ALEXANDER HAMILTON BRIDGE ALEXANDER HAMILTON BRIDGE RECONSTRUCTION PROJECTRECONSTRUCTION PROJECT
D260888 - X72681
Rehabilitation of the I-95 Corridor and Interchange with I-87 between
Amsterdam Avenue and Undercliff Avenue
New York State Department of TransportationRegion 11
Joan McDonald, CommissionerPhillip Eng P.E., Regional Director
State of New York
Governor Andrew Cuomo
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Meeting AgendaMeeting Agenda
I. Background/ Project HistoryII. Scope/ Elements of WorkIII. Current WorkIV. Future WorkV. Modifications to Original DesignsVI. Project Management Tools
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
The Project TeamThe Project Team• Area Construction Supervisor
– Manny Silva, NYSDOT• Engineer in Charge
– Mike McCotter, NYSDOT• Resident Engineer
– Albert Pozotrigo, M&J Eng. Ammann & Whitney Group• Contractor
– CCA Civil/Halmar International LLC• Community Liaison
– Kaitlyn Pezik, Zetlin Strategic Communications
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton BridgeAlexander Hamilton Bridge
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton Bridge MainlineAlexander Hamilton Bridge Mainline
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton Bridge MainlineAlexander Hamilton Bridge Mainline
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Background/Project HistoryBackground/Project History
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
I-87
Alexander Hamilton Bridge
George Washington Bridge181st Street Bridge
LocationLocation
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton Bridge HistoryAlexander Hamilton Bridge HistoryA new eight-lane arch span was
proposed - the Alexander Hamilton Bridge – to connect the Trans-Manhattan and Cross-Bronx
Expressways.
Currently, estimated traffic over the Hamilton Bridge is over 188,000 vehicles
per day.
The Alexander Hamilton Bridge has not undergone
major repair since it opened on January 15, 1963.
In 1955, Robert Moses determined that the 181st Street Bridge would not be able
handle the anticipated traffic demands from the proposed lower level of the
George Washington Bridge.
Information source: NYCRoads.com
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
• Final Design began: Winter 2002• Original Letting: March 29, 2007 (No Bidders)• NYSDOT redesigned temporary structures and
repackaged contract documents• 2nd Letting Date: January 22, 2009
Lowest Bidder- CCA Civil/ Halmar International $407 Million
• Construction Began: Spring 2009• Substantial Completion of Construction Work:
Winter 2013/2014– Approximately 55% completed
History of the ProjectHistory of the Project
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
• Alexander Hamilton Bridge (I-95)– Maintain All Through Lanes(other than night-time 12:01 am to 5:30 am)
• Highbridge Interchange - Ramps “A” & “D”- Maintain all lanes other than for lane shifts
• Weekend closures at nighttime only for lane shifts• Undercliff Avenue Bridge – No long term closure
(staged construction)• Ramp TE- Full Detour for Ramp Closure
Work Zone Traffic Control (MPT)Work Zone Traffic Control (MPT)
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Scope/Elements of WorkScope/Elements of Work
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
• Remove and replace existing deck• Fill in median framing• Widen deck by 11’ each side• Continuity splices in approach spans – make 2 span
continuous• Some floorbeam and stringer replacement• Eliminate some deck joints – reduce number of deck joints by
50% • Construct new cap beams at piers• Replace bearings • Repair substructure concrete• Retrofit substructure to meet current seismic requirements • Paint steel superstructure • Replace drainage, overhead sign structures & lighting
Alexander Hamilton Bridge Alexander Hamilton Bridge Reconstruction Scope of WorkReconstruction Scope of Work
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Existing Width: 115 ft.
Proposed Width: 137 ft.
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Construction Stages on the Construction Stages on the DeckDeck
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Arch reinforcement
Spandrel Column
reinforcement
Expansion Joint Elimination
Alexander Hamilton Bridge Alexander Hamilton Bridge Structural Modifications-Arch Structural Modifications-Arch
SpanSpan
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
2 span continuous
2 span continuous
2 span continuous
Alexander Hamilton Bridge Alexander Hamilton Bridge Structural Modifications-East Structural Modifications-East
ApproachApproach
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
2 span continuous
Alexander Hamilton Bridge Alexander Hamilton Bridge Structural Modifications-West Structural Modifications-West
ApproachApproach
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Highbridge Interchange Highbridge Interchange RampsRamps
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Ramp B
(R.H. Side)
Ramp Ramp DD
Ramp F
Ramp A
Ramp L
(L.H. Side)
Highbridge Interchange RampsHighbridge Interchange Ramps
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
• Provide temporary bridges adjacent to existing ramps to take traffic during construction
• Remove existing deck • Replace deck with new Cast-in-Place deck• Widen deck by 1’-9” each side – 2 sections of ramp• Replace deck in-kind – other sections of ramp • Replace bearings • Repair substructure concrete• Retrofit substructure to meet current seismic
requirements• Replace drainage, overhead sign structures &
lighting• Paint superstructure steel
Highbridge Ramps Scope of Highbridge Ramps Scope of WorkWork
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Ramp F: RedRamp A: BlueRamp D: Yellow
Highbridge Ramps Temporary Highbridge Ramps Temporary StructuresStructures
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Undercliff Avenue BridgeUndercliff Avenue Bridge
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
• Demolish existing 2 span concrete arch• Complete bridge replacement with single
span multi-stringer bridge• Relocate existing utilities
• Water Main• Electric• Gas
• Replace drainage & lighting
Undercliff Avenue Bridge Undercliff Avenue Bridge Scope of WorkScope of Work
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Undercliff Avenue BridgeUndercliff Avenue Bridge
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Ramp TE
Alexander Hamilton Bridge
Ramp TERamp TE
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
• Demolish existing concrete box superstructure• Complete bridge replacement except abutments• New steel box girder superstructure• Rehabilitate existing abutments to accommodate
new superstructure • Eliminate 5 piers and increase span lengths• Relocate 2 piers to accommodate Alexander
Hamilton Bridge widening• Rehabilitate 2 piers to accommodate new
superstructure• Replace drainage & lighting • Re-opened May 2011
Ramp TE Scope of WorkRamp TE Scope of Work
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Existing Ramp TE Existing Ramp TE
Demolition of TEDemolition of TE
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Ramp TERamp TETub GirdersTub Girders
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Ramp TERamp TE
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Ramp TERamp TE
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Ramp TERamp TE
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
• Prepared Alexander Hamilton Bridge Median• Provided temporary support to all of West and East Approach
Spans • Constructed cap beams and foundation strengthening• Reconstructed Ramp ‘TE’• Constructed temporary structures
Stage IStage I
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Stage IStage IExisting Median SidewalkExisting Median Sidewalk
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Stage IStage IMedian WorkMedian Work
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Stage IStage IMedian WorkMedian Work
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
• Widened Alexander Hamilton Bridge (WB)• Completed cap beams and foundations• Continued with temporary structures• Completed reconstruction of Ramp ‘TE’
Stage IIStage II
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Stage II WideningStage II Widening
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Stage IIStage IIRamp ARamp A
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Stage IIStage II
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Stage IIStage II
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Stage II & IIIStage II & III
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Current WorkCurrent Work
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
• Widening of Alexander Hamilton Bridge (EB)• Continue with temporary structures• To be completed June 2012
Stage IIIStage III
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Current Work- Stage IIICurrent Work- Stage IIIMDE Temporary Ramp DMDE Temporary Ramp D
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Stage III MainlineStage III Mainline
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Stage III WideningStage III Widening
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Future WorkFuture Work
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
• Rehabilitate remaining portion of EB side of Alexander Hamilton Bridge
• AHB EB lanes split around work-zone• Rehabilitation of Highbridge Ramps Ongoing• Duration 6 months• Incentive/Disincentive Clause of $55,000 per day is
applicable to the completion of Stage IV
Stage IVStage IV
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
• Rehabilitate remaining portion of WB side of Alexander Hamilton Bridge
• AHB WB lanes split around work-zone• Rehabilitation of Highbridge Ramps Ongoing• Duration 6 months• Incentive/Disincentive Clause of $25,000 per day is applicable to
the completion of Stage V
Stage VStage V
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
• Rehabilitate median of Alexander Hamilton Bridge• Replace on-grade pavement – Manhattan; Only off-peak lane
closures• Replace on-grade pavement – Highbridge Ramps; Closures for
lane shifts only• Duration 7 months
Stage VIStage VI
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Park Mitigation & ImprovementsPark Mitigation & ImprovementsRenovation of Quisqueya
and CPF Playgrounds
Coordination with NYC Parks Department
Highbridge Park Project on Bronx Side
New Park Elements Include: New Skateboard FeatureNew Overlook Terrace/AreaRehabilitation of Stairs, Brick Walls, Walk Paths & Access Road
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Park Mitigation & ImprovementsPark Mitigation & Improvements
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Modifications to Original Modifications to Original DesignsDesigns
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Ramp A & D WallsRamp A & D Walls
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Ramp A
Ramp D
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
MDE CrossoversMDE Crossovers
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Retrofit GirdersRetrofit Girders
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Support TowersSupport Towers
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Ramp TE FootingsRamp TE Footings
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Manny Silva, PE –Manny Silva, PE – NYSDOT Region 11 ConstructionNYSDOT Region 11 Construction
Area Construction Supervisor Area Construction Supervisor• NYSDOT R-11 Construction 1999 - Present
Area Construction Supervisor CPM Coordinator for Construction (2007 – 2009) AGC/NYSDOT Emerging Technologies Subcommittee
• Task Force Meeting on CPM (2008 – 2009)• NYSDOT R-8 Construction 1984 - 1999
Engineer in Charge 1991 - 1999 Inspector 1984 - 1991
• Major Projects Alexander Hamilton Bridge and Highbridge Ramps - Present
• Largest NYSDOT Construction Contract - $407 million West Side Highway Rehabilitation (Battery Place to W. 59th Street) –
1999 - 2003• 5 Construction Contracts - $500 million
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Project Management - AHBProject Management - AHB• Project Management Tools:
– Field Automated Communications System - FACS
• Inspection Reports• Diaries• Material Certifications• Estimates (CEES Export)• Contract Documents• Cost control
– Oracle Primavera • Contract Manager – Document Control• P6 – Schedule Control (CPM)
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Contract Manager – Document ControlContract Manager – Document Control
• Project Team Collaboration• Ball-In-Court (BIC) Feature
– Contractor has direct input– Field Office has direct access and control– Region management has access– Albany support groups have direct access
and input
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Project Team CollaborationProject Team Collaboration• Prime Contractor’s staff
– Subcontractors– Fabricators
• NYSDOT staff– Office of Construction
Field Office (includes consultant for Construction Support Services)
Regional OfficeMain Office
– Office of Structures - Structural Engineering Services BureauMetals Engineering UnitConstruction Support/Foundations Engineering UnitConcrete Engineering Unit
– Office of Technical ServicesGeotechnical Engineering BureauMaterials Bureau
• Federal Highway Administration (FHWA)
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Contract Manager – Document ControlContract Manager – Document Control• Manages submission & tracking of:
– Contractor Submittals• Shop Drawings• Erection Drawings• Design Calculations• Design Drawings• FCS Drawings• Demolition Drawings• Catalog Cuts
– Requests For information (RFI)– Progress Meeting Minutes– Correspondence– Contract Plan Sheet revisions– Issues
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
BenefitsBenefits– Reduces RFI turnaround times– Shortens submittal (Shop Drawing) approval times– Improves Field Office tracking of document submittals– Reduces costs - No mailing costs, reduced printing costs.– Increases productivity - Data is easily accessed.– Improves team collaboration. – Reduces disputes due to improved communication– Easy access to contract records and documents long
after contract completion
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Primavera P6 Primavera P6 CPM Scheduling SpecificationCPM Scheduling Specification
• P6 enterprise web based system• No import and export issues
• Weekly schedule updates• Maintain schedule
• Weekly schedule meetings• Constantly talk about schedule
• Monthly schedule submissions• Record all weekly data• Report on issues and impacts
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Important Project AidsImportant Project Aids• Winter concrete specification and Bid Item
– No winter calendars used on Bridge Deck concrete activities
– Pay winter concrete with bid item• Inspectors prepare electronic inspection
reports in FACS– Each inspection report includes the schedule
activity related to the operation– Inspectors choose schedule activity related to
their operation– Scheduler can follow progress by reviewing
inspection reports remotely
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Schedule AnalysisSchedule Analysis• Goal – Maintain Integrity of the Schedule
– Keeping schedule relevant– Able to use schedule– Tracking schedule impacts– Modeling mitigation – Modeling acceleration
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Weekly Update ProcessWeekly Update Process• Contractor physically updates
schedule with progress and prepares PDF prints for schedule meeting:– Weekly Update Critical Path– Weekly Update Look Ahead (3-4 months)– PDF of any proposed changes
• Also discuss additional changes that need to be made to schedule for monthly update
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Weekly Update Schedule Weekly Update Schedule MeetingMeeting
• Status of schedule for the week• Why did milestone dates move?• Who is responsible?• Key issues
– Important submittals and how they are or can affect schedule
– Construction Issues and how they are or can affect schedule
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Weekly Update Schedule Weekly Update Schedule MeetingMeeting
• Driving Critical Path activities– Do they make sense?– Are we working on them every day?
• Look ahead– Review low float or negative float activities
• Why?• Can the schedule be adjusted to fix float?
• Review upcoming changes– Direct Contractor to adjust schedule based on
approved changes– Allow Contractor to input changes – subject to
review with monthly submission
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Weekly Update Schedule Weekly Update Schedule MeetingMeeting
• Who attends?– NYSDOT Scheduler– Resident Engineer– Engineer in Charge– Area Supervisor*– Submittal Coordinator*– On-site Design Coordinator*– Contractor’s Scheduler– Contractor’s Engineering Management** Available on an as-need basis
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Issue- Floorbeam DeteriorationIssue- Floorbeam Deterioration
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
• Update 22 – July 2, 2011 Data Date286- CCD behind schedule
• Update 27- December 3, 2011 Data Date134- CCD behind scheduleSubstantial Completion: February 14, 2014
• Projections from arch floorbeam issue driving schedule– Schedule Plan
• Model impact in schedule immediately• Adjust frequently as more information comes available• Develop & model mitigation options• Make decisions
2011 Schedule Status2011 Schedule Status
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
AHB – Contractor Baseline TimelineAHB – Contractor Baseline Timeline
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
• Split up Stage 2 – start Stage 3 early
• Start Stage 6 west approach work early• Speedy review of critical submittals• Early opening of Temporary Bridge 7
Mitigation EffortsMitigation Efforts
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
• Eliminate Stage 3 Phase 2• Acceleration program• Used schedule to show how acceleration could
mitigate impacts and move bridge decks for remaining stages into preferred construction season
Additional Mitigation EffortsAdditional Mitigation Efforts
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11
Lessons LearnedLessons Learned• Buy-in by Project Team and Management is
key• Provide Design Schedule/Template to
Contractor in enterprise system• Schedule Specification• Minimum bid price for scheduling• If you maintain the integrity of the schedule
you can actually use it to manage the project
Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11