Bond Construction Update Citizens’ Oversight Committee. Cordoba Corporation. Long Beach Community College District April 21, 2008. BUILDING  TOMORROW  TODAY. Agenda. Completed Construction Projects Current & Upcoming Construction Projects South Quad Complex Structure - PowerPoint PPT Presentation

TRANSCRIPT

Bond Construction Bond Construction UpdateUpdateCitizens’ Oversight Citizens’ Oversight CommitteeCommittee

Bond Construction Bond Construction UpdateUpdateCitizens’ Oversight Citizens’ Oversight CommitteeCommittee

Long Beach Community College DistrictApril 21, 2008

BUILDING TOMORROW TODAY

Cordoba Corporation

Agenda Completed Construction Projects Current & Upcoming Construction Projects

South Quad Complex Structure LAC Central Plant Structure LAC Learning Resources Center – Structure LAC Building A, Student Services Retrofit PCC Central Plant PCC Learning Resources Center PCC Industrial Tech Phase 1 PCC MDAB (Multi-Disciplinary Administration Building)

Q & A

Construction Progress

Completed Construction Projects

PCC Industrial Technology Center Phase 2 – 7/07

PCC Central Plant Utilities, LAC Central Plant & SQC Utilities – 6/07

LAC/LRC Interim – 5/07 East Campus Demo – 12/06 LAC Men’s Gym Façade

Replacement (FEMA & Insurance Funded) – 8/06

LAC/LRC Utilities – 6/06 PCC CDC – 4/06 Men’s Gym Boiler

Replacement – 4/06 LAC Athletic Field – 3/06 District Facilities &

Warehouse Complex – 1/06

Various Projects – Completed in 2006 & 2007Various Projects – Completed in 2006 & 2007

LAC Facility Site Plan

l i b

e r

a l

a r

t s

Current and UpcomingConstruction Projects

Part of Infrastructure Master Plan Improvements

Awarded to Siemens on DBOM Contract

Construction 82% Complete Completion Anticipated

Summer 2008

LAC Central Plant – StructureLAC Central Plant – Structure

Current and UpcomingConstruction Projects

Construction 55% Complete

Combined into Single Construction Phase

Completion Anticipated December 2008

LAC/Learning Resources Center – StructureLAC/Learning Resources Center – Structure

Current and UpcomingConstruction Projects

Construction Approx. 52% Complete

Additional Modern Classrooms, Multi-purpose Rm., Offices, etc.

Shifts Campus Center South of Carson off Lew Davis

Completion Anticipated December 2008

South Quad Complex Structure (Bid Pkg. #3)South Quad Complex Structure (Bid Pkg. #3)

Current and UpcomingConstruction Projects

Martinez Architects received Board Approval as the Architect of Record

Contract was negotiated/signed and Notice to Proceed was issued

Programming work began on April 10, 2008

LAC Building A – Student Services RetrofitLAC Building A – Student Services Retrofit

PCC Facility Site Plan

p a

c i f

i c

c

o a

s t

Current and UpcomingConstruction Projects

Part of Infrastructure Master Plan Improvements

Early Utility Package Construction Complete

DBOM Contract Awarded to Siemens; Finalizing Value Engineering Negotiations

Construction Approximately 36% Complete

Completion Anticipated Summer 2008

PCC Central PlantPCC Central Plant

Current and UpcomingConstruction Projects

Construction 78% Complete Modern Facility with

Computer Lab and Multimedia

New Facility Bridge to Bldg. EE Completion Anticipated

July/August 2008

PCC Learning Resources CenterPCC Learning Resources Center

Current and UpcomingConstruction Projects

Replaces Existing Antiquated Structures

Construction is 12% Complete

Modern Facility Houses Machine Tool and Welding Departments

New Northern Face of the Campus

Completion Anticipated Spring 2009

PCC Industrial Technology Center Phase 1PCC Industrial Technology Center Phase 1

Current and UpcomingConstruction Projects

Programming is completed and submitted to the State for Approval

Schematic Design was completed in February 2008

PCC MDAB PCC MDAB (Multi-Disciplinary Academic Building) (Multi-Disciplinary Academic Building)

QUESTIONS & ANSWERS

Prepared byBond Management Team

April 21, 2008