Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016

Upload: trinhhanh

Post on 18-Aug-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

Bucks Relicensing ProjectFERC Project No. 619

Reservoir Level Assessment RR-S3(TM-16) Study Results Meeting

February 3, 2016

Page 2: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

2

Reservoir Level Assessment RR-S3

Page 3: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

3

Study Goals and Objectives

• Goal: Compile data to evaluate reservoir level effects on recreation.

• Objectives: Evaluate historical reservoir levels.– Map reservoir and identify shallow areas.

– Review boat ramp conditions and boat access.

– Compile and evaluate boat accident data.

Page 4: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

4

Study Area and Sites

Page 5: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

5

Methods

• Lake Levels– compile reservoir storage data 1931 - 2013

• Light Detection and Ranging (LiDAR) – 3d photos from fixed-wing aircraft

– GIS contour map

• Boat Launch– evaluate conditions of boat ramps

– evaluate launch suitability at low reservoir levels

• Accident– reports and interviews with Plumas County

Sheriff’s office & Cal Boating

Page 6: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

6

RESULTS – Historic Lake Levels

Average Daily Reservoir Elevation 1932 -2013

Page 7: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

7

RESULTS – Average Frequency of Summer Boating Opportunities

Reservoir Elevation Frequency 2004-2013

Page 8: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

8

RESULTS – LiDAR Bucks Lakeshore Resort

Page 9: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

9

RESULTS – LiDAR Haskins Boat Launch

Page 10: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

10

RESULTS – LiDAR Bucks Lake Dam

Page 11: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

11

RESULTS – Lakeshore Boat Launch

Page 12: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

12

RESULTS – Bucks Lake Marina Boat Launch

Page 13: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

13

RESULTS – Haskins Valley Boat Launch

Page 14: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

14

RESULTS – Sandy Point Boat Launch

Page 15: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

15

RESULTS – Boating Accidents

Total: Four (4) reported boating accidentsYear: 2001, 2002, 2004, 2013Month: June, July, August, SeptemberDay: Thursday (1), Saturday (2), Sunday (1)Holiday: One accident on holiday weekendTime: 12:00 noon to 2:00 p.m. (1); 4:00 p.m. to 6:00 p.m. (3)Type: Four accidents involved a collision between vesselsCause: Three accidents due to operator inattention, one due to operator

inexperience, and one due to moving at excessive speedVessel: Three motorboats, two jet skis, and two pontoon boatsCounty: About 3,200 vessels registered

Page 16: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

16

Summary of Results

• No documented accidents related to lake levels

• No documented instances of collisions with obstacles such as rocks or stumps

• Primary issue is access and aesthetics at low lake levels– Bucks Lake is almost always accessible for launching boats Labor

Day to Memorial Day– May and October, lake levels are occasionally lower than usable end

of boat ramps

• Condition of boat ramps maybe an issue– Sediment buildup at Sandy Point– Surface condition of Haskins– Operating season at Haskins

Page 17: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

17

Remaining Study Elements

• Implementation of the study is considered complete

• Technical Memorandum is considered final – Unless other studies determine that reservoir level affects

other resources.

– If so, Technical Memorandum may be updated, if needed.

Page 18: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

18

Study Description Variances

• One variance to the FERC-approved study. – The study used four water year types, Critically Dry, Dry,

Normal, and Wet, based on the California Department of Water Resources records of annual inflow to Lake Oroville

Page 19: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

19

Discussion

Page 20: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

20

RESULTS – LIDAR Bucks lake Dam

Page 21: Bucks Relicensing Project FERC Project No. 619 · Bucks Relicensing Project FERC Project No. 619 Reservoir Level Assessment RR-S3 (TM-16) Study Results Meeting February 3, 2016. 2

21

RESULTS – Reservoir Elevation Frequency May- Oct, Critically Dry