CASE STUDY Executive Summary Sales Order Scheduling for an advanced memory manufacturer was performed using the GATP components of allocation and rules-based availability check. Customer allocations could be at a monthly or weekly level, which was determined by the MRP type. Allocation check was performed at two levels i.e. Customer Entity and Customer Sales division. Certain products such as Solid State Drive (SSD) would have customer allocation and also the capacity allocation of the assembly line. After the allocation check was successful, then the ATP was carried out using RBA. Customization was built-in during RBA check to check the week-wise supply. Standard GATP check results would have multiple schedule lines for the sales order ATP check. The customer wanted to suppress multiple schedule lines. A lot of customization was built in ECC and APO to handle this business requirement. The Customer The advanced memory manufacturer technology designs and builds some of the world’s most advanced memory and semiconductor technologies for products from computing, networking, and server applications, to mobile, embedded, consumer, automotive, and industrial designs. The Business Objective The customer was using legacy ATP application (Adexa) for order scheduling. Orders were sent to these applications along the customer requirements in the form of attributes. They needed an application that could perform availability check across the entire supply chain by handling multiple products, in a rules based substitution. www.hcltech.com Allocation management & global ATP for an advanced memory manufacturer

Upload: others

Post on 05-Mar-2020

28 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Allocation management & global ATP for an advanced …...• SAP APO SNP (Supply Planning) • SAP ECC (ERP) • SAP APO DP (Demand Planning) • Legacy system for in house WIP •

CASE STUDY

Executive SummarySales Order Scheduling for an advanced memory manufacturer was performed using the GATP components of allocation and rules-based availability check. Customer allocations could be at a monthly or weekly level, which was determined by the MRP type. Allocation check was performed at two levels i.e. Customer Entity and Customer Sales division. Certain products such as Solid State Drive (SSD) would have customer allocation and also the capacity allocation of the assembly line. After the allocation check was successful, then the ATP was carried out using RBA. Customization was built-in during RBA check to check the week-wise supply. Standard GATP check results would have multiple schedule lines for the sales order ATP check. The customer wanted to suppress multiple schedule lines. A lot of customization was built in ECC and APO to handle this business requirement.

The CustomerThe advanced memory manufacturer technology designs and builds some of the world’s most advanced memory and semiconductor technologies for products from computing, networking, and server applications, to mobile, embedded, consumer, automotive, and industrial designs.

The Business ObjectiveThe customer was using legacy ATP application (Adexa) for order scheduling. Orders were sent to these applications along the customer requirements in the form of attributes. They needed an application that could perform availability check across the entire supply chain by handling multiple products, in a rules based substitution.

www.hcltech.com

Allocation management & global ATP for an advanced memory manufacturer

Page 2: Allocation management & global ATP for an advanced …...• SAP APO SNP (Supply Planning) • SAP ECC (ERP) • SAP APO DP (Demand Planning) • Legacy system for in house WIP •

CASE STUDY

• ATP model should consist of product and customer allocation, capacity allocation as well as rules based product substitutions.

• Standard GATP check confirmation results would have multiple schedule lines but the need was to suppress multiple schedule lines and have only one schedule line per confirmation.

• Order re-scheduling had to be performed with options for order selection and sorting of line items.

• Delivery scheduling need not pass through GATP check but would need validation of the customer requirements and the rules i.e. product substitutions.

• Establish following ATP metrics:

– On-time delivery performance—confirm to the promised dates

– Demand and supply match

– Counter delivery failures due to attributes mismatch

HCL Solution• SAP APO SNP (Supply Planning)

• SAP ECC (ERP)

• SAP APO DP (Demand Planning)

• Legacy system for in house WIP

• Serus third-party system for subcontractor location WIP

• Available to promise using SAP GATP

What HCL did for the customerTo address the need for an application that could perform availability check across the entire supply chain by handling multiple products, in a rules-based substitution, HCL offered and performed the following solutions:

• Perform availability check across the entire supply chain.

• Customer requirement attributes are modeled by handling multiple products. GATP rules based substitution is enabled to handle this requirement.

• Products that are relevant for GATP check are identified by the MRP type. CIF handles transfers of products, ATP, and sales orders that are relevant for GATP.

• GATP model consists of two checks that have to pass before a commit date for the sales order.

– The first check is to pass the allocation. Customer allocations could be maintained at a monthly or weekly level. MRP type determines the allocation model, replenishment lead time and also the receipts elements that are relevant for ATP check. Products which have monthly and weekly allocation model, have the customer allocation maintained at customer entity and customer sales division at a monthly and weekly level. Demand planning macro copies the allocation values from the DP planning book to the Product allocation group. At the end of the week, rollover macro is run in demand planning to move the allocation in product allocations in the next work week. HCL’s allocation accelerator is utilized for maintaining the allocations. Some products have the customer allocations as well as the capacity allocations. Capacity allocations are maintained at daily level to model the assembly line capacity.

Page 3: Allocation management & global ATP for an advanced …...• SAP APO SNP (Supply Planning) • SAP ECC (ERP) • SAP APO DP (Demand Planning) • Legacy system for in house WIP •

CASE STUDY

– After the allocation check is successful, ATP check is performed using rules based product substitutions. ATP check has stock, receipts and requirements. Product with allocation modeling will have the receipts planned from CTM, WIP and in-transit. Receipts will be ignored for products with weekly allocation models. A custom application is built in ECC for maintaining rules. This application creates product substitutions, rules and rule determination records in APO through a rule Job. Rule identification (Rule-id) is passed to APO through the field catalogue user exit and this is utilized for identifying the substitutions that are relevant for the customer.

– Availability check is limited to check supplies by week through a customized solution. Standard GATP check confirmation results will have multiple schedule lines. The need is to suppress multiple schedule lines and have only one schedule line per confirmation. Since there are multiple schedule lines, we create them as individual line items per schedule line confirmation. This functionality is achieved by enabling core-modification in ECC.

– Order rescheduling is performed using GATP BOP component. Customization is built for order selection and sorting of line items. Back-order processing is performed on daily basis for confirmed line items. Weekly BOP takes care of sales order lines i.e. items with and without confirmation.

– Delivery scheduling does not pass through GATP check in APO. Instead a customization application is built in ECC which validates the customer requirements and the rules, i.e. product substitutions.

MPS

Shop FloorPlan

ConfirmedDate

ConsumedATP

ATPPlan

Capacity Allocated Demand

ATP Request

Delivery Confirmation

Judged Demand

Demand Feedback

Demand

APO DPForecast Allocation Planning

Supply Plan

Allocation Management

Global Available to Promise

(ATP)

Order Management

P.O EntryPurchaseOrder Output Planning

Manufacturing Planning & Execution

ConfirmedDate

The Business Benefits Delivered• Real-time confirmations–able to provide a date and quantity at the time of order booking

even if that is not the final/best date

• Back order processing–to update order confirmations as changes to supply and demand occur, because companies run BOP on a daily basis. This resets (where needed) the confirmation based on flexible sorting criteria.

• Management of order scheduling through allocation and order management

• GATP check having order commitments, and delivery date and material availability in the sales order line item

• Original promise date, custom Material availability date and custom request are captured after the ATP check

• Date and quantity confirmation of orders at the time of booking, especially if any order is processed manually directly in ECC

Page 4: Allocation management & global ATP for an advanced …...• SAP APO SNP (Supply Planning) • SAP ECC (ERP) • SAP APO DP (Demand Planning) • Legacy system for in house WIP •

• Order back log having the orders with allocation confirmation and also the supply confirmation

• For large orders, commit updates done via standard back-order processing and native real-time updates of the sales order via the core interface

• Change in orders does not wipe out the previous confirmation but merely update the CRD or requested quantity triggering a review process

• Integration with ECC for master and transaction data

• ATP metrics to measure:

– On-time delivery performance—confirm to original promise dates

– Demand and supply match

– Countered delivery failures due to attributes mismatch

Hello there! I am an Ideapreneur. I believe that sustainable business outcomes are driven by relationships nurtured through values like trust, transparency and flexibility. I respect the contract, but believe in going beyond through collaboration, applied innovation and new generation partnership models that put your interest above everything else. Right now 100,000 Ideapreneurs are in a Relationship Beyond the Contract™ with 500 customers in 31 countries. How can I help you?