an xl project goes smoothly
TRANSCRIPT
government
AN XL PROJECT GOES SMOOTHLY EPA9s oft-criticized Project XL hits success with OSi Specialties by being small, focused
David J. Hanson C&EN Washington
U nder pressure to give the U.S. manufacturing industry some relief to burdensome regulations,
the Environmental Protection Agency set up Project XL in March 1995 as a way of increasing environmental protection and saving time and money for industry. In exchange for "superior environmental performance," EPA would be flexible with enforcement of some regulations.
It has been rough going for Project XL. Although more than two years have passed since its establishment, the agency has been able to complete only five XL agreements. Companies trying to participate have been faced with many roadblocks, not the least of which has been some inflexibility by EPA and sometimes smothering stakeholder involvement. But the latest XL agreement, with OSi Specialties, may hold some clues for improving the process for other companies.
OSi Specialties, a subsidiary of Witco Corp., has a single facility, a $450 mil-lion-per-year organo-silicone operation in Sistersville, W.Va., on the Ohio River. The plant produces a family of chemicals used in products ranging from electronic equipment, space technology, and automotive production to paints, polishes, and cosmetics.
According to OSi Environmental Technology Manager Okey G. Tucker, the plant became interested in doing an XL project because it had recently completed another environmental regulatory project that had actually benefited the environment very little.
A few years ago, OSi was forced to install pollution control devices on one of its process units in Sistersville to remove methyl chloride and ethyl chloride from wastewater. The control consisted of stripping the chemicals from the water and simply venting them into the air. "We would be transferring maybe 10 lb per day of these chemicals from the wa
ter to the air," Tucker says. "It cost us close to $2 million to do that."
By 1995, OSi was coming under the regulatory gun with respect to air emissions from surface impoundments it was using for its wastewater. Under the Resource Conservation & Recovery Act (RCRA), specifically subpart CC, these impoundments cannot release hazardous air pollutants. The regulation required that OSi put a cover over the impoundments and recover 95% of the emissions. The company was facing a December 1997 deadline for a commitment to do this. But because of the difficulty in covering the large impoundments, OSi could achieve compliance with the law by simply replacing the impoundments with aboveground storage tanks. According to Tucker, it would cost OSi about $2.5 million to build these tanks, and there would be no environmental benefit achieved at all.
The situation was compounded because by 2002, even surface tanks are expected to be required to have emission controls under regulations required by the Miscellaneous Organic National Emission Standards for Hazardous Air Pollutants, or MON, which is part of the Clean Air Act. So OSi needed a way to defer this control cost while at the same time cutting pollution enough to satisfy EPA.
The company also faced having to
comply with a section of the Clean Air Act if it tried to recover any hazardous chemicals from its waste stream. This section, subpart YYY, is ambiguous on whether OSi would fall under the requirements, but it could require the company to install expensive at-source controls and place a cover over its entire sewer system at an additional cost of $2.5 million. Faced with these regulatory problems, the company believed it could get some relief from the XL program.
"We looked around the plant for some other way to reduce pollution and found a source that we felt was a more promising idea," Tucker says. OSi has a process unit called a methyl capper, a two-step reactor that combines polyethylene oxide and polypropylene oxide ethers with excess methyl chloride to produce a methyl "capped" polyether. The unused methyl chloride is vented into the atmosphere. Tucker says there are no air pollution control regulations on this unit because it was in operation at the time the regulations were made and its pollution was grandfathered into the system. It releases an estimated 277,000 lb of methyl chloride annually.
The initial XL proposal to EPA would have put emission controls on the methyl capper unit to reduce methyl chloride emissions. This would be in turn for a deferral of the RCRA regulations that would have forced the company to build tanks for its surface impoundments. "In May 1996, after two or three revisions to the proposal based on suggestions from and discussions with EPA, the agency accepted our proposal to go forward with an XL project," Tucker says.
The company's initiative for regulatory relief from EPA was reinforced when Witco Corp. acquired OSi near the end of 1995, just as the company was prepar-
Air pollution and sludge are cut under OSi deal
Lb per year
Total air emissions under XL Air emissions from
capper unit Air emissions from
water treatment unit Organic discharges
from capper unit Sludge generated
by capper organics
Current
417,300
277,000
140,300
790,000
1,177,300
With XL
108,300
6,300
102,000
389,000
610,000
Without XL
417,300
277,000
140,300
940,000
1,425,000
Reduction due to XL
309,000
271,000
38,000
551,000
815,000
Note: Air emissions reductions are from thermal oxidizer on capper unit that destroys excess methyl chloride. Organic and sludge reductions are achieved by capturing methanol by-product from capper unit that currently goes into the plant's wastewater treatment unit. Source: Witco
18 DECEMBER 8, 1997 C&EN
ing its first proposal. Tucker says Witco was supportive of the project and provided OSi with valuable legal counsel. Witco Chief Executive Officer E. Gary Cook even traveled to the plant to personally sign off on the final agreement.
Witco Senior Attorney James A. Nortz says the decision by Witco to go ahead with the project was based on its economic potential. "We were pleased that OSi had been able to come up with a good idea for an XL proposal," Nortz says. "But if it hadn't made economic sense, we wouldn't have done it."
Cheryl Atkinson, an environmental engineer with EPA at Region m in Philadelphia who has worked with EPA headquarters and OSi on this XL project from the start, says when companies start these kinds of projects, they usually don't realize how much time it will take. "The original proposal has to go to headquarters where it is screened," she says. "Then it goes to the region where more people look at it to see if it is worth going forward with. I think the company can get a litde frustrated with this because it takes about a year before we are finally getting ready to sit down and talk." She adds that Project XL is still an experiment and that EPA is very cautious about approving any changes in its regulations.
The OSi proposal stated that the company was going to replace the old capper unit with a new, larger process unit, and that the emissions controlled from this capper would more than make up for the smaller emissions from the surface impoundments. The company was also going to recover methanol, which is produced by the capper as a by-product of the process, and make it available for recycling or reuse. According to Tucker, the numbers were straightforward, and the company expected the negotiations with EPA to proceed smoothly.
But a change in corporate plans almost scuttled the whole deal. OSi decided that the market didn't warrant expanded production and the company decided to keep its' old unit.
"We thought that was going to be the end of it," Atkinson says. "But OSi said that no, it still had the old unit and wanted to try some other things. At the time, it seemed like an insurmountable hurdle, but in time we worked it through."
"By November 1996, when we looked to be close to a final agreement, we decided not to build the new capper and that changed our project," Tucker confirms. "So we had to step back and find other ways for pollution reduction and waste
minimization [to occur] in place of the original plan." He says EPA pressed for more commitments for pollution reduction, and the company finally came up with a proposal to have a complete study of the waste streams generated at the plant, and an evaluation of any additional pollution prevention opportunities that were economically feasible. This then became part of the XL project.
The new plan called for the company to install by April 1998 a thermal oxidizing unit, essentially an incinerator, on the existing methyl capper unit that would destroy the excess methyl chloride currently being vented into the air. The company also would recover by-product methanol from the unit and offer it for reuse. The reduction in methanol that was going to the company's wastewater treatment unit also would result in a decrease in the amount of sludge generated there. That, too, was seen as a plus. And an outside consultant would do an evaluation of the plant's waste streams.
One of the primary components of any Project XL negotiation is input from the surrounding community. This stakeholder participation is supposed to make the final plans acceptable to all people who might be affected by the changes proposed. In some complicated Project XL negotiations, the stakeholder involvement can just about bring the process to a halt because of competing interests.
But the OSi project did not have these problems. "We are located in a very rural setting," Tucker says. "It's a small county in West Virginia, and we don't have a lot of neighbors." The company tried to generate some public interest in the project, but got little reaction. There were newsletters mailed and numerous advertisements in newspapers and on local radio stations announcing several public meetings. But when the meetings were held, essentially no one came.
EPA pushed OSi on this matter as strongly as it could, according to Atkinson, because the agency strongly believes that stakeholder participation is necessary for a successful XL project. "I think the community was just not too interested," concludes Atkinson, "because they thought it seemed like a good idea. There was one local environmental group that showed a little interest, but it concluded [the project] was a good idea and said to go for it."
The OSi project had some advantages over other XL projects. Foremost, it was a straightforward plan for reducing emissions that involved few regulations.
"From a technical perspective, this is a pretty tight project," Atkinson says. "The one regulation [OSi is] asking for exemption from is clear and not controversial. And for that exemption, they are putting on a control device. I think it's really that simple."
Tucker agrees with this assessment. "I think it was because we did not try to do a lot of the plantwide permitting that many of the XL projects are attempting," he says. "I think that is what a lot of the environmental groups have trouble with. And they understood the regulations clearly enough to know that we could put in the surface tanks and not be required to control any emissions."
The advantage of this project to OSi is in the deferral of the RCRA regulations for at least five years and the likelihood that it would be in compliance with future regulations under the Clean Air Act because of the methanol recovery. Tucker indicates that by spending about $600,000 now to have the thermal oxidizer built into the capper unit and recycling the methanol to another user, the company expects to save about $800,000 in the long term, based on capital cost estimates.
Despite the relative ease of this XL project, OSi still thinks EPA has made the process more difficult than it has to be. "There are so many agency people involved," Tucker says. "We had people from the air group, the RCRA group, the water group, and from the Office of General Counsel. The people themselves have been good to work with, but the regulatory process seems to have a stranglehold on them. We also had a lot of personnel changes during the negotiations. We would reach some agreement with an EPA person and then have to deal with someone new coming in with different ideas." Tucker says the EPA people are sometimes very protective of the regulations and seem to have little to offer in the way of flexibility. "EPA is not really ready to reinvent regulations. This is really more regulatory reapplication."
In the long run, this huge commitment of time and people on the part of EPA could lead to Project XL's end. Witco attorney Nortz says he is astounded by the time and personnel devoted to this project and doubts the government can keep up this kind of commitment in the face of such relatively small environmental improvements. "It is enormously burdensome for the government to do this," Nortz says. "Unless they can think of a more efficient way to do it, I'd be surprised if the program survives."^
DECEMBER 8, 1997 C&EN 19