appendix vibration analysis report - 'virginia avenue … · virginia avenue tunnel...
TRANSCRIPT
Appendix F Vibration Analysis Report
June 2013
VIRGINIA AVENUE TUNNEL RECONSTRUCTION PROJECT
WASHINGTON, DC
VIBRATION ANALYSIS REPORT
June 2013
Prepared by CLARK/PARSONS, JOINT VENTURE
100 M Street, SE, Suite 1200 Washington, DC 20003
Phone: 202-775-3300. Fax: 202-775-3420
i
TABLE OF CONTENTS
Table of Contents ..................................................................................................................... i
ACRONYMS AND ABBREVIATIONS .......................................................................................... iii
STANDARDS ........................................................................................................................... iv
EXECUTIVE SUMMARY ............................................................................................................. v
1 INTRODUCTION .................................................................................................................... 11.1 PurposeofVibrationStudy...................................................................................................................................11.2 ProjectDescription...................................................................................................................................................1
2 VIBRATION BACKGROUND .................................................................................................... 42.1 VibrationBackground.............................................................................................................................................4
3 IMPACT CRITERIA .................................................................................................................. 63.1 OperationVibrationImpactCriteria.................................................................................................................63.2 ConstructionImpactCriteria................................................................................................................................7
4 EXISTING SETTING................................................................................................................. 84.1 ExistingLandUse......................................................................................................................................................84.2 VibrationMeasurements.......................................................................................................................................9
5 IMPACT ASSESSMENT ......................................................................................................... 215.1 ConstructionVibration.........................................................................................................................................215.2 Post‐ConstructionOperationVibration.........................................................................................................23
6 MITIGATION ....................................................................................................................... 276.1 ConstructionVibrationMitigation...................................................................................................................276.2 Post‐ConstructionoperationVibrationMitigation...................................................................................28
APPENDIX A FIGURES ............................................................................................................ 29
ii
LIST OF TABLES
Table ES‐1. Impact Distances for Existing and Future Ground‐Born Vibration Train Pass
By in the Tunnel
Table ES‐2. Construction Equipment Vibration Impact Distances
Table 3‐1. Land Use Categories and Metrics for Rail Noise Impact Criteria
Table 3‐2. Ground‐Born Vibration Criteria for Special Buildings
Table 3 3. Construction Vibration Building Damage Criteria
Table 4 1. Existing Train Pass‐by Vibration Measurements
Table 4 2. Existing baseline Vibration Measurements
Table 4 3. Existing Nighttime Baseline and Train Pass‐by Vibration Measurements
Table 4 4. Soil Factor Derived from Existing Train Pass By Measurements at the East
Portal
Table 5‐1. Measured Vibrations Levels verses Calculated Vibrations for Building Sites
near the Tunnel
Table 5‐2. Impact Distances for existing and future Ground‐Born Vibration Train Pass
By
Table 5‐3. Highest Construction Equipment Vibration Levels
Table 5‐4. Ground‐Born Vibration Source Levels for Construction Equipment
Table 5‐5. Construction Equipment Vibration Impact Distances
LIST OF FIGURES
Figure 1‐1. Project Location Map
Figure 2 1. Typical Levels of Ground‐Borne Vibration
Figure 4 1. Existing Train Pass‐by Longitudinal Vibration Measurements
Figure 4 2. Existing Train Pass‐by Transverse Vibration Measurements
Figure 4 3. Existing Train Pass‐by Vertical Vibration Measurements
Figure 4 4. Existing Night Time Train Pass‐by Vertical Vibration Measurements
iii
ACRONYMS AND ABBREVIATIONS
CSX CSX Transportation, Inc.
DDOT District of Columbia Department of Transportation
FHWA Federal Highway Administration
FTA Federal Transit Administration
HVAC Heating, Ventilation, and Air Conditioning
Lmax Maximum level for a single vibration event
MTA Maryland Transit Administration
PPV Peak Particle Velocity
RMS Root Means Square
USDOT United States Department of Transportation
VAT Virginia Avenue Tunnel
VdB Vibration decibel
VRE Virginia Railway Express
iv
STANDARDS The following guidelines are utilized for the vibration impact and mitigation assessment:
FTA Noise and Vibration Impact Assessment, May 2006.
v
EXECUTIVE SUMMARY A study was conducted to assess potential vibration conditions during and after the expansion
of Virginia Avenue Tunnel (VAT) on the surrounding community. CSX intends to expand the
existing one track tunnel to two tracks and increase the tunnel minimum vertical clearance to 21
feet above top of rail. This study was conducted in accordance to the procedures outlined in the
Federal Transit Administration Noise and Vibration Impact Manual. Three proposed VAT
alignment alternatives were assessed for vibration impacts in both construction and post‐
construction phases. All three of the proposed alternatives run under Virginia Avenue, SE near
vibration sensitive land use areas and buildings along a 3,800 feet stretch of tunnel within
Washington, DC. Vibration measurements were conducted at three locations near the proposed
VAT expansion. Results of these measurements were used to determine vibration levels from
existing train pass bys and calculate vibration transferability characteristics of the soil which
could then be used for predicting the vibration levels from construction activities and post‐
construction train operations.
Vibration impacts were evaluated for human annoyance and building damage. The distance
between vibration sensitive receptors and the new track alignments were obtain from the
concept design files. The train source used for calculating impact distances was derived from
the measured vibration levels. Table ES‐1 shows impact distances from the edge of track for the
potential of projected building damage and human annoyance due to the existing and future
train operations, as well as during construction. As indicated in Table ES‐1, any structures
farther than 20 feet away from the edge of track would not have vibration building damage
impacts and human annoyance impacts would not occur at more than 36 feet away from the
edge of track even when there are two trains traveling through the tunnel or tunnels at the same
time. Vibration impacts are not anticipated due to future, post‐construction train operations
because the closest building to any of the project alignment alternatives is 44 feet from edge of
track.
The potential for vibration annoyance and building damage was also analyzed for major
vibration producing construction equipment that would be used on this project. Vibration levels
produced by construction equipment were obtained from the Federal Transit Administration
Noise and Vibration Impact Assessment Manual. These vibration levels were used to calculate
the distances at which vibration impacts would occur. As shown in Table ES‐2, mitigation
measures would need to be considered, if construction equipment were to operate near
residential or institutional buildings within these distances. Because detailed construction
activities and types of equipment that will be utilized for each phase are not available at this
time, overall vibration levels from each construction phase cannot be predicted. Once detailed
construction schedule for various phases of the construction is developed during the final
design, these predicted vibration levels need to be confirmed and expanded as needed.
vi
Table ES‐1. Impact Distances for Existing and Future Ground‐Born Vibration Train
Pass By in the Tunnel
Alternatives
Distance to Potential Vibration
Building Damage feet
Distance to Potential Vibration Human Annoyance
feet
Existing/ No Build 10 17
Alternative 2 (during construction) 10 17
Alternative 2 20 36
Alternative 3 20 36
Alternative 4 20 36
Table ES‐2. Construction Equipment Vibration Impact Distances
Equipment
Distance to Potential Vibration
Building Damage2 feet
Distance to Potential Vibration Human
Annoyance1 feet
Large bulldozer 21 38
Loaded trucks 20 35
Hoe Ram 21 38
Caisson drilling 21 38
Vibratory compactor/roller 33 59
Sheet Driver (Sonic) 30 53
Jackhammer 13 23
Notes: 1. This is the distance at which the PPV is 0.04 in/sec or less at the inside of the building structure. 2. This is the distance at which the peak particle velocity is 0.20 in/sec or less.
While ground‐borne vibrations are not expected to exceed FTA building damage and human
annoyance impact criteria for the train operations on proposed alignment alternatives,
construction activities such as earth moving with bulldozers, the use of vibratory compaction
rollers, and sheet piling would have the most likely potential to cause some human annoyance
impacts. There are cases where it may be necessary to use this type of equipment in close
proximity to residential buildings near vibration sensitive area; however, there are mitigation
measures that can be used to minimize human annoyance.
Vibration Analysis Report 1
1 INTRODUCTION
1.1 PURPOSE OF VIBRATION STUDY The purpose of this study is to assess future vibration conditions at vibration sensitive locations
along the Virginia Avenue Tunnel Project. The Virginia Avenue Tunnel Vibration Study is
divided into six sections. Section 1 presents the overall Virginia Avenue Tunnel project
description. Section 2 explains the general vibration terminology. Section 3 presents the
guidelines and criteria used to assess the impact of the proposed Virginia Avenue Tunnel
project. Section 4 presents the results of baseline vibration measurements. Section 5 analyzes the
future impacts of construction, operation, and supporting facilities. Section 6 discusses possible
mitigation measures that may be required to reduce the impact of the Virginia Avenue Tunnel
Project.
1.2 PROJECT DESCRIPTION CSX Transportation, Inc. (CSX) is proposing to reconstruct the Virginia Avenue Tunnel. The
tunnel is located in the Capitol Hill neighborhood of the District of Columbia beneath
eastbound Virginia Avenue SE from 2nd Street SE to 9th Street SE, Virginia Avenue Park and
the 11th Street Bridge right‐of‐way between 9th and 11th Streets SE, and is aligned on south
side of Interstate 695 (I‐695). The tunnel portals are located a short distance west of 2nd Street
SE and a short distance east of 11th Street SE. CSX also owns or has easements of the rail lines
immediately east and west of the tunnel. The tunnel and rail lines running through the District
are part of CSX’s eastern seaboard freight rail corridor, which connects Mid‐Atlantic and
Midwest states.
The CSX proposal includes the complete reconstruction of the tunnel, which was built over 100
years ago. In addition to its age, the tunnel is also a bottleneck to the freight rail network with
its single‐track configuration and with a vertical clearance that does not allow for double‐stack
intermodal container freight trains. The Project will transform the tunnel to a two‐track
configuration, matching the number of tracks immediately east and west of the tunnel, and
provide the minimum 21 feet of vertical clearance to allow double‐stack intermodal container
freight train operations. This will allow more efficient freight movement, especially in light of
expected increases in freight volume. Reconstructing the tunnel to allow double‐stack
intermodal container freight trains would require lowering the grade below the rail line’s New
Jersey Avenue SE Overpass to provide the 21‐foot minimum clearance.
The following alternatives are being considered for the Project:
Alternative 1 ‐ No Build: The No Build alternative, which is automatically carried
forward into the Draft EIS. The tunnel would not be rebuilt under this alternative.
However, the railroad would continue to operate trains through the tunnel and at some
point, emergency or unplanned major repairs or rehabilitation could be required to this
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 2
critical, aging infrastructure that might prove equally or even more disruptive to the
community than the Build Alternatives.
Alternative 2 ‐ Rebuilt Tunnel / Temporary Runaround Track: This alternative
involves rebuilding the existing Virginia Avenue Tunnel. It would be rebuilt with two
tracks and enough vertical clearance to accommodate double‐stack intermodal container
freight trains. It would be rebuilt in generally the same location, except aligned
approximately seven feet to the south of the existing tunnel center line. It would be
rebuilt using protected open trench construction methods. During construction, freight
trains would be temporarily routed through a protected open trench outside the existing
tunnel (runaround track). The runaround track would be aligned to the south of the
existing tunnel. It would be parallel to the existing tunnel and would be below street
level. Due to new columns associated with the rebuilt 11th Street Bridge, the runaround
track would slightly separate from the tunnel alignment on the east end starting just
west of Virginia Avenue Park. Safety measures such as securing fencing would be used
to prevent pedestrians and cyclists from accessing the runaround track.
Alternative 3 ‐ Two New Tunnels: This alternative involves replacing the existing
Virginia Avenue Tunnel with two new permanent tunnels constructed sequentially.
Each new tunnel would have a single track with enough vertical clearance to allow
double‐stack intermodal container freight trains. A new parallel south side tunnel would
be built first as trains continue operating in the existing Virginia Avenue Tunnel. After
the south side tunnel is completed, train operations would switch over to the new tunnel
and the existing Virginia Avenue Tunnel would be demolished and rebuilt. With the
exception of operating in a protected open trench for approximately 230 feet
immediately east of the 2nd Street portal (within the Virginia Avenue SE segment
between 2nd and 3rd Streets SE), trains would operate in enclosed tunnels throughout
construction under Alternative 3. Throughout most of the length, the two tunnels would
be separated by a center wall. This center wall would be the new centerline of the two
tunnels, and it would be aligned approximately 25 feet south of the existing tunnel
centerline, between 2nd and 9th Streets SE. Due to new columns associated with the
rebuilt 11th Street Bridge, the tunnels would be separated on the east end starting just
west of Virginia Avenue Park, resulting in two separate single‐track tunnels and
openings at the east portal.
Alternative 4 ‐ New Partitioned Tunnel / Online Rebuild: Alternative 4 would result in
a new tunnel with a center partition wall separating two permanent single tracks.
Similar to Alternative 3, the new partitioned tunnel would be partitioned and have
enough vertical clearance to allow double‐stack intermodal container freight trains. It
would be aligned approximately 17 feet south of the existing tunnel’s centerline. The
new partitioned tunnel would be built using protected open trench construction
methods. Safety measures such as secure fencing would be used to prevent pedestrians
and bikers from accessing the protected open trench. The rebuild would occur ‘online’
meaning that during the period of construction, the protected open trench would
accommodate both construction activities and train operations. Maintaining safe and
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 3
reliable temporary train operations is a more complicated endeavor under Alternative 4
than under the other two Build Alternatives because of the online rebuild approach.
Regardless of Build Alternative, the Project would extend the east portal by approximately 330
feet to a location northeast of the 12th Street and M Street T‐intersection.
The anticipated limits of work are estimated to be 1,500 feet south of the West Portal of the VAT
to 1,200 feet north of the East Portal of the VAT, a total of 6,500 feet. Figure 1‐1 shows the project
location.
Figure 1-1. Project Location Map
New Jersey Ave. SE Overpass
Vibration Analysis Report 4
2 VIBRATION BACKGROUND
This section describes the basic concepts of vibration methodology used in this study. This
information will provide background for the assessment procedures described in the later
sections.
2.1 VIBRATION BACKGROUND Vibration is an oscillatory motion, which can be described in terms of displacement, velocity, or
acceleration. Displacement, in the case of a vibrating floor, is simply the distance that a point on
the floor moves away from its static position. The velocity represents the instantaneous speed of
the floor movement, and acceleration is the rate of change of the speed. The response of
humans, buildings, and equipment to vibration is normally described using velocity or
acceleration. In this report, velocity will be used in describing ground‐borne vibration.
Vibration amplitudes are usually expressed as either peak particle velocity (PPV) or the root
mean square (RMS) velocity. The PPV is defined as the maximum instantaneous peak of the
vibration signal in inches per second. The RMS of a signal is the average of the squared
amplitude of the signal in inches per second. Although PPV is appropriate for evaluating the
potential of building damage, it is not suitable for evaluating human response. Since it takes
some time for the human body to respond to vibration signals, RMS amplitude is more
appropriate to evaluate human response to vibration than PPV.
The Federal Transit Administration (FTA) a division of the U.S. Department of Transportation
(USDOT) uses the abbreviation “VdB” for vibration decibels (FTA, 2006) to reduce the potential
for confusion with sound decibel and the reference value to covert PPV and RMS into VdB is 1
micro‐inch per second. For sources such as trains, PPV VdB levels are higher than RMS levels
and conversion factor of 4 is applied to PPV measurements when determining the VdB RMS
level this conversion number is known as the crest factor.
Figure 2‐1 illustrates common vibration sources and the human and structural responses to
ground‐borne vibration. As shown in Figure 2‐1, the threshold of perception for human
response is approximately 65 VdB; however, human response to vibration is not usually
significant unless the vibration exceeds 70 VdB, unless it’s a concert hall or other fine arts
performance venues. Vibration tolerance limits for sensitive instruments such as MRI or
electron microscopes could be much lower than the human vibration perception threshold.
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 5
Source: FTA (2006)
Figure 2-1. Typical Levels of Ground-Borne Vibration
Vibration Analysis Report 6
3 IMPACT CRITERIA
This section presents the guidelines, criteria, and regulations used to assess noise and vibration
impacts associated with the proposed project.
3.1 OPERATION VIBRATION IMPACT CRITERIA The District of Columbia Department of Transportation (DDOT) environmental regulations do
not address potential vibration impacts; therefore, the criteria in the FTA Transit Noise and
Vibration Impact Assessment (FTA, 2006) were used to evaluate vibration impacts from train
operations. The evaluation of vibration impacts can be divided into two categories: (1) human
annoyance and (2) building damage.
HUMAN ANNOYANCE CRITERIA Table 3‐1 presents the criteria for various land use categories as well as the frequency of events.
The criteria are related to ground‐borne vibration causing human annoyance or interfering with
the use of vibration sensitive equipment. The criteria for acceptable ground‐borne vibration are
expressed in terms of RMS velocity levels in VdB and are based on the maximum levels for a
single event (Lmax). PPV has been added to this table to make an easier comparison to the
measured data for this project.
Table 3‐1. Land Use Categories and Metrics for Rail Vibration Impact Criteria
Land Use Category
Ground‐Borne Vibration Impact Levels (dB re 1 micro‐inch/sec)
and PPV (in/sec)
Frequent1 Events Occasional Events2 Infrequent3 Events
Category 1: Buildings where vibration
would interfere with interior
operations.
65 VdB4 0.007
in/sec 65 VdB4
0.007
in/sec 65 VdB4
0.007
in/sec
Category 2: Residences and buildings
where people normally sleep. 72 VdB
0.016
in/sec 75 VdB
0.023
in/sec 80 VdB
0.040
in/sec
Category 3: Institutional land uses
with primarily daytime use. 75 VdB
0.023
in/sec 78 VdB
0.032
in/sec 83 VdB
0.056
in/sec
Source: FTA, 2006.
Notes:
1. “Frequent Events” is defined as more than 70 vibration events per day.
2. “Occasional Events” is defined as between 30 and 70 vibration events of the same source per day.
3. “Infrequent Events” is defined as fewer than 30 vibration events per day.
4. This criterion limit is based on levels that are acceptable for most moderately sensitive equipment
such as optical microscopes. Vibration‐sensitive manufacturing or research will require detailed
evaluation to define the acceptable vibration levels. Ensuring lower vibration levels in a building
often requires special design of the HVAC systems and stiffened floors.
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 7
There are some buildings, such as concert or band halls, TV and recording studios, as well as
theaters that can be sensitive to vibration and noise but do not fit into any of the three
categories. Because of the sensitivity of these buildings, they usually warrant special attention.
Table 3‐2 gives criteria for acceptable levels of ground‐borne vibration for various types of
special buildings.
Table 3‐2. Ground‐Born Vibration Criteria for Special Buildings
Type of Building or Room
Ground‐Borne Vibration Impact Levels (dB re 1 micro‐
inch/sec) and PPV (in/sec)
Frequent1 Events Occasional or Infrequent
Events2
Concert or Band Halls, TV Studios,
Recording Studios 65 VdB 0.007 in/sec 65 VdB 0.007 in/sec
Auditoriums, Theaters 72 VdB 0.016 in/sec 80 VdB 0.040 in/sec
Source: FTA, 2006.
Notes:
1. “Frequent Events” is defined as more than 70 vibration events per day.
2. "Occasional or Infrequent Events" is defined as fewer than 70 vibration events per day.
BUILDING DAMAGE CRITERIA Normally, vibration resulting from a train pass by would not cause building damage. However,
the potential for damage to fragile historic buildings located very near to or within the right‐of‐
way can be a concern. The FTA provides a vibration damage threshold criterion of 0.50 in/sec
PPV for fragile buildings and 0.12 in/sec PPV for extremely fragile historic buildings, for typical
train operations (FTA, 2006). The FTA recommends these criteria be used as a damage threshold
for the fragile structures located near the right‐of‐way of a rail project.
3.2 CONSTRUCTION IMPACT CRITERIA Construction activities can result in varying degrees of ground vibration, depending on the
equipment and method employed. The vibration associated with this transit construction
project involves demolition, excavation, and shoring of a tunnel and there is the potential for
building damage and it needs to be assessed. The construction vibration is generally assessed in
terms of PPV. Table 3‐3 summarizes the construction vibration limits shown in FTA guidelines.
Table 3‐3. Construction Vibration Building Damage Criteria
Building Category PPV (in/sec)
I. Reinforced-concrete, steel, or timber (no plaster) 0.5
II. Engineered concrete and masonry (no plaster) 0.3
III. Non-engineered timber and masonry buildings 0.2
IV. Buildings extremely susceptible to vibration damage 0.12
Source: FTA, 2006.
Vibration Analysis Report 8
4 EXISTING SETTING
4.1 EXISTING LAND USE The VAT Project alternatives use an alignment that runs under Virginia Avenue, SE near
vibration sensitive land use areas and buildings along a 3,800 feet stretch of tunnel within
Washington, DC. For the purpose of this study, vibration sensitive receptors were selected by
their proximity to the three build alternative alignments and by future and existing land use,
and are describe in the following paragraphs:
HISTORIC
The Project Area is located in proximity to various federal buildings and facilities; however,
these buildings are not in close vicinity of the tunnel. The St. Paul African Union Methodist
Church, located at 401 I Street SE is listed on the National Register of Historic Places. Another
historic site is the Marine Barracks, oldest active post in the U.S. Marine Corps, is located at 8th
and I Streets SE. The Marine Barracks was placed on the National Register of Historic Places by
the U.S. Department of the Interior in 1976.
RESIDENTIAL
Category 2 residential land uses dominant on the west side of Eleventh Street and the north side
of M Street. South of the Southeast/Southwest Freeway (I‐695) there is a large area of residential
development, and in the area surrounding (and including) the Marine Barracks. The closest
residential development to the tunnel are Capitol Quarter Townhouses and Capper Senior
Building, which are located on the blocks between Third and Fifth Streets, SE, south of Virginia
Avenue SE. The new enlisted men’s quarters within the grounds of the Marine Barracks are also
close to the tunnel.
INSTITUTIONAL
These are the Category 3 land uses and facilities occupied by schools, hospitals, religious
organizations and similar institutions with primarily daytime use. The project area contains
Tyler Elementary School, Eagle Academy (two locations). The project area also includes St. Paul
African Union Methodist Church. There are no hospitals or public libraries in the project area.
MARINE BAND PRACTICE HALL The Marine Band Practice Hall is located near 7th Street, SE and Virginia Avenue, SE. The
practice hall is considered as a Special Building land use.
COMMERCIAL
There are no commercial buildings that are classified as Category 1, 2, or 3 land uses or are
considered as Special Building land use.
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 9
4.2 VIBRATION MEASUREMENTS Vibration measurements were conducted to determine baseline vibration levels from existing
train pass bys, and to calculate vibration transferability characteristics of the soil for the purpose
of projecting expected vibration levels during construction and post‐construction train
operation phases. On May 22 to 23, 2012 vibration measurements from passing trains were
conducted at three separate sites. The first measurement site is just outside East Portal, east of
Eleventh Street. The other two sites were selected as measurement sites near to the two
vibration sensitive structures closest to the project, the Capitol Quarter Townhouses and the
Marine Building/Band Practice Hall.
Vibration levels attributed to passing trains were measured at outside locations for each of the
three sites, and also at one additional inside site within the Marine Band Practice Hall. The
vibration measurements were conducted using GeoSonic 3000EZ plus and 3000LC portable
seismographs. Vibration levels were measured on the vertical, transverse, and longitudinal
axes. The seismograph has an internal calibration sequence and was operated according to the
manufacturer’s specifications and recorded PPV vibrations (in inches per second). Vibration
measurements were conducted by Parsons staff.
At each measurement site, two probes were set up perpendicular to the tunnel. Measurements
close to the East Portal were at 19 and 74 feet from the edge of the track. These measurements
were the closest sites to the tracks where the strongest vibration signal can be measured and the
results can be used for calculating the soil vibration transferability characteristics.
Vibration probes at EYA Capitol Quarter townhouses were located in the grassy area between
Virginia Avenue, SE and side walk. The first probe was at 40 feet from the edge of track and the
second one at 73 feet which was the same distance as the closest building to the edge of track,
but still in public space.
The two outside measurement locations near Marine Building were located at 61 and 127 feet
distances from the edge of the track. The probe at 127 feet was next to the closest point of the
building to the track. The third probe was located inside a closet across the hallway from the
Band Practice Hall. This location was chosen instead of a location inside Band Practice Hall to
avoid interference from the vibration levels created by the activities in the Marine Band Practice
Hall. Figures 1 through 3 in Appendix A shows the measurement locations.
Vibration levels at each location were measured for at least five train pass by on May 22nd, 2012.
During each measurement, speed of the train was recorded near the east portal using a radar
gun and numbers of the locomotives as well as number of the cars were recorded for each train.
Three measurement probes were left overnight at the Marine Band Practice Hall location due to
the access issues. Four additional train pass by were also recorded by these three probes until
they were pickup on morning of May 23rd, 2012.
Baseline vibration levels without any trains present were also recorded at each measurement
site. The locations of the measurements are shown in Figures 1 through 3 in Appendix A and
the train pass by vibration measurements results are listed in Table 4‐1 for site locations along
with the time of the train pass by, the speed of the train, and the number of cars. Table 4‐2
contains the baseline vibration data collected just before and after each train pass by during the
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 10
day at each site. Table 4‐3 contains the baseline and train pass by vibration data collected
overnight at the Marine Band Practice Hall.
These measurements establish the basis to predict vibration levels at the study area using FTA
procedures and to determine the soil propagation characteristics that were used to assess
potential building damage and human annoyance impacts based on FTA procedures and
guidelines.
The soil vibration propagation characteristic was calculated by comparing the PPV at different
distances from the track. The East Portal Site was the most suitable location within the project
area to measure the train tunnel pass bys within 20 feet of the track which is crucial in order to
calculate the soil propagation characteristic. The vibration wave from the train pass by
dissipates as the wave transfers through the soil between two distances. This dissipation rate is
dependent on the local soil composition and is called the soil factor in this report. The soil
factors at the East Portal vibration measurement site were calculated using recorded vibration
levels at 30 second intervals for each train pass by event. These values were then averaged to
calculate the soil factor for the surrounding area of the project and are shown in Table 4‐4.
The vertical‐axis results were used for this analysis as recommended in the FTA manual (FTA,
2006) because the vertical vibration is usually transmitted more efficiently into building
foundations than transverse or longitudinal vibration. This can clearly be seen in Figures 4‐1
through 4‐3 for Site 7 and Site 6. The PPV measurements for all of the axes at Site 7, the site
closest to the train pass by, are comparable, where as longitudinal and transverse measurements
levels at Site 6 are much lower than the vertical measurement level which demonstrates that the
vertical waves are being transmitted more efficiently than the other waves from the train pass
by.
The overnight vibration measurements revealed that the building’s HVAC system had notable
affect on the vertical vibration measurements as shown in Figure 4‐4. Between 21:45 and 04:30
baseline measurements at Site 3 are much lower than baseline measurements outside this time
range when apparently HVAC system was off.
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 11
Table 4‐1. Existing Train Pass‐by Vibration Measurements
Site 7 Site 6 Site 5 Site 4 Site 3 Site 2 Site 1
19 ft from edge of track 74 ft from edge of track 61 ft from edge of track 127 ft from edge of track 147 ft from edge of track 40 ft from edge of track 73 ft from edge of track
Long. Trans. Vert. Long. Trans. Vert. Long. Trans. Vert. Long. Trans. Vert. Long. Trans. Vert. Long. Trans. Vert. Long. Trans. Vert.
11:44:00 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.010
11:44:30 0.005 0.005 0.005 0.005 0.005 0.005 0.008 0.008 0.005 0.008 0.005 0.005 0.005 0.005 0.015 0.005 0.005 0.005 0.005 0.005 0.008
11:45:00 0.088 0.053 0.083 0.018 0.020 0.050 0.013 0.010 0.013 0.005 0.005 0.005 0.005 0.005 0.013 0.008 0.008 0.013 0.010 0.008 0.010
11:45:30 0.053 0.040 0.048 0.013 0.013 0.025 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.008 0.005 0.010
11:46:00 0.038 0.035 0.043 0.010 0.010 0.023 0.008 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.008 0.005 0.005 0.008
11:46:30 0.050 0.030 0.048 0.013 0.013 0.023 0.008 0.008 0.008 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.008 0.005 0.005 0.008
11:47:00 0.075 0.038 0.065 0.013 0.013 0.030 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.008 0.008 0.005 0.008
11:47:30 0.038 0.030 0.050 0.010 0.010 0.023 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.015 0.005 0.005 0.005 0.005 0.005 0.008
11:48:00 0.048 0.028 0.068 0.010 0.013 0.028 0.005 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.008 0.005 0.005 0.008
11:48:30 0.053 0.033 0.053 0.010 0.013 0.030 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.015 0.005 0.005 0.008 0.008 0.005 0.008
11:49:00 0.038 0.033 0.055 0.008 0.010 0.020 0.003 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.010
11:49:30 0.005 0.005 0.005 0.005 0.005 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.003 0.005 0.005 0.005 0.005 0.008
11:50:00 0.005 0.005 0.008 0.005 0.005 0.008 0.008 0.008 0.008 0.005 0.005 0.005 0.005 0.005 0.015 0.005 0.005 0.005 0.005 0.005 0.008
12:39:00 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.018 0.005 0.005 0.005 0.005 0.005 0.008
12:39:30 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.018 0.005 0.005 0.005 0.005 0.005 0.008
12:40:00 0.053 0.050 0.065 0.018 0.018 0.030 0.005 0.005 0.005 0.005 0.005 0.008 0.005 0.005 0.015 0.005 0.008 0.013 0.008 0.008 0.010
12:40:30 0.043 0.033 0.050 0.013 0.013 0.028 0.008 0.008 0.010 0.005 0.005 0.008 0.005 0.005 0.015 0.008 0.008 0.015 0.008 0.005 0.013
12:41:00 0.038 0.028 0.058 0.010 0.010 0.023 0.008 0.008 0.010 0.008 0.005 0.008 0.005 0.005 0.013 0.008 0.008 0.013 0.008 0.008 0.010
12:41:30 0.040 0.023 0.075 0.018 0.013 0.028 0.008 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.013 0.008 0.005 0.013 0.008 0.005 0.010
12:42:00 0.055 0.035 0.058 0.010 0.013 0.023 0.008 0.008 0.010 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
12:42:30 0.015 0.020 0.015 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
12:43:00 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.010
12:43:30 0.005 0.005 0.005 0.005 0.005 0.005 0.003 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.015 0.003 0.005 0.005 0.005 0.005 0.008
ppv, (in/sec) ppv, (in/sec) ppv, (in/sec) ppv, (in/sec)
Near 3rd StreetNear East Portal Marine Band Practice Hall
Vibration
Source Time
ppv, (in/sec)
Train with
120 Cars
traveling at
19 mph
Train with 70
Cars traveling
at 12 mph
ppv, (in/sec) ppv, (in/sec)
Note:
Red text denotes that the measured train pass by data is greater than the baseline vibration levels
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 12
Table 4‐1. Existing Train Pass‐by Vibration Measurements (Cont.)
Site 7 Site 6 Site 5 Site 4 Site 3 Site 2 Site 1
19 ft from edge of track 74 ft from edge of track 61 ft from edge of track 127 ft from edge of track 147 ft from edge of track 40 ft from edge of track 73 ft from edge of track
Long. Trans. Vert. Long. Trans. Vert. Long. Trans. Vert. Long. Trans. Vert. Long. Trans. Vert. Long. Trans. Vert. Long. Trans. Vert.
13:46:30 0.005 0.005 0.005 0.005 0.005 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
13:47:00 0.005 0.005 0.008 0.005 0.005 0.005 0.003 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.015 0.005 0.005 0.005 0.005 0.005 0.008
13:47:30 0.080 0.040 0.070 0.015 0.015 0.048 0.005 0.008 0.008 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
13:48:00 0.050 0.030 0.063 0.010 0.010 0.030 0.013 0.010 0.010 0.005 0.005 0.005 0.005 0.005 0.013 0.003 0.005 0.005 0.005 0.005 0.008
13:48:30 0.050 0.025 0.065 0.013 0.010 0.028 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.003 0.005 0.005 0.005 0.005 0.008
13:49:00 0.053 0.033 0.063 0.015 0.013 0.028 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
13:49:30 0.060 0.038 0.083 0.013 0.010 0.023 0.008 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
13:50:00 0.055 0.025 0.065 0.010 0.010 0.025 0.005 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
13:50:30 0.070 0.025 0.050 0.013 0.010 0.028 0.005 0.008 0.008 0.005 0.005 0.003 0.005 0.005 0.015 0.005 0.005 0.005 0.005 0.005 0.008
13:51:00 0.058 0.033 0.060 0.018 0.013 0.030 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.008 0.005 0.008
13:51:30 0.063 0.033 0.055 0.015 0.013 0.030 0.005 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.010 0.010 0.005 0.008
13:52:00 0.063 0.033 0.055 0.013 0.013 0.025 0.008 0.005 0.010 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.010
13:52:30 0.043 0.020 0.040 0.005 0.005 0.005 0.008 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.008 0.005 0.005 0.008
13:53:00 0.005 0.005 0.008 0.005 0.005 0.005 0.005 0.003 0.003 0.005 0.005 0.005 0.005 0.005 0.013 0.008 0.008 0.008 0.008 0.008 0.010
13:53:30 0.005 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.015 0.005 0.005 0.005 0.010 0.008 0.008
13:59:30 0.005 0.005 0.008 0.005 0.005 0.005 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.015 0.005 0.005 0.008 0.005 0.005 0.008
14:00:00 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.008 0.008 0.005 0.008
14:00:30 0.063 0.050 0.088 0.015 0.018 0.050 0.013 0.010 0.013 0.008 0.005 0.008 0.005 0.005 0.013 0.008 0.008 0.010 0.005 0.005 0.010
14:01:00 0.040 0.045 0.033 0.010 0.013 0.028 0.008 0.005 0.010 0.008 0.005 0.005 0.005 0.005 0.015 0.008 0.008 0.015 0.008 0.005 0.010
14:01:30 0.048 0.043 0.050 0.013 0.015 0.030 0.008 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.015 0.005 0.005 0.005 0.008 0.005 0.008
14:02:00 0.038 0.030 0.070 0.013 0.013 0.035 0.008 0.005 0.010 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
14:02:30 0.033 0.023 0.035 0.005 0.008 0.015 0.008 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
14:03:00 0.005 0.005 0.005 0.005 0.005 0.005 0.003 0.005 0.005 0.005 0.005 0.003 0.005 0.005 0.015 0.003 0.005 0.005 0.005 0.005 0.010
14:03:30 0.005 0.005 0.005 0.005 0.005 0.005 0.003 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.005
14:15:00 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.015 0.005 0.005 0.005 0.005 0.005 0.008
14:15:30 0.013 0.018 0.010 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.010 0.008 0.010
14:16:00 0.068 0.063 0.080 0.015 0.020 0.043 0.015 0.015 0.015 0.005 0.005 0.005 0.005 0.005 0.013 0.008 0.008 0.013 0.008 0.008 0.013
14:16:30 0.035 0.028 0.038 0.013 0.013 0.033 0.010 0.008 0.010 0.005 0.005 0.008 0.005 0.005 0.010 0.005 0.005 0.010 0.005 0.005 0.010
14:17:00 0.023 0.018 0.025 0.013 0.010 0.030 0.008 0.008 0.008 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.008 0.005 0.005 0.008
14:17:30 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.015 0.003 0.005 0.005 0.005 0.005 0.008
14:18:00 0.003 0.005 0.005 0.005 0.005 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.015 0.005 0.005 0.005 0.005 0.005 0.008
ppv, (in/sec) ppv, (in/sec) ppv, (in/sec) ppv, (in/sec)
Near 3rd StreetNear East Portal Marine Band Practice Hall
Vibration
Source Time
Train with 28
Cars traveling
at 20 mph
ppv, (in/sec)
Train with
143 Cars
traveling at
14 mph
Train with 47
Cars traveling
at 20 mph
ppv, (in/sec) ppv, (in/sec)
Note:
Red text denotes that the measured train pass by data is greater than the baseline vibration levels
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 13
Table 4‐2. Existing Baseline Vibration Measurements
Site 7 Site 6 Site 5 Site 4 Site 3 Site 2 Site 1
19 ft from edge of track 74 ft from edge of track 61 ft from edge of track 127 ft from edge of track 147 ft from edge of track 40 ft from edge of track 73 ft from edge of track
Long. Trans. Vert. Long. Trans. Vert. Long. Trans. Vert. Long. Trans. Vert. Long. Trans. Vert. Long. Trans. Vert. Long. Trans. Vert.
11:42:00 0.005 0.005 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.015 0.003 0.005 0.005 0.005 0.005 0.010
11:42:30 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.010
11:43:00 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.010
11:43:30 0.005 0.005 0.008 0.005 0.005 0.005 0.003 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
11:44:00 0.005 0.005 0.005 0.005 0.005 0.005 0.003 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.003 0.005 0.005 0.005 0.005 0.010
11:44:30 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
11:49:30 0.005 0.005 0.005 0.005 0.005 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.015 0.005 0.005 0.005 0.005 0.005 0.008
11:50:00 0.005 0.005 0.008 0.005 0.005 0.008 0.008 0.008 0.008 0.005 0.005 0.005 0.005 0.005 0.013 0.003 0.005 0.005 0.005 0.005 0.008
11:50:30 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
11:51:00 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.015 0.005 0.005 0.005 0.005 0.005 0.005
11:51:30 0.005 0.008 0.008 0.005 0.005 0.008 0.005 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.008 0.005 0.005 0.008
11:52:00 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.003 0.005 0.003 0.005 0.005 0.008
12:37:00 0.005 0.005 0.008 0.005 0.005 0.005 0.005 0.008 0.008 0.005 0.005 0.005 0.005 0.005 0.015 0.005 0.005 0.005 0.005 0.005 0.010
12:37:30 0.005 0.005 0.008 0.005 0.005 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.015 0.005 0.005 0.005 0.005 0.005 0.008
12:38:00 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
12:38:30 0.005 0.005 0.005 0.005 0.005 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.010
12:39:00 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.015 0.005 0.005 0.005 0.005 0.005 0.008
12:39:30 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.018 0.005 0.005 0.005 0.005 0.005 0.008
12:42:30 0.015 0.020 0.015 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
12:43:00 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.003 0.005 0.005 0.005 0.005 0.008
12:43:30 0.005 0.005 0.005 0.005 0.005 0.005 0.003 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.010
12:44:00 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.015 0.005 0.005 0.005 0.005 0.005 0.008
12:44:30 0.005 0.005 0.005 0.005 0.008 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
12:45:00 0.005 0.008 0.005 0.005 0.005 0.008 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
13:44:30 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.008 0.008 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.010
13:45:00 0.005 0.008 0.008 0.005 0.005 0.005 0.013 0.010 0.010 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
13:45:30 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
13:46:00 0.005 0.008 0.008 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.008 0.008 0.005 0.005 0.008
13:46:30 0.005 0.005 0.005 0.005 0.005 0.005 0.008 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.008 0.005 0.005 0.008
13:47:00 0.005 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.008 0.008 0.005 0.008
13:53:00 0.005 0.005 0.008 0.005 0.005 0.005 0.008 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
13:53:30 0.005 0.005 0.008 0.005 0.005 0.005 0.005 0.003 0.003 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.010
13:54:00 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.015 0.005 0.005 0.005 0.005 0.005 0.005
13:54:30 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.008 0.005 0.005 0.005 0.003 0.005 0.005 0.015 0.005 0.005 0.005 0.005 0.005 0.010
13:55:00 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.003 0.005 0.005 0.018 0.005 0.005 0.005 0.005 0.005 0.010
13:55:30 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
Vibration
Source Time
ppv, (in/sec)
Baseline
vibration
level before
and after the
11:45 train
pass by event
Baseline
vibration
level before
and after the
12:40 train
pass by event
Baseline
vibration
level before
and after the
13:48 train
pass by event
ppv, (in/sec) ppv, (in/sec)ppv, (in/sec) ppv, (in/sec) ppv, (in/sec) ppv, (in/sec)
Near 3rd StreetNear East Portal Marine Band Practice Hall
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 14
Table 4‐2. Existing Baseline Vibration Measurements (Cont)
Site 7 Site 6 Site 5 Site 4 Site 3 Site 2 Site 1
19 ft from edge of track 74 ft from edge of track 61 ft from edge of track 127 ft from edge of track 147 ft from edge of track 40 ft from edge of track 73 ft from edge of track
Long. Trans. Vert. Long. Trans. Vert. Long. Trans. Vert. Long. Trans. Vert. Long. Trans. Vert. Long. Trans. Vert. Long. Trans. Vert.
13:57:30 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.010
13:58:00 0.005 0.005 0.005 0.005 0.005 0.005 0.003 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.020 0.005 0.005 0.005 0.005 0.005 0.008
13:58:30 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
13:59:00 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.008 0.008 0.005 0.005 0.008
13:59:30 0.005 0.005 0.008 0.005 0.005 0.005 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.015 0.005 0.005 0.008 0.005 0.005 0.008
14:00:00 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.008 0.008 0.005 0.008
14:03:00 0.005 0.005 0.005 0.005 0.005 0.005 0.008 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.015 0.005 0.005 0.005 0.008 0.005 0.008
14:03:30 0.005 0.005 0.005 0.005 0.005 0.005 0.003 0.005 0.005 0.005 0.005 0.003 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
14:04:00 0.005 0.005 0.008 0.005 0.005 0.008 0.003 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
14:04:30 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.003 0.005 0.005 0.005 0.005 0.010
14:05:00 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.005
14:05:30 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
14:13:00 0.005 0.005 0.005 0.005 0.005 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.015 0.003 0.005 0.005 0.005 0.005 0.008
14:13:30 0.005 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.010 0.003 0.005 0.005 0.005 0.005 0.008
14:14:00 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.003 0.005 0.005 0.005 0.005 0.008
14:14:30 0.005 0.008 0.005 0.005 0.005 0.008 0.005 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.013 0.003 0.005 0.005 0.005 0.005 0.010
14:15:00 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
14:15:30 0.013 0.018 0.010 0.005 0.005 0.005 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.010 0.008 0.010
14:17:30 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.003 0.005 0.005 0.005 0.005 0.008
14:18:00 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.015 0.005 0.005 0.005 0.005 0.005 0.008
14:18:30 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.003 0.005 0.005 0.005 0.005 0.008
14:19:00 0.005 0.008 0.008 0.005 0.005 0.005 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.010
14:19:30 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.003 0.005 0.005 0.005 0.005 0.008
14:20:00 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
Vibration
Source Time
Baseline
vibration
level before
and after the
14:16 train
pass by event
ppv, (in/sec)
Baseline
vibration
level before
and after the
14:00 train
pass by event
ppv, (in/sec) ppv, (in/sec)ppv, (in/sec) ppv, (in/sec) ppv, (in/sec) ppv, (in/sec)
Near 3rd StreetNear East Portal Marine Band Practice Hall
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 15
Table 4‐3. Existing Nighttime Baseline and Train Pass‐by Vibration Measurements
Site 5 Site 4 Site 3
Long. Trans. Vert. Long. Trans. Vert. Long. Trans Vert.
22:22:00 0.008 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.018
22:22:30 0.015 0.010 0.010 0.008 0.005 0.008 0.005 0.003 0.010
22:23:00 0.015 0.015 0.015 0.008 0.005 0.008 0.005 0.005 0.010
22:23:30 0.008 0.008 0.010 0.005 0.005 0.005 0.005 0.005 0.010
22:24:00 0.010 0.008 0.013 0.005 0.005 0.005 0.005 0.005 0.008
22:24:30 0.010 0.005 0.013 0.005 0.005 0.005 0.005 0.005 0.008
22:25:00 0.008 0.008 0.008 0.005 0.005 0.005 0.005 0.005 0.008
22:25:30 0.008 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.008
22:26:00 0.008 0.008 0.008 0.005 0.005 0.005 0.005 0.005 0.008
22:26:30 0.008 0.008 0.008 0.005 0.005 0.003 0.003 0.005 0.008
22:27:00 0.005 0.003 0.005 0.005 0.005 0.005 0.005 0.005 0.008
22:27:30 0.003 0.003 0.003 0.005 0.005 0.003 0.005 0.005 0.008
00:15:30 0.003 0.003 0.003 0.005 0.005 0.003 0.005 0.005 0.008
00:16:00 0.003 0.003 0.005 0.005 0.005 0.003 0.005 0.005 0.008
00:16:30 0.010 0.008 0.010 0.005 0.005 0.003 0.005 0.005 0.008
00:17:00 0.008 0.010 0.010 0.005 0.005 0.003 0.005 0.005 0.010
00:17:30 0.008 0.008 0.008 0.005 0.005 0.003 0.005 0.005 0.010
00:18:00 0.010 0.008 0.010 0.005 0.005 0.005 0.005 0.005 0.010
00:18:30 0.005 0.003 0.003 0.005 0.005 0.005 0.005 0.003 0.008
00:19:00 0.003 0.003 0.005 0.005 0.005 0.005 0.003 0.005 0.008
00:19:30 0.003 0.003 0.005 0.008 0.005 0.005 0.005 0.005 0.008
02:21:30 0.003 0.003 0.005 0.005 0.005 0.003 0.005 0.005 0.008
02:22:00 0.003 0.003 0.005 0.005 0.005 0.003 0.005 0.005 0.008
02:22:30 0.015 0.013 0.013 0.005 0.005 0.005 0.005 0.005 0.010
02:23:00 0.008 0.005 0.010 0.005 0.005 0.003 0.005 0.005 0.010
02:23:30 0.010 0.008 0.010 0.005 0.005 0.005 0.005 0.005 0.008
02:24:00 0.008 0.005 0.008 0.005 0.005 0.005 0.005 0.005 0.010
02:24:30 0.008 0.005 0.010 0.005 0.005 0.008 0.005 0.005 0.010
02:25:00 0.008 0.005 0.010 0.005 0.005 0.005 0.005 0.005 0.008
02:25:30 0.008 0.008 0.010 0.005 0.005 0.005 0.005 0.005 0.013
02:26:00 0.008 0.008 0.010 0.005 0.005 0.005 0.005 0.005 0.013
02:26:30 0.010 0.008 0.010 0.005 0.005 0.005 0.005 0.005 0.018
02:27:00 0.008 0.008 0.013 0.008 0.005 0.008 0.005 0.005 0.020
02:27:30 0.008 0.005 0.010 0.005 0.005 0.008 0.005 0.005 0.020
02:28:00 0.008 0.005 0.008 0.008 0.005 0.008 0.005 0.005 0.008
02:28:30 0.003 0.003 0.005 0.008 0.005 0.008 0.005 0.005 0.008
03:50:30 0.003 0.003 0.003 0.005 0.005 0.003 0.005 0.005 0.008
03:51:00 0.005 0.005 0.005 0.005 0.005 0.003 0.005 0.005 0.008
03:51:30 0.010 0.010 0.013 0.005 0.005 0.003 0.005 0.005 0.013
03:52:00 0.010 0.013 0.013 0.005 0.005 0.003 0.005 0.005 0.015
03:52:30 0.008 0.008 0.010 0.005 0.005 0.005 0.005 0.005 0.018
03:53:00 0.005 0.005 0.010 0.005 0.005 0.008 0.005 0.005 0.015
03:53:30 0.010 0.008 0.010 0.008 0.005 0.008 0.005 0.005 0.015
03:54:00 0.010 0.008 0.013 0.005 0.005 0.008 0.005 0.005 0.013
03:54:30 0.010 0.008 0.010 0.005 0.005 0.008 0.005 0.005 0.015
03:55:00 0.003 0.003 0.003 0.005 0.005 0.008 0.005 0.005 0.010
03:55:30 0.003 0.003 0.003 0.005 0.005 0.008 0.005 0.005 0.008
Train
Time
Train,
Speed and
number of
cars
unknown
Train,
Speed and
number of
cars
unknown
Train,
Speed and
number of
cars
unknown
Train,
Speed and
number of
cars
unknown
Marine Band Practice Hall
ppv, (in/sec) ppv, (in/sec) ppv, (in/sec)
Vibration
Source
Note:
Red text denotes that the measured train pass by data is greater than the baseline vibration
levels
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 16
Figure 4-1. Existing Train Pass-by Longitudinal Vibration Measurements
0.000
0.010
0.020
0.030
0.040
0.050
0.060
0.070
0.080
0.090
0.100
Site 7
Site 6
Site 5
Site 4
Site 3
Site 2
Site 1
Long. Vibration
PPV( in/sec)
Time
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 17
Figure 4-2. Existing Train Pass-by Transverse Vibration Measurements
0.000
0.010
0.020
0.030
0.040
0.050
0.060
0.070
0.080
0.090
0.100
Site 7
Site 6
Site 5
Site 4
Site 3
Site 2
Site 1
Trans. Vibration
Time
PPV( in/sec)
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 18
Figure 4-3. Existing Train Pass-by Vertical Vibration Measurements
0.000
0.010
0.020
0.030
0.040
0.050
0.060
0.070
0.080
0.090
0.100
Site 7
Site 6
Site 5
Site 4
Site 3
Site 2
Site 1
Trans. Vibration
Time
PPV( in/sec)
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 19
0.000
0.010
0.020
0.030
0.040
0.050
0.060
0.070
0.080
18:00:00
18:19:30
18:39:00
18:58:30
19:18:00
19:37:30
19:57:00
20:16:30
20:36:00
20:55:30
21:15:00
21:34:30
21:54:00
22:13:30
22:33:00
22:52:30
23:12:00
23:31:30
23:51:00
00:10:30
00:30:00
00:49:30
01:09:00
01:28:30
01:48:00
02:07:30
02:27:00
02:46:30
03:06:00
03:25:30
03:45:00
04:04:30
04:24:00
04:43:30
05:03:00
05:22:30
05:42:00
06:01:30
06:21:00
06:40:30
07:00:00
07:19:30
07:39:00
07:58:30
Site 3
Site 4
Site 5
Vert. Vibration
PPV( in/sec)
Time
Figure 4-4. Existing Night Time Train Pass-by Vertical Vibration Measurements
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 20
Table 4‐4. Soil Factor Derived from Existing Train Pass By Measurements
at the East Portal
RMS VdB1
PPV
(in/sec)
RMS
VdB1
PPV
(in/sec)
11:45:00 86 0.083 82 0.050 0.372762
11:45:30 82 0.048 76 0.025 0.479783
11:46:00 81 0.043 75 0.023 0.460204
11:46:30 82 0.048 75 0.023 0.54111
11:47:00 84 0.065 78 0.030 0.568678
11:47:30 82 0.050 75 0.023 0.571134
11:48:00 85 0.068 77 0.028 0.652608
11:48:30 82 0.053 78 0.030 0.418567
11:49:00 83 0.055 74 0.020 0.744029
12:40:00 84 0.065 78 0.030 0.568678
12:40:30 82 0.050 77 0.028 0.426454
12:41:00 83 0.058 75 0.023 0.680296
12:41:30 85 0.075 77 0.028 0.724672
12:42:00 83 0.058 75 0.023 0.680296
13:47:30 85 0.070 82 0.048 0.277499
13:48:00 84 0.063 78 0.030 0.545692
13:48:30 84 0.065 77 0.028 0.619422
13:49:00 84 0.063 77 0.028 0.596436
13:50:00 84 0.065 76 0.025 0.702775
13:50:30 82 0.050 77 0.028 0.426454
13:51:00 84 0.060 78 0.030 0.509807
13:51:30 83 0.055 78 0.030 0.445811
13:52:00 83 0.055 76 0.025 0.579907
14:00:30 87 0.088 82 0.050 0.415786
14:01:30 82 0.050 78 0.030 0.37571
14:02:00 85 0.070 79 0.035 0.509807
14:02:30 79 0.035 71 0.015 0.623184
14:16:00 86 0.080 81 0.043 0.456616
Avg. 84 0.060 77 0.030 0.522996
Soil
FactorTime Vert Vert.
Peak Measurements
Site 7 (Near) Site 6 (Far)
Note:
1 ‐ Levels in VdB (re: 10‐6 in/sec.)
Vibration Analysis Report 21
5 IMPACT ASSESSMENT
Construction of the Virginia Avenue Tunnel could potentially cause vibration impacts on
nearby building from construction and operation activities. The impact assessment and results
are presented in this section.
Construction related vibration predictions are preliminary because detailed construction
activities for various phase are not available yet. Construction vibration levels will be
recalculated during the final design when more details about construction activities become
available. Train pass by vibration levels may also need to be finalized if there are changes to the
project design that could affect the vibration levels.
5.1 CONSTRUCTION VIBRATION Two types of potential construction vibration impacts were analyzed: (1) human annoyance and
(2) building damage. The potential for human annoyance occurs when construction vibration
rises significantly above the threshold of human perception for extended periods of time.
Building damage can be cosmetic or structural. As a general matter, fragile buildings such as
historical structures have a greater potential to be susceptible to damage from ground vibration
than buildings that are not particularly fragile.
Vibration levels produced by construction equipment were obtained from the FTA Transit Noise
and Vibration Impact Assessment (FTA, 2006). Based on the typical vibration levels listed in Table
5‐1, calculations were performed to determine the distances at which vibration impacts would
occur according to the criteria discussed in Section 3.2. Table 5‐2 shows the results of those
calculations. The distances shown in Table 5‐2 are the maximum distances at which short‐term
construction vibration impacts may occur. Mitigation measures would need to be considered if
construction equipment were to operate closer to residential or institutional buildings than the
distances shown in Table 5‐2. However, using the distance information in Table 5‐2 as well as
knowing that the closest building to the alignment edge of track is 44 feet, as shown in Figures 1
through 3 in Appendix A, and that the two strongest construction vibration sources (sheet
driver and vibratory compactor operations), there should be no structural vibration impacts due
to construction operations under any of the alternatives. But there still remains the potential for
human annoyance impacts due to construction operation.
Table 5‐3 shows predicted vibration levels at nearby sensitive receivers from some of the major
construction equipment items that would create high vibration levels. In accordance to the
results presented in Table 5‐3, it is anticipated that certain major vibration producing
construction activities would cause annoyance to the closest units of Capitol Quarter
Townhouses and Capper Senior Building as well as occupancies of other close by buildings.
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 22
Table 5‐1. Ground‐Born Vibration Source Levels for Construction Equipment
Equipment PPV at 25 feet (in/sec)
Large bulldozer 0.089
Loaded trucks 0.076
Hoe Ram 0.089
Caisson drilling 0.089
Vibratory compactor/roller 0.210
Sheet Driver (Sonic) 0.170
Jackhammer 0.035
Source: FTA, 2006
Table 5‐2. Construction Equipment Vibration Impact Distances
Equipment
Distance to Potential Vibration Building
Damage1 feet
Distance to Potential Vibration Human
Annoyance2 feet
Large bulldozer 21 38
Dump trucks 20 35
Hoe Ram 21 38
Caisson drilling 21 38
Vibratory compactor/roller 33 59
Sheet Driver (Sonic) 30 53
Jackhammer 13 23
Notes: 1. This is the distance at which the PPV is 0.20 inch/sec or less. 2. This is the distance at which the PPV is 0.04 inch/sec or less at the inside of the building structure.
Source: FTA
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 23
Table 5‐3. Highest Construction Equipment Vibration Levels
Equipment
PPV (in/sec)
Capitol Quarter Townhouses and Capper Senior
Building (closest units)
St. Paul African Union Methodist
Church
Marine Band Practice Hall
Large bulldozer 0.036 0.004 0.010
Dump trucks 0.031 0.003 0.008
Hoe Ram 0.036 0.004 0.010
Caisson drilling 0.024 0.003 0.008
Vibratory compactor/roller 0.086 0.008 0.023
Sheet Driver (Sonic) 0.045 0.006 0.015
Jackhammer 0.014 0.001 0.004
Note: PPV are for single equipment but if more than one equipment is operating at the same time, PPV would be higher.
Base on the preliminary calculations and available project information; there would not be
construction vibration related building damages (e.g., plaster cracks) from individual
equipment items because there would not be buildings within the distances identified in Table
5‐2. However, this distance can vary depending on the soil composition and underground
geological layer between vibration source and receiver. In addition, not all buildings respond
similarly to vibration generated by construction equipment. Preliminary predictions presented
in Table 5‐3 indicate that certain construction activities could cause annoyance at the nearby
buildings.
Because detailed construction activities and types of equipment that will be utilized for each
phase are not available at this time, overall vibration levels from each construction phase cannot
be predicted. Once detailed construction schedule for various phases of the construction is
developed during the final design, the predicted vibration levels need to be confirmed and
expanded as needed.
Vibration from the train pass‐bys in the trench during the construction period for Alternative 2
was also considered.
5.2 POST-CONSTRUCTION OPERATION VIBRATION Train operational vibration assessment was conducted using the FTA procedures and impact
criteria along with the measured data at nearby vibration sensitive sites within the project area.
The three final design Alternatives include using one tunnel with two tracks or using two
tunnels with one track in each tunnel.
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 24
Vibration levels associated with train pass bys were calculated using four parameters: the
distance between the receptor and the edge of track recorded vibration measurements as the
vibration source reference for the train, soil factor calculated from the train pass by
measurements, and an adjustment factor to account for the train passing through the tunnel.
The distance between vibration sensitive receptors and the new track alignments were obtain
from the concept design files. The measured vibration levels from Site 7, the closest site to the
tracks, were used as the train source for calculating impact distances for the existing/ no build,
temporary trench route for Alternative 2, and the three future build alternatives. In the case of
temporary trench alternative and the three future design concepts, the highest recorded
vibration level was used as the train source to ensure that future impacts distances were not
under predicted; furthermore, the train source was doubled to take in account that two trains
can use the new tunnel simultaneously.
The soil factor calculated in Section 4 was used as a parameter to adjust the rate that the
vibration wave would decline in strength as it propagates away from the train. Also, the
vibration waves generated by a train moving along at grade rail travel more effectively along
the ground surface than when a train is moving through a tunnel. Because vibration waves do
not propagated as effectively from tunnel to the surface, the calculated impact distances must
include a tunnel adjustment factor. Table 5‐4 shows this factor for various pass by and the
averaged value which was used for calculating impact distances.
After all four parameters were taken into account; the distances to vibration impact were
calculated. These impact distances for building damage and human annoyance due to the
existing and future alternatives are shown Table 5‐5. As indicated in Table 5‐5, any structures
greater than 20 feet away from the edge of track would not have significant operational
vibration impacts and human annoyance impacts would not occur at more than 36 feet away
from the edge of track even when there are two trains using one tunnel with two tracks or using
two tunnels with one track in each tunnel at the same time.
Using the distance information in Table 5‐5 and knowing the closest building to the alignment
edge of track is 44 feet as shown in Figures 1 through 3 in Appendix A; therefore, there should
be no vibration impacts due to train operations under any of the alternatives.
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 25
Site 5 Site 4 Site 2
61 ft from nearest track 127 ft from nearest track 40 ft from nearest track 73 ft from nearest track
Meas Calc. Diff. Meas Calc. Diff. Meas Calc. Diff. Meas Calc. Diff.
11:45:00 0.013 0.054 0.041 0.005 0.041 0.036 0.013 0.063 0.050 0.01 0.050 0.040
11:45:30 0.005 0.027 0.022 0.005 0.019 0.014 0.005 0.034 0.029 0.01 0.025 0.015
11:46:00 0.005 0.025 0.020 0.005 0.018 0.013 0.008 0.031 0.023 0.008 0.023 0.015
11:46:30 0.008 0.026 0.018 0.005 0.017 0.012 0.008 0.032 0.024 0.008 0.023 0.015
11:47:00 0.005 0.033 0.028 0.005 0.022 0.017 0.008 0.043 0.035 0.008 0.030 0.022
11:47:30 0.005 0.026 0.021 0.005 0.017 0.012 0.005 0.033 0.028 0.008 0.023 0.015
11:48:00 0.008 0.032 0.024 0.005 0.020 0.015 0.008 0.042 0.034 0.008 0.028 0.020
11:48:30 0.005 0.033 0.028 0.005 0.024 0.019 0.008 0.039 0.031 0.008 0.030 0.022
11:49:00 0.003 0.023 0.020 0.005 0.013 0.008 0.005 0.032 0.027 0.01 0.020 0.010
12:40:00 0.005 0.033 0.028 0.005 0.022 0.017 0.013 0.043 0.030 0.01 0.030 0.020
12:40:30 0.01 0.030 0.020 0.005 0.022 0.017 0.015 0.036 0.021 0.013 0.028 0.015
12:41:00 0.01 0.026 0.016 0.008 0.016 0.008 0.013 0.035 0.022 0.01 0.023 0.013
12:41:30 0.008 0.032 0.024 0.005 0.019 0.014 0.013 0.044 0.031 0.01 0.028 0.018
12:42:00 0.01 0.026 0.016 0.005 0.016 0.011 0.005 0.035 0.030 0.008 0.023 0.015
13:47:30 0.008 0.051 0.043 0.005 0.041 0.036 0.005 0.057 0.052 0.008 0.048 0.040
13:48:00 0.01 0.033 0.023 0.005 0.022 0.017 0.005 0.042 0.037 0.008 0.030 0.022
13:48:30 0.005 0.032 0.027 0.005 0.020 0.015 0.005 0.041 0.036 0.008 0.028 0.020
13:49:00 0.005 0.031 0.026 0.005 0.020 0.015 0.005 0.040 0.035 0.008 0.028 0.020
13:50:00 0.008 0.029 0.021 0.005 0.017 0.012 0.005 0.039 0.034 0.008 0.025 0.017
13:50:30 0.008 0.030 0.022 0.005 0.022 0.017 0.005 0.036 0.031 0.008 0.028 0.020
13:51:00 0.005 0.033 0.028 0.005 0.023 0.018 0.005 0.041 0.036 0.008 0.030 0.022
13:51:30 0.008 0.033 0.025 0.005 0.024 0.019 0.01 0.039 0.029 0.008 0.030 0.022
13:52:00 0.01 0.028 0.018 0.005 0.018 0.013 0.005 0.036 0.031 0.01 0.025 0.015
14:00:30 0.013 0.054 0.041 0.008 0.040 0.032 0.01 0.065 0.055 0.01 0.050 0.040
14:01:30 0.008 0.032 0.024 0.005 0.024 0.019 0.005 0.038 0.033 0.008 0.030 0.022
14:02:00 0.01 0.039 0.029 0.005 0.027 0.022 0.005 0.048 0.043 0.008 0.035 0.027
14:02:30 0.008 0.017 0.009 0.005 0.011 0.006 0.005 0.022 0.017 0.008 0.015 0.007
Train with 28
Cars traveling at
20 mph
14:16:00 0.015 0.047 0.032 0.005 0.034 0.029 0.013 0.057 0.044 0.013 0.043 0.030
0.008 0.033 0.025 0.005 0.022 0.017 0.008 0.041 0.033 0.009 0.030 0.021Average
Near 3rd Street
ppv, (in/sec) ppv, (in/sec)
Marine Band Practice Hall
Site 1
Vibration Source Time
ppv, (in/sec)
Train with 120
Cars traveling at
19 mph
Train with 70
Cars traveling at
12 mph
Train with 143
Cars traveling at
14 mph
Train with 47
Cars traveling at
20 mph
ppv, (in/sec)
Table 5‐4. Measured Vibrations Levels verses Calculated Vibrations for Building Sites near the Tunnel
Virginia Avenue Tunnel Reconstruction Project
Vibration Analysis Report 26
Table 5‐5. Impact Distances for existing and future Ground‐Born Vibration Train Pass By
Alternatives
Distance to Vibration Potential Building
Damage feet
Distance to Vibration Potential Human
Annoyance feet
Train At Grade
Train in Tunnel
Train At Grade
Train in Tunnel
Existing/ No Build 13 10 24 17
Alternative 2 (during construction when there is a Temporary Trench Route)
13 10 24 17
Alternative 2 23 20 41 36
Alternative 3 23 20 41 36
Alternative 4 23 20 41 36
Vibration Analysis Report 27
6 MITIGATION
This section discusses the possible mitigation measures that can be implemented to either
reduce or mitigate the vibration impacts generated by the construction and operation of the
proposed project.
6.1 CONSTRUCTION VIBRATION MITIGATION It is possible that certain construction activities could cause intermittent localized concern from
vibration in the Project Area. Processes such as earth moving with bulldozers, the use of
vibratory compaction rollers, and sheet piling could cause some human annoyance impacts.
There are cases where it may be necessary to use this type of equipment in close proximity to
residential buildings.
A vibration monitoring and mitigation plan will be prepared by a qualified vibration engineer,
which would include vibration monitoring procedures at predetermined vibration sensitive
sites, revised calculation of vibration levels for various construction phases, and revised
mitigation measures based on the re‐calculations. No construction work or the operation of
vibration generating equipment at the construction site would start until DDOT has approved
the plan. The plan would be updated if there are any major changes to the planned construction
activities.
The following are some procedures that can be used to minimize the potential for annoyance
from construction vibration:
Provide to the owners of buildings that are close enough to a construction vibration
source that may cause vibration impacts the option of the pre‐construction survey for
documenting the pre‐construction condition of that structure;
Conduct vibration monitoring during vibration‐intensive activities;
Properly maintain all motorized equipment in a state of good repair to limit wear
induced vibration.
Where feasible, avoid the use of pile driving near residences, and instead use drilled
piles or the use of a sonic or vibratory pile driver, which cause lower vibration levels,
where the geological conditions permit their use;
When there is possibility of annoyance from construction activities such as the operation
of vibratory rollers, absent urgent and unexpected circumstances, conduct such activity
only during weekday daytime hours when many residents are away from their homes;
Develop a phasing plan so that high vibration generating activities do not occur within
the same time period, to the extent practicable;
Avoid routing heavily‐loaded trucks through densely concentrated residences, if
reasonably possible;
CSX Virginia Avenue Tunnel Clearance Improvement Project
Vibration Analysis Report 28
Where feasible, use demolition methods that do not involve impact; and
Avoid the use of vibratory rollers and packers near sensitive areas, if possible.
A combination of the mitigation techniques for equipment vibration control as well as
administrative measures, when properly implemented, can be selected to provide the most
effective means to minimize the effects of construction activity. Application of the mitigation
measures will reduce the construction impacts; however, temporary increases in vibration
would likely occur at some locations. The extent of potential impacts cannot be determined
until detail construction workplans for each phase of the construction operations have been
developed.
6.2 POST-CONSTRUCTION OPERATION VIBRATION MITIGATION According to vibration impact analysis, ground‐borne vibrations are not expected to exceed
FTA criteria for the train operations under any of the Project “Buildʺ alternatives; therefore,
vibration mitigation is not necessary.
s
A FIGURES