35824401 fidic guide to the use of fidic

260
FEDERATION INTERNATIONALE DES INGENJEURS-CONSEILS GUIDETOTHE USE OF FIDIC I FOURTH EDITION CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION

Upload: markck12345

Post on 21-Jun-2015

1.020 views

Category:

Documents


39 download

TRANSCRIPT

Page 1: 35824401 FIDIC Guide to the Use of FIDIC

FEDERATION INTERNATIONALE DES INGENJEURS-CONSEILS

GUIDETOTHE USE OF FIDIC

I

FOURTH EDITION

CONDITIONS OF CONTRACT

FOR WORKS OF CIVIL

ENGINEERING CONSTRUCTION

Page 2: 35824401 FIDIC Guide to the Use of FIDIC

First published byFédération Internationale desIngénieurs-Conseils (FIDIC)P0 Box 86CH 1000 Lausanne 12SwitzerlandTeI.+41 216544411Publications +41 21 654 44 15Fax+41 216544417

Copyright FIDIC 1989

All rights reserved.No part of this publication may bereproduced or transmitted in anyform or by any means withoutpermission of the publisher.

Page 3: 35824401 FIDIC Guide to the Use of FIDIC

U D I C FEDERATION INTERNATIONALE DES INGENIEURS-CONSEILS

GUIDETOTHE USE OF FIDICCONDITIONS OF CONTRACT

FOR WORKS OF CIVIL

ENGINEERING CONSTRUCTION

FOURTH EDITION

Page 4: 35824401 FIDIC Guide to the Use of FIDIC

Page blankin original

Page 5: 35824401 FIDIC Guide to the Use of FIDIC

FOREWORD

In 1957 the International Federation of Consulting Engineers(FIDIC) published for the first time a form of standard condi-tions of contract for works of civil engineering construction es-pecially designed for use in international projects.

Second and third editions were published in 1963 and 1977 re-spectively.

In 1983 the Executive Committee of FIDIC appointed a draftingcommittee comprised of members of the Civil Engineering Con-tracts Committee (CECC) which up to that time had beencharged with monitoring the use of the third edition.

The results of the work of the drafting committee were approvedin 1987 and the fourth edition of the Conditions of Contract forWorks of Civil Engineering Construction was published at theAnnual Conference of FIDIC held in Lausanne, Switzerland inSeptember of 1987.

There are many important differences between the third and fourtheditions and these are dealt with in detail in this Guide which givesa commentary on each clause of the fourth edition.

The Executive Conmiittee decided to drop the word 'International'from the title of the document as with slight modification in PartII it is also suitable for domestic contracts.

With the advances in technology of photo-copying it is possibletoday to produce photo-copies which appear to be true copies ofan original document but have in fact been changed without thealterations being apparent. To counter this, the Part I of theConditions has been printed in two colours (black and blue) andFIDIC strongly recommends all users of the Conditions to insistthat Part I of the document should be in the form published byFIDIC.

The CECC comprised the following members all of whom playedan active role in the preparation of the fourth edition, Messrs. H.Sørensen (Denmark) Chairman, R. Elsasser (Germany), R. Hems(USA), H. Kristensen (Sweden) and K.B. Norris (UK). TheExecutive Committee expresses its sincere thanks to the CECCMembers for four years of time-consuming voluntary work whichwas required to produce the fourth edition. The main responsibil-ity for coordinating the drafting fell upon Messrs. SØrensen andNorris and the Executive Committee would like to express aspecial commendation to them.

During their respective periods of office as President of FIDICMessrs. Miller, Eldridge and Frick-Meijer provided consider-able support to the drafting committee, The European InternationalContractors (EIC) on behalf of the Confederation of International

5

Page 6: 35824401 FIDIC Guide to the Use of FIDIC

Contractors' Associations (CICA) and supported by AssociatedGeneral Contractors of America (AGC) played a valuable consul-tative role and FIDIC particularly thanks Messrs. R. Aidred (UK)and G. Lodigiani (Italy) who were most active in this functionand were supported by many others, notably Messrs. R. Bollin-ger (EIC), J. Cuisinier (France), J. de Greef (Netherlands) andMessrs. D.G. Armstrong and C. Molineaux (USA).

Mr. Angus Cleaver of Bain Clarkson Ltd, London provided theknowledge and drafting skill for the insurance clauses and was avaluable adviser on risk allocation.

Mr. Christopher Seppala of White & Case, Paris, on behalf of theInternational Bar Association gave valuable advice on the legalaspects and a check to ensure legal conformity of the entire docu-ment was carried out by Mr. David Wightman of Turner KennethBrown, London.

Finally, the Executive Committee wishes to express its thanks toformer Managing Director, Mr. Burt Campbell, who assisted thedrafting committee throughout the revision process and who has,since he retired, undertaken the coordination of the production ofthis Guide.

FIDIC Secretariat receives requests from time to time to assist inthe interpretation of individual contracts which are based uponconditions of contract similar to those contained in the fourthedition. It should be evident that as a federation of ConsultingEngineers FIDIC cannot consider itself competent to give legaladvice and in any event the legal interpretation of a contract will,inter alia, depend upon the law governing the particular contractas well as the precise wording of the contract. One objective ofthis Guide is to indicate what the drafting committee intended indrafting the various clauses. The interpretation of individualclauses in a specific contract will be determined by the Courts orby arbitration.

The final section of this Guide contains a photo reproduction ofFIDIC's "Conditions of Contract for Works of Civil EngineeringConstruction, Fourth Edition 1987 (Reprinted 1988 with editorialamendments)", better known as "Red Book 4". Within the textof this Guide, the clauses from Red Book 4 are copied and areshown in italics. The italicized clauses should be identical to thecorresponding clauses in the final section. If any discrepency isfound between corresponding clauses, the reader should refer tothe photo reproduced final section to determine the correct word-ing.

Page 7: 35824401 FIDIC Guide to the Use of FIDIC

CONTENTS

FOREWORD 5CONTENTS 7INTRODUCTION 17TENDERING PROCEDURE 22

Conditions of Contract 22Specification 22Drawings 23Bill of Quantities 23The Tender 23Instructions to Tenderers 241. General 242. Documents 253. Completion and Submission of Tenders 254. Supplementary Information Required 255. Amendments to Tender Documents 266. Currency Requirements and Exchange Rates 277. Site Visits 278. Tender Bond 289. Bonus 2810. Local Legislation 2811. Examination of Tenders 2812. Acceptance of Tender 29Evaluation of Tenders 29Award of Contract 29Contract Agreement 30Procedural Flowchart 31

THE PARTIES TO THE CONTRACT 35

The Employer 35The Contractor 36

THE ENGINEER 38

COMMENTARY ON THE CONDITIONS 40General Comment

DEFINITIONS AND INTERPRETATION 40Clause 1

1.1 Definitions 401.2 Headings and Marginal Notes 441.3 Interpretation 441.4 Singular and Plural 441.5 Notices, Consents, Approvals, 44

Certificates and Determinations

ENGINEER AND ENGINEER'S REPRESENTATIVEClause 2 45

© FIDIC 1989 7

Page 8: 35824401 FIDIC Guide to the Use of FIDIC

2.1 Engineer's Duties and Authority 452.2 Engineer's Representative 462.3 Engineer's Authority to Delegate 462.4 Appointment of Assistants 472.5 Instructions in Writing 472.6 Engineer to Act Impartially 48

ASSIGNMENT AND SUBCONTRACTING 49

Clause 33.1 Assignment of Contract 49

Clause 44.1 Subcontracting 494.2 Assignment of Subcontractor's Obligations 50

CONTRACT DOCUMENTSClause 5

5.1 Language/s and Law 515.2 Priority of Contract Documents 51

Clause 66.1 Custody and Supply of Drawings and Documents 526.2 One Copy of Drawings to be Kept on Site 536.3 Disruption of Progress 536.4 Delays and Cost of Delay of Drawings 546.5 Failure by Contractor to Submit Drawings 54

Clause 77.1 Supplementary Drawings and Instructions 547.2 Permanent Works Designed by Contractor 547.3 Responsibility Unaffected by Approval 55

GENERAL OBLIGATIONS 56Clause 8

8.1 Contractor's General Responsibilities 5682 Site Operations and Methods of Construction 56

Clause 99.1 Contract Agreement 56

Clause 1010.1 Performance Security 5710.2 Period of Validity of Performance Security 58

10.3 Claims under Performance Security 58Source of Performance Security 58Clause 11

11.1 Inspection of Site 59Access to Data 60Clause 12

12.1 Sufficiency of Tender 60

12.2 Adverse Physical Obstructions or Conditions 61

Clause 1313.1 Work to be in Accordance with Contract 61

8 ©FIDIC 1989

Page 9: 35824401 FIDIC Guide to the Use of FIDIC

Clause 1414.1 Programme to be Submitted 6214.2 Revised Programme 6314.3 Cash Flow Estimate to be Submitted 6414.4 Contractor not Relieved of Duties or 64

ResponsibilitiesClause 15

15.1 Contractor's Superintendence 64Language Ability of Contractor's Representative 65Interpreter to be made Available 65Clause 16

16.1 Contractor's Employees 6516.2 Engineer at Liberty to Object 66

Language Ability of Superintending Staff 66Employment of Local Personnel 66Clause 17

17.1 Setting-Out 66Clause 18

18.1 Boreholes and Exploratory Excavation 67Clause 19

19.1 Safety, Security and Protection 67of the Environment

19.2 Employer's Responsibilities 68

ALLOCATION OF RESPONSIBILITY AND INSUR-ANCE OBLIGATIONS 69Clause 20

20.1 Care of Works 6920.2 Responsibility to Rectify Loss or Damage 69203 Loss or Damage Due to Employer's Risks 7020.4 Employer's Risks 70

Clause 2121.1 Insurance of Works and Contractor's Equipment 7121.2 Scope of Cover 7221.3 Responsibility for Amounts not Recovered 7321.4 Exclusions

Clause 2222.1 Damage to Persons and Property 7422.2 Exceptions22.3 Indemnity by Employer 75

Clause 2323.1 Third Party Insurance (including Employer's 75

Property)23.2 Minimum Amount of Insurance 7523.3 Cross Liabilities 75

Clause 2424.1 Accident or Injury to Workmen 7624.2 Insurance Against Accident to Workmen 76

© FIDIC 1989

Page 10: 35824401 FIDIC Guide to the Use of FIDIC

Clause 2525.1 Evidence and Terms of Insurances 7625.2 Adequacy of Insurances 7725.3 Remedy on Contractor's Failure to Insure 7725.4 Compliance with Policy Conditions 77

INSURANCES ARRANGED BY EMPLOYER 78Clause 21Insurance of Works 78Insurance of Contractor's Equipment 78Scope of Cover 78Responsibility for Amounts not Recovered 79Clause 23Third Party Insurance (including Employer's Property) 79Clause 25Evidence and Terms of Insurance 79Adequacy of Insurances 79Remedy on Employer's Failure to Insure 79Compliance with Policy Conditions 79

OTHER OBLIGATIONS OF THE CONTRACTOR 80Clause 26

26.1 Compliance with Statutes, Regulations 80Clause 27

27.1 Fossils 80Clause 28

28.1 Patent Rights 81282 Royalties 81

Clause 2929.1 Interference with Traffic and Adjoining Properties 82

Clause 3030.1 Avoidance of Damage to Roads 8230.2 Transport of Contractor's Equipment or 82

Temporary Works30.3 Transport of Materials or Plant 8330.4 Waterbome Traffic 83

Clause 3]31.1 Opportunities for Other Contractors 8431.2 Facilities for Other Contractors 84

Clause 3232.1 Contractor to Keep Site Clear 85

Clause 3333.1 Clearance of Site on Completion 85

LABOUR 86Clause 34

34.1 Engagement of Staff and Labour 86Rates of Wages and Conditions of Labour 86

10 © FIDIC 1989

Page 11: 35824401 FIDIC Guide to the Use of FIDIC

Employment of Persons in the Service of Others 86Repatriation of Labour 87Housing for Labour 87Accident Prevention Officer; Accidents 87Health and Safety 87Measures against Insect and Pest Nuisance 87

Epidemics 88Burial of the Dead 88Supply of Foodstuffs 88Supply of Water 88Alcoholic Liquor or Drugs 88Arms and Ammunition 88Festivals and Religious Customs 89Disorderly Conduct 89Clause 35

35.1 Returns of Labour and Contractor's Equipment 89Records of Safety and Health 89Reporting of Accidents 89

MATERIALS, PLANT AND WORKMANSHIP 90Clause 36

36.1 Quality of Materials, Plant and Workmanship 9036.2 Cost of Samples 9036.3 Cost of Tests 9036.4 Cost of Tests not Provided for 91

36.5 Engineer's Determination where Tests not 91

Provided forClause 37

37.1 Inspection of Operations 91

37.2 Inspection and Testing 9237.3 Dates for Inspection and Testing 9237.4 Rejection 9237,5 Independent Inspection 93

Clause 3838.1 Examination of Work before Covering up 9338.2 Uncovering and Making Openings 94

Clause 3939.1 Removal of Improper Work, Materials or Plant 94

39.2 Default of Contractor in Compliance 95

SUSPENSION 96Clause 40

40.1 Suspension of Work 9640.2 Engineer's Determination following Suspension 9640.3 Suspension lasting more than 84 days 97

COMMENCEMENT AND DELAYS 98

Clause 41

© FIDIC 1989 11

Page 12: 35824401 FIDIC Guide to the Use of FIDIC

41.1 Commencement of Works 98Clause 42

42.1 Possession of Site and Access Thereto 9842.2 Failure to Give Possession 9942.3 Wayleaves and Facilities 99

Clause 4343.1 Time for Completion 100

Clause 4444.1 Extension of Time for Completion 10044.2 Contractor to Provide Notification 101

and Detailed Particulars44.3 Interim Determination of Extension

Clause 4545.1 Restriction on Working Hours 102

Clause 4646.1 Rate of Progress 102

Clause 4747.1 Liquidated Damages for Delay 10347.2 Reduction of Liquidated Damages 104

Bonus for Completion 104Clause 48

48.1 Taking-Over Certificate 10548.2 Taking Over of Sections or Parts 10648.3 Substantial Completion of Parts 10648.4 Surfaces Requiring Reinstatement 107

Prevention from Testing 107

DEFECTS LIABILITY 108Clause 49

49.1 Defects Liability Period 10849.2 Completion of Outstanding Work 108

and Remedying Defects49.3 Cost of Remedying Defects 10949.4 Contractor's Failure to Carry Out 109

InstructionsExtension of Defects Liability 110No Remedying of Defects in Dredging 110Work after CompletionClause 50

50.1 Contractor to Search

ALTERATIONS, ADDITIONS AND OMISSIONSClause 51

51.1 Variations 11251.2 Instructions for Variations 113

Clause 5252.1 Valuation of Variations 11452.2 Power of Engineer to Fix Rates 115

12 ©FIDIC 1989

Page 13: 35824401 FIDIC Guide to the Use of FIDIC

52.3 Variations Exceeding 15 per cent 11652.4 Daywork 117

PROCEDURE FOR CLAIMS 119Clause 53

53.1 Notice of Claims 11953.2 Contemporary Records 11953.3 Substantiation of Claims 12053.4 Failure to Comply 12053.5 Payment of Claims 121

CONTRACTOR'S EQUIPMENT, TEMPORARYWORKS AND MATERIALS 122Clause 54

54.1 Contractor's Equipment, Temporary Works and 122Materials; Exclusive Use for the WorksVesting 122Revesting and Removal 123

54.2 Employer not Liable for Damage 12354.3 Customs Clearance 12354.4 Re-export of Contractor's Equipment 12354.5 Conditions of Hire of Contractor's Equipment 12454.6 Costs for the Purpose of Clause 63 12454.7 Incorporation of Clause in Subcontracts 12554.8 Approval of Materials not Implied 125

Suitability of Contractor's Equipment 125Preference for Local Products 125Contractor's Arrangements for Services 125Hazards on Site 125Maintenance of Roads, etc. 125

MEASUREMENT 126Clause 55

55.1 Quantities 126Clause 56

56.1 Works to be Measured 126Clause 57

57.1 Method of Measurement 12757.2 Breakdown of Lump Sum Items 127

PROVISIONAL SUMS 128Clause 58

58.1 Definition of 'Provisional Sum' 12858.2 Use of Provisional Sums 12958.3 Production of Vouchers 129

© FIDIC 1989 13

Page 14: 35824401 FIDIC Guide to the Use of FIDIC

NOMINATED SUBCONTRACTORS 130Clause 59

59.1 Definition of 'Nominated Subcontractors' 13059.2 Nominated Subcontractors; Objection 130

to Nomination59.3 Design Requirements to be Expressly Stated 13159.4 Payments to Nominated Subcontractors 13259.5 Certificates of Payment to Nominated 133

Subcontractors

CERTIFICATES OF PAYMENT 134Clause 60

60.1 Monthly Statements 13460.2 Monthly Payments 13560.3 Payment of Retention Money 13660.4 Correction of Certificates 13760.5 Statement at Completion 13760.6 Final Statement 13760.7 Discharge 13860.8 Final Certificate 13860.9 Cessation of Employer's Liability 13960.10 Time for Payment 139

Currency of Account and Rates of Exchange 140Payments to Contractor 140

Payments to Employer 141Currency of Account and Payments 141Place of Payment 141Advance Payment 142Clause 61

61.1 Approval only by Defects Liability 142CertificateClause 62

62.1 Defects Liability Certificate 14362.2 Unfulfilled Obligations 144

REMEDIES 144

Clause 6363.1 Default of Contractor 14463.2 Valuation at Date of Termination 14563.3 Payment after Termination 14663.4 Assignment of Benefit of Agreement 146

Clause 6464.1 Urgent Remedial Work 147

SPECIAL RISKS 147

Clause 6565.1 No Liability for Special Risks 14865.2 Special Risks 148

14 © FIDIC 1989

Page 15: 35824401 FIDIC Guide to the Use of FIDIC

65.3 Damage to Works by Special Risks 14965.4 Projectile, Missile 14965.5 Increased Costs arising from Special Risks 14965.6 Outbreak of War 15065.7 Removal of Contractor's Equipment 150

on Termination65.8 Payment if Contract Terminated 150

RELEASE FROM PERFORMANCE 152Clause 66

66.1 Payment in Event of Release from Performance 152

SETTLEMENT OF DISPUTES 153

Clause 6767.1 Engineer's Decision 153

67.2 Amicable Settlement 155

67.3 Arbitration 155

67.4 Failure to Comply with Engineer's Decision 156

NOTICES 157

Clause 6868.1 Notice to Contractor 157

68.2 Notice to Employer and Engineer 157

68.3 Change of Address 157

DEFAULT OF EMPLOYER 158

Clause 6969.1 Default of Employer 158

69.2 Removal of Contractor's Equipment 15969.3 Payment on Termination 15969.4 Contractor's Entitlement to Suspend Work 16069.5 Resumption of Work 160

CHANGES IN COST AND LEGISLATION 161

Clause 7070.1 Increase or Decrease of Cost 161

70.2 Subsequent Legislation 161

CURRENCY AND RATES OF EXCHANGE 169

Clause 7171.1 Currency Restrictions 169

Clause 7272.1 Rates of Exchange 169

72.2 Currency Proportions 170

72.3 Currencies of Payment for Provisional Sums 171

POSSIBLE SUPPLEMENTARY CLAUSES 172Bribes 172

© FIDIC 1989 15

Page 16: 35824401 FIDIC Guide to the Use of FIDIC

Confidentiality 172Restrictions on Expenditure 173Contractor as Joint Venture 173Special Provision for Duties and Taxes 173

APPENDIX

CONDITIONS OF CONTRACT FOR WORKS OFCIVILENGINEERING CONSTRUCTIONFourth Edition 174Part I GENERAL CONDITIONS

WITH FORMS OF TENDER AND AGREEMENTPart II CONDITIONS OF PARTICULAR APPLICATION

WITH GUIDELINES FOR PREPARATION OFPART II CLAUSES

© FIDIC 1989

Page 17: 35824401 FIDIC Guide to the Use of FIDIC

INTRODUCTION

Standardisation both in technical and administrative matters isessential for the satisfactory completion of projects of civil engi-neering construction. Construction projects today usually containelements of plant and machinery to form part of the completedproject and this makes the contract conditions more complex thanin the past when plant was usually installed under separate con-tracts after completion of the construction contract. In addition,the total finance for a major project is now customarily drawnfrom several sources and the likelihood that the Owner will be ableto obtain additional funding to meet substantial cost over-runs hasbecome exceedingly remote, if not impossible.

In order to complete a project within the required time and budgetit is essential that each phase of its preparation and execution,starting with the assessment of feasibility and terminating with thehanding over of the completed project by the Contractor to theOwner, be formulated with precision in order to limit delays,disputes and unforeseen additional costs.

The object of this publication is to comment on the Clausescontained in the fourth edition of the Conditions of Contract forWorks of Civil Engineering Construction published by the Inter-national Federation of (independent) Consulting Engineers(FIDIC). The extent of the comments on the Sub-Clauses differsconsiderably, as some Clauses are more complex than others, andthe length of a commentary should not be taken to reflect the rela-tive importance of the subject matter.

By way of introduction some notes are included relating to thetendering procedure recommended by FIDIC. More commentaryon this tendering procedure can be found in the FIDIC publicationentitled Tendering Procedure (Procedure for obtaining and evalu-ating tenders for civil engineering contracts) available from FIDICSecretariat.

There are obvious advantages to using detailed contract provi-sions based upon a standard form of contract which holds a rea-sonable balance between the requirements and interests of theparties concerned and in particular allocates fairly the risks andresponsibilities between the contracting parties. In the majority ofcases the contracting parties will react favourably to clearly statedobligations and this will do much to avoid unsatisfactory perform-ance, increased costs and disputes which can arise if the trust thatneeds to exist between the parties to a construction contract islacking.

The use of standard conditions of contract will not only facilitatethe successful completion of a contract but will, in all probability,result in lower tender prices, as tenderers will be familiar with theconditions that will apply under the contract. This implies thatthey will not need to make financial provision for contractconditions with which they are not familiar and whose conse-quences they may have difficulty in assessing. The widespreaduse of standard conditions of contract also provides a stable basisfor training and educating personnel responsible for contractmanagement and avoids their having to work with ever chang-ing contract conditions.

©FIDIC 1989 17

Page 18: 35824401 FIDIC Guide to the Use of FIDIC

The FIDIC Conditions of Contract for Works of Civil Engineer-ing Construction were first published in 1957. Up to that timethere were no conditions which had been specifically prepared togovern international contracts. The first edition of the FIDICConditions (the Red Book as it quickly became known becausethe title was long and the cover was red) was published at a timewhen international contracting was in its boom period and theneed for a standard set of conditions became apparent. The firstedition was based on a form of contract in use in the UnitedKingdom which was published by the Institution of Civil Engi-neers (ICE) and thus very much reflected traditions and a legalsystem that were specifically British.A second edition was issued in the mid-sixties but this did notchange the conditions contained in the first edition, it merelyadded a Part III to the first edition. This Part III was drafted toprovide particular changes to the General Conditions when thedocument was to be used for dredging and land reclamation con-tracts.A third edition which did involve a complete revision waspublished in 1977 and was accompanied by an explanatory docu-ment entitled 'Notes on Documents for Civil Engineering Con-tracts'.FIDIC maintains a committee, the Civil Engineering ContractsCommittee (CECC), which monitors the use of the Red Book andis responsible for reporting to the FIDIC Executive Committee. In1983 the CECC advised the Executive Committee that in somequarters the document was being criticised by Employers (Own-ers) for being too Anglo-Saxon in its concept and language, pre-sumably the result of a far wider use than it had previously en-joyed. Certain amendments were identified which were beingapplied almost consistently by Employers and it was consideredadvisable to bring the Conditions into line with current practice.Another factor was that in many cases where the Conditions werebeing used for projects in developing countries, the representativesof the Employer did not have the breadth of authority to delegateduties to the Engineer which it had been envisaged that they wouldhave when the third edition was prepared and it was felt desirableto reconcile the Conditions with current circumstances.Accordingly, the Executive Committee requested the CECC toprepare a fourth edition and the following is a brief summary ofthe terms of reference— Change only where change is necessary.— Maintain the basic role of the Engineer.— Pay close attention to some specific topics such as Bonds and

Guarantees, Apportionment of Risk, Insurance, Claims Proce-dures, Certificates and Payments and Dispute Procedures.

— Endeavour to update the language so that it is more understand-able to those charged with administering the Conditions on site.

There were some procedural differences in the drafting process ascompared with the third edition. In the preparation of the thirdedition, representatives of the Contractors' Associations had par-ticipated almost as co-drafters and it had been indicated on the

18 ©FIDIC 1989

Page 19: 35824401 FIDIC Guide to the Use of FIDIC

cover of the Conditions that the document was approved by thevarious contractors' groupings throughout the world. For the fourthedition it was agreed that the contractors' representatives wouldhave consultative status during the drafting process but the finaldocument would be the sole responsibility of FIDIC. EuropeanInternational Contractors (EIC) were mandated by the Confed-eration of International Contractors' Associations (CICA) to rep-resent CICA in this consultative role and the ETC representativeswere assisted by two representatives of the Associated GeneralContractors of America (AGC).In addition, during the course of the revision there was considera-bly more consultation with the World Bank than had been the casein previous revisions. Also, FIDIC was able to benefit frommeetings with representatives of the Joint Arab Funds, who havesubstantial experience in monitoring the use of the third edition.FIDIC greatly appreciated the opportunity for consultation withboth of these bodies, but this consultation does not imply that eitherorganisation approves the fourth edition in its entirety.The CECC members also availed themselves of the opportunity toconsult experts in the fields where they themselves did not claimany particular expertise other than practical experience. In particu-lar this applied to insurance and law.This book deals with each specific clause and gives a commentaryupon the clause by those responsible for the drafting but it willprobably be helpful at this point to summarise the principalchanges from the third edition.

EDITORIALPart II (Conditions of Particular Application) has been greatlyexpanded by going from an aide memoire to a fairly compre-hensive set of fully developed example clauses.

— Part II has been printed as a separate volume. This enables PartI (General Conditions) to be attached to the tender documents intheir printed form. This provides satisfactory evidence that nochanges have been made therein and that whatever changes arerequired will be effected by an entry in Part II.

— The previous Part III (Dredging and Reclamation Works) hasbeen incorporated into Part II.

— The listing of the various Contractors' Associations no longerappears but this does not affect the use of the Conditions bymembers of CICA Member Associations.

— The style of the language and the layout of the clauses has beenmodernised to some degree but the sequence numbering of theclauses has been preserved.

GENERAL PRINCIPLES— The role of the Engineer has been maintained.— The role of the Employer has been made more visible. Where

increases in cost or extensions of time are to be determined bythe Engineer, he has an obligation to consult with both theEmployer and the Contractor before making his determination.

1(WQ 19

Page 20: 35824401 FIDIC Guide to the Use of FIDIC

— Every endeavour has been made to maintain the overall balanceof rights and obligations between the two parties to the contract.

— Current practice has been reflected in the new edition.— Procedures have been set out in greater detail and in an action-

orientated way.— The Conditions cater for a larger degree of Plant.— Greater recognition has been made of the fact that some design

of Permanent Works is, on occasion, made the responsibility ofthe Contractor.

HARMONISATIONWhere possible, efforts have been made to harmonise with theConditions of Contract for Electrical and Mechanical Works (theYellow Book). However, having regard to the differing nature ofthe works some notable differences remain. This would not pre-vent the two sets of conditions being used by different contractorson the same site.

GENERALThe material in this Guide does not form part of the Conditionsnor is it intended to be incorporated in the Conditions other thanby the use of example clauses. Further, it does not purport to givean authoritative legal interpretation of the Conditions, but it is en-visaged that it will be helpful in the understanding of the intent ofthe Conditions and in drafting particular Part II Conditions.

For the successful achievement of a project the first essential is tohave Drawings and Specifications, based upon competent designs,together with a Bill of Quantities to enable the probable cost ofthe Works to be established.

These documents, together with the Conditions of Contract, formthe legal document which, under the applicable law, defines therights and obligations of the two parties, the Employer and theContractor, in their relationship for the realisation of the project.However, the legal document also establishes the working relation-ship within which an employer can expect to receive from anefficient contractor a soundly executed project to time and cost.Equally, a contractor can expect reasonable working conditions,fair and balanced application of the Contract and to be paidpromptly what he is entitled to receive.

To achieve optimum results it is essential that when tenders areinvited, tenderers are not expected to cover in the rates they quotefor risks which they could not reasonably foresee or evaluate atthe time of preparation of their tenders.

It is in the Employer's interest for him to assume responsibilityunder the Contract for costs arising from events which may neveroccur, which lie outside the Contractor's control or which cannotbe covered by insurance at a reasonable premium. Such eventsare classified in the fourth edition as Employer's Risks.

20 ©FIDIC 1989

Page 21: 35824401 FIDIC Guide to the Use of FIDIC

Against this background competent and experienced contractorsare able to submit competitive tenders, without the need to includelarge contingency sums to cover unpredictable hazards. TheEmployer will only meet the cost of such hazards if they actuallyoccur.

Close cooperation and teamwork between Employer, Contractorand Engineer, within the framework of the Contract, with a mu-tual desire to produce a satisfactory end product by well organi-sed, safe and efficient methods, will reduce to a minimum the riskof delays or misunderstandings. When mistrust or lack of confi-dence occurs troubles may arise and a contract may run into dif-ficulties. No wording in the Contract can prevent this from hap-pening if one or both of the parties or the Engineer fails to per-form his duty under the Contract responsibly and correctly.The FIDIC Conditions of Contract have been written for usewhere the services of an independent Engineer are used for super-vision of construction. The Conditions provide under Sub-Clause2.6 that where the Engineer is required to exercise his discretionhe shall act impartially. If the Engineer is an employee of theEmployer, such impartiality is still required.

© FIDIC 1989 21

Page 22: 35824401 FIDIC Guide to the Use of FIDIC

TENDERING PROCEDURE

The FIDIC Conditions of Contract envisage that a contractor willbe selected by the Employer following competitive tendering.FIDIC has published a document entitled 'Tendering Procedure'which presents a systematic approach to the selection of tenderersand the obtaining and evaluating of tenders. It is intended to assistthe Employer/Engineer to receive sound competitive tenders witha minimum of qualifications and formulated so that they can bequickly and efficiently assessed. At the same time, every efforthas been made to provide the opportunity and incentive for con-tractors to respond easily to invitations to tender for projects theyare well qualified to implement.

Experience has shown that, for major projects and those involvinginternational tendering, prequalification of tenderers is desirablesince it enables the Employer/Engineer to establish, in advance,the competence of firms subsequently invited to tender. It alsoensures that invitations are addressed to leading companies whowould not necessarily participate in open or unrestricted tender-ing. Such unrestricted tendering does not always facilitate appro-priate competition because the number of tenderers may be so greatas to make the odds against tendering successfully unacceptable.Additionally, prequalification has the advantage of reducing theinflationary effect which must arise where firms incur unproduc-tive expense in submitting a large number of tenders in the knowl-edge that a high proportion of these must be unsuccessful.A flowchart illustrating the recommended procedures for the pre-qualification of tenderers, for obtaining tenders and for openingand evaluation of tenders is reproduced on subsequent pages.The documents issued to tenderers (the Tender documents) nor-mally comprise Conditions of Contract, Specification, Drawings,Bill of Quantities and form of Tender, together with Instructionsto Tenderers. All except Instructions to Tenderers becomeContract documents on award of Contract. It is usual to send theTender documents to tenderers under cover of a letter whichshould be limited to identifying the documents and giving therecipient an invitation to tender.

Conditions of ContractThe Conditions of Contract will consist of Part I and Part II of theRed Book. The Conditions set out the legal/contractual arrange-ments that will apply to the Contract. The principles and themethod to be followed in their preparation are described in a laterchapter of this Guide.

SpecificationThe Specification will define the scope and the technical require-ments of the Contract. The quality of materials and the standardsof workmanship to be provided by the Contractor must be clearlydescribed, together with the extent, if any, to which the Contractorwill be responsible for the design of the permanent works. Detailsmust be included of samples to be provided and tests to be carriedout by the Contractor during the course of the Contract. Anylimitations on the Contractor's freedom of choice in the order,timing or methods of executing the work or sections of the works

22 © FIDIC 1989

Page 23: 35824401 FIDIC Guide to the Use of FIDIC

must be clearly set out and any restrictions in his use of thesite of the works, such as the provision of access or space for othercontractors, must be given.

DrawingsThe Drawings must be in sufficient detail to enable tenderers toassess accurately, in conjunction with the Specification and the Billof Quantities, the nature and scope of work included in the Con-tract. Only rarely is it possible to provide, at tender stage, acomplete set of drawings so fully detailed that the work can beexecuted without any further drawings becoming necessary. Onmost contracts supplementary drawings will be issued after awardas work proceeds.

Bill of QuantitiesThe Bill of Quantities is a list of items giving descriptions andestimated quantities of work to be executed under the Contract.The Red Book assumes a remeasurement form of contract, al-though that does not preclude the inclusion of a number of lumpsum items in the Bill of Quantities provided that the scope ofwork to be covered by each lump sum item is adequately defined.

The TenderIt is highly desirable when inviting competitive offers from anumber of tenderers, that the tenders received should be based asfar as possible on equal terms and conditions and presented in astandardised manner. In this way evaluation and comparison be-tween the tenders received can be made more simply and accu-rately with less risk of misunderstandings, errors and omissions.

The Tender is the most important single document submitted bythe tenderer. It is here that each tenderer confirms that he has readand understood the requirements of the Tender documents andbased on such requirements it is here that he states his tender sumfor undertaking and fulfilling all his obligations under the Con-tract. It is therefore essential for the Employer that all Tendersreceived are stated in identical terms and thus it is necessary forthe Employer, when inviting Tenders, to provide tenderers with astandard form of tender which each tenderer is required to com-plete and sign.The form of Tender which is included at the end of the first vol-ume of the Red Book following Part I of the Conditions of Con-tract is recommended for this purpose. It is short, it is clear andwhen signed and submitted creates a legally binding and validoffer.It is common for Tenders to be identified by a tender reference orcontract number which should be added to link the Tender to theproject in question.The organisation to which the Tender is being submitted must bestated in the appropriate space on the form.The sum to be entered under paragraph 1 of the Tender is thetenderer's total Tender sum, which should be the same as the total

© FIDIC 1989 23

Page 24: 35824401 FIDIC Guide to the Use of FIDIC

from the summary page of the Bill of Quantities. The amount shallbe entered in words and in figures and in the event of a discrep-ancy between the two it is common practice in most countries thatthe written amount shall prevail over the amount expressed infigures.The sum agreed may vary during the execution of the projectdepending on what circumstances occur, e.g. the instruction ofvariations, the occurrence of unforeseen events, which in accor-dance with the Conditions of Contract entitle the Contractor toadditional (or reduced) payment.Under paragraph 4 the Employer must state the time during whichhe requires the Tender to remain valid and open to acceptance.This time should be adequate to permit proper evaluation andaward procedures to be completed.

In the event that the stated time proves to be insufficient, theEmployer may ask tenderers to extend the period of validity oftheir Tenders for a further named period. At the same time ten-derers should be asked to extend the validity of any tender bondaccordingly. Tenderers are free to extend or not, if so requested,and in the event that they choose not to do so, the Employer hasno right to cash or hold their tender bond.The Employer must also fill in, before the issue of the Tenderdocuments, the necessary details in the list given in the Appendixto Tender, in accordance with the Notes at the foot of the Appen-dix.

No reference is given to a covering letter in the form of Tendergiven in the Red Book. The completed Tender is, in many cases,sufficient in itself. If tenderers are invited or required to submitsupplementary information, they should do so under a separatecovering letter and in such a case it may be necessary for tender-ers to add a reference to this letter in the Tender before submis-sion.

Instructions to TenderersInstructions to tenderers must be prepared to meet the requirementsof individual contracts. Their purpose is to convey informationand instructions which apply during the tendering period. Anymaterial on which it is intended to rely after award must be in-cluded elsewhere, e.g. in the Conditions of Contract or the Speci-fication.

The following notes provide a guide to subjects to be covered, butthey are not necessarily exhaustive.

1. GeneralUnder this heading should be included brief details of the or-ganisation (Government, Ministry, Department, Authority,etc.) calling for Tenders, together with an outline of the proj-ect to be covered by the Contract.

24 © FIDIC 1989

Page 25: 35824401 FIDIC Guide to the Use of FIDIC

Any stipulations regarding firms and persons qualified to ten-der, such as prior prequalification and/or requirements in theevent of formation of joint ventures, should be stated, togetherwith details of any special requirements to establish the valid-ity of the Tender and the authority of the signatory, e.g. Powerof Attorney.

Tenderers must be advised if the successful tenderer will berequired to establish a locally registered company for the pur-pose of the Contract.

2. DocumentsA list of documents issued to tenderers should be includedtogether with instructions as to which of these documents mustbe completed by the tenderer and handed in on the submissiondate.

If the Tender documents are not issued free of charge then thesum required for the original set and for any additional setsshould be stated and whether payment is to be made in localor equivalent foreign currency. Tenderers should be advisedas to how the extra sets of documents can be obtained and alsoof procedures to be followed for the return of the documentsby unsuccessful tenderers.

3. Completion and Submission of TendersConcise instructions as to the time, date and place for thesubmission of Tenders should be given.It should also be made clear to tenderers that all entries andsignatures should be in indelible ink and that no erasures oradditions are permitted other than those necessary to correcterrors. All such corrections must be initialled.It is normal to ask for more than one copy of the Tender, inwhich case tenderers should be instructed as to the manner inwhich the Tenders are to be packaged.It is usual to stipulate that one set of documents should beclearly marked 'Original Tender' and others marked 'Copy',and that if there are discrepancies the Original Tender takesprecedence. Photocopies of the Original Tender minimise therisk of discrepancies.The tenderer should be told whether, if he has handed in hisTender before the formal submission date or has sent it by post,he has the right to withdraw, modify or correct it after dispatch.This would normally be permitted, provided that a request formodification, etc., has been received by the Employer eitherin writing or by cable, telex or facsimile transmission beforethe time set for receiving Tenders. The Original Tender asamended would then be considered as the official offer.

4. Supplementary Information Required.Tenderers should be advised of any supplementary informa-tion to be submitted with the Tender documents, such as de-tails of the proposed sureties for any performance security,

©FIDIC 1989 25

Page 26: 35824401 FIDIC Guide to the Use of FIDIC

general terms of insurance (see Sub-Clause 25.1 of the Condi-tions of Contract) the constitution of the tenderer's organisa-tion together with the address to be used for the purposes ofthe Contract, a preliminary programme of work (the Instruc-tions to Tenderers should give an indication of what is re-quired) and a list of major items of Contractor's Equipmentrequired for the purpose of executing the works.

A forecast of labour and staff, local and foreign, may be re-quested. Where a Tender sum has been requested on the basisthat it is adjustable by reason of changes in the cost of labour,materials and transport, the tenderer should, unless the particu-lars are given by the Employer in the Tender documents, berequested to indicate the formula or formulae which he wishesto use as the basis for adjusting the sum. If his formula is tobe index based, officially published indices should be used.These would normally be indices published in the countrywhere the project is to be located. The tenderer should alsoprovide the names of any subcontractors he proposes toemploy, together with details of those parts of the worksproposed to be subcontracted.It must also be made clear in the Instructions to Tenderers towhat extent the supplementary information is required by theEmployer purely to demonstrate that the tenderer has under-stood the extent and nature of the work and the programmerequired and to what extent, if at all, the supplementary infor-mation is required as a part of the offer for inclusion in theContract documents on award.

5. Amendments to Tender DocumentsIt is possible that explanations, revisions, additions or deletionsto the documents issued to tenderers may be necessary duringthe tendering period. Tenderers should be told how these willbe dealt with, the normal method being by formal addenda. Ifa tenderer is in doubt about the meaning of some item in theTender documents, he should be advised to notify the Engi-neer not later than a given number of days (e.g. 42 days) beforethe Tender submission date. The Engineer will then issue toall tenderers an explanation in the form of an addendum. Eachaddendum should be accompanied by a receipt form whichmust be returned so that the Employer and the Engineer haveconfirmation that each tenderer has received all the necessaryinformation. Failure to acknowledge receipt of an addendummay result in rejection of a Tender. The addenda become partof the Tender documents and the numbers issued should beinserted by tenderers in the space provided in paragraph 1 ofthe form of Tender.Tenderers would normally be required to submit their offersstrictly in accordance with the requirements of the Tenderdocuments. If tenderers are permitted to offer an alternativeTender, any departure from the documents issued to tenderersshould be clearly identified and detailed. The option to sub-mit alternative Tenders may make the evaluation process dif-ficult.

26 © FIDIC 1989

Page 27: 35824401 FIDIC Guide to the Use of FIDIC

6. Currency Requirements and Exchange RatesTenderers should be required to give notice to the Employerof the various currencies in which they may wish to be paid ifthe Contract is awarded to them. This information should besupplied as soon as possible after invitations to tender havebeen issued and not less than a given number of days (e.g. 42days) before the Tender submission date.

The Employer may wish to specify in the Instructions to Ten-derers that payments will be made only in the currencies ofthe countries from which the goods and services are to be ac-quired.The Tender documents should include a schedule in whichtenderers record the sums in the various approved currenciesthat together constitute their total Tender sum. This schedulebecomes part of the Contract when awarded.

It is common practice to require tenderers to submit theirTenders in a single currency - usually of the country in whichthe Works are to be executed. If this is the case it is necessaryto define the rates of exchange which have been used toconvert the various currencies, in which payment is required,into a single currency unit. As more than one tenderer mayrequest part payment in one particular currency, it is prefer-able that the exchange rates to be used should be consistentand, therefore, that they should be defined by the Employerand notified by him, or the Engineer on his behalf, to eachtenderer a reasonable time before the date of submission. Inaccordance with Sub-Clause 72.2 of the Conditions of Con-tract, these rates shall be stated in Part II or, if not so stated,shall be those prevailing, as determined by the Central Bankof the country in which the works are to be executed, on thedate 28 days prior to the latest date for the submission ofTenders or as provided for in the Tender. The rates quoted areincorporated in the Contract when awarded.

In order to assist in forward budgeting it is useful to requesttenderers to provide an estimate of the payments to be madeby the Employer to the Contractor during the period of theContract, preferably in quarterly periods.The estimate of payments referred to above does not becomea part of the Contract and should not be regarded as binding.The figures may have to be reviewed and adjusted as the workproceeds. Expenditure under Provisional Sums will affect thefigures, and so also will changes in the source of supply ofmaterials and modifications to the programme or variations ofthe Works.

7. Site VisitsIt is customary to expect tenderers to visit the site of the projectduring the tender period. Details should be given of the dateand arrangements for visiting when staff of the Employer and

© FIDIC 1989 27

Page 28: 35824401 FIDIC Guide to the Use of FIDIC

the Engineer will be on site to answer questions and when anyexploratory work carried out will be available for inspection,e.g. borehole cores laid out and exploratory adits lit. Asummary of all questions and answers thereto should be issuedto all tenderers. Tenderers should not be restricted in their sitevisits and details of who to contact for further visits should begiven.

8. Tender BondIf a tender bond is required, a pro forma version of such bondshould be included in the Tender documents. The amount ofthe bond should be stated and the currency or currencies re-quired. In all cases the surety or sureties must be satisfactoryto the Employer. If a tender bond has been requested, anyTender that has not been so secured will be rejected unlessotherwise indicated.

Tenderers should be advised that the bond will be released aftera specified period, or earlier if one of the Tenders has, withinthe period, been accepted by the Employer and an acceptableperformance security has been submitted by the successful ten-derer. It should also be made clear what will happen to thetender bond if the tenderer who has been accepted fails toprovide a performance security within a specified number ofdays after being requested to do so. Usually the tender bondwill be forfeited.

9. BonusIf a bonus in relation to early completion is to be included inthe Contract, tenderers should be reminded to state in the spaceprovided in the Appendix to Tender what proportions of localand foreign currencies they wish to receive if they earn it.

10. Local LegislationIf there are any local laws or decrees or any special arrange-ments which the Employer wishes the tenderers to note par-ticularly, these should be listed in the Instructions to Tender-ers. It should be made clear that the list is not comprehensive.

11. Examination of TendersTenderers should be advised that the Employer, or the Engi-neer on behalf of the Employer, may ask any tenderer forclarification of his Tender, but that no tenderer will be permit-ted to alter his Tender sum after Tenders have been opened.Clarifications that do not change the Tender sum may, if theyare acceptable, be incorporated in the Contract.

It should be made clear that all Tenders must remain valid fora specified validity period and any extension thereto agreed toby the respective tenderer.

28 ©FIDIC 1989

Page 29: 35824401 FIDIC Guide to the Use of FIDIC

Tenderers should be advised if any factors other than theTender sum, such as foreign currency proportions, are to betaken into account when evaluating Tenders.

12. Acceptance of TenderThe Employer will normally state that he does not bind him-self to award the Contract to the tenderer submitting the lowesttender or to any tenderer.

Evaluation of TendersTenders for major and international contracts are generally openedin public when the names of the tenderers are announced togetherwith the Tender sum. No other details are given at that time.Thereafter the Tenders are checked and studied by the Engineeron behalf of the Employer.One of the first tasks of the Engineer is to establish whether theTenders are arithmetically correct and, if they are not, how toovercome any errors. Another task is to check that the Tendersare responsive, that all the required information has been providedand that everything is consistent with the terms of the Tender docu-ments.

If errors, omissions or inconsistencies are apparent a meetingshould be held with the lowest tenderer, and possibly with one ortwo other tenderers, to clarify the position and to agree how to dealwith the points in the event of an award. At such meetings, ten-derers should not be permitted to change the substance of theirTenders. If it does not prove possible to clarify and agree howdifferences are to be resolved, the particular Tender should betreated as unresponsive and no further consideration should begiven to that Tender.

Award of ContractWhen the Engineer has completed the evaluation of tenders, andhas obtained any necessary clarifications, he will make a recom-mendation to the Employer on the award of the Contract. If theEmployer agrees with the Engineer's recommendation and is in aposition to award the Contract immediately he will issue a Letterof Acceptance to the successful tenderer.

On occasions certain steps may still be necessary before the Em-ployer can award the Contract, e.g. Government approval or rati-fication of a loan agreement. In such a case, the Employer maydecide to issue to the potential Contractor a letter of intent. Sucha letter should state the conditions that must be met before theaward can be made. In most cases letters of intent are worded insuch a way as to create no commitment on the part of the Em-ployer and the potential Contractor carries out any preliminarywork or incurs costs at his own risk. Sometimes a letter of intentgives instructions to the potential Contractor to take someaction, such as to order materials and Plant or to carry out limitedwork. In this case, it is necessary for the letter of intent to be

©FIDIC 1989 29

Page 30: 35824401 FIDIC Guide to the Use of FIDIC

clear about how, and to what extent, the potential Contractor willbe paid for what he does if, for any reason, the Contract is notultimately entered into.In most cases it is the Employer's Letter of Acceptance which,together with the tenderer's Tender, will form a binding Contractbetween the two parties, valid from the date of issue of the Letter.If on account of errors, omissions or inconsistencies in the Ten-der, or for any other reason, any changes have been tentativelyagreed at a meeting of clarification, the Employer's letter mayconstitute only a counter-offer and the Contract will only be bind-ing on the date that the Contractor acknowledges and confirms, inwriting, agreement to the terms of the Letter of Acceptance.

Contract AgreementThe Conditions of Contract, Sub-Clause 9.1, make provision forthe execution of a Contract Agreement between the parties whichwill record all the terms of the Contract between them. However,the execution of this document is not normally necessary to createa legally binding contract.Nevertheless, in some countries a Contract Agreement is a require-ment of law to create a binding Contract irrespective of the exis-tence of a Tender and a Letter of Acceptance. In such cases, inparticular, the Contract Agreement must be carefully prepared tocomply with the requirements of the relevant law.An example form of Contract Agreement is included at the end ofthe first volume of the Red Book following Part I of the Condi-tions of Contract and may be used in the event that the Employerwishes to execute a formal agreement. In such event it isimportant to ensure that the exact wording of the Contract Agree-ment, including the documents listed as forming part thereof,properly records what has been agreed.The parties must ensure that the signatories and method of signa-ture are in accordance with all the applicable laws.

Note: The FIDIC publication 'Tendering Procedure' mentionedat the beginning of this chapter, gives fuller details of allstages of tendering and should be studied by all thoseinvolved in such process.

30 ©FIDIC 1989

Page 31: 35824401 FIDIC Guide to the Use of FIDIC

ANALYSE PREOUALIFICATIONDATA:• COMPANY/JOINT VENTURE

STRUCTURE.• EXPERIENCE• RESOURCES• FINANCIAL STABILITY• GENERAL SUITABILITY

NOTIFY ALL CONTRACTORS/JOINT VENTURES OF THELIST OF SELECTEDTEN DER ERS.

LIST OF TENOERERS

——+—REQUESTPREQUALIFICATIONDOCUMENTS

FOR SHORT" ______________________

LIST ONLY J ACKNOWLEDGE RECEIPT

i CONFIRM INTENTION TO

1 SUBMIT VALID TENDER

©FIDIC 1989 31

PROCEDURAL FLOWCHARTS

Recommended procedurefor the prequalification of tenderers

SEC1]ON — — EMPLOYER/ENGINEER — ..- — CONTRACTORS —

PLACE PREQUALIFICATIONADVERTISEMENT INPRESS, EMBASSIES ETC.AS APPROPR lATE STATING:• EMPLOYER & ENGINEER• OUTLINE OF PROJECT

(SCOPE, LOCATION,PROGRAMME)

• ENQUIRY ISSUE & TENDERSUBMISSION DATES

• INSTRUCTIONS FORAPPLYING FORPREOUALIFICATION

• SUBMISSION DATE FORCONTRACTORS' PRE-QUALIFICATION DATA.

/'——F

1.0 INVITATION TOCONTRACTORS TOPR EQUAL IFY

2.0 ISSUE & SUBMISSIONOF PREQUALIFICATIONDOCUMENTS

3.0 ANALYSIS OFPREQUALIFICATIONDATA AND SELECTION& NOTIFICATION OFLIST OF SELECTEDTENDERERS

ISSUE PREQUALIFICATIONINSTRUCTIONS &QUESTIONNAIRESREQUESTING FROMEACH COMPANY/JOINTVENTURE:• ORGAN ISATION AND

STRUCTURE.• EXPERIENCE IN THE

INTENDED TYPE OFWORK AND THECOUNTRY.

• RESOURCES:MANAGERIALTECHNICALLABOURPLANT

• FINANCIAL STATEMENTS

ACKNOWLEDGE RECEIPT

RESPOND TO QUESTIONNAIRESON COMPANIES AND, IFAPPROPRIATE, JOINT VENTURES I

I

- r —

wSELECT COMPANIES/ JOINTVENTURES FOR INCLUSIONIN LIST OF TENDER ERS

I

I

I

——f

Page 32: 35824401 FIDIC Guide to the Use of FIDIC

Recommended procedurefor obtaining tenders

SECTION — — — —— EMPLOYER/ENG'JEER — — — TENDERERS

32 ©FIDIC 1989

4.0 ENQUIRY LIST OFDOCUMENTS TENDERERS PREPARE

ENQUIRY DOCUMENTS

• LETFER OF INVITATIONTO TENDER

• INSTRUCTIONS TOTEN DER B AS

• CONDITIONS OFCONTRACT

• SPECIFICATION• DRAWINGS• BILL OF QUANTITIES• INFORMATION DATA• FOAMOFTENDER&

APPENDICES

5.0 ISSUE OFENQUIRYDOCUMENTS

6.0 VISITS TOSITE BYTENDERERS

ACKNOWLEDGE RECEIPT

COMMENCE PREPARATIONOF TENDERS

APPLY FOR VISIT TOSITE IF REQUIRED

7.0 AMENDMENTSTO ENQUIRYDOCUMENTS

ACKNOWLEDGE RECEIPT

Page 33: 35824401 FIDIC Guide to the Use of FIDIC

Recommended procedurefor obtaining tenders (continued)

SUPPLEMENTARY QUERIES & _________________ISSUE TEXTOF QUERIES.

jREPLIES TO ALL TENDERERS

RECORD DATE & TIME OFRECEIPT

ACKNOWLEDGE RECEIPT

ORRETURN UNOPENED ANYTENDERS RECEIVED LATE

TKEEP DATE — VALIDTENDERS SECURE UNTILOPENING TIME

——TENDER OPENING

RAISE QUERIES OF ANY)BY METHOD a) orb)BELOW:

a) BY CORRESPONDENCE:SUBMIT QUERIES INWA I TING

ORb) BYTENOERERS

CONFERENCE: SUBMITALL QUERIES IN WRITINGBY GIVEN DATE

ACKNOWLEDGE RECEIPTRETURN ENQUIRYDOCUMENTS

©FIDIC 1989 33

SECTION — — .EMPLOYER/ENGINEER'V TENDERERS 'V

PREPARE REPLIES

$ISSUE QUERIES & REPLIESTO ALL TENDERERS INWRITING

8.0 TENDERERS'QUERIESCorrespondenceMethod

OR

Tenderers'ConferenceMethod

9.0 SUBMISSION ANDRECEIPTOF TENDERS

ACKNOWLEDGE RECEIPT

PREPARE REPLIES

TENDERERS CONFERENCE

FIRST PHASE: INFORM TENDERERS PRESENTOF QUERIES & REPLIES.

SECOND PHASE: TENDERERS SUBMIT ANYSUPPLEMENTARY QUERIES INWRITING.

THIROPHASE: REPLIESTOSUPPLEMENTARYQUERIES GIVEN ORALLY.

r ADVISE TENDERERS —WHOSE TENDERS HAVE NOT (OPTIONAL)

I BEEN RECEIVED THREEL DAYSBEFORE CLOSING DATE

ACKNOWLEDGE RECEIPT

SUBMIT TENDERS

1

Page 34: 35824401 FIDIC Guide to the Use of FIDIC

Recommended procedure forthe opening and evaluation of tenders

— SECTKN — — yr EMPLOYER/ENGINEER w — — TENDERERS —

10.0 OPENING OF, ___________________________TENDERS

ADVISE UNSUCCESSFULTENDERERS. RETURNTENDER BONDS(IF PROVIDED)

34 ©FIDIC 1989

ATTEND PUBLIC/RESTRICTED OPENING IFDESIRED.

TENDER OPENING

MAY BE PUBLIC, RESTRICTED ORPRIVATE.

• ANNOUNCE AND RECORD THENAMES OF TENDERERS ANDPRICES, INCLUDING PRICES FORALTERNATIVE TENDERS IFAPPROPRIATE.

• ANNOUNCE AND RECORD NAMESOF TENDERERS (IF ANY)DISQUALIFIED DUE TO LATE ORNON-ARRIVAL OF TENDERS.

—--—*r——————11.0 EVALUATION OF EVALUATE TENDER

TENDERS• TECHNICAL• CONTRACTUAL• COMMERCIAL

RAISE POINTS REQUIRINGCLARIFICATION, IF ANY.

COMPLETE EVALUATION

MEETINGS WITH SELECTED TENDERERSINDIVIDUALLY. AS NECESSARY TODISCUSS ANY QUALIFICATIONS OR DTHEASPECTS NOT CONFORMING TO THE

tONONcONcT

AWARD OFCONTRACT

_)II.J PROVIDE CLARIFICATION

I

(IF APPROPRIATE)

V

DOCUMENTSPREPARE CONTRACT

SIGNATURE OF CONTRACTSIGNATURE OF CONTRACT(SUCCESSFUL TENDERER)

UNSUCCESSFUL TENDE PEASACKNOWLEDGE, RETURNENQUIRY DOCUMENTS IFSO INSTRUCTED

Page 35: 35824401 FIDIC Guide to the Use of FIDIC

THE PARTIES TO THE CONTRACT

The FIDIC Conditions of Contract are based on the assumptionthat the Employer, the first party, who has decided to have certainworks carried out for the implementation of a project, and issponsoring the Works, has decided to select a suitably qualifiedContractor, the second party, to execute the Works.It is also assumed that the selection of the Contractor will havebeen made through competitive tendering based on tender docu-ments prepared for the project by a Consulting Engineer. Thisprocess has been dealt with in the preceding section.The FIDIC Conditions of Contract cannot apply without an Engi-neer being appointed by the Employer to administer theContract. Usually this would be the Consulting Engineer whohas designed the project and prepared the tender documents. TheEngineer is not a party to the Contract, but he plays an impor-tant role in the development process of the Works. The dutiesthat the Engineer has to perform are defined under the Contractand he must have the necessary delegated authority from theEmployer if he is to be able to perform them. The delegation ofthis authority is usually to be found in the Agreement between theEmployer and the Consulting Engineer.FIDIC will soon publish an updated model form of such an agree-ment: Client/Consultant Model Services Contract (The "WhiteBook" — formerly called IGRA).The Agreement will stipulate as the primary duty of the Engineerthat he carefully observes the requirements of the Employer in therealisation of the project. It is important to note, however,that the Conditions of Contract between the Employer and the Con-tractor stipulate that where, under the Contract, any of the Engi-neer's duties are discretionary, the Engineer shall act fairly be-tween the Employer and the Contractor and apply the Contract inan unbiased manner. The Conditions are based upon this funda-mental principle and this requirement applies even if the Engi-neer is a member of the Employer's staff. The Contractor will, ofcourse, have to assess whether or not he has confidence in theability of an in-house Engineer to take independent decisions.

The EmployerAs stated in the section dealing with the tendering process, theEmployer notifies the successful tenderer that he has been awardedthe Contract by issuing a Letter of Acceptance which records anychanges to the the Tender documents as submitted by the Contrac-tor, resulting from agreement between the Employer and the Con-tractor, and the Contract Price.

The Employer consents to, or declines, requests by the Contractorto assign any portion of the Works, prepares the ContractAgreement (if any) for execution by both parties, approves thePerformance Security and the insurers as well as the terms ofthe insurance policies submitted by the Contractor. The Employerwill wish to ensure that the contract works insurance is in accor-dance with the laws and regulations of the country in which theWorks are to be executed and that the policy adequately coversthe Employer's Risks and the deductible limits are acceptable.

©FIDIC 1989 35

Page 36: 35824401 FIDIC Guide to the Use of FIDIC

Provided it is acceptable to the Employer the Contractor willnormally use his customary sources for the provision of secu-rities and insurance.

The Employer makes the advance payment (if any) againsta suitable guarantee from the Contractor and authorises theContractor to move on to the Site. During the period of theContract the Employer makes payments to the Contractor ascertified by the Engineer to be due under the Contract.The Employer takes over Sections of the Works as they reachsubstantial completion, if this is required under the Contract, andultimately takes over the whole of the Works following the issueof Certificates by the Engineer. In the event of the Contractorbecoming liable for liquidated damages, the Employer may deductan amount in accordance with the Conditions of Contract.The Employer may authorise work to be completed by others ifthe Contractor is in default. The Employer can terminate theContract in the event of the Contractor failing to perform or incertain other circumstances defined in, and subject to, the lawgoverning to the Contract. The Employer, if he defaults, canalso be subject to cancellation of the Contract by the Contractor orto suspension of work by the Contractor.The Employer and the Engineer should maintain such contact witheach other as will facilitate smooth and unhindered progress of theWorks. The Employer should respond, without delay, on allmatters for which the Engineer is required by the Contract toconsult the Employer before issuing an instruction, determiningan amount to be added to or deducted from the Contract Price orgranting an extension of time.

The ContractorThe obligation of the Contractor is to execute and complete theWorks, for which he has submitted his Tender, within the timespecified in the Contract. In addition he has an obligation toremedy any defects which appear during the Defects LiabilityPeriod.

As soon as is reasonably possible after receiving notification fromthe Engineer, the Contractor shall submit the securities, guaran-tees and insurance policies required by the Contract and shallcommence the Works. He prepares the construction programme,provides all necessary materials, Contractor's Equipment, Tempo-rary Works, management, superintendence and labour and selectsthe method of carrying out the Works. The Contractor is notresponsible for the design and specification of the PermanentWorks unless expressly provided for in the Contract nor for anyTemporary Works not designed by him.The Contractor receives and complies with instructions from theEngineer acting on behalf of the Employer and is responsible forthe care of the Works throughout the construction period untilthe Works are officially taken over by the Employer or are deemedto be taken over by the Employer.

36 ©FIDIC 1989

Page 37: 35824401 FIDIC Guide to the Use of FIDIC

The Contractor is responsible for his own staff and work forceand for taking out social and other insurances in respect of hispersonnel. He must comply with all applicable laws, by-laws andregulations and ensure that all those for whom he is responsiblealso comply.

Under normal circumstances the Contractor designs all Tempo-rary Works and submits his proposals, with supporting calcula-tions, to the Engineer for comment. If, during the constructionperiod, he encounters unforeseen physical obstructions or condi-tions on the Site he notifies the Engineer who issues relevantinstructions. The Engineer will review the circumstances and afterconsultation with both parties will determine to what extent, ifany, the Contractor may be reimbursed for additional costs orgranted an extension of the Time for Completion.

In the event of default by the Employer the Contractor maysuspend progress of the Works or reduce the rate of work andclaim an appropriate extension of time and/or additional payment.

Normally there will be one main or principal contractor who signsthe Contract and has overall responsibility for the execution andcompletion of the project. There will usually be a number ofSubcontractors working on the Site undertaking specialist con-tracting activities. The Subcontractors are responsible to theContractor for material, workmanship, performance and progressand the Contractor is responsible under the Contract for each Sub-contractor's work and behaviour.

On occasions the Employer will wish to have a particular Subcon-tractor engaged because of his knowledge of that Subcontrac-tor's skills or because of his knowledge of some process, mate-rials or plant particularly required by the Employer. A Sub-contractor selected in this way is known as a nominatedSubcontractor. Once he has been accepted by the main Contrac-tor the latter is responsible for the work of the nominatedSubcontractor to the same extent as applies to the work of all otherSubcontractors. For this reason it is important that nomination isnot misused by the Employer. Failure to perform satisfactorilyby a nominated Subcontractor can cause many difficulties on Site.The particular conditions applying to the appointment of nomi-nated Subcontractors are dealt with in Clause 59 ofthe Conditions.The Contractor may object to the nomination for good and suf-ficient reasons (e.g. lack of experience or financial strength) andengagement against the wishes of the Contractor will probablydisturb harmony on the Site. There would have to be veryexceptional reasons for such a thing to happen.

In very large or complex projects a number of contractors mayform a joint venture to act as the Contractor. In such cases thesame principles apply as in the situation with only one Contractor.In the case of a joint venture the Employer would normally re-quire that all the parties to the joint venture have joint and severalliability.In projects where several contractors are operating on a single siteunder individual contracts, each contractor must give the othercontractors reasonable cooperation and opportunities for carryingout their work and this should be reflected in the terms of thecontracts and in the respective programmes.

©FIDIC 1989 37

Page 38: 35824401 FIDIC Guide to the Use of FIDIC

THE ENGINEER

The Engineer is not a party to the Contract between the Employerand the Contractor but his terms of engagement are set out in anagreement between the Employer (Client) and the Engineer (Con-sultant). This agreement is often in the form recommended byFIDIC which is entitled International General Rules of Agree-ment Between Client and Consultant (IGRA). An updatedversion of this model form of agreement is scheduled for publica-tion in early 1990. The new IGRA will stipulate what authority isdelegated to the Engineer by the Employer and should specificallystate if any of the authority given to the Engineer under the FIDICConditions is subject to restriction.

The duties under the FIDIC Conditions which are allocated to theEngineer include the issue of information and instructions to theContractor as the work proceeds, commenting on the Contrac-tor's proposals for carrying out the work, ensuring that materialsand workmanship are as specified, agreeing measurements ofwork done and checking and issuing to the Employer interimand final payment certificates. In administration of the Con-tract all communications with the Contractor pass through theEngineer, thus avoiding possible confusion and misunderstand-ing although meetings between the Employer, the Contractor andthe Engineer should be held regularly. The Engineer's dutieswill normally include instructions relating to management of theContract and changes in the nature and extent of the work, thecost thereof and the time for completion. For example, the issue ofinstructions to proceed with or to suspend the progress of theWorks is a matter of management. In order to maintain confidencebetween the parties it is important that the Contract properlydiscloses the procedures for the Engineer's action in such mattersand that the Engineer duly observes such procedures.

Many of the functions allocated to the Engineer involve financialmatters. The certificates he issues for interim and finalpayments include all cost elements arising under the terms of theContract other than those (if any) resulting from arbitrationproceedings and the application of the liquidated damages clause.Under normal circumstances the payments certified by the Engi-neer will lie within the Contract Price and will, therefore, havealready been authorised by the Employer, but variations orderedunder Clause 51, fluctuations in the price of labour, materialsand freight under Clause 70, works done or materials and servicessupplied under Clause 58 and the settlement of the Contractor'srequest for additional payment under such Clauses as 12 and 53could each result in an adjustment to the Contract Price.

The FIDIC Conditions are based upon the principle that theEngineer has the authority to determine additional payments. Thisis in the interests of efficient management and avoidance ofduplication of effort. It also ensures that the Tender Price fromefficient contractors will be lower than would be the case if theContractor did not feel sure that when he was required to doadditional work his remuneration for such work would beevaluated by a professional able to judge the value of such work.In the event the Employer wishes to limit the authority of theEngineer this should be clearly stated in Part II so that theContractor is aware in advance of tendering the conditions under

38 ©FIDIC 1989

Page 39: 35824401 FIDIC Guide to the Use of FIDIC

which he is required to work. The degree to which the Employerleaves the Engineer to determine matters affecting the extent andcost of the Works and the time for their completion will depend toa large extent on the in-house capability of the Employer. There-fore, the Engineer should be selected having regard to his profes-sional integrity and his ability to fulfil his obligations under theContract and to administer the Contract fairly and impartiallyin the interests of both parties.In the exercise of his duties the Engineer accepts the responsi-bilities attached to them. These responsibilities should be clearlydefined in the Agreement between the Employer and the Engi-neer and should be made known to the Contractor.

As the Works progress the Engineer will be required by theContract to give instructions, give or refuse approval or con-sent, approve work, authorise payments, issue certificates, etc.It should be understood by both parties to the Contract that ingiving approval or consent and such other acts which are the dutyof the Engineer his objective is to ensure that the Employerreceives the Works at completion in accordance with the require-ments of the Contract and that the Contractor is suitably rewardedfor the work he carries out.

The Engineer's duty is to interpret the Contract as written. Indoing so he should endeavour to determine what the Contractorcould have reasonably foreseen would have been required of himwhen preparing his tender.It is important to realise, however, that neither the Employer northe Contractor is finally bound by the Engineer's interpretation ordetermination even if it is given in the fonn of a decision underClause 67. This Clause defines the steps to be taken where theEngineer's decision thereunder is not acceptable to one or bothparties. For further information see the commentary on Clause 67.

©FIDIC 1989 39

Page 40: 35824401 FIDIC Guide to the Use of FIDIC

COMMENTARY ON THE CONDITIONS

GENERAL COMMENT

The notes that follow comment upon some aspects of individual clauses of the fourthedition of Conditions of Contract for Works of Civil Engineering Construction. Allclauses and example sub-clauses are reproduced but the commentaries should not betaken as representing any definitive interpretation of the text of these clauses. In anygiven contract such interpretation will depend, among other things, on the law govern-ing the contract in question. The notes are, however, intended to give users a practicalguide to the operation of various clauses and to explain their relationship to each other.

The GENERAL CONDITIONS contained in Part I should always be included in thetender documents in their printed form as issued by FIDIC as in this way contractorsknow exactly what is contained in them. Any additions, deletions or variations toPart I should be effected solely by an appropriate entry in Part II, to reduce the risk ofambiguities. When Employers require the General Conditions to be attached to tendersthey should not accept photo-copies as such copies may contain provisions which differfrom those contained in the printed version.

DEFINITIONS AND INTERPRETATIONS

Clause 1 consists of definitions of keywords used throughout the Contract documents.It should be remembered when reading the text that in general any word which beginswith a capital letter represents a defined term which has the meaning given in Clause 1and no other meaning. The only exceptions are the definitions under (g) 'cost', 'day','foreign currency, and 'writing' which begin with letters in the lower case.

Where definitions are self-explanatory no comment is given.

Definitions 1.1 In the Contract (as hereinafter defined) the followingwords and expressions shall have the meanings herebyassigned to them, except where the context otherwiserequires:(a) (i) "Employer" means the person named as such in

Part II of these Conditions and the legal successorsin title to such person, but not (except with theconsent of the Contractor) any assignee of suchperson.(ii) "Contractor" means the person whose tenderhas been accepted by the Employer and the legalsuccessors in title to such person, but not (exceptwith the consent of the Employer) any assignee ofsuch person.

(iii) "Subcontractor" means any person named inthe Contract as a Subcontractor for a part of theWorks or any person to whom a part of the Workshas been subcontracted with the consent of theEngineer and the legal successors in title to suchperson, but not any assignee of any such person.

(iv) "Engineer" means the person appointed by theEmployer to act as Engineer for the purposes of theContract and named as such in Part II of theseConditions.

40 © FIDIC 1989

Page 41: 35824401 FIDIC Guide to the Use of FIDIC

It should be noted that this definition identifies the Engineer as the person named as suchin Part II of the Conditions the effect of which is to prevent the Employer from chang-ing the Engineer without the consent of the Contractor. The reason for this change fromthe third edition is that the identity of the Engineer (and his reputation) has been a factorin the calculation of the Contractor's Tender.

(v) "Engineer's Representative" means a person ap-pointed from time to time by the Engineer underSub-Clause 2.2.

(b) (i) "Contract" means these Conditions (Parts I andII), the Specification, the Drawings, the Bill ofQuantities, the Tender, the Letter of Acceptance, theContract Agreement (if completed) and such furtherdocuments as may be expressly incorporated in theLetter of Acceptance or Contract Agreement (ifcompleted).

(ii) "Specification" means the specification of theWorks included in the Contract and any modifica-tion thereof or addition thereto made under Clause51 or submitted by the Contractor and approved bythe Engineer.

(iii) "Drawings" means all drawings, calculationsand technical information of a like nature providedby the Engineer to the Contractor under the Con-tract and all drawings, calculations, samples, pat-terns, models, operation and maintenance manualsand other technical information of a like naturesubmitted by the Contractor and approved by theEngineer.(iv) "Bill of Quantities" means the priced and com-pleted bill of quantities forming part of the Tender.

(v) "Tender" means the Contractor's priced offer tothe Employer for the execution and completion ofthe Works and the remedying of any defects thereinin accordance with the provisions of the Contract,as accepted by the Letter of Acceptance.

(vi) "Letter of Acceptance" means the formal accep-tance by the Employer of the Tender.

The Letter of Acceptance, together with the Contractor's written acknowledgement (ifadjustments have been made to the Tender), have the effect of constituting a contractbetween the Employer and the Contractor. The Letter of Acceptance should include,either in the text or as appendices thereto, a statement to this effect, a complete list ofthe documents which comprise the Tender as accepted, together with confirmation ofthe adjustments (if any) which have been made to the Tender originally submitted, byagreement between the Employer and the Contractor, in correcting arithmetical errorsand modifying or eliminating reservations. The Letter of Acceptance will ordinarilyrecord the Contract Price, and will refer to the delivery of a performance security andthe execution of a formal Contract Agreement should these be required.

© FIDIC 1989 41

Page 42: 35824401 FIDIC Guide to the Use of FIDIC

The Letter of Acceptance is sometimes preceded by a letter of intent in which theEmployer expresses his intention to accept a tender, subject to defined conditions. Theletter of intent is not ordinarily binding upon the Employer unless it is stated thereinthat the Employer will make payment for specified work undertaken prior to the issueof the Letter of Acceptance. If the Contractor is required to undertake some workprior to the issue of the Letter of Acceptance it is sometimes advantageous to both theEmployer and the Contractor that a separate contract should be entered into in respect ofsuch work rather than that an attempt should be made to incorporate such work into theContract at a later stage. Should the potential Employer decide, after the issue of theletter of intent that he will not, after all, proceed with the Works the Contractor mightwell have difficulty in obtaining reimbursement for any work which he has alreadydone unless there is a specific undertaking by the Employer to pay him.

(vii) "Contract Agreement" means the contractagreement (if any) referred to in Sub-Clause 9.1.

(viii) "Appendix to Tender" means the appendixcomprised in the form of Tender annexed to theseConditions.

(c) (i) "Commencement Date" means the date uponwhich the Contractor receives the notice to com-mence issued by the Engineer pursuant to Clause4].

The Commencement Date and the Time for Completion have been related directly tothe receipt by the Contractor of the notice to commence. This notice should thereforebe sent or delivered against a signature of receipt. The Appendix to Tender makesprovision for stating the time interval after the issue of the Letter of Acceptance withinwhich the Contractor is to receive the notice.

ii) "Time for Completion" means the time for com-pleting the execution of and passing the Tests onCompletion of the Works or any Section or partthereof as stated in the Contract (or as extendedunder Clause 44) calculated from the Commence-ment Date.

(d) (i) "Tests on Completion" means the tests specifiedin the Contract or otherwise agreed by the Engineerand the Contractor which are to be made by theContractor before the Works or any Section or partthereof are taken over by the Employer.

It is specifically stated that the Tests on Completion must be carried out before theexpiry of the Time for Completion and adequate time should be allowed for thecarrying out of the tests.

(ii) "Taking-Over Certificate" means a certificate is-sued pursuant to Clause 48.

(e) (i) "Contract Price" means the sum stated in theLetter of Acceptance as payable to the Contractorfor the execution and completion of the Works andthe remedying of any defects therein in accordancewith the provisions of the Contract.

42 © FIDIC 1989

Page 43: 35824401 FIDIC Guide to the Use of FIDIC

The Contract Price is the sum stated for the provision of the whole of the Works but itis not necessarily the sum the Contractor will receive as throughout the Conditions thereare provisions for additions or deductions e.g., for variations.

(ii) "Retention Money" means the aggregate of allmonies retained by the Employer pursuant to Sub-Clause 60.2(a).

(f) (i) "Works" means the Permanent Works and theTemporary Works or either of them as appropriate.

(ii) "Permanent Works" means the permanent worksto be executed (including Plant) in accordance withthe Contract.

(iii) "Temporary Works" means all temporary worksof every kind (other than Contractor's Equipment)required in or about the execution and completionof the Works and the remedying of any defectstherein.

(iv) "Plant" means machinery, apparatus and thelike intended to form or forming part of the Perma-nent Works.

Plant, as such, is a new definition and is different from Constructional Plant whichappeared in the third edition. Plant, in the fourth edition means plant which is to beincorporated in the Permanent Works. It should be noted that the definition of Plantin the civil works document is different in one respect from the definition of Plant inthe third edition of the Yellow Book Conditions. In the Yellow Book Plant includesmaterials but in the Red Book it does not.

(v) "Contractor's Equipment" means all appliancesand things of whatsoever nature (other than Tem-porary Works) required for the execution and com-pletion of the Works and the remedying of any de-fects therein, but does not include Plant, materialsor other things intended to form or forming part ofthe Permanent Works.

(vi) "Section" means a part of the Works specificallyidentified in the Contract as a Section.

Where the Works are to be divided into Sections there should be a clear identification inPart II or in the Specification in order to operate Clauses 43 and 46 and suitable provi-sion should be included in the Appendix to Tender.

(vii) "Site" means the places provided by the Em-ployer where the Works are to be executed and anyother places as may be specifically designated in theContract as forming part of the Site.

It will probably be necessary to define the Site in detail in the Specification or by meansof a drawing included in the Contract documents.

(g) (i) "cost" means all expenditure properly incurredor to be incurred, whether on or off the Site, includ-ing overhead and other charges properly allocablethereto but does not include any allowance forprofit.

© FIDIC 1989 43

Page 44: 35824401 FIDIC Guide to the Use of FIDIC

Attention is drawn to the fact that 'cost' includes overhead charges which in turn in-clude financial costs but the defined term does not include profit.

(ii)"day" means calendar day.

All periods of time have been expressed in multiples of seven days, a 'day' meaninga calendar day not a working day.

(iii) "foreign currency" means a currency of a coun-try other than that in which the Works are to belocated.

(iv) "writing" means any hand-written, type-written,or printed communication, including telex, cableand facsimile transmission.

Two specific names must be entered in Part II under Clause I. These are:

Definitions 1.1 .(a)(i) The Employer is (insert name)

1.l.(a)(iv) The Engineer is (insert name)

If other identifications are essential e.g., the name of an International Financing Institu-tion (IFI) they should be added to the above entry.

Further definitions can be added in Part II should they be required. For example, ininternational contracts training of personnel has become a frequent requirement. Insuch cases a definition of 'Training' could be introduced with a requirement that de-tails are stated in Part II or in the Specification.

Headingsand 1.2 The headings and marginal notes in these ConditionsMarginal Notes shall not be deemed part thereof or be taken into con-

sideration in the interpretation or construction thereofor of the Contract.

Interpretation 1.3 Words importing persons or parties shall include firmsand corporations and any organisation having legalcapacity.

Singularand 1.4 Words importing the singular only also include thePlural plural and vice versa where the context requires.

Notices, 1.5 Wherever in the Contract provision is made for theConsents, giving or issue of any notice, consent, approval, certifi-

Approvals, cate or determination by any person, unless otherwiseCertificatesand specified such notice, consent, approval, certificate orDeterminations determination shall be in writing and the words "no-

tify", "certify" or "determine" shall be construed ac-cordingly. Any such consent, approval, certificate ordetermination shall not unreasonably be withheld ordelayed.

Two important requirements are contained in this Sub-Clause. The first is that all no-tices, etc., must be in writing. The second is that any consent, approval, certificate ordetermination must not be unreasonably withheld or delayed.

44 © FIDIC 1989

Page 45: 35824401 FIDIC Guide to the Use of FIDIC

ENGINEER AND ENGINEER'S REPRESENTATIVE

Engineer's 2.1 (a) The Engineer shall carry out the duties specified inDuties and the Contract.

Authority . .(b) The Engineer may exercise the authority specified inor necessarily to be implied from the Contract, pro-vided, however, that if the Engineer is required, underthe terms of his appointment by the Employer, to obtainthe specific approval of the Employer before exercisingany such authority, particulars of such requirementsshall be set out in Part II of these Conditions. Providedfurther that any requisite approval shall be deemed tohave been given by the Employer for any such authorityexercised by the Engineer.

(c) Except as expressly stated in the Contract, the Engi-neer shall have no authority to relieve the Contractorof any of his obligations under the Contract.

Reference has been made earlier to the function, duties and responsibilities of theEngineer.In a number of Clauses in the Conditions the Engineer is required to undertake dueconsultation with the Employer and the Contractor before making his determination. Theextent of such consultation will be at the discretion of the Engineer.

The Conditions establish that, with certain specified exceptions, all instructions from theEngineer to the Contractor will be in writing. Where an instruction from the Engineerto the Contractor is not confirmed in writing by the Engineer the Contractor has theright to confirm the instruction in writing to the Engineer, see Sub-Clause 2.5.

Restrictions on the Engineer's authority may derive from the requirements of legislationor regulations, governmental or other. Usually such restrictions will apply to the approvalof variations leading to increases in cost or extensions of time.

Sub-Clause 2.1(b) requires that any specific restrictions on the Engineer's authority shallbe set out in Part II, but nevertheless, if the Contractor carries out work involvingadditional cost on the instructions of the Engineer, the Contractor will be entitled topayment for such work even if the Engineer had not the authority to order such work.

The following is an example of a suitable clause to be added in Part II:

Engineer's 2.1 The Engineer shall obtain the specific approval of theDuties Employer before carrying out his duties in accordance

with the following Clauses of Part I:

(a) Clause (insert applicable number)

(b) Clause (insert applicable number)

(c) Clause (insert applicable number)

The list should be extended or reduced as necessary.

In some cases the obligation to obtain approval of the Employer may apply only to oneSub-Clause out of several in a Clause or approval may only be necessary beyond certainlimits, monetary or otherwise. Where this is so the wording must be varied accordingly.

If the obligation to obtain the approval of the Employer could lead to the Engineer beingunable to take action in an emergency, where matters of safety are involved, considera-tion should be given to adding the following paragraph to the example clause givenabove:

©FIDIC 1989 45

Page 46: 35824401 FIDIC Guide to the Use of FIDIC

Notwithstanding the obligation, as set out above, to ob-tain approval, if, in the opinion of the Engineer, anemergency occurs affecting the safety of life or of theWorks or of adjoining property, he may, without reliev-ing the Contractor of any of his duties and responsibili-ties under the Contract, instruct the Contractor to exe-cute all such work or to do all such things as may, inthe opinion of the Engineer, be necessary to abate orreduce the risk. The Contractor shall forthwith comply,despite the absence of approval of the Employer, withany such instruction of the Engineer. The Engineer shalldetermine an addition to the Contract Price, in respectof such instruction, in accordance with Clause 52 andshall notify the Contractor accordingly, with a copy tothe Employer.

Engineer's 2.2 The Engineer's Representative shall be appointed byRepresentative and be responsible to the Engineer and shall carry out

such duties and exercise such authority as may be dele-gated to him by the Engineer under Sub-Clause 2.3.

Engineer's 2.3 The Engineer may from time to time delegate to theAuthonty to Engineer's Representative any of the duties and authori-

Delegate ties vested in the Engineer and he may at any timerevoke such delegation. Any such delegation or revoca-tion shall be in writing and shall not take effect until acopy thereof has been delivered to the Employer and theContractor.

Any communication given by the Engineer's Represen-tative to the Contractor in accordance with such dele-gation shall have the same effect as though it had beengiven by the Engineer. Provided that:

(a) any failure of the Engineer's Representative to dis-approve any work, materials or Plant shall not preju-dice the authority of the Engineer to disapprove suchwork, materials or Plant and to give instructions for therectification thereof;

(b) fthe Contractor questions any communication of theEngineer's Representative he may refer the matter to theEngineer who shall confirm, reverse or vary the contentsof such communication.

Sub-Clauses 2.2 and 2.3 deal with the appointment and duties of the Engineer's Repre-sentative, frequently referred to as the Resident Engineer. In the third edition certainspecific duties were allocated to the Engineer's Representative. This has been changedin the fourth edition. The Engineer's Representative is appointed by the Engineer andthe Engineer is responsible for his actions. However, the identity of the person appointedmust be made known to the Employer and the Contractor before such appointment canbecome effective. Such duties and authority as the Engineer may wish to vest in theEngineer's Representative must be delegated in writing and care should be taken toensure that the written delegation is specific.

46 © FIDIC 1989

Page 47: 35824401 FIDIC Guide to the Use of FIDIC

The Engineer must determine what authority should be delegated in order to enable thework at the Site to proceed continuously and smoothly. The delegation must includeprovision for the Engineer's Representative to take action in an emergency such asurgent remedial work which is referred to in Clause 64.

The scope of delegation will vary depending on the size and nature of the project, itslocation in relation to the headquarters of the Employer and the Engineer and the capac-ity of the person appointed.For ease of reference clauses are listed below where the Engineer is mentioned:

4, 5, 6, 7, 12, 13, 14, 15, 16, 17, 18, 19, 20, 27, 30, 31, 33, 34(Part II), 35, 36, 37,38, 39, 40, 41, 42, 44, 45, 46, 48, 49, 50, 51, 52, 53, 54, 56, 57, 58, 59, 60, 62, 63, 64,65, 67, 68, 69, 70 and 73 onwards.

Delegation should not normally be considered in respect of clauses 41, 44, 48, 62,63, 65, 67 and 69.

In order not to cause unnecessary interruption of work at Site, delegation of authority(in whole or in part) is common in respect of the following clauses:

4, 5, 7, 12, 14, 16, 17, 18, 19, 20, 27, 30, 31, 33, 34, 35, 36, 37, 38, 39, 40, 42, 45, 49,50, 53, 54, 56, 59, 60 (except 60.6 and 60.8), 64 and 70.

Appointment 2.4 The Engineer or the Engineer's Representative mayofAssistants appoint any number of persons to assist the Engineer's

Representative in the carrying out of his duties underSub-Clause 2.2. He shall notify to the Contractor thenames, duties and scope of authority of such persons.Such assistants shall have no authority to issue anyinstructions to the Contractor save in so far as suchinstructions may be necessary to enable them to carryout their duties and to secure their acceptance of mate-rials, Plant or workmanship as being in accordance withthe Contract, and any instructions given by any of themfor those purposes shall be deemed to have been givenby the Engineer's Representative.

Sub-Clause 2.4 authorises the appointment of Assistants by the Engineer, or theEngineer's Representative. Such Assistants have limited duties. On a major project therewill be a number of Assistants on Site. A further example of where assistants are usedis in circumstances where pre-fabricated construction elements or Plant are being manu-factured in a Subcontractor's premises which are not situated in the country of theEngineer or the country in which the Site is situated.

Instructions 25 Instructions given by the Engineer shall be in writing,in Writing provided that if for any reason the Engineer considers

it necessary to give any such instruction orally, the Con-tractor shall comply with such instruction. Confirmationin writing of such oral instruction given by the Engineer,whether before or after the carrying out of the instruc-tion, shall be deemed to be an instruction within themeaning of this Sub-Clause. Provided further that ftheContractor, within 7 days, confirms in writing to theEngineer any oral instruction of the Engineer and suchconfirmation is not contradicted in writing within 7 daysby the Engineer, it shall be deemed to be an instructionof the Engineer.

© FIDIC 1989 47

Page 48: 35824401 FIDIC Guide to the Use of FIDIC

The provisions of this Sub-Clause shall equally apply toinstructions given by the Engineer's Representative andany assistants of the Engineer or the Engineer's Repre-sentative appointed pursuant to Sub-Clause 2.4.

Sub-Clause 2.5 contains the necessary obligation for the Engineer to give his instruc-tions in writing or, if the Engineer considers it necessary that instructions are given orally,that they are confirmed in writing as soon as possible thereafter. The importance ofkeeping records of all matters related to the work on Site cannot be over-emphasisedand it will be seen in later clauses that the maintenance of adequate contemporary rec-ords may be fundamental to payment of claims for additional work. It should be notedalso that where the Engineer does not give written confirmation of an instruction to theContractor then the Contractor may himself confirm to the Engineer that he has receivedsuch an instruction. If the Engineer fails, in writing, to contradict such a notice within 7days the instruction is deemed to have been given by the Engineer to the Contractor.

Engineer to Act 2.6 Wherever, under the Contract, the Engineer is requiredImpartially to exercise his discretion by:

(a) giving his decision, opinion or consent, or

(b) expressing his satisfaction or approval, or

(c) determining value, or

(d) otherwise taking action which may affect the rightsand obligations of the Employer or the Contractor

he shall exercise such discretion impartially within theterms of the Contract and having regard to all the cir-cumstances. Any such decision, opinion, consent, ex-pression of satisfaction, or approval, determination ofvalue or action may be opened up, reviewed or revisedas provided in Clause 67.

Sub-Clause 2.6 is a new introduction. It stipulates in the Contract what was treatedin previous conditions as a professional obligation of the Engineer. The Sub-Clauseprovides that whenever the Contract requires the Engineer to give decisions, opinionsor consents, to express satisfaction or approval, to determine value or to take anyother action requiring the Engineer to exercise his discretion, he shall do so in animpartial manner. Behaving impartially implies being prepared to listen to and considerthe views of both the Employer and the Contractor and then to make a determinationbased upon the facts.

The Engineer's determinations can be challenged by either party in accordance with theprocedure for dealing with disputes laid down in Clause 67. However, in order to avoiddelay or interruption to the Works, the Engineer's determinations must be adhered toby both the Employer and Contractor until and unless they are varied by the Engineerhimself, by amicable settlement or an arbitral tribunal, as provided for in Clause 67.

Although the Contractor may disagree with an instruction given by the Engineer theContractor is obliged, under Sub-Clause 13.1 to carry out the instructions. He wouldbe wise to record in writing his disagreement with the instruction and his reasons there-for.

48 © FIDIC 1989

Page 49: 35824401 FIDIC Guide to the Use of FIDIC

ASSIGNMENT AND SUBCONTRACTING

Assignment 3.1 The Contractor shall not, without the prior consent ofofContract the Employer (which consent, notwithstanding the pro-

visions of Sub-Clause 1.5, shall be at the sole discretionof the Employer), assign the Contract or any partthereof, or any benefit or interest therein or thereunder,otherwise than by:

(a) a charge in favour of the Contractor's bankers ofany monies due or to become due under the Contract,or

(b) assignment to the Contractor's insurers (in caseswhere the insurers have discharged the Contractor'sloss or liability) of the Contractor's rights to obtainrelief against any other party liable.

Usually the Contractor will have been selected by the Employer following pre-qualifi-cation, tendering and tender evaluation. The award of the Contract therefore impliesconfidence of the Employer in the Contractor. Obviously it is not envisaged by theEmployer that the Contractor he has selected would assign the Contract to a third party.This would be inconsistent with the objectives of the whole selection procedure. TheConditions, for this reason, provide that the Contract may not be assigned in whole or inpart without the express consent of the Employer. However, in recognition of the justi-fied need of the Contractor for financing and insurance (particularly export credit insur-ance) this Clause makes express exceptions for such purposes.

Subcontracting 4.1 The Contractor shall not subcontract the whole of theWorks. Except where otherwise provided by the Con-tract, the Contractor shall not subcontract any part ofthe Works without the prior consent of the Engineer.Any such consent shall not relieve the Contractor fromany liability or obligation under the Contract and heshall be responsible for the acts, defaults and neglectsof any Subcontractor, his agents, servants or workmenas fully as if they were the acts, defaults or neglects ofthe Contractor, his agents, servants or workmen.

Provided that the Contractor shall not be required toobtain such consent for:

(a) the provision of labour, or

(b) the purchase of materials which are in accordancewith the standards specified in the Contract, or

(c) the subcontracting of any part of the Works forwhich the Subcontractor is named in the Contract.

© FIDIC 1989 49

Page 50: 35824401 FIDIC Guide to the Use of FIDIC

Subcontracting of certain specialised parts of the work undertaken by the Contractor isnot an unusual occurrence in the execution of a contract. This may at first sight appearto be in conflict with the comment on Sub-Clause 3.1 but this is not really the case.Although as stated in relation to Sub-Clause 3.1 the Employer wishes to have the Con-tract carried out by the Contractor he has selected, it is generally recognised that otherpersons or firms, by reason of their greater specialisation, experience or capacity, maybe able to carry out specific works or services or furnish certain supplies, more effi-ciently than the Contractor. Accordingly, with the Employer's consent, which under theConditions should not be unreasonably withheld, the Contractor may subcontract works,services or supplies to others. The responsibility of the Contractor to the Employer forthe entire Contract remains and the Contractor retains responsibility for the work orservices which he subcontracts. It is the duty of the Contractor to justify the need, forsuch specialisation. It is sometimes the practice that the Engineer, with the agreement ofthe Contractor, deals directly with the Subcontractor on technical matters. In such caseit is essential that the Contractor is kept informed at all stages, particularly if matters ofpayment or programme are involved, so that the Contractor is immediately aware ofdiscussions or correspondence that have taken place between the Engineer and theSubcontractor and can comment or take such other action as he may consider appropri-ate.

Normally the tenderer will state in his tender what work or services he proposes tosubcontract and as far as possible the name of the subcontractors he proposes touse. There are occasions when the Employer will express the wish that certain tasks,operations or supplies of Plant or material be subcontracted to a particular spe-cialist nominated by him.

In the event of a Subcontractor having undertaken to-Assignmentof 4.2 wards the Contractor in respect of the work executed,

Subcontractors' or the goods, materials, Plant or services supplied byObligations such Subcontractor, any continuing obligation extend-

ing for a period exceeding that of the Defects LiabilityPeriod under the Contract, the Contractor shall at anytime, after the expiration of such Period, assign to theEmployer, at the Employer's request and cost, the bene-fit of such obligation for the unexpired duration thereof

Obviously, if at the expiry of the period during which the Contractor has a responsibilityto the Employer, that is at the end of the Defects Liability Period, there is still someunexpired guarantee or other obligation from a Subcontractor to the Contractor the lattermust assign this right to the Employer. The Contractor must ensure that the Subcontrac-tor will agree to such assignment.

50 ©FJDIC 1989

Page 51: 35824401 FIDIC Guide to the Use of FIDIC

CONTRACT DOCUMENTS

Language/s 5.1 There is stated in Part II of these Conditions:andLaw

(a) the language or languages in which the Contractdocuments shall be drawn up, and

(b) the country or state the law of which shall apply tothe Contract and according to which the Contract shallbe construed.

If the said documents are written in more than onelanguage, the language according to which the Contractshall be construed and interpreted is also stated in PartII of these Conditions, being therein designated the"Ruling Language".

It is important to establish the ruling language of the Contract and also the law to whichthe Contract is subject. The FIDIC Conditions have been drafted in the English lan-guage and great care is taken to ensure that FIDIC translations of these standard condi-tions convey the same meaning. If Part II of the Conditions is prepared in one languageand is then translated into another there is the possibility that ambiguities and discrepan-cies may occur. It is one of the Engineer's functions to deal with any ambiguities anddiscrepancies as may become apparent but in doing so he should carefully avoid dictat-ing to the Contractor how the work involved is to be carried out. The method of car-rying out the Works is the responsibility of the Contractor.

Sub-Clause 5.1 requires that the language/s and law should be stated in Part II. Thefollowing is an example of an appropriate Part II entry:

Language/s 5.1 (a) The language is (insert as applicable)and Law

(b) The law is that in force in (insert name of country)

If necessary (a) should be varied to read:

(a) The languages are (insert as applicable)

The Ruling Language is (insert as applicable)

Priority of 5.2 The several documents forming the Contract are to beContract taken as mutually explanatory of one another, but in

Documents case of ambiguities or discrepancies the same shall beexplained and adjusted by the Engineer who shall there-upon issue to the Contractor instructions thereon and insuch event, unless otherwise provided in the Contract,the priority of the documents forming the Contract shallbe as follows:

(1) The Contract Agreement (if completed);

(2) The Letter of Acceptance;

(3) The Tender;

©FIDIC 1989 51

Page 52: 35824401 FIDIC Guide to the Use of FIDIC

(4) Part II of these Conditions;

(5) Part I of these Conditions; and

(6) Any other document forming part of the Contract.

In the fourth edition the order of priority of the documents forming the Contract isspecified in more detail than in previous editions. However, this order of precedence setout in Part I is a proposal and other orders of preference might be preferred by theEmployer. Either of the two example clauses which follow can be an appropriate entryfor Part II of the Conditions:

Priority of 5.2 Delete the documents listed 1-6 and substitute:Contract

Documents (1) the Contract Agreement (if completed);(2) the Letter of Acceptance;

(3) the Tender;(4) the Conditions of Contract Part II;

(5) the Conditions of Contract Part I;

(6) the Specification;

(7) the Drawings; and

(8) the priced Bill of Quantities

or

where it is decided that no order of precedence of documents should be included, thisSub-Clause may be varied as follows:

Priority of 5.2 Delete the text of the Sub-Clause and substitute:Contract

Documents The several documents forming the Contract are to betaken as mutually explanatory of one another, but in thecase of ambiguities or discrepancies the priority shall bethat accorded by law. If, in the opinion of the Engineer,such ambiguities or discrepancies make it necessary toissue any instruction to the Contractor in explanation oradjustment, the Engineer shall have authority to issuesuch instruction.

Custodyand 6.1 The Drawings shall remain in the sole custody of theSupply of Engineer, but two copies thereof shall be provided to the

Drawings and Contractor free of charge. The Contractor shall makeDocuments at his own cost any further copies required by him.

Unless it is strictly necessary for the purposes of theContract, the Drawings, Specification and other docu-ments provided by the Employer or the Engineer shallnot, without the consent of the Engineer, be used orcommunicated to a third party by the Contractor. Uponissue of the Defects Liability Certificate, the Contractorshall return to the Engineer all Drawings, Specificationsand other documents provided under the Contract.

52 ©FIDIC 1989

Page 53: 35824401 FIDIC Guide to the Use of FIDIC

The Contractor shall supply to the Engineer four copiesof all Drawings, Specification and other documents sub-mitted by the Contractor and approved by the Engineerin accordance with Clause 7, together with a reproduc-ible copy of any material which cannot be reproducedto an equal standard by photocopying. In addition theContractor shall supply such further copies of suchDrawings, Specification and other documents as theEngineer may request in writing for the use of theEmployer, who shall pay the cost thereof

This Sub-Clause concerns the issue to the Contractor of Drawings and instructionsrequired to enable him to carry out the Works. The Contractor will normally haveprovided an outline programme with his tender followed by a more detailed programmein accordance with Clause 14. With this information available to him the Engineer canorganise the issue of Drawings and other information to meet the Contractor's require-ments.

On some occasions the Engineer may not himself have the responsibility for preparingsuch Drawings or information but will be the channel through which such Drawings orinformation are passed to the Contractor. It is customary for all Drawings and informa-tion to be supplied in reproducible form.

This Sub-Clause also envisages that some Drawings, Specification or other documentsmay be provided by the Contractor. For example, prefabricated elements to be manu-factured according to proprietary methods of the Contractor or where it is provided inthe Contract that design of a part of the Permanent Works is the responsibility of theContractor.

One Copy of 6.2 One copy of the Drawings, provided to or supplied byDrawings to be the Contractor as aforesaid, shall be kept by the Con-

Kept on Site tractor on the Site and the same shall at all reasonabletimes be available for inspection and use by the Engi-neer and by any other person authorised by the Engi-neer in writing.

It is obviously necessary to have a copy of the Drawings on Site and available duringworking hours to both the Contractor and the Engineer or the Engineer's Representa-tive.

Disruption of 6.3 The Contractor shall give notice to the Engineer, with aProgress copy to the Employer, whenever planning or execution

of the Works is likely to be delayed or disrupted unlessany further drawing or instruction is issued by theEngineer within a reasonable time. The notice shallinclude details of the drawing or instruction requiredand of why and by when it is required and of any delayor disruption likely to be suffered if it is late.

If the progress of the Contractor's work is likely to be hampered because of late issue ofDrawings or instructions by the Engineer it is important that the Engineer should beinformed by the Contractor that late issue will have certain cost and time effects.

©FIDIC 1989 53

Page 54: 35824401 FIDIC Guide to the Use of FIDIC

If, by reason of any failure or inability of the Engineerto issue, within a time reasonable in all the circum-stances, any drawing or instruction for which notice hasbeen given by the Contractor in accordance with Sub-Clause 6.3, the Contractor suffers delay and/or incurscosts then the Engineer shall, after due consultation withthe Employer and the Contractor, determine:

(a) any extension of time to which the Contractor isentitled under Clause 44, and

(b) the amount of such costs, which shall be added tothe Contract Price, and shall notify the Contractor ac-cordingly, with a copy to the Employer.

This Sub-Clause safeguards the Contractor if he is delayed or involved in extra costs asa result of late issue to him of Drawings or instructions in respect of which notice hasbeen given by the Contractor to the Engineer in accordance with Sub-Clause 6.3.

6.5 Iffailure or inability of the Engineer to issue any draw-ings or instructions is caused in whole or in part by thefailure of the Contractor to submit Drawings, Specifi-cation or other documents which he is required to sub-mit under the Contract, the Engineer shall take suchfailure by the Contractor into account when making hisdetermination pursuant to Sub-Clause 6.4.

If the Contractor contributes to the delay referred to in Sub-Clause 6.4 the degree towhich he is responsible will be taken into account when additional cost or time iscalculated.

Supplementary 71 The Engineer shall have authority to issue to the Con-Drawingsand tractor,from time to time, such supplementary Drawings

Instructions and instructions as shall be necessary for the purposeof the proper and adequate execution and completion ofthe Works and the remedying of any defects therein. TheContractor shall carry out and be bound by the same.

This Sub-Clause authorises the Engineer to issue such additional Drawings and instruc-tions as are necessary for the Contractor to execute the Works and remedy any defectsobserved before the end of the Defects Liability Period. It should be noted thatunder this Sub-Clause the Contractor is required to carry out all such instructionsissued by the Engineer.

Permanent Works 7.2 Where the Contract expressly provides that part of theDesignedby Permanent Works shall be designed by the Contractor,

Contractor he shall submit to the Engineer, for approval:

(a) such drawings, specifications, calculations and otherinformation as shall be necessary to satisfy the Engineeras to the suitability and adequacy of that design, and

54 © FIDIC 1989

Delays and 6.4Cost of Delay

of Drawings

Failure byContractor to

Submit Drawings

Page 55: 35824401 FIDIC Guide to the Use of FIDIC

(b) operation and maintenance manuals together withdrawings of the Permanent Works as completed, in suf-ficient detail to enable the Employer to operate, main-tain, dismantle, reassemble and adjust the PermanentWorks incorporating that design. The Works shall notbe considered to be completed for the purposes of tak-ing over in accordance with Clause 48 until such opera-tion and maintenance manuals, together with drawingson completion, have been submitted to and approved bythe Engineer.

This Sub-Clause lays down the procedure for submission by the Contractor to theEngineer of drawings, etc., for such design of Permanent Works as is specified in theContract as the responsibility of the Contractor. The Sub-Clause refers to submissionto the Engineer for approval. It should be noted that approval by the Engineer of suchdocuments does not absolve the Contractor from responsibility for their contents. Theapproval given by the Engineer signifies that in general what is proposed appears toconform to the requirements of the Contract.

It is important to note that under Sub-Clause 7.2(b) the Works are not to be consideredas completed until maintenance manuals and other documents specified in theContract have been submitted to and approved by the Engineer. Delay by theContractor in submitting maintenance manuals will delay the issue of the Taking-Over Certificate.

Where part of the Works is designed by the Contractor based upon proprietary informa-tion it may be necessary for agreements concerning confidentiality, secrecy or thelicensing of such proprietary information or related rights to be concluded between theContractor, the Employer and the Engineer.

Responsibility 7.3 Approval by the Engineer, in accordance with Sub-Unaffectedby Clause 7.2, shall not relieve the Contractor of any of his

Approval responsibilities under the Contract.

This Sub-Clause emphasises the extent of the approval by the Engineer of Contractor'sDrawings refened to in Sub-Clause 7.2.

©FIDIC 1989 55

Page 56: 35824401 FIDIC Guide to the Use of FIDIC

GENERAL OBLIGATIONS

Contractor's 8.1 The Contractor shall, with due care and diligence,Genera! design (to the extent provided for by the Contract),

Responsibilities execute and complete the Works and remedy any defectstherein in accordance with the provisions of the Con-tract. The Contractor shall provide all superintendence,labour, materials, Plant, Contractor's Equipment andall other things, whether of a temporary or permanentnature, required in and for such design, execution,completion and remedying of any defects, so far as thenecessity for providing the same is specified in or isreasonably to be inferred from the Contract.

This Sub-Clause states the Contractor's overall responsibility for the execution of theWorks and for the remedying of any defects observed before the expiry of the DefectsLiability Period.

SiteOperations 8.2 The Contractor shall take full responsibility for the ade-andMethods of quacy, stability and safety of all Site operations and

Construction methods of construction. Provided that the Contractorshall not be responsible (except as stated hereunder oras may be otherwise agreed) for the design or specifi-cation of Permanent Works, or for the design or speci-fication of any Temporary Works not prepared by theContractor. Where the Contract expressly provides thatpart of the Permanent Works shall be designed by theContractor, he shall be fully responsible for that part ofsuch Works, notwithstanding any approval by the Engi-neer.

The Contractor is responsible for the safety of all Site operations and methods ofconstruction. Responsibility for design and specification of the Permanent Worksgenerally rests with the Engineer, but there may be exceptions such as the detaileddesign of specialised items of Plant or prefabricated elements (as referred to inthe comment on Sub-Clause 6.1) designed and manufactured by the Contractor or by anominated Sub-contractor (refer to the definition in Sub-Clause 59.1).

Temporary Works are normally designed and specified by the Contractor. Where this isthe case the Engineer may, depending upon the nature or importance of the TemporaryWorks, require information about their design. Where parts of the Permanent Worksare to be used during construction as Temporary Works the design may riot necessarilybe carried out by the Contractor. In these circumstances the Contractor shall not beresponsible for this design. Where such exceptions occur, these should be defined ei-ther in Part II of the Conditions of Contract or in the Specification.

This Clause should be read in conjunction with Clauses 20-25 dealing with allocationof responsibilities and insurance.

Contract 9.1 The Contractor shall, if called upon so to do, enter intoAgreement and execute the Contract Agreement, to be prepared and

completed at the cost of the Employer, in the formannexed to these Conditions with such modification asmay be necessary.

56 ©FIDIC 1989

Page 57: 35824401 FIDIC Guide to the Use of FIDIC

Under the laws of many countries the offer (the Tender) submitted by the Contractorand its acceptance (Letter of Acceptance) by the Employer are sufficient to constitute alegal contract. However, in some countries and particularly in less developed coun-tries, a Contract Agreement between the Employer and the Contractor is required. Theform of the Agreement must be annexed to Part I of the Conditions when the Tenderdocuments are issued.

The legal aspects in connection with a Contract Agreement should be borne in mind (e.g.the need of counter-signature or ratification, liability in law, period of limitation for actionin law).

In large international contracts, the Contractor will sometimes be a joint venture.In such event a Clause would ordinarily be added in Part II subsequent to Clause 72 (seeexample text 'Joint and Several Liability' on page 173).

Performance 10.1 If the Contract requires the Contractor to obtain secu-Security rityfor his proper performance of the Contract, he shall

obtain and provide to the Employer such security within28 days after the receipt of the Letter of Acceptance, inthe sum stated in the Appendix to Tender. When provid-ing such security to the Employer, the Contractor shallnotify the Engineer of so doing. Such security shall bein the form annexed to these Conditions or in such otheras may be agreed between the Employer and the Con-tractor. The institution providing such security shall besubject to the approval of the Employer. The cost ofcomplying with the requirements of this Clause shall beborne by the Contractor, unless the Contract otherwiseprovides.

In addition to Retention Money and the requirement that the Contractor's Equipment iskept on Site (Sub-Clause 54.1), the majority of international contracts require theContractor to provide a financial security entitling the Employer to some form of mone-tary compensation in the event that the Contractor fails to execute the Contract satisfac-torily.

Such security may take various forms depending among other things upon the require-ments of the Employer and the types of security available.

If such security is to be provided, the form must be annexed to the Conditions. Twoexample forms of performance security are given on pages 7, 8 and 9 of the secondvolume of the Red Book comprising Part II. The Clause and the wording of the ex-ample forms may have to be varied to comply with applicable law and practice.

The amount of the security is customarily expressed as a percentage of the Contract Pricebut the percentage may vary from project to project Performance guarantees for inter-national contracts are usually ten percent of the Contract Price whereas surety bondswhich guarantee completion of the Contract are usually set at a much higher percent-age. It should be noted that the Employer holding a surety bond cannot call upon thesurety for payment of a sum of money - he calls for completion of the Contract.

Where there is provision in the Contract for payments to the Contractor to be made inforeign currency, Sub-Clause 10.1 may need to be varied. As an example,the followingaddition could be made in Part II to Sub-Clause 10.1:

©FIDIC 1989 57

Page 58: 35824401 FIDIC Guide to the Use of FIDIC

Performance 10.1 Add the following after the first sentence:Security The security shall be denominated in the types and pro-

portions of currencies stated in the Appendix to Tender.

Periodof 10.2 The performance security shall be valid until the Con-Validityof tractor has executed and completed the Works and

Performance remedied any defects therein in accordance with theSecurity Contract. No claim shall be made against such security

after the issue of the Defects Liability Certificate inaccordance with Sub-Clause 62.1 and such securityshall be returned to the Contractor within 14 days of theissue of the said Defects Liability Certificate.

In contrast to previous editions, the Sub-Clause contains stipulations covering the periodof validity of the security, the time limit for making claims and the time limit for thereturn of the security to the Contractor.

Claims under 10.3 Prior to making a claim under the performance securityPerformance the Employer shall, in every case, notify the Contractor

Security stating the nature of the default in respect of which theclaim is to be made.

A further difference from previous editions is that the Employer, prior to making a claim,is required to notify the Contractor stating the nature of the breach (default) in respect ofwhich the claim is to be made. During the drafting, the possibility of including a periodof notice was examined but it was considered that such a provision might impede theuse of the Conditions. Normal practice is that when the Contractor is notified of anydefault, he is given an opportunity to remedy it prior to a claim under the security beingmade.

Where restrictions on the source of the security are imposed this should be dealt withby adding an additional Sub-Clause to Clause 10 in Part II. Examples are:

Source of 10.4 The performance security, submitted by the ContractorPerformance in accordance with Sub-Clause 10.1, shall be furnished

Security by an institution registered in (insert the country wherethe Works are to be executed) or licensed to do businessin such country.

or

Source of 10.4 Where the security is in the form of a bank guarantee, itPerformance shall be issued by:

Security(a) a bank located in the country of the Employer, or

(b) a foreign bank through a correspondent bank locatedin the country of the Employer.

FIDIC does not advocate the use of on-demand guarantees. As such guarantees canbe called without justification, their use is likely to increase the tender sum to reflectthis risk.

58 ©FIDIC 1989

Page 59: 35824401 FIDIC Guide to the Use of FIDIC

Inspection 11.1 The Employer shall have made available to the Contrac-ofSite tor, before the submission by the Contractor of the Ten-

der, such data on hydrological and sub-surface condi-tions as have been obtained by or on behalf of theEmployer from investigations undertaken relevant to theWorks but the Contractor shall be responsible for hisown interpretation thereof

The Contractor shall be deemed to have inspected andexamined the Site and its surroundings and informationavailable in connection therewith and to have satisfiedhimself (so far as is practicable, having regard to con-siderations of cost and time) before submitting hisTender, as to:

(a) the form and nature thereof, including sub-surfaceconditions,

(b) the hydrological and climatic conditions,

(c) the extent and nature of work and materials neces-sary for the execution and completion of the Works andthe remedying of any defects therein, and

(d) the means of access to the Site and the accommoda-tion he may require

and, in general, shall be deemed to have obtained allnecessary information, subject as above mentioned, asto risks, contingencies and all other circumstanceswhich may influence or affect his Tender.

The Contractor shall be deemed to have based hisTender on the data made available by the Employer andon his own inspection and examination, all as aforemen-tioned.

During the preliminary stages of a project the Employer and his Engineer will havecollected data upon which to base designs, cost estimates, contract documents anddrawings. It is in the interests of the Employer to have the design of the PermanentWorks properly developed and for this reason he would be well advised to have carriedout as thorough an investigation of the Site as is practicable. In that way he will deter-mine the extent of the investigation he considers necessary and will pay only for theone investigation. If tenderers were regularly obliged to undertake expensive inves-tigations, they would have to include in their tender price the investigation costsfor unsuccessful tenders which would result in generally higher tender prices to Employ-ers.

Moreover, tenderers are usually given a limited period in which to prepare tenders andit is impracticable, and in many cases impossible, for them to carry out a full siteinvestigation programme, particularly sub-surface exploration involving drilling andsub-seabed investigations for dredging, in the time available.

©FIDIC 1989 59

Page 60: 35824401 FIDIC Guide to the Use of FIDIC

For these reasons this Clause provides that the Employer shall make available all data athis disposal when issuing invitations to tender. Some of the information made availableby the Employer may be too bulky to distribute or it may be available at a central point(e.g., borehole cores) or it may only be available on film or tape or in reference volumessuch as hydrological and meteorological records. In such cases the Contract must includean additional Sub-Clause in Part II indicating where the information can be inspected.The following is an example of such a Sub-Clause:

Access 11.2 Data made available by the Employer in accordanceto Data with Sub-Clause 11.1 shall be deemed to include data

listed elsewhere in the Contract as open for inspectionat (insert particulars of the office or offices where suchdata is stored).

However, the Clause presupposes specifically that the Contractor should visit the Siteand collect such further information as may be required for the preparation of his tender.The Contractor will be expected to have checked upon the availability of the materialsand the labour he needs to execute the Works. He will also be expected to take samplesof materials from borrow areas or make test pits, as he may determine to be necessary.Further, he must check among other things the conditions for transportation to the Site.

Where the Contract comprises dredging and reclamation work it may be appro-priate to vary Sub-Clause 11.1 by an entry in Part II as follows:

Inspection 11.1 In the first paragraph, delete the words 'hydrological andof Site sub-surface' and substitute 'hydrographic and sub-sea-

bed'.

In the second paragraph, under (a) delete the word 'sub-surface' and substitute 'sub-seabed' and under (b) deletethe word 'hydrological' and substitute 'hydrographic".

Sufficiency 12.1 The Contractor shall be deemed to have satisfied him-of Tender self as to the correctness and sufficiency of the Tender

and of the rates and prices stated in the Bill of Quanti-ties, all of which shall, except insofar as it is otherwiseprovided in the Contract, cover all his obligations underthe Contract (including those in respect of the supply ofgoods, materials, Plant or services or of contingenciesfor which there is a Provisional Sum) and all mattersand things necessary for the proper execution andcompletion of the Works and the remedying of any de-fects therein.

Both Sub-Clauses within Clause 12 have links with Clause 11. Sub-Clause 12.1emphasises that the tenderer is deemed to have made a thorough investigation ofthe Site and its surroundings as far as was practicable within the time allowed for thepreparation of his tender.

60 ©FIDIC 1989

Page 61: 35824401 FIDIC Guide to the Use of FIDIC

Adverse 12.2 If, however, during the execution of the Works the Con-Physical tractor encounters physical obstructions or physical

Obstructions conditions, other than climatic conditions on the Site,orConditions which obstructions or conditions were, in his opinion,

not foreseeable by an experienced contractor, the Con-tractor shall forthwith give notice thereof to the Engi-neer, with a copy to the Employer. On receipt of suchnotice, the Engineer shall, if in his opinion such obstruc-tions or conditions could not have been reasonablyforeseen by an experienced contractor, after due consul-tation with the Employer and the Contractor, determine:

(a) any extension of time to which the Contractor isentitled under Clause 44, and

(b) the amount of costs which may have been incurredby the Contractor by reason of such obstructions or con-ditions having been encountered, which shall be addedto the Contract Price,

and shall notify the Contractor accordingly, with a copyto the Employer. Such determination shall take accountof any instruction which the Engineer may issue to theContractor in connection therewith, and any proper andreasonable measures acceptable to the Engineer whichthe Contractor may take in the absence of specific in-structions from the Engineer.

In spite of the pre-tender investigations of the Site by the parties, the Contractor mayencounter unforeseen physical obstructions or physical conditions. Sub-Clause 12.2lays down the procedure to be applied to such situations. The Contractor is required togive the earliest possible notice to the Engineer.

If the Engineer is of the opinion that such obstructions or conditions could not reasona-bly have been foreseen, he may after consultation with the Employer and Con-tractor determine an extension of time to be allowed to the Contractor and any additionalcosts to be added to the Contract Price.

Where the Contract comprises dredging and some types of reclamation work thisSub-Clause may require to be varied in Part II in the following manner:

Adverse 12.2 Delete the words 'other than the climatic conditions onPhysical the Site'.

Obstructionsor Conditions

Work to be in 13.1 Unless it is legally or physically impossible, the Con-Accordance tractor shall execute and complete the Works and rem-

with Contract edy any defects therein in strict accordance with theContract to the satisfaction of the Engineer. The Con-tractor shall comply with and adhere strictly to theEngineer's instructions on any matter, whether men-tioned in the Contract or not, touching or concerningthe Works. The Contractor shall take instructions onlyfrom the Engineer or, subject to the provisions of Clause2, from the Engineer's Representative.

©FIDIC 1989 61

Page 62: 35824401 FIDIC Guide to the Use of FIDIC

This Sub-Clause should be read in conjunction with Clause 8 which stipulates that it isthe Contractor's duty to execute the Works in accordance with the Contract and that hehas the full responsibility for all Site operations and methods of construction. However,when a problem arises, prompt action may be required. This Sub-Clause is central tothe management of the Contract in that it gives the Engineer authority to determinewhether, for example, certain work has the quality and dimensions prescribed by theContract, whether a programme is sufficient to ensure timely completion or whethera payment is due. In turn this authority of the Engineer must be exercised in accor-dance with Sub-Clause 2.6.

Sub-Clause 13.1 obliges the Contractor to comply with and adhere strictly to the Engi-neer's instructions and, by signing the Contract, the parties agree to abide by theEngineer's interpretation of the Contract unless and until varied under the provisions ofClause 67.

The authority of the Engineer to issue instructions is very wide. He may instruct theContractor to do any work under the Contract which he considers necessary for theWorks, but he should consider carefully whether additional money and/or time is justi-fied within the terms of the Contract.

Programme to 14.1 The Contractor shall, within the time stated in Part IIbe Submitted ofthese Conditions after the date of the Letter of Accep-

tance, submit to the Engineer for his consent a pro-gramme, in such form and detail as the Engineer shallreasonably prescribe, for the execution of the Works.The Contractor shall, whenever required by the Engi-neer, also provide in writing for his information a gen-eral description of the arrangements and methods whichthe Contractor proposes to adopt for the execution of theWorks.

Tenderers will normally have been required to submit with their tenders a preliminaryprogramme for the execution of the Works with a list of the major items of Contractor'sEquipment, a forecast of labour and staff and of the incidence of expenditure invarious currencies (if applicable) during the Contract period.

This information is essential for evaluation of the tenders and particularly for establish-ing that tenderers have correctly appreciated the activities required to ensure compli-ance with the Time for Completion. It is also required in order to ascertain howthe phasing of operations affects any other contracts and any activities of the Employerof which tenderers may not be aware. However, this information is usually not incorpo-rated into the Contract on award.

Once the Contract has been awarded an accurate and up to date programme assistsall involved in the ordering and allocation of resources and so contributes to thesuccessful conclusion of the Contract.

The earlier the programme is produced, the better will be the flow of information,but in stating in Part lithe time within which it is to be provided, the Engineer shouldhave regard to the detailed work which the Contractor has to do after the Contractaward. Too short a period will lead to the preparation being done in a hurry with theconsequent risk of inaccuracies. The programme is needed for monitoring prog-ress and for enabling the Engineer to make arrangements for the provision of Draw-ings, instructions, etc., under Clause 6, the timing of nominated Subcontracts underClause 59, the discharge of the Contractor's duty under Clause 46 and the coordina-tion with other contractors engaged in the project dealt with in Clause 31.

62 © FIDIC 1989

Page 63: 35824401 FIDIC Guide to the Use of FIDIC

Depending upon the length of the construction period it may be appropriate to plan theimmediate period in detail and later periods in general terms and update and refine theprogramme at regular intervals, for example every three months. If later, claims aresubmitted by the Contractor, the programme will probably be of assistance in theirevaluation.

In considering the programme, the Engineer should comment to the Contractor on anyaspect which does not appear to be in conformity with the Contract, but the Contractorhas control over the provision of resources (labour, Contractor's Equipment andmaterials) needed to carry out the Works in accordance with Clause 13. If the Worksare not proceeding in accordance with the programme, and the Engineer requires theprogramme to be updated, it is important that any extension of time to which theContractor is entitled under Clause 44 should be determined before the revisedprogramme is considered. Accordingly, it is important that the Contractor complieswith Sub-Clause 44.2. Failure to observe this point may complicate the assessment ofany extra payments to which the Contractor may be entitled on this account.

As stated above an entry is required in Part II stating the time within which the pro-gramme is required to be submitted to the Engineer for his consent. This differs fromprevious editions as the programme, in the third and preceding editions, wasrequired to be submitted to the Engineer for his approval. The programme is thereponsibility of the Contractor and it is submitted to the Engineer for constructivecomment i.e., if the Engineer considers the Contractor's submission to be unclear orinadequate the Engineer will inform the Contractor of his views and in practice theywill usually meet to discuss the Engineer's comments. The Engineer should not giveconsent to a programme which is unrealistically optimistic.

The Engineer has discretion to call for information on the Contractor's arrangements andmethods of working, and will normally do so for major Temporary Works and construc-tion operations. The Engineer will ordinarily scrutinise this information with referenceto safety and the effect that such arrangements and methods may have on the PermanentWorks and will satisfy himself that if the work is carried out as proposed, the programmecan be achieved. He will draw to the attention of the Contractor any matters which causehim concern.

Hence, the Engineer monitors the progress of the Works on behalf of the Employer butis not entitled to alter or interfere with the Contractor's obligation to complete the Workssafely, properly and on time.

As stated above, it is necessary for an entry to appear in Part II stating the time withinwhich the programme is to be submitted and the following is an example of a suitableentry:

Programme to 14.1 The time within which the programme shall be submit-be Submitted ted shall be (insert number) days.

Revised 14.2 Ifat any time it should appear to the Engineer that theProgramme actual progress of the Works does not conform to the

programme to which consent has been given under Sub-Clause 14.1, the Contractor shall produce, at the re-quest of the Engineer, a revised programme showing themodifications to such programme necessary to ensurecompletion of the Works within the Time for Completion.

© FIDIC 1989 63

Page 64: 35824401 FIDIC Guide to the Use of FIDIC

If during the execution of the Contract it becomes apparent to the Engineer that theContractor is not maintaining satisfactory progress in accordance with the programmethe Engineer will require the Contractor to produce a revised programme to showhow he proposes to complete the Works within the Time for Completion. The Contrac-tor will not be entitled to any additional payment for the preparation of the revisedprogramme as it will have become necessary because of the Contractor's failure tomaintain satisfactory progress. The Contractor is obliged under this Sub- Clause toproduce a revised programme when so requested by the Engineer.

Cash Flow 14.3 The Contractor shall, within the time stated in Part IIEstimate to ofthese Conditions after the date of the Letter of Accep-

be Submitted tance, provide to the Engineer for his information adetailed cash flow estimate, in quarterly periods, of allpayments to which the Contactor will be entitled underthe Contract and the Contractor shall subsequentlysupply revised cash flow estimates at quarterly intervals,if required to do so by the Engineer.

The Employer will require a cash-flow estimate to enable him to ensure that funding isavailable when required. It is also in the interests of the Contractor that the Employershould be aware of the dates when payments are expected to be due to the Contractor.Under this Sub-Clause the obligation of the Contractor to produce such a cash-flowestimate and to up-date it as required by the Engineer is specified. The Contractor shoulddifferentiate in this estimate between payments in local and foreign currencies.

It is necessary to state in Part lithe date by which the cash-flow estimate must besubmitted and the following is an example of an appropriate entry:

Cash Flow 14.3 The time within which the detailed cash-flow estimateEstimate to shall be submitted shall be (insert number) days.

be Submitted

For the Part II entries in respect of 14.1 and 14.3 it is desirable for consistency withthe rest of the Conditions that the number of days inserted should be a multiple of seven.

Contractor 14.4 The submission to and consent by the Engineer of suchnotRelieved programmes or the provision of such general descrip-ofDuties or tions or cash flow estimates shall not relieve the Con-

Responsibilities tractor of any of his duties or responsibilities under theContract.

The submission of the programme by the Contractor to the Engineer does not imply thatfailure of the Engineer to disapprove the programme relieves the Contractor of his re-sponsibility. The same applies to the submission to the Engineer of the detailed cash-flow estimate.

Contractor's 15.1 The Contractor shall provide all necessary superinten-Superintendence dence during the execution of the Works and as long

thereafter as the Engineer may consider necessary forthe proper fulfilling of the Contractor' s obligations un-der the Contract. The Contractor, or a competent andauthorised representative approved of by the Engineer,which approval may at any time be withdrawn, shallgive his whole time to the superintendence of the Works.

64 ©FIDIC 1989

Page 65: 35824401 FIDIC Guide to the Use of FIDIC

Such authorised representative shall receive, on behalfof the Contractor, instructions from the Engineer or,subject to the provisions of Clause 2, the Engineer'sRepresentative.

If approval of the representative is withdrawn by theEngineer, the Contractor shall, as soon as is practi-cable, having regard to the requirement of replacinghim as hereinafter mentioned, after receiving notice ofsuch withdrawal, remove the representative from theWorks and shall not thereafter employ him again on theWorks in any capacity and shall replace him by anotherrepresentative approved by the Engineer.

This Sub-Clause specifies the Contractor's responsibilities for superintendence.

The authority of the Engineer to disapprove an individual as Contractor's representativeentails very serious responsibilities for the Engineer and such authority should be exer-cised only by the Engineer and should not be delegated. Clashes of personality on Sitecan occur and the Engineer himself should take any action required in such a matter. Itshould be noted that the Contractor is obliged to act if the Engineer so orders.

Where the language in which the Contract documents have been drawn up is not thelanguage of the country in which the Works are to be executed, or where for any otherreason it is necessary to stipulate that the Contractor's authorised representative shallbe fluent in a particular language, appropriate Sub-Clauses should be added in Part II.The following are examples:

Language 15.2 The Contractor's authorised representative shall beAbility of fluent in (insert name of language).

Contractor'sRepresentative

or

Interpreter 15.2 If the Contractor's authorised representative is not, into be made the opinion of the Engineer, fluent in (insert name of

Available language), the Contractor shall have available on Site atall times a competent interpreter to ensure the propertransmission of instructions and information.

Contractor's 16.1 The Contractor shall provide on the Site in connectionEmployees with the execution and completion of the Works and the

remedying of any defects therein

(a) only such technical assistants as are skilled andexperienced in their respective callings and such fore-men and leading hands as are competent to give propersuperintendence of the Works, and

(b) such skilled, semi-skilled and unskilled labour as isnecessary for the proper and timely fulling of theContractor's obligations under the Contract.

This Sub-Clause specifies certain requirements in regard to the staff and labour forceemployed by the Contractor on the Site.

© FIDIC 1989 65

Page 66: 35824401 FIDIC Guide to the Use of FIDIC

Engineer at 16.2 The Engineer shall be at liberty to object to and requireLiberty to the Contractor to remove forthwith from the Works any

Object person provided by the Contractor who, in the opinionof the Engineer, misconducts himself, or is incompetentor negligent in the proper performance of his duties, orwhose presence on Site is otherwise considered by theEngineer to be undesirable, and such person shall notbe again allowed upon the Works without the consentof the Engineer. Any person so removed from the Worksshall be replaced as soon as possible.

As in the case of the Contractor's authorised representative the Engineer has the powerto order the removal from the Site of any member of the Contractor's labour force. It isreiterated that such decisions should be taken by the Engineer and should not be dele-gated.

Where the language in which the Contract documents have been drawn up is not thelanguage of the country in which the Works are to be executed, or where for any otherreason it is necessary to stipulate that members of the Contractor's superintending staffshall be fluent in a particular language, a Sub-Clause in the following terms may be addedin Part II:

Language 16.3 A reasonable proportion of the Contractor's superintend-Ability of ing staff shall have a working knowledge of (insert name

Superintend- of language) or the Contractor shall have available oning Staff Site at all times a sufficient number of competent inter-

preters to ensure the proper transmission of instructionsand information.

Where there is a desire, but not a legal requirement, that the Contractor makes reason-able use of persons resident in the country in which the Works are to be executed, anadditional Sub-Clause in the following terms may be added in Part II:

Employment 16.4 The Contractor is encouraged, to the extent practicableof Local and reasonable, to employ staff and labour from sources

Personnel within (insert name of country).

See the commentary to Sub-Clause 36.1 where reference is made to the use of localmaterials.

Setting-out 17.1 The Contractor shall be responsible for.

(a) the accurate setting-out of the Works in relation tooriginal points, lines and levels of reference given by theEngineer in writing,

(b) the correctness, subject as above mentioned, of theposition, levels, dimensions and alignment of all partsof the Works, and

(c) the provision of all necessary instruments, appli-ances and labour in connection with the foregoing re-sponsibilities.

66 © FIDIC 1989

Page 67: 35824401 FIDIC Guide to the Use of FIDIC

If, at any time during the execution of the Works, anyerror appears in the position, levels, dimensions oralignment of any part of the Works, the Contractor, onbeing required to do so by the Engineer, shall, at hisown cost, rectify such error to the satisfaction of theEngineer, unless such error is based on incorrect datasupplied in writing by the Engineer, in which case theEngineer shall determine an addition to the ContractPrice in accordance with Clause 52 and shall notify theContractor accordingly, with a copy to the Employer.

The checking of any setting-out or of any line or levelby the Engineer shall not in any way relieve the Con-tractor of his responsibility for the accuracy thereof andthe Contractor shall carefully protect and preserve allbench-marks, sight-rails, pegs and other things used insetting-out the Works.

The Engineer supplies the Contractor with the essential information upon which thesetting out of the Works by the Contractor is to be based. This information will nor-mally consist of a coordinated reference point, a datum level and a bearing. Rectifica-tion costs resulting from incorrect data supplied by the Engineer are recoverable by theContractor from the Employer should it be established that the data supplied by theEngineer was incorrect.

If, at any time during the execution of the Works, theEngineer requires the Contractor to make boreholes orto carry out exploratory excavation, such requirementshall be the subject of an instruction in accordance withClause 51, unless an item or a Provisional Sum in re-spect of such work is included in the Bill of Quantities.

This Sub-Clause deals with additional exploratory operations and how payment shouldbe made for them. There are various means of dealing with the payment. It may be dealtwith as a variation under Clause 51, a progress payment under an item in the Bill ofQuantities or a payment under a Provisional Sum which, in accordance with Sub-Clause58.2, will be either under Clause 52 or Sub-Clause 59.4.

Where the Contract comprises dredging and reclamation work this Sub-Clause mayrequire to be varied in Part II in the following manner:

Add second sentence as follows:

Such exploratory excavation shall be deemed to includedredging.

The Contractor shall, throughout the execution andcompletion of the Works and the remedying of any de-fects therein:

(a) have full regard for the safety of all persons entitledto be upon the Site and keep the Site (so far as the sameis under his control) and the Works (so far as the sameare not completed or occupied by the Employer) in anorderly state appropriate to the avoidance of danger tosuch persons, and

© FIDIC 1989 67

Boreholes and 18.1ExploratoryExcavation

Boreholes 18.1ExploratoryExcavation

Safety, 19.1Security

and Protectionof the

Environment

Page 68: 35824401 FIDIC Guide to the Use of FIDIC

(b) provide and maintain at his own cost all lights,guards,fencing, warning signs and watching, when andwhere necessary or required by the Engineer or by anyduly constituted authority, for the protection of theWorks or for the safety and convenience of the publicor others, and

(c) take all reasonable steps to protect the environmenton and off the Site and to avoid damage or nuisance topersons or to property of the public or others resultingfrom pollution, noise or other causes arising as a con-sequence of his methods of operation.

This Sub-Clause provides that the Contractor is responsible for the safety of persons onSite and for installation of such facilities as will protect the Works, the public and theenvironment from injury or damage.

Depending upon the location of the Works in relation to public services and upon thesize of the Works, it may be appropriate to elaborate specifically on the Contractor'sobligation to provide fire protection equipment and organisation.

Where the Contract includes dredging the possibility of pollution should be given par-ticular attention and additional wording may be required. For example, where fishingand recreation areas might be affected, the Contractor should be required to plan andexecute the dredging so that the impact thereof is kept to a minimum. Where there is arisk of chemical pollution from soluble sediments in the dredging area, for instance in aharbour, it is important that sufficient information is provided with the tenderdocuments and that responsibilities are clearly and unambiguously defined. The ap-propriate text should be included in Part II.

Employer's 19.2 Ifunder Clause 31 the Employer shall carry out workResponsibilities on the Site with his own workmen he shall, in respect of

such work:

(a) have full regard to the safety of all persons entitledto be upon the Site, and

(b) keep the Site in an orderly state appropriate to theavoidance of danger to such persons.

If under Clause 31 the Employer shall employ othercontractors on the Site he shall require them to have thesame regard for safety and avoidance of danger.

This Sub-Clause stipulates that the Employer shall have obligations similar to those ofthe Contractor in respect of work he is carrying out with his own workmen on the Siteand cause other contractors who execute work for him on the Site to assume such obli-gations in respect of their work.

68 © FIDIC 1989

Page 69: 35824401 FIDIC Guide to the Use of FIDIC

ALLOCATION OF RESPONSIBILITY AND INSURANCE OBLIGATIONS

Clause 20 allocates responsibility between the Contractor and the Employer for damagewhich may be suffered by the Works. The Contractor is to bear the cost of rectificationof loss or damage which arises from any cause, other than those which are described as'Employer's Risks'. Where damage is caused by an Employer's Risk there is an obli-gation upon the Contractor, if requested by the Engineer, to rectify, but the costs of suchwork are to be borne by the Employer.

This allocation of responsibility is effective from the commencement of the Works untilthe issue of the Taking-Over Certificate. In addition, the Contractor is responsible formaterials he may be required to supply and for the care of outstanding work which hemay be required to complete under the terms of the Defects Liability Period obligations.

The Contractor is also liable for damage which he may do to the Works while on theSite for the purpose of complying with his obligations under Clauses 49 and 50.

Care of 20.1 The Contractor shall take full responsibility for the careWorks ofthe Works and materials and Plant for incorporation

therein from the Commencement Date until the date ofissue of the Taking-Over Certificate for the whole of theWorks, when the responsibility for the said care shallpass to the Employer. Provided that:

(a) if the Engineer issues a Taking-Over Certificate forany Section or part of the Permanent Works the Con-tractor shall cease to be liable for the care of thatSection orpartfrom the date of issue of the Taking-OverCertificate, when the responsibility for the care of thatSection or part shall pass to the Employer, and

(b) the Contractor shall take full responsibility for thecare of any outstanding Works and materials and Plantfor incorporation therein which he undertakes to finishduring the Defects Liability Period until such outstand-ing Works have been completed pursuant to Clause 49.

This Sub-Clause, which specifies the responsibilities of the Contractor in regard to theWorks, clearly states that these responsibilities continue until the 'date of issue of theTaking-Over Certificate', as distinct from the date of taking over stated in the Certifi-cate. This makes it clear at what point in time the obligations change in cases wheretaking over has been backdated.

Responsibility 20.2 If any loss or damage happens to the Works, or any partto Rectify thereof, or materials or Plant for incorporation therein,

Loss or during the period for which the Contractor is respon-Damage sible for the care thereof, from any cause whatsoever,

other than the risks defined in Sub-Clause 20.4, theContractor shall, at his own cost, rectify such loss ordamage so that the Permanent Works conform in everyrespect with the provisions of the Contract to the satis-faction of the Engineer. The Contractor shall also beliable for any loss or damage to the Works occasionedby him in the course of any operations carried out byhim for the purpose of complying with his obligationsunder Clauses 49 and 50.

© FIDIC 1989 69

Page 70: 35824401 FIDIC Guide to the Use of FIDIC

This Sub-Clause establishes the Contractor's obligation to make good any defects forwhich he has responsibility under Sub-Clause 20.1.

Loss or 20.3 In the event of any such loss or damage happening fromDamage Due to any of the risks defined in Sub-Clause 20.4, or in corn-

Employer's bination with other risks, the Contractor shall, f and toRisks the extent required by the Engineer, rectify the loss or

damage and the Engineer shall determine an additionto the Contract Price in accordance with Clause 52 andshall notify the Contractor accordingly, with a copy tothe Employer. In the case of a combination of riskscausing loss or damage any such determination shalltake into account the proportional responsibility of theContractor and the Employer.

As stated in the introductory comments to Clause 20, the Contractor has a responsibilityto make good damage which occurs from Employer's Risks but shall recover from theEmployer the cost of making good such damage. The amount to be recovered by theContractor shall be determined by the Engineer.

Employer's 20.4 The Employer's Risks are:iS S

(a) war, hostilities (whether war be declared or not),invasion, act of foreign enemies,

(b) rebellion, revolution, insurrection, or military orusurped power, or civil war,

(c) ionising radiations, or contamination by radio-activ-ity from any nuclear fuel, or from any nuclear wastefrom the combustion of nuclear fuel, radio-active toxicexplosive, or other hazardous properties of any explo-sive nuclear assembly or nuclear component thereof,

(d) pressure waves caused by aircraft or other aerialdevices travelling at sonic or supersonic speeds,

(e) riot, commotion or disorder, unless solely restrictedto employees of the Contractor or of his Subcontractorsand arising from the conduct of the Works,(f) loss or damage due to the use or occupation by theEmployer of any Section or part of the PermanentWorks, except as may be provided for in the Contract,(g) loss or damage to the extent that it is due to thedesign of the Works, other than any part of the designprovided by the Contractor or for which the Contractoris responsible,

(h) any operation of the forces of nature against whichan experienced contractor could not reasonably havebeen expected to take precautions.

This Sub-Clause lists certain risks which are outside the control of the Contractor.These risks were referred to in the previous edition as 'excepted risks' but this was aconfusing title as it was sometimes taken to be 'accepted risks'. The term 'Employer'sRisks' has been used in the fourth edition for clarity.

70 © FIDIC 1989

Page 71: 35824401 FIDIC Guide to the Use of FIDIC

There are two particular changes in these risks from those in the third edition.

20.4 (g) loss or damage to the extent that it is due to thedesign of the Works, other than any part of the designprovided by the Contractor or for which the Contractoris responsible,

The third edition included in the 'excepted risks' a cause solely due to the Engineer'sdesign of the Works. It has been decided to change this so that the Contractor is onlyresponsible for errors in the designs for which he has been responsible. This is consid-ered to be more balanced than was the third edition. It is now possible to establishdesign responsibility from the outset, rather than applying a test after the event (i.e.,was there contribution to the error by another party or was it solely caused by theEngineer?). In practice that question was exceedingly difficult to answer.

Should damage occur to the Works in circumstances where an error in design is a con-tributory factor, the Contractor is only relieved of responsibility to the extent that thedamage was caused by a design not provided by him.

20.4 (h) any operation of the forces of nature against whichan experienced contractor could not reasonably havebeen expected to take precautions.

This Sub-Clause has removed two difficulties. The third edition referred to risks whichcould not be foreseen, although it could be argued that all risks of the forces of naturecan be foreseen. The third edition also referred to risks from the forces of nature whichcould not be insured against. The Sub-Clause is concerned with very unlikely risks,whereas it is these very unlikely risks for which insurance is generally available.The words 'could not insure against' have been removed as this test is difficult toapply. Insurance against a particular risk of nature may be available but only at anexorbitant premium. Conversely, insurers may not offer cover against a risk which theyfeel is almost certain to arise because of the nature or location of the Works.

Under the fourth edition the Contractor is not responsible if the Works are damaged byan operation of the forces of nature against which he could not reasonably have beenexpected to take precautions, i.e., a risk that is so unlikely that it would not be reason-able to spend time and money in taking precautions.

Insurance of 21.1 The Contractor shall, without limiting his or the Em-Worksand ployer's obligations and responsibilities under Clause

Contractor's 20, insure:Equipment (a) the Works, together with materials and Plant for

incorporation therein, to the full replacement cost(b) an additional sum of 15 per cent of such replacementcost, or as may be specified in Part II of these Condi-tions, to cover any additional costs of and incidental tothe rectification of loss or damage including profes-sional fees and the cost of demolishing and removingany part of the Works and of removing debris of what-soever nature(c) the Contractor's Equipment and other things broughtonto the Site by the Contractor, for a sum sufficient toprovide for their replacement at the Site.

©FIDIC 1989 71

Page 72: 35824401 FIDIC Guide to the Use of FIDIC

This Sub-Clause sets out the requirements for insurance of the Works and of the Con-tractor's Equipment. The fact that insurance is in force does not alter the obligations ofboth parties as defined in Clause 20.

Although the insurance is to be for full replacement cost, it is not always necessary toinsure for the replacement of an entire project, particularly if there is a wide geographi-cal spread of work or if, for some other reason, it is felt that it would never be neces-sary to replace the whole of the project. It is the intention that a 'First Loss' value wouldbe acceptable - that is, a sum less than the full value of the project, but sufficient toprovide for the cost of repair of the most serious damage envisaged.

Where there is provision in the Contract for payments to the Contractor to be made inforeign currency, it may be appropriate to vary the Sub-Clause by an entry in Part II asfollows:

Insurance of 21.1 Add final sentence as follows:

,Worksan,d The insurance in paragraphs (a) and (b) shall provide.1n1rac1ors for compensation to be payable in the types and propor-

qu P e tions of currencies required to rectify the loss or dam-age incurred.

It is advisable in the interests of equitable tendering that the deductible limits for theEmployer's Risks are stated in the Tender documents. To this end this Sub-Clause maybe varied in Part II in the following manner.

Insurance of 21.1 Add to paragraph (a) as follows:Works

an,d and with deductible limits for the Employer's Risks notContractor sexceeding (insert amounts).Equipment

It may also be considered appropriate to state in the Tender documents other factors,such as the total cover required, relating to Employer's Risks.

Sco e of 21.2 The insurance in paragraphs (a) and (b) of Sub-Clauseover 21.1 shall be in the joint names of the Contractor and

the Employer and shall cover:(a) the Employer and the Contractor against all loss ordamage from whatsoever cause arising, other than asprovided in Sub-Clause 21.4, from the start of work atthe Site until the date of issue of the relevant Taking-Over Certificate in respect of the Works or any Sectionor part thereof as the case may be, and

(b) the Contractor for his liability:

(i) during the Defects Liability Period for loss ordamage arising from a cause occurring prior to thecommencement of the Defects Liability Period, and(ii) for loss or damage occasioned by the Contractorin the course of any operations carried out by him forthe purpose of complying with his obligations underClauses 49 and 50.

Previously the Contractor was to insure the Works against those risks of damage forwhich he was responsible. However, some of the Employer's Risks were also insur-able, notably damage resulting from design errors and from the forces of nature. For aproject to be fully insured, it was therefore theoretically necessary for the Employer totake out a second policy, on the same project, to cover his risks.

72 ©FIDIC 1989

Page 73: 35824401 FIDIC Guide to the Use of FIDIC

Modem practice is to avoid the problems of two parallel policies applying to the sameproject, by having a single policy in the joint names of both parties, and insuring eachparty for his risks. The fourth edition provides for this and has the effect of making theContractor responsible for insuring against all risks that can be insured.

Contract Works insurance is not generally available for the costs of rectification ofdefects. The insurance relates to the costs of the repair of the damage which resultsfrom the defect. In insurance terminology this is known as 'resultant damage'. Itshould be noted that Sub-Clause 21.2 requires the insurance to be against 'loss ordamage' and not for the part of the work which was itself defective.

The insurance of the Works is to be in the joint names of the Employer and the Con-tractor. However, during the Defects Liability Period the insurance is only against thatdamage which the Contractor is required to repair under the terms of the Defects Liabil-ity Clause, and so the Employer has no insurable interest in this part of the policy.This section of the insurance could, therefore, be in the name of the Contractor alone.

Similarly, the Employer may not have an insurable interest in the Contractor's Equip-ment, and so this is insured in the name of the Contractor.

The Employer will wish to be certain that the Contractor has arranged these insurances,but the Employer would not be in a position to receive the insurance monies himselfdirectly, should there be damage.

Although it is not a requirement of the Clause, there may be cases where it is decided toinclude the name of the Engineer as a joint insured in the policy which is to be arrangedpursuant to Sub-Clause 21.2. In many cases, the inclusion of the Engineer as a jointinsured may have little effect on the premium.

The Contractor's obligation to insure begins "from the start of work at the Site" - seesub-para 21.2(a). Where a Contract contains a substantial Plant element or on anyContract where it is anticipated that there may be significant exposure before work startsat Site, consideration should be given to varying Clause 21 to ensure that the risks arecovered.

One way of avoiding any 'gap' in cover might be to alter sub-para 21.2(a) by replacingthe wording quoted above with "from the Commencement Date". However, such achange could lead to complications in arranging insurance and other wording might bemore appropriate in the context of a particular contract. It should also be borne in mindthat a change linking insurance to the Commencement Date could result in some delayin the issue by the Engineer of a notice to commence in accordance with Sub-Clause41.1. The definition of Commencement Date - see sub-para 1.1 (c)(i) - relates the dateto the Engineer's notice. It might take the Contractor a little time to effect the insuranceand the Engineer might feel obliged to satisfy himself that the Employer had receivedevidence of insurance before he (the Engineer) issued the notice. A delay in the issue ofthe notice to commence would, in many cases, not be in the interests of either theEmployer or the Contractor.

Whatever course is adopted, it would be prudent to take the advice of an insurance expertbefore determining the exact wording to use in order to be confident that the requisiteinsurance could be obtained. Furthermore, any change made to Sub-Clause 21.1 mightalso require a change to Sub-Clause 25.1 in order to maintain consistency.

Responsibility 21.3 Any amounts not insured or not recovered from theforAmounts insurers shall be borne by the Employer or the Contrac-

notRecovered tor in accordance with their responsibilities underClause 20.

©FIDIC 1989 73

Page 74: 35824401 FIDIC Guide to the Use of FIDIC

If the sum selected for insurance proved to be insufficient to pay for the replacementthen there would be a breach of Sub-Clause 21.1. The party responsible under Clause20 for the costs of the repair would be unable to recover the deficiency from the insur-ance but would nevertheless be responsible for making good the damage.

Exclusions 21.4 There shall be no obligation for the insurances in Sub-Clause 21.1 to include loss or damage caused by(a) war, hostilities (whether war be declared or not),invasion, act of foreign enemies,(b) rebellion, revolution, insurrection, or military orusurped power, or civil war,(c) ionising radiations, or contamination by radio-activ-ity from any nuclear fuel, or from any nuclear wastefrom the combustion of nuclear fuel, radio-active toxicexplosive, or other hazardous properties of any explo-sive nuclear assembly or nuclear component thereof,(d) pressure waves caused by aircraft or other aerialdevices travelling at sonic or supersonic speeds.

This Sub-Clause permits the exclusion from the insurance of certain risks which cannotnormally be insured. In addition to the exclusions listed, some projects may be under-taken where other risks may not be insurable, for example, flood risks when workingbelow water level alongside a river. In these circumstances an amendment appropri-ate to the particular project should be made in Part II.

Damage to 22.1 The Contractor shall, except if and so far as the Con-Personsand tract provides otherwise, indemnify the Employer

Property against all losses and claims in respect of:

(a) death of or injury to any person, or(b) loss of or damage to any property (other than theWorks),which may arise out of or in consequence of the execu-tion and completion of the Works and the remedying ofany defects therein, and against all claims, proceedings,damages, costs, charges and expenses whatsoever inrespect thereof or in relation thereto, subject to theexceptions defined in Sub-Clause 22.2.

This Sub-Clause requires the Contractor to indemnify the Employer for any claims thatmay arise from death or injury to third parties, or loss of or damage to any property(other than the Works), as a result of the execution of the Works.

Exceptions 22.2 The "exceptions" referred to in Sub-Clause 22.1 are:

(a) the permanent use or occupation of land by theWorks, or any part thereof,(b) the right of the Employer to execute the Works, orany part thereof, on, over, under, in or through anyland,(c) damage to property which is the unavoidable resultof the execution and completion of the Works, or theremedying of any defects therein, in accordance with theContract,

74 © FIDIC 1989

Page 75: 35824401 FIDIC Guide to the Use of FIDIC

(d) death of or injury to persons or loss of or damage toproperty resulting from any act or neglect of the Em-ployer, his agents, servants or other contractors, notbeing employed by the Contractor, or in respect of anyclaims, proceedings, damages, costs, charges and ex-penses in respect thereof or in relation thereto or, wherethe injury or damage was contributed to by the Contrac-tor, his servants or agents, such part of the said injuryor damage as may be just and equitable having regardto the extent of the responsibility of the Employer, hisservants or agents or other contractors for the injury ordamage.

This Sub-Clause sets out the exceptions to the obligation of the Contractor stated in Sub-Clause 22.1.

indemnityby 22,3 The Employer shall indemnify the Contractor against allEmployer claims, proceedings, damages, costs, charges and ex-

penses in respect of the matters referred to in the excep-tions defined in Sub-Clause 22.2.

The Contractor is absolved from responsibility if the death, injury or damage arises fromany of the exceptions listed in Sub-Clause 22.2. Where these exceptions apply, theEmployer is to indemnify the Contractor against any claims he may receive from thirdparties.

ThirdParty 23.1 The Contractor shall, without limiting his or the Em-Insurance ployer's obligations and responsibilities under Clause(including 22, insure, in the joint names of the Contractor and the

Employer's Employer, against liabilities for death of or injury to anyProperty) person (other than as provided in Clause 24) or loss of

or damage to any property (other than the Works) aris-ing out of the performance of the Contract, other thanthe exceptions defined in paragraphs (a), (b) and (c) ofSub-Clause 22.2.

The Contractor is to arrange a Third Party insurance, to protect both the Contractor andthe Employer against the liabilities described in Clause 22.

It is possible that damage or injury may be suffered by a third party as a result of thenegligence of the Employer and it is reasonable that the Contractor should not berequired to indemnify the Employer in these circumstances. This is the effect ofSub-Clause 22.2(d). The Third Party liability insurance should protect the Employer inthese circumstances and this is the reason why exception (d) is not mentioned in Sub-Clause 23.1.

Minimum Amount 23.2 Such insurance shall be for at least the amount statedofInsurance in the Appendix to Tender.

The Appendix to Tender should stipulate the minimum amount of insurance to be pro-vided. However, it is for the Contractor to decide whether the minimum amount issufficient and, if he considers it necessary, to insure for a greater amount. The policyshould cover an unlimited number of claims in any one year.

Cross 23.3 The insurance policy shall include a cross liabilityLiabilities clause such that the insurance shall apply to the Con-

tractor and to the Employer as separate insureds.

©FIDIC 1989 75

Page 76: 35824401 FIDIC Guide to the Use of FIDIC

This Sub-Clause stipulates the right of the Employer or the Contractor to act individu-ally in respect of a claim despite the fact that the policy is in their joint names.

Accidentor 24.1 The Employer shall not be liable for or in respect of anyInjury to damages or compensation payable to any workman or

Workmen otherperson in the employment of the Contractor or anySubcontractor, other than death or injury resulting fromany act or default of the Employer, his agents or ser-vants. The Contractor shall indemnify and keep indem-nified the Employer against all such damages andcompensation, other than those for which the Employeris liable as aforesaid, and against all claims, proceed-ings, damages, costs, charges, and expenses whatsoeverin respect thereof or in relation thereto.

The Employer has no responsibility for injuries that may be suffered by employees ofthe Contractor, unless such injury results from an act or default of the Employer.In such circumstances the injured person would be regarded as a 'third party' to theEmployer and the Employer would have the benefit of the Third Party insurance de-scribed in Clause 23.

Insurance against accident to workmen is usually regulated by statutory provisions. TheContractor should consider whether such provisions are sufficient for the Contract.

Insurance 242 The Contractor shall insure against such liability andAgainst shall continue such insurance during the whole of the

Accident to time that any persons are employed by him on theWorkmen Works. Provided that, in respect of any persons em-

ployed by any Subcontractor, the Contractor's obliga-tions to insure as aforesaid under this Sub-Clause shallbe satisfied if the Subcontractor shall have insuredagainst the liability in respect of such persons in suchmanner that the Employer is indemnified under thepolicy, but the Contractor shall require such Subcon-tractor to produce to the Employer, when required, suchpolicy of insurance and the receipt for the payment ofthe current premium.

The Contractor is required to insure his liability for death or injury to his own employ-ees and he should also ascertain that all Subcontractors have similar insurance inforce in regard to their employees.

Evidence and 25.1 The Contractor shall provide evidence to the EmployerTerms of prior to the start of work at the Site that the insurances

Insurances required under the Contract have been effected andshall, within 84 days of the Commencement Date, pro-vide the insurance policies to the Employer. When pro-viding such evidence and such policies to the Employer,the Contractor shall notify the Engineer of so doing.Such insurance policies shall be consistent with thegeneral terms agreed prior to the issue of the Letter ofAcceptance. The Contractor shall effect all insurancesfor which he is responsible with insurers and in termsapproved by the Employer.

76 ©FIDIC 1989

Page 77: 35824401 FIDIC Guide to the Use of FIDIC

This Sub-Clause contains certain general requirements applicable to the various insur-ances which are required by the Contract.

Evidence that the insurances have been arranged must be provided by the Contractorprior to the start of work on Site. This evidence might be a cover note or insurancecertificate. These documents do not provide sufficient detail to enable the Employeror his insurance adviser to agree the scope of cover and accordingly there is a require-ment that the actual policy documents must be provided within 84 days of the Com-mencement Date.

The general terms of the insurance, particularly levels of excess/deductible, and anyadditional exclusions, conditions and warranties, should be agreed between the Employerand the Contractor prior to the issue of the Letter of Acceptance.

Adequacyof 25.2 The Contractor shall notify the insurers of changes inInsurances the nature, extent orprogrammefor the execution of the

Works and ensure the adequacy of the insurances at alltimes in accordance with the terms of the Contract andshall, when required, produce to the Employer the in-surance policies in force and the receipts for paymentof the current premiums.

Construction insurance may be invalidated if the insurers are not made aware of changesto the Works. In order to avoid doubt as to who will perform this duty this Sub-Clauseemphasises the obligation of the Contractor to notify the Insurer of changes.

Remedyon 25.3 If the Contractor fails to effect and keep in force any ofContractor's the insurances required under the Contract, or fails to

Failure to provide the policies to the Employer within the periodInsure required by Sub-Clause 25.1, then and in any such case

the Employer may effect and keep in force any such in-surances and pay any premium as may be necessary forthat purpose and from time to time deduct the amountso paid from any monies due or to become due to theContractor, or recover the same as a debt due from theContractor.

Should the Contractor fail to arrange or maintain any of the insurances which he isrequired to provide, then the Employer may do so, but at the cost of the Contractor.

Compliance 25.4 In the event that the Contractor or the Employer fails towith Policy comply with conditions imposed by the insurance poli-Conditions cies effected pursuant to the Contract, each shall indem-

nfy the other against all losses and claims arising fromsuch failure.

Insurers may be able to avoid paying claims if certain conditions of the policy, particu-larly warranties, are breached by either of the insured parties. Sub-Clause 25.4 providesthat in these circumstances the party who is in breach of policy conditions shall indem-nify the other for any resulting loss.

©FIDIC 1989 77

Page 78: 35824401 FIDIC Guide to the Use of FIDIC

INSURANCES ARRANGED BY EMPLOYER

In certain circumstances, such as where a number of separate contractors are employedon a single project, or phased take-over is involved, it may be preferable for theEmployer to arrange insurance of the Works, and third Party insurance. In such case itmust be clear in the Contract that the Contractor is not precluded from taking out anyadditional insurance, should he desire to do so, over and above that arranged by the Em-ployer.

Tenderers must be provided at the Tender stage with details of the insurance to be ar-ranged by the Employer, in order to assess what provision to make in their rates andprices for any additional insurance, and for the amount of policy deductibles whichthey will be required to bear. Such details shall form part of the Contract between theEmployer and the Contractor.

The following example clauses for inclusion in Part II provide for the arrangement ofinsurance by the Employer:

Clause 21

Delete the text of the Clause and substitute the following re-numbered Sub-Clauses:

Insurance 21.1 Without limiting his or the Contractor's obligations andof Works responsibilities under Clause 20, the Employer will in-

sure:

(a) the Works, together with materials and Plant for in-corporation therein, to the full replacement cost

(b) an additional sum to cover any additional costs ofand incidental to the rectification of loss or damage

and incidental to the rectification of loss or damageincluding professional fees and the cost of demolishingand removing any part of the Works and of removingdebris of whatsoever nature.

Insurance of 21.2 The Contractor shall, without limiting his obligationsContractor's and responsibilities under Clause 20, insure the Contrac-

Equipment tor's Equipment and other things brought onto the Siteby the Contractor, for a sum sufficient to provide fortheir replacement at the Site.

Scope of 21.3 The insurance in Sub-Clause 21.1 shall be in the jointCover names of the Contractor and the Employer and shall

cover:

(a) the Employer and the Contractor against loss ordamage as provided in the details of insurance annexedto these Conditions, from the start of work at the Siteuntil the date of issue of the relevant Taking-Over Cer-tificate in respect of the Works or any Section or partthereof as the case may be, and

(b) the Contractor for his liability:(i) during the Defects Liability Period for loss ordamage arising from a cause occurring prior to thecommencement of the Defects Liability Period, or

78 ©FLDIC 1989

Page 79: 35824401 FIDIC Guide to the Use of FIDIC

(ii) occasioned by the Contractor in the course of anyoperations carried out by him for the purpose ofcomplying with his obligations under Clauses 49 and50.

Responsibility 21.4 Any amounts not insured or not recovered from theforAmounts insurers shall be borne by the Employer or the Contrac-

not Recovered tor in accordance with their responsibilities under Clause20.

Clause 23

Delete the text of the Clause and substitute:

Third Party 23.1 Without limiting his or the Contractor's obligations andInsurance responsibilities under Clause 22, the Employer will in-(including sure in the joint names of the Contractor and the Em-

Employer's ployer, against liabilities for death of or injury to anyProperty) person (other than as provided in Clause 24) or loss of

or damage to any property (other than the Works) aris-ing out of the performance of the Contract, as providedin the details of insurance referred to in Sub-Clause21.3.

Clause 25

Delete the text of the Clause and substitute:

Evidence 25.1 The insurance policies to be arranged by the Employerand pursuant to Clauses 21 and 23 shall be consistent with

Terms of the general terms described in the Tender and copies ofInsurances such policies shall when required be supplied by the

Employer to the Contractor.

Adequacy 25.2 The Employer shall notify the insurers of changes in theof nature, extent or programme for execution of the Works

Insurances and ensure the adequacy of the insurances at all timesin accordance with the terms of the Contract and shall,when required, produce to the Contractor the insurancepolicies in force and the receipts for payment of thepremiums. No variations shall be made to the insur-ances by the Employer without the prior approval of theContractor.

Remedy on 25.3 If and so far as the Employer fails to effect and keep inEmployer's force any of the insurances referred to in Sub-Clause

Failure to 25.1, then the Contractor may effect and keep in forceInsure any such insurance and pay any premiums as may be

necessary for that purpose and add the amount so paidto any monies due or to become due to the Contractor,or recover the same as a debt due from the Employer.

Compliance 25.4 In the event that the Contractor or the Employer fails towith Policy comply with conditions imposed by the insurance poli-Conditions cies effected pursuant to the Contract, each shall indem-

nify the other against all losses and claims arising fromsuch failure.

©FIDIC 1989 79

Page 80: 35824401 FIDIC Guide to the Use of FIDIC

OTHER OBLIGATIONS OF THE CONTRACTOR

Compliance 26.1 The Contractor shall conform in all respects, includingwith Statutes, by the giving of all notices and the paying of all fees,

Regulations with the provisions of:

(a) any National or State Statute, Ordinance, or otherLaw, or any regulation, or bye-law of any local or otherduly constituted authority in relation to the executionand completion of the Works and the remedying of anydefects therein, and

(b) the rules and regulations of all public bodies andcompanies whose property or rights are affected or maybe affected in any way by the Works,

and the Contractor shall keep the Employer indemnifiedagainst all penalties and liability of every kind forbreach of any such provisions. Provided always that theEmployer shall be responsible for obtaining any plan-ning, zoning or other similar permission required for theWorks to proceed and shall indemnify the Contractor inaccordance with Sub-Clause 22.3.

Depending upon the location, the nature and size of the project as well as its status inthe country where the Works are to be executed, it may not be in the Employer's bestinterests to require the Contractor to provide in his tender price for the cost of all localfees, etc., in relation to the Works. However, in order to avoid conflicts or ambiguities,this Sub-Clause requires the Contractor to give all notices and make all paymentsduly imposed. A supplementary clause in Part II, drafted for the individual projectcan provide for the Contractor to be reimbursed or exempted from any particular impo-sition specified therein. Otherwise all fees, etc., will be paid by the Contractor and mustbe included by him in his tender, with the exception of such costs as are related to theuse of the land of the Site as stated in Sub-Clause 22.2 and the consequences of a fail-ure to obtain permission required for the Works to proceed, as mentioned in the finalsentence of Sub-Clause 26.1

Fossils 27.1 Allfossils, coins, articles of value or antiquity and struc-tures and other remains or things of geological or ar-chaeological interest discovered on the Site shall, asbetween the Employer and the Contractor, be deemedto be the absolute property of the Employer. The Con-tractor shall take reasonable precautions to prevent hisworkmen or any other persons from removing or dam-aging any such article or thing and shall, immediatelyupon discovery thereof and before removal, acquaint theEngineer of such discovery and carry out the Engineer'sinstructions for dealing with the same. If, by reason ofsuch instructions, the Contractor suffers delay and/orincurs costs then the Engineer shall, after due consulta-tion with the Employer and the Contractor, determine:

(a) any extension of time to which the Contractor isentitled under Clause 44, and

80 © FIDIC 1989

Page 81: 35824401 FIDIC Guide to the Use of FIDIC

(b) the amount of such costs, which shall be added tothe Contract Price,

and shall notify the Contractor accordingly, with a copyto the Employer.

For the purpose of the Contract all articles of geological or archeological interest dis-covered on the Site are considered the property of the Employer. It is the Employer'sresponsibility to deal with them in accordance with the applicable laws and regulations.

The Engineer has an obligation, after consultation with the Employer and the Contrac-tor, to determine whether the Contractor shall be granted an extension of time or addi-tional costs to compensate him for additional work or delay.

Patent 28.1 The Contractor shall save harmless and indemnify theRights Employerfrom and against all claims and proceedings

for or on account of infringement of any patent rights,design trademark or name or other protected rights inrespect of any Contractor's Equipment, materials orPlant used for or in connection with or for incorpora-tion in the Works and from and against all damages,costs, charges and expenses whatsoever in respectthereof or in relation thereto, except where such in-fringement results from compliance with the design orSpecification provided by the Engineer.

The Contractor is responsible for dealing with patent and other rights and royalties inrespect of Plant, materials or Contractor's Equipment. The Contractor is not required todeal with similar matters arising from the design or specification provided by theEngineer, but where such design or specification includes certain patents this should bestated in the relevant document.

In projects where a substantial element of Plant is to be incorporated in the project,guidance for drafting a supplementary clause for inclusion in Part II can be obtained fromClause 16 of the Yellow Book third edition.

Royalties 28.2 Except where otherwise stated, the Contractor shall payall tonnage and other royalties, rent and other paymentsor compensation, if any,for getting stone, sand, gravel,clay or other materials required for the Works.

Particular conditions may apply in contracts comprising dredging and reclamation workor any other contract involving the dumping of materials. In the event that the Sub-Clause needs to be varied for such reasons the following entry in Part II may be appro-priate:

Royalties 28.2 Add second sentence as follows:

The Contractor shall also be liable for all payments orcompensation, if any, levied in relation to the dumpingof part or of all of any such materials.

It is sometimes the case on dredging contracts that the Employer shall bear the costs oftonnage and other royalties, rent and other payments or compensation. If such conditionsare to apply, Sub- Clause 28.2 should be varied either by adding wording or bydeleting the existing wording and substituting new wording.

©FIDIC 1989 81

Page 82: 35824401 FIDIC Guide to the Use of FIDIC

Interference 29.1 All operations necessary for the execution and comple-with Traffic tion of the Works and the remedying of any defects

andAdjoining therein shall, as far as compliance with the requirementsProperties of the Contract permits, be carried on so as not to in-

terfere unnecessarily or improperly with.

(a) the convenience of the public, or

(b) the access to, use and occupation of public or pri-vate roads and footpaths to or of properties whether inthe possession of the Employer or of any other person.The Contractor shall save harmless and indemnify theEmployer in respect of all claims, proceedings, dam-ages, costs, charges and expenses whatsoever arisingout of, or in relation to, any such matters insofar as theContractor is responsible therefor.

This Sub-Clause places an obligation upon the Contractor to limit the interference whichhis operations may cause to public or private thoroughfares or to properties adjoiningthe Site. The Sub-Clause should be read in conjunction with Clause 22.

Avoidance 30.1 The Contractor shall use every reasonable means toofDamage prevent any of the roads or bridges communicating with

to Roads or on the routes to the Site from being damaged orinjured by any traffic of the Contractor or any of hisSubcontractors and, in particular, shall select routes,choose and use vehicles and restrict and distribute loadsso that any such extraordinary traffic as will inevitablyarise from the moving of materials, Plant, Contractor'sEquipment or Temporary Works from and to the Siteshall be limited, as far as reasonably possible, and sothat no unnecessary damage or injury may be occa-sioned to such roads and bridges.

The basic principle expressed in this Sub-Clause is that the Contractor is required touse all reasonable care and means to prevent damage to roads or bridges due to excep-tional loads or intense traffic, whether the transported goods are materials, Plant, Con-tractor's Equipment or Temporary Works.

Transportof 30.2 Save insofar as the Contract otherwise provides, theContractor's Contractor shall be responsible for and shall pay the

Equipmentor cost of strengthening any bridges or altering or improv-Temporary ing any road communicating with or on the routes to the

Works Site to facilitate the movement of the Contractor'sEquipment or Temporary Works and the Contractorshall indemnify and keep indemnified the Employeragainst all claims for damage to any such road orbridge caused by such movement, including such claimsas may be made directly against the Employer, and shallnegotiate and pay all claims arising solely out of suchdamage.

In the case of transportation of Contractor's Equipment and/or Temporary Works, ordi-narily the Contractor shall pay any extra cost as well as indemnify the Employer againstany claims arising therefrom.

82 © FIDIC 1989

Page 83: 35824401 FIDIC Guide to the Use of FIDIC

Transport of 30.3 If, notwithstanding Sub-Clause 30.1, any damage occursMaterialsor to any bridge or road communicating with or on the

Plant routes to the Site arising from the transport of materi-als or Plant, the Contractor shall notify the Engineerwith a copy to the Employer, as soon as he becomesaware of such damage or as soon as he receives anyclaim from the authority entitled to make such claim.Where under any law or regulation the haulier of suchmaterials or Plant is required to indemnify the roadauthority against damage the Employer shall not beliable for any costs, charges or expenses in respectthereof or in relation thereto. In other cases the Em-ployer shall negotiate the settlement of and pay all sumsdue in respect of such claim and shall indemnify theContractor in respect thereof and in respect of allclaims, proceedings, damages, costs, charges and ex-penses in relation thereto. Provided that if and so faras any such claim or part thereof is, in the opinion ofthe Engineer, due to any failure on the part of theContractor to observe and peiform his obligations underSub-Clause 30.1, then the amount, determined by theEngineer, after due consultation with the Employer andthe Contractor, to be due to such failure shall be recov-erable from the Contractor by the Employer and may bededucted by the Employer from any monies due or tobecome due to the Contractor and the Engineer shallnotify the Contractor accordingly, with a copy to theEmployer. Provided also that the Employer shall notifythe Contractor whenever a settlement is to be negotiatedand, where any amount may be due from the Contrac-tor, the Employer shall consult with the Contractorbefore such settlement is agreed.

For the transportation of materials and/or Plant, if any law or regulation requires thehaulier to be responsible for any damage or additional cost due to transport thereof, theEmployer shall not be liable. In all other cases, because materials for the PermanentWorks and Plant are specified in the Contract and are not solely at the choice of theContractor, the Employer shall meet the costs and negotiate the settlement except thatthe Contractor shall repay such parts thereof which could have been avoided with rea-sonable care (see Sub-Clause 30.1). Subject always that he shall be consulted prior toany negotiated settlement.

Waterborne 30.4 Where the nature of the Works is such as to require theTraffic use by the Contractor of waterborne transport the fore-

going provisions of this Clause shall be construed asthough "road" included a lock, dock, sea wall or otherstructure related to a waterway and "vehicle" includedcraft, and shall have effect accordingly.

This Sub-Clause imposes similar conditions on waterborne traffic to those relevant toroad transport.

©FIDIC 1989 83

Page 84: 35824401 FIDIC Guide to the Use of FIDIC

Opportunities 31.1 The Contractor shall, in accordance with the require-for Other ments of the Engineer, afford all reasonable opportuni-

Contractors tiesfor carrying out their work to:

(a) any other contractors employed by the Employer andtheir workmen,

(b) the workmen of the Employer, and

(c) the workmen of any duly constituted authorities whomay be employed in the execution on or near the Site ofany work not included in the Contract or of any contractwhich the Employer may enter into in connection withor ancilliary to the Works.

In the case of a complex project, it is not unusual for several contractors of the Employer,workmen of the Employer and, sometimes, workmen from one or more public authori-ties to be engaged in the execution of the project on the Site simultaneously. In suchcases, each contractor of the Employer must allow the others working on the Sitereasonable opportunities for working in accordance with the overall plan for theproject and this obligation should be clearly stated in the tender documents. In orderthat each contractor can properly pian his particular work, the tender documents for eachcontract should give maximum information on all other activities which will be goingon at the Site at the same time.

Where the particular requirements of other contractors are known within reasonable limitsat the time of preparation of the Contract documents, details must be stated. The Speci-fication is usually the appropriate place to do so but, exceptionally, some reference maybe desirable in the Conditions. In that case, an additional Sub-Clause or Sub-Clauses canbe added to this Clause in Part II.

Facilities 31.2 If, however, pursuant to Sub-Clause 31.1 the Contrac-forOther tor shall, on the written request of the Engineer:

Contractors(a) make available to any such contractor, or to theEmployer or any such authority, any roads or ways forthe maintenance of which the Contractor is responsible,or

(b) permit the use, by any such, of Temporary Works orContractor's Equipment on the Site, or

(c) provide any other service of whatsoever nature forany such,

the Engineer shall determine an addition to the ContractPrice in accordance with Clause 52 and shall notify theContractor accordingly, with a copy to the Employer.

In a project with more than one organisation present on the Site at any one time it ispreferable to include in the scope of work of one of the contracts, responsibility forproviding necessary facilities and services to contractors under other contracts. Suchfacilities and services may include housing, water, sewage, electricity, compressedair, use of temporary roads, scaffolding, cranes, storage facilities, office accommo-dation, hospital beds and medical attention, radio communication and telephone, work-shop services, etc.

84 © FIDIC 1989

Page 85: 35824401 FIDIC Guide to the Use of FIDIC

Normally the main civil works contractor is best equipped to provide the facilities andservices required. It is important that the nature and extent of the responsibility forservices as well as the rates and prices therefor are clearly established so that boththe supplier and the users can make appropriate allowances in their tenders.

Contractor to 32.1 During the execution of the Works the Contractor shallKeep Site keep the Site reasonably free from all unnecessary ob-

Clear struction and shall store or dispose of any Contractor'sEquipment and surplus materials and clear away andremove from the Site any wreckage, rubbish or Tempo-rary Works no longer required.

It is in the best interests of all concerned and particularly in respect of their safety thatthe Site shall be free of unnecessary obstruction and that the Contractor's Equipment,materials and stores of every sort are maintained in a secure and orderly manner.

Clearance of 33.1 Upon the issue of any Taking-Over Certificate the Con-Site on tractor shall clear away and remove from that part of

Completion the Site to which such Taking-Over Certificate relatesall Contractor's Equipment, surplus material, rubbishand Temporary Works of every kind, and leave such partof the Site and Works clean and in a workmanlikecondition to the satisfaction of the Engineer. Providedthat the Contractor shall be entitled to retain on Site,until the end of the Defects Liability Period, such mate-rials, Contractor's Equipment and Temporary Works asare required by him for the purpose of fulfilling hisobligations during the Defects Liability Period.

This Sub-Clause requires that on completion of any part of the Works, the Contractorclears completely the part of the Site related to the Works which have been completedso that it can be occupied by the Employer with freedom of operation. Only suchmaterials, Contractor's Equipment and Temporary Works shall be allowed to remainwhich the Contractor will need for the purpose of remedying defects. This entitlementof the Contractor should be borne in mind by the Engineer at the time of preparation ofthe tender documents and subsequently when considering the Contractor's methods ofoperation.

The Clause may be amplified or amended in Part II in the event that the Employer wishesto take over part of the Temporary Works and should state the conditions for such takingover. The state of repair of such Temporary Works should then be stipulated in theSpecification.

© FIDIC 1989 85

Page 86: 35824401 FIDIC Guide to the Use of FIDIC

LABOUR

Engagement of 34.1 The Contractor shall, unless otherwise provided in theStaffand Contract, make his own arrangements for the engage-

Labour ment of all staff and labour, local or other, and for theirpayment, housing, feeding and transport.

This Sub-Clause in Part I is drawn in very general terms and requires elaboration inPart II or in the Specification combined with items included in the Bill of Quantities.The provision of housing and amenities generally on the Site is frequently the cause ofargument if the Contract is not explicit in the first instance. It is particularly dif-ficult if there are no established standards for housing and amenities within the coun-try in which the Works are being executed. The Employer and the Engineer shouldtogether decide what is necessary, before inviting tenders, and the Specification shouldinclude a detailed description of facilities which the Contractor is to provide for the useof the Employer and the Engineer and of the minimum standards he must observe inproviding facilities for his own staff and labour, for Subcontractors and other contrac-tors (see the commentary on Clause 31).

In setting the requirements as to the facilities which the Contractor should provide, itshould be observed that such facilities are normally of a temporary nature. If,however, the Employer wishes to take over part of the facilities upon completion ofthe Works, the conditions therefor should be specified in the Contract. Where suchfacilities are to become part of the Permanent Works, this should be clearly specified.

As stated above, the Part I Clause is drawn in general terms and it will normally benecessary to add a number of Sub-Clauses in Part II, to take account of the circum-stances and locality of the Works, covering such matters as: permits and registrationof expatriate employees; repatriation to place of recruitment; provision of tempo-rary housing for employees; requirements in respect of accommodation for staff ofEmployer and Engineer; standards of accommodation to be provided; provision ofaccess roads, hospital, school, power, water, drainage, fire services, refuse collection,communal buildings, shops, telephones; hours and conditions of working; rates of pay;compliance with labour legislation; maintenance of records of safety and health.

The following are example sub-clauses covering some of the more usual provi-sions. They should be adapted and supplemented in accordance with the requirementsof the project and the locality of the Works:

Rates of 34. The Contractor shall pay rates of wages and observeWages and conditions of labour not less favourable than those es-Conditions tablished for the trade or industry where the work is

of Labour being carried out. In the absence of any rates of wagesor conditions of labour so established, the Contractorshall pay rates of wages and observe conditions oflabour which are not less favourable than the generallevel of wages and conditions observed by other em-ployers whose general circumstances in the trade orindustry in which the Contractor is engaged are similar.

Employment 34. The Contractor shall not recruit or attempt to recruit hisof Persons staff and labour from amongst persons in the service of

in the Service the Employer or the Engineer.of Others

86 © FIDIC 1989

Page 87: 35824401 FIDIC Guide to the Use of FIDIC

Repatriation 34. The Contractor shall be responsible for the return to theof Labour place where they were recruited or to their domicile of

all such persons as he recruited and employed for thepurposes of or in connection with the Contract and shallmaintain such persons as are to be so returned in a suit-able manner until they shall have left the Site or, in thecase of persons who are not nationals of and have beenrecruited outside (insert name of country), shall have left(insert name of country).

Housing 34. Save insofar as the Contract otherwise provides, thefor Contractor shall provide and maintain such accommo-

Labour dation and amenities as he may consider necessary forall his staff and labour, employed for the purposes of orin connection with the Contract, including all fencing,water supply (both for drinking and other purposes),electricity supply, sanitation, cookhouses, fire preven-tion and fire-fighting equipment, air conditioning, cook-ers, refrigerators, furniture and other requirements inconnection with such accommodation or amenities. Oncompletion of the Contract, unless otherwise agreedwith the Employer, the temporary camps/housing pro-vided by the Contractor shall be removed and the Sitereinstated to its original condition, all to the approval ofthe Engineer.

Accident 34. The Contractor shall have on his staff at the Site anPrevention officer dealing only with questions regarding the safety

Officer; and protection against accidents of all staff and labour.Accidents This officer shall be qualified for this work and shall

have the authority to issue instructions and shall takeprotective measures to prevent accidents.

Health 34. Due precautions shall be taken by the Contractor, andand at his own cost, to ensure the safety of his staff and

Safety labour and, in collaboration with and to the requirementsof the local health authorities, to ensure that medicalstaff, first aid equipment and stores, sick bay and suit-able ambulance service are available at the camps,housing and on the Site at all times throughout theperiod of the Contract and that suitable arrangements aremade for the prevention of epidemics and for all neces-sary welfare and hygiene requirements.

Measures 34. The Contractor shall at all times take the necessary pre-against cautions to protect all staff and labour employed on the

Insect and Site from insect nuisance, rats and other pests and re-Pest Nuisance duce the dangers to health and the general nuisance

occasioned by the same.

© FIDIC 1989 87

Page 88: 35824401 FIDIC Guide to the Use of FIDIC

The Contractor shall provide his staff and labour withsuitable prophylactics for the prevention of malaria andtake steps to prevent the formation of stagnant pools ofwater. He shall comply with all the regulations of thelocal health authorities in these respects and shall inparticular arrange to spray thoroughly with approvedinsecticide all buildings erected on the Site. Such treat-ment shall be carried out at least once a year or as in-structed by the Engineer. The Contractor shall warn hisstaff and labour of the dangers of bilharzia and wildanimals.

Epidemics 34. In the event of any outbreak of illness of an epidemicnature, the Contractor shall comply with and carry outsuch regulations, orders and requirements as may bemade by the Government, or the local medical or sani-tary authorities, for the purpose of dealing with andovercoming the same.

Burial of 34. The Contractor shall make all necessary arrangementsthe Dead for the transport, to any place as required for burial, of

any of his expatriate employees or members of theirfamilies who may die in (insert country). The Contrac-tor shall also be responsible, to the extent required bylocal regulations, for making any arrangements withregard to burial of any of his local employees who maydie while engaged upon the Works.

Supply of 34. The Contractor shall arrange for the provision of a suf-Foodstufts ficient supply of suitable food at reasonable prices for

all his staff and labour, or his Subcontractors, for thepurposes of or in connection with the Contract.

Supply 34. The Contractor shall, so far as is reasonably practical,Water having regard to local conditions, provide on the Site an

adequate supply of drinking and other water for the useof his staff and labour.

Alcoholic 34. The Contractor shall not, otherwise than in accordanceLiquor or with the Statutes, Ordinances and Government Regula-

Drugs lions or Orders for the time being in force, import, sell,give, barter or otherwise dispose of any alcoholic liquoror drugs, or permit or suffer any such importation, sale,gift, barter or disposal by his Subcontractors, agents,staff or labour.

Arms and 34. The Contractor shall not give, barter or otherwise dis-Ammunition pose of to any person or persons, any arms or ammuni-

tion of any kind or permit or suffer the same as afore-said.

88 © FIDIC 1989

Page 89: 35824401 FIDIC Guide to the Use of FIDIC

Festivals and 34. The Contractor shall in all dealings with his staff andReligious labour have due regard to all recognised festivals, daysCustoms of rest and or other customs.

Discorderly 34. The Contractor shall at all times take all reasonableConduct precautions to prevent any unlawful, riotous or disor-

derly conduct by or amongst his staff and labour and forthe preservation of peace and protection of persons andproperty in the neighbourhood of the Works against thesame.

Attention is drawn to possible requirements for 'on the job' training of local labour underspecified guidelines. When this is required, training should be included as a separatepayment item in the Bill of Quantities.

Returnsof 35.1 The Contractor shall, if required by the Engineer, de-Labourand liver to the Engineer a return in detail, in such form and

Contractor's at such intervals as the Engineer may prescribe, show-Equipment ing the staff and the numbers of the several classes of

labour from time to time employed by the Contractor onthe Site and such information respecting Contractor'sEquipment as the Engineer may require.

This Sub-Clause requires the Contractor to provide records of staff, labour and Contrac-tor's Equipment on Site. The information may be needed for reports to local authoritiesbut also, in respect of labour, for the operation of any provision for changes in labourwages and, in respect of Contractor's Equipment, in connection with any advance paidby the Employer, or for control required by customs authorities for import on temporaryadmission.

The following example Sub-Clauses are typical of those which are frequently added inPart II:

The Contractor shall maintain such records and makesuch reports concerning safety, health and welfare ofpersons and damage to property as the Engineer mayfrom time to time prescribe.

Reporting 35. The Contractor shall report to the Engineer details ofof Accidents any accident as soon as possible after its occurrence. In

the case of any fatality or serious accident, the Contrac-tor shall, in addition, notify the Engineer immediatelyby the quickest available means.

© FIDIC 1989 89

Page 90: 35824401 FIDIC Guide to the Use of FIDIC

MATERIALS, PLANT AND WORKMANSHIP

Quality of 36.1 All materials, Plant and workmanship shall beMaterials,Plant and (a) of the respective kinds described in the Contract and

Workmanship in accordance with the Engineer's instructions, and

(b) subjected from time to time to such tests as theEngineer may require at the place of manufacture,fab-rication or preparation, or on the Site or at such otherplace or places as may be specified in the Contract, orat all or any of such places.

The Contractor shall provide such assistance, labour,electricity, fuels, stores, apparatus and instruments asare normally required for examining, measuring andtesting any materials or Plant and shall supply samplesof materials, before incorporation in the Works, fortesting as may be selected and required by the Engineer.

This Sub-Clause sets out the requirements of the Contract as to materials, Plant andworkmanship in broad outline. These need to be developed in detail in other contractdocuments, particularly in the Specification. If the Employer wishes to make referenceto the utilisation of local materials, an appropriate additional Sub-Clause should be addedin Part II.

Cost of 36,2 All samples shall be supplied by the Contractor at hisSamples own cost if the supply thereof is clearly intended by or

provided for in the Contract.

The Contractor should make provision in his tender for the cost of supplying sampleswhich are required under the Contract.

Cost of 36.3 The cost of making any test shall be borne by the Con-Tests tractor if such test is

(a) clearly intended by or provided for in the Contract,or

(b) particularised in the Contract (in cases only of a testunder load or of a test to ascertain whether the designof any finished or partially finished work is appropriatefor the purposes which it was intended to fulfil) in suf-ficient detail to enable the Contractor to price or allowfor the same in his Tender.

This Sub-Clause deals with the question of payment for the cost of carrying out teststo prove compliance with the Specification. It is necessary that the Specification shouldset out clearly and in detail the samples and tests required by the Employer or the Engi-neer.

90 © FIDIC 1989

Page 91: 35824401 FIDIC Guide to the Use of FIDIC

Cost of 36.4 If any test required by the Engineer which isTests not

Provided for (a) not so intended by or provided for, or

(b) (in the cases above mentioned) not so particularised,or

(c) (though so intended or provided for) required by theEngineer to be carried out at any place other than theSite or the place of manufacture, fabrication or prepa-ration of the materials or Plant tested,

shows the materials, Plant or workmanship not to be inaccordance with the provisions of the Contract to thesatisfaction of the Engineer, then the cost of such testshall be borne by the Contractor, but in any other caseSub-Clause 36.5 shall apply.

The Engineer may require the Contractor to carry out tests other than those stated inthe Specification and the Contractor is obliged to carry out such tests but if the tests donot reveal the Contractor's work to be deficient the Contractor will not have to bear thecosts of carrying out such tests.

Engineer's 36.5 Where, pursuant to Sub-Clause 36.4, this Sub-ClauseDetermination applies the Engineer shall, after due consultation with

where Tests the Employer and the Contractor, determine:notProvided .

for (a) any extension of time to which the Contractor isentitled under Clause 44, and

(b) the amount of such costs, which shall be added tothe Contract Price,

and shall notfy the Contractor accordingly, with a copyto the Employer.

This Sub-Clause enables the Engineer, after consultation with the Employer and theContractor, to determine to what additional cost and extension of time the Contractorshall be entitled in respect of tests additional to those specified in the Contract.

Inspectionof 37.1 The Engineer, and any person authorised by him, shallOperations at all reasonable times have access to the Site and to

all workshops and places where materials or Plant arebeing manufactured, fabricated or prepared for theWorks and the Contractor shall afford every facility forand every assistance in obtaining the right to suchaccess.

Sub-Clause 37.1 is included to ensure that persons carrying out inspection of the Worksare properly authorised to do so. Control is necessary on those who visit the Site bothfor reasons of safety and to avoid any unnecessary disruption of progress of the Works.

Authorised persons for the purpose of this Sub-Clause may be the Engineer, the Engi-neer's Representative, any assistant appointed under Sub-Clause 2.4 or any personauthorised by the Engineer. The latter would include representatives of the Employer.

© FIDIC 1989 91

Page 92: 35824401 FIDIC Guide to the Use of FIDIC

Inspection 37.2 The Engineer shall be entitled, during manufacture,fab-and Testing rication or preparation to inspect and test the materials

and Plant to be supplied under the Contract. If materi-als or Plant are being manufactured, fabricated orprepared in workshops or places other than those of theContractor, the Contractor shall obtain permission forthe Engineer to carry out such inspection and testing inthose workshops or places. Such inspection or testingshall not release the Contractor from any obligationunder the Contract.

This Sub-Clause provides for inspection and testing, by authorised persons, of materialsand Plant which are to be components of the Works. Such inspection and testing maytake place in the Contractor's premises on or off the Site, or in any other premises. It isthis Sub-Clause that authorises inspection and testing of Plant being manufactured incountries other than that of the Contractor or the country where the Works are beingexecuted.

Dates for 37.3 The Contractor shall agree with the Engineer on theInspection time and place for the inspection or testing of any

and Testing materials or Plant as provided in the Contract. TheEngineer shall give the Contractor not less than 24hours notice of his intention to carry out the inspectionor to attend the tests. If the Engineer, or his duly au-thorised representative, does not attend on the dateagreed, the Contractor may, unless otherwise instructedby the Engineer, proceed with the tests, which shall bedeemed to have been made in the presence of the Engi-neer. The Contractor shall forthwith forward to theEngineer duly certified copies of the test readings. If theEngineer has not attended the tests, he shall accept thesaid readings as accurate.

Arrangements will have to be made for times and dates of tests and it is necessary thathaving made such arrangements they are adhered to unless alternative arrangements areagreed between the Contractor and the Engineer. Sub-Clause 37.3 states the procedurein the event that the Engineer is not represented at any pre-arranged test.

Rejection 37.4 If, at the time and place agreed in accordance with Sub-Clause 37.3, the materials or Plant are not ready forinspection or testing or if, as a result of the inspectionor testing referred to in this Clause, the Engineer deter-mines that the materials or Plant are defective or oth-erwise not in accordance with the Contract, he mayreject the materials or Plant and shall notify the Con-tractor thereof immediately. The notice shall state theEngineer's objections with reasons. The Contractorshall then promptly make good the defect or ensure thatrejected materials or Plant comply with the Contract. If

92 © FIDIC 1989

Page 93: 35824401 FIDIC Guide to the Use of FIDIC

the Engineer so requests, the tests of rejected materialsor Plant shall be made or repeated under the sameterms and conditions. All costs incurred by the Employerby the repetition of the tests shall, after due consulta-tion with the Employer and the Contractor, be deter-mined by the Engineer and shall be recoverable from theContractor by the Employer and may be deducted fromany monies due or to become due to the Contractor andthe Engineer shall notify the Contractor accordingly,with a copy to the Employer.

The previous Sub-Clause dealt with non-attendance by the Engineer. This Sub-Clausedeals with the situation where the Contractor is not ready on the pre-arranged date. TheSub-Clause also deals with the consequences of unsatisfactory test results.

Independent 37.5 The Engineer may delegate inspection and testing ofInspection materials or Plant to an independent inspector. Any

such delegation shall be effected in accordance withSub-Clause 2.4 and for this purpose such independentinspector shall be considered as an assistant of theEngineer. Notice of such appointment (not being lessthan 14 days) shall be given by the Engineer to theContractor.

This Sub-Clause should be read in conjunction with Sub-Clause 37.2 and will usuallyapply when the tests are to be carried out on materials or Plant being supplied from athird country.

Examination 38.1 No part of the Works shall be covered up or put out ofofWork view without the approval of the Engineer and the

before Contractor shall afford full opportunity for the EngineerCovering up to examine and measure any such part of the Works

which is about to be covered up or put out of view andto examine foundations before any part of the Works isplaced thereon. The Contractor shall give notice to theEngineer whenever any such part of the Works orfoun-dations is or are ready or about to be ready for exami-nation and the Engineer shall, without unreasonabledelay, unless he considers it unnecessary and advisesthe Contractor accordingly, attend for the purpose ofexamining and measuring such part of the Works or ofexamining such foundations.

Arrangements must exist for the Engineer to inspect work which is to be covered up.This Sub-Clause stipulates that work shall not be covered up before the Engineer hashad an opportunity to examine and measure it, and the Contractor has the obligation tocall upon the Engineer for that purpose. The Contractor should not be unreasonablydelayed in proceeding with his work because of delay by the Engineer in carrying outthis task and the Engineer is obliged by the Conditions to attend without undue delay.

©FIDIC 1989 93

Page 94: 35824401 FIDIC Guide to the Use of FIDIC

Uncovering 38.2 The Contractor shall uncover any part of the Works orandMaking make openings in or through the same as the Engineer

Openings may from time to time instruct and shall reinstate andmake good such part. If any such part has been coveredup or put out of view after compliance with the require-ment of Sub-Clause 38.1 and is found to be executed inaccordance with the Contract, the Engineer shall, afterdue consultation with the Employer and the Contractor,determine the amount of the Contractor's costs in re-spect of such of uncovering, making openings in orthrough, reinstating and making good the same, whichshall be added to the Contract Price, and shall notifythe Contractor accordingly, with a copy to the Em-ployer. In any other case all costs shall be borne by theContractor.

The Engineer may require, as a consequence of later discovery, that work already cov-ered up be uncovered and inspected and tested. Sub-Clause 38.2 specifies under whatcircumstances payment will be made to the Contractor for extra work which this open-ing up has incurred.

Removal of 39.1 The Engineer shall have authority to issue instructionsImproper Work, from time to time, for:

Materials or . .

Plant (a) the removal from the Site, within such time or timesas may be specified in the instruction, of any materialsor Plant which, in the opinion of the Engineer, are notin accordance with the Contract.

(b) the substitution of proper and suitable materials orPlant, and

(c) the removal and proper re-execution, notwithstand-ing any previous test thereof or interim payment there-for, of any work which, in respect of

(i) materials, Plant or workmanship, or

(ii) design by the Contractor or for which he is responsible,

is not, in the opinion of the Engineer, in accordance withthe Contract.

The Contractor is required to remove faulty materials, Plant and work and to replace thesame at his own cost. The Engineer, in giving his instructions, would be wise to relyon tests or other objective criteria, as well as to specify a reasonable time for the Con-tractor to act, as sanctions are provided under Sub-Clause 39.2 if the Contractor doesnot act within the time specified by the Engineer or, if no time is specified, within areasonable time.

94 © FIDIC 1989

Page 95: 35824401 FIDIC Guide to the Use of FIDIC

As far as case (c) of Sub-Clause 39.1 is concerned, the situation in practice will be morecomplex. Generally, the failure of any work to meet the requirements of the Contract,whether in terms of materials, Plant or workmanship, or whether in terms of designprovided by the Contractor, will have been disclosed in tests, e.g., a faulty casting, in-sufficient packing of layers in an earth dam, a deflection of a precast beam. In suchcases removal will be a minor impediment, and would have been provided for to a certainextent in the programme. On the other hand, when tests have shown no failure, interimpayment has been made and work has proceeded normally, and only at a later stage isit realised that the work fails to meet the requirements of the Contract, bearing in mindthe provisions of Sub-Clause 2.1(c), the Engineer should investigate with the parties tothe Contract whether an acceptable solution can be found on the basis of redesign andadjustment of payment. The instructions to remove the faulty work should, in suchcase, be an exceptional remedy and, again, the Engineer should specify a reasonable timefor the Contractor to act.

Defaultof 39,2 In case of default on the part of the Contractor in car-Contractor in rying out such instruction within the time specified

Compliance therein or, if none, within a reasonable time, the Em-ployer shall be entitled to employ and pay other personsto carry out the same and all costs consequent thereonor incidental thereto shall, after due consultation withthe Employer and the Contractor, be determined by theEngineer and shall be recoverable from the Contractorby the Employer, and may be deducted by the Employerfrom any monies due or to become due to the Contrac-tor and the Engineer shall notify the Contractor accord-ingly, with a copy to the Employer.

The sanction contained in this Sub-Clause is included to protect the Employer in casethe Contractor refuses to comply with an instruction of the Engineer under Sub-Clause39.1.

© FIDIC 1989 95

Page 96: 35824401 FIDIC Guide to the Use of FIDIC

SUSPENSION

Suspension 40.1 The Contractor shall, on the instructions of the Engi-ofWork neer, suspend the progress of the Works or any part

thereof for such time and in such manner as the Engi-neer may consider necessary and shall, during suchsuspension, properly protect and secure the Works orsuch part thereof so far as is necessary in the opinionof the Engineer. Unless such suspension is

(a) otherwise provided for in the Contract, or

(b) necessary by reason of some default of or breach ofcontract by the Contractor or for which he is respon-sible, or

(c) necessary by reason of climatic conditions on theSite, or

(d) necessary for the proper execution of the Works orfor the safety of the Works or any part thereof (save tothe extent that such necessity arises from any act ordefault by the Engineer or the Employer or from any ofthe risks defined in Sub-Clause 20.4),

Sub-Clause 40.2 shall apply.

This Sub-Clause describes the Engineer's authority to suspend the progress of the Worksand indicates the circumstances in which the Contractor will be considered respon-sible for the suspension.

For a Contract comprising dredging and some types of reclamation work the Sub-Clausemay be varied in Part II as follows:

Suspension 40.1 Delete paragraph (c) and renumber paragraph (d) as (c).of Work

Engineer's 40.2 Where, pursuant to Sub-Clause 40.1, this Sub-ClauseDetermination applies the Engineer shall, after due consultation with

following the Employer and the Contractor, determineSuspension

(a) any extension of time to which the Contractor isentitled under Clause 44, and

(b) the amount, which shall be added to the ContractPrice, in respect of the cost incurred by the Contractorby reason of such suspension,

and shall notify the Contractor accordingly, with a copyto the Employer.

This Sub-Clause authorises the Engineer, after consultation with the Employer and theContractor, to determine what extension of time and/or extra costs the Contractor shallbe entitled to receive if he is not responsible for the suspension.

96 © FIDIC 1989

Page 97: 35824401 FIDIC Guide to the Use of FIDIC

Suspension 40.3 If the progress of the Works or any part thereof is sus-lastingmore pended on the written instructions of the Engineer andthan 84 days ifpermission to resume work is not given by the Engi-

neer within a period of 84 days from the date of suspen-sion then, unless such suspension is within paragraph(a), (b), (c) or (d) of Sub-Clause 40.1, the Contractormay give notice to the Engineer requiring permission,within 28 days from the receipt thereof, to proceed withthe Works or that part thereof in regard to which pro g-ress is suspended. If, within the said time, such permis-sion is not granted, the Contractor may, but is not boundto, elect to treat the suspension, where it affects partonly of the Works, as an omission of such part underClause 51 by giving a further notice to the Engineer tothat effect, or, where it affects the whole of the Works,treat the suspension as an event of default by the Em-ployer and terminate his employment under the Contractin accordance with the provisions of Sub-Clause 69.1,whereupon the provisions of Sub-Clauses 69.2 and 69.3shall apply.

This Sub-Clause provides that if the progress of the Works or any part thereof is sus-pended for 84 days then, unless the Contractor is responsible for the suspension, theContractor may, by notice to the Engineer, require permission, within 28 days, to pro-ceed. If such permission is not granted, the Contractor may elect to treat the suspendedwork as omitted or, where all work has been suspended, treat the Contract as repudiated.

For a Contract comprising dredging and some types of reclamation work this Sub-Clause may be varied in Part II as follows:

Suspension 40.3 In the first sentence delete the words ",(c) or (d)" andlasting more substitute "or (c)".than 84 days

© FIDIC 1989 97

Page 98: 35824401 FIDIC Guide to the Use of FIDIC

COMMENCEMENT AND DELAYS

Commencement 41.1 The Contractor shall commence the Works as soon asofWorks is reasonably possible after the receipt by him of a

notice to this effect from the Engineer, which noticeshall be issued within the time stated in the Appendix toTender after the date of the Letter of Acceptance. There-after, the Contractor shall proceed with the Works withthe due expedition and without delay.

The Appendix to Tender specifies a time period after the date of the Letter of Accep-tance within which the Engineer is to send to the Contractor a notice to commence. Thisnotice should be sent, against receipt, to the Contractor's principal place of business (seeClause 68). Under Sub-Clause 41.1 the Contractor undertakes to commence the Worksas soon as is reasonably possible after the date upon which he receives this notice. Thisdate is the Commencement Date defined in Sub-Clause 1.1(c) (i), and the Time forCompletion is calculated from the Commencement Date (see Sub-Clause 43.1).

The wording of Sub-Clause 41.1 is consistent with paragraph 3 of the form of Tender.

The time limit for sending the notice to commence is important as the Contractor mayhave prior commitments from Subcontractors, suppliers or others, who may request priceincreases if orders cannot be executed promptly. Moreover, before such notice is sentthe Employer must be in possession of the Site and have clear access to it, as well ashaving other legal and financial formalities completed in accordance with an establishedprogramme. It is particularly important that the Employer is able to comply with anyobligation to make advance payments to the Contractor. It is helpful for the Engineer togive his client advice on such matters.

When, for a particular project, the Employer has to comply with certain legal or admin-istrative procedures e.g. ratification of the Contract by a political body or the approvalof a Board, the allocation of a budget (which may affect subsequent budget periods), theprovision of import licences before the Contract is validly established or before the noticeto commence can be given, this should be stated in the tender documents.

Any additional Sub-Clauses relating to commencement should be added in Part II.

Sub-Clause 41.1 should be read in conjunction with Clauses 26 and 42.

Possession of 42.1 Save insofar as the Contract may prescribe:Site and Access

Thereto (a) the extent of portions of the Site of which the Con-tractor is to be given possession from time to time, and

(b) the order in which such portions shall be madeavailable to the Contractor

and subject to any requirement in the Contract as to theorder in which the Works shall be executed, the Em-ployer will, with the Engineer's notice to commence theWorks, give to the Contractor possession of

(c) so much of the Site, and

98 © FIDIC 1989

Page 99: 35824401 FIDIC Guide to the Use of FIDIC

(d) such access as, in accordance with the Contract, isto be provided by the Employer

as may be required to enable the Contractor to com-mence and proceed with the execution of the Works inaccordance with the programme referred to in Clause14, if any, and otherwise in accordance with such rea-sonable proposals as the Contractor shall, by notice tothe Engineer with a copy to the Employer, make. TheEmployer will, from time to time as the Works proceed,give to the Contractor possession of such further por-tions of the Site as may be required to enable the Con-tractor to proceed with the execution of the Works withdue dispatch in accordance with such programme orproposals, as the case may be.

The Contractor is given possession of the Site only for the purpose of carrying out theWorks, and his occupation of the Site is subject to the terms of the Contract.

Failure to 42.2 Ifthe Contractor suffers delay and/or incurs costs fromGive failure on the part of the Employer to give possession

Possesion in accordance with the terms of Sub-Clause 42.1, theEngineer shall, after due consultation with the Employerand the Contractor, determine:

(a) any extension of time to which the Contractor isentitled under Clause 44, and

(b) the amount of such costs, which shall be added tothe Contract Price,

and shall notify the Contractor accordingly, with a copyto the Employer.

The Employer must give the Contractor possession of the Site (or portions thereof whereappropriate) at the same time as the Engineer gives the notice to commence the Workspursuant to Clause 41. Delay may result in deferral of the date when the Works reachsubstantial completion and also in extra cost to the Employer.

Wayleavesand 42.3 The Contractor shall bear all costs and charges forFacilities special or temporary wayleaves required by him in con-

nection with access to the Site. The Contractor shall alsoprovide at his own cost any additional facilities outsidethe Site required by him for the purposes of the Works.

If the Contractor requires any special arrangements, e.g. for transporting exceptionallyheavy equipment, the Contractor shall bear all costs and charges related thereto.

© FIDIC 1989 99

Page 100: 35824401 FIDIC Guide to the Use of FIDIC

Time for 43.1 The whole of the Works and, if applicable, any SectionCompletion required to be completed within a particular time as

stated in the Appendix to Tender, shall be completed, inaccordance with the provisions of Clause 4, within thetime stated in the Appendix to Tender for the whole ofthe Works or the Section (as the case may be), calcu-lated from the Commencement Date, or such extendedtime as may be allowed under Clause 44.

This Sub-Clause links Time for Completion with Taking Over under Clause 48. It shouldbe read in conjunction with the form of Tender, the Appendix to Tender and with Clause47 which deals with liquidated damages and bonuses, if any.

Attention is particularly drawn to the possible need for defining Sections of the Works,see Sub-Clause 1.1 .(f)(vi) and for drafting corresponding provisions for completion andliquidated damages and bonuses (if any), in the Appendix to Tender.

Where completion is stated to be by a date and not within a period of time, this Sub-Clause will need to be varied in Part II. The following is an example of appropriatewording:

Time for 43.1 Delete the words "within the time...such extended time"Completion and substitute "by the date or dates stated in the Ap-

pendix to Tender for the whole of the Works or theSection (as the case may be) or such later date or dates".

Extension of 44.1 In the event of

Completion (a) the amount or nature of extra or additional work, or

(b) any cause of delay referred to in these Conditions,or

(c) exceptionally adverse climatic conditions, or

(d) any delay, impediment or prevention by the Em-ployer, or

(e) other special circumstances which may occur, otherthan through a default of or breach of contract by theContractor or for which he is responsible,

being such as fairly to entitle the Contractor to an ex-tension of the Time for Completion of the Works, or anySection or part thereof, the Engineer shall, after dueconsultation with the Employer and the Contractor, de-termine the amount of such extension and shall notifythe Contractor accordingly, with a copy to the Em-ployer.

The granting of an extension of time, to which the Contractor may become entitled, mightarise from such factors as delay in obtaining possession of the Site (Clause 42), delayin the issue of drawings or instructions (Clause 6), adverse physical obstructions orconditions (Clause 12), suspensions (Clause 40), extra work (Clause 51) or damage ordelays to the Works (Clauses 20 and 65).

100 © FIDIC 1989

Page 101: 35824401 FIDIC Guide to the Use of FIDIC

As liquidated damages and bonuses (if any) are affected, it is important that, when-ever an extension of time is granted, a new completion date is clearly established tosupersede the completion date established in accordance with Clause 43.

Although the granting of an extension of time does not necessarily entail extra cost tothe Employer, the effects of delay may entitle the Contractor to extra payment -see forexample Sub- Clauses 6.4 and 42.2.

The granting of an extension of time is based on the Engineer's interpretation of theContract and his assessment of the circumstances involved during the execution of theWorks and the basis for the claim stated by the Contractor in his notification. It shouldbe noted that the Engineer makes his determination after consultation with the Employerand the Contractor.

Contractor to 44.2 Provided that the Engineer is not bound to make anyProvide determination unless the Contractor has

Notificationand Detailed (a) within 28 days after such event has first arisen no-

Particulars tified the Engineer with a copy to the Employer, and

(b) within 28 days, or such other reasonable time asmay be agreed by the Engineer, after such not ifi cationsubmitted to the Engineer detailed particulars of anyextension of time to which he may consider himselfentitled in order that such submission may be investi-gated at the time.

It is important that the events which may give rise to an entitlement to an extension aredealt with as and when they occur and can be identified and investigated. The require-ment of notification and the submission of particulars has therefore been expanded inthe fourth edition. This requirement further underlines the necessity of good commu-nication and understanding between the Employer, the Engineer and the Contractor, aswell as the importance of the Engineer's role in acting in an impartial and unbiasedmanner as required by Sub-Clause 2.6 of these Conditions.

Interim 4.3 Provided also that where an event has a continuingDetermination effect such that it is not practicable for the Contractor

ofExtension to submit detailed particulars within the period of 28days referred to in Sub-Clause 44.2(b), he shall never-theless be entitled to an extension of time provided thathe has submitted to the Engineer interim particulars atintervals of not more than 28 days and final particularswithin 28 days of the end of the effects resulting fromthe event. On receipt of such interim particulars, the En-gineer shall, without undue delay, make an interim de-termination of extension of time and, on receipt of thefinal particulars, the Engineer shall review all the cir-cumstances and shall determine an overall extension oftime in regard to the event. In both such cases theEngineer shall make his determination after due consul-tation with the Employer and the Contractor and shall

© FIDIC 1989 101

Page 102: 35824401 FIDIC Guide to the Use of FIDIC

notify the Contractor of the determination, with a copyto the Employer. No final review shall result in a de-crease of any extension of time already determined bythe Engineer.

Events entitling a Contractor to an extension of time may be continuing, in which casedetailed particulars can only be established during a longer period than is envisaged inSub-Clause 44.2. Sub-Clause 44.3 provides for the submission of interim particulars atintervals. This implies that contemporary records will be available when the claim iseventually finalised.

Restriction 45.1 Subject to any provision to the contrary contained in theon Working Contract, none of the Works shall, save as hereinafter

Hours provided, be carried on during the night or on locallyrecognised days of rest without the consent of the Engi-neer, except when work is unavoidable or absolutelynecessary for the saving of life or property or for thesafety of the Works, in which case the Contractor shallimmediately advise the Engineer. Provided that theprovisions of this Clause shall not be applicable in thecase of any work which it is customary to carry out bymultiple shifts.

This Sub-Clause stipulates that the Contractor will ordinarily plan to execute the Worksduring normal working hours at the Site. It recognises, however, that some work willhave to go on more or less continuously, when it is unavoidable or when required forsafety reasons or custom, e.g. construction of a cofferdam during a critical period, drain-age and dewatering, underground excavation work, maintenance and repair of Contrac-tor's Equipment. This Sub-Clause should be read in conjunction with the Contrac-tor's obligation to avoid nuisance in accordance with Clause 19. The Contractor isrequired to obtain the Engineer's consent to work other than during normal workinghours (Clause 46).

For a Contract located in an area, where environmental restrictions do not apply, orwhere a Contract comprises work such as dredging and reclamation that mayrequire continuous working, the Clause may need to be varied in Part II as follows:

Working 45.1 Delete Sub-Clause 45.1 and substitute:Hours

Subject to any provision to the contrary contained in theContract, the Contractor shall have the option to workcontinuously by day and by night and on locally recog-nised days of rest.

The Contractor's option may be further extended by substituting, in place of the last threewords in the above example Sub-clause:

holidays or days of rest.

Rate of 46.1 Iffor any reason, which does not entitle the ContractorProgress to an extension of time, the rate of progress of the Works

or any Section is at any time, in the opinion of theEngineer, too slow to comply with the Time for Com-pletion, the Engineer shall so notify the Contractor whoshall thereupon take such steps as are necessary, sub-ject to the consent of the Engineer, tc expedite progress

102 © FIDIC 1989

Page 103: 35824401 FIDIC Guide to the Use of FIDIC

so as to comply with the Time for Completion. TheContractor shall not be entitled to any additional pay-ment for taking such steps. If, as a result of any noticegiven by the Engineer under this Clause, the Contrac-tor considers that it is necessary to do any work at nightor on locally recognised days of rest, he shall be entitledto seek the consent of the Engineer so to do. Providedthat if any steps, taken by the Contractor in meeting hisobligations under this Clause, involve the Employer inadditional supervision costs, such costs shall, after dueconsultation with the Employer and the Contractor, bedetermined by the Engineer and shall be recoverablefrom the Contractor by the Employer, and may be de-ducted by the Employer from any monies due or tobecome due to the Contractor and the Engineer shallnotify the Contractor accordingly, with a copy to theEmployer.

This Sub-Clause deals with the case where the Contractor is not maintaining progressadequately to achieve timely completion and is not entitled to an extension of time.Notice under this Sub-Clause is generally a prerequisite to invoking Sub-Clause 63.1 (d).

Provision is also made in Sub-Clause 46.1 that any additional supervision costs incurredby the Employer due to steps taken by the Contractor to expedite progress pursuant toa notification by the Engineer may be recovered by the Employer from the Contractor.

Liquidated 47.1 Ifthe Contractor fails to comply with the Time for Com-Damages pletion in accordance with Clause 48, for the whole of

for the Works or, if applicable, any Section within the rele-Delay vant time prescribed by Clause 43, then the Contractor

shall pay to the Employer the relevant sum stated in theAppendix to Tender as liquidated damages for suchdefault and not as a penalty (which sum shall be the onlymonies due from the Contractor for such default) forevery day or part of a day which shall elapse betweenthe relevant Time for Completion and the date stated ina Taking-Over Certificate of the whole of the Works orthe relevant Section, subject to the applicable limitstated in the Appendix to Tender. The Employer may,without prejudice to any other method of recovery,deduct the amount of such damages from any moniesdue or to become due to the Contractor. The paymentor deduction of such damages shall not relieve theContractor from his obligation to complete the Works,or from any other of his obligations and liabilities underthe Contract.

The amount of liquidated damages is determined by the Employer, before tenders areinvited, as a reasonable assessment of the actual damages which he would suffer in theevent of delay in completion of the Works. Tenderers are, therefore, aware of the natureof their commitment at the time of tendering but it is important to specify a limit on thetotal liquidated damages which can become due.

Should liquidated damages become due, deduction is made by the Employer, as providedfor in Sub-Clause 47.1.

© FIDIC 1989 103

Page 104: 35824401 FIDIC Guide to the Use of FIDIC

Reduction of 47.2 If, before the Time for Completion of the whole of theLiquidated Works or, if applicable, any Section, a Taking-Over

Damages Certificate has been issued for any part of the Works orof a Section, the liquidated damages for delay in com-pletion of the remainder of the Works or of that Sectionshall, for any period of delay after the date stated insuch Taking-Over Certificate, and in the absence ofalternative provisions in the Contract, be reduced in theproportion which the value of the part so certified bearsto the value of the whole of the Works or Section, asapplicable. The provisions of this Sub-Clause shall onlyapply to the rate of liquidated damages and shall notaffect the limit thereof.

If delay in completion does not affect the whole of the Works, arrangements for a pro-rata reduction are set out in Sub-Clause 47.2. If it is considered by the Employer that apro-rata reduction would not be equitable, alternative provisions should be included inPart II.

If the Employer can make use of the Works on early completion (that is to say if per-formance under other contracts would not prevent their use) and can adapt his financingto the circumstances, the Employer may consider making provision for a bonus to bepaid to the Contractor in case of early completion. The bonus could be related tocompletion of the whole of the Works or to any part thereof, e.g. the first generatingunit in a power station.

In the case where a bonus is to be provided for early completion of the whole of theWorks the following example Sub-Clause can be added in Part II:

Bonus for 47.3 If the Contractor achieves completion of the Works priorCompletion to the time prescribed by Clause 43, the Employer shall

pay to the Contractor a sum (insert figure) for every daywhich shall elapse between the date stated in the Tak-ing-Over Certificate in respect of the Works issued inaccordance with Clause 48 and the time prescribed inClause 43.

In the case where bonuses are provided for early completion of Sections of the Worksand details, other than dates, are given in the Specification, the following Sub-Clausecan be considered for addition in Part II:

Bonus for 47.3 Sections are required to be completed by the dates givenCompletion in the Appendix to Tender in order that such Sections

may be occupied and used by the Employer in advanceof the completion of the whole of the Works.

Details of the work required to be executed to entitle theContractor to bonus payments and the amounts of thebonuses are stated in the Specification.

For the purposes of calculating bonus payments, thedates given in the Appendix to Tender for completionof Sections are fixed and, unless otherwise agreed, noadjustments of the dates by reason of granting an exten-

104 ©FIDIC 1989

Page 105: 35824401 FIDIC Guide to the Use of FIDIC

sion of time pursuant to Clause 44 or any other Clauseof these Conditions will be allowed.

Issue of certificates by the Engineer that the Sectionswere satisfactory and complete by the dates given on thecertificates shall, subject to Clause 60, entitle the Con-tractor to the bonus payments calculated in accordancewith the Specification.

Taking-Over 48.1 When the whole of the Works have been substantiallyCertificate completed and have satisfactorily passed any Tests on

Completion prescribed by the Contract, the Contractormay give notice to that effect to the Engineer, with acopy to the Employer, accompanied by a written under-taking to finish with due expedition any outstandingwork during the Defects Liability Period. Such noticeand undertaking shall be deemed to be a request by theContractor for the Engineer to issue a Taking-OverCertificate in respect of the Works. The Engineer shall,within 21 days of the date of delivery of such notice,either issue to the Contractor, with a copy to the Em-ployer, a Taking-Over Certificate, stating the date onwhich, in his opinion, the Works were substantiallycompleted in accordance with the Contract, or give in-structions in writing to the Contractor specifying all thework which, in the Engineer's opinion, is required to bedone by the Contractor before the issue of such Certifi-cate. The Engineer shall also notify the Contractor ofany defects in the Works affecting substantial comple-tion that may appear after such instructions and beforecompletion of the Works specified therein. The Contrac-tor shall be entitled to receive such Taking-Over Cer-tificate within 21 days of completion, to the satisfactionof the Engineer, of the Works so specified and remedy-ing any defects so notified.

This Sub-Clause sets out the procedural steps for the issue of a certificate when theWorks have been substantially completed. The question is frequently posed, 'What issubstantial completion?' It is rarely the case that when application is made for the Taking-Over Certificate there is no outstanding work at all to be completed by the Contractor.Generally speaking the Works are substantially completed when they are in such acondition that they are capable of being occupied and used by the Employer for thepurpose for which they are intended, although there areminor tasks to be completed bythe Contractor. Substantial completion can only be achieved after the Works have satis-factorily passed the Tests on Completion (if any).

The Contractor generally takes the initiative in asking for a Taking-Over Certificate forthe whole of the Works. The Certificate is issued by the Engineer provided that the extentof any outstanding work is of a minor character and the Works are capable of being usedfor the purposes for which they were intended and if the Contractor has given a writtenundertaking to finish with due expedition any such outstanding work during the DefectsLiability Period.

© FIDIC 1989 105

Page 106: 35824401 FIDIC Guide to the Use of FIDIC

The Taking-Over Certificate will confirm that the work has been substantially completed,and will include a list of outstanding items (if any) to be completed during the DefectsLiability Period. The Certificate will also establish the date on which substantial com-pletion was achieved and the Works were taken over by the Employer and the DefectsLiability Period in respect thereof began. In accordance with Sub-Clause 20.1 the respon-sibility for the care of the Works passes to the Employer on the date of issue of theTaking-Over Certificate. The Employer should prepare in good time for taking overreponsibility for the Works and arrange insurance if he wishes to do so.

It should be noted that, other than in Sub-Clause 62.1 which refers to completion of theContract, all other clauses refer to completion of the Works in terms of Clause 48.

Taking Over 48.2 Similarly, in accordance with the procedure set out inofSections Sub-Clause 48.1, the Contractor may request and the

orParts Engineer shall issue a Taking-Over Certificate in re-spect of:

(a) any Section in respect of which a separate Time forCompletion is provided in the Appendix to Tender, or

(b) any substantial part of the Permanent Works whichhas been both completed to the satisfaction of the Engi-neer and, otherwise than as provided for in the Con-tract, occupied or used by the Employer, or

(c) any part of the Permanent Works which the Em-ployer has elected to occupy or use prior to completion(where such prior occupation or use is not provided forin the Contract or has not been agreed by the Contrac-tor as a temporary measure).

The Appendix to Tender may specify different completion dates for various Sections ofthe Works and in this event the Contractor may apply for a Taking-Over Certificate fora completed Section or Sections. Similarly, the Contractor may apply for a Taking-OverCertificate for a substantial part of the Permanent Works which have been completedand occupied or used by the Employer. The provisions for the issue of a Taking-OverCertificate will apply to a Section or part in the same way as to the whole of the Worksin Sub-Clause 48.1.

If the Employer should elect to take over or use a part of the Works prior to completionsimilar arrangements apply.

Substantial 48.3 If any part of the Permanent Works has been substan-Cornpletion tially completed and has satisfactorily passed any Tests

ofParts on Completion prescribed by the Contract, the Engineermay issue a Taking-Over Certificate in respect of thatpart of the Permanent Works before the completion ofthe whole of the Works and, upon the issue of suchCertificate, the Contractor shall be deemed to haveundertaken to complete with due expedition any out-standing work in that part of the Permanent Worksduring the Defects Liability Period.

As stated in the commentary to Sub-Clause 48.1, the Contractor generally takes theinitiative in asking for a Taking-Over Certificate. Alternatively Sub-Clause 48.3 allows

106 © FIDIC 1989

Page 107: 35824401 FIDIC Guide to the Use of FIDIC

the Engineer to initiate action if the extent of outstanding work is of a minor characterand does not prevent the Employer from taking occupation and using the part of theWorks for its intended purpose. The Certificate is issued by the Engineer and in suchcase the Contractor is deemed to have given a written undertaking to finish with dueexpedition any outstanding work during the Defects Liability Period.

Surfaces 484 Provided that a Taking-Over Certificate given in respectRequiring of any Section or part of the Permanent Works before

Reinstatement completion of the whole of the Works shall not bedeemed to certify completion of any ground or surfacesrequiring reinstatement, unless such Taking-Over Cer-tificate shall expressly so state.

If it becomes apparent that any ground or surface requires reinstatement the fact thatthis was not stipulated in the Taking-Over Certificate will not relieve the Contractor ofhis responsibility to carry out such reinstatement at his own cost.

Sub-Clause 48.1 presupposes that the Works will normally have satisfactorily passed theTests on Completion (if any), when the Contractor makes his request, and the Engineerissues the Taking-Over Certificate. Circumstances outside the control of the Contractormay prevent the Tests on Completion from being performed. The following proposedSub-Clause 48.5 sets out a procedure to deal with such a case and it may be introducedinto the Contract if it is foreseen that such event may occur:

Prevention 48.5 If the Contractor is prevented from carrying out thefrom Tests on Completion by a cause for which the Employer

Testing or the Engineer or other contractors employed by theEmployer are responsible, the Employer shall have beendeemed to have taken over the Works on the date whenthe Tests on Completion would have been completed butfor such prevention. The Engineer shall issue a Taking-Over Certificate accordingly. Provided always that theWorks shall not be deemed to have been taken over ifthey are not substantially in accordance with the Con-tract.

If the Works are taken over under this Sub-Clause theContractor shall nevertheless carry out the Tests onCompletion during the Defects Liability Period. TheEngineer shall require the Tests to be carried out bygiving 14 days notice to the Contractor.

Any additional cost to which the Contractor may be put,in making the Tests on Completion during the DefectsLiability Period, shall be added to the Contract Price.

Other circumstances outside the control of both the Employer and the Contractor mayoccur preventing the Tests on Completion from being performed e.g., the water level ina reservoir being so low as to prevent the testing of hydraulic equipment such as gates.If such circumstances are foreseen, the first pragraph of the above example Sub-Clausemust be modified appropriately.

© FIDIC 1989 107

Page 108: 35824401 FIDIC Guide to the Use of FIDIC

DEFECTS LIABILITY

Defects 49.1 In these Conditions the expression "Defects LiabilityLiability Period" shall mean the defects liability period named

Period in the Appendix to Tender, calculated from:

(a) the date of completion of the Works certified by theEngineer in accordance with Clause 48, or

(b) in the event of more than one certificate having beenissued by the Engineer under Clause 48, the respectivedates so certified

and in relation to the Defects Liability Period the ex-pression "the Works" shall be construed accordingly.

This Sub-Clause defines the Defects Liability Period. The Defects Liability Period isusually for a period of one year but on certain projects may exceptionally be for a periodof two years or even more. The length of the Defects Liability Period will be in-serted in the Appendix to Tender.

There may be a number of Defects Liability Periods each tied to a Section or part of theWorks and linked to a Taking-Over Certificate (Clause 48).

The main purpose of the Defects Liability Period (which in previous editions was re-ferred to as the Maintenance Period) is to demonstrate under operational conditions thatthe requirements of the Contract have been complied with. During this period the Con-tractor must not only complete such outstanding items of work as are listed in the Taking-Over Certificate but also remedy any defects which appear. The Contract does notobligate the Contractor to perform operational maintenance during the Defects LiabilityPeriod, unless it is specifically included as part of the Works with an item in the Bill ofQuantities and a corresponding paragraph in the Specification, or otherwise made obvi-ous in the tender documents.

Completion 49.2 To the intent that the Works shall, at or as soon asOutstanding practicable after the expiration of the Defects Liability

Work and Period, be delivered to the Employer in the conditionRemedying required by the Contract, fair wear and tear excepted,

Defects to the satisfaction of the Engineer, the Contractor shall:

(a) complete the work, if any, outstanding on the datestated in the Taking-Over Certificate as soon as practi-cable after such date and

(b) execute all such work of amendment, reconstruction,and remedying defects, shrinkages or other faults as theEngineer may, during the Defects Liability Period orwithin 14 days after its expiration, as a result of aninspection made by or on behalf of the Engineer priorto its expiration, instruct the Contractor to execute.

108 © FIDIC 1989

Page 109: 35824401 FIDIC Guide to the Use of FIDIC

This Sub-Clause stipulates that, at the end of the Defects Liability Period, the Worksmust be ready for final delivery 'in the condition required by the Contract, fair wearand tear excepted'. Minor items may still be outstanding and the Sub-Clause allowsa further 14 days for the Engineer to issue instructions to the the Contractor to com-plete items recorded prior to the expiration of the period.

Cost of 49.3 All work referred to in Sub-Clause 49.2 (b) shall beRemedying executed by the Contractor at his own cost if the neces-

Defects shy thereof is, in the opinion of the Engineer, due to:

(a) the use of materials, Plant or workmanship not inaccordance with the Contract, or

(b) where the Contractor is responsible for the designof part of the Permanent Works, any fault in such de-sign, or

(c) the neglect or failure on the part of the Contractorto comply with any obligation, expressed or implied, onthe Contractor's part under the Contract.

If, in the opinion of the Engineer, such necessity is dueto any other cause, he shall determine an addition to theContract Price in accordance with Clause 52 and shallnotify the Contractor accordingly, with a copy to theEmployer.

Sub-Clause 49.3 sets out the defects which must be remedied by the Contractor at hisown cost. It also states the procedure to be followed where the remedying of thedefect(s) is not at the cost of the Contractor.

Contractor's 494 In case of default on the part of the Contractor in car-Failure to rying out such instruction within a reasonable time, theCarry Out Employer shall be entitled to employ and pay other

Instructions persons to carry out the same and ifsuch work is workwhich, in the opinion of the Engineer, the Contractorwas liable to do at his own cost under the Contract, thenall costs consequent thereon or incidental thereto shall,after due consultation with the Employer and the Con-tractor, be determined by the Engineer and shall berecoverable from the Contractor by the Employer, andmay be deducted by the Employer from any monies due

to become due to the Contractor and the Engineershall notify the Contractor accordingly, with a copy tothe Employer.

If the Contractor fails to carry out the instructions of the Engineer to remedy defectswhich are to be at the cost of the Contractor, the Employer is entitled to arrange for themto be carried out at the Contractor's cost.

©FIDIC 1989 109

Page 110: 35824401 FIDIC Guide to the Use of FIDIC

There are two cases referred to which may require an additional sub-clause in Part II.

The first may be necessary for a Contract which includes a high proportion of Plant:

Extension 49.5 The provisions of this Sub-Clause shall apply to allof Defects replacements or renewals of Plant carried out by the

Liability Contractor to remedy defects and damage as if the re-placements and renewals had been taken over on thedate they were completed. The Defects Liability Periodfor the Works shall be extended by a period equal to theperiod during which the Works cannot be used by rea-son of a defect or damage. If only part of the Works isaffected the Defects Liability Period shall be extendedonly for that part. In neither case shall the DefectsLiability Period extend beyond 2 years from the date oftaking over.

When progress in respect of Plant has been suspendedunder Clause 40, the Contractor's obligations under thisClause shall not apply to any defects occurring morethan 3 years after the Time for Completion establishedon the date of the Letter of Acceptance.

The second may be necessary for a Contract comprising dredging work:

No Remedying 49.5 Not withstanding Sub-Clause 49.2, the Contractor shallof Defects in have no responsibility for the remedying of defects,

Dredging Work shrinkages or other faults in respect of dredging workafter Completion after the date stated in the Taking-Over Certificate.

Contractor 50.1 If any defect, shrinkage or other fault in the Worksto Search appears at any time prior to the end of the Defects

Liability Period, the Engineer may instruct the Contrac-tor, with copy to the Employer, to search under thedirections of the Engineer for the cause thereof. Unlesssuch defect, shrinkage or other fault is one for which theContractor is liable under the Contract, the Engineershall, after due consultation with the Employer and theContractor, determine the amount in respect of the costsof such search incurred by the Contractor, which shallbe added to the Contract Price and shall notify the Con-tractor accordingly, with a copy to the Employer. If suchdefect, shrinkage or other fault is one for which theContractor is liable, the cost of the work carried out insearching as aforesaid shall be borne by the Contrac-tor and he shall in such case remedy such defect, shrink-age or other fault at his own cost in accordance withthe provisions of Clause 49.

110 © FIDIC 1989

Page 111: 35824401 FIDIC Guide to the Use of FIDIC

It is an obligation of the Contractor, if required by the Engineer, to search for the causeof any defect, shrinkage or other fault in the Works, both during the execution of theWorks and after their completion until the end of the Defects Liability Period.

Whereas during the execution of the Works the Contractor shall do such searchingat his own cost unless the cause is one for which the Employer is responsible, duringthe Defects Liability Period the searching shall be paid for by the Employer unless theContractor is liable for such fault due to the use of faulty materials, Plant or work-manship or through other breach of contract.

As dredging work is carried out under special circumstances, it may be justified to adda sub-clause which relieves the Contractor of any responsibility for the cost of searchingafter the date stated in the Taking-Over Certificate. The following is an appropriateSub-Clause for addition in Part II where the second example sub-clause of Sub-Clause49.5 has been adopted:

No Responsi- 50.2 Notwithstanding Sub-Clause 50.1, the Contractor shallbility for Cost of have no responsibility to bear the cost of searching for

Searching any defect, shrinkage or other fault in respect of dredg-of Dredging ing work after the date stated in the Taking-Over Cer-

Work tificate.

© FIDIC 1989 111

Page 112: 35824401 FIDIC Guide to the Use of FIDIC

ALTERATIONS, ADDITIONS AND OMISSIONS

Variations 51.1 The Engineer shall make any variation of the form,quality or quantity of the Works or any part thereof thatmay, in his opinion, be necessary and for that purpose,or if for any other reason it shall, in his opinion, beappropriate, he shall have the authority to instruct theContractor to do and the Contractor shall do any of thefollowing:

(a) increase or decrease the quantity of any work in-cluded in the Contract,

(b) omit any such work (but not if the omitted work is tobe carried out by the Employer or any other contrac-tor),

(c) change the character or quality or kind of any suchwork,

(d) change the levels, lines, positions and dimensions ofany part of the Works,

(e) execute additional work of any kind necessary for thecompletion of the Works,

(f) change any specified sequence or timing of construc-tion of any part of the Works.

No such variation shall in any way vitiate or invalidatethe Contract, but the effect, if any, of all such variationsshall be valued in accordance with Clause 52. Providedthat where the issue of an instruction to vary the Worksis necessitated by some default of or breach of contractby the Contractor or for which he is responsible, any ad-ditional cost attributable to such default shall be borneby the Contractor.

The Engineer instructs the Contractor to make a variation when the Engineer determinesto make a change in the Works from that envisaged in the Drawings and other Contractdocuments upon which tenders were based. A variation may in exceptional cases alsobe necessitated by a default of the Contractor but, in such case, the resulting cost isnecessarily borne by the Contractor. A variation is not, however, required if the actualquantities of the work envisaged at the time of tendering prove, on remeasurement,to be different from those recorded in the Bill of Quantities. The effect of any variationis taken into account in determining whether Sub-Clause 52.3 applies.

In the fourth edition the Engineer's power to vary the Works has been extendedwith a case (f) covering specified sequence or timing of construction. Theemphasis here is on the word "specified", i.e. the sequence or timing must havebeen prescribed in the Specification and consequently have been a matter under theresponsibility of the Employer.

For a Contract comprising dredging and some types of reclamation work this Sub-Clause may require to be varied in Part II in the following manner:

112 ©FIDIC 1989

Page 113: 35824401 FIDIC Guide to the Use of FIDIC

Variations 51.1 Add final sentence as follows:Provided also that the Contractor shall be under no ob-ligation to execute any variation which cannot be exe-cuted by the Contractor's Equipment being used or tobe used on the Works.

Dredging and reclamation work normally involves the use of major items of Contrac-tor's Equipment, often few in number, and the Contract is entered into upon the basis ofthat Equipment. If additional work is required which would involve bringing or return-ing to the Site major items of Contractor's Equipment it is reasonable that this should beregarded as a new contract and not a variation of the original Contract unless the twoparties to the Contract agree to treat it as such.

A variation will normally have cost consequences and the Employer should be kept fullyinformed by the Engineer. Even if the variation can be carried out within a budget agreedby the Employer, he may require the opportunity to approve the instruction before it isgiven to the Contractor, see Sub-Clause 2.1. The Contract should establish in Part IIa procedure for such approval. The steps in such a procedure could be:

1. The Engineer prepares an authorisation request with proposed variations to the Speci-fication and Contract quantities as well as an estimate of cost together with the basisand justification for the variation.

2. After the authorisation request has been approved by the Employer, the Engineernegotiates with the Contractor to determine the price of the variation. If the price is equal.to or less than the amount sanctioned by the Employer, the Engineer is authorised toissue the necessary instructions for the variation to the Contractor. If the price is morethan the sanctioned amount the Engineer should seek further authorisation from theEmployer.

3. Irrespective of the procedure described above occasions will arise when it will benecessary for the Engineer to issue an instruction for a variation prior to reaching anagreement with the Contractor as to price, in order to avoid delaying work. Under suchcircumstances a two-part instruction for the variation will be issued, the first partinstructing the Contractor to proceed with the work without stating the rates andprices, and the second part to be issued after further negotiations stating the rates andprices applicable.

Nothing stated in this procedure should be construed as affecting the right of the Engi-neer to fix any rate or price which cannot be agreed between the Engineer and theContractor as provided in Sub-Clauses 52.1 and 52.2.

4. In an emergency the Engineer shall not be restricted from issuing such instructions tothe Contractor as the Engineer considers necessary. If he acts in such an emergency heshall inform the Employer as soon as possible having regard to the circumstances. Seethe example in the commentary under Sub-Clause 2.1.

Instructions 51.2 The Contractor shall not make any variation without anfor Variations for instruction of the Engineer. Provided that no in-

struction shall be required for increase or decrease inthe quantity of any work where such increase or de-crease is not the result of an instruction given under thisClause, but is the result of the quantities exceeding orbeing less than those stated in the Bill of Quantities.

©FIDIC 1989 113

Page 114: 35824401 FIDIC Guide to the Use of FIDIC

The Contractor should be aware that there is no provision in the Conditions for theContractor to make a variation without the written instruction of the Engineer. If theContractor acts without an instruction he will have no grounds to claim for the cost ofsuch variation.

Earlier editions of the FIDIC Conditions had, in Sub-Clause 51.2, a stipulation thatinstructions for variations should be in writing. The obligation for this is dealt with inthe fourth edition in Sub-Clause 2.5 which requires that all instructions given by theEngineer under the Contract must be in writing.

Valuation of 52.1 All variations referred to in Clause 51 and any additionsVariations to the Contract Price which are required to be deter-

mined in accordance with Clause 52 (for the purposesof this Clause referred to as "varied work"), shall bevalued at the rates and prices set out in the Contract if,in the opinion of the Engineer, the same shall be appli-cable. If the Contract does not contain any rates orprices applicable to the varied work, the rates andprices in the Contract shall be used as the basis forvaluation so far as may be reasonable, failing which,after due consultation by the Engineer with the Em-ployer and the Contractor, suitable rates or prices shallbe agreed upon between the Engineer and the Contrac-tor. In the event of disagreement the Engineer shall fixsuch rates or prices as are, in his opinion, appropriateand shall notify the Contractor accordingly, with a copyto the Employer. Until such time as rates or prices areagreed or fixed, the Engineer shall determine provi-sional rates or prices to enable on-account payments tobe included in certificates issued in accordance withClause 60.

Work included in variations is valued in accordance with this Clause using, whereverreasonable, the rates and prices in the Bill of Quantities. If there are no applicable ratesor prices, new rates or prices are to be based upon the Contract rates and prices so far asit may be reasonable to do so. Otherwise, suitable rates and prices are to be agreed.The exercise of his authority by the Engineer, under this Clause, may be subject to thespecific approval of the Employer. See commentary under Sub-Clause 2.1.

A portion of the payments to be made will often be in foreign currency. Any agreementfixing or determining rates or prices should deal with the proportions payable in differ-ent currencies.

Where provision is made in the Contract for payments in foreign currency, it may beadvisable to make the following addition to this Sub-Clause in Part II.

Valuation of 52.1 Add final sentence as follows:Variations

The agreement, fixing or determination of any rates orprices as aforesaid shall include any foreign currencyand the proportion thereof.

114 © FIDIC 1989

Page 115: 35824401 FIDIC Guide to the Use of FIDIC

Power of 52.2 Provided that if the nature or amount of any varied workEngineer to relative to the nature or amount of the whole of the

Fix Rates Works or to any part thereof, is such that, in the opin-ion of the Engineer, the rate or price contained in theContract for any item of the Works is, by reason of suchvaried work, rendered inappropriate or inapplicable,then, after due consultation by the Engineer with theEmployer and the Contractor, a suitable rate or priceshall be agreed upon between the Engineer and theContractor. In the event of disagreement the Engineershall fix such other rate or price as is, in his opinion,appropriate and shall notify the Contractor accordingly,with a copy to the Employer. Until such time as rates orprices are agreed or fixed, the Engineer shall determineprovisional rates or prices to enable on-account pay-ments to be included in certificates issued in accordancewith Clause 60.

Provided also that no varied work instructed to be doneby the Engineer pursuant to Clause 51 shall be valuedunder Sub-Clause 52.1 or under this Sub-Clause unless,within 14 days of the date of such instruction and, otherthan in the case of omitted work, before the commence-ment of the varied work, notice shall have been giveneither:

(a) by the Contractor to the Engineer of his intention toclaim extra payment or a varied rate or price, or

(b) by the Engineer to the Contractor of his intention tovary a rate or price.

If the nature or amount of the work involved differs so much from that included in theoriginal Contract that the rates and prices are rendered inapplicable, it is the Engineer'stask to agree appropriate rates and prices with the Contractor, or, if agreement cannot bereached, to fix the rates and prices. Existing rates and prices shall be used as a guide forthe valuation as far as reasonable. The importance of consultation with both the partiesis now highlighted in the Clause. Failure to reach agreement should not prevent theContractor from receiving a payment on account for the work in question. In principle,the various prices of a lump sum character for the Contractor's preliminary and generalcosts are not affected each time a variation is valued, see Sub-Clause 52.3.

Both the Engineer and the Contractor should pay particular attention to their respectiveobligations to give notice in accordance with the second sub-paragraph of Sub-Clause52.2.

As in the case of Sub-Clause 52.1 it is important that where payments in foreign curren-cies are provided for in the Contract a reference to this should be made in dealing withthe power of the Engineer to fix rates. In such cases the following entry in Part II wouldbe appropriate:

©FIDIC 1989 115

Page 116: 35824401 FIDIC Guide to the Use of FIDIC

Power of 52.2 Add to the first paragraph final sentence as follows:Engineer

to Fix The agreement or fixing of any rates or prices as afore-Rates said shall include any foreign currency and the propor-

tion thereof.

Where it is required to place some limitation on the range of items for which the ratesand prices may be subject to review, this Sub-Clause may be varied in Part II as fol-lows:

Power of 52.2 At the end of the first paragraph add:Engineer

to Fix Provided further that no change in the rate or price forRates any item contained in the Contract shall be considered

unless such item accounts for an amount more than 2percent of the Contract Price, and the actual quantity ofwork executed under the item exceeds or falls short ofthe quantity set out in the Bill of Quantities by morethan 25 per cent.

Variations 52.3 If, on the issue of the Taking-Over Certificate for theExceeding whole of the Works, it is found that as a result of:15 per cent

(a) all varied work valued under Sub-Clauses 52.1 and52.2, and

(b) all adjustments upon measurement of the estimatedquantities set out in the Bill of Quantities, excludingProvisional Sums, dayworks and adjustments of pricemade under Clause 70,

but not from any other cause, there have been additionsto or deductions from the Contract Price which taken to-gether are in excess of 15 per cent of the "EffectiveContract Price" (which for the purposes of this Sub-Clause shall mean the Contract Price, excluding Provi-sional Sums and allowance for dayworks, if any) thenand in such event (subject to any action already takenunder any other Sub-Clause of this Clause), after dueconsultation by the Engineer with the Employer and theContractor, there shall be added to or deducted from theContract Price such further sum as may be agreed be-tween the Contractor and the Engineer or,failing agree-ment, determined by the Engineer having regard to theContractor's Site and general overhead costs of theContract. The Engineer shall notify the Contractor ofany determination made under this Sub-Clause, with acopy to the Employer. Such sum shall be based only onthe amount by which such additions or deductions shallbe in excess of 15 per cent of the Effective ContractPrice.

116 ©FIDIC 1989

Page 117: 35824401 FIDIC Guide to the Use of FIDIC

In preparing a tender, a contractor may distribute his on-costs and profit in various ways,of which the following are examples:

(a) On-costs such as mobilisation, demobilisation, installation of camps and workshopsare usually dealt with as separate fixed sum items in the Bill of Quantities.

(b) On-cost and profit on Provisional Sums may be covered by supplementary items inthe Bill, see Sub-Clauses 58.2 and 59.4.

(c) On-cost and profit on dayworks ordered under Sub-Clause 52.4 will often be includedin the rates inserted in the daywork schedule, or may be expressed as a percentage fig-ure.

(d) All other on-costs and profit are likely to be spread over the unit rates in the Bill.These rates are to be applied (see Sub-Clause 52.1) to the valuation of variations.

Part of the Contractor's on-costs, such as for the purchase of petrol, oil, lubricants, tyresand other consumable stores, will be directly related to the quantities of work actuallycarried out. Other on-costs, such as head office charges, senior superintendence anditems such as those described in (a) above, are more of a fixed or lump sum characterand not directly related to the amount of work done.

It is for this reason that Sub-Clause 52.3 has been included. If the total value of thework under (a) and (d) above (excluding price adjustment which is dealt with separately)differs from the total of the corresponding items in the Contract Price, the Contractormay gain on his fixed on-costs if the overall value is increased, or lose if the total is lessthan that in the original Bill. The extent to which the Contractor is affected by suchincreases or decreases will depend on the degree to which the fixed on-costs have beencovered by items described in (a) above instead of being spread over the unit rates.

Under Sub-Clause 52.3, the first 15 per cent (not 10 per cent as in the third edition) upor down is disregarded, but any increase or decrease beyond this percentage may requirean adjustment to the amount due to the Contractor. Any adjustment already made underanother Sub-Clause of this Clause must be discounted.

As is the case in Sub-Clauses 52.1 and 52.2 an addition to Sub-Clause 52.3 may benecessary in contracts where payments in foreign currency have been provided for. Thefollowing would be appropriate:

Variations 52.3 Add final sentence as follows:Exceeding

15 per cent The adjustment or fixing of any sum as aforesaid shallhave due regard to any foreign currency included in theEffective Contract Price and the proportion thereof.

Daywork 52.4 The Engineer may, if in his opinion it is necessary ordesirable, issue an instruction that any varied work shallbe executed on a daywork basis. The Contractor shallthen be paid for such varied work under the terms setout in the daywork schedule included in the Contractand at the rates and prices affixed thereto by him in theTender.

© FIDIC 1989 117

Page 118: 35824401 FIDIC Guide to the Use of FIDIC

The Contractor shall furnish to the Engineer such re-ceipts or other vouchers as may be necessary to provethe amounts paid and, before ordering materials, shallsubmit to the Engineer quotations for the same for hisapproval.

In respect of such Works executed on a daywork basis,the Contractor shall, during the continuance of suchwork, deliver each day to the Engineer an exact list induplicate of the names, occupation and time of allworkmen employed on such work and a statement, alsoin duplicate, showing the description and quantity of allmaterials and Contractor's Equipment used thereon ortherefor other than Contractor's Equipment which isincluded in the percentage addition in accordance withsuch daywork schedule. One copy of each list and state-ment will, if correct, or when agreed, be signed by theEngineer and returned to the Contractor.

At the end of each month the Contractor shall deliver tothe Engineer a priced statement of the labour, materi-als and Contractor's Equipment, except as aforesaid,used and the Contractor shall not be entitled to anypayment unless such lists and statements have been fullyand punctually rendered. Provided always that if theEngineer considers that for any reason the sending ofsuch lists or statements by the Contractor, in accor-dance with the foregoing provision, was impracticablehe shall nevertheless be entitled to authorise paymentfor such work, either as daywork, on being satisfied asto the time employed and the labour, materials andContractor's Equipment used on such work, or at suchvalue therefor as shall, in his opinion, be fair and rea-sonable.

Sub-Clause 52.4 deals with daywork, usually covered by a Provisional Sum in the Billof Quantities, to be used for minor supplementary work for which no Bill item is appli-cable. A Daywork Schedule of Rates and Prices is normally included in the Contract asan annex to the Bill.

118 ©FIDIC 1989

Page 119: 35824401 FIDIC Guide to the Use of FIDIC

PROCEDURE FOR CLAIMS

Clause 53 is a new clause which has not appeared in previous editions of the FIDICConditions. The intention of the clause generally is to set out a disciplined manner ofdealing with claims which will be of advantage to both the Employer and the Contrac-tor. Claims are certain to provoke differences particularly if the claim is established longafter the work giving rise to the claim has been completed. Frequently in the past claimshave been made when the project has been completed and the workforce has been dis-persed and then both the Employer and the Contractor are dependent upon incompleterecords and inevitably regard their memories of the events as being indisputable. As theirrespective memories were rarely identical it is understandable that they were both dis-satisfied with the outcome. The fourth edition has introduced a claims procedure whichplaces time limits for the notification and substantiation of claims and requires contem-porary records to be kept. If such records are not kept, the Contractor may be limited inhis entitlement.

Notice of 53.1 Notwithstanding any other provisions of the Contract, ifClaims the Contractor intends to claim any additional payment

pursuant to any Clause of these Conditions or otherwise,he shall give notice of his intention to the Engineer, witha copy to the Employer, within 28 days after the eventgiving rise to the claim has first arisen.

This Sub-Clause requires the Contractor to give notice to the Engineer "within 28 daysafter the event giving rise to the claim has first arisen". This is a practical requirementand not difficult to comply with. Contractors will generally maintain a Site diary andwill have noted therein when the event first arises. Note that the Sub-Clause does notrequire the Contractor to make his claim then - it requires him to give notice of hisintention to make a claim.

The words 'or otherwise' are intended to encompass claims made on some legal ground(e.g. under the law governing the Contract) and not made pursuant to any Clause of theseConditions.

Contemporary 53.2 Upon the happening of the event referred to in Sub-Records Clause 53.1, the Contractor shall keep such contempo-

rary records as may reasonably be necessary to supportany claim he may subsequently wish to make. Withoutnecessarily admitting the Employer's liability, the En-gineer shall, on receipt of a notice under Sub-Clause53.1, inspect such contemporary records and may in-struct the Contractor to keep any further contemporaryrecords as are reasonable and may be material to theclaim of which notice has been given. The Contractorshall permit the Engineer to inspect all records keptpursuant to this Sub-Clause and shall supply him withcopies thereof as and when the Engineer so instructs.

©FIDIC 1989 119

Page 120: 35824401 FIDIC Guide to the Use of FIDIC

The event giving rise to the claim having occurred, the Contractor is required to main-tain contemporary records. This would be a logical act for a responsible contractor. Itis to the advantage of the Contractor that he can call upon the Engineer to inspect suchrecords and state if he (the Engineer) requires other records to be kept. In this mannerthe Contractor can satisfy himself that the records he is keeping will be suitable for theEngineer to evaluate the claim in due course. Note that the Engineer has a duty to inspectthe records on being notified under Sub-Clause 53.1.

Substantiation 53.3 Within 28 days, or such other reasonable time as mayofClaims be agreed by the Engineer, of giving notice under Sub-

Clause 53.1, the Contractor shall send to the Engineeran account giving detailed particulars of the amountclaimed and the grounds upon which the claim is based.Where the event giving rise to the claim has a continu-ing effect, such account shall be considered to be aninterim account and the Contractor shall, at such inter-vals as the Engineer may reasonably require, send fur-ther interim accounts giving the accumulated amount ofthe claim and any further grounds upon which it isbased. In cases where interim accounts are sent to theEngineer, the Contractor shall send a final accountwithin 28 days of the end of the effects resulting fromthe event. The Contractor shall, if required by theEngineer so to do, copy to the Employer all accountssent to the Engineer pursuant to this Sub-Clause.

If the circumstances giving rise to the claim are not continuing the Contractor has theobligation, but also the benefit, of submitting his claim to the Engineer for agreement ordiscussion while the event is still sufficiently recent for Site personnel to have the factsat their fingertips and the records readily available. If the circumstances are continu-ing the Engineer will inspect the records at reasonable intervals and should raise anypoints with which he disagrees or on which he wishes to have further information whenhe inspects the records.

Failure to 53.4 Ifthe Contractor fails to comply with any of the provi-Comply sions of this Clause in respect of any claim which he

seeks to make, his entitlement to payment in respectthereof shall not exceed such amount as the Engineer orany arbitrator or arbitrators appointed pursuant to Sub-Clause 67.3 assessing the claim considers to be verifiedby contemporary records (whether or not such recordswere brought to the Engineer's notice as required un-der Sub-Clauses 53.2 and 53.3).

120 © FIDIC 1989

Page 121: 35824401 FIDIC Guide to the Use of FIDIC

This Sub-Clause deals with the situation where the Contractor fails to comply with anyof his obligations under Sub-Clause 53.1, 53.2 or 53.3 and defines the extent of hisentitlement under such circumstances.

If the Contractor does not comply with the procedure laid down in the Conditions hisentitlement to payment may be limited. It is considered that failure by the Contractor tomake a claim in accordance with the provisions of Sub-Clauses 53.1, 53.2 or 53.3 shouldnot bar the Contractor from receiving remuneration for any work which the Contractorcan substantiate from contemporary records.

Paymentof 53.5 The Contractor shall be entitled to have included in anyClaims interim payment certified by the Engineer pursuant to

Clause 60 such amount in respect of any claim as theEngineer, after due consultation with the Employer andthe Contractor, may consider due to the Contractorprovided that the Contractor has supplied sufficient par-ticulars to enable the Engineer to determine the amountdue. If such particulars are insufficient to substantiatethe whole of the claim, the Contractor shall be entitledto payment in respect of such part of the claim as suchparticulars may substantiate to the satisfaction of theEngineer. The Engineer shall notify the Contractor ofany determination made under this Sub-Clause, with acopy to the Employer.

This Sub-Clause deals with payments in respect of claims including interim payments inrespect of continuing claims and should be studied in conjunction with Sub-Clauses 60.5to 60.9. It is intended to remove any possibility of contention that payments in respectof a claim must await the finalisation of the whole claim.

©FIDIC 1989 121

Page 122: 35824401 FIDIC Guide to the Use of FIDIC

CONTRACTOR'S EQUIPMENT, TEMPORARY WORKS AND MATERIALS

Clause 54 in the fourth edition combines Clauses 53 and 54 in the previous editions.Sub-Clause 53.2 of the third edition has been dropped from the fourth edition as therequirement of removal of Equipment, etc., is now covered by Clause 33.

Contractor's 54.1 All Contractor's Equipment, Temporary Works andEquipment, materials provided by the Contractor shall, whenTemporary brought on to the Site, be deemed to be exclusively in-Worksand tendedfor the execution of the Works and the Contrac-Materials; tor shall not remove the same or any part thereof, ex-Exclusive cept for the purpose of moving it from one part of the

Use for the Site to another, without the consent of the Engineer.Works Provided that consent shall not be required for vehicles

engaged in transporting any staff, labour, Contractor'sEquipment, Temporary Works, Plant or materials to orfrom the Site.

The principle of the Contract is that while the Employer becomes responsible for thecare of the Permanent Works, Plant and materials on taking over the Works, the Con-tractor remains the owner of the Contractor's Equipment and Temporary Works be-cause the Employer, under the Contract, is only paying for their use during the construc-tion of the Permanent Works. However, the Employer must have some control over theContractor's Equipment, Plant and materials brought on to the Site and his control isthat they cannot be removed from the Site without the approval of the Engineer.

In some contracts the Employer requires that the Contractor's Equipment, TemporaryWorks and materials be vested in the Employer and where this is the case it can becovered by two additional sub-clauses in Part II. The following wording may be appro-priate:

Sub-Clauses 54.2 and 54.3 shall be renumbered as 54.3 and 54.4 and Sub-Clauses 54.4to 54.8 shall be renumbered as 54.6 to 54.10. Add additional Sub-Clauses as follows:

Vesting 54.2 All Contractor's Equipment, Temporary Works andmaterials owned by the Contractor, or by any companyin which the Contractor has a controlling interest, shall,when on the Site, be deemed to be the property of theEmployer. Provided always that the vesting of suchproperty shall not prejudice the right of the Contractorto the sole use of the said Contractor's Equipment,Temporary Works and materials for the purpose of theWorks nor shall it affect the Contractor's responsibilityto operate and maintain the same under the provisionsof the Contract.

122 ©FIDIC 1989

Page 123: 35824401 FIDIC Guide to the Use of FIDIC

Revesting 54.5 Upon the removal, with the consent of the Engineerand under Sub-Clause 54.1, of any such Contractor's Equip-

Removal ment, Temporary Works or materials as have beendeemed to have become the property of the Employerunder Sub-Clause 54.2, the property therein shall bedeemed to revest in the Contractor and, upon comple-tion of the Works, the property in the remainder of suchContractor's Equipment, Temporary Works and materi-als, shall, subject to Clause 63, be deemed to revest inthe Contractor.

Employernot 54.2 The Employer shall not at any time be liable, save asLiable for Damage mentioned in Clauses 20 and 65, for the loss of or

damage to any of the said Contractor's Equipment,Temporary Works or materials.

As the Contractor is the owner or lessee of the Contractor's Equipment, etc., and as inany case he is responsible for the care of the Works from the Commencement Date untilthe Taking Over of the Works it follows that the Contractor is responsible for any lossor damage thereto, see Clauses 20 and 65.

Customs 54.3 The Employer will use his best endeavours in assistingClearance the Contractor, where required, in obtaining clearance

through the Customs of Contractor's Equipment, mate-rials and other things required for the Works.

Clearance through customs, import and export licences, port regulations, storage andtransport regulations are normally the responsibility of the Contractor and he should takeall necessary steps in sufficient time to meet the requirements of his programme. TheContractor is also required to pay the customs duties (unless exempted therefrom) andother dues for whatever he imports for the Contract.

The Employer undertakes to render whatever assistance he can to the Contractor inconnection with clearances through customs, but the Contractor must ultimately behimself responsible.

Re-exportof 54.4 In respect of any Contractor's Equipment which theContractor's Contractor has imported for the purposes of the Works,

Equipment the Employer will use his best endeavours to assist theContractor, where required, in procuring any necessaryGovernment consent to the re-export of such Contrac-tor's Equipment by the Contractor upon the removalthereof pursuant to the terms of the Contract.

© FIDIC 1989 123

Page 124: 35824401 FIDIC Guide to the Use of FIDIC

The Contractor is often allowed to import his Equipment and Temporary Works itemson a temporary admittance basis, i.e., free of customs duties. Under such circumstancesit is important to clarify the limits on the use of such Equipment and Temporary Worksitems as well as any time limit for their re-export and the consequences if such limit isnot met and the Equipment and Temporary Works items remain in the country of theWorks.

Conditions of 54,5 With a view to securing, in the event of terminationHire of under Clause 63, the continued availability, for the

Contractor's purpose of executing the Works, of any hired Contrac-Equipment tor's Equipment, the Contractor shall not bring on to the

Site any hired Contractor's Equipment unless there isan agreement for the hire thereof (which agreementshall be deemed not to include an agreement for hirepurchase) which contains a provision that the ownerthereof will, on request in writing made by the Employerwithin 7 days after the date on which any terminationhas become effective, and on the Employer undertakingto pay all hire charges in respect thereoffrom such date,hire such Contractor's Equipment to the Employer onthe same terms in all respects as the same was hired tothe Contractor save that the Employer shall be entitledto permit the use thereof by any other contractor em-ployed by him for the purpose of executing and complet-ing the Works and remedying any defects therein, un-der the terms of the said Clause 63.

The location of the Site and the availability of Contractor's Equipment may present theEmployer with substantial problems in the event that the Contractor fails to completethe execution of the Works and the Employer has to find an alternative means of com-pleting the Works. This Sub-Clause has been inserted to ensure that if the Employerhas to find another contractor, or himself complete the Works, the Equipment andTemporary Works which will be required will be available if they are already on Site.

Costs for the 54.6 In the event of the Employer entering into any agree-Purpose of ment for the hire of Contractor's Equipment pursuantClause 63 to Sub-Clause 54.5, all sums properly paid by the

Employer under the provisions of any such agreementand all costs incurred by him (including stamp duties)in entering into such agreement shall be deemed,for thepurpose of Clause 63, to be part of the cost of executingand completing the Works and the remedying of anydefects therein.

This Sub-Clause deals with the cost consequences in the event that Sub-Clause 54.5becomes operative. Reference should be made to Clause 63.

124 ©FIDLC 1989

Page 125: 35824401 FIDIC Guide to the Use of FIDIC

Incorporation 54.7 The Contractor shall, where entering into any subcon-of Clause in tractfor the execution of any part of the Works, incor-

Subcontracts porate in such subcontract (by reference or otherwise)the provisions of this Clause in relation to Contractor'sEquipment, Temporary Works or materials brought onto the Site by the Subcontractor.

The conditions imposed upon the Contractor by Sub-Clauses 54.5 and 54.6 must beimposed upon all Subcontractors by the Contractor.

Approvalof 54.8 The operation of this Clause shall not be deemed toMaterials imply any approval by the Engineer of the materials or

not Implied other matters referred to therein nor shall it prevent therejection of any such materials at any time by the Engi-neer.

There is nothing in Clause 54 which implies that under it approval is given to materialsor any other matters but the Sub-Clause has been included to prevent any misunderstand-ing.

It may be necessary to deal with other issues in supplementary Sub-Clauses in Part IIand these will possibly include:

—Any limitations on the selection of Contractor's Equip-ment and Temporary Works.

—Any preference for local products.

—Contractor to make his own arrangements for the tem-porary supply and distribution of services (water, elec-tricity, fuel, etc.), his obligations as to the needs ofother contractors on the Site (in addition to his obliga-tions under Clause 31), to his own Subcontractors, theEmployer and the Engineer.

—Contractor to deal with special hazards from water,etc., on the Site and to take necessary safeguards.

—Contractor to provide necessary maintenance for roadsat the Site, permanent and temporary, and his obliga-tions at completion of the Works.

Any Sub-Clauses to Clause 54 to be added in Part II should be considered in relation toPart II Sub-Clauses of Clause 34. Ambiguities and unnecessary repetition should beavoided.

© FIDIC 1989 125

Page 126: 35824401 FIDIC Guide to the Use of FIDIC

MEASUREMENT

Quantities 55.1 The quantities set out in the Bill of Quantities are theestimated quantities for the Works, and they are not tobe taken as the actual and correct quantities of theWorks to be executed by the Contractor in fulfilment ofhis obligations under the Contract.

The quantities in the Bill of Quantities are the quantities of work estimated when theTender documents are prepared based upon the Drawings and the Specification. Theactual quantities of work performed in the execution of the Contract are to be ascer-tained by measurement.

Works to be 56.1 The Engineer shall, except as otherwise stated, ascer-Measured tam and determine by measurement the value of the

Works in accordance with the Contract and the Con-tractor shall be paid that value in accordance withClause 60. The Engineer shall, when he requires anypart of the Works to be measured, give reasonablenotice to the Contractor's authorised agent, who shall:

(a) forthwith attend or send a qualified representativeto assist the Engineer in making such measurement, and

(b) supply all particulars required by the Engineer.

Should the Contractor not attend, or neglect or omit tosend such representative, then the measurement made bythe Engineer or approved by him shall be taken to bethe correct measurement of such part of the Works. Forthe purpose of measuring such Permanent Works as areto be measured by records and drawings, the Engineershall prepare records and drawings as the work pro-ceeds and the Contractor, as and when called upon todo so in writing, shall, within 14 days, attend to exam-ine and agree such records and drawings with theEngineer and shall sign the same when so agreed. If theContractor does not attend to examine and agree suchrecords and drawings, they shall be taken to be correct.If, after examination of such records and drawings, theContractor does not agree the same or does not sign thesame as agreed, they shall nevertheless be taken to, becorrect, unless the Contractor, within 14 days of suchexamination, lodges with the Engineer notice of therespects in which such records and drawings areclaimed by him to be incorrect. On receipt of suchnotice, the Engineer shall review the records and draw-ings and either confirm or vary them.

126 © FIDIC 1989

Page 127: 35824401 FIDIC Guide to the Use of FIDIC

This Sub-Clause lays down the procedural rules for measuring the Works. Where theWorks are to be measured by records and drawings, the Engineer prepares such recordsand drawings and obtains the Contractor's agreement thereto. Under Clause 60, theContractor is paid based on monthly statements and the Engineer, when certifying, willtake into account the value of work done as measured pursuant to this Sub-Clause.

Under some circumstances it may be appropriate for the Contractor to measure certainparts of the Works under the observation and the control of the Engineer.

Standard methods of measurement have been developed and to some extent used inter-nationally. Should such a method be adopted in preparing the Bill of Quantities, itshould be stated in the Contract and the same method should be used in the measure-ment of actual work done.

However, should no such standard method be adopted, the principles for measurementand valuation to be applied should be clearly defined in the preamble to the Bill of Quan-tities.

Method of 57.1 The Works shall be measured net, notwithstanding anyMeasurement general or local custom, except where otherwise pro-

vided for in the Contract.

This Sub-Clause requires measurements to be taken net where no other principle isprescribed. Thus, the quantity of shuttering is the net area in contact with the finishedface of the concrete. However, there may be deviations from the general principle, e.g.,for rock excavation where over-breakage is often measured and paid for under a sepa-rate item in the Bill of Quantities.

Breakdown of 57.2 For the purposes of statements submitted in accordanceLump Sum Items with Sub-Clause 60.1, the Contractor shall submit to the

Engineer, within 28 days after the receipt of the Letterof Acceptance, a breakdown for each of the lump sumitems contained in the Tender. Such breakdowns shallbe subject to the approval of the Engineer.

This Sub-Clause requires a breakdown of lump sum items included in the Bill of Quan-tities in order that progress payments may reasonably reflect the distribution of the lumpsums over the period of the Contract. It is not intended that such breakdowns willnecessarily apply to the valuation of variations.

© FIDIC 1989 127

Page 128: 35824401 FIDIC Guide to the Use of FIDIC

PROVISIONAL SUMS

Definition of 58.1 "Provisional Sum" means a sum included in the Con-Provisional tract and so designated in the Bill of Quantities for the

Sum execution of any part of the Works or for the supply ofgoods, materials, Plant or services, or for contingencies,which sum may be used, in whole or in part, or not atall, on the instructions of the Engineer. The Contractorshall be entitled to only such amounts in respect of thework, supply or contingencies to which such ProvisionalSums relate as the Engineer shall determine in accor-dance with this Clause. The Engineer shall notify theContractor of any determination made under this Sub-Clause, with a copy to the Employer.

This Sub-Clause defines a Provisional Sum. A normal unit rate contract is likely toinclude in the Bill of Quantities, Provisional Sums for one or both of the followingpurposes (in separate sums or combined):

—daywork (see Sub-Clause 52.4)

—contingencies.

Beyond the above purposes, Provisional Sums should only be used when absolutelynecessary as they introduce an element of uncertainty to the Contractor in the require-ments of the Contract. They should cover only such instances where it is not feasibleto reach a conclusion at the time of preparation of the tender documents, e.g.:

— it has not been possible at the time of inviting tenders for the Contract to define somepart of the Works in sufficient detail to allow tenderers to quote firm rates and prices,or

— it has not been decided at the time of inviting tenders whether a particular item ofwork will actually be included in the Contract, or

— it has been decided to invite separate tenders for an item of work, goods, materials,Plant or services from specialist firms and to make this the subject of a nominatedSubcontract.

The amounts to be included in the Contract under Provisional Sum items are assessedand inserted in the Bill of Quantities by the Engineer prior to issue to tenderers.

Items covered by Provisional Sums may include the supply and delivery to the Site ofPlant and/or materials, (e.g., in the interests of standardisation of operation and mainte-nance and supply of spare parts), work carried out at Site and the provision of suchservices as superintendence of erection and commissioning. Such work may be carriedout either by the Contractor or by a nominated Subcontractor, see Clause 59.

128 ©FIDIC 1989

Page 129: 35824401 FIDIC Guide to the Use of FIDIC

Use of 58.2 In respect of every Provisional Sum the Engineer shallProvisional have authority to issue instructions for the execution of

Sums work or for the supply of goods, materials, Plant orservices by.

(a) the Contractor, in which case the Contractor shallbe entitled to an amount equal to the value thereof de-termined in accordance with Clause 52,

(b) a nominated Subcontractor, as hereinafter defined,in which case the sum to be paid to the Contractortherefor shall be determined and paid in accordancewith Sub-Clause 59.4.

The authority of the Engineer to give instructions for work included under ProvisionalSums may be restricted under Clause 2.

If it is decided to invite tenders for work covered by a Provisional Sum, the proceduresto be followed are similar to those for the Contract. Should the Contractor have theappropriate capability and experience, and wish to do so, there is no reason why heshould not be invited to tender, but he must be prepared to compete with other tender-ers.

Productionof 58.3 The Contractor shall produce to the Engineer all quo-Vouchers tations, invoices, vouchers and accounts or receipts in

connection with expenditure in respect of ProvisionalSums, except where work is valued in accordance withrates or prices set out in the Tender.

This Sub-Clause stipulates that in order to obtain payment for work under ProvisionalSums the Contractor must satisfy the Engineer that competitive quotations have beenobtained and all relevant vouchers must be produced unless the work can be valued inaccordance with rates and prices set out in the Bill of Quantities.

© FIDIC 1989 129

Page 130: 35824401 FIDIC Guide to the Use of FIDIC

NOMINATED SUBCONTRACTORS

Definition 59.1 All specialists, merchants, tradesmen and others execut-of ing any work or supplying any goods, materials, Plant

Nominated or services for which Provisional Sums are included inSubcontractors the Contract, who may have been or be nominated or

selected or approved by the Employer or the Engineer,and all persons to whom by virtue of the provisions ofthe Contract the Contractor is required to subcontractshall, in the execution of such work or the supply of suchgoods, materials, Plant or services, be deemed to besubcontractors to the Contractor and are referred to inthis Contract as "nominated Subcontractors".

The term "nominated Subcontractor" is defined in Sub-Clause 59.1. Once appointed, thenominated Subcontractor's relationship with the Contractor, is defined in a Subcon-tract Agreement drawn up and signed by the Contractor and the Subcontractor. Theimportant element in the arrangement is that the Employer wishes the Contractor to beresponsible for the administration and co-ordination of the Subcontract and pays theContractor for such services. This is not the case where the Employer enters into aseparate direct contract for such work as, under the latter circumstances, theEngineer provides the administration and co-ordination on behalf of the Employer.

Nominated 59.2 The Contractor shall not be required by the EmployerSubcontractors; or the Engineer, or be deemed to be under any obliga-

Objection to tion, to employ any nominated Subcontractor againstNomination whom the Contractor may raise reasonable objection, or

who declines to enter into a subcontract with the Con-tractor containing provisions:

(a) that in respect of the work, goods, materials, Plantor services the subject of the subcontract, the nominatedSubcontractor will undertake towards the Contractorsuch obligations and liabilities as will enable the Con-tractor to discharge his own obligations and liabilitiestowards the Employer under the terms of the Contractand will save harmless and indemnify the Contractorfrom and against the same and from all claims, proceed-ings, damages, costs, charges and expenses whatsoeverarising out of or in connection therewith, or arising outof or in connection with any failure to perform suchobligations or to fulfil such liabilities, and

(b) that the nominated Subcontractor will save harmlessand indemnify the Contractor from and against any neg-ligence by the nominated Subcontractor, his agents,workmen and servants and from and against any mis-use by him or them of any Temporary Works providedby the Contractor for the purposes of the Contract andfrom all claims as aforesaid.

130 ©HDIC 1989

Page 131: 35824401 FIDIC Guide to the Use of FIDIC

It is important to ensure that the Contractor approves of the Subcontractor and isprepared to collaborate with him. The Contractor can refuse the nomination if he hasreasonable grounds for so doing. The Subcontractor has to undertake toward the Con—tractor such obligations and liabilities as will enable the Contractor to discharge hisown obligations and liabilities to the Employer. Such obligations and liabilities of thenominated Subcontractor will in many respects be the same as those of the Contractor(materials and workmanship, Contractor's Equipment, labour, insurances, securities,Engineer's instructions, care of the Works,etc.), but they may also be adapted to the sizeof the Subcontract. Liquidated damages (see Clause 47) is an example. It is important,however, that the nominated Subcontractor has at least the same incentive as the Con-tractor to complete on time.

The failure of a nominated Subcontractor to perform could have serious consequencesfor both the Contractor and the Employer. It is, therefore, recommended that beforetenders are invited for a Subcontract, not only the Employer but also the Contractorapprove the firms to be invited. The Contractor is then able to request the deletion ofany firm to which he reasonably objects and to suggest the addition of any firm in whichhe has confidence and past experience of good working relations. Such deletions oradditions would be subject to the consent of the Employer and the Engineer.

As the documents issued to tenderers for a nominated Subcontract will eventually be-come part of the Subcontract Agreement, the Contractor should be given the opportu-nity to comment upon them before they are issued. He should also have an opportunityto comment upon any reservations inserted by potential Subcontractors in theirtenders. This procedure is not possible when a nominated Subcontract has to beplaced before tenders are invited for the Contract, due, for instance, to long deliveryperiods. In such a case all tenderers for the Contract must be provided with full detailsof the nominated Subcontract in the tender documents and the Engineer should en-deavour, when inviting tenders for the nominated Subcontract, to make the terms ofthe nominated Subcontract compatible with those he will expect to include in the tenderdocuments for the Contract.

If the Contractor declines to enter into a Subcontract with a nominated Subcontractor,the Engineer will have alternative lines of action open to him. He can:

— nominate an alternative Subcontractor, or

— modify the terms of the Subcontract, or

arrange for the Contractor to carry out the work himself through a variation underClause 51.

Design 59.3 If in connection with any Provisional Sum the servicesRequirements to be provided include any matter of design or specifi-

tobe Expressly cation of any part of the Permanent Works or of anyStated Plant to be incorporated therein, such requirement shall

be expressly stated in the Contract and shall be includedin any nominated Subcontract. The nominated Subcon-tract shall specify that the nominated Subcontractorproviding such services will save harmless and indem-nfy the Contractor from and against the same and fromall claims, proceedings, damages, costs, charges andexpenses whatsoever arising out of or in connection withany failure to perform such obligations or to fulfil suchliabilities.

©FIDIC 1989 131

Page 132: 35824401 FIDIC Guide to the Use of FIDIC

It is often the case that specialist nominated Subcontractors are required to undertakeand be responsible for the detailed design of items or works included in the Subcon-tract. The Engineer must provide an outline of any such design and specificationrequirement in the documents issued to tenderers for the Contract, and the Subcon-tract documents issued to tenderers must contain an outline specification giving thebasic requirements within which the nominated Subcontractor can offer his own speci-ality.

So far as the Employer is concerned, the Contractor remains responsible to him underthe Contract for the Subcontractor's designs and operations. Nominated Subcontractorssometimes allege that they are cut off from access to the Engineer and through himto the Employer. This problem can be alleviated if the Contractor agrees that on tech-nical matters related to specification and design details, the Subcontractor and the Engi-neer deal directly with each other, keeping the Contractor fully informed, and providingfor his participation whenever appropriate.

Payments to 59.4 For all work executed or goods, materials, Plant orNominated services supplied by any nominated Subcontractor, the

Subcontractors Contractor shall be entitled to:

(a) the actual price paid or due to be paid by the Con-tractor, on the instructions of the Engineer, and inaccordance with the subcontract;

(b) in respect of labour supplied by the Contractor, thesum, if any, entered in the Bill of Quantities or, if in-structed by the Engineer pursuant to paragraph (a) ofSub-Clause 58.2, as may be determined in accordancewith Clause 52;

(c) in respect of all other charges and profit, a sumbeing a percentage rate of the actual price paid or dueto be paid calculated, where provision has been madein the Bill of Quantities for a rate to be set against therelevant Provisional Sum, at the rate inserted by theContractor against that item or, where no such provi-sion has been made, at the rate inserted by the Contrac-tor in the Appendix to Tender and repeated where pro-vision for such is made in a special item provided in theBill of Quantities for such purpose.

It may be convenient to include in the Bill of Quantities, after each Provisional Sumitem which may become the subject of a nominated Subcontract, a supplementary itemto permit tenderers for the Contract to enter a percentage figure to cover the cost (plusoverhead charges and profit) of the Contractor's superintendence of the Subcontractor.As the extent of the Contractor's superintendence will depend on the nature of individ-ual Subcontracts, this is a more satisfactory method than inserting a single percent-age in the Appendix to Tender and applying this percentage to expenditure under anyor all of the Provisional Sums. It is important to ensure that the Specification containsprecise instructions as to what is to be covered by percentage figures.

132 ©FIDIC 1989

Page 133: 35824401 FIDIC Guide to the Use of FIDIC

Certificate 59.5 Before issuing, under Clause 60, any certificate, whichofPayments includes any payment in respect of work done or goods,

to Nominated materials, Plant or services supplied by any nominatedSubcontractors Subcontractor, the Engineer shall be entitled to demand

from the Contractor reasonable proof that all payments,less retentions, included in previous certificates in re-spect of the work or goods, materials, Plant or servicesof such nominated Subcontractor have been paid ordischarged by the Contractor. If the Contractor fails tosupply such proof then, unless the Contractor

(a) satisfies the Engineer in writing that he has reason-able cause for withholding or refusing to make suchpayments and

(b) produces to the Engineer reasonable proof that hehas so informed such nominated Subcontractor in writ-ing,

the Employer shall be entitled to pay to such nominatedSubcontractor direct, upon the certificate of the Engi-neer, all payments, less retentions, provided for in thenominated Subcontract, which the Contractor has failedto make to such nominated Subcontractor and to deductby way of set-off the amount so paid by the Employerfrom any sums due or to be become due from theEmployer to the Contractor.

Provided that, where the Engineer has certified and theEmployer has paid direct as aforesaid, the Engineershall, in issuing any further certificate in favour of theContractor, deduct from the amount thereof the amountso paid, direct as aforesaid, but shall not withhold ordelay the issue of the certificate itself when due to beissued under the terms of the Contract.

Serious difficulties can arise if the Contractor fails or refuses to pay at the appropriatetime the amounts due to a nominated Subcontractor. This Sub-Clause lays down theprocedure if the Contractor cannot, or will not, without giving satisfactory reasons to theEngineer, make payments due to nominated Subcontractors. Under given circumstancesthe Employer may pay the nominated Subcontractor directly and recover the amount fromthe Contractor, possibly by deduction from payments due to be made to the Contractorby the Employer.

The subject matter of Sub-Clause 59 (6) in the third edition appears in Sub-Clause 4.2of the fourth edition.

©FIDIC 1989 133

Page 134: 35824401 FIDIC Guide to the Use of FIDIC

CERTIFICATES OF PAYMENT

In previous editions of FIDIC Conditions of Contract, the payment arrangements havebeen left for individual drafting for each contract with guidance in the Part II aide-memoire. However, experience has shown that certain payment arrangements are usedso frequently that they should be reflected in Part I, and they are so included in thefourth edition. Examples of supplementary stipulations which are more likely to varyfrom contract to contract and which should appear in Part II are given below. To-gether, the Part I and appropriate Part II sub-clauses should form a complete paymentclause. They should be carefully examined and adapted as necessary for each indi-vidual contract.

The Clause assumes that progress payments will be made on a monthly basis accordingto the unit rates for the work carried out, as is generally the case for contracts of worksof civil engineering construction. Other methods of payment include: lump sum withstage payments of fixed parts at fixed time intervals, or lump sum with stage paymentsof fixed parts corresponding to defined parts of the works as and when each partof the Works has been completed , or payments on a cost reimbursement basis.

In an international civil engineering contract, different methods of payment could applyto different parts of the Works, e.g., measurement at unit rates for the Permanent Works,cost reimbursement for daywork, lump sums in the section of the Bill of Quantities forTemporary Works, stage payments payable at fixed time intervals for the running ofTemporary Works (camp, water supply, electricity, roads, etc.,) and as stage paymentspayable in fixed parts for construction of camp, of roads, of water supply facilities, etc.It is therefore important that the Contract makes it quite clear how the different parts ofthe Works shall be paid for, see commentary to Clause 57.

Monthly 60.1 The Contractor shall submit to the Engineer after theStatements end of each month six copies, each signed by the Con-

tractor's representative approved by the Engineer inaccordance with Sub-Clause 15.1, of a statement, insuch form as the Engineer may from time to time pre-scribe, showing the amounts to which the Contractorconsiders himself to be entitled up to the end of themonth in respect of

(a) the value of the Permanent Works executed

(b) any other items in the Bill of Quantities includingthose for Contractor's Equipment, Temporary Works,dayworks, and the like

(c) the percentage of the invoice value of listed materi-als, all as stated in the Appendix to Tender, and Plantdelivered by the Contractor on the Site for incorpora-tion in the Permanent Works but not incorporated insuch Works

(d) adjustments under Clause 70

(e) any other sum to which the Contractor may be en-titled under the Contract.

134 © FIDIC 1989

Page 135: 35824401 FIDIC Guide to the Use of FIDIC

In recognition of the importance to the Contractor of a predictable and prompt cash flow,payments are to be made monthly on the basis of statements submitted by the Contrac-tor and checked and certified by the Engineer. If, following the check by the Engineer,the amount due to the Contractor is less than the minimum amount stated in the Appen-dix to Tender, no certificate is issued and the payment is included in the following cer-tificate.

The monthly statements shall cover the five items listed in Sub-Clause 60.1. As to thelisted materials, item (c), it is assumed that the Appendix to Tender will identify basicmaterials of importance to the Contract, such as, for example, cement, reinforcement steeland structural steel. It is also assumed that the Engineer shall have approved thematerials for incorporation in the Works. The payment for listed materials isreduced to 90 per cent of the invoice value (or other suitable percentage) in recognitionthat there is likely to be some wastage.

Monthly 60.2 The Engineer shall, within 28 days of receiving suchPayments statement, certify to the Employer the amount of pay-

ment to the Contractor which he considers due andpayable in respect thereof, subject:

(a) firstly, to the retention of the amount calculated byapplying the Percentage of Retention stated in the Ap-pendix to Tender, to the amount to which the Contrac-tor is entitled under paragraphs (a), (b), (c) and (e) ofSub-Clause 60.1 until the amount so retained reachesthe Limit of Retention Money stated in the Appendix toTender, and

(b) secondly, to the deduction, other than pursuant toClause 47, of any sums which may have become due andpayable by the Contractor to the Employer.

Provided that the Engineer shall not be bound to certifyany payment under this Sub-Clause if the net amountthereof, after all retentions and deductions, would beless than the Minimum Amount of Interim Certificatesstated in the Appendix to Tender.

Notwithstanding the terms of this Clause or any otherClause of the Contract no amount will be certified bythe Engineer for payment until the performance security,frequired under the Contract, has been provided by theContractor and approved by the Employer.

Before certifying for payment, the Engineer shall make such deductions as the Contractprescribes. Most important are the payments on account previously made and theRetention Money stated in the Appendix to Tender, normally ten per cent of each state-ment (except for adjustments under Clause 70), but subject to a maximum in total,also given in the Appendix to Tender (five per cent would be reasonable for a bigcomplex contract).

FIDIC 1989 135

Page 136: 35824401 FIDIC Guide to the Use of FIDIC

It should be observed that this Sub-Clause leaves to the Employer the responsibility ofdetermining in the case that liquidated damages are due whether to make the appropriatededuction or not. In addition, the Employer may be required by law to effect certaindeductions, e.g., for taxes. All other deductions should be made by the Engineer, takinginto consideration information received from the Employer if appropriate.

The Sub-Clause contains strict stipulations regarding the time allowed to the Engineerfor issuing the payment certificates. The time within which payment must be madeby the Employer, after the Engineer has certified, is covered by Sub-Clause 60.10. It isthe duty of the Engineer to comply with his certification obligation as, if he is notsatisfied concerning any particular item or part thereof, he can omit such item or partand deal with it under Sub-Clause 60.4. In the event of failure by the Employer tomake payment within the times stated, the Employer will be liable to pay interest on theamount overdue, in accordance with Sub-Clause 60.10 and the Contractor may, underClause 69, suspend work or terminate his employment under the Contract.

Paymentof 60.3 (a) Upon the issue of the Taking-Over Certificate withRetention respect to the whole of the Works, one half of the Re-

Money tention Money, or upon the issue of a Taking-OverCertificate with respect to a Section or part of the Per-manent Works only such proportion thereof as theEngineer determines having regard to the relative valueof such Section or part of the Permanent Works, shallbe certified by the Engineer for payment to the Contrac-tor.

(b) Upon the expiration of the Defects Liability Periodfor the Works the other half of the Retention Moneyshall be certified by the Engineer for payment to theContractor. Provided that, in the event of differentDefects Liability Periods having become applicable todifferent Sections or parts of the Permanent Workspursuant to Clause 48, the expression "expiration of theDefects Liability Period" shall, for the purposes of thisSub-Clause, be deemed to mean the expiration of thelatest of such periods. Provided also that if at such time,there shall remain to be executed by the Contractor anywork ordered, pursuant to Clauses 49 and 50, in respectof the Works, the Engineer shall be entitled to withholdcertification until completion of such work of so muchof the balance of the Retention Money as shall, in theopinion of the Engineer, represent the cost of the workremaining to be executed.

The Retention Money is one of the securities held by the Employer to ensure fulfil-ment by the Contractor of his obligations in respect of defects. This Sub-Clause speci-fies under what conditions the Retention Money shall be released to the Contractor.

136 ©FIDIC 1989

Page 137: 35824401 FIDIC Guide to the Use of FIDIC

Correction of 60,4 The Engineer may by any interim certificate make anyCertificates correction or modification in any previous certificate

which shall have been issued by him and shall haveauthority, if any work is not being carried out to hissatisfaction, to omit or reduce the value of such work inany interim certificate.

As stated in the comment on Sub-Clause 60.2 the Engineer may, if he is not satisfiedwith any item, or part thereof, included by the Contractor in his monthly statement,delete such item and include it in a later certificate when he is satisfied that it representsan amount due. Also, the Engineer may make corrections in any monthly certificate toa certificate he has previously issued which he subsequently deems needs correction.

Statementat 60.5 Not later than 84 days after the issue of the Taking-OverCompletion Certificate in respect of the whole of the Works, the

Contractor shall submit to the Engineer a Statement atCompletion with supporting documents showing in de-tail, in the form approved by the Engineer,

(a) the final value of all work done in accordance withthe Contract up to the date stated in such Taking-OverCertificate

(b) any further sums which the Contractor considers tobe due and

(c) an estimate of amounts which the Contractor con-siders will become due to him under the Contract.

The estimated amounts shall be shown separately insuch Statement at Completion. The Engineer shall cer-tify payment in accordance with Sub-Clause 60.2.

It is sometimes contended that the period of 84 days allowed to the Contractor to pro-duce the Statement at Completion is short having regard to the work which is requiredto produce this statement and its binding nature. Much will depend upon the mainte-nance of satisfactory records on the Site and on progressive calculations as the work isexecuted. It is after all in the best interests of the Contractor himself to have hisstatement submitted and substantiated as soon as is practicable.

Final 60.6 Not later than 56 days after the issue of the DefectsStatement Liability Certificate pursuant to Sub-Clause 62.1, the

Contractor shall submit to the Engineer for considera-tion a draft final statement with supporting documentsshowing in detail, in the form approved by the Engineer,

(a) the value of all work done in accordance with theContract and

(b) any further sums which the Contractor considers tobe due to him under the Contract.

©FIDIC 1989 137

Page 138: 35824401 FIDIC Guide to the Use of FIDIC

If the Engineer disagrees with or cannot verify any partof the draft final statement, the Contractor shall submitsuch further information as the Engineer may reasona-bly require and shall make such changes in the draft asmay be agreed between them. The Contractor shall thenprepare and submit to the Engineer the final statementas agreed (for the purposes of these Conditions referredto as the "Final Statement").

The practice for the Contractor to submit a draft final statement to the Engineer, afterthe issue of the Defects Liability Certificate, for agreement between them before the FinalStatement is submitted is one which has proved to operate satisfactorily. Again thereare those who will argue that the time allowed (56 days) is too short but whatever timewas fixed there would be complaints by some that the time is insufficient. If there aresubstantial grounds for the period to be extended the Engineer should request theEmployer's agreement to a reasonable extension. If there are differences of opinionwhich take time to resolve, the Engineer should issue a further interim certificate orcertificates for that part of the draft final statement on which there is no difference ofopinion.

Discharge 60.7 Upon submission of the Final Statement, the Contrac-tor shall give to the Employer, with a copy to the Engi-neer, a written discharge confirming that the total of theFinal Statement represents full and final settlement ofall monies due to the Contractor arising out of or inrespect of the Contract. Provided that such dischargeshall become effective only after payment due under theFinal Certificate issued pursuant to Sub-Clause 60.8 hasbeen made and the performance security referred to inSub-Clause 10.1, if any, has been returned to the Con-tractor.

The Contractor's entitlement to make a claim under the Contract expires when the FinalStatement is submitted. Hence it is reasonable to require the Contractor to give a writ-ten discharge confirming the total. Many Employers require such a discharge. Note thatthe Contractor has two safeguards, namely that the discharge does not take effect untilpayment of the Final Certificate has been made and the performance security, if any, hasbeen returned to the Contractor.

Final 60.8 Within 28 days after receipt of the Final Statement, andCertificate the written discharge, the Engineer shall issue to the

Employer (with a copy to the Contractor) a Final Cer-tificate stating

(a) the amount which, in the opinion of the Engineer, isfinally due under the Contract, and

138 ©FIDIC 1989

Page 139: 35824401 FIDIC Guide to the Use of FIDIC

(b) after giving credit to the Employer for all amountspreviously paid by the Employer and for all sums towhich the Employer is entitled under the Contract, otherthan Clause 47, the balance, if any, due from the Em-ployer to the Contractor or from the Contractor to theEmployer as the case may be.

A time limit is imposed upon the Engineer in regard to his certification to the Employerof the amount due to the Contractor under the Final Certificate. As the Engineer and theContractor will have reached agreement on the basis of the draft final statement, sub-mitted by the Contractor, there is no reason why the Engineer cannot comply within the28 days. In a similar manner to Sub-Clause 60.2, relating to interim certificates, thededuction of liquidated damages, if due, is left to the Employer.

Cessationof 60.9 The Employer shall not be liable to the Contractor forEmployer's any matter or thing arising out of or in connection with

Liability the Contract or execution of the Works, unless theContractor shall have included a claim in respectthereof in his Final Statement and (except in respect ofmatters or things arising after the issue of the Taking-Over Certificate in respect of the whole of the Works)in the Statement at Completion referred to in Sub-Clause 60.5.

This Sub-Clause complements what is written in Sub-Clause 60.7. The subject matter isderived from Sub-Clause 62 (2) of the third edition.

Time for 60.10 The amount due to the Contractor under any interimPayment certificate issued by the Engineer pursuant to this

Clause, or to any other term of the Contract, shall,subject to Clause 47, be paid by the Employer to theContractor within 28 days after such interim certificatehas been delivered to the Employer, or, in the case ofthe Final Certificate referred to in Sub-Clause 60.8,within 56 days, after such Final Certificate has beendelivered to the Employer. In the event of the failure ofthe Employer to make payment within the times stated,the Employer shall pay to the Contractor interest at therate stated in the Appendix to Tender upon all sumsunpaid from the date by which the same should havebeen paid. The provisions of this Sub-Clause are with-out prejudice to the Contractor's entitlement underClause 69.

As a recompense for meeting specific time limits for the submission of the draft finalstatement and the agreement thereof with the Engineer, the Contractor has the right toreceive payment from the Employer within specific time limits.

©FIDIC 1989 139

Page 140: 35824401 FIDIC Guide to the Use of FIDIC

If the Employer fails to meet his commitments under this Sub-Clause, the Contractorbecomes entitled to interest on overdue payments as well as his entitlements under Clause69.

Example sub-clauses for inclusion in Part II to deal with other aspects of payments aregiven below. All are examples only and care should be taken to ensure that the formadopted is consistent with the payment procedures of the country in question and, in theevent that international funding is being provided, complies with the requirements of thefinancing institutions concerned.

Where payments are to be made in various currencies in predetermined proportions andcalculated at fixed rates of exchange the following 3 Sub-Clauses, which should be takentogether, may be added:

Currency 60. The currency of account shall be the (insert name ofof Account currency) and for the purposes of the Contract conver-and Rates sion between (insert name of currency) and other cur-

of Exchange rencies stated in the Appendix to Tender shall be madein accordance with the Table of Exchange Rates in theAppendix to Tender. Conversion between the currenciesstated in such Table other than the (insert name of cur-rency) shall be made at rates of exchange determined byuse of the relative rates of exchange between suchcurrencies and the (insert name of currency) set outtherein.

Payments 60. All payments to the Contractor by the Employer shallto be made

Contractor(a) in the case of payment(s) under Sub-Clauses 70.2

and (insert number of any other applicable Clause),in (insert name of currency/ies);

(b) in the case of payments for certain provisional sumitems excluded from the Appendix to Tender, in thecurrencies and proportions applicable to these itemsat the time when the Engineer gives instructions forthe work covered by these items to be carried out;

(c) in any other case, including Increase or Decrease ofCosts under Sub-Clause 70.1, in the currencies andproportions stated in the Appendix to Tender as ap-plicable to such payment provided that the propor-tion of currencies stated in the Appendix to Tendermay from time to time upon the application of eitherparty be varied as may be agreed.

140 © FIDIC 1989

Page 141: 35824401 FIDIC Guide to the Use of FIDIC

Payments 60. All payments to the Employer by the Contractor includ-to ing payments made by way of deduction or set-off shall

Employer be made

(a) in the case of credit(s) under Sub-Clause(s) 70.2 and(insert number of any other applicable Clause), in(insert name of currency/ies);

(b) in the case of liquidated damages under Clause 47,in (insert name of currency/ies);

(c) in the case of reimbursement of any sum previouslyexpended by the Employer, in the currency in whichthe sum was expended by the Employer;

(d) in any other case, in such currency as may be agreed.

If the part payable in a particular currency of any sumpayable to the Contractor is wholly or partly insufficientto satisfy by way of deduction or set-off a payment dueto the Employer in that currency, in accordance with theprovisions of this Sub-Clause, then the Employer mayif he so desires make such deduction or set-off whollyor partly as the case may be from the balance of suchsum payable in other currencies.

Where all payments are to be made in one currency the following Sub-Clause may beadded:

Currency 60. The currency of account shall be the (insert of name ofof Account currency) and all payments made in accordance with the

and Contract shall be in (insert name of currency). SuchPayments (insert name of currency) other than for local costs, shall

be fully convertible. The percentage of such paymentsattributed to local costs shall be as stated in the Appen-dix to Tender.

Where place of payment is to be defined the following Sub-Clause may be added:

Place of 60. Payments to the Contractor by the Employer shall bePayment made into a bank account nominated by the Contractor

in the country of the currency of payment. Where pay-ment is to be made in more than one currency separatebank accounts shall be nominated by the Contractor inthe country of each currency and payments shall bemade by the Employer accordingly.

©FIDIC 1989 141

Page 142: 35824401 FIDIC Guide to the Use of FIDIC

Where provision is to be included for an advance payment the following Sub-Clause maybe added:

Advance 60. An advance payment of the amount stated in the Appen-Payment dix to Tender shall, following the presentation by the

Contractor to the Employer of an approved performancesecurity in accordance with Sub-Clause 10.1 and a Guar-antee in terms approved by the Employer for the fullvalue of the advance payment, be certified by the Engi-neer for payment to the Contractor. Such Guaranteeshall be progressively reduced by the amount repaid bythe Contractor as indicated in interim certificates of theEngineer issued in accordance with this Clause. Theadvance payment shall not be subject to retention. Theadvance payment shall be repaid by way of reduction ininterim certificates commencing with the next certificateissued after the total certified value of the PermanentWorks and any other items in the Bill of Quantities(excluding the deduction of retention) exceeds (insertfigure) per cent of the sum stated in the Letter of Ac-ceptance. The amount of the reduction in each interimcertificate shall be one (insert fraction) of the differencebetween the total value of the Permanent Works and anyother items in the Bill of Quantities (excluding thededuction of retention) due for certification in such in-terim certificate and the said value in the last precedinginterim certificate until the advance payment has beenrepaid in full. Provided that upon the issue of a Taking-Over Certificate for the whole of the Works or upon thehappening of any of the events specified in Sub-Clause63.1 or termination under Clauses 65, 66 or 69, thewhole of the balance then outstanding shall immediatelybecome due and payable by the Contractor to the Em-ployer.

Approval only 61.1 Only the Defects Liability Certificate, referred to inby Defects Clause 62, shall be deemed to constitute approval of the

Liability Works.Certificate

In major contracts, it is common for the Works to be taken over in Sections or parts,each giving rise to a separate Taking-Over Certificate and, consequently, to a separateDefects Liability Period. However, Clauses 61 and 62 make it clear that there isonly one Defects Liability Certificate, which is issued at the expiration of the last DefectsLiability Period to occur under the Contract. This Certificate establishes that the Con-tractor has fulfilled his obligation under the Contract to execute, complete and remedyany defects in the Works to the satisfaction of the Engineer, and that in consequence,the Contractor's physical obligations in relation to the Contract have been completed.

142 © FIDIC 1989

Page 143: 35824401 FIDIC Guide to the Use of FIDIC

Defects 62.1 The Contract shall not be considered as completed untilLiability a Defects Liability Certificate shall have been signed by

Certificate the Engineer and delivered to the Employer, with a copyto the Contractor, stating the date on which the Con-tractor shall have completed his obligations to executeand complete the Works and remedy any defects thereinto the Engineer's satisfaction. The Defects Liability Cer-tificate shall be given by the Engineer within 28 daysafter the expiration of the Defects Liability Period, or,if different defects liability periods shall become appli-cable to different Sections or parts of the PermanentWorks, the expiration of the latest such period, or assoon thereafter as any works instructed, pursuant toClauses 49 and 50, have been completed to the satisfac-tion of the Engineer. Provided that the issue of theDefects Liability Certificate shall not be a conditionprecedent to payment to the Contractor of the secondportion of the Retention Money in accordance with theconditions set out in Sub-Clause 60.3.

Although the Defects Liability Periods expire automatically the expiration of each isnormally recorded in a letter from the Engineer to the Employer with a copy to theContractor. When the last Defects Liability Period ends, any outstanding work willnormally only represent a very small proportion of the total Contract value but, to pro-tect the Employer, the Defects Liability Certificate is not issued until this work has beensatisfactorily completed.

The procedure for the release of the Retention Money in relation to the Taking-OverCertificates and to the expiration of the Defects Liability Period for the Works is de-tailed in Sub-Clause 60.3.

Unfulfilled 62.2 Notwithstanding the issue of the Defects Liability Cer-Obligations tificate the Contractor and the Employer shall remain

liable for the fulfilment of any obligation incurred un-der the provisions of the Contract prior to the issue ofthe Defects Liability Certificate which remains unper-formed at the time such Defects Liability Certificate isissued and, for the purposes of determining the natureand extent of any such obligation, the Contract shall bedeemed to remain in force between the parties to theContract.

Notwithstanding the issue of the Defects Liability Certificate, each party remains liablefor the fulfilment of any obligation incurred under the Contract which remains unper-formed at the time such Defects Liability Certificate is issued and, for this purpose, theContract remains in force between the parties. Such unperformed obligations can onlybe of a financial or administrative nature as, with the issue of the Defects LiabilityCertificate, the Contractor's physical obligations will have been completed (see commen-tary to Sub-Clause 61.1).

Any outstanding liabilities of the Employer to the Contractor should not delay either therelease of the performance security or the issue of the Defects Liability Certificate.

© FIDIC 1989 143

Page 144: 35824401 FIDIC Guide to the Use of FIDIC

REMEDIES

Default of 63.1 If the Contractor is deemed by law unable to pay hisContractor debts as they fall due, or enters into voluntary or invol-

untary bankruptcy, liquidation or dissolution (other thana voluntary liquidation for the purposes of amalgama-tion or reconstruction), or becomes insolvent, or makesan arrangement with, or assignment in favour of, hiscreditors, or agrees to carry out the Contract under acommittee of inspection of his creditors, or if a receiver,administrator, trustee or liquidator is appointed overany substantial part of his assets, or if, under any lawor regulation relating to reorganisation, arrangement orreadjustment of debts, proceedings are commencedagainst the Contractor or resolutions passed in connec-tion with dissolution or liquidation or if any steps aretaken to enforce any security interest over a substantialpart of the assets of the Contractor, or if any act is doneor event occurs with respect to the Contractor or hisassets which, under any applicable law has a substan-tially similar effect to any of the foregoing acts orevents, or if the Contractor has contravened Sub-Clause3.1, or has an execution levied on his goods, or if theEngineer certifies to the Employer, with a copy to theContractor that, in his opinion, the Contractor:

(a) has repudiated the Contract, or

(b) without reasonable excuse has failed(i) to commence the Works in accordance with Sub-Clause 41.1, or(ii) to proceed with the Works, or any Section thereof,within 28 days after receiving notice pursuant to Sub-Clause 46.1, or

(c) has failed to comply with a notice issued pursuantto Sub-Clause 37.4 or an instruction issued pursuant toSub-Clause 39.1 within 28 days after having received,it, or

(d) despite previous warning from the Engineer, in writ-ing, is otherwise persistently or flagrantly neglecting tocomply with any of his obligations under the Contract,or

(e) has contravened Sub-Clause 4.1,

then the Employer may, after giving 14 days' notice tothe Contractor, enter upon the Site and the Works andterminate the employment of the Contractor withoutthereby releasing the Contractor from any of his obli-gations or liabilities under the Contract, or affecting therights and authorities conferred on the Employer or the

144 © FIDIC 1989

Page 145: 35824401 FIDIC Guide to the Use of FIDIC

Engineer by the Contract, and may himself complete theWorks or may employ any other contractor to completethe Works. The Employer or such other contractor mayuse for such completion so much of the Contractor'sEquipment, Temporary Works and materials as he orthey may think proper.

This Sub-Clause defines the events which, under the Conditions, constitute events ofdefault by the Contractor. The Sub-Clause also provides that, if an event of defaultoccurs, the Employer may enter on the Site, terminate the Contractor's employment andthereby become entitled to certain rights as against the Contractor, the Contractor'sEquipment, Temporary Works and materials.

The Sub-Clause presupposes that if an event of default of the Contractor has occurredand the Employer elects to terminate the Contractor's employment, the Employer willwish to have the Works completed with as little delay as possible. If this is the case itmay be useful to clarify that the event of default referred to in this Sub-Clause, sub-para (d) i.e., "...persistently or flagrantly neglecting to comply with any of his obliga-tions under the Contract" would include seriously deviating from the programme orfrom the Specification (or both), or putting the Works seriously at risk. With this typeof event, the Engineer takes the initiative and the Sub-Clause stipulates that heshall, before certifying the event, give the Contractor a "warning" by a written notice.Unlike the third edition, only one "warning" is required by the fourth edition. It istherefore important that the Engineer, in his "warning" explicitly refers to Clause 63 andclearly describes the event which gives rise to the "warning".

The Employer may, after giving fourteen days' notice, enter upon the Site and terminatethe Contractor's employment. This fourteen-day period is not intended to give theContractor an opportunity to remedy the default, but to permit the Contractor to makethe preparations necessary to leave the Site.

After terminating the Contractor's employment, the Employer may himself complete theWorks or employ another contractor to do so. For this purpose the Employer or suchother contractor may use the Contractor's Equipment, Temporary Works and materi-als.

Valuation 63.2 The Engineer shall, as soon as may be practicable afterat Date of any such entry and termination by the Employer, fix and

Termination determine ex parte, or by or after reference to the par-ties or after such investigation or enquiries as he maythink fit to make or institute, and shall certify:

(a) what amount (if any) had, at the time of such entryand termination, been reasonably earned by or wouldreasonably accrue to the Contractor in respect of workthen actually done by him under the Contract, and

© FIDIC 1989 145

Page 146: 35824401 FIDIC Guide to the Use of FIDIC

(b) the value of any of the said unused or partially usedmaterials, any Contractor's Equipment and any Tempo-rary Works.

After the Employer terminates the Contractor's employment, the Engineer determinesthe amount (if any) earned by the Contractor in respect of work performed and thevalue of any unused or partially used materials, Contractor's Equipment andTemporary Works. The Engineer may make such determination himself (ex parte)or after hearing the parties to the Contract. The Engineer's determination andresulting certification, establishes the financial position between the two parties as atthe time of termination.

Paymentafter 63.3 Ifthe Employer terminates the Contractor's employmentTermination under this Clause, he shall not be liable to pay to the

Contractor any further amount (including damages) inrespect of the Contract until the expiration of the De-fects Liability Period and thereafter until the costs ofexecution, completion and remedying of any defects,damages for delay in completion (if any) and all otherexpenses incurred by the Employer have been ascer-tained and the amount thereof certified by the Engineer.The Contractor shall then be entitled to receive onlysuch sum (if any) as the Engineer may certify wouldhave been payable to him upon due completion by himafter deducting the said amount. If such amount exceedsthe sum which would have been payable to the Contrac-tor on due completion by him, then the Contractor shall,upon demand, pay to the Employer the amount of suchexcess and it shall be deemed a debt due by the Con-tractor to the Employer and shall be recoverable ac-cordingly.

If the Employer terminates the Contractor's employment, he is not liable to pay theContractor any further amounts (including damages) until the expiration of the De-fects Liability Period and the certification by the Engineer of the cost of executionand remedying of any defects, damages for delay in completion (if any) and otherexpenses incurred by the Employer as a result of the Contractor's default.

Assignment 63.4 Unless prohibited by law, the Contractor shall, if soofBenefit instructed by the Engineer within 14 days of such entry

ofAgreement and termination referred to in Sub Clause 63.1, assignto the Employer the benefit of any agreement for thesupply of any goods or materials or services and/or forthe execution of any work for the purposes of the Con-tract, which the Contractor may have entered into.

146 © FIDIC 1989

Page 147: 35824401 FIDIC Guide to the Use of FIDIC

The Contractor is obliged, if instructed by the Engineer, to assign to the Employer thebenefit of any agreement for the supply of goods, materials or services required for theexecution of the Works and/or for the purposes of the Contract.

If the event of default referred to in Sub-Clause 63.1(c) occurs, the Contract providesalternative measures under Clause 39 and (in case of urgency) Clause 64. Furthermore,upon the occurrence of any event of default under Sub-Clause 63.1, in addition to therights prescribed by the Clause, the Employer may be entitled to other rights and reme-dies under the law governing the Contract. However, it is unlikely in most cases that therights and remedies under the law governing the Contract will be more favourable to theEmployer than those provided for in Clause 63.

Urgent 641 If, by reason of any accident, or failure, or other eventRemedial occurring to, in, or in connection with the Works, or any

Work part thereof, either during the execution of the Works,or during the Defects Liability Period, any remedial orother work is, in the opinion of the Engineer, urgentlynecessary for the safety of the Works and the Contrac-tor is unable or unwilling at once to do such work, theEmployer shall be entitled to employ and pay otherpersons to carry out such work as the Engineer mayconsider necessary. If the work or repair so done by theEmployer is work which, in the opinion of the Engineer,the Contractor was liable to do at his own cost underthe Contract, then all costs consequent thereon or inci-dental thereto shall, after due consultation with theEmployer and the Contractor, be determined by theEngineer and shall be recoverable from the Contractorby the Employer, and may be deducted by the Employerfrom any monies due or to become due to the Contrac-tor and the Engineer shall notify the Contractor accord-ingly, with a copy to the Employer. Provided that theEngineer shall, as soon after the occurence of any suchemergency as may be reasonably practicable, notify theContractor thereof

If, during the execution of the Works or during the Defects Liability Period, the Engi-neer finds that repair work is urgently necessary for the safety of the Works, and theContractor does not comply with an instruction to carry out the work at once, Sub-Clause64.1 empowers the Employer to engage others to carry out such work. If, in theopinion of the Engineer, the Contractor was liable to do such work at his own cost underthe Contract, then the costs thereof are recoverable from the Contractor.

Other Clauses that may be relevant to urgent repair work include Sub-Clauses 20.1, 39.2and, for the Defects Liability Period, Sub-Clauses 49.4 and 50.1. Sub-Clause 40.1dealing with suspension might also have some relevance.

© FIDIC 1989 147

Page 148: 35824401 FIDIC Guide to the Use of FIDIC

SPECIAL RISKS

Although the Contractor is responsible for the care of the Works until the date of issueof the Taking-Over Certificate there are certain risks for which he is not responsiblewhich are now referred to as Employer's Risks (see Sub-Clause 20.4). Risks listed undersub-paragraphs a,b,c,d and e of Sub-Clause 20.4 are included under the definition ofSpecial Risks in Sub-Clause 65.2 with the exception that the Employer is not respon-sible for the risks covered by Sub-Clause 20.4 (b) - 'rebellion, revolution, insurrection,or military or usurped power, or civil war' outside the country in which the Works arebeing constructed. The reason for this is that the Employer should be able to assesssuch risks in the country where the Works are to be constructed but it would beunreasonable for the Employer to bear such risks in the country of the Contractor orcountries through which, for example, the Contractor may have elected to transportTemporary Works, Contractor's Equipment, Plant and materials as well as staff andlabour.

No Liability 65.1 The Contractor shall be under no liability whatsoeverforSpecial in consequence of any of the special risks referred to in

Risks Sub-Clause 65.2, whether by way of indemnity or oth-erwise, for or in respect of:

(a) destruction of or damage to the Works, save to workcondemned under the provisions of Clause 39 prior tothe occurrence of any of the said special risks, or

(b) destruction of or damage to property, whether of theEmployer or third parties, or

(c) injury or loss of life.

This Sub-Clause states clearly that the Contractor is not responsible for the consequencesof special risks in respect of certain designated events.

SpecialRisks 65.2 The special risks are:

(a) the risks defined under paragraphs (a), (c), (d) and(e) of Sub-Clause 20.4, and

(b) the risks defined under paragraph (b) of Sub-Clause20.4 insofar as these relate to the country in which theWorks are to be executed.

This Sub-Clause defines the special risks.

148 © FIDIC 1989

Page 149: 35824401 FIDIC Guide to the Use of FIDIC

Damage to 65.3 If the Works or any materials or Plant on or near or inWorks by transit to the Site, or any of the Contractor's Equipment,

Special Risks sustain destruction or damage by reason of any of thesaid special risks, the Contractor shall be entitled topayment in accordance with the Contract for any Per-manent Works duly executed and for any materials orPlant so destroyed or damaged and, so far as may berequired by the Engineer or as may be necessary for thecompletion of the Works, to payment for:

(a) rectifying any such destruction or damage to theWorks, and

(b) replacing or rectifying such materials or Contrac-tor's Equipment

and the Engineer shall determine an addition to theContract Price in accordance with Clause 52 (whichshall in the case of the cost of replacement of Contrac-tor's Equipment include the fair market value thereof asdetermined by the Engineer) and shall notify the Con-tractor accordingly, with a copy to the Employer.

The manner in which the Contractor will be compensated for any loss or damage sus-tained as a result of special risks is set out here.

Projectile, 65.4 Destruction, damage, injury or loss of life caused by theMissile explosion or impact, whenever and wherever occurring,

of any mine, bomb, shell, grenade, or other projectile,missile, munition, or explosive of war, shall be deemedto be a consequence of the said special risks.

The responsibility under this Sub-Clause differs from the general case in that destruc-tion, damage, injury or loss of life resulting from the impact or explosion of variousexplosives of war including missiles, mines, bombs, etc., are special risks wherever theyoccur and the Employer's Risk in relation thereto is not limited to the country in whichthe Works are being constructed.

Increased 65.5 Save to the extent that the Contractor is entitled toCostsarising payment under any other provision of the Contract, thefrom Special Employer shall repay to the Contractor any costs of the

Risks execution of the Works (other than such as may be at-tributable to the cost of reconstructing work condemnedunder the provisions of Clause 39 prior to the occur-rence of any special risk) which are howsoever attrib-utable to or consequent on or the result of or in any waywhatsoever connected with the said special risks, sub-ject however to the provisions in this Clause hereinaf-ter contained in regard to outbreak of war, but theContractor shall, as soon as any such cost comes to hisknowledge, forthwith notify the Engineer thereof. The

© FIDIC 1989 149

Page 150: 35824401 FIDIC Guide to the Use of FIDIC

Engineer shall, after due consultation with the Employerand the Contractor, determine the amount of the Con-tractor's costs in respect thereof which shall be addedto the Contract Price and shall notify the Contractoraccordingly, with a copy to the Employer.

This Sub-Clause deals with compensation of the Contractor by the Employer for costsof executing the Works as the result of a Special Risk.

Outbreakof 65.6 If, during the currency of the Contract, there is an out-War break of war, whether war is declared or not, in any

part of the world which, whether financially or other-wise, materially affects the execution of the Works, theContractor shall, unless and until the Contract is termi-nated under the provisions of this Clause, continue touse his best endeavours to complete the execution of theWorks. Provided that the Employer shall be entitled, atany time after such outbreak of war, to terminate theContract by giving notice to the Contractor and, uponsuch notice being given, the Contract shall, except as tothe rights of the parties under this Clause and to theoperation of Clause 67, terminate, but without prejudiceto the rights of either party in respect of any antecedentbreach thereof.

This Sub-Clause sets out the responsibilities of the parties in the event that a war, whetherdeclared or not, materially affects the execution of the Contract.

Removalof 65.7 If the Contract is terminated under the provisions ofContractor's Sub-Clause 65.6, the Contractor shall, with all reason-

Equipmenton able dispatch, remove from the Site all Contractor'sTermination Equipment and shall give similar facilities to his Sub-

contractors to do so.

If war causes the termination of the Contract the Contractor will wish, if it is possible,to remove his Contractor's Equipment, etc., from the Site. This Sub-Clause obliges himto do so and requires him to give the same facilities to his Subcontractors.

Payment if 65.8 Ifthe Contract is terminated as aforesaid, the Contrac-Contract tor shall be paid by the Employer, insofar as such

Terminated amounts or items have not already been covered bypayments on account made to the Contractor, for allwork executed prior to the date of termination at therates and prices provided in the Contract and in addi-tion.

150 ©FIDIC 1989

Page 151: 35824401 FIDIC Guide to the Use of FIDIC

(a) The amounts payable in respect of any preliminaryitems referred to in the Bill of Quantities, so far as thework or service comprised therein has been carried outor performed, and a proper proportion of any such itemswhich have been partially carried out or performed.

(b) The cost of materials, Plant or goods reasonablyordered for the Works which have been delivered to theContractor or of which the Contractor is legally liableto accept delivery, such materials, Plant or goods be-coming the properly of the Employer upon such pay-ments being made by him.

(c) A sum being the amount of any expenditure reasona-bly incurred by the Contractor in the expectation ofcompleting the whole of the Works insofar as suchexpenditure has not been covered by any other paymentsreferred to in this Sub-Clause.

(d) Any additional sum payable under the provisions ofSub-Clauses 65.3 and 65.5.

(e) Such proportion of the cost as may be reasonable,taking into account payments made or to be made forwork executed, of removal of Contractor's Equipmentunder Sub-Clause 65.7 and, f required by the Contrac-tor, return thereof to the Contractor's main plant yardin his country of registration or to other destination, atno greater cost.

(f) The reasonable cost of repatriation of all the Con-tractor's staff and workmen employed on or in connec-tion with the Works at the time of such termination.

Provided that against any payment due from the Em-ployer under this Sub-Clause, the Employer shall beentitled to be credited with any outstanding balancesdue from the Contractor for advances in respect of Con-tractor's Equipment, materials and Plant and any othersums which, at the date of termination, were recoverableby the Employer from the Contractor under the terms ofthe Contract. Any sums payable under this Sub-Clauseshall, after due consultation with the Employer and theContractor, be determined by the Engineer who shallnotify the Contractor accordingly, with a copy to theEmployer.

This Sub-Clause sets out the entitlement of the Contractor in the event that the Contractis terminated as the result of special risks.

©FIDIC 1989 151

Page 152: 35824401 FIDIC Guide to the Use of FIDIC

RELEASE FROM PERFORMANCE

Payment in 66.1 Ifany circumstance outside the control of both partiesEventof arises after the issue of the Letter of Acceptance which

Release from renders it impossible or unlawful for either party to fulfilPerformance his contractual obligations, or under the law governing

the Contract the parties are released from further per-formance, then the sum payable by the Employer to theContractor in respect of the work executed shall be thesame as that which would have been payable underClause 65 if the Contract had been terminated under theprovisions of Clause 65.

This Sub-Clause deals with any situation which makes it impossible or unlawful for oneor both parties to meet their obligations under the Contract because of circumstanceswhich are beyond the control of both parties or where under the law governing theContract the parties are released from further performance. This concept is very similarto the force majeure (exemption) clause of the International Chamber of Commerce (ICC)publication No. 421. The party claiming release from performance is required to provethe effect of the impediment on the performance of his contractual obligations. TheClause can be invoked by either of the parties whereas, under Sub-Clause 65.6, termina-tion can only be invoked by the Employer.

It should be observed that the effect of this Sub-Clause is different from that of the usualforce majeure clause. Under the usual force majeure clause, upon the occurrence of anevent of force majeure each party is released from further performance and, consequently,bears its own losses. Here, upon the occurrence of circumstances which prevent per-formance, though the parties are released from further performance, the Contractor isentitled to payment on the basis provided for in Clause 65. If and when the circum-stances which prevent performance should cease, the parties may enter into a new con-tract.

Other Clauses in the FIDIC Conditions which refer to preventing impediments are:Clause 40 - Suspension, in particular Sub-Clause 40.3, Clause 13 referring to physicalimpossibility and Clause 20 dealing with Care of the Works and Employer's Risks.

152 ©FIDIC 1989

Page 153: 35824401 FIDIC Guide to the Use of FIDIC

SETTLEMENT OF DISPUTES

Although this Clause is generally referred to as the arbitration clause it has a far widerimpact. It provides mechanisms for resolving disputes between the parties as well asincluding provisions for the dispute or disputes to be referred to arbitration as a lastresort. An important factor to note is that by this Clause the parties waive their rights tosubmit disputes related to the Contract to any other legal means of dispute resolution, inparticular to any public court which might have jurisdiction over the dispute.

It also contains an agreement between the parties to take two steps before enteringinto arbitration viz., first to submit the dispute to the Engineer for his decision and,second, if such decision is not acceptable, to attempt to settle the dispute amicably be-tween themselves. However, arbitration may be commenced 56 days (or as otherwiseagreed between the parties) after a notification to that effect, whether or not the secondstep has been taken. A second step was not included in previous editions and its inser-tion draws the attention of the parties to a means of avoiding costly arbitration pro-ceedings which consume both time and effort. The new provisions can possibly openup that avenue for a party who could not otherwise be allowed by regulations to enterinto discussions to achieve amicable settlement.

Another innovation in the fourth edition is to be found in Sub-Clause 67.4. Under thisSub-Clause, either party may, if the other has failed to comply with a final and bindingdecision of the Engineer, refer such failure to arbitration. The intention of so doing wouldbe to have the decision made an arbitral award and thereby enforceable under interna-tional conventions.

It has been contended in the past by some commentators on the FIDIC Conditions thatthe Engineer who is retained and paid by the Employer should not undertake a quasi-arbitral role. This comment has often stemmed from a misunderstanding of what theConditions state. In the third edition the Engineer's decision was not binding upon theparties and it is not binding in the fourth edition, if either party challenges it in accor-dance with the procedure laid down in Clause 67.

Engineer's 67.1 Ifa dispute of any kind whatsoever arises between theDecision Employer and the Contractor in connection with, or

arising out of, the Contract or the execution of theWorks, whether during the execution of the Works orafter their completion and whether before or after re-pudiation or other termination of the Contract, includ-ing any dispute as to any opinion, instruction, determi-nation, certificate or valuation of the Engineer, thematter in dispute shall, in the first place, be referred inwriting to the Engineer, with a copy to the other party.Such reference shall state that it is made pursuant to thisClause. No later than the eighty-fourth day after the dayon which he received such reference the Engineer shallgive notice of his decision to the Employer and theContractor. Such decision shall state that it is madepursuant to this Clause.

Unless the Contract has already been repudiated orterminated, the Contractor shall, in every case, continueto proceed with the Works with all due diligence and theContractor and the Employer shall give effect forthwithto every such decision of the Engineer unless and until

©FIDIC 1989 153

Page 154: 35824401 FIDIC Guide to the Use of FIDIC

the same shall be revised, as hereinafter provided, in anamicable settlement or an arbitral award.

If either the Employer or the Contractor be dissatisfiedwith any decision of the Engineer, or if the Engineerfails to give notice of his decision on or before theeighty-fourth day after the day on which he received thereference, then either the Employer or the Contractormay, on or before the seventieth day after the day onwhich he received notice of such decision, or on orbefore the seventieth day after the day on which the saidperiod of 84 days expired, as the case may be, givenotice to the other party, with a copy for information tothe Engineer, of his intention to commence arbitration,as hereinafter provided, as to the matter in dispute. Suchnotice shall establish the entitlement of the party givingthe same to commence arbitration, as hereinafter pro-vided, as to such dispute and, subject to Sub-Clause67.4, no arbitration in respect thereof may be com-menced unless such notice is given.

If the Engineer has given notice of his decision as to amatter in dispute to the Employer and the Contractorand no notice of intention to commence arbitration asto such dispute has been given by either the Employeror the Contractor on or before the seventieth day afterthe day on which the parties received notice as to suchdecision from the Engineer, the said decision shallbecome final and binding upon the Employer and theContractor.

The term 'decision', in the FIDIC Conditions, has been reserved for use in Clause 67. Ifthere is a difference of opinion between the parties to the Contract that is, between theEmployer and the Contractor, it is probable that such difference of opinion will havearisen as the result of an instruction given by the Engineer. If the matter cannot beclarified to the satisfaction of both parties, either may in the first instance refer the disputeto the Engineer for a decision, stating that reference is made under Clause 67.

Any such reference to the Engineer must be copied to the other party. In this respect,it should be noted that generally when the reference of a dispute is made to the Engi-neer, under Clause 67, it is dealt with by a senior person in the Engineer's firm, andpreferably one who has not been involved in the day to day administration of the Con-tract. The Engineer's decision which is given under Clause 67 for settlement of thedispute will not be final and binding upon either of the two parties if one of the partiesdisagrees with it and gives notice within 70 days of an intention to commence arbitra-tion. This is a shorter period for challenging a decision than in the third edition wherethe period was 90 days.

The action necessary to prevent a decision from becoming final and binding is a notifi-cation by one party (no longer to the Engineer) to the other party of his intention tocommence arbitration as to the subject matter of the decision. The notification shall becopied to the Engineer for information but the legal effect lies in the notice to the otherparty, which establishes the entitlement of the party giving the notification to arbitratethe matter in dispute.

154 ©FIDIC 1989

Page 155: 35824401 FIDIC Guide to the Use of FIDIC

This Clause does not make any exception as to the reference to the Engineer for hisdecision on matters in dispute having mainly a legal character. It has been argued that,with respect to disputes having mainly a legal character, the Engineer could alwaysrefrain from giving a decision. More in line with the intention of the Clause would bethat the Engineer gives his decision after having taken legal advice on the matter indispute.

Amicable 67.2 Where notice of intention to commence arbitration as toSettlement a dispute has been given in accordance with Sub-Clause

67.1, arbitration of such dispute shall not be commencedunless an attempt has first been made by the parties tosettle such dispute amicably. Provided that, unless theparties otherwise agree, arbitration may be commencedon or after the fifty-sixth day after the day on whichnotice of intention to commence arbitration of suchdispute was given, whether or not any attempt at ami-cable settlement thereof has been made.

If the parties can discuss and agree upon a solution to a matter in dispute between themthis will have many advantages over going to arbitration. However, in some countries ithas been maintained that if there is no reference to amicable settlement in the Contractthen the individual responsible for administering the Contract may have no right to enterinto negotiations for an amicable settlement. This Sub-Clause makes provision for thispossibility but sets a time limit so that the settlement discussions will not be prolongedindefinitely. Whether or not an attempt at amicable settlement has been made within 56days, the parties can thereafter proceed with arbitration.

The parties may consider it to be advantageous to agree to a procedure for amicablesettlement at an early stage in the Contract before any dispute arises.

The amicable settlement is essentially a process to be left to the Employer and theContractor. Of course, assistance may be called for from the Engineer, where appropri-ate.

Arbitration 67,3 Any dispute in respect of which:(a) the decision, fany, of the Engineer has not becomefinal and binding pursuant to Sub-Clause 67.1, and(b) amicable settlement has not been reached within theperiod stated in Sub-Clause 67.2shall be finally settled, unless otherwise specified in theContract, under the Rules of Conciliation and Arbitra-tion of the International Chamber of Commerce by oneor more arbitrators appointed under such Rules. Thesaid arbitrator/s shall have full power to open up, re-view and revise any decision, opinion, instruction, de-termination, certificate or valuation of the Engineerrelated to the dispute.

Neither party shall be limited in the proceedings beforesuch arbitrator/s to the evidence or arguments put be-fore the Engineer for the purpose of obtaining his saiddecision pursuant to Sub-Clause 67.1. No such decisionshall disqualify the Engineer from being called as awitness and giving evidence before the arbitrator/s onany matter whatsoever relevant to the dispute.

©FIDIC 1989 155

Page 156: 35824401 FIDIC Guide to the Use of FIDIC

Arbitration may be commenced prior to or after com-pletion of the Works, provided that the obligations of theEmployer, the Engineer and the Contractor shall not bealtered by reason of the arbitration being conductedduring the progress of the Works.

Arbitration proper may be commenced any time prior to completion of the Works or aftersuch completion provided that the parties have first attempted to settle the disputeamicably (Sub-Clause 67.2) but not succeeded or the stipulated time period for ami-cable settlement has elapsed.

In selecting the place of arbitration the parties should consider, among other things, theneutrality of the location, the suitability of local law and the administration servicesavailable. If no place of arbitration is stipulated then, under the Rules of Arbitration ofthe International Chamber of Commerce (ICC), the place would be chosen by the ICCCourt of Arbitration.

The Sub-Clause provides that if no alternative system of arbitration is stated in Part IIthen any arbitration will be under the ICC arbitration rules. If consideration is given toreplacing these rules by any other it should be borne in mind that the ICC Court ofArbitration in Paris has functioned for more than 60 years in the administration ofarbitration and that arbitrators and legal counsel in a great number of countries through-out the world have experience of this system.

However, there are other organisations, such as UNCITRAL, which have issued rulesfor dealing with disputes under international contracts. Where it is decided that a settle-ment of dispute procedure, other than that of the ICC, should be used, the Sub-Clausemay be varied in Part II. The following is an example text:

Arbitration 67.3 Following paragraph (b), delete the words 'shall befinally settled ... International Chamber of Commerce'and substitute 'shall be finally settled under UN-CITRAL Arbitration Rules as administered by (insertname of administering authority)'.

Where an alternative to the ICC procedure is selected, care should be taken to establishthat the alternative is appropriate for the circumstances of the Contract and that thewording of Clause 67 is checked and amended as may be necessary to avoid any ambi-guity with the alternative.

Failure to 67.4 Where neither the Employer nor the Contractor hasComply with given notice of intention to commence arbitration of a

Engineer's dispute within the period stated in Sub-Clause 67.1 andDecision the related decision has become final and binding, ei-

ther party may, if the other party fails to comply withsuch decision, and without prejudice to any other rightsit may have, refer the failure to arbitration in accor-dance with Sub-Clause 67.3. The provisions of Sub-Clauses 67.1 and 67.2 shall not apply to any such ref-erence.

It may happen that a party who has not disputed an Engineer's decision subsequentlyfails to comply with it. This Sub-Clause affords the opportunity for the other party torefer such failure to arbitration for the purposes of obtaining an arbitration award thatmay be enforced internationally.

156 ©FIDIC 1989

Page 157: 35824401 FIDIC Guide to the Use of FIDIC

NOTICES

Notice to 68.1 All certificates, notices or instructions to be given to theContractor Contractor by the Employer or the Engineer under the

terms of the Contract shall be sent by post, cable, telexor facsimile transmission to or left at the Contractor'sprincipal place of business or such other address as theContractor shall nominate for that purpose.

Notice to 68.2 Any notice to be given to the Employer or the EngineerEmployer under the terms of the Contract shall be sent by post,

andEngineer cable, telex or facsimile transmission to or left at therespective addresses nominated for that purpose in PartII of these Conditions.

Change of 68.3 Either party may change a nominated address to an-Adress other address in the country where the Works are being

executed by prior notice to the other party, with a copyto the Engineer, and the Engineer may do so by priornotice to both parties.

This Clause deals with communications of various kinds between the parties and withthe Engineer.

Formal notices are required by the Contract in different situations: to the Contractor, forexample, in Sub-Clause 41.1 (Commencement of Works), Sub-Clause 52.2 (Power ofEngineer to Fix Rates), Sub-Clause 63.1 (Default of Contractor), Sub-Clause 65.6 (Out-break of War) and Clause 67 (Settlement of Disputes); to the Employer, for example, inClause 67 (Settlement of Disputes) and in Sub-Clause 69.4 (Contractor's Entitlement toSuspend Work); and to the Engineer, for example, in Sub-Clause 6.3 (Disruption ofProgress), Sub-Clause 12.2 (Adverse Physical Obstructions or Conditions), Sub-Clause52.2 (Power of Engineer to Fix Rates), Sub-Clause 53.1 (Notice of Claims), etc.

It is important that any such notice complies with the Clause being relied upon and besent to the address nominated for such receipt. For the Contractor, the address would beits principal place of business (the head office). Later, during the execution of theContract, this might be changed to an office near the location of the Employer (but notnecessarily the Site office).

The Contract requires numerous other types of communications such as certificates andinstructions and each party should establish at an early stage appropriate procedures forsending and receiving these.

The following entry is required to be included in Part II:

Notice to 68.2 For the purposes of this Sub-Clause the respective ad-Employer dresses are:

Engineer (a) The Employer (insert address)

(b) The Engineer (insert address)

©FIDIC 1989 157

Page 158: 35824401 FIDIC Guide to the Use of FIDIC

DEFAULT OF EMPLOYER

Clause 69 emphasises the importance of an uninterrupted flow to the Contractor ofpayments to which he is entitled.

Default of 69.1 In the event of the Employer:Employer

(a) failing to pay to the Contractor the amount dueunder any certificate of the Engineer within 28 daysafter the expiry of the time stated in Sub-Clause 60.10within which payment is to be made, subject to anydeduction that the Employer is entitled to make underthe Contract, or

(b) interfering with or obstructing or refusing any re-quired approval to the issue of any such certificate, or

(c) becoming bankrupt or, being a company, going intoliquidation, other than for the purpose of a scheme ofreconstruction or amalgamation, or

(d) giving notice to the Contractor that for unforeseenreasons, due to economic dislocation, it is impossible forhim to continue to meet his contractual obligations

the Contractor shall be entitled to terminate his employ-ment under the Contract by giving notice to the Em-ployer, with a copy to the Engineer. Such terminationshall take effect 14 days after the giving of the notice.

This Sub-Clause lists in (a) to (d) the reasons (all of which relate to the Employer's abilityto make payment to the Contractor) for which the Contractor can, by giving notice tothe Employer, terminate his employment under the Contract. The termination takes effectautomatically 14 days after such notice is given to the Employer.

The parties are of course free to negotiate the Contractor's return to work during or afterthe period of notice, but resumption of work is not automatic, even if the default isrectified during the period of notice. It should be emphasised that the termination of acontract is an important legal matter, and that, in addition to the terms of the Contract,the law governing the Contract should be examined to ascertain the effects thereof onthe parties.

158 ©FIDIC 1989

Page 159: 35824401 FIDIC Guide to the Use of FIDIC

If the Employer is a government or public authority, it may be appropriate to delete case(c) by a supplement to Sub-Clause 69.1 in Part II. In addition, the law governing theContract may contain mandatory provisions the effect of which is to make amendmentsto the Clause desirable. The following are examples of what it may be necessary to addin Part II:

Where the Employer is a government it may be considered appropriate to vary the Sub-Clause:

Default 69.1 Delete paragraph (c) and renumber paragraph (d) as (c).of the

Employer

Where the terms of the Sub-Clause, when read in conjunction with Sub-Clause 69.3,are in conflict with the law governing the Contract, the Sub-Clause may need to be variedas follows:

Default 69.1 Delete 'or' at the end of paragraph (c) and delete para-of the graph(d).

Employer

Removal of 69.2 Upon the expiry of the 14 days' notice referred to inContractor's Sub-Clause 69.1, the Contractor shall, notwithstanding

Equipment the provisions of Sub-Clause 54.1, with all reasonabledespatch, remove from the Site all Contractor's Equip-ment brought by him thereon.

Upon such termination the Contractor is obliged to remove his Equipment from the Site.

Paymenton 69.3 in the event of such termination the Employer shall beTermination under the same obligations to the Contractor in regard

to payment as if the Contract has been terminated underthe provisions of Clause 65, but, in addition to thepayments specified in Sub-Clause 65.8, the Employershall pay to the Contractor the amount of any loss ordamage to the Contractor arising out of or in connec-tion with or by consequence of such termination.

The Employer is obliged to make payment to the Contractor as stipulated in Sub-Clause69.3 which, in addition to the payment for termination under Clause 65, could includecompensation for the Contractor's loss of profit.

©FIDIC 1989 159

Page 160: 35824401 FIDIC Guide to the Use of FIDIC

Contractor's 694 Withoutprejudice to the Contractor's entitlement to in-Entitlement to terest under Sub-Clause 60.10 and to terminate under

Suspend Work Sub-Clause 69.1, the Contractor may, if the Employerfails to pay the Contractor the amount due under anycertificate of the Engineer within 28 days after theexpiry of the time stated in Sub-Clause 60.10 withinwhich payment is to be made, subject to any deductionthat the Employer is entitled to make under the Con-tract, after giving 28 days' prior notice to the Employer,with a copy to the Engineer, suspend work or reduce therate of work.

If the Contractor suspends work or reduces the rate ofwork in accordance with the provisions of this Sub-Clause and thereby suffers delay or incurs cost theEngineer shall, after due consultation with the Employerand the Contractor, determine(a) any extension of time to which the Contractor isentitled under Clause 44, and(b) the amount of such costs, which shall be added tothe Contract Price,

and shall notify the Contractor accordingly, with a copyto the Employer.

Clause 69 in the fourth edition has been supplemented with an additional, but less se-vere, remedy for the Contractor, if the Employer fails to pay any certificate promptly,which may be suitable where both parties in reality wish to complete the Contract.The Contractor can give notice to the Employer under Sub-Clause 69.4 which entitlesthe Contractor, after a period of 28 days, to suspend work or reduce the rate of such work.

Such suspension could involve anything from stopping all production (maintaining onlysafety work to protect the Site and work already done) to a nominal reduction in workto demonstrate the Contractor's dissatisfaction, all at the Contractor's discretion. He thushas the possibility to resume normal work when the cause for his action has been re-moved, and he is entitled to obtain compensation for any delay (time extension) and forhis extra costs.

Resumption 695 Where the Contractor suspends work or reduces the rateof Work of work, having given notice in accordance with Sub-

Clause 69.4, and the Employer subsequently pays theamount due, including interest pursuant to Sub-Clause60.10, the Contractor's entitlement under Sub-Clause69.1 shall, if notice of termination has not been given,lapse and the Contractor shall resume normal workingas soon as is reasonably possible.

This Sub-Clause deals with the resumption of work.

160 ©FIDIC 1989

Page 161: 35824401 FIDIC Guide to the Use of FIDIC

CHANGES IN COST AND LEGISLATION

Increase or 70.1 There shall be added to or deducted from the ContractDecrease Price such sums in respect of rise or fall in the cost of

ofCost labour and/or materials or any other matters affectingthe cost of the execution of the Works as may be deter-mined in accordance with Part II of these Conditions.

Subsequent 70.2 If, after the date 28 days prior to the latest date forLegislation submission of tenders for the Contract there occur in the

country in which the Works are being or are to beexecuted changes to any National or State Statute,Ordinance, Decree or other Law or any regulation orbye-law of any local or other duly constituted author-ity, or the introduction of any such State Statute, Ordi-nance, Decree, Law, regulation or bye-law which causesadditional or reduced cost to the Contractor, other thanunder Sub-Clause 70.1, in the execution of the Contract,such additional or reduced cost shall, after due consul-tation with the Employer and the Contractor, be deter-mined by the Engineer and shall be added to or de-ducted from the Contract Price and the Engineer shallnotify the Contractor accordingly, with a copy to theEmployer.

Particularly in periods of inflation and of instability in currency exchange rates, theEmployer should not, in his own best interests, and especially on long-tenn contracts,ask tenderers to quote firm prices with no provision for adjustments, at least in thecountry in which the Works are to be executed.

If contractors do not have to allow for price variations when preparing their tenders, theEmployer will receive better and more competitive offers from reputable contractors, andwill only have to meet such net variations in cost as actually occur.

Clause 70 is intended to make provision for the possible effect of such matters asvariation in the cost of labour and materials arising during the execution of the Worksand of new or amended national and local laws and regulations introduced during orafter the final stages of the preparation of the tenders.

Ideally, the net increase (or decrease) in the cost of labour and materials, consumables,etc., arising after a date when tenderers can be assumed to have completed the compu-tation of the rates and prices inserted in their tenders, should be assessed and the Con-tract Price adjusted accordingly. Where such variation can be checked from officialinformation, the task is comparatively easy. In many cases such information is notavailable and alternative methods must be devised.

© FIDIC 1989 161

Page 162: 35824401 FIDIC Guide to the Use of FIDIC

The wording of Clause 70 in Part I cannot, therefore, be too specific and must allow forindividual drafting to suit particular local conditions. Guidance for such individualdrafting is given below.

For contracts of short duration, e.g., one year at maximum, it may be reasonable torequire firm prices. The following Part II entries will probably be appropriate:

Increase 70.1 Delete the text of the Sub-Clause and substitute:or

Decrease Subject to Sub-Clause 70.2 the Contract Price shall notin Cost be subject to any adjustment in price in respect of rise

or fall in the cost of labour, materials or any othermatters affecting the cost of execution of the Contract.

Subsequent 70.2 Delete the words 'other than under Sub-Clause 70.1'Legislation

For contracts of longer duration, adjustments of prices should be allowed. Twomethods are given below, the first adjustment based upon 'basic prices' and the secondbased upon 'indices'.

Of these two methods the one based on 'indices' is recommended wherever suitableindices can be obtained. It is easier to administer and enables the Contractor who pur-chases skillfully to be rewarded.

The following Part II entry should be made where price adjustment is to be made byestablishing the difference in cost between basic price and the current price of locallabour and specified materials:

Increase 70.1 Delete the text of the Sub-Clause and substitute:or

Decrease Adjustments to the Contract Price shall be made inin Cost respect of rise or fall in the cost of local labour and

specified materials as set out in this Sub-Clause.

(a) Local Workmen

(i) For the purpose of this Sub-Clause:

'Local Workmen' means skilled, semi-skilled andunskilled workmen of all trades engaged by the Con-tractor on the Site for the purpose of or in connec-tion with the Contract or engaged full time by theContractor off the Site for the purpose of or in con-nection with the Contract (by way of illustration butnot limitation: workmen engaged full time in anyoffice, store, workshop or quarry).

162 © FIDIC 1989

Page 163: 35824401 FIDIC Guide to the Use of FIDIC

'Basic Rate' means the applicable basic minimumwage rate prevailing on the date 28 days prior to thelatest date for submission of tenders by reason of anyNational or State Statute, Ordinance, Decree or otherLaw or any regulations or bye-law of any local orother duly constituted authority, or in order to con-form with practice amongst good employers gener-ally in the area where the Works are to be carriedout.

'Current Rate' means the applicable basic minimumwage rate for Local Workmen prevailing on any datesubsequent to the date 28 days prior to the latest dateset for the submission of tenders by reason of anyNational or State Statute, Ordinance, Decree or otherLaw or any regulation or bye-law of any local orother duly constituted authority, or in order to con-form with practice amongst good employers gener-ally in the area where the Works are to be carriedout.

(ii) The adjustment to the Contract Price under theterms of this Sub-Clause shall be calculated bymultiplying the difference between the Basic andCurrent Rates for Local Workmen by:

(a) the number of hours actually worked, and also

(b) in respect of those hours worked at overtimerates, by the product of the number of said hoursand the percentage addition required by the lawto be paid by the Contractor for overtime.

Such adjustment may be either by an addition toor a deduction from the Contract Price.

(iii) No other adjustment of the Contract Price onaccount of fluctuation in the remuneration of LocalWorkmen shall be made.

(b) Specified Materials

(i) For the purpose of this Sub-Clause:

'Specified Materials' means the materials stated inAppendix (insert reference) to Tender required onthe Site for the execution and completion of theWorks.

'Basic Prices' means the current prices for the speci-fied materials prevailing on the date 28 days prior tothe latest date for submission of tenders.

'Current Prices' means the current prices for thespecified materials prevailing at any date subsequentto the date 28 days prior to the latest date for sub-mission of tenders.

©FIDIC 1989 163

Page 164: 35824401 FIDIC Guide to the Use of FIDIC

(ii) The adjustment to the Contract Price under theterms of this Sub-Clause shall be calculated by ap-plying the difference between the Basic and CurrentPrices to the quantity of the appropriate SpecifiedMaterials which is delivered to the Site during theperiod for which the particular Current Price is ef-fective. Such adjustment may be either an additionto or a deduction from the Contract Price.

(iii) The Contractor shall use due diligence to ensurethat excessive wastage of Specified Materials shallnot occur. Any Specified Materials removed fromthe Site shall be clearly identified in the records re-quired under paragraph (d) of this Sub-Clause.

(iv) The provisions of this Sub-Clause shall apply tofuels used in Contractor's Equipment engaged on theSite for the purposes of executing theWorks,including vehicles owned by the Contractor(or hired by him under long term arrangements un-der which the Contractor is obligated to supply fuel)engaged in transporting any staff, labour, Contrac-tor's Equipment, Temporary Works, Plant or mate-rials to and from the Site. Such fuels shall be clearlyidentified in the records required under paragraph (d)of this Sub-Clause. The provisions of this Sub-Clause shall not apply to any fuels sold or suppliedto any employee of the Contractor or to any personfor use in any motor vehicle not being used for thepurposes of the Contract.

(v) The Contractor shall at all times have regard tosuitable markets and shall, whenever buying materi-als a variation in the cost of which would give riseto an adjustment of the Contract Price under thisSub-Clause, be diligent to buy or procure the sameat the most economical prices as are consistent withthe due performance by the Contractor of his obli-gations under the Contract.

If at any time there shall have been any lack of dili-gence, default or negligence on the part of the Con-tractor, whether in observing the above requirementsor otherwise, then, for the purposes of adjusting theContract Price pursuant hereto, no account shall betaken of any increase in cost which may be attribut-able to such lack of diligence, default or negligenceand the amount by which any cost would have beendecreased but for such lack of diligence, default ornegligence shall be deducted from the ContractPrice.

(vi) No other adjustment to the Contract Price onaccount of fluctuation in the cost of materials shallbe made.

164 © FIDIC 1989

Page 165: 35824401 FIDIC Guide to the Use of FIDIC

(c) Overheads and Profits Excluded

In determining the amount of any adjustment to theContract Price pursuant to this Sub-Clause no accountshall be taken of any overheads or profits.

(d) Notices and Records

The Contractor shall forthwith, upon the happening of• any event which may or may be likely to give rise to

the adjustment of the Contract Price pursuant to thisSub-Clause, give notice thereof to the Engineer and theContractor shall keep such books, accounts and otherdocuments and records as are necessary to enable adjust-ment under this Sub-Clause to be made and shall, at therequest of the Engineer, furnish any invoices, accounts,documents or records so kept and such other informa-tion as the Engineer may require.

(e) Adjustment after Date of Completion

The Contractor shall forthwith, upon the happening ofany event which may or may be likely to give rise tothe adjustment of the Contract Price pursuant to thisSub-Clause, give notice thereof to the Engineer and theContractor shall keep such books, accounts and otherdocuments and records as are necessary to enable adjust-ment under this Sub-Clause to be made and shall, at therequest of the Engineer, furnish any invoices, accounts,documents or records so kept and such other informa-tion as the Engineer may require.

(f) Determination of Adjustment to Contract Price

The amount of any adjustment to the Contract Price pur-suant to this Sub-Clause shall be determined by the En-gineer in accordance with the foregoing rules.

©FIDIC 1989 165

Page 166: 35824401 FIDIC Guide to the Use of FIDIC

EXAMPLE APPENDIX TO TENDERfor use in connection with the above.

SPECIFIED MATERIALS

Material Unit Price andLocation

Transportto Site

Price RemarksDeliveredto Site

Bitumen

DieselPetrolLubricants

Cement

ReinforcingSteel

Explosives

NOTES:

1. The Contractor shall provide copies of quotations tosubstantiate all prices included in the above table.

2. All subsequent price substantiation shall be from thesame source as original unless otherwise agreed by theEngineer.3. The Contractor shall submit full explanation and pro-vide substantiating documentation for the mode of trans-port to Site he proposes. Only the proposed documentedmode of transport shall qualify for price adjustment.

(Note: Materials stated in the Appendix to Tendershould be those of which substantial quantities are in-volved.)

The following Part II entry should be made where price adjustment is to be made throughthe application of indices in a formula:

Increase 70.1 Delete the text of the Sub-Clause and substitute:

Decrease (a) Adjustments to the Contract Price in respect of rise

in Cost and fall in the cost of labour and materials and othermatters affecting the cost of execution of the Worksshall be calculated for each monthly statement pursu-ant to Sub-Clause 60.1, the Statement at Completionpursuant to Sub-Clause 60.5 and the Final Statementpursuant to Sub-Clause 60.6 in accordance with theprovisions of this Sub-Clause if there shall be anychanges in the following index figures compiled by (in-sert details of source of indices) and published by (in-sert details of publication):

166 ©FIDIC 1989

Page 167: 35824401 FIDIC Guide to the Use of FIDIC

(i) the Index of the cost of Labour in (insert nameof country)

(ii) the Index of the cost of (insert other factor, asrelevant)

(iii) the Index of the cost of (insert other factor, asrelevant)

(b) For the purpose of this Sub-Clause:

(i) 'Base Index Figure' shall mean the index fig-ure applicable on the date 28 days prior to the lat-est date for submission of tenders.

(ii) 'Current Index Figure' shall mean the indexfigure applicable on the last day of the period towhich the particular statement relates.

Provided that in respect of any work the value ofwhich is included in any such monthly statement(or Statement at Completion or Final Statement)and which was executed after the due date (or ex-tended date) for completion of the wholeWorks, pursuant to Clause 43, the Current IndexFigure shall be the index figure applicable on theaforesaid due date (or extended date) for comple-tion of the whole of the Works.

(iii) 'Effective Value' shall be the difference be-tween:

(a) The amount which is due to the Contractorunder the provisions of Sub-Clauses 60.2, 60.5or 60.8 (before deducting retention and exclud-ing repayment of the advance payment) lessany amounts for:

work executed under nominated Subcontracts

materials and Plant on the Site, as referred toin Sub-Clause 60.1(c)

dayworks, variations or any other items basedon actual cost or current prices, and bonuses (ifany)

adjustments under Clause 70,

and

(b) The amount calculated in accordance with(b)(iii)(a) of this Sub-Clause and included inthe last preceding statement.

© FIDIC 1989 167

Page 168: 35824401 FIDIC Guide to the Use of FIDIC

(c) The adjustment to the Contract Price shallbe calculated by multiplying the EffectiveValue by a Price Fluctuation Factor whichshall be the net sum of the products obtainedby multiplying each of the proportions given inparagraph (d) of this Sub-Clause by the follow-ing fraction:

Current Index Figure - Base Index Figure

Base Index Figure

calculated using the relevant index figures.

(d) For the purpose of calculating the PriceFluctuation Factor, the proportions referred toin paragraph (c) of this Sub-Clause shall (irre-spective of the actual constituents of the work)be as follows:

0.x in respect of labour (and supervision)costs subject to adjustment by reference tothe Index referred to in (a)(i) of this Sub-Clause;

0.x in respect of by reference to the Indexreferred to in (a)(ii) of this Sub-Clause;

0.x in respect of by reference to the Indexreferred to in (a)(iii) of this Sub-Clause;

0.x in respect of all other costs which shallnot be subject to any adjustment;

1.00 Total

(e) Where the value of an Index is not knownat the time of calculation, the latest availablevalue shall be used and any adjustment neces-sary shall be made in subsequent monthlystatements.

(Note: The number of indices included under (a) of this Sub-Clause may be varied, ifit is determined that a different number of factors should be separately identified, andin such case (d) of this Sub-Clause must be altered to be consistent.)

168 © FIDIC 1989

Page 169: 35824401 FIDIC Guide to the Use of FIDIC

CURRENCY AND RATES OF EXCHANGE

Currency 71.1 If, after the date 28 days prior to the latest date for sub-Restrictions mission of tenders for the Contract, the Government or

authorised agency of the Government of the country inwhich the Works are being or are to be executed im-poses currency restrictions and/or transfer of currencyrestrictions in relation to the currency or currencies inwhich the Contract Price is to be paid, the Employershall reimburse any loss or damage to the Contractorarising therefrom, without prejudice to the right of theContractor to exercise any other rights or remedies towhich he is entitled in such event.

This Clause protects the Contractor against currency restrictions and/or transfer of cur-rency restrictions in relation to the currencies in which the Contract Price is to bepaid. If such restrictions are imposed after the Contractor will normally have priced histender, the Contractor is entitled to be reimbursed by the Employer for any consequentloss or damage.

The Contractor will normally need to transfer funds to the country of the Works duringthe mobilisation stage and to repatriate the funds later. The Contract may provide forspecial advance payments by the Employer, for the purchase of Contractor's Equip-ment and for repayment by the Contractor during the period of the Contract. Paymentsof retention sums, liquidated damages and bonus may also be affected and so may alsothe valuation of the Contractor's Equipment for possible tax or customs duty assess-ment on re-export or sale at the end of the Contract.

It is common for the Contract Price to be paid in one or more foreign currencies inaddition to the local currency of the country where the Works are to be executed. Wherethis is the case, consideration should be given to nominating a place of payment (a bank)in each of the countries of the foreign currencies applicable. See example Sub-Clauseunder Clause 60.

Rates of 72.1 Where the Contract provides for payment in whole orExchange in part to be made to the Contractor in foreign currency

or currencies, such payment shall not be subject to vari-ations in the rate or rates of exchange between suchspecified foreign currency or currencies and the cur-rency of the country in which the Works are to be exe-cuted.

In this Sub-Clause it is assumed that the Contractor has quoted his tender price asconsisting of sums in one or more foreign currencies in addition to a sum to be paid inthe currency of the country where the Works are to be constructed, the local cur-rency. In a unit rate contract, this would normally require that each and every itemto be paid for is quoted in one or more foreign currencies in addition to the localcurrency. Such an arrangement gives a complicated Bill of Quantities but ensuresthat the Contractor receives the appropriate currencies.

© FIDIC 1989 169

Page 170: 35824401 FIDIC Guide to the Use of FIDIC

Currency 72,2 Where the Employer has required the Tender to be ex-Proportions pressed in a single currency but with payment to be

made in more than one currency and the Contractor hasstated the proportions or amounts of other currency orcurrencies in which he requires payment to be made, therate or rates of exchange applicable for calculating thepayment of such proportions or amounts shall, unlessotherwise stated in Part II of these Conditions, be thoseprevailing, as determined by the Central Bank of thecountry in which the Works are to be executed, on thedate 28 days prior to the latest date for the submissionof tenders for the Contract, as has been notified to theContractor by the Employer prior to the submission oftenders or as provided for in the Tender.

This Sub-Clause deals with the procedure to be followed if tenderers have been requiredto submit their tenders in a single currency. Full details of requirements will have beenissued by the Employer when inviting tenders and during the tendering period. Eachpay-ment certificate will then be calculated in such currency based on rates for each pay-ment item in that currency. But for payment, the sum certified will be converted into thevarious currencies in the proportions required by the Contractor in his tender. The ratesof exchange for conversion shall be fixed for the duration of the Contract at the ratescommunicated to the tenderers by the Employer during the tendering period. The Con-tractor will thus always receive currencies in the same proportions, which may not al-ways correspond to his actual use of the currencies (the advance payment will have aninfluence also). However, what he receives should eventually correspond to his require-ments, if the Works have not been varied substantially or increases and decreases of vari-ous work items have not unbalanced his estimate. The possibility of imbalance can bereduced if the Contractor is required in his tender to stipulate currency proportions fordifferent parts of the Bill of Quantities.

If an Intematonal Financing Institution is involved in the financing of the project it wouldprobably insist that the currency requirements relate to the countries from which goodsand services are to be obtained.

Where it is decided that the rate or rates of exchange shall be established from a sourceother than the Central Bank of the country, it may be appropriate to make the followingvariation to the Sub-Clause in Part II:

Currency 72.2 Delete the words from 'prevailing.' to the end ofProportions the sentence and substitute 'stated in the Appendix to

Tender'.

170 © FIDIC 1989

Page 171: 35824401 FIDIC Guide to the Use of FIDIC

Currencies of 72.3 Where the Contract provides for payment in more thanPayment for one currency, the proportions or amounts to be paid inProvisional foreign currencies in respect of Provisional Sums shall

Sums be determined in accordance with the principles setforth in Sub-Clause 72.1 and 72.2 as and when thesesums are utilised in whole or in part in accordance withthe provisions of Clauses 58 and 59.

This Sub-Clause emphasises the need to deal separately and individually with the cur-rency content of Provisional Sums as and when they are used.

©FIDIC 1989 171

Page 172: 35824401 FIDIC Guide to the Use of FIDIC

POSSIBLE SUPPLEMENTARY CLAUSES

Part I contains only the 72 Clauses dealt with above but each individual contract willalmost always need additional clauses drafted specifically to meet the needs of the proj-ect covered by the Contract. Such clauses may deal with taxes, duties and dues of vari-ous kinds, with particular points of law, e.g., the joint and several liability of membersof a joint venture, with bribery, confidentiality and with restrictions as to the use offunds imposed by a financing institution. These would appear as additional clauses inPart II and examples for the four latter cases are given below.

Protection against bribery.

Where the law applicable to the Contract does not cover bribery it may well be of ad-vantage to add the following clause or a clause of a similar nature:

Bribes .1 If the Contractor or any of his Sub-contractors, agentsor servants offers to give or agrees to offer or give toany person, any bribe, gift, gratuity or commission as aninducement or reward for doing or forbearing to do anyaction in relation to the Contract or any other contractwith the Employer or for showing or forbearing to showfavour or disfavour to any person in relation to the Con-tract or any other contract with the Employer, then theEmployer may enter upon the Site and the Works andterminate the employment of the Contractor and the pro-visions of Clause 63 hereof shall apply as if such entryand termination had been made pursuant to that Clause.

Confidentiality

Where circumstances require that particular confidentiality is observed, the followingclause might be appropriate:

Details .1 The Contractor shall treat the details of the Contract asto be private and confidential, save in so far as may be neces-

Confidential sary for the purposes thereof, and shall not publish ordisclose the same or any particulars thereof in any tradeor technical paper or elsewhere without the previousconsent in writing of the Employer or the Engineer. Ifany dispute arises as to the necessity of any publicationor disclosure for the purpose of the Contract the sameshall be referred to the Employer whose award shall befinal.

172 ©FIDIC 1989

Page 173: 35824401 FIDIC Guide to the Use of FIDIC

Restrictions on Expenditure

Where the Contract is being financed wholly or in part by an International FinancingInstitution whose Articles require a restriction on the use of the funds provided, the fol-lowing clause may be added:

Expenditure .1 The Contractor shall not make any expenditures for theRestricted purpose of the Contract in the territories of any country

which is not a member of (insert name of InternationalFinancing Institution) nor shall he make any expenditurefor goods produced in or services supplied from suchterritories.

Contractor as Joint Venture

In the event that the Contractor is a joint venture it is recommended that considerationbe given by the Employer to the inclusion of the following clause:

Joint and .1 If the Contractor is a joint venture of two or more per-Several sons, all such persons shall be jointly and severallyLiability bound to the Employer for the fulfilment of the terms

of the Contract and shall designate one of such personsto act as leader with authority to bind the joint venture.The composition or the constitution of the joint ventureshall not be altered without the prior consent of the Em-ployer.

Special Provision for Duties and Taxes

In regard to local taxes, duties and dues, etc., the Contract may stipulate that no ex-emption whatsoever shall be allowed, or that the Contractor will not be exempted fromany such imposition but reimbursed under the Contract, or that he will be exempted fromturnover tax and income tax on the Contract and his expatriate personnel likewise ontheir income tax while stationed in the country of the Works, but will not be exemptedfrom customs duties, other duties and dues, etc., in order not to disturb the market forproducts and services in the country of the Works. When the Employer is a governmentor public authority, even customs duties and similar impositions may, in exceptionalcases, be excluded from the Contract Price by specific mention in the Tender documentsin order that the funds provided by financing institutions may be directed towards theproject only.There are numerous ways of dealing with such arrangements and it is considered thatit would not be helpful to include some of these in this present publication as thatmay appear to exclude others which would be appropriate. A clause should be drawnto respond precisely to the intentions of the Employer and should be included in the Ten-der documents.

©FIDIC 1989 173

Page 174: 35824401 FIDIC Guide to the Use of FIDIC

F I D I C FEDERATION INTERNATIONALE DES INGENIEURS-CONSEILS

GUIDETOTHE USEOFFIDICCONDITIONS OF CONTRACT

FOR WORKS OF CIVIL

ENGINEERING CONSTRUCTION

PART I GENERAL CONDITIONSWITH FORMS OF TENDER AND AGREEMENT

FOURTH EDITION 1987Renrinted 1988 with editorial amendments

Page 175: 35824401 FIDIC Guide to the Use of FIDIC

FOREWORD

The terms of the Fourth Edition of the Conditions of Contract for Works of CivilEngineering Construction have been prepared by the Fédération Internationaledes Ingénieurs Conseils (FIDIC) and are recommended for general use for thepurpose of construction of such works where tenders are invited on aninternational basis. The Conditions, subject to minor modifications, are alsosuitable for use on domestic contracts.

The version in English of the Conditions is considered by FIDIC as the officialand authentic text for the purpose of translation.

In the preparation of the Conditions it was recognised that while there arenumerous Clauses which will be generally applicable there are some Clauseswhich must necessarily vary to take account of the circumstances and locality ofthe Works. The Clauses of general application have been grouped together in thisdocument and are referred to as Part I — General Conditions. They have beenprinted in a form which will facilitate their inclusion as printed in the contractdocuments normally prepared.

The General Conditions are linked with the Conditions of ParticularApplication, referred to as Part H, by the corresponding numbering of theClauses, so that Parts I and II together comprise the Conditions governing therights and obligations of the parties.

Part II must be specially drafted to suit each individual Contract.

When dredging and certain types of reclamation work are involved specialconsideration must be given to Part II.

To assist in the preparation of Part II explanatory material and example clausesare published with the Conditions in a separately bound document entitled"Conditions of Contract for Works of Civil Engineering Construction, Part II —Conditions of Particular Application, with Guidelines for preparation of Part IIClauses, Fourth Edition".

FIDIC anticipates publishing shortly a new edition of its booklet "Notes onDocuments for Civil Engineering Contracts" (1977 reprinted 1979) which willinclude comments on provisions of the Fourth Edition of the Conditions. Usersof the Fourth Edition may find it helpful to refer to the new edition of the Notes.

It may also be helpful for users to refer to other FIDIC publications, such as:

Tendering Procedure (First Edition 1982)Construction, Insurance and Law (1986)

FIDIC gratefully acknowledges the suggestions and comments it has receivedduring the preparation of this edition from European International Contractors(EIC) as mandatory of Confederation of International Contractors Associations(CICA) with participation of Associated General Contractors of America(AGC).

Page 176: 35824401 FIDIC Guide to the Use of FIDIC

CONTENTS

PART I: GENERAL CONDITIONSDefinitions and Interpretation

1.1 Detinitions 1811.2 Headings and Marginal Notes 1821.3 Interpretation 1821.4 Singular and Plural 1821.5 Notices, Consents, Approvals, Certificates 183

and Determinations

Engineer and Engineer's Representative2.1 Engineer's Duties and Authority 1832.2 Engineer's Representative 1832.3 Engineer's Authority to Delegate 1832.4 Appointment of Assistants 1832.5 Instructions in Writing 1832.6 Engineer to Act Impartially 184

Assignment and Subcontracting3.1 Assignment of Contract 1844.1 Subcontracting 1844.2 Assignment of Subcontractors' Obligations 184

Contract Documents5.1 Language/s and Law 1845.2 Priority of Contract Documents 1856.1 Custody and Supply of Drawings and Documents 1856.2 One Copy of Drawings to be Kept on Site 1856.3 Disruption of Progress 1856.4 Delays and Cost of Delay of Drawings 1856.5 Failure by Contractor to Submit Drawings 1867.1 Supplementary Drawings and Instructions 1867.2 Permanent Works Designed by Contractor 1867.3 Responsibility Unaffected by Approval 186

General Obligations8.1 Contractor's General Responsibilities 1868.2 Site Operations and Methods of Construction 1869.1 Contract Agreement i 86

10.1 Performance Security 18610.2 Period of Validity of Performance Security 18710.3 Claims under Performance Security 18711.1 Inspection of Site 18712.1 Sufficiency of Tender 18712.2 Adverse Physical Obstructions or Conditions 18713.1 Work to be in Accordance with Contract 18814.1 Programme to be Submitted 18814.2 Revised Programme 18814.3 Cash Flow Estimate to be Submitted 18814.4 Contractor not Relieved of Duties or Responsibilities 18815.1 Contractor's Superintendence 188

fl,

Page 177: 35824401 FIDIC Guide to the Use of FIDIC

16.1 Contractor's Employees i8816.2 Engineer at Liberty to Object 18817.1 Setting-out 18918.1 Boreholes and Exploratory Excavation 18919.1 Safety, Security and Protection of the Environment 18919.2 Employer's Responsibilities 18920.1 CareofWorks 18920.2 Responsibility to Rectify Loss or Damage 19020.3 Loss or Damage Due to Employer's Risks 19020.4 Employer's Risks io21.1 Insurance of Works and Contractor's Equipment21.2 ScopeofCover 19121.3 Responsibility for Amounts not Recovered 19121.4 Exclusions ii22.1 Damage to Persons and Property 19122.2 Exceptions ii22.3 Indemnity by Employer 19223.1 Third Party Insurance (including Employer's Property) 19223.2 Minimum Amount of Insurance i 9223.3 Cross Liabilities 19224.1 Accident or Injury to Workmen 19224.2 Insurance Against Accident to Workmen 19225.1 Evidence and Terms of Insurances 19225.2 Adequacy of Insurances 19225.3 Remedy on Contractor's Failure to Insure 19225.4 Compliance with Policy Conditions 19226.1 Compliance with Statutes, Regulations 19327.1 Fossils 19328.1 Patent Rights 19328.2 Royalties 19329.1 Interference with Traffic and Adjoining Properties 19330.1 Avoidance of Damage to Roads 19430.2 Transport of Contractor's Equipment or Temporary Works 19430.3 Transport of Materials or Plant 19430.4 Waterborne Traffic 19431.1 Opportunities for Other Contractors 19431 .2 Facilities for Other Contractors 19432.1 Contractor to Keep Site Clear 19533.1 Clearance of Site on Completion 195

Labour34.1 Engagement of Staff and Labour 19535.1 Returns of Labour and Contractor's Equipment 195

Materials, Plant and Workmanship36.1 Quality of Materials, Plant and Workmanship 19536.2 Cost of Samples 19536.3 Cost of Tests 19536.4 Cost of Tests not Provided for 19636.5 Engineer's Determination where Tests not Provided for 19637.1 Inspection of Operations 19637.2 Inspection and Testing 19637.3 Dates for Inspection and Testing 196

Page 178: 35824401 FIDIC Guide to the Use of FIDIC

37.4 Rejection 196375 Independent Inspection 19738.1 Examination of Work before Covering up 19738.2 Uncovering and Making Openings 19739.1 Removal of Improper Work, Materials or Plant 19739.2 De1ault of Contractor in Compliance 197

Suspension40.1 Suspension of Work 19740.2 Engineer's Determination following Suspension 19840.3 Suspension lasting more than 84 Days 198

Commencement and Delays41.1 Commencement of Works 19842.1 Possession of Site and Access Thereto 19842.2 Failure to Give Possession 19942.3 Wayleaves and Facilities 19943.1 Time for Completion 19944.1 Extension of Time for Completion 19944.2 Contractor to Provide Notification and Detailed Particulars 19944.3 Interim Determination of Extension 20045.1 Restriction on Working Hours 20046.1 Rate of Progress 20047.1 Liquidated Damages for Delay 20047.2 Reduction of Liquidated Damages 20048.1 Taking-Over Certificate 20148.2 Taking-Over of Sections or Parts 20148.3 Substantial Completion of Parts 20148.4 Surfaces Requiring Reinstatement 201

Defects Liability49.1 Defects Liability Period 20149.2 Completion of Outstanding Work and Remedying Defects 20249.3 Cost of Remedying Defects 20249.4 Contractor's Failure to Carry Out Instructions 20250.1 Contractor to Search 202

Alterations. Additions and Omissions51.1 Variations 20251.2 Instructions for Variations 20352.1 Valuation of Variations 20352.2 Power of Engineer to Fix Rates 20352.3 Variations Exceeding 15 percent 20352.4 Daywork 204

Procedure for Claims53.1 Notice of Claims 20453.2 Contemporary Records 20453.3 Substantiation of Claims 20553.4 Failure to Comply 20553.5 Payment of Claims 205

Page 179: 35824401 FIDIC Guide to the Use of FIDIC

Contractor's Equipment, Tern porary Worksand Materials

54.1 Contractor's Equipment, Temporary Works and Materials; Exclusive 205Use for the Works

54.2 Employer not Liable for Damage 20554.3 Customs Clearance 20554.4 Re-export of Contractor's Equipment 20554.5 Conditions of Hire of Contractor's Equipment 20654.6 Costs for the Purpose of Clause 63 20654.7 Incorporation of Clause in Subcontracts 20654.8 Approval of Materials not Implied 206

Measurement55.1 Quantities 20656.1 Works to be Measured 20657.1 Method of Measurement 20757.2 Breakdown of Lump Sum Items 207

Provisional Sums58.1 Definition of "Provisional Sum" 20758.2 Use of Provisional Sums 20758.3 Production of Vouchers 207

Nominated Subcontractors59.1 Definition of "Nominated Subcontractors" 20759.2 Nominated Subcontractors; Objection to Nomination 20759.3 Design Requirements to be Expressly Stated 20859.4 Payments to Nominated Subcontractors 20859.5 Certification of Payments to Nominated Subcontractors 208

Certificates and Payment60.1 Monthly Statements 20960.2 Monthly Payments 20960.3 Payment of Retention Money 20960.4 Correction of Certificates 21060.5 Statement at Completion 21060.6 Final Statement 21060.7 Discharge 21060.8 Final Certificate 21060.9 Cessation of Employer's Liability 21060.10 TimeforPayment 211

61.1 Approval only by Defects Liability Certificate 21162.1 Defects Liability Certificate 21162.2 Unfulfilled Obligations 211

Remedies63.1 Default of Contractor 21163.2 Valuation at Date of Termination 21263.3 Payment after Termination 21263.4 Assignment of Benefit of Agreement 21264.1 Urgent Remedial Work 213

Special Risks65.1 No Liability for Special Risks 21365.2 Special Risks 213

Page 180: 35824401 FIDIC Guide to the Use of FIDIC

65.3 Damage to Works by Special Risks 21365.4 Projectile, Missile 21 365.5 Increased Costs arising from Special Risks 21465.6 Outbreak of War 21465.7 Removal of Contractor's Equipment on Termination 21465.8 PaymentIf Contract Terminated 214

Release from Performance66.1 Payment in Event of Release from Performance 215

Settlement of Disputes67.1 Engineer's Decision 21567.2 Amicable Settlement 21667.3 Arbitration 21667.4 Failure to Comply with Engineer's Decision 216

Notices68.1 Notice to Contractor 21668.2 Notice to Employer and Engineer 21668.3 Change of Address 216

Default of Employer69.1 Default of Employer 21769.2 Removal of Contractor's Equipment 21769.3 Payment on Termination 21769.4 Contractor's Entitlement to Suspend Work 21769.5 Resumption of Work 217

Changes in Cost and Legislation70.1 Increase or Decrease of Cost 21770.2 Subsequent Legislation 218

Currency and Rates of Exchange71.1 Currency Restrictions 21872.1 Rates of Exchange 21872.2 Currency Proportions 21872.3 Currencies of Payment for Provisional Sums

REFERENCE TO PART IIINDEXTENDERAGREEMENTEDITORIAL AMENDMENTS

Page 181: 35824401 FIDIC Guide to the Use of FIDIC

PART I - GENERAL CONDITIONSDefinitions and Interpretation

Definitions 1.1 In the Contract (as hereinafter defined) the following words and expressions shallhave the meanings hereby assigned to them, except where the context otherwiserequires:

(a) (i) "Employer" means the person named as such in Part II of these Conditionsand the legal successors in title to such person, but not (except with the consentof the Contractor) any assignee of such person.

(ii) "Contractor" means the person whose tender has been accepted by theEmployer and the legal successors in title to such person, but not (except withthe consent of the Employer) any assignee of such person.

(iii) "Subcontractor" means any person named in the Contract as aSubcontractor for a part of the Works or any person to whom a part of theWorks has been subcontracted with the consent of the Engineer and the legalsuccessors in title to such person, but not any assignee of any such person.

(iv) "Engineer" means the person appointed by the Employer to act asEngineer for the purposes of the Contract and named as such in Part II ofthese Conditions.

(v) "Engineer's Representative" means a person appointed from time to timeby the Engineer under Sub-Clause 2.2.

(b) (i) "Contract" means these Conditions (Parts I and II), the Specification, theDrawings, the Bill of Quantities, the Tender, the Letter of Acceptance, theContract Agreement (if completed) and such further documents as may beexpressly incorporated in the Letter of Acceptance or Contract Agreement (ifcompleted).(ii) "Specification" means the specification of the \'orks included in theContract and any modification thereof or addition thereto made under Clause51 or submitted by the Contractor and approved by the Engineer.

(iii) "Drawings" means all drawings, calculations and technical informationof a like nature provided by the Engineer to the Contractor under the Contractand all drawings, calculations, samples, patterns, models, operation andmaintenance manuals and other technical information of a like naturesubmitted by the Contractor and approved by the Engineer.

(iv) "Bill of Quantities" means the priced and completed bill of quantitiesforming part of the Tender.

(v) "Tender" means the Contractor's priced offer to the Employer for theexecution and completion of the Works and the remedying of any defectstherein in accordance with the provisions of the Contract, as accepted by theLetter of Acceptance.

(vi) "Letter of Acceptance" means the formal acceptance by the Employer ofthe Tender.

(vii) "Contract Agreement" means the contract agreement (if any) referred toin Sub-Clause 9.1.

(viii) "Appendix to Tender" means the appendix comprised in the form ofTender annexed to these Conditions.

(c) (i) "Commencement Date" means the date upon which the Contractorreceives the notice to commence issued by the Engineer pursuant to Clause 41.

© FIDIC 1987

Page 182: 35824401 FIDIC Guide to the Use of FIDIC

(ii) "Time for Completion" means the time for completing the execution ofand passing the Tests on Completion of the Works or any Section or partthereof as stated in the Contract (or as extended under Clause 44) calculatedfrom the Commencement Date.

(d)(i) "Tests on Completion" means the tests specified in the Contract orotherwise agreed by the Engineer and the Contractor which are to be made bythe Contractor before the Works or any Section or part thereof are taken overby the Employer.(ii) "Taking-Over Certificate" means a certificate issued pursuant to Clause48.

(e) (i) "Contract Price" means the sum stated in the Letter of Acceptance aspayable to the Contractor for the execution and completion of the Works andthe remedying of any defects therein in accordance with the provisions of theContract.(ii) "Retention Money" means the aggregate of all monies retained by theEmployer pursuant to Sub-Clause 60.2(a).

(f) (i) "Works" means the Permanent Works and the Temporary Works or eitherof them as appropriate.

(ii) "Permanent Works" means the permanent works to be executed(including Plant) in accordance with the Contract.

(iii) "Temporary Works" means all temporary works of every kind (otherthan Contractor's Equipment) required in or about the execution andcompletion of the Works and the remedying of any defects therein.

(iv) "Plant" means machinery, apparatus and the like intended to form orforming part of the Permanent Works.

(v) "Contractor's Equipment" means all appliances and things of whatsoevernature (other than Temporary Works) required for the execution andcompletion of the Works and the remedying of any defects therein, but doesnot include Plant, materials or other things intended to form or forming partof the Permanent Works.

(vi) "Section" means a part of the Works specifically identified in theContract as a Section.

(vii) "Site" means the places provided by the Employer where the Works areto be executed and any other places as may be specifically designated in theContract as forming part of the Site.

(g) (i) "cost" means all expenditure properly incurred or to be incurred, whetheron or off the Site, including overhead and other charges properly allocablethereto but does not include any allowance for profit.

(ii) "day" means calendar day.(iii) "foreign currency" means a currency of a country other than that inwhich the Works are to be located.

(iv) "writing" means any hand-written, type-written, or printedcommunication, including telex, cable and facsimile transmission.

Headings and 1.2 The headings and marginal notes in these Conditions shall not be deemed partMarginal Notes thereof or be taken into consideration in the interpretation or construction

thereof or of the Contract.

Interpretation 1.3 Words importing persons or parties shall include firms and corporations and anyorganisation having legal capacity.

Singular and 1.4 Words importing the singular only also include the plural and vice versa where thePlural context requires.

© FIDIC 1987

Page 183: 35824401 FIDIC Guide to the Use of FIDIC

Notices, 1.5 Wherever in the Contract provision is made for the giving or issue of any notice,Consents, consent, approval, certificate or determination by any person, unless otherwise

Approvals, specified such notice, consent, approval, certificate or determination shall be inCertificates and writing and the words "notify", "certify" or "determine" shall be construedDeterminations accordingly. Any such consent, approval, certificate or determination shall not

unreasonably be withheld or delayed.

Engineer and Engineer's Representative

Engineer's 2.1 (a) The Engineer shall carry out the duties specified in the Contract.Duties and (b) The Engineer may exercise the authority specified in or necessarily to be

implied from the Contract, provided, however, that if the Engineer is required,under the terms of his appointment by the Employer, to obtain the specificapproval of the Employer before exercising any such authority, particulars ofsuch requirements shall be set out in Part II of these Conditions. Provided furtherthat any requisite approval shall be deemed to have been given by the Employerfor any such authority exercised by the Engineer.

(c) Except as expressly stated in the Contract, the Engineer shall have noauthority to relieve the Contractor of any of his obligations under the Contract.

Engineer's 2.2 The Engineer's Representative shall be appointed by and be responsible to theRepresentative Engineer and shall carry out such duties and exercise such authority as may be

delegated to him by the Engineer under Sub-Clause 2.3.

Engineer's 2.3 The Engineer may from time to time delegate to the Engineer's RepresentativeAuthority to any of the duties and authorities vested in the Engineer and he may at any time

Delegate revoke such delegation. Any such delegation or revocation shall be in writing andshall not take effect until a copy thereof has been delivered to the Employer andthe Contractor.

Any communication given by the Engineer's Representative to the Contractor inaccordance with such delegation shall have the same effect as though it had beengiven by the Engineer. Provided that:

(a) any failure of the Engineer's Representative to disapprove any work,materials or Plant shall not prejudice the authority of the Engineer to disapprovesuch work, materials or Plant and to give instructions for the rectificationthereof;

(b) if the Contractor questions any communication of the Engineer'sRepresentative he may refer the matter to the Engineer who shall confirm, reverseor vary the contents of such communication.

Appointment 2.4 The Engineer or the Engineer's Representative may appoint any number ofof Assistants persons to assist the Engineer's Representative in the carrying out of his duties

under Sub-Clause 2.2. He shall notify to the Contractor the names, duties andscope of authority of such persons. Such assistants shall have no authority toissue any instructions to the Contractor save in so far as such instructions may benecessary to enable them to carry out their duties and to secure their acceptance ofmaterials, Plant or workmanship as being in accordance with the Contract, andany instructions given by any of them for those purposes shall be deemed to havebeen given by the Engineer's Representative.

Instructions 2.5 Instructions given by the Engineer shall be in writing, provided that if for anyin Writing reason the Engineer considers it necessary to give any such instruction orally, the

Contractor shall comply with such instruction. Confirmation in writing of suchoral instruction given by the Engineer, whether before or after the carrying out ofthe instruction, shall be deemed to be an instruction within the meaning of thisSub-Clause. Provided further that if the Contractor, within 7 days, confirms inwriting to the Engineer any oral instruction of the Engineer and suchconfirmation is not contradicted in writing within 7 days by the Engineer, it shallbe deemed to be an instruction of the Engineer.

© FIDIC 1987

Page 184: 35824401 FIDIC Guide to the Use of FIDIC

The provisions of this Sub-Clause shall equally apply to instructions given by theEngineer's Representative and any assistants of the Engineer or the Engineer'sRepresentative appointed pursuant to Sub-Clause 2.4.

Engineerto Act 2.6 Wherever, under the Contract, the Engineer is required to exercise his discretionImpartially by:

(a) giving his decision, opinion or consent, or

(b) expressing his satisfaction or approval, or

(c) determining value, or(d) otherwise taking action which may affect the rights and obligations of theEmployer or the Contractor

he shall exercise such discretion impartially within the terms of the Contract andhaving regard to all the circumstances. Any such decision, opinion, consent,expression of satisfaction, or approval, determination of value or action may beopened up, reviewed or revised as provided in Clause 67.

Assignment and Subcontracting

Assignment 3.1 The Contractor shall not, without the prior consent of the Employer (whichof Contract consent, notwithstanding the provisions of Sub-Clause 1.5, shall be at the sole

discretion of the Employer), assign the Contract or any part thereof, or anybenefit or interest therein or thereunder, otherwise than by:

(a) a charge in favour of the Contractor's bankers of any monies due or tobecome due under the Contract, or

(b) assignment to the Contractor's insurers (in cases where the insurers havedischarged the Contractor's loss or liability) of the Contractor's right to obtainrelief against any other party liable.

Subcontracting 4.1 The Contractor shall not subcontract the whole of the Works. Except whereotherwise provided by the Contract, the Contractor shall not subcontract anypart of the Works without the prior consent of the Engineer. Any such consentshall not relieve the Contractor from any liability or obligation under theContract and he shall be responsible for the acts, defaults and neglects of anySubcontractor, his agents, servants or workmen as fully as if they were the acts,defaults or neglects of the Contractor, his agents, servants or workmen.

Provided that the Contractor shall not be required to obtain such consent for:

(a) the provision of labour, or(b) the purchase of materials which are in accordance with the standards specifiedin the Contract, or

(c) the subcontracting of any pan of the Works for which the Subcontractor isnamed in the Contract.

Assignment of 4.2 In the event of a Subcontractor having undertaken towards the Contractor inSubcontractors' respect of the work executed, or the goods, materials, Plant or services supplied

Obligations by such Subcontractor, any continuing obligation extending for a periodexceeding that of the Defects Liability Period under the Contract, the Contractorshall at any time, after the expiration of such Period, assign to the Employer, atthe Employer's request and cost, the benefit of such obligation for the unexpiredduration thereof.

Contract Documents

Language/s 5.1 There is stated in Part II of these Conditions:and Law

(a) the language or languages in which the Contract documents shall be drawn up,and

© FIDIC 1987

Page 185: 35824401 FIDIC Guide to the Use of FIDIC

(b) the country or state the law of which shall apply to the Contract and according- to which the Contract shall be construed.

If the said documents are written in more than one language, the languageaccording to which the Contract shall be construed and interpreted is also statedin Part II of these Conditions, being therein designated the "Ruling Language".

Priority of 5.2 The severaVdocuments forming the Contract are to be taken as mutuallyContract explanatory of one another, but in case of ambiguities or discrepancies the same

Documents shall be explained and adjusted by the Engineer who shall thereupon issue to theContractor instructions thereon and in such event, unless otherwise provided inthe Contract, the priority of the documents forming the Contract shall be asfollows:

(1) The Contract Agreement (if completed);

(2) The Letter of Acceptance;

(3) The Tender;

(4) Part II of these Conditions;

(5) Part I of these Conditions; and

(6) Any other document forming part of the Contract.

Custody and 6.1 The Drawings shall remain in the sole custody of the Engineer, but two copiesSupply of thereof shall be provided to the Contractor free of charge. The Contractor shall

Drawings and make at his own cost any further copies required by him. Unless it is strictlyDocuments necessary for the purposes of the Contract, the Drawings, Specification and other

documents provided by the Employer or the Engineer shall not, without theconsent of the Engineer, be used or communicated to a third party by theContractor. Upon issue of the Defects Liability Certificate, the Contractor shallreturn to the Engineer all Drawings, Specification and other documents providedunder the Contract.

The Contractor shall supply to the Engineer four copies of all Drawings,Specification and other documents submitted by the Contractor and approved bythe Engineer in accordance with Clause 7, together with a reproducible copy ofany material which cannot be reproduced to an equal standard by photocopying.In addition the Contractor shall supply such further copies of such Drawings,Specification and other documents as the Engineer may request in writing for theuse of the Employer, who shall pay the cost thereof.

One Copy of 6.2 One copy of the Drawings, provided to or supplied by the Contractor asDrawings to be aforesaid, shall be kept by the Contractor on the Site and the same shall at all

Kept on Site reasonable times be available for inspection and use by the Engineer and by anyother person authorised by the Engineer in writing.

Disruption of 6.3 The Contractor shall give notice to the Engineer, with a copy to the Employer,Progress whenever planning or execution of the Works is likely to be delayed or disrupted

unless any further drawing or instruction is issued by the Engineer within areasonable time. The notice shall include details of the drawing or instructionrequired and of why and by when it is required and of any delay or disruptionlikely to be suffered if it is late.

Delays and 6.4 If, by reason of any failure or inability of the Engineer to issue, within a timeCost of Delay reasonable in all the circumstances, any drawing or instruction for which notice

of Drawings has been given by the Contractor in accordance with Sub-Clause 6.3, theContractor suffers delay and/or incurs costs then the Engineer shall, after dueconsultation with the Employer and the Contractor, determine:

(a) any extension of time to which the Contractor is entitled under Clause 44, and

(b) the amount of such costs, which shall be added to the Contract Price,

and shall notify the Contractor accordingly, with a copy to the Employer.

(ci FIDIC 1987

Page 186: 35824401 FIDIC Guide to the Use of FIDIC

Failure by 6.5 If the failure or inability of the Engineer to issue any drawings or instructions isContractor to caused in whole or in part by the failure of the Contractor to submit Drawings,

Submit Drawings Specification or other documents which he is required to submit under theContract, the Engineer shall take such failure by the Contractor into accountwhen making his determination pursuant to Sub-Clause 6.4.

Supplementary 7.1. The Engineer shall have authority to issue to the Contractor, from time to time,Drawings and such supplementary Drawings and instructions as shall be necessary for the

Instructions purpose of the proper and adequate execution and completion of the Works andthe remedying of any defects therein. The Contractor shall carry out and bebound by the same.

Permanent Works 7.2 Where the Contract expressly provides that part of the Permanent Works shall be

Designed by designed by the Contractor, he shall submit to the Engineer, for approval:Contractor

(a) such drawings, specifications, calculations and other information as shall benecessary to satisfy the Engineer as to the suitability and adequacy of that design,and(b) operation and maintenance manuals together with drawings of the PermanentWorks as completed, in sufficient detail to enable the Employer to operate,maintain, dismantle, reassemble and adjust the Permanent Works incorporatingthat design. The Works shall not be considered to be completed for the purposesof taking over in accordance with Clause 48 until such operation andmaintenance manuals, together with drawings on completion, have beensubmitted to and approved by the Engineer.

Responsibility 7.3 Approval by the Engineer, in accordance with Sub-Clause 7.2, shall not relieveUnaffected by the Contractor of any of his responsibilities under the Contract.

Approval

General ObligationsContractor's 8.1 TheContractor shall, with due care and diligence, design (to the extent provided

General for by the Contract), execute and complete the Works and remedy any defectsResponsibilities therein in accordance with the provisions of the Contract. The Contractor shall

provide all superintendence, labour, materials, Plant, Contractor's Equipmentand all other things, whether of a temporary or permanent nature, required inand for such design, execution, completion and remedying of any defects, so faras the necessity for providing the same is specified in or is reasonably to beinferred from the Contract.

Site Operations 8.2 The Contractor shall take full responsibility for the adequacy, stability and safetyand Methods of of all Site operations and methods of construction. Provided that the Contractor

Construction shall not be responsible (except as stated hereunder or as may be otherwiseagreed) for the design or specification of Permanent Works, or for the design orspecification of any Temporary Works not prepared by the Contractor. Wherethe Contract expressly provides that part of the Permanent Works shall bedesigned by the Contractor, he shall be fully responsible for that part of suchWorks, notwithstanding any approval by the Engineer.

Contract 9.1 The Contractor shall, if called upon so to do, enter into and execute the ContractAgreement Agreement, to be prepared and completed at the cost of the Employer, in the

form annexed to these Conditions with such modification as may be necessary.

Performance 10.1 If the Contract requires the Contractor to obtain security for his properSecurity performance of the Contract, he shall obtain and provide to the Employer such

security within 28 days after the receipt of the Letter of Acceptance, in the sumstated in the Appendix to Tender. When providing such security to the Employer,the Contractor shall notify the Engineer of so doing. Such security shall be in theform annexed to these Conditions or in such other form as may be agreedbetween the Employer and the Contractor. The institution providing suchsecurity shall be subject to the approval of the Employer. The cost of complyingwith the requirements of this Clause shall be borne by the Contractor, unless theContract otherwise provides.

© FIDIC 1987

Page 187: 35824401 FIDIC Guide to the Use of FIDIC

Period of 10.2 The performance security shall be valid until the Contractor has executed andValidity of completed the Works and remedied any defects therein in accordance with the

Performance Contract. No claim shall be made against such security after the issue of theSecurity Defects Liability Certificate in accordance with Sub-Clause 62.1 and such

security shall be returned to the Contractor within 14 days of the issue of the saidDefects Liability Certificate.

Claims under 10.3 Prior to making a claim under the performance security the Employer shall, inPerformance every case, notify the Contractor stating the nature of the default in respect of

Security which the claim is to be made.

Inspection 11 .1 The Employer shall have made available to the Contractor, before the submissionof Site by the Contractor of the Tender, such data on hydrological and sub-surface

conditions as have been obtained by or on behalf of the Employer frominvestigations undertaken relevant to the Works but the Contractor shall beresponsible for his own interpretation thereof.The Contractor shall be deemed to have inspected and examined the Site and itssurroundings and information available in connection therewith and to havesatisfied himself (so far as is practicable, having regard to considerations of costand time) before submitting his Tender, as to:

(a) the form and nature thereof, including the sub-surface conditions,

(b) the hydrological and climatic conditions,

(c) the extent and nature of work and materials necessary for the execution andcompletion of the Works and the remedying of any defects therein,and

(d) the means of access to the Site and the accommodation he may require

and, in general, shall be deemed to have obtained all necessary information,subject as above mentioned, as to risks, contingencies and all other circumstanceswhich may influence or affect his Tender.

The Contractor shall be deemed to have based his Tender on the data madeavailable by the Employer and on his own inspection and examination, all asaforementioned.

Sufficiency 12.1 The Contractor shall be deemed to have satisfied himself as to the correctness andof Tender sufficiency of the Tender and of the rates and prices stated in the Bill of

Quantities, all of which shall, except insofar as it is otherwise provided in theContract, cover all his obligations under the Contract (including those in respectof the supply of goods, materials, Plant or services or of contingencies for whichthere is a Provisional Sum) and all matters and things necessary for the properexecution and completion of the Works and the remedying of any defects therein.

Adverse Physical 12.2 If, however, during the execution of the Works the Contractor encountersObstructions or physical obstructions or physical conditions, other than climatic conditions on

Conditions the Site, which obstructions or conditions were, in his opinion, not foreseeable byan experienced contractor, the Contractor shall forthwith give notice thereof tothe Engineer, with a copy to the Employer. On receipt of such notice, theEngineer shall, if in his opinion such obstructions or conditions could not havebeen reasonably foreseen by an experienced contractor, after due consultationwith the Employer and the Contractor, determine:

(a) any extension of time to which the Contractor is entitled under Clause 44, and

(b) the amount of any costs which may have been incurred by the Contractor byreason of such obstructions or conditions having been encountered, which shallbe added to the Contract Price,and shall notify the Contractor accordingly, with a copy to the Employer. Suchdetermination shall take account of any instruction which the Engineer may issueto the Contractor in connection therewith, and any proper and reasonablemeasures acceptable to the Engineer which the Contractor may take in theabsence of specific instructions from the Engineer.

© FIDIC 1987

Page 188: 35824401 FIDIC Guide to the Use of FIDIC

Work to be in 13.1 Unless it is legally or physically impossible, the Contractor shall execute andAccordance with complete the Works and remedy any defects therein in strict accordance with the

Contract Contract to the satisfaction of the Engineer. The Contractor shall comply withand adhere strictly to the Engineer's instructions on any matter, whethermentioned in the Contract or not, touching or concerning the Works. TheContractor shall take instructions only from the Engineer or, subject to theprovisions of Clause 2, from the Engineer's Representative.

Programme to 14.1 The Contractor shall, within the time stated in Part II of these Conditions afterbe Submitted the date of the Letter of Acceptance, submit to the Engineer for his consent a

programme, in such form and detail as the Engineer shall reasonably prescribe,for the execution of the Works. The Contractor shall, whenever required by theEngineer, also provide in writing for his information a general description of thearrangements and methods which the Contractor proposes to adopt for theexecution of the Works.

Revised 14.2 If at any time it should appear to the Engineer that the actual progress of theProgramme Works does not conform to the programme to which consent has been given

under Sub-Clause 14.1, the Contractor shall produce, at the request of theEngineer, a revised programme showing the modifications to such programmenecessary to ensure completion of the Works within the Time for Completion.

Cash Flow 14.3 The Contractor shall, within the time stated in Part II of these Conditions afterEstimate to be the date of the Letter of Acceptance, provide to the Engineer for his information

Submitted a detailed cash flow estimate, in quarterly periods, of all payments to which theContractor will be entitled under the Contract and the Contractor shallsubsequently supply revised cash flow estimates at quarterly intervals, if requiredto do so by the Engineer.

Contractor not 14.4 The submission to and consent by the Engineer of such programmes or theRelieved of Duties provision of such general descriptions or cash flow estimates shall not relieve theorResponsibilities Contractor of any of his duties or responsibilities under the Contract.

Contractor's 15.1 The Contractor shall provide all necessary superintendence during the executionSuperintendence of the Works and as long thereafter as the Engineer may consider necessary for

the proper fulfilling of the Contractor's obligations under the Contract. TheContractor, or a competent and authorised representative approved of by theEngineer, which approval may at any time be withdrawn, shall give his wholetime to the superintendence of the Works. Such authorised representative shallreceive, on behalf of the Contractor, instructions from the Engineer or, subject tothe provisions of Clause 2, the Engineer's Representative.

If approval of the representative is withdrawn by the Engineer, the Contractorshall, as soon as is practicable, having regard to the requirement of replacing himas hereinafter mentioned, after receiving notice of such withdrawal, remove therepresentative from the Works and shall not thereafter employ him again on theWorks in any capacity and shall replace him by another representative approvedby the Engineer.

-

Contractor's 16.1 The Contractor shall provide on the Site in connection with the execution andEmployees completion of the Works and the remedying of any defects therein

(a) only such technical assistants as are skilled and experienced in their respectivecallings and such foremen and leading hands as are competent to give propersuperintendence of the Works, and

(b) such skilled, semi-skilled and unskilled labour as is necessary for the properand timely fulfilling of the Contractor's obligations under the Contract.

Engineer at 16.2 The Engineer shall be at liberty to object to and require the Contractor to removeLiberty to Object forthwith from the Works any person provided by the Contractor who, in the

opinion of the Engineer, misconducts himself, or is incompetent or negligent inthe proper performance of his duties, or whose presence on Site is otherwiseconsidered by the Engineer to be undesirable, and such person shall not be againallowed upon the Works without the consent of the Engineer. Any person soremoved from the Works shall be replaced as soon as possible.

FIDIC 1987

Page 189: 35824401 FIDIC Guide to the Use of FIDIC

Setting-out 17.1 TheContractor shall be responsible for:(a) the accurate setting-out of the Works in relation to original points, lines andlevels of reference given by the Engineer in writing,

(b) the correctness, subject as above mentioned, of the position, levels,dimensions and alignment of all parts of the Works, and

(c) the provision of all necessary instruments, appliances and labour inconnection with the foregoing responsibilities.

If, at any time during the execution of the Works, any error appears in theposition, levels, dimensions or alignment of any part of the Works, theContractor, on being required so to do by the Engineer, shall, at his own cost,rectify such error to the satisfaction of the Engineer, unless such error is based onincorrect data supplied in writing by the Engineer, in which case the Engineershall determine an addition to the Contract Price in accordance with Clause 52and shall notify the Contractor accordingly, with a copy to the Employer.

The checking of any setting-out or of any line or level by the Engineer shall not inany way relieve the Contractor of his responsibility for the accuracy thereof andthe Contractor shall carefully protect and preserve all bench-marks, sight-rails,pegs and other things used in setting-out the Works.

Boreholes and 18.1 If, at any time during the execution of the Works, the Engineer requires theExploratory Contractor to make boreholes or to carry out exploratory excavation, suchExcavation requirement shall be the subject of an instruction in accordance with Clause 51,

unless an item o a Provisional Sum in respect of such work is included in the Billof Quantities.

Safety, Security 19.1 The Contractor shall, throughout the execution and completion of the Worksand Protection of and the remedying of any defects therein:the Environment (a) have full regard for the safety of all persons entitled to be upon the Site and

keep the Site (so far as the same is under his control) and the Works (so far as thesame are not completed or occupied by the Employer) in an orderly stateappropriate to the avoidance of danger to such persons, and

(b) provide and maintain at his own cost all lights, guards, fencing, warning signsand watching, when and where necessary or required by the Engineer or by anyduly constituted authority, for the protection of the Works or for the safety andconvenience of the public or others, and

(c) take all reasonable steps to protect the environment on and off the Site and toavoid damage or nuisance to persons or to property of the public or othersresulting from pollution, noise or other causes arising as a consequence of hismethods of operation.

Employer's 19.2 If under Clause 31 the Employer shall carry out work on the Site with his ownResponsibilities workmen he shall, in respect of such work:

(a) have full regard to the safety of all persons entitled to be upon the Site, and

(b) keep the Site in an orderly state appropriate to the avoidance of danger to suchpersons.If under Clause 31 the Employer shall employ other contractors on the Site heshall require them to have the same regard for safety and avoidance of danger.

Care of Works 20.1 The Contractor shall take full responsibility for the care of the Works andmaterials and Plant for incorporation therein from the Commencement Dateuntil the date of issue of the Taking-Over Certificate for the whole of the Works,when the responsibility for the said care shall pass to the Employer. Providedthat:

(a) if the Engineer issues a Taking-Over Certificate for any Section or part of thePermanent Works the Contractor shall cease to be liable for the care of thatSection or part from the date of issue of the Taking-Over Certificate, when theresponsibility for the care of that Section or part shall pass to the Employer, and

FIDIC t987

Page 190: 35824401 FIDIC Guide to the Use of FIDIC

(b) the Contractor shall take full responsibility for the care of any outstandingWorks and materials and Plant for incorporation therein which he undertakes tofinish during the Defects Liability Period until such outstanding Works have beencompleted pursuant to Clause 49.

Responsibility 20.2 Ifany loss or damage happens to the Works, or any part thereof, or materials orto Rectify Loss Plant for incorporation therein, during the period for which the Contractor is

or Damage responsible for the care thereof, from any cause whatsoever, other than the risksdefined in Sub-Clause 20.4, the Contractor shall, at his own cost, rectify such lossor damage so that the Permanent Works conform in every respect with theprovisions of the Contract to the satisfaction of the Engineer. The Contractorshall also be liable for any loss or damage to the Works occasioned by him in thecourse of any operations carried out by him for the purpose of complying with hisobligations under Clauses 49and 50.

Loss or 20.3 In the event of any such loss or damage happening from any of the risks definedDamage Due to in Sub-Clause 20.4, or in combination with other risks, the Contractor shall, if

Employer's Risks and to the extent required by the Engineer, rectify the loss or damage and theEngineer shall determine an addition to the Contract Price in accordance withClause 52 and shall notify the Contractor accordingly, with a copy to theEmployer. In the case of a combination of risks causing loss or damage any suchdetermination shall take into account the proportional responsibility of theContractor and the Employer.

Employer's Risks 20.4 The Employer's risks are:

(a) war, hostilities (whether war be declared or not), invasion, act of foreignenemies,

(b) rebellion, revolution, insurrection, or military or usurped power, or civil war,

(c) ionising radiations, or contamination by radio-activity from any nuclear fuel,or from any nuclear waste from the combustion of nuclear fuel, radioactive toxicexplosive, or other hazardous properties of any explosive nuclear assembly ornuclear component thereof,

(d) pressure waves caused by aircraft or other aerial devices travelling at sonic orsupersonic speeds,

(e) riot, commotion or disorder, unless solely restricted to employees of theContractor or of his Subcontractors and arising from the conduct of the Works,

(f) loss or damage due to the use or occupation by the Employer of any Section orpart of the Permanent Works, except as may be provided for in the Contract,

(g) loss or damage to the extent that it is due to the design of the Works, otherthan any part of the design provided by the Contractor or for which theContractor is responsible,

(h) any operation of the forces of nature against which an experienced contractorcould not reasonably have been expected to take precautions.

Insurance of 21.1 The Contractor shall, without limiting his or the Employer's obligations andWorks and responsibilities under Clause 20, insure:

Contractor's(a) the Works, together with materials and Plant for incorporation therein, to the

qu pme full replacement cost

(b) an additional sum of 15 per cent of such replacement cost, or as may bespecified in Part II of these Conditions, to cover any additional costs of andincidental to the rectification of loss or damage including professional fees andthe cost of demolishing and removing any part of the Works and of removingdebris of whatsoever nature

(c) the Contractor's Equipment and other things brought onto the Site by theContractor, for a sum sufficient to provide for their replacement at the Site.

FIDIC 1987

Page 191: 35824401 FIDIC Guide to the Use of FIDIC

Scope of Cover 21.2 The insurance in paragraphs (a) and (b) of Sub-Clause 21.1 shall be in the jointnames of the Contractor and the Employer and shall cover:

(a) the Employer and the Contractor against all loss or damage from whatsoevercause arising, other than as provided in Sub-Clause 21.4, from the start of workat the Site until the date of issue of the relevant Taking-Over Certificate in respectof the Works or any Section or part thereof as the case may be, and

(b) the Contractor for his liability:

(i) during the Defects Liability Period for loss or damage arising from a causeoccurring prior to the commencement of the Defects Liability Period, and

(ii) for loss or damage occasioned by the Contractor in the course of anyoperations carried out by him for the purpose of complying with hisobligations under Clauses 49 and 50.

Responsibility for 21.3 Any amounts not insured or not recovered from the insurers shall be borne by theAmounts not Employer or the Contractor in accordance with their responsibilities under

Recovered Clause 20.

Exclusions 21.4 There shall be no obligation for the insurances in Sub-Clause 21.1 to include lossor damage caused by

(a) war, hostilities (where war be declared or not), invasion, act of foreignenemies,

(b) rebellion, revolution, insurrection, or military or usurped power, or civil war,

(c) ionising radiations, or contamination by radio-activity from any nuclear fuel,or from any nuclear waste from the combustion of nuclear fuel, radio-active toxicexplosive, or other hazardous properties of any explosive nuclear assembly ornuclear component thereof,

(d) pressure waves caused by aircraft or other aerial devices travelling at sonic orsupersonic speeds.

Damage to 22.1 The Contractor shall, except if and so far as the Contract provides otherwise,Persons and indemnify the Employer against all losses and claims in respect of:

Property (a) death of or injury to any person, or

(b) loss of or damage to any property (other than the Works),

which may arise out of or in consequence of the execution and completion of theWorks and the remedying of any defects therein, and against all claims,proceedings, damages, costs, charges and expenses whatsoever in respect thereofor in relation thereto, subject to the exceptions defined in Sub-Clause 22.2.

Exceptions 22.2 The "exceptions"referred to in Sub-Clause 22.1 are:

(a) the permanent use or occupation of land by the Works, or any part thereof,

(b) the right of the Employer to execute the Works, or any part thereof, on, over,under, in or through any land,(c) damage to property which is the unavoidable result of the execution andcompletion of the Works, or the remedying of any defects therein, in accordancewith the Contract,

(d) death of or injury to persons or loss of or damage to property resulting fromany act or neglect of the Employer, his agents, servants or other contractors, notbeing employed by the Contractor, or in respect of any claims, proceedings,damages, costs, charges and expenses in respect thereof or in relation thereto or,where the injury or damage was contributed to by the Contractor, his servants oragents, such part of the said injury or damage as may be just and equitable havingregard to the extent of the responsibility of the Employer, his servants or agentsor other contractors for the injury or damage.

© FIDIC 1987 1 C1

Page 192: 35824401 FIDIC Guide to the Use of FIDIC

Indemnity by 22.3 The Employer shall indemnify the Contractor against all claims, proceedings,Employer damages, costs, charges and expenses in respect of the matters referred to in the

exceptions defined in Sub-Clause 22.2.

Third Party 23.1 The Contractor shall, without limiting his or the Employer's obligations andInsurance responsibilities under Clause 22, insure, in the joint names of the Contractor and(including the Employer, against liabilities for death of or injury to any person (other than

Employer's as provided in Clause 24) or loss of or damage to any property (other than theProperty) Works) arising out of the performance of the Contract, other than the exceptions

defined in paragraphs (a), (b) and (c) of Sub-Clause 22.2.

Minimum Amount 23.2 Such insurance shall be for at least the amount stated in the Appendix to Tender.of Insurance

Cross Liabilities 23.3 The insurance policy shall include a cross liability clause such that the insuranceshall apply to the Contractor and to the Employer as separate insureds.

Accident or Injury 24.1 The Employer shall not be liable for or in respect of any damages orto Workmen compensation payable to any workman or other person in the employment of the

Contractor or any Subcontractor, other than death or injury resulting from anyact or default of the Employer, his agents or servants. The Contractor shallindemnify and keep indemnified the Employer against all such damages andcompensation, other than those for which the Employer is liable as aforesaid, andagainst all claims, proceedings, damages, costs, charges, and expenseswhatsoever in respect thereof or in relation thereto.

Insurance 24.2 The Contractor shall insure against such liability and shall continue suchAgainst Accident insurance during the whole of the time that any persons are employed by him on

to Workmen the Works. Provided that, in respect of any persons employed by anySubcontractor, the Contractor's obligations to insure as aforesaid under thisSub-Clause shall be satisfied if the Subcontractor shall have insured against theliability in respect of such persons in such manner that the Employer isindemnified under the policy, but the Contractor shall require suchSubcontractor to produce to the Employer, when required, such policy ofinsurance and the receipt for the payment of the current premium.

Evidence and 25.1 The Contractor shall provide evidence to the Employer prior to the start of workTerms of at the Site that the insurances required under the Contract have been effected and

Insurances shall, within 84 days of the Commencement Date, provide the insurance policiesto the Employer. When providing such evidence and such policies to theEmployer, the Contractor shall notify the Engineer of so doing. Such insurancepolicies shall be consistent with the general terms agreed prior to the issue of theLetter of Acceptance. The Contractor shall effect all insurances for which he isresponsible with insurers and in terms approved by the Employer.

Adequacy of 25.2 The Contractor shall notify the insurers of changes in the nature, extent orInsurances programme for the execution of the Works and ensure the adequacy of the

insurances at all times in accordance with the terms of the Contract and shall,when required, produce to the Employer the insurance policies in force and thereceipts for payment of the current premiums.

Remedyon 25.3 If the Contractor fails to effect and keep in force any of the insurances requiredContractor's under the Contract, or fails to provide the policies to the Employer within the

Failure to Insure period required by Sub-Clause 25.1, then and in any such case the Employer mayeffect and keep in force any such insurances and pay any premium as may benecessary for that purpose and from time to time deduct the amount so paid fromany monies due or to become due to the Contractor, or recover the same as a debtdue from the Contractor.

Compliance 25.4 In theevent that the Contractor or the Employer fails to comply with conditionswith Policy imposed by the insurance policies effected pursuant to the Contract, each shallConditions indemnify the other against all losses and claims arising from such failure.

© FIDIC 1987

Page 193: 35824401 FIDIC Guide to the Use of FIDIC

Compliance with 26.1 TheContractor shall conform in all respects, including by the giving of all noticesStatutes, and the paying of all fees, with the provisions of:

Regulations (a) any National or State Statute, Ordinance, or other Law, or any regulation, orbye-law of any local or other duly constituted authority in relation to theexecution and completion of the Works and the remedying of any defects therein,and

(b) the rules and regulations of all public bodies and companies whose property orrights are affected or may be affected in any way by the Works,

and the Contractor shall keep the Employer indemnified against all penalties andliability of every kind for breach of any such provisions. Provided always that theEmployer shall be responsible for obtaining any planning, zoning or other similarpermission required for the Works to proceed and shall indemnify the Contractorin accordance with Sub-Clause 22.3.

Fossils 27.1 All fossils, coins, articles of value or antiquity and structures and other remainsor things of geological or archaeological interest discovered on the Site shall, asbetween the Employer and the Contractor, be deemed to be the absolute propertyof the Employer. The Contractor shall take reasonable precautions to prevent hisworkmen or any other persons from removing or damaging any such article orthing and shall, immediately upon discovery thereof and before removal,acquaint the Engineer of such discovery and carry out the Engineer's instructionsfor dealing with the same. If, by reason of such instructions, the Contractorsuffers delay and/or incurs costs then the Engineer shall, after due consultationwith the Employer and the Contractor, determine:

(a) any extension of time to which the Contractor is entitled under Clause 44, and

(b) the amount of such costs, which shall be added to the Contract Price,

and shall notify the Contractor accordingly, with a copy to the Employer.

Patent Rights 28.1 The Contractor shall save harmless and indemnify the Employer from andagainst all claims and proceedings for or on account of infringement of anypatent rights, design trademark or name or other protected rights in respect ofany Contractor's Equipment, materials or Plant used for or in connection with orfor incorporation in the Works and from and against all damages, costs, chargesand expenses whatsoever in respect thereof or in relation thereto, except wheresuch infringement results from compliance with the design or Specificationprovided by the Engineer.

Royalties 28.2 Except where otherwise stated, the Contractor shall pay all tonnage and otherroyalties, rent and other payments or compensation, if any, for getting stone,sand, gravel, clay or other materials required for the Works.

Interference 29.1 All operations necessary for the execution and completion of the Works and thewith Traffic remedying of any defects therein shall, so far as compliance with the requirements

and Adjoining of the Contract permits, be carried on so as not to interfere unnecessarily orProperties improperly with:

(a) the convenience of the public, or

(b) the access to, use and occupation of public or private roads and footpaths toor of properties whether in the possession of the Employer or of any other person.

The Contractor shall save harmless and indemnify the Employer in respect of allclaims, proceedings, damages, costs, charges and expenses whatsoever arising Outof, or in relation to, any such matters insofar as the Contractor is responsibletherefor.

© FIDIC 1987 101 ¶3

Page 194: 35824401 FIDIC Guide to the Use of FIDIC

Avoidance 30.1 The Contractor shall use every reasonable means to prevent any of the roads orof Damage bridges communicating with or on the routes to the Site from being damaged or

to Roads injured by any traffic of the Contractor or any of his Subcontractors and, inparticular , shall select routes, choose and use vehicles and restrict and distributeloads so that any such extraordinary traffic as will inevitably arise from themoving of materials, Plant, Contractor's Equipment or Temporary Works fromand to the Site shall be limited, as far as reasonably possible, and so that nounnecessary damage or injury may be occasioned to such roads and bridges.

Transport of 30.2 Save insofar as the Contract otherwise provides, the Contractor shall beContractor's responsible for and shall pay the cost of strengthening any bridges or altering or

Equipment or improving any road communicating with or on the routes to the Site to facilitateTemporary Works the movement of Contractor's Equipment or Temporary Works and the

Contractor shall indemnify and keep indemnified the Employer against all claimsfor damage to any such road or bridge caused by such movement, including suchclaims as may be made directly against the Employer, and shall negotiate and payall claims arising solely out of such damage.

Transport of 30.3 If, notwithstanding Sub-Clause 30.1, any damage occurs to any bridge or roadMaterials or communicating with or on the routes to the Site arising from the transport of

Plant materials or Plant, the Contractor shall notify the Engineer with a copy to theEmployer, as soon as he becomes aware of such damage or as soon as he receivesany claim from the authority entitled to make such claim. Where under any lawor regulation the haulier of such materials or Plant is required to indemnify theroad authority against damage the Employer shall not be liable for any costs,charges or expenses in respect thereof or in relation thereto. In other cases theEmployer shall negotiate the settlement of and pay all sums due in respect of suchclaim and shall indemnify the Contractor in respect thereof and in respect of allclaims, proceedings, damages, costs, charges and expenses in relation thereto.Provided that if and so far as any such claim or part thereof is, in the opinion ofthe Engineer, due to any failure on the part of the Contractor to observe andperform his obligations under Sub-Clause 30.1, then the amount, determined bythe Engineer, after due consultation with the Employer and the Contractor, to bedue to such failure shall be recoverable from the Contractor by the Employer andmay be deducted by the Employer from any monies due or to become due to theContractor and the Engineer shall notify the Contractor accordingly, with a copyto the Employer. Provided also that the Employer shall notify the Contractorwhenever a settlement is to be negotiated and, where any amount may be duefrom the Contractor, the Employer shall consult with the Contractor before suchsettlement is agreed.

Waterborne 30.4 Where the nature of the Works is such as to require the use by the Contractor ofTraffic waterborne transport the foregoing provisions of this Clause shall be construed as

though "road" included a lock, dock, sea wall or other structure related to awaterway and "vehicle" included craft, and shall have effect accordingly.

Opportunities 31.1 The Contractor shall, in accordance with the requirements of the Engineer,for Other afford all reasonable opportunities for carrying out their work to:

Contractors(a) any other contractors employed by the Employer and their workmen,

\(b) the workmen of the Employer, and

(c) the workmen of any duly constituted authorities who may be employed in theexecution on or near the Site of any work not included in the Contract or of anycontract which the Employer may enter into in connection with or ancillary to theWorks.

Facilities for 31.2 If, however, pursuant to Sub-Clause 31.1 the Contractor shall, on the writtenOther Contractors request of the Engineer:

(a) make available to any such other contractor, or to the Employer or any suchauthority, any roads or ways for the maintenance of which the Contractor isresponsible, or

(Ci FIDIC 1987

Page 195: 35824401 FIDIC Guide to the Use of FIDIC

(b) permit the use, by any such, of Temporary Works or Contractor's Equipmenton the Site, or

(c) provide any other service of whatsoever nature for any such,

the Engineer shall determine an addition to the Contract Price in accordance withClause 52 and shall notify the Contractor accordingly, with a copy to theEmployer.

Contractor to 32.1 During the execution of the Works the Contractor shall keep the Site reasonablyKeep Site Clear free from all unnecessary obstruction and shall store or dispose of any

Contractor's Equipment and surplus materials and clear away and remove fromthe Site any wreckage, rubbish or Temporary Works no longer required.

Clearance of Site 33.1 Upon the issue of any Taking-Over Certificate the Contractor shall clear awayon Completion and remove from that part of the Site to which such Taking-Over Certificate

relates all Contractor's Equipment, surplus material, rubbish and TemporaryWorks of every kind, and leave such part of the Site and Works clean and in aworkmanlike condition to the satisfaction of the Engineer. Provided that theContractor shall be entitled to retain on Site, until the end of the Defects LiabilityPeriod, such materials, Contractor's Equipment and Temporary Works as arerequired by him for the purpose of fulfilling his obligations during the DefectsLiability Period.

Labour

Engagement of 34.1 The Contractor shall, unless otherwise provided in the Contract, make his ownStaff and Labour arrangements for the engagement of all staff and labour, local or other, and for

their payment, housing, feeding and transport.Returns of Labour 35.1 The Contractor shall, if required by the Engineer, deliver to the Engineer a returnand Contractor's in detail, in such form and at such intervals as the Engineer may prescribe,

Equipment showing the staff and the numbers of the several classes of labour from time totime employed by the Contractor on the Site and such information respectingContractor's Equipment as the Engineer may require.

Materials, Plant and Workmanship

Quality of 36.1 All materials, Plant and workmanship shall be(a) of the respective kinds described in the Contract and in accordance with theEngineer s instructions, and

(b) subjected from time to time to such tests as the Engineer may require at theplace of manufacture, fabrication or preparation, or on the Site or at such otherplace or places as may be specified in the Contract, or at all or any of such places.

The Contractor shall provide such assistance, labour, electricity, fuels, stores,apparatus and instruments as are normally required for examining, measuringand testing any materials or Plant and shall supply samples of materials, beforeincorporation in the Works, for testing as may be selected and required by theEngineer.

Cost of Samples 36.2 All samples shall be supplied by the Contractor at his own cost if the supplythereof is clearly intended by or provided for in the Contract.

Cost of Tests 36.3 The cost of making any test shall be borne by the Contractor if such test is

(a) clearly intended by or provided for in the Contract, or

(b) particularised in the Contract (in cases only of a test under load or of a test toascertain whether the design of any finished or partially finished work isappropriate for the purposes which it was intended to fulfil) in sufficient detail toenable the Contractor to price or allow for the same in his Tender.

© FIDIC 1987

Page 196: 35824401 FIDIC Guide to the Use of FIDIC

Cost of Tests not 36.4 If any test required by the Engineer which isProvided for

(a) not so intended by or provided for, or

(b) (in the cases above mentioned) not so particularised, or

(c) (though so intended or provided for) required by the Engineer to be carried outat any place other than the Site or the place of manufacture, fabrication orpreparation of the materials or Plant tested,

shows the materials, Plant or workmanship not to be in accordance with theprovisions of the Contract to the satisfaction of the Engineer, then the cost ofsuch test shall be borne by the Contractor, but in any other case Sub-Clause 36.5shall apply.

Engineer's 36.5 Where, pursuant to Sub-Clause 36.4, this Sub-Clause applies the Engineer shall,Determination after due consultation with the Employer and the Contractor, determine:

where Tests not . .

Provided for (a) any extension of time to which the Contractor is entitled under Clause 44,and

(b) the amount of such costs, which shall be added to the Contract Price,

and shall notify the Contractor accordingly, with a copy to the Employer.

Inspection of 37.1 The Engineer, and any person authorised by him, shall at all reasonable timesOperations have access to the Site and to all workshops and places where materials or Plant

are being manufactured, fabricated or prepared for the Works and theContractor shall afford every facility for and every assistance in obtaining theright to such access.

Inspection and 37.2 The Engineer shall be entitled, during manufacture, fabrication or preparation toTesting inspect and test the materials and Plant to be supplied under the Contract. If

materials or Plant are being manufactured, fabricated or prepared in workshopsor places other than those of the Contractor, the Contractor shall obtainpermission for the Engineer to carry out such inspection and testing in thoseworkshops or places. Such inspection or testing shall not release the Contractorfrom any obligation under the Contract.

Dates for 37.3 The Contractor shall agree with the Engineer on the time and place for theInspection inspection or testing of any materials or Plant as provided in the Contract. The

and Testing Engineer shall give the Contractor not less than 24 hours notice of his intention tocarry out the inspection or to attend the tests. If the Engineer, or his dulyauthorised representative, does not attend on the date agreed, the Contractormay, unless otherwise instructed by the Engineer, proceed with the tests, whichshall be deemed to have been made in the presence of the Engineer. TheContractor shall forthwith forward to the Engineer duly certified copies of thetest readings. If the Engineer has not attended the tests, he shall accept the saidreadings as accurate.

Rejection 37.4 If, at the time and place agreed in accordance with Sub-Clause 37.3, the materialsor Plant are not ready for inspection or testing or if, as a result of the inspectionor testing referred to in this Clause, the Engineer determines that the materials orPlant are defective or otherwise not in accordance with the Contract, he mayreject the materials or Plant and shall notify the Contractor thereof immediately.The notice shall state the Engineer's objections with reasons. The Contractorshall then promptly make good the defect or ensure that rejected materials orPlant comply with the Contract. If the Engineer so requests, the tests of rejectedmaterials or Plant shall be made or repeated under the same terms andconditions. All costs incurred by the Employer by the repetition of the tests shall,after due consultation with the Employer and the Contractor, be determined bythe Engineer and shall be recoverable from the Contractor by the Employer andmay be deducted from any monies due or to become due to the Contractor andthe Engineer shall notify the Contractor accordingly, with a copy to theEmployer.

© FIDiC 1987

Page 197: 35824401 FIDIC Guide to the Use of FIDIC

Independent 37.5 The Engineer may delegate inspection and testing of materials or Plant to anInspection independent inspector. Any such delegation shall be effected in accordance with

Sub-Clause 2.4 and for this purpose such independent inspector shall beconsidered as an assistant of the Engineer. Notice of such appointment (not beingless than 14 days) shall be given by the Engineer to the Contractor.

Examination of 38.1 No part of the Works shall be covered up or put out of view without the approvalWork before of the Engineer and the Contractor shall afford full opportunity for the EngineerCovering up to examine and measure any such part of the Works which is about to be covered

up or put out of view and to examine foundations before any part of the Works isplaced thereon. The Contractor shall give notice to the Engineer whenever anysuch part of the Works or foundations is or are ready or about to be ready forexamination and the Engineer shall, without unreasonable delay, unless heconsiders it unnecessary and advises the Contractor accordingly, attend for thepurpose of examining and measuring such part of the Works or of examiningsuch foundations.

Uncovering 38.2 The Contractor shall uncover any part of the Works or make openings in orand Making through the same as the Engineer may from time to time instruct and shall

Openings reinstate and make good such part. If any such part has been covered up or putout of view after compliance with the requirement of Sub-Clause 38.1 and isfound to be executed in accordance with the Contract, the Engineer shall, afterdue consultation with the Employer and the Contractor, determine the amount ofthe Contractor's costs in respect of such of uncovering, making openings in orthrough, reinstating and making good the same, which shall be added to theContract Price, and shall notify the Contractor accordingly, with a copy to theEmployer. In any other case all costs shall be borne by the Contractor.

Removal of 39.1 The Engineer shall have authority to issue instructions from time to time, for:Improper Work, . . . . .

Materials or Plant (a) the removal from the Site, within such time or times as may be specified in theinstruction, of any materials or Plant which, in the opinion of the Engineer, arenot in accordance with the Contract,

(b) the substitution of proper and suitable materials or Plant, and

(c) the removal and proper re-execution, notwithstanding any previous testthereof or interim payment therefor, of any work which, in respect of

(i) materials, Plant or workmanship, or

(ii) design by the Contractor or for which he is responsible,

is not, in the opinion of the Engineer, in accordance with the Contract.

Default of 39.2 In case of default on the part of the Contractor in carrying out such instructionContractor in within the time specified therein or, if none, within a reasonable time, the

Compliance Employer shall be entitled to employ and pay other persons to carry out the sameand all costs consequent thereon or incidental thereto shall, after dueconsultation with the Employer and the Contractor, be determined by theEngineer and shall be recoverable from the Contractor by the Employer, and maybe deducted by the Employer from any monies due or to become due to theContractor and the Engineer shall notify the Contractor accordingly, with a copyto the Employer.

Suspension

Suspension 40.1 TheContractor shall, on the instructions of the Engineer, suspend the progress ofof Work the Works or any part thereof for such time and in such manner as the Engineer

may consider necessary and shall, during such suspension, properly protect andsecure the Works or such part thereof so far as is necessary in the opinion of theEngineer. Unless such suspension is

(a) otherwise provided for in the Contract, or

FIDIC 1987

Page 198: 35824401 FIDIC Guide to the Use of FIDIC

(b) necessary by reason of some default of or breach of contract by theContractor or for which he is responsible, or

(c) necessary by reason of climatic conditions on the Site, or

(d) necessary for the proper execution of the Works or for the safety of the Worksor any part thereof (save to the extent that such necessity arises from any act ordefault by the Engineer or the Employer or from any of the risks defined inSub-Clause 20.4),

Sub-Clause 40.2 shall apply.

Engineer's 40.2 Where, pursuant to Sub-Clause 40.1, this Sub-Clause applies the Engineer shall,Determination after due consultation with the Employer and the Contractor, determine

following .

Suspension(a) any extension of time to which the Contractor is entitled under Clause 44, and

(b) the amount, which shall be added to the Contract Price, in respect of the costincurred by the Contractor by reason of such suspension,

and shall notify the Contractor accordingly, with a copy to the Employer.

Suspension 40.3 If the progress of the Works or any part thereof is suspended on the writtenlasting more instructions of the Engineer and if permission to resume work is not given by thethan 84 Days Engineer within a period of 84 days from the date of suspension then, unless such

suspension is within paragraph (a), (b), (c) or (d) of Sub-Clause 40.1, theContractor may give notice to the Engineer requiring permission, within 28 daysfrom the receipt thereof, to proceed with the Works or that part thereof in regardto which progress is suspended. If, within the said time, such permission is notgranted, the Contractor may, but is not bound to, elect to treat the suspension,where it affects part only of the Works, as an omission of such part under Clause51 by giving a further notice to the Engineer to that effect, or, where it affects thewhole of the Works, treat the suspension as an event of default by the Employerand terminate his employment under the Contract in accordance with theprovisions of Sub-Clause 69.1, whereupon the provisions of Sub-Clauses 69.2and 69.3 shall apply.

Commencement and Delays

Commencement 41.1 TheContractor shall commence the Works as soon as is reasonably possible afterof Works the receipt by him of a notice to this effect from the Engineer, which notice shall

be issued within the time stated in the Appendix to Tender after the date of theLetter of Acceptance. Thereafter, the Contractor shall proceed with the Workswith due expedition and without delay.

Possession of 42.1 Save insofar as the Contract may prescribe:Site and Access . . .

Thereto (a) the extent of portions of the Site of which the Contractor is to be givenpossession from time to time, and

(b) the order in which such portions shall be made available to the Contractor

and subject to any requirement in the Contract as to the order in which the Worksshall be executed, the Employer will, with the Engineer's notice to commence theWorks, give to the Contractor possession of

(c) so much of the Site, and

(d) such access as, in accordance with the Contract, is to be provided by theEmployer

© FIDIC 1987

Page 199: 35824401 FIDIC Guide to the Use of FIDIC

as may be required to enable the Contractor to commence and proceed with theexecution of the Works in accordance with the programme referred to in Clause14, if any, and otherwise in accordance with such reasonable proposals as theContractor shall, by notice to the Engineer with a copy to the Employer, make.The Employer will, from time to time as the Works proceed, give to theContractor possession of such further portions of the Site as may be required toenable the Contractor to proceed with the execution of the Works with duedispatch in accordance with such programme or proposals, as the case may be.

Failure to Give 42.2 Ifthe Contractor suffers delay and/or incurs costs from failure on the part of thePossession Employer to give possession in accordance with the terms of Sub-Clause 42.1, the

Engineer shall, after due consultation with the Employer and the Contractor,determine:

(a) any extension of time to which the Contractor is entitled under Clause 44, and

(b) the amount of such costs, which shall be added to the Contract Price,

and shall notify the Contractor accordingly, with a copy to the Employer.

Wayleaves and 42.3 The Contractor shall bear all costs and charges for special or temporaryFacilities wayleaves required by him in connection with access to the Site. The Contractor

shall also provide at his own cost any additional facilities outside the Site requiredby him for the purposes of the Works.

Time for 43.1 The whole of the Works and, if applicable, any Section required to be completedCompletion within a particular time as stated in the Appendix to Tender, shall be completed,

in accordance with the provisions of Clause 48, within the time stated in theAppendix to Tender for the whole of the Works or the Section (as the case maybe), calculated from the Commencement Date, or such extended time as may beallowed under Clause 44.

Extension of Time 44.1 In the event offor Completion (a) the amount or nature of extra or additional work, or

(b) any cause of delay referred to in these Conditions, or

(c) exceptionally adverse climatic conditions, or

(d) any delay, impediment or prevention by the Employer, or

(e) other special circumstances which may occur, other than through a default ofor breach of contract by the Contractor or for which he is responsible,

being such as fairly to entitle the Contractor to an extension of the Time forCompletion of the Works, or any Section or part thereof, the Engineer shall,after due consultation with the Employer and the Contractor, determine theamount of such extension and shall notify the Contractor accordingly, with acopy to the Employer.

Contractor 44.2 Provided that the Engineer is not bound to make any determination unless theto Provide Contractor has

(a) within 28 days after such event has first arisen notified the Engineer with a

Particulars copy to the Employer, and

(b) within 28 days, or such other reasonable time as may be agreed by theEngineer, after such notification submitted to the Engineer detailed particulars ofany extension of time to which he may consider himself entitled in order that suchsubmission may be investigated at the time.

© FIDIC 1987

Page 200: 35824401 FIDIC Guide to the Use of FIDIC

Interim 44.3 Provided also that where an event has a continuing effect such that it is notDetermination practicable for the Contractor to submit detailed particulars within the period of

of Extension 28 days referred to in Sub-Clause 44.2(b), he shall nevertheless be entitled to anextension of time provided that he has submitted to the Engineer interimparticulars at intervals of not more than 28 days and final particulars within 28days of the end of the effects resulting from the event. On receipt of such interimparticulars, the Engineer shall, without undue delay, make an interimdetermination of extension of time and, on receipt of the final particulars, theEngineer shall review all the circumstances and shall determine an overallextension of time in regard to the event. In both such cases the Engineer shallmake his determination after due consultation with the Employer and theContractor and shall notify the Contractor of the determination, with a copy tothe Employer. No final review shall result in a decrease of any extension of timealready determined by the Engineer.

Restriction on 45.1 Subject to any provision to the contrary contained in the Contract, none of theWorking Hours Works shall, save as hereinafter provided, be carried on during the night or on

locally recognised days of rest without the consent of the Engineer, except whenwork is unavoidable or absolutely necessary for the saving of life or property orfor the safety of the Works, in which case the Contractor shall immediately advisethe Engineer. Provided that the provisions of this Clause shall not be applicablein the case of any work which it is customary to carry out by multiple shifts.

Rate of Progress 46.1 If for any reason, which does not entitle the Contractor to an extension of time,the rate of progress of the Works or any Section is at any time, in the opinion ofthe Engineer, too slow to comply with the Time for Completion, the Engineershall so notify the Contractor who shall thereupon take such steps as arenecessary, subject to the consent of the Engineer, to expedite progress so as tocomply with the Time for Completion. The Contractor shall not be entitled to anyadditional payment for taking such steps. If, as a result of any notice given by theEngineer under this Clause, the Contractor considers that it is necessary to do anywork at night or on locally recognised days of rest, he shall be entitled to seek theconsent of the Engineer so to do. Provided that if any steps, taken by theContractor in meeting his obligations under this Clause, involve the Employer inadditional supervision costs, such costs shall, after due consultation with theEmployer and the Contractor, be determined by the Engineer and shall berecoverable from the Contractor by the Employer, and may be deducted by theEmployer from any monies due or to become due to the Contractor and theEngineer shall notify the Contractor accordingly, with a copy to the Employer.

Liquidated 47.1 If the Contractor fails to comply with the Time for Completion in accordanceDamages with Clause 48, for the whole of the Works or, if applicable, any Section withinfor Delay the relevant time prescribed by Clause 43, then the Contractor shall pay to the

Employer the relevant sum stated in the Appendix to Tender as liquidateddamages for such default and not as a penalty (which sum shall be the onlymonies due from the Contractor for such default) for every day or part of a daywhich shall elapse between the relivant Time for Completion and the date statedin a Taking-Over Certificate of the whole of the Works or the relevant Section,subject to the applicable limit stated in the Appendix to Tender. The Employermay, without prejudice to any other method of recovery, deduct the amount ofsuch damages from any monies due or to become due to the Contractor. Thepayment or deduction of such damages shall not relieve the Contractor from hisobligation to complete the Works, or from any other of his obligations andliabilities under the Contract.

Reduction of 47.2 If, before the Time for Completion of the whole of the Works or, if applicable,Liquidated anySection, a Taking-Over Certificate has been issued for any part of the Works

Damages or of a Section, the liquidated damages for delay in completion of the remainderof the Works or of that Section shall, for any period of delay after the date statedin such Taking-Over Certificate, and in the absence of alternative provisions inthe Contract, be reduced in the proportion which the value of the part so certifiedbears to the value of the whole of the Works or Section, as applicable. The

© FIDIC 1987

Page 201: 35824401 FIDIC Guide to the Use of FIDIC

provisions of this Sub-Clause shall only apply to the rate of liquidated damagesand shall not affect the limit thereof.

Taking-Over 48.1 When the whole of the Works have been substantially completed and haveCertificate satisfactorily passed any Tests on Completion prescribed by the Contract, the

Contractor may give a notice to that effect to the Engineer, with a copy to theEmployer, accompanied by a written undertaking to finish with due expeditionany outstanding work during the Defects Liability Period. Such notice andundertaking shall be deemed to be a request by the Contractor for the Engineer toissue a Taking-Over Certificate in respect of the Works. The Engineer shall,within 21 days of the date of delivery of such notice, either issue to theContractor, with a copy to the Employer, a Taking-Over Certificate, stating thedate on which, in his opinion, the Works were substantially completed inaccordance with the Contract, or give instructions in writing to the Contractorspecifying all the work which, in the Engineer's opinion, is required to be done bythe Contractor before the issue of such Certificate. The Engineer shall also notifythe Contractor of any defects in the Works affecting substantial completion thatmay appear after such instructions and before completion of the Works specifiedtherein. The Contractor shall be entitled to receive such Taking-Over Certificatewithin 21 days of completion, to the satisfaction of the Engineer, of the Works sospecified and remedying any defects so notified.

Taking Over of 48.2 Similarly, in accordance with the procedure set out in Sub-Clause 48.1, theSections or Parts Contractor may request and the Engineer shall issue a Taking-Over Certificate in

respect of:

(a) any Section in respect of which a separate Time for Completion is provided inthe Appendix to Tender, or

(b) any substantial part of the Permanent Works which has been both completedto the satisfaction of the Engineer and, otherwise than as provided for in theContract, occupied or used by the Employer, or

(c) any part of the Permanent Works which the Employer has elected to occupy oruse prior to completion (where such prior occupation or use is not provided for inthe Contract or has not been agreed by the Contractor as a temporary measure).

Substantial 48.3 If any part of the Permanent Works has been substantially completed and hasCompletion satisfactorily passed any Tests on Completion prescribed by the Contract, the

of Parts Engineer may issue a Taking-Over Certificate in respect of that part of thePermanent Works before completion of the whole of the Works and, upon theissue of such Certificate, the Contractor shall be deemed to have undertaken tocomplete with due expedition any outstanding work in that part of the PermanentWorks during the Defects Liability Period.

Surfaces 48.4 Provided that a Taking-Over Certificate given in respect of any Section or part ofRequiring the Permanent Works before completion of the whole of the Works shall not be

Reinstatement deemed to certify completion of any ground or surfaces requiring reinstatement,unless such Taking-Over Certificate shall expressly so state.

Defects Liability

Defects Liability 49.1 In these Conditions the expression "Defects Liability Period" shall mean thePeriod defects liability period named in the Appendix to Tender, calculated from:

(a) the date of completion of the Works certified by the Engineer in accordancewith Clause 48, or

(b) in the event of more than one certificate having been issued by the Engineerunder Clause 48, the respective dates so certified

and in relation to the Defects Liability Period the expression "the Works" shallbe construed accordingly.

) FIDIC 1987 CI

Page 202: 35824401 FIDIC Guide to the Use of FIDIC

Completion of 49.2 To theintent that the Works shall, at or as soon as practicable after the expirationOutstanding Work of the Defects Liability Period, be delivered to the Employer in the condition

and Remedying required by the Contract, fair wear and tear excepted, to the satisfaction of theDefects Engineer, the Contractor shall:

(a) complete the work, if any, outstanding on the date stated in the Taking-OverCertificate as soon as practicable after such date and

(b) execute all such work of amendment, reconstruction, and remedying defects,shrinkages or other faults as the Engineer may, during the Defects LiabilityPeriod or within 14 days after its expiration, as a result of an inspection made byor on behalf of the Engineer prior to its expiration, instruct the Contractor toexecute.

Cost of 49.3 All work referred to in Sub-Clause 49.2 (b) shall be executed by the Contractor atRemedying his own cost if the necessity thereof is, in the opinion of the Engineer, due to:

Defects(a) the use of materials, Plant or workmanship not in accordance with theContract, or

(b) where the Contractor is responsible for the design of part of the PermanentWorks, any fault in such design, or

(c) the neglect or failure on the part of the Contractor to comply with anyobligation, expressed or implied, on the Contractor's part under the Contract.

If, in the opinion of the Engineer, such necessity is due to any other cause, he shalldetermine an addition to the Contract Price in accordance with Clause 52 andshall notify the Contractor accordingly, with a copy to the Employer.

Contractor's 49.4 In case of default on the part of the Contractor in carrying out such instructionFailure to Carry withina reasonable time, the Employer shall be entitled to employ and pay other

Out Instructions persons to carry out the same and if such work is work which, in the opinion ofthe Engineer, the Contractor was liable to doathis own cost under the Contract,then all costs consequent thereon or incidental thereto shall, after dueconsultation with the Employer and the Contractor, be determined by theEngineer and shall be recoverable from the Contractor by the Employer, and maybe deducted by the Employer from any monies due or to become due to theContractor and the Engineer shall notify the Contractor accordingly, with a copyto the Employer.

Contractor 50.1 Ifany defect, shrinkage or other fault in the Works appears at any time prior toto Search the end of the Defects Liability Period, the Engineer may instruct the Contractor,

with copy to the Employer, to search under the directions of the Engineer for thecause thereof. Unless such defect, shrinkage or other fault is one for which theContractor is liable under the Contract, the Engineer shall, after due consultationwith the Employer and the Contractor, determine the amount in respect of thecosts of such search incurred by the Contractor, which shall be added to theContract Price and shall notify the Contractor accordingly, with a copy to theEmployer. If such defect, shrinkage or other fault is one for which the Contractoris liable, the cost of the work carried out in searching as aforesaid shall be borneby the Contractor and he shall in such case remedy such defect, shrinkage or otherfault at his own cost in accordance with the provisions of Clause 49.

Alterations, Additions and OmissionsVariations 51.1 The Engineer shall make any variation of the form, quality or quantity of the

Works or any part thereof that may, in his opinion, be necessary and for thatpurpose, or if for any other reason it shall, in his opinion, be appropriate, he shallhave the authority to instruct the Contractor to do and the Contractor shall doany of the following:

(a) increase or decrease the quantity of any work included In the Contract,

(b) omit any such work (but not if the omitted work is to be carried out by theEmployer or by another contractor),

© FIDIC 1987

Page 203: 35824401 FIDIC Guide to the Use of FIDIC

(c) change the character or quality or kind of any such work,

(d) change the levels, lines, position and dimensions of any part of the Works,

(e) execute additional work of any kind necessary for the completion of theWorks,

(f) change any specified sequence or timing of construction of any part of theWorks.

No such variation shall in any way vitiate or invalidate the Contract, but theeffect, if any, of all such variations shall be valued in accordance with Clause 52.Provided that where the issue of an instruction to vary the Works is necessitatedby some default of or breach of contract by the Contractor or for which he isresponsible, any additional cost attributable to such default shall be borne by theContractor.

Instructions for 51.2 The Contractor shall not make any such variation without an instruction of theVariations Engineer. Provided that no instruction shall be required for increase or decrease

in the quantity of any work where such increase or decrease is not the result of aninstruction given under this Clause, but is the result of the quantities exceeding orbeing less than those stated in the Bill of Quantities.

Valuation of 52.1 All variations referred to in Clause 51 and any additions to the Contract PriceVariations which are required to be determined in accordance with Clause 52 (for the

purposes of this Clause referred to as "varied work"), shall be valued at the ratesand prices set out in the Contract if, in the opinion of the Engineer, the same shallbe applicable. If the Contract does not contain any rates or prices applicable tothe varied work, the rates and prices in the Contract shall be used as the basis forvaluation so far as may be reasonable, failing which, after due consultation by theEngineer with the Employer and the Contractor, suitable rates or prices shall beagreed upon between the Engineer and the Contractor. In the event ofdisagreement the Engineer shall fix such rates or prices as are, in his opinion,appropriate and shall notify the Contractor accordingly, with a copy to theEmployer. Until such time as rates or prices are agreed or fixed, the Engineer shalldetermine provisional rates or prices to enable on-account payments to beincluded in certificates issued in accordance with Clause 60.

Power 52.2 Provided that if the nature or amount of any varied work relative to the nature orof Engineer amount of the whole of the Works or to any part thereof, is such that, in theto Fix Rates opinion of the Engineer, the rate or price contained in the Contract for any item

of the Works is, by reason of such varied work, rendered inappropriate orinapplicable, then, after due consultation by the Engineer with the Employer andthe Contractor, a suitable rate or price shall be agreed upon between the Engineerand the Contractor. In the event of disagreement the Engineer shall fix such otherrate or price as is, in his opinion, appropriate and shall notify the Contractoraccordingly, with a copy to the Employer. Until such time as rates or prices areagreed or fixed, the Engineer shall determine provisional rates or prices to enableon-account payments to be included in certificates issued in accordance withClause 60.

Provided also that no varied work instructed to be done by the Engineer pursuantto Clause 51 shall be valued under Sub-Clause 52.1 or under this Sub-Clauseunless, within 14 days of the date of such instruction and, other than in the case ofomitted work, before the commencement of the varied work, notice shall havebeen given either:

(a) by the Contractor to the Engineer of his intention to claim extra payment or avaried rate or price, or

(b) by the Engineer to the Contractor of his intention to vary a rate or price.

Variations 52.3 If, on the issue of the Taking-Over Certificate for the whole of the Works, it isExceeding 15 found that as a result of:

per cent(a) all varied work valued under Sub-Clauses 52.1 and 52.2, and

© FIDIC 1987

Page 204: 35824401 FIDIC Guide to the Use of FIDIC

(b) all adjustments upon measurement of the estimated quantities set out in theBill of Quantities, excluding Provisional Sums, dayworks and adjustments ofprice made under Clause 70,

but not from any other cause, there have been additions to or deductions from theContract Price which taken together are in excess of 15 per cent of the "EffectiveContract Price" (which for the purposes of this Sub-Clause shall mean theContract Price, excluding Provisional Sums and allowance for dayworks, if any)then and in such event (subject to any action already taken under any otherSub-Clause of this Clause), after due consultation by the Engineer with theEmployer and the Contractor, there shall be added to or deducted from theContract Price such further sum as may be agreed between the Contractor and theEngineer or, failing agreement, determined by the Engineer having regard to theContractor's Site and general overhead costs of the Contract. The Engineer shallnotify the Contractor of any determination made under this Sub-Clause, with acopy to the Employer. Such sum shall be based only on the amount by which suchadditions or deductions shall be in excess of 15 per cent of the Effective ContractPrice.

Daywork 52.4 The Engineer may, if in his opinion it is necessary or desirable, issue aninstruction that any varied work shall be executed on a daywork basis. TheContractor shall then be paid for such varied work under the terms set out in thedaywork schedule included in the Contract and at the rates and prices affixedthereto by him in the Tender.

The Contractor shall furnish to the Engineer such receipts or other vouchers asmay be necessary to prove the amounts paid and, before ordering materials, shallsubmit to the Engineer quotations for the same for his approval.

In respect of such of the Works executed on a daywork basis, the Contractorshall, during the continuance of such work, deliver each day to the Engineer anexact list in duplicate of the names, occupation and time of all workmenemployed on such work and a statement, also in duplicate, showing thedescription and quantity of all materials and Contractor's Equipment usedthereon or therefor other than Contractor's Equipment which is included in thepercentage addition in accordance with such daywork schedule.One copy of eachlist and statement will, if correct, or when agreed, be signed by the Engineer andreturned to the Contractor.

At the end of each month the Contractor shall deliver to the Engineer a pricedstatement of the labour, materials and Contractor's Equipment, except asaforesaid, used and the Contractor shall not be entitled to any payment unlesssuch lists and statements have been fully and punctually rendered. Providedalways that if the Engineer considers that for any reason the sending of such listsor statements by the Contractor, in accordance with the foregoing provision, wasimpracticable he shall nevertheless be entitled to authorise payment for suchwork, either as daywork, on being satisfied as to the time employed and thelabour, materials and Contractor's Equipment used on such work, or at suchvalue therefor as shall, in his opinion, be fair and reasonable.

Procedure for Claims

Notice of Claims 53.1 Notwithstanding any other provision of the Contract, if the Contractor intends toclaim any additional payment pursuant to any Clause of these Conditions orotherwise, he shall give notice of his intention to the Engineer, with a copy to theEmployer, within 28 days after the event giving rise to the claim has first arisen.

Contemporary 53.2 Upon the happening of the event referred to in Sub-Clause 53.1, the ContractorRecords shall keep such contemporary records as may reasonably be necessary to support

any claim he may subsequently wish to make. Without necessarily admitting theEmployer's liability, the Engineer shall, on receipt of a notice under Sub-Clause53.1, inspect such contemporary records and may instruct the Contractor to keep

Ut..© FIDIC 1987

Page 205: 35824401 FIDIC Guide to the Use of FIDIC

any further contemporary records as are reasonable and may be material to theclaim of which notice has been given. The Contractor shall permit the Engineer toinspect all records kept pursuant to this Sub-Clause and shall supply him withcopies thereof as and when the Engineer so instructs.

Substantiation 53.3 Within 28 days, or such other reasonable time as may be agreed by the Engineer,of Claims ofgiving notice under Sub-Clause 53.1, the Contractor shall send to the Engineer

an account giving detailed particulars of the amount claimed and the groundsupon which the claim is based. Where the event giving rise to the claim has acontinuing effect, such account shall be considered to be an interim account andthe Contractor shall, at such intervals as the Engineer may reasonably require,send further interim accounts giving the accumulated amount of the claim andany further grounds upon which it is based. In cases where interim accounts aresent to the Engineer, the Contractor shall send a final account within 28 days ofthe end of the effects resulting from the event. The Contractor shall, if requiredby the Engineer so to do, copy to the Employer all accounts sent to the Engineerpursuant to this Sub-Clause.

Failure to Comply 53.4 If the Contractor fails to comply with any of the provisions of this Clause inrespect of any claim which he seeks to make, his entitlement to payment in respectthereof shall not exceed such amount as the Engineer or any arbitrator orarbitrators appointed pursuant to Sub-Clause 67.3 assessing the claim considersto be verified by contemporary records (whether or not such records werebrought to the Engineer's notice as required under Sub-Clauses 53.2 and 53.3).

Payment of Claims 53.5 The Contractor shall be entitled to have included in any interim payment certifiedby the Engineer pursuant to Clause 60 such amount in respect of any claim as theEngineer, after due consultation with the Employer and the Contractor, mayconsider due to the Contractor provided that the Contractor has suppliedsufficient particulars to enable the Engineer to determine the amount due. If suchparticulars are insufficient to substantiate the whole of the claim, the Contractorshall be entitled to payment in respect of such part of the claim as such particularsmay substantiate to the satisfaction of the Engineer. The Engineer shall notify theContractor of any determination made under this.Sub-Clause, with a copy to theEmployer.

Contractor's Equipment, Temporary Worksand Materials

Contractor's 54.1 All Contractor's Equipment, Temporary Works and materials provided by theEquipment, Contractor shall, when brought on to the Site, be deemed to be exclusively

Temporary Works intended for the execution of the Works and the Contractor shall not remove theand Materials; same or any part thereof, except for the purpose of moving it from one part of theExclusive Use Site to another, without the consent of the Engineer. Provided that consent shallfor the Works not be required for vehicles engaged in transporting any staff, labour,

Contractor's Equipment, Temporary Works, Plant or materials to or from theSite.

Employer not 54.2 TheEmployer shall not at any time be liable, save as mentioned in Clauses 20 andLiable for Damage 65, for the loss of or damage to any of the said Contractor's Equipment,

Temporary Works or materials.

Customs 54.3 The Employer will use his best endeavours in assisting the Contractor, whereClearance required, in obtaining clearance through the Customs of Contractor's

Equipment, materials and other things required for the Works.

Re-export of 54.4 In respect of any Contractor's Equipment which the Contractor has imported forContractor's thepurposes of the Works, the Employer will use his best endeavours to assist the

Equipment Contractor, where required, in procuring any necessary Government consent tothe re-export of such Contractor's Equipment by the Contractor upon theremoval thereof pursuant to the terms of the Contract.

© FIDIC 1987 2c5

Page 206: 35824401 FIDIC Guide to the Use of FIDIC

Conditions of Hire 54.5 With a view to securing, in the event of termination under Clause 63, theof Contractor's continued availability, for the purpose of executing the Works, of any hired

Equipment Contractor's Equipment, the Contractor shall not bring on to the Site any hiredContractor's Equipment unless there is an agreement for the hire thereof (whichagreement shall be deemed not to include an agreement for hire purchase) whichcontains a provision that the owner thereof will, on request in writing made by theEmployer within 7 days after the date on which any termination has becomeeffective, and on the Employer undertaking to pay all hire charges in respectthereof from such date, hire such Contractor's Equipment to the Employer onthe same terms in all respects as the same was hired to the Contractor save that theEmployer shall be entitled to permit the use thereof by any other contractoremployed by him for the purpose of executing and completing the Works andremedying any defects therein, under the terms of the said Clause 63.

Costs for the 54.6 In the event of the Employer entering into any agreement for the hire ofPurpose of Contractor's Equipment pursuant to Sub-Clause 54.5,all sums properly paid byClause 63 the Employer under the provisions of any such agreement and all costs incurred

by him (including stamp duties) in entering into such agreement shall be deemed,for the purpose of Clause 63, to be part of the cost of executing and completingthe Works and the remedying of any defects therein.

Incorporationof 54.7 The Contractor shall, where entering into any subcontract for the execution ofClause in any part of the Works, incorporate in such subcontract (by reference or

Subcontracts otherwise) the provisions of this Clause in relation to Contractor's Equipment,Temporary Works or materials brought on to the Site by the Subcontractor.

Approval of 54.8 The operation of this Clause shall not be deemed to imply any approval by theMaterials Engineer of the materials or other matters referred to therein nor shall it prevent

not Implied the rejection of any such materials at any time by the Engineer.

Measurement

Quantities 55.1 The quantitiesset out in the Bill of Quantities are the estimated quantities for theWorks, and they are not to be taken as the actual and correct quantities of theWorks to be executed by the Contractor in fulfilment of his obligations under theContract.

Works to be 56.1 The Engineer shall, except as otherwise stated, ascertain and determine byMeasured measurement the value of the Works in accordance with the Contract and the

Contractor shall be paid that value in accordance with Clause 60. The Engineershall, when he requires any part of the Works to be measured, give reasonablenotice to the Contractor's authorised agent, who shall:

(a) forthwith attend or send a qualified representative to assist the Engineer inmaking such measurement, and

(b) supply all particulars required by the Engineer.

Should the Contractor not attend, or neglect or omit to send such representative,then the measurement made by the Engineer or approved by him shall be taken tobe the correct measurement of such part of the Works. For the purpose ofmeasuring such Permanent Works as are to be measured by records anddrawings, the Engineer shall prepare records and drawings as the work proceedsand the Contractor, as and when called upon to do so in writing, shall, within 14days, attend to examine and agree such records and drawings with the Engineerand shall sign the same when so agreed. If the Contractor does not attend toexamine and agree such records and drawings, they shall be taken to be correct.If, after examination of such records and drawings, the Contractor does notagree the same or does not sign the same as agreed, they shall nevertheless betaken to be correct, unless the Contractor, within 14 days of such examination,lodges with the Engineer notice of the respects in which such records anddrawings are claimed by him to be incorrect. On receipt of such notice, theEngineer shall review the records and drawings and either confirm or vary them.

'' FIDIC 1987

Page 207: 35824401 FIDIC Guide to the Use of FIDIC

Method of 57.1 The Works shall be measured net, notwithstanding any general or local custom,Measurement except where otherwise provided for in the Contract.

Breakdown of 57.2 For the purposes of statements submitted in accordance with Sub-Clause 60.1,Lump Sum Items theContractor shall submit to the Engineer, within 28 days after the receipt of the

Letter of Acceptance, a breakdown for each of the lump sum items contained inthe Tender. Such breakdowns shall be subject to the approval of the Engineer.

Provisional Sums

Definition of 58.1 "Provisional Sum" means a sum included in the Contract and so designated in"Provisional the Bill of Quantities for the execution of any part of the Works or for the supply

Sum" of goods, materials, Plant or services, or for contingencies, which sum may beused, in whole or in part, or not at all, on the instructions of the Engineer. TheContractor shall be entitled to only such amounts in respect of the work, supplyor contingencies to which such Provisional Sums relate as the Engineer shalldetermine in accordance with this Clause. The Engineer shall notify theContractor of any determination made under this Sub-Clause, with a copy to theEmployer.

Use of 58.2 In respect of every Provisional Sum the Engineer shall have authority to issueProvisional instructionsfor the execution of work or for the supply of goods, materials, Plant

Sums or services by:

(a) the Contractor, in which case the Contractor shall be entitled to an amountequal to the value thereof determined in accordance with Clause 52,

(b) a nominated Subcontractor, as hereinafter defined, in which case the sum tobe paid to the Contractor therefor shall be determined and paid in accordancewith Sub-Clause 59.4.

Production of 58.3 The Contractor shall produce to the Engineer all quotations, invoices, vouchersVouchers and accounts or receipts in connection with expenditure in respect of Provisional

Sums, except where work is valued in accordance with rates or prices set out in theTender.

Nominated Subcontractors

Definition of 59.1 All specialists, merchants, tradesmen and others executing any work or supplying"Nominated any goods, materials, Plant or services for which Provisional Sums are included

Subcontractors" in the Contract, who may have been or be nominated or selected or approved bythe Employer or the Engineer, and all persons to whom by virtue of theprovisions of the Contract the Contractor is required to subcontract shall, in theexecution of such work or the supply of such goods, materials, Plant or services,be deemed to be subcontractors to the Contractor and are referred to in thisContract as "nominated Subcontractors".

Nominated 59.2 The Contractor shall not be required by the Employer or the Engineer, or beSubcontractors; deemed to be under any obligation, to employ any nominated Subcontractor

Objection to against whom the Contractor may raise reasonable objection, or who declines toNomination enter into a subcontract with the Contractor containing provisions:

(a) that in respect of the work, goods, materials, Plant or services the subject ofthe subcontract, the nominated Subcontractor will undertake towards theContractor such obligations and liabilities as will enable the Contractor todischarge his own obligations and liabilities towards the Employer under theterms of the Contract and will save harmless and indemnify the Contractor fromand against the same and from all claims, proceedings, damages, costs, chargesand expenses whatsoever arising out of or in connection therewith, or arising outof or in connection with any failure to perform such obligations or to fulfil suchliabilities, and

2cs(c FIDIC 1987

Page 208: 35824401 FIDIC Guide to the Use of FIDIC

(b) that the nominated Subcontractor will save harmless and indemnify theContractor from and against any negligence by the nominated Subcontractor, hisagents, workmen and servants and from and against any misuse by him or themof any Temporary Works provided by the Contractor for the purposes of theContract and from all claims as aforesaid.

Design 59.3 If in connection with any Provisional Sum the services to be provided include anyRequirements matter of design or specification of any part of the Permanent Works or of any

to be Expressly Plant to be incorporated therein, such requirement shall be expressly stated in theStated Contract and shall be included in any nominated Subcontract. The. nominated

Subcontract shall specify that the nominated Subcontractor providing suchservices will save harmless and indemnify the Contractor from and against thesame and from all claims, proceedings, damages, costs, charges and expenseswhatsoever arising out of or in connection with any failure to perform suchobligations or to fulfil such liabilities.

Payments to 59.4 For all work executed or goods, materials, Plant or services supplied by anyNominated nominated Subcontractor, the Contractor shall be entitled to:

Subcontractors(a) theactual price paid or due to be paid by the Contractor, on the instructions ofthe Engineer, and in accordance with the subcontract;

(b) in respect of labour supplied by the Contractor, the sum, if any, entered in theBill of Quantities or, if instructed by the Engineer pursuant to paragraph (a) ofSub-Clause 58.2, as may be determined in accordance with Clause 52;

(c) in respect of all other charges and profit, a sum being a percentage rate of theactual price paid or due to be paid calculated, where provision has been made inthe Bill of Quantities for a rate to be set against the relevant Provisional Sum, atthe rate inserted by the Contractor against that item or, where no such provisionhas been made, at the rate inserted by the Contractor in the Appendix to Tenderand repeated where provision for such is made in a special item provided in theBill of Quantities for such purpose.

Certification of 59.5 Before issuing, under Clause 60, any certificate, which includes any payment inPayments to respect of work done or goods, materials, Plant or services supplied by any

Nominated nominated Subcontractor, the Engineer shall be entitled to demand from theSubcontractors Contractor reasonable proof that all payments, less retentions, included in

previous certificates in respect of the work or goods, materials, Plant or servicesof such nominated Subcontractor have been paid or discharged by theContractor. If the Contractor fails to supply such proof then, unless theContractor

(a) satisfies the Engineer in writing that he has reasonable cause for withholdingor refusing to make such payments and

(b) produces to the Engineer reasonable proof that he has so informed suchnominated Subcontractor in writing,

the Employer shall be entitled to pay to such nominated Subcontractor direct,upon the certificate of the Engineer, all payments, less retentions, provided for inthe nominated Subcontract, which the Contractor has failed to make to suchnominated Subcontractor and to deduct by way of set-off the amount so paid bythe Employer from any sums due or to become due from the Employer to theContractor.

Provided that, where the Engineer has certified and the Employer has paid directas aforesaid, the Engineer shall, in issuing any further certificate in favour of theContractor, deduct from the amount thereof the amount so paid, direct asaforesaid, but shall not withhold or delay the issue of the certificate itself whendue to be issued under the terms of the Contract.

© FIDIC 1987

Page 209: 35824401 FIDIC Guide to the Use of FIDIC

Certificates and Payment

Monthly 60.1 The Contractor shall submit to the Engineer after the end of each month sixStatements copies, each signed by the Contractor's representative approved by the Engineer

in accordance with Sub-Clause 15.1, of a statement, in such form as the Engineermay from time to time prescribe, showing the amounts to which the Contractorconsiders himself to be entitled up to the end of the month in respect of

(a) the value of the Permanent Works executed

(b) any other items in the Bill of Quantities including those for Contractor'sEquipment, Temporary Works, dayworks and the like

(c) the percentage of the invoice value of listed materials, all as stated in theAppendix to Tender, and Plant delivered by the Contractor on the Site forincorporation in the Permanent Works but not incorporated in such Works

(d) adjustments under Clause 70

(e) any other sum to which the Contractor may be entitled under the Contract.

Monthly Payments 60.2 The Engineer shall, within 28 days of receiving such statement, certify to theEmployer the amount of payment to the Contractor which he considers due andpayable in respect thereof, subject:(a) firstly, to the retention of the amount calculated by applying the Percentage ofRetention stated in the Appendix to Tender, to the amount to which theContractor is entitled under paragraphs (a), (b), (c) and (e) of Sub-Clause 60.1until the amount so retained reaches the Limit of Retention Money stated in theAppendix to Tender, and

(b) secondly, to the deduction, other than pursuant to Clause 47, of any sumswhich may have become due and payable by the Contractor to the Employer.

Provided that the Engineer shall not be bound to certify any payment under thisSub-Clause if the net amount thereof, after all retentions and deductions, wouldbe less than the Minimum Amount of Interim Certificates stated in the Appendixto Tender.

Notwithstanding the terms of this Clause or any other Clause of the Contract noamount will be certified by the Engineer for payment until the performancesecurity, if required under the Contract, has been provided by the Contractor andapproved by the Employer.

Payment of 60.3 (a) Upon the issue of the Taking-Over Certificate with respect to the whole of theRetention Money Works, one half of the Retention Money, or upon the issue of a Taking-Over

Certificate with respect to a Sectionor part of the Permanent Works only suchproportion thereof as the Engineer determines havingregard to the relative valueof such Section or part of thePermanentWorks, shall be certified by the Engineerfor payment to the Contractor.

(b) Upon the expiration of the Defects Liability Period for the Works the otherhalf of the Retention Moneyshall be certified by the Engineer for payment to theContractor. Provided that, in the event of different Defects Liability Periodshaving become applicable to different Sections or parts of the Permanent Workspursuant to Clause 48, the expression "expiration of the Defects LiabilityPeriod" shall, for the purposes of this Sub-Clause, be deemed to mean theexpiration of the latest of such periods. Provided also that if at such time, thereshall remain to be executed by the Contractor any work ordered, pursuant toClauses 49 and 50, in respect of the Works, the Engineer shall be entitled towithhold certification untilcompletionof such work of so much of the balance ofthe Retention Money as shall, in the opinion of the Engineer, represent the cost ofthe work remaining to be executed.

© FIDIC 1987

Page 210: 35824401 FIDIC Guide to the Use of FIDIC

Correction of 60.4 The Engineer may by any interim certificate make any correction or modificationCertificates in any previous certificate which shall have been issued by him and shall have

authority, if any work is not being carried out to his satisfaction, to omit orreduce the value of such work in any interim certificate.

Statement at 60.5 Not later than 84 days after the issue of the Taking-Over Certificate in respect ofCompletion the whole of the Works, the Contractor shall submit to the Engineer a Statement

at Completion with supporting documents showing in detail, in the formapproved by the Engineer,

(a) the final value of all work done in accordance with the Contract up to the datestated in such Taking-Over Certificate

(b) any further sums which the Contractor considers to be due and

(c) an estimate of amounts which the Contractor considers will become due tohim under the Contract.

The estimated amounts shall be shown separately in such Statement atCompletion. The Engineer shall certify payment in accordance with Sub-Clause60.2.

Final Statement 60.6 Not later than 56 days after the issue of the Defects Liability Certificate pursuantto Sub-Clause 62.1, the Contractor shall submit to the Engineer for considerationa draft final statement with supporting documents showing in detail, in the formapproved by the Engineer,

(a) the value of all work done in accordance with the Contract and

(b) any further sums which the Contractor considers to be due to him under theContract.

If the Engineer disagrees with or cannot verify any part of the draft finalstatement, the Contractor shall submit such further information as the Engineermay reasonably require and shall make such changes in the draft as may be agreedbetween them. The Contractor shall then prepare and submit to the Engineer thefinal statement as agreed (for the purposes of these Conditions referred to as the"Final Statement").

Discharge 60.7 Upon submission of the Final Statement, the Contractor shall give to theEmployer, with a copy to the Engineer, a written discharge confirming that thetotal of the Final Statement represents full and final settlement of all monies dueto the Contractor arising out of or in respect of the Contract. Provided that suchdischarge shall become effective only after payment due under the FinalCertificate issued pursuant to Sub-Clause 60.8 has been made and theperformance security referred to in Sub-Clause 10.1, if any, has been returned tothe Contractor.

Final Certificate 60.8 Within 28 days after receipt of the Final Statement, and the written discharge, theEngineer shall issue to the Employer (with a copy to the Contractor) a FinalCertificate stating

(a) the amount which, in the opinion of the Engineer, is finally due under theContract, and

(b) after giving credit to the Employer for all amounts previously paid by theEmployer and for all sums to which the Employer is entitled under the Contract,other than Clause 47, the balance, if any, due from the Employer to theContractor or from the Contractor to the Employer as the case may be.

Cessation of 60.9 The Employer shall not be liable to the Contractor for any matter or thing arisingEmployer's out of or in connection with the Contract or execution of the Works, unless the

Liability Contractor shall have included a claim in respect thereof in his Final Statementand (except in respect of matters or things arising after the issue of theTaking-Over Certificate in respect of the whole of the Works) in the Statement atCompletion referred to in Sub-Clause 60.5.

© FIDIC 1987

Page 211: 35824401 FIDIC Guide to the Use of FIDIC

Time for Payment 60.10 The amount due to the Contractor under any interim certificate issued by theEngineer pursuant to this Clause, or to any other term of the Contract, shall,subject to Clause 47, be paid by the Employer to the Contractor within 28 daysafter such interim certificate has been delivered to the Employer, or, in the case ofthe Final Certificate referred to in Sub-Clause 60.8, within 56 days, after suchFinal Certificate has been delivered to the Employer. In the event of the failure ofthe Employer to make payment within the times stated, the Employer shall pay tothe Contractor interest at the rate stated in the Appendix to Tender upon all sumsunpaid from the date by which the same should have been paid. The provisions ofthis Sub-Clause are without prejudice to the Contractor's entitlement underClause 69.

Approval only by 61 .1 Only the Defects Liability Certificate, referred to in Clause 62, shall be deemed toDetects Liability constitute approval of the Works.

Certificate

Defects Liability 62.1 The Contract shall not be considered as completed until a Defects LiabilityCertificate Certificate shall have been signed by the Engineer and delivered to the Employer,

with a copy to the Contractor, stating the date on which the Contractor shall havecompleted his obligations to execute and complete the Works and remedy anydefects therein to the Engineer's satisfaction. The Defects Liability Certificateshall be given by the Engineer within 28 days after the expiration of the DefectsLiability Period, or, if different defects liability periods shall become applicableto different Sections or parts of the Permanent Works, the expiration of the latestsuch period, or as soon thereafter as any works instructed, pursuant to Clauses 49and 50, have been completed to the satisfaction of the Engineer. Provided thatthe issue of the Defects Liability Certificate shall not be a condition precedent topayment to the Contractor of the second portion of the Retention Money inaccordance with the conditions set out in Sub-Clause 60.3.

Unfulfilled 62.2 Notwithstanding the issue of the Defects Liability Certificate the Contractor andObligations the Employer shall remain liable for the fulfilmnt of any obligation incurred

under the provisions of the Contract prior to the issue of the Defects LiabilityCertificate which remains unperformed at the time such Defects LiabilityCertificate is issued and, for the purposes of determining the nature and extent ofany such obligation, the Contract shall be deemed to remain in force between theparties to the Contract.

Remedies

Default of 63.1 If the Contractor is deemed by law unable to pay his debts as they fall due, orContractor enters into voluntary or involuntary bankruptcy, liquidation or dissolution (other

than a voluntary liquidation for the purposes of amalgamation orreconstruction), or becomes insolvent, or makes an arrangement with, orassignment in favour of, his creditors, or agrees to carry out the Contract under acommittee of inspection of his creditors, or if a receiver, administrator, trustee orliquidator is appointed over any substantial part of his assets, or if, under any lawor regulation relating to reorganization, arrangement or readjustment of debts,proceedings are commenced against the Contractor or resolutions passed inconnection with dissolution or liquidation or if any steps are taken to enforce anysecurity interest over a substantial part of the assets of the Contractor, or if anyact is done or event occurs with respect to the Contractor or his assets which,under any applicable law has a substantially similar effect to any of the foregoingacts or events, or if the Contractor has contravened Sub-Clause 3.1, or has anexecution levied on his goods, or if the Engineer certifies to the Employer, with acopy to the Contractor, that, in his opinion, the Contractor:

(a) has repudiated the Contract, or

(b) without reasonable excuse has failed(i) to commence the Works in accordance with Sub-Clause 41.1, or

© FIDIC 1987

Page 212: 35824401 FIDIC Guide to the Use of FIDIC

(ii) to proceed with the Works, or any Section thereof, within 28 days afterreceiving notice pursuant to Sub-Clause 46.1, or

(c) has failed to comply with a notice issued pursuant to Sub-Clause 37.4 or aninstruction issued pursuant to Sub-Clause 39.1 within 28 days after havingreceived it, or

(d) despite previous warning from the Engineer, in writing, is otherwisepersistently or flagrantly neglecting to comply with any of his obligations underthe Contract, or

(e) has contravened Sub-Clause 4.1,

then the Employer may, after giving 14 days' notice to the Contractor, enter uponthe Site and the Works and terminate the employment of the Contractor withoutthereby releasing the Contractor from any of his obligations or liabilities underthe Contract, or affecting the rights and authorities conferred on the Employer orthe Engineer by the Contract, and may himself complete the Works or mayemploy any other contractor to complete the Works. The Employer or such othercontractor may use for such completion so much of the Contractor's Equipment,Temporary Works and materials as he or they may think proper.

Valuation at Date 63.2 The Engineer shall, as soon as may be practicable after any such entry andof Termination termination by the Employer, fix and determine ex parte, or by or after reference

to the parties or after such investigation or enquiries as he may think fit to makeor institute, and shall certify:

(a) what amount (if any) had, at the time of such entry and termination, beenreasonably earned by or would reasonably accrue to the Contractor in respect ofwork then actually done by him under the Contract, and

(b) the value of any of the said unused or partially used materials, anyContractor's Equipment and any Temporary Works.

Payment after 63.3 If the Employer terminates the Contractor's employment under this Clause, heTermination shall not be liable to pay to the Contractor any further amount (including

damages) in respect of the Contract until the expiration of the Defects LiabilityPeriod and thereafter until the costs of execution, completion and remedying ofany defects, damages for delay in completion (if any) and all other expensesincurred by the Employer have been ascertained and the amount thereof certifiedby the Engineer. The Contractor shall then be entitled to receive only such sum (ifany) as the Engineer may certify would have been payable to him upon duecompletion by him after deducting the said amount. If such amount exceeds thesum which would have been payable to the Contractor on due completion by him,then the Contractor shall, upon demand, pay to the Employer the amount of suchexcess and it shall be deemed a debt due by the Contractor to the Employer andshall be recoverable accordingly.

Assignment of 63.4 Unless prohibited by law, the Contractor shall, if so instructed by the EngineerBenefit of within 14 days of such entry and termination referred to in Sub-Clause 63.1,

Agreement assign to the Employer the benefit of any agreement for the supply of any goodsor materials or services and/or for the execution of any work for the purposes ofthe Contract, which the Contractor may have entered into.

FIDIC 1987

Page 213: 35824401 FIDIC Guide to the Use of FIDIC

Urgent Remedial 64.1 If, by reason of any accident, or failure, or other event occurring to, in, or inWork connection with the Works, or any part thereof, either during the execution of the

Works, or during the Defects Liability Period, any remedial or other work is, inthe opinion of the Engineer, urgently necessary for the safety of the Works andthe Contractor is unable or unwilling at once to do such work, the Employer shallbe entitled to employ and pay other persons to carry out such work as theEngineer may consider necessary. If the work or repair so done by the Employeris work which, in the opinion of the Engineer, the Contractor was liable to do athis own cost under the Contract, then all costs consequent thereon or incidentalthereto shall, after due consultation with the Employer and the Contractor, bedetermined by the Engineer and shall be recoverable from the Contractor by theEmployer, and may be deducted by the Employer from any monies due or tobecome due to the Contractor and the Engineer shall notify the Contractoraccordingly, with a copy to the Employer. Provided that the Engineer shall, assoon after the occurrence of any such emergency as may be reasonablypracticable, notify the Contractor thereof.

Special Risks

No Liability for 65.1 The Contractor shall be under no liability whatsoever in consequence of any ofSpecial Risks the special risks referred to in Sub-Clause 65.2, whether by way of indemnity or

otherwise, for or in respect of:

(a) destruction of or damage to the Works, save to work condemned under theprovisions of Clause 39 prior to the occurrence of any of the said special risks, or

(b) destruction of or damage to property, whether of the Employer or thirdparties, or

(c) injury or loss of life.

Special Risks 65.2 The special risks are:

(a) the risks defined under paragraphs (a), (c), (d) and (e) of Sub-Clause 20.4, and

(b) the risks defined under paragraph (b) of Sub-Clause 20.4 insofar as theserelate to the country in which the Works are to be executed.

Damage to Works 65.3 Ifthe Works or any materials or Plant on or near or in transit to the Site, or any ofby Special Risks the Contractor's Equipment, sustain destruction or damage by reason of any of

the said special risks, the Contractor shall be entitled to payment in accordancewith the Contract for any Permanent Works duly executed and for any materialsor Plant so destroyed or damaged and, so far as may be required by the Engineeror as may be necessary for the completion of the Works, to payment for:

(a) rectifying any such destruction or damage to the Works, and

(b) replacing or rectifying such materials or Contractor's Equipment

and the Engineer shall determine an addition to the Contract Price in accordancewith Clause 52 (which shall in the case of the cost of replacement of Contractor'sEquipment include the fair market value thereof as determined by the Engineer)and shall notify the Contractor accordingly, with a copy tothe Employer.

Projectile, Missile 65.4 Destruction, damage, injury or loss of life caused by the explosion or impact,whenever and wherever occurring, of any mine, bomb, shell, grenade, or otherprojectile, missile, munition, or explosive of war, shall be deemed to be aconsequence of the said special risks.

© FIDIC 987

Page 214: 35824401 FIDIC Guide to the Use of FIDIC

Increased Costs 65.5 Save to the extent that the Contractor is entitled to payment under any otherarising from provision of the Contract, the Employer shall repay to the Contractor any costs

Special Risks of the execution of the Works (other than such as may be attributable to the costof reconstructing work condemned under the provisions of Clause 39 prior to theoccurrence of any special risk) which are howsoever attributable to or consequenton or the result of or in any way whatsoever connected with the said special risks,subject however to the provisions in this Clause hereinafter contained in regard tooutbreak of war, but the Contractor shall, as soon as any such cost comes to hisknowledge, forthwith notify the Engineer thereof. The Engineer shall, after dueconsultation with the Employer and the Contractor, determine the amount of theContractor's costs in respect thereof which shall be added to the Contract Priceand shall notify the Contractor accordingly, with a copy to the Employer.

Outbreak of War 65.6 If, during the currency of the Contract, there is an outbreak of war, whether waris declared or not, in any part of the world which, whether financially orotherwise, materially affects the execution of the Works, the Contractor shall,unless and until the Contract is terminated under the provisions of this Clause,continue to use his best endeavours to complete the execution of the Works.Provided that the Employer shall be entitled, at any time after such outbreak ofwar, to terminate the Contract by giving notice to the Contractor and, upon suchnotice being given, the Contract shall, except as to the rights of the parties underthis Clause and to the operation of Clause 67, terminate, but without prejudice tothe rights of either party in respect of any antecedent breach thereof.

Removal of 65.7 If the Contract is terminated under the provisions of Sub-Clause 65.6, theContractor's Contractor shall, with all reasonable dispatch, remove from the Site all

Equipment on Contractor's Equipment and shall give similar facilities to his Subcontractors toTermination do so.

Payment if 65.8 If the Contract is terminated as aforesaid, the Contractor shall be paid by theContract Employer, insofar as such amounts or items have not already been covered by

Terminated payments on account made to the Contractor, for all work executed prior to thedate of termination at the rates and prices provided in the Contract and inaddition:

(a) The amounts payable in respect of any preliminary items referred to in the Billof Quantities, so far as the work or service comprised therein has been carried outor performed, and a proper proportion of any such items which have beenpartially carried out or performed.

(b) The cost of materials, Plant or goods reasonably ordered for the Works whichhave been delivered to the Contractor or of which the Contractor is legally liableto accept delivery, such materials, Plant or goods becoming the property of theEmployer upon such payments being made by him.

(c) A sum being the amount of any expenditure reasonably. incurred by theContractor in the expectation of completing the whole of the Works insofar assuch expenditure has not been covered by any other payments referred to in thisSub-Clause.

(d) Any additional sum payable under the provisions of Sub-Clauses 65.3 and65.5.

(e) Such proportion of the cost as may be reasonable, taking into accountpayments made or to be made for work executed, of removal of Contractor'sEquipment under Sub-Clause 65.7 and, if required by the Contractor, returnthereof to the Contractor's main plant yard in his country of registration or toother destination, at no greater cost.

(f) The reasonable cost of repatriation of all the Contractor's staff and workmenemployed on or in connection with the Works at the time of such termination.

© FIDIC 1987

Page 215: 35824401 FIDIC Guide to the Use of FIDIC

Provided that against any payment due from the Employer under thisSub-Clause, the Employer shall be entitled to be credited with any outstandingbalances due from the Contractor for advances in respect of Contractor'sEquipment, materials and Plant and any other sums which, at the date oftermination, were recoverable by the Employer from the Contractor under theterms of the Contract. Any sums payable under this Sub-Clause shall, after dueconsultation with the Employer and the Contractor, be determined by theEngineer who shall notify the Contractor accordingly, with a copy to theEmployer.

Release from Performance

Payment in Event 66.1 Ifany circumstance outside the control of both parties arises after the issue of theof Release from Letter of Acceptance which renders it impossible or unlawful for either party to

Performance fulfil his contractual obligations, or under the law governing the Contract theparties are released from further performance, then the sum payable by theEmployer to the Contractor in respect of the work executed shall be the same asthat which would have been payable under Clause 65 if the Contract had beenterminated under the provisions of Clause 65.

Settlement of Disputes

Engineer's 67.1 If a dispute of any kind whatsoever arises between the Employer and theDecision Contractor in connection with, or arising out of, the Contract or the execution of

the Works, whether during the execution of the Works or after their completionand whether before or after repudiation or other termination of the Contract,including any dispute as to any opinion, instruction, determination, certificate orvaluation of the Engineer, the matter in dispute shall, in the first place, bereferred in writing to the Engineer, with a copy to the other party. Such referenceshall state that it is made pursuant to this Clause. No later than the eighty-fourthday after the day on which he received such reference the Engineer shall givenotice of his decision to the Employer and the Contractor. Such decision shallstate that it is made pursuant to this Clause.

Unless the Contract has already been repudiated or terminated, the Contractorshall, in every case, continue to proceed with the Works with all due diligence andthe Contractor and the Employer shall give effect forthwith to every such decisionof the Engineer unless and until the same shall be revised, as hereinafter provided,in an amicable settlement or an arbitral award.

If either the Employer or the Contractor be dissatisfied with any decision of theEngineer, or if the Engineer fails to give notice of his decision on or before theeighty-fourth day after the day on which he received the reference, then either theEmployer or the Contractor may, on or before the seventieth day after the day onwhich he received notice of such decision, or on or before the seventieth day afterthe day on which the said period of 84 days expired, as the case may be, givenotice to the other party, with a copy for information to the Engineer, of hisintention to commence arbitration, as hereinafter provided, as to the matter indispute. Such notice shall establish the entitlement of the party giving the same tocommence arbitration, as hereinafter provided, as to such dispute and, subject toSub-Clause 67.4, no arbitration in respect thereof may be commenced unless suchnotice is given.

If the Engineer has given notice of his decision as to a matter in dispute to theEmployer and the Contractor and no notice of intention to commence arbitrationas to such dispute has been given by either the Employer or the Contractor on orbefore the seventieth day after the day on which the parties received notice as tosuch decision from the Engineer, the said decision shall become final and bindingupon the Employer and the Contractor.

© FIDIC 1987

Page 216: 35824401 FIDIC Guide to the Use of FIDIC

Amicable 67.2 Wherenotice of intention to commence arbitration as to a dispute has been givenSettlement in accordance with Sub-Clause 67.1, arbitration of such dispute shall not be

commenced unless an attempt has first been made by the parties to settle suchdispute amicably. Provided that, unless the parties otherwise agree, arbitrationmay be commenced on or after the fifty-sixth day after the day on which notice ofintention to commence arbitration of such dispute was given, whether or not anyattempt at amicable settlement thereof has been made.

Arbitration 67.3 Any dispute in respect of which:

(a) the decision, if any, of the Engineer has not become final and bindingpursuant to Sub-Clause 67.1, and

(b) amicable settlement has not been reached within the period stated inSub-Clause 67.2

shall be finally settled, unless otherwise specified in the Contract, under the Rulesof Conciliation and Arbitration of the International Chamber of Commerce byone or more arbitrators appointed under such Rules. The said arbitrator/s shallhave full power to open up, review and revise any decision, opinion, instruction,determination, certificate or valuation of the Engineer related to the dispute.

Neither party shall be limited in the proceedings before such arbitrator/s to theevidence or arguments put before the Engineer for the purpose of obtaining hissaid decision pursuant to Sub-Clause 67.1. No such decision shall disqualify theEngineer from being called as a witness and giving evidence before thearbitrator/s on any matter whatsoever relevant to the dispute.

Arbitration may be commenced prior to or after completion of the Works,provided that the obligations of the Employer, the Engineer and the Contractorshall not be altered by reason of the arbitration being conducted during theprogress of the Works.

Failure to Comply 67.4 Where neither the Employer nor the Contractor has given notice of intention towith Engineer's commence arbitration of a dispute within the period stated in Sub-Clause 67.1

Decision and the related decision has become final and binding, either party may, if theother party fails to comply with such decision, and without prejudice to any otherrights it may have, refer the failure to arbitration in accordance with Sub-Clause67.3. The provisions of Sub-Clauses 67.1 and 67.2 shall not apply to any suchreference.

Notices

Notice to 68.1 All certificates, notices or instructions to be given to the Contractor by theContractor Employer or the Engineer under the terms of the Contract shall be sent by post,

cable, telex or facsimile transmission to or left at the Contractor's principal placeof business or such other address as the Contractor shall nominate fur thatpurpose.

Notice to 68.2 Any notice to be given to the Employer or to the Engineer under the terms of theEmployer and Contract shall be sent by post, cable, telex or facsimile transmission to or left at

Engineer the respective addresses nominated for that purpose in Part H of theseConditions.

Change of 68.3 Either party may change a nominated address to another address in the countryAddress where the Works are being executed by prior notice to the other party, with a copy

to the Engineer, and the Engineer may do so by prior notice to both parties.

© FIDIC 1987

Page 217: 35824401 FIDIC Guide to the Use of FIDIC

Default of Employer

Default of 69.1 In the event of the Employer:Employer (a) failing to pay to the Contractor the amount due under any certificate of the

Engineer within 28 days after the expiry of the time stated in Sub-Clause 60.10within which payment is to be made, subject to any deduction that the Employeris entitled to make under the Contract, or(b) interfering with or obstructing or refusing any required approval to the issueof any such certificate or

(c) becoming bankrupt or, being a company, going into liquidation, other thanfor the purpose of a scheme of reconstruction or amalgamation, or

(d) giving notice to the Contractor that for unforeseen reasons, due to economicdislocation, it is impossible for him to continue to meet his contractualobligationsthe Contractor shall be entitled to terminate his employment under the Contractby giving notice to the Employer, with a copy to the Engineer. Such terminationshall take effect 14 days after the giving of the notice.

Removal of 69.2 Upon the expiry of the 14 days' notice referred to in Sub-Clause 69.1, theContractor's Contractor shall, notwithstanding the provisions of Sub-Clause 54.1, with all

Equipment reasonable despatch, remove from the Site all Contractor's Equipment broughtby him thereon.

Payment on 69.3 In the event of such termination the Employer shall be under the same obligationsTermination to the Contractor in regard to payment as if the Contract had been terminated

under the provisions of Clause 65, but, in addition to the payments specified inSub-Clause 65.8, the Employer shall pay to the Contractor the amount of any lossor damage to the Contractor arising out of or in connection with or byconsequence of such termination.

Contractor's 69.4 Without prejudice to the Contractor's entitlement to interest under Sub-ClauseEntitlement to 60.10 and to terminate under Sub-Clause 69.1, the Contractor may, if the

Suspend Work Employer fails to pay the Contractor the amount due under any certificate of theEngineer within 28 days after the expiry of the time stated in Sub-Clause 60.10within which payment is to be made, subject to any deduction that the Employeris entitled to make under the Contract, after giving 28 days' prior notice to theEmployer, with a copy to the Engineer, suspend work or reduce the rate of work.

If the Contractor suspends work or reduces the rate of work in accordance withthe provisions of this Sub-Clause and thereby suffers delay or incurs cost theEngineer shall, after due consultation with the Employer and the Contractor,determine

(a) any extension of time to which the Contractor is entitled under Clause 44, and

(b) the amount of such costs, which shall be added to the Contract Price,

and shall notify the Contractor accordingly, with a copy to the Employer.

Resumption 69.5 Where the Contractor suspends work or reduces the rate of work, having givenof Work notice in accordance with Sub-Clause 69.4, and the Employer subsequently pays

the amount due, including interest pursuant to Sub-Clause 60.10, theContractor's entitlement under Sub-Clause 69.1 shall, if notice of terminationhas not been given, lapse and the Contractor shall resume normal working assoon as is reasonably possible.

Changes in Cost and LegislationIncrease or 70.1 There shall be added to or deducted from the Contract Price such sums in respect

Decrease ofrise or fall in the cost of labour and/or materials or any other matters affectingof Cost the cost of the execution of the Works as may be determined in accordance with

Part II of these Conditions.

FIDIC 1987

Page 218: 35824401 FIDIC Guide to the Use of FIDIC

Subsequent 70.2 If, after the date 28 days prior to the latest date for submission of tenders for theLegislation Contract there occur in the country in which the Works are being or are to be

executed changes to any National or State Statute, Ordinance, Decree or otherLaw or any regulation or bye-law of any local or other duly constituted authority,or the introduction of any such State Statute, Ordinance, Decree, Law,regulation or bye-law which causes additional or reduced cost to the Contractor,other than under Sub-Clause 70.1, in the execution of the Contract, suchadditional or reduced cost shall, after due consultation with the Employer and theContractor, be determined by the Engineer and shall be added to or deductedfrom the Contract Price and the Engineer shall notify the Contractoraccordingly, with a copy to the Employer.

Currency and Rates of Exchange

Currency 71 .1 If, after the date 28 days prior to the latest date for submission of tenders for theRestrictions Contract, the Government or authorised agency of the Government of the

country in which the Works are being or are to be executed imposes currencyrestrictions and/or transfer of currency restrictions in relation to the currency orcurrencies in which the Contract Price is to be paid, the Employer shall reimburseany loss or damage to the Contractor arising therefrom, without prejudice to theright of the Contractor to exercise any other rights or remedies to which he isentitled in such event.

Rates of 72.1 Wherethe Contract provides for payment in whole or in part to be made to theExchange Contractorin foreign currency or currencies, such payment shall not be subject to

variations in the rate or rates of exchange between such specified foreign currencyor currencies and the currency of the country in which the Works are to beexecuted.

Currency 72.2 Where the Employer has required the Tender to be expressed in a single currencyProportions but with payment to be made in more than one currency and the Contractor has

stated the proportions or amounts of other currency or currencies in which herequires payment to be made, the rate or rates of exchange applicable forcalculating the payment of such proportions or amounts shall, unless otherwisestated in Part II of these Conditions, be those prevailing, as determined by theCentral Bank of the country in which the Works are to be executed, on the date 28days prior to the latest date for the submission of tenders for the Contract, as hasbeen notified to the Contractor by the Employer prior to the submission oftenders or as provided for in the Tender.

Currencies of 72.3 Where the Contract provides for payment in more than one currency, thePayment for proportions or amounts to be paid in foreign currencies in respect of Provisional

Provisional Sums Sums shall be determined in accordance with the principles set forth inSub-Clauses 72.1 and 72.2 as and when these sums are utilised in whole or in partin accordance with the provisions of Clauses 58 and 59.

REFERENCE TO PART II

As stated in the Foreword at the beginning of this document, the FIDICConditions comprise both Part I and Part II. Certain Clauses, namelySub-Clauses 1.1 paragraph (a) (i) and (iv), 5.1 part 14.1, 14.3, 68.2 and 70.1 mustinclude additional wording in Part II for the Conditions to be complete. OtherClauses may require additional wording to supplement Part I or to coverparticular circumstances or the type of work (dredging is an example).

Part II Conditions of Particular Application with guidelines for the preparationof Part II are printed in a separately bound document.

© FIDIC 1987

Page 219: 35824401 FIDIC Guide to the Use of FIDIC

PART I — GENERAL CONDITIONS

Index Clause Page

Access to Site 42.1 198Access to Works, Engineer 37.1 196Access, Contractor to Satisfy Himself 11.1 187Accident or Injury to Workmen — Insurance Against 24.2 192Accident or Injury to Workmen — Liability for 24.1 192Address, Change of 68.3 216Adequacy of Insurance 25.2 192Adjustment of Contract Price if Variations Exceed 15 per cent of Tender Sum 52.3 203Adverse Physical Obstructions or Conditions 12.2 187Agreement 9.1 186Alterations, Additions and Omissions 51. 202

&52. 203Ambiguities in Contract Documents 5.2 185Amicable Settlement of Disputes 67.2 216Appointment of Assistants to Engineer 2.4 183Approval by the Engineer 7.3 186Approval of Materials not Implied 54.8 206ApprovalOnly by Defects Liability Certificate 61.1 211Arbitration 67.3 216Assignment of Contract 3.1 184Avoidanceof Damage to Roads 30.1 194

Bills of Quantities — Estimated Only 55.1 206Boreholes and Exploratory Excavation 18.1 189Breakdown of Lump Sum Items 57.2 207Careof Works 20.1 189Cash Flow Estimate to be Submitted 14.3 188Certificate, Final 60.8 210Certificates and Payment, Monthly Statements 60.1 209Certificates, Correction of 60.4 210Certificate, Taking-Over 48.1 201Certification of Completion of Works 48.1 201Certification of Completion of Sections or Parts 48.2 201Cessation of Employer's Liability 60.9 210Change of Address, Notice of 68.3 216Claims, Contemporary Records 53.2 204Claims, Notice of 53.1 204Claims, Payment of 53.5 205Claims, Substantiation of 53.3 205Claims Under Performance Security 10.3 187Clearance of Site on Completion 33.1 195Commencement of Works 41.1 198Completion of Works, Time for 43.1 199Completion of Works, Time for, Extension of 44.1 199Completion, Statement at 60.5 210Compliance with Insurance Policy Conditions 25.4 192Compliance with Statutes and Regulations 26.1 193Contemporary Records for Claims 53.2 204Contract Agreement 9.1 186Contractor Not Relieved of Duties or Responsibilities 14.4 188Contractor's Employees 16.1 188Contractor's Employees, Engineer at Liberty to Object 16.2 188Contractor's Entitlement to Suspend Work for Employer's Default 69.4 217Contractor's Equipment, Conditions of Hire 54.5 206Contractor's Equipment, Employer not Liable for Damage 54.2 205

Q2tO1

Page 220: 35824401 FIDIC Guide to the Use of FIDIC

Index Clause Page

Contractor's Equipment, Insurance of 21.1 190Contractor's Equipment, Reference in Subcontracts 54.7 206Contractor's Equipment, Temporary Works and Materials;

Exclusive Use for the Works 54.1 205Contractor's Equipment, Transport of 30.2 194Contractor'sFailure to Carry Out Instructions 202Contraor's Failure to Insure, Remedy 25.3 192Contractor's General Responsibilities 8.1 186Contractor's Superintendence 15.1 188Contractor to Keep Site Clear 32.1 195Contractor to Search 50.1 202Correction of Certificates 60.4 210Cost of Remedying Defects 202Cost of Samples 36.2 195Cost of Tests 36.3 195Cost of Tests not Provided for 36.4 196Covering up Work, Examination Before 38.1 197Cross Liabilities 23.3 192Currencies of Payment for Provisional Sums 72.3 218Currencies, Rates of Exchange 72.1 218Currency Restrictions 71.1 218Custody and Supply of Drawings and Documents 6.1 185Customs Clearance 54.3 205Damage to Persons and Property 22.1 191

Damage to Roads, Avoidance of 30.1 194Damage to Works, Special Risks 65.3 213Damages, Liquidated 47.1 206Dates for Inspection and Testing 37.3 196Daywork 52.4 204Decrease or Increase of Costs 70.1 217Defaultof Contractor in Compliance with Instructions on Improper Work 39.2 197Defaultof Contractor, Remedies for 63.1 211Defaultof Employer 69.1 217Defective Materials and Work 39.1 197Defects, Contractor to Search for, if Required 50.1 202Defects, Cost of Remedying 49.3 202Defects Liability Certificate 62.1 211Defects Liability Period 49.1 201Defects, Remedying of 49.2 202Definitions 1.1 181Delay, Liquidated Damages for 47.1 200Delays and Cost of Delay of Drawings 6.4 , 185Design by Nominated Subcontractors 59.3 208Discharge 60.7 210Discrepancies in Documents 5.2 185Dismissal of Contractor's Employees 16.2 188Disorderly Conduct, etc. 34.1 195Disputes, Engineer's Decision 67.1 215Disruption of Progress 6.3 185Documents Mutually Explanatory 5.2 185Drawings 6&7 185,186Drawings and Documents — Custodyand Supply of 6.1 185Drawings and Instructions — Supplementary 7.1 186Drawings, Copy to be Kept on Site 6.2 185Drawings, Delays and Cost of Delay of Drawings 6.4 185Drawings, Failure by Contractor to Submit 6.5 186

Employernot Liable for Damage to Contractor's Equipment etc. 54.2 205

Page 221: 35824401 FIDIC Guide to the Use of FIDIC

Index Clause Page

Employer's Liability, Cessation of 60.9 210Employer's Responsibilities 19.2 189Employer's Risks 20.4 190Engagement of Staff and Labour 34.1 195Engineer's Authority to Delegate 2.3 183Engineer's Determination Where Tests not Provided for 36.5 196Engineer's Duties and Authority 2.1 183Engineer to Act Impartially 2.6 184Environment — Protection of 19.1 189Errors in Setting Out 17.1 189Evidence and Terms of Insurance 25.1 192Examination of Work before Covering Up 38.1 197Exceptions 22.2 191Exchange, Rates of 72.1 218Exclusions 21.4 191Extension of Time, due to Employer's Failure to give Possession of Site 42.2 199Extension of Time for Completion 44.1 199Extension of Time for Completion, Contractor's Claim 44.2 199Extension of Time for Completion, Engineer's Determination 44.3 200Extraordinary Traffic 30. 194

Facilities for Other Contractors 31.2 194Failure by Contractor to Submit Drawings 6.5 186Failure to Comply with Claims Procedure 53.4 205Failure to Comply with Engineer's Decision 67.4 216Failure to Give Possession of Site 42.2 199Faulty Work, Removal of 39.1 197Fees and Notices 26.1 193Fencing, Watching, Lighting, etc. 19.1 189Final Certificate 60.8 210Final Statement 60.6 210Foreign Currencies. Payment in 72. 218Fossils 27.1 193Foundations, Examination of 38.1 197General Responsibilities of Contractor 8.1 186Giving of Notices — Payment of Fees 26.1 193

Headings and Marginal Notes 1.2 182

Improper Work and Materials, Removal of 39.1 197Increase or Decrease of Costs 70.1 218Indemnity by Contract 22.1 191

&24.1 192Indemnity by Employer 22.3 192Independent Inspection 37.5 197Injury to Persons — Damage to Property 22.1 191Injury to Workmen 24.1 192Inspection and Testing 37.2 196Inspection and Testing, Dates for 37.3 196Inspection of Foundations, etc. 38.1 197Inspection of Operations 37.1 197Inspection of Site by Contractor 11.1 187Instructions for Variations 51.2 203Instructions in Writing 2.5 183Instructions, Supplementary 7.1 186Insurance, Adequacy of 25.2 192Insurance, Evidence and Terms of 25.1 192Insurance, Minimum Amount of 23.2 192Insurance of Works and Contractor's Equipment 21.1 191

Page 222: 35824401 FIDIC Guide to the Use of FIDIC

22z

Index Clause Page

Insurance, Remedy on Failure to Insure 25.3 192Insurance, Responsibility for Amounts not Recovered 21.3 191insurance, Scope of Cover 21.2 191Insurance, Third Party 23.1 192Insurance, Workmen 24.2 192Interference with Traffice and Adjoining Properties 29.1 193Interim Determination of Extension 44.3 200Interpretations 1.3 182

Labour, Engagement of 34.1 195Language/s and Law 5.1 184Law to which Contract Subject 5.1 184Legislation, Subsequent 70.2 218Lighting, Fencing, Watching, etc. 19.1 189Liquidated Damages for Delay 47.1 200Liquidated Damages, Reduction of 47.2 200Loss or Damage due to Employer's Risks 20.3 190Loss or Damage — Responsibility to Rectify 20.2 190Lump Sum Items — Breakdown of 57.2 207

Materials and Plant, Transport of 30.3 194Materials — Approval of, etc. not Implied 54.8 206Materials, Improper — Removal of 39.1 197Materials, Quality of 36.1 197Materials, Supply of 8.1 186Measurement by Engineer 56.1 206Measurement, Method of 57.1 207Measurement, Quantities Estimated Only 55.1 206Methods of Construction 8.2 186Minimum Amount of Insurance 23.2 192Monthly Payments 60.2 211Nominated Subcontractors, Certification of Payments to 59.5 208Nominated Subcontractors, Definition 59.1 207Nominated Subcontractors, Design by 59.3 208Nominated Subcontractors, Objection to Nomination 59.2 207Nominated Subcontractors, Payment to 59.4 208Notice of Claims 53.1 207Notices andFees, Payment of 26.1 193Notices, Consents and Approvals 1.5 183Notice to Contractor 68.1 216Notice to Employer and Engineer 68.2 216Objections to Contractor's Employees 16.2 188Omissions, Alterations and Additions 59. 207Openings, Uncovering and making 38.2 197Operations, Inspection of 37.1 196Order of Work, Contractor to Furnish Programme 14.1 188Other Contractors, Opportunities for 31.1 194

Patent Rights 28.1 193Payment if Contract Terminated for Contractor's Default 63.3 212Payment if Contract Terminated for Employer's Default 69.3 217Payment of Claims 53.5 205Payment, Time for 60.10 211Performance Security 10.1 186Performance Security — Claims Under 10.3 187Performance Security — Period of Validity 10.2 187Period of Defects Liability 49.1 201Permanent Works Designed by Contractor 7.2 186

Page 223: 35824401 FIDIC Guide to the Use of FIDIC

Index Clause Page

Physical Obstructions or Conditions — Adverse 12.2 187Physical Obstructions or Conditions — Engineer's Determination 12.3 187Plant and Materials, Transport of 30.3 194Plant, Conditions of Hire 54.5 206Plant, Customs Clearance 54.3 205Plant, Employer not Liable for damage to 54.2 205Plant, etc. — Exclusive Use for the Works 54.1 205Plant, Quality of 36.1 195Plant, Re-export of 54.4 205Plant, Removal of 39.1 197Policy of Insurance — Compliance with Conditions 25.4 197Possession of Site 42.1 198Possession of Site, Failure to Give 42.2 199Power of Engineer to Fix Rates 52.2 203Priority of Contract Documents 5.2 185Programme to be Submitted 14.1 188Progress— Disruption of 6.3 185Progress — Rate of 46.1 200Protection of Environment 19.1 189Provision to Indemnify Contractor 22.3 192Provision to Indemnify Employer 22.2 191Provisional Sums, Currencies of Payment 72.3 218Provisional Sums, Definition 58.1 207Provisional Sums, Production of Vouchers 58.3 207Provisional Sums, Use of 58.2 207

Quality of Materials and Workmanship 36.1 195Quantities 55.1 206

Rate of Progress 46.1 200Rates of Exchange 72.1 218Rates, Power of Engineer to Fix 52.2 203Rectification of Loss or Damage 20.2 190Reduction of Liquidated Damages 47.2 200Re-export of Plant 54.4 205Regulations, Statutes, etc., Compliance with 26.1 193Rejection 37.4 196Release from Performance 66.1 215Remedies for Default of Contractor 63.1 211Remedying of Defects 49.2 202Remedying of Defects, Cost of 49.3 202Remedy on Contractor's Failure to Insure 25.3 192Removal of Contractor's Employees 16.2 188Removal of Contractor's Equipment 69.2 217Removal of Improper Work, Materials or Plant 39.1 197Removal of Plant, etc. 65.7 214Responsibility to Rectify Loss or Damage 20.2 190Responsibility Unaffected by Approval 7.3 186Restriction on Working Hours 45.1 200Resumption of Work 69.5 217Retention Money, Payment of 60.3 209Returns of Labour and Contractor's Equipment 35.1 195Revised Programme 14.2 188Risks, Employer's 20.4 190Risks, Special 65. 213Roads, etc., — Damageby Extraordinary Traffic 301 194Roads, Interference with Access to 29.1 193Royalties 28.2 193

223

Page 224: 35824401 FIDIC Guide to the Use of FIDIC

Index Clause Page

Safety, Security and Protection of the Environment 19.1 189Samples, Cost of 36.2 195Security, Safety and Protection of the Environment 19.1 189Setting-Out 17.1 189Singular and Plural 1.4 182Site, Clearance on Completion 33.1 195Site Contractor to Keep Clear 32 1 195Site, Inspection of by Contractor 11.1 187Site Operations and Methods of Construction 8.2 186Site, Possession of 42.1 198Special Risks 65. 213Staff, Engagement of 34.1 195Statement at Completion 60.5 210Statement, Final 60.6 210Statutes, Regulations, etc. — Compliance with 26.1 193Subcontracting 4.1 184Subcontractors, Nominated 59. 207Subcontractors, Responsibility of the Contractor for Acts and Default of 4.1 184Subsequent Legislation 70.2 218Substantial Completion of Sections or Parts 48.3 201Sufficiency of Tender 12.1 187Supply of Plant, Materials and Labour 8.1 186Surfaces Requiring Reinstatement 48.4 201Suspension, Engineer's Determination 40.2 198Suspension lasting more than 84 days 40.3 198Suspension of Work 40.1 197

Taking-Over Certificate 48.1 201Taking Over of Sections or Parts 48.2 201Tender Documents' 11.1 187Tender, Sufficiency of 12.1 187Termination of Contract by Employer 63.1 211Termination of Contract by Employer, Assignment of Benefit 63.4 212Terms of Insurance 25.1 192Tests, Cost of 36.3 195Tests riot Provided for — Cost of 36.4 196Third Party Insurance 23.1 192Time for Completion 43.1 199Time for Completion, Extension of 44.1 199Time for Payment 60.10 211Traffic, Extraordinary 30.1 194Traffic, Interference with 29.1 193Traffic, Waterborne 30.4 194Transport of Contractor's Equipment and Temporary Works 30.2 194Transport of Materials and Plant 30.3 194

Uncovering Work and Making Openings 38.2 197Unfulfilled Obligations 62.2 211Urgent Remedial Work 64.1 213

Valuation at Date of Termination by the Employer 63.2 212Variations 51.1 202Variations, Daywork Basis 52.4 204Variations, Exceeding 15 per cent 52.3 203Variations, Instructions for 51 .2 203Variations, Power of the Engineer to Fix Rates 52.2 203Variations, Valuation of 51.3 203Vouchers, Production of 58.3 207

Page 225: 35824401 FIDIC Guide to the Use of FIDIC

Index Clause Page

War, Outbreak of 20.4 190Watching and Lighting, etc. 19.1 189Waterborne Traffic 30.4 194Wayleaves and Facilities 42.3 199Work, Examination of Before Covering Up 38.1 197Work, Improper, Removal of 39.1 197Working Hours, Restriction of 45.1 200Workmanship, Quality of 36.1 195Workmen, Accident or Injury to 24.1 192Works, Care of 20.1 189Works, Completion of (Defects Liability Certificate) 62.1 211Works, Commencement of 41.1 198Works, Insuranceof 21.1 190Works, Remedying of Defects 49.2 201Works, Time for Completion of 43.1 199Works to be Measured 56.1 206Work, Suspension of 40.1 197Work to be in Accordance with the Contract 13.1 188

Z25

Page 226: 35824401 FIDIC Guide to the Use of FIDIC

TENDER

NAME OF CONTRACT: *

TO: *_____________

Gentlemen,

1. Having examined the Conditions of Contract, Specification, Drawings, and Bill ofQuantities and Addenda Nos __________ for the execution of the above-named Works,we the undersigned, offer to execute and complete such Works and remedy any defectstherein in conformity with the Conditions of Contract, Specification, Drawings, Bill ofQuantities and Addenda for the sum of

or such other sums as may be ascertained in accordance with the said Conditions.

2. We acknowledge that the Appendix forms part of our Tender.

3. We undertake, if our Tender is accepted, to commence the Works as soon as is reasonablypossible after the receipt of the Engineer's notice to commence, and to complete thewhole of the Works comprised in the Contract within the time stated in the Appendix toTender.

4. We agree to abide by this Tender for the period of * days from the date fixed forreceiving the same and it shall remain binding upon us and may be accepted at any timebefore the expiration of that period.

5. Unless and until a formal Agreement is prepared and executed this Tender, together withyour written acceptance thereof, shall constitute a binding contract between us.

6. We understand that you are not bound to accept the lowest or any tender you mayreceive.

Datedthis dayof _______________________ 19 _____

Signature in the capacity of ___________________

dulyauthorised to sign tenders for and on behalf of ________________________

(IN BLOCK CAPITALS)

Address

Witness

Address

Occupation

(Note: All details marked * shall be inserted before issue of Tender documents.)

Page 227: 35824401 FIDIC Guide to the Use of FIDIC

22

AppendixSub-Clause

Amount of security (if any) 10.1 _________________ percentof the Contract Price

Minimum amount of third party insurance 23.2 _____________________ peroccurrence, with the numberof occurrences unlimited

Time for issue of notice to commence 41.1 ____________________ days

Time for Completion _________________ 43.1 _________________ days

Amount of liquidated damages ___________ 47.1 _________________ per day

Limit of liquidated damages _____________ 47.1 _______________________

DefectsLiabilityPeriod _________________ 49.1 ___________________days

Percentage for adjustment of ProvisionalSums 59.4(c) percent

Percentage of invoice value of listed materials 60.1(c) per cent

Percentage of Retention __________________ 60.2 per cent

Limit of Retention Money 60.2 _____________________

MinimumAmount of Interim Certificates — 60.2 —____________________

Rateofinterestupon unpaidsums 60.10 _______________ percent

Initials of Signatory of Tender __________________________________________________

(Notes: All details in the list above, other than percentage figure against Sub-Clause 59.4,shall be inserted before issue of Tender documents. Where a number of days is to beinserted, it is desirable, for consistency with the Conditions, that the number should be amultiple of seven.

Additional entries are necessary where provision is included in the Contract for:

(a) completion of Sections (Sub-Clauses 43.1 and 48.2(a))(b) liquidated damages for Sections (Sub-Clause 47.1)(c) a bonus (Sub-Clause 47.3 — Part II)(d) payment for materials on Site (Sub-Clause 60.1(c))(e) payment in foreign currencies (Clause 60 — Part II)(f) an advance payment (Clause 60 — Part II)(g) adjustments to the Contract Price on account of Specified Materials

(Sub-Clause 70.1 — Part 11)(h) rates of exchange (Sub-Clause 72.2 — Part II))

Page 228: 35824401 FIDIC Guide to the Use of FIDIC

Agreement

This Agreement made the __________________ dayof __________________ 19_____

Between

of(hereinafter called "the Employer") of the one part and

___________________________________ of ___________________________________

(hereinafter called "the Contractor") of the other part

Whereas the Employer is desirous that certain Works should be executed by the

Contractor, viz

and has accepted a Tender by the Contractor for the execution and completion of such

Works and the remedying of any defects therein

Now this Agreement witnesseth as follows:

1. In this Agreement words and expressions shall have the same meanings as are respectivelyassigned to them in the Conditions of Contract hereinafter referred to.

2. The following documents shall be deemed to form and be read and construed as part ofthis Agreement, viz:-

(a) The Letter of Acceptance;(b) The said Tender;(c) The Conditions of Contract (Parts I and II);(d) The Specification;(e) The Drawings; and(f) The Bill of Quantities.

3. In consideration of the payments to be made by the Employer to the Contractor ashereinafter mentioned the Contractor hereby covenants with the Employer to execute andcomplete the Works and remedy any defects therein in conformity in all respects with theprovisions of the Contract.

4. The Employer hereby covenants to pay the Contractor in consideration of the executionand completion of the works and the remedying of defects therein the Contract Price orsuch other sum as may become payable under the provisions of the Contract at the timesand in the manner prescribed by the Contract.

In Witness whereof the parties hçreto have caused this Agreement to be executed the dayand year first before written in accordance with their respective laws.

The Common Seal of __________________________________________________

was hereunto affixed in the presence of:-

orSigned Sealed and Delivered by the

said

in the presence of:

22

Page 229: 35824401 FIDIC Guide to the Use of FIDIC

EDITORIAL AMENDMENTS

Following publication of the Fourth Edition in 1987 of the Conditions ofContract for Works of Civil Engineering Construction, a number of editorialamendments were agreed by FIDIC. The amendments have been incorporatedduring reprinting and the list below clarifies the differences between this copy andthe original document.

Foreword The last sentence of the first paragraph previously read 'The Conditions areequally suitable for use on domestic contracts.'

Page 186 Sub-Clause 10.1. A comma has been inserted after the word 'Contract' in thesecond line.The third sentence previously read 'Such security shall be in such form as may beagreed between the Employer and the Contractor.'

Page 1 91 Sub-Clause 22.1 (b) was previously one complete paragraph, ie there was nospace between the words ". . . other than the Works)," and the remainder of theSub-Clause.

Page 1 95 Sub-Clause 31.2(c) was previously one complete paragraph, ie there was no spacebetween the words ". . . nature for any such," and the remainder of theSub-Clause.

Page 200 Sub-Clause 44.3. The penultimate sentence was previously, "In both such casesthe Engineer shall notify the Contractor accordingly, with a copy to theEmployer."

Page.201 Sub-Clause 49.1 (a). The word 'substantial' has been deleted.

Page 209 Sub-Clause 60.3 (b) was previously two paragraphs, the second beginning withthe words 'Provided also that if at such time. .

Page 21 0 Sub-Clause 60.5. The word 'The' has been inserted at the beginning of the finalparagraph.

Page 21 5 Sub-Clause 67.1. In the second line of the fourth paragraph, the word 'notice'replaces the word 'notification'.

Page 21 8 Reference to Part II. In the third line, the words 'and (iv)' have been inserted afterparagraph (a) (i).

TenderItem 3. The word 'Works' has been capitalised.

Agreement -Line 4 Inverted commas have been inserted following the words 'the Employer.'

Line 6 Inverted commas have been inserted before the word 'the' instead of before theword 'Contractor.'

Line 8 The word Contractor has been capitalised.

Line 9 The words "Tender by the Contractor" were previously "Tender byContractor."

Line 11 The word 'Agreement' has been capitalised.

Last lines The Agreement previously ended with the words 'Binding Signature ofEmployer' and 'Binding Signature of Contractor'.

2(2c:

Page 230: 35824401 FIDIC Guide to the Use of FIDIC

1.

UDIC FEDERATION INTERNATIONALE DES INGENIEURS-CONSEILS

GUIDE TO THE USE OF FIDICCONDITIONS OF CONTRACT

FOR WORKS OF CIVIL

PART II CONDITIONS OF PARTICULARAPPLICATION WITH GUIDELINES FORPREPARATION OF PART II CLAUSES

FOURTH EDITION 1987Reprinted 1988 with editorial amendments

ENGINEERING CONSTRUCTION

Page 231: 35824401 FIDIC Guide to the Use of FIDIC

CONTENTS

PART II: CONDITIONS OF PARTICULARAPPLICATION

Page

Introduction (including special reference to Dredging and 232Reclamation Work)

1 Definitions 2352 Engineer's Duties 2355 Language/s and Law and Documents 2359 Contract Agreement 240

10 Performance Security 24111 Inspection of Site 23712 Adverse Physical Obstructions or Conditions 23714 Programme and Cash Flow Estimate 23715 Contractor's Superintendence 24116 Contractor's Employees 24118 Boreholes and Exploratory Excavation 24119 Safety, Security and Protection of the Environment 24121 Insurance of Works and Contractor's Equipment 242,243

21,23& 25 Insurances Arranged by Employer 243

28 Royalties 24331 Opportunities for Other Contractors 24434 Labour 24435 Records and Reports 24540 Suspension 24643 Time for Completion 24645 Restriction on Working Hours 24647 Bonuses 24648 Prevention from Testing 24749 Defects Liability 24750 Contractor to Search 24851 Variations 24852 Payment in Foreign Currency 24854 Vesting of Contractor's Equipment 24960 Certificates and Payments 24967 Settlement of Disputes 25168 Notices 25169 Default of Employer 25170 Changes in Cost and Legislation 25272 Currency Proportions 25573 Additional Clauses 256,257

Page 232: 35824401 FIDIC Guide to the Use of FIDIC

INTRODUCTION

The terms of the Fourth Edition of the Conditions of Contract for Works of CivilEngineering Construction have been prepared by the Fédération Internationaledes Ingénieurs Conseils (FIDIC) and are recommended for general use for thepurpose of construction of such works where tenders are invited on aninternational basis. The Conditions are equally suitable for use on domesticcontracts.

The version in English of the Conditions is considered by FIDIC as the officialand authentic text for the purpose of translation.

The Clauses of general application have been grouped together in a separatelybound document and are referred to as Part I —General Conditions. They havebeen printed in a form which will facilitate their inclusion, as printed, in thecontract documents normally prepared.

In the preparation of the Conditions it was recognised that while there arenumerous Clauses which will be generally applicable there are some Clauseswhich must necessarily vary to take account of the circumstances and locality ofthe Works.

Part I — General Conditions and Part II — Conditions of Particular Applicationtogether comprise the Conditions governing the rights and obligations of theparties.

For this reason a Part II standard form has not been produced. It will benecessary to prepare a Part II document for each individual contract and theGuidelines are intended to aid in this task by giving options for various clauseswhere appropriate.

Part II clauses may arise for one or more reasons, of which the following areexamples:

(i) Where the wording in Part I specifically requires that further information isto be included in Part II and the Conditions would not be complete withoutthat information, namely in Sub-Clauses 1.1 paragraphs (a) (i) and (iv), 5.1(part), 14.1, 14.3, 68.2 and 70.1

(ii) Where the wording in Part I indicates that supplementary information maybe included in Part II, but the conditions would still be complete without anysuch information, namely in Sub-Clauses 2.1 paragraph (b), 5.1 (part), 21.1paragraph (b) and 72.2.

(iii) Where the type, circuristances or locality of the Works necessitatesadditional Clauses or Sub-Clauses.(iv) Where the law of the country or exceptional circumstances necessitate analteration in Part I. Such alterations should be effected by stating in Part IIthat a particular Clause, or part of a Clause, in Part I is deleted and giving thesubstitute Clause, or part, as applicable.

As far as possible, in the Clauses that are mentioned hereunder, example wordingis provided. In the case of some Clauses, however, only an aide-memoire for thepreparation is given. Before incorporating any example wording it must bechecked to ensure that it is wholly suitable for the particular circumstances and, ifnot, it must be varied. Where example wording is varied and in all cases whereadditional material is included in Part II, care must be taken that no ambiguity iscreated with Part I or between the Clauses in Part II.

's FIDIC 1987

Page 233: 35824401 FIDIC Guide to the Use of FIDIC

Dredging and Reclamation Work

Special consideration must be given to Part H where dredging and certain types ofreclamation work are involved. Dredgers are considerably more expensive thanmost items of Contractor's Equipment and the capital value of a dredger canoften exceed the value of the Contract on which it is used.

For this reason, it is in the interests of both the Employer and the Contractor thata dredger is operated intensively in the most economic fashion, subject to thequality of work and any other over-riding factors. With this end in view, it iscustomary to allow the Contractor to execute dredging work continuously by dayand by night seven days a week. Another difference from most civil engineering isthat on dredging work the Contractor is not normally held responsible for theremedying of defects after the date of completion as certified under Clause 48.Part II contains explanations and example wording to cover the above points andothers relating to dredging. Clauses 11, 12, 18, 19, 28, 40, 45, 49, 50 and 51 arethose which most often require attention in Part II when dredging work isinvolved and reference is included under each of these Clauses. Other Clausesmay also need additions in Part II in certain circumstances. Reclamation workvaries greatly in character and each instance must be considered before decidingwhether it is appropriate to introduce in Part II changes similar to those adoptedfor dredging, or to use the standard civil engineering form unaltered.

© FIDIC 1987

Page 234: 35824401 FIDIC Guide to the Use of FIDIC

Page blankin original

Page 235: 35824401 FIDIC Guide to the Use of FIDIC

PART II CONDITIONS OF PARTICULAR APPLICATION

Clause 1

Sub-Clause 1.1 — Definitions

(a) (i) The E,nployer is (insert name)

(a) (iv) The Engineer is (insert name)

If further definitions are essential, for example the name of an International FinancingInstitution (IFI), additions should be made to thelist.

Clause 2Sub-Clause 2.1 — Engineer's Duties

EXAMPLE

The Engineer shall obtain the specific approval of the Employer before carryingout his duties in accordance with the following Clauses of Part 1:

(a) Clause (insert applicable number)(b) Clause (insert applicable number)(c) Clause (insert applicable number)

This list should be extended or reduced as necessary.

In some cases the obligation to obtain the approval of the Employer may apply to onlyone Sub-Clause out of several in a Clause or approval may only be necessary beyondcertain limits, monetary or otherwise. Where this is so, the example wording must bevaried.

If the obligation to obtain the approval of the Employer could lead to the Engineer beingunable to take aëtion in an emergency, where matters of safety are involved, an additionalparagraph may be necessary.

EXAMPLENotwithstanding the obligation, as set out above, to obtain approval, if, in theopinion of the Engineer, an emergency occurs affecting the safety of life or of theWorks or of adjoining property, he may, without relieving the Contractor of anyof his duties and responsibilities under the Contract, instruct the Contractor toexecute all such work or to do all such things as may, in the opinion of theEngineer, be necessary to abate or reduce the risk. The Contractor shallforth withcomply, despite the absence of approval of the Employer, with any suchinstruction of the Engineer. The Engineer shall determine an addition to theContract Price, in respect of such instruction, in accordance with Clause 52 andshall notify the Contractor accordingly, with a copy to the Employer.

Clause 5Sub-Clause 5.1 — Language/s and Law

(a) The language is (insert as applicable)(b) The law is that in force in (insert name of country)

If necessary (a) above should be varied to read:The languages are (insert as applicable)

and there should be addedThe Ruling Language is (insert as applicable)

© FIDIC 1987

Page 236: 35824401 FIDIC Guide to the Use of FIDIC

Sub-Clause 5.2 — Priority of Contract Documents

Where it is decided that an order of precedence of all documents should be included, thisSub-Clause may be varied as follows:

EXAMPLEDelete the documents listed 1—6 and substitute:

(1) the Contract Agreement (if completed);

(2) the Letter of Acceptance;(3) the Tender;(4) the Conditions of Contract Part II;(5) the Conditions of Contract Part I;

(6) the Specification;(7) the Drawings; and

(8) the priced Bill of Quantities

orWhere it is decided that no order of precedence of documents shouldbe included, this Sub-Clause may be varied as follows:

EXAMPLEDelete the text of the Sub-Clause and substitute:The several documents forming the Contract are to be taken as mutuallyexplanatory of one another, but in the case of ambiguities or discrepancies thepriority shall be that accorded by law. If, in the opinion of the Engineer, suchambiguities or discrepancies make it necessary to issue any instruction to theContractor in explanation or adjustment, the Engineer shall have authority toissue such instruction.

Clause 9Where it is decided that a Contract Agreement should be entered into and executed theform must be annexed to these Conditions as stated in Sub-Clause 9.1 of theseConditions.

A suitable form is annexed to Part 1 —General Conditions.

Clause 10

Sub-Clause 10.1 — Performance Security

Where it is decided that a performance security should be obtained by the Contractor, theform must be annexed to these ConditiQns as stated in Sub-Clause 10.1 of Part I of theseConditions.

Two example forms of performance security are given on pages 7, 8 and 9. The Clauseand wording of the example forms may have to be varied to comply with the law of theContract which may require the forms to be executed under seal.

Where there is provision in the Contract for payments to the Contractor to be made inforeign currency, Sub-Clause 10.1 of Part I of these Conditions may be varied.

EXAMPLE

After the first sentence, insert the following sentence:The security shall be denominated in the types and proportions of currenciesstated in the Appendix to Tender.

Where the source of the performance security is to be restricted, an additional Sub-Clausemay be added.

© FIDIC 1987

Page 237: 35824401 FIDIC Guide to the Use of FIDIC

EXAMPLE SUB-CLAUSES

Sourceof 10.4 The performance security, submitted by the Contractor in accordance withPerformance Sub-Clause 10.1, shall be furnished by an institution registered in (insert the

Security country where the Works are to be executed) or licensed to do business in suchcountry.

or

Source of 10.4 Wherethe performance security is in the form of a bank guarantee, it shall bePerformance issued by:

Security (a) a bank located in the country of the Employer, or(b) a foreign bank through a correspondent bank located in the country of theEmployer.

Clause 11

Wherethe bulk or complexity of the data, or reasons of security enforced by the countrywhere the Works are to be executed, makes it impracticable for the Employer to make alldata available with the Tender Documents and inspection of some data by the Contractorat an office is therefore expected, it would be advisable to make the circumstances clear.

EXAMPLE SUB-CLAUSE

Access 11.2 Data made available by the Employer in accordance with Sub-Clause 11.1 shallto Data be deemed to include data listed elsewhere in the Contract as open for inspection

at (insertparticulars of the office or offices where such data is stored)

Sub-Clause 11.1 — Inspection of Site

For a Contract comprising dredgIng and reclamation work the Clause may be varied asfollows:

EXAMPLE

In the first paragraph, delete the words 'hydrological and sub-surface' andsubstitute 'hydrographic and sub-seabed'.

In the second paragraph, under (a) delete the word 'sub-surface' and substitute'sub-seabed' and under (b) delete the word 'hydrological' and substitute'hydrographic'.

Clause 12Sub-Clause 12.2 — Adverse Physical Obstructions or Conditions

For a Contract comprising dredging and some types of reclamation work the Sub-Clausemay require to be varied.

EXAMPLEDelete the words ',other than climatic conditions on the Site,'.

Clause 14Sub-Clause 14.1 — Programme to be Submitted

The time within which the programme shall be subm itted shall be (insert number)days.

Sub-Clause 14.3 — Cash Flow Estimate to be Submitted

The time within which the detailed cash flow estimate shall be submitted shall be(insert number) days.

In both examples given above it is desirable for consistency with the rest of the Conditionsthat the number of days inserted should be a multiple of seven.

© FIDIC 1987

Page 238: 35824401 FIDIC Guide to the Use of FIDIC

EXAMPLE PERFORMANCE GUARANTEE

By this guarantee We,

whose registered office isat ____________________________________________

(hereinafter called "the Contractor") and _______________________________

whose registered office is at ______________________________________________

(hereinafter called "the Guarantor") are held and firmly bound unto

(hereinafter called "the Employer")

in the sum of for the payment of which sum

the Contractor and the Guarantor bind themselves, their successors and assignsjointly and severally by these presents.

Whereas the Contractor by an Agreement made between the Employer of the onepart and the Contractor of the other part has entered into a Contract (hereinaftercalled "the said Contract") to execute and complete certain Works and remedyany defects therein as therein mentioned in conformity with the provisions of thesaid Contract.

Now the Condition of the above-written Guarantee is such that if the Contractorshall duly perform and observe all the terms provisions conditions andstipulations of the said Contract on the Contractor's part to be performed andobserved according to the true purport intent and meaning thereof or if ondefault by the Contractor the Guarantor shall satisfy and discharge the damagessustained by the Employer thereby up to the amount of the above-writtenGuarantee then this obligation shall be null and void but otherwise shall be andremain infuilforce and effect but no alteration in terms of the said Contract or inthe extent or nature of the Works to be executed, completed and defects thereinremedied thereunder and no allowance of time by the Employer or the Engineerunder the said Contract nor any forbearance or forgiveness in or in respect of anymatter or thing concerning the said Contract on the part of the Employer or thesaid Engineer shall in any way release the Guarantor from any liability under theabove-written Guarantee. Provided always that the above obligation ofGuarantor to satisfy and discharge the damages sustained by the Employer shallarise only

(a) on written notice from both the Employer and the Contractor that theEmployer and the Contractor have mutually agreed that the amount of damagesconcerned is payable to the Employer or(b) on receipt by the Guarantor of a legally certified copy of an award issued inarbitration proceeding carried out in conformity with the terms of the saidContract that the amount of the damages is payable to the Employer.

Signed on _____________________ Signedon _____

onbehalf of ____________________ onbehalf of

by by

in the capacity of_________________ in the capacity of.

in the presence of ___________________ in the presence of

© FIDIC 1987

Page 239: 35824401 FIDIC Guide to the Use of FIDIC

EXAMPLE SURETY BOND FOR PERFORMANCE

Know all Men by these Presents that (name and address of Contractor)

as Principal (hereinafter called "the Contractor") and (name, legal title and

address of Surety)

as Surety (herein after called "the Surety"), are held and firmly bound unto

(name and address of Employer) —________________

__________________________________________ as Obligee (hereinafter called"the Employer") in the amount of for the payment of which sum, welland truly to be made, the Contractor and the Surety bind themselves, theirsuccessors and assigns, jointly and severally, firmly by these presents.

Whereas the Contractor has entered into a written contract agreement with the

Employerdated the _______________ dayof_______________ 19

for (name of Works)in accordance with the plans and specifications and amendments thereto, to theextent herein provided for, are by reference made part hereof and are hereinafterreferred to as the Contract.

Now, therefore, the Condition of this Obligation is such that, if the Contractorshall promptly and faithfully perform the said Contract (including anyamendments thereto) then this obligation shall be null and void; otherwise it shallremain in fullforce and effect.

Whenever Contractor shall be, and declared by Employer to be, in default underthe Contract, the Employer having performed the Employer's obligationsthereunder, the Surety may promptly remedy the default, or shall promptly:-

(1) Complete the Contract in accordance with its terms and conditions; or(2) Obtain a bid or bids for submission to the Employer for completing theContract in accordance with its terms and conditions, and upon determination byEmployer and Surety of the lowest responsible bidder, arrange for a contractbetween such bidder and Employer and make available as work progresses (eventhough there should be a default or a succession of defaults under the contract orcontracts of completion arranged under this paragraph) sufficient funds to paythe cost of completion less the balance of the Contract Value; but not exceeding,including other costs and damages for which the Surety may be liable hereunder,the amount set forth in the first paragraph hereof The term "balance of theContract Value", as used in this paragraph, shall mean the total amount payableby Employer to Contractor under the Contract, less the amount properly paid byEmployer to Contractor; or(3) Pay the Employer the amount required by Employer to complete the Contractin accordance with its terms and conditions any amount up to a total notexceeding the amount of this Bond.

FIDIC 1987

Page 240: 35824401 FIDIC Guide to the Use of FIDIC

The Surety shall not be liable for a greater sum than the specified penalty of thisBond.

Any suit under this Bond must be instituted before the issue of the DefectsLiability Certificate.

No right of action shall accrue on this Bond to or for the use of any person orcorporation other than the Employer named herein or the heirs, executors,administrators or successors of the Employer.

Signed on ______________________ Signed on ______________________

onbehalf of____________________ on be ha If of

by by

in the capacity of in the capacity of

in the presence of ___________________ in the presence of

(C) FIDIC 1987

Page 241: 35824401 FIDIC Guide to the Use of FIDIC

Clause 15Where the language in which the Contract documents have been drawn up is not thelanguage of the country in which the Works are to be executed, or where for any otherreason it is necessary to stipulate that the Contractor's authorised representative shall befluent in a particular language, an additional Sub-Clause may be added.

EXAMPLE SUB-CLAUSES

Language Ability 15.2 The Contractor's authorised representative shall be fluent in (insert name ofof Contractor's language).Representative

or

Interpreterto be 15.2 If the Contractor's authorised representative is not, in the opinion of theMade Available Engineer, fluent in (insert name of language), the Contractor shall have available

on Site at all times a competent interpreter to ensure the proper transmission ofinstructions and information.

Clause 16Where the language in which the Contract documents have been drawn up is not thelanguage of the country in which the Works are to be executed, or where for any otherreason it is necessary to stipulate that members of the Contractor's superintending staffshall be fluent in a particular language, an additional Sub-Clause may be added.

EXAMPLE SUB-CLAUSE

LanguageAbility 16.3 A reasonable proportion of the Contractor's superintending staff shall have aofSuperintending working knowledge of (insert name of language) or the Contractor shall have

Staff available on Site at all times a sufficient number of competent interpreters toensure the proper transmission of instructions and information.

Where there is a desire, but not a legal requirement, that the Contractor makes reasonableuse of materials from or persons resident in the country in which the Works are to beexecuted, an additional Sub-Clause may be added.

EXAMPLE SUB-CLAUSE

Employment of 16.4 The Contractor is encouraged, to the extent practicable and reasonable, toLocal Personnel employstaff and labour from sources within (insert name of country).

Clause 18Sub-Clause 18.1 — Boreholes and Exploratory Excavation

For a Contract comprising dredging and reclamation work the Sub-Clause may require tobe varied.

EXAMPLE

Add second sentence as follows:

Such exploratory excavation shall be deemed to include dredging.

Clause 19

Sub-Clause 19.1 — Safety, Security and Protection of the Environment

Where a Contract includes dredging the possibilityof pollution should be given particularattention and additional wording may be required. For example, where fishing andrecreation areas might be influenced, the Contractor should be required to plan andexecute the dredging so that the effect is kept to a minimum. Where there is a risk ofchemical pollution from soluble sediments in the dredging area, for instance in a harbour,it is important that sufficient information is provided with the Tender documents.Responsibilities should be clearly defined.

IIDIC 1987 2_4_I

Page 242: 35824401 FIDIC Guide to the Use of FIDIC

Clause 21

Sub-Clause 21.1 — Insurance of Works and Contractor's Equipment

Where there is provision in the Contract for payments to the Contractor to be made inforeign currency, this Sub-Clause may be varied.

EXAMPLE

Add final sentence as follows:

The insurance in paragraphs (a) and (b) shall provide for compensation to bepayable in the types and proportions of currencies required to rectify the loss ordamage incurred.

Where it is decided to state the deductible limits for the Employer's Risks, thisSub-Clause may be varied.

EXAMPLE

Add to paragraph (a) as follows:

and with deductible limits for the Employer's Risks not exceeding (insertamounts)

Clause 21, 23 and 25. Insurances Arranged by EmployerIn certain circumstances, such as where a number of separate contractors are employedon a single project, or phased take-over is involved, it may be preferable for the Employerto arrange insurance of the Works, and Third Party insurance. In such case, it must beclear in the Contract that the Contractor is not precluded from taking out any additionalinsurance, should he desire to do so, over and above that to be arranged by the Employer.

Tenderers must be provided at the Tender stage with details of the insurance to bearranged by the Employer, in order to assess what provision to make in their rates andprices for any additional insurance, and for the amount of policy deductibles which theywill be required to bear. Such details shall form part of the Contract between theEmployer and the Contractor.

Example wording to allow for the arrangement of insurance by the Employer is asfollows:

EXAMPLE

Clause 21

Delete the text of the Clause and substitute the following re-numberedSub-Clauses:

Insurance 21.1 Without limiting his or the Contractor's obligations and responsibilities underof Works Clause 20, the Employer will insure:

(a) the Works, together with materials and Plant for incorporation therein, to thefull replacement cost(b) an additional sum to cover any additional costs of and incidental to therectification of loss or damage including professional fees and the cost ofdemolishing and removing any part of the Works and of removing debris ofwhatsoever nature.

Insurance of 21.2 The Contractor shall, without limiting his obligations and responsibilities underContractor's Clause20, insure the Contractor's Equipment and other things brought onto the

Equipment siteby the Contractor, for a sum sufficient to provide for their replacement at theSite.

Scope of Cover 21 3 The insurance in Sub Clause 21 1 shall be in the joint names of the Contractorand the Employer and shall cover:

(çj FIDIC 1987

Page 243: 35824401 FIDIC Guide to the Use of FIDIC

(a) the Employer and the Contractor against loss or damage as provided in thedetails of insurance annexed to these Conditions, from the start of work at theSite until the date of issue of the relevant Taking-Over Certificate in respect of theWorks or any Section or part thereof as the case may be, and

(b) the Contractor for his liability:(i) during the Defects Liability Period for loss or damage arising from a causeoccurring prior to the commencement of the Defects Liability Period, or

(ii) occasioned by the Contractor in the course of any operations carried out byhim for the purpose of complying with his obligations under Clauses 49 and 50.

Responsibility for 21.4 Anyamounts not insured or not recoveredfrom the insurers shall be borne by theAmounts not Employer or the Contractor in accordance with their responsibilities under

Recovered Clause 20.

Clause 23Delete the text of the Clause and substitute:

ThirdParty 23.1 Without limiting his or the Contractor's obligations and responsibilities underInsurance Clause 22, the Employer will insure in the joint names of the Contractor and the(Including Employer, against liabilities for death of or injury to any person (other than as

Employer's provided in Clause 24) or loss of or damage to any property (other than theProperty) Works) arising out of the performance of the Contract, as provided in the details

of insurance referred to in Sub-Clause 21.3.

Clause 25Delete the text of the Clause and substitute:

Evidence 25.1 The insurance policies to be arranged by the Employer pursuant to Clauses 21 andand Terms of 23 shall be consistent with the general terms described in the Tender and copies of

Insurances suchpolicies shall when required be supplied by the Employer to the Contractor.

Adequacy of 25.2 The Employer shall notify the insurers of changes in the nature, extent orInsurances programme for execution of the Works and ensure the adequacy of the

insurances at all times in accordance with the terms of the Contract and shall,when required, produce to the Contractor the insurance policies in force and thereceipts for payment of the premiums. No variations shall be made to theinsurances by the Employer without the prior approval of the Contractor.

Remedyon 25.3 If andso far as the Employerfails to effect and keep in force any of the insurancesEmployer's referred to in Sub-Clause 25.1, then the Contractor may effect and keep in force

Failure to Insure anysuch insurance and pay any premium as may be necessary for that purposeand add the amount so paid to any monies due or to become due to theContractor, or recover the same as a debt due from the Employer.

Compliance with 25.4 In the event that the Contractor or the Employer fails to comply with conditionsPolicy Conditions imposed by the insurance policies effected pursuant to the Contract, each shall

indemnify the other against all losses and claims arising from such failure.

Clause 28Sub-Clause 28.2 — Royalties

For a Contract comprising dredging and reclamation work and for any other Contractinvolving the dumping of materials the Sub-Clause may require to be varied.

EXAMPLE

Add second sentence as follows:

The Contractor shall also be liable for all payments or compensation, if any,levied in relation to the dumping of part or all of any such materials.

© FIDIC 1987 412

Page 244: 35824401 FIDIC Guide to the Use of FIDIC

It is sometimes the case on dredging contracts for the Employer to bear the costs oftonnage and other royalties, rent and other payments or compensation. If suchconditions are to apply, Sub-Clause 28.2 should be varied either by adding wording or bydeleting the existing wording and substituting new wording.

Clause 31

Where the particular requirements of other contractors are known within reasonablelimits at the time of preparation of the Contract documents, details must be stated. TheSpecification is usually the appropriate place to do so but, exceptionally, some referencemay be desirable in the Conditions. In that case, an additional Sub-Clause or Sub-Clausescould be added to this Clause.

Clause 34It will generally be necessary to add a number of Sub-Clauses, to take account of thecircumstances and locality of the Works, covering such matters as: permits andregistration of expatriate employees; repatriation to place of recruitment; provision oftemporary housing for employees; requirements in respect of accommodation for staff ofEmployer and Engineer; standards of accommodation to be provided; provision ofaccess roads, hospital, school, power, water, drainage, fire services, refuse collection,communal buildings, shops, telephones; hours and conditions of working; rates of pay;compliance with labour legislation; maintenance of records of safety and health.

EXAMPLE SUB-CLAUSES (to be numbered, as appropriate)

Rates of Wages 34. The Contractor shall pay rates of wages and observe conditions of labour not lessand Conditions favourable than those established for the trade or industry where the work is

ofLabour carried out. In the absence of any rates of wages or conditions of labour soestablished, the Contractor shall pay rates of wages and observe conditions oflabour which are not less favourable than the general level of wages andconditions observed by other employers whose general circumstances in the tradeor industry in which the Contractor is engaged are similar.

Employmentof 34. The Contractor shall not recruit or attempt to recruit his staff and labour fromPersons in the amongst persons in the service of the Employer or the Engineer.

Service of Others

Repatriation of 34. The Contractor shall be responsible for the return to the place where they wereLabour recruitedor to their domicile of all such persons as he recruited and employed for

the purposes of or in connection with the Contract and shall maintain suchpersons as are to be so returned in a suitable manner until they shall have left theSite or, in the case of persons who are not nationals of and have been recruitedoutside (insert name of country), shall have left (insert name of country).

Housing for Labour 34. Save insofar as the Contract otherwise provides, the Contractorshall provide andmaintain such accommodation and amenities as he may consider necessary for allhis staff and labour, employed for the purposes of or in connection with theContract, including all fencing, water supply (both for drinking and otherpurposes), electricity supply, sanitation, cookhouses, fire prevention andfire-fighting equipment, air conditioning, cookers, refrigerators, furniture andother requirements in connection with such accommodation or amenities. Oncompletion of the Contract, unless otherwise agreed with the Employer, thetemporary camps/housing provided by the Contractor shall be removed and thesite reinstated to its original condition, all to the approval of the Engineer.

AccidentPrevention 34. The Contractor shall have on his staff at the Site an officer dealing only withOfficer; Accidents questions regarding the safety and protection against accidents of all staff and

labour. This officer shall be qualifiedfor this work and shall have the authority toissue instructions and shall take protective measures to prevent accidents.

Cc) FDIC 1987

Page 245: 35824401 FIDIC Guide to the Use of FIDIC

Health and Safety 34. Due precautions shall be taken by the Contractor, and at his own cost, to ensurethe safety of his staff and labour and, in collaboration with and to therequirements of the local health authorities, to ensure that medica/staff, first aidequipment and stores, sick bay and suitable ambulance service are available at thecamps, housing and on the Site at al/times throughout the period of the Contractand that suitable arrangements are made for the prevention of epidemics and forall necessary welfare and hygiene requirements.

Measures against 34. The Contractorshallat all times take the necessary precautions to protect al/staffInsectand Pest and labour employed on the site from insect nuisance, rats and other pests and

Nuisance reduce the dangers to health and the general nuisance occasioned by the same.The Contractor shall provide his staff and labour with suitable prophylactics forthe prevention of malaria and take steps to prevent the formation of stagnantpools of water. He shall comply with all the regulations of the local healthauthorities in these respects and shall in particular arrange to spray thoroughlywith approved insecticide all buildings erected on the Site. Such treatment shall becarried out at least once a year or as instructed by the Engineer. The Contractorshall warn his staff and labour of the dangers of bilharzia and wild animals.

Epidemics 34. In the event of any outbreak of illness of an epidemic nature, the Contractor shallcomply with and carry out such regulations, orders and requirements as may bemade by the Government, or the local medical or sanitary authorities, for thepurpose of dealing with and overcoming the same.

Burialof the Dead 34. The Contractor shall make all necessary arrangements for the transport, to anyplace as required for burial, of any of his expatriate employees or members oftheir families who may die in (insert name of country). The Contractor shall alsobe responsible, to the extent required by the local regulations, for making anyarrangements with regard to burial of any of his local employees who may diewhile engaged upon the Works.

Supplyof 34. The Contractor shall arrange for the provision of a sufficient supply of suitableFoodstuffs food at reasonable prices for all his staff and labour, or his Subcontractors, for

the purposes of or in connection with the Contract.

Supply of Water 34. The Contractor shall, so far as is reasonably practicable, having regard to localconditions, provide on the Site an adequate supply of drinking and other waterfor the use of his staff and labour.

AlcoholicLiquor 34. The Contractor shall not, otherwise than in accordance with the Statutes,or Drugs Ordinances and Government Regulations or Orders for the time being in force,

import, sell, give, barter or otherwise dispose of any alcoholic liquor or drugs, orpermit or suffer any such importation, sale, gift, barter or disposal by hisSubcontractors, agents, staff or labour.

Arms and 34. The Contractor shall not give, barter or otherwise dispose of to any person orAmmunition persons, any arms or ammunition of any kind or permit or suffer the same as

aforesaid.Festivals and 34. The Contractor shall in all dealings with his staff and labour have due regard to

Religious Customs allrecognised festivals, days of rest and religious or other customs.

Disorderly Conduct 34. The Contractor shall at all times take all reasonable precautions to prevent anyunlawful, riotous or disorderly conduct by or amongst his staff and labour andfor the preservation of peace and protection of persons and property in theneighbourhood of the Works against the same.

Clause 35Additional Sub-Clauses may be desirable to cover circumstances which require themaintenance of particular records or the provision of certain specific reports.

EXAMPLE SUB-CLAUSES (to be numbered, as appropriate)

© FWIC 1987

Page 246: 35824401 FIDIC Guide to the Use of FIDIC

Records of Safety 35. The Contractor shall maintain such records and make such reports concerningand Health safety, health and welfare of persons and damage to property as the Engineer

may from time to time prescribe.

Reporting of 35. The Contractor shall report to the Engineer details of any accident as soon asAccidents possible after its occurrence. In the case of any fatality or serious accident, the

Contractor shall, in addition, notify the Engineer immediately by the quickestavailable means.

Clause 40Fora Contract comprising dredging and some types of reclamation work the Clause maybe varied.

Sub-Clause 40.1 — Suspension of Work

EXAMPLEDeleteparagraph (c) and renumber paragraph (d) as (c).

Sub-Clause 40.3 — Suspension Lasting more than 84 Days

EXAMPLEIn the first sentence delete the words ', (c) or (d)' and substitute 'or (c)'.

Clause 43Sub-Clause 43.1 — Time for Completion

Where completion is stated to be by a date and not within a period of time, theSub-Clause will require to be varied.

EXAMPLEDelete the words, 'within the time.. .such extended time' and substitute 'by thedate or dates stated in the Appendix to Tender for the whole of the Works or theSection (as the case may be) or such later date or dates'.

Clause 45

For a Contract located in an isolated area, where environmental restrictions do not apply,or where a Contract comprises work, such as dredging and reclamation, that may requirecontinuous working, the Clause may be varied.

EXAMPLE

Delete Sub-Clause 45.1 and substitute:

Working Hours 45. 1 Subject to any provision to the contrary contained in the Contract, theContractor shall have the option to work continuously by day and by night andon locally recognised days of rest.

The Contractor's option may be further extended by substituting, in place of the lastthree words:

holidays or days of rest.

Clause 47Where it is desired to make provision for the payment of a bonus or bonuses for earlycompletion, an additional Sub-Clause may be added.

In the case where a bonus is provided for early completion of the whole of the Works:

(C FIDIC' 1987

Page 247: 35824401 FIDIC Guide to the Use of FIDIC

EXAMPLE SUB-CLAUSE

Bonus for 47.3 If the Contractor achieves completion of the Works prior to the time prescribedCompletion by Clause 43, the Employer shall pay to the Contractor a sum of(insertfigure)for

every day which shall elapse between the date stated in the Taking-OverCertificate in respect of the Works issued in accordance with Clause 48 and thetime prescribed in Clause 43.

or

In the case where bonuses are provided for early completion of Sections of the Works anddetails, other than the dates, are given in the Specification:

EXAMPLE SUB-CLAUSE

Bonus for 47.3 Sections are required to be completed by the dates given in the Appendix toCompletion Tender in order that such Sections may be occupied and used by the Employer in

advance of the completion of the whole of the Works.

Details of the work required to be executed to entitle the Contractor to bonuspayments and the amount of the bonuses are stated in the Specification.

For the purposes of calculating bonus payments, the dates given in the Appendixto Tender for completion of Sections are fixed and, unless otherwise agreed, noadjustments of the dates by reason of granting an extension of time pursuant toClause 44 or any other Clause of these Conditions will be allowed.

Issue of certificates by the Engineer that the Sections were satisfactory andcomplete by the dates given on the certificates shall, subject to Clause 60, entitlethe Contractor to the bonus payments calculated in accordance with theSpecification.

Clause 48Where it can be foreseen that, when the whole of the Works have been substantiallycompleted, the Contractor may be prevented by reasons beyond his control from carryingout the Tests on Completion, an additional Sub-Clause may be added.

EXAMPLE SUB-CLAUSE

Prevention 48.5 If the Contractor is prevented from carrying out the Tests on Completion by afrom Testing causefor which the Employer or the Engineer or other contractors employed by

the Employer are responsible, the Employer shall be deemed to have taken overthe Works on the date when the Tests on Completion would have been completedbut for such prevention. The Engineer shall issue a Taking-Over Certificateaccordingly. Provided always that the Works shall not be deemed to have beentaken over if they are not substantially in accordance with the Contract.

if the Works are taken over under this Sub-Clause the Contractor shallnevertheless carry out the Tests on Completion during the Defects LiabilityPeriod. The Engineer shall require the Tests to be carried out by giving 14 daysnotice.

Any additional costs to which the Contractor may be put, in making the Tests onCompletion during the Defects Liability Period, shall be added to the ContractPrice.

Clause 49For a Contract which includes a high proportion of Plant, an additional Sub-Clause maybe necessary.

( FIDIC 1987

Page 248: 35824401 FIDIC Guide to the Use of FIDIC

EXAMPLE SUB-CLAUSE

Extension of 49.5 The provisions of this Clause shall apply to all replacements or renewals of PlantDefects Liability carried out by the Contractor to remedy defects and damage as if the

replacements and renewals had been taken over on the date they were completed.The Defects Liability Period for the Works shall be extended by a period equal tothe period during which the Works cannot be used by reason of a defect ordamage. If only part of the Works is affected the Defects Liability Period shall beextended only for that part. In neither case shall the Defects Liability Periodextend beyond 2 years from the date of taking over.

When progress in respect of Plant has been suspended under Clause 40, theContractor's obligations under this Clause shall not apply to any defectsoccurring more than 3 years after the Time for Completion established on thedate of the Letter of Acceptance.

For a Contract comprising dredging work an additional Sub-Clause may be added.

EXAMPLE SUB-CLAUSE

No Remedying 49.5 Notwithstanding Sub-Clause 49.2, the Contractor shall have no responsibility forof Defects in the remedying of defects, shrinkages or other faults in respect of dredging work

Dredging Work after the date stated in the Taking-Over Certificate.after Completion

Clause 50For a Contract comprising dredging work and where the second Example Sub-Clause49.5 has been adopted, an additional Sub-Clause should be added.

EXAMPLE SUB-CLAUSE

NoResponsibility for 50.2 Notwithstanding Sub-Clause 50.1, the Contractor shall have no responsibility toCost of Searching of bear the cost of searching for any defect, shrinkage or other fault in respect of

Dredging Work dredging work after the date stated in the Taking-Over Certificate.

Clause 51

Sub-Clause 51.1 — Variations

For a Contract comprising dredging and some types of reclamation work the Sub-Clausemay require to be varied.

EXAMPLE

Addfinal sentence as follows:

Provided also that the Contractor shall be under no obligation to execute anyvariation which cannot be executed by the Contractor's Equipment being used orto be used on the Works.

Clause 52Where provision is made in the Contract for payment in foreign currency, this Clausemay be varied.

Sub-Clause 52.1 — Valuation of Variations

EXAMPLE

Addfinal sentence as follows:

The agreement, fixing or determination of any rates or prices as aforesaid shallinclude any foreign currency and the proportion thereof.

© FIDIC i987

Page 249: 35824401 FIDIC Guide to the Use of FIDIC

Sub-Clause 52.2 — Power of Engineer to Fix Rates

Add to first paragraph final sentence as follows:

The agreement or fixing of any rates or prices as aforesaid shall include anyforeign currency and the proportion thereof.

Sub-Clause 52.3 — Variations Exceeding 15 per cent

Add final sentence as follows:

The adjustment or fixing of any sum as aforesaid shall have due regard to anyforeign currency included in the Effective Contract Price and the proportionthereof.

Where it is required to place some limitation on the range of items for which the rates andprices may be subject to review, the Clause may be varied.

Sub-Clause 52.2 — Power of Engineer to Fix Rates

EXAMPLE

At the end of the first paragraph add:

Provided furt her that no change in the rate orpricefor any item contained in theContract shall be considered unless such item accounts for an amount more than2 per cent of the Contract Price, and the actual quantity of work executed underthe item exceeds or falls short of the quantity set out in the Bill of Quantities bymore than 25 per cent.

Clause 54

Where vesting of Contractor's Equipment, Temporary Works and materials in theEmployer is required, additional Sub-Clauses may be added.

EXAMPLE WORDING AND SUB-CLAUSESSub-Clauses 54.2 and 54.3 shall be renumbered as 54.3 and 54.4 and Sub-Clauses54.4 to 54.8 shall be renumbered as 54.6 to 54.10. Add additional Sub-Clauses asfollows:

Vesting 54.2 All Contractor's Equipment, Temporary Works and materials owned by the-Contractor, or by any company in which the Contractor has a controllinginterest, shall, when on the Site, be deemed to be the property of the Employer.Provided always that the vesting of such property in the Employer shall notprejudice the right of the Contractor to the sole use of the said Contractor'sEquipment, Temporary Works and materials for the pwpose of the Works norshall it affect the Contractor's responsibility to operate and maintain the sameunder the provisions of the Contract.

Revesting and 54.5 Upon the removal, with the consent of the Engineer under Sub-Clauses 54.1, ofRemoval anysuch Contractor's Equipment, Temporary Works or materials as have been

deemed to have become the property of the Employer under Sub-Clause 54,2, theproperty therein shall be deemed to revest in the Contractor and, uponcompletion of the Works, the property in the remainder of such Contractor'sEquipment, Temporary Works and materials shall, subject to Clause 63, bedeemed to revest in the Contractor.

Clause 60Additional Sub-Clauses may be necessary to cover certain other matters relating topayments.Where payments are to be made in various currencies in predetermined proportions andcalculated at fixed rates of exchange the following 3 Sub-Clauses, which should be takentogether, may be added:

© FIDIC 1987

Page 250: 35824401 FIDIC Guide to the Use of FIDIC

EXAMPLE SUB-CLAUSES (to be numbered, as appropriate)

Currency 60. The currency of account shall be the (insert name of currency) and for theofAccount purposes of the Contract con version between (insert name of currency) and otherandRates currencies stated in the Appendix to Tender shall be made in accordance with the

ofExchange Table of Exchange Rates in the Appendix to Tender. Conversion between thecurrencies stated in such Table other than the (insert name of currency) shall bemade at rates of exchange determined by use of the relative rates of exchangebetween such currencies and the (insert name of currency) set out therein.

Payments to 60. Al/payments to the Contractor by the Employer shall be madeContractor

(a) in the case of payment (s) under Sub-Clause(s) 70.2 and (insert number of anyother applicable Clause), in (insert name of currency/ies);

(b) in the case of payments for certain provisional sum items excluded from theAppendix to Tender, in the currencies and proportions applicable to these itemsat the time when the Engineer gives instructions for the work covered by theseitems to be carried out;

(c) in any other case, including Increase or Decrease of Costs under Sub-Clause70.1, in the currencies and proportions stated in the Appendix to Tender asapplicable to such payment provided that the proportions of currencies stated inthe Appendix to Tender may from time to time upon the application of eitherparty be varied as may be agreed.

Payments to 60. Allpayments to the Employer by the Contractor including payments made byEmployer way of deduction or set-off shall be made

(a) in the case of credit(s) under Sub-Clause(s) 70.2 and (insert number of anyother applicable Clause) in (insert name of currency/ies);

(b) in the case of liquidated damages under Clause 47, in (insert name ofcurrency/ies);

(c) in the case of reimbursement of any sum previously expended by theEmployer, in the currency in which the sum was expended by the Employer;

(d) in any other case, in such currency as may be agreed.

If the part payable in a particular currency of any sum payable to the Contractoris wholly qrpartly insufficient to satisfy by way of deduction or set-off a paymentdue to the Employer in that currency, in accordance with the provisions of thisSub-Clause, then the Employer may if he so desires make such deduction orset-off wholly or partly as the case may be from the balance of such sum payablein other currencies.

Where all payments are to be made in one currency the following Sub-Clause may beadded:

EXAMPLE SUB-CLAUSE (to be numbered, as appropriate)

Currencyof 60. The currency of account shall be the (insert name of currency) and all paymentsAccount made in accordance with the Contract shall be in (insert name of currency). Such

andPayments (insert name of currency), other than for local costs, shall be fully convertible.The percentage of such payments attributed to local costs shall be as stated in theAppendix to Tender.

Where place of payment is to be defined the following Sub-Clause may be added:

EXAMPLE SUB-CLAUSE (to be numbered, as appropriate)

Place of Payment 60. Payments to the Contractor by the Employer shall be made into a bank accountnominated by the Contractor in the country of the currency of payment. Wherepayment is to be made in more than one currency separate bank accounts shall benominated by the Contractor in the country of each currency and payments shallbe made by the Employer accordingly.

2 © FIDIC 1987

Page 251: 35824401 FIDIC Guide to the Use of FIDIC

Where provision is to be included for an advance payment the following Sub-Clause maybe added:

EXAMPLE SUB-CLAUSE (to be numbered, as appropriate)

Advance Payment 60. An advance payment of the amount stated in the Appendix to Tender shall,following the presentation by the Contractor to the Employer of an approvedperformance security in accordance with Sub-Clause 10.1 and a Guarantee interms approved by the Employer for the full value of the advance payment, becertified by the Engineer for payment to the Contractor. Such Guarantee shall beprogressively reduced by the amount repaid by the Contractor as indicated ininterim certificates of the Engineer issued in accordance with this Clause. Theadvance payment shall not be subject to retention. The advance payment shall berepaid by way of reduction in interim certificates commencing with the nextcertificate issued after the total certified value of the Permanent Works and anyother items in the Bill of Quantities (excluding the deduction of retention) exceeds(insert figure) per cent of the sum stated in the Letter ofAcceptance. The amountof the reduction in each interim certificate shall be one (insert fraction) of thedifference between the total value of the Permanent Works and any other items inthe Bill of Quantities (excluding the deduction of retention) due for certificationin such interim certificate and the said value in the last preceding interimcertjficate until the advance payment has been repaid in full. Provided that uponthe issue of a Taking-Over Certificate for the whole of the Works or upon thehappening of any of the events specified in Sub-Clause 63.1 or termination underClauses 65, 66 or 69, the whole of the balance then outstanding shall immediatelybecome due and payable by the Contractor to the Employer.

Clause 67Where it is decided that a settlement of dispute procedure, other than that of theInternational Chamber of Commerce (ICC), should be used the Clause may be varied.

Sub-Clause 67.3 — Arbitration

EXAMPLE

Following paragraph (b), delete the words 'shall be finally settled.. .InternationalChamber of Commerce' and substitute 'shall be finally settled under theUNCITRAL Arbitration Rules as administered by (insert name of administeringauthority)'.

Where alternatives to ICC are considered care should be taken to establish that thefavoured alternative is appropriate for the circumstances of the Contract and that thewording of Clause 67 is checked and amended as may be necessary to avoid anyambiguity with the alternative.

Clause 68

Sub-Clause 68.2 — Notice to Employer and Engineer

For the purposes of this Sub-Clause the respective addresses are:

(a) The Employer (insert address)

(b) The Engineer (insert address)

The addresses should be inserted when the documents are being prepared prior to invitingtenders.

Clause 69Sub-Clause 69.1 — Default of Employer

Where the Employer is a government it may be considered appropriate to vary theSub-Clause.

(c FIDIC 1987

Page 252: 35824401 FIDIC Guide to the Use of FIDIC

EXAMPLEDelete paragraph (c) and renumber paragraph (d) as (c).

Where the terms of the Sub-Clause, when read in conjunction with Sub-Clause 69.3, arein conflict with the law of the country the Sub-Clause may require to be varied.

EXAMPLE

Delete 'or' at the end of paragraph (c) and delete paragraph (d).

Clause 70Three alternative methods of dealing with price adjustment are given below.

The first alternative is suitable where a contract is of short duration and no priceadjustment is to be made:

Sub-Clause 70.1 — Increase or Decrease in Cost

EXAMPLEDelete the text of the Sub-Clause and substitute

Subject to Sub-Clause 70.2, the Contract Price shall not be subject to anyadjustment in respect of rise or fall in the cost of labour, materials or any othermatters affecting the cost of execution of the Contract.

Sub-Clause 70.2 — Subsequent Legislation

EXAMPLEDelete the words ',other than under Sub-Clause 70.1,'.

The second alternative is suitable where price adjustment is to be made by establishing thedifference in cost between the basic price and the current price of local labour andspecified materials:

Sub-Clause 70.1 — Increase or Decrease in Cost

EXAMPLEDelete the text of the Sub-Clause and substitute

Adjustments to the Contract Price shall be made in respect of rise or fall in thecost of local labour and specified materials as set oul in this Sub-Clause.

(a) Local Workmen(i) For the purpose of this Sub-Clause:"Local Workmen" means skilled, semi-skilled and unskilled workmen of alltrades engaged by the Contractor on the Site for the purpose of or inconnection with the Contract or engaged full time by the Contractor off theSite for the purpose of or in connection with the Contract (by way ofillustration but not limitation: workmen engaged full time in any office, store,workshop or quarry)."Basic Rate" means the applicable basic minimum wage rate prevailing on thedate 28 days prior to the latest date for submission of tenders by reason of anyNational or State Statute, Ordinance, Decree or other Law or any regulationsor bye-law of any local or other duly constituted authority, or in order toconform with practice amongst good employers generally in the area where theWorks are to be carried out."Current Rate" means the applicable basic minimum wage rate for LocalWorkmen prevailing on any date subsequent to the date 28 days prior to thelatest date set for submission of tenders by reason of any National or StateStatute, Ordinance, Decree or other Law or any regulation or bye-law of anylocal or other duly constituted authority, or in order to conform with practiceamongst good employers gen erally in the area where the works are to be carriedout.

© FIDIC 1987

Page 253: 35824401 FIDIC Guide to the Use of FIDIC

(ii) The adjustment to the Contract Price under the terms of this Sub-Clauseshall be calculated by multiplying the difference between the Basic and CurrentRates for Local workmen by:

(a) the number of all hours actually worked, and also(b) in respect of those hours worked at overtime rates, by the product of thenumber of said hours and the percentage addition required by the law to bepaid by the Contractor for overtime.

Such adjustment may be either an addition to or a deduction from the ContractPrice.(iii) No other adjustment of the Contract Price on account offluctuation in theremuneration of Local Workmen shall be made.

(b) Specified Materials(i) For the purpose of this Sub-Clause:"Specified Materials" means the materials stated in Appendix (insertreference) to Tender required on the Site for the execution and completion ofthe Works."Basic Prices" means the current prices for the specified materials prevailingon the date 28 days prior to the latest date for submission of tenders."Current Prices" means the current prices for the specified materials

prevailing at any date subsequent to the date 28 days prior to the latest date forsubmission of tenders.(ii) The adjustment to the Contract Price under the terms of this Sub-Clauseshall be calculated by applying the difference between the Basic and CurrentPrices to the quantity of the appropriate Specified Material which is deliveredto the Site during the period for which the particular Current Price is effective.Such adjustment may be either an addition to or a deduction from the ContractPrice.

(iii) The Con tractor shall use due diligence to ensure that excessive wastage ofthe Specified Materials shall not occur. A fly Specified Materials removedfromthe Site shall be clearly identified in the records required under paragraph (d)of this Sub-Clause.(iv) The provisions of this Sub-Clause shall apply to fuels used in Contractor'sEquipment engaged on the Site for the purposes of executing the Works1including vehicles owned by the Contractor (or hired by him under long termarrangements under which the Contractor is obligated to supply fuel) engagedin transporting any staff, labour, Contractor's Equipment, TemporaryWorks, Plant or materials to and from the Site. Such fuels shall be clearlyidentified in the records required under paragraph (d) of this Sub-Clause. Theprovisions of this Sub-Clause shall not apply to any fuels sold or supplied toany employee of the Contractor or to any person for use in any motor vehiclenot being used for the purposes of the Contract.(v) The Contractor shall at all times have regard to suitable markets and shall,whenever buying materials a variation in the cost of which would give rise to anadjustment of the Contract Price under this Sub-Clause, be diligent to buy orprocure the same at the most economical pri ces as are consistent with the dueperformance by the Contractor of his obligations under the Contract.If at any time there shall have been any lack of diligence, default or negligenceon the part of the Contractor, whether in observing the above requirements orotherwise, then, for the purposes of adjusting the Contract Price pursuanthereto, no account shall be taken of any increase in cost which may beattributable to such lack of diligence, default or negligence and the amount bywhich any cost would have been decreased but for such lack of diligence,default or negligence shall be deducted from the Contract Price.(vi) No other adjustment to the Contract Price on account offluctuation in thecost of materials shall be made.

© FIDIC 1987 253

Page 254: 35824401 FIDIC Guide to the Use of FIDIC

(c) Overheads and Profits Excluded

In determining the amount of any adjustment to the Contract Price pursuant tothis Sub-Clause no account shall be taken of any overheads or profits.(d) Notices and Records

The Contractor shallforth with, upon the happening of any event which may ormay be likely to give rise to adjustment of the Contract Price pursuant to thisSub-Clause, give notice thereof to the Engineer and the Contractor shall keepsuch books, accounts and other documents and records as are necessary to enableadjustment under this Sub-Clause to be made and shall, at the request of theEngineer, furnish any invoices, accounts, documents or records so kept and suchother information as the Engineer may require.(e) Adjustment after Date of CompletionAdjustment to the Contract Price, after the due date for completion of the wholeof the Works pursuant to Clause 43, or after the date of completion of the wholeof the Works certified pursuant to Clause 48, shall be made in accordance withCurrent Rates or Current Prices, as applicable, ruling at the due date forcompletion or the date stated in the Taking-Over Certificate, whichever is theearlier.

(f) Determination of Adjustment to Contract PriceThe amount of any adjust nient to the Contract Price pursuant to this Sub-Clauseshall be determined by the Engineer in accordance with the foregoing rules.

EXAMPLE APPENDIX TO TENDERfor use in conjunction with the second alternative.

SPECIFIED MATERIALS

MATERIAL UNIT PRICE ANDLOCA TION

TRANSPORTTO SITE

PRICE REMARKSDELIVEREDTO SITE

Bitumen

DieselPetrolLubricants

Cement

ReinforcingSteel

Explosives

NOTES:

1. The Contractor shall provide copies of quotations to substantiate all pricesincluded in the above table.2. All subsequent price substantiation shall be from the same source as originalunless otherwise agreed by the Engineer.3. The Contractor shall submit full explanation and provide substantiatingdocumentation for the mode of transport to Site he proposes. Only the proposeddocumented mode of transport shall qualify for price adjustment.

(Note: Materials stated in the Appendix to Tender should be those of whichsubstantial quantities are involved.)

'ç FIDIC 1987

Page 255: 35824401 FIDIC Guide to the Use of FIDIC

The third alternative is suitable where price adjustment is to be made through theapplication of indices in a formula:

Sub-Clause 70.1 — Increase or Decrease in Cost

EXAMPLEDelete the text of the Sub-Clause and substitute

(a) Adjustments to the Contract Price in respect of rise and fall in the cost oflabour and materials and other matters affecting the cost of execution of theWorks shall be calculated for each monthly statement pursuant to Sub-Clause60.1, the Statement at Completion pursuant to Sub-Clause 60.5 and the FinalStatement pursuant to Sub-Clause 60.6 in accordance with the provisions of thisSub-Clause if there shall be any changes in the following Index figures compiledby (insert details of source of indices) and published by (insert details ofpublication):-

(i) the Index of the cost of Labour in (insert name of country)

(ii) the Index of the cost of (insert other factor, as relevant)(iii) the Index of the cost of (insert other factor, as relevant)

(b) For the purpose of this Sub-Clause:(I) "Base Index Figure" shall mean the index figure applicable on the date 28days prior to the latest date for submission of tenders.

(ii) "Current Index Figure" shall mean the index figure applicable on the lastday of the period to which the particular statement relates.Provided that in respect of any work the value of which is included in any suchmonthly statement (or Statement at Completion or Final Statement) and whichwas executed after the due date (or extended date)for completion of the wholeof the Works, pursuant to Clause 43, the Current Index Figure shall be theindex figure applicable on the aforesaid due date (or extended date) forcompletion of the whole of the Works.

(iii) "Effective Value" shall be the difference between:(a) The amount which is due to the Contractor under the provisions ofSub-Clauses 60.2, 60.5 or 60.8 (before deducting retention and excludingrepayment of the advance payment) less any amounts for:work executed under nominated Subcon tractsmaterials and Plant on the Site, as referred to in Sub-Clause 60.1(c)

day works, variations or any other items based on actual cost or currentprices, and bonuses (if any)adjustments under Clause 70,and(b) The amount calculated in accordance with (b) (iii) (a) of this Sub-Clauseand included in the last preceding statement.

(c) The adjustment to the Contract Price shall be calculated by multiplying theEffective Value by a Price Fluctuation Factor which shall be the net sum of theproducts obtained by multiplying each of the proportions given in paragraph (d)of this Sub-Clause by the following fraction:

Current Index Figure — Based Index FigureBase Index Figure

calculated using the relevant index figures.

© FIDIC 1987

Page 256: 35824401 FIDIC Guide to the Use of FIDIC

(d) For the purpose of calculating the Price Fluctuation Factor, the proportionsreferred to in paragraph (c) of this Sub-Clause shall (irrespective of the actualconstituents of the work) be as follows:

0. in respect of labour (and supervision) costs subject to adjustment byreference to the Index referred to in (a) (i) of this Sub-Clause;

0. in respect of by reference to the Index referredto in (a) (ii) of this Sub-Clause;

0. in respect of by reference to me Index referredto in (a) (iii) of this Sub-Clause;

0. in respect of all other costs which shall not be subject to anyadjustment;

1.00 Total(e) Where the value of an Index is not known at the time of calculation, the latestavailable value shall be used and any adjustment necessary shall be made insubsequent monthly statements.

(Note: The number of indices included under (a) of this Sub-Clause may be varied, if it isdetermined that a different number of factors should be separately identified, and in suchcase (d) of this Sub-Clause must be altered to be consistent.)

Clause 72Sub-Clause 72.2 — Currency ProportionsWhere it is decided that the rate or rates of exchange shall be established from a sourceother than the Central Bank of the country, the Sub-Clause may be varied.

EXAMPLE

Delete the words from 'prevailing...' to the end of the sentence and substitute

'stated in the Appendix to Tender'.

Clause 73 onwardsWherecircumstances require, additional Clauses may be added.

EXAMPLE CLAUSES (to be numbered, starting with Clause 73, asappropriate).

Where the law applicable to the Contract does not cover bribery, the following exampleClause may be added.

Bribes .1 If the Contractor or any of his Sub-contractors, agents or servants offers to giveor agrees to offer or give to any person, any bribe, gift, gratuity or commission asan inducement or reward for doing or forbearing to do any action in relation tothe Contract or any other contract with the Employer or for showing orforbearing to show favour or disfavour to any person in relation to the Contractor any other contract with the Employer, then the Employer may enter upon theSite and the Works and terminate the employment of the Contractor and theprovisions of Clause 63 hereof shall apply as if such entry and termination hadbeen made pursuant to that Clause.

Where circumstances require that particular confidentiality is observed, the followingexample Clause may be added.

CE) FIDIC 1987

Page 257: 35824401 FIDIC Guide to the Use of FIDIC

Details to be .1 TheContractor shall treat the details of the Contract as private and confidential,Confidential save in so far as may be necessary for the purposes thereof, and shall not publish

or disclose the same or any particulars thereof in any trade or technical paper orelsewhere without the previous consent in writing of the Employer or theEngineer. If any dispute arises as to the necessity of any publication or disclosurefor the purpose of the Contract the same shall be referred to the decision of theEmployer whose award shall be final.

Where the Contract is being financed wholly or in part by an International FinancingInstitution whose Articles require a restriction on the use of the funds provided, thefollowing example Clause may be added.

Expenditure .1 The Contractor shall not make any expenditures for the purpose of the ContractRestricted in the territories of any country which is not a member of (insert name of

International Financing Institution) not shall he make any expenditure for goodsproduced in or services supplied from such territories.

Where the Contractor may be a joint venture, the following example Clause may beadded.

Jointand Several .1 If the Contractor is a joint venture of two or more persons, all such persons shallLiability be jointly and severally bound to the Employer for the fulfilment of the terms of

the Contract and shall designate one of such persons to act as leader withauthority to bind the joint venture. The composition or the constitution of thejoint venture shall not be altered without the prior consent of the Employer.

© FIDIC 1987 251-

Page 258: 35824401 FIDIC Guide to the Use of FIDIC

PARTIJ—CONDITIONS OF PARTICULAR APPLICATION

index Clause Page

Access to Data 11.2 237Accident Prevention Officer 34. 244Accidents, Reporting of 35. 246Additional Clauses 73. 255Adverse Physical Obstructions or Conditions 12.2 237Alcoholic Liquor 34. 245Arbitration 67. 251Arms and Ammunition 34. 245Bonus for Completion 47.3 247Boreholes and Exploratory Excavation 18.1 241Burial of the Dead 34.0 245Cash Flow Estimate to be Submitted 14.3 237Changes in Cost and Legislation 70. 252Conditions of Labour and Rates of Wages 34. 244Contract Agreement 9.1 236Contractor's Equipment, Insurance of 21.1 242Contractor's Representative, Language Ability of 15.2 241Currency of Account and Rates of Exchange 60. 250Currency Proportions 72.2 256

Data, Access to 11.2 237Default of Employer 69.1 251DisorderlyConduct 34. 245Documents, Order of Precedence 5.2 235Drugs 34. 245

Employer, Name and Address 1.1 235Employment of Local Personnel 16.4 241Employment of Persons in Service of Others 34. 244Engineer, Name and Address 1.1 235Engineer's Duties 2.1 235Environment, Protection of 19.1 241Epidemics 34. 245ExploratoryExcavation and Boreholes 18.1 241Extension of Defects Liability 49.5 248

Facilities for Other Contractors 31.2 244Festivals and Religious Customs 34. 245Foodstuffs, Supply of 34. 245

Health and Safety of Staff and Labour 34. 245Housing for Labour 34. 244

Inspection of Site 11.1 237Insurance of the Works and Contractor's Equipment 21.1 242Insurances Arranged by the Employer 21, 242

23 & 25 242,243Interpreter to be made Available 15.2 241

Labour, Conditions of and Rates of Wages 34. 244Labour, Health and Safety 34. 244Labour, Housing for 34. 244Labour, Rates of Wages and Conditions 34. 244Labour, Repatriation of 34. 244Labour, Special Provision for 34. 244Language, Ability of Contractor's Representative 15.2 241

Page 259: 35824401 FIDIC Guide to the Use of FIDIC

2q

Index Clause Page

Language, Ability of Superintending Staff 16.3 241Language, Ruling 5.1 235Language/s 5.1 235Law Applicable 5.1 235Local Personnel, Employment of 16.4 241Measures Against Insect and Pest Nuisance 34. 245No Remedying of Defects in Dredging Work after Completion 49.5 248No Responsibility for Cost of Searching of Dredging Work 50.2 249Notice to Employer and Engineer 68.2 251

Other Contractors, Facilities for 31.2 244Other Contractors, Opportunities for 31.1 244

Payments to Contractor 60. 249Payments to Employer 60. 249Performance, Example of Security Bond for 10.1 236Performance Guarantee, Example 10.1 236Performance Security 10.1 236Performance Security, Source of 10.4 237Physical Conditions or Obstructions, Adverse 12.2 237Place of Payment 60. 249Powerof Engineer to Fix Rates 52.2 249Prevention from Testing 48.5 247Programme to be Submitted 14.1 237Protection of the Environment 19.1 241

Rates of Exchange 60. 249Rates of Wages and Conditions of Labour 34. 244Records of Safety and Health 35. 246Religious Customs and Festivals 34. 245Repatriation of Labour 34. 244Reporting of Accidents 35. 246Revesting and Removal of Contractor's Equipment,

Temporary Works and Materials 54.5 249Royalties 28.2 243

Safety, Security and Protection of the Environment 19.1 241Security, Safety and Protection of the Environment 19.1 241Site, Inspection of 11.1 237Source of Performance Security 10.4 237Staff, Health and Safety of 34. 244Submission of Cash Flow Estimate 14.3 237Submission of Programme 14.1 237Superintending Staff, Language Ability of 16.3 241Supply of Foodstuffs 34. 245Supply of Water 34. 245Surety Bond for Performance, Example of 10.1 236Suspension of Work 40.1 246

Testing, Prevention from 48.5 247Time for Completion 43.1 246

Valuationof Variations 52.1 248Variations 51.1 248Variations Exceeding 15 per cent 52.3 249Vesting of Contractor's Equipment, Temporary Works and Materials 54.2 249

Water, Supply of 34. 245Working Hours 45.1 246Works, Insurance of 21.1 242

Page 260: 35824401 FIDIC Guide to the Use of FIDIC

EDITORIAL AMENDMENTS

Following publication in 1987 of the Fourth Edition of the Conditions ofContract for Works of Civil Engineering Construction, a number of editorialamendments were agreed by FIDIC. The amendments have been incorporatedduring reprinting and the list below clarifies the differences between this copy andthe original document.

Page 236 Clause 9. The words 'as stated in Sub-Clause 9.1 of Part 1 of these Conditions'have been added to the final line of the first paragraph.

Page 237 Sub-Clause 12.2. A comma has been moved from after the word 'words' toimmediately before the word 'other'. The word 'Site' has been capitalised.

Page 238 Example performance guarantee. A comma previously appeared between thewords 'and' and 'complete' in the third line of the paragraph beginning'Whereas'.The fifth line of the paragraph beginning 'Now the Condition . . .' previouslyread'. . . default by the Contract. .

Page 243 Sub-Clause 21.3. (b) (ii). A full stop has been inserted following '50'.

Page 244 Sub-Clause 34. Repatriation of Labour. A comma has been inserted between thewords 'country)' and 'shall'.

Page 245 Sub-Clause 34. Epidemics. The word 'Contractor' has been capitalised in the firstline.Sub-Clause 34. Alcoholic Liquor or Drugs. The word 'Contractor' has beencapitalised in the first line.

Page 246 Sub-Clause 40.3. This wa previously incorrectly listed as 40.2.

Page 248 Sub-Clause 49.5. The last line of the first paragraph previously read'. . . extendbeyond 730 days'.

Page 251 Sub-Clause 67.3. The word 'a' previously appeared before the bracket on thepenultimate line of the Example.

Line 21 Sub-Clause 70.2. A comma has been moved from after the word 'words' toimmediately before the word 'other'.