ceb report

155
NATIONAL DIPLOMA IN ENGINEERING SCIENCES TRAINING REPORT GENARAL INDUSTRIAL TRAINING AT CEYLON ELECTRICITY BOARD SUBMITED BY : P.A.U.A.BANDARA ADD. NO : EP\01\4701 FIELD : ELECTRICAL ENGINEERING (POWER) DURATION : 06 / 10/ 2003 TO 31/ 08/ 2004 TECHNICIAN TRAINING INSTITUTE KATUNAYAKE.

Upload: sameera-vithana

Post on 30-Oct-2014

508 views

Category:

Documents


18 download

TRANSCRIPT

Page 1: Ceb Report

NATIONAL DIPLOMA IN ENGINEERING SCIENCES

TRAINING REPORTGENARAL INDUSTRIAL TRAINING

AT

CEYLON ELECTRICITY BOARD

SUBMITED BY : P.A.U.A.BANDARA

ADD. NO : EP\01\4701

FIELD : ELECTRICAL ENGINEERING (POWER) DURATION : 06 / 10/ 2003 TO 31/ 08/ 2004

TECHNICIAN TRAINING INSTITUTE KATUNAYAKE.

CONTENTS

Page 2: Ceb Report

Acknowledgement Chapter 1 Introduction

1.1 Introduction1.2 Vision1.3 Mission1.4 The board’s statuary obligation1.5 Environment policy statement1.6 Power stations operated by CEB

Chapter 2 Government Installation2.1 Introduction2.2 Cinnamon Garden Depot2.3 Wiring Installation & testing2.4 Trip switch

Chapter 3 High Tension Maintenance3.1 Introduction3.2 Main element connected in Ring system3.3 Underground Cables3.4 Construction of cables3.5 Cables for three-phase service3.6 Types of cable faults3.7 Fault location3.8 Cable fault Locating Methods

Chapter 4 Sub Stations (Kolonnawa & Biyagama Grid Sub Station)4.1 Introduction4.2 Types of Sub Stations according to the service4.3 Types of Sub Stations according to the construction4.4 Switch yard Equipment4.5 Oil breakers 4.6 Circuit breaker testing4.7 Interlocking System4.8 Transformer protection4.9 Operation of transformers4.10 Transformer testing

4.11 Laying underground cablesChapter 5Generation (Victoriya power station)

5.1 Introduction5.2 Water ways5.3 Underground Power station5.4 Generators5.5 Protection of generators5.6 Excitation5.7 Control room

5.8 Switch yardChapter 6 Medium voltage maintenance

6.1 Introduction6.2 Equipment applied in overhead distribution lines6.3 Hot line Maintenance

2

Page 3: Ceb Report

6.4 sub Station Maintenance6.5 Line Maintenance

Acknowledgement

It is indeed a great pleasure to present the training report in the

3

Page 4: Ceb Report

completion of the second practical training 6 months of general industrial training at

Ceylon electricity board which were very satisfactory places to cover most of the

modules that gave me technical and management knowledge.

It is pleasure to thank the chairmen and all the managers and engineers

at C.E.B for contributing the optimum support and guidance to receive a standard

training in electrical field. Further I’m very much thankful to other engineers,

electrical superintendents, foremen, supervisors in various technical work shops &

fields in addition I received the fullest cooperation from all segments of general

workforce.

I would also like to thank the TTI management Including all the IT & Academic staff

for providing necessary instructions, guidance, and giving me the fullest cooperation.

Finally I thank all my colleagues for been with me exchanging views, sharing

experiences, etc during this period.

Thank You,

P. A.U.A.Bandara

EP / 01/4701

TRAINING SCHEDULE OF CEB

4

Page 5: Ceb Report

Period Work site

From To

Government installation (Cineman garden)High Tension Maintenance (Maligawatta)Grid substation (Biyagama)Grid substation (Kolonnawa)

Mahaweli complex (Victoriya power station)Medium Voltage Maintenance (Piliyandala)

5

Page 6: Ceb Report

1.1 INTRODUCTION

CEB is a leading government institute. It has the responsibility of handling almost all the

control of electricity sector in Sri Lanka.

Namely,

Generation

Transmission

6

Page 7: Ceb Report

Distribution (major part)

Ceylon Electricity Board has the monopoly of electrical power sector in Sri

Lanka. C.E.B. constituted under the Ceylon Electricity Board Act No 17 of 1969, which

had been subsequently amended by Act No 31 of 1969 and Act No 29 of 1979. Now

CEB is under ministry of energy and power and the ministry of energy and power is Mr.

Susil Premjayantha

1.2 Vision

Be an internationally recognized efficient utility providing high quality service to

all its stakeholders.

1.3 Mission

To provide reliable quality electricity to the entire nation at internationally competitive

prices effectively and efficiently through a meaningful partnership with skilled and

motivated employees using appropriate state-of-the-art technology for the socio economic

development of the country in an economically sustainable manner while meeting

acceptable environment standards.

1.4 The board’s statutory obligation

“The Board is under a statutory duty to develop and maintain an efficient,

coordinated and economical system of Electricity Supply. It is also the duty of the Board

to generate or acquire supplies of electricity; to construct, maintain and operate the

necessary works for the generation of electricity by all means, to construct, maintain and

operate the necessary works for the inter-connection of Generating Stations and Sub-

stations and for the transmission of electricity in bulk from

 

7

Chairman, Vice ChairmanAnd

Board of Directors

General Manager

A.G.M.Transmission

A.G.M. Distribution Operation

A.G.M.Commercial

Manager Investigation

D.G.M.Engineering Audit

FinanceManager

A.G.M.Human Resources

A.G.M. DistributionDevelopment and Services

A.G.M.Generation

Chief Internal Auditor

Secretary To The Board

Pension and Provident Fund

Page 8: Ceb Report

Generating Stations and Sub-stations to such places as may be necessary from time to

time; to distribute and sell electricity in bulk or otherwise”.

“It is the duty of the Board to exercise its powers and perform its functions so as

to secure that the revenue of the Board are sufficient to meet its total outgoing properly

Chargeable to revenue account including depreciation and interest on capital, and to meet

a reasonable proportion of the cost of the development of the services of Board”.

8

Page 9: Ceb Report

1.5 Environment policy statement

Ceylon Electricity Board will manage all its business activities in a manner,

which cares for the natural and manmade environment and contribute to sustainable

development. By means of openness in dealing with environmental issues, CEB intends

to create confidence in their activities on the part of the public, customers, authorities,

employees, and owners. CEB will actively pursue a policy of incorporating and

integrating environmental considerations into CEB activities.

CEB policy is elaborated below in more concrete terms

a. CEB will lead the development of environmentally compatible and efficient

energy solutions.

b. CEB will, by means of quantifiable environmental targets, endeavor to cause

minimum impact on the environment.

c. CEB will, in all our operations, economize on natural resources and energy.

d. CEB will attach key importance to human health and safety.

e. CEB will analyze in advance the environmental impact of all new activities.

f. CEB will improve the environmental awareness of their staff by training and

motivating them to take responsibility for the environmental consequences of

their activities.

g. CEB will place the same high environmental demands on our suppliers,

contractors and business partners as CEB place on their own operations.

h. CEB will be able to discuss environmental issues with their customers from an

overall perspective and promote electricity's environmental benefits.

i. CEB will openly report on our environmental work and their impact on the

environment, and conduct a close dialogue with various interested parties on

environmental issues important to our activities.

9

Page 10: Ceb Report

1.6 Power station operated by CEB

The details of power stations operated by CEB are given in Table.1.1and Table. 1.2

PlantInstalled Capacity

MWGeneration (million

units/yr)Commissioning

Laxapana Complex

Canyon 2 * 30 60 137.3Unit 1 March 1983Unit 2 1988

Wimalasurendra 2 * 25 50 122.1 Jan 1965

Old Laxapana3 * 8.33 502 *12.5

260.8Dec 1950Dec 1958

New Laxapana 2*50 100 465.8Unit 1 Feb 1974Unit 2 Mar 1974

Polpitiya 2*37.5 75 396.8 April 1969

Laxapana Total 335 1382.8

Mahawelli Complex

Victoria 3* 70 210 663.7 Unit 1 Jan 1985Unit 2 Oct 1985Unit 3 Feb 1986

Kotmale 3*67 201 445.13 Unit 1 April 1985Unit 2 Feb 1988Unit 3 Feb 1988

Randenigala 2*61 122 326.4 July 1986

Ukuwela 2*19 38 164.4 Unit 1 July 1976Unit 2 Aug 1976

Bowatenna 1*40 40 48.8 Jan 1981

Rantambe 2*24.5 49 189.1 Jan 1990

Mahawelli total 660 1837.53

Samanalawewa 2*60 120277.3 Oct 1992

Small hydro Plants

Inginiyagala2*2.475 112*3.15

26.8June 1963

10

Page 11: Ceb Report

Uda walawe 3*2 6 7.6 April 1969

Nilambe 2*1.6 3 11.6 July 1988

Small hydro Total 20

Under construction

Kukule 2*35 70 306 Jan 2002

Total hydro 1205 3803.63Table1.1Hydro Power plants of Sri Lanka

Thermal Plant Installed Capacity (MW)

Commissioning

Kelanitissa Gas Turbines

6 * 20 1201* 115 115

Nov 1980-Mar 1982August 1997

Kelanitissa Steam 2*22 44

June 1962 & Sep 1963

Sapugaskanda Diesel 4*18 72

May 1984- Oct 1984

Sapugaskanda Diesel Extension (ADB)

4*10 40

Sep 1997

Lakdanawi Diesel (BOO)

22.5

Late 1997

Asia power diesel (BOO)

51

Mid 1998

Under construction

Kelanitissa combined Cycle

1*150 150

Late 1999 - 2000

Sapugaskanda Diesel Extension

4*10 40

Early 1999

11

Page 12: Ceb Report

2.1 INTRODUCTION

The government installation branch of CEB has established to under take the

installation and maintenance of electricity supply in government organizations. All the

materials used by government installation branch are satisfied with British Standard and

all the wiring is carried out according to the IEE regulations. After the installation they

check whole wiring to make sure that all the wirings have done properly.

They check – Earthling are proper

- Correct wires have used for correct place

2.2 Cinnamon Gardens depot

At Cinnamon Gardens depot we studied the following things,

Brief idea about the motor windings of fans

Direct online starter

Operation of MCB and trip switches

Domestic consumer box

Electric wiring planning of a house

2.3 WIRING INSTALLATIONS AND TESTING

Main elements of a wiring installation are

- Main switch

- Distribution Board

- RCD (Trip switch)

12

Page 13: Ceb Report

- MCB’s

- Electrical equipments

- Earthings

Testing

Check live, neutral and earth are properly connected

Check earthings are properly connected

Live and neutral and live and earth are properly insulated

L N

Coil

Test Live

Button Neutral

E Second Main earth wire Earth

Earth wire

Fig 2.1

Voltage Control Trip Switch

N L

Test

Resister

L

Test button N

13

Page 14: Ceb Report

E

Fig 2.2

Current Control Trip Switch

INSULATION TESTInsulation test for wiring is usually carried out with a 500v megger and tests

should be made.

Insulation Test Between Live and Neutral ConductorsBefore carryout this test, Circuit breakers must be closed, Switches must be on

and lamps out. Then megger is connected between live and neutral. The reading should

not be less than 1Ω.

INSULATION TESTS BETWEEN LIVE AND EARTH

Live and neutral must be connected together. Circuit breakers must be closed. All

switches must be on and lamps must be in. The megger is connected between conductor

and earth. The reading should not be less than 1 Ω.

Trip switch

There are mainly two types of trip switches and they are

Voltage control trip switch

Current control trip switch (Rcd)

The function of operation of Voltage control trip switch is based on the leakage current in

the earth wire. Hence these types of trip switches prevent the electric hazards, which

could arise from any electric appliances and protect the human body.

Current control trip switch operation is based on current different between live and

neutral conductor. Hence prevents having electric shocks from live conductor.

14

Page 15: Ceb Report

2.4 OPERATION OF MCB

Miniature circuit breaker (MCB) is a device which act as switch and it can be

operated either manually or automatically.

The tripping action may be either magnetic or thermal. Both these actions have applied in

the MCBs, which is observed in the G.I. branch. Protection against current slightly higher

than the rated current is given by the bending of a bimetal strip, while high-speed

protection against a short circuit is given by magnetic operation.

3.1 INTRODUCTION

High-tension maintenance can be divided into 6 parts.

Routine maintenance

Seasonal maintenance

Breakdowns

Shifting

Augmentation

Civil and other minor works

Routine maintenance is done without interrupting the supply .eg: cleaning, visual

inspection. Seasonal maintenance are done without supply.(Oil circuit breakers –

3yrs,Vacuum circuit breakers/ Air circuit breakers-1yr.,Ring main unit-3yrs.)

Breakdowns are done as they incur.

Other three are very rare situations.

Colombo City

Colombo city electricity distribution is carried out order of area office namely

South, East, West and North. An Area Engineer leads each area.

Area staff does commercial functions, LT breakdown and LT maintenance work.

A control center is opened over 24 hrs a day at Maligawatta to accommodate

consumer complaints, coordinating breakdown staff, HT operation and maintenance.

HT operation, HT maintenance, primary substations maintenance and fault

location staff and rehabilitation staff are located at Maligawatta.

Colombo city demand is supplied by approximately 1020 substations (11kV/HT)

as shown in figure 7.1, which are having ring connections to enable alternative

feeding.

15

Page 16: Ceb Report

There are 8 primary substations (33kV/11kV)namely A, B, C, D, E, F, G and H

Substations are connected to primary substation in ring, radial and satellite

Primary substations A, B, C, D, E, F, G and H are fed from Kolonnawa receiving

station, Kelanitissa power station, etc. (at 33kV or 132kV levels)

11kV/LT substations: There are few types,

Ring substation

Radial substation

Satellite substation

Test terminal Test terminal

To Ring To Ring

Fuse

16

Page 17: Ceb Report

Power taking off

To the sub T/F

Fig 6.3Internal wiring of ring main unit

3.2 MAIN ELEMENT CONNECTED IN RING SYSTEM

Ring main unit

This is very important device is connected to ring in 11KV underground

system 11KV supply will be feed through the RMU for each transformers. To protect

transformers against over current RMU contains three 50A fuses are available in each

phase. In the RMU fuses will immerse in oil because to get a high insulation between

each phase reduces heat build up in each phase.

Transformers

In underground system used step down transformers (132KV/33KV),

(132KV/11KV ), (33KV/11KV), (11KV/415V). Mostly used 11KV/415V transformers

because out put is directly connected to the consumers. Where transformers KVA rating

is depend on the consumers requirement. Generally following ratings are commonly used

800 KVA, 500 KVA and 1000 KVA.

Bus-bar panel

This is a metal box, which is consisting of Cu bars that are isolated from fiber

plates. The current rating of the bus bar depending upon the consumer capacity and the

requirement. In general 1600A, 800A, 400A rating bus bars panels are placed in Colombo

city.

Feeder piller panels

17

Page 18: Ceb Report

This is a low voltage panel same as bus bar panels. But this panel has neutral

bus bar, which is connected to transformer neutral point. To protect the human life to the

electric shock metal panel casing should be grounded properly.

Circuit brakers

Circuit breakers are placed low voltage side for purpose of protect the

transformer where overload the consumer side.

3.3 UNDERGROUND CABLES

Electric power can be transmitted or distributed either by overhead system or

by underground cables. I n modern cities and towns, the distribution of power by bare

over head conductors is avoided for reasons of safety and cables laid in air are not

pleasing to the eye. Therefore we use underground cable system. An under ground cable

essentially consists of one or more conductor covered with suitable insulation and

surrounded by a protecting cover.

ADVANTAGES OF UNDERGROUND SYSTEM

In the under ground system, the cable is not effected by weather condition, such

as rain, storm, snow, etc. On the other hand, overhead lines are exposed to

weather conditions with consequent chances of interruption of power.

Under ground cables do not suffer from such fault as birdcage, breaking of

conductors owing to falling objects, flash over fault because of lightening.

In densely populated areas, overhead line is unsafe and can lead to accidents.

Since the chances of faults on underground cable are low, the maintenance cost of

the under ground system is low.

The underground system does not disturb the environmental because of its

location. Therefore, it is increasingly preferred in modern town and cities.

Because of the metallic sheath covering g on the underground cables, the system

concerned does not interfere with telecommunication cables.

18

Page 19: Ceb Report

The inductive reactance of cables is less compared to that case of overhead

conductors. This is because the spacing between the cables is less. Therefore the

voltage drop on the under ground system is less compared to the overhead system.

DISADVANTAGES OF UNDERGROUND SYSTEM

The capital cost of laying under ground cable is high

The incidence of fault in under ground system rare. However, once a fault occurs

it is difficult to locate and repair it.

The current carrying capacity of the cable is reduced due to the close grouping of

cables and unfavorable conditions for distribution of heat.

3.4 CONSTRUCTION OF CABLE

Core or conductor

A cable may have one or more than one core (conductor) depending upon the type

of service for which if is intended. For instance, the three-conductor cable as shown

above used for phase service. The conductors are made of tinned copper or aluminum and

are usually stranded in order to provide flexibility to the cable.

Insulation

Each core or conductor is provided with a suitable thickness of layer depending

upon the voltage to be with stood by the cable. The commonly used material for

insulation ate impregnated paper, varnished cambric or rubber mineral compound.

Metallic sheath

In order to protect the cable from moisture, gases or other damaging liquids (acids

or alkalies ) in the soil and atmosphere, a metallic sheath of lead or aluminium is

provided over the insulation as shown in figure.

Bedding

Over the metallic sheath is applied a layer of bedding, which consists of a fibrous

material. The purpose of bedding is to protect the metallic sheath against corrosion and

from mechanical injury due to armoring.

19

Page 20: Ceb Report

Armouring

Over the bedding armoring is provided which consists of one or two layers of

galvanized steel wire or steel tape. Its purpose protects the cable from mechanical injury

while laying and during the course of handling. Armoring may not be done the case of

some cables.

Serving

In order to protect armoring from atmospheric condition, a layer of fibrous

material (like jute) similar to deeding is providing over the armoring. This is known as

serving.

3.5 CABLES FOR THREE PHASE SERVICE

Belted cables

These cables are used for voltages up to 11kv but in extraordinary cases, their use

may be extend up to 22kv. The cores are insulated from each other by layers of

impregnated paper. Another layer of impregnated paper tape, called paper belt is wound

round the grouped insulated cores. The gap between the insulated cores is filled with

fibrous insulating material to give circular cross section to the cable. The belt is covered

with lead sheath to protect the cable against moisture and mechanical injury. The lead

sheath is covered with one or more layers of armouring with an outer serving.

Screened cables

These cable are used for voltage up to 33KV but in particular cases their use may

be extended to operating voltage up to 66KV.There are two types of screened cable.

H type cable

20

Page 21: Ceb Report

In this layer of impregnated paper insulates each core. The insulation in each core

is covered with a metallic screen, which usually consist of perforated aluminum and oil.

The cores are laid in such a way that metallic screens make contact with one another.

An additional conducting belt (copper woven fable tape) is wrapped round the

three cores. The cable has no insulating belt but lead sheath, bedding, armoring and

serving as usual.

SL type cable

It is basically H type cable but the screen around each insulation is covered by its

own lead sheath. There is no overall lead sheath but only armoring and serving is

provided.

There are two main advantages than H type. Frost the separate sheaths minimizes

the possibility of core-to-core breakdown. Secondary, bending of cables because easy due

to the elimination to overall lead sheath.

Pressure cable

For voltage beyond 66KV,solid cable is unreliable because there is a danger

of breakdown of insulation due to the presence of voids. When

the operation voltages are greater of than 66KV, pressure cables are used. There are two

types of pressure cable.

Oil filled cable

Gas pressure cable

Oil filled cable

In such type of cables, channels of duets in the cable for oil circulation. The

oil under pressure is kept constantly supplied to the channel by means of external

21

Page 22: Ceb Report

reservoirs placed at suitable distance along the tout of the cable oil filled cables are of

three types, viz. single core conductor channel, single core sheath channel and there core

filler space channel.

Gas pressure cable

The voltage required setting up ionization inside void increases as the

pressure is increased. Therefore, if ordinary cable is subjected to another eliminated

3.6 TYPES OF CABLE FAULTS

Cables are generally laid directly in the underground distribution system. For this reason,

there are little chances of faults in under ground cables. However, if a fault does occur, it

is difficult to locate and repair the fault because conductor is not visible. Nevertheless,

the following are the faults most likely to occur in underground cables.

Open circuit fault

When there is a break in the conductor of a cable, it is called open circuit fault.

The open circuit fault can be checked by a megger. For this purpose, the three conductors

of the 3-corecable at the far end are shorted and earthed. Then resistance between each

conductor and earth is measured by a megger. The megger will indicate zero resistance in

the circuit of the conductor that is not broken. How ever if the conductor is broken, the

megger will indicate infinite resistance in its circuit.

Short circuit fault

When two conductors of a multi-core cable come in electrical contact with each

other due to insulation failure, it is called a short circuit fault. We can seek the help of

megger to check this fault. For this purpose, the two terminals of the megger are

connected two any two conductors. If the megger gives zero reading, it indicates short

22

Page 23: Ceb Report

circuit fault between these two conductors. The same step is repeated for other conductors

taking two at a time.

Earth fault

When the conductor of a cable comes in contact with earth, it is called earth fault

or ground fault. To identify this fault, one terminal of the megger is connected to the

conductor and the other terminal connected to earth. If the megger indicates zero reading,

it means the conductor is earthed. The same procedure is repeated for other conductors of

the cable.

3.7 Fault Location In a good power system stability and continuity are very important.. When a fault

occurs on the network and power is lost, the company’s priority is to reconnect as many

customers as quickly as possible. ‘Switching’ customers to alternative supplies wherever

possible does this. The fault location and maintenance is done by operation control center

and HTM complex to Maligawatta. The maintenance and repairing of high-tension line of

11KV and 33KV and low tension of Colombo city is done by above branch. All of the

high-tension lines are installed in an underground ring system. Therefore special kinds of

underground cables, special type of joints and special kind of insulation are used to

maintain that system.

Test-Vans

The branch has three state-of-the-art test vans equipped with the latest fault finding

technology. This equipment on board enables faults to be detected by sending a signal

down the cable to highlight any inaccuracies, which are shown on a computer screen. A

trace is put on the signal to pick up any mismatch to determine how far down the cable

the problem is. The exact fault is found by using a surge generator to pinpoint the area of

irregularity. The equipment is used mainly on the 11,000-volt and 33,000 volt

underground cable network

Rezaps

23

Page 24: Ceb Report

Low voltage cables are designed to be very resilient and when a fault does occur, they

have a tendency to rectify them, which can make fault location and repair extremely

difficult. This ability to self-repair means that low voltage faults can often be intermittent.

To help engineers locate them, the branch uses devices called ‘Rezaps’. Connected at a

local substation, this device automatically switches the power back on after a fuse has

blown, restoring customer supplies in seconds if the fault has cleared. Once the fault

develops permanently, engineers are dispatched to locate and repair it. Although

customers will experience short interruptions to their supply during this period, it does

reduce the time off supply from several hours to a minute or so.

Transient interruptions

Brief supply interruptions with duration of less than one minute are called transient

interruptions. There are many causes, such as lightning strikes, contact by animals and

birds, and high winds blowing tree branches onto overhead lines. By using sensitive

electrical equipment to disconnect the supply for a few seconds and then restoring it, the

cause of the fault is given the chance to clear.

This ensures customers’ supplies are restored quickly and prolonged interruptions are

often avoided. The HTM knows that transient interruptions are inconvenient to customers

and continues to work towards reducing the causes. This work involves extensive tree

cutting near overhead lines and installing modern, automatic switches, which can be set to

operate more sensitively without causing transient interruptions. These measures will

reduce the number of transients.

3.8 CABLE FAULT LOCATING METHODS

Echo Meter (Tele Fault)

Battery operated and portable, the instrument is microprocessor based and

utilizes the well-established pulse echo technique of fault location but with an entirely

new level of simplicity of operation and accuracy. The unique combination of hardware

24

Page 25: Ceb Report

and software filtering in the echo meter allows it to continue operating normally, without

distortion or instability of the displayed fraces, even when connected to energize low

voltage power cables. Echo meter can therefore be used locate many types of faults on

low voltage on low voltage power cables, e.g. open circuit s, phase to phase etc. Without

the need to disconnect supplies to consumers. In addition if echo meter is triggered from

an external fault-detecting device such as a ct or voltage dip detector transitory faults may

also be located.

The LCD graphics panel displays the reflected pulse signals and calibrated

cursors are used to measure the distance to the fault. In addition the LCD panel displays

alphanumeric message giving the instrument status and measured fault distance. We can

be measured approximately 3.2 km distance. According to the waveform we can identify

the types of the fault.

Cable Finder (CAT)

Complicated cities electrical network go through as underground network.

The under ground cables lay different different directions in consumers requested. After

few years any one don’t know underground cable layouts and the further extension are

also carried out. At this times electrical company face to more problems find out the

cables for maintenance work. In this time electrical company is used handiness,

ruggedness and reliability in and interesting design equipment as called cable finder

(CAT), the cable finder consists of two parts. Those are one hand locater and signal

transmitter.

First we select cable end and the signal transmitter is connected the cable end. The signal

transmitter consist two terminals. One terminal is connected to the “good” earth and there

other terminal is connected to the one of conductor of the cable.

We can find the cable layout by using one hand locator. The track of the

line is determined by swiveling the CAT from one side of the line to the other, where by

the instrument is carried crosswise to the track of the line. Both visual and acoustic

indications reach a maximum directly over the line. In this way the track can be selected

continuously.

25

Page 26: Ceb Report

Surge (Thumber) Method

This method consists if using a charge capacitor to transmit high-energy pulse

between the conductor and ground. The pulses creates an arc at the fault, which in turn

heats the surrounding air, and the energy is released as an audible thump. The fault

location can be found by listening to the acoustical thump or by tracing the magnetic field

generated by the air. The surge source is a capacitate discharge circuit consisting of

power supply, capacitor bank and high voltage switch. The surge signal can be detected

by means of a magnetic loop antenna, a microphone, an earth gradient detector, or a

seismic transducer.

3.9 LAYING OF UNDERGROUD CABLES

The reliability of underground cable network depends to a considerable extent

upon the proper laying and attachment of fittings. There are three main methods of laying

underground cables.

Direct laying

Draw in system

Solid system

Direct laying

This method of laying underground cables is simple and cheap and is much

favored in modern practice. In this method, a trench of about 1.5 m deep and 45 cm wide

is dug. The trench is covered with a layer of fine sand bed. The sand prevents the enter of

moisture from the ground and thus protects the cable from decay. After the cable has been

laid in the trench, it is covered with another layer of sand of about 10 cm thickness. The

trench is then covered with bricks and other materials in order to protect the cable from

mechanical injury. When more than one cable is to be laid in the same trench, A

horizontal or vertical inter axis spacing of at least 30 cm is provided in order to reduce the

effect of mutual heating and also to ensure that a fault occurring on one cable does not

damage the adjacent cable.

This method of laying cables is used in open areas where excavation can be done

conveniently and at low cost.

26

Page 27: Ceb Report

Draw-in system

In this method, conduit or duct of glazed stone or cast iron or concrete are laid in

the ground with manholes at suitable positions along the cable route. The cables are then

pulled into position from manholes. Figure shows section through four way underground

duct line. Three of the ducts carry transmission cables and the fourth duct carries relay

protection connection, pilot wires. The distance between the manholes should not be too

long so as to simplify the pulling in of the cables.

This method of cable laying is suitable for congested areas where excavation is

expensive and inconvenient, for once the conduits have been laid, repairs or alterations

can be made without opening the ground. This method is generally used for short length

cable routes such as in workshops, road crossing where frequent digging is costlier or

impossible.

Solid system

In this method of laying, the cable is laid in open pipes or through dug out in earth

along the cable route. The troughing is of cast iron, stoneware, asphaltic compound and

covered over. Cables laid in this method are usually plain lead covered because troughing

affords good mechanical protection.

This method of laying underground cables is rarely used now a days. Because it is

more expensive than direct laying system & due to poor heat dissipation facilities, the

current carrying capacity of the cable is reduced.

27

Page 28: Ceb Report

4.1 INTRODUCTION

The Present day Electrical power system is Generated, transmitted and

distributed in the form of alternating current. The electric power is produced at the power

stations which are located quite away from the consumers. It is delivered to the

consumers through a large network of transmission and distribution. Substation is the

assembly of apparatus with use to transform the electrical characteristic from one form to

another. Near the consumer localities, the voltage may have to be stepped down to

utilization level. This job is done by sub stations.

Kolonnawa Stanley substation had four switchyards. There are 33kv, 66kv, 132kv

and 11kv. 11kvswitchyard is indoor switchyard and other three are out door switchyards.

But these outdoor switchyards converted to the indoor substation and gas insulation

substation (GIS). It has two switchyards. Those are 33kv and 132kv.

4.2 TYPES OF SUBSTATIONS ACCORDING TO SERVICE

REQUIREMENT.

Transformer sub-stations

Switching sub-stations

Power factor correction sub-stations

Frequency changer sub-stations

Converting sub stations

28

Page 29: Ceb Report

Industrial sub-stations

Transformer substations

Those sub stations which change the voltage level of electric supply are called as

transformer substations. These substations receive power at some voltage and deliver it at

some other voltage. Transformer is the main component in such substations.

Switching substations

These substations do not change the voltage level. There for incoming and

outgoing lines have the same voltage. They simply perform the switching operations of

power lines.

Power factor correction substations

Those sub stations which improve the power factor of the system are called power

factor correction substations. Such substations are generally located at the receiving end

of transmission lines.

Frequency changer substations

Those substations which change the supply frequency are known as frequency

changer substation. Such a frequency change may be required for industrial utilization.

Converting substations

These substations which change a.c power into d.c power are called converting

sub stations. These substations recive a.c power and convert it into d.c power with

suitable apparatus to supply for such purpose as electroplating, electric welding etc.

Industrial sub stations.

29

Page 30: Ceb Report

Those substations which supply power to individual industrial concern are known

as industrial sub stations.

4.3 TYPES OF SUBSTATIONS ACCORDING TO

CONSTRUCTIONAL FEATURES.

Pole mounted substation

Out door substation

Indoor substation

Underground substation

4.4 SWITCHYARD EQUIPMENT

Isolators

Isolators are the disconnectors. There are two types according to operating

mechanism.

Manual (spring loaded)

Motor controlled

After closing the isolator physically checking is required. (If possible). Also

isolators can categorized in two parts there are single operated and ganged operated (3

phase together)

Circuit breakers

Mainly circuit breakers are used for protection of equipment in a grid substation.

Also it is avoided over current faults and earth faults. Circuit breaker should be defiantly

placed in between two isolators. When close the circuit breaker first the isolators must be

disconnected.

Operating principle

A circuit breaker essentially consists of fixed and moving contacts, called

electrodes. Under normal operating conditions, these contacts remain closed and will not

open automatically until and unless the system becomes faulty. The contacts can be

opened manually or by remote control whenever desired, When a fault occurs on any part

30

Page 31: Ceb Report

of the system, the trip coils of the circuit breaker get energized and the moving contacts

are pulled apart by some mechanism, thus opening the circuit.

When the contacts of a circuit breaker are separated under fault conditions, an arc

is struck between them. Therefore, the main problem in a circuit breaker is to extinguish

the arc within the shortest possible time so that heat generated by it may not reach a

dangerous value.

Methods of arc extinction

There are two methods of extinguishing the arc in circuit breakers.

High resistance method

Low resistance or current zero method

High resistance method

The resistance of the arc may be increased by,

(i) Lengthening the arc

The resistance of the arc is directly proportional to its length. The length of the

arc can be increased by increasing the gap between contacts.

(ii) Cooling the arc

Cooling helps in the deionisation of the medium between contacts. This increase

the arc resistance. Efficient cooling may be obtained by a gas blasted direct along the arc.

(iv)Splitting the arc

The resistance of the arc can be increased by splitting the arc into a number of

smaller arcs in series. Each one of these arc experiences the effect of lengthen and

cooling. The arc may be split by introducing some conducting plates between

the contacts.

Low resistance method

This method is employed for arc extinction in a.c circuits only. In this method, arc

resistance is kept low until current is zero where the arc extinguishes naturally and is

prevented from restriking in spite of the rising voltage across the contacts. There are

several ways of classifying the circuit breakers.

31

Page 32: Ceb Report

Circuit breakers are divided in to three types according to operating mechanism.

There are;

Mechanical (spring chargeable)

This is two types. Spring is charge manually and spring is charge by using motor.

Pneumatic

Hydraulic

Also circuit breakers are classified in to parts according to arc extinguishing

medium. There are; oil circuit breakers, SF6 gas breakers, air breakers.

4.5 OIL CIRCUIT BREAKERS

In such circuit breakers, some insulating oil is used as an arc quenching medium.

The contacts are opened under oil and an arc is struck between them. The heat of the

evaporates the surrounding oil and dissociates it in to a substantial volume of gaseous

hydrogen at high pressure. The hydrogen gas occupies a volume about one thousand

times that of the oil decomposed. The oil is there for pushed away from the arc and an

expanding hydrogen gas bubble surrounding the arc region and adjacent portions of the

contacts as shown in the figure.

The advantages of oil as an arc quenching medium are;

It absorbs the arc energy to decompose the oil into gases which have excellent

cooling properties.

It acts as an insulator and permits smaller clearance between live conductors and

earthed components.

The surrounding oil presents cooling surface in close proximity to the arc.

The disadvantages of oil as an arc quenching medium are;

It is inflammable and there is a risk of a fire

It may form an explosive mixture with air

The arcing products remain in the oil and its quality deteriorates with successive

operations. This necessitates periodic checking and replacement of oil.

32

Page 33: Ceb Report

The breaking unit consists of braking chamber, top cap and mechanism housing. The

unit is hermetically sealed, filled with oil and nitrogen. The breaker chamber contains an

inner support cylinder, manufactured of glass fiber reinforced epoxy resin and

constituting a consolidating and pressure absorbing element. The cylinder is housed in an

outer porcelain insulator. The active elements are the upper terminal, the fixed contact,

the extinguishing chamber, the moving contact, the rolling contacts and lower terminal.

The contact unit consists of the fixed sleeve contact and the moving plug

contact/The contact material is silver plated copper. Those parts of the contacts, which are

exposed to arcs during the breaking, which reduces, contact bum to a minimum.

The top cap is made of welded steel and constitution the expansion chamber

for the gases, which develop when high current are interrupted. It also houses the gas

cushion providing the permanent overpressure, which ensures restrike free interruption of

capacitive current. A magnetic oil level indicator and a pressure gauge shown oil level

and internal readings are clearly visible from ground level. A control valve maintains the

overpressure within the permissible limits.

The mechanism housing is a light alloy casting and contains the actuating

mechanism for the moving contact. It is furnished with an oil drain cock. The operating

force is transmitted via the link gear and operating insulator to the rectilinear motion

mechanism and further to the contact unit.

SF6 CIRCUIT BREAKERS

The most used gas circuit breakers are SF 6 gas circuit breaker. In such

breakers, sulphur hexafluoride (SF6) gas is used as the arc-quenching medium. The SF6 is

an electro negative gas and has a strong tendency to absorb free electron. The contacts of

the breaker are opened in a high-pressure flow of sf6 gas and an arc is stuck between

them. The sf6 circuit breakers have been found to be very effective for high power and

high voltage service.

4.6 CIRCUIT BREAKER TESTING

Gas leakage test

This instrument is used for find gas leakages but this instrument is sensed

only SF6gas .If gas leakage is in any where of pole, instrument detect it and came sound.

33

Page 34: Ceb Report

Dew point test

Temperature of SF6 vapor is measured by dew point instrument. According

to this temperature, moisture amount of SF6 vapor is conformed by a chart. Moisture

particles per mass should be less than 150.

Resistance test

Micrometers are used to measure contact resistance in high voltage breakers,

disconnecting switches (isolators), bus joints, line joints etc. Resistance should be less

than 50 micro ohms.

4.7 INTERLOCKING SYSTEM

First off the isolators between circuit breakers and then can off circuit breaker.

First off the line isolator then can on earth isolator.

This is used castle key system.

Busbar

Bus bars are the hollow circular Cu bars. Basically this bus bar arrangement

is classified in to five parts. There are;

Single

Double

One and half

Ring

Mesh (complicated ring system)

Bus section

Bus section is a breaker which it can connect and disconnect both side of bus bar.

Bus coupler

Bus coupler is the circuit breaker which it can connect and disconnect two bus

bars.

Current transformer

34

Page 35: Ceb Report

An instrument current transformer also called a CT is used to step down a

relatively high current to some lower value for the operation of instruments and isolate

current measuring instruments and relay s from the high voltage line. The primary of the

CT is connected in series with the load circuit and the secondary is connected to the

instruments or relays.

The CT is filled with oil and fine grain quartz sand for mechanical stabilization

and reduction of the oil quantity .The CT is completely sealed and expansion space is

filled with dry nitrogen gas.

Voltage transformer

It is essentially a step down transformer and step down the voltage to a

known ratio. The primary of this transformer consists of a large number of turns of fine

wire connected across the line. The secondary winding consists of a few turns and

provides for measuring instruments and relays a voltage which is known fraction of the

line voltage.

PARTS OF A TRANSFORMER

Conservator

Conservator is a sort of drum, mounted on the top of the transformer. A

level indicator is fixed to it. Conservator is connected through a pipe to the transformer

tank containing oil. This oil expands and contracts’ depending upon the heat produced

and sob the oil level in the conservator rises and falls. Pipes connected to the conservator

is left open to the atmosphere through a breather so that the extra air may go out or come

in.

Breather

Breather is mounted on the top of the conservator tank & it is a small cylindrical

unit containing silica gel to absorb moisture of air entering the conservator tank.

Radiator

35

Page 36: Ceb Report

These are fitted for cooling the transformer oil. The hot oil circulate through these

unit where it becomes cool due to the air touching.

windings

Transformer windings are wound with rectangular, cable paper insulated copper

wires. There are two windings HV side and LV side.

Tap changer

Tap changer is used for on load changing of the voltage ratio. It is a three-

phase unit located in one container, which is placed in the transformer tank.

Each phase regulating winding is located at the star point of HV side of transformer. Tap

changer is controlled from a motor drive unit, fixed to the transformer tank.

Transformer voltage may have to be constantly regulated and it is often very

inconvenient to cut off the power supply each time. On load tap changer solve

such problems, and are being used increasingly as a means of offering better power

supply service as well as for general power receiving purposes.

Tap changer may be classified in to three groups; there are D type, V type

and MS type.

4.8 TRANSFORMER PROTECTION

Buchholz relay

This relay is situated in the pipe connected between the transformer and the

conservator. Relay is a gas actuated relay which is meant for the protection of oil

immersed transformer from insulation failure, core heating or any type of internal fault

which may cause the heating of coil beyond the specified temperature due to this faults

either alarm circuit or the trip circuit operate.

Pressure & relief valve

36

Page 37: Ceb Report

If is the fault condition in transformer a signal is came to relief valve and it

is operated. There fore circuit breaker is tripped.

Temperature meters

Those meters measure oil temperature and winding temperature and meters

are set to fixed temperature when temperature is rise over that settings circuit breakers

tripped.

Arching horns

Arching horns are situated top of the transformer it is protected transformer by

lightings.

Differential

When two or three transformers are parallel, if the tap or impedance differs

from each other, this tripped without alarm.

4.9 OPERATIONS OF TRANSFORMERS

Master follower method

This method is used in substations. One transformer act as a master and

other transformers are followed it. In this case master transformer keep to operate

manually and other one or two transformers act auto mode. If master transformer had a

fault another transformer will be master or transformers will be run individual.

4.10 TRANSFORMER TESTING

Transformer oil testing

The oil is to be tested is poured in to the glass container supply with the

tester. This should be done in a dry day. Because humidity can change the actual reading

that the oil test shows. Oil samples should be taken carefully without opening to the

atmosphere. Applying a voltage across terminals is increased slowly until the sparking

occurred. Now the reading of the indicator is the break down voltage of the insulating oil.

This is done several times to obtain average breaking voltage of oil.

We have use two different kinds of oil testers. In one tester we have to

manually increase the voltage apply to it and the final value that the dial shows is the test

37

Page 38: Ceb Report

reading. And the other tester voltage is automatically increased by it self and it shows the

voltage that the sparking occurs.

Meter reading > 30Kv -it is good for breakers

Meter reading > 45Kv -it is good for transformers

After this test, if transformer oil is bad oil refilling or oil filtering.

Vector group test

Normally transformer vector group is represented by this format; DY1 or

DY11. It means;

DY1

delta star angle between primary and secondary=300

Always vector group is in transformer nameplate. Sometimes if vector group is

not showing clearly or nameplate missing we can use this method to check vector group.

Firstly R and r terminals are shorted. Then these voltages are taken.

Rr-0V Yr-409V Br-410V RY-409V

Ry-138V Yy-298V By-298V YB-409V

Rb-138V Yb-430V Bb-299V RB-409V

RN-80V YN-375V BN-315V

Diagram (vector group) was plotted by using those readings.

38

Page 39: Ceb Report

6.1 INTRODUCTION

Medium Voltage maintenance (MVM) branch is responsible for maintaining

33KV distribution system of entire Island. [i.e. both routine maintenance and restoration

of supply after major break down in 33KV lines or primary substations] There are four

sections.

Substation maintenance

Distribution line maintenance

Hot line maintenance

Service primary substations

6.2 EQUIPMENT APPLIED IN OVER HEAD DISTRIBUTION LINE

Overhead distribution lines are generally to faults due to high winds,

lighting, falling tree, bird’s etc. Most faults are transient in nature and the system would

be ready for operation again as soon as the fault has been interrupted by the system

protection. The fault current might have been caused by a falling tree, which falls across

the high voltage line .In many tree will fall off the line again after a circuit breaker has

de-energized line. Alighting stroke will cause the same transient fault; a flash over will

cause a short circuit current to flow, but as soon as this current is interrupted, the system

is back to normal again.

39

Page 40: Ceb Report

Usually majority of the faults recoded in an overhead line system is of a

transient in nature. This is in contrast to a cable network distribution system where most

faults are of a permanent nature.

Expulsion Fuse

A non-current-limiting device interruption the current by the melting of a

fuse element and an arc is drawn inside a gas evolving type. These may be recharged with

limited cost. Interruption principal similar to load –break switch.

Drop Down Lift Over (DDLO)

An expulsion fuses in a holder, arranged in such a way that the expulsion

fuse tube drops out of the electrical circuit when the fuse has operated. These are

commonly used in the CEB distribution network mainly for the protection of distribution

transformers and some cases for sectionalizing spur MV lines.

Air break Switch

A switch device, which is normally, only used as a disconnection, i.e. only

operated in a de energized system. However a very limiting making and breaking and

breaking performance. Contact velocity at making is operator dependent; an arcing horn

may give a high arcing contact velocities at oppugn sufficient for the interruption of load

transformers.

The switch can in most cases be equipped with a load current interrupting

device. Still, the switch has only very limited making performance .In the CEB, the ABS

were installed in area boundaries, interconnection points and on long spur line etc. to

facilitate isolation of section for fault location, maintenance and repair works.

Load Break Switch

The so-called “general purpose” switch is according to standards defined as

follows; mechanical switching device capable of making, carrying the breaking currents

40

Page 41: Ceb Report

under normal. A circuit condition, which may include specified operating overload

conditions, such as those of a short circuit .It may also be capable of as those of a short

circuit. It may be capable to making but not breaking of short circuit current. The load

break switch contains some special arts .One of the interrupter head. It reduces there

formed. When the switch is operate.

Aout Recloser

Auto reclosers are self contaminated devises that make and break the

distribution system under normal at and fault conditions. A basic feature of a recloser is to

reclose immediately once the circuit under which it served breaks due to temporary fault.

Recloser will lock out its operation whenever it senses a permanent fault clears before

lock out, recloser will reset for another cycle of operation.

Before CEB has introduced auto reclosers to the distribution system, only

DDLO’s are provided as the protective devices.

But this needs some one to operate the DDLO in order to isolate the line

from the power supply. Therefore by introducing auto reclosers to distribution system, the

speed of fault clearing has improved and hence which promotes the stability of the power

system. Because of these reasons the concepts of auto reclosers entered as a time and

money saving method [the interruption period becomes less].

The minimum requirement for installing an auto recloser is 100 km 1 MVA.

The reclosers are sensitive for over current, and in modern types sensitive earth faults too.

There are three types of auto reclosers available in medium voltage system in

CEB.

SF6 gas auto recloser

Oil auto recloser

Vacuum auto recloser

McGraw Edison type

These type reclosers are insulated with oil. This is the earliest type of auto

reclosers installed in distribution system by CEB. The major disadvantage of this type is

that its tripping times are fixed and cannot be adjusted at the site. The set time is 2

seconds. And also after some operations the oil contained in the recloser should change.

The faulty level is about 14.1Ka.

41

Page 42: Ceb Report

PMR Dynatrip type

These type reclosers are mainly installed in DERP gantries. Only 33KV

dynatrip model is available in CEB system. They are filled with SF6 gas at normal

pressure.

These reclosers are equipped with following devices;

A closing coil protection system

A control battery supply 12V and 24V battery pack for control circuit and

energized auxiliary closing coil and main trip coil.

Electronic control unit; the settings can be change within a range at 25% to 225%

with 25 % intervals.

Dynatrip reclosers having CT ratio of200/1 is available in CEB .The

advantage of this type is that the recloser s are independent of thee total no of trips can be

set as dead time, reclosing time, auto/non auto switch and earth protection enable /disable.

The major disadvantage of this type is that the possibility to leak SF6 gas if the bushings

are damaged.

PMR Micro type

The following types are available in CEB 33KV CT ratio 300/100/1, 11KV

CT ratio 300/100/1.

The main advantage of this type is;

Micro trip type is programmable and therefore different settings can be given

Availability of memory facility, data for later viewing can be stored. This will

includes the no of tripping occurred, the no of occurred as over current and earth

fault or sensitive earth fault and the percentage of these failures .The only thing is

to maintain the pressure of the gas in side at specified region given in the name

plate.

The tripping period (dead time) for this type when connecting in the

distribution system are selected as follows;

1st tripping operation 0.25 sec.

2nd tripping operation 0.50 sec

3rd tripping operation 1.00 sec

4th tripping operation trip /lockout

42

Page 43: Ceb Report

This type of reclosers is guarantied for 2500 tripping operations without

maintenance. Not like in previous type there is no any possibility to leakage of SF6 gas

under a damage of bushings.

6.3 HOT LINE MAINTANANCE

Hot Line Maintenance includes routine inspection and maintenance in

33kV tower lines all over the country. The purpose of the hot line maintenance is to carry

out the operations without the power being cutoff. This promotes the reliability and the

stability of the system. The main functions of the hot line maintenance are

Inspection and replacement of suspension and pin insulators of the 33kV towers

Replacement of cross arms on poles

To do above functions specially trained sets of people (Gangs) are needed.

There are three gangs and each gang has eight workers. The workers are working with the

live 33KV wires. If there is a small mistake, it will cause damages to their lives. So the

safety precautions shown below are extremely needed.

Always use safety belts and helmets.

Use the appropriate tools

Do maintenance in suitable weather conditions

Always keep the required clearance with the live wire.

6.4 SUBSTATION MAINTANANCE

Substation maintenance is the major functions of this branch are;

Maintaining existing primary substations

43

Page 44: Ceb Report

Building and commissioning new primary substations.

Primary substation is always converted 33KV to 11 KV. Always 33KV side

is in out door and 11 KV side is indoor. There is the normal diagram of primary

substation.

6.5 LINE MAINTANANCE

This section involves in maintenance of 33KV tower lines, routine

maintenance, installation and restoration of air break switch [ABS], load break switch

[LBS] and DDLO, identification of breakdowns, and preventive maintenance of 33KV

network.

5.1 INTRODUCTIOn

The Victoriya Project is one of five major hard works projects being under taken the

accelerated Mahaweliganga Scheme. It is the most upstream of these projects and

develops the hydro potential of a major right bank tributary of the MahaweliGanga,at

Hakuruthale. The Victoriya is SriLanka largest power station. The primary functions of

the project is the generation of electric power but additional irrigation and power benefits

will arise from the improved regulation of river flows at the Randenigala &Rantabe

division Woter way tunnel is 5.8 km ,before the power generating water way has many

main point.

There are 3 machines 71 MW each,(Type vertical axis medium head Francis)

On the first day we reported at the Mahawelli complex office at Ampitiya, and the next

day visited the power station. We were given the training schedule and an explanation

about the power station.

5.2 WATER WAYS

44

Page 45: Ceb Report

We studied about the waterways. It includes Reservoir, Tunnel intake, Tunnel,

Surge shaft, Penstock, Spiral casing, Draft tube and Tailrace.

Dam and reservoir

The dam is constructed as 438 m high with concrete membrane dam across

the reservoir.

Top water level 438 m - MSL

Maximum operation level 370 m - MSL

Tunnel and Penstock

Penstocks is begin in 516 m down from the surge shaft and 60^ angled to the horizontal

axis. The penstock is steel lined.

Length of tunnel 5.8 km

Type linier concrete lined (Steel line at base)

Diameter of penstock 3 m

Surge shaft

The surge tank is a concrete lined, 145 This is situated in 5 km from the

beginning of the tunnel. These are some of the functions of a surge chamber.

When the load on the turbine decreases, the governor closes the gates of turbine,

reducing water supply to the turbine. The excess water at the lower end of the

conduit rushes back to the surge tank and increases its water level.

When load on the turbine increases, additional water is drawn from the surge tank

to meet the increased load requirement. Hence the surge tank acts as a reservoir

during increase of load on the turbine.

The gat in the surge chamber is use to separate low-pressure tunnel and high-

pressure tunnel.

45

Page 46: Ceb Report

Draft Tube

This is the end of the water way . Draft tube divide to 2 part four end s at tail raise with

rectangular opening. The two gates per machine availability insulated draft tube from tail

raise.

Tail Race

The water after having done its usual work in the turbine is discharged to the

tailrace, which may lead it to the same stream or to another one.

5.3 POWER STATION

Main Inlet Valve

Each turbine is protected on the upstream side by a 2.7 m inlet valve of the lattice

blade butterfly type, constructed in cast steel and operated by two double acting oil

operated servo motors is supplied from an air/oil 60 bar hydraulic accumulator which is

charged by an oil pumping set. In the event of power failure, the valve can be closed

using the residual oil pressure in the accumulator. So that the inlet valve does not have to

open against full different at head, an oil operated needed valve is provided as a bypass to

balance the penstock the pressure between the penstock and the spiral casing of the

turbine prior to opening.

spiral casing and guide vanes

Water flows through the spiral casing and is guided 18 guide vanes on to

the 2.25m stainless steel one-piece runner. Each guide vane is connected by links and

levers to a regulating ring which is moved by two hydraulic servo motors .The oil to

move the servomotors is provided by an air/oil receiver and pumping set similar to that

provided for the main inlet valve.

Governor

Each turbine is controlled by an electronic governor taking its speed and

power signals from the generator terminals, with the toothed wheel mounted on the shaft

46

Page 47: Ceb Report

providing signals for the speed relays. The electronic governor cubicle is located on the

turbine floor and transmits instructions electrically to and electro hydraulic actuator

which converts them to oil hydraulic signals to the guide vane servomotors.

Turbine

Water turbines are divided in to two main categories. The impulse type and

reaction type. In the impulse type, water flows out of a nozzle in the form of a jet such

that all the pressure energy is converted in to kinetic energy. This jet hits one of a series

buckets mounted on a runner. Because of the impact, the runner is rotated about the axis.

There for the turbine is called the impulse turbine.

The reaction type turbines works on the principle of reaction. Water enters the turbine at

high pressure and low velocity in the guide passage. Some pressure energy is converted in

to kinetic energy and water then enters the runner and pressure energy is converted in to

kinetic energy. As the water flowing through the runner is accelerated, it creates a

reaction on the runner vane and the runner is rotated.

According to the type of flow of water, the water turbines used as prime

movers in hydroelectric power stations are of four types.

Pelton weel type

This is suitable for high head and low flow plants. Pelton type used above 300m

to 1800 m head.

47

Page 48: Ceb Report

48

Page 49: Ceb Report

Francis type

This is suitable for low to medium head and water flow plants. These type

turbines can be constructed in vertical and horizontal forms. In Kotmale the three

vertical shaft turbines are designed to operate at 375rev/min, and to deliver 90 MW

under a net head of 201.5m.

Spiral case

This is an angular spiral-shaped casing forming the circumference

of the turbine. One end of it is connected to the penstock to receive the

water under pressure from it, and this water is admitted uniformly all over

the circumference of the runner. The cross sectional area of the casing

decreases progressively, as more and more water is diverted on the runner

so that the velocity of the flow is constant. The inner shape of the casing

is cylindrical, Where the stay vanes ring is attached.

The Stay vanes ring

This is a ring with a number of fin-shaped stay vanes welded

between two angular rings. The functions of the stay vanes are,

(i) To guide the water received from the Spiral case at a proper angle

on the movable guide vanes for which their shape is carefully

designed.

(ii) To strengthen the spiral case against the high pressure of the water

passing through it. There for it is rigidly welded to the spiral case.

Guide Vanes

The guide vanes are located between the stay vanes and the

runner.This serves three functions

(i) To receive water from the stay vanes and direct it at proper angles on

the runner vanes

Kaplan type

Low loads due to rotary motion of water in Francis turbine is overcome.

49

Page 50: Ceb Report

5.4 GENERATORS

The three generators are of the vertical shaft, salient rotor type of

construction and are designed for counter clockwise rotation as viewed from above the

unit. Each generator has a rated output of 95MVA at 0.85 power factor with a stator

winding temperature rise of 600c and a maximum continuous output of 95,000 kVA with

a rise of 40c. The generated voltage is 1250 V at 50 Hz and the normal running speed is

333.3 rev/min.

It will be noted that a semi umbrella arrangement has been adopted in which

a combined thrust and guide bearing is mounted below the rotor and a second guide

bearing is located above the rotor. The thrust bearing is designed for a maintain the

maximum load.

The generator stator is enclosed above the machine floor level by a D shaped

sheet steel casing, which completes the air circuit and also forms an integrated design

with the line and neutral terminal cubicles. The ventilating air is circulated by axial fan

mounted at each end of the rotor. These fans are assisted by the natural fan action on the

rotating salient pole s.

Cool air is drawn in at each end of the machine and forced between the poles,

where it flows across the machine air gap into radial ducts formed in the stator core. After

passing through these ducts and cooling the stator winding and core, the hot air passes

through to water cooled air cooler units mounted on the back of the stator frame. The

cooled air is then re circulated to the top and bottom of the machine. The generator slip

ring s and brush gear, together with creep detector unit and a speed signal toothed wheel

are mounted in a separate enclosure located above the casing floor panels for ease of

access and maintenance.

Six combined braking and jacking units are mounted on the bottom

bracket .W hen used as breaks the units are operate by compressed air from the unit break

air compressor and when used as jacks by oil from a portable high pressure pump.

Installed capacity 80.75 MW

Turbine - Type Vertical Francis

Rating 71 MW

Speed 333.3 R.P.M.

50

Page 51: Ceb Report

5.5 PROTECTION OF GENERATORS

The generating units, especially the large ones, are relatively few in number and

higher in individual cost than most other equipments. Therefore it is desirable and

necessary to provide protection to cover the wide range of faults which may occur in the

modern generating plant.

Some of the important faults which may occur on a generator are;

(i) Over voltage

(ii) Over speed

(iii) Stator winding faults

(iv) Unbalanced loading

(v) Stator over voltage

(vi) Loss of excitation

(vii) External faults

5.6 EXITATION

D.C current should be fed to the poles to excite them. Standby battery bank use

for first excitation. Now a days static excitation system is used in which a transformer

brings down the generator voltage to 230 V and thyristors convert it to D.C and feed it to

the rotor .

In Victoriya, excitation system is as follows. When the r.p.m is increased up to

300 the battery supply disconnects and the need voltage is taken from the generator out

put. From the excitation transformer the 415 v out put is step down into 230v and then the

thyristors convert this A.C supply in to D.C. Then it is given to the stator winding through

the field breaker.

51

Page 52: Ceb Report

5.7 CONTROL ROOM

The special room called, control room where all controlling of the plant and

system being done. In controlling room, the main task is to control the system frequency

and it is tried to maintain within the range of (49-51) Hz. The rated frequency is 50 Hz. In

there, all equipments including the protective devices, auxiliary devices being controlled

and inspections are done. There is a computer which being used to locate the faults,

which happened in the past and analyze them. There are so many panel boards, which are

used to indicate the controlling position of the all the equipments. For example if we want

to maintain particular generator first we should indicate it in the board so that it may

make the controller clear idea about the generators, which are in operation. Then it will

help to get idea about total load, which can be handled and the total generating capacity.

2.8 SWITCH YARD

Net work of all controlling backing & distribution equipments are situated at

switch yard. Mainly it consists of transformers, Isolators, Lighting arrestors, CTs, VTs &

several busbars.

Victoriya power Station

On the first day we had to go to the Mahawelli complex office at Ampitiya. On

the second day we went to the power station. We were given a training schedule and we

were to follow that schedule. Studied about the general layout of the power station. We

had the opportunity to attend to a routine maintenance of the generator number 3. For a

routine maintenance they were cleaned and a visual inspection is done. We studied about

the 220KV switchyard and their operations. In the switchyard there were two outgoing

feeders. One feeder is to Randenigala and others are to the . We were able to do Circuit

Breaker MeggerTest& Contact resistance test. There is a Diesel Generator for

Emergency auxiliary supply .

Normally auxiliary supply is taken as follow.33kv Generating voltage is step

down to 415v by using earthing transformer

52

Page 53: Ceb Report

Indoor sub stations

Generally, local substations, which control a large no: of LT feeders are of

indoor type. In these substations usually the primary voltage is 11kV and the secondary is

400/440 volts. Gas insulation substation is the indoor substation. All apparatus are inside

therefore cannot see close or open condition.

There are only two Gas Insulated Sub stations in Sri Lanka. One is in

Kolonnawa And the other is in Kelanitissa. In these sub stations all the apparatus are

computerized and all the readings for voltages and current can be read from the

computers.

Outdoor sub stations

Generally, main substations for primary and secondary transmission are outdoor

type substations for which control 11kV to 132 kV. It is because for such voltages the

clearance between conductors and the space required for switches, circuit breakers and

other equipment become so great that it is not economical to install the equipment indoor.

Pole mounted sub stations

This type of substation is suitable for low rating say ,up to about 100kVA . It

does not require much attention for its operation. It is cheaper in first cost and

maintenance cost is also low. For village electrification work, distributions to small

residential colonies, and medium consumers pole mounted type of substations are most

common.

It consists of H type of structure for the poles at the end of the line. At a

suitable height, a platform of roll steel joint is created for placing transformer. Other

accessories are:

HRC fuse on primary side

Gang operating switch on HT side

Lighting arresters

Switch and fuses for secondary distribution

53

Page 54: Ceb Report

Underground sub stations

In thickly populated areas, the space available for equipment and building

is limited and the cost of land is high. Under such situations, the sub station is created

underground.

generating station to the substations and from substations to the consumer’s premises. So

conductors are made of that material which has;

High electrical conductivity

High tensile strength in order to withstand mechanical stresses

Low cost so that it can be used for long distance

Low specific gravity so that weight per unit volume is small

Following conductors are used for overhead line:

Copper

Aluminium

ACSR (Aluminium Conductor Steel Reinforced)

AAC (All Aluminium Conductor)

ABC ( Arial Bundle conductors)

54

Page 55: Ceb Report

55

Page 56: Ceb Report

4.1 INTRODUCTION

Electric power can be transmitted or distributed either by means of under ground

cables or by overhead lines. The underground cables are rarely used for power

transmission due to two main reasons. Firstly, power is generally transmitted over long

distances to load centers. Obviously, the installation costs for under ground transmission

will be very heavy. Secondly, electric power has to be transmitted at high voltages for

economic reasons. It is very difficult to provide proper insulation to the cables to

withstand such higher pressures. Therefore as a rule, power transmission over long

distances is carried out by using overhead lines. With the growth in power demand and

consequent rise in voltage levels, power transmission by overhead lines has assumed

considerable importance.

An overhead line is subjected to uncertain weather conditions and other

external interferences. This calls for the use of proper mechanical factors of safety in

order to ensure the continuity of operation in the line.

4.2 CONDUCTORS AND THEIR MATERIALS

The purposes of the conductors are to carry the load current from the

CU

From the point of view of conduct and tensile strength copper conductor is used,

but being very costly and requiring to be imported, nowadays, it is not used as conductor

material for overhead lines in our country.

ACSR

Due to low tensile strength, aluminium conductors produce greater sag. This

prohibits their use for larger spans and makes them unsuitable for long distance

56

Page 57: Ceb Report

transmission. In order to increase the tensile strength, the aluminium conductor is rain

forced with a core of galvanized steel wires. In CEB the mostly used conductor is ACSR.

AAC

These are stranded conductors made of aluminium wires. Stranded aluminium

conductors are durable and flexible. Stranded Aluminium conductors are durable and

light. Mainly used of this conductor on low voltage distribution system.

Aluminium has conductivity of 60% that of copper and therefore, for the same

resistance and voltage drop in carrying same current, aluminium conductor has 1.6 times

the cross sectional area of copper. The density of aluminium is 2.7 gm/cc as against that

of 8.89 gm/cc for copper. Taking combined effect of low conductivity and low density of

aluminium into account, the weight of aluminium required for the same resistance of the

line, is nearly half that of copper. This is big advantage in favor of aluminium.

Moreover, the aluminium is cheep and easily available, main drawback of

aluminium is that its ultimate tensile strength is about half that of copper and therefore, it

cannot be used as such for long spans.

ABC

A bundled conductor is made up of two or more stranded ACSR sub conductors

per phase. Bundle conductors are called duplex, triplex etc. With the higher effective

diameter of the bundle conductor the corona inception increases. Bundle conductors are

used for 400 kv lines. The sub conductors are held apart by means of spacers at regular

intervals along the length of line.

57

Page 58: Ceb Report

4.3 MAIN COMPONENTS OF OVERHEAD LINES

An overhead line maybe used to transmit or distribute electric power. The

successful operation of an overhead line depends to a great extent upon the mechanical

design of the line. While constructing an overhead line, it should be ensured that

mechanical strength of the line is such so as to provide against most probable weather

conditions.

58

Page 59: Ceb Report

INSULATORS

The successful operation of an overhead line depends of a considerable

extent upon the proper selection of an insulator. There are several types of insulators but

the most commonly used are pin type, suspension type, strain insulator and shackle

insulator.

Pin insulators

The part section of a pin type insulator is shown in figure 5.1. As the name

suggests the pin type is secured to the cross arm on the pole. There is a groove on the

upper end of the insulator for housing the conductor. The conductor passes through this

groove and is bound by the annealed wire of the same material.

Pin type insulators are used for transmission and distribution of electric

power at voltages up to 33KV.Beyond operating voltage of 33KV, the pin type insulators

become too bulky, and hence uneconomical.

Suspension insulators

The cost of pin type insulator increases rapidly as the working voltage is

increased. Therefore, this type of insulator is not economical beyond 33KV. For high

voltage (>33KV), it is a usual practice to use suspension type insulators shown in figure

5.2. They consist of a number of porcelain discs connected in series by metal link in the

form of a string. The conductor is suspended at the bottom end of this string while the

other end of the string is secured to the cross arm of the tower. Each unit or disc is

designed for low voltage, say 11KV .

The number of discs in series would obviously depend upon the working voltage .For

instance, if the working voltage is 66KV, than six discs in series will be provided on the

string.

Strain insulators

When there is a dead end of the line or there is corner or sharp curve, the line is

subjected to greater tension .In order to relive the line of excessive tension, strain

59

Page 60: Ceb Report

insulators are used for low voltage lines (<11KV), shackle insulators are used as strain

insulators. However, for high voltages transmission lines, strain insulators shown in

figure 5.3. The discs of strain insulators are used in the vertical plane. When the tension

in the lines is exceedingly high, as at long river spans, two or more strings are used in

parallel.

Shackle insulators

Now a days shackle insulators are frequently used for low voltage distribution

lines. Such insulators can be used either in horizontal position or in a vertical position.

They can be directly fixed to the pole with a bolt or to the cross arm. Figure shows a

shackle insulator fixed to the pole. The conductor in the groove is fixed with a soft

binding wire.

LINE SUPPORTS

The supporting structures for overhead line conductors are various types of

poles and towers called “line supports”. In general the line supports should have the

following properties.

High mechanical strength to withstand the weight of conductors and wind loads

etc.

Light in weight without the loss of mechanical strength.

Cheap in cost and economical to maintain

Long life

Easy accessibility of conductors for maintenance

The line supports used for transmission and distribution of electric power are of

various types including wooden poles, RCC poles, steel poles and lattice steel towers .The

choice of supporting structure for a particular case depends upon the line span, cross

sectional area, line voltage, cost and local conditions.

Towers

60

Page 61: Ceb Report

For every great heights and extra high voltage, transmission towers are used.

Various angle iron sections are used to form a close cage to form tower.

Wooden poles

These are light in weight and cheap in comparison with all other types of

poles, made up of modern beam. These are easily affected and spoiled by atmosphere,

rain water, white ant soil, moisture, etc. These are used for temporary works and with

special chemical coating for works of permanent nature.

R.C.C poles

These are made by reinforcing steel rods in concrete slabs of pole shape .The

usual ratio of mixture is 1:1:5:3 for cement, sand, stone rubbles and steel rods

respectively. These poles are of permanent nature, long life, unaffected by rain sunlight

etc. So are usually used nowadays. Ducts are provided inside the poles section along its

length for,

Drawing cables/wires

To keep its weight less

Steel poles

Steel poles are of L shape, rail type and tubular in shape. These poles are

heavy in weight and cheaper than R.C.C poles. Atmospheric moisture, rain etc., affect

these poles hence while using, these poles are always painted or coated with chemicals to

avoid rusting.

4.4 LINE CONSTRUCTION

Selection of route

Following factors should be considered when selecting a line route.

One side of the road is used as far as possible.

Amount of way leave to be cleared shall be minimized.

61

Page 62: Ceb Report

Inconvenience caused to the other services shall be minimized.

Swampy ground and areas liable to flood shall be avoided.

Routes which would involve excavation in rock shall be avoided

The use of taller poles at uplifts shall be avoided and construction of tension

points at uplifts also be avoided.

As far as possible route shall be least expensive to board.

Selection of poles

All poles used in the LV lines should be concrete poles. However wooden

poles may be used in difficult terrain with the recommendation of the chief engineer

(construction) of the province.

8.3 m 100 kg RC poles shall be used for LV lines. However 9m 115 kg poles may be used

to maintain the ground clearances where necessary. 8.3 m 100 kg pre stressed poles also

may use in difficult terrain.

Erection of self-supported 8.3 m 500 kg RC pole may be recommended

where erection of stays and struts is not possible due to ground conditions.

Handling and transportation of concrete pole

Concrete poles for electrical distribution networks are designed to have a

strength in the down line direction at least ¼ the strength in the transverse direction. The

shape of a section through a typical concrete pole easily demonstrates this difference in

strength.

Therefore a pole must be stored, transported, and handled at all times with

its longer axis in the vertical plane to ensure that the resulting forces are always resisted

by the poles stronger direction.

Poles must not be dropped off a truck but lifted by means of crane. Poles should

not be jarred by twisting the cross arm.

During erection the pole should not be allowed to bend on the flat or wide sides,

or to lurch against the side of the hole when it is dropped into place.

62

Page 63: Ceb Report

The poles should be transported on a suitable vehicle supported full length or

with a limited amount of overhang. The poles should be lifted by crane from the

transporter and placed on the ground. They must not be dropped.

Hole digging

The position of the hole is usually indicated by a peg. The hole must be dug

so that as nearly as possible the pole is erected in its correct position. If the peg indicates

the center of the hole it is a good idea to place a temporary peg at a definite distance away

so that it is not disturbed during digging operations .The hole can be excavated either by

hand, or by truck mounted augers.

The depth of the hole is usually made equal to one sixth the length of the pole.

Precautions should be taken to prevent soil subsidence in loose ground or in

close proximity to roadways or buildings. One method taken to prevent soil subsidence is

to support the hole by wood planks and struts similar to cable trench work, but the struts

should be arranged such that they can be removed easily during pole erection.

When it is required to excavate a hole adjacent to an existing pole, temporary

stays should be added on the existing pole prior to excavating.

Foundation design

For the purpose of support foundation design it is convenient to consider

three categories of soil, good, poor and water logged. The allowable ultimate vertical

bearing pressure for each category of soil has a fixed value but lateral soil resistance is

assumed to increase with depth and to be inversely proportional to the width of

bearing surface of the foundation. The inverse relationship has been introduced to take

account of the dimensioning contribution of the boundary effect as the foundation, which

increases.

Foundation types

Where poles have to be erected in wet or swampy locations, special

foundations are required to prevent the pole sinking. Where the conditions are very wet

63

Page 64: Ceb Report

and soft additional outrigger supports must be added bellow the ground surface to prevent

sideways movement of the pole.

A 100 mm layer of concrete is poured in the bottom before erection of pole

and allowed to harden. The cuission is backfilled with concrete. Temporary stays can be

used to support the pole until the concrete has hardened.

Erecting of poles

The preferred method of erection is by cranes of adequate size for the weight

of pole being handled. Traffic wardens should be posted when the crane obstructs the

road and interference with normal traffic flow must be kept to an absolute minimum.

Manual methods of inaccessible to cranes.

Poles should be erected vertically

The face of the narrow side must be aligned with the LV line in straight sections

of the line. This method is applicable to both tension and terminal poles.

Pole should be erected to be bisect the angle at angle points

D brackets, stay clamps and earth damps shall be fixed end to the pole using nut

and bolts at the ground level before erection of the pole.

Facing poles

The fact of a pole is defined as the side of the pole on which the D brackets

are mounted the narrow side of the pole.

In straight sections of the line, the face must be line with the distribution line

Poles should be erected vertical

Back filling of pole pits

The back filling of pole pits and stay pits shall be done with earth or gravel

and well rammed. The filling shall be up to a height not less than 25 cm above ground

level.

64

Page 65: Ceb Report

4.5 installation of stays and struts

When a line changes direction, an additional force is introduced at the angle

pole. This force is the resultant of line tensions acting at the pole .The resultant force tries

to move the top of the pole in the direction that bisect the angle between the wires. These

forces, due to angles, can be considerable. The stays, struts and flying stays shall be fixed

to neutralize the resultant force on the poles.

Number of stays to be used at any particular pole location is designed on the

overturning force acting on the pole. The force acting on the pole depends on the

following factors;

Number of conductors and size of the conductor along with conductor tension.

Length of adjacent spans.

Angle of deviation of the line.

Equipment mounted on the pole.

Geographical position of the pole.

Stay insulators, thimbles and brackets shall be used in all stays. Following

shall be noted in fixing stays and struts.

The angle between pole and the stay wire or strut pole shall not be less than 300

Stay, strut and flying stays should be erected so as to avoid disturbances to

pedestrians or vehicular traffic.

If shall be ensured that the correct side of the ratchet nut faces the ratchet force of

the cross head of the buckle before tighting the stay buckle.

Stay and flying stay wire over a street must not be less than 5.5m from the

ground.

Stay shall be installed conforming to drawing.

In flat terrain poles used for struts and flying stays shall be of the same size as line

poles.

Stay insulator shall be positioned below the level of the lowest current carrying

conductor and not less than 3.7 m above the ground.

Splicing of stay wire shall be done according to drawing. Depth of the pole pit of

the strut pole shall not be less than 800mm.

65

Page 66: Ceb Report

String of conductors

During running out, the cable drum should be securely supported on drum

jacks, with and the axle should be level.

The work areas should have sufficient employees on site to ensure that the

conductors are not damaged by contact with the ground or pole equipment during running

out. Care should be taken to avoid kinking, twisting or abrading the conductor in any

manner. Conductor should not be trampled on, run over by vehicles or dragged over the

ground. Vehicles should not be used to run out conductors.

Special care must be taken when running out conductors near other existing

electrical systems, whether they are alive or not.

4.6 TENSIONING AND BINDING (BARE CONDUCTORS)

All aluminium 7/3.40 mm (fly) and all aluminium 7/4.39mm (wasp)

conductors shall be used for LV lines.

Earth wire no: 8 shall be strung on the top of the pole before stringing the

bare conductors. Conductors shall be strung in vertical formation as per drawings. After

final tension of the conductor LV shackle insulator shall be fixed to the D brackets of the

intermediate poles. Conductors shall be bound to the insulator at each

support using aluminium-binding wire no: 11. Only one mid span joint per conductor

shall be allowed for a shackle point span .All mid span joints shall be compression type.

During stringing of conductors maximum precautions shall be taken to

prevent excessive strain and damage to the conductor. Standard sag and tensions

applicable ton the particular size of conductor shall be maintained.

The conductors shall be tensioned using ratchet pullers and wire grips (come

along clamps) designed to prevent damage to the conductor using tensioning.

4.7 EARTHING ARRENGMENT

Bottom part of the down run of the shackle point and the terminal point shall

be covered using 2m length of 12mm PVC conduit pipe. No: 8 GS wire shall be

connected to the copper clad earth rod using a crimp type tinned copper adaptor at the

66

Page 67: Ceb Report

ground level to ensure a proper connection of the GS wire and the earth rod. Down run

shall be clamped along the pole by stainless steel at three positions.

The earthing rod shall be grounded approximately 500mm away from the base

of pole. The top of the earthing rod shall be approximately 300 mm below finished

ground after installation is completed.

All hardware parts of the pole shall be bridged together and connected to the

earth clamp on the pole top-using no: 8 GS wire.

8.2 TYPES OF ELECTRIC ENERGY METERS

Single phase watt-hour meter

Three phase watt-hour meter

kVA meter

67

Page 68: Ceb Report

kVAr meter

Maximum demand meter

Two rate meter (peak-normal)

Poly phase meter

NAME PLATE OF A SIGLE PHASE METER

10A – base current

40A – the maximum load current

Class 2- accuracy class is 2. i.e. error can be varied +2% to –2%

240 v- rated voltage

50 Hz – frequency

2002- manufactured year

- Some adjustment are there

- Indicate disk rotation

8.3 ELECTRIC ENERGY

The Electric Power Company (PC) supplies electric energy (W) to its

consumers. Although these customers are considered as consumers, the electric energy

delivered to them is only converted into mechanical work, heat or light. The electrical

devices (appliances, machines, motors etc.), which transform electric energy into some

other form to satisfy the needs of the consumers, have, in modern times, become legion.

The consumer turns them on and off at will. Those, which are switched on at

any given moment, constitute the consumer load, as they load the power company’s

supply and distribution network. Although the expression “power” belongs to the power

company’s domain and the expression “load” to that of the consumer, “power” and “load”

are generally interchangeable In order to bill the consumer for the exact amount of energy

supplied to him, the power company measures this energy with an electricity meter.

The magnitude of the load is generally measured in kilowatts (KW). The power

company uses the kilowatt hour (KWh) as the units of measurement for the energy it

supplies to its customers.

68

Page 69: Ceb Report

8.4 MECHANICAL PRINCIPLE

The electricity meter uses on aluminium disc as a rotor. Electromagnetic

forces are produced in this disc. In order to obtain rotation, a torque must drive the disc

the driving torque.

The operating principle of the meter requires that the driving torque be

proportional to the consumer load. As the load becomes larger, the driving torque

constant determines the rate at which driving torque is increased as a function

of the load.

A breaking torque opposes the driving torque. The breaking torque must be

proportional to the meter disc speed. As the disc rotates more rapidly, the breaking torque

is linearly increased. Disc speed is measured in revolution per minute (r/min).

For steady-state equilibrium, i.e. when no other force (no friction) is present,

driving torque is equal and opposed to the braking torque.

Thus, disc speed is proportional to consumer load. As the load becomes

larger, the disc speed is linearly increased. The meter constant (k) determines the ratio:

Disc speed /consumer load = Meter constant (revolutions per kwh = r/kwh)

The meter constant is an important parameter, which is always a shown on the

meter dial plate. Disc revolutions are proportional to the energy. Therefore

Meter constant = disc revolutions /energy

KWh-Display on Register

A register is used to count the disc revolutions. However, the register

should display “KWh” and not disc revolutions.

The register has 6 figure rollers. The figures: 0, 1, 2, 3, 4, 5, 6, 7, 8, 9

(evenly spaced over the roller circumference) are printed on each roller. Only that figure

is displayed, which appears in a small opening of the dial plate.

It is, therefore, possible to count from “000000” to “999999” with this

register. In order to display the measured energy (KWh), and not the disc revolutions, the

disc speed must be geared down according to the meter constant.

69

Page 70: Ceb Report

8.5 MEASUREMENT OF ACTIVE ENERGY

Today, single-phase and three-phase AC distribution networks are

universally used by the power companies to supply electric energy to their consumers.

For the large majority of consumer only the active energy (kilowatt-hours) is measured

and billed.

We shall, therefore, deal only with the active energy meter, and

concentrates on the task it must be perform.

P P

supply Load

70

KWH METER

1 2 3 4

Page 71: Ceb Report

N N

Figure 8.1

Wiring diagram of a single phase meter

8.6 SINGLE-PHASE METER APPLICATION

The description of electrical meter operation is restricted to the measurement of

active energy [KWH] in single-phase network.

However, active energy meters in other networks [e.g. three phase network] are

similar to the single-phase meter in design and operation.

Basically, to measure the active load, the meter must perform the

multiplication operation, voltage X current. As a measure of the quantities to be

multiplied, two magnetic fluxes, voltage flux and current flux, are produced in the

meter .In preparation for the multiplication operation, eddy current s are induced by these

fluxes in the meter disc.

To measure the load, the line voltage and the consumer load current must

be introduced into the meter. The current phase displacement (cos Φ) must also be

measured, in order to produce a driving torque, which is proportional to the active load.

The current is measured by driving it through a coil (the current coil) in

the meter current coil is in series with the consumer load, always in the phase wire.

To measure the voltage a second coil (the voltage coil) in the meter is

connected to the line voltage between the phase wire and the neutral wire.

The ends of the both coils are connected to the terminal block inside the

meter. The cable from the power company and the consumer wiring are connected to the

outside of the terminal box.

71

Page 72: Ceb Report

The phase wire current enters and leaves the meter via the two terminals

[1 and 4]. Two terminals [2 and 3] serve to connect the neutral wire and the voltage coil.

The other end of the voltage coil is connected internally [2] to the current input terminal

[1], which carries phase potential.

A link [called calibration link] serves to separate the voltage circuit from the

Current when the meter is beginning tested and calibrated. The consumer load, i.e. the

power at the metering location, is measured by individual measurement of the voltage (U)

and the current (I).

The consumer load, i.e. the power at the metering location, is measured by

individual measurement of the voltage and the current.

The magnitude of current and voltage and their phase position, i.e. the lag angle of the

current with respect to the voltage, are measured.

8.7 METERING ELEMENT DESIGN

The metering element produces two torques, the driving torque [MD] and

the barking torque [MB], required to measure the electric energy. The metering element

comprises, primarily;

The voltage element

With voltage coil, voltage core and counter -pole

The current element

With current coil and current core

The brake magnet

The meter disc [as rotor]

The voltage element produces a magnetic field, the voltage flux, which

traverses the meter disc [From voltage core to counter-pole].

The current element produces a magnetic field, the current flux that

traverses the meter disc.

The brake magnet produces a magnetic field, the braking flux that

traverses the meter disc.

72

Page 73: Ceb Report

The magnetic fluxes are utilized to produce a driving torque [MD] and a

barking torque [MB] in the meter disc.

Together, the voltage fluxes, representing the voltage and the current

flux, representing the current, act to produce a driving torque (MD) proportional to

consumer load.

The breaking flux is issued to produce a breaking torque (MB) proportional

to the speed of the meter disc.

Induced disk current

Voltages and Currents are induced in all conductors, which move through

a magnetic field. No currents are produced in a stationary meter disc. Only a magnetic

flux, whose magnitude varies, would induce currents in the disc.

As soon as the disc begins to rotate, however eddy currents are induced in

the area, where the braking flux traverses the disc.

The eddy currents flow in closed loops, to both sides of the magnetic flux,

whereby the sense of rotation on one side is opposed to that on the other side.

8.8 TESTING PROCEDURE OF SINGLE PHASE METERS

wiring

- Remove the cover and disconnect the inner voltage link between the current and

voltage terminal.

- Place the meter onto the test bench and connect the wires.

- Check the tightness of accessible screws.

Heating

Pre heat the meters by applying the rated voltage and basic current at 1.0

power factor for approximate 30 minutes.

Quality test

Check the meters by applying the maximum current (40 A ) for approximate 5

minutes.

Full load check

Set the power source to the base current (IB) at 1.0 power factor (unity).

73

Page 74: Ceb Report

Power factor test

Set the power source to the base current (IB) at 0.5 power factor.

Low load test

Set the power source to the rated voltage 0.5% of basic current at 1.0 power factor.

Starting current test

Check that the rotor of the meter rotates and continues to run at the rated voltage,

frequency, 1.0 power factor and 0.5% of the rated current.

74

Page 75: Ceb Report

75

Page 76: Ceb Report

Creep test

With no current in the current circuit, check that the rotor of the meter does not make one

complete revolution when a voltage between 80% and 110% of the rated voltage is

applied.

Dial test

Set the meter to rotate rated speed (420rev/kwh) and check the unit consumption.

Shown in fig: 6.testing report of single-phase meters.

8.9 WIRING OF ENERGY METERS

There are several types of L.T. single phase, three phase (Direct) and

three phase (CT operated) meters in CEB. Hence the wiring methods are also different

from type to type of the meter, especially in CT operated meters.

Wrong wiring of a meter would result a high magnitude error. Therefore it

is very essential to wire the meters correctly. Following steps should be taken when

meters are wired.

Direct Meters

1. Meter should be selected according to the consumer load

2. Meter should be installed vertically

3. Load wire should be connected properly.

CT Operated Meters

1. Meter should be selected according to the consumer load

2. Meter should be installed vertically.

3. CT’s should be inserted correctly (correct direction)

4. CT connection to the meter should be correct.

5. Voltage connection to the meter should be correct.

6. Do not use single strand wire for meter wiring. Always use multi strand wires.

7. Check phase sequence.

8. Terminal cover should be sealed properly after meter connection.

76

Page 77: Ceb Report

Connect to 11th

Terminal

P N

Connect to 11th

terminal

P N

Supply

Wiring Diagram of 3 phase two rate kWh meter GEC with timer(English type)

Figure 8.3

77

P

N

1 2 3 4 5 6 7 8 9 10 11 1212

Timer(English Type)

1 2 3 E 4 56 6

Page 78: Ceb Report

8.9 TIMERS

1.correct wiring of the timer.

2.proper wind up by using the key (when the timer is mechanical one)

3.To set the time turn the dial in direction of arrow until pointer indicates the time of

day at the moment of setting.

4.turn dial one round to the correct side and check whether the solenoid in the timer

operates in set time.

5.Timer also should be sealed properly.

8.10 ELECTRICITY METERING ERROR

The electric meter serves the CEB to measure and bill electrical energy

consumption. It is essential that the meter reading represent, with the smallest possible

deviation, the true value of the energy supplied to the consumer. All disturbance factors,

which can cause metering errors, must be recognized and attended to.

Metering error=actual value-nominal value

nominal value

where,

Actual value=the result of the measurement as indicated by the measuring device

Nominal value=the true value of the measured

On the first day we had the chance to dismantle a kWh meter and to identify various parts

and to reconnect. Then an idea about the basic procedure of a meter testing was taken.

Also we had the chance to study about the causes and methods of meter repairing.

CT testing procedure was observed.

78

Page 79: Ceb Report

79

Page 80: Ceb Report

9.1 INTRODUCTION

Lift has been an essential component in modern multi storied buildings.

It makes easy for passengers and it is economically worth and it save most of the time

that takes to travel up and down of a building.

All the Lifts in the Government Buildings are maintain by the lift branch.

9.2 MAIN PARTS OF A LIFT

Lift well

In most buildings lift well is situated near the main entrance. Lift well is created

to cover machinery and open space to present a smooth finished surface for passenger

protection. The area of the well depend on the size and number of the cars, and by the

disposition of the car and landing entrance. The necessary clearance for the car and

counter weight is also determine when creating the lift well.

Car and the two door system

There is a door provided for the car extending the full height and width of the car

opening and Another door is provided at all landing openings. When the lift reaches to a

floor these two doors open together. These are provided for the protection of the

passengers.

Counter weight

The object of the counter weight is to provide traction and to balance the weight

of the car. Incidentally the counter weight provides a certain measure of safety when

landing on its buffer and removing traction from the car. This is made up of cast iron

sections firmly secured against movement by at least two steel tie rod having lock nuts or

split pins at each end and passing through each section.

Car traveling cable

This is made by means of multi core hanging flexible cable, one end is connected

to a terminal box fitted under the car floor. The other to a terminal box fitted in the well at

approximately the mid position to remove any twist in the cable.

80

Page 81: Ceb Report

Machine room

This is at the top of the well and it consists of driving motor, break, gearing and

the control panel.

9.3 THE OPERATING MECHANISM OF LIFTS

There are mainly two types of roping system in lifts. Those are

(i) 2 x 2 system

(ii) 2 x 1 system

In first type there are four or six ropes as sown in the figure. There is a spring connected

to one end of the cable. So that if there is a break in any rope the spring get release and it

operate a switch for emergency stop. In the Second type The one end of the rope is

connected to the car and the other to the counter weight.

Over load alarm

Modern lifts are made to give maximum protection to the passengers. There are

four springs which acts as resistors and those are connected according to the principle of

vinston bridge.

If R1 R3

R2 R4

The voltage between Point A & B is zero.

If the lift is over load the ratio get unbalance & there will be a voltage difference at point

a& B. This makes an alarm to operate.

Read contactor

This is use to stop the lift at a floor. Normally it is in close position because of the

Magnetic field of the magnet in the floor level. When The lift reaches in between of the

read contactor and the magnet The magnetic field breaks and the contactor open and the

lift stop at the floor.

81

Page 82: Ceb Report

10.1 INTRODUCTION

In Western Province There are five area offices as follows. Kelaniya, Ja-Ela,

Gampha, Negambo and Veyangoda. Under Kelaniya area office there are three Consumer

Service Centers. Those are Delgoda, Mavaramandiya andKirillawala.

We were at the Kelaniya area office for three week. During that period, we were

asked to go to the Mawaramandiya depot for One week, to Area Maintenance Branch

Kiribathgoda for One week and one week at the area office.

Kelaniya depot is responsible for billing, new connections, disconnections

Maintain the low voltage lines and Take actions for consumer complains.

The main function of an area office is making bills. There are meter readers and they

take the reading and the billing part is done by the area office. Electricity bill chargings

are different from each other according to the purpose of the building. Tariff is the rate at

which electrical energy is supplied to a consumer. There are five main types.

1. Domestic tariff

2. Tariff applicable to religious premises and charitable institutions

3. Tariff applicable for bulk sales to Lanka Electricity Company (pvt)Limited.

4. General purpose Tariff

5. Industrial Tariff.

10.2 MAVARAMANDIYA CONSUMER SERVICE CENTER

At mavaramandiya depot we identified some equipments and units used in power

distribution. Main activities of the Consumer Service Center are

1. Give new service connections

2. Service maintenance of H.T Lines & L.T Lines

3. 24 hours breakdown service

10.3 TYPES OF SERVICE CONNECTIONS1. Single phase - 30 A only

2. Three phase - 30 A & 60 A

82

Page 83: Ceb Report

83

Page 84: Ceb Report

1. Giving new connections

There are four steps to follow when giving new connection

1. Receiving an application

2. Estimation

3. Payment

4. Giving connection

Connections are giving according to the regulations.

2.Service maintenance

Replacement of Service wires, meters, Meter boxes

3.Bulk supply connections

There are two types of bulk consumers.

1. L.T Bulk consumers

2. H.T Bulk consumers

L.T bulk supply is given using a L.T transformer. Consumption is measured

through KWH meters and KVh meters, using CTs .

H.T bulk connection is given through a CT/PT transformer. Consumption is

measured by using CT/PT. H.T bulk supply is given in 11 KV or 33KV.

4. Maintenance of H.T & L.T lines

The depot with the assistance of Area Maintenance Unit does both H.T & L.T

Line Maintenance.

5. Break down service

Break downs occur at both H.T & L.T lines and bulk supply connection are

reported to the depot break down section. There is a 24 hour break down service to attend

to the service.

10.4 AREA MAINTENANCE UNIT

We were able to study about cable Joints, Sub stations, Auto reclosers,

Breakers, Insulators,……….etc. The duties of this unit is to maintain the overhead

lines in Kelaniya area, take actions for customer complains and requests……etc.

84

Page 85: Ceb Report

10.5 CLEARANCES

When laying a voltage line we must keep particular distance between conductors, and

high enough from ground. It is always pre calculated value, mainly depend on line

voltage.

Clearances between low voltage bear/aerial bundled conductor

Across the road or street 5.5 m

In any other plane 4.9 m

Clearances above

Voltage exceeding 650 V & below 11 KV

Across the road street 6.1 m

In any other plane 5.2 m

Place in accessible to vehicular traffic 4.6 m

Voltage exceeding 11 KV & below 33 KV

Across the road street 6.1 m

In any other plane 5.2 m

Place in accessible to vehicular traffic 4.6 m

Clearances between other conductors

Conductors of same circuit

Over head line conductors must have following clearances from other

conductors of same circuit.

low voltage 0.2 m 0.3 m

11 kV 7.0 m 0.6 m

33 kV 6.7 m 0.9 m

circuit voltage clearance

low voltage & 11 kV 0.2 m

85

Page 86: Ceb Report

low voltage & 33 kV 0.5 m

33 kV & 11 kV 0.9 m

11 kV & 11kV 0.9 m

33 kV & 33 kV 0.2 m

Bare conductors of different circuit on the same supports.

The medium voltage circuits & the vertical clearances between conductors of the

different circuits at any point of the support under normal working conditions

shall not be less then specified below;

Horizontal spacing between different circuit.

The horizontal spacing between different shall not be less than specified

below.

circuit voltage clearance

low voltage & 11 kV 1.2 m

low voltage & 33 kV 1.5 m

33 kV & 11 kV 1.2 m

11 kV & 11kV 0.9 m

33 kV & 33 kV 1.2 m

Safety clearances

To ensure personnel safety, the following maximum safety clearances shall be

maintained.

Medium voltage bare conductors

Any part of human body 0.8 m

Any construction building 5.0 m

Low voltage bare conductors

Any part of human body 0.15

86

Page 87: Ceb Report

Location of poles

Poles are located so as to provide a easy access for maintenance works. some compromise

may also be needed to ensure that poles located on corners and drive way will not unduly

obstruct vehicular traffic maximum pole spacing are :

Pole height Along the road Across the road

MV on 11m pole 70m 35m

MV on 30m pole 70m 35m

10m pole only be used with maximum span of 80m, when runs across country.

The distance between shackle poles are not exceed either of following.

Pole height Distance between two

adjacent poles

Maximum number of poles

MV 12m 560m 07

MV 11m 490m 07

MV 11m 490m 07

87

Page 88: Ceb Report

11.1 INTRODUCTION

Demand side management activities are those involve action on the demand

side of the electric meter either directly caused or indirectly simulated by the utility.

DSM branch of CEB provides a range of services to industrial and

commercial electricity consumers. Features of some DSM services are described below.

Energy audit : an analysis of energy consumption patterns and measures available

to reduce monthly energy cost.

Pre construction consultancy services :an overview of technical drawings and

recommendations based on energy efficiency.

Power quality analyzing :an analysis of voltage, power, harmonic variations and

measures available to suppress harmonic and improve voltage quality.

Lighting design :professional lighting design for buildings

Implementation monitoring and testing :monitoring and testing of implementation

of DSM recommendations based on energy audits to verify the saving potential

and testing on customers request.

Customer education programs

11.2 MODERN EQUIPMENT AND SOFTWARE

It is necessary to use various types of modern equipment and software in the

Demand Side Management branch when giving the several services specially to their

industrial and commercial customers. Those are;

1. Power analyzer

2. Recording poly phase power meter (Data logger) with software

3. Flue gas analyzer

4. Light meter

5. Infra Red thermometer

6. Digital thermometer / humidity meter

7. Energy balance software

8. Photo/ Contact tacho meter

9. Power quality analyzer

88

Page 89: Ceb Report

1. Power analyzer

Power analyzer is mainly used for getting any reading of consumed electricity.

According to the customer’s required, when gives the service like energy audit we

must used the power analyzer. By using current transformers and other component it

must be connected to the supply and can get readings.

2. Data Logger

Also data logger is act as the power analyzer. By using data logger we can

record the data of the supply within number of days as required. After setting the data

logger to the supply, it can be recorded any data and after required days, it must be

down loaded and disconnect from the electricity supply.

The comparison between power analyzer and data logger

Power analyzer Data logger

Can record the harmonics Can’t recorded harmonics, only can seen

Need external power supply Not need external power supply

Memory capacity is less Memory capacity is high

All data were recorded Recorded only the selected data

3. Flue gas analyzer

Mainly it is used for measuring the combustion efficiency of the boilers.

Inserting the flue gas analyzer in to the chimney and can get the measurement of

content of gases like CO2, CO in air as a percentage.

4. Light meter

By using this we can measure the amount of light rays in unit of “ Lux “ in

any required area.

5. Infra red thermometer

In the places or equipment that we can’t reach like boilers, used this for

measuring the temperature. By using the beam of red light rays, it can be detected the

temperature of element.

89

Page 90: Ceb Report

6. Digital thermometer

By using this can be measure the temperature of any thing like water, ice…

7. Photo/ contact tachometer

For measuring the RPM value of any rotating device like motor shaft the

tachometer is used. If the meter cannot touch that surface can use the photo sensor

method.

8. Power quality analyzer

Its action is same as the action of power analyzer. But it can’t save data and

we can see the data at the required time.

11.2 DSM OBJECTIVES

DSM activities are broadly categorized under the headings such as

load management

strategic conservation

electrification ,

strategic growth.

Those objectives are intended to achieve by,

Peak clipping generally involves reduction of load during peak hours(for Srilanka

system peak is experienced from 6.00 to 9.00 p.m.) to defer the need to install new

capacity by reducing the peak demand. Peak clipping will also reduce the energy

requirement, thus saving on expensive fuels.

Peak reduction can be achieved through the use of more efficient end-use equipment or

direct utility control of end-use equipment as well as time-of-use and interruptible tariffs

For example effective use of efficient lights such as compact fluorescent lamps can

substantially reduce the peak load.

90

Page 91: Ceb Report

Peak Clipping Valley Filling

figure 11.1 figurer 11.2

LOAD SHIFTING STRATEGIC CONSERVATION

figure 11.3 figure 11.4

FLEXIBLE LOAD SHAPE

figure 11.5

91

Page 92: Ceb Report

Valley Filling

Valley filling essentially includes building off-peak loads resulting in an increase in the

total energy consumption with no increase in the peak load. This is applicable for utilities

with low cost plants running on low load factors.

In the case of Srilanka, for example railway electrification can successfully achieve high

utilization of inexpensive plants in the system during off-peak hours.

Load Shifting

Load shifting can be viewed as a combination of peak clipping and valley filling.

Consumers are encouraged to reduce consumption during the peak hours by shifting their

consumption from peak to off-peak hours.

Some industrial consumers whose consumption can be shifted to off-peak hours with

minimum disturbance can take advantage of load shifting .

This is achieved mostly through introduction of two-part (time-of-use) tariffs. Other

methods such as direct load control and thermal energy storage can also be used .

Strategic Conservation

Strategic conservation targets selected applications for energy conservation .Reduction of

electricity consumption mostly through efficient use of end-use equipment, will generally

cause a downward shift in the load curve. The reduction in the peak demand will be

determined by the coincidence factor.

Flexible Load Shape

Some customers may be willing to trade reliability for some incentive such as reduced

rates. Utilities are then able to make some adjustments to the load shape according to their

operating needs. Utilities (by offering a choice of reliability) can effectively reduce the

necessity for adding peaking plants.

92

Page 93: Ceb Report

11.3 Activities of DSM

Customer education

Energy survey/ audits

Seminars

Workshops

Promotional programs

Publicity programs

Introduce DSM programs

Provide direct incentives and other financial options for customer to adopt DSM

measures

Low interest loans

Cash grants

Subsidised installation

Rebates

Promote the manufacture of energy efficient appliances and equipment.

Set efficiency standards for electrical machinery /equipment /appliances(co-

ordinate with SLS)

Proposals to GOSL on taxes /tariffs to promote the use of energy efficient

appliances.

BENEFITS FROM DSM PROGRAMS

Customer

Reduced electricity bills.

Utility incentives.

Utility

Avoided supply cost.

Reduced demand.

The DSM branch identifies the customer segments as follows;

Retail sector (Domestic customers, Small Industry, Small commercial buildings)

Industry sector

Hotel and large commercial buildings sector

93

Page 94: Ceb Report

From the figure we can see that that the most electricity consumption is taken by the

industrial sector and the retail sector is the least contributor to the electric power

consumption.

11.5 ENERGY EFFICIENCY

Energy efficiency measures available for domestic customers

Efficiency lighting.

Efficient refrigerators

Good house keeping.

ENERGY EFFICIENCY MEASURES AVAILABLE FOR INDUSTRIES

Energy audits/surveys

Efficient motors

Power factor correction

Efficient lighting.

Load management.

Fuel switching.

Captive generation.

Efficiency A/C and ventilation system.

Efficient boilers and steam distribution system.

ENERGY EFFICIENCY MEASURES AVAILABLE FOR HOTELS/ BUILDINGS.

Energy audits/surveys

Power factor correction

Efficient lighting.

Load management.

Fuel switching.

Captive generation.

Efficiency A/C and ventilation system.

94

Page 95: Ceb Report

Energy Audit

The main service provided by DSM to industrial and commercial customers is

conducting “Energy Audit” programs.

Energy audit is an analysis of your energy consumption pattern. In addition it,

provides an array of recommendations on the measures available to reduce the

monthly energy costs. The fees on energy audit based on the contract demand.

The energy audit involves the following major functions

Power quality analysis

The voltage, power ,harmonic variations are analysed, and measures are

recommended to suppress undesirable harmonics and to improve the voltage.

Energy management programs

Conduction of employee education programs

Load research services

Pre construction consultancy services

Make recommendations for energy efficiency improvements.

System monitoring

Lighting designs

Energy efficiency building code

Applicable for new commercial buildings of more than 4 storied

Covers lighting ,ventilation and air conditioning ,building envelope ,electrical power and

distribution, and service water heating.

11.6 ENERGY EFFICIENCY BUILDING CODE (EEBC)

Purpose

Reduce energy consumption of new buildings by 40%.

Reduce energy consumption of existing building by 20%.

This is used for commercial buildings only. Initial requirements of this;

Four stories or higher

Floor area of 2000m2 or greater

95

Page 96: Ceb Report

Energy efficiency lighting

Maximum allowable power

Power credit for lighting controls

Recommended light levels

Equipment efficiency levels

Energy efficiency ventilation and airconditing

Efficient A/C system design

Equipment efficiency levels

Commissioning and testing

Maintenance

Water treatment

Building structure

Building orientation

Wall construction to reduce heat gain

Window design and selection of glass to reduce heat gain

Air leakages

Electrical power and distribution

Equipment efficiency

Internal distribution requirements

Motor rewinding

11.7 ENERGY LABELING

CEB in association with the SLSI & ECF has decided to implement energy labeling

program on a voluntary basis.

Main Objectives of the program is to promote use of energy efficient electrical items to

save energy.

The purpose of energy labels

- To provide information to consumers regarding the energy efficiency of products

- To encourage consumers to buy the most energy-efficient appliances

96

Page 97: Ceb Report

Main components of energy labelingFigure 11.6

Figure 11.7

97

Standards Labeling

Testing Facilities

Testing Procedures

Evaluation

Monitoring & Enforcement

Page 98: Ceb Report

How does energy labels work?

- Influences consumer purchase decisions

- Influences manufacturer production and marketing

(More stars means more energy efficient)

Watt loss Star rating

loss <4 W * * * * *

4 W < loss < 6 W * * * *

6 W < loss < 8 W * * *

8 W < loss < 10 W * *

10 W < loss < 12 W *

loss > 12 W no stars

11.8 ENERGY AUDIT

An energy audit is a systematic gathering and evaluation of energy data about

a plant/process, for the purpose of promoting energy efficiency.

COMPONENTS OF AN ENERGY AUDIT

Pre audit consultation

Site analysis and data logging including metering

Preparation of report

AUDIT PROCEDURE

Customer request

Information to customer

Analysis of historical data

Customer interview/ incoming electricity supply logging

Sub section data logging

Data collection

Analysis of data

Preparation of energy balance

Identification of energy efficiency measures

Preparation Of costs/benefits

98

Page 99: Ceb Report

Formulate recommendations

Preparation of audit report

Prepare monitoring schedules

Presentation of report

11.9 POWER FACTOR CORRECTION

Power factor (PF) is given by the ratio of useful current to the total current; it

is also the ratio of useful power expressed in kW to total power expressed in kilowatt

amperes (kVA). Power factor is usually expressed as a decimal number or a percentage.

PF = Useful power (kW)/Total power (kVA)

11.10 FUNCTION OF CAPACITORS

Electrical used by industrial plants consists of two major components:

Real power (generally expressed in kilowatt) that produces useful work ranging

from providing motive power to industrial machinery to lighting a single bulb in

one’s home.

Reactive power (generally expressed in kilovar), necessary to generate magnetic

fields to operate electrical machinery.

Inductive electrical equipment such as motors and transformers draw their

reactive power requirements from the electricity distribution system to which they are

connected.

The ratio of useful power to total power is called the power factor. When

equipment has a low power factor, it will require a relatively large amount of reactive

power. The power factor correction capacitors essentially provide the necessary reactive

power requirements from the electricity distribution system

99

Page 100: Ceb Report

11.12 TYPES AND SELECTION OF CAPACITORS

The load in typical industrial installation changes virtually every instance. As a

result, the amount of kVAr to be provided externally to maintain a desired power factor

also changes with the changing kW demand. Although it may be technically possible to

provide the correct amount of kVAr in other words, to follow the load curve so as to

maintain a fixed power factor, it is generally uneconomical to do so.

Fixed capacitors: Power factor correction capacitors are commercially

manufactured to provide a fixed quantity of reactive power (5kVAr, 10kVAr, 50kVAr,

etc). In some situations, installing a fixed capacitor may suffice to improve the power

factor to an adequate level. For example, fixed capacitors are often recommended for

individual machines such as motors or installations exhibiting relatively steady demands.

One should, however, exercise caution in selecting the correct rating of fixed capacitors

as a higher rating than necessary (over compensation0 could lead to problems.

Automatic capacitor banks: In some situations, fixed capacitors may not provide

the necessary correction. A bank of capacitors with the facility to “sense” the reactive

power demand and provide the right amount of reactive power demand and provide the

right amount of reactive power (by connecting the required number of capacitors) is more

appropriate in such situations. This method, obviously, is more expensive than installing

fixed capacitors as additional switching circuits are involved. Switched capacitor banks,

however, are superior in performance as they could “follow” the load curve closely

(provided capacitor selection is done carefully).

FACTORS THAT AFFECT THE ELECTRICITY BILL

The energy charge number of units used during the billing period in kilowatt

hours (kWh);

Demand charge this charge compensates the utility for the capital investment

required to serve the plant’s peak load. Demand charge can be a large portion of

the total electricity bill. Demand charge can be reducing by smoothing out the

peaks. This charge usually involved power factor or kVAr.

100

Page 101: Ceb Report

101

Page 102: Ceb Report

11.13 LOAD RESEARCH PROJECT

Load research is primarily aimed at analyzing and understanding the utility’s

system load profile. This entails breakdown of the system load profile into various sub

components. Therefore, the main objectives of the load research can be identified as

follows:

To develop shapes at the system, regional, and customer sector level

To develop shapes database by major end uses within customer sectors.

It will be evident that these objectives are quite flexible to accommodate any

sub system of the main network and to analyse any sub categories of end uses.

Load research may either be conducted by starting from customer end use to

build and develop the total system load shape or by starting form the total system load

shape and breaking it down to customer end use .it may well be a combination of the

two.

Both approach require primary and secondary data collection and are

generally accomplish through a combination of the following data collection methods:

Metering

Market survey

Statical methods

Using engineering models

By analyzing other data

Substation log book data

System control data

Sales and billing data

Fig: 11.8 Shows the conceptual approach that was used in the load research

of the CEB system. It has used the bottom-up approach, with a combination of data

collection by metering, customer surveys and using other recorded load data.

RESULTS

Final results of the load research project consisted of the following load

profiles and the associated data for the CEB network.

102

Page 103: Ceb Report

1. CEB system

2. Provincial load profiles

3. System load profiles by sectors

4. Domestic sector by segments

5. End use load profiles

Domestic

Domestic (by lighting technology)

Small commercial and industrial

Industrial and commercial (bulk) customers

11.14 LOAD SHAPE OBJECTIVES

DSM activities in Sri Lanka cannot considered to be an alternative to supply

side options available for power system capacity expansion. But some load shape

objectives of demand side management could effectively complement the supply side

options.

The knowledge available from load research regarding the composition of the

load shape is of valuable to design any of these DSM activities and to forecast their

impacts. Through subsequent load research, i.e. after implementing the DSM measures,

the utility would also be able to evaluate and monitor the impacts of such measures.

11.15 AIR CONDITIONING

INTRODUCTION

Air conditioning is the control the temperature and moisture content of the

occupied space.

103

Page 104: Ceb Report

Figure 11.9

104

Evaporator

Compressor

Discharge lineHot vaporHigh pressure

Suction lineCold vaporLow pressure

Filter

Expansion valve

Liquid line

Page 105: Ceb Report

Evaporation

Liquid Vapor

Condensation

Most air conditioners have their capacity rated in British Thermal Units

(BTU). Generally speaking a BTU is the amount of heat required to raise the temperature

of one found (0.45 kg) of water 1 degree Fahrenheit (0.560C).

11.16 REFRIGERATION CYCLE

An air conditioner is basically a refrigerator without the insulated box. It

uses the evaporation of a refrigerant, like Freon, to provide cooling. The mechanics of the

Freon evaporation cycle are the same in a refrigerator as in an air conditioner.

This is how the evaporation cycle in an air conditioner works.The

compressor compresses cool Freon gas, causing it to become hot, high-pressure Freon

gas. This hot gas runs through a set of coils so it can dissipate its heat, and it condenses

into a liquid. The Freon liquid runs through an expansion valve, and in the process it

evaporates to become cold, low-pressure Freon gas. This cold gas runs through a set of

coils that allow the gas to absorb heat and cool down the air inside the building.

11.17 AIR CONDITIONING SYSTEMS

NON DUCTABLE SYSTEM

This system is categorized in two types. There are window type and split

type.

105

Page 106: Ceb Report

Window type

Normal small size air conditioning plants are available in this form. We can

identify the following parts and assures in this plant, there are compressor, condenser,

evaporator, blower, fan expansion valve and controlling arrangement etc.

Window type plants are available in as a compact set including all

mentioned above. But the unit can be filter, exporter, motor drives fan remote bulb and

refrigerant control. The out side part consists of compressor condenser and motor driven

fan. The two fan driven by the same motor. The condenser cooling system is air-cooling.

Split type

This type air-conditioning plants are available in small and medium size,

which differ from the other parts. This type has several advantages than window type or

package type, which is not noise. Evaporator can be installed very suitable place etc. This

plant consists of air-cooling and water-cooling system.

DUCTABLE SYSTEM

This system is categorized in two types. There are package type and chill

water type.

Package type

This type air conditioning plants available in large sizes , which are better to

use corridors and large halls. Where condensing unit and evaporator are separate one and

the duct line are used to distribute cooled air into rooms or anything. This is two types

fresh air type and return air type .In fresh air type we supply atmospheric gas into room

through the evaporator and the return air type cooled air release to evaporator from the

room and then re cooled the gas.

Central type

Large size air conditioning system are commonly used this system. Which

has as advantage of comparatively low refrigerant volume is used for

106

Page 107: Ceb Report

Figure 11.10

107

Condenser Water (95°)

Outdoor Air

Outdoor Air

Condenser Water (85°)

Page 108: Ceb Report

refrigerant cycle. According to condenser cooling system the chill water plants are two

types.

Chill water plants with condenser water cooling system

Chill water plants with condenser air cooling system

Generally chill water plant is consists of high power compressor (normally use

centrifugal or reciprocating type), water cooled or air cooled condenser, filter, cooling

tower, duct line, evaporator with large chill water system expansion valve and various

types of controlling and protection device.

Compressor

Compressors may be classified as either open or hermetic.

Open compressor: A compressor unit consisting of a compressor, motor, and

safety controls mounted as a unit.(see fig:8. )

Hermetic: A condensing unit consisting of a compressor unit plus an

interconnected water cooled or air cooled condenser mounted as a unit.

Cooling tower

The cooling tower is used in a conjunction with the water-cooled condenser

(see fig:11.). Water in passing through the condenser water tubes only gets warmed up

but does not get contained. It can therefore be used again, after cooling. The cooling

tower cools the warm water for re circulating it in the condenser. It is thus a water

conservation equipment .The heat removed by the refrigeration system from the space or

product to be cooled is ultimately thrown to the atmosphere through the cooling tower in

a water-cooled condenser system. Thus cooling tower should function efficiently for the

refrigeration system to perform well.

The warm water from the condenser is pumped to the top of the cooling

tower. From there it is allowed to fall down a substantial height to the cooling tank or

through at the bottom. The falling water droplets are cooled by the air circulating through

the tower. The cooling is brought about both by sensible heat transfer and by the

evaporation of the water.

108