appendix a initial scoping report - savethemaryriversavethemaryriver.com/downloads/ghdreport/z...
TRANSCRIPT
41/14840/332913 Bulk Infrastructure Task Group BSI04 Desk Top Review of Identified Dam and Weir Sites
Appendix A
Initial Scoping Report
South East Queensland Regional Water Supply
Strategy
Desk Top Review and TOR Development Consultancy Desktop Review of Identified
Dam and Weir Sites
Initial Scoping Report to the Bulk Supply Infrastructure Task Group
November 2005
Contents
1. Introduction 1
1.1 Background 1
1.2 Objective of Part 3 1
2. Proposed Scope of Works 3
2.1 BSI 04 Desk Top Review of Identified Dam and Weir Sites 3
3. Identification and Collation of Sites/Projects 5
3.1 Sources of Information 5
3.2 Dam and Weir Water Supply Projects 6
3.3 Cost per ML/a Yield 7
3.4 Recommended Sites for Further Review 8
4. Identification of Contributions from BSI Task Group 11
5. Proposed Timings 12
5.1 What can be started now? 12
5.2 Proposed Schedule 12
Table Index Table 1 Dams Returned to Service 8Table 2 Bulk Water Supply Projects Recommended for
Further Evaluation 9
Figure Index Figure 1A Approximate Dam and Weir Locations - Southern
South East Queensland Figure 1B Approximate Dam and Weir Locations - Northern
South East Queensland
Appendices27th January Workshop – Summary of FindingsSummary of Project Evaluation Considerations for Bulk Water Supply
Projects
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
1. Introduction
1.1 Background The Terms of Reference (TOR) for the “South East Queensland Regional Water Supply Strategic Project Bulk Infrastructure Task Group” (RWSS) require a desktop review and TOR development (BSI-04) be undertaken in four parts as follows:
Part 1 – Review of Gold Coast Water Supply Options;
Part 2 – Review of Other Augmentation Planning;
Part 3 – Desktop Review of Identified Dam and Weir Sites; and,
Part 4 – Preparation of TORs for Further Consultancies.
A sub-requirement of Part 3 of the consultancy is the preparation of scoping reports indicating:
The proposed scope of work for this task;
A refinement of the cost estimates for the task (exclusive of in-kind work by the Bulk Supply Infrastructure Task Group);
A proposed methodology for screening dam and weir sites with a view to updating cost estimates only for those projects worthy of further analysis;
Identification of any work contribution required from the BSI Task Group; and,
A proposed schedule for the work for this task giving regard to timing of outputs required to other BSI Tasks and to other task groups.
An initial scoping report is required under Part 3 summarising infrastructure options identified, with recommendations regarding which projects are to be included for further analysis as part of the desk top study.
This report constitutes the initial scoping report.
Following BSI Task Group approval of the options to be included for further review as outlined in the initial scoping report, a further scoping report is required which refines the scope and proposes a work schedule for the specific options to be further considered in the desk top review.
1.2 Objective of Part 3 The overall objective for Part 3 of the consultancy is to address the work required under Task BSI04 “The Desk Top Review of Identified Dam and Weir Sites” as outlined in the Bulk Supply Infrastructure Task Group Scoping Paper, which was attached to the brief for this consultancy. Consequently, the consultant is to:
Acquire and review existing information on previous investigations; and,
Prepare and submit to the Project Officer, a Report (the BSI04 Report) summarising the Infrastructure Options identified from a review of the existing reports and information, with recommendations on which warrant further
141/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
consideration, and identification of the further investigation required to firm up the information on these sites.
The initial scoping report is the first report in a series of reports with the overall objective to:
Identify possible infrastructure options to improve water supply including:
– New dams and weirs;
– Existing dams or weirs that could be raised;
– The associated delivery infrastructure; and,
Determine which of the identified infrastructure options warrants detailed investigations and eliminate all others from further consideration.
Each of the previous studies is to be evaluated to identify any major gaps in information on aspects such as environmental impact, cultural heritage or foundation conditions giving particular attention to the identification of potential “show stoppers”.
A report (the BSI04 Report) is to be submitted to the Project Officer incorporating the following:
The costs associated with the development of selected sites to a range of capacities, including land acquisitions and modifications to infrastructure such as roads and powerlines. The costs are also to be shown in schedules including quantities, unit rates and allowances for overheads and contingencies. Plans showing arrangements of structures, relocations, resumption areas etc are also to be provided;
Recommendations on further studies (including costs and timelines) necessary to assess potential “show stoppers”. These recommendations will also be provided progressively in a series of interim reports and will lead to the preparation of TORs for work under BSI 05;
Recommendations on the infrastructure necessary to connect the storages to the regional network (identified in broad terms) together with preliminary cost estimates of pipelines and water treatment;
Recommendations on the infrastructure necessary to connect the storages to the regional network in broad terms together with preliminary cost estimates of pipelines and water treatment; and,
TORs for BSI 05 provided progressively.
In addition an oral presentation of the findings will be made to the Bulk Supply Infrastructure Task Group and the Strategy Management Group on completion of the task.
241/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
2. Proposed Scope of Works
2.1 BSI 04 Desk Top Review of Identified Dam and Weir Sites Subject to approval of the Initial Scoping Report by the BSI Task Group, a more detailed review of the existing Investigation Reports and Preliminary Designs will be undertaken and the costs will be updated on a common basis. This may require some new desktop preliminary design where modification from previous arrangements is desirable, or where existing information was insufficient.
Some desk top preliminary design may also be required for the delivery infrastructure on an individual basis recognising that water demand and points of delivery will not be fully understood.
After screening to determine the sites with the greatest potential, a range of capacities will be assessed to determine the upper limit for development at each of the sites.Whilst this upper limit may result in a higher cost per megalitre than an alternative the marginal cost may be less than the marginal cost of the next alternative. At least two capacities are to be investigated at each site: the nominated capacity and the upper limit.
The tasks to be undertaken include:
Identify all the sites to be considered in the desktop review. The BSI Task Group Scoping Document attached to the brief for this consultancy suggested that this is likely to amount to five or six new dam sites, three potential raisings and up to four weir sites, though the brief itself and review of existing reports to date have suggested an increased number of sites will need to be considered;
A review of the infrastructure projects nominated by the Steering Committee Workshop 27th January 05;
Review of the existing documents on previous investigations including the cost estimates and identify shortfalls;
Review any previous assessments of environmental and cultural heritage impacts. Carry out additional desktop studies where appropriate in order to develop an appreciation of whether potential impacts may affect the likelihood of the proposal proceeding and identify those sites unlikely to be developed due to social or environmental impacts;
Prepare updated cost estimates based on the available information and form an appreciation of the accuracy of the estimates, for those projects that might be considered further in the development of the RWSS;
Identify in broad terms the infrastructure necessary to connect the storages to the regional network;
Prepare preliminary estimates of the costs of this connecting infrastructure and water treatment;
341/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
For competing options, for example, alternative weir sites on a river or alternative pipeline routes, determine which is preferable considering cost, supply and impact criteria;
Prepare a list of options that appear to be feasible and preferred;
Prepare, following consultation with the BSI Task Group, for each site included in this program, a schedule of additional (pre-feasibility level) studies required to confirm that the project warrants detailed investigation, including estimated costs of the studies;
Prepare a risk management assessment for each site/project in the context of it being struck off the list or included for further consideration;
441/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
3. Identification and Collation of Sites/Projects
3.1 Sources of Information A review of the following documents indicated that there have been a large number of dam and weir sites considered to supplement the raw water supply in the South East Queensland region. The documents reviewed included:
1. JWP, “Future Water Source Options for the Sunshine Coast” Table 16.1(draft), Aquagen, July 2005;
2. 27th January 2005 RWSS Steering Committee Workshop minutes;
3. Sunwater, “Water Supply Study of the Upper Mary Valley – Security of Supply”, August 2004;
4. GHD/Kinhill, “South East Queensland Water and Waste Water Management and Infrastructure Study – Final Report for Phase 1 – Water Sources and Infrastructure Needs”, Department of Natural Resources, April 1999;
5. Queensland DPI Water Resources, “An Appraisal Study of Water Supply Sources for The Sunshine Coast and The Mary River Valley”, December 1994;
6. Queensland Water Resources Commission and Brisbane Area Water Board “Water Supply Sources in South East Queensland”, January 1991;
7. A review of the information in the Department of Natural Resources and Mines library and the DPI library is underway, but has not as yet been collated and added to this report;
8. A review of the information held by each of the Councils and Water Authorities in the study area has commenced but has not yet reached a stage where information can be added to the Initial Scoping Report; and,
9. GHD, “South East Queensland Regional Water Supply Study, Stage 1 Report”, 2004.
10. DNR, “Seismic Refraction Reconnaissance Survey On Bremer River 67.7 km and 70.0 km Damsites,” work files, 1981, DNR reference 27207.
11. DNR, “Further progress report on Lockyer Valley water resources investigation,” work files, 1982, DNR reference 26837.
12. DNR, “Reedy Creek scheme, preliminary report,” work files, 1977, DNR reference 61079.
13. DNR, “Report on the water resources of Tinana Creek,” work files, 1950, DNR reference 24021.
14. P.E. Mann, “Yabba Creek 19.3 km and Amamoor Creek 14.7 km dam sites, seismic refraction survey, Queensland,” work files, 1959, DNR reference 64799.
15. DNR, "Geology and Mineral Resources: Damsites - Perserverence and Westbrook," work files, 2002 DNR reference 42848.
541/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
16. Department of Development and Mines: Geological Survey Queensland, “Brisbane River Damsites: Middle Creek damsite geological plan an sections”, map, 1970, DNR BRN reference no. 70189.
17. Queensland Irrigation and Water Supply Commission, “Preliminary Report on Bremer River Weir Site 25.9 km feasibility study”, Warrill Valley Irrigation Project, 1973, DNR BRN reference no. 27431.
3.2 Dam and Weir Water Supply Projects The potential water supply improvement projects mentioned in the 27th January Workshop are summarised in Appendix A and of these bulk water supply options associated with dam and weir developments were:
Glendower Dam Feasibility (investigation);
Upper Mary Coles Crossing Weir and Noosa Pump Station;
Ewen Maddock Dam rehabilitation; and,
Wyaralong Dam site acquisition.
A summary of the information on the dam and weir projects referred to in the reports listed in Section 3.1 (Ref 1 to 6) are provided in the tables in Appendix B with each project tabulated according to the potential yield identified in the previous reports. The yield was assessed a number of years ago. Since then procedures have changed and additional data has now become available. Yield analyses will be undertaken on the projects with the greatest potential. It is anticipated that these yield estimates will result in a reduction in the potential yield from a number of these projects. The projects have been subdivided into four supply capacity options so that the projects can be reviewed on the basis of their potential benefits. The supply categories chosen were:
Potential bulk water supply greater than 50,000 ML/a;
Potential bulk water supply between 20,000 and 50,000 ML/a;
Potential bulk water supply between 5,000 and 20,000 ML/a; and,
Potential bulk water supply less than 5,000 ML/a.
The categories were chosen to categorise options that at the upper supply range had the potential to supply water to the entire region and in the lower supply range would result in supply only to the local area.
More than 80 bulk water supply options have been assessed in the existing reports. The general characteristics for these options are summarised in Appendix B, and the location of each of the sites are indicated in Figures 1-A and 1-B. A number of these sites have variations in potential storage capacity and yield from one source of information to another.
641/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
3.3 Cost per ML/a Yield Cost to supply the anticipated yield has been determined for a number of the sites listed in Appendix B based on. :
The escalated cost of the projects as indicated in the appropriate reports. Generally the costs include the capital cost for the works, land acquisition and infrastructure relocation costs. However for some of the cost estimates it is not clear whether all the above costs have been included. Bulk water supply transfer costs generally have not been included in the costs provided in the previous studies and therefore has not been included here.
Cost estimates provided in the reports have been escalated to July 2005 using a combination of the Rawlinsons building price adjustment and the Rider Hunt tender level index. This has been undertaken to provide a reasonable comparison of costs between the various reports. Both these indexes indicate a significant increase in costs over the past three years when compared to previous years. The Rawlinsons index indicates much greater increase when compared to the Rider Hunt Index. The Rawlinsons index for Brisbane is reported to provide a good guide to building cost increases over the past two years and reflects the shortage of labour and materials being experienced in the industry. As the bulk water supply projects are a mixture of building and civil construction and as it is anticipated that the cost increases currently being experienced may be short term in nature the cost index chosen for escalation was a mean of the two indexes.
The yield estimates given in the reports are currently considered to be optimistic, however, these have been used for the comparison of projects as it is likely that all of the projects will be impacted by a similar proportion when the additional drought information and new calculation techniques are taken into account.
In reviewing the costs it was found that there were four types of project:
Existing dams not currently utilised that may provide a small increase in yield for the system;
Projects previously costed and able to be compared;
Projects that have not been costed but may have potential; and,
Projects that were favoured but had been excluded previously on social or environmental grounds.
3.3.1 Dams Returned to Service
Projects identified that are likely to increase the available water supply to the community and are likely to be of very low capital cost to return to service are identified in Table 1 below, though these projects were considered of local significance only.
741/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
Table 1 Dams Returned to Service
Yield (ML/a)
Ewen Maddock Dam (return to service) 5,000
Lake Manchester, Enoggera and Gold Creek Dams (return to service) 12,000
3.4 Recommended Sites for Further Review In general the reports indicate that there are environmental or social issues on most, if not all of the projects.
The earlier reports have not been assessed on the basis of potential green house gas production/ energy consumption as a result of pumping etc or the potential to manage the environmental/social risks with engineered works. The environmental impact relative to the benefit has not been evaluated.
Each of the sites was reviewed on the basis of the potential yield as indicated above, the potential environmental constraints as identified in the available reports and the potential social issues as identified in the previous reports. A summary of some 80 identified sites is included as Appendix B. Of these 14 dam sites and a water harvesting option were considered to be appropriate for more detailed review. These are indicated in Table 2:
841/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
Tabl
e 2
Bul
k W
ater
Sup
ply
Proj
ects
Rec
omm
ende
d fo
r Fur
ther
Eva
luat
ion
Bul
k W
ater
Sup
ply
Proj
ects
Rec
omm
ende
d fo
r Fur
ther
Eva
luat
ion
Cat
chm
ent /
Str
eam
D
amsi
te N
ame
AM
TD
(km
)
Cap
acity
1
(ML)
Full
Supp
ly
Leve
l
(m) E
L
Rep
orte
d Po
tent
ial Y
ield
(ML/
a)
Alb
ert R
iver
G
lend
ower
Dam
in c
onju
nctio
n w
ith w
eir o
n Lo
gan
Riv
er
60.2
86,0
0076
21,0
00 (R
ef 9
)
Bris
bane
Riv
er
Rai
se W
iven
hoe2
40,0
00 (R
ef 4
)
Cab
ooltu
re R
iver
Zi
llman
s C
ross
ing
36.4
70,0
0073
13,6
80 (R
ef 6
)
Loga
n R
iver
C
edar
Gro
ve3
81.8
403,
000
4212
2,30
0(R
ef 6
)
Loga
n R
iver
Ti
lleys
Brid
ge n
ear R
athd
owne
y in
co
njun
ctio
n w
ith a
wei
r on
Loga
n R
iver
153.
423
0,00
0 12
070
,050
(Ref
6)
Loga
n R
iver
/ Te
viot
B
rook
W
yara
long
Dam
with
Ced
ar
Gro
ve W
eir
14.8
104,
000
35,0
00 (R
ef 9
)
Mar
ooch
y R
iver
R
aisi
ng W
appa
Dam
4,
600
to 9
5,00
0 44
.8 to
80
19,7
00 (R
ef 1
& 5
)
Mar
y R
iver
Tr
aves
ton
206.
766
6,00
0 29
6,00
0 (R
ef 5
)
Mar
y R
iver
C
ambr
oon
274
200,
000
75,0
00 (R
ef 5
)
1 The
Cap
aciti
es g
iven
are
indi
cativ
e on
ly b
ased
on
the
Full
Sup
ply
Leve
ls li
sted
as
prev
ious
ly n
oted
in th
e lit
erat
ure
revi
ewed
. The
se le
vels
, and
con
sequ
ently
the
capa
citie
s, w
ill b
e su
bjec
t to
furth
er re
finem
ent.
2 Pro
ject
s be
ing
inve
stig
ated
by
the
SE
QW
B a
nd G
CC
thou
gh re
view
of i
nfor
mat
ion
avai
labl
e at
the
time
will
nee
d to
be
incl
uded
in th
e de
sk to
p re
view
. 3 P
roje
cts
with
insu
ffici
ent i
nfor
mat
ion,
but
may
be
suita
ble
for B
ulk
Wat
er S
uppl
y.
941
/148
40/3
3330
2
So
uth
East
Que
ensl
and
Reg
iona
l Wat
er S
uppl
y St
rate
gy
Bul
k S
uppl
y In
frast
ruct
ure
Task
Gro
up D
esk
Top
Rev
iew
and
TO
R D
evel
opm
ent C
onsu
ltanc
y
Bul
k W
ater
Sup
ply
Proj
ects
Rec
omm
ende
d fo
r Fur
ther
Eva
luat
ion
Cat
chm
ent /
Str
eam
D
am S
ite
AM
TD
Cap
acity
1Fu
ll Su
pply
Le
vel
Rep
orte
d Po
tent
ial Y
ield
(ML/
a)
Mar
y R
iver
/ O
bi O
bi
Cre
ek
Kid
aman
6.3
300,
000
60,6
75 (R
ef 5
)
Mar
y R
iver
B
orum
ba D
am R
aise
25m
–
Sta
ge II
I 31
.124
0,00
0 15
7.28
30,0
00 (R
ef 9
)
Mar
y R
iver
/ A
mam
oor
Cre
ek
Am
amoo
r 19
.222
0,00
0 14
517
,000
(Ref
9)
Ner
ang
Riv
er /
Coo
mer
a R
iver
C
oom
era
30.4
238,
000
65,0
00 (R
ef 6
)
Ner
ang
Riv
er
Rai
se H
inze
Dam
Sta
ge II
I136
.439
4,00
0 99
.215
,000
(Ref
9)
Ner
ang
Riv
er -
Wat
er H
arve
stin
g in
to e
xist
ing
or ra
ised
Hin
ze D
am
Can
ungr
a C
reek
Coo
mer
a R
iver
C
oom
era
30.4
km
Mud
gera
bah
Cre
ek
Ner
anw
ood
21.1
km
Talle
budg
era
Cre
ek
Ingl
esid
e 14
.0 k
m
Cur
rum
bin
Cre
ek
Cra
igs
Cro
ssin
g 12
.7 k
m
1041
/148
40/3
3330
2
So
uth
East
Que
ensl
and
Reg
iona
l Wat
er S
uppl
y St
rate
gy
Bul
k S
uppl
y In
frast
ruct
ure
Task
Gro
up D
esk
Top
Rev
iew
and
TO
R D
evel
opm
ent C
onsu
ltanc
y
4. Identification of Contributions from BSI Task Group
It is expected that the BSI Task Group or its representative would:
Arrange for updated yield assessments for appropriate dam and weir sites. Those projects requiring updated yield information are summarised in Table 2.
Assist with co-ordination to manage the exchange of information with other task groups;
Obtain relevant reports or results of the studies from the other task groups and make this information available to the further work as required, especially updated yield information;
Provide contacts within the other task groups to enable the further consultants to liaise as required;
Organise logistics associated with the oral presentations by any consultants to the BSI Task Group;
Be responsible for reviewing and providing comment on draft documentation produced by the consultants; and,
Gain approval/advice from the State Government, South East Queensland Regional Organisation of Councils (SEQROC), and the Regional Coordination Committee (RCC) as appropriate before formally identifying such sites/projects.
1141/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
5. Proposed Timings
5.1 What can be started now? The work to be completed in Part 3 can be started now and has commenced with the summary of projects previously identified.
5.2 Proposed Schedule The Terms of Reference require that a draft of the BSI04 report be submitted for review on 28th October 2005. The completion of this task is dependent on:
Yield estimates being provided in a timely manner;
Approval of the BSI Task Group of the projects to be included in the report;
Responses from the Councils and Water authorities being received in a timely manner;
Availability of suitable topographic plans for the sites being considered;
Engineering analysis of previous reports and data plus development of engineering options;
Availability of ecological, social and archaeological information on the sites/projects; and,
Identification of the demand requirements and locations of the demand centres suitable for pre-planning of the raw water distribution requirements.
This means that the proposed schedule may need to be amended depending on when inputs are available from other tasks or task groups. If the relevant inputs are available when required the engineering assessments could be completed by 28th October 2005.
1241/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
Figures
Figure 1A - Dam Locations Figure 1B - Dam Locations
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
!
!
! !
!
!!
!
!
!
!
!
!
!
!
!!
!!
!
!
!
! !
! !
!
!
!
!
!
!
!
!!
!
!
!
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(
2
1
89
87
81
8079
66
65
64
63 62
61
60
59
58
57
56
46
42
41
40
3938
36
35
34
27
26
20
19
18
17
68
37
33
28
Mary River
Noosa River
Maroochy River
Burru
m
River
Brisbaneriver
Tinana Creek
MunnaC
reek
Ob i Obi creek
Yabba Cre
ek
Wide Bay Creek
Amamoor Creek
Wid
gee
Cr
eek
Cooyar creek
LAKE COOTHARABA
LAKE COOROIBAH
LAKE BAROONEudlo
Jimna
Imbil
Dagun
Tiaro
Yerra
Cooray
Pomona
Cooran
Gympie
Bauple
Howard
Woombye
Nambour
Yandina
BroolooEumundi
Kin Kin
Goomeri
Gunalda
TewantinKandanga
Kilkivan
Woolooga
Theebine
Gootchie
Nikenban
Palmwoods
Boonooroo
Brooweena
Torbanlea
Dundowran
Kenilworth
Elgin Vale
Maryborough
Landsborough
Manumber Mill
Lagoon Pocket
Kadanga Creek
Skyring Creek
SEQ Bulk WaterDam and Weir Sites
Approximate Dam and WeirSite Locations - Northern SEQ
Figure 1a
Copyright: This document is and shall remain the property of GHD Pty Ltd. The document may only be used for the purpose for which it was commissioned and in accordance with the terms of engagement for the commission. Unauthorised use of this document in any way is prohibited.
Legend
!( Potential Storage Sites
! Towns
River
Creek
Highway
Major Road
Source: GIS data supplied byGeoscience AustraliaProjection: MGA Zone 56Date Printed: 15 August 2005File: M:\41\14840\Maps\dam_locations_a3_north.mxdSize: A3
²0 5 10
Kilometers
1:500,000
Figure 1a
Figure 1b
Id Site Description AMTD (km)1 Mary River - Kenilworth 270.002 Brisbane River - Linville Dam Site 282.10
17 Mary River - Traveston 206.9018 Mary River - Cambroon 274.0019 Mary River - Conondale 291.0020 Obi Obi Creek - Kidaman 6.3026 Munna Creek 22.2027 Munna Creek - Merodian 32.5028 Yabba Creek - Borumba Dam 31.1033 Mary River - Coles Crossing Weir 213.5034 Burrum River - Lenthalls Dam 34.6035 Mary River - Mary River Barrage 58.7036 Mary River - Moy Pocket Weir Site 244.0037 Mary River - Water harvesting into Burumba -38 Wappa Dam -39 Cooloolabin Dam -40 Amamoor Creek 19.2041 Skyring Creek 10.3042 Widgee Creek -46 Cooyar Creek 12.4056 Ewen Maddock Dam -57 Lake MacDonald -59 Baroon Pocket Dam -60 Munna Creek 36.0061 Kadanga Creek 12.2062 Kadanga Creek 21.4063 Kadanga Creek 28.5064 Maroochy River -65 Noosa River -66 Mary River - Small weirs btn 178.5 - 185km 178.5068 Yabba Creek - Lge offstream storages D/S -79 Wide Bay Creek 36.2080 Wide Bay Creek 30.4081 Amamoor Creek 14.7087 Mary River - Damsite 156.0089 Mary River - Teddington Weir -
!
!
!
!
!
!
! !!
!
!
!
!
!
!
!!
!
!
!
!
!
!
!
!
!
!
!!
!
! !
!
!
!
!!
!!
!
!
!
!
!
!
!!
!
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!( !(
!(
!(!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
9
8
5
2
91
90
88
86
8483
82
78
77
76
75
74
72
58
56
54
53
52
5150
49
4847
46
45
44
43
32
30
25
2423
19
16
1514
13
12
11
10
7
6
4
3
85
73
71
70
55
31
29
22
21
Brisbane river
Logan river
Albertriv
er
Stanley rive r
Bre
merR
iver
Coo
mera river
Nerang Rive
Caboolture river
South pine river
Mary River
Teviot br ook
War
rillCre
ek
Lockyer Creek
Laid
ley
Creek
Emu Creek
Canungracreek
Tenth
illl
Creek
Mud
geeraba cree
k
Esk Creek
Burpengary CreekReedy Creek
NeuremC
reek
Christmas
Creek
Middle Creek
Ob i Obi creek
LAKE WIVENHOE
LAKE SOMERSET
LAKE SAMSONVALE
LAKE ATKINSON
LAKE MAROON
LAKE CLARENDON
TINGALPA RESERVOIR
LAKE KURWONGBAH
LAKE MANCHESTER
LAKE BAROON
ENOGGERA RESERVOIR
Esk
Kerry
Moore
Eudlo
BoonahNerang
Kalbar
Gatton
Harlin
Kilcoy
Laidley
Helidon
Mt Nebo
Samford
Dayboro
Beerwah
Ipswich
LaravaleCanungra
Fernvale
Woodford
Benarkin
Linville
Brisbane
Freestone Beechmont
Mt Alford
Jimboomba
Beenleigh
Woodridge
Kallangur
Redcliffe
Blackbutt
Rathdowney
Mudgeeraba
Beaudesert
Brooklands
Park Ridge
Bald Hills
Caboolture
Forest Hill
Toogoolawah
Slacks Creek
Landsborough
Peak Crossing
Deception Bay
North Tamborine
Glass House Mountains
Ma
Ma
Cree
k
Back
Cre
ek
Cooyar creek
Flagsto
neCreek
Tallebudgeracre
ek
Currum
bincre
ek
Cainbable
Creek
ton Creek
SEQ Bulk WaterDam and Weir Sites
Approximate Dam and WeirLocations - Southern SEQ
Figure 1b
Copyright: This document is and shall remain the property of GHD Pty Ltd. The document may only be used for the purpose for which it was commissioned and in accordance with the terms of engagement for the commission. Unauthorised use of this document in any way is prohibited.
Legend
!( Potential Storage Sites
! Towns
River
Creek
Highway
Major Road
Source: GIS data supplied byGeoscience AustraliaProjection: MGA Zone 56Date Printed: 15 August 2005File: M:\41\14840\Maps\dam_locations_a3_south.mxdSize: A3
²0 5 10
Kilometers
1:500,000
Figure 1a
Figure 1b
Id Site Description AMTD (km)2 Brisbane River - Linville Dam Site 282.103 Stanley River - Peachester Dam Site 86.204 Cabooluture River - Zillmans Crossing Dam Site 36.405 South Pine River - Greenwood Dam Site 19.506 Teviot Brook - Braford Hills Dam Site 18.007 Logan River - Cedar Grove Dam Site 81.808 Albert River - Glendower Dam Site 60.209 Canungra Creek - Bega Hills Dam Site 29.60
10 Coomera River - Dam Site 30.4011 Coomera River - Army Camp Dam Site 41.4012 Nerang River - Hinze Dam Stage III 36.4013 Mudgeeraba Creek - Neranwood Dam Site 21.1014 Tallebudgera Creek - Ingleside Dam Site 14.0015 Currumbin Creek - Craigs Crossing Dam Site 12.7016 Logan River - Tilleys Bridge Dam Site 153.4019 Mary River - Conondale 291.0021 Albert River - Wolffdene 19.3022 Albert River - Mancha Meadows 51.0023 Albert River - Mundoolun 46.0024 Teviot Brook - Wyaralong 14.8025 Middle Creek - Middle Creek 1.3029 Caboolture River - Gregors Creek 35.3030 Brisbane River - Wivenhoe dam 149.0031 Emu Creek - Emu Creek 52.5032 Logan River - Upper Logan 171.2043 South Pine River - Cashs Crossing 14.0044 Caboolture River - Haussmans 31.0045 Caboolture River - River Junction 39.0046 Cooyar Creek 12.4047 Neurem Creek - Neurem Creek Weir 12.1048 Neurem Creek - Neurem Creek Dam 16.1049 Lake Manchester -50 Enoggera Dam -51 Gold Creek Dam -52 Cainbable Creek - Nindooinbah 9.9053 Christmas Creek -54 Teviot Brook - The Overflow 22.2055 Teviot Brook - Cedar Grove Weir w/o Wyaralong 81.8056 Ewen Maddock Dam -70 Stanley River - Peachester 86.2071 Emu Creek 52.5072 Bremer River - Mt Walker 69.8073 Lockyer Valley - Ma Ma Creek 21.9074 Lockyer Valley - Tenthill Creek 29.8075 Lockyer Valley - Lockyer Creek 50.5076 Teviot Brook 88.3077 Teviot Brook - Croftby 83.3078 Warrill Creek - Warrill Creek -82 Back Creek - Beechmont area water study -83 Bremer River 25.9084 Laidley Creek - Bill Gunn Dam (Lake Dyer) -85 Ma Ma Creek 20.2086 Ma Ma Creek - Recharge Weir 14.0088 Reedy Creek - Reedy Creek Scheme -90 Burpengary Creek - Caboolture Weir -91 Flagstone Creek - Mar Mar 10.30
Appendix A (to Appendix A of Overall Report)
27th January Workshop – Summary of Findings
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
Summary of Workshop Findings
The 27th January 2005 RWSS Steering Committee Workshop listed a number of projects for development over approximately the next 20 years. This list together with its relevance to this study, that is, increasing the bulk water supply in the South East Queensland region, is indicated in the Table below.
January 27th Steering Committee Workshop Options
SEQ Infrastructure Plan Project Items, Estimated Timeframes and Costs
Impact on Increasing Bulk Water Supply or relevance to Bulk Water Infrastructure for this study
1. Southern regional pipeline project Minor to Nil
2. Wivenhoe; Somerset; North Pine Catchments rehabilitation – 20 years, remediation and sewerage infrastructure
Minor to Nil
3. Coomera-Pimpama advanced wastewater plant Minor to Nil
4. Wyaralong Dam site acquisition Potential
5. Cedar Grove Weir Potential
6. WaterFutures Toowoomba, comprising:
a. Groundwater - $30m over 3-5 years Minor to Nil
b. Advanced water treatment (indirect reuse) - $40m over 5-10 years Minor to Nil
7. Southern Moreton Bay Island sewerage - $160m Minor to Nil
8. Groundwater – Redland (investigation) Minor to Nil
9. Regional Sludge incinerator (investigation) Minor to Nil
10. West Brisbane-Ipswich recycled water scheme Minor to Nil
11. SEQ RWSS Stage 2 ???
12. Future Sunshine Coast water sources (investigation) – 2006, options/impacts ???
13. Water mains duplication Sunshine Coast – 2006, $29m Minor to Nil
14. Ewen Maddock Dam Rehabilitation – 2016, $25-30m Potential
15. South Maroochy upgrade – 2010-2017, $30m Minor to Nil
16. Sunshine Coast Cane land re-development t t t li i
Minor to Nil
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
SEQ Infrastructure Plan Project Items, Estimated Timeframes and Costs
Impact on Increasing Bulk Water Supply or relevance to Bulk Water Infrastructure for this study
strategy – water recycling, remove river discharge, 2007, $185m
17. Maroochy River pilot study – 2006, $30m Minor to Nil
18. Desalination pilot plant – 2007, $30m, Sunshine Beach – Coolangatta Minor to Nil
19. SEQ RWQMS – 2006, $2m incorporating sustainable loads to SEQ waterways, including load-based monitoring
Minor to Nil
20. Lockyer/Bremer catchment rehabilitation – 2020, $20m Minor to Nil
21. Northern region pipeline upgrade – 2007, $10m Minor to Nil
22. Brisbane bulk system upgrade – 2010 Minor to Nil
23. Australia Trade Coast recycling scheme – 2010, $20m Minor to Nil
24. Rochedale dual reticulation – 2010 Minor to Nil
25. Moodlu Quarry – 2006, $4m Minor to Nil
26. Demonstrate aquifer storage and recovery and capacity assessment (investigation) – 2007, $2m
Minor to Nil
27. Petrie water treatment upgrade Minor to Nil
28. Septics improvement – 2007, $1m Minor to Nil
29. Upper Mary-Coles Crossing Weir and Noosa Pump Station – 2006-2010, $9m Potential
30. Glendower Dam feasibility (investigation) – 2006, $0.5m Potential
31. Mt Crosby Water Treatment Plant upgrade – 2010, $60m Minor to Nil
32. Fairfield recycling – 2007, $2m Minor to Nil
33. Transit-oriented development (investigation) – 2006 Minor to Nil
34. Inter-catchment sewerage transfer (investigation) – 2006 Minor to Nil
35. Water mining / micro treatment (investigations) – 2006 Minor to Nil
36. Behavioural change – Water wise – 2020, $10m Minor to Nil
37. Stormwater re-use (investigation) Minor to Nil
38. Narangba recycled water – 2008, $4m Minor to Nil
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
SEQ Infrastructure Plan Project Items, Estimated Timeframes and Costs
Impact on Increasing Bulk Water Supply or relevance to Bulk Water Infrastructure for this study
39. Re-use mains – parks and open space – Redland - $85m Minor to Nil
40. Water Research centre and training centre including plumbers training Minor to Nil
41. Cash incentives for retro-fitting water devices Minor to Nil
42. Rural water use efficiency initiative Minor to Nil
43. Tarong recycled water Minor to Nil
44. Smart metering project to better understand in-residence consumption – 3 sites in SEQ, $3m, 2005-2006
Minor to Nil
45. Groundwater resource characterisation – SEQ (including Great Artesian Basin and Toowoomba basalts)
Minor to Nil
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
Appendix B (to Appendix A of Overall Report)
Summary of Project Evaluation Considerations for Bulk Water Supply Projects
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
PROJECTS WITH POTENTIAL YIELD GREATER THAN 50,000 ML/a
Cost and Benefit Summary
ProjectCost ($ million)
Yield(ML/a) $/ML/a
Comment
Albert River – Mancha Meadows
AMTD 51.0 in storage area of Wolffdene
(Reference 6)
? Very High social and financial cost.
Albert River – Mundoolun
AMTD 46.0 km in storage area of Wolffdene
(Reference 6)
? Very High social and financial cost.
Albert River – Wolffdene
AMTD 19.3 km
(Reference 6)
687132,600
(Unknown % PMFR)
5,179 Very High social and financial cost.
Coomera River – Army Camp
AMTD 41.4 km
FSL 133.3
Capacity 248,000 ML
(Reference 6)
493
54,600
(Nofailure)
56,500
(1% PMFR)
8,722
Strategically located for demand.
Rural-residential growth area.
Land warfare centre.
May be suitable for water harvesting into Hinze dam.
Rainforest and eucalypt forest.
Three known rare/threatened species.
National Parks and Wildlife expressed interest in protecting forests.
Population affected 583 and 292 army.
Vegetation and wildlife impact high.
River impact moderate.
Note: PMFR = Probable Monthly Failure Rate
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
PROJECTS WITH POTENTIAL YIELD GREATER THAN 50,000 ML/a
Cost and Benefit Summary
ProjectCost ($ million)
Yield(ML/a) $/ML/a
Comment
Coomera River
AMTD 30.4 km
FSL 84
Capacity 238,000 ML
(Reference 6)
548
65,000
(Nofailure)
67,000
(1% PMFR)
8,182
Strategically located for demand.
Rural-residential growth area.
Land warfare centre.
May be suitable for water harvesting into Hinze dam.
Over half of ponded area cleared for agriculture.
Complex notophyl vine forest
Potential rare and threatened species.
Fish.
Water quality same as others.
European and Aboriginal heritage but not listed by Department of Environment.
Rainforest eucalypt.
Three known rare/threatened species.
313 residents affected.
Vegetation and wildlife impact high.
River impact mod-low.
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
PROJECTS WITH POTENTIAL YIELD GREATER THAN 50,000 ML/a
Cost and Benefit Summary Comment
ProjectCost ($ million)
Yield(ML/a) $/ML/a
Logan River – Cedar Grove
AMTD 81.8 km
FSL 42 m
Capacity 403,000 ML
(Reference 6)
693
122,300
(Nofailure)
139,270
(1% PMFR)
4,974
May be worth considering further due to relatively large yield.
Previously Wyaralong preferred over dam at Cedar Grove Weir.
Eucalypt forest.
Two likely rare/threatened species.
Population affected 378.
Low vegetation and wildlife impact.
Low to moderate river impact.
Logan River – Tilley’s Bridge near Rathdowney
AMTD 153.4 km in conjunction with a weir on Logan River
FSL 120 m
Capacity 230,000 ML
(Reference 6)
236
70,050
(Nofailure)
75,200
(1% PMFR)
3,132
Potential as a stand alone or part of the system.
Eucalypt forest.
Two likely rare/threatened species.
Wild life corridor.
Population affected 119.
Low to moderate vegetation and wildlife impact.
Moderate river impact.
Mary River - Cambroon
AMTD 274 km
Capacity 200,000 ML
(Reference 5)
75,000
(Unknown % PMFR)
Potential for storage to supply Mary valley and Sunshine coast.
Conondale township needs to be moved.
Transfer to Somerset possible.
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
PROJECTS WITH POTENTIAL YIELD GREATER THAN 50,000 ML/a
Cost and Benefit Summary Comment
ProjectCost ($ million)
Yield(ML/a) $/ML/a
Mary River – Conondale
AMTD 291.0 km
Capacity 100,000 ML
(Reference 5)
30,000
(Unknown % PMFR)
National Park impacted
Mary River near Kenilworth
AMTD 270.0
FSL 135
Capacity 410,000 ML
(Reference 6)
211
105,500
(Nofailure)
110,950
(1% PMFR)
1,899
Major Environmental and social issues including State forest feature protection area No 22. Charles Moreland State Forest Park.
Rainforest/ Eucalypt forest.
1 plant (others likely) and 8 animals
Known rare/threatened species 2 known 4 likely.
Mary River Cod.
Uncontrolled river DPI opposition.
Population affected 144.
Medium-high potential for aboriginal sites. Potential vegetation, wildlife and river impact very high.
Mary River - Traveston
AMTD 206.7 km
Capacity 666,000 ML
(Reference 5)
296,000
(Unknown % PMFR)
Alluvial flood plain on right bank.
Inundation of prime agricultural land and displacement of rural population.
Mary River Cod may be affected.
Kadanga may be flooded.
Obi Obi Creek - Kidaman
AMTD 6.3 km
300,000 ML
(Reference 1 and 5)
60,675
(Unknown% PMFR)
Closest source of water to Caloundra and Maroochy.
Tunnelling costs may be costly.
Teviot Brook – Braford Hills AMTD 18 km in conjunction with a weir on Logan River FSL 72 Capacity 176,000 ML
174
61,340(Nofailure) 66,820(1% PMFR)
2,606
Wyaralong was the preferred site in Reference 6.
Eucalypt forest.
Two likely rare threatened species.
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
PROJECTS WITH POTENTIAL YIELD GREATER THAN 50,000 ML/a
Cost and Benefit Summary Comment
ProjectCost ($ million)
Yield(ML/a) $/ML/a
(Reference 6) Population affected 98.
Low vegetation and wildlife impact.
Moderate river impact.
Brisbane River - Linville
AMTD 282.1km
FSL 160
Capacity 416000 ML
(Reference 6)
265
Incremental System Yield = 64,400(Nofailure)
28,400
(1% PMFR)
9,338
Detracts from Wivenhoe Yield
Eucalypt forest.
5 known rare/threatened species.
Population affected 34.
Vegetation and wildlife low impact.
River moderate impact.
Yield affected by flood mitigation
Teviot Brook – Wyaralong (The Yards)
AMTD 14.8 km.
Wyaralong Dam with Cedar Grove Weir
Capacity 104,000ML
(Reference 6)
99
35,000
(Nofailure,RWSSStage 1 Report)
60,300
(Nofailure,Ref 6)
1,634
Ponded area cleared for grazing.
Fish, vertebrates, invertebrates impacted.
Possible water quality issues.
Sewage treatment plants downstream proposed.
No aboriginal heritage recorded potential noted.
98 residents affected.
Land purchased.
Legend
Bold Text and shaded cells indicate projects recommended for further evaluation under the desk top review as summarised in Table 1.
NOTE: Comments are in the main based on information contained in reports published in the 1990's and data may no longer be accurate.
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
PROJECTS WITH POTENTIAL YIELD BETWEEN 20,000 ML/a AND 50,000 ML/a
Summary Project
Cost ($million)
Yield(ML/a) $/ML/a
Comment
Albert River – Canungra Creek Bega Hills
AMTD 47 km in conjunction with downstream weir on Albert River
FSL 160
Capacity 92,000 ML
(Reference 6)
249
44,600
(Nofailure)
46,820
(1% PMFR)
5,326
National Park and other environmental issues.
Rain forest.
Eucalypt, 3 likely rare/threatened species
1.4 ha Sarabah National Park and "Glen Withering" property.
Population affected 114.
Vegetation and wildlife impact high.
River impact moderate to low.
Glendower is the preferred option
Albert River - Glendower Dam
AMTD 60.2 km (upstream of Wolffdene) in conjunction with weir on Logan River
FSL 79 m
Capacity 112,000ML
FSL 76m
86,000 ML
(Reference 2 and 6)
206
FSL 79m
54,270
(Ref 6)
FSL 76m
45,600
(Ref 2)
FSL 76m
21,000
(Ref 9)
3,533
Strategically located for demand.
Ponded area cleared for cultivation and grazing.
Modified swamp and wetland areas.
Fish impact.
Possible water quality impact.
Aboriginal cave shelter carved trees.
Nindooinbah listed homestead. 81 residents affected.
Wetland.
Wetland may be of scientific interest.
2 likely rare/threatened species.
Low vegetation impact.
Moderate river impact.
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
PROJECTS WITH POTENTIAL YIELD BETWEEN 20,000 ML/a AND 50,000 ML/a
Summary Project
Cost ($million)
Yield(ML/a)
Comment
$/ML/a
Mary River - Borumba Dam raising 25m
AMTD 31.1 km
FSL 157.28
Capacity 240,000 ML
(Reference 4)
71
30,000
(Nofailure - RWSSStage 1 Report)
52,000(Unknown % PMFR - Ref 4)
1,781
Disturbed forest.
Rare and endangered species.
Fish.
Water quality? No information.
15 residents affected.
Preliminary cost estimates only.
DPI costs look low.
Caboolture River – Gregoors Creek
AMTD 35.3km
Capacity 72,000 ML
(Reference 6)
172 21,700 7,919Zillmans crossing more cost effective.
Currumbin Creek – Craigs Crossing
AMTD 12.7 (12.4) km
FSL 70
Capacity 92,900 ML
(Reference 6)
245
20,460
(Nofailure)
21,200
(1% PMFR)
11,576
Ponded area cleared for agriculture.
Fish.
Water Quality.
Septic tanks in catchment.
1 known 4 likely rare/threatened species.
296 residents affected.
Vegetation and wildlife impact low.
River impact mod-low.
Flood mitigation benefit strategically located to demand area.
High social and environmental issues.
Logan River - Upper Logan
AMTD 171.2 (170.9) km
120,000 ML
(Reference 6)
23724,000
(Unknown % PMFR)
9,896Delivery cost is high.
Tilley’s bridge option preferred.
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
PROJECTS WITH POTENTIAL YIELD BETWEEN 20,000 ML/a AND 50,000 ML/a
Summary Project
Cost ($million)
Yield(ML/a)
Comment
$/ML/a
The 1994 Appraisal Study Report included Amamoor Creek as part of a possible longer term strategy with reallocation of part of the Borumba Dam supply from the Mary River Valley to the Sunshine Coast with the Amamoor Creek Dam supplying downstream urban and agricultural water needs of the Mary River Valley.
Munna Creek
AMTD 22.2 km
Capacity 385,000 ML
(Reference 5)
46,700
(Unknown % PMFR)
The Amamoor Creek site is the preferred longer term element of the strategy rather than the other available options, the Wide Bay Creek or Munna Creek sites, because of its better cost effectiveness, smaller impacts and because of its more strategic location to serve demands in the middle and lower parts of the Mary River Valley.
Munna Creek - Merodian
AMTD 32.5 km
Capacity 150,000
(Reference 5)
25,000
(Unknown % PMFR)
22.2 km option has higher yield
Nerang River - Raise Hinze Dam Stage III (Note B)
AMTD 36.4 km
FSL 99.2
Capacity 394,000 ML
(Reference 6)
142
15,000
(Nofailure - RWSSStage 1 Report )
11,200
(Unknown % PMFR -Ref 6)
5,137
Eucalypt and rain forest issues.
Fish.
Water quality issues.
29 residents affected.
Eucalypt and rain forest, 4 likely rare/threatened species.
Vegetation and Wildlife moderate impact.
River low impact.
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
PROJECTS WITH POTENTIAL YIELD BETWEEN 20,000 ML/a AND 50,000 ML/a
Summary Project
Cost ($million)
Yield(ML/a)
Comment
$/ML/a
Raising Wivenhoe (Note B)
(Reference 4) 182
40,000
(Nofailure)
4,547SEQWB undertaking cost evaluation
Stanley River at Peachester
AMTD 86.2 km
FSL 153
Capacity 13,200 ML
(Reference 6)
251
42,400
(Nofailure)
45,500
(1% PMFR)
5,524
Detracts from Wivenhoe yield.
Rain forest and eucalypt forest.
1 known 2 likely rare/threatened species.
Vegetation and wildlife impact moderate.
River impact high.
Tallebudgera Creek - Ingleside
AMTD 14.0 km
FSL 75
Capacity 231,000 ML
(Reference 4 and 6)
350
33,000
(Nofailure)
36,320
(1% PMFR)
9,645
Flood mitigation benefit.
Strategically located to demand area.
340 ha forest fauna corridor.
Vegetation clearance extensive.
Fish, vertebrates, and invertebrates.
Water quality issues.
RESIDENTS HAVE STRONG ENVIRONMENTAL INTEREST.
No sites of archaeological or heritage value recorded.
306 residents.
Eucalypt, 1 known 4 likely rare/threatened species.
River Impact low.
Significant social and environmental issues.
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
PROJECTS WITH POTENTIAL YIELD BETWEEN 20,000 ML/a AND 50,000 ML/a
Summary Project
Cost ($million)
Yield(ML/a)
Comment
$/ML/a
Tallebudgera Creek - Ingleside
AMTD 14.0 km
May be appropriate for water harvesting into Hinze Dam.
Legend
Bold Text and shaded cells indicate projects recommended for further evaluation under the desk top review as summarised in Table 1.
Notes
(A) Indicates projects with insufficient information but may be suitable for Bulk Water Supply.
(B) Indicates projects being evaluated by dam owners ie SEQWB and GCCC.
NOTE: Comments are in the main based on information contained in reports published in the 1990's and data may no longer be accurate.
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
PROJECTS WITH POTENTIAL YIELD BETWEEN 5,000 ML/a AND 20,000 ML/a
Summary Projects
Cost ($million)
Yield(ML/a) $/ML/a
Comment
Albert River - Cainbable Creek
AMTD 71 km
Albert River - Nindooinbah
AMTD 9.9 km
Capacity 16,000 ML
(Reference 6)
6,000 Glendower preferred.
Amamoor Creek Dam
AMTD 19.2 km
FSL 145 m
Capacity 220,000 ML
(Reference 1, 5 and 9)
11217,000
(Nofailure)
Relatively undisturbed native forest.
Plumed frogmouth.
Mary river cod.
6 residents.
Brisbane River - Cooyar Creek
AMTD 12.4km
Capacity 185,000 ML
(Reference 6)
12,000
Linville gives greater yield.
Potential for local supply but not of regional significance.
Brisbane River – Emu Creek
AMTD 52.5 km
Capacity 60,000 ML
(Reference 6)
11,000 to 17,700(Eastern Downs Urban Water Supply Appraisal)
Incremental yield is insufficient to be of regional significance but individual projects could be of local significance to reduce transfer costs or to manage other water distribution options.
Eucalypt forest.
Five known rare/threatened species.
Population.
Detracts from Wivenhoe yield.
Low yield at Crosby Weir (nearby).
Caboolture Creek – River Junction
AMTD 39
(Reference 6)
<10,000
Damsite unsuitable to give yield 10,000 ML.
River uncontrolled.
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
PROJECTS WITH POTENTIAL YIELD BETWEEN 5,000 ML/a AND 20,000 ML/a
Summary Projects
Cost ($million) $/ML/a
Comment Yield
(ML/a)
Caboolture River - Haussmans
AMTD 31.0 km
(Reference 6)
<10,000
Damsite unsuitable to give yield 10,000 ML.
River uncontrolled
Caboolture River - Zillmans Crossing
AMTD 36.4 km
FSL 73 m
Capacity 70,000 ML
(Reference 6)
158
13,680
(Nofailure)
14,500
(1% PMFR)
10,919
Most of ponded area cleared for agriculture.
100 ha disturbed.
Eucalypt forest.
Fish.
Water Quality.
Axe grinding site.
96 residents.
Five known, one likely rare/threatened species.
River uncontrolled.
Strategically located for demand.
Cedar Grove Weir without Wyaralong
(Reference 4) 6,500
Local significance but not of regional significance.
Christmas Creek
Capacity 20,000 ML
(Reference 6)
11,800 Feasibility questioned
Coles Crossing Weir
Capacity 3,897 ML
(Reference 3)
13 7,600 1,711
Being considered for local water supply and is of no regional significance.
Lake Manchester, Enoggera and Gold Creek Dams (Reference 6) 12,000
Not being utilised.
Minor regional significance.
Possible emergency supply during severe droughts.
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
PROJECTS WITH POTENTIAL YIELD BETWEEN 5,000 ML/a AND 20,000 ML/a
Summary Projects
Cost ($million) $/ML/a
Comment Yield
(ML/a)
Mary River - Moy Pocket Weir
AMTD 244.0 km
Capacity 5,000 ML
(Reference 3)
7,600
The cost of Moy pocket weir is higher than Coles Crossing Weir.
Probably has better foundations and bank stability then Coles Crossing site.
Mudgerabah Creek- Neranwood
AMTD 21.1km
FSL 110
Capacity 117 000 ML
(Reference 6)
277 17,250 16,062
Ponded area generally cleared.
Fish.
Canal estate flushing?
Water Quality.
No archaeological or historic sites known.
204 residents affected.
Eucalypt forest.
One known, four likely rare/threatened species.
Vegetation and wildlife low impact.
River mod-low.
Flood mitigation benefit.
Strategically located in demand area.
Very high social cost.
Neranwood
(Reference 4) 155 13,000 11,891
Local significance but not of regional significance.
Neurem Creek Dam upstream of Kilcoy
AMTD 16.1 km and weir AMTD 12.1 km
Capacity 25000 ML
(Reference 6)
10,000 Offers some potential.
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
PROJECTS WITH POTENTIAL YIELD BETWEEN 5,000 ML/a AND 20,000 ML/a
Summary Projects
Cost ($million) $/ML/a
Comment Yield
(ML/a)
Maroochy River - Raising Wappa Dam
FSL 44.8 to 80 m
Capacity 4600 to 95000 ML
(Reference 1 and 5)
19719,700
(Unknown % PMFR)
9,990
Skyring Creek
AMTD 10.3 km
Capacity 30000 ML
(Reference 5)
10,000Amamoor Creek dam preferred.
South Pine River - Cashs Crossing
AMTD 14 km
72,600 ML
(Reference 6)
25,700
Eucalypt wetland.
Two known, two likely rare/threatened species.
Wetland may be of scientific interest.
River uncontrolled.
Potential to supply part of study area.
Very high social cost.
South Pine River - Greenwood
AMTD 19.5 km
FSL 50 Capacity
65900 ML
(Reference 6)
451 18,220 24,766
Eucalypt wetland.
Two known, two likely rare/threatened species.
Wetland may be of scientific interest.
River uncontrolled.
Potential to supply part of study area.
Very high social cost.
Teviot Brook – The Overflow
AMTD 22.2 km ? Not of regional significance.
Water Harvesting into Cooloolabin Dam (Reference 1) 0
Being considered for local water supply and is of no regional significance
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
PROJECTS WITH POTENTIAL YIELD BETWEEN 5,000 ML/a AND 20,000 ML/a
Summary Projects
Cost ($million) $/ML/a
Comment Yield
(ML/a)
Water Harvesting from Mary River into Borumba Dam 20 7,600 2,665
Being considered for local water supply and is of no regional significance.
May not be cost effective.
Wide Bay Creek
AMTD 30.4 km
(Reference 5)
??Amamoor Creek dam preferred.
Wide Bay Creek
AMTD 36.2 km
Capacity 100000 ML
(Reference 5)
25,000Amamoor Creek dam preferred.
Widgee Creek
(Reference 5) ??
Amamoor Creek dam preferred.
Legend
Bold Text and shaded cells indicate projects recommended for further evaluation under the desk top review as summarised in Table 1.
NOTE: Comments are in the main based on information contained in reports published in the 1990's and data may no longer be accurate.
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
PROJECTS WITH POTENTIAL YIELD LESS THAN 5,000 ML/a
Summary Projects
Cost ($million)
Yield(ML/a) $/ML/a
Comment
Additional allocation from Baroon Pocket Dam
(Reference 3) 0 ?
Supply exceeds short-term needs.
Allocation of unsold water from Borumba Stage II
(Reference 3) ? ?
Conversion to high priority water uncertain.
May be suitable for local supply but not regional.
Bremer River
AMTD 25.9km
(Reference 17)
?
Bremer River - Mt Walker
AMTD 69.8 km
60,000ML
(Reference 6 and 10)
5,100May be suitable for local supply but not regional.
Ewen Maddock Dam
(Return to service)
(Reference 1, 2, 3, 4, and 6)
5,000 0 Return to service.
Kandanga Creek
AMTD 12.2 km
(Reference 5)
??May be suitable for local supply but not regional.
Kandanga Creek
AMTD 21.4 km
(Reference 5)
??
Kandanga Creek
AMTD 28.5 km
(Reference 5)
??
Large off stream storages D/S Coles Crossing
2700 ML
(Reference 3 and 7) 5 3,000
May be suitable for local supply but not regional.
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
PROJECTS WITH POTENTIAL YIELD LESS THAN 5,000 ML/a
Summary Projects
$/ML/aComment
Cost ($million)
Yield(ML/a)
Large off stream storages near Degans Pocket
(Reference 3 and 7) ? ?
May be suitable for local supply but not regional.
Large off stream storages D/S Yabba Creek
2700 ML
(Reference 3 and 7)
5 3,000May be suitable for local supply but not regional.
Lockyer Valley - Laidley creek
AMTD 50.5 (51) km
24,600ML
(Reference 6)
May also be contained in Reference 11
3,500May be suitable for local supply but not regional.
Lockyer Valley - Laidley creek
AMTD 110.1 km
39,400 ML
(Reference 6)
May also be contained in Reference 11
4,700May be suitable for local supply but not regional.
Lockyer Valley - Ma Ma Creek
AMTD 20.2 (21.9) km
24700 ML
(Reference 6)
May also be contained in Reference 11
4,900May be suitable for local supply but not regional.
Lockyer Valley - Tenthill Creek
AMTD 29.8 km
46,700 ML
(Reference 6)
May also be contained in Reference 11
5,400May be suitable for local supply but not regional.
Maroochy River
(Reference 6) ?
May be suitable for local supply but not regional.
Small Weirs on Mary River between AMTD 178.3 km and 185 km
(Reference 3) 1 500May be suitable for local supply but not regional.
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
PROJECTS WITH POTENTIAL YIELD LESS THAN 5,000 ML/a
Summary Projects
$/ML/aComment
Cost ($million)
Yield(ML/a)
Middle Creek
AMTD 1.3 km
Capacity 20,000 ML (Reference 16)
5,000May be suitable for local supply but not regional.
Munna Creek
AMTD 36.0 km
(Reference 5)
??
Noosa Shire apply for extra supply from Lake MacDonald
(Reference 3) 0 ?
High priority but only in drought?
May be suitable for local supply but not regional.
Noosa River?
(Reference 6) ?
May be suitable for local supply but not regional.
Raise Baroon Pocket Dam
5m to FSL 222
Capacity 82000 ML
(Reference 5)
3,000May be suitable for local supply but not regional.
Small off stream storages
(Reference 3) ??
May be suitable for local supply but not regional.
Stanley River at Peachester
AMTD 86.2 km
(Reference 6)
??
Detracts from Wivenhoe yield.
322 people affected.
Rain Forest.
Eucalypt.
1 known 2 likely rare/threatened species.
State forest and private land.
Department of Fisheries wish to stock with Mary River Cod.
Reduce yield from Somerset divert to Caboolture.
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy
PROJECTS WITH POTENTIAL YIELD LESS THAN 5,000 ML/a
Summary Projects
$/ML/aComment
Cost ($million)
Yield(ML/a)
May be suitable for local supply but not regional.
Teviot Brook – Croftby
AMTD 83.3 km
(Reference 6)
?
Teviot Brook
AMTD 88.3 km
(Reference 6)
4,825
May be suitable for local supply but not regional.
Tinana Creek Weir?
(Reference 5 and 13) ?
Suitable for local supply but not regional.
Warril Creek
(Reference 6) ? Unlikely to be developed.
Westbrook Creek
Dam and Pump Storage?
(Reference 15)
? ".
Likely to be too small a supply to be of regional significance.
Legend
Bold Text and shaded cells indicate projects recommended for further evaluation under the desk top review as summarised in Table 1.
NOTE: Comments are in the main based on information contained in reports published in the 1990's and data may no longer be accurate.
41/14840/333302 South East Queensland Regional Water Supply Strategy Bulk Supply Infrastructure Task Group Desk Top Review and TOR Development Consultancy