7. maintenance depot and workshop - mumbai railway … chapter 7... · 7. maintenance depot and...
TRANSCRIPT
TECHNO-ECONOMIC SURVEY AND PREPARATION OF DPR FOR PANVEL-DIVA-VASAI-VIRAR CORRIDOR
Draft Feasibility Report APRIL, 2013 7-1
77.. MMAAIINNTTEENNAANNCCEE DDEEPPOOTT AANNDD
WWOORRKKSSHHOOPP
7.1 INTRODUCTION
The Panvel-Virar Suburban corridor would require a dedicated Depot cum workshop
facility for the maintenance of the rakes. The total coach holding would increase to
about 576i.e 48 Rakes of 12 car in the horizon year 2041 to meet the traffic demand.
All the rakes will be serviced at main Depot cum workshop for the scheduled
inspections, major schedules viz Periodical overhaul (POH) and major unscheduled
repairs. The main depot will also house Operation Control Centre (OCC),
Administrative Building, maintenance facilities for Civil – track, buildings, water
supply; Electrical – traction, E&M; Signalling & Telecomm.; etc. apart from necessary
facilities viz stabling lines, scheduled inspection lines, workshop for overhaul,
unscheduled maintenance including major repairs, wheel profiling, heavy
interior/under frame/roof cleaning etc. for the rolling stock operational on the
corridor.
For starting the morning services, some rakes will have to be kept at terminal
stations and stabling facilities for the remaining rakes will have to be provided at the
depots.
All the systems at the depot would be designed to cater for 12 Car composition
trains in order to serve the ultimate passenger traffic on Panvel-Virar suburban
corridor.
This chapter covers following aspects of depot -
• Conceptual design of Stabling lines, Inspection Shed and Workshop to provide
maintenance facilities and stabling facilities for the Rolling Stock.
• Operational and functional safety requirements.
• Ancillary buildings for other maintenance facilities.
• Electrical & Mechanical Services, power supply system etc.
• Location for Depot cum Workshop
This section provides conceptual design of the depot and will only work as a guide
for the detailed design later.
7.2 MAINTENANACE PHILOSOPHY
The main outlines of the maintenance philosophy followed are:
TECHNO-ECONOMIC SURVEY AND PREPARATION OF DPR FOR PANVEL-DIVA-VASAI-VIRAR CORRIDOR
Draft Feasibility Report APRIL, 2013 7-2
� Monitoring of the performance of equipment by condition monitoring of key
parameters. The concept is to progressively evolve the need based
maintenance regime, which can be suitably configured in the form of minor &
major schedules.
� Unit replacement and to get essential repairs done by the OEMs, will be
preferred. Since the cost is a constraint, certain activities of the workshop can
be outsourced.
� Labour intensive procedures be kept to the minimum & emphasis laid on
more automation with state of the art machinery to ensure quality with
reliability.
� Multi skilling of the Maintenance staff to ensure quality and productivity in
their performance.
� Energy conservation shall be given due attention
7.3 PLANNING OF THE MAINTENANCE FACILITIES SETUP
The projected Rolling Stock requirements for the corridor are as follows:
Table 7.1
Year 2021 2026 2031 2041 Designed
Headway (minutes) 15 12 8 5 3
No of Cars/Train 12 12 12 12 12
Rakes Required 19 21 33 48 78
Coaches Required 228 252 396 576 936
The operation plan envisages 12-car rakes operation at 15 minutes headway in the
inception year 2021, requiring total 228 coaches (19 Rakes of 12 car each). The
services increase to 5 minutes headway in the horizon year 2041, requiring total 576
coaches (48 Rakes of 12 car each) as the traffic demand grows.
7.4 ROLLING STOCK MAINTENANCE NEEDS
The servicing requirement is to be determined from the Rolling Stock manufacturer.
Depending upon manufacturer's requirements, servicing facilities may be provided
to include the ability to carry out the inspection, maintenance, overhaul and repair of
the rolling stock fleet, including the following components:
� Body;
� Bogies;
� Wheels;
� Traction motors;
TECHNO-ECONOMIC SURVEY AND PREPARATION OF DPR FOR PANVEL-DIVA-VASAI-VIRAR CORRIDOR
Draft Feasibility Report APRIL, 2013 7-3
� Electrical components;
� Electronics; PA/ PIS
� Mechanical components;
� Batteries;
� Rolling stock air conditioning;
� Brake modules;
� Vehicle doors, windows and internal fittings.
The modern, fully equipped facilities are proposed to be provided to meet these
requirements efficiently and in full. In meeting these requirements, it is envisaged
that the average daily distance travelled by each rolling stock unit is approximately
650 km.
The following maintenance schedule recommended by RDSO in Para (k) of SMI no.
RDSO/PE/SMI/EMU/0037-2007(rev.0) dated April-2007, has been followed for
conceptual design -
Table 7.2: Periodicity of Maintenance Schedules for Rakes
Schedule Periodicity
As per SMI With 10 days frequency
Trip Schedule (TI) 10 days 10 days
IA Inspection 45 days 40-50 days
IC Inspection 180 days 180-190 days
POH 18 months 18 months (540 days)
7.5 WASHING NEEDS OF ROLLING STOCK
To maintain high degree of cleanliness, following schedules (Table 7.2) are proposed
for cleaning of rakes.
Table 7.3: Schedule of Cleaning
S.
No
.
Kind of Inspection Maint.
Cycle
Time Maintenance Place
1. Outside Cleaning (wet washing
on automatic washing plant)
3 Days 10 mins Automatic washing
plant of Depot Single
Pass
2. Outside heavy Cleaning (wet
washing on automatic washing
30
days
3 Hrs Automatic washing
Plant & heavy cleaning
TECHNO-ECONOMIC SURVEY AND PREPARATION OF DPR FOR PANVEL-DIVA-VASAI-VIRAR CORRIDOR
Draft Feasibility Report APRIL, 2013 7-4
plant and Front Face, Vestibule/
Buffer area, Floor, walls inside/
outside and roof Manually)
on nominated stabling
line
7.6 DEPOT CUM WORKSHOP
The layout plans of proposed Main Depot cum Workshop will be evolved for
maintenance & POH of 93 Rakes of 12 car length. The concept plan will include
following operational features.
7.7 OPERATION FEATURES
The rake induction and withdrawal from depot to the open line will have to be so
planned that the headway of open line is not affected. For the purpose, facilities for
simultaneous receipt and dispatch of trains from depot to open line should be
created. The stabling area should be interlocked with the open line so that the
induction of train from the stabling can be done without loss of time. The rake
washing can be done at automatic coach washing plant provided at the entry of
depot i.e before rake is placed on stabling lines.
The other movements in the depot, viz from the stabling to the inspection shed or
workshop and vice versa may be non-interlocked. An ART line and 2 emergency re-
railing lines will be provided from which emergency rescue vehicles can be
dispatched to open line in the event of any emergency. To cater to the peak
requirements, all trains except trains under maintenance would be in the service.
However during the off-peak hour in daytime, approximately half of the trains will be
withdrawn from the service. There would be pathways between the stabling lines,
which are necessary for the “Safe to Run” examination and to facilitate the workers
to move trolleys for the sweeping work. The scheduled inspections are envisaged to
carry out during the day off-peak hours and night.
The stabling and the yard layout would be at grade level for least power
requirements in shunting movements and to avoid accidental rolling of Rolling Stock
resulting into accidents and damages to the property.
7.8 INFRASTRUCTURE FACILITIES PLANNED AT DEPOT
The schedule sequence for rakes with 10 days frequencies of inspection will be as
given below:
TECHNO-ECONOMIC SURVEY AND PREPARATION OF DPR FOR PANVEL-DIVA-VASAI-VIRAR CORRIDOR
Draft Feasibility Report APRIL, 2013 7-5
As per the above frequency of inspections, the visits of rakes to car sheds are as
given in Table 7.4 below:
Table 7.4: Rake Visit periodicity for Depot
Rake visits to car shed/depot
Schedule Total visits in 18 months Average visits per year
TI 43* 28.667
IA 9 6
IC 2 1.333
POH 1 0.667
*includes one additional inspection in car shed after POH in workshop
Assumptions: To assess the number of lines required to maintain the rakes,
following assumptions are made:
For Washing of rakes, an automatic washing plant will be proposed. Hence no
separate washing line is needed exclusively for washing. However, one line will be
provided for heavy cleaning (Manual cleaning of Floor, walls inside/outside and
roof).
In a day, two rakes are taken for Trip Inspection on a pit line.
In a day, one rake is taken for IA schedule on a pit line.
Pit line occupancy for IC schedule (Down time 16 hrs) is taken for two days.
Based on the number of holidays as given below, total number of working days is
taken as 300 for calculating the requirement of lines.
No. of days of Public holidays in a year : 13
No. of Sundays in a year : 52
No. of available working days in a yea : 365 - 65 = 300 days
TECHNO-ECONOMIC SURVEY AND PREPARATION OF DPR FOR PANVEL-DIVA-VASAI-VIRAR CORRIDOR
Draft Feasibility Report APRIL, 2013 7-6
Table 7.5: Total requirement of Maintenance Lines in Depot
Schedule
Schedule
per rake
per Year
Total Arising per
day for designed
holding of 78 of 12
car
Rakes
attended
on a line /
day
Number
of lines
needed
Lines
required
(roundoff)
Trip Insp. 28.67 7.45 2 3.73 3
IA 6 1.56 1 1.56 1
IC 1.33 0.35 0.5 0.69 1
Add for unscheduled shed attention & adjustment/shunting etc. 1
Total no of lines needed in Inspection shed 6
Similarly lines needed for Workshop Activities
Schedule
Schedule
per rake
per Year
Total Arising per
year for designed
holding of 78 of 12
car
Time taken
in over
haul
Number
of lines
needed
Lines
required
(roundoff)
POH 0.667 52.03 24 2.17 2
Add for unscheduled major Repairs /Lifting & adjustment/shunting
etc. 2
Total no of lines needed in Workshop 4
Total Lines needed in Depot for Maintenance 10
All lines in workshop to be provided with lifting facility
7.9 LINES FOR STABLING OF RAKES
There will be a holding of 48 rakes of 12-Car in year 2041, and elaborate
arrangement for stabling of these rakes will have to be done in depot cum work
shop, terminal stations and at few places enroute the section.
The train operation plan envisages operation with 12-Car composition in the
inception year itself in year 2021. Accordingly, all the infra structure facilities has
been provided for 12-Car length and stabling lines are also provided for 12 car length
and accommodate trains as detailed in Table 7.6below:
Table 7.6: Stabling Line Provisions of 12-car length
Year 2021 2031 2041
Stabling lines at the terminal station for
morning & evening peak period services 4 4 4
En-route Stabling lines at convenient
location such as Bhivandi Road or/and
Taloje or/and Kalamboli
------ 9 20
Rakes to be stabled in the Depot 15 20 24
TECHNO-ECONOMIC SURVEY AND PREPARATION OF DPR FOR PANVEL-DIVA-VASAI-VIRAR CORRIDOR
Draft Feasibility Report APRIL, 2013 7-7
Total Stabling Lines of 12 car length 19 33 48
Twenty five (24) number of 12-car length-stabling lines, Five (5) number of
inspection lines and Five (5) number of workshop lines will have to be provided in
the main depot. For starting the morning services, it will be necessary to stable the
rakes at the terminal station & suitable sidings enroute as indicated above.
Design of Stabling Lines
The length of 12 cars Rolling Stock is approx 252 m Stabling lines are designed for
278 m length or more to cater for provision of the friction buffer stops and the
signaling/interlocking needs - assuming the speed of the Rolling Stock in the depot to
be 15 kmph. The breakup is as follows:
252 m (length of 12 car Rolling Stock) + 15 m (length of the Buffer for 12 car Rolling
Stock & signaling / interlocking needs) + 1m (clear distance between Rolling Stock &
buffer) + 10 m (clearance between three 4 car trains running initially) = 278 m.
Accordingly, stabling lines as well as inspection & workshop lines be designed for 280
m length. The track centre in stabling lines would be 4.9~5.3m and in inspection lines
6.25~8.5m. Thus, sufficient space shall be provided to construct pathway in stabling
area and in inspection shed to provide easy access for internal train cleaning /
attention to equipments in passenger area.
7.10 POWER SUPPLIES
An auxiliary substation of 2X3000 KVA capacities has been planned for catering to
the power supply requirement of the main depot. Details of connected load, feeder
may be worked out during detailed designing stage.
7.11 STANDBY POWER SUPPLY
The standby power supply will be proposed through silent DG set of 3X320 KVA
capacities to supply all essential loads without over loading.
7.12 WATER SUPPLY, SEWERAGE AND DRAINAGE WORKS
In-house facilities should be developed for water supply for the entire depot cum
workshop. Sewerage, storm water drainage may be given due care while designing
the depot for efficient system functioning. Rainwater harvesting should be given due
emphasis to charge the underground reserves.
7.13 ENGINEERING TRAIN UNIT WORKSHOP
Since the workshop cum depot is designed optimally, it would not be wise to waste
its capacity in maintaining the other than passenger Rolling Stock vehicles. Carrying
these vehicles to the inspection shed affects the RS maintenance as shunting is also
involved. Therefore other vehicles like diesel locomotive, tower wagons, wagon for
TECHNO-ECONOMIC SURVEY AND PREPARATION OF DPR FOR PANVEL-DIVA-VASAI-VIRAR CORRIDOR
Draft Feasibility Report APRIL, 2013 7-8
material trains etc may be housed and given required inspection attention in a
separate shed called ETU workshop, for which 2 lines shall be provided in the main
depot. However for the heavy lifting needs, these vehicles may be taken to the area
where such facilities are available.
7.14 PLANT AND MACHINERY
Requirement of major plants and machinery, which are vital for operational needs, is
given in Annexure-I.
7.15 DEPOT LOCATIONS
The proposed Corridor would require a dedicated Depot cum Workshop (Main
Depot) in the inception year 2021 itself. A plot of 34.8 hactare has been marked at
Kalwar between Kalwar and Dunge station.
Car Depot Site requirements
The pre requisites of coach maintenance depot site are as under –
i. A plot size of adequate area - about 34 Ha for main depot
ii. Proximity to alignment: Site must be located as close to the alignment as
possible so that no time is wasted in placement/retrieval of rakes from depot.
In addition, it will save expenditure in constructing link from corridor to
depot,
iii. Ease of movement – there should not be any obstruction to movement of
rakes in either direction so that defective rakes can be withdrawn from
service & placed in depot for maintenance and healthy rakes can be retrieved
from depot & pressed in service.
iv. A store depot within car-depot premises is to be set up.
The conceptual layout plan of Depot with above infrastructure will be developed
upon finalization of suitable location with adequate area for the depot.
Depending upon the type of rolling stock procured and recommendations of original
equipment manufacturers of rolling stock and sub assemblies, exhaustive list of
machinery and plants along with tool and tackles shall be prepared for procurement
so as to develop healthy maintenance practices for reliable operation of the rolling
stock. An indicative list of such items is given in annexure I.
For maintenance of OHE, PSI, signaling, Telecom, P-WAY, Works etc standard
facilities as per practice in vogue shall be planned at the time of detailed project
report. Special attention shall be however given for procurement of machinery and
plants to introduce mechanized maintenance to reduce dependence on man power.
TECHNO-ECONOMIC SURVEY AND PREPARATION OF DPR FOR PANVEL-DIVA-VASAI-VIRAR CORRIDOR
Draft Feasibility Report APRIL, 2013 7-9
ANNEXURE-I
LIST OF MAJOR PLANT & MACHINERY FOR DEPOT
Sl no. PLANT & MACHINERY Qty.
A. Material Handling
1 Travelling over head EOT cranes for workshop 35/10T 2
2 Travelling over head EOT cranes for inspection bay 2.0T 2
3 Travelling over head EOT cranes for ETU shed 5T 1
4 Jib crane for workshop 3 T 2
5 Synchronized pit jacks system for lifting (3 cars as one set) 1
6 Car body stands for keeping car shells 32
7 Dummy bogies 6
8 Mobile lifting jacks-15T 2
9 Mobile lifting jacks 10T 2
10 Battery powered Electric locomotive 2
11 OHE Inspection car 2
12 Road mobile Crane 5T cap 1
13 Fork lift trucks 3T cap 2
14 Pallet trucks 4
15 Pick up van 1
16 TATA Truck 2
B. Wheel shop
17 500T Hydraulic wheel press 1
18 Vertical boring m/c / Turret Lathe for wheel machining 1
19 Multipurpose Wheel Lathe/CNC surface wheel lathe 1
20 CNC Axle turning lathe/Axle journal turning & burnishing lathe 1
21 Axle UST inspection machine 2
22 Induction Heater 2
23 Bearing Extractor 4
C. Bogie shop
24 Bosch Tank : Bogie wash/cleaning plant (manual) 1
25 Bogie static load testing m/c 1
26 Shock absorber testing m/c 1
27 Spring scragging &testing m/c 1
TECHNO-ECONOMIC SURVEY AND PREPARATION OF DPR FOR PANVEL-DIVA-VASAI-VIRAR CORRIDOR
Draft Feasibility Report APRIL, 2013 7-10
Sl no. PLANT & MACHINERY Qty.
28 Magnacheck crack detector 1
29 Glowcheck crack detector 1
D. Rotating m/cs
30 Air blow plant/Cleaning booth for Traction Motor 1
31 Baking Oven for traction motor drying 1
32 Dynamic balancing 1
E. Other m/cs
33 Under floor Pit wheel lathe, Chip crusher and conveyor, Electric
tractor for movement over under floor wheel lathe 1
34 Bogie Drop Table 1
35 Automatic Washing plant for Metro cars. 1
36 High-pressure washing pump for front and rear end cleaning of
cars 2
37 Turn table for one car 1
38 Turntable for bogies 6
39 Driving Cab Simulator 1
40 Water de-mineralizing plant (Distillation plant) 2
41 Painting booth for separate parts 1
42 Floor cleaning machine 5
43 Welding equipments (Mobile welding, oxyaccetelene, fixed arc
welding) 5
44 Compressor 500Cfm, 10 kg/sq.cm for depot air supply 2
45 DG set 320 KVA 3
46 EMU Battery charger 2
F. Machine shop
47 Guillotine Shearing m/c 1
48 Shearing, punching & cropping 1
49 Universal tool cutter & grinder 1
50 Vertical surface grinder 1
51 Centre lathe 2m bed 1
52 Centre lathe 1m bed 1
53 Radial drill m/c 1
G. Test Benches/Instruments
54 Traction motor test console 1
TECHNO-ECONOMIC SURVEY AND PREPARATION OF DPR FOR PANVEL-DIVA-VASAI-VIRAR CORRIDOR
Draft Feasibility Report APRIL, 2013 7-11
Sl no. PLANT & MACHINERY Qty.
55 Motor compressor test bench 1
56 Brake test bench 2
57 Speedometer test bench 2
58 Door test bench 2
59 Inverter test bench 1
60 Other test benches (MCB, RMPU etc.) 1
H. Furniture/material storage/Small tools
61 Vertical carousel storage system for DCOS store 1
62 Computer MMIS with LAN connectivity for depot 1
63 Storage racks LS
64 Industrial furniture, work benches etc. LS
65 Electric and pneumatic tools LS
66 Measuring and testing equipments LS
67 Tool kits LS
68 Other small tools, machines & misc items etc LS