catching rays: solar pv commissioning - · pdf filethis presentation will outline the...

Download Catching Rays: Solar PV Commissioning -  · PDF fileThis presentation will outline the commissioning process for solar ... Solar Roadways? ( ) Planes, Trains & Automobiles?

If you can't read please download the document

Upload: nguyencong

Post on 06-Feb-2018

223 views

Category:

Documents


1 download

TRANSCRIPT

  • Wayne A. Dunn, PE, PEng

    Catching Rays Solar PV Commissioning

  • AIA Quality Assurance

    The Building Commissioning Association is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES). Credit(s) earned on completion of this program will be reported to AIA/CES for AIA members. Certificates of Completion for both AIA members and non-AIA members are available upon request.

    This program is registered with AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product.

    Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.

  • This presentation will outline the commissioning process for solar photovoltaic systems and cover lessons learned from a recent 150 kW (nominal) construction project in the state of Florida.

    Commissioning providers, owners, designers and construction teams working with these special systems can apply lessons learned from these experiences to benefit their own projects.

    Course DescriptionCourse Description

  • At the end of this session, participants will be able to apply lessons learned in the following categories:

    1. Solar Energy Profile2. Risk Management During Design3. Quality Assurance During Construction4. System Testing & Performance Verification5. Technology Transfer / Operation & Maintenance6. Solar PV ---future

    Learning ObjectivesLearning Objectives

  • Catching Rays

  • Catching Rays

  • Passive Solar

  • Solar Heating & Furnace

  • Concentrated Solar

  • Solar PV Types & Efficiencies (NREL)

  • Solar PV Applied

  • Photovoltaic Project OverviewFL Dept. of Health

    State Owned Campus 17 buildings ~1.7 M Sq. Ft.

    ARRA funded $1,340,982

    150 kW (Nominal) Fixed 21 Angle South-Facing 2 Sub-Arrays

    Suniva ART 240 Modules Satcon PVS 75 kW

    Inverters Remote Monitoring System

  • Project Design Criteria

    Decision Cycle Which Building? How much roof? Watts / Panel Buy America Inverter Locations Lightning Protection Equipment Installation

    Roof Access Elevators vs. Stairs

  • Project Metrics

    Solar Power System Array Breakdown1 Panel (Module)240 W

    60 Cells

    1 String3120 W

    13 Panels

    1 Group18.7 kW

    6 Strings(78 panels)

    1 Sub-Array75 kW

    4 Groups(24 Strings)(312 Panels)

    Total System150 kW

    2 Sub-Arrays(8 Groups)(48 Strings)(624 Panels)

  • Project Design Criteria

    System Design Watts / Panel MFG / UL Requirements Panels / String

    Max System Voltage: 600 VDC UL- 5% Voc Tolerance- -0.332 (%Voc / F) Temp. Coeff. vs. STC- 37.2 Voc / Panel

    581.8 VDC at Record Low 13 Panels / String

    Strings/Combiner Wire Sizing

  • Design Phase Cx - Overview

    Recommendations Factory Testing

    Modules Not inverter

    Cx Requirements Documentation Testing Methodology Meters / Verification

    Remote Monitoring Weather Station Software

    Labeling / ID

  • Design Phase Cx Factory Testing

    Recommendations Confirm the Following:

    Production Capacity Manufacturing Processes

    - Cell here, modules there Quality Control Processes Proof of Performance

  • Design Phase Cx Solar Panel Installation

    Design Considerations Efficiency Size Panels per String Panel Mounting

    Clamps Height Above Roof

  • Design Phase Cx Interface

    Communications Remote Monitoring

    Software Status / Maintenance Weather Performance

    - Predicted- Actual

    Dashboard

  • Design Phase Cx Communications

    Challenges Department IT

    Infrastructure Coordination

    Contractor Submittals What are we Getting? What format?

    Implementation When are we Getting It? Hardware Features Lacking Who Configures Software? Not my Responsibility

  • Design Phase Cx Weather Station

    Weather Station Panel Cell

    Temperature Ambient Temperature Solar Irradiance

    (W/m2) Wind Speed / Direction Remote Monitoring

  • Design Phase Cx Weather Station

    Challenges Communications Application

    Solar Radiation Sensor Angle- Installed Horizontal

    UV / Sun tan application- No adjustment

    Jury rigged angle Cell Temperature Sensor

    - Installed Loose Under Panels No Relative Humidity No Barometric Pressure

  • Design Phase Cx Labeling / Identification

    Design Approach Clear and Consistent

    Individual panels Strings String Groups Inverters

    Challenges Panels not labeled Combiner Boxes not labeled As-Built vs. As-Labeled

    String 4-A on Inverter B?

  • Construction Phase Cx Submittal ReviewEquipment Submittals

    PV Modules Inverters Combiner Boxes Re-Combiner Boxes Weather Station

    Software Submittals Remote Monitoring Dashboard

    Coordination Submittals Equipment

    Labeling Layout

  • Factory ReviewFactory Inspection

    Buy America Confirmed Made in China Assembled in US

    Comfort Level Production Capacity Factory Quality Control Quality Assurance

    Technical Insight Performance Verification Troubleshooting

  • Construction Phase Cx Installation VerificationInstallation Verification

    DC System Wiring / Conduits

    - UV / Weather Protection- Clamp Installation- Check Torques

    Solar PV Panel Mounting- Ponding- Clamp Installation

    Combiners / Recombiners Disconnects

    Oh yeahSafety

  • Construction Phase Cx Installation VerificationInstallation Verification

    AC System Inverters

    - 4 vs. 5-Wire- Ethernet Comm Board

    Wiring / Conduits Disconnects / Shunt Trip

    Weather Station Communications Lightning Protection

    No UL Certificate

  • Construction Phase Cx Performance Verification

  • Construction Phase Cx Performance Verification

  • Technology TransferSystems Manual

    Provide O&M Staff System Level Understanding Useful Information Instructions Diagrams

    Record Documents Content Turnover Schedule

    Training Content Scheduling / Coordination Agenda

  • Technology Transfer I am SO confusedRecord Documents

    As-Builts not latest drawing revision.

    Missing O&Ms and Warranties. Afterthought.

    Trainingin spec?!! Not Coordinated. Agenda not Approved. Inadequate

    No Software Training

    Not worth the fight.

  • DC-to-AC Derate as Advertised?

    77% Typical (NREL.gov)

    88% DOH

    Why? Module Tolerances Inverter Losses Wiring Losses Soiling System Availability

    O&M - Expected vs. Actual Performance

  • O&M Ongoing Performance Verification

    Why Bother? Solar Panel Warranties often Performance Based Predictive Maintenance Maximize Energy Savings

  • O&M Lessons Learned

    Whos the Boss? Help Owner Determine Key O&M Staff

    Building Manager vs. Electrical Group

    Develop Preventative Maintenance ProgramSystem Integration

    Too Many Systems to Monitor Multiple Solar System Web Interfaces Not integrated to main campus BAS.

    BAS / EMS Critical Information Status Key Power Information Weather Data Useful for HVAC Control

  • O&M Ongoing Performance Verification

  • O&M Ongoing Performance Verification

  • O&M Ongoing Performance Verification

  • O&M Solar Power Dashboard

  • Solar Future(dead, dying or retrenching & growing)

    Major Closures for First Solar, SunpowerSteven Leone (renewableenergyworld.com)

    Despite Solyndra's Death, the Future of Solar Energy Is SunnySteven Pleging CEO/ President Quantum Solar (Huffington Post)

  • Solar Future(tipping point)

    McKinsey & Company: Solar Power: Darkest before dawnApril 2012 : Krister Aanesen, Stefan Heck, and Dickon Pinner

  • Solar Future(tipping point)

  • Cool Concentrator?(www.coolearthsolar.com)

  • Solar Roadways?(www.solarroadways.com)

  • Planes, Trains & Automobiles?

  • Give Credit Where Credit is Due

    Aaron Fancher, PE (www.pegengineering.com ) Troy Strand (www.indenergysolutions.com ) Blake Gleason, PE (www.sunlightandpower.com ) Adrian Brunoi (www.solarsource.net ) Mckinsey & Co. (www.mckinsey.com ) All who freely publish on the WEB

  • Wayne A. Dunn, PE, PEng

    E.W. Dunn

    [email protected]