advanced project management project planning phase ghazala amin

22
Advanced Project Management Project Planning Phase Ghazala Amin

Upload: andrea-hawkins

Post on 18-Jan-2018

232 views

Category:

Documents


5 download

DESCRIPTION

3 PM Framework and Integration Project Life Cycle Team Development Managing Project Human Resources Project Initiation Planning Executing/Control Closeout Project Organizing Project Scheduling WBS Control Meetings Project Monitoring Project Closeout Change and Risk Management Contract and Customer Relationship Management Process Groups Activities

TRANSCRIPT

Page 1: Advanced Project Management Project Planning Phase Ghazala Amin

Advanced Project Management

Project Planning PhaseGhazala Amin

Page 2: Advanced Project Management Project Planning Phase Ghazala Amin

Project Management Processes

» PM processes are divided into five phases or process groups

InitiatingProcesses

ClosingProcesses

ControllingProcesses Executing

Processes

PlanningProcesses

Professional Responsibility

Page 3: Advanced Project Management Project Planning Phase Ghazala Amin

3

PM Framework and IntegrationProject Life CycleTeam Development

Managing Project Human Resources

Project Initiation Planning Executing/Control Closeout

Project Organizing Project

Scheduling

WBSControl

Meetings

Project Monitoring

Project Closeout

Change and Risk Management

Contract and Customer Relationship Management

Process Groups

Act

iviti

es

Page 4: Advanced Project Management Project Planning Phase Ghazala Amin

05/04/23 4

Page 5: Advanced Project Management Project Planning Phase Ghazala Amin

5

Project Planning

• The purpose of Project Planning is to;• establish and• maintain • plans that define project activities.

Majority of Project Manager’s time is spent to effectively plan the project activities.

Page 6: Advanced Project Management Project Planning Phase Ghazala Amin

6

When Project Planning is not done well….

• Poor estimates lead to cost and schedule over runs.• Inability to discover deviations from undocumented

plans• Resources are not available or applied when needed.• Inability to meet commitments• PROJECTS FAIL

2004-2005 by Carnegie Mellon University Introduction to CMMI V 1.1

Page 7: Advanced Project Management Project Planning Phase Ghazala Amin

7

When Project Planning is not done well….

• Why Should we care? Because• Customers don’t trust suppliers who waste their resources (i.e.

loss of future business)• No lessons learned for future projects means making the same

mistakes on multiple projects.• Unhappy customers, employees, stockholders (short life for the

business)“IF YOU FAIL TO PLAN, THEN YOU PLAN TO FAIL”

2004-2005 by Carnegie Mellon University Introduction to CMMI V 1.1

Page 8: Advanced Project Management Project Planning Phase Ghazala Amin

8

Project Planning Goals

• Establish Estimates• Estimates of project planning parameters are established and

maintained.• Develop a Project Plan

• A project plan is established and maintained as basis for managing the project.

• Obtain Commitment to the Plan• Commitments from relevant stakeholders are established and

maintained.2004-2005 by Carnegie Mellon University Introduction to CMMI V 1.1

Page 9: Advanced Project Management Project Planning Phase Ghazala Amin

9

Project Planning Context

2004-2005 by Carnegie Mellon University Introduction to CMMI V 1.1

Establish Estimates

Obtain Commitment to the plan

Develop a Project PlanPlanning Data

Project Plan

PM&C

Relevant Stakeholders

Page 10: Advanced Project Management Project Planning Phase Ghazala Amin

10

Project Planning – Establishing Estimates

2004-2005 by Carnegie Mellon University Introduction to CMMI V 1.1

Estimate the Project Scope

Establish Estimates of the Work

products and Tasks

Define Project Life Cycle

Determine EstimateOf Effort and Cost

Planning Data

Page 11: Advanced Project Management Project Planning Phase Ghazala Amin

11

Project Planning Context

2004-2005 by Carnegie Mellon University Introduction to CMMI V 1.1

Establish Estimates

Obtain Commitment to the plan

Develop a Project PlanPlanning Data

Project Plan

PM&C

Relevant Stakeholders

Page 12: Advanced Project Management Project Planning Phase Ghazala Amin

12

Project Planning – Develop Project Plan

2004-2005 by Carnegie Mellon University Introduction to CMMI V 1.1

Establish the Budget

and Schedule

Identify Project Risks

Plan Stakeholder Involvement

Establish theProject Plan

Project Plan

Plan for Project

ResourcesPlan for Data Management

Plan for Needed

knowledgeAnd skills

Planning Data

Page 13: Advanced Project Management Project Planning Phase Ghazala Amin

13

Project Plan» Formal, approved document used to manage and

control project execution. Includes….� Project Charter� WBS - Task and resource assignment� Major milestones and baseline target delivery dates� Project Communication Plan� Responsibility Assignment Matrix� Risk Management document� Issues Management Document� Change Management Document� Milestone Chart� Project Status Plan template� Quality Assurance Document� Lessons Learned …..

The above documents need to be in place to be ready to execute, manage and track project performance

Page 14: Advanced Project Management Project Planning Phase Ghazala Amin

14

Project Planning Context

2004-2005 by Carnegie Mellon University Introduction to CMMI V 1.1

Establish Estimates

Obtain Commitment to the plan

Develop a Project PlanPlanning Data

Project Plan

PM&C

Relevant Stakeholders

Page 15: Advanced Project Management Project Planning Phase Ghazala Amin

15

Project Planning – Obtaining Plan Commitment

2004-2005 by Carnegie Mellon University Introduction to CMMI V 1.1

Review Plans Affecting the

Project

Project Plan

Obtain Plan Commitment

Reconcile Work and

Resource Level

Relevant Stakeholders

Page 16: Advanced Project Management Project Planning Phase Ghazala Amin

16

Relevant Stakeholder-Sponsor• Sponsor

– An individual or an organization who has the authority to perform, delegate, or ensure completion of the following project commitments:

• Formalization of an agreement with the project delivery organization.

• Approval to proceed with the start of the project or of a project phase.

• Spending for the cost/price of the project as specified in the agreement.

• The sponsor may be internal or external to the project delivery team’s organization.

Page 17: Advanced Project Management Project Planning Phase Ghazala Amin

17

Relevant Stakeholder-Sponsor• Sponsor Agreement Management

– The processes necessary to build the agreement;– Present it to the sponsor– Negotiate the changes– And at the end of the project or phase, close out the

agreement.

Phase end reviews should be used to help the sponsor determine if the project should continue to next phase

Page 18: Advanced Project Management Project Planning Phase Ghazala Amin

18

Project Planning

• The purpose of good Project Planning is to ensure;

• All detailed plans for managing the project are defined• Formal commitments are established• Team is ready to execute !!!•

Effective project planning = readiness for performance.

Page 19: Advanced Project Management Project Planning Phase Ghazala Amin

19

Project Planning Checkpoint

• As a project manager you must;• Validate financial commitment to the business• Set expectation with client and project sponsor• Recognize that this is hard go/no go decision• Have your project team committed to the plan• Be ready to be accountable for the project execution

Project Planning is crucial point in the project life cycle when you decide if the project is ready to commit to future execution tasks

Page 20: Advanced Project Management Project Planning Phase Ghazala Amin

20

How does an estimate become a budget

• Validate estimate with the project team• Review assumptions, hours, risks etc.

• Validate estimate with the sponsors, financial executive, quality assurance team ..

• Business rationale, timings and cost estimates, any cost buffers or contingency reserves, profit contribution…

• Baseline the budget• Report monthly status .

• Plan what the senior management would like to see

Page 21: Advanced Project Management Project Planning Phase Ghazala Amin

21

Remember !!

• Project Managers are responsible for;• Cost• Project Profit• Project team efficiency• Project expenses• Quality control• …………….

At the end of the project planning process, your business executives decide if your project can/should target meeting specific business objectives .

Page 22: Advanced Project Management Project Planning Phase Ghazala Amin

22

Few Causes of troubled projects (Planning Phase)

• Failure to set and manage customer expectations• Customer unprepared to take on project responsibilities• Lack of common understanding of requirements• Poor quality proposals• Lack of information in charter• Unclear organization roles and responsibilities• Failure to plan and manage project risks• Lack of defined quality control mechanisms• Inaccurate and uncommitted project estimates …..