2.5_rivermoor energy_tourtelotte_epri/snl microgrid symposium
TRANSCRIPT
August 29, 2016
Overview for EPRI-Sandia Microgrid Symposium
City of Northampton Community Resiliency
2
22
Rivermoor Energy Page 3
Northampton Resiliency Planning Page 4 - 7
Appendix Page 8
National Grid Dorchester, Boston Page 9
Boston Water & Sewer Commission Page 10
Contact Information Page 11
Table of Contents
3
3
Energy development and investment company focused on large
municipal, commercial and utility-scale solar assets, resiliency, storage
and microgrids. Founded in 2008, Rivermoor was an “early entrant” to
the New England utility and commercial solar market.
Rivermoor Energy works with leading commercial, governmental and
utility clients with a focus on resiliency solutions, energy storage and
solar development.
Rivermoor Energy’s clients and partners include (partial list):
Rivermoor Energy: Summary
3
4
Northampton – Critical Assets and Duration
• 10 days chosen as planning
length for an emergency
outage
• 21 day outage would require
significant additional effort
integrating local business
community
• City Department Heads
developed consensus on
critical buildings list
• 42 critical assets evaluated
• Collaborative planning,
shared resources and
leadership are the foundation
for community resiliencymileskm
12
5
Outage Duration Creates Performance “Gaps”
Fuel Diversity and Redundancy
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
110.00%
1 2 3 5 7 10 14 21 30
RELIABILITY
DAYS
GENERATORRELIABILITY DPW
WTP
DPW Garage & HQ Fire Dept HQ Police Dept HQ
Buildings Served
# Critical assets 2 1 1
All protected ✓ ✓ ✓
Critical Load Served
Peak Critical Load - - -
Load Fully Supported ✗ ✓ ✓
Generator Sized ✗ ✓ ✓
Generator Reliability
Target Reliability 0.95 0.95 0.95
Generator Rel. (<10d) ✗ ✗ ✗
Generator Rel. (>10d) ✗ ✗ ✗
Fuel Duration
2-Day Outage ✓ ✓ ✓
5-Day Outage ✓ ✓ ✓
10-Day Outage ✗ ✗ ✗
21-Day Outage ✗ ✗ ✗
N-1 Protection
Protected ✗ ✗ ✗
Full Bypass ✗ ✗ ✗
6
Risks:
- Single onsite backup generator –
has failed in the past
- Redundancy & disaster recovery “gap”
Fuel Diversity Recommendations:
- Solar PV, Battery storage and energy
efficiency
- Genset testing & maintenance
- Mobile genset solution “pool”: Pin &
Sleeve set up would be installed
- Benefits: Cost savings, on-site plus
“mobile pool” redundancy, emergency fuel
savings, and fuel diversity
Fire Department HQ: Dispatch, EMT & 911 ServicesCase Study for Redundancy & Fuel Diversity
Boston Water Commission Solar
Rivermoor Energy, 2010
7
Hospital, Red Cross Shelter & City Operations Center
G
Tank
ATS
Utility Generator
Non-critical loads
Critical loads
UPS
Backup Generator A
Fuel Storage Tank
Backup Power System A
Critical Facility A
BK-AG
G
Tank
ATS
Utility Generator
Non-critical loads
Critical loads
UPS
Backup Generator B
Fuel Storage Tank
Backup Power System B
Critical Facility B
NO
NO
BK-AT
BK-BGBK-BT
Figure: Typical campus microgrid
Source: Sandia Nat’l Labs
1. Integrate Solar Assets,
Energy Storage and CHP
2. Campus Microgrid
Leverage hospital’s CHP,
existing and new solar & new
energy storage assets
Campus microgrid will provide
resiliency improvement for long
outages plus cost savings on
utility energy & demand charges
CHP “advantage” for two +
facilities rather than one
8
88
Appendix
9
Rivermoor Energy developed this solar
asset for the benefit of property owner
National Grid in a development-
construction partnership with Fischbach &
Moore electrical contractors.
Largest solar asset in Boston.
1.2 megawatts on a seven acre
contaminated “brownfield” in front of
landmark multi-colored LNG tanks on
Boston’s Route 93.
Provides clean, local power directly to the
utility grid. Owned by National Grid and
connected to the utility grid by
Eversource.
$7 + million asset, largest solar asset in
City of Boston.
Case Study: National Grid – Boston
10
10
Rivermoor Energy developed
this solar asset, working
successfully with Boston Water,
local utility NSTAR (Eversource)
and our design and construction
team of Fischbach & Moore to
develop the largest solar roof in
downtown Boston.
First solar asset to successfully
utilize Massachusetts SREC
incentives.
Development, engineering and
construction completed in 2010.
$1.25 million asset
Case Study: Boston Water Commission
10
11
1111
John H. Tourtelotte
Rivermoor Energy
Riverside Center
275 Grove Street, Suite 2-400
Newton, MA 02466
617-213-8677 (phone)
www.rivermoorenergy.com
Contact Information