cathode connections – item no · cathode connections – item no. reference cells ... cathodic...

30
CATHODE CONNECTIONS – Item No. REFERENCE CELLS – Item No. CATHODIC PROTECTION CABINETS – Item No. CONCRETE PADS FOR CATHODIC PROTECTION – Item No. ANODE MESH – Item No. EXTRA LOW VOLTAGE CABLES FOR CATHODIC PROTECTION – Item No. CATHODIC PROTECTION RECTIFIERS – Item No. CATHODIC PROTECTION REMOTE MONITORING AND CONTROL UNITS – Item No. RIGID DUCTS AND JUNCTION BOXES FOR CATHODIC PROTECTION – Item No. ACCEPTANCE TESTING FOR CATHODIC PROTECTION – Item No. Special Provision No. 999S27 January 2004 CONSTRUCTION SPECIFICATION FOR CATHODIC PROTECTION ON BRIDGE DECKS TABLE OF CONTENTS 1.0 SCOPE 2.0 REFERENCES 3.0 DEFINITIONS 4.0 SUBMISSION AND DESIGN REQUIREMENTS 5.0 MATERIALS 6.0 EQUIPMENT 7.0 CONSTRUCTION 8.0 QUALITY ASSURANCE 9.0 MEASUREMENT FOR PAYMENT 10.0 BASIS FOR PAYMENT 1.0 SCOPE This special provision covers the requirements for the rehabilitation of bridge decks by means of a cathodic protection system using anode mesh. 2.0 REFERENCES This specification refers to the following standards, specifications or publications: January 2004 Pg. 1 of 30 SSP999S27

Upload: phamdat

Post on 27-Aug-2018

276 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

CATHODE CONNECTIONS – Item No. REFERENCE CELLS – Item No. CATHODIC PROTECTION CABINETS – Item No. CONCRETE PADS FOR CATHODIC PROTECTION – Item No. ANODE MESH – Item No. EXTRA LOW VOLTAGE CABLES FOR CATHODIC PROTECTION – Item No. CATHODIC PROTECTION RECTIFIERS – Item No. CATHODIC PROTECTION REMOTE MONITORING AND CONTROL UNITS – Item No. RIGID DUCTS AND JUNCTION BOXES FOR CATHODIC PROTECTION – Item No. ACCEPTANCE TESTING FOR CATHODIC PROTECTION – Item No.

Special Provision No. 999S27 January 2004

CONSTRUCTION SPECIFICATION FOR CATHODIC PROTECTION ON BRIDGE DECKS TABLE OF CONTENTS 1.0 SCOPE 2.0 REFERENCES 3.0 DEFINITIONS 4.0 SUBMISSION AND DESIGN REQUIREMENTS 5.0 MATERIALS 6.0 EQUIPMENT 7.0 CONSTRUCTION 8.0 QUALITY ASSURANCE 9.0 MEASUREMENT FOR PAYMENT 10.0 BASIS FOR PAYMENT 1.0 SCOPE This special provision covers the requirements for the rehabilitation of bridge decks by means of a cathodic protection system using anode mesh. 2.0 REFERENCES This specification refers to the following standards, specifications or publications:

January 2004 Pg. 1 of 30 SSP999S27

Page 2: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

Ontario Provincial Standards Specifications, General: OPSS 180 Management and Disposal of Excess Material Ontario Provincial Standards Specifications, Construction: OPSS 601 Electrical Work - General OPSS 603 The Installation of Ducts OPSS 604 Cable Installation OPSS 609 Grounding OPSS 616 Footings and Pads for Electrical Equipment OPSS 904 Concrete Structures OPSS 913 Embedded Work in Structures for Electrical Systems OPSS 928 Structure Rehabilitation - Concrete Removal OPSS 929 Abrasive Blast Cleaning - Concrete Construction OPSS 930 Structure Rehabilitation - Concrete Patches and Overlays Ontario Provincial Standards Specifications, Material: OPSS 1302 Water OPSS 1350 Concrete - Materials and Production OPSS 2320 Cathodic Protection Terminal Block Assembly OPSS 2321 Cathodic Protection Cabinet OPSS 2322 Cathodic Protection Equipment Assembly OPSS 2323 Cathodic Protection AC Power Distribution Assembly OPSS 2324 Cathodic Protection Remote Monitoring and Control Unit OPSS 2325 Cathodic Protection Rectifier OPSS 2410 Extra Low Voltage Cables Canadian Standards Association Standards: CSA A23.1/A23.2-94 - Concrete Materials and Methods of Construction/Methods of Test for Concrete CSA C22.2 No. 38-95 - Thermoset Insulated Wires and Cables CSA C22.2 No. 56-1977(R1992) - Flexible Metal Conduit and Liquid Tight Flexible Metal Conduit CSA C22.2 No. 65-93 - Wire Connectors CAN/CSA C22.2 No. 85-M89 - Rigid PVC Boxes and Fittings CSA C57-1966 (R1994) - Electrical Power Connectors for Use in Overhead Line Conductors American Standards for Testing and Materials Standards: ASTM B 265-95 - Titanium and Titanium Alloy Strip, Sheet and Plate ASTM D 4285-83 (1993) - Test Method for Indicating Oil or Water in Compressed Air Others: Ontario Traffic Signal Control Equipment Specifications Model 401C Cabinet Specifications NACE - National Association of Corrosion Engineers

January 2004 Pg. 2 of 30 SSP999S27

Page 3: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

3.0 DEFINITIONS Cathode Connection: means a cable connection of the following two types, made to reinforcing bars: a) CS: a current carrying cathode connection that is connected to the negative terminal of the

rectifier. b) CM: a non-current carrying cathode connection that is used to monitor the potential of the

reinforcing steel with respect to a reference cell. Corrosion Specialist: means an individual retained by the contractor, having all of the following qualifications: 1. A minimum of five years experience in cathodic protection of reinforced concrete structures. 2. Is a NACE accredited cathodic protection specialist. 3. Is a professional engineer. Distribution Bar: means a component of the anode that distributes current from the power feed point. Instant Off Potential: means the potential reading taken immediately after the current flowing to the system has been interrupted. RMU (Remote Monitoring Unit): means a device used to control operating parameters of a rectifier, collect and transfer operating data of the rectifier and embedded instrumentation to a remote computer, and perform depolarization tests; and is designated herein as RMU. Subzone: means the division of a concrete component into areas where the anode in an area is not continuous with the anode in the adjacent area. Zone: means an area of a concrete component, energized by one rectifier unit, consisting of one or more subzones. 4.0 SUBMISSION AND DESIGN REQUIREMENTS 4.01 Submissions 4.01.01 Working Drawings At least four weeks prior to commencement of the production of the equipment, five copies of working drawings, obtained from the supplier of the cathodic protection equipment assembly, for each of the following pieces of equipment shall be submitted to the Contract Administrator: a) The Cathodic Protection Remote Monitoring And Control Unit b) The Cathodic Protection Rectifier c) The Cathodic Protection Cabinet d) The Cathodic Protection AC Power Distribution Assembly e) The Cathodic Protection Terminal Block Assembly f) The Cathodic Protection Equipment Assembly

January 2004 Pg. 3 of 30 SSP999S27

Page 4: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

The working drawings shall include the information specified in the applicable OPS Specifications. The working drawings shall be certified by the Corrosion Specialist that the drawings are in conformance with the contract documents. The Ministry will not return stamped working drawings. 4.01.02 Operating and Maintenance Manual Prior to commencement of the production of the equipment, two copies of an operating and maintenance manual for the cathodic protection system shall be submitted to the Contract Administrator. Included with the manual shall be: a) Complete schematic diagrams and parts lists b) Manufacturer’s data sheets and engineering data for all electronic, electrical components and

mechanical parts of the unit c) Detailed information and test procedures for trouble-shooting d) Performance report of the rectifier and remote monitoring unit, including environmental testing. 4.01.03 Corrosion Specialist At least one week prior to commencement of work on the structure, the name and qualifications of the Corrosion Specialist shall be submitted to the Contract Administrator. 4.01.04 Plastic Spacer Mesh At least one week prior to the installation of the anode mesh, a letter from the anode mesh manufacturer specifying the plastic spacer mesh recommended for use with their product shall be submitted to the Contract Administrator. 4.01.05 Anode Mesh and Distribution Bars At least one week prior to the commencement of the installation of the distribution bars and the anode mesh, the following samples fabricated with the equipment and procedures to be used in the work, together with the power setting used in welding the samples, shall be submitted to the Contract Administrator: a) Two 300 mm lengths of distribution bar overlapped and welded at four locations at 10 mm

intervals. b) Anode mesh welded at the diamond junctions to two 500 mm lengths of distribution bars. 4.01.06 Test Results Within three working days of the completion of the tests required, the results of all tests that are specified to be recorded by the Contractor shall be submitted in writing to the Contract Administrator. Each test result shall be identified by the corresponding test location.

January 2004 Pg. 4 of 30 SSP999S27

Page 5: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

4.01.07 Notification of Production Notification of the date of commencement of fabrication, the date of completion of fabrication and the date of shipping as specified in the Material Specifications OPSS 2320, 2321, 2322, 2323, 2324, and 2325 shall be submitted to the Contract Administrator. 5.0 MATERIALS 5.01 Concrete Pad For Cathodic Protection The concrete pad shall conform to OPSS 616. 5.02 Cathodic Protection Equipment Assembly The cathodic protection equipment assembly shall be supplied according to OPSS 2322. The cathodic protection equipment assembly shall consist of a cathodic protection cabinet in which the equipment required to control and monitor the cathodic protection system is installed and wired. The control and monitoring equipment consists of the remote monitoring unit, the rectifier, the cathodic protection AC power distribution assembly, the cathodic protection terminal block assembly, a fan with thermostat and, when specified, the cellular modem antenna. Table 1 from OPSS 2320.05.01 shall be deleted and replaced with the following table, which represents a typical arrangement. Each terminal block zone assembly shall have a varying amount of terminal points, which will be design specific.

January 2004 Pg. 5 of 30 SSP999S27

Page 6: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

Table 1

Terminal Terminal Colour

Lettering

Extra Low

Voltage - Cable Size AWG

1

Anode

Black

A1

#6 2

Anode

Black

A2

#6

3

Anode

Black

A3

#6 4

Anode

Black

A4

#6

5

Cathode

White

CS1

#6 6

Cathode

White

CS2

#6

7

Cathode

White

CS3

#6 8

Cathode

White

CS4

#6

9

Cathode

Red

CM1

#10 10

Cathode

Red

CM2

#10

11

Cathode

Red

CM3

#10 12

Cathode

Red

CM4

#10

13

Graphite Reference Cell

Green

R1

#10 14

Graphite Reference Cell

Green

R2

#10

15

Graphite Reference Cell

Green

R3

#10 16

Silver-Silver Chloride Reference Cell

Blue

R4

#10

Each terminal point shall be capable of accommodating all wire sizes from #6 to #14. 5.03 Cathodic Protection Cabinet The cathodic protection equipment cabinet shall be Model 401C Cabinet specified in the Ontario Traffic Signal Control Equipment Specifications and shall meet the requirements specified herein. The cabinet shall be according to OPSS 2321, except that the cabinet shall be fabricated out of aluminium with a finished gloss thermosetting powder paint protective coating. 5.04 Cathodic Protection Rectifier The rectifier shall be according to OPSS 2325 and as specified herein. The rectifier shall be supplied by: Corrosion Service Company Ltd. 369 Rimrock Road Downsview, Ontario M3J 3G2 Telephone: (416) 630-2600

January 2004 Pg. 6 of 30 SSP999S27

Page 7: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

Corrpro Canada Inc. 7895 Transmere Drive, Unit 11 Mississauga, Ontario L5S 1V9 Telephone: (905) 677-2700 The rectifier and RMU shall be fully compatible in operation. The Contractor shall select the rectifier and RMU from the same supplier. AC surge and lightning protection shall be installed inside the 401C cathodic protection cabinet used on AC input side of both the rectifiers and RMU. The AC surge and lightning protection shall be model LPC 11765U-13 manufactured by Lightning Protection Corporation. DC surge and lightning protection shall be installed inside the 401C cathodic protection cabinet used on DC power output side for rectifiers. The DC surge and lightning protection shall be model LPC 11850-52 manufactured by Lightning Protection Corporation The AC and DC surge and lightning protection shall be distributed by: Lightning Protection Corporation 5750 Thornwood Dr. Goleta, CA 93117 Telephone: (805) 967-4577 Subsection 2325.07.03 of OPSS 2325 is amended by the addition of the following: The 180 hour burn–in test required for the entire rectifier operating unit (including control cards) shall be carried out at a testing facility that is certified to ISO 9001 (International Standards Organization). 5.05 Cathodic Protection Remote Monitoring And Control Unit The RMU shall be according to OPSS 2324 and as specified herein. The RMU shall be supplied by: Corrosion Service Company Ltd. 369 Rimrock Road Downsview, Ontario M3J 3G2 Telephone: (416) 630-2600 Corrpro Canada Inc. 7895 Transmere Drive, Unit 11 Mississauga, Ontario L5S 1V9 Telephone: (905) 677-2700 The RMU and rectifier shall be fully compatible in operation. The Contractor shall select the RMU and rectifier from the same supplier. The RMU software shall be compatible to Microsoft Windows 2000 or latest version. The Contractor shall submit 2 copies of the RMU software to the Ministry, and shall provide a demonstration for the use of the software to the Ministry Representative.

January 2004 Pg. 7 of 30 SSP999S27

Page 8: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

Telephone line surge and lightning protection shall be installed inside the 401C cathodic protection cabinet. The telephone line surge and lightning protection shall be manufactured by Sixnet, part number SP-TELCO-1. The telephone line surge and lightning protection shall be distributed by: Ontor Ltd. 12 Leswyn Rd. Toronto, Ontario M6A 1K3 Telephone: (416) 781-5286 Subsection 2324.07.03 of OPSS 2324 is amended by the addition of the following: The 180 hour burn–in test required for the entire RMU operating unit (including control cards) shall be carried out at a testing facility that is certified to ISO 9001 (International Standards Organization). 5.06 Extra Low Voltage Cables For Cathodic Protection All extra low voltage cable shall be according to OPSS 2410 or shall be type RWU90, cross link, -40ºC, minimum 19-strand copper conforming to CSA C22.2 No. 38. 5.06.01 Anode Bus Cables The anode bus cable from the junction box to the control panel of the cathodic protection cabinet shall be extra low voltage cable AWG #6 with black insulation, without splicing. 5.06.02 Cathode Connection Cables The cathode CS bus cable from the junction box to the rectifier of the cathodic protection cabinet shall be extra low voltage cable AWG #6 with white insulation, without splicing. The cathode CM extension cable from the junction box to the control panel of the cathodic protection cabinet shall be extra low voltage cable AWG #10 with red insulation, without splicing. 5.06.03 Reference Cell Cables 5.06.03.01 Graphite Reference Cell Cables The reference cell extension cable from the junction box to the control panel of the cathodic protection cabinet shall be extra low voltage cable AWG #10 with green insulation, without splicing. 5.06.03.02 Silver-Silver Chloride Reference Cell Cables The reference cell extension cable from the junction box to the control panel of the cathodic protection cabinet shall be extra low voltage cable AWG #10 with blue insulation, without splicing.

January 2004 Pg. 8 of 30 SSP999S27

Page 9: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

5.06.04 Thermocouple Cables The thermocouple wire shall be solid wire size AWG #20, T Type. Wire insulation shall be chemically inert and thermally stable. Insulation shall be high temperature fluorocarbon, rated for 200oC. The outside insulation shall be 0.20 mm extruded fluorocarbon and the jacket 0.25 mm extruded fluorocarbon. The thermocouple shall be fitted with sufficient wire to extend from the point of embedment in the deck to the cathodic protection cabinet, without splicing. Thermocouple precision shall be +/- 0.5oC and shall be manufactured by: Thermo-Electric Canada Ltd. 12 Rutherford Road South Brampton, Ontario L6W 3J2 Telephone: (905) 451-0813 5.07 Grounding Materials The ground wire, ground electrodes, and connectors shall be according to OPSS 609. 5.08 Connectors The cable connectors shall be according to CSA C22.2 No. 65 and CSA C57. 5.09 Ducts and Fittings The ducts and fittings shall be rigid RE/PVC watertight, and shall be according to OPSS 603. The flexible liquid tight ducts and fittings shall be according to CSA C22.2 No. 56. 5.10 Junction Boxes The junction boxes shall be rigid PVC watertight boxes with screw down lids according to CAN/CSA C22.2 No. 85. The boxes shall be supplied with predrilled holes for connectors and two 6 mm diameter drain holes. The drain holes shall be located with a minimum separation of 250 mm at the lowest point in the box where water may collect. 5.11 Anode Mesh The anode mesh material shall be high purity titanium Grade 1, according to ASTM B265, coated with a mixed metal oxide catalyst. The diamond dimensions for the anode mesh shall be 80 x 40 mm maximum. The anode mesh shall be supplied in rolls with a minimum width of 1 m and shall be Elgard 210 diamond type mesh.

January 2004 Pg. 9 of 30 SSP999S27

Page 10: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

The Elgard 210 diamond type mesh is supplied by: Corrpro Canada Inc. 7895 Transmere Drive, Unit 11 Mississauga, Ontario L5S 1V9 Telephone: (905) 677-2700 5.12 Distribution Bars The distribution bars shall be titanium Grade 1, according to ASTM B265 . The bars shall be 12 mm wide x 1 mm thick and shall be supplied in lengths at least 3 m long. The surfaces of the bar shall be free of oxides, grease and other contaminants. The bars shall be supplied by: Corrpro Canada Inc. (listed above) 5.13 Anode Mesh Fasteners The fasteners shall be fabricated from nylon 6/6 grade plastic suitable for long term embedment in concrete, shall be resistant to acid and shall be capable of securing the mesh anodes in place on concrete surfaces. The portion of the fastener embedded in the concrete shall be no larger than 8 mm diameter and no more than 33 mm in length. The fasteners shall be manufactured by ITW Fastex, Part No. 354-260300-00-0078 or Spae-Naur Inc., Part. No. 086-617. The ITW Fastex fasteners are distributed by: Spencer Products Co. 1859 Summit Commerce Park Twinsburg, Ohio 44087 Telephone: (330) 487-5200 The Spae-Naur Inc. fasteners are distributed by: Spae-Naur Inc. 815 Victoria Street N. Kitchener, Ontario N2G 4B1 Telephone: (519) 744-3521 5.14 Spacer Mesh The spacer mesh shall be not less than 75 x 75 mm, nor more than 100 x 100 mm and shall be fabricated from plastic suitable for long term embedment in concrete and shall be resistant to acid.

January 2004 Pg. 10 of 30 SSP999S27

Page 11: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

The plastic spacer mesh shall be as approved by or supplied by: Corrpro Canada Inc. (listed above) 5.15 Reference Cells 5.15.01 Graphite Reference Cell Graphite reference cells shall be 40 x 40 x 150 mm graphite bars, grade SR-45 or equivalent. Cables for graphite reference cells shall be extra low voltage cables according to OPSS 2410 or shall be AWG #10 with green insulation, type RWU90, cross link, -40oC, minimum 19-strand copper conforming to CSA C22.2 No. 38. The 40 x 40 x 150 mm graphite reference cell shall be fitted with a length of extra low voltage cable AWG #10 with green insulation. The extra low voltage cable shall be sufficiently long to extend from the point of embedment to the splice in the junction box, without splicing. The extra low voltage cable shall be securely attached to the graphite bar by means of a threaded brass connector. The cable shall be soldered in a hole in the centre of the brass connector. The brass connector shall be fitted into a drilled and tapped hole in the graphite bar. The brass connector shall be recessed at least 15 mm and shall have side clearances of 15 mm. After soldering, the recess shall be filled to fully seal out water from soldered area. The supplier shall install the cable prior to delivery of the reference cells to the site. The resistance between the end of the cable and the end of the graphite block shall not exceed 1 ohm. The graphite reference cells shall be supplied by: Corrosion Service Company Ltd. 369 Rimrock Road Downsview, Ontario M3J 3G2 Telephone: (416) 630-2600 Inter Provincial Corrosion Control 930 Sheldon Court Burlington, Ontario L7L 5K6 Telephone: (905) 634-7751 5.15.02 Silver-Silver Chloride Reference Cell Cables for silver-silver chloride reference cells shall be extra low voltage cables according to OPSS 2410 or shall be AWG #10 with blue insulation, type RWU90, cross link, -40oC, minimum 19-strand copper conforming to CSA C22.2 No. 38. The silver-silver chloride reference cell shall be fitted with a length of extra low voltage cable AWG #10 with blue insulation. The extra low voltage cable shall be sufficiently long to extend from the point of embedment to the splice in the junction box, without splicing.

January 2004 Pg. 11 of 30 SSP999S27

Page 12: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

The silver-silver chloride reference cells shall be C-PROBE Model CP10P and supplied by: Corrosion Service Company Ltd (listed above) 5.16 Cathode Connections Cables for cathode connections shall be extra low voltage cables according to OPSS 2410 or shall be type RWU90, cross link, -40oC, minimum 19 strand copper conforming to CSA C22.2 No. 38. The cathode CS cable from the point of connection of the reinforcing steel to the junction box shall be extra low voltage AWG #10 with white insulation, without splicing. The cathode CM cable from the point of connection of the reinforcing steel to the junction box shall be extra low voltage AWG #10 with red insulation, without splicing. 5.17 Silicone Seal The silicone seal shall be suitable for electrical applications and burial in concrete. 5.18 Heat Shrink Tubing and Splice Kits The heat shrink tubing and splice kit shall fully insulate and seal out water from the connection area of the splice and shall be suitable for burial applications. The heat shrink tubing shall be type”WCSM”, and motor connection kits for encapsulating the splices shall be type “MCK” manufactured by: Tyco Electronics 20 Esna Park Dr. Markham, Ontario L3R 1E1 Telephone: (905) 475-6222 5.19 Heat Shrink Tape The heat shrink tape shall fully insulate and seal out water from the connection area of the splice. 5.20 Concrete for Blockout The concrete used to fill blockouts for installation of cables in curbs, sidewalks and barrier walls shall have a 28 day strength of 30 MPa according to OPSS 1350. Nominal maximum size of aggregate shall be 9.5 mm. 5.21 Water Water shall be according to OPSS 1302. 5.22 Epoxy The epoxy shall be non-conductive, low viscosity type, and suitable for burial in concrete.

January 2004 Pg. 12 of 30 SSP999S27

Page 13: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

The epoxy shall be Rezi-Weld gel paste construction epoxy unitised cartridge system manufactured by: W.R. Meadows of Canada 70 Hannant Crt. Milton, Ontario L9T 5C1 Telephone: (905) 878-4122 5.23 Thermite Weld Cathode connections to the reinforcing steel shall be made by thermite weld. The thermite weld shall be CA15 Cadweld manufactured by: Erico Inc. 34600 Solon Rd. Solon, Ohio 44139 U.S.A. Telephone: 1-800-677-9089 5.24 Non-Shrink Grout The non-shrink grout shall be Masterflow 713 Plus Grout or Master Builders Set Non-Shrink Grout supplied by: Degussa Building Systems 5655 Kennedy Road Mississauga, Ontario L4Z 3E1 Telephone: (905) 712-3724 5.25 Thread Locking Compound The thread locking compound shall be a removable anaerobic setting liquid compound that when used in metal to metal contact positively locks and seals the threaded fastener to prevent corrosion and loosening. 6.0 EQUIPMENT 6.01 AC Resistance Meter The AC resistance meter shall be capable of measuring from 0.1 ohm to 10,000 ohms, with an accuracy of ± 1 % of full scale, and shall be insensitive to AC and DC ground currents. 6.02 Multimeter The multimeter shall have an input impedance of not less than 10 megohms when operated at a full scale of 100 mV. The meter shall have an accuracy of ± 2.5 % of the reading in DC volts with a resolution of 0.1 mV.

January 2004 Pg. 13 of 30 SSP999S27

Page 14: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

6.03 Air Compressor – Air Blasting The air compressor for air blasting shall have a minimum capacity of 3.5 m3/min. The compressed air shall be free of oil according to ASTM D 4285-83 (1993) and be forced through a nozzle at a minimum pressure of 300 kPa. 6.04 Pressure Wash Equipment The pressure wash equipment shall produce a minimum pressure at the nozzle of 1.4 MPa. 6.05 Holiday Detector The holiday detector shall have pulse type output voltages adjustable to produce from 300 to 3000 volts. The device shall be equipped with a 300 mm wide conductive steel or copper brush to scan the concrete surface and shall produce a loud audible signal when metals which are electrically connected to the reinforcement are detected. 6.06 Concrete Cover Meter The cover meter shall have a digital read out for measurement of cover and an audio signal indicating detection of reinforcing steel bars in concrete with cover up to 150 mm. The accuracy of the meter shall be ± 5% of full scale. 6.07 Concrete Saw The concrete saw shall be capable of sawing the concrete to the lines and depths specified in the Contract. 6.08 Resistance Welder A resistance welder shall be suitable to the application and as recommended by the anode system manufacturer. 6.09 Thermocouple Meter The thermocouple meter shall have a digital readout capable for measurement of T-type thermocouples. 7.0 CONSTRUCTION 7.01 General 7.01.01 Work Content The operations of concrete removal and replacement and abrasive blast cleaning associated with the installation of various components are part of that work. 7.01.02 Sequence of Work The cathodic protection work shall not commence until the repairs in the areas to receive cathodic protection have been completed, fully or in sections, and accepted by the Contract Administrator.

January 2004 Pg. 14 of 30 SSP999S27

Page 15: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

7.01.03 Access Adequate access shall be provided to facilitate: a) Performance of work; b) Inspection and measurement of the work by the Contract Administrator. The Contractor shall arrange, through the supplier of the cathodic protection equipment assembly, for the Contract Administrator to have access to the place of manufacture of the cathodic protection control and monitoring equipment. 7.01.04 Electrical All electrical work shall be according to OPSS 601 and as specified herein. Except when measuring resistance between two cathode connections where resistance measurements are specified, measurement shall be made with an A.C. meter. 7.01.05 Concrete Removal in Recesses and Cable Slots The recesses for the embedded components and cable slots shall be saw cut prior to concrete removal. Concrete removal shall be according to OPSS 928. 7.01.06 Abrasive Blast Cleaning Abrasive blast cleaning shall be according to OPSS 929. 7.01.07 Concrete Concrete shall be according to OPSS 904. 7.01.08 Curing Curing of concrete and non-shrink grout shall be according to OPSS 904 utilizing the wet burlap method. 7.02 Cathode Connections 7.02.01 Installation 7.02.01.01 Scheduling Cathode connections to the reinforcing steel shall be made after removal of concrete and abrasive blast cleaning in the removal areas. 7.02.01.02 Layout The cathode CS and CM cables shall be connected to the reinforcing steel at the locations specified. Alternative locations for cathode CS and CM connections will be specified by the Contract Administrator, if required.

January 2004 Pg. 15 of 30 SSP999S27

Page 16: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

Adjustment up to 1 metre will be allowed for the cathode CS connections. The cathode CM connections shall be located between 600 mm and 1 metre of the respective reference cells. At the cathode connection positions specified, the location of the reinforcing steel bars shall be determined by means of a cover meter. 7.02.01.03 Preparation of Reinforcement and Recess Concrete shall be removed to expose a 150 mm length of reinforcing bar. The reinforcing steel and the concrete surface of the recess shall be abrasive blast cleaned and cleaned of all deleterious material by means of air blasting. The reinforcing bar shall be ground locally to expose bare metal prior to making the thermite weld connection. 7.02.01.04 Connection of Reinforcing Steel The connection shall be made centred on the ground portion of the reinforcing steel, as specified. The bare portion of the cathode cable shall be protected by a copper sleeve and shall be connected by thermite welding to the reinforcing bar. Mechanical connections shall not be used. When the weld has cooled, slag shall be removed and a 5 mm thick layer of silicone seal shall be applied to the entire weld area of the bar and to all exposed copper cable. After setting of the silicone seal, all debris shall be removed from the recess and the surface of the recess shall be dampened. All free water shall be removed from the recess and the recess shall be filled with non-shrink grout according to the manufacturer’s recommendations. 7.02.01.05 Cable Installation Cable slots, each 6 mm wide by 10 mm deep, shall be sawn between the cathode connection locations and the junction box for the installation of cathode connection cables as specified. The edges of the slot shall be rounded where the slot meets the recess. Each slot shall contain only one cable. Immediately prior to placing material, the recesses shall be abrasive blast cleaned and all deleterious material contained inside the recesses and slots shall be removed by means of air blasting. The cable shall be continuously contained in the slot between the cathode connection and the junction box, and held in place with non-metallic plugs spaced at 600 mm on centres to prevent migration of the cable towards the surface. Cables that will be unconnected at the junction box location for more than one week shall have a heat shrink end boot installed until the permanent connection is made. Cable slots shall be backfilled with non-conductive, low viscosity epoxy to the level of the original concrete surface according to the manufacturer’s recommendations. Care shall be exercised to ensure that the slots are completely filled with epoxy and there is no excess epoxy spilled over the adjacent concrete surface along the slots.

January 2004 Pg. 16 of 30 SSP999S27

Page 17: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

7.02.01.06 Testing During Installation Before filling cathode recesses, the mechanical soundness of each completed cathode connection shall be verified and the resistance and voltage between the ends of cables from cathode connections shall be measured and recorded. The resistance between any two cathode connection cables in a single zone shall be less than 1.0 ohm and voltage shall be less than 1 mV. If the resistance is greater than 1.0 ohm, or voltage is greater than 1 mV, each individual cathode connection cable shall be checked and remedial work shall be performed as follows. a) When the resistance between the end of the cable and the reinforcing bar to which it is connected

is greater than 1.0 ohm, or the voltage is greater than 1 mV, the cable shall be cut and reattached to the same reinforcing bar at least 150 mm away from the previous connection.

b) When the resistance between the end of the cable and the reinforcing bar to which it is connected

is less than 1.0 ohm and voltage is less than 1 mV, additional cathode connections shall be installed at locations determined by the Contract Administrator.

Resistance and voltage measurements between pairs of cathode connection cables shall be repeated and recorded following remedial work. When mechanical soundness of the cathode connections and continuity of reinforcing steel have been verified, patching of cathode cavities may proceed. After patches are placed, the resistance and voltage between pairs of cathode connection cables shall be measured and recorded to check the connections prior to placing anode. The Contractor shall submit the results of all tests to the Contract Administrator and the test results shall be certified by the Corrosion Specialist. 7.03 Reference Cells (Graphite & Silver-Silver Chloride) 7.03.01 Installation 7.03.01.01 Scheduling The recesses for reference cells and cable slots shall be saw cut prior to concrete removal. Reference cells shall be installed after removal of concrete and abrasive blast cleaning in the removal areas. 7.03.01.02 Layout The reference cells shall be placed at the locations specified in the contract. At the reference cell positions specified, the location of the reinforcing steel bars shall be determined by means of a cover meter. A recess, 200 mm wide by 400 mm long, to accommodate the reference cell shall be cut into the concrete within 10 to 25 mm from a reinforcing steel bar with the longitudinal axis of the cell parallel to the reinforcing steel bar. The Contract Administrator may specify a smaller size recess if necessary.

January 2004 Pg. 17 of 30 SSP999S27

Page 18: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

When reinforcing steel interferes with the placement of a cell, the recess shall be extended to permit installing the cell without cutting the reinforcing steel, or a new recess shall be cut. Reference cells shall not be positioned in a patched area or within 600 mm of a patched area. To comply with the above requirements the cell may be moved a maximum of 1 metre from the location specified on the drawings. The Contract Administrator will specify alternative locations when the above conditions cannot be satisfied or when required. 7.03.01.03 Preparation of Recess and Cell Placement The depth of the recess shall permit the reference cell to be installed with the adjacent reinforcing steel bar at the mid height of the cell. When 10 mm of cover is not provided to the top of the cell under the above conditions, the recess shall be deepened to provide the 10 mm of cover. Reference cells installed adjacent to ducts containing post-tensioning steel shall be installed at the specified depth or as directed by the Contract Administrator. The concrete surface in the recess shall be abrasive blast cleaned and all deleterious material removed by means of air blasting. The surfaces of the recess shall be dampened, all free water removed, and coated with non-shrink grout. The reference cell shall be placed tight against the side of the recess closest to the reinforcing steel; however, contact between the cell and the exposed reinforcing steel shall not be permitted. The recess, including cavities induced by saw cutting, shall be filled with non-shrink grout, according to the manufacturers recommendations, to the level of the original concrete surface. 7.03.01.04 Cable Installation Cable slots, each 6 mm wide by 10 mm deep, shall be sawn between the reference cell recess and the junction box for the installation of the reference cell cables as specified. The edges of the slot shall be rounded where the slot meets the recess. Each slot shall contain only one cable. The wiring from the two thermocouples shall be contained in two reference cell cable slots as directed by the Contract Administrator. Immediately prior to placing material, the recesses shall be abrasive blast cleaned and all deleterious material contained inside the recesses and slots shall be removed by means of air blasting. The cable shall be continuously contained in the slot between the reference cell recess and the junction box, and held in place with non-metallic plugs spaced at 600 mm on centres to prevent migration of the cable towards the surface. Cables that will be unconnected at the junction box location for more than one week shall have a heat shrink end boot installed until the permanent connection is made. Cable slots shall be backfilled with non-conductive, low viscosity epoxy to the level of the original concrete surface, according to the manufacturer’s recommendations. Care shall be exercised to ensure that

January 2004 Pg. 18 of 30 SSP999S27

Page 19: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

the slots are completely filled with epoxy and there is no excess epoxy spilled over the adjacent concrete surface along the slots. 7.03.01.05 Testing During Installation Upon completion of cell installation, the voltage and resistance between the reference cell and the cathode CM connection shall be measured and recorded. If the resistance between the graphite cell and the cathode connection is less than 10 ohms or more than 1000 ohms, or if the voltage reading is unstable, the cell shall be removed and replaced. The voltage and resistance measurements shall be repeated and recorded. The Contractor shall submit the results of all tests to the Contract Administrator and the test results shall be certified by the Corrosion Specialist. 7.04 Thermocouple 7.04.01 Installation 7.04.01.01 Scheduling The recesses for thermocouples and cable slots shall be saw cut prior to concrete removal. Thermocouples shall be installed after removal of concrete and abrasive blast cleaning in the removal areas. 7.04.01.02 Layout Two thermocouples shall be installed in the deck at locations specified by the Contract Administrator. 7.04.01.03 Preparation of Recess and Placement Each thermocouple shall be installed in a common recess with a reference cell, as specified by the Contract Administrator. The end of thermocouple should be placed at the level of the steel. 7.04.01.04 Cable Installation The wiring from the two thermocouples shall be contained in two reference cell cable slots, as directed by the Contract Administrator. The thermocouple shall be fitted with sufficient wire to extend from the point of embedment to the cathodic protection cabinet, without splicing. Prior to installation, the installer must remove approximately 6 mm of teflon jacket from one end of each thermocouple wire, remove the separate red and blue insulation from the copper and constantan wires, twist them together, followed by silver soldering and a coating of silicone seal. 7.04.01.05 Testing During Installation Upon completion of the thermocouple installation, manual readings shall be taken with a digital meter capable of reading T-type thermocouples.

January 2004 Pg. 19 of 30 SSP999S27

Page 20: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

7.05 Rigid Ducts and Junction Boxes, Surface Mounted The duct, fittings and junction boxes shall be installed in neat straight lines. Rigid ducts shall be installed vertically and either horizontally or parallel to structural surfaces using offset bends or fittings where changes in alignment are necessary. When holes are specified to permit installation through concrete components, they shall be core drilled. Expansion and contraction joints shall be installed according to the manufacturer's recommendations with at least one expansion joint between adjacent junction boxes. The temperature range to be used to determine expansion and contraction requirements is –50oC to +50oC. Duct straps and junction boxes shall be fastened to the concrete surface by drilling and inserting anchors and bolts. Stainless steel anchors and bolts shall be used as fasteners to secure the rigid duct and junction boxes to the concrete surface. Duct straps shall be located at a maximum of 1.5 m centres and shall be one trade size larger than the conduit supported. The duct shall be free sliding in the straps. The duct shall be attached to the junction boxes using P.V.C. cement. Ducts and junction boxes shall be installed after concrete repairs have been completed. 7.06 Rigid Ducts and Junction Boxes, Embedded in Concrete The installation of rigid PVC junction boxes and rigid duct embedded in concrete shall be according to OPSS 913. When cables are to be routed through the curb to a junction box mounted on the outside face of a deck, concrete shall be removed at the curb locations to the width and depth specified. All sharp edges of concrete shall be rounded off. A hole shall be drilled to provide access to the junction box or to provide a deck entry hole where indicated in the contract. A non-conductive duct shall be installed and grouted in place with non-shrink grout. After the installation of the cables, the duct embedded in the curb shall be sealed with a silicone plug to a depth of 50 mm. The cavities in the curb, barrier wall or sidewalk shall be filled with concrete to the original surface according to OPSS 930. 7.07 Rigid Ducts, Direct Buried The installation of rigid ducts direct buried shall be according to OPSS 603. 7.08 Extra Low Voltage Cables The installation of the extra low voltage cables shall be according to OPSS 604. The run of extra low voltage cable from the initial splice in the junction box to the cathodic protection cabinet shall be of one continuous length. Heat shrink identification sleeves shall be placed over the free

January 2004 Pg. 20 of 30 SSP999S27

Page 21: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

end of each cable at the cathodic protection cabinet and at the end of each cable from the structure in the junction boxes, with the number of the component as shown in the Contract. All splices, with the exception of anode distribution bars, shall be made in the junction boxes with compression connectors. Each splice shall be soldered after installation. Both ends of the connector shall be soldered to the cable. All splices for reference cells and cathode CM cables shall be sealed and insulated with heat shrink tubing. The splices for the cathode CS cables shall be sealed and insulated with a motor splice kit. Cable that will be unconnected at the junction box location for more than one week shall have a heat shrink end boot installed until the permanent connection is made. 7.09 Installation of Cathodic Protection Equipment Assembly 7.09.01 Concrete Pad and Ground Electrode The concrete pad shall be constructed according to OPSS 616, except that the anchor bolts shall be drilled in place. The installation of the ground wires and ground electrode shall be according to OPSS 609. 7.09.02 Installation of Cabinet The pedestal and cabinet shall be installed squarely and symmetrically on the concrete pad with a neoprene gasket installed on the bottom channel of the enclosure and the bottom of the pedestal. Holes for mounting bolts shall be drilled as required and anchor bolts installed. 7.09.03 Grounding The ground bar installed on the bottom part of the cabinet shall be connected to the external ground electrode. 7.09.04 Connection of Incoming Cables The AC power supply shall be connected to the AC power distribution assembly. Each cable from the structure shall be connected to the proper terminal on the terminal block assembly conforming to the colour code and labelling. The thermocouple wires shall be connected to the RMU. Upon completion of wiring and connection, all incoming cables shall be bundled and held in place with nylon cable ties. Cables and connectors shall not be subject to stress during or after installation.

January 2004 Pg. 21 of 30 SSP999S27

Page 22: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

7.09.05 Phone Lines for RMU When a land line to the RMU is specified, the Contractor shall notify Bell Canada to arrange for the installation of the land line to the cabinet. Sufficient notice shall be provided so as to prevent untimely delays during the acceptance testing and commissioning of the cathodic protection system. The costs for the installation and monthly service charges of the phone line will be paid by the Ministry with a billing address to be provided. The Contractor shall connect the land line to the RMU. 7.10 Anode Mesh and Distribution Bars 7.10.01 Handling and Storing The anode mesh and distribution bars shall be handled and stored in such a manner to avoid breakage or shape distortion due to stretching. The anode mesh and distribution bar shall be kept clean and dry prior to installation. 7.10.02 Installation 7.10.02.01 Scheduling The anode mesh and distribution bars shall be installed after all concrete patching and abrasive blast cleaning of the concrete surface has been carried out and before placement of the concrete overlay. 7.10.02.02 Layout The anode mesh and distribution bars shall be installed on the concrete surfaces as specified in the Contract. Alternative arrangement of anode mesh rows may be considered where it may be practical to use odd shapes of anode mesh, subject to the approval of the Contract Administrator. 7.10.02.03 Isolation The Contractor shall ensure that the anode mesh is electrically isolated from the reinforcing steel and from any metallic components on the surface of the structure prior to proceeding with the work. Isolation shall be accomplished by the use of non-metallic fasteners, cutting of the anode mesh to remain clear of objects, or by installation of insulating materials such as neoprene beneath conduits, as specified by the Contract or by the Contract Administrator. When a deck has been scarified, a concrete cover survey on a 1.5 m x 1.5 m grid shall be done after scarifying and prior to the installation of the anode mesh. A plastic spacer mesh shall be placed between the anode mesh and the concrete in areas where cover to the reinforcing steel is less than 15 mm. The results of the survey shall be recorded and submitted to the Contract Administrator. Immediately prior to installation of the anode mesh, all concrete surfaces shall be inspected for exposed metal such as tie-wire, tie-rods, reinforcing steel, bolts, and other metallic components. All exposed metal and metal within 5 mm of the concrete surface, which is continuous with the reinforcing steel, shall be identified by visual means and by means of a holiday detector, and the metal shall be insulated by coating with two coats of epoxy or shall be removed as directed by the Contract Administrator. When epoxy is used only the metal shall be coated.

January 2004 Pg. 22 of 30 SSP999S27

Page 23: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

7.10.02.04 Anode Mesh Placement Adjacent rolls of anode mesh within the same zone shall be in contact with a minimum overlap of 100 mm. When two or more zones or subzones are specified, the separation between anode mesh in adjacent zones or subzones shall be 150 ± 25 mm. Anode mesh shall be cut, where necessary, to provide a separation of 150 ± 25mm between the anode mesh and metal features mounted on or protruding from concrete surface. At splices and at joints where irregularly shaped sections are added, the anode mesh shall be overlapped a minimum of 75 mm and both sections of the anode mesh shall be welded to the distribution bar. The anode mesh shall be either offset a maximum of 75mm from a concrete corner or shall be wrapped tightly around the corner. The edge of anode mesh shall be offset 150 ± 25mm from the curb face throughout the length of the deck. The location of embedded cables shall be determined and marked on the concrete prior to drilling for fasteners. The anode mesh shall be held in place by non-conductive fasteners inserted in drilled holes. There shall be at least three fasteners installed across the full width of each roll of the anode mesh such that two anchors are placed 50-75 mm from the anode mesh edge with a third anchor in the centre. The maximum distance between two adjacent anchors along the length and width of the anode mesh shall not exceed 600 mm. Overlapping anode mesh may be attached with a common fastener. The anode mesh shall be installed as close to the concrete surface as practical, with a maximum offset from the surface of 3 mm. Bulges shall be pressed down and additional fasteners shall be installed to maintain the specified clearance. The anode mesh shall not be tensioned to such an extent that the anode mesh pattern is distorted. Edges of anode mesh cut to avoid contact with objects on the concrete surface shall be fastened at no more than 300 mm intervals. All debris and dirt resulting from drilling holes for fasteners and others work associated with the installation of the anode mesh shall be removed from the concrete surface by air blasting at a minimum frequency of once per day. Under no circumstances shall the anode mesh be subjected to abrasive blast cleaning. 7.10.02.05 Distribution Bar Placement Distribution bars shall be installed in straight lines as indicated in the Contract. The locations shall line up with junction box locations to facilitate connection within the box.

January 2004 Pg. 23 of 30 SSP999S27

Page 24: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

Where specified, distribution bars may be extended, by overlapping approximately 200 mm and resistance welding every 12 mm. The anode mesh shall be resistance welded to the distribution bars at every diamond intersection point. The welding procedures used shall be according to the anode mesh manufacturer's recommendations and shall be those used in making the samples for submission. The distribution bars shall be protected by the application of heat-shrinkable tubing: a) in conduit connecting to junction box b) where passing through curb c) where traversing concrete cracks greater than 1 mm d) where specified in the Contract or by Contract Administrator Jumper wires shall be welded to the distribution bar at concrete crack locations greater than 1 mm in width. The distribution bars shall enter the junction box through the conduit as indicated in the Contract. The two distribution bars shall be jumpered by a short stub of distribution bar resistance welded to them in the junction box. The distribution bars shall be connected to the Anode bus cable by means of a bolted connector. The threads of the bolt shall be coated with a locking compound. The connection and any exposed distribution bars shall be sealed and insulated with heat shrink tubing and heat shrink tape. 7.10.02.06 Concrete Surface Preparation After Anode Installation Immediately after installation of the anode mesh and distribution bars, all debris resulting from the drilling of anchor holes and other accumulated dirt shall be removed from the concrete surface by air blasting. The surface of the concrete with anode mesh and distribution bars in place shall be prewetted with water before application of the concrete overlay. 7.10.02.07 Protection During Placement of Concrete Overlay During placement of concrete overlay, the anode mesh and distribution bars shall be protected against potential damage caused by construction equipment and workers by means of 20 mm thick plywood sheeting. The plywood sheets shall be removed as the placement of the overlay progresses. 7.10.02.08 Junction Box Entry When wiring is to be routed to junction boxes embedded in new barrier walls or sidewalks, a blockout shall be created to permit installation of conduit and wiring. After installation of the cables, the conduit in the curb shall be sealed with a silicone plug to a depth of 50 mm. The cavities in the curb, barrier wall or sidewalks shall be filled with concrete to the original surface in conformance with OPSS 930. Alternatively, the cavity may be filled with non-shrink grout.

January 2004 Pg. 24 of 30 SSP999S27

Page 25: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

7.10.03 Testing 7.10.03.01 Before Installation Prior to installing anode mesh and distribution bars, the Contractor shall test the quality of the weld between the anode mesh and current distribution bar by preparing a sample weld and pulling the anode mesh from the distribution bar using pliers. If metal is pulled from one substrate, the weld is good. If the anode mesh strand/strip breaks or is burned through, the weld power setting is too high. If the weld breaks, the power setting is too low. A similar test should be carried out to determine the quality of the weld when two distribution bars are welded together. The weld power setting shall be adjusted, if necessary, to obtain satisfactory welds. One week prior to the commencement of the installation of the distribution bars and the anode mesh, the following samples, fabricated with the equipment and procedures to be used in the work together with the power setting used in welding the samples, shall be submitted to the Contract Administrator: a) Two 300 mm lengths of distribution bars overlapped and welded at four locations at 10 mm

intervals. b) Anode mesh weld at the diamond junctions to two 500 mm lengths of distribution bars. 7.10.03.02 During Installation 7.10.03.02.01 Weld Between Anode Mesh and Distribution Bars During installation of the anode mesh and distribution bars, random pull tests shall be performed on the weld connecting a) the anode mesh to the distribution bar, and b) the distribution bar to the distributor bar, to verify the adequacy of the welds. 7.10.03.02.02 Short Circuits Tests for short circuits between the anode mesh, the reinforcing steel, and all metallic appurtenances shall be done during installation of the anode mesh and continuously monitored during application of the concrete overlay. Short circuits shall be removed and the area retested prior to proceeding with the concrete overlay. When the area requiring treatment to correct short circuits is equal to or less than 150 mm x 150 mm, the anode mesh shall be cut clear. When the area requiring treatment is greater than 150 mm x 150 mm, the anode mesh shall be separated from the concrete surface using a plastic spacer mesh. The location and extent of the areas requiring treatment, and the treatment undertaken to eliminate the short circuit shall be recorded and submitted to the Contract Administrator. Before installation of the waterproofing on the concrete overlay and at each stage, a test shall be done to confirm that there are no short circuits by temporarily applying a direct current using a portable DC power supply sufficient to produce and applied current density of 10 mA/m2. When the occurrence of a short circuit is detected, the short circuit shall be located and removed. The Contractor shall submit results of all tests to the Contract Administrator and the test results shall be certified by the Corrosion Specialist.

January 2004 Pg. 25 of 30 SSP999S27

Page 26: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

7.10.04 Trial Operating Period – Acceptance Testing 7.10.04.01 General Prior to the acceptance of the Work, the Contractor shall demonstrate that all components of the cathodic protection system, including the rectifier and RMU, are in proper working order. No short circuits are permitted between the anode mesh and its hardware and the reinforcing steel or any other metallic components of the structure in contact with the reinforcing steel, such as drainage pipe or expansion joints. Field readings taken during the trial operating period shall be taken by a NACE accredited cathodic protection/corrosion technologist under the direct corporate supervision of the Corrosion Specialist. The system shall be energized for a period of 72 hours at a power level that applies an average current density of 2 mA/m2 on all cathodically protected areas of the structure. If AC power is not available at the site at the time of the trial operating period, power shall be provided to the rectifier and remote monitoring by means of a portable generator supplied by the Contractor. When field testing of the installed cathodic protection system is being conducted, the Contractor shall arrange to have the Contract Administrator and Ministry Representative in attendance. The Ministry may choose to have a qualified representative present during the acceptance testing. The Contract Administrator shall be informed 4 working days in advance of the planned trial operating period. When measuring the potential of reference cells, the negative lead of the multimeter shall be connected to the reference cell lead wire and the positive lead to the cathode CM wire. The polarity sign of the reading shall be recorded. Testing shall be done when the air temperature is at least 5oC. The Contractor shall submit the results of all tests to the Contract Administrator and the test results shall be certified by the Corrosion Specialist. 7.10.04.02 Testing Prior to Energizing the System 7.10.04.02.01 Embedded Components Immediately prior to activating the system, the following measurements shall be made at the control panel and recorded: a) Reference cell potential, in mV, relative to cathode CM cable. b) Voltage between each anode or anode bus and cathode CS cable, in volts. c) Resistance, AC, between each reference cell and cathode CM cable, in ohms. d) Resistance, AC, between each anode or anode bus and cathode CS cable, in ohms. e) Resistance between CM and CS cathode connections, in ohms. f) Voltage between CM and CS cathode connections, in mV. To meet the requirements of this specification the readings obtained shall be according to requirements of Table 2.

January 2004 Pg. 26 of 30 SSP999S27

Page 27: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

Table 2 COMPONENT RESISTANCE (OHMS) VOLTAGE Reference Cell – Graphite 10 – 1000 Stable Reference Cell – Silver-Silver Chloride

As per MFG. recommendations

Stable

Cathode Connection < 2 < 1 mV Anode < 3 stable 7.10.04.02.02 Rectifier The Contractor shall demonstrate that the rectifier assemblies will function properly throughout the full operating range of the output current and voltage according to OPSS 2325. The rectifier assemblies shall not be connected to the cathodic protection system at the time the testing is conducted. 7.10.04.02.03 Remote Monitoring Unit The Contractor shall demonstrate that the operation of the RMU meets the requirements specified in OPSS 2324. The following readings shall be taken manually at the site and by the RMU using a portable computer on site and a computer at a remote location. a) Voltage b) Current c) Reference cells d) Temperature All the measurements obtained by the RMU shall be the same as the readings obtained manually on site. The Contractor shall provide results of all tests to the Contract Administrator and the test results shall be certified by the Corrosion Specialist. 7.10.04.03 Testing after Energizing the System After the system is activated, the following readings shall be made for a period of 72 hours using the manual on site or automatic remote technique. a) Current and voltage. b) Current flow to each area of the system, zones and/or subzones, or anode bus, as applicable. c) Reference cell potentials, on and instant-off. d) Thermocouples. The manual readings shall be taken on an hourly basis during the work hours, and the readings obtained from the RMU shall be taken on an hourly basis. Immediately after the 72-hour readings are made, the system shall be switched off and allowed to depolarize for a period of four hours. At the end of the four-hour depolarization period, reference cell

January 2004 Pg. 27 of 30 SSP999S27

Page 28: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

potentials shall be recorded and the differences between instant-off readings at 72 hours and the 76-hour readings shall be calculated. Voltage between anodes and cathode shall also be recorded. The performance of the system shall be monitored during the trial operating period and appropriate actions shall be taken to repair any defects detected. The trial operating period shall be repeated as many times as required to prove proper functioning of the system. Within seven days of the completion of the trial operating period, a report shall be submitted to the Contract Administrator recording: a) The dates and times of the periods of trial operation. b) Names of individuals collecting and recording data. c) Equipment used, including power source if applicable. d) All readings noted above, labelled as to appropriate zone, subzone, or bus, as applicable. e) All remedial action taken. The report shall be signed by the Corrosion Specialist verifying that: a) The rectifier and remote monitoring unit are functional. b) The wiring of the system complies with contract drawings, and the labelling and identification of

wire terminations is correct in the control panel. c) All areas, zones and subzones, or buses, as applicable, of the system were functional and received

current flow during the trial operating period. d) There are no short circuits between anodes and cathodes. e) There are no short circuits between reference cells and cathode. f) The accuracy of all meters and proper circuit polarity has been verified using a multimeter. 7.11 Remedial Work Work not meeting the acceptance requirements shall be repaired or replaced. Proposals for correcting the deficiency shall be submitted to the Contract Administrator for review and comment prior to commencement of the remedial work. 7.12 Management and Disposal of Excess Material Management and disposal of excess material shall be according to OPSS 180. 8.0 QUALITY ASSURANCE 8.01 Anode Mesh A manual pull test will be randomly conducted on the weld connecting the anode mesh to the distribution bar to check the weld quality.

January 2004 Pg. 28 of 30 SSP999S27

Page 29: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

8.02 Control and Monitoring Equipment The Contractor, through the agreement to purchase control and monitoring equipment, shall ensure the Ministry's representative be permitted access to the place of assembly of the cathodic protection equipment assembly while work on the unit is being performed, for the purpose of inspecting the work and examining plant records, certificates, materials being used, process of fabrication and to request further tests as required. 8.03 Acceptance and Rejection Work not meeting the requirements of this specification will be subject to rejection. 9.0 MEASUREMENT FOR PAYMENT 9.01 Plan Quantity Measurement 9.01.01 Cathode Connections Reference Cells Cathodic Protection Cabinets Concrete Pad For Cathodic Protection Measurement for payment will be made for each of the above tender items by Plan Quantity, as may be revised by adjusted Plan Quantity. The unit of measure is each. 9.01.02 Anode Mesh Measurement shall be made in square metres for the full face of the concrete being treated and with no deduction for minor areas not covered at corners, cutouts and the like, nor any addition for areas which require overlapping mesh, by Plan Quantity as may be revised by Adjusted Plan Quantity. 9.02 Non Measurement 9.02.02 Extra Low Voltage Cables For Cathodic Protection Cathodic Protection Rectifiers Cathodic Protection Remote Monitoring And Control Units Rigid Ducts And Junction Boxes For Cathodic Protection Acceptance Testing For Cathodic Protection There will be no measurement for the above tender items when designated in the tender as Lump Sum.

January 2004 Pg. 29 of 30 SSP999S27

Page 30: CATHODE CONNECTIONS – Item No · cathode connections – item no. reference cells ... cathodic protection rectifiers – item no. cathodic protection remote monitoring and control

10.0 BASIS FOR PAYMENT 10.01 Cathode Connections – Item Reference Cells – Item Cathodic Protection Cabinets – Item Concrete Pads For Cathodic Protection – Item Anode Mesh - Item Extra Low Voltage Cables For Cathodic Protection - Item Cathodic Protection Rectifiers - Item Cathodic Protection Remote Monitoring And Control Units – Item Rigid Ducts And Junction Boxes For Cathodic Protection - Item Acceptance Testing For Cathodic Protection - Item Payment at the contract price for the above tender items shall be full compensation for all labour, equipment and materials to do the work.

January 2004 Pg. 30 of 30 SSP999S27