catching rays: solar pv commissioning - · pdf filethis presentation will outline the...
TRANSCRIPT
Wayne A. Dunn, PE, PEng
Catching Rays Solar PV Commissioning
AIA Quality Assurance
The Building Commissioning Association is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES). Credit(s) earned on completion of this program will be reported to AIA/CES for AIA members. Certificates of Completion for both AIA members and non-AIA members are available upon request.
This program is registered with AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product.
Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
This presentation will outline the commissioning process for solar photovoltaic systems and cover lessons learned from a recent 150 kW (nominal) construction project in the state of Florida.
Commissioning providers, owners, designers and construction teams working with these special systems can apply lessons learned from these experiences to benefit their own projects.
Course DescriptionCourse Description
At the end of this session, participants will be able to apply lessons learned in the following categories:
1. Solar Energy Profile2. Risk Management During Design3. Quality Assurance During Construction4. System Testing & Performance Verification5. Technology Transfer / Operation & Maintenance6. Solar PV ---future
Learning ObjectivesLearning Objectives
Catching Rays
Catching Rays
Passive Solar
Solar Heating & Furnace
Concentrated Solar
Solar PV Types & Efficiencies (NREL)
Solar PV Applied
Photovoltaic Project OverviewFL Dept. of Health
State Owned Campus 17 buildings ~1.7 M Sq. Ft.
ARRA funded $1,340,982
150 kW (Nominal) Fixed 21 Angle South-Facing 2 Sub-Arrays
Suniva ART 240 Modules Satcon PVS 75 kW
Inverters Remote Monitoring System
Project Design Criteria
Decision Cycle Which Building? How much roof? Watts / Panel Buy America Inverter Locations Lightning Protection Equipment Installation
Roof Access Elevators vs. Stairs
Project Metrics
Solar Power System Array Breakdown1 Panel (Module)240 W
60 Cells
1 String3120 W
13 Panels
1 Group18.7 kW
6 Strings(78 panels)
1 Sub-Array75 kW
4 Groups(24 Strings)(312 Panels)
Total System150 kW
2 Sub-Arrays(8 Groups)(48 Strings)(624 Panels)
Project Design Criteria
System Design Watts / Panel MFG / UL Requirements Panels / String
Max System Voltage: 600 VDC UL- 5% Voc Tolerance- -0.332 (%Voc / F) Temp. Coeff. vs. STC- 37.2 Voc / Panel
581.8 VDC at Record Low 13 Panels / String
Strings/Combiner Wire Sizing
Design Phase Cx - Overview
Recommendations Factory Testing
Modules Not inverter
Cx Requirements Documentation Testing Methodology Meters / Verification
Remote Monitoring Weather Station Software
Labeling / ID
Design Phase Cx Factory Testing
Recommendations Confirm the Following:
Production Capacity Manufacturing Processes
- Cell here, modules there Quality Control Processes Proof of Performance
Design Phase Cx Solar Panel Installation
Design Considerations Efficiency Size Panels per String Panel Mounting
Clamps Height Above Roof
Design Phase Cx Interface
Communications Remote Monitoring
Software Status / Maintenance Weather Performance
- Predicted- Actual
Dashboard
Design Phase Cx Communications
Challenges Department IT
Infrastructure Coordination
Contractor Submittals What are we Getting? What format?
Implementation When are we Getting It? Hardware Features Lacking Who Configures Software? Not my Responsibility
Design Phase Cx Weather Station
Weather Station Panel Cell
Temperature Ambient Temperature Solar Irradiance
(W/m2) Wind Speed / Direction Remote Monitoring
Design Phase Cx Weather Station
Challenges Communications Application
Solar Radiation Sensor Angle- Installed Horizontal
UV / Sun tan application- No adjustment
Jury rigged angle Cell Temperature Sensor
- Installed Loose Under Panels No Relative Humidity No Barometric Pressure
Design Phase Cx Labeling / Identification
Design Approach Clear and Consistent
Individual panels Strings String Groups Inverters
Challenges Panels not labeled Combiner Boxes not labeled As-Built vs. As-Labeled
String 4-A on Inverter B?
Construction Phase Cx Submittal ReviewEquipment Submittals
PV Modules Inverters Combiner Boxes Re-Combiner Boxes Weather Station
Software Submittals Remote Monitoring Dashboard
Coordination Submittals Equipment
Labeling Layout
Factory ReviewFactory Inspection
Buy America Confirmed Made in China Assembled in US
Comfort Level Production Capacity Factory Quality Control Quality Assurance
Technical Insight Performance Verification Troubleshooting
Construction Phase Cx Installation VerificationInstallation Verification
DC System Wiring / Conduits
- UV / Weather Protection- Clamp Installation- Check Torques
Solar PV Panel Mounting- Ponding- Clamp Installation
Combiners / Recombiners Disconnects
Oh yeahSafety
Construction Phase Cx Installation VerificationInstallation Verification
AC System Inverters
- 4 vs. 5-Wire- Ethernet Comm Board
Wiring / Conduits Disconnects / Shunt Trip
Weather Station Communications Lightning Protection
No UL Certificate
Construction Phase Cx Performance Verification
Construction Phase Cx Performance Verification
Technology TransferSystems Manual
Provide O&M Staff System Level Understanding Useful Information Instructions Diagrams
Record Documents Content Turnover Schedule
Training Content Scheduling / Coordination Agenda
Technology Transfer I am SO confusedRecord Documents
As-Builts not latest drawing revision.
Missing O&Ms and Warranties. Afterthought.
Trainingin spec?!! Not Coordinated. Agenda not Approved. Inadequate
No Software Training
Not worth the fight.
DC-to-AC Derate as Advertised?
77% Typical (NREL.gov)
88% DOH
Why? Module Tolerances Inverter Losses Wiring Losses Soiling System Availability
O&M - Expected vs. Actual Performance
O&M Ongoing Performance Verification
Why Bother? Solar Panel Warranties often Performance Based Predictive Maintenance Maximize Energy Savings
O&M Lessons Learned
Whos the Boss? Help Owner Determine Key O&M Staff
Building Manager vs. Electrical Group
Develop Preventative Maintenance ProgramSystem Integration
Too Many Systems to Monitor Multiple Solar System Web Interfaces Not integrated to main campus BAS.
BAS / EMS Critical Information Status Key Power Information Weather Data Useful for HVAC Control
O&M Ongoing Performance Verification
O&M Ongoing Performance Verification
O&M Ongoing Performance Verification
O&M Solar Power Dashboard
Solar Future(dead, dying or retrenching & growing)
Major Closures for First Solar, SunpowerSteven Leone (renewableenergyworld.com)
Despite Solyndra's Death, the Future of Solar Energy Is SunnySteven Pleging CEO/ President Quantum Solar (Huffington Post)
Solar Future(tipping point)
McKinsey & Company: Solar Power: Darkest before dawnApril 2012 : Krister Aanesen, Stefan Heck, and Dickon Pinner
Solar Future(tipping point)
Cool Concentrator?(www.coolearthsolar.com)
Solar Roadways?(www.solarroadways.com)
Planes, Trains & Automobiles?
Give Credit Where Credit is Due
Aaron Fancher, PE (www.pegengineering.com ) Troy Strand (www.indenergysolutions.com ) Blake Gleason, PE (www.sunlightandpower.com ) Adrian Brunoi (www.solarsource.net ) Mckinsey & Co. (www.mckinsey.com ) All who freely publish on the WEB
Wayne A. Dunn, PE, PEng
E.W. Dunn