AIESEC International Q1 2015 Report
PROJECT/SUBTEAM BOTTOMLINE -‐ New BD product por/olio -‐ completed -‐ Revenue generated to achieve financial sustainability (BD goal, 604,000) -‐ 1 million people reached YouthSpeak Pla/orm + website evolved into
pla/orm -‐ 3 new partnerships created
PEOPLE INVOLVED Tala :Project Coordiantion (20%) YouthSpeak Forums + Survey (40%), Global Parterships (40%) Laura: Network support (100%) Gordon: YouthSpeak Survey & Platform (100%) Karolina: YouthSpeak Forums (60%), Global Partnerships (40%) Orion: BD Product Evolution (100%)
Picture of your project or sub-team
results
AIESEC International Q1 2015 Report
COMMENTS Partnerships: • GMAC Launched at all XPROs (Kevin) • Teach For All (Global NGO) Partnership – in the final stages • Unilever Global GCDP Project – in the final stages • Negotiation with 4-5 MNCs YouthSpeak: • YouthSpeak Forums delivered at IPM, APC, EuroXpro were successful and required much capacity – IPM Report is done • IC Agenda is completed, secured Host and 4 partners (GPP, Teach for All, UN Millenium Campaign, Morgan Stanley) • Evolving the website to include more than the survey wil require more capacity and budget (major focus for Q4)
Goal Name Planned Achieved %
YouthSpeak Forums 3 3 100%
2.0 Survey Launched 1 1 100%
Partnerships Created 1 0 50%
People reached via platform
N/A N/A N/A
OUTCOMES
AIESEC International Q1 2015 Report
Q1 MILESTONES CHECK
YouthSpeak Forums (achieved)
YouthSpeak Survey 2.0 (achieved) BD Portfolio YouthSpeak Platform
• Delivered 3 YouthSpeak Forums at IPM, APC, EuroXPro.
• Partnership Deliverables all complete
• Led change management process (new branding, social media)
• IPM Report complted • IC Agenda completed, concept
note completed • Recruited 2 new GSTs to
support with PR in US and overall guideline creation for forums to support the network
• Estbalished partnership with ThinkYoung – all data analysis for the report
• Created the campaign for YouthSpeak 2.0 Launch
• Decided to go ahead without Unilever questions
• Created 1.0 version of PwC report
• All stages of the product
development completed (research, entity insight)
• Project ievolved into 2 key things – revamp current portolfio & create custom portolios for regional markets (such as Africa)
• Some information from Y2B website has migrated
OUTCOMES
AIESEC International Q1 2015 Report
Q1 MILESTONES CHECK
AIESEC Ecosystem New Global Partnerships
• ER theme objectives defined • Consultancy delivered at IPM • Sessions delivered at IPM and
XPROs • Recruited 1 GST to work on all
the guideliens in Q4 • Working closely with 3 entities
to role model and pilot
• On track to achieve BD Goal • Closing stage with 4-5 MNCs • New partnership with GMAC • New partnership with Teach for
All
OUTCOMES
AIESEC International Q1 2015 Report
MAIN KPIs MONITORING
• Since not all the workshops and spaces were filled at XPROs, we changed around the agendas to accomodate.
• Deliverables for YouthSpeak forum were completed for partners – last one is reporting. • No KPI monitering was done for YouthSpeak platform reach because we did not create the new platform.
KPI Planned Achieved % YouthSpeak Reach N/A N/A N/A
New Partnerships 4 1 25%
YouthSpeak Forum Deliverables 100% 90% 90%
Revenue 604.000 580.000 85%
All spaces at YSFs were filled 100% 80% 80%
efforts
AIESEC International Q1 2015 Report
ACTIVITIES OVERVIEW
COMMENTS • We need to review all budgets for the projects – especially the platform and IC YouthSpeak Forum because right now we
are under budget for both in order to deliver the activites planned. • IC serves as an opportunity to close the deal for many negotiations for partners, as well as a fantastic entry point to
engaging with AIESEC – therefore it will continue to remain a huge priority and it is a goal to have the event 100% fully ready to be delivered by AI 15-16.
• BD Portfolio creation will be created.
January- March had a huge focus on YouthSpeak forums – between delivering 3 different forums and also planning and inviting high level people to IC in India, it required much capacity and will continue to require much effort from different people. There was not enough capacity or resources to invest in evolving the YouthSpeak website into a platform, including all the migration of data and resources, however it will be a big priority for the next 3 months.
Q2 2015 plan
AIESEC International Q1 2015 Report
RESULTS
MAIN ACTIVITIES • Huge campaign launch for YouthSpeak 2.0 survey • Web developers and GSTs working on the YouthSpeak
platform, data migration, and content, guidelines for entities about YouthSpeak as a concept
• Partnership closing and sales for IC
Goal Name Planned Achieved %
New Partnerships 3 1 30%
YouthSpeak Platform Completion 1 1 0%
New BD Portfolio 1 1 30%
# of Projects out of YSF 3 N/A
Partners for IC YSF (2015) 12 6 50%
MILESTONES • Final sales wave (move along from negotiation to
closed/committed) • Fill all the workshop spaces for IC and have the forum
100% logistically planned • Reach out target for 50,000 responses in the survey
KPIs
Goal Name Planned Achieved %
YouthSpeak Survey 50,000 27,000 54%
Focus entities with growth in YouthSpeak
100%