Avoiding Pitfalls and Managing Performance

Page 2: Avoiding Pitfalls and Managing Performance

PLANNING STAGE

Page 3: Avoiding Pitfalls and Managing Performance

3

Solution or Preventive Measure: Identify other organizations within your

agency or other State agencies that have recently faced a similar need and how that organization handled their procurement.

What procurement vehicle did they use?What method of award?What problems did they encounter in procurement

or managing performance?

Pitfall:Agency identifies a need for contractual services.

Page 4: Avoiding Pitfalls and Managing Performance

4

Pitfall:The agency does not know what product,

service or technology the vendor community has available.

Solution or Preventive Measure:Survey current providers through a Request

for Information (RFI) to assess the availability, types, and options of goods and services and to help identify potential suppliers.

Page 5: Avoiding Pitfalls and Managing Performance

5

Request For Information (RFI)

The agency prepares a document which: Provides a preliminary description of the

program objectives and goals, and, Solicits input from the vendor community

as to the availability of products, services and/or technology to meet their needs.

Page 6: Avoiding Pitfalls and Managing Performance

6

RFI – Mandatory Requirements(Procurement Guidelines, Section Seven, IV.C.3.a)

Notification of the RFI must be published in the Contract Reporter.The RFI is mailed to all potential offerors known by the agency at the time of mailing.An open meeting to solicit additional information is the recommended approach. All offerors responding to the RFI must be notified in writing of questions submitted and kept informed of the any open meetings.

Page 7: Avoiding Pitfalls and Managing Performance

7

RFI – Other Requirements

No award may be made under the RFI process.

Page 8: Avoiding Pitfalls and Managing Performance

8

Pitfall:Department lacks adequate resources for

managing the project.

Solution or Preventive Measure:Seek outside assistance by identifying

organizations within your agency or other State agencies that may have qualified staff.

Determine if you need to procure the services of a project manager to accomplish your project goals.

Page 9: Avoiding Pitfalls and Managing Performance

9

Pitfall:Agency incurs large cost overruns during

project.

Solution or Preventive Measure:At outset of the procurement process, agency

should perform a detailed cost analysis of staff training time, equipment needs, contractual costs, set-aside for contingencies (unexpected events), etc.

Page 10: Avoiding Pitfalls and Managing Performance

10

Effective contract management is dependent on four

key elementsMethods used to select the contractors (procurement).Adequacy of contract provisions (contract establishment).Processes used to establish contract payments (rate-setting/reimbursement methodology).Processes used to monitor contractor performance (contract oversight).

Page 11: Avoiding Pitfalls and Managing Performance

11

DEVELOPMENT STAGE

Page 12: Avoiding Pitfalls and Managing Performance

12

Pitfall:All available procurement vehicles were not

evaluated in developing bid documents.

Solution or Preventive Measure:Review all procurement vehicles to insure the

correct fit. Consider Preferred Sources, OGS centralized contracts, OGS backdrop contracts, discretionary purchasing, IFB’s, RFP’s, single or sole source.

Page 13: Avoiding Pitfalls and Managing Performance

13

Pitfall:An RFP was used when an IFB would have fit

the scope of services, causing:An unnecessary administrative burden. Increase in processing time (inception to

commencement of work). Extra cost.

Page 14: Avoiding Pitfalls and Managing Performance

14

Solution or Preventive Measure:An IFB should be the best approach if:

Exact technical solution is known.Price is very important.

An RFP should be the best approach if:A technical solution is needed (generally complex

in nature).Technical appraisal outweighs importance of cost.

Page 15: Avoiding Pitfalls and Managing Performance

15

Types of services which should be procured by these methods: IFB: Commodity purchases (required);

janitorial; guard duty; auditing.RFP: Modernization of an existing system

(Human Resources, Payroll, Financial Management, etc.); Development of a new system (Electronic Benefits Transfer-EBT, Rebid of MMIS – eMed NY, Connections, etc.).

Page 16: Avoiding Pitfalls and Managing Performance

16

Pitfall:Contract performance did not produce a

meaningful result.

Solution or Preventive Measure:RFP/IFB/Contract should,wherever possible:

Specify outcomes of deliverables (clear statement of expected goods and services).

Reflect identifiable measures of performance.Require liquidated damages, a letter of credit or

performance bond.

Page 17: Avoiding Pitfalls and Managing Performance

17

Pitfall:A price increase for a renewal year was

negotiated but the original RFP/IFB and contract did not allow for price escalation (no contract escalation clause).

Solution or Preventive Measure:The RFP/IFB and original contract must have

an escalation clause to allow price adjustments.

If not, the amendment would be returned unapproved and the agency would be required to submit a reduced amendment amount.

Page 18: Avoiding Pitfalls and Managing Performance

18

Why is Contract Management Important?

Effective contract management is essential to ensure:Contractors produce desired results.Public funds are protected from fraud,

waste, or inefficient use.

Page 19: Avoiding Pitfalls and Managing Performance

19

Historical PerspectiveWhat are the Costs of Poor

Contract Management?A Commission placed under conservatorship due to widespread contract mismanagement.An agency circumvents procurement requirements on a $33.7 million contract.Gross fiscal mismanagement of Smart Jobs contracts administered by a State agency.Poor contract performance oversight causing over $100 million in cost overruns (double the original project estimate) and still on-going.

Page 20: Avoiding Pitfalls and Managing Performance

20

Liquidated DamagesConsequential Damages:

Vendor’s inability to deliver contract deliverables in accordance with specifications and timeliness, i.e. non-conformance.

Disruption to agency programs. Loss of Federal or other

reimbursement funds.Creates other negative impacts.

Page 21: Avoiding Pitfalls and Managing Performance

21

Liquidated DamagesThese losses should be quantified in dollars and

assessed against the vendor.Some examples of non-conformance are:

Not delivering agreed to system up-time percentage.

Not meeting processing standards for claims.Causing systems to be inoperable.

Page 22: Avoiding Pitfalls and Managing Performance

22

Liquidated DamagesDirect Damages:

Termination for Cause provision is exercised; agency is forced to rebid.

If termination results in extra costs above the original contract amount, the terminated vendor should be held responsible for the difference.

Page 23: Avoiding Pitfalls and Managing Performance

23

Liquidated DamagesThe RFP/IFB/Contract should state a

specific dollar limit for which liquidated damages may be assessed for either consequential or direct damages.

Liquidated damages may be specified in advance if reasonably related to the anticipated harm that will result from default.

Unreasonably high amounts are regarded as penalties that may not be legally enforced under the guide of “liquidated damages.”

Page 24: Avoiding Pitfalls and Managing Performance

24

Liquidated DamagesThese damages are not “penalties.”Solely intended to compensate the State for harm caused by default.Availability of liquidated damage remedy intended to have only an incidental incentive/disincentive effect on contractor’s performance.Full assessment (dollars) of liquidated damage clause is not required; the actual assessment should be proportionate to the harm suffered by the State.

Page 25: Avoiding Pitfalls and Managing Performance

25

Pitfall: Agency develops an unclear specification and/or

provides insufficient bidding information; this can result in an insufficient number of firms bidding or a bid protest, etc.

Solution or Preventive Measure: Develop clear, detailed specifications allowing bidders

to submit responsive proposals. If needed, seek outside assistance:

Identify other organizations within your agency or other State agencies for qualified staff.

Solicit outside consultant services. Section 163.A of the New York State Finance Law

reminder.

Page 26: Avoiding Pitfalls and Managing Performance

26

Pitfall:Agency writes restrictive specifications

resulting in a lack of adequate competition, complaints or protests, etc.

Solution or Preventive Measure:Restrictive specifications may be a reason for

rejection and rebid of a contract. Transaction may be returned to agency unapproved.

Page 27: Avoiding Pitfalls and Managing Performance

27

Pitfall:Did not establish criteria prior to receipt of

bids (“lock box”), including the use of a finalist slate, if applicable.

Solution or Preventive Measure:Review Section 163.7 of NYS Finance Law.Contract will be returned unapproved.

Page 28: Avoiding Pitfalls and Managing Performance

28

Pitfall:Did not publish relative weights in bid

document (technical vs. cost).

Solution or Preventive Measure:Review Section 163.9.b of NYS Finance Law.The contract will be returned unapproved.

Page 29: Avoiding Pitfalls and Managing Performance

29

Pitfall:Price offered should be reviewed objectively.

The content or level of effort should be considered when evaluating the technical proposals.

Solution or Preventive Measure:Technical proposal should include a manning

schedule to help determine if the proposed level of effort is realistic in regard to achieving the end work product.

Page 30: Avoiding Pitfalls and Managing Performance

30

Pitfall:Points assigned to cost did not represent a

meaningful worth.

Solution or Preventive Measure:Review intent of State Finance Law, Article 11

(particularly Sections 163.1.j, 163.7 and 163.9.b) and Procurement Guidelines.

Page 31: Avoiding Pitfalls and Managing Performance

31

Pitfall:When using the formula in the Procurement

Guidelines, a high dollar bid may skew the points assigned to the mid-range bids.

Solution or Preventive Measure:Use the following recommended formula to

provide a more balanced assignment of cost points.

Page 32: Avoiding Pitfalls and Managing Performance

32

Recommended Cost FormulaLow bid / bid being evaluated x maximum points for cost = cost

scoreSample Bid Tabulation

PG Formula (max. pts. 25)

Recommended Formula (max. pts. 25)

$150,000 25.00 25.00

$160,000 24.72 23.44$190,000 23.89 19.74$390,000 18.33 9.62$900,000 4.17 4.17

Page 33: Avoiding Pitfalls and Managing Performance

33

Pitfall:Multiple award not in RFP/IFB or without a

defined selection procedure as to how the work will be distributed.

Solution or Preventive Measure:Review Section 163.10.c of NYS Finance

Law.You must define the “up to” number of firms

that can be awarded a contract.You must define your selection procedure for

the actual work (task orders etc.).

Page 34: Avoiding Pitfalls and Managing Performance

34

Evaluation and Award Stage

Page 35: Avoiding Pitfalls and Managing Performance

35

Pitfall:Agency did not respond to a vendor’s request

for debriefing; did not notify unsuccessful vendors in a timely manner.

Solution or Preventive Measure:Review Procurement Guidelines, Section

Seven, VI.2.Debriefing is mandatory.

Page 36: Avoiding Pitfalls and Managing Performance

36

Pitfall:The agency’s application of evaluation scoring

differs from their RFP/IFB/evaluation instrument.

Solution or Preventive Measure:Review State Finance Law, Article 11, and the

Procurement Guidelines. A rebid of the services may be required.

Develop the RFP and evaluation instrument at the same time.

Page 37: Avoiding Pitfalls and Managing Performance

37

Pitfall:Award made to a non-responsive bidder, i.e.,

vendor did not meet specification requirements or submit proper forms, etc.

Solution or Preventive Measure:This is not acceptable. The transaction will be

returned to agency unapproved.

Page 38: Avoiding Pitfalls and Managing Performance

38

Example: Non-Responsive Bidder

The RFP/IFB requires unlimited liability on the part of the vendor. During negotiation with the awarded vendor, the agency negotiates a lesser liability, creating a material change to the original procurement.Consider and weigh:Reasonableness of this requirement.Necessity of this requirement.Are there a sufficient number of vendors who

will bid on the specific services being procured if this requirement is present?

Page 39: Avoiding Pitfalls and Managing Performance

39

Example: Non-Responsive Bidder

Any material change(s) to a procurement document (RFP/IFB) may prejudice other offerors as well as potential offerors who did not submit a bid. These awards are subject to re-bid.

Page 40: Avoiding Pitfalls and Managing Performance

40

Use Electronic Payments

Page 41: Avoiding Pitfalls and Managing Performance

41

Pitfall:Electronic payments process not used for

payments to vendors.

Page 42: Avoiding Pitfalls and Managing Performance

42

Solution or Preventive Measure:Payee completes an Electronic Payments

Authorization Form to enroll in this program.Benefits:

Faster access to cash by your vendors. Direct deposit; access within 24 hours.

Less paperwork to process for New York State. OSC Payment Bureau’s volume:

• 4.6 million transactions annually.• 18,500 daily payments to vendors, municipalities and

employees.Vendor receives e-mail alerts when monies are ready

to be deposited in their accounts.Vendors receive one electronic payment for all their

invoices for that day.

Page 43: Avoiding Pitfalls and Managing Performance

43

Solution or Preventive Measure:For further information, contact OSC’s

Bureau of Accounting Operations at (518) 474-4032 or e-mail: [email protected]

Visit OSC website at http://nysosc3.osc.state.ny.us/epay/index.htm

Page 44: Avoiding Pitfalls and Managing Performance

44

Pitfall:Agency awards a reduced scope of work from

originally requested in the RFP/IFB.

Solution or Preventive Measure:This is not acceptable unless it is a minor

reduction. The agency must be able to defend that any bidder or potential bidder was not prejudiced.

Page 45: Avoiding Pitfalls and Managing Performance

45

We strongly recommend publishing your mandatory contract provisions into the RFP or IFB, since:This allows potential bidders to raise concerns

prior to submitting a bid, and,Eliminates a vendor or vendors unwilling to

meet these mandatory provisions, thus avoiding prolonged and fruitless contract negotiations if this vendor is the highest ranked firm; thus saving the agency time and money, and avoiding delay of their program needs being met.

Page 46: Avoiding Pitfalls and Managing Performance

46

Summary

Page 47: Avoiding Pitfalls and Managing Performance

47

In Summary:

OpennessQuestions and answers are disclosed to all

bidders.No verbal (one on one) communications

with vendors.Debriefing losing vendors upon request.

Page 48: Avoiding Pitfalls and Managing Performance

48

In Summary:

FairnessCreate an even playing field.Clear, detailed specifications.No altering of evaluation criteria after bids

have been received.

Page 49: Avoiding Pitfalls and Managing Performance

49

In Summary:

Due DiligenceKnowledge of applicable rules and

regulations.Procurement Guidelines.Procurement Stewardship Act.OSC G-Bulletins.

Page 50: Avoiding Pitfalls and Managing Performance

50

In Summary:

Achieving GoalsCommunicate your needs/goals and reach

a full understanding with the awarded vendor.

Page 51: Avoiding Pitfalls and Managing Performance

51

In Summary:

Following these outlined steps should produce a protest-free procurement and a smooth approval process.