ALEXANDER HAMILTON BRIDGE ALEXANDER HAMILTON BRIDGE RECONSTRUCTION PROJECT RECONSTRUCTION PROJECT D260888 - X72681 Rehabilitation of the I-95 Corridor and Interchange with I-87 between Amsterdam Avenue and Undercliff Avenue New York State Department of Transportation Region 11 Joan McDonald, Commissioner Phillip Eng P.E., Regional Director State of New York Governor Andrew Cuomo

Upload: manuel-j-silva-pe

Post on 17-Jan-2017

144 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: AGC Presentation_Final_12.6.11(2)

ALEXANDER HAMILTON BRIDGE ALEXANDER HAMILTON BRIDGE RECONSTRUCTION PROJECTRECONSTRUCTION PROJECT

D260888 - X72681

Rehabilitation of the I-95 Corridor and Interchange with I-87 between

Amsterdam Avenue and Undercliff Avenue

New York State Department of TransportationRegion 11

Joan McDonald, CommissionerPhillip Eng P.E., Regional Director

State of New York

Governor Andrew Cuomo

Page 2: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Meeting AgendaMeeting Agenda

I. Background/ Project HistoryII. Scope/ Elements of WorkIII. Current WorkIV. Future WorkV. Modifications to Original DesignsVI. Project Management Tools

Page 3: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

The Project TeamThe Project Team• Area Construction Supervisor

– Manny Silva, NYSDOT• Engineer in Charge

– Mike McCotter, NYSDOT• Resident Engineer

– Albert Pozotrigo, M&J Eng. Ammann & Whitney Group• Contractor

– CCA Civil/Halmar International LLC• Community Liaison

– Kaitlyn Pezik, Zetlin Strategic Communications

Page 4: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Alexander Hamilton BridgeAlexander Hamilton Bridge

Page 5: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Alexander Hamilton Bridge MainlineAlexander Hamilton Bridge Mainline

Page 6: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Alexander Hamilton Bridge MainlineAlexander Hamilton Bridge Mainline

Page 7: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Background/Project HistoryBackground/Project History

Page 8: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

I-87

Alexander Hamilton Bridge

George Washington Bridge181st Street Bridge

LocationLocation

Page 9: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Alexander Hamilton Bridge HistoryAlexander Hamilton Bridge HistoryA new eight-lane arch span was

proposed - the Alexander Hamilton Bridge – to connect the Trans-Manhattan and Cross-Bronx

Expressways.

Currently, estimated traffic over the Hamilton Bridge is over 188,000 vehicles

per day.

The Alexander Hamilton Bridge has not undergone

major repair since it opened on January 15, 1963.

In 1955, Robert Moses determined that the 181st Street Bridge would not be able

handle the anticipated traffic demands from the proposed lower level of the

George Washington Bridge.

Information source: NYCRoads.com

Page 10: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

• Final Design began: Winter 2002• Original Letting: March 29, 2007 (No Bidders)• NYSDOT redesigned temporary structures and

repackaged contract documents• 2nd Letting Date: January 22, 2009

Lowest Bidder- CCA Civil/ Halmar International $407 Million

• Construction Began: Spring 2009• Substantial Completion of Construction Work:

Winter 2013/2014– Approximately 55% completed

History of the ProjectHistory of the Project

Page 11: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

• Alexander Hamilton Bridge (I-95)– Maintain All Through Lanes(other than night-time 12:01 am to 5:30 am)

• Highbridge Interchange - Ramps “A” & “D”- Maintain all lanes other than for lane shifts

• Weekend closures at nighttime only for lane shifts• Undercliff Avenue Bridge – No long term closure

(staged construction)• Ramp TE- Full Detour for Ramp Closure

Work Zone Traffic Control (MPT)Work Zone Traffic Control (MPT)

Page 12: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Scope/Elements of WorkScope/Elements of Work

Page 13: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

• Remove and replace existing deck• Fill in median framing• Widen deck by 11’ each side• Continuity splices in approach spans – make 2 span

continuous• Some floorbeam and stringer replacement• Eliminate some deck joints – reduce number of deck joints by

50% • Construct new cap beams at piers• Replace bearings • Repair substructure concrete• Retrofit substructure to meet current seismic requirements • Paint steel superstructure • Replace drainage, overhead sign structures & lighting

Alexander Hamilton Bridge Alexander Hamilton Bridge Reconstruction Scope of WorkReconstruction Scope of Work

Page 14: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Existing Width: 115 ft.

Proposed Width: 137 ft.

Page 15: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Construction Stages on the Construction Stages on the DeckDeck

Page 16: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Arch reinforcement

Spandrel Column

reinforcement

Expansion Joint Elimination

Alexander Hamilton Bridge Alexander Hamilton Bridge Structural Modifications-Arch Structural Modifications-Arch

SpanSpan

Page 17: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

2 span continuous

2 span continuous

2 span continuous

Alexander Hamilton Bridge Alexander Hamilton Bridge Structural Modifications-East Structural Modifications-East

ApproachApproach

Page 18: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

2 span continuous

Alexander Hamilton Bridge Alexander Hamilton Bridge Structural Modifications-West Structural Modifications-West

ApproachApproach

Page 19: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Highbridge Interchange Highbridge Interchange RampsRamps

Page 20: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Ramp B

(R.H. Side)

Ramp Ramp DD

Ramp F

Ramp A

Ramp L

(L.H. Side)

Highbridge Interchange RampsHighbridge Interchange Ramps

Page 21: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

• Provide temporary bridges adjacent to existing ramps to take traffic during construction

• Remove existing deck • Replace deck with new Cast-in-Place deck• Widen deck by 1’-9” each side – 2 sections of ramp• Replace deck in-kind – other sections of ramp • Replace bearings • Repair substructure concrete• Retrofit substructure to meet current seismic

requirements• Replace drainage, overhead sign structures &

lighting• Paint superstructure steel

Highbridge Ramps Scope of Highbridge Ramps Scope of WorkWork

Page 22: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Ramp F: RedRamp A: BlueRamp D: Yellow

Highbridge Ramps Temporary Highbridge Ramps Temporary StructuresStructures

Page 23: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Undercliff Avenue BridgeUndercliff Avenue Bridge

Page 24: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

• Demolish existing 2 span concrete arch• Complete bridge replacement with single

span multi-stringer bridge• Relocate existing utilities

• Water Main• Electric• Gas

• Replace drainage & lighting

Undercliff Avenue Bridge Undercliff Avenue Bridge Scope of WorkScope of Work

Page 25: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Undercliff Avenue BridgeUndercliff Avenue Bridge

Page 26: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Ramp TE

Alexander Hamilton Bridge

Ramp TERamp TE

Page 27: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

• Demolish existing concrete box superstructure• Complete bridge replacement except abutments• New steel box girder superstructure• Rehabilitate existing abutments to accommodate

new superstructure • Eliminate 5 piers and increase span lengths• Relocate 2 piers to accommodate Alexander

Hamilton Bridge widening• Rehabilitate 2 piers to accommodate new

superstructure• Replace drainage & lighting • Re-opened May 2011

Ramp TE Scope of WorkRamp TE Scope of Work

Page 28: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Existing Ramp TE Existing Ramp TE

Demolition of TEDemolition of TE

Page 29: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Ramp TERamp TETub GirdersTub Girders

Page 30: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Ramp TERamp TE

Page 31: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Ramp TERamp TE

Page 32: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Ramp TERamp TE

Page 33: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

• Prepared Alexander Hamilton Bridge Median• Provided temporary support to all of West and East Approach

Spans • Constructed cap beams and foundation strengthening• Reconstructed Ramp ‘TE’• Constructed temporary structures

Stage IStage I

Page 34: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Stage IStage IExisting Median SidewalkExisting Median Sidewalk

Page 35: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Stage IStage IMedian WorkMedian Work

Page 36: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Stage IStage IMedian WorkMedian Work

Page 37: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

• Widened Alexander Hamilton Bridge (WB)• Completed cap beams and foundations• Continued with temporary structures• Completed reconstruction of Ramp ‘TE’

Stage IIStage II

Page 38: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Stage II WideningStage II Widening

Page 39: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Stage IIStage IIRamp ARamp A

Page 40: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Stage IIStage II

Page 41: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Stage IIStage II

Page 42: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Stage II & IIIStage II & III

Page 43: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Current WorkCurrent Work

Page 44: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

• Widening of Alexander Hamilton Bridge (EB)• Continue with temporary structures• To be completed June 2012

Stage IIIStage III

Page 45: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Current Work- Stage IIICurrent Work- Stage IIIMDE Temporary Ramp DMDE Temporary Ramp D

Page 46: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Stage III MainlineStage III Mainline

Page 47: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Stage III WideningStage III Widening

Page 48: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Future WorkFuture Work

Page 49: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

• Rehabilitate remaining portion of EB side of Alexander Hamilton Bridge

• AHB EB lanes split around work-zone• Rehabilitation of Highbridge Ramps Ongoing• Duration 6 months• Incentive/Disincentive Clause of $55,000 per day is

applicable to the completion of Stage IV

Stage IVStage IV

Page 50: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Page 51: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

• Rehabilitate remaining portion of WB side of Alexander Hamilton Bridge

• AHB WB lanes split around work-zone• Rehabilitation of Highbridge Ramps Ongoing• Duration 6 months• Incentive/Disincentive Clause of $25,000 per day is applicable to

the completion of Stage V

Stage VStage V

Page 52: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Page 53: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

• Rehabilitate median of Alexander Hamilton Bridge• Replace on-grade pavement – Manhattan; Only off-peak lane

closures• Replace on-grade pavement – Highbridge Ramps; Closures for

lane shifts only• Duration 7 months

Stage VIStage VI

Page 54: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Park Mitigation & ImprovementsPark Mitigation & ImprovementsRenovation of Quisqueya

and CPF Playgrounds

Coordination with NYC Parks Department

Highbridge Park Project on Bronx Side

New Park Elements Include: New Skateboard FeatureNew Overlook Terrace/AreaRehabilitation of Stairs, Brick Walls, Walk Paths & Access Road

Page 55: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Park Mitigation & ImprovementsPark Mitigation & Improvements

Page 56: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Modifications to Original Modifications to Original DesignsDesigns

Page 57: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Ramp A & D WallsRamp A & D Walls

Page 58: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Page 59: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Page 60: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Ramp A

Ramp D

Page 61: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Page 62: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

MDE CrossoversMDE Crossovers

Page 63: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Page 64: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Page 65: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Retrofit GirdersRetrofit Girders

Page 66: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Page 67: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Page 68: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Page 69: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Support TowersSupport Towers

Page 70: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Page 71: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Page 72: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Ramp TE FootingsRamp TE Footings

Page 73: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Page 74: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Page 75: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Page 76: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Manny Silva, PE –Manny Silva, PE – NYSDOT Region 11 ConstructionNYSDOT Region 11 Construction

Area Construction Supervisor Area Construction Supervisor• NYSDOT R-11 Construction 1999 - Present

Area Construction Supervisor CPM Coordinator for Construction (2007 – 2009) AGC/NYSDOT Emerging Technologies Subcommittee

• Task Force Meeting on CPM (2008 – 2009)• NYSDOT R-8 Construction 1984 - 1999

Engineer in Charge 1991 - 1999 Inspector 1984 - 1991

• Major Projects Alexander Hamilton Bridge and Highbridge Ramps - Present

• Largest NYSDOT Construction Contract - $407 million West Side Highway Rehabilitation (Battery Place to W. 59th Street) –

1999 - 2003• 5 Construction Contracts - $500 million

Page 77: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Project Management - AHBProject Management - AHB• Project Management Tools:

– Field Automated Communications System - FACS

• Inspection Reports• Diaries• Material Certifications• Estimates (CEES Export)• Contract Documents• Cost control

– Oracle Primavera • Contract Manager – Document Control• P6 – Schedule Control (CPM)

Page 78: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Page 79: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Contract Manager – Document ControlContract Manager – Document Control

• Project Team Collaboration• Ball-In-Court (BIC) Feature

– Contractor has direct input– Field Office has direct access and control– Region management has access– Albany support groups have direct access

and input

Page 80: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Project Team CollaborationProject Team Collaboration• Prime Contractor’s staff

– Subcontractors– Fabricators

• NYSDOT staff– Office of Construction

Field Office (includes consultant for Construction Support Services)

Regional OfficeMain Office

– Office of Structures - Structural Engineering Services BureauMetals Engineering UnitConstruction Support/Foundations Engineering UnitConcrete Engineering Unit

– Office of Technical ServicesGeotechnical Engineering BureauMaterials Bureau

• Federal Highway Administration (FHWA)

Page 81: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Contract Manager – Document ControlContract Manager – Document Control• Manages submission & tracking of:

– Contractor Submittals• Shop Drawings• Erection Drawings• Design Calculations• Design Drawings• FCS Drawings• Demolition Drawings• Catalog Cuts

– Requests For information (RFI)– Progress Meeting Minutes– Correspondence– Contract Plan Sheet revisions– Issues

Page 82: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Page 83: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

BenefitsBenefits– Reduces RFI turnaround times– Shortens submittal (Shop Drawing) approval times– Improves Field Office tracking of document submittals– Reduces costs - No mailing costs, reduced printing costs.– Increases productivity - Data is easily accessed.– Improves team collaboration. – Reduces disputes due to improved communication– Easy access to contract records and documents long

after contract completion

Page 84: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Primavera P6 Primavera P6 CPM Scheduling SpecificationCPM Scheduling Specification

• P6 enterprise web based system• No import and export issues

• Weekly schedule updates• Maintain schedule

• Weekly schedule meetings• Constantly talk about schedule

• Monthly schedule submissions• Record all weekly data• Report on issues and impacts

Page 85: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Important Project AidsImportant Project Aids• Winter concrete specification and Bid Item

– No winter calendars used on Bridge Deck concrete activities

– Pay winter concrete with bid item• Inspectors prepare electronic inspection

reports in FACS– Each inspection report includes the schedule

activity related to the operation– Inspectors choose schedule activity related to

their operation– Scheduler can follow progress by reviewing

inspection reports remotely

Page 86: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Schedule AnalysisSchedule Analysis• Goal – Maintain Integrity of the Schedule

– Keeping schedule relevant– Able to use schedule– Tracking schedule impacts– Modeling mitigation – Modeling acceleration

Page 87: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Weekly Update ProcessWeekly Update Process• Contractor physically updates

schedule with progress and prepares PDF prints for schedule meeting:– Weekly Update Critical Path– Weekly Update Look Ahead (3-4 months)– PDF of any proposed changes

• Also discuss additional changes that need to be made to schedule for monthly update

Page 88: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Weekly Update Schedule Weekly Update Schedule MeetingMeeting

• Status of schedule for the week• Why did milestone dates move?• Who is responsible?• Key issues

– Important submittals and how they are or can affect schedule

– Construction Issues and how they are or can affect schedule

Page 89: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Weekly Update Schedule Weekly Update Schedule MeetingMeeting

• Driving Critical Path activities– Do they make sense?– Are we working on them every day?

• Look ahead– Review low float or negative float activities

• Why?• Can the schedule be adjusted to fix float?

• Review upcoming changes– Direct Contractor to adjust schedule based on

approved changes– Allow Contractor to input changes – subject to

review with monthly submission

Page 90: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Weekly Update Schedule Weekly Update Schedule MeetingMeeting

• Who attends?– NYSDOT Scheduler– Resident Engineer– Engineer in Charge– Area Supervisor*– Submittal Coordinator*– On-site Design Coordinator*– Contractor’s Scheduler– Contractor’s Engineering Management** Available on an as-need basis

Page 91: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Issue- Floorbeam DeteriorationIssue- Floorbeam Deterioration

Page 92: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

• Update 22 – July 2, 2011 Data Date286- CCD behind schedule

• Update 27- December 3, 2011 Data Date134- CCD behind scheduleSubstantial Completion: February 14, 2014

• Projections from arch floorbeam issue driving schedule– Schedule Plan

• Model impact in schedule immediately• Adjust frequently as more information comes available• Develop & model mitigation options• Make decisions

2011 Schedule Status2011 Schedule Status

Page 93: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

AHB – Contractor Baseline TimelineAHB – Contractor Baseline Timeline

Page 94: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

• Split up Stage 2 – start Stage 3 early

• Start Stage 6 west approach work early• Speedy review of critical submittals• Early opening of Temporary Bridge 7

Mitigation EffortsMitigation Efforts

Page 95: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

• Eliminate Stage 3 Phase 2• Acceleration program• Used schedule to show how acceleration could

mitigate impacts and move bridge decks for remaining stages into preferred construction season

Additional Mitigation EffortsAdditional Mitigation Efforts

Page 96: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Lessons LearnedLessons Learned• Buy-in by Project Team and Management is

key• Provide Design Schedule/Template to

Contractor in enterprise system• Schedule Specification• Minimum bid price for scheduling• If you maintain the integrity of the schedule

you can actually use it to manage the project

Page 97: AGC Presentation_Final_12.6.11(2)

Alexander Hamilton Bridge ReconstructionNew York State Department of TransportationRegion 11

Contact InfoContact Info• Field Office Address:

– 26 Bruckner Blvd. Suite #32B Bronx, NY 10454

• Office Phone:– (718) 402-9001

• Community Liaison: Kaitlyn Pezik (718) 402-9008