ceu making project management work in the real world

51
CEU Making Project Management Work in the Real World

Upload: harvey-moody

Post on 17-Dec-2015

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CEU Making Project Management Work in the Real World

CEU

Making Project Management Work in the Real World

Page 2: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 2013

The best way to manage projects is by properly using proper Project Cost Management

Page 3: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 2013

ACRONYM TERM / FORMULA MEANING

AC Actual Cost What did it actually cost us to do the work/complete the work?

BAC Budget at Completion How much did we budget to do the work for the entire/total project?

CPI Cost Performance Index EV/AC

The amount of money we are getting back for each $ 1.00 we spent on the project. A measure of efficiency. ( Good = > $1.00; Bad = < $1.00)

CV Cost Variance EV-AC=

When we check the costs, are we under budget or over budget? [Positive = under budget; negative = over budget] ( Good = + Bad = -– )

EAC Estimate at Completion Today, what do we anticipate/expect/estimate it will have cost us to have completed the total or entire project?

ETC Estimate to Complete BAC/CPI =

or AC+ETC= or AC + (BAC-EV)= or

AC + [(BAC-EV)/CPI]=

From today, what do we think it will cost us to complete the total or entire project? [We know how much we spent already up to today, so how much more will we need to spend to complete all the rest of the work to complete the entire/total project?]

EV Earned Value What is the expected or estimated cost of the work we have actually completed?

PV Planned Value What is the expected or estimated cost of the work we planned to complete or get done?

SPI Schedule Performance Index

EV/PV=

When we check the schedule, we are only progressing at ____% of the rate we planned to progress at. This is a measure of efficiency. ( Good = > 100%; Bad = < 100%)

SV Schedule Variance EV-PV=

When we check the schedule are we ahead of schedule or behind schedule. [Positive = ahead of schedule; negative = behind schedule] ( Good = + Bad = -– )

VAC Variance at Completion BAC – EAC =

At the end of the project, how much under or over budget do we expect to be?

4

Earned Value Acronyms

Page 4: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 2013

Earned Value Analysis

Planned Value = Budgeted Cost of Work Scheduled PV = BCWS

Earned Value = Budgeted Cost of Work Performed EV = BCWP

Actual Cost = Actual Cost of Work Performed AC = ACWP

Page 5: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 2013

Spending PlansPoint in Time e.g. Today

BAC

EAC

PV

AC

Original Spending Plan

Actual Spending Plan

Future Spending Plan

ETC

VAC

Page 6: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 2013

Earned Value FormulasEarned Value EV = BAC * % Comp

Cost Variance CV = EV - AC

Schedule Variance

SV = EV - PV

Cost Perf Index

CPI = EV / AC

Schedule Perf Index

SPI = EV / PV

Est at Completion

EAC = AC / % Comp

Est to Complete

ETC = EAC - AC

Variance at Completion

VAC = BAC - EAC

New with 4th Edition

TCPI = BAC-EV / BAC-AC

Page 7: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 2013

Net Present Value (NPV)• NPV is the present value of cash inflow

minus the initial capital investment. Always take the greater NPV choice.

• Present Value = (Future Value) / (1 + r)n

– r = interest rate

– n = number of interest rate time periods

• NPV = sum of [ FV / (1+r)n ] - II- II represents the Initial Investment

Page 8: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 2013

Types of CostCost estimates can be comprised of multiple types of cost

Cost Type Description Example

Fixed Costs that stay the same throughout the life of a project

Piece of equipment

Variable Costs that vary on the project Hourly laborFuel for equipment

Direct Costs that are billed directly to the project

Software licensesTeam’s salary

Indirect Overhead costs that are shared and allocated among several/all projects

Manager’s salary

Sunk Costs that have been invested or expended

Unrecoverable past expenditures

13

Page 9: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 2013

Budget EstimatingTop-Down Estimating (Rough Estimate)

Bottom-Up Estimating

Rough Order of Magnitude (ROM) - 50 % to + 100 %

Completed during initiation (not very accurate)

Budget - 10 % to + 25 %

Completed during early planning (better accuracy)

Definitive - 5 % to + 10 %

Completed during late planning

Budget Estimates

“Most Accurate”

Page 10: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 2013

EARNED VALUE MANAGEMENT

15

Page 11: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201316

What Is It ?

Why Do I Need It ?

How Do I Do It?

Earned Value Analysis

Page 12: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201317

Today’s Situation

• Need for accurate and consistent status information• Numerous complex (and interrelated) projects

– Projects with many WBS activities– Virtual offices– Diverse technology platforms

Page 13: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201318

There’s Room For Improvement

70% of projects are:• Over budget• Behind schedule

52% of all projects finish at 189% of their initial budget

And some, after huge investments of time and money, are simply never complete

Source: The Standish Group

Page 14: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201319

How to answer the question: “Have we done what we said we’d do?”

• % complete estimating • % of Budget spent• % of work done• % of time elapsed

– subjective, incomplete – draws false conclusions

Page 15: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201320

Enter Earned Value Analysis“Earned Value Analysis” is:• an industry standard way to:

• measure a project’s progress,• forecast its completion date and final cost, and• provide schedule and budget variances along the way.

By integrating three measurements, it provides consistent, numerical indicators with which you can evaluate and compare projects.

Page 16: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201321

What’s more Important?

• Knowing where you are on schedule?

• Knowing where you are on budget?

• Knowing where you are on work accomplished?

Page 17: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201322

EVA Integrates All Three

• It compares the PLANNED amount of work with what has actually been COMPLETED, to determine if COST , SCHEDULE, and WORK ACCOMPLISHED are progressing as planned.

• Work is “Earned” or credited as it is completed.

Page 18: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201323

Earned Value needed because...

• Different measures of progress for different types of tasks

• Need to “roll up” progress of many tasks into an overall project status

• Need for a uniform unit of measure (dollars or work-hours).

Page 19: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201324

Earned Value needed because...

• Provides an “Early Warning” signal for prompt corrective action.

– Bad news does not age well.

– Still time to recover

– Timely request for additional funds

Page 20: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201325

And One More Reason

Why You Need EVA

?

Page 21: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201326

Because It’s the law !

These Set the Stage:

GPRA; 1993

FASA, Title V; 1994

Clinger-Cohen Act; 1996

And Then Along Came OMB! (Circular A-11, Part 7)

"Agencies must use a performance based acquisition management system, based on ANSI/EIA Standard 748, to measure achievement of the cost, schedule, and performance goals."

Page 22: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201327

How’s this project doing?

0

20000

40000

60000

80000

100000

120000

Jan-03 Feb-03 Mar-03 Apr-03 May-03 Jun-03 Jul-03 Aug-03 Sep-03 Oct-03 Nov-03 Dec-03

Projected

Actual

Page 23: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201328

Let’s Take A Look Under The Hood

Page 24: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201329

But First! - We gotta get organized

EVA works best when work is ‘compartmentalized’.

Compartmentalization is best achieved with a well-planned Work Breakdown Structure.

So, how do I create a WBS for a really complex project?

Page 25: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201330

Proper WBS Design

One WBS per program• Deliverable-oriented• Work not in the WBS is out-of-scope• Each descending level represents more detail

Full (and accurate) definition is key• Defined deliverable(s)• Timeframe for delivery of product

• Total cost (direct and indirect) to deliver product

Let’s Look at an example:

Page 26: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201331

WBS & Decomposition…

A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Fifth Edition, Figure 5-13

Page 27: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201332

WBS Units are “Work Packages”

Lowest level WBS elements

Have an accompanying narrative

Have three measurable components• Scope of work to be accomplished• Total (direct and indirect) cost• Timeframe for completion

Page 28: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201333

Some New(er) TermsBCWS - Budgeted Cost of Work Scheduled

ACWP - Actual Cost of Work Performed

BCWP - Budgeted Cost of Work Performed

Page 29: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201334

Earned Value Definitions

BCWS: “Budgeted Cost of Work Scheduled”

Planned cost of the total amount of work scheduled to be performed by the milestone date.

Page 30: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201335

BCWS - Budgeted Cost of Work Scheduled

0

20000

40000

60000

80000

100000

120000

Jan-

03

Feb

-03

Mar

-03

Apr

-03

May

-03

Jun-

03

Jul-0

3

Aug

-03

Sep

-03

Oct

-03

Nov

-03

Dec

-03

BCWS

Page 31: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201336

Earned Value Definitions (cont.)

ACWP: “Actual Cost of Work Performed”

Cost incurred to accomplish the work that has been done to date.

Page 32: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201337

ACWP - Actual Cost of Work Performed

49000

56000

0

20000

40000

60000

80000

100000

120000

Jan-

03

Feb

-03

Mar

-03

Apr

-03

May

-03

Jun-

03

Jul-0

3

Aug

-03

Sep

-03

Oct

-03

Nov

-03

Dec

-03

BCWP

ACWP

Page 33: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201338

Earned Value Definitions (cont.)

•BCWP: Budgeted Cost of Work Performed

The planned (not actual) cost to complete the work that has been done.

Page 34: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201339

BCWP - Budgeted Cost of Work Performed

49000

55000

0

20000

40000

60000

80000

100000

120000

Jan-

03

Feb

-03

Mar

-03

Apr

-03

May

-03

Jun-

03

Jul-0

3

Aug

-03

Sep

-03

Oct

-03

Nov

-03

Dec

-03

BCWP

BCWS

Page 35: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201340

5500049000

56000

0

20000

40000

60000

80000

100000

120000

Jan-

03

Feb

-03

Mar

-03

Apr

-03

May

-03

Jun-

03

Jul-0

3

Aug

-03

Sep

-03

Oct

-03

Nov

-03

Dec

-03

BCWS

BCWP

ACWP

The Whole Story

Page 36: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201341

Some Derived Metrics

•SV: Schedule Variance (BCWP-BCWS)–A comparison of amount of work performed during a

given period of time to what was scheduled to be performed.

–A negative variance means the project is behind schedule

•CV: Cost Variance (BCWP-ACWP)–A comparison of the budgeted cost of work performed

with actual cost.–A negative variance means the project is over budget.

FYI

Page 37: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201342

Schedule Variance & Cost Variance

Schedule Variance = BCWP-BCWS

$49,000- 55,000

SV = - $6,000

Cost Variance = BCWP-ACWP

$49,000- 56,000

CV = - $7,000

FYI

Page 38: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201343

•SPI: Schedule Performance IndexSPI=BCWP/BCWS SPI<1 means project is behind schedule•CPI: Cost Performance Index

CPI= BCWP/ACWPCPI<1 means project is over budget•CSI: Cost Schedule Index (CSI=CPI x SPI)

The further CSI is from 1.0, the less likely project recovery becomes.

Some More Derived MetricsFYI

Page 39: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201344

Performance MetricsSPI: BCWP/BCWS

49,000/55,000 = 0.891

CPI: BCWP/ACWP

49,000/56000 = 0.875

CSI*: SPI x CPI

.891 x .875 = 0.780

Cost Schedule Index (combined)

Page 40: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201345

Making ProjectionsOnce a project is 10% complete, theoverrun at completion will not be lessthan the current overrun.

Once a project is 20% complete,the CPI does not vary from its currentvalue by morethan 10%.

The CPI and SPI are statistically accurate indicators of final cost results.

Source: Defense Acquisition University

Page 41: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201346

10200090882

103865

0

20000

40000

60000

80000

100000

120000

Jan-

03

Feb

-03

Mar

-03

Apr

-03

May

-03

Jun-

03

Jul-0

3

Aug

-03

Sep

-03

Oct

-03

Nov

-03

Dec

-03

BCWS

BCWP

ACWP

Making Projections

Today

Page 42: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 2013

47

102000

116,571

0

20000

40000

60000

80000

100000

120000

140000

Jan-

03

Mar

-03

May

-03

Jul-0

3

Sep-0

3

Nov-03

Jan-

04

Mar

-04

BCWS

BCWP

ACWP

Estimate to Complete

Today

Page 43: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201348

A New Criteria

Activities “earn value” as they are completed.

The value earned is the WBS budgeted cost of the activity completed to date.

Page 44: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201349

Value of Earned Value

• Schedule Status Reporting• Cost Status Reporting• Forecasting

Page 45: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201350

A-11, Part 7 Requires an EVMS“ . . . based on ANSI/EIA Standard 748”

And what does that mean?

ANSI/EIA 748 provides a list of guidelines• Organization• Planning, Scheduling, and Budgeting• Accounting Considerations• Analysis and Management Reports• Revisions and Data Maintenance

But, ANSI/EIA 748 doesn’t identify ‘approved systems’

FYI

Page 46: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201351

A-11, Part 7 Requires an EVMSSo where do I get one?Buy a prepackaged one. (Lot of ‘em around)

Make your own.

• Microsoft Project

• Microsoft Excel

Or it could be as simple as this:

FYI

Page 47: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201352

Requirements of Earned Value

• Proper WBS Design• Baseline Budget Control Accounts • Baseline Schedule• Work measurement by Control Account

– work-hours, dollars, units, etc.• Good Project Management Practices

Page 48: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201353

Shortcomings of Earned Value

• Quantifying/measuring work progress can be difficult.

• Time required for data measurement, input, and manipulation can be considerable.

Page 49: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201354

Summary• EVA & EVMS will help reduce guesswork in:

– Measuring performance– forecasting

• Need to get beyond misleading measures of progress.

• Reasons to use EVA and EVMS:– Good project management practice– OMB requirement

• Incorporate into contracts

Page 50: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 201355

Summary

In order to manage a real-world project, a complete understanding and accounting of all time, costs and work must be part of your regular routine.

Page 51: CEU Making Project Management Work in the Real World

Proprietary Information Of Energy 2013

Earned Value Analysis