brunswick county schools · southport elementary school supply elementary brunswick county schools...
TRANSCRIPT
Board Members: Catherine D. Cooke, Chairman • Ellen G. Milligan, Vice-Chairman • Charles W. Miller • Harry E. Lemon, Jr. • Gerald D. Benton, Jr.
Dr. Jerry L. Oates, Superintendent
BRUNSWICK COUNTY SCHOOLS
35 Referendum Drive · Bolivia, North Carolina 28422 · Phone: 910-253-2900 · Fax: 866-291-7891
Date: May 5, 2020 Bid Request No: 153.VAR.20.BOND.128
Bids Due By: May 18 at 3:00 PM
Project Name and Location: Restroom Renovations-South South Brunswick High School South Brunswick Middle School Virginia Williamson Elementary School Southport Elementary School Supply Elementary
Brunswick County Schools is informally requesting bids for the performance of the following work or services. Bids shall be binding for 30 days. Information regarding this Informal Bid Request may be obtained from David Barbour at Office (910) 253-1060, Mobile (910) 274-1076 or [email protected]. Bids can be emailed to [email protected] with READ RECIEPT REQUESTED on Emailed bids. PROJECT DESCRIPTION: See Exhibit 1 for a detailed description of the project scope and requirements, and for school addresses. PROJECT SCHEDULE: The Contractor shall begin the work upon receipt of the Purchase Order, and expeditiously, with adequate forces, complete the work within the specified calendar days. The required milestone dates, and completion date are included in Exhibit 1. The contractor shall coordinate all work with Operations personnel to ensure minimal disruption to school activities. Should the Contractor fail to substantially complete the Work on or before the date stipulated for Substantial Completion, or such later date as may result from extension of time granted by Owner, he shall pay the Owner, as liquidated damages, the sum of Two Hundred and Fifty Dollars ($250.00) for each consecutive calendar day that terms of the contract remain unfulfilled beyond the date allowed by the Contract, which sum is agreed upon as a reasonable and proper measure of damages which the Owner will sustain per day by failure of the Contractor to complete Work within time as stipulated; it being recognized by the Owner and the Contractor that the injury to the Owner which could result from a failure of the Contractor to complete on schedule is uncertain and cannot be computed exactly. In no way shall costs for liquidated damages be construed as a penalty on the Contractor. TERMS AND CONDITIONS Brunswick County Schools Contract, is included in Exhibit 2. The selected contractor will be required to sign this contract, and Sexual Offender Registry Check Certification Form, included as Exhibit 2.1, as each are a part of this Request for Bid and will govern this work.
FORM OF BID The Form of Bid is included as Exhibit 3
Board Members: Catherine D. Cooke, Chairman • Ellen G. Milligan, Vice-Chairman • Charles W. Miller • Harry E. Lemon, Jr. • Gerald D. Benton, Jr.
Dr. Jerry L. Oates, Superintendent
EXHIBIT 1 – SCOPE OF WORK
PRE-BID MEETING: There will be a pre- bid meeting scheduled for this bid. Pre-Bid meeting will be held at 10:00 AM on May 11, 2020 at North Brunswick High School and then move to Leland Middle School. Bidding Contractors can visit sites upon contacting Capital Projects and Planning to receive a Site Visit Authorization Form. Please confirm by emailing David Barbour at [email protected]. .
SCOPE OF WORK & SCHEDULE The contractors are responsible for all items required to complete the scope of services, those items being included in the scope of services even if not listed below. The subcontractor’s workmanship shall be equal to or exceed the workmanship of reputable contractors performing similar work in the Wilmington Metropolitan Service Area. Contractor shall perform the following scope of work in compliance with all federal, state, and local codes and in accordance with any plans, specifications and engineered drawings, design or criteria. The general scope involves demolition and renovation of specified staff restrooms along with some restrooms at
high school gymnasiums. Work to include but not limited to Demolition of tile, epoxy and VCT flooring, Installation of new Quarry Tile Flooring and Base, plumbing fixture replacement, electrical fixture replacement, paint, stain, drywall repair, door hardware replacement, Toilet Partition removal/replacement/re-use, HVAC grill replacement and all incidental work relating to the project in order to provide complete and fully functional operating restroom facilities. Contractor is responsible for scope and to verify all dimensions and sizes.
For Estimating purposes Bidders should estimate Toilet Partitions as Standard Stalls 2’ x 5’ and ADA Stalls 5’ x 6’.
GENERAL Brunswick County Schools has a policy of No Contact, Socialization, Or Fraternization between contractor
personnel and students or school staff. All Brunswick County Board of Education property is designated as non-smoking non-tobacco use areas. All employees must sign a Policy Compliance Form prior to mobilization to the site.
Lump Sum Bid to include all applicable taxes, shipping costs, and delivery lead time once selections made. The contractor shall provide Brunswick County Schools with a list of subcontractors along with subcontractor’s
contact information that will be performing work for the contractor. The contractor shall supply submittals, shop drawings, color selections samples, schedule of
construction, and a schedule of values prior to commencement of the work. The contractor shall schedule and perform the work without impeding or interfering with day to day school
activities, functions, classes, etc… This may include installing temporary routes, barricades, etc… for The protection of the public where the work is to be performed
Contractor shall obtain all required permits and pay all fees associated with this work. Contractor will be responsible for having all utilities, power lines, water lines, sewer lines, gas lines, telephone
lines, data lines, communication lines, etc… located by locating service as necessary. Contractor shall maintain a safe and clean work environment. Contractor shall maintain a dumpster on site for
duration of the project with periodic hauling off of trash and construction debris. Contractor is responsible for daily cleanup of any trash and construction debris to maintain a safe and clean job site.
Contractor shall provide its employees and subcontractors with a portable restroom facility to be maintained, cleaned and emptied weekly.
Work area is to be left safe at the close of each workday. Leave no unfilled/protected holes. Remove all aluminum cuttings/waste immediately. Do not interrupt power, telephone or communication systems. Coordinate work with Capital Projects Office.
Safety: Contractor shall erect barriers as needed, to prevent pedestrians and vehicles from entering the work area. Contractor to provide and use any and all equipment needed to complete the work following all OSHA guidelines and requirements.
Contractor shall complete Architect’s, Engineer’s, or Owner’s punch list before final payments and release of retainage will be issued.
Upon completion of the work the contractor is to perform a final construction cleaning of all surfaces and areas associated with this project.
Scope: The Scope of work includes but is not limited to the following Scope Sheets and Scope Sheet items for each Restroom as listed below:
South Brunswick High School:
SBHS-Boys @ Cafeteria
SBHS-Girls @ Cafeteria
Main Office-Staff
South Brunswick Middle School:
SBMS-Boys-Cafeteria SBMS-Girls-Cafeteria
Virginia Williamson Elementary School:
Boys 4th/5th Grade Hall Girls 4th/5th Grade Hall
Southport Elementary School
Boys-Cafeteria Girls-Cafeteria
Supply Elementary School:
Boys K-1 ALLOWANCES:
1. Each Contractor shall include an allowance of $ 7,500.00 for a general owners allowance in their Base Bid amount. Allowances will be used for Owner requested and authorized, out-of-scope work. The contractor will invoice allowance amounts as a separate line item.
Warranty: Provide Mfg Standard Warranty on all Materials; Provide Standard Industry Warranty on Installation. SCHEDULE:
- Anticipated Project Start Date: June 1, 2020 - Project Completion Date: August 14, 2020 - Submittals to be provided upon receipt of PO to assure materials available at project start date - Contractor to provide Schedule to CPP including permitting, submittals, construction start, delivery
dates, timeline for major construction activities, final clean-up, and punch list - If work involves weekends or holidays Contractor to have schedule approved in advance by Capital
Projects & Planning. Access into the schools facilities will have to be coordinated three days in advance.
- TOILET PARTITIONS Field Measurements: Verify actual locations of toilet fixtures, walls, columns, ceilings, and other construction contiguous with toilet compartments by field measurements before fabrication. PERFORMANCE REQUIREMENTS
A. Surface-Burning Characteristics: Comply with ASTM E 84; testing by a qualified testing agency. Identify products with appropriate markings of applicable testing agency.
1. Flame-Spread Index: 25 or less. 2. Smoke-Developed Index: 450 or less.
B. Regulatory Requirements: Comply with applicable provisions in the U.S. Architectural & Transportation Barriers Compliance Board's ADA-ABA Accessibility Guidelines for Buildings and Facilities and ICC A117.1 for toilet compartments designated as accessible.
MANUFACTURERS
A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
1. Accurate Partitions Corporation. 2. Ampco, Inc. 3. Bradley Corporation; Mills Partitions 4. Comtec Industries/Capitol Partitions 5. General Partitions Mfg. Corp. 6. Global Partitions 7. Hadrian Manufacturing Inc. 8. Hiny Hiders; Division of Scranton Products 9. Metpar Corp. 10. Partition Systems Incorporated of South Carolina 11. Rockville Partitions Incorporated. 12. Santana Products, Inc. 13. Weis-Robart Partitions, Inc.
SOLID-PLASTIC TOILET COMPARTMENTS
A. Door, Panel, and Pilaster Construction: Solid, high-density polyethylene (HDPE) panel material, not less than 1 inch thick, seamless, with eased edges, and with homogenous color and pattern throughout thickness of material.
1. Heat-Sink Strip: Manufacturer's standard continuous, stainless-steel strip fastened to exposed bottom edges of solid-polymer components to prevent burning. 2. Color and Pattern: As indicated on Finish Legend or as selected by Architect from manufacturer's full range.
B. Urinal-Screen Construction: Flat-panel urinal screen matching panel construction.
C. Pilaster Shoes: Stainless-steel sheet, not less than 0.031-inch nominal thickness and 3 inches high, finished to match hardware. D. Urinal-Screen Post: Manufacturer's standard post design of material matching the thickness and construction of pilasters; with shoe matching that on the pilaster.
E. Brackets (Fittings): Full-height (continuous) type of manufacturer's standard design; stainless steel.
HARDWARE AND ACCESSORIES
A. Hardware and Accessories: Manufacturer's standard design, heavy-duty operating hardware and accessories.
1. Material: Stainless steel. 2. Hinges: Manufacturer's premium grade paired, self-closing type that can be adjusted to hold doors open at any angle up to 90 degrees. 3. Latch and Keeper: Manufacturer's premium grade surface-mounted latch unit designed for emergency access and with combination rubber-faced door strike and keeper. Provide units that comply with regulatory requirements for accessibility at compartments designated as accessible. 4. Coat Hook: Manufacturer's premium grade combination hook and rubber-tipped bumper, sized to prevent in-swinging door from hitting compartment-mounted accessories.
5. Door Bumper: Manufacturer's premium grade rubber-tipped bumper at out-swinging doors. 6. Door Pull: Manufacturer's premium grade unit at out-swinging doors that complies with regulatory requirements for accessibility. Provide units on both sides of doors at compartments designated as accessible.
B. Overhead Bracing: Manufacturer's standard continuous, extruded-aluminum head rail with antigrip profile and in manufacturer's standard finish.
C. Anchorages and Fasteners: Manufacturer's standard exposed fasteners of stainless steel, finished to match the items they are securing, with theft-resistant-type heads. Provide sex-type bolts for through-bolt applications. For concealed anchors, use stainless steel, hot-dip galvanized steel, or other rust-resistant, protective-coated steel.
MATERIALS
A. Stainless-Steel Sheet: ASTM A 666, Type 304, stretcher-leveled standard of
flatness.
B. Stainless-Steel Castings: ASTM A 743/A 743M.
C. Aluminum Extrusions: ASTM B 221. FABRICATION
A. Fabrication, General: Fabricate toilet compartment c o m p o n e n t s to sizes indicated. Coordinate requirements and provide cutouts for through-partition toilet accessories where required for attachment of toilet accessories.
B. Overhead-Braced U n i t s : Provide manufacturer's s t a n d a r d corrosion-resistant s u p p o r t s , leveling mechanism, and anchors at pilasters to suit floor conditions. Provide shoes at pilasters to conceal supports and leveling mechanism.
C. Floor-Anchored Units: Provide manufacturer's standard corrosion-resistant anchoring assemblies with leveling adjustment nuts at pilasters for structural connection to floor. Provide shoes at pilasters to conceal anchorage.
D. Urinal-Screen Posts: Provide manufacturer's standard corrosion-resistant anchoring assemblies with leveling adjustment at bottoms of posts. Provide shoes at posts to conceal anchorage.
E. Door Size and Swings:
1. Standard Compartments: Provide 24-inch clear opening with door swing. 2. Wheelchair and Ambulatory Accessible Compartments: Provide 32-inch clear opening with Door swing.
- EXECUTION EXAMINATION
A. Examine areas and conditions, with Installer present, for compliance with requirements for fastening, support, alignment, operating clearances, and other conditions affecting performance of the Work.
1. Confirm location and adequacy of blocking and supports required for
installation.
B. Proceed with installation only after unsatisfactory conditions have been
corrected.
INSTALLATION
A. General: Comply with manufacturer's written installation instructions. Install units rigid, straight, level, and plumb. Secure units in position with manufacturer's recommended anchoring devices.
1. Maximum Clearances:
a. Pilasters and Panels: 1/2 inch. b. Panels and Walls: 1 inch.
2. Full-Height (Continuous) Brackets: Secure panels to walls and to pilasters with full-height brackets.
a. Locate bracket fasteners so holes for wall anchors occur in masonry or tile joints. b. Align brackets at pilasters with brackets at walls.
B. Overhead-Braced Units: Secure pilasters to floor and level, plumb, and tighten. Set pilasters with anchors penetrating not less than 1-3/4 inches into structural floor unless otherwise indicated in manufacturer's written instructions. Secure continuous head rail to each pilaster with no fewer than two fasteners. Hang doors to align tops of doors with tops of panels, and adjust so tops of doors are parallel with overhead brace when doors are in closed position.
C. Floor-Anchored Units: Set pilasters with anchors penetrating not less than 2 inches into
structural floor unless otherwise indicated in manufacturer's written instructions. Level, plumb, and tighten pilasters. Hang doors and adjust so tops of doors are level with tops of pilasters when doors are in closed position.
D. Urinal Screens: Attach with anchoring devices to suit supporting structure. Set units level and
plumb, rigid, and secured to resist lateral impact. ADJUSTING
A. Hardware Adjustment: Adjust and lubricate hardware according to hardware manufacturer's written instructions for proper operation. Set hinges on in-swinging doors to hold doors open approximately 30 degrees from closed position when unlatched. Set hinges on out-swinging doors to return doors to fully closed position.
Staff Restroom Renovations Scope Sheet
School: South Brunswick High SchoolRest Room Location: Boys Restroom‐Cafeteria
Item: Quantity Sqft. lnft.
Signage 1
Door
Door Frame 1 Hollow Metal
Door Hardware
Floors 478
Walls 944 118
Ceilings 8'‐0" 478
Lavatory 3
Lavatory Drain Lines 3
Water Closet 4
Urinal & Flush Valve
8
Faucets 3
Hose Bib 1
Flush Valves (Water Closet) 4
2
Clean Out Covers 2 Painted
Toilet Partitions 4/8.
Mirror 1
Soap Dispenser 2
Sanitary Napkin Receptacle
Toilet Paper Dispenser 4
Paper Towel Dispenser
Trash Receptacle 1
Access Panel/Door
Shelving
Grab Bars 2
HVAC 3Electrical
1
1
Switches
1
Lights 10 2 bulb recessed
Furnish and Install 2 x 4 stainless steel blank cover where switch has been removed
Leave in Place/Furnish and Install (1) New Lens/Clean All Lens
Remove and Replace with New HVAC Grilles
Remove/Furnish and Install New GFCI Receptacle 120 volt 20 amp (Gray Color)
Remove/Furnish and Install New GFCI Stainless Steel Cover Plate
N/A
HVAC
GFCI (White)
Remove/Replace with new 4" center, Hot and Cold water supply self‐closing metered push down faucet by
Chicago, Zurn, or approved equal. Installation to include all associated fitting, gaskets, escutcheons, etc… for
fully functioning properly operating faucets. (Chrome Finish)
Leave in Place/Clean Paint off
Remove/Replace with new 1.6 GPF Flush valve with 1" screwdriver angle check stop, vandal resistant stop
cap, ADA flush handle, vacuum breaker, 1" chrome plated wall supply cover pipe, chrome plated cast brass
escutcheon with set screw, 1‐1/2" chrome plated flush pipe, Zurn Z‐6000XL‐WSI‐YBYCYK, Sloan No. 111‐
1.6YK or Delany F‐414‐1.6‐T42‐T36, or approved equal by American Standard. Finish to be Chrome.
Prep Epoxy Floor with Multi Purpose Bonding Primer (MAPEI‐Eco Prim Grip or Equal)
‐Install 6 x6 Quarry Tile/Slope to Floor Drain/Install New Threshold /Contractor may Install 6" or 8" Quarry
Tile Base to cover existing Base Line of Previous Floor Type (Color
selection by Owner)
Prep/Point Up, Mortar Cracks,Holes,Joints,Caulk as needed/Scrape Flaking Paint/ Prime (1) coat/Paint (2)
coats. Top Coat to be Interior Pre‐catalyzed epoxy, (semi gloss) (Color selection by Owner)
Prep/Patch, Sand, Caulk as needed/Prime (1) coat/Paint (2) coats. Top Coat to be Interior Pre‐catalyzed
epoxy, (semi gloss) (Color selection by Owner)
N/A
Leave In Place/Paint Interior side of Frame
N/A
Remove/Furnish and Install with New American Standard 3461.001 16‐1/2" high, floor mounted, vitreous
china, elongated siphon jet water saver 1.6 GPF bowl with 1‐1/2" top spud, china caps or approved equal
Kohler or Zurn. Provide new open front, elongated plastic seat with concealed stainless steel check hinge
Church, Bemis or approved equal. Installation to include but not limited to fittings, escutcheons, gaskets,
etc... for fully functional and properly operational water closet.
(Color to be White)
Remove/Replace with 0.125 GPF American Standard 6590.001.020 or Zurn, Kohler approved equal. (Color to
be White) Flush Valve to be .0125 GPF American Standard, Zurn, Sloan
Existing Description
Epoxy
Remove/Install New/Adjust floor drain grate to proper height with newly installed floor tile and not rising
above new floor tile elevation
Remove (4) HDPE Stalls with Doors/Furnish and Install (4) New HDPE Toilet Partition Stalls with doors and
hardware after painting is complete. (Owner to Select Color)
‐ Remove (8) HDPE Urinal Screens/Furnish and Install (8) New HDPE Urinal Screens (Color Selected By
Owner)
Remove/Replace with 20" by 18" enameled cast iron with 3 deck holes for Hot, Cold Water and Faucet with
4" center set, back ledge, wall hanger, front overflow by American Standard, Zurn or Kohler or approved
equal. Installation To Include but not limited to new supply line, fittings, escutcheons, etc... for the fully
functional and properly operating lavatory. Wrap waterlines with Lav Guard or approved equal.
(Color to be White)
Remove/Replace with new Chrome finish drain line including escutcheons at wall. Wrap with Lav Guard or
equal pipe protection.
Remove/Furnish and Install New clean out cover /Stainless Steel.
Floor Mount
Wall hung
metered push handle
Action
Leave in Place
Receptacles
Remove/Clean/Re‐Install existing grab bars/ Contractor to add any grab bars necessary to meet most recent
ADA code after painting is complete.
N/A
Floor Drain Grate
wall hung
Stall/wall hung Remove/Clean/Re‐Install after New HDPE Stalls have been Installed
N/A
Remove Plywood Cover 2' x 5'/Fill in Hole with New CMU/Paint
N/A
Furnish and Install (1) new 24" x 60" mirror with stainless steel edge after Painting is complete
Remove/Clean/Re‐Install after painting in different location chosen by Owner
N/A
5/4/2020
Receptacle Cover Plate
Switch Cover Plate
One Wall at Entrance
Stainless Steel Edge
Removed
GFCI (Stainless Steel)
Removed/Plywood Covering Hole
Wall Mounted
brass
CMU/Painted
Drywall
Wall hung
(4) HDPE Stalls with Doors ‐1 is HC
(8) HDPE Urinal Screens
Staff Restroom Renovations Scope Sheet
School: South Brunswick High SchoolRest Room Location: Girls Restroom‐Cafeteria
Item: Quantity Sqft. lnft.
Signage 1
Door
Door Frame 1 Hollow Metal
Door Hardware
Floors 555
Walls 1000 125
Ceilings 8'‐0" 555
Lavatory 4
Lavatory Drain Lines 4
Water Closet 14
Urinal & Flush Valve
Faucets 4
Hose Bib 1
Flush Valves (Water Closet) 14
2
Clean Out Covers 2 Painted
Toilet Partitions 14
Mirror 1
Soap Dispenser 2Sanitary Napkin Receptacle 14
Toilet Paper Dispenser 14
Paper Towel Dispenser
Trash Receptacle 1
Access Panel/Door
Shelving
Grab Bars 4
HVAC 5Electrical
1
1
Switches
Lights 14
5/4/2020
Receptacle Cover Plate
Switch Cover Plate
One Wall at Entrance
Stainless Steel Edge
GFCI (Stainless Steel)
Recessed Stainless Steel
Wall Mounted
brass
CMU/Painted
Drywall
Wall hung
(14) HDPE Stalls with Doors ‐2 is HC
Receptacles
Remove/Furnish and Install New Grab Bars/ Contractor to add any grab bars necessary to meet most recent
ADA code after painting is complete.
N/A
Floor Drain Grate
wall hung
Stall/Wall Mounted
Stall/wall hung Remove/Clean/Re‐Install after New HDPE Stalls have been Installed
N/A
Remove/Fill in 2' x 5' Hole with New CMU/Paint
N/A
Furnish and Install (1) new 24" x 60" mirror with stainless steel edge after Painting is complete
Remove/Clean/Re‐Install after painting in different location chosen by Owner
Remove/Furnish and Install (14) New Stainless Steel Sanitary Napkin Receptacles
Existing Description
Epoxy
Remove/Install New/Adjust floor drain grate to proper height with newly installed floor tile and not rising
above new floor tile elevation
Remove (14) HDPE Stalls with Doors/Furnish and Install (14) New HDPE Toilet Partition Stalls with doors and
hardware after painting is complete. (Owner to Select Color)
Remove/Replace with 20" by 18" enameled cast iron with 3 deck holes for Hot, Cold Water and Faucet with
4" center set, back ledge, wall hanger, front overflow by American Standard, Zurn or Kohler or approved
equal. Installation To Include but not limited to new supply line, fittings, escutcheons, etc... for the fully
functional and properly operating lavatory. Wrap waterlines with Lav Guard or approved equal.
(Color to be White)
Remove/Replace with new Chrome finish drain line including escutcheons at wall. Wrap with Lav Guard or
equal pipe protection.
Remove/Furnish and Install New clean out cover /Stainless Steel.
Floor Mount
metered push handle
Action
Leave in Place
N/A
Leave In Place/Paint Interior side of Frame
N/A
Remove/Furnish and Install with New American Standard 3461.001 16‐1/2" high, floor mounted, vitreous
china, elongated siphon jet water saver 1.6 GPF bowl with 1‐1/2" top spud, china caps or approved equal
Kohler or Zurn. Provide new open front, elongated plastic seat with concealed stainless steel check hinge
Church, Bemis or approved equal. Installation to include but not limited to fittings, escutcheons, gaskets,
etc... for fully functional and properly operational water closet.
(Color to be White)
N/A
Remove/Replace with new 4" center, Hot and Cold water supply self‐closing metered push down faucet by
Chicago, Zurn, or approved equal. Installation to include all associated fitting, gaskets, escutcheons, etc… for
fully functioning properly operating faucets. (Chrome Finish)
Leave in Place/Clean
Remove/Replace with new 1.6 GPF Flush valve with 1" screwdriver angle check stop, vandal resistant stop
cap, ADA flush handle, vacuum breaker, 1" chrome plated wall supply cover pipe, chrome plated cast brass
escutcheon with set screw, 1‐1/2" chrome plated flush pipe, Zurn Z‐6000XL‐WSI‐YBYCYK, Sloan No. 111‐
1.6YK or Delany F‐414‐1.6‐T42‐T36, or approved equal by American Standard. Finish to be Chrome.
Prep Epoxy Floor with Multi Purpose Bonding Primer (MAPEI‐Eco Prim Grip or Equal)
‐Install 6 x6 Quarry Tile/Slope to Floor Drain/Install New Threshold /Contractor may Install 6" or 8" Quarry
Tile Base to cover existing Base Line of Previous Floor Type (Color
selection by Owner)
Prep/Point Up, Mortar Cracks,Holes,Joints,Caulk as needed/Scrape Flaking Paint/ Prime (1) coat/Paint (2)
coats. Top Coat to be Interior Pre‐catalyzed epoxy, (semi gloss) (Color selection by Owner)
Prep/Patch, Sand, Caulk as needed/Prime (1) coat/Paint (2) coats. Top Coat to be Interior Pre‐catalyzed
epoxy, (semi gloss) (Color selection by Owner)
2 bulb recessed
N/A
Leave in Place/Clean Lens
Remove and Replace with New HVAC Grilles
Remove/Furnish and Install New GFCI Receptacle 120 volt 20 amp (Gray Color)
Remove/Furnish and Install New GFCI Stainless Steel Cover Plate
N/A
HVAC
GFCI (Almond)
Staff Restroom Renovations Scope Sheet
School: South Brunswick High SchoolRest Room Location: Main Office‐Staff
Item: Quantity Sqft. lnft.
Signage 1
Door 3070 1 Wood
Door Frame 1 Hollow Metal
Door Hardware 1 each
Floors 33
Walls 264 ‐5'‐8"CMU
‐16'‐8"
DrywallCeilings 8'‐0" 33
Lavatory 1
Lavatory Drain Lines 1
Water Closet 1
Urinal & Flush Valve
Faucets 1
Hose Bib
Flush Valves (Water Closet) 1
Clean Out Covers 1 Stainless Steel
Toilet Partitions
Mirror 1
Soap Dispenser 1Sanitary Napkin Receptacle 1
Toilet Paper Dispenser 1
Paper Towel Dispenser 1
Trash Receptacle
Access Panel/Door
Shelving
Grab Bars 2
HVAC 1Electrical
1
1
Switches 2
2
Lights 1 2 bulb recessed
Fan/Light (Almond)
Remove/Furnish and Install New Stainless Steel Switch Plates after Paint is Complete
Leave in Place/Clean Lens
Remove and Replace with New HVAC Grilles
Remove/Furnish and Install New GFCI Receptacle 120 volt 20 amp (Gray Color)
Remove/Furnish and Install New GFCI Stainless Steel Cover Plate
Remove/Furnish and Install New Switches 120 volt 20amp (Gray Color)
HVAC
GFCI (Almond)
Remove/Replace with new Single lever, chrome plated, lead free supply faucet with 0.5
GPM vandal resistant aerator shall be Zurn Z7440‐XL‐FC, or approved equal by Chicago Faucets, Delta, or
Moen. Installation to include all associated fittings, gaskets, escutcheons, etc… for fully functioning properly
operating faucets. (Chrome Finish)
N/A
Remove/Replace with new 1.6 GPF Flush valve with 1" screwdriver angle check stop, vandal resistant stop
cap, ADA flush handle, vacuum breaker, 1" chrome plated wall supply cover pipe, chrome plated cast brass
escutcheon with set screw, 1‐1/2" chrome plated flush pipe, Zurn Z‐6000XL‐WSI‐YBYCYK, Sloan No. 111‐
1.6YK or Delany F‐414‐1.6‐T42‐T36, or approved equal by American Standard. Finish to be Chrome.
Remove Tile/Prep/ Install 6 x6 Quarry Tile/Slope to Floor Drain/Install New Threshold at Entrances/ ‐
Contractor may Install 6" or 8" Quarry Tile Base to cover existing Base Line of Previous Floor Type
(Color selection by Owner)
CMU‐Prep/Point Up, Mortar Cracks,Holes,Joints,Caulk as needed/Scrape Flaking Paint/ Prime Drywall‐
Prep/Patch, Sand, Caulk as needed/Prime (1) coat/Paint (2) coats. Top Coat to be Interior Pre‐catalyzed
epoxy, (semi gloss) (Color selection by Owner)
Prep/Patch, Sand, Caulk as needed/Prime (1) coat/Paint (2) coats. Top Coat to be Interior Pre‐catalyzed
epoxy, (semi gloss) (Color selection by Owner)
Leave In Place/Clean/Protect
Leave In Place/Paint Interior side of Frame
Leave in Place/Clean/Protect
Remove/Furnish and Install with New American Standard 3461.001 16‐1/2" high, floor mounted, vitreous
china, elongated siphon jet water saver 1.6 GPF bowl with 1‐1/2" top spud, china caps or approved equal
Kohler or Zurn. Provide new open front, elongated plastic seat with concealed stainless steel check hinge
Church, Bemis or approved equal. Installation to include but not limited to fittings, escutcheons, gaskets,
etc... for fully functional and properly operational water closet.
(Color to be White)
N/A
Existing Description
Handles/Thumb Bolt Latch/Kick Plates/ Hinges/Closer
Epoxy
N/A
N/A
Remove/Replace with 20" by 18" enameled cast iron with 3 deck holes for Hot, Cold Water and Faucet with
4" center set, back ledge, wall hanger, front overflow by American Standard, Zurn or Kohler or approved
equal. Installation To Include but not limited to new supply line, fittings, escutcheons, etc... for the fully
functional and properly operating lavatory. Wrap waterlines with Lav Guard or approved equal.
(Color to be White)
Remove/Replace with new Chrome finish drain line including escutcheons at wall. Wrap with Lav Guard or
equal pipe protection.
Remove/Furnish and Install New clean out cover /Stainless Steel.
Floor Mount
Lever Handle
Action
Leave in Place
Receptacles
Remove/Furnish and Install New Grab Bars/ Contractor to add any grab bars necessary to meet most recent
ADA code after painting is complete.
N/A
Floor Drain Grate
wall hung
Wall Mounted
wall hung Remove/Clean/Re‐Install after New HDPE Stalls have been Installed
Remove/Clean/Re‐Install after paint is complete
N/A
N/A
Furnish and Install (1) new 24" x 36" mirror with stainless steel edge after Painting is complete
Remove/Clean/Re‐Install after painting in different location chosen by Owner
Remove/Clean/Re‐Install after Paint is Complete
5/4/2020
Receptacle Cover Plate
Switch Cover Plate
One Wall at Entrance
24" x 36" over sink/Stainless Steel Edge
Single pole (Stainless Steel)
GFCI (Stainless Steel)
wall hung
Wall Mounted
CMU/Drywall/Painted
Drywall
Wall hung
Staff Restroom Renovations Scope Sheet
School: South Brunswick Middle School
Rest Room Location: Boys‐Cafeteria
Item: Quantity Sqft. lnft.
Signage 1
Door
Door Frame 1 Hollow Metal
Door Hardware
Floors 215
Walls 560 70
Ceilings 8'‐0" 215
Lavatory 2
Lavatory Drain Lines 2
Water Closet 3
Urinal & Flush Valve 3
Faucets 2
Hose Bib 1
Flush Valves(Water Closet) 2
1
Clean Out Covers
Toilet Partitions 3
Mirror
Soap Dispenser 1
Sani Seat Dispenser
Toilet Paper Dispenser 3
Paper Towel Dispenser
Trash Receptacle
Access Panel/Door
Shelving
Grab Bars 2
HVAC 2
Electrical
1 Electric Wall Hung
1
1
Switches 1
1
Lights 2
4/28/2020
Receptacle Cover Plate
Switch Cover Plate
One wall at entrance
Painted white
Stainless Steel
Stall and Wall Mounted
brass
CMU/Painted
Drywall
Wall hung
(3) Part CMU wall, Part HDPE Stall with Doors
CMU Partition 4'‐0" Long x 4'‐8" High‐1 is HC
Receptacles
Remove/Install new grab bars and add any necessary grab bars to meet most recent ADA code
N/A
Floor Drain Grate
wall hung
wall Hung Remove/Clean/Re‐Install on new stalls
N/A
N/A
N/A
Install (2) New mirrors 24" x 36" with Stainless Steel edging, one mirror at each sink.
Remove/Clean/Re‐Install between mirrors and sinks after painting
Hand Dryer
Existing Description
Ceramic Tile
Remove/Install New/Adjust floor drain grate to proper height with newly installed floor tile and not rising
above new floor tile elevation
Remove (3) CMU‐HDPE Stall Walls/Repair CMU where stall walls tie into main CMU walls/Replace with new
HDPE toilet partitions, doors, and hardware/Furnish and Install (1) New Urinal Screen. (Color Selected By
Owner)
Remove/Replace with 20" by 18" enameled cast iron with one hole center for faucet, back ledge, wall
hanger, front overflow by American Standard, Zurn or Kohler or approved equal. Installation To Include but
not limited to new supply line, fittings, escutcheons, etc... for the fully functional and properly operating
lavatory. Wrap waterline with Lav Guard or approved equal. (Color to be White)
Remove/Replace with new Chrome finish drain line including escutcheons at wall. Wrap with Lav Guard or
equal pipe protection.
N/A
Wall Hung
Wall hung
push down metered (cold water only)
Action
Remove/Furnish and Install New ADA Compliant Sign/ Owner to Select Color
N/A
Prep/Caulk/Prime (1) coat/Paint (2) coats ‐From door stop interior side to interior side of frame (Color
selection by Owner)
N/A
Remove/Replace with new wall mounted, vitreous china, elongated bowl, 1.6 GPF American Standard or
Zurn, Kohler approved equal. Contractor to verify bolt pattern of new toilet match existing wall bracket.
Provide new open front, elongated plastic seat with concealed stainless steel check hinges Church 9500CT,
Bemis 1955SSCT or approved equal. Installation to include but not limited to fittings, escutcheons, gaskets,
etc... for fully functional and properly operational water closet.
(Color to be White)
Remove/Replace with 0.125 GPF American Standard 6590.001.020 or Zurn, Kohler approved equal. (Color to
be White) Flush Valve to be .0125 GPF American Standard, Zurn, Sloan
Remove/Replace with new single hole, single supply self‐closing metered push down faucet by Chicago, Zurn,
or approved equal. Installation to include all associated fitting, gaskets, escutcheons, etc… for fully
functioning properly operating faucets. (Chrome Finish)
Leave in Place/Clean/Polish
Remove/Replace with new 1.6 GPF Flush valve with 1" screwdriver angle check stop, vandal resistant stop
cap, ADA flush handle, vacuum breaker, 1" chrome plated wall supply cover pipe, chrome plated cast brass
escutcheon with set screw, 1‐1/2" chrome plated flush pipe, Zurn Z‐6000XL‐WSI‐YBYCYK, Sloan No. 111‐
1.6YK or Delany F‐414‐1.6‐T42‐T36, or approved equal by American Standard. Finish to be Chrome.
Remove Tile/Prep/ Install 6 x6 Quarry Tile/Slope to Floor Drain/Install New Threshold at Entrances/ ‐
Contractor may Install 6" or 8" Quarry Tile Base to cover existing Base Line of Previous Floor Type
(Color selection by Owner)
Prep/Point Up, Mortar Cracks,Holes,Joints,Caulk as needed/Scrape Flaking Paint/ Prime (1) coat/Paint (2)
coats. Top Coat to be Interior Pre‐catalyzed epoxy, (semi gloss) (Color selection by Owner)
Prep/Patch, Sand, Caulk as needed/Prime (1) coat/Paint (2) coats. Top Coat to be Interior Pre‐catalyzed
epoxy, (semi gloss) (Color selection by Owner)
2 bulb fluorescent
single pole/Slotted key switch
Remove/Replace with new stainless steel cover after paintingRemove/Replace with new Lithonia FMLWL, LED, wraparound light, 120volt, or approved equal (Contractor
to verify voltage before ordering lighting)
Clean/Paint to Match Ceiling
Remove/Furnish and Install New GFCI (Gray Color)/Paint Box and Conduit same as walls/ 120 volt 20 amp
Remove/Furnish and Install New GFCI Cover Plate (Stainless Steel)
N/A
HVAC
Surface Mounted GFCI
Leave in Place/ Clean/Protect
Staff Restroom Renovations Scope Sheet
School: South Brunswick Middle School
Rest Room Location: Girls‐Cafeteria
Item: Quantity Sqft. lnft.
Signage 1
Door
Door Frame 1 Hollow Metal
Door Hardware
Floors 215
Walls 560 70
Ceilings 8'‐0" 215
Lavatory 2
Lavatory Drain Lines 2
Water Closet 5
Urinal & Flush Valve
Faucets 2
Hose Bib 1
Flush Valves(Water Closet) 5
1
Clean Out Covers
Toilet Partitions 5
Mirror
Soap Dispenser 1
Sanitary Napkin Receptacle 5
Toilet Paper Dispenser 5
Paper Towel Dispenser
Trash Receptacle
Access Panel/Door 1
Shelving
Grab Bars 6
HVAC 2
Electrical
1 Electric Wall Hung
1
1
Switches 1
3
Lights 2 2 bulb fluorescent
single pole/Slotted key switch
Remove/Replace with new stainless steel cover after painting
Remove/Replace with new Lithonia FMLWL, LED, wraparound light, 120volt, or approved equal (Contractor
to verify voltage before ordering lighting)
Clean/Paint to Match Ceiling
Remove/Furnish and Install New GFCI (Gray Color)/Paint Box and Conduit same as walls/ 120 volt 20 amp
Remove/Furnish and Install New GFCI Cover Plate (Stainless Steel)
N/A
HVAC
Surface Mounted GFCI
Leave in Place/ Clean/Protect
Remove/Replace with new single hole, single supply self‐closing metered push down faucet by Chicago, Zurn,
or approved equal. Installation to include all associated fitting, gaskets, escutcheons, etc… for fully
functioning properly operating faucets. (Chrome Finish)
Leave in Place/Clean/Polish
Remove/Replace with new 1.6 GPF Flush valve with 1" screwdriver angle check stop, vandal resistant stop
cap, ADA flush handle, vacuum breaker, 1" chrome plated wall supply cover pipe, chrome plated cast brass
escutcheon with set screw, 1‐1/2" chrome plated flush pipe, Zurn Z‐6000XL‐WSI‐YBYCYK, Sloan No. 111‐
1.6YK or Delany F‐414‐1.6‐T42‐T36, or approved equal by American Standard. Finish to be Chrome.
Remove Tile/Prep/ Install 6 x6 Quarry Tile/Slope to Floor Drain/Install New Threshold at Entrances/ ‐
Contractor may Install 6" or 8" Quarry Tile Base to cover existing Base Line of Previous Floor Type
(Color selection by Owner)
Prep/Point Up, Mortar Cracks,Holes,Joints,Caulk as needed/Scrape Flaking Paint/ Prime (1) coat/Paint (2)
coats. Top Coat to be Interior Pre‐catalyzed epoxy, (semi gloss) (Color selection by Owner)
Prep/Patch, Sand, Caulk as needed/Prime (1) coat/Paint (2) coats. Top Coat to be Interior Pre‐catalyzed
epoxy, (semi gloss) (Color selection by Owner)
N/A
Prep/Caulk/Prime (1) coat/Paint (2) coats ‐From door stop interior side to interior side of frame (Color
selection by Owner)
N/A
Remove/Replace with new wall mounted, vitreous china, elongated bowl, 1.6 GPF American Standard or
Zurn, Kohler approved equal. Contractor to verify bolt pattern of new toilet match existing wall bracket.
Provide new open front, elongated plastic seat with concealed stainless steel check hinges Church 9500CT,
Bemis 1955SSCT or approved equal. Installation to include but not limited to fittings, escutcheons, gaskets,
etc... for fully functional and properly operational water closet.
(Color to be White)
N/A
Existing Description
Ceramic Tile
Remove/Install New/Adjust floor drain grate to proper height with newly installed floor tile and not rising
above new floor tile elevation
Remove (5) CMU‐HDPE Stall Walls/Repair CMU where stall walls tie into main CMU walls/Replace with new
HDPE toilet partitions, doors, and hardware (Color
Selected By Owner)
Remove/Replace with 20" by 18" enameled cast iron with one hole center for faucet, back ledge, wall
hanger, front overflow by American Standard, Zurn or Kohler or approved equal. Installation To Include but
not limited to new supply line, fittings, escutcheons, etc... for the fully functional and properly operating
lavatory. Wrap waterline with Lav Guard or approved equal. (Color to be White)
Remove/Replace with new Chrome finish drain line including escutcheons at wall. Wrap with Lav Guard or
equal pipe protection.
N/A
Wall Hung
push down metered (cold water only)
Action
Remove/Furnish and Install New ADA Compliant Sign/ Owner to Select Color
Receptacles
Remove/Install new grab bars and add any necessary grab bars to meet most recent ADA code
N/A
Floor Drain Grate
wall hung
Plastic
wall Hung Remove/Clean/Re‐Install on new stalls
N/A
N/A
Furnish and Install Access Panel, with secure panel option, under sink where exterior fastened sheet metal
panel is covering hole in wall.
Install (2) New mirrors 24" x 36" with Stainless Steel edging, one mirror at each sink.
Remove/Clean/Re‐Install between mirrors and sinks after painting
Remove/Furnish and Install (5) New Stainless Steel Sanitary Napkin Receptacles
Hand Dryer
4/28/2020
Receptacle Cover Plate
Switch Cover Plate
One wall at entrance
(1) Stainless Steel/ (2) Painted
White GCFI Cover Plate
Sheet Metal Cover (Under Sink)
Stall and Wall Mounted
brass
CMU/Painted
Drywall
Wall hung
Part CMU wall, Part HDPE Stall with Doors CMU
Partition 4'‐0" Long x 4'‐8" High‐(3) is HC
Staff Restroom Renovations Scope Sheet
School: Southport Elementary School
Rest Room Location: Boys‐Cafeteria
Item: Quantity Sqft. lnft.
Signage 1
Door 3070 Wood(Birch)
Door Frame 1 Hollow Metal
Door Hardware 1 Each
Floors 190
Walls 576 72
Ceilings 8'‐0" 190
Lavatory 2
Lavatory Drain Lines 2
Water Closet 1
Urinal & Flush Valve
1
Faucets 2
Hose Bib 1
Flush Valves (Water Closet) 1
1
Floor Clean Out Cover 1 brass
Toilet Partitions 1/1.
Mirror 1
Soap Dispenser 1
Toilet Paper Dispenser 1
Paper Towel Dispenser 1
Trash Receptacle 1
Access Panel/Door
Shelving
Grab Bars 2
HVAC 1Electrical
1
1
Switches 1
1
Lights 3
4/30/2020
Receptacle Cover Plate
Switch Cover Plate
One wall at entrance
(1) 24" x 60"" with stainless steel edging
GFCI Stainless
wall hung
Recessed in wall
Wall Mounted
brass
CMU/Painted
ACT
Wall hung
(1)HC‐ CMU stall with HDPE door
6'‐8" High x 5'‐0" Long ,
(1) CMU Urinal Screen
Receptacles
Remove/Furnish and Install New Grab Bars after painting/Add any new grab bars to meet most recent ADA
code
N/A
Floor Drain Grate
wall hung
wall Hung Remove/Clean/Re‐Install after paint is complete
Remove/Clean/Re‐Install Wall Hung after painting.
Leave in Place/Clean/Protect
N/A
Remove/Dispose/ Install (2) new 24" x 36"" mirror with stainless steel edging over Sinks/Install (1) New 24" x
60" Mirror with Stainless Steel Edging.
Remove/Clean/Re‐Install after painting between sinks
Existing Description
kick plate, push plate, pull handle, closer, hinges
Welded Seam Sheet Vinyl
Remove/Install New/Adjust floor drain grate to proper height with newly installed floor tile and not rising
above new floor tile elevation
Remove CMU Toilet Partition and HDPE door/Repair Masonry wall where CMU Toilet partition tied into wall/
Furnish and Install New HDPE Toilet Partition with door and hardware. (Color Selected by Owner)
‐ Leave CMU Urinal Screen in Place, Paint same as Walls
Remove/Replace with 20" by 18" enameled cast iron with 3 deck holes for Hot, Cold Water and Faucet with
4" center set, back ledge, wall hanger, front overflow by American Standard, Zurn or Kohler or approved
equal. Installation To Include but not limited to new supply line, fittings, escutcheons, etc... for the fully
functional and properly operating lavatory. Wrap waterlines with Lav Guard or approved equal.
(Color to be White)Remove/Replace with new Chrome finish drain line including escutcheons at wall. Wrap with Lav Guard or
equal pipe protection.
Remove and Install new brass clean out cover. New clean out should not rise above new floor elevation.
Floor Mount
Wall hung
Lever handle
Action
Remove/Furnish and Install New ADA Compliant Sign. (Owner to Select Color)
Remove/Furnish and Install New Pre‐Finished Wood Door. (Owner to Select Finish)
Prep/Caulk/Prime (1) coat/Paint (2) coats ‐From door stop interior side to interior side of frame (Color
selection by Owner)
Remove/Install New Door Hardware
Remove/Furnish and Install (2) to be American Standard 3461.001 16‐1/2" high, floor mounted, vitreous
china, elongated siphon jet water saver 1.6 GPF bowl with 1‐1/2" top spud, china caps or approved equal
Kohler or Zurn. Provide new open front, elongated plastic seat with concealed stainless steel check hinge
Church, Bemis or approved equal. Installation to include but not limited to fittings, escutcheons, gaskets,
etc... for fully functional and properly operational water closet.
(Color to be White)
Remove/Replace with 0.125 GPF Kohler (Dexter) K‐5452, American Standard, Zurn, or approved equal. (Color
to be White) Flush Valve to be .0125 GPF Kohler, American Standard, Zurn, Sloan or approved equal.
*Note: Raise Urinal Height to Regular ADA Standard Height. Repair CMU wall after pipe has been adjusted in
wall.
Remove/Replace with new 4" center, Hot and Cold water supply self‐closing metered push down faucet by
Chicago, Zurn, or approved equal. Installation to include all associated fitting, gaskets, escutcheons, etc… for
fully functioning properly operating faucets. (Chrome Finish)
Leave in Place/Clean/Polish
Remove/Replace with new 1.6 GPF Flush valve with 1" screwdriver angle check stop, vandal resistant stop
cap, ADA flush handle, vacuum breaker, 1" chrome plated wall supply cover pipe, chrome plated cast brass
escutcheon with set screw, 1‐1/2" chrome plated flush pipe, Zurn Z‐6000XL‐WSI‐YBYCYK, Sloan No. 111‐
1.6YK or Delany F‐414‐1.6‐T42‐T36, or approved equal by American Standard. Finish to be Chrome.
Remove Welded Seam Sheet Vinyl/Prep Floor to receive New 6 x6 Quarry Tile/install New Threshold/Slope
floor towards Floor Drain/ ‐Contractor may Install 6" or 8" Quarry Tile Base to cover existing Base Line of
Previous Floor Type (Color selection by Owner)
Prep/Point Up, Mortar Cracks,Holes,Joints,Caulk as needed/Scrape Flaking Paint/ Prime (1) coat/Paint (2)
coats. Top Coat to be Interior Pre‐catalyzed epoxy, (semi gloss) (Color selection by Owner)
Remove Ceiling Tile/Furnish and Install New Vinyl Coated Ceiling Tile
4 bulb fluorescent Lay In
Remove/Furnish and Install New Switch Cover Plate (Stainless Steel)
Leave in Place/Remove Lens Covers and clean
Leave in Place/Clean/Protect
Remove/Furnish and Install New GFCI 120 volt 20 amp (Gray Color)
Remove/Furnish and Install New GFCI Cover Plate (Stainless Steel)
Remove/Furnish and Install New Switch 120 volt 20 amp (Gray Color)
HVAC
GFCI (White)
Staff Restroom Renovations Scope Sheet
School: Southport Elementary School
Rest Room Location: Girls‐Cafeteria
Item: Quantity Sqft. lnft.
Signage 1
Door 3070 Wood(Birch)
Door Frame 1 Hollow Metal
Door Hardware 1 Each
Floors 190
Walls 576 72
Ceilings 8'‐0" 190
Lavatory 2
Lavatory Drain Lines 2
Water Closet 2
Urinal & Flush Valve
Faucets 2
Hose Bib 1
Flush Valves (Water Closet) 1
1
Floor Clean Out Cover 1 brass
Toilet Partitions 2
Mirror 1
Soap Dispenser 1
Toilet Paper Dispenser 1
Paper Towel Dispenser 1
Trash Receptacle 1
Access Panel/Door
Shelving
Grab Bars 2
HVAC 1Electrical
1
1
Switches 1
1
Lights 3 4 bulb fluorescent Lay In
Remove/Furnish and Install New Switch Cover Plate (Stainless Steel)
Leave in Place/Remove Lens Covers and clean
Leave in Place/Clean/Protect
Remove/Furnish and Install New GFCI 120 volt 20 amp (Gray Color)
Remove/Furnish and Install New GFCI Cover Plate (Stainless Steel)
Remove/Furnish and Install New Switch 120 volt 20 amp (Gray Color)
HVAC
GFCI (White)
Remove/Replace with new 4" center, Hot and Cold water supply self‐closing metered push down faucet by
Chicago, Zurn, or approved equal. Installation to include all associated fitting, gaskets, escutcheons, etc… for
fully functioning properly operating faucets. (Chrome Finish)
Leave in Place/Clean/Polish
Remove/Replace with new 1.6 GPF Flush valve with 1" screwdriver angle check stop, vandal resistant stop
cap, ADA flush handle, vacuum breaker, 1" chrome plated wall supply cover pipe, chrome plated cast brass
escutcheon with set screw, 1‐1/2" chrome plated flush pipe, Zurn Z‐6000XL‐WSI‐YBYCYK, Sloan No. 111‐
1.6YK or Delany F‐414‐1.6‐T42‐T36, or approved equal by American Standard. Finish to be Chrome.
Remove Welded Seam Sheet Vinyl/Prep Floor to receive New 6 x6 Quarry Tile/install New Threshold/Slope
floor towards Floor Drain/ ‐Contractor may Install 6" or 8" Quarry Tile Base to cover existing Base Line of
Previous Floor Type (Color selection by Owner)
Prep/Point Up, Mortar Cracks,Holes,Joints,Caulk as needed/Scrape Flaking Paint/ Prime (1) coat/Paint (2)
coats. Top Coat to be Interior Pre‐catalyzed epoxy, (semi gloss) (Color selection by Owner)
Remove Ceiling Tile/Furnish and Install New Vinyl Coated Ceiling Tile
Remove/Furnish and Install New Pre‐Finished Wood Door. (Owner to Select Finish)
Prep/Caulk/Prime (1) coat/Paint (2) coats ‐From door stop interior side to interior side of frame (Color
selection by Owner)
Remove/Install New Door Hardware
Remove/Furnish and Install (2) to be American Standard 3461.001 16‐1/2" high, floor mounted, vitreous
china, elongated siphon jet water saver 1.6 GPF bowl with 1‐1/2" top spud, china caps or approved equal
Kohler or Zurn. Provide new open front, elongated plastic seat with concealed stainless steel check hinge
Church, Bemis or approved equal. Installation to include but not limited to fittings, escutcheons, gaskets,
etc... for fully functional and properly operational water closet.
(Color to be White)
N/A
Existing Description
kick plate, push plate, pull handle, closer, hinges
Welded Seam Sheet Vinyl
Remove/Install New/Adjust floor drain grate to proper height with newly installed floor tile and not rising
above new floor tile elevation
Remove (2) CMU Toilet Partitions and HDPE door/Repair Masonry wall where CMU Toilet partition tied into
wall/ Furnish and Install New HDPE Toilet Partition with door and hardware. (Color Selected by Owner)
Remove/Replace with 20" by 18" enameled cast iron with 3 deck holes for Hot, Cold Water and Faucet with
4" center set, back ledge, wall hanger, front overflow by American Standard, Zurn or Kohler or approved
equal. Installation To Include but not limited to new supply line, fittings, escutcheons, etc... for the fully
functional and properly operating lavatory. Wrap waterlines with Lav Guard or approved equal.
(Color to be White)Remove/Replace with new Chrome finish drain line including escutcheons at wall. Wrap with Lav Guard or
equal pipe protection.
Remove and Install new brass clean out cover. New clean out should not rise above new floor elevation.
Floor Mount
Lever handle
Action
Remove/Furnish and Install New ADA Compliant Sign. (Owner to Select Color)
Receptacles
Remove/Furnish and Install New Grab Bars after painting/Add any new grab bars to meet most recent ADA
code
N/A
Floor Drain Grate
wall hung
wall Hung Remove/Clean/Re‐Install after paint is complete
Remove/Clean/Re‐Install Wall Hung after painting.
Leave in Place/Clean/Protect
N/A
Remove/Dispose/ Install (2) new 24" x 36"" mirror with stainless steel edging over Sinks/Install (1) New 24" x
60" Mirror with Stainless Steel Edging.
Remove/Clean/Re‐Install after painting between sinks
4/30/2020
Receptacle Cover Plate
Switch Cover Plate
One wall at entrance
(1) 24" x 60"" with stainless steel edging
GFCI Stainless
wall hung
Recessed in wall
Wall Mounted
brass
CMU/Painted
ACT
Wall hung
(2)CMU stall with HDPE door ‐1 is HC
‐(1) 7'‐6" Long x 6'‐8" Tall
‐(1) 5'‐4" Long x 6'‐8" Tall
Staff Restroom Renovations Scope Sheet
School: Supply Elementary School
Rest Room Location: K1 Boys
Item: Quantity Sqft. lnft.
Signage 1
Door
Door Frame
Door Hardware
Floors 261
Walls 810 81
Ceilings 10'‐0" 261
Lavatory 4
Lavatory Drain Lines 4
Water Closet 3
Urinal & Flush Valve 2
Faucets 8
Hose Bib
Flush Valves(Water Closet) 3
1
Clean Out Covers
Toilet Partitions 3/1.
Mirror 1
Soap Dispenser 2
Sani Seat Dispenser
Toilet Paper Dispenser 3
Paper Towel Dispenser 1
Trash Receptacle 1
Access Panel/Door 1
Shelving
Grab Bars 2
HVAC 2
Electrical
Switches
Lights 4 (4) 4' 2 bulb recessed Fluorescent
N/A
Leave In Place/Clean Lens
Leave In Place/Clean
N/A
N/A
N/A
HVAC
N/A
Remove/Replace with new 4" center, Hot and Cold water supply self‐closing metered push down faucet by
Chicago, Zurn, or approved equal. Installation to include all associated fitting, gaskets, escutcheons, etc… for
fully functioning properly operating faucets. (Chrome Finish)
N/A
Remove/Replace with new 1.6 GPF Flush valve with 1" screwdriver angle check stop, vandal resistant stop
cap, ADA flush handle, vacuum breaker, 1" chrome plated wall supply cover pipe, chrome plated cast brass
escutcheon with set screw, 1‐1/2" chrome plated flush pipe, Zurn Z‐6000XL‐WSI‐YBYCYK, Sloan No. 111‐
1.6YK or Delany F‐414‐1.6‐T42‐T36, or approved equal by American Standard. Finish to be Chrome.
Remove Tile/Prep/ Install 6 x6 Quarry Tile/Slope to Floor Drain/Install New Threshold at Entrances/ ‐
Contractor may Install 6" or 8" Quarry Tile Base to cover existing Base Line of Previous Floor Type
(Color selection by Owner)
Prep/Point Up, Mortar Cracks,Holes,Joints,Caulk as needed/Scrape Flaking Paint/ Prime (1) coat/Paint (2)
coats. Top Coat to be Interior Pre‐catalyzed epoxy, (semi gloss) (Color selection by Owner)
Prep/Patch, Sand, Caulk as needed/Prime (1) coat/Paint (2) coats. Top Coat to be Interior Pre‐catalyzed
epoxy, (semi gloss) (Color selection by Owner)
N/A
N/A
N/A
Remove/Replace with new wall mounted, vitreous china, elongated bowl, 1.6 GPF American Standard or
Zurn, Kohler approved equal. Contractor to verify bolt pattern of new toilet match existing wall bracket.
Provide new open front, elongated plastic seat with concealed stainless steel check hinges Church 9500CT,
Bemis 1955SSCT or approved equal. Installation to include but not limited to fittings, escutcheons, gaskets,
etc... for fully functional and properly operational water closet.
(Color to be White)
Remove/Replace with 0.125 GPF , American Standard Allbrook .5gpf, Kohler (Dexter) K‐5452 Zurn, or
approved equal. (Color to be White) Flush Valve to be .0125 GPF Kohler, American Standard, Zurn, Sloan or
approved equal
Existing Description
Ceramic Tile
Remove/Install New/Adjust floor drain grate to proper height with newly installed floor tile and not rising
above new floor tile elevation
Remove (3) CMU Stalls and repair Masonry wall where CMU tied into/Furnish and Install new HDPE toilet
partition with doors, and hardware. (Owner to Select Color)
‐Leave In Place (1) CMU Urinal Screen. (paint the same as walls.
Remove/Replace with 20" by 18" enameled cast iron with one hole center for faucet, back ledge, wall
hanger, front overflow by American Standard, Zurn or Kohler or approved equal. Installation To Include but
not limited to new supply line, fittings, escutcheons, etc... for the fully functional and properly operating
lavatory. Wrap waterline with Lav Guard or approved equal. (Color to be White)
Remove/Replace with new Chrome finish drain line including escutcheons at wall. Wrap with Lav Guard or
equal pipe protection.
N/A
Wall Hung
Wall hung
Lever Handle (Hot and Cold)
Action
Leave In Place
Receptacles
Remove/Install new grab bars and add any necessary grab bars to meet most recent ADA code
N/A
Floor Drain Grate
wall hung
wall/stall Hung Remove/Clean/Re‐Install on new stalls
Remove/Clean/Re‐Install after painting.
Leave in Place/Clean/Protect
Paint to match ceiling
Remove/Furnish and Install (4) New mirrors 24" x 36" with Stainless Steel edging over sinks. Furnish and
Install (1) new 24' x 60" Mirror with stainless steel edging (Location selected by Owner).
Remove/Clean/Re‐Install after painting
N/A
Hand Dryer
4/30/2020
Receptacle Cover Plate
Switch Cover Plate
One wall at entrance
24" x 60" stainless steel edge
wall hung
Recessed Stainless Steel
Ceiling
Wall Mounted
brass
CMU/Painted
Drywall
Wall hung
(3) CMU Stalls 6'‐8" Long x 8'‐0" high ( with Hollow
Metal Frames and Wood Door HDPE Stalls with Doors‐
1 is HC/ (1) CMU Urinal Screens
Staff Restroom Renovations Scope Sheet
School: Virginia Williams Elementary School
Rest Room Location: 4th/5th Grade Boys
Item: Quantity Sqft. lnft.
Signage 1
Door
Door Frame
Door Hardware
Floors 261
Walls 810 81
Ceilings 10'‐0" 261
Lavatory 2
Lavatory Drain Lines 2
Water Closet 2
Urinal & Flush Valve 3
Faucets 2
Hose Bib 2
Flush Valves(Water Closet) 2
1
Clean Out Covers 2 Painted (under sinks)
Toilet Partitions 2/2.
Mirror
1
Soap Dispenser 2
Sani Seat Dispenser
Toilet Paper Dispenser 2
Paper Towel Dispenser 1
Trash Receptacle
Access Panel/Door 1
Shelving
Grab Bars 2
HVAC 1
Electrical
1
1
Switches
Lights 4
4/30/2020
Receptacle Cover Plate
Switch Cover Plate
One wall at entrance
24" x 60" stainless steel edge
GFCI (Painted Over)
wall hung
Ceiling
Wall Mounted
brass
CMU/Painted
Drywall
Wall hung
(2) HDPE Stalls with Doors ‐1 is HC/ (2) HDPE Urinal
Screens
Receptacles
Remove/Install new grab bars and add any necessary grab bars to meet most recent ADA code
N/A
Floor Drain Grate
wall hung
stall Hung Remove/Clean/Re‐Install on new stalls
Remove/Clean/Re‐Install after painting.
N/A
Paint to match ceiling
Remove/Furnish and Install (2) New mirror 24" x 36" with Stainless Steel edging over sinks. Furnish and Install
(1) new 24' x 60" Mirror with stainless steel edging (Location selected by Owner).
Remove/Clean/Re‐Install after painting
N/A
Hand Dryer
Existing Description
Ceramic Tile
Remove/Install New/Adjust floor drain grate to proper height with newly installed floor tile and not rising
above new floor tile elevation
Remove/Furnish and Install new HDPE toilet partition with doors, and hardware. Furnish and Install (2) new
Urinal Screen. (Color Selected By Owner)
Remove/Replace with 20" by 18" enameled cast iron with one hole center for faucet, back ledge, wall
hanger, front overflow by American Standard, Zurn or Kohler or approved equal. Installation To Include but
not limited to new supply line, fittings, escutcheons, etc... for the fully functional and properly operating
lavatory. Wrap waterline with Lav Guard or approved equal. (Color to be White)
Remove/Replace with new Chrome finish drain line including escutcheons at wall. Wrap with Lav Guard or
equal pipe protection.
Remove/Furnish and Install New Stainless Steel Clean Out Covers
Floor Mount
Wall hung
Lever Handle (Hot and Cold)
Action
Leave In Place
N/A
N/A
N/A
Remove/Furnish and Install with New American Standard 3461.001 16‐1/2" high, floor mounted, vitreous
china, elongated siphon jet water saver 1.6 GPF bowl with 1‐1/2" top spud, china caps or approved equal
Kohler or Zurn. Provide new open front, elongated plastic seat with concealed stainless steel check hinge
Church, Bemis or approved equal. Installation to include but not limited to fittings, escutcheons, gaskets,
etc... for fully functional and properly operational water closet.
(Color to be White)
Remove/Replace with 0.125 GPF Kohler (Dexter) K‐5452, American Standard, Zurn, or approved equal. (Color
to be White) Flush Valve to be .0125 GPF Kohler, American Standard, Zurn, Sloan or approved equal
Remove/Replace with new 4" center, Hot and Cold water supply self‐closing metered push down faucet by
Chicago, Zurn, or approved equal. Installation to include all associated fitting, gaskets, escutcheons, etc… for
fully functioning properly operating faucets. (Chrome Finish)
Leave in Place
Remove/Replace with new 1.6 GPF Flush valve with 1" screwdriver angle check stop, vandal resistant stop
cap, ADA flush handle, vacuum breaker, 1" chrome plated wall supply cover pipe, chrome plated cast brass
escutcheon with set screw, 1‐1/2" chrome plated flush pipe, Zurn Z‐6000XL‐WSI‐YBYCYK, Sloan No. 111‐
1.6YK or Delany F‐414‐1.6‐T42‐T36, or approved equal by American Standard. Finish to be Chrome.
Remove Tile/Prep/ Install 6 x6 Quarry Tile/Slope to Floor Drain/Install New Threshold at Entrances/ ‐
Contractor may Install 6" or 8" Quarry Tile Base to cover existing Base Line of Previous Floor Type
(Color selection by Owner)
Prep/Point Up, Mortar Cracks,Holes,Joints,Caulk as needed/Scrape Flaking Paint/ Prime (1) coat/Paint (2)
coats. Top Coat to be Interior Pre‐catalyzed epoxy, (semi gloss) (Color selection by Owner)
Prep/Patch, Sand, Caulk as needed/Prime (1) coat/Paint (2) coats. Top Coat to be Interior Pre‐catalyzed
epoxy, (semi gloss) (Color selection by Owner)
(4) 4' 2 bulb recessed Fluorescent
Leave In Place/Clean Lens
Leave In Place/Clean
Remove/Furnish and Install New GFCI Receptacle (Gray Color) 120 volt 20 amp
Remove/Furnish and Install New GFCI Receptacle Cover (Stainless Steel)
HVAC
GFCI (Painted Over)
Staff Restroom Renovations Scope Sheet
School: Virginia Williams Elementary School
Rest Room Location: 4th/5th Grade Girls
Item: Quantity Sqft. lnft.
Signage 1
Door
Door Frame
Door Hardware
Floors 265
Walls 830 83
Ceilings 10'‐0" 265
Lavatory 2
Lavatory Drain Lines 2
Water Closet 5
Urinal & Flush Valve
Faucets 2
Hose Bib 2
Flush Valves(Water Closet) 5
1
Clean Out Covers 1 Painted (under sinks)
Toilet Partitions 5
Mirror 1
Soap Dispenser 2
Sani Seat Dispenser
Toilet Paper Dispenser 5
Paper Towel Dispenser 1
Trash Receptacle
Access Panel/Door 1
Shelving
Grab Bars 2
HVAC 1
Electrical
1
1
Switches
Lights 4
4/30/2020
Receptacle Cover Plate
Switch Cover Plate
One wall at entrance
24" x 60" stainless steel edge
GFCI (Painted Over)
wall hung
Ceiling
Wall Mounted
brass
CMU/Painted
Drywall
Wall hung
HDPE Stalls with Doors‐1 is HC
Receptacles
Remove/Install new grab bars and add any necessary grab bars to meet most recent ADA code
N/A
Floor Drain Grate
wall hung
stall Hung Remove/Clean/Re‐Install on new stalls
Remove/Clean/Re‐Install after painting.
N/A
Paint to match ceiling
Remove/Furnish and Install (2) New mirror 24" x 36" with Stainless Steel edging over sinks. Furnish and Install
(1) new 24' x 60" Mirror with stainless steel edging (Location selected by Owner).
Remove/Clean/Re‐Install after painting
N/A
Hand Dryer
Existing Description
Ceramic Tile
Remove/Install New/Adjust floor drain grate to proper height with newly installed floor tile and not rising
above new floor tile elevation
Remove/Furnish and Install new HDPE toilet partition with doors, and hardware. (Color Selected By
Owner)
Remove/Replace with 20" by 18" enameled cast iron with one hole center for faucet, back ledge, wall
hanger, front overflow by American Standard, Zurn or Kohler or approved equal. Installation To Include but
not limited to new supply line, fittings, escutcheons, etc... for the fully functional and properly operating
lavatory. Wrap waterline with Lav Guard or approved equal. (Color to be White)
Remove/Replace with new Chrome finish drain line including escutcheons at wall. Wrap with Lav Guard or
equal pipe protection.
Remove/Furnish and Install New Stainless Steel Clean Out Cover
Floor Mount
Lever Handle (Hot and Cold)
Action
Leave In Place
N/A
N/A
N/A
Remove/Furnish and Install with New American Standard 3461.001 16‐1/2" high, floor mounted, vitreous
china, elongated siphon jet water saver 1.6 GPF bowl with 1‐1/2" top spud, china caps or approved equal
Kohler or Zurn. Provide new open front, elongated plastic seat with concealed stainless steel check hinge
Church, Bemis or approved equal. Installation to include but not limited to fittings, escutcheons, gaskets,
etc... for fully functional and properly operational water closet.
(Color to be White)
N/A
Remove/Replace with new 4" center, Hot and Cold water supply self‐closing metered push down faucet by
Chicago, Zurn, or approved equal. Installation to include all associated fitting, gaskets, escutcheons, etc… for
fully functioning properly operating faucets. (Chrome Finish)
Leave in Place
Remove/Replace with new 1.6 GPF Flush valve with 1" screwdriver angle check stop, vandal resistant stop
cap, ADA flush handle, vacuum breaker, 1" chrome plated wall supply cover pipe, chrome plated cast brass
escutcheon with set screw, 1‐1/2" chrome plated flush pipe, Zurn Z‐6000XL‐WSI‐YBYCYK, Sloan No. 111‐
1.6YK or Delany F‐414‐1.6‐T42‐T36, or approved equal by American Standard. Finish to be Chrome.
Remove Tile/Prep/ Install 6 x6 Quarry Tile/Slope to Floor Drain/Install New Threshold at Entrances/ ‐
Contractor may Install 6" or 8" Quarry Tile Base to cover existing Base Line of Previous Floor Type
(Color selection by Owner)
Prep/Point Up, Mortar Cracks,Holes,Joints,Caulk as needed/Scrape Flaking Paint/ Prime (1) coat/Paint (2)
coats. Top Coat to be Interior Pre‐catalyzed epoxy, (semi gloss) (Color selection by Owner)
Prep/Patch, Sand, Caulk as needed/Prime (1) coat/Paint (2) coats. Top Coat to be Interior Pre‐catalyzed
epoxy, (semi gloss) (Color selection by Owner)
(4) 4' 2 bulb recessed Fluorescent
Leave In Place/Clean Lens
Leave In Place/Clean
Remove/Furnish and Install New GFCI Receptacle (Gray Color) 120 volt 20 amp
Remove/Furnish and Install New GFCI Receptacle Cover (Stainless Steel)
HVAC
GFCI (Painted Over)
OWNER-CONTRACTOR AGREEMENT
THIS AGREEMENT is made this ____ day of ________ 2020 by and between the
Brunswick County Board of Education (herein referred to as the Owner), whose mailing address is
35 Referendum Dr., Bolivia, NC 28422 and _______________ (herein referred to as the
AContractor@), whose mailing address is __________________, North Carolina ______.
Correspondence, submittals, and notices relating to or required under this Agreement shall be sent
in writing to the above addresses unless either party is notified in writing by the other of a change
in address.
WITNESSETH:
WHEREAS, it is the intent of the Owner to obtain the services of the Contractor in
connection with ____________________: and
WHEREAS, the Contractor desires to perform such construction in accordance with the
terms and conditions of this Agreement.
NOW, THEREFORE, in consideration of the promises made herein and other good and
valuable consideration, the following terms and conditions are hereby mutually agreed to, by and
between the Owner and Contractor:
1. Scope of Services. The Contractor shall perform the Work in accordance with the terms
of this Agreement, any plans and specifications prepared for this Project, and the
description of services attached to this Agreement as Exhibit A, all of which are
incorporated into and made a part of this Agreement. The Contractor agrees that any
general terms and conditions that are attached to Exhibit A that are inconsistent with this
Agreement shall not be applicable to this Agreement, and any such provisions shall be
deemed null and void.
a. The Contractor shall provide and pay for all materials, tools, equipment, and labor, and
shall perform all other acts and supply all other services and things necessary to fully
and properly perform and complete the Work as required by this Agreement.
b. The Contractor shall perform the Work in compliance with all governmental laws and
regulations, including all applicable local, state and federal rules and regulations.
c. The Contractor shall, unless otherwise specified, supply and pay for all labor,
transportation, materials, tools, apparatus, lights, power, fuel, sanitary facilities, and
incidentals necessary for the completion of his work, and shall install, maintain and
remove all equipment of the construction, other utensils or things, and be responsible
for the safe, proper and lawful construction, maintenance and use of same, and shall
construct in the best and most workmanlike manner, a complete job and everything
incidental thereto, as shown on the plans, stated in the specifications, or reasonably
implied therefrom, all in accordance with the Agreement documents.
Small Project Construction Contract Form v.2
d. All materials shall be new and of quality specified, except where reclaimed material is
authorized herein and approved for use. Workmanship shall at all times be of a grade
accepted as the best practice of the particular trade involved, and as stipulated in
written standards of recognized organizations or institutes of the respective trades
except as exceeded or qualified by the specifications.
e. Products are generally specified by ASTM or other reference standard and/or by
manufacturer's name and model number or trade name. When specified only by
reference standard, the Contractor may select any product meeting this standard, by
any manufacturer. When several products or manufacturers are specified as being
equally acceptable, the Contractor has the option of using any product and
manufacturer combination listed. However, the Contractor shall be aware that the cited
examples are used only to denote the quality standard of product desired and that they
do not restrict bidders to a specific brand, make, manufacturer or specific name; that
they are used only to set forth and convey to bidders the general style, type, character
and quality of product desired; and that equivalent products will be acceptable.
Substitution of materials, items or equipment of equal or equivalent design shall be
submitted to the architect or engineer for approval or disapproval; such approval or
disapproval shall be made by the architect or engineer prior to the opening of bids.
f. The Contractor shall designate a foreman/superintendent who shall direct the work.
g. If at any time during the construction and completion of the work covered by this
Agreement, the conduct of any workman be adjudged a nuisance to the Owner or
considered detrimental to the work, the Contractor shall order such parties removed
immediately from the Owner’s property.
h. The Contractor shall keep the sites and surrounding area reasonably free from rubbish
at all times and shall remove debris from the site from time to time or when directed to
do so by the Owner. Before final inspection and acceptance of the Project, the
Contractor shall thoroughly clean the sites, and completely prepare the Project and site
for use by the Owner.
i. Temporary electricity and water shall be arranged by the Contractor at the Contractor’s
expense.
2. Compensation. Provided that the Contractor shall strictly and completely perform all of
its obligations under this Agreement, the Owner shall pay the Contractor the amount of
_______ dollars ($______) (herein referred to as the AContract Sum@). No compensation
shall be paid for any additional work that is not approved in advance by the Owner. One
progress payment, if any, may be made by the Owner to the Contractor only after
certification that the Work is complete and will be based upon the completion of the
identified interim work agreed to by the Owner. Under no circumstances will the Owner
make more than one interim payment. The Owner will retain five percent (5%) of the
amount of any progress payment and/or the Contract Sum until all of the Work is finally
completed and accepted, whether or not the Owner has occupied any or all of the Project
before such time. Final payment will be withheld until the Contractor’s North Carolina
Small Project Construction Contract Form v.2
sales and use tax report is received. The report shall accurately list any and all sales and
use tax paid on materials for the entire Project.
3. Time. The Contractor shall commence the Work promptly upon the date established in
the Notice to Proceed, the date of this Agreement, or such other date as may be established
by the Owner. Time is of the essence. The Contractor shall perform work in a timely
manner.
4. Codes, Permits and Inspections.
a. The Contractor shall obtain the required permits, give all notice and comply with all
laws, ordinances, codes, rules and regulations bearing on the conduct of the work under
this Agreement. If the Contractor observes that the drawings and specifications are at
variance therewith, he shall promptly notify the architect or engineer in writing. If the
Contractor performs any work knowing it to be contrary to such laws, ordinances,
codes, rules and regulations, and without such notice to the Owner, he shall bear all
cost arising therefrom.
b. All work under this Agreement shall conform to the North Carolina State Building
Codes and other state and national codes as are applicable.
5. Safety Requirements.
a. The Contractor shall be responsible for the entire site and the construction of the same
and provide all the necessary protections as required by laws or ordinances governing
such conditions and as required by the Owner, architect or engineer. He shall be
responsible for any damage to the Owner's property or that of others on the job, by
himself, his personnel or his subcontractors, and shall make good such damages. He
shall be responsible for and pay for any claims against the Owner arising from such
damages.
b. The Contractor shall adhere to the rules, regulations and interpretations of the North
Carolina Department of Labor relating to Occupational Safety and Health Standards
for the Construction Industry (Title 29, Code of Federal Regulations, Part 1926
Construction and Part 1910 General Industry).
c. The Contractor shall provide all necessary safety measures for the protection of all
persons on the work, including the requirements of the AGC Accident Prevention
Manual in Construction as amended, and shall fully comply with all state laws or
regulations and North Carolina State Building Code requirements to prevent accident
or injury to persons on or about the location of the work. He shall clearly mark or post
signs warning of hazards existing, and shall barricade excavations and similar hazards.
He shall protect against damage or injury resulting from falling materials and he shall
maintain all protective devices and signs throughout the progress of the work.
6. Warranties. The Contractor guarantees and warrants to the Owner all Work as follows:
that all materials and equipment furnished under this Agreement will be new and the best
of its respective kind unless otherwise specified; that all Work will be of good quality in
accordance with the industry standards for reputable contractors; that the Work will be free
Small Project Construction Contract Form v.2
of omissions and faulty, poor quality, imperfect and defective material or workmanship;
that the Work, including but not limited to, mechanical and electrical machines, devices
and equipment, shall be fit and fully usable for its intended and specified purpose and shall
operate satisfactorily with ordinary care; that the products or materials incorporated in the
Work will not contain asbestos; and that all agents or employees of Contractor who will
provide services under this Agreement will be fully qualified, possess any requisite
licenses, and otherwise be legally entitled to perform the services provided; and that the
person(s) executing this Agreement on behalf of Contractor have authority to do so as an
official, binding act of Contractor.
If, within one year after the Date of Substantial Completion of the Work or designated
portion thereof or within one year after acceptance by the Owner of designated equipment
or within such longer period of time as may be prescribed by law or by the terms of any
applicable special warranty required by this Agreement, any of the Work is found to be
defective, not in accordance with this Agreement, or not in accordance with the guarantees
and warranties specified in this Agreement, the Contractor shall correct it within five (5)
working days or such other period as mutually agreed, after receipt of a written notice from
the Owner to do so. For items which remain incomplete or uncorrected on the date of
Substantial Completion, the one year warranty shall begin on the date of Final Completion
of the Work.
7. Contractor-Subcontractor Relationships. The Contractor agrees that the terms of these
Agreement documents shall apply equally to a subcontractor as to the Contractor, and that
the subcontractor is bound by those terms as an agent of the Contractor.
8. Hold Harmless. The Contractor shall indemnify and hold the Owner harmless from and
against any and all losses, liabilities, claims, lawsuits, judgments, and demands
whatsoever, including costs of investigation (including reimbursement of reasonable legal
fees and all costs) caused solely by any negligent act or omission or intentional
wrongdoing of the Contractor or its agents, employees or subcontractors, or caused solely
by the maintenance, presence, use, location or removal of any equipment or other property
owned or operated by the Contractor or its agents, employees or subcontractors. The
parties agree that this indemnification clause is an “evidence of indebtedness” for purpose
of N. C. Gen. Stat. § 6-21.2. The Owner shall not be responsible for any damage to the
Contractor=s property, business, agents or employees, unless said damage is due solely to
the negligence of Owner.
9. Insurance. The Contractor shall obtain and maintain in effect during the term of this
Agreement, general liability and automobile liability insurance in which the Owner and the
Contractor shall each be named as insured parties, which insurance shall protect the Owner
and the Contractor from claims in an amount not less than $1,000,000 for personal injury,
including death, to any one person and in an amount not less than $1,000,000 for any one
occurrence, and from claims for property damages in an amount of not less than
$1,000,000 for each occurrence arising from any act or omission of Contractor, its agents,
employees or subcontractors. The Contractor shall obtain and maintain in effect during
the term of this Agreement, a policy of workers compensation liability insurance in which
the policy shall protect the Owner and the Contractor from claims in an amount not less
Small Project Construction Contract Form v.2
than the statutory amount.
The Contractor shall promptly furnish to the Owner certificates of insurance evidencing
such insurance coverage. Insurance required hereunder shall be maintained by insurance
companies properly licensed by the Insurance Department of the State of North Carolina
and rated A or better by Best Insurance Guide.
10. Termination for Convenience. The Board may terminate this Agreement at any time in its
complete discretion upon twenty (20) days written notice. In the event of a termination
for convenience, all finished or unfinished work and materials pursuant to this Agreement
shall be turned over to the Board and become its property. If the Agreement is terminated
by the Board in accordance with this section, the Board shall only be responsible for paying
Contractor for all Work performed and accepted and all materials delivered to the site as of
the date of termination.
11. Termination by the Owner for Cause. The Owner may terminate the Agreement upon five
(5) days written notice if the Board is dissatisfied with the quality or timeliness of the Work
performed. If the Owner becomes dissatisfied with the Work, the Owner may without
prejudice to any other rights or remedies of the Owner and after giving the Contractor five
days’ written notice, terminate employment of the Contractor and may:
1. Exclude the Contractor from the site and take possession of all materials,
equipment, tools, and construction equipment and machinery thereon owned by
the Contractor;
2. Accept assignment of any subcontracts; and
3. Finish the Work by whatever reasonable method the Owner may deem
expedient. Upon written request of the Contractor, the Owner shall furnish to
the Contractor a detailed accounting of the costs incurred by the Owner in
finishing the Work.
If the Owner terminates the whole or any part of the Work, the Owner may procure, upon
such terms and in such manner as the Owner may deem appropriate, supplies or services
similar to those so terminated, and the Contractor shall be liable to the Owner for any
excess costs for such similar supplies or services. The Contractor shall continue the
performance of the Agreement to the extent not terminated hereunder.
When the Owner terminates the Agreement, the Contractor shall not be entitled to receive
further payment until the Work is finished. If the unpaid balance of the Contract Sum
exceeds costs of finishing the Work, including compensation for the Architect’s and legal
services and expenses made necessary thereby, and other damages incurred by the Owner
and not expressly waived, such excess shall be paid to the Contractor. If such costs and
damages exceed the unpaid balance, the Contractor shall pay the difference to the Owner.
The amount to be paid to the Contractor or Owner, as the case may be, shall be certified by
the Architect and this obligation for payment shall survive this Agreement.
Small Project Construction Contract Form v.2 6
12. Lunsford Act/Criminal Background Checks. The Contractor shall conduct or arrange to
have conducted at its own expense sexual offender registry checks on each of its owners,
employees, agents, or subcontractors (“contractual personnel”) who will engage in any
service on or delivery of goods to school system property or at a school-system sponsored
event, except checks shall not be required for individuals who are solely delivering or
picking up equipment, materials, or supplies at: (1) the administrative office or loading
dock of a school; (2) non-school sites; (3) schools closed for renovation; or (4) school
construction sites. The checks shall include at a minimum checks of the State Sex
Offender and Public Protection Registration Program, the State Sexually Violent Predator
Registration Program, and the National Sex Offender Registry (“the Registries”). For the
Contractor’s convenience only, all of the required registry checks may be completed at no
cost by accessing the United States Department of Justice Sex Offender Public Website at
http:// www. nsopw.gov/. The Contractor shall provide certification that the registry
checks were conducted on each of its contractual personnel providing services or
delivering goods under this Agreement prior to the commencement of such services or the
delivery of such goods (Registry Check Certification Form – Exhibit B). The Contractor
shall conduct a current initial check of the registries (a check done more than 30 days prior
to the date of this Agreement shall not satisfy this contractual obligation). In addition,
Contractor agrees to conduct the registry checks and provide a supplemental certification
before any additional contractual personnel are used to deliver goods or provide services
pursuant to this Agreement. Contractor further agrees to conduct annual registry checks
of all contractual personnel and provide annual certifications at each anniversary date of
this Agreement. Contractor shall not assign any individual to deliver goods or provide
services pursuant to this Agreement if said individual appears on any of the listed
registries. Contractor agrees that it will maintain all records and documents necessary to
demonstrate that it has conducted a thorough check of the registries as to each contractual
personnel, and agrees to provide such records and documents to the school system upon
request. Contractor specifically acknowledges that the school system retains the right to
audit these records to ensure compliance with this section at any time in the school
system’s sole discretion. Failure to comply with the terms of this provision shall be
grounds for immediate termination of the Agreement. In addition, the Owner may
conduct additional criminal records checks at the Owner’s expense. If the school system
exercises this right to conduct additional criminal records checks, Contractor agrees to
provide within seven (7) days of request the full name, date of birth, state of residency for
the past ten years, and any additional information requested by the school system for all
contractual personnel who may deliver goods or perform services under this Agreement.
Contractor further agrees that it has an ongoing obligation to provide the school system
with the name of any new contractual personnel who may deliver goods or provide services
under the Agreement. The Owner reserves the right to prohibit any contractual personnel
of Contractor from delivering goods or providing services under this Agreement if the
Owner determines, in its sole discretion, that such contractual personnel may pose a threat
to the safety or well-being of students, school personnel or others.
13. Governing Law. This Agreement and the relationship of the parties shall be governed by
Small Project Construction Contract Form v.2 7
the laws of the state of North Carolina.
14. Entire Agreement. All of the representations and obligations of the parties are contained
herein, and no modification, waiver or amendment of this Agreement or of any of its
conditions or provisions shall be binding upon a party unless in writing signed by that
party. The waiver by any party of a breach of any provision of this Agreement shall not
operate or be construed as a waiver of any subsequent breach of that provision by the same
party, or of any other provision or condition of the Agreement.
15. Severability. If any section, subsection, term or provision of this Agreement or the
application thereof to any party or circumstance shall, to any extent, be invalid or
unenforceable, the remainder of said section, subsection, term or provision of the
Agreement or the application of the same to parties or circumstances other than those to
which it was held invalid or unenforceable, shall not be affected thereby and each
remaining section, subsection, term or provision of this Agreement shall be valid or
enforceable to the fullest extent permitted by law.
16. Compliance with Applicable Laws. Contractor shall comply with all applicable laws and
regulations in providing services under this Agreement. In particular, Contractor shall not
employ any individuals to provide services to the Owner who are not authorized by federal
law to work in the United States. Contractor represents and warrants that it is aware of
and in compliance with the Immigration Reform and Control Act and North Carolina law
(Article 2 of Chapter 64 of the North Carolina General Statutes) requiring use of the
E-Verify system for employers who employ twenty-five (25) or more employees and that it
is and will remain in compliance with these laws at all times while providing services
pursuant to this Agreement. Contractor shall also ensure that any of its subcontractors (of
any tier) will remain in compliance with these laws at all times while providing
subcontracted services in connection with this Agreement. Contractor is responsible for
providing affordable health care coverage to all of its full-time employees providing
services to the School System. The definitions of “affordable coverage” and “full-time
employee” are governed by the Affordable Care Act and accompanying IRS and Treasury
Department regulations.
17. Restricted Companies List. Contractor represents that as of the date of this Agreement,
Contractor is not included on the Final Divestment List created by the North Carolina State
Treasurer pursuant to N.C. Gen. Stat. § 147-86.58. Contractor also represents that as of
the date of this Agreement, Contractor is not included on the list of restricted companies
determined to be engaged in a boycott of Israel created by the North Carolina State
Treasurer pursuant to N.C. Gen. Stat. § 147-86.81.
18. Anti-Nepotism. Contractor warrants that, to the best of its knowledge and in the exercise
of due diligence, none of its corporate officers, directors, or trustees and none of its
employees who will directly provide services under this Agreement are immediate family
members of any member of the Brunswick County Board of Education or of any principal
Small Project Construction Contract Form v.2 8
or central office staff administrator employed by the Board. For purposes of this provision,
“immediate family” means spouse, parent, child, brother, sister, grandparent, or
grandchild, and includes step, half, and in-law relationships. Should Contractor become
aware of any family relationship covered by this provision or should such a family
relationship arise at any time during the term of this Agreement, Contractor shall
immediately disclose the family relationship in writing to the Superintendent of the
Schools. Unless formally waived by the Board, the existence of a family relationship
covered by this Agreement is grounds for immediate termination by Owner without further
financial liability to Contractor.
19. Applicable School Board of Education Policies. Contractor acknowledges that the
Brunswick County Board of Education has adopted policies governing conduct on School
System property and agrees to abide by any and all relevant Board policies while on School
System property. The Contractor acknowledges that Board’s policies are available on the
School System’s website.
20. Exhibits.
Exhibit A: Scope of Services
Exhibit B: Sexual Registry Check Certification Form
Small Project Construction Contract Form v.2 9
IN WITNESS WHEREOF, the Owner has caused these presents to be signed and the
Contractor has caused these presents to be signed by a person with the authority to enter this
Agreement, as hereinafter attested, all as of the day and year first above written.
BRUNSWICK COUNTY BOARD OF EDUCATION
By: _____________________________________________________________(Seal)
__________________, Chairperson
Attest: _____________________________________________________________(Seal)
__________________, Superintendent
[INSERT CORPORATE NAME OF CONTRACTOR]
By: ____________________________________________________________(Seal)
[INSERT NAME OF CORPORATE PRESIDENT OR VICE PRESIDENT]
Attest: _____________________________________________________________(Seal)
[INSERT NAME OF CORPORATE SECRETARY]
This instrument has been preaudited in the manner required by the School Budget and Fiscal
Control Act.
________________________________________________
(Date)
________________________________________________
(Signature of finance officer)
BUDGET CODE: _____________________
Small Project Construction Contract Form v.2 10
Exhibit B
Sexual Offender Registry Check Certification Form
Check the appropriate box to indicate the type of check:
□ Initial
□ Supplemental
□ Annual
I, _______________ (insert name), ______________ (insert title) of ____________ (insert
company name) hereby certify that I have performed all of the required sexual offender registry
checks required under this Agreement for all contractual personnel (employees, agents, ownership
personnel, or contractors ) who may be used to deliver goods or provide services under this
Agreement, including the North Carolina Sex Offender and Public Protection Registration
Program, the North Carolina Sexually Violent Predator Registration Program, and the National
Sex Offender Registry. I further certify that none of the individuals listed below appears on any
of the above-named registries and that I will not assign any individual to deliver goods or perform
services under this Agreement if said individual appears on any of the sex offender registries. I
agree to maintain all records and documents associated with these registry checks, and that I will
provide such records and documents to the school system upon request. I specifically
acknowledge that the school system retains the right to audit these records to ensure compliance
with this section at any time in the school system’s sole discretion. I acknowledge that I am
required to perform these checks and provide this certification form before any work is performed
under the Agreement (initial check), any time additional contractual personnel may perform work
under the Agreement (supplemental check), and at each anniversary date of the Agreement (annual
check).
Contractual Personnel Names Job Title
1. ________________________ ________________________
2. ________________________ ________________________
3. ________________________ ________________________
4. ________________________ ________________________
5. ________________________ ________________________
(attach additional page(s) if needed)
I attest that the forgoing information is true and accurate to the best of my knowledge.
_____________________ (print name) _____________________ (signature)
_____________________ (title) ______________________ (date)
•Board Members: Charles Miller., Chairman • Catherine Cooke, Vice-Chairman • Ed Lemon, Jr. • John Thompson • Ellen Milligan • Leslie K. Tubb, Superintendent
EXHIBIT C - BID FORM BID REQUEST NO.: 153.VAR.20.BOND.128
PROJECT DESCRIPTION: Restroom Renovations - South ___________________________________________________________________________________________
Company Name:
Street Address:
City, State, Zip Code:
Contact Person:
Contact Information:
It has been determined that the above specified project is a Capital Improvement as defined in E505 (09-17). Brunswick
County Board of Education will issue a E589-CI, Affidavit of Capital Improvement, upon award of the bid.
It has been determined that the above specified project is:
Subject to NC Sales & Use Tax
Not Subject to NC Sales & Use Tax
________________________________ proposes to do the above specified project for:
Company Name
Project Expense $____________
Owner Contingency $_7500.00___________
Total Project Cost $____________
Unless otherwise noted, the Total Project Cost includes all material, labor, permitting, freight, taxes,
allowances, and other charges. . Bids are to be valid for 30 days. “N.C.G.S. § 133-32 and Executive Order 24 prohibit the offer to, or acceptance by, any State Employee
of any gift from anyone with a contract with the State, or from any person seeking to do business with the State. By execution of any
response in this procurement, you attest, for your entire organization and its employees or agents, that you are not aware that any such
gift has been offered, accepted, or promised by any employees of your organization.
________________________________ ___________________
Name, Position of Company Representative Signature Date
Projects will be awarded based on cost, adherence to Informal Bid Request requirements, contractor’s ability to meet the
schedule, and contractor’s references. Contractor must be able to comply with Brunswick County Schools Terms and
Conditions (attached). The Brunswick County Board of Education has a right to reject any or all bids, pursuant to NC Statute
and Board of Education Policy, and to waive any or all informalities.