booster issues for numi eric prebys fnal beams division

22
Booster Issues for NuMI Eric Prebys FNAL Beams Division

Upload: hester-johns

Post on 13-Dec-2015

232 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Booster Issues for NuMI Eric Prebys FNAL Beams Division

Booster Issues for NuMI

Eric Prebys

FNAL Beams Division

Page 2: Booster Issues for NuMI Eric Prebys FNAL Beams Division

The Basics

• One of two electrostatic pre-accs accelerates H- ions to 750 keV. • The linac accelerates these ions to 400 MeV• The ions are injected over several (up to 15) turns into the booster, and passed through a foil to strip off the

electrons.• The booster accelerates the protons from 400 MeV to 8 GeV.• The booster lattice is in an offset 15 Hz (line/4) resonant circuit. This sets an overall quantum of time for

the whole accelerator (“tick”, “click”, “clink”).• Instantaneous 15 Hz rep rate routinely achieved.• Average rep rate limited by

– Power dissipation of ramped elements– Above ground radiation (safety issues)– Below ground radiation (activation issues)

• Some numbers:– Historical high*: 3E12 ppp @2.5 Hz (3E16 pph)– Run II needs: 5E12 ppp @.7 Hz (1.3E16 pph)– BooNE+Run II: 5E12 ppp @5.7 Hz (1.1E17 pph)– NuMI + Run II: 5E12 ppp @3.2 Hz (6E16 pph)– NuMI + Run II+BooNE: 5E12 [email protected] (1.7E17 pph)

*MR fixed target, back when life was cheap

Factor 8!

Page 3: Booster Issues for NuMI Eric Prebys FNAL Beams Division

Pulsed element limits

• Linac chopper: 15 Hz

• ORBUMP Magnets: 7.5 Hz (lots of work to go to 15Hz)

• Booster RF: 7.5 Hz (Maybe go to 15 if we use existing cooling lines).

• BEXBMP: 15 Hz

• Extraction kickers: 15 Hz

• MP02 extraction septum: 2.5 Hz (New PS -> 4.5 Hz ~9/02, New magnet + PS -> 7.5Hz ~1/03, + more cables -> 15 Hz)

• -> We currently take 7.5 Hz as a practical limit for BooNE and beyond.

Page 4: Booster Issues for NuMI Eric Prebys FNAL Beams Division

Radiation Issues

• Radiation Limitations– Above ground (want to avoid turning towers into controlled

access area).• Shielding

• Reduce beam losses

– Below ground (must avoid making booster elements too hot to handle).

• Reduce beam losses

Page 5: Booster Issues for NuMI Eric Prebys FNAL Beams Division

Proton Timelines

• Everything measured in 15 Hz “clicks”• Minimum M.I. Ramp = 22 clicks = 1.4 s• MiniBoone batches “don’t count”.• Cycle times of interest

– Stack cycle: 1 inj + 22 MI ramp = 23 clicks = 1.5 s– NuMI cycle: 6 inj + 22 MI ramp = 28 clicks = 1.9 s– Full Slipstack cycle (total 11 batches):

6 inject+ 2 capture (6 -> 3)+ 2 inject+ 2 capture (2 -> 1)+ 2 inject+ 2 capture (2 -> 1)+ 1 inject+ 22 M.I. Ramp----------------------39 clicks = 2.6 s

Page 6: Booster Issues for NuMI Eric Prebys FNAL Beams Division

Summary of Proton Ecomomics

 

Batches Protons delivered ( x E12 pps)* Total Scenario Cycle (clicks)

prepulse Stack MB NuMI

Rep rate (ave. Hz) Stack MB NuMI E12 /RunII

Stack 23 2 1 2.0 3.3 0. 0. 3.3 1.

Stack/MB 23 2 1 8 7.2 3.3 26.1 0. 29.3 9.0

Stack/NuMI 28 2 1 5 4.3 2.7 0. 13.4 16.1 4.9

Stack/NuMI/MB 28 2 1 10 5 9.6 2.7 28.8 13.4 42.9 13.1

Slipstack/NuMI 39 2 2 9 5.0 3.8 0. 17.3 21.2 6.5

Slipstack/NuMI/MB 39 2 2 13 9 10.0 3.8 25.0 17.3 46.2 14.2

Booster Hardware Issues Radiation Issues

NUMI “baseline” = 13.4E12 pps x 2E7 s/year 2.7E20 p/year

*assuming 5E12 protons per batch

Page 7: Booster Issues for NuMI Eric Prebys FNAL Beams Division

Best Performance + Shielding + BooNE Intensities

0.00

0.20

0.40

0.60

0.80

1.00

1.20

1.40

L1

L2

L3

L4

S4

S5

S6

S7

S8

S9

S1

0

S1

1

S1

2

Ext

L1

4

L1

5

L1

6

L1

7

L1

8

L1

9

L2

0

L2

1

L2

2

L2

3

L2

4

MI8

Fra

ctio

n o

f tr

ip @

1.2

E17

p/h

r

Jun 18, 2001 00:00 to Jun 18, 2001 11:00, <p/cycle> = 4.5E+12

Jun 17, 2001 10:00 to Jun 18, 2001 00:00, <p/cycle> = 4.7E+12

Year-averaged Limit @ 60% duty factor

Collimators Should clean up this region

Page 8: Booster Issues for NuMI Eric Prebys FNAL Beams Division

Bottom Line for Above Ground Radiation

• It looks like with a combination of shielding and careful beam handling, we should be able to keep above ground radiation to acceptable levels, even at BooNE+Run II intensities.

Page 9: Booster Issues for NuMI Eric Prebys FNAL Beams Division

Below Ground Radiation Issues

• Harder to quantify (no hard limits)• Worry about high service components becoming so

activated that they can’t be worked on (e.g. RF cavities).

• Some are already disturbingly hot (~200-300 mRem @ 1 foot)

• More about this in a minute…

Page 10: Booster Issues for NuMI Eric Prebys FNAL Beams Division

Collimators

Basic Idea…

A scraping foil deflects the orbit of halo particles…

…and they are absorbed by thick copper collimators.

All are moveable, and the Copper collimators are located in areas (period 6&7) where radiation is less of an issue. Once their operation has been established, these areas will be heavily shielded.

It is hoped that this collimation could reduce important losses by up to a factor of two.

Status: All collimators are in and have been exercised. We are learning how to use them. They cannot be regularly used until the shielding is in place (by the shutdown).

Page 11: Booster Issues for NuMI Eric Prebys FNAL Beams Division

Collimator Performance

Time

Position

Rel

ativ

e L

oss

Page 12: Booster Issues for NuMI Eric Prebys FNAL Beams Division

Ramped Closed Orbit Corrections

• The main beam elements ramp with the momentum, but up until now, the corrector elements have been operated DCBeam can “wander” by up to a few cm’s during ramp.

• Ramping control cards were installed during the shutdown.

• Closure control program almost ready. Still needs to be tested.

• Correctors not powerful enough to steer the beam all the way through the cycle. Still, should help.

Page 13: Booster Issues for NuMI Eric Prebys FNAL Beams Division

Steered (flattened) Beam with Collimators

Position

Steered

unsteered

Relative Losses near extraction septum. Overall performance improved over unsteered collimation

Page 14: Booster Issues for NuMI Eric Prebys FNAL Beams Division

MiniBooNE Comes on Line

MiniBooNE

Stacking

Total

Want Relative Sizes of MB and Stacking to Reverse!

Page 15: Booster Issues for NuMI Eric Prebys FNAL Beams Division

Beam Power Loss (Beam Losses)

Present Limit (will at least be doubled)

5 min. Beam Power Loss

Protons delivered per minute (~ 1/10 of full MiniBooNE).

Page 16: Booster Issues for NuMI Eric Prebys FNAL Beams Division

Bottom Line

• We have a LONG way to go to reduce losses to the level where MiniBooNE can run, let alone NUMI.

Page 17: Booster Issues for NuMI Eric Prebys FNAL Beams Division

The “Notch”

• The Booster uses multi-turn injection, resulting in a continuous beam around the ring.

• If beam is passing through the extraction septum while it is ramping, some of it will be steered into beam elements.

• This is the single largest source of radiation resulting from the booster.

• Solution: Early in the cycle, the old extraction kicker is pulsed, blowing a “notch” in the beam. Extraction is timed to coincide with the notch.

• Problem: although it’s a factor of 20 better to lose the beam early in the cycle, it’s still not negligible (more in a minute)

• The notch raises serious complications in timing the booster relative to the main injector (beam cogging)

Page 18: Booster Issues for NuMI Eric Prebys FNAL Beams Division

Timing: The One NuMI Specific Booster Problem

• In order to Reduce radiation, a “notch” is made in the beam early in the booster cycle.

• Currently, the extraction time is based on the counted number of revolutions (RF buckets) of the Booster. This ensures that the notch is in the right place.

• The actual time can vary by > 5 usec!• This is not a problem if booster sets the timing, but

it’s incompatible with multi-bunch running.• We must be able to fix this total time so we can

synchronize to the M.I. orbit.• This is called “beam cogging”.

Page 19: Booster Issues for NuMI Eric Prebys FNAL Beams Division

Active cogging

• Detect slippage of notch relative to nominal and adjust radius of beam to compensate.

Allow to slip by integer turns, maintaining the same total time.

• Does not currently work at high intensities.• Still do not really understand the problem. Suspect

TCLK drift relative to magnet phase, but no correlation seen.

Page 20: Booster Issues for NuMI Eric Prebys FNAL Beams Division

> 5E12 ppp ????

• Early losses are extremely non-linear with number of turns of injection.

• Space charge effects are typically blamed, but the details are not well understood.

• A study group is working on this. • Too late for BooNE, by maybe NuMI?• Increasing the ppp would allow you to almost double

your total protons before hitting the BooNE rad limits!!

Page 21: Booster Issues for NuMI Eric Prebys FNAL Beams Division

Improved Beam Characterization

• We now have the ability to measure the Booster tune for the first time in many years.

• A number of improved monitoring tools have been added over the last year (e.g. linac energy meter), and have dramatically improved consistency.

Page 22: Booster Issues for NuMI Eric Prebys FNAL Beams Division

Some Good News

• In spite of some recent disturbing comments… “If it’s not Run II, I don’t want to talk about it” -Sign on Steve Holmes’ Door

… we have just been promised “substantial” support from the Computing Division for proton source (Booster+Linac) projects.

• It is envisioned that these people work on building and improving tools to monitor machine machine performance.

• “Proton Source” = “MiniBooNE+NUMI”