo-E. Duran-Gemaraganan Rd. (Sta. 745+500-

Sta. 749+340) w/ exceptions, Bobon & Lope de Vega 03/20/13 VIII 96.971 390 C 0.459 0.133 0.300 - - - 89.20 90.58% V. Satisfactory

Unitec Builder, Inc. / EZJones Construction, Inc. (JV) JV-11-300 Const./Repair/Rehab./Impv't. of San Isidro-Lope de Vega

Rd. 03/20/13 VIII 142.362 364 C 0.420 0.200 0.300 - - - 92.00 90.35% V. Satisfactory

Unitec Builder, Inc. / EZJones Construction, Inc. (JV) JV-11-573 Upgrading of Trujillo-E. Duran-Gemaraganan Road 03/20/13 VIII 47.646 200 C 0.392 0.200 0.300 - - - 89.20 *89.20%

V. SatisfactoryUnitec Builder, Inc. / RNMK

Construction and Development (JV)

JV-12-315Rd. Upgrading (Gravel to Paved) of Bugko-Nenita-Mirador Cagpanitan-De Maria-San Jose Rd., Sta.6+141-Sta.11+091

w/ exceptions08/09/13 VIII 134.287 300 O 0.356 0.289 0.150 0.030 0.060 0.050 93.50

Unitec Builder, Inc./EZJones Construction Inc. (JV) JV-11-230 Conc. of Trujillo-E. Duran-Gemaraganan Rd. (Sta.745+500-

Sta.749+340.00) w/ exceptions, Bobon & Lope De Vega 11/27/12 VIII 96.971 330 O 0.362 0.300 0.150 0.030 0.040 0.033 91.50 -

Unitec Builder, Inc./EZJones Construction Inc. (JV) JV-11-121 Const./Repair/Rehab./Impvt. of San Isidro-Lope de Vega

Rd., Sta. 00+000-Sta. 3+650 11/27/12 VIII 98.694 380 C 0.470 0.133 0.300 - - - 90.30 89.55% V. Satisfactory

Unitec Builder, Inc./EZJones Construction Inc. (JV) JV-11-230 Const./Repair/Rehab./Impvt. of San Isidro-Lope de Vega

Rd. 11/27/12 VIII 142.362 304 O 0.367 0.240 0.150 0.030 0.045 0.033 86.50 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page283

Page 284: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

UNITEC BUILDER, INC./RNMK CONSTRUCTION AND

DEVELOPMENT JOINT VENTUREJV-12-315

Road Upgrading (Gravel to Concrete) of Bugko - Nenita - Mirador Capinitan De Maria - San Jose Road, Sta.6+141 -

Sta.11+091 with exceptions8/9/2014 VIII 142.819 390 C 0.418 0.133 0.300 85.10 90.14%

Very Satisfactory

Unitec Builders 4803 Catarman Airport Development Project 02/12/14 DOTC 14.408 240 C 0.493 0.200 0.300 - - - 99.30 95.68% Very Satisfactory

Unitec Builders 4803 Catarman Airport Development Project 11/26/12 DOTC 14.408 240 O 0.391 0.300 0.150 0.015 0.035 0.050 94.10 -

UNITEC BUILDERS, INC. 4803 Widening Apitong - Paterno Road, K0908+(-868) - K0908+082 10/30/2014 VIII 26.558 179 O 0.342 0.240 0.150 0.023 0.040 0.050 84.50% 84.5%

Satisfactory

Unitec Builders, Inc. 4803 Rehab./Reconst. Of Damaged Paved Nat'l Road along Catarman-Laoang, K0744+(-348)-K0747+1001 03/21/12 VIII 25.702 240 C 0.300 0.200 0.300 - - - 80.00 84.38%

SatisfactoryUnitec Builders, Inc./Ezjones

Construction Inc. JV-11-121 Road Upgrading of San Isidro-Lope de Vega Road 03/22/12 VIII 94.084 350 O 0.400 0.225 0.150 0.030 0.033 0.033 87.10 -

UY CONDEV CORPORATION 12336 Const./Rehab. of Flood Control Project along Sayre Highway Km. 1508+500 - K1513+000 w/ exception 10/24/2014 X 17.171 195 C 0.372 0.200 0.252 - - - 82.40% 90.44%

Very Satisfactory

UY CONDEV CORPORATION 12336 Const. of Misamis Oriental - Bukidnon By-Pass Road PHIVIDEC - Alae Section 8/9/2014 X 46.318 209 C 0.455 0.200 0.300 95.50 90.34%

Very Satisfactory

UY CONDEV CORPORATION 12336 Construction/Rehab. Of Flood Control Projects along Sayre Highway K1508+500 - K1513+300 (with exception) 8/5/2014 X 17.171 195 OG 0.400 0.300 0.150 0.030 0.045 0.033 95.80

UY CONSTRUCTION 12336Construction/Widening/Upgrading/Rehabilitation of Access

Road to RORO Port, Sta. 0+000 to Sta. 1+706, K0000+560 to K0000+593.71 (Segment 3), K0001+520 to K0001+579.49

10/28/2014 III 45.895 239 O 0.356 0.300 0.029 0.030 0.051 0.000 76.60% 76.6% Unsatisfactory

Uy Construction & Development 12336 Reconst./Replacement of Juan Colon Bridge, Brgy. Mayabon 09/15/09 VII 26.141 389 O 0.390 0.240 0.150 0.030 0.042 0.050 90.20 -

Uy Construction & Development 12336 Imprv't/Concrete Paving of Dumaguete South Rd. Sta.0+859-Sta.1+100 and Sta. 1+900-Sta.5+380 09/15/09 VII 61.645 240 O 0.400 0.240 0.150 0.030 0.037 0.033 89.00 -

Uy Construction & Development 12336 Imprv't. of Bayawan-Kabankalan Rd. Sta. 1+250-Sta.3+020 09/16/09 VII 29.868 210 O 0.385 0.240 0.150 0.030 0.033 0.033 87.10 -

Uy Construction & Development 12336 Rehab./Reconst./Upgrading of Damaged National Rd. Dumaguete South Rd. Giligaon Sect. 06/09/10 VII 11.214 160 O 0.336 0.293 0.150 0.030 0.025 0.033 86.70 -

Uy Construction & Development 12336 Rehab. of Dumaguete South Road 09/03/10 VII 17.309 240 O 0.386 0.224 0.150 0.030 0.051 0.050 89.10 -

Uy Construction & Development 12336Rehab./Reconst./Upgrading of Guimaras Circ. Road,

Salvacion-Lucmayan Section, Km.84+000-Km.88+643 with exceptions

08/30/10 VI 24.179 360 O 0.372 0.238 0.150 0.030 0.051 0.033 87.40 -

Uy Construction & Development 12336 Rehab./Recons. of Iloilo East Coast Capiz Road, Barotac Viejo Section 06/09/09 VI 38.180 150 O 0.351 0.240 0.150 0.008 0.035 0.050 83.40 -

Uy Construction & Development 12336 Re-const./Replacement of Juan Colon Bridge Brgy. Mayabon 05/27/09 VII 26.141 389 O 0.345 0.300 0.150 0.030 0.051 0.050 92.60 -

Uy Construction & Development 12336 Concreting of Bais-Kabankalan Road (Intermittent Section) 05/27/09 VII 94.413 369 O 0.343 0.238 0.150 0.030 0.051 0.050 86.20 -

Uy Construction & Development 12336 Conc. of Dumaguete South Road (DSR) 03/12/09 VII 21.739 190 O 0.389 0.225 0.150 0.030 0.061 0.033 88.80 -

Uy Construction & Development 12336 Conc. of Dumaguete South Road (DSR) 11/26/08 VII 21.705 160 O 0.380 0.300 0.100 0.030 0.038 0.100 94.80 -

Uy Construction & Development/ARN Builders (JV) JV-07-001 Conc. of Bais-Kabankalan Road @ Intermittent Section 08/20/08 VII 95.268 300 O 0.295 0.221 0.070 0.030 0.065 0.100 78.10 -

Uy Construction and Development 12336 Const. of Misamis Oriental-Bukidnon By-Pass Rd. PHIVEDEC-Alae Sect., Mantibugao 08/07/13 X 46.318 209 O 0.330 0.281 0.150 0.030 0.045 0.033 86.90

Uy Construction and Development 12336 Const. of Iloilo Circ. Rd. (C-1) Sect. C-Jct. Jaro-Tocas Rd. to Jct. Iloilo Sta. Barbara Rd. 03/22/13 VI 123.507 353 C 0.470 0.133 0.300 - - - 90.30 86.70%

Satisfactory

Uy Construction and Development 12336 Const. of Misamis Oriental-Bukidnon By-Pass Rd. (PHIVEDEC-Alae) Capid Sect. 03/21/13 X 44.030 340 C 0.353 0.200 0.300 - - - 85.30 86.26%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page284

Page 285: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Uy Construction and Development 12336 Road Upgrading (Gravel to Paved) of Jct. SH. Manolo Fortich-Libona-Indahag Road (Camp 9-Poblacion Sect.) 03/31/11 X 14.984 172 O 0.368 0.225 0.054 0.030 0.042 0.050 76.90 -

Uy Construction and Development 12336 Rehab of Iloilo East Capiz Road, K193+895-K195+170.08 03/22/12 VI 14.029 120 C 0.413 0.200 0.300 - - - 91.30 87.04% Satisfactory

Uy Construction and Development 12336 Repair/Rehab. of Balabag-Sulangan Road, Km.27+950-Km.33+950 03/22/12 VI 31.271 300 C 0.461 0.133 0.300 - - - 89.40 85.92%

Satisfactory

V U C Engineering 7918Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd.

along Kalinga-Cagayan Rd. (Calanan-Enrile Sect.) K0398+366-K0499+000 & K0499+306-K0499+892

08/09/13 CAR 32.811 196 O 0.350 0.300 0.150 0.030 0.040 0.033 90.30

V U C Engineering 7918Rehab./Reconst./Upgrading of Damaged Paved Nat'l. Rd.

along Kalinga-Cagayan Rd. (Calanan-Enrile Sect.) K0398+366-K0499+000 & K0499+306-K0499+892

03/20/13 CAR 32.811 166 O 0.362 0.208 0.150 0.023 0.060 0.050 85.30 -

V. R. D. J. Construction 19837 Repair/ Rehabilitation of Manager's Residence, Ilagan Branch 07/04/12 DBP 1.377 180 C 0.323 0.200 0.300 - - - 82.34 82.60% Satisfactory

V. R. GUEVARRA CONSTRUCTION & TRADING 14-01-637 Hot Mix Asphalt Overlay at the Bellhouse Driveway and

Liberty Loop Road 01/13/15 BCDA 5.326 56 C 0.438 0.106 0.300 - - - - *84.34% Satisfactory

V. S. Cerdon Iron Works and Construction 24989 Plaridel-Pulilan Port Development Project 08/05/13 DOTC 4.358 120 C 0.430 0.200 0.300 - - - 93.00 *93.00%

V. Satisfactory V.B Manubay Construction 32705 Magat River Flood Control (Camarunggayan Sect.) 05/31/10 II 4.821 120 O 0.368 0.300 0.150 0.018 0.042 0.033 91.10 -V.B Manubay Construction 32705 Magat River Flood Control (Kalabaza Sect.) 05/31/10 II 4.823 120 O 0.343 0.300 0.150 0.024 0.042 0.033 89.20 -V.B Manubay Construction 32705 Magat River Flood Control (Apiat Sect.) 05/31/10 II 4.823 120 O 0.342 0.300 0.150 0.024 0.042 0.033 89.10 -

V.B. Gines Construction 21993 Rehab./Reconst./Upgrading of Damaged Paved Nat'l. Rds. (IS) Daang Maharlika, K0255+000-K0256+000, Abian Sect. 08/15/12 II 10.531 68 C 0.408 0.200 0.300 - - - 90.80 82.52%

Satisfactory

V.B. MANUBAY CONSTRUCTION 32705 Rehabilitation/Construction of Flood Control Facilities, Gucab Flood Control 10/27/2014 II 14.318 150 O 0.291 0.240 0.150 0.030 0.033 0.050 79.40% 79.4%

Unsatisfactory

V.B. Manubay Construction 32705 Road Upgrading (IS.) along Ilagan-Delfin Alfonso-Mallig Road (K0434+453-K0434+670), K0434+677-K0435+009 08/08/12 II 4.738 90 C 0.367 0.200 0.300 - - - 86.70 85.38%

Satisfactory

V.B. Manubay Construction 32705 Road Upgrading (IS) along Ilagan-Delfin Albano-Mallig Road (K0434+453-K0434+670), K0434+611-K0435+009 03/17/12 II 4.738 90 O 0.332 0.238 0.150 0.030 0.045 0.050 84.50 -

V.B. Manubay Construction 32705 Repair/Rehab./Impvt. of Daang Maharlika, K0314+500-K0315+856 w/ exceptions 03/15/13 II 10.000 90 C 0.494 0.133 0.300 - - - 92.70 *92.70%

V. Satisfactory

V.R Patron Builders & Developers 13487 Rehab./Reconst./Upgrading of Damaged National Roads along Bauan-Mabini Rd., Bauan Side 06/04/10 IVA 19.295 120 O 0.390 0.225 0.150 0.023 0.060 0.050 89.80 -

V.R. PATRON BUILDERS & DEVELOPERS 13487Widening of Lipa-Rosario Road, San Felipe-Poblacion

Section, Padre Garcia, (A) K0087+280 to K088+604 (Right Side), K088+920 to K0089+199.5 (Left Side)

12/5/2014 IV 27.356 232 C 0.463 0.133 0.300 - - - 89.60% 89.6% Very Satisfactory

V.R. PATRON BUILDERS & DEVELOPERS 13487Widening of Batangas-Quezon Road, Rosario Section, a)

K0117+600.00 to K0118+194.20; b) K0117+600.00 to K0118+555.70

12/5/2014 IV 18.231 150 C 0.492 0.133 0.300 - - - 92.50% 92.5% Very Satisfactory

V.R. Patron Builders & Developers 1487Widening of Lipa-Rosario Road, San Felipe-Poblacion Section K0087+280 to K0088+604 (RS), K088+920 to

K0089+199.5 (LS)8/8/2014 IV-A 27.356 210 OG 0.368 0.300 0.143 0.015 0.063 0.033 92.20

V.R. Patron Builders & Developers 13487 Construction/ Replacement of Doña Alicia Bridge at Batangas-Lobo Road 8/8/2014 IV-A 38.800 405 C 0.390 0.200 0.300 89.00 86.54%

Satisfactory

V.R. Patron Builders & Developers 13487 Const. of Two (2) Pedestrian Overpass at Manila-Batangas Rd. Alangilan (BSU) & Kumintang Ibaba Sect. 07/31/13 IVA 27.936 420 C 0.462 0.133 0.300 - - - 89.50 88.03%

Satisfactory

V.R. Patron Builders & Developers 13487 Const./Replacement of Doña Alicia Bridge at Batangas-Lobo Rd. 07/29/13 IVA 38.800 405 O 0.347 0.300 0.100 0.030 0.047 0.025 84.90

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page285

Page 286: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

V.R. Patron Builders & Developers 13487Widening of Manila-Batangas Road inc. Drainage

Structure, Banay-Banay-San Jose Sect. Km.85+200-Km.86+400 (One Side Only) w/ exception

07/29/13 IVA 19.159 180 C 0.373 0.165 0.300 - - - 83.80 84.46% Satisfactory

V.R. Patron Builders & Developers 13487 Const. of Two (2) Pedestrian Overpass at Manila-Batangas Rd., Alangilan (BSU) and Kumintang Ibaba Sect. 03/12/13 IVA 27.936 400 O 0.373 0.240 0.150 0.030 0.030 0.033 85.60 -

V.R. Patron Builders & Developers 13487Widening of Manila-Batangas Rd., inc. Drainage Structure, Banay-banay-San Jose Sect., Km.85+200-Km.86+400 (One

Slide Only) (w/ exception)03/11/13 IVA 18.362 150 O 0.358 0.240 0.150 0.023 0.045 0.033 84.90 -

V.R. Patron Builders & Developers 13487 Widening of Manila-Batangas Road at Tambo Sect. (4 lanes w/ exception) 03/19/12 IVA 47.593 280 C 0.429 0.168 0.300 - - - 89.70 88.14%

Satisfactory

V.R. Patron Builders & Developers 13487 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Roads Manila-Batangas Rd. 03/21/12 IVA 24.576 120 C 0.430 0.200 0.300 - - - 93.00 86.34%

Satisfactory

V.R. Patron Builders & Developers 13487Widening of Daang Maharlika inc. Bridge and Drainage System, Sto. Tomas Sect., Batangas Cabaong Bridge &

Approaches11/21/12 IVA 19.423 240 C 0.485 0.133 0.300 - - - 91.80 89.10%

V. Satisfactory

V.R. Patron Builders & Developers 13487 Const. of Two (2) Pedestrian Overpass at Manila-Batangas Rd., Alangilan (BSU) & Kumintang Ibaba Sect. 11/23/12 IVA 27.936 339 O 0.345 0.300 0.150 0.030 0.027 0.033 88.50 -

V.R. Patron Builders and Developers 13487 Impvt./Rehab. along Palico-Balayan-Batangas City Rd.,

K0135+789-K0137+190 11/21/12 IVA 17.411 165 C 0.436 0.200 0.300 - - - 93.60 89.70% V. Satisfactory

V.R. Patron Builders and Developers 13487 Const./Impvt. of Flood Control & Drainage System along

Manila-Batangas Pob. Road, Sabang Sect. 08/10/12 IVA 17.197 180 C 0.447 0.133 0.300 - - - 88.00 90.10% V. Satisfactory

V.R. Patron Builders and Developers 13487

Widening of Daang Maharlika inc. Bridge & Drainage System Sto. Tomas Sect., Batangas, Cabaong Bridge &

Approaches, K0063+509.50-K0063+726.5008/08/12 IVA 19.012 210 O 0.360 0.240 0.150 0.030 0.060 0.033 87.30 -

V.R. Patron Builders and Developers 13487 Impvt./Rehab. along Palico-Balayan-Batangas City Rd.,

K0135+789-K1037+190 08/10/12 IVA 17.411 164 O 0.331 0.240 0.150 0.030 0.070 0.050 87.10 -

V.R.D.J Construction 19837 Const. of Sto. Tomas MPB 11/18/08 II 3.818 120 O 0.317 0.240 0.100 0.030 0.037 0.067 79.10 -

V3 Industrial Corporation 31403Rehab./Reconst./Upgrading of Damaged Paved Nat'l

Secondary Rd. along Bacolod Circ. Rd. (S), K0009+424-K0009+844

08/06/13 VI 8.514 91 C 0.471 0.133 0.300 - - - 90.40 *90.40% V. Satisfactory

Valley Construction & Aggregates 14315 Road Upgrading (Gravel to Conc.) Acop-Kapangan-Kibungan-Bakun Rd. Km.283+800-Km.289+849 (V.S.) 08/15/11 CAR 21.458 523 O 0.386 0.225 0.150 0.030 0.051 0.050 89.20 -

Valley Construction & Aggregates 14315 Impvt. of the Acop-Kapangan National Road 08/13/08 CAR 18.822 240 O 0.321 0.240 0.100 0.023 0.030 0.100 81.40 -

Valley Construction & Aggregates 14315Road Upgrading (Gravel to Concrete) Acop-Kapangan-

Kibungan-Bakun Road Km.264+794-Km.283+800, Tublay & Kapangan

03/15/12 CAR 31.773 267 C 0.459 0.133 0.300 - - - 89.20 90.46% V. Satisfactory

Valley Construction & General Merchandise 13777 Repair/Maint. of Brgy. 09 Revetment 03/16/13 II 2.992 73 C 0.375 0.200 0.300 - - - 87.50 87.08%

SatisfactoryValley Construction & General

Merchandise 13777 Repair/Maint. of Cagayan River Bank Protection, San Vicente 03/16/13 II 9.282 177 C 0.419 0.133 0.300 - - - 85.20 *85.20%

SatisfactoryVannie General Merchandise 27335 Const. of 425 ln.m. Drainage Canal, Purok Riverside 03/03/09 VI 5.793 564 O 0.281 0.300 0.150 0.030 0.042 0.050 85.30 -

Vannie General Merchandise 27335 Const. of Pototan Flood Control Suage River Brgy. Poblacion 09/09/09 VI 2.895 180 O 0.383 0.240 0.150 0.015 0.050 0.033 87.10 -

Vannie General Merchandise 27335 Const. of 425 ln.m. Drainage Canal 11/18/08 VI 5.738 154 O 0.320 0.200 0.070 0.030 0.032 0.133 78.50 -

Vannie General Merchandising 27335 Rehabilitation of Aklan-Panakuyan RIS 11/13/13 NIA 7.154 150 C 0.383 0.200 0.300 - - - 88.28 *88.28% Satisfactory

Vanvi Construction 29387 Construction of MPB, Brgy. Poblacion 09/16/09 XII 0.286 75 O 0.364 0.300 0.150 0.030 0.052 0.050 94.60 -

VC Varin Construction and Hardware Supply 12475

Rehab./Reconst./Upgrading of Damaged Paved National Roads including Drainage based on PMS/HDM-4,

Intermittent Section, Arterial Road, Daang Maharlika, K0360+000 - K0361+000

8/5/2014 V 14.141 60 C 0.431 0.133 0.300 86.40 86.40% Satisfactory

VCD Construction 13949 Construction of 2-Storey School Building @ San Nicolas E/S 06/04/09 I 1.348 132 O 0.325 0.240 0.150 0.030 0.050 0.033 82.80 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page286

Page 287: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

VCD CONSTRUCTION AND SUPPLY

Help for Catubig Agricultural Advancement Project HCAAP-LCB-C4-2012 03/15/14 NIA 14.250 180 O 0.351 0.300 0.000 0.030 0.070 0.050 80.07 -

VCH Construction and Trading 32050 Const. of Barutuan Bridge I Revetment, Km.291+797 03/13/13 IVB 1.129 53 C 0.440 0.133 0.300 - - - 87.30 86.40% Satisfactory

VCH Construction and Trading 30250 Completion of MPB Poblacion 03/15/12 IVB 2.384 120 C 0.484 0.200 0.000 - - - 68.40 72.47% POOR

VCH Construction and Trading 32050 Repair/Maint. of Dakeranen River Control Dumarao 03/13/13 IVB 1.877 83 C 0.399 0.183 0.300 - - - 88.20 *88.20% Satisfactory

Velonta Construction & Supply 32346 Prev. Maint. (Int. Sect.), Arterial Rd., N. Bacalso Ave. (Cebu South), Chainage 0810-Chainage 0850 08/24/13 VII 0.969 29 C 0.486 0.200 0.000 - - - 68.60 63.20%

Poor

Velonta Construction & Supply 32346 Prev. Maint. (Int. Sect.) Arterial Rd., N. Bacalso Ave. (Cebu South), Chainage 0810-Chainage 0850 03/21/13 VII 0.969 5 O 0.400 0.133 0.000 0.020 0.026 0.017 59.60 -

VEN RAY CONSTRUCTION 18310 Access Road Leading to Sagpulon Falls (Upgrading Gravel to Concrete) 10/27/2014 X 46.000 239 O 0.257 0.240 0.000 0.008 0.037 0.033 57.50% 57.5%

Poor

Ven Ray Construction 18310 Conc. of Balilihan-Hanopol-Batuan Rd., K0023+(-263)-K0024+863 08/15/13 VII 37.644 320 C 0.419 0.151 0.300 - - - 87.00 *87.00%

Satisfactory

Ven Ray Construction 18310 Repair/Rehab./Impv't. of Natalio Bacalso Ave., Carcar Sect., Km.39+999-Km.0040+592 w/ exceptions 08/06/13 VII 9.381 45 C 0.476 0.133 0.300 - - - 90.90 *90.90% V.

Satisfactory

Ven Ray Construction 18310 Repair/Rehab. of Terminal Bldg. Access Rd., Lapu-Lapu City, Chainage 0000-Chainage 0989 (Prev. Maint.) 08/12/13 VII 28.638 82 C 0.401 0.200 0.300 - - - 90.10 *90.10% V.

Satisfactory

Ven Ray Construction 18310 Repair/Rehab./Impv't. along Santander-Barili-Toledo Rd., K0160+036-K0161+636 08/09/13 VII 9.595 60 C 0.441 0.137 0.300 - - - 87.80 *87.80%

Satisfactory

Ven Ray Construction 18310 Repair/Rehab./Impv't. along Santander-Barili-Toledo Rd., K0156+890-K0157+740 08/09/13 VII 9.589 60 C 0.418 0.137 0.300 - - - 85.50 *85.50%

Satisfactory

Ven Ray Construction 18310

Prev. Maint. (Asphalt Overlay) along North Hagnaya Wharf Rd. (Int. Sect.), Sect. 1- K0045+800-K0046+000; Sect. 2- K0046+000-K0046+170; Sect. 3- K0046+918-K0047+154;

Sect. 4- K0047+596-K0047+736; Sect. 5- K0048+583-K0049+200; Sect. 6- K0049+200-K0050+000; Sect. 7-

K0051+400-K0051+700; Sect. 8- K0051+700-K0052+058

08/13/13 VII 42.263 110 C 0.422 0.133 0.300 - - - 85.50 *85.50% Satisfactory

Ven Ray Construction 18310

Prev. Maint. (Asphalt Overlay) along Cebu North Hagnaya Wharf Rd (Int. Sect.) Sect. 1 -K0061+399-K0062+691;

Section 2-K0069+149-K0070+009; Section 3- K0070+009-K0070+159; Section 4- K0070+159-K0070+567

08/13/13 VII 41.402 84 C 0.416 0.133 0.300 - - - 84.90 *84.90% Satisfactory

Ven Ray Construction 18310 Repair/Asphalt Overlay of Rd., Cugman 08/22/13 X 9.493 45 C 0.431 0.133 0.300 - - - 86.40 *86.40% Satisfactory

Ven Ray Construction 18310 Conc. of Unisan-Jct.-Panaon Rd. (Poctol Sect.), K0192+262-K0194+045 08/08/13 IVA 38.151 180 C 0.395 0.144 0.300 - - - 83.90 84.52%

Satisfactory

Ven Ray Construction 18310Prev. Maint.(Int. Sect.), Arterial Rd., N. Bacalso Ave.

(Osmeña Blvd. Sect.); a)K0001+000-K0001+726 & b)K0001+(-105)-K0001+000

08/24/13 VII 22.202 108 O 0.327 0.300 0.150 0.030 0.055 0.050 91.20

Ven Ray Construction 18310Const./Replacement of Cabitoonan Bridge & Approaches

along Toledo-Pinamungajan-Aloguinsan-Mantalongon Rd., K0052+(-20)

08/07/13 VII 25.628 174 O 0.384 0.240 0.150 0.030 0.047 0.033 88.40

Ven Ray Construction 18310 Rd. Upgrading (Conc.) of Tapal (Carcar)-Zaragosa-Olango-Aloguinsan Rd., K0080+065-K0081+622 08/07/13 VII 43.174 219 O 0.337 0.263 0.150 0.030 0.055 0.033 86.80

Ven Ray Construction 18310 Rehab. of Cebu North Hagnaya Wharf Rd. 08/13/13 VII 124.975 270 C 0.377 0.200 0.300 - - - 87.70 84.46% Satisfactory

Ven Ray Construction 18310Asphalt Overlay (Prev.) of Toledo-Pinamungajan-

Aloguinsan-Mantalongon Rd., K0055+033-K0057+000, Brgy. Bato

08/07/13 VII 13.163 30 C 0.459 0.200 0.300 - - - 95.90 82.76% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page287

Page 288: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Ven Ray Construction 18310Conc. of Shoulders w/ Provisions of Turn-Outs & Lined Canal along Butuan City-Cagayan de Oro-Iligan City Rd.

(BCIR), Tagbocboc-Balingoan-Esperanza Sect.08/21/13 X 5.702 75 C 0.414 0.200 0.300 - - - 91.40 82.16%

Satisfactory

Ven Ray Construction 18310 Conc. of Shoulders along Suggbongcogon-Binuangan-Ampenican-Lagonglong Sect. 08/21/13 X 5.116 75 C 0.411 0.200 0.300 - - - 91.10 82.04%

Satisfactory

Ven Ray Construction 18310 Conc. of Unisan-Jct.-Panaon Rd. (Poctol Sect.) K0192+262-K0194+045 03/17/13 IVA 38.151 180 O 0.346 0.253 0.150 0.030 0.040 0.033 85.20 -

Ven Ray Construction 18310Asphalt Overlay (Prev.) of Toledo-Pinamungajan-

Aloguinsan-Mantalongon Rd., K0055+033-K0057+000, Brgy. Bato

03/17/13 VII 12.909 30 O 0.389 0.300 0.000 0.020 0.014 0.017 74.00 -

Ven Ray Construction 18310 Road Upgrading (Gravel to Paved) along Argao-Ronda Road (Argao-Ronda Sect.) 05/29/09 VII 18.718 75 O 0.388 0.288 0.150 0.030 0.055 0.033 94.40 -

Ven Ray Construction 18310 Rehab./Reconst. of Siquijor Circ. Rd, .Km.22.860-Km.25.268, Larena -E. Villanueva-Maria Rd. Sect. 09/08/09 VII 47.680 515 O 0.353 0.244 0.150 0.030 0.033 0.033 84.30 -

Ven Ray Construction 18310 Rehab./Reconst. of Siquijor Circ. Rd. Km.10.475-Km.13.020, Larena-E. Villanueva Rd. Sect. 09/08/09 VII 47.085 459 O 0.345 0.247 0.150 0.030 0.033 0.033 83.80 -

Ven Ray Construction 18310 Concrete Paving of Siquijor Circ.Rd. San Juan Rd. Sec. Km. 61.820-Km.62.883 09/08/09 VII 18.685 326 O 0.344 0.246 0.150 0.030 0.033 0.033 83.60 -

Ven Ray Construction 18310Conc. of Siquijor Circ. Rd. Km.72.707-Km.74.427 San Juan

Siquijor Rd. Sect. Km. 13.020-Km. 14.22-Larena E. villanueva Rd. Sect.

09/07/09 VII 52.030 270 O 0.325 0.242 0.150 0.030 0.033 0.050 83.00 -

Ven Ray Construction 18310 Rehab./Reconst. of Siquijor Circumferential Road, Siquijor, -Larena Road Section 06/02/09 VII 31.724 351 O 0.255 0.300 0.150 0.030 0.051 0.050 83.60 -

Ven Ray Construction 18310 Conc. of Toledo-Pinamungajan-Aloguinsan Barili Na'tl. Road Km. 84+450 - Km. 85+891 03/12/09 VII 19.093 180 O 0.205 0.040 0.000 0.010 0.016 0.050 32.10 -

Ven Ray Construction 18310 Concreting of Roads Sitio Sta. Cruz 03/09/09 VII 0.245 90 O 0.273 0.000 0.150 0.015 0.030 0.050 51.80 -

Ven Ray Construction 18310 Rehab./Reconst. of Siquijor Circ., Larena-Enrique Villanueva Rd. Sect. 03/10/09 VII 46.671 368 O 0.319 0.219 0.150 0.023 0.033 0.033 77.70 -

Ven Ray Construction 18310 Rehab./Reconst. of Siquijor Circ., Siquijor-Larena Rd. Sect. 03/10/09 VII 31.733 328 O 0.340 0.222 0.150 0.030 0.047 0.033 82.20 -

Ven Ray Construction 18310 Rehab./Reconst. of Siquijor Circumferential Road, Km. 10.475-Km.13.020, Larena, E. Villanueva Road Section 06/03/09 VII 47.085 428 O 0.220 0.300 0.150 0.030 0.047 0.050 79.70 -

Ven Ray Construction 18310 Impvt. of Cagayan de Oro-Talakag-Camp Kabaritan Sto. Niño Dagumbaan-Basak Road 09/17/09 X 66.400 270 O 0.400 0.300 0.034 0.030 0.047 0.017 82.80 -

Ven Ray Construction 18310 Conc. of Antonio de Pio Highway, (Tigabawan-Olivio-Luyang Section) 09/02/08 VII 14.154 90 O 0.295 0.300 0.000 0.010 0.022 0.100 72.70 -

Ven Ray Construction 18310 Rehab./Reconst. of Siquijor Circ., Larena-Enrique Villanueva Rd. Sect. 11/22/08 VII 46.671 330 O 0.331 0.246 0.100 0.022 0.027 0.100 82.60 -

Ven Ray Construction 18310 Rehab./Reconst. of Siquijor Circ., Siquijor-Larena Rd. Sect. 11/22/08 VII 31.737 313 O 0.363 0.238 0.100 0.030 0.032 0.100 86.30 -

Ven Ray Construction 18310 Const./Widening/Upgrading/Rehab. of Access Road to RORO Port 03/29/12 VII 7.358 120 O 0.394 0.240 0.150 0.030 0.050 0.050 91.40 -

Ven Ray Construction 18310 Rehab./Reconst. along Toledo-Pinamungajan-Aloguinsan-Mantalongon Road 03/21/12 VII 14.998 125 C 0.351 0.179 0.300 - - - 83.00 89.18%

V. Satisfactory

Ven Ray Construction 18310 Road Upgrading/Conc. of Pinamungajan-Cadre Road, Chainage 0-835.35 03/21/12 VII 14.913 85 O 0.311 0.240 0.150 0.030 0.050 0.050 83.10 -

Ven Ray Construction 18310 Rehab./Reconst. of Sogod-Tabuelan Rd. 11/24/12 VII 95.584 390 C 0.387 0.143 0.300 - - - 83.00 87.44% Satisfactory

Ven Ray Construction 18310 Road Upgrading/Conc. of Pinamungajan-Cadre Road, Chainage 0-835.50 11/22/12 VII 14.913 115 C 0.347 0.200 0.300 - - - 84.70 83.74%

SatisfactoryVen Ray Construction 18310 Rehab. of Cebu North Hagnaya Wharf Rd. 11/24/12 VII 115.419 240 O 0.313 0.240 0.150 0.030 0.040 0.050 82.30 -

Ven Ray Construction 18310 Conc. of Shoulders along Sugbongcogon-Binuangan-Ampenican-Lagonglong Sect. 11/21/12 X 5.116 45 O 0.400 0.300 0.000 0.030 0.030 0.000 76.00 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page288

Page 289: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Ven Ray Construction 18310Conc. of Shoulders with Provisions of Turn-Outs & Lined Canal along Butuan City-Cagayan de Oro City-Iligan City

Rd. (BCIR), Tagbocboc-Balingoan-Esperanza Sect.11/22/12 X 5.701 45 O 0.400 0.300 0.000 0.030 0.030 0.000 76.00 -

Ven Ray Construction 18310 Rehab./Reconst. of Sogod-Tabuelan Rd. 08/06/12 VII 87.221 360 O 0.377 0.259 0.150 0.030 0.055 0.033 90.40 -

Ven Ray Construction 18310Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd.

along Natalio Bacalso Ave. (Cebu South Rd.), K0112+016-K0114+264

03/18/13 VII 29.543 115 C 0.424 0.133 0.300 - - - 85.70 *85.70% Satisfactory

Ven Ray Construction 18310Repair/Rehab./Impvt. (Asphalt Overlay) of Cagayan de Oro City Airport-Bukidnon Rd., Km.1444+000 Km.1445+500 w/

exception, Upper Balulang08/23/12 X 9.600 45 C 0.438 0.133 0.300 - - - 87.10 85.66%

Satisfactory

VEN RAY CONSTRUCTION/JEJOR'S

CONSTRUCTION CORPORATION JOINT VENTURE

JV-13-436 Widening of Sayre Highway including RROW, Puerto-Alae Section K1432+674 - K1437+799 10/20/2014 X 132.384 300 O 0.311 0.285 0.150 0.015 0.047 0.050 85.80% 85.8%

Satisfactory

VENRAY CONSTRUCTION 18310

Assets Preservation of National Roads Preventive Maintenance Based on Pavement Management

System/Highway Development Management-4 (HDM-4), Intermittent Section, (K0015+000 to K0035+900),

(K0036+000 to K0036+695)

10/28/2014 VII 27.408 209 C 0.361 0.200 0.300 - - - 86.10% 86.1% Satisfactory

VENRAY CONSTRUCTION 18310 Asphalt Overlay of Brgy. Road, Brgy. Marigondon, Lapu-Lapu City, Cebu 10/21/2014 VII 44.004 120 C 0.427 0.135 0.300 - - - 86.20% 86.2%

Satisfactory

VENRAY CONSTRUCTION 18310

Repair/Reconst./Upgrading of Damaged Paved National Roads including Drainage Based on Pavement

Management System/Highway Development and Mangement System/Highway Development and

Management-4 (HDM-4), Dalaguete-Mantalongon - Badian Road (Badian Side)

8/5/2014 VII 24.063 155 C 0.369 0.200 0.300 86.90 86.90% Satisfactory

VENRAY CONSTRUCTION 18310 Road Upgrading of Tapal (Carcar)-Zaragosa-Olango - Alonguinsan Road 8/6/2014 VII 48.173 168 C 0.419 0.159 0.300 87.80 87.20%

Satisfactory

VENRAY CONSTRUCTION 18310Const./Replacement of Cabitoonan Bridge & Approaches along Toledo - Pinamungajan - Aloguinsan - Mantalongon

Road8/6/2014 VII 25.628 174 C 0.480 0.146 0.300 92.60 90.08%

Very Satisfactory

VENRAY CONSTRUCTION 18310 Construction of Drainage System along Cebu North Hagnaya Wharf Road Carmen Section, Carmen, Cebu 8/8/2014 VII 17.650 210 OG 0.344 0.266 0.150 0.022 0.047 0.050 87.90

VENRAY CONSTRUCTION 18310Cluster III -RBH: Preventive Maintenance, (Int. Sect.)

Arterial Road, N. Bacalso Avenue (Osmena Blvd. Section) A. K0001+000 to K0001+726 B. K0001+(-105) to K0001+000

8/9/2014 VII 22.202 108 C 0.446 0.135 0.300 88.10 88.10% Satisfactory

Venus Engineering & Construction 33614 Rehab. of Brgy. Rd., Brgys. Anahawan-Himama-a Baliw 08/08/13 VIII 4.805 90 C 0.471 0.133 0.300 - - - 90.40 *90.40% V. Satisfactory

VERTICAL BUILDERS 14029 Widening of Jct. Digos-Buayan Airport Road, K1650+500 - K1652+079 8/16/2014 XII 33.435 156 C 0.449 0.133 0.300 88.20 88.20%

Satisfactory

Vertical Builders 14029 Widening of Jct. Digos-Makar-Buayan Rd., Gen. Santos City, K1649+095-K1650+425 08/23/13 XII 23.121 125 C 0.387 0.191 0.300 - - - 87.80 *87.80%

Satisfactory

Vertical Builders 14029 Conc./Widening of Marbel-Makar Rd., Polonuling/Simbo Sect. 08/23/13 XII 18.962 185 C 0.428 0.195 0.300 - - - 92.30 89.60% V.

Satisfactory

Vertical Builders 14029Address Critical Bottlenecks, Traffic Decongestion,

Conc./Widening of Marbel-Makar Rd., South Cotabato, Sub-DEO, Simbo Sect.

08/23/13 XII 18.818 107 C 0.444 0.200 0.216 - - - 86.00 86.42% Satisfactory

Vertical Builders 14029 Conc. /Widening of Marbel-Makar Rd., Polonuling/Simbo Sect. 03/23/13 XII 18.962 180 O 0.353 0.240 0.150 0.030 0.055 0.050 87.80 -

Vertical Builders 14029 Address Critical Bottlenecks Traffic Decongestion, Conc./Widening of Marbel-Makar Rd., Simbo Sect. 03/23/13 XII 18.818 102 O 0.361 0.238 0.150 0.030 0.055 0.033 86.70 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page289

Page 290: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Vertical Builders 14029 Rebranding/ Renovation of DBP - Tacurong Branch Building 11/16/12 DBP 3.988 180 C 0.492 0.200 0.300 - - - 99.20 88.62% Satisfactory

Vertical Builders 14029 Rebranding/ Renovation of DBP - Marbel Branch Building 11/15/12 DBP 3.180 150 C 0.484 0.200 0.300 - - - 98.36 89.53% V. Satisfactory

VERZONTAL BUILDERS JV-11-197 Pagadian Airport Development Project 08/28/15 DOTC 35.607 420 C 0.479 0.200 0.300 - - - 97.90 93.40% V. Satisfactory

VERZONTAL BUILDERS 31579 Gigaquit Port Development Project 03/28/14 DOTC 4.943 90 C 0.445 0.200 0.300 - - - 94.50 94.50% Very Satisfactory

Verzontal Builders JV-11-197 Pagadian Airport Development Project 09/12/13 DOTC 35.612 300 O 0.365 0.300 0.150 0.020 0.035 0.033 90.30 -

Verzontal Builders Land Dev't of NHA-Hernandezville Housing Project 06/22/13 NHA 17.527 250 C 0.470 0.200 0.300 - - - 97.03 69.43% Poor

Verzontal Builders Land Dev't of NHA-Hernandezville Housing Project 10/19/12 NHA 20.285 250 O 0.328 0.071 0.032 0.030 0.019 0.030 51.03 -

Vesa Engineering 32344 Ports Horizontal Structures 10/09/13 DOTC 4.489 75 C 0.321 0.200 0.300 - - - 82.11 *82.11% Satisfactory

Vesa Engineering & Construction 32334 Tanjay Port Development Project 08/13/15 DOTC 8.659 150 O 0.382 0.300 0.150 0.030 0.026 0.033 92.11 -

VESA ENGINEERING AND CONSTRUCTION 32344 Catarman Airport Development Project 03/26/15 DOTC 7.520 90 C 0.428 0.200 0.300 - - - - *92.80%

V. SatisfactoryVESA Engineering and

Construction 32334 Cantupa Port Development Project 01/23/14 DOTC 1.996 90 C 0.477 0.200 0.300 - - - 97.73 *97.73% Outstanding

Vesa Engineering and Construction 32334 Tanjay Port Development Project 08/29/13 DOTC 1.884 90 C 0.393 0.200 0.300 - - - 89.30 *89.30% V. Satisfactory

Vesa Engineering and Construction 32334 Siaton Port Development Project 08/29/13 DOTC 1.885 90 C 0.434 0.200 0.300 - - - 93.40 *93.40% V. Satisfactory

Vesa Engineering and Construction 32334 Gumaca Port Development Project 08/07/13 DOTC 4.564 120 C 0.429 0.200 0.300 - - - 92.90 *92.90% V. Satisfactory

Vesa Engineering and Construction 32334 Pagadian LTFRB Regional Office Project 09/11/13 DOTC 3.725 150 C 0.433 0.200 0.300 - - - 93.30 *93.30% V. Satisfactory

VF CONSTRUCTION 10048 Upgrading/Improvement of Road Sta. Rosario and Sta. Cruz 11/7/2014 III 9.221 60 C 0.435 0.133 0.300 - - - 86.80% 86.8%

Satisfactory

Vicente Lao Construction 7040 Construction of RC Landing and Rehabilitation of Existing Bulkhead PPA 28.625 510 O 38.100 30.000 11.850 2.400 7.000 1.670 91.02 -

Vicente T. Lao Construction 7040 Dipolog Airport Development Project 08/26/15 DOTC 27.578 404 O 0.385 0.300 0.150 0.020 0.063 0.050 96.80 -

Vicente T. Lao Construction 7040 Cotabato Airport Development Project 09/09/15 DOTC 55.676 270 O 0.357 0.300 0.130 0.020 0.061 0.033 90.10 -

Vicente T. Lao Construction 7040 Central Mindanao Airport Development Project 06/10/14 DOTC 110.216 360 C 0.335 0.200 0.300 - - - 83.48 *90.87% V.Satisfactory

VICENTE T. LAO CONSTRUCTION REHABILITATION/ UPGRADING OF WESTERN WHARF 10/09/15 PPA 102.156 420 O 0.400 0.300 0.105 0.030 0.070 0.050 95.50 -

VICENTE T. LAO CONSTRUCTION 7040 Construction/Rehabilitation of Flood Control Structure at Olave River, Siquijor, Circumferential Road, K0025+252 10/28/2014 VII 18.387 261 O 0.370 0.300 0.014 0.030 0.056 0.000 77.00% 77%

Unsatisfactory

VICENTE T. LAO CONSTRUCTION 7040

Assets Preservation of National Road Preventive Maintenance Based on Pavement Management

System/Highway Development and Management-4 (HDM-4) (Intermittent Section) Dipolog-Oroquieta National Road K

1796+100 to K 1797+774

10/28/2014 IX 11.043 30 C 0.440 0.199 0.300 - - - 93.90% 93.9% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page290

Page 291: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

VICENTE T. LAO CONSTRUCTION 7040

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Road Including Drainage based on

Pavement Management System/Highway Development and Management-4 (HDM-4) (Intermittent Section), Dipolog-

Polanco-Piñan-Jct. Oroquieta Road K 1815+600 to K 1817 +005

10/28/2014 IX 20.443 166 C 0.472 0.196 0.230 - - - 89.80% 89.8% Very Satisfactory

VICENTE T. LAO CONSTRUCTION 7040Completion of Lower Sultan Bridge (Phase II) aong

crossing Sta. Clara-Sandayong Road Km. 1792+171.551 to Km. 1792+214.371

10/23/2014 IX 15.854 230 O 0.345 0.286 0.022 0.030 0.040 0.017 74.00% 74% Poor

VICENTE T. LAO CONSTRUCTION 7040Construction/Improvement of Access Road Leading to Declared Tourism Destinations: Turno By-Pass Road

Leading to Linabo Peak (3003) steps, Dipolog City10/29/2014 IX 27.893 239 C 0.298 0.300 0.049 - - - 73.90% 73.9%

Poor

VICENTE T. LAO CONSTRUCTION 7040 Repair/Rehab./Impvt. Along Daang Maharlika (Agusan-Davao) Road, San Roque Section 10/26/2014 XI 9.309 84 C 0.415 0.145 0.300 - - - 86.00% 86%

Satisfactory

VICENTE T. LAO CONSTRUCTION 7040Concreting/Widening of Dulawan-Marbel Road (New

Carmen-Kalandagan Section), K1766+815 - K1769+071 w/ exceptions

10/23/2014 XII 40.181 224 O 0.338 0.215 0.082 0.020 0.045 0.033 73.30% 73.3% Poor

VICENTE T. LAO CONSTRUCTION 7040 Rehabilitation/Retrofitting of Molo Bridge along Demolos-Little Baguio, Alabel Road 10/29/2014 XII 12.318 140 C 0.446 0.104 0.300 - - - 85.00% 85%

Satisfactory

VICENTE T. LAO CONSTRUCTION 7040Road Upgrading (Gravel-Paved) of Dinagat-Loreto Road

(Llamera-Garcia Section), K48+700 - K52+500 with exception

10/27/2014 XIII 118.390 285 O 0.380 0.300 0.061 0.023 0.037 0.033 83.40% 83.4% Satisfactory

VICENTE T. LAO CONSTRUCTION 7040

Asset Preservation of National Roads Generated from Pavement System/Higway Dev't and Management -4 (HDM-4), Preventive Maintenance (Intermittent Sections) Bacolod

South Road (Kabankalan - Hinoba-an Section)

8/8/2014 VI 18.291 180 C 0.376 0.200 0.300 87.60 86.22% Satisfactory

Vicente T. Lao Construction 7040

Rehabilitation/Reconstructtion/Upgrading of Damaged Paved National Road including Drainage based on Pavement Management System /Highway Devt. &

Management-4 (HDM-4) (Intermittent Section), Dipolog-Polanco-Piñan-Jct. Oroqueta Road K1815+600 to

K1817+005

8/14/2014 IX 20.062 168 C 0.407 0.196 0.300 90.30 90.30% Very Satisfactory

Vicente T. Lao Construction 7040Preventiive Maintenance (Intermittent Section) Zamboanga

City-Lubuan-Limpapa Road, Sta. 1938+141 to Sta. 1945+520.39

8/4/2014 IX 98.847 380 C 0.418 0.133 0.300 85.10 84.86% Satisfactory

VICENTE T. LAO CONSTRUCTION 7040 Dipolog Airport Development Project 02/12/15 DOTC 27.578 321 O 0.342 0.300 0.150 0.010 0.062 0.050 91.40 -

Vicente T. Lao Construction 7040 Cotabato Airport Development Project 05/14/14 DOTC 55.695 210 O 0.320 0.300 0.150 0.030 0.032 0.050 88.14 -

Vicente T. Lao Construction 7040 Impv't. of Bacolod South Rd., Recreo-Tuguis Sect., K0043+967-K0044+308 08/11/13 VI 8.013 83 C 0.491 0.133 0.300 - - - 92.40 *92.40%

V. Satisfactory

Vicente T. Lao Construction 7040 Asphalt Overlay/Repair & Rehab. of Nabunturan-Mainit Park Rd., Pob. Sect., Km.1425+723-Km.1426+174 08/14/13 XI 9.588 53 C 0.390 0.133 0.300 - - - 82.30 *82.30%

Satisfactory

VICENTE T. LAO CONSTRUCTION 7040 Central Mindanao Airport Development Project 02/04/14 DOTC 110.291 360 O 0.387 0.300 0.150 0.010 0.061 0.050 95.80 -

Vicente T. Lao Construction 7040 Widening/Reconst. along Davao-Cotabato Rd. (Davao City-Jct. Digos) 08/21/13 XI 50.141 243 O 0.346 0.300 0.126 0.030 0.030 0.033 86.50

Vicente T. Lao Construction 7040 Prev. Maint. (Int. Sect.), Bacolod South Rd. (Kabankalan-Hinoba-an Sect.) 08/08/13 VI 17.286 150 O 0.363 0.300 0.071 0.030 0.056 0.033 85.30

Vicente T. Lao Construction 7040Prev. Maint. along Dipolog-Polanco-Piñan Jct.-Oroquieta

Rd., 1)Km.1833+834-Km.1834+600; 2)Km.1834+600-Km.1834+700

08/22/13 IX 6.996 46 C 0.399 0.133 0.300 - - - 83.20 86.32% Satisfactory

Vicente T. Lao Construction 7040 Prev. Maint. (Int. Sect.) Zamboanga City-Labuan-Limpapa Rd., Sta.1938+141-Sta.1945+490 08/05/13 IX 95.845 300 O 0.346 0.300 0.099 0.030 0.037 0.033 84.50

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page291

Page 292: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Vicente T. Lao Construction 7040Rd. Upgrading (Gravel to Paved) of Sindangan-Siayan-Dumingag-Mahayag Rd., Sta.1942+320-Sta.1948+380 w/

exceptions08/23/13 IX 184.569 484 O 0.274 0.278 0.150 0.023 0.059 0.050 83.40 -

Vicente T. Lao Construction 7040 Restoration/Rehab. of Jct. Pontevedra-La Castellana Rd., Sta.47+975-Sta.54+020 (w/ exceptions) 03/14/13 VI 78.418 389 C 0.363 0.200 0.300 - - - 86.30 84.26%

Satisfactory

Vicente T. Lao Construction 7040Prev. Maint. along Dipolog-Polanco-Piñan Jct.-Oroquieta

Rd., 1) Km.1833+834-Km.1834+600; 2) Km.1834+600-Km.1834+700

03/23/13 IX 6.996 46 O 0.376 0.240 0.150 0.030 0.038 0.050 88.40 -

Vicente T. Lao Construction 7040 Concrete Sheet Piling & Impv't. & Const. of Seawall of R.T. Lim Blvd. (Phases II & III), Sta.0+487-Sta.0+827 03/11/13 IX 30.457 449 O 0.358 0.240 0.140 0.030 0.047 0.050 86.50 -

Vicente T. Lao Construction 7040 Prev. Maint. (Int. Sect.) Zamboanga City-Labuan-Limpapa Rd., Sta.1938+141-Sta.1945+490 03/12/13 IX 95.845 240 O 0.385 0.300 0.059 0.030 0.042 0.033 84.90 -

Vicente T. Lao Construction 7040 Rd. Upgrading (Gravel to Paved) Jct. Alicia-Imelda Rd. (Lambuyugan-Alicia Sect.) 03/18/13 IX 88.196 402 O 0.378 0.300 0.023 0.030 0.061 0.033 82.50 -

Vicente T. Lao Construction 7040 Revetment of Cagayan de Oro River (Carmen Side, Acacia Sect.) 03/11/13 X 46.548 248 O 0.281 0.300 0.150 0.010 0.047 0.050 83.80 -

Vicente T. Lao Construction 7040 Prev. Maint. (Intermittent Sect.) along Daang Maharlika Rd. 03/17/13 XI 99.893 297 C 0.412 0.133 0.300 - - - 84.50 83.78% Satisfactory

Vicente T. Lao Construction 7040 Const. of Calinan-Toril Road inc. ROW 03/21/13 XI 81.765 445 O 0.327 0.240 0.124 0.030 0.055 0.050 82.60 -

Vicente T. Lao Construction 7040 Strengthening of Tunggol Bridge II Km.1660+562 (Approach "A") along Davao-Cotabato Rd. 03/18/13 XII 46.452 340 O 0.317 0.299 0.150 0.030 0.065 0.050 91.10 -

Vicente T. Lao Construction 7040 Asphalt Overlay of Fil-Am Friendship Ave., (GSC Airport Rd.) 03/23/13 XII 10.240 120 O 0.370 0.240 0.150 0.030 0.050 0.050 89.00 -

Vicente T. Lao Construction 7040 Repair/Rehab. of Cotabato-Lanao Nat'l. Rd. Simuay-Landasan-Parang Sect., Km.1865+553.40-Km.1878+442 03/15/13 XII 122.303 375 C 0.408 0.133 0.300 - - - 84.10 88.30%

Satisfactory

Vicente T. Lao Construction 7040 Road Upgrading (Gravel to Conc.) of Jct. Lingig-Trento Rd., Km.1478+265-Km.1482+620 03/22/13 XIII 95.636 345 O 0.305 0.296 0.150 0.030 0.033 0.050 86.40 -

Vicente T. Lao Construction 7040 Initial Dredging of Rio Grande de Mindanao 08/12/11 XII 144.550 601 O 0.400 - 0.188 0.050 0.043 0.250 93.10 -

Vicente T. Lao Construction 7040 Preventive Maintenance (Intermittent Sections) a.) Daang Maharlika (MN): 1)Km.1497+914-Km.1498+473.25 08/25/11 XI 16.990 90 O 0.300 0.240 0.150 0.030 0.055 0.050 82.50 -

Vicente T. Lao Construction 7040 Road Upgrading (Gravel to Paved), Kibawe-Kadilingan-Kalilangan Road, K1585+152-K1586+000, Brgy. Domagook 08/09/11 X 7.671 87 O 0.338 0.287 0.150 0.030 0.040 0.033 87.80 -

Vicente T. Lao Construction 7040 Const. of Ozamiz Port Expansion (Ports & Harbor) 03/7-11/11 PPA 150.033 819 O 0.399 0.299 0.150 0.030 0.059 0.050 98.70 -

Vicente T. Lao Construction 7040Upgrading/Improvement/Rehab. of National Road along

Sindangan-Liloy- Ipil National Road Section Km. 1961+050 -Km. 1987+000 w/ exception

03/03/10 IX 37.150 95 O 0.292 0.300 0.150 0.022 0.037 0.050 85.10 -

Vicente T. Lao Construction 7040Impvt. of Zamboanga West Coast Rd., Gutalac-Jct.

Baliguian-Siocon-Sirawai-Sibuco Rd., Upper Kauswagan Sect., Sta.2019+600 to Sta.2063+910 w/ exceptions

06/03/10 IX 668.190 700 O 0.299 0.240 0.150 0.030 0.042 0.033 79.40 -

Vicente T. Lao Construction 7040 Const. of Allah River Bank Protection/River Control along Colongolo-Centralla Section 03/06/10 XII 18.152 140 O 0.276 0.300 0.150 0.030 0.035 0.033 82.40 -

Vicente T. Lao Construction 7040 Rehab./Reconst./Upgrading of Damaged Road of Dipolog-Polanco-Oroquieta Road 06/10/09 IX 10.490 180 O 0.389 0.240 0.150 0.030 0.047 0.050 90.60 -

Vicente T. Lao Construction 7040 Impvt./Concrete Paving of Gutalac-Baliguian-Siocon Road, Nonoyan-Sta. Maria Section 05/28/09 IX 48.156 732 O 0.388 0.240 0.150 0.030 0.047 0.050 90.50 -

Vicente T. Lao Construction 7040 Rehab./Reconst./Upgrading of Damaged Paved National Road Junction, Polo-Dapitan Park Road 06/09/09 IX 15.268 126 O 0.391 0.240 0.150 0.020 0.037 0.033 87.10 -

Vicente T. Lao Construction 7040 Impvt. of Access Road Leading to Dipolog Airport, Minaog 06/10/09 IX 4.762 100 O 0.357 0.240 0.150 0.030 0.047 0.033 85.70 -

Vicente T. Lao Construction 7040 Rehab./Reconst./Upgrading of Junction Pulauan Port Road 06/09/09 IX 15.268 130 O 0.386 0.240 0.150 0.010 0.037 0.033 85.60 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page292

Page 293: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Vicente T. Lao Construction 7040 Impvt./Concrete Paving of Gutalac-Baliguian-Siocon Road, Nonoyan-Sta. Maria Section 03/07/09 IX 48.156 539 O 0.378 0.261 0.150 0.030 0.047 0.050 91.60 -

Vicente T. Lao Construction 7040 Impv't/Conc. Paving of Dipolog-Punta-Dansullan-S. Osmeña Road (Dilawa Section) 03/16/09 IX 19.092 210 O 0.368 0.300 0.150 0.030 0.030 0.050 92.80 -

Vicente T. Lao Construction 7040 Impv't/Conc. Paving of Dipolog-Punta-Dansullan-S. Osmeña Road, Macleodes Sect. 03/16/09 IX 19.092 210 O 0.376 0.300 0.150 0.030 0.030 0.050 93.60 -

Vicente T. Lao Construction 7040 Repair/Asphalt Overlay along Titay-Ipil, Kitabog Section, Km. 2004+457-Km. 2005+457 09/04/09 IX 19.286 110 O 0.367 0.300 0.150 0.030 0.050 0.033 93.00 -

Vicente T. Lao Construction 7040 Repair/Asphalt Overlay along Titay-Ipil, Kitabog Section, Km. 2005+457-Km. 2008+197 length 1000 meters 09/04/09 IX 19.286 160 O 0.350 0.300 0.150 0.030 0.050 0.033 91.30 -

Vicente T. Lao Construction 7040 Rehab./Reconst./Upgrading of Damaged Road of Dipolog-Polanco-Oroquieta Road 09/16/09 IX 10.490 180 O 0.298 0.300 0.150 0.030 0.040 0.033 85.10 -

Vicente T. Lao Construction 7040 Road Upgrading/Asphalting of Don Carlos-Kadingilan Road 09/03/09 X 38.171 120 O 0.378 0.245 0.150 0.003 0.051 0.050 87.70 -

Vicente T. Lao Construction 7040 Asphalting of Don Carlos - Kadilingan Road 09/03/09 X 48.250 210 O 0.310 0.300 0.000 0.030 0.056 0.050 74.60 -

Vicente T. Lao Construction 7040 Impvt./Conc. Paving of Sindangan-Siayan-Dumingag Road 09/04/08 IX 28.546 475 O 0.304 0.240 0.000 0.030 0.042 0.100 71.60 -

Vicente T. Lao Construction 7040 Impvt./Conc. Paving of Sindangan-Siayan-Dumingag Road 12/04/08 IX 28.948 345 O 0.345 0.240 0.100 0.030 0.040 0.100 85.50 -

Vicente T. Lao Construction 7040 Impvt./Concrete Paving of Gutalac-Baliguian-Siocon Road, Sta. Maria Section 08/26/08 IX 48.156 290 O 0.270 0.252 0.000 0.030 0.042 0.100 69.40 -

Vicente T. Lao Construction 7040 Road Upgrading (Gravel to Concrete) along Butuan City-Talacogon-Loreto-Veruela-Sta. Josefa Road, 03/29/12 XIII 11.245 255 C 0.476 0.133 0.300 - - - 90.90 89.64%

V. Satisfactory

Vicente T. Lao Construction 7040 Conc. of NRJ Cuevas-Bislig Road Km.1379+089.20-Km.1386+000 03/27/12 XIII 83.718 300 O 0.375 0.300 0.101 0.030 0.035 0.017 85.80 -

Vicente T. Lao Construction 7040 Impv't./Upgrading of Nat'l Rd. along Surigao-Davao Coastal Rd., Surigao-Davao Coastal Sect. 03/23/12 XIII 6.587 150 O 0.367 0.300 0.053 0.030 0.050 0.033 83.30 -

Vicente T. Lao Construction 7040 Conc. of General Santos City, Circ. Rd., Sinawal-Apopong Sect. (Island) 03/25/13 XII 10.977 56 C 0.436 0.133 0.300 - - - 86.90 *86.90%

Satisfactory

Vicente T. Lao Construction 7040Asphalt Overlay along Midsayap-Makar Rd., Pob. Midsayap

Sect., Km.1694+634-Km.1695+450 w/ exception (816.35 ln.m.)

03/17/13 XII 7.847 45 C 0.433 0.133 0.300 - - - 86.60 *86.60% Satisfactory

Vicente T. Lao Construction 7040 Asphalt Overlay along Lanao-Pagadian-Zamboanga City Rd. Km.1797+000-Km.1797+2040 03/21/12 IX 20.565 138 C 0.449 0.133 0.300 - - - 88.20 90.36%

V. Satisfactory

Vicente T. Lao Construction 7040Impvt. of Zamboanga West Coast Road, Gutalac-Jct.

Baliguian-Siocon-Sirawai-Sibuco Road, Upper Kauswagan Sect., Sta.2019+600-Sta.2063+910 w/ exception

03/23/12 IX 668.190 915 C 0.361 0.200 0.300 - - - 86.10 86.76% Satisfactory

Vicente T. Lao Construction 7040Rehab./Reconst./Upgrading of Damaged Paved Nat'l Roads Gen. from Pvt. Mgt. System/HDM-4 Sindangan-Liloy Road Km.1957+200-Km.1958+750 & Km.1964+000-Km.1964+930

03/22/12 IX 22.183 104 C 0.286 0.133 0.300 - - - 71.90 82.22% Satisfactory

Vicente T. Lao Construction 7040Rds. Upgrading (Gravel to Paved) of Sindangan-Siayan-Dumingag-Mahayag Rd., Sta.1942+320-Sta.1948+380 w/

exception11/28/12 IX 184.569 348 O 0.309 0.240 0.150 0.030 0.059 0.050 83.80 -

Vicente T. Lao Construction 7040 Rd. Upgrading (Gravel to Paved) Jct. Alicia-Imelda Rd. (Lambuyugan-Alicia Sect.) 11/23/12 IX 88.196 314 O 0.344 0.294 0.072 0.030 0.054 0.033 82.70 -

Vicente T. Lao Construction 7040 Concrete Sheet Piling & Impvt. & Const. of Seawall of R.T. Lim Blvd. (Phases II & III), Sta.0+487-Sta.0+827 11/19/12 IX 29.215 389 O 0.380 0.240 0.080 0.030 0.060 0.033 82.30 -

Vicente T. Lao Construction 7040 Revetment of Cagayan de Oro River (Carmen Side, Acacia Sect.) 11/24/12 X 46.548 195 O 0.300 0.300 0.150 0.030 0.050 0.033 86.30 -

Vicente T. Lao Construction 7040 Strengthening of Tunggol Bridge II, Km. 1660+562 (Approach "A") along Davao-Cotabato Rd. 11/22/12 XII 44.887 295 O 0.352 0.300 0.150 0.030 0.055 0.050 93.70 -

Vicente T. Lao Construction 7040 Rd. Upgrading (Gravel to Concrete) along Sarangani-Sultan Kudarat Coastal Rd., Km 1770+129-Km 1772+000 11/28/12 XII 41.341 210 C 0.450 0.133 0.300 - - - 88.30 89.14%

V. Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page293

Page 294: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Vicente T. Lao Construction 7040 Impv't./Upgrading of Nat'l Rd. along Surigao-Davao Coastal Rd., Surigao-Davao Coastal Sect. 11/22/12 XIII 6.587 209 C 0.432 0.200 0.300 - - - 93.20 87.11%

Satisfactory

Vicente T. Lao Construction 7040Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd., Km1150+274.50-Km.1152+907.80 w/ exceptions, Surigao-

Davao Coastal Rd.11/21/12 XIII 35.804 390 C 0.423 0.200 0.285 - - - 90.80 86.30%

Satisfactory

Vicente T. Lao Construction 7040 Conc. of NRJ-Cuevas-Bislig Rd., Km. 1400+000-Km.1402+000 11/26/12 XIII 44.644 330 O 0.343 0.300 0.055 0.030 0.060 0.033 82.10 -

Vicente T. Lao Construction 7040 Conc. of NRJ-Cuevas-Bislig Rd., Km. 1395+000-Km.1396+915.50 11/26/12 XIII 41.552 326 O 0.333 0.300 0.065 0.030 0.060 0.033 82.10 -

Vicente T. Lao Construction 7040 Concrete Sheet Piling & Impvt. & Const. of Seawall of R.T. Lim Blvd. (Phase II & III), Sta.0+487-Sta.0+827 08/13/12 IX 27.690 359 O 0.385 0.240 0.135 0.030 0.032 0.033 85.50 -

Vicente T. Lao Construction 7040 Rd. Upgrading (Gravel to Paved) Jct. Alicia-Imelda Rd. (Lambuyugan-Alicia Sect.) 08/28/12 IX 88.196 290 O 0.334 0.286 0.115 0.030 0.038 0.033 83.60 -

Vicente T. Lao Construction 7040Prev. Maint. along Tagum City Diversion Road, Km.1455+(-825)-Km.1455+(-469.22) & Km.1455+(-469.22)-Km.1455+(-

29.83)08/13/12 XI 13.023 55 C 0.429 0.135 0.300 - - - 86.40 88.80%

Satisfactory

Vicente T. Lao Construction 7040 Strengthening of Tunggol Bridge II Km.1660+562 (Approach "A") along Davao-Cotabato Rd. 08/15/12 XII 44.887 280 O 0.391 0.240 0.150 0.030 0.051 0.050 91.20 -

Vicente T. Lao Construction 7040 Rd. Upgrading (Gravel to Concrete) along Sarangani-Sultan Kudarat Coastal Rd,. Km.1770+129-Km.1772+000 08/20/12 XII 41.341 210 O 0.370 0.246 0.150 0.030 0.051 0.050 89.70 -

Vicente T. Lao Construction 7040 Conc. of NRJ-Cuevas Bislig Rd., Km.1373+608-Km.1374+422; Km.1394+840-Km.1395+000 08/17/12 XIII 20.677 235 O 0.374 0.298 0.070 0.030 0.050 0.033 85.50 -

Vicente T. Lao Construction 7040 Conc. of NRJ-Cuevas Bislig Rd., Km.1395+000-Km.1396+915.50 08/17/12 XIII 41.323 296 O 0.347 0.248 0.130 0.030 0.050 0.033 83.80 -

Vicente T. Lao Construction 7040 Impvt./Upgrading of Nat'l Rd. along Surigao-Davao Coastal Rd., Surigao-Davao Coastal Rd. Sect. 08/08/12 XIII 6.587 180 O 0.389 0.300 0.004 0.030 0.055 0.050 82.80 -

Vicente T. Lao Construction 7040 Conc. of NRJ-Cuevas Bislig Rd., Km.1400+000-Km.1402+000 08/17/12 XIII 42.679 285 O 0.361 0.293 0.059 0.030 0.050 0.033 82.60 -

Vicente T. Lao Construction Proposed Ozamis Port Expansion Project 05/25/12 PPA 150.034 909 C 0.500 0.200 0.300 - - - 100.00 97.82% Outstanding

Vicente T. Lao Construction 7040 Improvement of Back-up Area, Port of Davao 08/17/12 PPA 53.936 360 O 0.398 0.300 0.000 0.030 0.070 0.033 83.10 -

Vicente T. Lao Construction 7040 Port Improvement Project of Port of Glan 10/18/12 PPA 28.625 706 O 0.433 0.200 0.300 - - - 93.30 91.91% V. Satisfactory

Vicente T. Lao Construction 7040 Cotobato Airport Development Project 05/07/12 DOTC 128.985 360 C 0.453 0.196 0.300 - - - 94.90 93.90% V. Satisfactory

Vicente T. Lao Construction 7040 Improvement of Back-up Area, Port of Davao 11/23/12 PPA 53.936 404 C 0.500 0.159 0.300 - - - 95.90 88.19% Satisfactory

Vicmar Construction 28997 Repair of Causeway 09/14/12 PPA 35.513 215 O 0.310 0.300 0.150 0.030 0.053 0.050 89.30 -

Vicmar Construction Inc. 28997Road Upgrading (Gravel to Paved) along Batangas-

Tabangao-Lobo Rd. (Talahib-Pandayan Sect.) Km.140+402 -Km.140+853 with exception

06/04/10 IVA 9.645 85 O 0.347 0.225 0.150 0.023 0.059 0.050 85.40 -

Vicmar Construction Inc. 28997 Conc. of Palapag-Mapanas Gamay-Lapinig Road 03/03/09 VIII 77.044 298 O 0.349 0.237 0.150 0.030 0.047 0.050 86.30 -

Vicmar Construction Inc. 28997 Construction of RC Platform Connecting Phase 1 and 2 11/15/13 PPA 21.173 210 C 0.492 0.200 0.300 - - - 99.20 97.70% Outstanding

VICMAR CONSTRUCTION, INC. 28997 Construction and Rehabilitation of MPB Structure (Covered Court) Brgy. Sambat 11/8/2014 IV 2.790 90 C 0.392 0.133 0.300 - - - 82.50% 82.5%

Satisfactory

VICMAR CONSTRUCTION, INC. 28997

Widening of Nat'l. Arterial Road along Palico-Balayan-Batangas Road incl. Drainage, Batangas 1st Legislative

District, K0125+260-K0125+660 & K0125+080-K0125+260, Bukal-Tubigan Section

11/8/2014 IV 18.715 198 C 0.444 0.133 0.300 - - - 87.70% 87.7% Satisfactory

Vicmar Construction, Inc. 28997 Const. of Flood Control System along Palico-Balayan-Lemery Diversion Rd., K0129+560-K0131+700 (Int. Sect.) 07/30/13 IVA 9.695 150 C 0.382 0.200 0.300 - - - 88.20 88.32%

Satisfactory

Vicmar Construction, Inc. 28997 Const. of Flood Control System along Palico-Balayan-Lemery Diversion Rd., K0129+560-K0131+700 (Int. Sect.) 03/13/13 IVA 9.695 150 O 0.381 0.240 0.150 0.030 0.050 0.033 88.40 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page294

Page 295: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Vicmar Construction, Inc. 28997 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. at Bauan-Mabini Rd. (K0149+771 to K0150+626) 03/20/12 IVA 14.247 170 C 0.439 0.200 0.300 - - - 93.90 88.08%

Satisfactory

Vicmar Construction, Inc. 28997 Const. of Box Culvert at K0172+797 along Mabini Circ. Road, Ligaya Sect. 03/22/12 IVA 13.823 120 O 0.283 0.300 0.150 0.030 0.037 0.050 85.00 -

Vicmar Construction, Inc. 28997 Const. of Box Culvert @ K0172+797 along Mabini Circ. Rd., Ligaya Sect. 08/16/12 IVA 13.823 120 C 0.423 0.133 0.300 - - - 85.60 85.24%

Satisfactory

Vicmar Construction, Inc. 28997Cluster III - Prev. Maint. (MFO-1) (Intermittent Sect.)

Secondary Rd. at Talisay-Laurel-Agoncillo Rd.: 1.K0122+(-225)-K0122+532 & 2.K0122+532-K0122+934

03/13/13 IVA 11.837 30 C 0.493 0.133 0.300 - - - 92.60 *92.60% V. Satisfactory

Vicmar Construction, Inc. 28997 Construction of R.C. Platform Connecting Phase 1 to Phase 2 04/25/13 PPA 21.206 210 O 0.400 0.300 0.150 0.030 0.054 0.033 96.70 -

VICTORIA DEVELOPMENT & CONSTRUCTION SUPPLY CORP 32638 BCIDP-IC 06/07/14 NIA 24.559 150 O 0.369 0.262 0.150 0.030 0.065 0.050 92.60 -

VIGAN FORTUNE CONST. & SUPPLY 3887 COMPLETION OF BOY'S DORMITORY 08/01/13 DOST 4.999 195 C 0.459 0.200 0.300 - - - - *95.9%

V. SatisfactoryVIGAN FORTUNE CONST. &

SUPPLY 3887 IMPROVEMENT OF GIRLS DORMITORY 08/01/13 DOST 1.982 120 C 0.500 0.200 0.300 - - - 100.00 *100.00% Outstanding

VIGAN FORTUNE CONST. & SUPPLY 3887 COMPLETION OF GYMNASIUM 08/01/13 DOST 22.686 525 C 0.470 0.200 0.170 - - - - 79.19%

Unsatisfactory

VIGAN FORTUNE CONSTRUCTION 3887 Construction/ Rehabilitation of Drainage Protection Works along National Roads, Bucong Flood Control 10/24/2014 I 9.403 171 C 0.400 0.133 0.300 - - - 83.30% 83.3%

Satisfactory

Vigan Fortune Construction 3887 Replacement/Rehab. Strengthening of Permanent Bridge Sta. Lucia Bridge along Manila North Road 8/10/2014 I 11.047 200 C 0.369 0.200 0.300 86.90 85.37%

Satisfactory

Vigan Fortune Construction 3887 Widening of Manila North Road: K0412+200 to K0415+080 8/7/2014 I 8.178 213 C 0.451 0.133 0.300 88.40 84.53% Satisfactory

Vigan Fortune Construction 3887 Widening of Manila North Rd.: a) K0405+000-K0407+880; b)K0409+583-K0412+500-K0415+080 08/13/13 I 8.178 213 O 0.319 0.285 0.150 0.030 0.042 0.050 87.60

Vigan Fortune Construction 3887 Replacement/Rehab./Strengthening of Permanent Bridge, Sta. Lucia Bridge along MNR 08/13/13 I 11.047 201 O 0.371 0.200 0.150 0.030 0.042 0.033 82.60

Vigan Fortune Construction 3887 Replacement/Rehab./Strengthening of Permanent Bridge, Sta. Lucia Bridge along MNR 03/19/13 I 11.049 180 O 0.350 0.300 0.113 0.030 0.035 0.033 86.10 -

Vigan Fortune Construction 3887 Widening of MNR: a)K0405+000-K0407+880; b)K0409+583-K0412+463; c)K0412+200-K0415+080 03/20/13 I 8.178 179 O 0.352 0.300 0.007 0.030 0.041 0.033 76.30 -

Vigan Fortune Construction 3887 Rehab./Reconst./Upgrading of Damaged Paved National Roads, Tagudin Section 09/04/09 I 19.090 222 O 0.338 0.300 0.150 0.022 0.040 0.033 88.30 -

Vigan Fortune Construction 3887 Flood Control Structures along Manila North Rd., Bucong Sect. 03/19/13 I 19.200 398 C 0.442 0.133 0.300 - - - 87.50 *87.50%

Satisfactory

VIGUZ CONSTRUCTION CORPORATION -

Rehabilitation/Reconstruction of Critical Section along Secondary Roads, Roadslip along Jaro-Dagami-Burauen-

La Paz Road, K0953+30810/29/2014 VIII 9.356 200 C 0.456 0.133 0.300 - - - 88.90% 88.9%

Satisfactory

VIGUZ CONSTRUCTION CORPORATION (Formerly : Viguz

Construction)8178 Const. of Busay Bridge, along Barugo - Babatngon Road 8/9/2014 VIII 17.689 190 C 0.429 0.133 0.300 86.20 86.20%

Satisfactory

VIGUZ CONSTRUCTION CORPORATION (Formerly : Viguz

Construction)5463

Road Upgrading (Gravel to paved) Based on Gravel Road Strategies Traffic Benchmark for Upgrading to Paved Road Standard (HDM-4) Project Analysis (Intermittent Section) National Secondary Roads Jaro-Dagami - Buraen - La Paz

road , km. 957+657 …………………….

8/8/2014 VIII 44.251 205 OG 0.364 0.231 0.150 0.030 0.045 0.033 85.30

Viguz Construction Corporation (Formerly: Viguz Construction) 8178 Const. of Busay Bridge, along Barugo-Babatngon Rd. 08/17/13 VIII 17.689 190 O 0.377 0.231 0.150 0.015 0.047 0.050 87.00

Viguz Construction Corporation (Formerly: Viguz Construction) 8178

Rehab./Reconst. of Damaged Paved Nat'l Rds., Dulag-Julita-Burauen Rd., K0954+000-K0955+162; K0952+794-

K0953+00008/17/13 VIII 21.985 160 C 0.461 0.133 0.300 - - - 89.40 86.88%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page295

Page 296: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Viguz Construction Corporation (Formerly: Viguz Construction) 8178

Rehab./Reconst. of Damaged Paved Nat'l. Rds., Dulag-Julita-Burauen Rd., K0954+000-K0955+162; K0952+794-

K0953+00003/11/13 VIII 21.019 130 O 0.394 0.180 0.150 0.023 0.055 0.050 85.20 -

Viguz Construction Corporation (Formerly: Viguz Construction) 8178 Road Slip along Liloan-Sogod Road Section 05/26/09 VIII 9.542 270 O 0.382 0.238 0.150 0.030 0.047 0.033 88.00 -

Viguz Construction Corporation (Formerly: Viguz Construction) 8178 Road Upgrading (Gravel to Paved), Libungao-Matag-ob-

Palompon Road 05/30/09 VIII 18.225 225 O 0.367 0.239 0.150 0.030 0.042 0.033 86.10 -

Viguz Construction Corporation (Formerly: Viguz Construction) 8178 Widening of Carigara Wharf 06/06/09 VIII 1.885 120 O 0.381 0.240 0.150 0.022 0.033 0.033 85.90 -

Viguz Construction Corporation (Formerly: Viguz Construction) 8178 Const. of Bagahupi-Babatngon-Sta. Cruz-Barugo-Carigara

Road, Barugo-Carigara Road Section 06/06/09 VIII 18.887 150 O 0.340 0.240 0.150 0.030 0.037 0.033 83.00 -

Viguz Construction Corporation (Formerly: Viguz Construction) 8178 Rehab./Reconst./Upgrading of Palompon-Isabel-Merida-

Ormoc Road 05/30/09 VIII 12.764 180 O 0.341 0.237 0.105 0.030 0.033 0.017 76.30 -

Viguz Construction Corporation (Formerly: Viguz Construction) 8178 Rehabilitation along Maharlika Highway (Paril Section Km

986+280) 03/04/09 VIII 7.130 222 O 0.343 0.226 0.000 0.030 0.025 0.050 67.40 -

Viguz Construction Corporation (Formerly: Viguz Construction) 8178 Road Slip along Liloan-Sogod Road Section 03/05/09 VIII 9.542 240 O 0.320 0.246 0.150 0.030 0.030 0.050 82.60 -

Viguz Construction Corporation (Formerly: Viguz Construction) 8178

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Secondary Rds., Jaro-Dagami-Burauen-La Paz Rd.

K0952+813-K0969+46003/19/12 VIII 25.952 240 O 0.358 0.238 0.150 0.030 0.045 0.050 87.10 -

Viking Construction & Supplies 18129 Rehab. of Mangitayag Flood Control along Dingris River 08/03/12 I 13.698 114 O 0.314 0.235 0.150 0.020 0.035 0.033 78.70 -

Viking Construction & Supplies / B.M.K. Construction (JV) JV-10-002

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Roads, Generated from PMS/HDM-4, Laoag-Bacarra-

Pasuquin-Burgos-Bangui-Pagudpud03/16/12 I 209.308 360 C 0.389 0.200 0.300 - - - 88.90 89.38%

V. Satisfactory

VIKING CONSTRUCTION AND SUPPLIES 18129

Preventive Maintenance Based on Pavement Management System, HDM-4 Intermittent Section, Laoag-Sarrat-Piddig-

Solsona Road K0498+000 to K0503-65110/21/2014 I 14.020 31 C 0.381 0.200 0.300 - - - 88.10% 88.1%

Satisfactory

VIKING CONSTRUCTION AND SUPPLIES 18129 Replacement of Bulag Bridge 2 along Manila North Road,

Bantay, Ilocos Sur, Sta.401+766.10 to Sta. 401+799.90 10/23/2014 I 5.940 199 C 0.489 0.143 0.300 - - - 93.20% 93.2% Very Satisfactory

Viking Construction and Supplies 18129

Construction/Widening/ Upgrading/Rehabilitation of Access Road to Declared Tourism Destinations Maoini-

Baduang-Saud Road a) Sta 0+000 (Equivalent to Km. 558+500) to Sta. 5+021.90 (Section 1) b) Sta. 3+282.52 to

Sta. 8+000 (with exceptions)

8/10/2014 I 88.609 240 C 0.457 0.133 0.300 89.00 88.58% Satisfactory

Viking Construction and Supplies 18129 Rehab./Improvement of Manila North Road, K0412+000 - K0416+000 with exception 8/7/2014 I 32.307 209 C 0.462 0.133 0.300 89.50 86.98%

Satisfactory

Viking Construction and Supplies 18129 Replacement of Bulag Bridge 2 along Manila orth Road, Sta. 401+766.1 to Sta. 401+799.90 8/6/2014 I 5.940 199 OG 0.330 0.240 0.150 0.030 0.045 0.033 82.80

Viking Construction and Supplies 18129Const. of Slope Protection (Upstream) Installation of Rd. Signs & Pvmt. Studs/Impv't. of Masonry Walls of Bungao

Bridge along MNR08/16/13 I 1.732 22 C 0.428 0.133 0.300 - - - 86.10 *86.10%

Satisfactory

Viking Construction and Supplies 18129 Prev. Maint. (Int. Sect.) Nat'l Arterial Rd., K0490+(-839)-K0490+074, Ilocos Norte-Apayao Rd. 08/16/13 I 12.067 74 C 0.411 0.133 0.300 - - - 84.40 89.50% V.

Satisfactory

Viking Construction and Supplies 18129 Rehab./Impv't. of MNR, K0412+000-K0416+000 w/ exceptions 08/13/13 I 32.307 209 O 0.326 0.264 0.150 0.030 0.047 0.033 85.00

Viking Construction and Supplies 18129 Prev. Maint. (Int. Sect.) Nat'l Arterial Rd., K0490+(-839)-K0490+074, Ilocos Norte-Apayao Rd. 03/22/13 I 12.067 74 O 0.363 0.297 0.150 0.030 0.039 0.050 92.90 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page296

Page 297: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Viking Construction and Supplies 18129 Rehab./Impv't of MNR, K0412+000-K0416+000 w/ exceptions 03/20/13 I 32.307 99 O 0.338 0.300 0.114 0.030 0.041 0.033 85.60 -

Viking Construction and Supplies 18129 Repair/Rehab. of Cabuloan Flood Control 03/23/13 CAR 13.539 124 C 0.035 0.133 0.300 - - - 46.80 67.98% Poor

Viking Construction and Supplies 18129 Const. of Sch. Bldg., A.P. Santos E/S 03/17/12 I 4.307 131 C 0.410 0.187 0.300 - - - 89.70 85.71% Satisfactory

Viking Construction and Supplies 18129 Rehab. of Mangitayag Flood Control along Dingris River 01/24/13 I 16.698 144 C 0.477 0.133 0.300 - - - 91.00 83.62% Satisfactory

Viking Construction and Supplies 18129 Repair/Rehab./Impv't. of Nat'l. Rds., Abra-Ilocos Norte Rd., K0413+168-K0414+328 03/23/13 CAR 9.894 16 C 0.356 0.133 0.300 - - - 78.90 *78.90%

Unsatisfactory

Viking Construction and Supplies 18129 Prev. Maint. (Int. Sect.) Manila North Rd., K0500+000-K0501+000, Bacarra-Pasuquin Sect. 03/22/13 I 6.879 26 C 0.457 0.133 0.300 - - - 89.00 *89.00%

Satisfactory

VIKING CONSTRUCTION AND SUPPLIES/JAJR CONSTRUCTION

(JV)JV-13-267

Preventive Maintenance along San Fernando-Bagulin Road at K0270+ (-)1016 to K0270+(-773), K0270+(-647) to K0270+000, K0270+379 to K0271+000 and K0274+416 to

K0274+448

8/9/2014 I 25.834 181 C 0.417 0.141 0.300 - - - 85.80% 85.8% Satisfactory

Viking Construction and Supply 18129

Const./Widening/Upgrading/Rehab.of Acess Rds. to Declared Tourism destinations Maoini Baduang-Saud Rd., a)Sta. 0+00 equivalent to Sta. 558+000-Sta. 5+021.90 (Sect.

1) b)Sta. 3+282.52-Sta. 0+000 (w/ exceptions)

08/15/13 I 88.609 180 O 0.369 0.300 0.104 0.030 0.047 0.033 88.30

Villar General Construction and Supplies 22540 Impvt./Upgrading of Flood Control & Drainage Structure

along MNR, Km. 239+000 - Km. 250+500 w/ exception 8/5/2014 I 13.538 180 C 0.356 0.200 0.300 85.60 85.60% Satisfactory

Villar General Construction and Supplies 22540

Impvt./Upgrading of Flood Control & Drainage Structures along Manila North Rd., Km. 239+000-Km.250+500 w/

exception08/01/13 I 13.539 180 O 0.358 0.300 0.150 0.030 0.037 0.033 90.80

Villaram Builders 21632 Widening of Causeway, Constn. Of RoRo Ramp and RC Pier 11/06/15 PPA 25.707 300 O 0.368 0.300 0.111 0.030 0.065 0.050 92.37 -

VIRAC NRC CONSTRUCTION 11396 Construction of Multi Purpose Building, Isaac Lopez Integrated School 8/8/2014 NCR 9.659 120 C 0.425 0.133 0.300 85.80 84.33%

Satisfactory

Virac NRC Construction 11369 Const. of MPB, Isaac Lopez Integrated Sch., Brgy. Vergasa 08/06/13 NCR 9.659 120 O 0.326 0.240 0.150 0.030 0.041 0.050 83.70

Virac NRC Construction 11396 Rehab./Road Opening of San Antonio St., Brgy. Cabugao 08/16/11 V 9.594 225 O 0.375 0.122 0.150 0.020 0.028 0.050 74.50 -

Virlo Construction 5765 Conc. of Bacolod South Road (Su-ay Section) 03/06/09 VI 22.306 319 O 0.231 0.300 0.150 0.030 0.060 0.050 82.10 -

Virlo Construction 5765 Impv't/Conc. of JCT.LIR Carmen-Sagbayan-Bacani Road 03/07/09 VII 23.600 252 O 0.388 0.200 0.150 0.030 0.047 0.033 84.80 -

Virlo Construction 5765 Conc. of Bacolod South Road (Su-ay Section) 11/21/08 VI 22.306 319 O 0.335 0.225 0.100 0.010 0.038 0.067 77.50 -

Vites Construction & Development Corporation (Formerly: Vites

Trading & Const.)9444 Proposed Const./Repair/Rehab. of School Bldg. Manila

Science H/S 02/16/10 NCR 4.819 116 O 0.364 0.240 0.150 0.022 0.041 0.050 86.70 -

VIVID CONSTRUCTION, INC. (Formerly: Vivid Construction) 21115 Slope Protection/Bank Improvement of Paranaque River

Diversion Channel (Phase II), Brgy. San Dionisio 11/18/2014 NCR 8.669 159 C 0.357 0.200 0.300 - - - 85.70% 85.7% Satisfactory

VIVID CONSTRUCTION, INC. (Formerly: Vivid Construction) 21115 Proposed Rehabilitation/Improvement of Existing Seawall

and Open Canal along Roxas Boulevard 11/20/2014 NCR 7.857 120 C 0.436 0.133 0.300 - - - 86.90% 86.9% Satisfactory

Vivid Construction, Inc. (Formerly: Vivid Construction) 21115 Proposed/Repair/Rehab./Impv't. of Drainage System along

Taft Ave., Baclaran (Gil Puyat Ave. to EDSA) 03/13/13 NCR 9.594 289 O 0.386 0.240 0.150 0.023 0.030 0.033 86.20 -

Vivid Construction, Inc. (Formerly: Vivid Construction) 21115 Proposed Const./Rehab. of MPB (Phase I) Brgy. 190, BAC II

St. 03/13/13 NCR 4.747 147 C 0.457 0.185 0.300 - - - 94.20 73.55% Poor

VNKC Construction

Package X-I: Construction of lateral "N" (Sta. 10+100-Sta. 11+880), sub-lat. "N-7" (Sta. 0+000-Sta. 1+600) and "N-8" (Sta. 0+000-Sta. 0+905) including related structures and

supply, delivery and installation of steel gates

02/07/15 NIA 22.118 180 O 0.328 0.281 0.150 0.030 0.014 0.050 85.27 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page297

Page 298: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

VNKC Construction 12614 Construction of Canal Lining @ Lateral F-2a Extra, Sta. 1+740-2+040 07/21/12 NIA 3.376 75 O 0.369 0.252 0.150 0.030 0.051 0.050 90.20 -

VRF Construction 15301 Rehab./Reconst./Upgrading of Damaged Paved Daang Maharlika Rd., Nueva Ecija 2nd Congressional 08/09/13 III 91.277 335 C 0.466 0.133 0.300 - - - 89.90 89.90% V.

Satisfactory

VRF Construction 15301Asset Preservation of Nat'l Rd. Generated from Pvmt. Mgt. System/Highway Dev. & Mgt. System (HDM-4), Dingalan-

Gabaldon Rd., K0177+801-K0179+00008/10/13 III 19.475 79 C 0.427 0.133 0.300 - - - 86.00 *86.00%

Satisfactory

VRF Construction 15301Repair/Restoration of Washed-out Overflow Bridge &

Approaches (Calaocan Brgidge) Bongabon-Rizal-Aurora Rd.

06/08/10 III 9.366 110 O 0.336 0.240 0.150 0.023 0.032 0.050 83.10 -

VRF Construction 15301 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Road Gapan-Fort Magsaysay Road 03/21/12 III 73.156 210 O 0.277 0.300 0.150 0.030 0.056 0.050 86.30 -

VRF Construction 15301 Rehab./Reconst./Upgrading Gapan-Forty Magsaysay Rd. 08/04/12 III 73.156 209 C 0.320 0.200 0.300 - - - 82.00 84.58% Satisfactory

VRF Construction 15301 Construction of Caridad Pump Irrigation Project UPRSIIS-2011-08; Package No. II 08/03/12 NIA 21.390 90 O 0.392 0.270 0.150 0.030 0.045 0.050 93.71 -

VRF Construction / Allen Construction Joint Venture JV-12-544 Const. of Flood Control Project along Talavera River,

Basang Hamog 08/13/13 III 13.750 90 C 0.388 0.133 0.300 - - - 82.10 *82.10% Satisfactory

VRF Construction / D.G. Sarmenta Construction Joint Venture JV-12-598 Const. of Digmala River Control Calaanan Sect., Sta.

0+279.97-Sta. 0+994.01 (714.04 LM) 08/10/13 III 19.117 120 C 0.425 0.133 0.300 - - - 85.80 *85.80% Satisfactory

VUC ENGINEERING 7918

Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Road Along Kalinga-Cagayan Road (Calanan-Enrile Section), K0398+366-K0499+000 &

K0499+306-K0499+892

8/7/2014 CAR 33.197 381 C 0.396 0.133 0.300 82.90 85.84% Satisfactory

VVER Construction 14122 Const. of Level III Water System at Poblacion Norte Maria 06/07/10 VII 1.446 155 O 0.325 0.300 0.150 0.030 0.019 0.050 87.40 -

VVER Construction 14122 Const./Completion of MPB at Poblacion 06/07/10 VII 1.927 180 O 0.296 0.284 0.150 0.030 0.040 0.050 85.00 -VVER Construction 14122 Const. of Multi-Purpose Building at Brgy. Poblacion 06/02/09 VII 1.924 150 O 0.364 0.241 0.150 0.030 0.038 0.050 87.30 -VVER Construction 14122 Repair/Rehabilitation of Punta Road, Poblacion 03/13/09 VII 1.832 193 O 0.400 0.200 0.150 0.030 0.033 0.033 84.60 -

VVH CONSTRUCTION CORPORATION 32689

Construction/Maint of Flood Mitigation Structures and Drainage System, Repair/Rehabilitation of Abaca Flood

Control10/21/2014 I 18.042 212 O 0.407 0.160 0.300 86.70% 86.7%

Satisfactory

VVH Construction Corporation 32689 BSP Batac Branch Various Improvement Works 07/08/14 BSP 11.325 75 C 0.459 0.200 0.300 - - - - *95.90% V. Satisfactory

W B X Construction 28370 Rehab./Rconst./Upgrading of Damaged Paved National Road at Daang Maharlika Rd. 06/09/10 III 19.113 100 O 0.377 0.300 0.150 0.008 0.027 0.050 91.20 -

W B X Construction 28370 Construction of Slope Protection along Bocaue River 05/29/09 III 9.543 60 O 0.376 0.240 0.150 0.030 0.038 0.050 88.40 -

W B X Construction 28370 Const. of Multi-Purpose Building at Senior Citizens Federation 03/06/09 III 0.473 12 O 0.368 0.284 0.150 0.030 0.020 0.017 86.90 -

W B X Construction 28370Rehab./Reconst./Upgrading of Damaged Paved Nat'l

Roads, Plaridel-Pulilan Diversin Road (IS) Km.42+(-1015)-Km.42+652.29 w/ exceptions

03/14/12 III 13.394 70 C 0.453 0.180 0.300 - - - 93.30 91.02% V. Satisfactroy

W B X Construction 28370 Const. of Drainage Panginay, Guiguinto & Dampol 03/18/13 III 0.948 25 C 0.417 0.133 0.300 - - - 85.00 *85.00% Satisfactory

W.D Navarro Construction, Co. 14327 New Const./Completion/Continuation On-going Maxingal Bridge along Cagayan Valley Rd. 05/25/10 II 16.710 290 O 0.372 0.300 0.150 0.024 0.033 0.033 91.20 -

W.D Navarro Construction, Co. 14327 New Const./Completion/Continuation of On-going Maxingal Bridge along Cagayan Valley Road 08/17/10 II 16.710 290 O 0.342 0.300 0.042 0.020 0.004 0.000 70.80 -

W.D Navarro Construction, Co. 14327 Upgrading/Improvement of Manila North Road (JCt. Bangag-Paraddum Section) 05/20/09 II 9.445 251 O 0.354 0.240 0.150 0.030 0.047 0.050 87.10 -

W.D. Navarro Construction Co. 14327 Construciton/Widening/ Rehabilitation of Access Road at Aparri Airport 8/5/2014 II 28.825 194 C 0.370 0.200 0.115 68.50 77.02%

Unsatisfactory

W.D. Navarro Construction Co. 14327 Widening/Improvement of Dugo-San Vicente Road 8/4/2014 II 13.561 136 C 0.409 0.200 0.256 86.50 76.18% Unsatisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page298

Page 299: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

W.D. Navarro Construction Co. 14327 Const./Widening//Upgrading/Rehab. of Access Rd. at Aparri Airport, Maura 07/30/13 II 27.645 179 O 0.384 0.200 0.071 0.030 0.060 0.050 79.50

W.D. Navarro Construction Co. 14327 Widening/Impv't. of Dugo-San Vicente Rd. 07/31/13 II 12.980 121 O 0.353 0.238 0.000 0.030 0.055 0.017 69.30

W.D. Navarro Construction Co. 14327 Const./Widening/Upgrading/Rehab. of Access Rd., Aparri-Airport, Maura 03/12/13 II 27.645 179 O 0.353 0.225 0.150 0.030 0.051 0.050 85.90 -

W.D. Navarro Construction Co. 14327 Widening/Upgrading/Rehab. Of Access Road to Airports at Aparri Airport Road, Maura-Buguey, Cagayan Sect. 03/13/12 II 24.694 240 C 0.358 0.200 0.300 - - - 85.80 85.56%

Satisfactory

W.D. Navarro Construction Co. 14327 Widening/Upgrading/Rehab. Of Access Road to Airports at Aparri Airport Road, Maura 03/12/12 II 19.295 240 C 0.207 0.200 0.300 - - - 70.70 76.79%

Unsatisfactory

W.D. Navarro Construction CO. 14327Rehab./Reconst./Upgrading of Damaged Paved Nat'l.

Roads, at K0569+000-K0572+000 along Cagayan Valley Rd. (Magapit-Jct. Aparri Airport Rd.)

07/31/12 II 8.830 120 C 0.319 0.200 0.000 - - - 51.90 61.56% Poor

W.J.P. Construction & Supply 23192 Construction of Lateral "A" at Sta. 4+256 - Sta 4+876 of Laris 02/27-03/03/12 NIA 11.523 120 O 0.355 0.264 0.150 0.030 0.051 0.050 89.91 -

W.T.G Construction and Development Corporation 7494 Const./Rehab. of River Control including Seawall at

Tabajan 06/05/09 VII 9.363 300 O 0.226 0.300 0.150 0.030 0.047 0.033 78.60 -

Wakaii Construction 34526 Repair/Maint. of Casili Flood Control Proj. (Casili Creek), Casili 03/18/13 II 1.493 60 C 0.417 0.133 0.300 - - - 85.00 85.84%

Satisfactory

WALDY CONSTRUCTION 32473

Rehab./Recons'n/ Upgrading of Damaged Paved National Roads Including Drainage Based on Pavement Management System/Highway Development &

Management-4 (HDM-4), Intermittent Sections Junction Sta. Cruz-Pinpin Road, K0334+290 to K0335+000

10/24/2014 I 1.479 43 O 0.345 0.258 0.150 0.030 0.056 0.050 88.90% 88.9% Satisfactory

Waldy Construction 32473 Rd. Upgrading (Gravel to Paved) along Sta. Cruz-Pinipin Rd., 0337+(-182)-K0337+(-045) 03/19/13 I 2.659 37 C 0.416 0.133 0.300 - - - 84.90 *84.90%

Satisfactory

Walter Ng Lao Construction 23739 Balingasag River Irrigation Project 09/26-27/11 NIA 199.249 515 O 0.350 0.240 0.000 0.024 0.056 0.017 68.68 -

Walter Ng Lao Construction 23739 Panansalan-Cartagena Communal Irrigation System 10/6-10/08 NIA 5.787 148 O 0.370 0.160 0.070 0.015 0.053 0.200 86.72 -

Walter Ng Lao Construction 23739 Const. of Multi-Purpose Building (Phase II) 06/03/09 X 4.820 120 O 0.309 0.240 0.150 0.030 0.013 0.050 79.20 -

Walter Ng Lao Construction 23739 Road Upgrading (Gravel to Paved) OroquietaCity-Calamba Mt. Road Km. 1760+400-Km. 1761+274 w/ exceptions 09/15/09 X 3.211 120 O 0.392 0.297 0.000 0.030 0.061 0.017 79.70 -

Walter Ng Lao Construction 23739 Const./Repair/Rehab. of MPB @ Brgy. 23 08/14/12 X 3.326 150 C 0.476 0.200 0.300 - - - 97.60 86.89% Satisfactory

Walter Ng Lao Construction 23739Rehab./Reconst./Upgrading of Damaged Paved Nat't. Rd.

Butuan City-Cagayan de Oro City- Iligan City Rd., Gingoog-Claveria-Villanueva Rd. (Km.1378+0-Km.1380+736)

08/17/12 X 18.496 180 C 0.422 0.200 0.300 - - - 92.20 86.80% Satisfactory

Walter ng Lao Construction Balingasag River Irrigation Project 03/31/12 NIA 14.405 150 O 0.316 0.295 0.109 0.030 0.042 0.050 84.16 -

Walter Ng Lao Construction/ RG & K Construction and General

Merchandise (JV)JV-10-071

Rd. Upgrading (Gravel to Paved) Gingoog-Claveria-Villanueva Rd. K01330+520-K01334+315, K01334+336-

K01337+096, K01337+311-K01338+50008/17/12 X 43.377 180 C 0.425 0.200 0.300 - - - 92.50 88.48%

Satisfactory

Wangjo Construction 29924 Asphalt Overlay/Conc. Reblocking along Nueva Vizcaya-Ifugao-Mt. Province Bdry. Road Km. 324+000-Km.334+000 05/26/09 CAR 9.601 200 O 0.372 0.300 0.150 0.010 0.040 0.050 92.20 -

Water Dragon Construction 33046 MARIIS-D1-POW#3-2014, Package 2 04/24/15 NIA 14.055 90 O 0.431 0.195 0.150 0.010 0.027 0.017 83.00 -

Waterton Construction & Realty Development Corporation 32492

Rd. Upgrading (Gravel to Paved) of Bacon-Sawanga-Prieto Diaz Rd., (Sect. A - K0618+(-035)-K0618+457); (Sect. B -

K0618+484-K0618+655)08/15/13 V 6.825 58 C 0.417 0.133 0.300 - - - 85.00 *85.00%

Satisfactory

WATERTON CONSTRUCTION & REALTY DEVELOPMENT

CORPORATION32492 Construction of Flood Control (Cluster I) Sorsogon Second

District 11/6/2014 V 4.132 90 C 0.460 0.133 0.300 - - - 89.30% 89.3% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page299

Page 300: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Waterton Construction & Realty Development Corporation 32492 Construction of Protection Works (Cluster 1) Sorsogon 8/12/2014 V 7.361 90 C 0.333 0.200 0.300 83.30 83.30%

Satisfactory

Waterton Construction & Realty Development Corporation 32492 Const. of Hanging Bridge Across Creek, Alnay 08/08/12 V 1.904 120 O 0.353 0.231 0.150 0.030 0.029 0.033 82.60 -

Watertone Construction & Realty Development Corporation 32492 Const. of Hanging Bridge Across Creek 11/25/12 V 1.904 120 C 0.469 0.133 0.300 - - - 90.20 85.64%

Satisfactory

WAWOT BUILDERS 33592 Const. of School Building (1-unit - 1-Storey 3 CL & 1 unit - 1-Storey 2 CL, San Juan Tismo NHS 8/10/2014 VIII 2.958 165 C 0.491 0.133 0.300 92.40 92.40%

Very Satisfactory

Wawot Builders 33592 Const. of Sch. Bldg. (1 unit - 1 storey 3CL & 1 unit - 1 storey 2 CL, Juan Tismo NHS 08/30/13 VIII 2.963 165 O 0.357 0.300 0.090 0.012 0.051 0.033 84.30

WBX CONSTRUCTION 28370Preventive Maintenance based on Pavement Management System/HDM-4 Gen. Alejo Santos Highway Km. 50+383 to

Km. 51+00011/7/2014 III 4.328 18 C 0.458 0.133 0.300 - - - 89.10% 89.1%

Very Satisfactory

WBX Construction 28370 Construction/Rehabilitation of Pecsonville Road 9/27/2014 Special 3 18.571 149 C 0.350 0.190 0.300 84.00 84.00% Satisfactory

WCS CONSTRUCTION INC. (Formerly: WCS Construction) 6516 Preventive Maintenance based on Pavement Management

System/HDM-4 (Intermittent Section) Asphalt Overlay of 11/14/2014 V 7.199 60 C 0.469 0.133 0.300 - - - 90.20% 90.2% Very Satisfactory

WCS CONSTRUCTION INC. (Formerly: WCS Construction) 6516 Preventive Maintenance of Daang-Maharlika (K0608+000-

K0609+103) with exception 11/6/2014 V 16.291 75 C 0.471 0.133 0.300 - - - 90.40% 90.4% Very Satisfactory

WCS CONSTRUCTION INC. (Formerly: WCS Construction) 6516

Preventive Maintenance Based on Pavement Management/HDM-4 (Intermittent Section) Asphalt Overlay

of Matacon-Libon-11/14/2014 V 8.674 35 C 0.447 0.133 0.300 - - - 88.00% 88%

Satisfactory

WCS CONSTRUCTION INC. (Formerly: WCS Construction) 6516 Construction/Rehabilitation of Flood Control System Along

San Vicente River, Brgy. San Vicente, Bulan, Sorsogon 11/6/2014 V 46.348 169 C 0.462 0.133 0.300 - - - 89.50% 89.5% Very Satisfactory

WCS CONSTRUCTION INC. (Formerly: WCS Construction) 6516

Cluster 1 - Assets Preservation of National Roads from Pavement Management System HDM-4, Intermittent

Secondary Roads, Sorsogon Diversion Road, Jct. Putiao-Pilar-Donsol Road, Jct. Abuyog-Gubat-Ariman Road, 1st

District of Sorsogon

11/5/2014 V 6.081 75 C 0.435 0.133 0.300 - - - 86.80% 86.8% Satisfactory

WCS Construction Inc. (Formerly: WCS Construction) 6516

Preventive Maintenance Based on PMS/HDM-4 (Intermittent Section), Asphalt Overlay at Matacon-Libon-

Polangui Jct. Road, K0491+000 - K0491+9908/11/2014 V 8.674 35 C 0.434 0.133 0.300 86.70 86.70%

Satisfactory

WCS Construction Inc. (Formerly: WCS Construction) 6515 Construction/Improvement of Yawa River Control,

Bogtong-Rawis Section 8/15/2014 V 46.077 214 C 0.365 0.200 0.300 86.50 86.26% Satisfactory

WCS Construction Inc. (Formerly: WCS Construction) 6516 Replacement of Bonga Bridge #2 along DM Jct. Legazpi-

Sto. Domingo-Tabaco-Cam Sur Bdry. Rd, K0547+132 08/12/13 V 5.156 163 C 0.464 0.133 0.300 - - - 89.70 *89.70% V. Satisfactory

WCS Construction Inc. (Formerly: WCS Construction) 6516 Const./Impv't. of Yawa River Control, Bogtong-Rawis Sect. 08/10/13 V 46.077 214 O 0.332 0.265 0.150 0.030 0.051 0.033 86.10

WCS Construction Inc. (Formerly: WCS Construction) 6516

Rehab./Reconst. of Damaged Paved Nat'l Rds. along DM Jct.-Legazpi-Sto. Domingo-Tabaco-Cam. Sur Bdry. Rd.,

K0571+000-K0573+000 w/ exception11/22/12 V 17.348 180 C 0.485 0.140 0.300 - - - 92.50 89.56%

V. Satisfactory

WCS Construction Inc. (Formerly: WCS Construction) 6516 Const. of Flood Control Structure in Pob. Bacon River

(Reconst. of Slope Protection at Downstream (left side) 11/20/12 V 28.444 210 O 0.302 0.300 0.150 0.030 0.052 0.033 86.70 -

WCS Construction Inc. (Formerly: WCS Construction) 6516 Rehab./Reconst. of Damaged Paved Nat'l Rds. along Bacon-

Sawanga-Prieto Diaz Rd., Bacon Dist. 11/20/12 V 18.478 150 C 0.432 0.133 0.300 - - - 86.50 86.62% Satisfactory

WCS Construction Inc. (Formerly: WCS Construction) 6516 Bobonsoran, Bonga, Tuburan, Batingkal, Pinit, Cavasi &

Tagpo Flood Control, Ligao City 08/07/12 V 42.793 270 C 0.450 0.133 0.300 - - - 88.30 89.20% V. Satisfactory

WCS Construction Inc. (Formerly: WCS Construction) 6516 Const. of Flood Control Project along Cogon Gully

(Upstream & Downstream), Gulang-Gulang Bridge 08/03/12 V 41.950 180 C 0.465 0.133 0.300 - - - 89.80 88.36% Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page300

Page 301: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

WCS Construction Inc. (Formerly: WCS Construction) 6516

Rehab./Reconst. Of Damaged Paved Nat'l Rds. along DM Junction-Legazpi-Sto. Domingo-Tabaco-Cam. Sur Bdry.

Rd. K0571+000-K0573+000 w/ exception08/02/12 V 17.348 180 O 0.369 0.240 0.150 0.030 0.054 0.033 87.60 -

WCS Construction Inc. (Formerly: WCS Construction) 6516 Repair/Rehab./Impvt. of Daang Maharlika, Bascaran Sect.,

Km. 0531+000-Km. 0532+246 w/ exception 07/30/12 V 19.622 150 C 0.422 0.133 0.300 - - - 85.50 86.88% Satisfactory

WCS Construction, Inc. 6516 Pili Port Development Project 07/13/13 DOTC 8.650 120 C 0.457 0.200 0.300 - - - 95.70 *95.70% V. Satisfactory

WCS Construction, Inc. 6516 Ligao LTO District Office Project 09/04/13 DOTC 12.873 240 O 0.380 0.300 0.150 0.020 0.053 0.050 95.30 -

WCS Construction, Inc. 6516 Ligao LTO District Office Project 12/11/13 DOTC 12.873 240 C 0.418 0.200 0.300 - - - 91.80 94.20% V. Satisfactory

WCS Construction, Inc. 6516 Sto. Domingo Port Development Project 07/24/13 DOTC 6.931 120 C 0.453 0.200 0.300 - - - 95.30 *95.30% V. Satisfactory

WCS Construction, Inc. (Formerly: WCS Construction) 6516 Completion of Padang Bridge, Sto Domingo-Legaspi City

Boundary 05/28/10 V 11.500 120 O 0.344 0.240 0.150 0.030 0.045 0.050 85.90 -

WCS Construction, Inc. (Formerly: WCS Construction) 6516 Const. of Basud (Labanon Section) River Control 05/28/10 V 8.158 180 O 0.336 0.240 0.150 0.030 0.040 0.050 84.60 -

WCS Construction, Inc. (Formerly: WCS Construction) 6516 Rehab./Impvt. of Catbalogan North Road, Km. 801+000-Km.

802+000 with exception, 06/05/09 VIII 18.696 120 O 0.289 0.240 0.150 0.030 0.045 0.033 78.70 -

WCS Construction, Inc. (Formerly: WCS Construction) 6516 Road Conc. of San Juanico-Basey-Sohoton Road, Km.

908+890-Km. 910+140 06/04/09 VIII 18.697 202 O 0.171 0.240 0.150 0.030 0.040 0.033 66.40 -

WCS Construction, Inc. (Formerly: WCS Construction) 6516 Repair/Rehab. of National Rd. along Wright-Taft-Borongan

Rd., Km.827+252 - Km.828+512 06/10/10 VIII 24.375 240 O 0.347 0.300 0.150 0.030 0.042 0.033 90.20 -

WCS Construction, Inc. (Formerly: WCS Construction) 6516 Land Development of Polangui Resettlement Project 7/21-25/08 SLB 23.994 150 O 0.332 0.243 0.000 0.030 0.065 0.033 70.29 -

WCS Construction, Inc. (Formerly: WCS Construction) 6516 Construction of Comon Bridge 09/01/09 V 28.813 180 O 0.380 0.240 0.150 0.030 0.047 0.050 89.70 -

WCS Construction, Inc. (Formerly: WCS Construction) 6516 Const. of Bayandong Bridge 09/01/09 V 12.466 233 O 0.353 0.240 0.150 0.030 0.047 0.050 87.00 -

WCS Construction, Inc. (Formerly: WCS Construction) 6516 Conc. of San Juanico-Basey-Sohotan Road 03/12/09 VIII 18.697 150 O 0.357 0.000 0.110 0.030 0.033 0.050 58.00 -

WCS Construction, Inc. (Formerly: WCS Construction) 6516 Const. of Flood Control Proj. along Cogon Gully (Upstream

& Downstream), Gulang-Gulang Bridge 03/12/12 V 41.950 180 O 0.384 0.232 0.150 0.030 0.045 0.033 87.40 -

WCS Construction, Inc. (Formerly: WCS Construction) 6516 Channel Impvt./Widening/Diking of Talisay River &

Impvt./Diking of Velasco River 03/17/12 V 45.726 210 O 0.300 0.300 0.117 0.030 0.059 0.033 83.90 -

WCS Construction, Inc. (Formerly; WCS Construction) 6516 Const. of Flood Control Structure in Pob. Bacon River

(Reconst. of Slope Protection at Downstream (left side) 03/16/13 V 28.444 210 C 0.424 0.133 0.300 - - - 85.70 86.30% Satisfactory

WCS Construction, Inc. (Formerly; WCS Construction) 6516 Upgrading of Asgad Spillway along Catanduanes Circ. Rd. 03/17/13 V 9.604 275 C 0.412 0.133 0.300 - - - 84.50 84.86%

Satisfactory

WCS Construction, Inc. / DSB Construction & Supply Inc. (JV) JV-08-206 Construction of Calbayog Bridge, Phase I, Calbayog 05/18/09 V 19.178 180 O 0.358 0.240 0.150 0.023 0.040 0.050 86.10 -

WCS Construction, Inc./Makapa Corporation (JV) 6516 Construction of Breakwater 08/24/09 V 23.763 145 O 0.333 0.300 0.150 0.030 0.051 0.033 89.70 -

WCS CONSTRUCTION, INC./WEARR ENTERPRISES &

DEVELOPMENT CORP. (JV)

SL1-SN-0007568

Const./Improvement of Cagraray Circumferential Road and Access Road, Sta. 563+400-Sta.565+400 11/7/2014 V 70.951 473 C 0.460 0.133 0.300 - - - 89.30% 89.3%

Very Satisfactory

WDM Construction & Supplies 18877 Const. of MPB 03/09/09 X 0.940 105 O 0.347 0.240 0.150 0.030 0.035 0.050 85.20 -

WDM Construction & Supplies 18877 Upgrading of Kibungsod-Cabantian FMR 08/14/12 X 9.647 239 O 0.240 0.300 0.150 0.030 0.050 0.050 82.00 -

WDM CONSTRUCTION & SUPPLIES / ME 3 CONSTRUCTION

JOINT VENTUREJV-13-737

Restoration of Mambayaan Bridge I Approach "B" and Const. of 100 lm Revetment, along BCIR,

Mambayaan,Balingasag, Misamis Oriental8/11/2014 X 29.871 169 OG 0.378 0.300 0.150 0.030 0.050 0.050 95.80

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page301

Page 302: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

WDM Construction and Supplies 18877Rehab./Reconst./Upgrading Damaged Paved (Asphalt to Concrete) of CDO City-Dominorog-Camp Kibaritan Road

(Sto Niño Sect.) Km.1476+082-Km.1476+80203/22/12 X 3.416 104 C 0.433 0.200 0.140 - - - 77.30 83.30%

Satisfactory

WDM Construction and Supplies 18877 Upgrading of Kibungsod-Cabantian FMR 11/22/12 X 9.647 239 C 0.440 0.200 0.300 - - - 94.00 86.80% Satisfactory

WEARR ENTERPRISES & DEVELOPMENT CORP. 14123 Major Repair/Maintenance of Existing Permanent Bridge,

Nale Bridge along Albay West Coast Road 11/14/2014 V 2.741 135 C 0.479 0.133 0.300 - - - 91.20% 91.2% Very Satisfactory

Wearr Enterprises & Development Corp. 14123 Major Repair/Maintenance of Existinf Permanent Bridge,

Nale Bridge along Albay West Coast Road 8/11/2014 V 2.741 135 C 0.359 0.200 0.300 85.90 85.90% Satisfactory

Wearr Enterprises & Development Corp. 14123 Const./Ext. of Sch. Bldg. inc. Fence, Sogod NHS 08/12/13 V 1.404 120 C 0.437 0.133 0.300 - - - 87.00 *87.00%

SatisfactoryWearr Enterprises & Development

Corp. 14123 Const. of Carriedo River Control w/ Floodway Clearing 08/14/13 V 18.889 195 C 0.443 0.133 0.300 - - - 87.60 84.90% Satisfactory

Wearr Enterprises & Development Corp. 14123 Const. of Carriedo River Control with Floodway Clearing 03/15/13 V 18.889 195 O 0.356 0.232 0.150 0.030 0.030 0.033 83.10 -

Wearr Enterprises & Development Corp. 14123 Cullat-Bongalon-Kidaco FMR 05/28/10 V 2.828 180 O 0.351 0.240 0.150 0.030 0.035 0.033 83.90 -

Wearr Enterprises & Development Corp. 14123 Const. of 17-Units, 1-CL Modified Type School Building

(7.00Mx7.00M) various Locations, Catbalogan I CES 06/05/09 VIII 0.441 124 O 0.336 0.240 0.150 0.030 0.035 0.050 84.10 -

Wearr Enterprises & Development Corp. 14123 Dredging of Nagas River 08/01/12 V 16.935 116 C 0.367 - 0.500 - - - 86.70 85.32%

SatisfactoryWearr Enterprises & Development

Corp. 14123 Const. of Line Canal at Brgy. Tagas, Daraga to Brgy. Bogtong, Legazpi City 07/31/12 V 9.178 195 C 0.421 0.133 0.300 - - - 85.40 84.14%

SatisfactoryWearr Enterprises & Development

Corp. 14123 Impvt./Widening/Rehab. of Nagasgasan Creek (Phase I-B) 08/08/12 V 12.765 150 C 0.470 0.014 0.300 - - - 78.40 82.18% Satisfactory

WEE BUILDERS 16375 Construction of Local Road at Cawit-Baluno, Nangkal Road 10/21/2014 IX 3.744 53 C 0.389 0.135 0.300 - - - 82.40% 82.4%

Satisfactory

Wee Builders 16375 Concreting of Zamboanga City-Labuan-Limpapa Road (Bangayan Section) 05/25/09 IX 18.887 185 O 0.343 0.240 0.150 0.030 0.056 0.050 86.90 -

Wee Builders 16375 Conc. of Zamboanga City-Labuan-Limpapa Road (Bangayan Section) 09/01/09 IX 18.887 185 O 0.192 0.300 0.150 0.030 0.050 0.033 75.50 -

Wee Eng Construction Inc. 16380 Const. of SCDR Marihatag-Hinatuan-Bislig Road (Marihatag-San Agustin-Lianga Sect) 08/30/08 XIII 146.935 480 O 0.351 0.300 0.100 0.030 0.045 0.100 92.60 -

Wee Eng Construction Inc. 16380 Const. of SDCR (Lianga-Barobo Subsection) along Marihatag-Hinatuan-Bislig Sect 11/27/08 XIII 257.508 480 O 0.317 0.300 0.100 0.030 0.065 0.100 91.20 -

Wee Eng Construction Inc. 16380 Conc. of Surigao-Davao Coastal Rd.(Lianga-Borobo Subsection)along Marihatag-Hinatuan-Bislig Sect. 09/09/09 XIII 257.508 480 O 0.385 0.285 0.150 0.030 0.056 0.050 95.60 -

Wee Eng Construction Inc. 16380 Conc. of Surigao-Davao Coastal Rd.(Marihatag-San Agustin-Lianga, Salvacion-Lianga Sect) 09/09/09 XIII 373.799 405 O 0.392 0.300 0.124 0.030 0.065 0.033 94.40 -

Wee Eng Construction Inc. 16380 Concreting of SDCR (Marihatag-San Agustin-Lianga) Salvacion-Lianga Sect. 06/05/09 XIII 373.799 405 O 0.358 0.300 0.150 0.030 0.056 0.050 94.40 -

Wee Eng Construction Inc. 16380 Conc. of SDCR (Lianga-Barobo Subsection) along Marihatag-Hinatuan-Bislig Sect. 06/04/09 XIII 257.508 480 O 0.365 0.300 0.150 0.030 0.056 0.033 93.40 -

Wee Eng Construction Inc. 16380 Concreting of Surigao-Davao Coastal Road (Marihatag-San Agustin-Lianga), Salvacion-Lianga Section Section 03/13/09 XIII 373.799 405 O 0.330 0.300 0.150 0.030 0.047 0.050 90.70 -

WEE ENG CONSTRUCTION, INC. 16380 Construction of Saug Bridge and Approaches along Provincial Road 10/25/2014 XI 72.217 240 O 0.396 0.300 0.023 0.030 0.050 0.033 83.20% 83.2%

Satisfactory

WEE ENG CONSTRUCTION, INC. 16380Construction/ Maintenance of Flood Mitigation Structures

and Drainage System 1) Construction of Lasang River Flood Control

10/30/2014 XI 23.973 175 C 0.397 0.200 0.300 - - - 89.70% 89.7% Very Satisfactory

WEE ENG CONSTRUCTION, INC. 16380 Completion of On-going Bridges (Including Approaches) of Lipadas Bridge II along Davao - Cotabato Road 8/5/2014 XI 42.346 269 C 0.421 0.133 0.300 85.40 88.10%

Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page302

Page 303: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

WEE ENG CONSTRUCTION, INC. 16380 Road Upgrading (Gravel to Concrete) along Montevista-Compostela-Mati-Boundary Road (Intermittent Sections) 8/15/2014 XI 103.791 243 OG 0.366 0.225 0.150 0.030 0.037 0.050 85.80

Wee Eng Construction, Inc. 16380 Completion of on-going Bridges (inc. Approaches) of Lipadas Bridge II along Davao-Cotabato Rd. 08/07/13 XI 42.346 209 O 0.359 0.294 0.150 0.030 0.033 0.033 89.90

Wee Eng Construction, Inc. 16380 Widening of Davao-Bukidnon Rd. 08/19/13 XI 27.929 72 C 0.348 0.200 0.300 - - - 84.80 85.70% Satisfactory

Wee Eng Construction, Inc. 16380 Const. of Lasang River Flood Control 08/22/13 XI 65.421 302 C 0.400 0.133 0.300 - - - 83.30 83.84% Satisfactory

Wee Eng Construction, Inc. 16380 Widening of Davao-Bukidnon Rd. 03/22/13 XI 27.911 72 O 0.293 0.300 0.150 0.030 0.040 0.050 86.30 -

Wee Eng Construction, Inc. 16380 Conc. of Jct. Gamut-San Miguel-Bayugan Rd., Km.1315+913.714-Km.1320+200 (w/ exception) 03/20/13 XIII 67.735 435 C 0.330 0.200 0.300 - - - 83.00 84.56%

Satisfactory

Wee Eng Construction, Inc. 16380 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds. (IS) along Quezon Blvd., Km.1510+100-Km.1510+700 11/29/12 XI 36.780 297 C 0.449 0.133 0.300 - - - 88.20 87.69%

Satisfactory

Wee Eng Construction, Inc. 16380 Const. of Lasang River Flood Control 11/28/12 XI 65.422 260 O 0.327 0.240 0.150 0.030 0.045 0.050 84.20 -

Wee Eng Construction, Inc. 16380 Completion of Bunawan Bridge inc. Partial Const. of Approaches 08/20/12 XI 37.529 281 C 0.436 0.133 0.300 - - - 86.90 90.32%

V. Satisfactory

Wee Eng Construction, Inc. 16380 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. (IS) along Quezon Blvd., Km.1510+100-Km.1510+700 08/20/12 XI 36.780 240 O 0.369 0.240 0.150 0.030 0.060 0.033 88.20 -

Wee Eng Construction, Inc. 16380 Prev. Maint. Tagum-Panabo Circ. Rd., Km.1463+000-Km.1463+748 03/18/13 XI 14.652 80 C 0.421 0.133 0.300 - - - 85.40 *85.40%

Satisfactory

Wee Eng Construction, Inc. 16380 Repair/Rehab./Impv't. of Digos-Jct. Rd., K1565+(-732)-K1565+(-331) 03/16/13 XI 4.776 21 C 0.420 0.133 0.300 - - - 85.30 *85.30%

Satisfactory

Wee Eng Construction, Inc. 16380 Repair/Rehab./Impv't. of Davao-Bukidnon Rd., Km.1694+(-018)-Km.1695+006 (Int. Sect.) 03/12/13 XI 6.450 60 C 0.393 0.133 0.300 - - - 82.60 *82.60%

SatisfactoryWee Eng Construction, Inc./P.L

Sebastian Construction (JV) JV-06-056 CP-3, Const./Impv't. of Maguindanao-Sultan Kudarat-Bdry. Lebak-Kalamansig Road 03/11/09 XII 764.659 670 O 0.347 0.300 0.149 0.030 0.070 0.033 92.90 -

WELEX Construction 9323 Land Dev't & Housing Const. of San Lorenzo Res. Project 05/31/13 NHA 25.130 187 C 0.493 0.200 0.300 - - - 99.30 89.68% V. Satisfactory

WELEX Construction 9323 Land Dev't & Housing Const. of San Lorenzo Res. Project 06/27/12 NHA 24.925 120 O 0.359 0.300 0.066 0.033 0.045 0.033 83.60 -

Welex Construction 9323 Land Dev't. of Taysan Resettlement Project 9/16-18/08 SLBMO-Region V 49.802 244 O 0.382 0.288 0.000 0.030 0.070 0.067 83.70 -

WELEX CONSTRUCTION, INCORPORATED (Formerly: Welex

Construction)9323 Construction of Flood Control System, Pawa River, Bulan,

Sorsogon 11/6/2014 V 18.764 140 C 0.428 0.153 0.300 - - - 88.10% 88.1% Satisfactory

WERR CORP. (INTERNATIONAL) 14133Replacement of Chaya Bridge (Temporary to Permanent) along Banaue-Mayoyao-Alfonso Lista-Isabela Boundary

Road11/25/2014 CAR 13.085 249 C 0.448 0.133 0.300 - - - 88.10% 88.1%

Satisfactory

WERR CORP. (INTERNATIONAL) 14133 Construction of River Wall along Tullahan River, Phase X 11/22/2014 NCR 22.450 150 O 0.271 0.300 0.150 0.030 0.045 0.033 82.90% 82.9% Satisfactory

Werr Corp. (International) 14133 Construction/Improvement of Flood Control and Drainage Structures San Pedro Section Puerto Princesa South Road 8/8/2014 IV-B 13.985 270 C 0.434 0.133 0.300 86.70 85.20%

Satisfactory

Werr Corp. (International) 14133

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. (Int.Sect.) along Baguio-Bontoc Rd., K0269+000-K0275+000 (v.s.), K0286+000-K0289+000 (v.s.), K0299+000-K0300+900 (v.s.), K0305+000-K0308+500 (v.s.), K0309+000-K0311+000

(v.s.), K0323+000-K0328+000 (v.s.)

08/01/13 CAR 94.803 390 C 0.437 0.133 0.300 - - - 87.00 89.40% V. Satisfactory

Werr Corp. (International) 14133 Const. Impv't. of Flood Control & Drainage Structure 08/16/13 IVB 13.788 270 O 0.387 0.206 0.150 0.024 0.042 0.033 84.20

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page303

Page 304: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Werr Corp. (International) 14133

Rehab./Reconst./Upgrading of Damaged Paved Nat'l. Rd. (Int. Sect.) along Baguio-Bontoc Rd., K0269+000-

K0275+000 (V.S.), K0286+000-K0289+000 (V.S.), K0299+000-K0300+900 (V.S.), K0305+000-K0308+500 (V.S.), K0309+000-

K0311+000 (V.S.), K0323+000-K0328+000 (V.S.)

03/15/13 CAR 11.422 390 O 0.336 0.300 0.150 0.030 0.061 0.033 91.00 -

Werr Corp. (International) 14133 Replacement of Pangi Bridge 1 along Dinagat-Loreto Rd. 03/13/13 XIII 9.976 257 C 0.481 0.191 0.222 - - - 89.40 87.12% Satisfactory

Werr Corp. (International) 14133 Replacement of Bayantian Bridge along Jct. Magsaysay-Cagdianao Rd. 03/13/13 XIII 6.937 214 O 0.366 0.300 0.000 0.015 0.005 0.000 68.60 -

Werr Corp. (International) 14133 Rehab./Reconst./Upgrading (Conc.) of Puerto Princesa South Rd. (Km.2+760-Km.10+010 w/ exceptions) 11/19/12 IVB 103.153 330 C 0.393 0.187 0.300 - - - 88.00 86.38%

Satisfactory

Werr Corp. (International) 14133 Restoration of Roadslip along Dinagat-Loreto Road (Tag-abaca Sect.) 11/22/12 XIII 9.377 217 C 0.446 0.200 0.300 - - - 94.60 89.98%

V. Satisfactory

Werr Corp. (International) 14133 Conc. of Dinagat-Loreto Road (Doña Helene-Tag-abaca Sect.) 11/22/12 XIII 19.930 209 C 0.433 0.200 0.300 - - - 93.30 82.68%

Satisfactory

Werr Corp. (International) 14133 Rehab./Reconst./Upgrading (Concreting) of Puerto Princesa South Rd. Km.2+760-Km.10+010 w/ exceptions) 07/31/12 IVB 94.208 240 O 0.287 0.286 0.150 0.030 0.045 0.033 83.10 -

Werr Corp. (International) / Alfalfa Construction (JV) JV-12-375 Const. of Guihob Bridge & Approaches, Phase II,

K0345+169-K0345+240 08/04/13 CAR 16.343 165 C 0.470 0.133 0.300 - - - 90.30 86.82% Satisfactory

Werr Corp. (International) / Alfalfa Construction (JV) JV-12-375 Const. of Guihob Bridge & Approaches (Phase II),

Sta.345+169-Sta.345+240 03/18/13 CAR 16.344 135 O 0.332 0.240 0.150 0.023 0.050 0.050 84.50 -

Werr Corp. (International) / Avatar Construction Company (JV) JV-11-201 Conc. of Dinagat-Loreto Road (Dinagat-San Jose Sect.) 08/09/12 XIII 42.000 315 O 0.376 0.240 0.150 0.030 0.055 0.033 88.40 -

WERR CORP. (INTERNATIONAL) / BUGANI CONSTRUCTION AND

ENTERPRISES, INC. / JOVIC CONSTRUCTION AND SUPPLY (JV)

JV-13-553 Road Upgrading (Gravel to Paved) along Banaue-Hungduan-Benguet Bdry Road KO370+123 - KO374+000 11/24/2014 CAR 111.422 315 O 0.355 0.254 0.150 0.030 0.055 0.050 89.40% 89.4%

Very Satisfactory

Werr Corp. (International) / Gemma Construction Supply Inc. Joint

VentureJV-11-198 Prev. Maint. of Kidapawan-Ala Jct. Km. 1647+981-Km.

1660+777 (w/ exception) 11/23/12 XII 111.511 230 C 0.435 0.200 0.300 - - - 93.50 93.56% V. Satisfactory

Werr Corp. (International) / Gemma Construction Supply, Inc. (JV) JV-11-198 Prev. Maint. of Kidapawan-Ala Jct., Km.1647+981-

Km.1660+777 (w/ exception) Datu Paglas 08/10/12 XII 111.511 230 O 0.355 0.300 0.150 0.030 0.051 0.050 93.60 -

Werr Corp. (International) / K.D.C.M. Construction (JV) JV-08-141

Conc. of Bontoc-Tabuk-Tuguegarao Road (Package BLT-16), Tinglayan Boundary-Lubuagan-Tabuk Section II, Km.

483+500- Km 499+310 Balani-Tulyao Section09/04/09 CAR 93.305 310 O 0.347 0.240 0.150 0.030 0.060 0.033 86.00 -

Werr Corp. (International)/Avatar Construction Company Joint

VentureJV-11-201 Conc. of Dinagat-Loreto Road (Dinagat-San Jose Sect.),

San Jose 03/21/12 XIII 42.001 315 O 0.400 0.300 0.150 0.022 0.033 0.033 93.80 -

WERR CORP. (INTERNATIONAL)/GALENO CONSTRUCTION, INC. JOINT

VENTURE

JV-12-499 Reconst./Replacement of Sum-ag Bridge 1 along Bacolod South Road, Brgy. Sum-ag Bacolod City 8/11/2014 VI 36.693 252 C 0.299 0.200 0.300 79.90 83.92%

Satisfactory

Werr Corp. International / Alfalfa Construction (JV) JV-12-314 Rd. Upgrading (Gravel to Conc.) of Banaue-Hungduan-

Benguet Bdry. Rd. K0374+000-K0376+300 08/04/13 CAR 43.787 296 O 0.328 0.240 0.150 0.023 0.055 0.050 84.60

Werr Corp.. (International) / Galeno Construction, Inc. (JV) JV-12-499 Reconst./Replacement of Sum-ag Bridge 1 along Bacolod

South Rd., Brgy. Sum-ag 08/07/13 VI 34.401 252 O 0.376 0.240 0.150 0.030 0.037 0.033 86.60

WERR CORPORATION INTERNATIONAL 14133 Polambato Port Development Project 09/23/15 DOTC 27.875 180 C 0.482 0.200 0.000 - - - 68.15 *68.15% POOR

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page304

Page 305: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

WERR CORPORATION INTERNATIONAL 14133 Dumangas Port Development Project 01/28/15 DOTC 39.962 270 C 0.355 0.200 0.300 - - - - 88.70%

Satisfactory

WERR Corporation International 14133 Dumangas Port Development Project 06/05/14 DOTC 39.962 270 O 0.328 0.300 0.150 0.030 0.050 0.050 90.80 -

Westmin Enterprises & Construction Services 20989 Completion of Multi-Purpose Building 03/09/10 IX 3.795 150 O 0.327 0.300 0.150 0.030 0.041 0.050 89.80 -

Westmin Enterprises & Construction Services 20989 Construction of Drainage Canal at Brgy. Dawo 06/09/09 IX 4.770 180 O 0.347 0.240 0.150 0.030 0.037 0.050 85.40 -

Westmin Enterprises and Construction Services 20989

Road Upgrading (Gravel to Concrete) Based on Gravel Road Strategies (HDM-4) Project Analysis Intermittent Sections, Dipolog-Punta-Dansullan-Sergio Osmeña,

Zamboanga del Norte/Sur Boundary K1889+246 - K1889+588

8/14/2014 IX 9.430 89 C 0.392 0.200 0.300 89.20 89.20% Very Satisfactory

Westmin Enterprises and Construction Services 20989 Repair/Maint. of Polanco River Control 08/23/12 IX 2.700 140 C 0.394 0.133 0.300 - - - 82.70 85.10%

SatisfactoryWestmin Enterprises and

Construction Services 20989 Const. of Three (3) Classroom School Bldg. at Piñan Nat'l. High Sch. 03/22/13 IX 1.261 69 C 0.472 0.133 0.300 - - - 90.50 *90.50%

V. Satisfactory

WILKINSON CONSTRUCTION 21422 Construction/Rehabilitation of Drainage/Slope Protection along Bacolod San Carlos Road (Pagla-Um Village) 10/27/2014 VI 17.513 240 C 0.417 0.133 0.300 - - - 85.00% 85%

Satisfactory

WILKINSON CONSTRUCTION 21422Rehab./Reconst./Upgrading of Damaged Paved National Secondary Road along Bacolod Circumferencial Roads

K003+700 - K004+8518/11/2014 VI 27.772 255 C 0.387 0.200 0.300 88.70 86.60%

Satisfactory

Wilkinson Construction 21422 Rehab. of Magbaboy Bridge along Bacolod North Rd. 08/12/13 VI 14.033 330 C 0.482 0.200 0.300 - - - 98.20 88.69% Satisfactory

Wilkinson Construction 21422 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Sec. Rd. along Bacolod Circ. Rd. (S), K003+700-K004+851 08/06/13 VI 26.955 204 O 0.377 0.300 0.050 0.030 0.045 0.050 85.20

Wilkinson Construction 21422Rehab.n/Strengthening (Reconst.) of Bridges at Poncian Bridge along Bacolod-Murcia-DS Benedicto-San Carlos

City Rd.08/12/13 VI 25.631 343 O 0.376 0.300 0.000 0.030 0.040 0.033 77.90

Wilkinson Construction 21422 Rehab. of Magbaboy Bridge along Bacolod North Rd. 03/15/13 VI 14.033 255 O 0.321 0.300 0.000 0.023 0.040 0.033 71.70 -

Wilkinson Construction 21422Rehab./Strengthening (Reconst.) of Bridges at Poncian

Bridge along Bacolod-Murcia-D.S. Benedicto-San Carlos City Rd.

03/15/13 VI 26.631 340 O 0.270 0.300 0.000 0.022 0.035 0.033 66.00 -

Wilkinson Construction 21422 Rehab. of Magbaboy Bridge along Bacolod North Rd. 11/27/12 VI 14.033 225 O 0.400 0.240 0.150 0.030 0.060 0.050 93.00 -

Wilkinson Construction 21422Rehab./Strengthening (Reconst.) of Bridges at Poncian

Bridge along Bacolod-Murcia-D.S. Benedicto-San Carlos City Rd.

11/27/12 VI 25.631 280 O 0.321 0.258 0.150 0.030 0.055 0.033 84.70 -

William Integrated Contractor 7669 Proposed Rehab./Impv't. of Baliwasan Seaside (Intermittent Sect.) 09/08/10 IX 9.104 162 O 0.335 0.228 0.150 0.023 0.035 0.050 82.10 -

Wilper Construction / Paula Mae Buhong Construction (JV) JV-08-196 Widening / Conc. of Bontoc-Banaue Road View Point to

Awan-Igid Section, Km. 345+828 - Km. 354+550 08/30/09 CAR 106.072 405 O 0.366 0.240 0.150 0.030 0.056 0.033 87.50 -

Wilper Construction / Paula Mae Buhong Construction (JV) JV-08-179

Conc. of Bontoc-Tuguegarao Road, Bontoc-Tinglayan Bdry. Section I Betwangan to Ampawile Sect. Km. 406+220-

Km. 411+140 (with exception)08/30/09 CAR 130.727 420 O 0.384 0.240 0.000 0.030 0.056 0.017 72.70 -

Wilper Construction Inc. 1632 Const. of San Vicente-Gutan-Lubak-Anguib Road 02/19/10 II 96.100 360 O 0.336 0.240 0.150 0.030 0.053 0.033 84.20 -

Wilper Construction Inc. 1632 Conc. of San Carlos-Dumaguete Rd., Dumaguete City and Bais City 09/12/09 VII 47.369 373 O 0.366 0.240 0.150 0.030 0.037 0.050 87.30 -

Wilper Construction Inc. 1632 Conc. of San Carlos-Dumaguete Road Dumaguete City and Bais City 03/02/10 VII 47.369 370 O 0.204 0.292 0.000 0.030 0.045 0.050 62.10 -

Wilper Construction Inc. 1632 Concreting of Guiuan Airport (Access Road) 06/07/09 VIII 12.865 120 O 0.296 0.300 0.150 0.030 0.045 0.033 85.40 -

Wilper Construction Inc. 1632 Concreting of San Carlos-Dumaguete Road, Dumaguete City & Bais City 03/12/09 VII 44.001 310 O 0.391 0.221 0.150 0.030 0.051 0.033 87.60 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page305

Page 306: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Wilper Construction Inc. 1632 Concreting of San Carlos-Dumaguete Road, Dumaguete City and Bais City 05/26/09 VII 44.001 310 O 0.380 0.243 0.148 0.030 0.056 0.033 89.00 -

Wilper Construction Inc. 1632 Const. of TESDA Training Center Bldg. (Phase I) 05/29/09 X 4.741 120 O 0.326 0.265 0.150 0.030 0.027 0.033 83.10 -

Wilper Construction Inc. 1632 Impvt. (Concreting) of Access Road leading Dawis Port 05/29/09 XI 43.322 220 O 0.368 0.300 0.150 0.030 0.037 0.033 91.80 -

Wilper Construction Inc. 1632 Improvement (Concreting) of Access Road Leading to Dawis Port 09/05/09 XI 43.322 220 O 0.384 0.240 0.107 0.030 0.059 0.033 85.30 -

Wilper Construction Inc. / MG Samidan Construction (J.V.) JV-10-146

Road Upgrading (Gravel to Concrete) of Nat'l Roads along Gurel-Bokod-Kabayan-Buguias-Abatan Rd. K0357+000-

K0358+187 (I.S.)03/14/12 CAR 19.233 139 C 0.439 0.133 0.300 - - - 87.20 87.26%

Satisfactory

Wilper Construction Inc. / Wangjo Construction (JV) JV-08-195 Widening / Conc. of Bontoc-Banaue Road Awan-Igid to

Mt.polis Section, Km.354+550 - Km.362+200 (IS) 08/30/09 CAR 106.560 405 O 0.367 0.240 0.139 0.030 0.056 0.033 86.50 -

Wilper Construction Incorporated 1632 Talakag Irrigation Project 09/26-10/01/11 NIA 14.432 451 O 0.327 0.300 0.000 0.030 0.051 0.050 75.82 -

Wilper Construction Incorporated 33066 Bukidnon Irrigation Management Office / Region 10 03/31/12 NIA 14.166 451 O 0.366 0.272 0.119 0.030 0.045 0.050 88.09 -

Wilper Construction, Inc. / MG Samidan Construction (JV) JV-10-129 Upgrading of Mt. Province-Ilocos Sur Rd. via Kayan Rd.,

Km.391+000-Km.392+452 08/03/12 CAR 21.533 330 C 0.395 0.200 0.300 - - - 89.50 89.08% V. Satisfactory

WILPRES ENTERPRISES 19698Rehabilitation of Lateral Drainage along Lingayen-Capitol Loop to Lingayen Cadre Road (Phase I) K0364+(-)278 to

K0364+242 & Sta. 0+000 to Sta. 0+48010/28/2014 I 7.385 130 C 0.453 0.133 0.300 - - - 88.60% 88.6%

Satisfactory

Winces Construction & Supply 32341 Rehabilitation of Barotac Viejo RIS Bench Flume 08/31/13 NIA 12.074 150 O 0.347 0.200 0.300 - - - 84.72 *84.72% Satisfactory

Wind River Court Construction and Development 36144 Rehab./Reconst./Strengthening of Tobgon Bridge along

Ligao-Tabaco Rd., Brgy. Batang 08/09/13 V 5.695 120 C 0.375 0.200 0.300 - - - 87.50 *87.50% Satisfactory

Wiro Construction 22236 Improvement of Lateral F, SDA 08/03/12 NIA 1.382 60 C 0.480 0.122 0.300 - - - 90.14 90.14% V. Satisfactory

WIRO Construction 22236 Concrete Pavement 07/27/13 NIA 7.588 75 C 0.418 0.200 0.300 - - - 91.84 *91.84% V. Satisfactory

Wismon Construction 33687Rehab./Reconst./Upgrading of Damaged Paved National

Rd. along Daang Maharlika San Luis-Isabela Bdry. Sect. w/ exception

06/10/10 II 19.285 90 O 0.369 0.244 0.150 0.030 0.047 0.033 87.30 -

Wismon Construction & Development Corp. (Formerly:

Wismon Construction)33087 Const. of Brgy. Road, Pob. South 08/12/13 III 2.850 60 C 0.427 0.133 0.300 - - - 86.00 *86.00%

Satisfactory

Wizard Trading & Construction 21921 Upgrading of Muñoz-Lupao Road 06/07/10 III 4.899 30 O 0.338 0.240 0.150 0.030 0.054 0.050 86.20 -WIZARD TRADING AND

CONSTRUCTION 21921 Construction of School Building, Malasin E/S 11/21/2014 III 4.262 188 C 0.492 0.133 0.300 - - - 92.50% 92.5% Very Satisfactory

WIZARD TRADING AND CONSTRUCTION 21921 Preventive Maintenance of San Jose City-Rizal Road via

Pinili Porais Villa Joson, KO175+870 to KO176+300 11/21/2014 III 5.821 74 C 0.458 0.133 0.300 - - - 89.10% 89.1% Very Satisfactory

Wizard Trading and Construction 21921 Preventive Maintenance of San Jose City-Rizal Road via Pinili-Porais-Villa Joson, KO 175+870 to KO 176+300 9/25/2014 Special 3 5.826 75 C 0.468 0.133 0.300 90.10 90.10%

Very Satisfactory

Wizard Trading and Construction 21921 Rehab./Reconst./Upgrading of San Jose City-Rizal Rd., via Pinili-Porais-Villa Joson Rd., K0164+000-K0165+109 08/13/13 III 17.867 90 C 0.444 0.133 0.300 - - - 87.70 *87.70%

Satisfactory

Wizard Trading and Construction 21921 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rds, Daang Maharlika Rd. 08/09/13 III 77.161 315 C 0.461 0.133 0.300 - - - 89.40 88.86%

SatisfactoryWMLC Trading & Construction

Supply 24535 Rehab./Reconst./Upgrading of Damaged Roads along Rosario-San Juan Rd. 06/07/10 IVA 4.820 90 O 0.400 0.225 0.150 0.023 0.040 0.050 88.80 -

Wood Rabbit Construction 33722 Colocol Integrated CIS Rehabilitation & Extension Project 05/12/12 NIA 7.545 256 C 0.410 0.195 0.300 - - - 90.47 90.49% V. Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page306

Page 307: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

WORLDWIDE BUILDERS 31408

Preventive Maintenance Based on Pavement Management System/Highway Development and Management-4 (HDM-

4), Secondary Road, General Maxilom Ext., Chainage 0000 -Chainage 0340

10/20/2014 VII 12.074 60 C 0.458 0.137 0.300 - - - 89.50% 89.5% Very Satisfactory

Worldwide Builders 31408 Improvement of Multi-Purpose Building 03/03/09 VII 0.948 50 O 0.342 0.277 0.150 0.030 0.019 0.050 86.80 -

Worldwide Builders 31408 Const. of MPB, Doldol 03/18/13 VII 1.958 60 C 0.331 0.154 0.300 - - - 78.50 *78.50% Unsatisfactory

WT Construction Inc., "JV" A.M. Oreta and Company, Inc. JV-12-229 Improvement of Natalio Bacalso Avenue Km. 47+000 to

Km. 48+297, Carcar-Sibonga, Cebu Province 8/4/2014 VII 17.870 360 C 0.338 0.200 0.300 83.80 84.70% Satisfactory

WT CONSTRUCTION, INC. 5490

Preventive Maintenance Based on Pavement Management System/Highway Development and Management-4 (HDM-4)

Secondary Road, Osmeña Boulevard, Chainage 0225 - Chainage 1313

10/20/2014 VII 27.989 150 C 0.433 0.149 0.300 - - - 88.20% 88.2% Satisfactory

WT Construction, Inc. 5490Prev. Maint. (Int. Sect.), Secondary Rd., Imus Rd;

a)Chainage 0000-Chainage 0825 & b)Chainage 0865-Chainage 1070

08/24/13 VII 22.897 100 C 0.411 0.136 0.300 - - - 84.70 *84.70% Satisfactory

WT Construction, Inc. 5490 Repair/Rehab. of Cebu North Hagnaya Wharf Rd., Mandaue Sect., K0009+474-K0010+409 03/20/13 VII 13.255 42 C 0.442 0.124 0.300 - - - 86.60 *86.60%

Satisfactory

WT Construction, Inc. / A.M. Oreta & Company, Inc. (JV) JV-12-230

Widening of San Isidro Bridge & Approaches, Sta.27+100 inc. the Impv't. of Cross-Drainage from Sta.27+083-

Sta.28+470 along Natalio Bacalso Ave.08/05/13 VII 25.878 378 O 0.339 0.281 0.150 0.030 0.045 0.033 87.80

WT Construction, Inc. / A.M. Oreta & Company, Inc. (JV) JV-12-229 Impv't. of Natalio Bacalso Ave., Carcar-Sibonga Sect.,

Cebu Province, Km.47+000-K0048+297 08/05/13 VII 16.248 360 O 0.274 0.300 0.150 0.030 0.049 0.050 85.30

WTG CONSTRUCTION & DEVELOPMENT CORP 7494 Expansion of Back-Up Area and Construction of PTB 04/10/15 PPA 59.890 369 O 0.358 0.300 0.112 0.030 0.070 0.030 90.00 -

WTG Construction & Development Corp 7494 Rehabilitation of R.C. Pier 1 04/03/14 PPA 74.084 456 C 0.451 0.200 0.300 - - - 95.10 96.35%

OutstandingWTG CONSTRUCTION & DEVELOPMENT CORP. 7494 Expansion of Back-Up Area and Construction of PTB 08/05/15 PPA 59.890 429 O 0.399 0.300 0.090 0.030 0.070 0.050 93.95 -

WTG Construction & Development Corporation 7494 Rehabilitation of R.C. Pier 1 03/21/13 PPA 74.160 420 O 0.399 0.300 0.150 0.030 0.054 0.033 96.60 -

WTG Construction and Development Corp. (Formerly:

W.T.G. Construction)7494 Retrofitting of Ilog Bridge 03/29/12 VI 56.181 300 O 0.320 0.240 0.150 0.030 0.060 0.050 85.00 -

WTG Construction and Development Corporation 7494 Rehabilitation of R.C. Pier 1 08/16/13 PPA 74.084 420 O 0.397 0.300 0.150 0.030 0.050 0.050 97.70 -

WTG Construction and Development Corporation

(Formerly: W.T.G Construction)7494 Reconst. of Third Concrete Bridge along Marikina-Infanta

Rd. (Marcos Highway) Km.35+861 Brgy. San Jose 06/08/10 IVA 56.621 180 O 0.362 0.300 0.150 0.030 0.047 0.050 93.90 -

WTG Construction and Development Corporation

(Formerly: W.T.G Construction)7494

Rehab./Recons./Upgrading of Dumaguete North Rd. (Jct. Kabankalan, Negros Occ. Boundary) Sta.39+000-

Sta.42+000;Sta.47+180-Sta47+280;Canlargo-Talongon-Bais City Rd. Sec.)

09/16/09 VII 48.070 270 O 0.347 0.240 0.150 0.030 0.037 0.033 83.70 -

WTG Construction and Development Corporation

(Formerly: W.T.G Construction)7494 Rehab./Reconst. of Toledo-Tabuelan-San Remegio Road,

Tuburan Section 05/29/09 VII 23.119 120 O 0.268 0.240 0.150 0.030 0.050 0.033 77.10 -

WTG Construction and Development Corporation

(Formerly: W.T.G Construction)7494 Impvt./Rehab./Reconst. of Toledo-Tabuelan-San Remegio

Road, Km. 48+806-Km. 55+361, Brgy. Dumhog-Sto. Niño 05/26/09 VII 8.428 90 O 0.217 0.225 0.150 0.022 0.050 0.050 71.40 -

WTG Construction and Development Corporation

(Formerly: W.T.G Construction)7494 Rehab./Reconst. of Toledo-Tabuelan-San Remegio Road,

Km. 47+000-Km. 103+667 05/27/09 VII 76.969 365 O 0.173 0.222 0.150 0.030 0.045 0.033 65.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page307

Page 308: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

WTG Construction and Development Corporation

(Formerly: W.T.G Construction)7494

Conc. of Jct.TER, Jagna-Sierra Bullones Rd. Km.62.5220-Km.63.365;Km.72.812-Km.75.031;Km.75.250-Km.76.526,

Canijulao-Boctol-Mayana-Jagna09/04/09 VII 87.044 270 O 0.368 0.240 0.150 0.030 0.037 0.033 85.80 -

WTG Construction and Development Corporation

(Formerly: W.T.G Construction)7494

Conc. of Jct. TER, Jagna-Sierra Bullones Road Km. 62.522-Km. 63.365; Km.72+812-Km. 75.031 & Km. 72.25-Km.

76.526, Canjulao-Boctol-Mayana Section02/23/10 VII 87.044 270 O 0.333 0.238 0.150 0.030 0.045 0.033 82.90 -

WTG Construction and Development Corporation

(Formerly: W.T.G Construction)7494 Rehab./Reconst./Upgrading (Conc.) of Toledo-Tabuelan-

San Remegio Rd., Km.68+720 - Km.96+340 w/ exception 06/12/10 VII 40.903 210 O 0.289 0.240 0.150 0.030 0.050 0.050 80.90 -

WTG Construction and Development Corporation

(Formerly: W.T.G Construction)7494

Rehab./Reconst. of Damaged Paved National Rd. at LIPATA Surigao Del Norte Davao City Highway through

Daang Maharlika Rd. (Agusan to Davao Rd.) Panacan Sect.06/16/10 XI 19.289 115 O 0.393 0.240 0.150 0.030 0.042 0.050 90.50 -

WTG Construction and Development Corporation

(Formerly: W.T.G Construction)7494 Const. of Gov. Cuenco Flyover, Gov. Cuenco Ave. , Jct.

A.S. Fortuna St. 03/02/09 VII 95.036 559 O 0.301 0.300 0.150 0.030 0.054 0.050 88.50 -

WTG Construction and Development Corporation

(Formerly: W.T.G Construction)7494

Rehab./Reconst. of Damaged Paved National Roads Tagbilaran East Road (TER) (Loay-Guildulman) Intermittent

Secton06/05/09 VII 9.363 200 O 0.299 0.300 0.150 0.030 0.051 0.033 86.30 -

WTG Construction and Development Corporation

(Formerly: W.T.G Construction)7494

Rehab./Reconst./Upgrading (Concreting) of Toledo-Tabuelan-San Remegio Road, Km. 68+720-Km. 96+340 w/

exceptions08/26/10 VII 40.903 210 O 0.311 0.287 0.150 0.030 0.040 0.050 86.80 -

WTG Construction and Development Corporation

(Formerly: W.T.G Construction)7494 Const. of Pedestrian Overpass along Davao Diversion

Road (Laverna Hills Section) 06/11/09 XI 4.710 120 O 0.350 0.300 0.150 0.030 0.056 0.050 93.60 -

WTG Construction and Development Corporation

(Formerly: W.T.G Construction)7494 Const. of Gov. Cuenco Flyover, Gov. Cuenco Ave. , Jct.

A.S. Fortuna St. 09/03/08 VII 86.914 300 O 0.281 0.220 0.100 0.030 0.047 0.100 77.80 -

WTG Construction and Development Corporation

(Formerly: W.T.G Construction)7494 Dapa-Cancohoy Rd., Cancohoy-Del Carmen 09/03/09 XIII 19.249 240 O 0.349 0.289 0.150 0.030 0.065 0.050 93.30 -

WTG Construction and Development Corporation

(Formerly: W.T.G Construction)7494 Jct. Canchohoy-Pilar Rd., San Isidro Rd. Sect. 09/03/09 XIII 19.269 240 O 0.358 0.291 0.095 0.030 0.065 0.033 87.20 -

WTG CONSTRUCTION AND DEVELOPMENT CORPORATION (Formerly: W.T.G. Construction)

7494Rehabilitation/Improvement of M.L. Quezon Street,

Mandaue City, K0008+(-865) to K0008+535, Mandaue City, Cebu

10/21/2014 VII 43.709 360 O 0.375 0.240 0.150 0.024 0.047 0.033 86.90% 86.9% Satisfactory

WTG CONSTRUCTION AND DEVELOPMENT CORPORATION (Formerly: W.T.G. Construction)

7494 Construction/Concreting of Brgy. Road Leading to Malabago - Kalangkang - Sulsogon Kawasan Falls 10/24/2014 VII 45.678 196 O 0.309 0.300 0.150 0.022 0.065 0.050 89.60% 89.6%

Very Satisfactory

WTG CONSTRUCTION AND DEVELOPMENT CORPORATION (Formerly: W.T.G. Construction)

7494 Construction of Flood Control at Sapang Daku River 8/6/2014 VII 28.485 165 C 0.386 0.200 0.300 88.60 89.74% Very Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page308

Page 309: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

WTG CONSTRUCTION AND DEVELOPMENT CORPORATION (Formerly: W.T.G. Construction)

7494 Construction of Drainage System along Cebu North Hagnay Wharf RoadBorbon Section 8/8/2014 VII 17.567 210 OG 0.351 0.272 0.150 0.022 0.051 0.050 89.60

WTG CONSTRUCTION AND DEVELOPMENT CORPORATION (Formerly: W.T.G. Construction)

7494 Rehab./Imprv't. of M.L.Quezon St., Mandaue City K0008+(-865) to K0008+535, Mandaue City 8/8/2014 VII 43.709 360 OG 0.357 0.243 0.150 0.024 0.061 0.033 86.80

WTG Construction and Development Corporation

(Formerly: W.T.G. Construction)7494 Const. of Flood Control at Sapangdaku River 08/06/13 VII 28.485 210 O 0.320 0.300 0.150 0.030 0.055 0.050 90.50

WTG Construction and Development Corporation

(Formerly: W.T.G. Construction)7494 Const. of Flood Control at Sapangdaku River 03/17/13 VII 28.485 180 O 0.251 0.300 0.150 0.030 0.047 0.050 82.80 -

WTG Construction and Development Corporation

(Formerly: W.T.G. Construction)7494

Prev. Maint. along Santander-Barili-Toledo Road, K0218+450-K0219+617, K0220+182-K0220+518 &

K0221+062-K0221+54703/18/13 VII 29.017 107 C 0.461 0.196 0.300 - - - 95.70 *95.70%

V. Satisfactory

WTG Construction and Development Corporation

(Formerly: W.T.G. Construction)7494 Prev. Maint. along Cebu North Haganaya Wharf Road

(Intermittent Sect.) K00021+000-K0021+860 03/19/13 VII 17.794 28 C 0.385 0.192 0.300 - - - 87.70 *87.70% Satisfactory

WTG Construction and Development Corporation

(Formerly: W.T.G. Construction)7494 Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd.,

Corrales Ext. St. Port Rd., Km.1438+000-Km.1439+557 11/24/12 X 23.507 267 C 0.458 0.200 0.300 - - - 95.80 83.56% Satisfactory

WTG Construction and Development Corporation

(Formerly: W.T.G. Construction)7494 Rehab./Reconst./Upgrading of Toledo-Tabuelan-San

Remegio Rd., K0070+540-K0071+626, Looc Norte 08/20/12 VII 15.308 122 C 0.401 0.133 0.300 - - - 83.40 85.02% Satisfactory

WTG Construction and Development Corporation

(Formerly: W.T.G. Construction)7494 Rehab./Reconst./Upgrading of Corrales Extension St. Port

Rd., Km.1438+000-Km.1439+557 08/06/12 X 26.118 210 O 0.289 0.300 0.000 0.030 0.035 0.033 68.70 -

Wynn Construction 19358 Siquijor Airport Development Project 09/09/15 DOTC 10.522 90 C 0.447 0.200 0.300 - - - 94.71 *94.71% V.Satisfactory

WYNN CONSTRUCTION 19358 Road Upgrading (Gravel to Paved), Balilihan - Hanopol - Butuan Road, K0037+498 to K0037+893 10/26/2014 VII 13.581 195 C 0.359 0.162 0.285 - - - 80.60% 80.6%

Unsatisfactory

WYNN Construction Emergency Repair and Rehabilitation of Alegria-Bang-Hagbuaya-Hanopol Norte Provincial Road 01/20/15 Bohol 13.897 184 O 0.384 0.286 0.147 0.030 0.060 0.050 95.70 -

Wynn Construction 19358 Dimiao Port Development Project 09/11/14 DOTC 4.933 105 C 0.411 0.200 0.300 - - - 91.11 *91.11% V. Satisfactory

Wynn Construction 19358 Bien Unido Port Development Project 01/22/14 DOTC 4.975 75 C 0.446 0.200 0.300 - - - 94.64 *94.64% Very Satisfactory

Wynn Construction 19358 Cayacay Small River Impounding Project 07/13/13 NIA 4.916 120 O 0.400 0.300 0.000 0.020 0.070 0.030 82.00 -

Wynn Construction 19358 Repair of RoRo Ramp 1 & 2, Pavement And Scoured Bulkhead 05/23-27/11 PPA 7.883 221 O 0.400 0.225 0.144 0.030 0.065 0.050 91.33 -

Wynn Construction 19358 Bohol Ports Cluster Project 08/27/13 DOTC 5.614 90 C 0.451 0.200 0.000 - - - 65.10 65.10% Poor

Y S Construction 11928 Conc./Impvt. of Sagbayan-Danao Rd. 03/13/13 VII 46.485 315 C 0.459 0.163 0.300 - - - 92.20 88.42% Satisfactory

Y S Construction 11928 Const. of MPB (Senior Citizen Hall Bldg.), Poblacion II 08/18/11 VII 2.700 120 O 0.376 0.300 0.150 0.030 0.032 0.033 92.10 -

Y S Construction 11928 Conc./Widening of Dauis-Panglao Center Road 08/24/11 VII 42.300 280 O 0.350 0.300 0.150 0.030 0.040 0.033 90.30 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page309

Page 310: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Y S Construction 11928 Conc./Widening of Dauis-Panglao Center Rd. 08/08/12 VII 42.300 280 C 0.473 0.133 0.300 - - - 90.60 90.42% V. Satisfactory

Y S Construction 11928 Sagbayan Flood Control/Drainage along Nat'l Rds. 08/10/12 VII 13.976 144 C 0.426 0.166 0.300 - - - 89.20 89.86% V. Satisfactory

YAKAL CONSTRUCTION 9685Rehabilitation/Reconstruction of Critical Sections along

National Roads, Road Slip along Bato-Bontoc Road, K1113+500 - K1114+500

10/28/2014 VIII 8.648 130 C 0.471 0.133 0.300 - - - 90.40% 90.4% Very Satisfactory

YAKAL CONSTRUCTION 9685 Construction of River Control Structure, Pob. Cuardero, Capiz 8/15/2014 VI 29.000 312 C 0.405 0.200 0.300 90.50 85.64%

Satisfactory

YAKAL CONSTRUCTION 9685 Completion for Repair/Rehab. Of Layog Bridge along Taft - Borongan - San Julian, Eastern Samar 8/14/2014 VIII 15.316 714 C 0.454 0.133 0.300 88.70 89.42%

Very Satisfactory

Yakal Construction 28289 Const. of River Control 08/19/13 VI 27.593 312 O 0.392 0.231 0.101 0.030 0.037 0.033 82.40

Yakal Construction 9685 Restoration & Const. of Flood Control Structure, Sitio Purisima, Brgy. Guindapunan 08/20/13 VIII 45.859 395 C 0.451 0.133 0.300 - - - 88.40 85.28%

Satisfactory

Yakal Construction 9685 Completion for Repair/rehab. Of Layog Bridge along Taft-Borongan 08/19/13 VIII 15.316 714 O 0.390 0.240 0.150 0.030 0.055 0.033 89.80

Yakal Construction 9685 Rehab. of Wright-Taft-Borongan Road, including Layug Bridge, Km. 860+570-Km. 938+500 06/07/09 VIII 161.048 403 O 0.324 0.240 0.150 0.030 0.050 0.050 84.40 -

Yakal Construction 9685 Upgrading/Concreting of Taft-Borongan Road with exceptions 06/07/09 VIII 166.287 365 O 0.247 0.300 0.150 0.030 0.050 0.050 82.70 -

Yakal Construction 9685 Upgrading/Concreting of Borongan-MacArthur Road with exceptions 06/07/09 VIII 161.533 355 O 0.321 0.240 0.150 0.030 0.050 0.033 82.40 -

Yakal Construction 9685 Rehabilitation of Tagbilaran North Road, Clarin-Talibon Section, Km. 58.000-112.500 (w/ exception) 03/05/09 VII 14.077 240 O 0.360 0.229 0.150 0.030 0.033 0.050 85.20 -

Yakal Construction 9685 Upgrading/Conc. of Taft-Borongan Road with exception 09/17/09 VIII 166.281 365 O 0.371 0.240 0.150 0.030 0.055 0.050 89.60 -

Yakal Construction 9685 Road Upgrading of Bagahupi-Babatngon-Sta. Cruz-Barugo-Carigara Road, Km. 923+038-Km.927+610 w/ exceptions 03/30/12 VIII 37.792 325 O 0.313 0.245 0.150 0.030 0.035 0.050 82.30 -

Yakal Construction 9685 Restoration & Const. of Flood Control Structure, Sitio Purisima, Brgy. Guindapunan 08/23/12 VIII 44.721 365 O 0.322 0.240 0.150 0.030 0.040 0.050 83.20 -

YAP MABUHAY ENTERPRISES, INC. 15540 Construction of Multi-Purpose Building-Maasim West

Central Elementary School, Brgy. Poblacion 10/28/2014 XII 2.991 60 C 0.492 0.133 0.300 - - - 92.50% 92.5% Very Satisfactory

YAP MABUHAY ENTERPRISES, INC. 15540 Construction of Multi-Purpose Building Poblacion

Tantangan 10/21/2014 XII 4.408 150 O 0.398 0.224 0.150 0.020 0.043 0.033 86.80% 86.8% Satisfactory

Yap Mabuhay Enterprises, Incorporated 15540 Const. of Multi-Purpose Building @ Poblacion 09/12/09 XII 0.950 84 O 0.363 0.300 0.150 0.030 0.023 0.033 89.90 -

Yap Mabuhay Enterprises, Incorporated 15540 Construction of Multi-Purpose Building @ Poblacion 09/12/09 XII 0.952 126 O 0.364 0.262 0.150 0.030 0.035 0.033 87.40 -

Yap Mabuhay Enterprises, Incorporated 15540 Construction of 2-CL School Building @ San Vicente NHS 09/11/09 XII 1.297 105 O 0.329 0.280 0.150 0.030 0.041 0.033 86.30 -

YL Trading General Merchandising 22543 Conc. of San Remegio-Bugo Road 06/10/10 VI 9.479 100 O 0.339 0.300 0.150 0.015 0.033 0.033 87.00 -

YL Trading General Merchandising 22543 Concreting of Road, Funda Dalipe-San Pedro (San Jose) 06/04/09 VI 9.502 180 O 0.371 0.240 0.150 0.030 0.040 0.033 86.40 -

YL Trading General Merchandising 22543 Conc. of Hamtic-Bia-an-Egana-Sibalom Road, Catungan Section 03/13/09 VI 19.259 300 O 0.280 0.294 0.150 0.024 0.050 0.033 83.10 -

Young Builders Corporation 15807 Rehab. of Bulwang Curve Section-Lumbangan Section, Bais Mabinay Road 09/01/10 VII 57.809 240 O 0.360 0.300 0.150 0.030 0.047 0.033 92.00 -

Yoyen Enterprises 15541 Road Upgrading of Libungao-Matag-ob-Palompon Rd. 06/04/10 VIII 18.227 225 O 0.372 0.240 0.150 0.030 0.042 0.050 88.40 -

Yoyen Enterprises 15541 Conc. of Culaba-Caibiran National Circ. Road, Culaba-Looc Section 11/18/08 VIII 3.742 160 O 0.320 0.281 0.100 0.015 0.037 0.100 85.30 -

Yoyen Enterprises 15541 Conc. of Dayhagan-Salvacion-Coob-Libertad Road 08/26/08 VIII 12.537 150 O 0.317 0.220 0.100 0.020 0.038 0.100 79.50 -

Yoyen Enterprises 15541 Const. of Tagaytay Bridge & Approaches (Phase II) 08/13/12 VIII 28.323 945 C 0.402 0.200 0.300 - - - 90.20 93.62% V. Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page310

Page 311: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Yoyen Enterprises 15541 Const. of MPB @ Brgy. Tubog 03/13/13 V 2.394 135 C 0.476 0.133 0.300 - - - 90.90 *90.90% V. Satisfactory

Yoyen Enterprises 15541 Repair/Rehab./Impvt. of Masbate-Cataingan-Placer Rd. (Km.87+000-Km.88+000 w/ exceptions) 03/13/13 V 9.599 36 C 0.402 0.133 0.300 - - - 83.50 *83.50%

SatisfactoryYoyen Enterprises/Uy Construction

& Dev't. (JV) JV-08-263 Upgrading/Conc. of MacArthur-Guiuan Road exception 09/17/09 VIII 90.226 300 O 0.367 0.240 0.150 0.030 0.050 0.050 88.70 -

YS CONSTRUCTION 11928 Construction of Drainage System along National Road 8/11/2014 VII 9.261 193 OG 0.349 0.298 0.150 0.022 0.047 0.050 91.60

YS Construction 11928 BERRRP-Inabanga-Danao via Lapacan-Magtangtang rd. 01/20/15 Bohol 21.908 365 O 0.368 0.300 0.066 0.030 0.051 0.050 86.50 -

YS Construction 11928 Const./Imprvt. Of Vallehermoso-Canlaon City-La Castellana Rd. (VLCR) 09/14/09 VII 20.753 260 O 0.386 0.240 0.150 0.030 0.037 0.050 89.30 -

YS Construction 11928 Widening/Concrete Paving of Tubigon Port Access Road 06/09/09 VII 4.639 91 O 0.375 0.296 0.150 0.030 0.047 0.050 94.80 -

YS Construction 11928 Road Upgrading (Gravel to Paved) Danao-Sagbayan Road 03/27/12 VII 19.110 240 C 0.439 0.133 0.300 - - - 87.20 84.74% Satisfactory

YSA Construction and Supply 33968Rehab./Impv't. of Drainage System & Slope Protection

Works along Bagong Silang-Capalonga Nat'l Secondary Rds. (Phase 2)

08/08/13 V 5.523 60 C 0.410 0.200 0.300 - - - 91.00 *91.00% V. Satisfactory

YSL Builder 19516 Construction of Tangub City LTO District Office 08/26/14 DOTC 4.989 150 C 0.485 0.200 0.300 - - - 98.53 *98.53% Outstanding

YSL Builder 19516 Concreting of Dipolog-Punta-Dansullan-Segio Osmeña Road, Cogon Section 06/10/09 IX 12.322 210 O 0.375 0.240 0.150 0.030 0.042 0.050 88.70 -

YSL Builder 19516 Road Upgrading (Gravel to Concrete) Sindangan-Siayan-Dumingag-Mahayag Road, Buyos Secion 06/11/09 IX 16.151 270 O 0.353 0.240 0.150 0.030 0.042 0.050 86.50 -

YSL Builder 19516 Road Conc. along Dipolog-Punta-Dansullan-Sergio Osmeña Road, Sangkol Section 06/10/09 IX 12.319 210 O 0.352 0.240 0.150 0.030 0.037 0.050 85.90 -

YSL Builder 19516 Conc. of Dipolog-Dansullan-Sergio Osmeña Road, Cogon Section 09/17/09 IX 12.322 210 O 0.336 0.300 0.150 0.030 0.045 0.033 89.40 -

YSL Builder 19516 Road Conc. along Dipolog-Dansullan-Sergio Osmeña Road, Sangkol Sect. 09/17/09 IX 12.319 210 O 0.334 0.300 0.150 0.030 0.045 0.033 89.20 -

Yu Construction 10470 Emergency Repair and Rehabilitation of Abatan-Agahay-Busao-Toril-Aghao Road 05/14/15 Bohol 22.058 272 C 0.500 0.200 0.300 - - - 100.00 *100.00%

Outstanding

YU CONSTRUCTION 10470Construction/Improvement of Dauis - Panglao Road,

Section 1) K0009+570 to K0010+569.15; Section 2) K0010+748 to K0017+278.56

10/27/2014 VII 89.233 240 O 0.297 0.300 0.150 0.030 0.060 0.033 87.00% 87% Satisfactory

YU CONSTRUCTION 10470

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road Standard (HDM-4 Project Analysis (Intermittent

Section) Balilihan-Hanopol-Batuan Road, Batuan Section

8/12/2014 VII 44.400 179 OG 0.360 0.252 0.150 0.022 0.047 0.050 88.10

YU Construction 10470 Emergency Repair and Rehabilitation of Antequera-Balilihan via Dorol Road 01/19/15 Bohol 20.744 284 O 0.393 0.300 0.119 0.030 0.054 0.050 94.60 -

Yu Construction 10470 Upgrading (Gravel to Concrete) of Balilihan-Hanopol-Batuan Rd. 08/20/13 VII 40.386 209 O 0.349 0.257 0.150 0.030 0.065 0.050 90.10

Yu Construction 10470 Impv't. of Balilihan-Hanopol-Batuan Rd., Batuan Sect., K0046+702-K0048+594.23 (w/ exception) 03/14/13 VII 40.545 257 C 0.482 0.200 0.300 - - - 98.20 92.68%

V. Satisfactory

Yu Construction 10470 Impv't. of Rd., Jct. (TNR) Manbojoc-Antiquera-Catagbacan (Loon) Rd., Km.29+000-Km.31+125 (w/ exceptions) 03/12/13 VII 48.280 285 C 0.417 0.152 0.300 - - - 86.90 87.50%

Satisfactory

Yu Construction 10470Impv't./Widening of Jct. Catagbacan, Loon Rd. leading to

Int'l. Cruise Ship Port (inc. Causeway) Km.35+540-Km.36+048.20, Catagbacan

03/12/13 VII 19.025 240 C 0.423 0.162 0.300 - - - 88.50 87.30% Satisfactory

Yu Construction 10470Const./Impvt. of Concepcion, Danao-Buenavista, Carmen

Rd. Sect. 1: K0068+170- K0069+429.03 Sect. 2: K0069+630.64-K0069+740

03/14/13 VII 28.069 241 C 0.282 0.200 0.300 - - - 78.20 83.12% Satisfactory

Yu Construction 10470 Const. of MPB (Municipal Building), Poblacion 03/31/11 VII 16.398 300 O 0.389 0.240 0.150 0.030 0.060 0.050 91.90 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page311

Page 312: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Yu Construction 10470 Talibon Small Reservoir Irrigation Project 9/29/08 10/308 SRIP 14.630 373 O 0.322 0.177 0.100 0.030 0.047 0.200 87.60 -

Yu Construction 10470 Const. of MPB, Poblacion 03/26/12 VII 1.832 90 C 0.409 0.133 0.300 - - - 84.20 90.01% V. Satisfactory

Yu Construction 10470 Const. of Concepcion, Danao-Buenavista, Carmen Road 03/28/12 VII 25.790 197 C 0.423 0.133 0.300 - - - 85.60 84.64% Satisfactory

Yu Construction / SCP Construction (JV) JV-12-152 Upgrading of Jct., Dat-an, Carmen-Sierra Bullones-Pilar,

Alicia Rd., K0084+272.04-K0088+724.4 08/15/13 VII 60.752 316 O 0.374 0.251 0.150 0.030 0.055 0.033 89.30

Z & L Construction & Supplies 25322 Talakag IP 04/13-18/09 NIA 4.748 240 O 0.323 0.251 0.150 0.023 0.063 0.050 89.40 -

Z & L Construction & Supplies 25322 Const. of Multi-Purpose Bldg. @ Agusan Del Sur State College of Agriculture and Technology 06/08/09 XIII 2.799 135 O 0.349 0.300 0.150 0.030 0.032 0.033 89.40 -

Z F Construction 17676 Road Upgrading (Gravel to Paved) Baler-Casiguran Rd., Km.284+627.38-Km.286+042.45 03/23/12 III 11.510 120 O 0.455 0.133 0.300 - - - 88.80 87.30%

Satisfactory

Z M Construction 9052 Rehab. Of Damaged Paved Nat'l Roads, along OBR Km.194+700-Km.196+545 03/24/12 III 44.946 180 C 0.455 0.144 0.300 - - - 89.90 91.40%

V. Satisfactory

Z M Construction 9052 Const. of MPB, San Isidro 11/22/12 III 4.310 105 C 0.469 0.181 0.300 - - - 95.00 82.96% Satisfactory

Z M Construction 9052 Const. of MPB, Malabon 11/22/12 III 4.310 105 C 0.460 0.181 0.300 - - - 94.10 82.83% Satisfactory

Z M Construction 9052 Const. of MPB, Malabon 08/16/12 III 4.310 90 O 0.362 0.300 0.020 0.030 0.035 0.033 78.00 -Z M Construction 9052 Const. of MPB, San Isidro 08/15/12 III 4.310 90 O 0.360 0.300 0.020 0.030 0.035 0.033 77.80 -

Zabu Engineering 31104 Replacement of Limood Bridge along Kalinga-Abra Rd., Limood, Balenciagao Sur, Pasil 03/19/13 CAR 10.959 285 C 0.446 0.133 0.000 - - - 57.90 69.54%

Poor

Zabu Engineering 31104 Rehab. of Bulanao-Paracelis Rd. Km.510+880-Km.510+680, Magabbangon, Cudal 08/09/12 CAR 2.049 180 C 0.428 0.200 0.300 - - - 92.80 87.46%

Satisfactory

Zact Builders 33702 Conc./Drainage Impv't. of Rds., Alleys & Pathwalks, Masigla St., Brgy. Central 08/05/13 NCR 5.862 111 C 0.408 0.133 0.300 - - - 84.10 *84.10%

Satisfactory

ZEDIK BUILDERS 33330 Construction/Concreting of Road-Pilipinas Road @ Brgy. Centro-1 10/22/2014 II 4.878 78 C 0.365 0.200 0.300 - - - 86.50% 86.5%

Satisfactory

Zedik Builders 33330 Rehab./Impv't. of MNR, Pagudpud, Ilocos Norte Sect., K0558+049-K0558+622 10/20/13 I 3.841 85 C 0.434 0.133 0.300 - - - 86.70 *86.70%

Satisfactory

Zedik Builders 33330

Immediate Repair/Restoration (Infrastructure Facilities affected by recent Typhoons "Gener & Heavy Monsoons

Rains" & Flashfloods) along Ilocos Norte-Apayao Rd., Km.517+010 & Km.517+720 (Rd. Slip)

03/21/13 I 1.920 48/ C 0.375 0.133 0.300 - - - 80.80 *80.80% Unsatisfactory

ZET Construction 12615 Completion of Pangangan Causeway 09/22/15 DOTC 23.481 180 O 0.337 0.300 0.140 0.020 0.029 0.033 85.87 -

ZET CONSTRUCTION 12615 Lupon Port Development Project 02/05/14 DOTC 30.848 150 C 0.458 0.200 0.300 - - - 95.80 92.60% Very Satistactory

Zet Construction 12615 Lupon Port Development Project 09/18/13 DOTC 29.727 150 O 0.389 0.300 0.104 0.020 0.061 0.033 90.70 -

Zet Construction 12615 Replacement & Installation of Rubber Dock Fenders Phase I & II 05/31/13 PPA 28.122 120 C 0.490 0.200 0.300 - - - 99.00 98.31%

Outstanding

ZET Construction 12615 Repair/Renovation of Passenger Terminal Building (PTB-1) 09/28/12 PPA 15.463 272 O 0.399 0.270 0.150 0.030 0.064 0.050 96.30 -

ZET Construction 12615 Replacement and Installation of Rubber Dock Fenders, Phase I & II 02/15/13 PPA 28.122 120 O 0.400 0.300 0.150 0.030 0.049 0.050 97.85 -

ZF Construction 17676 Road Upgrading (Gravel to Paved) Baler-Casiguran Rd., Km.284+627.38 to Km.286+042.45 08/16/11 III 11.510 120 O 0.355 0.240 0.150 0.030 0.055 0.033 86.30 -

Zion Construction (Formerly Masterpiece Construction and

Supply)14881 Rehab./Reconst./Upgrading of Sibonga-Dumanjug Road,

Tubod-Dugoan Section 05/29/09 VII 14.175 75 O 0.383 0.240 0.150 0.030 0.055 0.050 90.80 -

Zion Construction (Formerly Masterpiece Construction and

Supply)14881 Widening of H. Abellana Road 06/05/09 VII 4.656 320 O 0.343 0.240 0.150 0.030 0.047 0.050 86.00 -

Zion Construction (Formerly Masterpiece Construction and

Supply)14881 Conc. of Jct.(LIR) Dat-an,Carmen-S. Bullones-Pilar-Alicia

Rd. Sta.90+290-Sta.92+240(Alicia Sec.) with exception 09/04/09 VII 18.637 232 O 0.337 0.237 0.150 0.030 0.037 0.033 82.40 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page312

Page 313: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

Zion Construction (Formerly Masterpiece Construction and

Supply)14881

Impv't./Conc. of Jct. (LIR) Dat-an, Carmen-Sierra Bullones-Pilar-Alicia Rd.(Pilar Sec.)Km. 81+980-Km.82+890 with

exemption09/04/09 VII 18.386 224 O 0.340 0.237 0.144 0.030 0.037 0.033 82.10 -

Zion Construction (Formerly Masterpiece Construction and

Supply)14881 Completion of MPB, Agape 08/25/10 VII 1.416 107 O 0.347 0.300 0.150 0.030 0.032 0.033 89.20 -

Zion Construction (Formerly Masterpiece Construction and

Supply)14881 Widening of H. Abellena Road 03/05/09 VII 4.656 261 O 0.343 0.300 0.150 0.030 0.027 0.050 90.00 -

Zion Construction (Formerly Masterpiece Construction and

Supply)14881

Conc. of Jct. (LIR) Dat-an, Carmen-Sierra Bullones-Pilar-Alicia Road (Sta. 90+290-Sta. 92+240 with exception), Alicia

Section06/05/09 VII 18.637 206 O 0.363 0.300 0.150 0.030 0.047 0.033 92.30 -

Zion Construction (Formerly: Masterpiece Const. & Supply) 14881

Rehab./Reconst./Upgrading of Damaged Pvmt. along Loay Interior Rd., K0197+576-K0198+980 & Sect. K0200+073-

K0200+772.52 (LIR) Loboc Sect.11/30/12 VII 35.192 342 C 0.419 0.133 0.300 - - - 85.20 85.56%

Satisfactory

Zion Construction (Formerly: Masterpiece Const. & Supply) 14881

Rehab./Reconst./Upgrading of Damaged Pavement along Loay Interior Rd. (LIR), Loboc Sect. 1: K0197+576-

K0198+980 & Sect. 2: K0200+073-K0200+772.5208/09/12 VII 33.372 281 O 0.355 0.240 0.150 0.030 0.050 0.033 85.80 -

ZION CONSTRUCTION (Formerly: Masterpiece Construction and

Supply)14881

Road Upgrading (Gravel to Concrete) Based on Gravel Road Strategies, Traffic Benchmarks (HDM-4 Project

Analysis), Argao - Ronda Road, K0085+090 to K0086+91710/22/2014 VII 12.550 158 C 0.420 0.138 0.300 - - - 85.80% 85.8%

Satisfactory

ZION CONSTRUCTION (Formerly: Masterpiece Construction and

Supply)14881

Preventive Maintenance Based on Pavement Management System/Highway Development and Management-4 (HDM-

4), Natalio Bacalso Avenue, K0069+086 to K0071+62510/24/2014 VII 32.811 125 C 0.424 0.196 0.300 - - - 92.00% 92%

Very Satisfactory

ZION CONSTRUCTION (Formerly: Masterpiece Construction and

Supply)14881

Repair/Restoration of Damaged Slope Protection and Slope Lined Canal along Natalio Bacalso Avenue,

K0059+500 to K0140+200 (Intermittent Section)8/5/2014 VII 1.806 195 C 0.427 0.171 0.300 89.80 90.40%

Very Satisfactory

ZION CONSTRUCTION (Formerly: Masterpiece Construction and

Supply)14881 Construction of Two (2) Storey, Four (4) Classroom School

Building at Argao National High School, Argao, Cebu 8/5/2014 VII 7.006 150 C 0.432 0.184 0.300 91.60 91.04% Very Satisfactory

ZION CONSTRUCTION (Formerly: Masterpiece Construction and

Supply)14881 Construction of Flood Control/Slope Protection along

Lambusan Bridge (Upstream and Down Stream) 8/7/2014 VII 18.136 140 C 0.391 0.200 0.300 89.10 89.10% Very Satisfactory

Zion Construction (Formerly: Masterpiece Construction and

Supply)14881 Repair/Maint. of Suba River Control, Brgy. Suba,

K0152+588 Upstream A & Downstream B 08/09/13 VII 4.889 107 C 0.482 0.147 0.300 - - - 92.90 *92.90% V. Satisfactory

Zion Construction (Formerly: Masterpiece Construction and

Supply)14881

Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd. along Natalio Bacalso Ave. (Cebu South Rd.), K0132+028-

K0134+00008/09/13 VII 44.218 172 C 0.419 0.200 0.300 - - - 91.90 *91.90% V.

Satisfactory

Zion Construction (Formerly: Masterpiece Construction and

Supply)14881 Const. of 2-Storey 4-CL Sch. Bldg. at Argao NHS 08/08/13 VII 4.730 150 O 0.355 0.270 0.150 0.030 0.053 0.050 90.80 -

Zion Construction (Formerly: Masterpiece Construction and

Supply)14881

Repair/Restoration of Damaged Slope Protection & Slope Line Canal along Natalio Bacalso Ave., K0059+500-

K0140+200 (Int. Sect.)08/09/13 VII 18.085 195 O 0.356 0.300 0.150 0.030 0.050 0.050 93.60

Zion Construction (Formerly: Masterpiece Construction and

Supply)14881 Road Upgrading (Gravel to Paved) along Argao-Moalboal

Road, Km.62+728-Km.63+978 03/23/12 VII 18.190 210 C 0.418 0.133 0.300 - - - 85.10 90.86% V. Satisfactory

Zion Construction (Formerly: Masterpiece Construction and

Supply)14881

Rehab./Reconst. of Damaged Paved Nat'l Road, Bogo-Curva-Medellin-Daanbantayan-Maya Rd. Daanbantayan

Sect.03/24/12 VII 15.164 158 C 0.442 0.133 0.300 - - - 87.50 90.44%

V. Satisfactory

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page313

Page 314: CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY … · CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 1, 2012 to June 30, 2015

ESH RDRSTATUSCPES VISIT

RATINGWMS MTL TIME FAC

FINAL RATING/ QUALITATIVE DESCRIPTION

AMOUNT (Php, M)

DUR (C.D.)

CONTRACT*IMPL. AGENCYNAME OF CONSTRUCTOR LICENSE

NO. PROJECT DATE OF EVALUATION

ZIRCON BUILDER 16158

Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved

Road Standards (HDM-4 Project Analysis), National Arterial Road, Nueva Ecija - Aurora Road, K0175+984 to K0176+140

8/8/2014 III 11.569 121 OG 0.352 0.240 0.150 0.012 0.042 0.033 82.90

ZKR Construction & Supply 34348Repalcement (Temp. to Perm.) of Ologon Bridge #2

(B00308 LZ) along Libon-San Vicente-Buga Rd., Brgy. Ologon K0489+677-K0489+685

11/25/12 V 5.561 195 C 0.463 0.133 0.300 - - - 89.60 83.96% Satisfactory

ZKR Construction & Supply 34348Replacement (Temporary to Permanent) of Ologon Bridge

#2 (B00308LZ) along Libon-San Vicente-Buga Rd. Brgy. Ologon, K0489+677-K0489+685

08/07/12 V 5.561 195 O 0.346 0.240 0.110 0.030 0.043 0.033 80.20 -

ZM / DMJ Construction (JV) JV-08-056 Replacement of Bravo Bridge 03/03/09 III 42.820 180 O 0.382 0.300 0.150 0.030 0.033 0.050 94.50 -

ZM / VRF Construction (JV) JV-08-014 Construction of Bridge and Approaches (Contact Package II) 03/03/09 III 38.937 210 O 0.357 0.244 0.150 0.020 0.028 0.050 84.90 -

ZM Construction / R.Z. Roncal Construction and Trading (JV) JV-11-036 Road Upgrading (Gravel to Paved) of Nueva Ecija-Aurora

Rd. 08/02/12 III 98.573 360 O 0.398 0.300 0.150 0.030 0.042 0.033 95.30 -

ZM Construction /DMJ Construction (JV) JV-07-084

Impvt./Widening of McArthur Highway (Manila North Road) Phase V Meycauayan Bulacan) to Mabalacat Pampanga

Sect., (Angeles-Mabalacat Section) CP108/28/09 III 85.883 240 O 0.392 0.240 0.150 0.030 0.050 0.033 89.50 -

ZM Construction/R.Z. Roncal Construction and Trading (JV) JV-11-036 Rd. Upgrading (Gravel to Paved) of Nueva Ecija-Aurora Rd. 08/10/13 III 98.572 540 C 0.438 0.133 0.300 - - - 87.10 92.02%

V. Satisfactory

ZMS CONST. & DEV. CORP (Formerly: ZMS Construction) 10471 Construction of Two (2) Storey Four (4) Classroom School

Building, Sominot NHS, (Don Mariano Marcos) 10/27/2014 IX 4.565 150 C 0.498 0.145 0.300 - - - 94.30% 94.3% Very Satisfactory

ZMS CONST. & DEV. CORP (Formerly: ZMS Construction) 10471 Widening of Pagadian City-Zamboanga City Road K

1662+950 -K 1664+950 10/27/2014 IX 48.389 229 C 0.454 0.133 0.300 - - - 88.70% 88.7% Satisfactory

ZMS Const. & Dev. Corp. (Formerly: ZMS Construction) 10471 Widening of Pagadian City, Zamboanga del Sur 8/13/2014 IX 45.582 174 OG 0.293 0.300 0.150 0.030 0.055 0.050 87.80

Zoniuq Enterprises 25223 Const. of FMR, Brgy. P. Burgos, Sinioan Public Market Expansion Site 03/17/12 IVA 4.728 129 C 0.482 0.133 0.300 - - - 91.50 82.74%

Satisfactory

Zota Trading & Construction 32641 Const./Impv't./Rehab. of FMR @ Lucao & Bonuan Boquig 08/06/13 I 0.980 45 C 0.466 0.133 0.300 - - - 89.90 *89.90% V. Satisfactory

Zota Trading & Construction 32641 Upgrading of Lateral Drainage along Urdaneta Jct.-Dagupan-Lingayen Rd. (via Zambales) Tapuac Sect. 03/16/13 I 3.680 155 O 0.378 0.300 0.000 0.030 0.023 0.000 73.10 -

*1st/Final* For DPWH, only the region and PMO office are listed

21st CPES Release Page314