baglihar hydro electric power plant

69
A MAJOR PROJECT REPORT ON CONSTRUCTION OF HYDRO ELECTRIC POWER PLANT Submitted in partial fulfillment of the requirement for Degree of Bachelor of Engineering In CIVIL Discipline Submitted To [RAJIV GANDHI PRODYOGIKI VISHWAVIDYALAYA, BHOPAL (M.P.)] Submitted By: RAHUL SINGH (0171EC101069) RAJA HAFIZANA AFROZ (0171CE101080) STANZIN SPALZANG (0171CE101099) Under The Guidance Of: Prof. VIKRAM PARIHAR (HOD, Department of Civil Engineering) DEPARTMENT OF CIVIL ENGINEERING ACROPOLIS INSTITUTE OF TECHNOLOGY& RESEARCH, BHOPAL

Upload: raja-katoch

Post on 07-May-2015

993 views

Category:

Engineering


5 download

TRANSCRIPT

Page 1: Baglihar hydro electric power plant

A MAJOR PROJECT REPORT

ON

CONSTRUCTION OF

HYDRO ELECTRIC POWER PLANT

Submitted in partial fulfillment of the requirement for Degree of

Bachelor of Engineering

In

CIVIL Discipline

Submitted To

[RAJIV GANDHI PRODYOGIKI VISHWAVIDYALAYA, BHOPAL (M.P.)]

Submitted By:

RAHUL SINGH (0171EC101069)

RAJA HAFIZANA AFROZ (0171CE101080)

STANZIN SPALZANG (0171CE101099)

Under The Guidance Of:

Prof. VIKRAM PARIHAR

(HOD, Department of Civil Engineering)

DEPARTMENT OF CIVIL ENGINEERING

ACROPOLIS INSTITUTE OF TECHNOLOGY& RESEARCH,

BHOPAL

Page 2: Baglihar hydro electric power plant

SESSION: 2013-20114

Acropolis Institute of Technology & Research,

Bhopal (M.P.) Department of Civil Engineering

CERTIFICATE

This is to certify that the work embodies in this Project Report entitled

“CONSTRUCTION OF HYDRO ELECTRIC POWER PLANT” being submitted

by “Rahul Singh ” (0171EC101069),Raja Hafizana Afroz (0171CE101080),

Stanzin Spalzang (0171CE101099)for partial fulfillment of the requirement

for the degree of “Bachelor of Engineering in Civil Engineering”

discipline to “Rajiv Gandhi Praudyogiki Vishwavidyalaya, Bhopal(M.P.)”

during the academic year 2014-15 is a record of bonafide piece of work,

carried out by him under my guidance and guidance in the “Department

of Civil Engineering”, Acropolis Institute of Technology& Research,

Bhopal (M.P.).

APPROVED & GUIDED BY:

Prof. VIKRAM PARIHAR

(HOD, Department of Civil Engineering)

FORWARDED BY:

(Prof. VIKRAM PARIHAR) (Dr. Kunal Basu)

Head of Civil Engineering Director

AITR, Bhopal AITR, Bhopal

Page 3: Baglihar hydro electric power plant

Acropolis Institute of Technology &Research

Bhopal (M.P.)

Department of Civil Engineering

Acropolis Institute of Technology & Research,

Bhopal (M.P.)

Department of Civil Engineering

DECLARATION

We, Rahul Singh (0171EC101069), Raja Hafizana Afroz

(0171CE101080), Stanzin Spalzang (0171CE101099)” students of

Bachelor of Engineering in Civil discipline, session: 2013-2014,

Acropolis Institute of Technology& Research, Bhopal (M.P.), hereby

declare that the work presented in this Project Report entitled

“CONSTRUCTION OF HYDRO ELECTRIC POWER PLANT” is

the outcome of my own work, is bonafide and correct to the best of my

knowledge and this work has been carried out taking care of Engineering

Ethics. The work presented does not infringe any patented work and has

not been submitted to any other university or anywhere else for the award

of any degree or any professional diploma.

Date: Rahul Singh(0171EC101069)

Raja Hafizana Afroz (0171CE101080)

Stanzin Spalzang (0171CE101099)

Page 4: Baglihar hydro electric power plant

4

ACKNOWLEDGEMENT

I take the opportunity to express our sincere gratitude and deep sense of

indebtedness to our guide “Prof. Vikram Parihar” for the valuable guidance and

inspiration throughout the project duration. We feel thankful to him for his

innovative ideas, which led to successful completion of this project work. We feel

fortunate to work under such an outstanding mentor in the field of

“CONSTRUCTION OF HYDRO ELECTRIC POWER PLANT”. He has always

welcomed our problem and helped us to clear our doubt. We will always be

grateful to him for providing us moral support and sufficient time.

I owe sincere thanks to our GM Lt. Col.(Retd.) Lakhmeer Singh and all other

staff of JAYPEE ASSOCIATES LIMTED who helped us duly in time during our project work

in the Department.

At the same time, we would like to thank Prof. Vikram Parihar (HOD, CE) Sir

and all other faculty members and all non-teaching staff in Civil Department for

their valuable co-operation.

Rahul Singh (0171EC101069)

Raja Hafizana Afroz (0171CE101080)

Stanzin Spalzang (0171CE101099)”

Page 5: Baglihar hydro electric power plant

5

LIST OF PLANS AND SECTIONS

Layout of Stage-II Power House Complex.

L-Section of Baglihar Hydro Electric Project Stage-II.

Layout Plan & Sectional Details of Headrace Tunnel(HRT-II)

Layout Plan & Sections of Power House Cavity.

Layout Plan & Sections of Underground Cable Tunnel.

Layout Plan &Sections of Transformer Hall Cavity

Layout Plan &Sections of Tail Race Tunnel (TRT-II).

Page 6: Baglihar hydro electric power plant

6

TABLE OF CONTENTS

Certificate …………………………………………………………………................i

Declaration ………………………………………………………………….............ii

Acknowledgement …………………………………………………………………...iii

List of Plan……. ……………………………………………………………………iv

CHAPTER PAGE NO

CHAPTER 1

Dam………………………………………………………………….. 1

CHAPTER 2

Introduction about Hydro electricity…………………………….…… 2

Introduction about BHEP…………………………………………..… 3

CHAPTER 3

Specifications………………………………………………………… 4

CHAPTER 4

Page 7: Baglihar hydro electric power plant

7

Equipments used………………………………………………………. 8

CHAPTER 5

HRT……………………………………………………………………. 19

CHAPTER PAGE NO

CHAPTER 6

TRT…………………………………………………………………. 23

CHAPTER 7

Surveying………………………………………………………………. 25

CHAPTER 8

Quality control………….……………………………………………….. 30

CHAPTER 9

Grouting and Rock Bolting……………………………………………….. 46

CHAPTER 10

Adit and Tunnel Construcion Methods……………………………………. 52

CHAPTER 11

Conclusion…………………………………………………………………. 55

Page 8: Baglihar hydro electric power plant

8

CHAPTER 1

DAM

The type of dam is Solid gravity concrete dam 143.0 m high from deep foundation level. It

consists of 5spillway bays having radial gates (10.0 m x10.5 m) with hydraulic hoists, 3chute

spillways of 12m width each and one auxiliary spillway of 6m Height having radial gates with

hydraulic hoists. There are 7 non over flow blocks on the left bank and 6 non-overflow blocks on

the right bank. The total length of the dam at top is 362.862m. The roadway on top of dam is at

EL 843m allowing a free board of 3m. The deepest foundation level for dam is at EL 700m. Thus

the height of dam is 143m above the deepest foundation level.

Based on the pond levels the inlets of intake has been kept at EL 821m and the spillway crest

level has been kept at EL 808m. The energy dissipation arrangement consists of splitters and

ledge on spillway surface. A 70m long plunge pool is provided below the spillway.

Page 9: Baglihar hydro electric power plant

9

CHAPTER 2

INTRODUCTION ABOUT HYDRO ELECTRICITY

Hydropower functions by converting the energy in flowing water into electricity. The volume of

water flow and the height (called the head) from the turbines in the power plant to the water

surface created by the dam determines the quantity of electricity generated. Simply, the greater

the flow and the taller the head means the more electricity produced.

The simple working of a hydropower plant has water flowing through a dam, which turns a

turbine, which then turns a generator. A hydropower plant (including a powerhouse) generally

includes the following steps:

1. The dam holds water back and stores water upstream in a reservoir, or large artificial

lake. The reservoir is often used for multiple purposes, such as the recreational Lake

Page 10: Baglihar hydro electric power plant

10

Roosevelt at the Grand Coulee Dam. Some hydroelectric dams do not impound water, but

instead use the power of the flowing river, and are known as run-of-the-river.

2. Gates open on the dam, allowing gravity to pull the water down through the penstock. An

intake conduit carries water from the reservoir to turbines inside the powerhouse.

Pressure builds up as water flows through the pipeline.

3. The water then hits the large blades of the turbine , making them turn. The vertical blades

are attached through a shaft to a generator located above. Each turbine can weigh as

much as 172 tons and turn at a rate of 90 revolutions per minute.

4. The turbine blades turn in unison with a series of magnets inside the generator. The large

magnets rotate past copper coils, which produce alternating current (AC).

5. The transformer inside the powerhouse takes the AC and converts it to higher-voltage

current so as to allow electricity to flow to customers.

6. Out of every power plant exit four power lines consisting of three wires (associated with

three power phases) and a neutral (ground) wire.

7. Used water is carried through outflow pipelines, which reenters the river downstream.

INTRODUCTION ABOUT BHEP

Baglihar Dam (Hindi: बगलिहार बााँध Baglihār Bāndh), also known as Baglihar Hydroelectric

Power Project, is a run-of-the-river power project on the Chenab River in the Ramban district of

the Indian state of Jammu and Kashmir. This project was conceived in 1992, approved in 1996

and construction began in 1999. The project is estimated to cost USD $1 billion. The first phase

of the Baglihar Dam was completed in 2004. With the second phase completed on 10 October

2008, Prime Minister Manmohan Singh of India dedicated the 900-MW Baglihar hydroelectric

power project to the nation.

The 900 MW capacity Baglihar Hydroelectric Project (J&K) is located on Jammu-Srinagar

highway, about 141 km from Jammu and is proposed to be constructed in two stages. BHEP

Stage-I (450 MW) is under construction and comprises a 144.5 m high concrete gravity dam on

Page 11: Baglihar hydro electric power plant

11

river Chenab, Power Intake Structure (2 x 430 cumec capacity for both stages), about 2.08 km

longHead Race Tunnel (HRT, 10.15 m dia circular), a 27.5 m dia and 77.0 m high restricted

orifice type upstream surge tank, three pressure shafts, an Underground Powerhouse cavity (3 x

150 MW installed capacity), Transformer hall cavity, Downstream Collection Gallery, about 160

m long Tail Race Tunnel (TRT, 10 m wide) and cable tunnel system (including pothead yard) for

both stages. In underground powerhouse complex there are three parallel large caverns i.e. 121 m

(L) x 24 m (W) x 50 m (H) size Powerhouse cavity, 112.25 m (L) x 15.0 m (W) x 24.5 m (H)

Transformer Hall cavity and 75 m (L) x 12.5 m (W) x 44.0 m (H) cavity for Collection Gallery.

The Main Access Tunnel (MAT) to the erection bay of BHEP Stage-I is 7.5m D-Shaped and

355.0 m long. Cavities for BHEP Stage-II are the extension of BHEP Stage-I. The layout of the

powerhouse complex is shown in PLAN Longitudinal Section along the powerhouse complex is

shown in PLAN

CHAPTER 3

SPECIFICATION

LOCATION State

District

Longitude

Latitude

Jammu & Kashmir

Ramban

75*18‟10” – 75*20‟s

33*9‟30” – 33*11‟

Page 12: Baglihar hydro electric power plant

12

HYDROLOGY Name of the River

Type of Scheme

Design Flood (PMF)

Diversion Flood (1:25 year)

Maximum and minimum

temperature in summer

Maximum and minimum

temperature in winter

Full Reservoir Level

Chenab

Run-of-the-river

16,500 cumec

3000 cumec

42*c 20*c

15*c and 1*c

840m

RESERVOIR Minimum Draw Down Level

Before Stage – 2

After Stage – 2

Gross Storage upto FRL

Live Storage Capacity

838m

836m

475 Million m

15 Million m

DAM Type

Length

Height (from deepest foundation

level)

Road level at top

Solid gravity concrete dam

362.862m

143.0m

843.0m

(SULICE TYPE) Location

Design Flood

Spillway Crest Elevation

Number of Spillway bays

Size of gate

Type of gate

River bed portion

10,667 cumec

808m

5 Nos.

10.0m(W)x10.5m(H)

Radial gates with Hydraulic

Hoists

CHUTE SPILLWAY Location

Design Flood

Crest Elevation

Number of bays

Size of gate

Type of gate

On left flank

5790 cumec

821.0m

3 Nos.

12m(W)x19m(H)

Radial gates with Hydraulic

Hoists

Page 13: Baglihar hydro electric power plant

13

AUXILIARY SPILLWAY Crest Elevation

Design Flood

Number of bays

Size of gate

Type of gate

837.0m

60 cumec

One

6.0m(W)x3.0mH)

Fixed Wheel Gate

DIVERSION TUNNELS Location

Number

Finished Size

Shape

Length DT-1 , DT-2

Diversion Capacity

Invert setting:

DT-1

DT-2

Construction adit & cross adits for

approaching diversion tunnels

On right bank

Two

10.481m(W)x10.637m(H)

Horse Shoe with flSat invert

360M ,515M.

3000 cumec

Inlet end

EI. 710.0m

EI. 710.5m

7.5m D-shaped construction adit

265m long

7.5m D-shaped , 4nos. Cross

adits

(3x30m+1x38m long)

NEW RIVER DIVERSION

ARRANGEMENT

i)6.8m diameter circular bottom

outlet.

ii) 4nos.temporary diversion sluices

of size 3.5m(W)*8.2m(H)

iii) Escape Channel (12m

wide*86.366long).Its height varies

from 8m at RD 200md/s of dam

axis.

It located in block # 11 at EI.

733 at Inlet ant EL. 732 at

outlet.

2nos.are located in block # 12 at

EI. 766 and 2nos. in block # 13

at EI. 763.S

It is located at d/s of lip of Hill

Side Chute Channel in block # 4.

INTAKE(FOR STAGE-1

WORKS)

Capacity

Sill Elevation

Openings – 2 Nos.

Type of Gates

.

430 cumec

EL 821.0m

10m(W)x705m(H)

Fixed wheel gates with

Hydraulic Hoists

Page 14: Baglihar hydro electric power plant

14

INTAKE(FOR STAGE-2

WORKS)

Capacity

Sill Elevation

Openings

Type of Gates

430 cumec

EL 821.0m

10m(W)x7.5m(H)

Fixed wheel gates with

Hydraulic Hoists

HEAD RACE TAIL

TUNNEL

Number

Size and Shape

Length

Discharge

Invert level at intake(After vertical

S-Curve)

Invert level at junction with surge

shaft

ONE

10.15 m dia Circular

2075.37m(sloping Length upto

centre of Orifice)

430cumec

815.133m

775.35m

SURGE SHAFT Location

Type

Size

Height

Emergency Gates

Upstream of powerhouse(fully

underground approach to top

through an access cum airvent

adit)

Restricted Orifice Type

27.5m dia.

77m

Fixed wheel gates(Bonnet Type)

with Hydraulic Hoists for each

pressure shaft located in gate

chamber downstream of surge

Shaft

PRESSURE

SHAFTS/PENSTOCKS

Number

Shape

Size

Length(from centre of orfice upto

u/s wall of Machine hall)

Three

Circular

5.5m dia

No. 1 224.166m

No.2 206.936m

NO.3 202.116m

ACCESS TUNNEL TO

POWERHOUSE

Size

Length

7.5m D-Shaped

354.8m

Page 15: Baglihar hydro electric power plant

15

(Outdoor Pothead yard) Size 120mx30m (Combined for

Stage-I & II)

TAILRACE TUNNEL Shape

Size

Length

Discharge

D- Shaped

9m (W) x 19 to 27.5m (H)

130m

430 cumec

POWER PLANT

EQUIPMENT

Turbines

M.I Valves

Hydro-generators

Transformers

Switchgear

E.O.T Cranes

Francis

Butterfly type located in

Machine Hall

Vertical shaft, synchronous

generator. 166.67 MVA

Corresponding to turbine rated

output of 150 MW. RPM 187.5

50Hz.

Epoxy type. Class F insulation

11kw/400kv single phase

transformers (10 nos. including

one spare transformer)

400kv SF3 gas insulated switch

gear comprising 6 bays (3

incoming. 2 transmission line

bays and one bus coupler bay)

2 nos. Cranes with Lifting Beam

POWER OUTPUT Installed Capacity

Minimum discharge in 90%

available year

Minimum mean Discharge

Firm power(based on minimum

mean discharge)

Annual energy generation

90% availability year

50% availability year(maen year)

3x150 MW

119 cumec

131 cumec

141 MW

2643 GWH

2699 GWH

Page 16: Baglihar hydro electric power plant

16

CHAPTER 4

EQUIPMENTS USED

Dump Truck

Dump trucks or production trucks are those that are used for transporting loose material such as

sand, dirt, and gravel for construction. The typical dump truck is equipped with a hydraulically

operated open box bed hinged at the rear, with the front being able to be lifted up to allow the

contents to fall out on the ground at the site of delivery. Dump trucks come in many different

configurations with each one specified to accomplish a specific task in the construction chain.

Standard dump truck

The standard dump truck is a full truck chassis with the dump body mounted onto the frame. The

dump body is raised by a hydraulic ram lift that is mounted forward of the front bulkhead,

normally between the truck cab and the dump body. The standard dump truck also has one front

axle, and one or more rear axles which normally has dual wheels on each side. The common

configurations for standard dump trucks include the six wheeler and ten wheeler.

Page 17: Baglihar hydro electric power plant

17

Transfer dump truck

For the amount of noise made when transferring, the transfer dump truck is easy to recognize.

It‟s a standard dump truck that pulls a separate trailer which can be loaded with sand, asphalt,

gravel, dirt, etc. The B box or aggregate container on the trailer is

powered by an electric motor and rides on wheels and rolls off of the trailer and into the main

dump box. The biggest advantage with this configuration is to maximize payload capacity

without having to sacrifice the maneuverability of the short and nimble dump truck standards.

Semi trailer end dump truck

The semi end dump truck is a tractor trailer combination where the trailer itself contains the

hydraulic hoist. The average semi end dump truck has a 3 axle tractor that pulls a 2 axle semi

trailer. The advantage to having a semi end dump truck is rapid unloading.

Semi trailer bottom dump truck

A bottom dump truck is a 3 axle tractor that pulls a 2 axle trailer with a clam shell type dump

gate in the belly of the trailer. The biggest advantage of a semi bottom dump truck is the ability

to lay material in a wind row. This type of truck is also maneuverable in reverse as well, unlike

the double and triple trailer configurations.

Double and triple trailer

The double and triple bottom dump trucks consist of a 2 axle tractor pulling a semi axle semi

trailer and an additional trailer. These types of dump trucks allow the driver to lay material in

wind rows without having to leave the cab or stop the truck. The biggest disadvantage is the

difficulty in going in reverse.

Side dump trucks

Side dump trucks consist of a 3 axle trailer pulling a 2 axle semi trailer. It offers hydraulic rams

that tilt the dump body onto the side, which spills the material to the left or right side of the

trailer. The biggest advantages with these types of dump trucks are that they allow rapid

unloading and carry more weight than other dump trucks.

In addition to this, side dump trucks are almost impossible to tip over while dumping, unlike the

semi end dump trucks which are very prone to being upset or tipped over. The length of these

trucks impede maneuverability and limit versatility.

Off road dump trucks

Page 18: Baglihar hydro electric power plant

18

off road trucks resemble heavy construction equipment more than they do highway dump trucks.

They are used strictly for off road mining and heavy dirt hauling jobs, such as excavation work.

They are very big in size, and perfect for those time when you need to dig out roads and need

something to haul the massive amounts of dirt to another location.

Front Loader

Also known as a front end loader, bucket loader, scoop loader, or shovel, the front loader is a

type of tractor that is normally wheeled and uses a wide square tilting bucket on the end of

movable arms to lift and move material around. The loader assembly may be a removable

attachment or permanently mounted on the vehicle. Often times, the bucket can be replaced with

other devices or tools, such as forks or a hydraulically operated bucket.

Larger style front loaders, such as the Caterpillar 950G or the Volvo L120E, normally have only

a front bucket and are known as front loaders, where the small front loaders are often times

equipped with a small backhoe as well and called backhoe loaders or loader backhoes. Loaders

are primarily used for loading materials into trucks, laying pipe, clearing rubble, and also

digging. Loaders aren‟t the most efficient machines for digging, as they can‟t dig very deep

below the level of their wheels, like the backhoe can.

The deep bucket on the front loader can normally store around 3 – 6 cubic meters of dirt, as the

bucket capacity of the loader is much bigger than the bucket capacity of a backhoe loader.

Loaders aren‟t classified as excavating machinery, as their primary purpose is other than moving

dirt. In construction areas, mainly when fixing roads in the middle of the city, front loaders are

used to transport building materials such as pipe, bricks, metal bars, and digging tools. Front

loaders are also very useful for snow removal as well, as you can use their bucket or as a snow

plow. They can clear snow from the streets and highways, even parking lots. They will

sometimes load the snow into dump trucks which will then haul it away.

Page 19: Baglihar hydro electric power plant

19

Unlike the bulldozer, most loaders are wheeled and not tracked. The wheels will provide better

mobility and speed and won‟t damage paved roads near as much as tracks, although this will

come at the cost of reduced traction. Unlike backhoes or tractors fitted with a steel bucket, large

loaders don‟t use automotive steering mechanisms, as they instead steer by a hydraulically

actuated pivot point set exactly between the front and rear axles. This is known as articulated

steering and will allow the front axle to be solid, therefore allowing it to carry a heavier weight.

Articulated steering will also give a reduced turn in radius for a given wheelbase. With the

front wheels and attachment rotating on the same axis, the operator is able to steer his load in an

arc after positioning the machine, which can come in quite handy. The problem is that when the

machine is twisted to one side and a heavy load is lifted high in the air, it has a bigger risk of

turning over.

Various Types Of Cranes

A crane is a tower or derrick that is equipped with cables and pulleys that are used to lift and

lower material. They are commonly used in the construction industry and in the manufacturing

of heavy equipment. Cranes for construction are normally temporary

structures, either fixed to the ground or mounted on a purpose built vehicle.

They can either be controlled from an operator in a cab that travels along with the crane, by a

push button pendant control station, or by radio type controls. The crane operator is ultimately

responsible for the safety of the crews and the crane.

Mobile Cranes

The most basic type of crane consists of a steel truss or telescopic boom mounted on a mobile

platform, which could be a rail, wheeled, or even on a cat truck. The boom is hinged at the

bottom and can be either raised or lowered by cables or hydraulic cylinders.

Page 20: Baglihar hydro electric power plant

20

Telescopic Crane

This type of crane offers a boom that consists of a number of tubes fitted one inside of the other.

A hydraulic mechanism extends or retracts the tubes to increase or decrease the length of the

boom.

Tower Crane

The tower crane is a modern form of a balance crane. When fixed to the ground, tower cranes

will often give the best combination of height and lifting capacity and are also used when

constructing tall buildings.

Truck Mounted Crane

Cranes mounted on a rubber tire truck will provide great mobility. Outriggers that extend

vertically or horizontally are used to level and stabilize the crane during hoisting.

Page 21: Baglihar hydro electric power plant

21

Loader Crane

A loader crane is a hydraulically powered articulated arm fitted to a trailer, used to load

equipment onto a trailer. The numerous sections can be folded into a small space when the crane

isn‟t in use.

Overhead Crane

Also refered to as a suspended crane, this type is normally used in a factory, with some of them

being able to lift very heavy loads. The hoist is set on a trolley which will move in one direction

along one or two beams, which move at angles to that direction along elevated or ground level

tracks, often mounted along the side of an assembly area.

Page 22: Baglihar hydro electric power plant

22

In the excavation world, cranes are used to move equipment or machinery. Cranes can quickly

and easily move machinery into trenches or down steep hills, or even pipe. There are many types

of cranes available, serving everything from excavation to road work.

Cranes are also beneficial to building bridges or construction. For many years, cranes have

proven to be an asset to the industry of construction and excavating. Crane operators make really

good money, no matter what type of crane they are operating.

Compact Excavator

The compact hydraulic excavator can be a tracked or wheeled vehicle with an approximate

operating weight of 13,300 pounds. Normally, it includes a standard backfill blade and features

an independent boom swing. The compact hydraulic excavator is also known as a mini

excavator.

A compact hydraulic excavator is different from other types of heavy machinery in the sense that

all movement and functions of the machine are accomplished through the transfer of hydraulic

fluid. The work group and blade are activated by hydraulic fluid acting upon hydraulic cylinders.

The rotation and travel functions are also activated by hydraulic fluid powering hydraulic

motors.

Most types of compact hydraulic excavators have three assemblies – house, undercarriage, and

the work group.

Page 23: Baglihar hydro electric power plant

23

House

The house structure contains the compartment for the operator, engine compartment, hydraulic

pump and also the distribution components. The house structure is attached to the top of the

undercarriage via swing bearing. Along with the work group, them house is able to rotate upon

the undercarriage without limit due to a hydraulic distribution valve that supplies oil to the

undercarriage components.

Undercarriage

The undercarriage of compact excavators consists of rubber or steel tracks, drive sprockets,

rollers, idlers, and associated components and structures. The undercarriage is also home to the

house structure and the work group.

Work group

The work group consists of the boom, dipper or arm, and attachment. It is connected to the front

of the house structure via a swinging frame that allows the work group to be hydraulically

pivoted left or right in order to achieve offset digging for trenching parallel with the tracks.

Independent boom swing

The purpose of the boom swing is for offset digging around obstacles or along foundations,

walls, and forms. Another use is for cycling in areas that are too narrow for cab rotation. Another

major advantage of the compact excavator is the independent boom swing.

Backfill blade

The backfill blade on compact excavators are used for grading, leveling, backfilling, trenching,

Page 24: Baglihar hydro electric power plant

24

and general dozer work. The blade can also be used to increase the dumping height and digging

depth depending on it‟s position in relation to the workgroup.

The most common place you‟ll find compact excavators is in residential dwellings. When

digging phone lines or other things, these pieces of equipment are very common for getting

between houses. Due to their small size, they can fit almost anywhere. Over the years, the

capabilities for compact excavators have expanded far beyond the tasks of excavation. With

hydraulic powered attachments such as breakers, clamps, compactors and augers, the compact

excavator is used with many other applications and serves as an effective attachment tool as well.

Serving many purposes, the compact excavator is a great addition to any job that requires the use

of machinery.

Bulldozer

The bulldozer is a very powerful crawler that is equipped with a blade. The term bulldozer is

often used to mean any type of heavy machinery, although the term actually refers to a tractor

that is fitted with a dozer blade. Often times, bulldozers are large and extremely powerful tracked

vehicles. The tracks give them amazing ground mobility and hold through very rough terrain.

Wide tracks on the other hand, help to distribute the weight of the dozer over large areas,

therefore preventing it from sinking into sandy or muddy ground.

Bulldozers have great ground hold and a torque divider that‟s designed to convert the power of

the engine into dragging ability, which allows it to use its own weight to push heavy objects and

even remove things from the ground. Take the Caterpillar D9 for example; it can easily tow

tanks that weight more than 70 tons. Due to these attributes, bulldozers are used to clear

obstacles, shrubbery and remains of structures and buildings.

The blade on a bulldozer is the heavy piece of metal plate that is installed on the front. The

blade pushes things around. Normally, the blade comes in 3 varieties:

1. A straight blade that is short and has no lateral curve, no side wings, and can be used

only for fine grading.

2. A universal blade, or U blade, which is tall and very curved, and features large side wings to

carry more material around.

3. A combination blade that is shorter,offers less curvature, and smaller side wings.

Page 25: Baglihar hydro electric power plant

25

Modifications

Over time, bulldozers have been modified to evolve into new machines that are capable of things

the original bulldozers weren‟t. A good example is that loader tractors were created by removing

the blade and substituting a large volume bucket and hydraulic arms which will raise and lower

the bucket, therefore making it useful for scooping up the earth and loading it into trucks. Other

modifications to the original bulldozer include making it smaller to where it can operate in small

working areas where movement is very limited, such as mining caves and tunnels. Very small

bulldozers are known as calfdozers.

History

The first types of bulldozers were adapted from farm tractors that were used to plough fields. In

order to dig canals, raise earth dams, and partake in earthmoving jobs, the tractors were equipped

with a thick metal plate in the front. Later on, this thick metal plate earned the name blade.

The blade of the bulldozer peels layers of soil and pushes it forward as the tractor advances. The

blade is the heart and soul of the bulldozer, as it was the first accessory to make full use for

excavation type jobs. As the years went by, when engineers needed equipment to complete larger

jobs, companies such as CAT, Komatsu, John Deere, Case, and JCB started to manufacture large

Page 26: Baglihar hydro electric power plant

26

tracked earthmoving equipment. They were very loud, very large, and very powerful and

therefore earned the nickname “bulldozer”. Over the years, the bulldozers got bigger, more

powerful, and even more sophisticated. The important improvements include better engines,

more reliable drive trains, better tracks, and even hydraulic arms that will enable more precise

manipulation of the blade and automated controls.As an added option, bulldozers can come

equipped with a rear ripping claw to break up pavement or loosen rocky soil.The best known

manufacturer of bulldozer is CAT,which has earned a vast reputation for making

tough and durable, yet reliable machines.Even though the bulldozer started off a modified

farmtractor, it rapidly became one of the most useful pieces of equipment with excavating and

construction.

Backhoe Loader

Also referred to as a loader backhoe, the backhoe loader is an engineering and excavation vehicle

that consists of a tractor, front shovel and bucket and a small backhoe in the rear end. Due to the

small size and versatility, backhoe loaders are common with small construction projects and

excavation type work. Originally invented in Burlington Iowa back in 1857, the backhoe loader

is the most common variation of the classic farm tractor .As the name implies, it has a loader

assembly on the front and a backhoe attachment on the back.

Anytime the loader and backhoe are attached it is never referred to as a tractor, as it is not

normally used for towing and doesn‟t normally have a PTO. When the backhoe is permanently

attached, the machine will normally have a seat that can swivel to the rear to face the backhoe

controls. Any type of removable backhoe attachments will normally have a separate seat on the

attachment itself. Backhoe loaders are common and can be used for many tasks, which include

construction, light transportation of materials, powering building equipment, digging holes and

excavating, breaking asphalt, and even paving roads. You can often replace the backhoe bucket

with other tools such as a breaker for breaking and smashing concrete and rock. There are some

loader buckets that offer a retractable bottom, which enable it to empty the load more quickly

and efficiently.

Page 27: Baglihar hydro electric power plant

27

The retractable bottom loader buckets are often times used for grading and scratching off

sand.The front assembly on a backhoe may be either removable or permanently attached. Often

times,the bucket can be replaced with other tools or devices. In order to mount different

attachments to the loader, it must be equipped with a tool coupler. The coupler consists of two

hydraulic cylinders on the end of the arm assembly, which can expand and retract to allow

different tools to be attached to the unit. There are several types of backhoe loader brands,

including New Holland, John Deere, and Case. Some will offer you cabs, while others won‟t.

The newer types of backhoe loaders even offer you air conditioning, radios, and other

accessories that make you feel like you are working with luxury. Common with excavating jobs,

the backhoe can serve many purposes. It can haul equipment and supplies in the loader bucket.

Another great use is to cover up dirt when filling in trench lines or covering up pipe that was just

put in the ground. The backhoe attachment at the rear is ideal for digging water pipes and sewer

pipes. The best thing about the backhoe loader is the fact that they are easy to operate. You don‟t

need to be a rocket scientist to fully operate this nifty piece of equipment.

Page 28: Baglihar hydro electric power plant

28

CHAPTER 5

HEAD RACE TUNNEL

It is a 2080m long 10.15m dia. concrete lined and grouted circular water conductor system to

carry a design of 430 cumecs. with a maximum velocity of 5.28m/sec. It has been constructed by

conventional method of drilling blasting and mucking. The shape of head race tunnel (HRT) is

circular.

SURGE SHAFT

A restricted orifice type surge shaft has been provided at the end of HRT. The surge shaft is 77m

high having 27.5m finished diameter. The area for the orifice is provided by an opening of 6.14m

dia. In orifice slab. The surge shaft is fully under ground. The approach adit cum air vent of

308m in length. The three turbines of the powerhouse are fed through separate pressure shafts of

5.5m dia. each starting from the bottom of the surge shaft. The pressure shafts negotiable a drop

of 84.425m between center line of HRT at junction with the surge shaft at EL 780.425 and

Page 29: Baglihar hydro electric power plant

29

centerline of machine EL 696m. The length of pressured shafts PS #1, PS # 2 & PS #3 is

215m,196m and 193m respectively.

Penstock

The penstock is a pipe that carries water from the intake to the turbine. Most hydropower system

will include some type of penstock. Depending on the site characteristics, the pen stock length

any range from a few feet for manmade structure with an open flume. This type of site has no

penstock. Developers with an open flume leading to the turbine can proceed to the next section.

If you have received a penstock recommendation from the turbine manufacturer, you should

contact suppliers to obtain pipe specification and pricing information. If you plan to follow the

turbine manufacturer‟s recommendation, you should review the contents of this section before

ordering the pipe in order to facilitate making a design layout of the penstock and to make sure

that you have considered all materials and costs.

The following are the some of the major factors that must be considered in selecting a penstock

route:

Accessibility. The route should be accessible to personnel and equipment required for

pipe installation, inspection, and maintenance. In those areas where equipment access is

difficult or impossible, installation and maintenance must be performed manually.

Page 30: Baglihar hydro electric power plant

30

Soil Conditions. Soils along the pipeline should be examined to identify rock

outcropping, soft or unstable soils , or other characteristics that would interfere with

penstock installation or damage the penstock.

Natural or Man-Made Obstructions. These include trees, roadways, buildings, stream

crossing, and other features that require special care.

Gradient. The penstock is best routed to take advantage of the natural downward

gradient. If the line cannot be located so as to have a constant downward gradient, an air

relief valve or equivalent device is required at very local high point, and a drain valve is

required at very local low point.

Above or Below-Ground Installation. A buried penstock has certain advantages over an

above-ground installations. Anchoring and supporting the pipe are simplified, ultraviolet

radiation effects on PVC pipe are eliminated, and the effects of weather (thermal

expansion, freezing) are reduced. In addition, physical damage to the pipe from falling

rocks and trees or other sources is also prevented. On the other hand, and above –ground

pipe will have a lower construction cost, may allow for more direct routing (fewer

bends), and is readily accessible for inspection or repair. Another alternative is to have a

combination of above and below ground installation.

Material Selection:

The turbine manufacturer may have recommended a certain material for penstock. You

may want to consider other material that might be less expensive. The most common

materials include:

PVC (polyvinyl chloride)

Steel

Polyethylene

FRE (fiber reinforced epoxy)

Transite (asbestos cement)

Page 31: Baglihar hydro electric power plant

31

Cost

Availability

Physical properties (friction , strength , chemistry)

Joining methods and installation limitations.

Penstock Sizing:

A satisfactory penstock diameter depends on three factors:

Energy (head) losses due to friction between the water flowing in the pipe and the inside

pipe wall.

Pressure limitations of the pipe as a function of wall thickness.

Cost of the pipe and installation.

In this dam we use three penstocks. It is circular in shape, having diameter 5.5m and length of

penstock(from center of Orifice up to u/s wall of Machine

Hall)are(i)224.166m(ii)206.936m(iii)202.116m.

Page 32: Baglihar hydro electric power plant

32

CHAPTER 6

TAIL RACE TUNNEL

Tailrace

A tailrace is a canal or conduit that carries water from the powerhouse to the next

desired location (usually back into the stream).

Size of the Tailrace

Page 33: Baglihar hydro electric power plant

33

The tailrace should be large enough to carry the design flow. The velocity in the tailrace

can be 2 fps. In parts of the country where fish migration is a consideration, the velocity at the

tailrace exit should be reduced to less than 0.5 fps. Migrating fish will be attracted into the

tailrace if the velocity is too high.

For sizing the tailrace for 2 fps, refer to section on power canals, Subsection 4.4.2.2. The

power canal and tailrace will have the same cross-sectional area. Note that the slope for the

tailrace must also be equal or greater than that of the power canal. If the reduced velocity is

needed at the stream entrance, make the end of the tailrace four times wider. If the same depth

is maintained, the velocity will be reduced to

0.5 fps.

Tail race Intake

Generally, the tailrace will start below the powerhouse and is an integral part of the

powerhouse design. The width and depth is set by the area for 2 fps. The powerhouse footings

and the tailrace intake are usually constructed from concrete. The concrete can either be precast

or poured in place.

In this project tail race system of a collection gallery of size 12.5m (W) x 44m (H) x 75m

(L),tail race tunnel of 130m length and outlet structure. The collection gallery also functions as

downstream surge chamber. The draft tube gates located at the junctions of draft tube tunnels

with collection gallery are operated from collection gallery at EL 726m which is 10m above the

roof of collection gallery. The 130m long concrete lined tail race tunnel is 9m wide and meets

the outfall structures at EL 700m(meters above sea level).Consult to plan of TRT for actual

parameretrs.

Page 34: Baglihar hydro electric power plant

34

Page 35: Baglihar hydro electric power plant

35

CHAPTER 7

SURVEYING

TOTAL STATION INSTRUMENT

While working in BHEP Under JayPee construction ltd. As per our schedule we have to work

under surveying department for few days but because of bad weather condition (rain) we weren‟t

able to work as much in field as we want so our training was limited to just instrument setup.

INTRODUCTION

In the past, transits and theodolites were the most commonly used surveying instruments

For making angle observations. These two devices were fundamentally

Equivalent and could accomplish basically the same tasks. Today, the total station

Instrument has replaced transits and theodolites. Total station instruments can

Accomplish all of the tasks that could be done with transits and theodolites and do

Them much more efficiently. In addition, they can also observe distances accurately

And quickly. Furthermore, they can make computations with the angle and

Distance observations, and display the results in real time. These and many other

significant advantages have made total stations the predominant instruments used

in surveying practice today.They are used for all types of surveys including topographic,

hydrographic, cadastral, and construction surveys.

Page 36: Baglihar hydro electric power plant

36

To use the total station, it is set over one end of the line to be measured and

some reflector is positioned at the other end such that the line of sight between

the instrument and the reflector is unobstructed.

-The reflector is a prism attached to a detail pole

-The telescope is aligned and pointed at the prism

-The measuring sequence is initiated and a signal is sent to the reflector and a

part of this signal is returned to the total station

-This signal is then analysed to calculate the slope distance together with the

horizontal and vertical angles.

-Total stations can also be used without reflectors and the telescope is pointed at

the point that needs to be measured

-Some instruments have motorised drivers and can be use automatic target

recognition to search and lock into a prism – this is a fully automated process and

does not require an operator.

-Some total stations can be controlled from the detail pole, enabling surveys to

be conducted by one person..A total station is levelled and centred in the same way as a

theodolite.Most total stations have a distance measuring range of up to a few kilometres,

when using a prism, and a range of at least 100m in reflector less mode and an

accuracy of 2-3mm at short ranges, which will decrease to about 4-5mm at 1km. Although

angles and distances can be measured and used separately, the most

Page 37: Baglihar hydro electric power plant

37

common applications for total stations occur when these are combined to define

position in control surveys.

Handaling of total station

A total station instrument should be carefully lifted from its carrying case by

grasping the standards or handle, and the instrument securely fastened to the tripod

by means of the tribrach. For most surveys, prior to observing distances and

angles, the instrument must first be carefully set up over a specific point.The setup

process using an instrument with an optical plummet, tribrach mount with circular

bubble, and adjustable-leg tripod is accomplished most easily using the following

steps: (1) extend the legs so that the scope of the instrument will be at an appropriate

elevation for view and then adjust the position of the tripod legs by lifting and

moving the tripod as a whole until the point is roughly centered beneath the tripod

head (beginners can drop a stone from the center of the tripod head, or use a

plumb bob to check nearness to the point); (2) firmly place the legs of the tripod in

the ground and extend the legs so that the head of the tripod is approximately

level; repeat step (1) if the tripod head is not roughly centered over the point;

(3) roughly center the tribrach leveling screws on their posts; (4) mount the tribrach

approximately in the middle of the tripod head to permit maximum translation in

step (9) in any direction; (5) focus the plummet properly on the point, making sure

to check for parallax; (6) manipulate the leveling screws to aim the plummet‟s

pointing device at the point below; (7) center the circular bubble by adjusting the

lengths of the tripod extension legs; (8) and level the instrument using the plate

bubble and leveling screws; and (9) if necessary, loosen the tribrach screw and

translate the instrument (do not rotate it) to carefully center the plummet‟s pointing

device on the point; (10) repeat steps (8) and (9) until precise leveling and

centering are accomplished.With total stations that have their plummets in the

tribrach, the instrument can and should be left in the case until step (8).

To level a total station instrument that has a plate-level vial, the telescope is

rotated to place the axis of the level vial parallel to the line through any two leveling

screws, as the line through A and B.The bubble is centered

leveling

screws, as the line through A and B.The bubble is centeredby turning these two screws, then

rotated 90°, as shown in Figure, and centered again using the third screw (C) only. This process

is repeated in the initial two positions and carefully checked to ensure that the bubble remains

centered. As illustrated in, the bubble moves in the direction of the left thumb when the foot

screws are turned.A solid tripod setup is essential, and the instrument must be shaded if set up in

Page 38: Baglihar hydro electric power plant

38

bright sunlight. Otherwise, the bubble will expand and run toward the warmer end as the liquid is

heated. Many instruments, such as the LEICA TPS 300, do not have traditional level vials.

Rather, they are equipped with an electronic, dualaxis leveling system in which four probes sense

a liquid (horizontal) surface. After preliminary leveling is performed by means of the tribrach‟s

circular bubble, signals from the probes are processed to form an image on the LCD display,

which guides an operator in performing rough leveling.The three leveling screws are used, but

the instrument need not be turned about its vertical axis in the leveling process. After rough

leveling, the amount and direction of any residual dislevelment is automatically and continuously

received by the microprocessor, which corrects observed horizontal and vertical angles

accordingly in real time. As noted earlier, total stations are controlled with entries made either

through their built-in keypads or through the keypads of handheld data collectors. Details for

operating each individual total station vary somewhat and therefore are not described here. They

are covered in the manuals provided with the purchase of instruments. When moving between

setups in the field, proper care should be taken. Before the total station is removed from the

tripod, the foot screws should be returned to the midpoints of the posts. Many instruments have a

line on the screw post that indicates the halfway position. The instrument should NEVER be

transported on the tripod since this causes stress to tripod head, tribrach, and instrument base.

depicts the proper procedure for carrying equipment in the field.With adjustable-leg tripods,

retracting them to their shortest positions and lightly clamping them in position can avoid stress

on the legs. When returning the total station to its case, all locking mechanisms should

be released. This procedure protects the threads and reduces wear when the instrument

is jostled during transport and also prevents the threads from seizing during long periods of

storage. If the instrument is wet, it should be wiped down and left in an open case until it is dry

.When storing tripods, it is important to loosen or lightly clamp all legs. This is especially true

with wooden tripods where the wood tends to expand and contract with humidity in the air.

Failure to loosen the clamping mechanism on wooden tripods can result in crushed wood fibers,

which inhibit the ability of the clamp to hold the leg during future use.

Coordinate measurement

Coordinates of an unknown point relative to a known coordinate can be determined using the

total station as long as a direct line of sight can be established between the two points. Angles

and distances are measured from the total station to points under survey, and the coordinates (X,

Y, and Z or easting, northing and elevation) of surveyed points relative to the total station

position are calculated using trigonometry and triangulation. To determine an absolute location a

Total Station requires line of sight observations and must be set up over a known point or with

line of sight to 2 or more points with known location.

Page 39: Baglihar hydro electric power plant

39

For this reason, some total stations also have a Global Navigation Satellite System receiver and

do not require a direct line of sight to determine coordinates. However, GNSS measurements

may require longer occupation periods and offer relatively poor accuracy in the vertical axis.

Angle measurement

Most modern total station instruments measure angles by means of electro-optical scanning of

extremely precise digital bar-codes etched on rotating glass cylinders or discs within the

instrument. The best quality total stations are capable of measuring angles to 0.5 arc-second.

Inexpensive "construction grade" total stations can generally measure angles to 5 or 10 arc-

seconds.

Distance measurement

Measurement of distance is accomplished with a modulated microwave or infrared carrier signal,

generated by a small solid-state emitter within the instrument's optical path, and reflected by a

prism reflector or the object under survey. The modulation pattern in the returning signal is read

and interpreted by the computer in the total station. The distance is determined by emitting and

receiving multiple frequencies, and determining the integer number of wavelengths to the target

for each frequency. Most total stations use purpose-built glass corner cube prism reflectors for

the EDM signal. A typical total station can measure distances with an accuracy of about 1.5

millimetres (0.0049 ft) + 2 parts per million over a distance of up to 1,500 metres (4,900 ft).

Reflectorless total stations can measure distances to any object that is reasonably light in color,

up to a few hundred meters.

Data processing

Some models include internal electronic data storage to record distance, horizontal angle, and

vertical angle measured, while other models are equipped to write these measurements to an

external data collector, such as a hand-held computer.

Page 40: Baglihar hydro electric power plant

40

When data is downloaded from a total station onto a computer, application software can be used

to compute results and generate a map of the surveyed area. The new generation of total stations

can also show the map on the touch-screen of the instrument right after measuring the points.

CHAPTER 8

Quality Control lab

As per the schedule we have to work for few days in quality control laboratory to understand the

strength and other parameters of material used.

Here are the few tests that we performed in the quality control lab.

Lab tests on Cement:

DETERMINATION OF COMPRESSIVE STRENGTH OF CEMENT.

(IS: 4031 – Part – 6)

Object:

Determination of the compressive strength of standard cement mortar cubes compacted by means

of a standard vibration machine.

Apparatus:

Vibration machine, cube moulds of size 7.06 cms(confirming to IS : 4031 – 1968), and Standard

Sand to be used in the test shall be confirm to IS : 650 – 1966.

Procedure:

Mix Proportions and Mixing: Clean appliances shall be used for mixing and the temperature of

the water and that of the test room at the time when the above operations are being performed

shall be 270 +/- 2

0C. Place in a container a mixture of cement and standard sand in the proportion

of 1 : 3 by weight; mix it dry, with a trowel for one minute and then with water until the mixture

is of uniform colour. The quantity of water to be used shall be as specified below. In any event, it

should not take more than 4 minutes to obtain uniform colored mix. If it exceeds 4 minutes, the

mixture shall be rejected and the operation repeated with a fresh quantity of cement, sand and

water.

Page 41: Baglihar hydro electric power plant

41

The material for each cube shall be mixed separately and the quantity of cement, standard sand

and water shall be as follows: Percentage of water to be added to the cement and sand in ( 1:3 )

cm (P/4 + 3) X % combined weight of cement and sand = (P/4 + 3) X 800/100.

Cement 200 gms, standard sand 600 gms, water (P/4 + 3) per cent of combined weight of cement

and sand, where P is the percentage of water required to produce a paste of standard consistency.

Molding Specimens:

In assembling the moulds ready for use, cover the joints between the halves of the mould with a

thin film of petroleum jelly and apply a similar coating of petroleum jelly between the contact

surfaces of the bottom of the mould and its base plate in order to ensure that no water escapes

during vibration. Treat the interior faces of the mould with a thin coating of mould oil. Place the

assembled mould on the table of the vibration machine and firmly hold it in position by means of

suitable clamps. Securely attach a Hooper of suitable size and shape at the top of the mould to

facilitate filling and this Hooper shall not be removed until completion of the vibration.

Immediately after mixing the mortar, place the mortar in the cube mould and rod with a rod. The

mortar shall be rodded 20 times in about 8 seconds to ensure elimination of entrained air and

honey combing. Place the remaining quantity of mortar in the Hooper of the cube mould and rod

again as specified for the first layer and then compact the mortar by vibration. The period of

vibration shall be two minutes at the specified speed of 12000 +/- 400 vibrations per minutes. At

the end of vibration remove the mould together with the base plate from the machine and finish

the top surface of the cube in the mould by smoothing surface with the blade of a trowel.

Curing Specimens:

Keep the filled moulds at a temperature of 270C +/- 2

0C in an atmosphere of at least 90% relative

humidity for about 24 hours after completion of vibration. At the end of that period remove them

from the moulds immediately submerge in clean fresh water and keep them under water until

testing. The water in which the cubes are submerged shall be renewed every 7 days and shall be

maintained at a temperature of 270C +/- 2

0C. After they have been taken out and until they are

tested, the cubes shall not be allowed to become dry.

Testing:

Test three cubes for compressive strength at the periods mentioned under the relevant

specifications for different hydraulic cements, the periods being reckoned from the completion of

vibration. The compressive strength shall be the average of the strengths of the three cubes for

each period of curing. The cubes shall be tested on their sides without any packing between the

Page 42: Baglihar hydro electric power plant

42

cube and the steel platens of the testing machine. One of the platens shall be carried base and

shall be self-adjusting and the load shall be steadily and uniformly applied, starting from zero at

a rate of 350 kgs/cm2/min.

Calculation:

Calculate the compressive strength from the crushing load and the average area over which the

load is applied. Express the results in kgs/cm2 to the nearest 0.5 kg/cm

2.

Compressive strength, kg/cm2 = P/A, where „P‟ is the crushing load in kg, and „A‟ is the area in

cm2.

FINENESS BY DRY SIEVING REFERENCE: IS 4031 – (PART – 1)

1996

IMPORTANCE:

During manufacturing, cement must be ground to be uniformly fine

Otherwise concrete needs large amount of water for mixing which results in bleeding as

well as poor workmanship.

Test sieve of non-corrodible metal having 150 mm to 200 mm dia, and 40 mm to

100 mm depth fitted with 90 µm mesh sieve cloth of woven stainless steel or

other abrasion resistant non- corrodible wires.

Suitable tray with lid to fit sieve size.

Stoppered jar with blunt ended stirrer rod

Weighing balance to weigh up to 10 gms to nearest 10 mg.

Nylon or pure bristle brush (25 mm / 40 mm bristles) for cleaning sieves.

Page 43: Baglihar hydro electric power plant

43

PROCEDURE:

Determination of cement residue:

• Agitate the cement sample by shaking for 2 minutes in a stoppered jar to disperse the

agglomerates. Wait for few minutes.

• Stir the resulting powder gently with dry rod to distribute the fines throughout the sample.

• Weigh approx. 10 gm of cement and put in sieve fitted with bottom tray and top lid.

• Agitate and shake the sieve thoroughly

• Weigh the residue – retained on sieve.

• Clean base of sieve gently by brush to remove fine material.

• Find out % (R1) of residue in comparison with total weight of sample.

• Repeat the procedure at least twice till results do not differ by more than 1%.

CALCULATION

Find out mean of observations and express this percentage as R

CEMENT: DETERMINATION OF SETTING TIME REFERENCE:

IS 4031 – (PART – 5) 1996

Page 44: Baglihar hydro electric power plant

44

IMPORTANCE OF TEST: The object is to distinguish between, quick setting and

normal setting time and to detect the deterioration due to storage.

APPARATUS

• Vicat Apparatus

• Balance (capacity 1000 gms, accuracy 0.1 gm)

• Annular attachment of Vicat Apparatus

TEMPERATURE & HUMIDITY

• Dry Materials, Water and Moulding Room : 27 + 2O C

• Relative Humidity in Laboratory : 65 + 5 %

PROCEDURE

On a non-porous platform

• Mix neat cement with enough water to give a paste of Standard

Consistency.

• Start stop watch immediately on adding water to cement. Note

Stop watch reading (To)

Page 45: Baglihar hydro electric power plant

45

• Rest Vicat mould on non-porous plate and fill it completely with cement paste. Level of top

surface and expel air by shaking.

• Place test block with mould under the rod bearing needle of Vicat apparatus and b r ing rod

l eve l with t op o f test specimen. Release needle slowly and let it penetrate in the test block.

• Repeat the procedure until needle stops of distance of (5 + 0.5) mm from base of test block.

Read the stop watch and note the time (T1).

• Replace needle by annular attachment. Repeat procedure of releasing the needle till needle

makes an impression on top of test block while attachment fails to do so. Read the stop

watch and note time (T2).

CALCULATION

Initial Setting Time (IST) = (T1 – T0)

Final Setting Time (FST) = (T2 – T 0)

REPORTING

Report IST & FST to nearest 5 minutes

Lab Tests on Aggregates:

WATER ABSORPTION TEST

This test helps to determine the water absorption of coarse aggregates as per IS: 2386 (Part III) –

1963. For this test a sample not less than 2000g should be used. The apparatus used for this test

are :-

Wire basket – perforated, electroplated or plastic coated with wire hangers for suspending it from

Page 46: Baglihar hydro electric power plant

46

the balance, Water-tight container for suspending the basket, Dry soft absorbent cloth – 75cm x

45cm (2 nos.), Shallow tray of minimum 650 sq.cm area, Air-tight container of a capacity similar

to the basket and Oven.

Procedure to determine water absorption of Aggregates.

i) The sample should be thoroughly washed to remove finer particles and dust, drained and then

placed in the wire basket and immersed in distilled water at a temperature between 22 and 32oC.

ii) After immersion, the entrapped air should be removed by lifting the basket and allowing it to

drop 25 times in 25 seconds. The basket and sample should remain immersed for a period of 24

+ ½ hrs afterwards.

iii) The basket and aggregates should then be removed from the water, allowed to drain for a few

minutes, after which the aggregates should be gently emptied from the basket on to one of the

dry clothes and gently surface-dried with the cloth, transferring it to a second dry cloth when the

first would remove no further moisture. The aggregates should be spread on the second cloth and

exposed to the atmosphere away from direct sunlight till it appears to be completely surface-dry.

The aggregates should be weighed (Weight „A‟).

iv) The aggregates should then be placed in an oven at a temperature of 100 to 110oC for 24hrs.

It should then be re moved from the oven, cooled and weighed (Weight „B‟).

Formula used is Water absorption = [(A - B)/B] x 100%.

Two such tests should be done and the individual and mean results should be reported. A sample

Performa for the record of the test is

Page 47: Baglihar hydro electric power plant

47

AGGREGATE IMPACT VALUE

This test is done to determine the aggregate impact value of coarse aggregates as per IS: 2386

(Part IV) – 1963. The apparatus used for determining aggregate impact value of coarse

aggregates is

Impact testing machine conforming to IS: 2386 (Part IV)- 1963,IS Sieves of sizes – 12.5mm,

10mm and 2.36mm, A cylindrical metal measure of 75mm dia. and 50mm depth, A tamping rod

of 10mm circular cross section and 230mm length, rounded at one end and Oven.

Preparation of Sample

i) The test sample should conform to the following grading:

- Passing through 12.5mm IS Sieve – 100%

- Retention on 10mm IS Sieve – 100%

ii) The sample should be oven-dried for 4hrs. at a temperature of 100 to 110oC and cooled.

iii) The measure should be about one-third full with the prepared aggregates and tamped with 25

strokes of the tamping rod.

A further similar quantity of aggregates should be added and a further tamping of 25 strokes

given. The measure should finally be filled to overflow, tamped 25 times and the surplus

aggregates struck off, using a tamping rod as a straight edge. The net weight of the aggregates in

the measure should be determined to the nearest gram (Weight „A‟).

Page 48: Baglihar hydro electric power plant

48

Procedure to determine Aggregate Impact Value

i) The cup of the impact testing machine should be fixed firmly in position on the base of the

machine and the whole of the test sample placed in it and compacted by 25 strokes of the

tamping rod.

ii) The hammer should be raised to 380mm above the upper surface of the aggregates in the cup

and allowed to fall freely onto the aggregates. The test sample should be subjected to a total of

15 such blows, each being delivered at an interval of not less than one second.

Reporting of Results

i) The sample should be removed and sieved through a 2.36mm IS Sieve. The fraction passing

through should be weighed (Weight „B‟). The fraction retained on the sieve should also be

weighed (Weight „C‟) and if the total weight (B+C) is less than the initial weight (A) by more

than one gram, the result should be discarded and a fresh test done.

ii) The ratio of the weight of the fines formed to the total sample weight should be expressed as a

percentage.

Page 49: Baglihar hydro electric power plant

49

Aggregate impact value = (B/A) x 100%

iii) Two such tests should be carried out and the mean of the results should be reported.

AGGREGATE ABRASION VALUE

This test helps to determine the abrasion value of coarse aggregates as per IS: 2386 (Part IV) –

1963.

The apparatus used in this test are Los Angles abrasion testing machine, IS Sieve of size –

1.7mm, Abrasive charge – 12 nos. cast iron or steel spheres approximately 48mm dia. and each

weighing between 390 and 445g ensuring that the total weight of charge is 5000 +25g and Oven.

Sample Preparation

The test sample should consist of clean aggregates which has been dried in an oven at 105 to

110oC to a substantially constant weight and should conform to one of the gradings shown in the

table below:

Page 50: Baglihar hydro electric power plant

50

Procedure to determine Aggregate Abrasion Value

The test sample and the abrasive charge should be placed in the Los Angles abrasion testing

machine and the machine rotated at a speed of 20 to 33 revolutions/minute for 1000 revolutions.

At the completion of the test, the material should be discharged and sieved through 1.70mm IS

Sieve.

Reporting of Results

i) The material coarser than 1.70mm IS Sieve should be washed, dried in an oven at a

temperature of 100 to 110oC to a constant weight and weighed (Weight „B‟).

ii) The proportion of loss between weight „A‟ and weight „B‟ of the test sample should be

expressed as a percentage of the original weight of the test sample. This value should be reported

as,

Aggregate abrasion value = (A-B)/B x 100

Flakiness index and Elongation Index of Coarse Aggregates

APPARATUS:

The apparatus for the shape tests consists of the following:

(i) A standard thickness gauge

(ii) A standard length gauge

(iii) IS sieves of sizes 63, 50 40, 31.5, 25, 20, 16, 12.5,10 and 6.3mm

(iv) A balance of capacity 5kg, readable and accurate up to 1 gm.

Page 51: Baglihar hydro electric power plant

51

THEORY:

The particle shape of aggregates is determined by the percentages of flaky and

elongated particles contained in it. For base course and construction of bituminous and

cement concrete types, the presence of flaky and elongated particles are considered

undesirable as these cause inherent weakness with possibilities of breaking down under

heavy loads. Thus, evaluation of shape of the particles, particularly with reference to

flakiness and elongation is necessary.

The Flakiness index of aggregates is the percentage by weight of particles whose

least dimension (thickness) is less than three- fifths (0.6times) of their mean dimension.

This test is not applicable to sizes smaller than 6.3mm.

The Elongation index of an aggregate is the percentage by weight of particles

whose greatest dimension (length) is greater than nine-fifths (1.8times) their mean

dimension. This test is not applicable for sizes smaller than 6.3mm.

PROCEDURE:

i) Sieve the sample through the IS sieves (as specified in the table).

ii) Take a minimum of 200 pieces of each fraction to be tested and weigh them.

iii) In order to separate the flaky materials, gauge each fraction for thickness on a

thickness gauge. The width of the slot used should be of the dimensions specified in

column (4) of the table for the appropriate size of the material.

iv) Weigh the flaky material passing the gauge to an accuracy of at least 0.1 per cent of

the test sample.

(v) In order to separate the elongated materials, gauge each fraction for length on a length

gauge. The width of the slot used should be of the dimensions specified in column (6)

of the table for the appropriate size of the material.

(vi) Weigh the elongated material retained on the gauge to an accuracy of at least 0.1 per

cent of the test sample.

Size of aggregates Weight of

fraction

Thickness

gauge

Weight of

aggregates

Length

gauge

Weight of

aggregates Passing Retained

Page 52: Baglihar hydro electric power plant

52

through

IS Sieve,

mm

on IS

Sieve,

mm

consisting

of at least

200

pieces,g

size, mm in each

fraction

passing

thickness

gauge,mm

size,

mm

in each

fraction

retained on

length

gauge,mm

1 2 3 4 5 6 7

63 50 W1 23.90 X1 - -

50 40 W2 27.00 X2 81.00 Y1

40 31.5 W3 19.50 X3 58.00 Y2

31.5 25 W4 16.95 X4 - -

25 20 W5 13.50 X5 40.5 Y3

20 16 W6 10.80 X6 32.4 Y4

16 12.5 W7 8.55 X7 25.5 Y5

12.5 10 W8 6.75 X8 20.2 Y6

10 6.3 W9 4.89 X9 14.7 Y7

Total W = X = Y =

Page 53: Baglihar hydro electric power plant

53

OBSERVATIONS:

Flakiness Index = (X1+ X2+…..) / (W1 + W2 + ….) X 100

Elongation Index = (Y1 + Y2 + …) / (W1 + W2 + ….) X 100

RESULT:

i) Flakiness Index =

ii) Elongation Index =

Page 54: Baglihar hydro electric power plant

54

Lab Tests on Concrete

DETERMINATION OF COMPRESSIVE STRENGTH OF

CONCRETE.

(IS: 516 – 1959)

Apparatus:

The testing machine may be of any reliable type of sufficient capacity for the tests and capable

of applying the load at the specified rate. The permissible error shall not be greater than 2 percent

of the maximum load. The testing machine shall be equipped with two steel bearing platens with

hardened faces. One of the platens shall be fitted with a ball seating in the form the portion of a

sphere, the center of which coincides with the central point of the face of the platen. The other

compression platen shall be plain rigid bearing block. The bearing faces of both platens shall be

at least as larger as, and preferably larger than the nominal size of the specimen to which the load

is applied. The bearing surface of the platens, when new, shall not depart from a plane by more

than 0.01mm at any point, and they shall be maintained with a permissible variation limit of

0.02mm. the movable portion of the spherical seated compression platen shall be held on the

spherical seat, but the design shall be such that the bearing face can be rotated freely and tilted

through small angles in any direction.

Page 55: Baglihar hydro electric power plant

55

Age at test: Tests shall be made at recognized ages of the test specimens, the most usual being 7

and 28 days. The ages shall be calculated from the time of the addition of water of the dry

ingredients.

Number of Specimens: At least three specimens, preferably from different batches, shall be made

for testing at each selected age.

Procedure:

Specimens stored in water shall be tested immediately on removal from the water and while they

are still in the wet condition. Surface water and grit shall be wiped off the specimens and any

projecting find removed specimens when received dry shall be kept in water for 24 hours before

they are taken for testing. The dimensions of the specimens to the nearest 0.2mm and their

weight shall be noted before testing.

Placing the specimen in the testing machine the bearing surface of the testing machine shall be

wiped clean and any loose sand or other material removed from the surface of the specimen,

which are to be in contact with the compression platens. In the case of cubes, the specimen shall

be placed in the machine in such a manner that the load shall be applied to opposite sides of the

cubes as cast, that is, not to the top and bottom. The axise of the specimen shall be carefully

aligned with the center of thrust of the spherically seated platen. No packing shall be used

between the faces of the test specimen and the steel platen of the testing machine. As the

spherically seated block is brought to bear on

the specimen the movable portion shall be rotated gently by hand so that uniform seating may be

obtained. The load shall be applied without shock and increased continuously at a rate of

approximately 140 kg/cm2/min.until the resistance of the specimen to the increasing load breaks

down and no grater load can be sustained. The maximum load applied to the specimen shall then

be recorded and the appearance of the concrete and any unusual features in the type of failure

shall be noted.

Calculation: The measured compressive strength of the specimen shall be calculated by dividing

the maximum load applied to the specimen during the test by the cross sectional area, calculated

from the mean dimensions of the section and shall be expressed to the nearest kg per cm2.

Average of three values shall be taken as the representative of the batch provided the individual

variation is not more than +/-15 percent of the average. Otherwise repeat tests shall be made.

Page 56: Baglihar hydro electric power plant

56

A correction factor according to the height / diameter ratio of specimen after capping shall be

obtained from the curve shown in Fig.1 of IS:516-1959. The product of this correction factor and

the measured compressive strength shall be known as the corrected compressive strength this

being the equivalent strength of a cylinder having a height/diameter ratio of two. The equivalent

cube strength of the concrete shall be determined by multiplying the corrected cylinder strength

by 5/4.

DETERMINATION OF FLEXURAL STRENGTH OF CONCRETE.

(IS: 516 – 1959)

Apparatus:

a) Standard moulds of size 15 X 15 X 70 cms for preparing the specimen.

b) Tamping bar.

c) Testing Machine.

Procedure:

Test specimens stored in water at a temperature of 250C to 30

0C for 48 hours before testing shall

be tested immediately on removal from the water, whilst they are still in a wet condition. The

dimensions of each specimen shall be noted before testing. No preparation of the surface is

required.

Placing the specimen in the testing machine: The bearing surfaces of the supporting and loading

rollers shall be wiped clean, and any loose sand or other material removed from the surfaces of

the specimen where they are to make contact with the rollers. The specimen shall then be placed

in the machine in such a manner that the load shall be applied to the upper most surface as cast in

Page 57: Baglihar hydro electric power plant

57

the mould, along two lines spaced 20 or 13.30 cms apart. The axis of the specimen shall be

carefully aligned with the axis of the loading device. No packing shall be used between the

bearing surface of the specimen and the rollers. The load shall be applied with shock and

increasing continuously at a rate such that the extreme fiber stress increases at approximately 7

kgs/cm2/mm for the 10 cm specimens, the load shall be increased until the specimen falls, and

the maximum load applied to the specimen during the test shall be recorded. The appearance of

the fractured faces of the concrete and any unusual features in the type of failure shall be noted.

Calculation:

The flexural strength of the specimen shall be expressed as the modules of rapture „ fb‟ which if

„a‟ equals the distance between the line of fracture and the nearer support measured on the

centerline of the tensile side of the specimen, in cm, shall be calculated to the nearest 0.5 kg/cm2

as follows.

fb = ( p X l ) / ( b X d2 )

When „a‟ is greater than 20.0 cm . for 15.0 cm specimen or greater than 13.30 cm for a 10.0 cm

specimen, or

fb = ( 3p X a ) / ( b X d2 )

When „a‟ is less than 20.0 cms. but greater than 17.0 cms for 15.00 cms specimen, or less than

13.30 cms but greater than 11.0 cms for a 10.0 cms specimen, where b = measured width in cms

of the specimen, d = measured depth in cms of the specimen at the point of failure, l = length in

cm. of the span on which the specimen was supported, and p = maximum load in kg. applied to

the specimen.

If „a‟ is less than 17.0 cm. for a 15 cm specimen or less than 11.0 cm for a 10.0 cm specimen, the

result of the test shall be discard

CHAPTER 9

GROUTING AND ROCK BOLTING

GROUTING

Grounds that the purpose of improving the poor soils with heavy loading conditions, them are

affected by natural disasters such as earthquakes or landslides, tunnels around or buildings main

floor of the features that help to bring more appropriate and sufficient conditions.

Ground Improvement Technique, the Affecting Selection of the Parameters

Ground /rock profiles and characteristic,

Page 58: Baglihar hydro electric power plant

58

Groundwater of status and amount,

Favored level of improvement,

Improve the necessary space and depth,

Productions factors,

Environmental factors,

Cost,

Maintenance, durability, and operational requirements,

Types of Grouting Method

PERMEATION GROUTING:- This method describes the process of filling joints

or fractures in rock or pore spaces in soil with a grout without disturbing the formation.

COMPACTION GROUTING: Grout mix is specifically designed so as not to

permeate the soil voids or mix with the soil. Instead, it displaces the soil in to which it is

injected.

HYDRO FRACTURE GROUTING: Hydro fracture grouting is the deliberate

fracturing of the ground (soil or rock) using grout under pressure. Typically it is used to

compact and stiffen the ground or to access otherwise inaccessible voids.

JET GROUTING: The high-pressure water or grout is used to physically disrupt the

ground, in the process modifying it and thereby improving it.

ROCK GROUTING: Rock grouting is the filling by grout injection of fissures,

fractures or joints in a rock mass with grout without creating new or opening existing

fractures.

COMPENSATION GROUTING: Compensation grouting is the responsive use

of compaction, permeation or hydro fracture grouting as an intervention between an

existing structure and an engineering operation.

DEEP MIXING METHODS (DMM): Today accepted world-wide as a soil

improvement method this is performed to improve the strength, deformation properties

and permeability of the soil.

Page 59: Baglihar hydro electric power plant

59

APPLICATIONS:

1. Following to prevent excessive settlement

2. To increase allowable pressure of the soil both for new structures and/or additions to

existing structures.

3. Control of groundwater flow

4. Prevention of loose – Loose to medium sand densification under adjacent structures

(i.e. both for vertical and lateral movements) Due to adjacent excavations, pile

driving etc.

5. Ground movement control during tunneling operations.

6. Soil strengthening to reduce lateral support requirement.

7. Soil strengthening to increase lateral and vertical resistance of piles.

8. Stabilization of loose sands against liquefaction.

9. Foundation underpinning.

10. Slope stabilization.

11. Volume change control of expensive soils through pressure injection of lime slurry

(only for some expensive soils not at all)

AREAS OF USE:

Cement Grouts: For both impermeabilisation and strength increase.

Soil, Clay and Chemical Grouts: Impermeabilisation and compaction grouting.

Clay Grouts: Limited use (usually filling voids etc.)

Clay-Cement Grouts: Filling voids, mudjacking.

Although the two type of grouting used at BHEP with specification are

1) CONTACT GROUTING:-Such type of grouting is used for crown

in tunnel in one stage.

Specification: - 80lit/4bag, pressure:-4 bar

1m packer is used. 40mm inside

Dia. Of hole= 53mm (Boomer), 49mm dia. Of packer

1.5HP grouting pump( 6 line)

Considered parameter:- 1.Flow:- Magnetic flux flow meter is used(krohne

Marshall Batch Box 5500C). Capacity 0 to1000 liters but usually the flow is

below 100litre.

Pressure: - The pressure sensor is 0-40 Bar.

Page 60: Baglihar hydro electric power plant

60

The flow and pressure data is interpret through PLC (Programmable Logic Controller)

.The program work on window SCADA. It gives RS view.

GROUTING PUMP:-

1. Agitator: - It is a container in which we mix water and cement (grout). The size ofs

agitator is 600 liter.

2. Water and Cement Ratio:- The water and cement ratio is 0.4

3. In this 1.5 HP motor is used.

4. In grouting pump there is one pump which is distributing the grout in six lanes.

5. Density = 1.9

6. Flow rate = 11 avg.

2) CONSOLIDATION GROUTING:- It is used on overall circumference of tunnel.

The consolidation grouting is used after one month of contact grouting.

Specification:- 120lit/2bag,

5m packer is used.

Hole dia. 10m.

Grout use is 1:1.5

STAGES:-In consolidation grouting there is two stages.

S1 – 5m packer used

S2 – 5m packer used

The grout ratio is 1:1.5. In this 100kg of cement and 150 liter mix of water and Bentonite(124ltr

water and 27ltr bentonite). Bentonite is clay verities‟ which is 0.0016mm

In profile there are 12 holes. First we grouted the odd holes after that we will grout the even

holes.

PRESSURE:-

1. Pressure use on grouting is 12kg maximum.

2. Pressure use on packer is 16kg to 25kg .The pressure on packer should not be less than 16kg.

Page 61: Baglihar hydro electric power plant

61

CONCLUSION:

Modern injection materials that ensure good permeation, short setting times and continuous work

progress have proven to give very dry tunnels at reasonable cost levels.

ROCK BOLT

Long anchor bolt for stablization rock excavations, which may be used in tunnels or rock

cuts.

Transfers load from unstable exterior, to the confined interior of rock mass.

Always installed in pattern, design (rock type excavation)

Work by knitting.

A zone of compression is induced in the region betweenrock bolt.

Provide effective reinforcement to rock mass when

i) Rock Bolt spacing (s) <3 average rock piller diameter.

ii) Rock bolt length (L) =2s.

DYWIDAG ROCK BOLTS

At the request of Jaiprakash Industries Ltd.,Delhi, DSI developed a specialized DYWIDAG

Rock Bolts System that was successfully used for the construction of several hydro caverns

in Northern India. The new system was developed in close cooperation between DSI

Germany and DSI UK. From initial consultations it was clear that the client required an

efficient fast track solution to facilite urgent power station construction. Within short time an

appropriate concept was developed by DSI UK and successfully tested and demonstrated in

site trials in Chamera.

The development of the specialized DYWIDAG Rock Bolting System is based on

DYWIDAG Pre-stressing Steel THREADBARS, utilizing mechanical expansion shell

anchorages. Fast setting bearing pads and head arrangements were design to suit the

application. The system proved its efficiency on site and met the clients need for rapid

installation and virtually immediate stressing using hydraulic jacks. Grouting after stressing

provided the required corrosion protection.

Page 62: Baglihar hydro electric power plant

62

The ability to apply the design working load to DYWIDAG Rock Bolts so quickly enabled

cavern excavation to continue without delay.

During the period January to April 2001, DSI forwarded 12 shipping containers from

Germany to India with a total of 235 tons of the newly developed DYWIDAG Rock Bolting

to satisfy the customer urgent program. A total of 7,720 rock bolts in single section lengths

between 6 and 10 meters were supplied as follows:

2,390No. rock bolts 20 mm dia., grade 900/1100, THREADBARS - ultimate load

345 KN

5,330No. rock bolts 26.5 mm dia., grade 900/1030, THREADBARS - ultimate load

586 KN.

The DYWIDAG Rock Bolting has been very successful and continued use of the

system is expected.

The DYWI® Drill Hollow Bar is a fully threaded self-drilling anchorage system which can be

simultaneously drilled and grouted into loose or collapsing soils and brittle rock without the need

for a casing. Furthermore, the bar features a left-hand thread for standard rotary percussive

drilling. Manufactured from high grade steel tubing to EN 10083-1, DYWI® Drill Hollow Bar is

cold rolled to form standard rope thread or “T” thread profiles. The DYWI® Drill rolling process

refines the grain structure of the steel, increasing the yield strength and producing a robust drill

steel suitable for a range of drilling and grouting applications. The DYWI® Drill Hollow Bar

System includes a full range of drill bits, adaptor sleeves, couplers, nuts and bearing plates. In

addition, thanks to a wide range of DYWI® Drill injection adaptors and drill tooling, the hollow

bar can be used with DYWI® Drill Hollow Bar soil nails are idea l for loose or collapsing soils

as they can be installed without the need for a casing. The system is used for mixed fills, granular

material and loose overburden. The DYWI® Drill hollow bar system allows drilling and

grouting to be combined as a single operation and complies fully with EN 14490 (European

standard for soil nails).Soil nails are typically classified as lightly loaded (30-150 KN ), passive

installations. The fully bonded feature enables the loose wedge at the surface to be tied into the

deeper stable zone. Soil nails are normally regarded as low risk installations, with an element of

redundancy existing in the stabilized face. The design of soil nailed faces should incorporate a

diamond grid layout to ensure efficient distribution of the reinforcement. Suitable drainage must

be incorporated within the nailed face to prevent build up of water within the slope. This would

lead to uncontrolled loads at the facing at a later stage.

Page 63: Baglihar hydro electric power plant

63

CHAPTER 10

ADIT AND TUNNEL CONSTRUCTION METHOD

Before starting construction of any underground structure we have to study tunneling method as

most of the structures are constructed inside a hill. For any construction we have to excavate. So

Adits are passage ways to main structures inside like HRT, TRT, Machine Hall, Transformer hall

extra. So in order to excavate the any structure inside the hill we have to reach there. The

passageway used is called Adit. It is constructed by the similar way as other underground

structures in this project. In this project we have many Adits leading to different structures inside

all the Adits are of different length the width is same but the width, height & length of other

underground structure varies.

The method of construction used is Drill Blast Method.

Drill and Blast

Page 64: Baglihar hydro electric power plant

64

This tunneling method involves the use of explosives. Drilling rigs are used to bore blast holes

on the proposed tunnel surface to a designated depth for blasting. Explosives and timed

detonators are then placed in the blast holes. Once blasting is carried out, waste rocks and soils

are transported out of the Tunnel before further blasting. Most tunneling construction in rock

involves ground that is somewhere between two extreme conditions of hard rock and soft

ground. Hence adequate structural support measures are required when adopting this method for

tunneling.

Fig : Drill Blast cycle

DRILLING PATTERN DESIGN

The drilling pattern ensures the distribution of the explosive in the rock and desired blasting

result. Several factors must be taken into account when designing the drilling pattern: rock

drillability and blastability, the type of explosives, blast vibration restrictions and accuracy

requirements of the blasted wall etc. The basic drilling & blasting factors, and drilling pattern

design are discussed below. Since every mining and construction site has its own characteristics,

the given drilling patterns should be considered merely as guidelines.

DRIFTING AND TUNNELING

Many mines and excavation sites still plan their drilling patterns manually, but advanced

computer programs are available and widely used. Computer programs make it easier to modify

the patterns and fairly accurately predict the effects of changes in drilling, charging, loading

and production. Computer programs are based on the same design information used in

preparing patterns manually.

Page 65: Baglihar hydro electric power plant

65

Basic design factors

The tunnel of drift face can be roughly divided into four sections (FIGURE 6.2.-1.).

Drilling pattern design in tunneling and drifting is based on the following factors:

- Tunnel dimensions

- Tunnel geometry

- Hole size

- Final quality requirements

- Geological and rock mechanical conditions

- Explosives availability and means of detonation

- Expected water leaks

- Vibration restrictions

Page 66: Baglihar hydro electric power plant

66

Drilling equipment Depending on site conditions, all or some of the above factors are considered important enough

to determine the tunnel drilling pattern. Construction sites typically have several variations of

drilling patterns to take into account the changing conditions in each tunnel.

Drifting in mines is carried out with 5 to 10 drilling patterns for different tunnel sizes (production

drifters, haulage drifters, draw points, ramps etc.) The pattern is finalized at the drilling site.

Tunnel blasting differs from bench blasting in that tunnels have only one free surface available

when blasting starts. This restricts round length, and the volume of rock that can be blasted at

one time. Similarly, it means that specific drilling and charging increases as the tunnel face area

decreases. When designing a drilling pattern in tunneling, the main goal is to ensure the optimum

number of correctly placed and accurately drilled holes. This helps to ensure successful charging

and blasting, as well as produce accurate and smooth tunnel walls, roof and floor.

Page 67: Baglihar hydro electric power plant

67

CHAPTER 11

CONCLUSION

We are very thankful to JAYPRAKASH ASSOCIATES LIMITED to give us the opportunity to

work in hydropower project.

In this project there are three turbine receiving 430 cumec from three penstock generating power

of450 MW. Although the project is having two stage each stage of 450 MW but stage 1 had

already been completed in 2005.the working of stage 2 was going on so our project is only on

stage 2.

However this project have the capability to generate 5 times more energy but due to shortage of

required discharge during winter the project is consistent to produce only 450MW in the entire

year

This project was completely echo friendly,uses renewable source and having high benefit to cost

ratio.

Due to weak rock of Precambrian age having Muree thrust lots of difficulties arises .thus the use

of the concept of rock stabilization considered to be very effective.

This project uses latest technique like Dywidey rock bolting, Shotcrete of steelfibre R/F,radial

gates with hydraulic hoists.

Page 68: Baglihar hydro electric power plant

68

PLANS

Page 69: Baglihar hydro electric power plant

69