Page 1: building of Sea wolf project 2007

Seawolf Project

Building a charter boat service on Lake Ray Hubbard

Page 2: building of Sea wolf project 2007

Steps

• First step was to get my USCG Master Captains license – the course took a total of 10 days and costs $1200.

• Second was to make sure I could get Liability insurance

• Third was to make a deal for docking and pick up of passengers

• Next was to find a boat

Page 3: building of Sea wolf project 2007

Make or Buy

• I found you can buy a 40 ft white fiberglass sailing catamaran that can take 40 passengers in South Florida New for about $650,000. The problem was that it was 25 feet wide and would cost $100,000 to ship to North Texas

• I determined that I could build one for much less and make out wood leaving a natural wood finish.

Page 4: building of Sea wolf project 2007

How much time and Money?

• Cost of Materials $200,000

• Labor $100,000

• Time: July 2006 to April 2008

• Two years of my life

• Survey shows that most boats take out about 2,000 passengers a year.

• The boat comes apart so if it does not work on Lake Ray Hubbard, I can move it.

Page 5: building of Sea wolf project 2007

Sail Plan – Malcolm Tennent is world Famous Yacht Designer

Cost of plans $5,500

Page 6: building of Sea wolf project 2007

Interior of Hull Malcolm Tennent – New Zealand

Page 7: building of Sea wolf project 2007

Setting up forms

Page 8: building of Sea wolf project 2007

Lofting the hulls

Page 9: building of Sea wolf project 2007

Setting forms in place

Page 10: building of Sea wolf project 2007

Spanish Cedar from Stuart Florida 16,000 liner feet at $2.65 a foot

Page 11: building of Sea wolf project 2007

Forms are set up in Oct 2006

Page 12: building of Sea wolf project 2007

Setting the bow stem

Page 13: building of Sea wolf project 2007

Planking of the Hull

Page 14: building of Sea wolf project 2007

Planking the hull

Page 15: building of Sea wolf project 2007

Fairing the hull

Page 16: building of Sea wolf project 2007

Adding the bow

Page 17: building of Sea wolf project 2007

Filling the gaps

Page 18: building of Sea wolf project 2007

One hull done starting number 2

Page 19: building of Sea wolf project 2007

Finishing hull # 1

Page 20: building of Sea wolf project 2007

Sand and fair the Hull, Nov. 2007

Page 21: building of Sea wolf project 2007

Apply layer of fiberglass

Page 22: building of Sea wolf project 2007

Taking deck off to fiberglass

Page 23: building of Sea wolf project 2007

Filling gaps in strip planks

Page 24: building of Sea wolf project 2007

Building seats into deck

Page 25: building of Sea wolf project 2007

Greg Working on Deck

Page 26: building of Sea wolf project 2007

Installing ring frame

Page 27: building of Sea wolf project 2007

6 oz glass and epoxy

Page 28: building of Sea wolf project 2007

Taking the deck off

Page 29: building of Sea wolf project 2007

Finishing Seawolf Hulls

Page 30: building of Sea wolf project 2007

Aluminum cross beams

Page 31: building of Sea wolf project 2007

Working on Mast

Page 32: building of Sea wolf project 2007

Leaving factory for Marina

Page 33: building of Sea wolf project 2007

Ready to move to Marina

Page 34: building of Sea wolf project 2007

Mounting the Crossbeams

Page 35: building of Sea wolf project 2007

Stepping the Mast

Page 36: building of Sea wolf project 2007

Mounting Deck beams

Page 37: building of Sea wolf project 2007

Ready to launch

Page 38: building of Sea wolf project 2007

Seawolf under sail

Page 39: building of Sea wolf project 2007

Boarding the boat

Page 40: building of Sea wolf project 2007

Enjoying the sail on Seawolf

Page 41: building of Sea wolf project 2007

Parties and Romanic moments

Page 42: building of Sea wolf project 2007

Plenty of space for up to 49

Page 43: building of Sea wolf project 2007

Great Publicity in Dallas

Page 44: building of Sea wolf project 2007

Seawolf at a distance

Page 45: building of Sea wolf project 2007

2 minute video of the Project

By Mark Walsh’

nVision Digital

469 556 9408

Nvisiondigital.net

Page 46: building of Sea wolf project 2007

How are we doing?

• In 2012 we had over 11,500 passengers

• Over 52,000 passengers since beginning.

• I hope to keep doing this until 2020.

• Our season starts again April 16.