205610 managing p6 from an owners schedule
TRANSCRIPT
Managing the P6
Schedule From An
Owner’s Perspective
April 7-10, 2013
Raquel Speers Shohet, PSP
Vice President
Hill International
Speaker Biography
Degree: BS – Civil Engineering
Years of Controls Experience: 22EPC
Consultant
50% Public and Private Owners
50% Contractors
Built and managed 350+ schedules
Something you do not know about me: I was
goalkeeper for University of California, Irvine
Women‟s Soccer Team
Conceptual Presentation Topics
Limitations/ Capabilities of P6
Accessing Current Environment
Managing schedule progress
Incorporating varied contractor schedules
into a single enterprise system
Performing schedule review/analysis
Reporting/ Tracking critical events
Potential EV analysis
Managing owner‟s long-term goals/budget
Challenges for Enterprise Software
Rollout
Understanding the Technology
Getting past the Software Sales Pitch
Re-thinking Processes
Standardizing the Processes
Training New Processes
Executive Buy-in
Commitment
Making the Commitment
Define the Processes Scheduling Specification at Implementation
Scheduling Appendix (Project Value $1M, $5-10M, $10M+)
Schedule Department Roles and Responsibilities (SOP, “A” Team)
IT Discovery (Hardware, License Costs, Hosting)
Design the ProcessesBest Practices
System Implementation
Pilot Project
Develop the ProcessesProcess Flow Charts (Baselines, Monthly Updates, Reviews)
Templates
Reporting
Deliver the ProcessesLive Environment
Training
Advanced ConsiderationsSTANDARDIZATION IS KEY!!!!!!!!!!!!!!!!!!!!
Minimum Scheduling
Requirements
Scheduler Qualification
Requirements
Scheduling Software
Requirements
Schedule Acceptance
Critical Path Method
Work Breakdown Structure
(WBS)
Float
Calendars
Durations
Relationships
Contingency Time
Change of Contract Time
Submittal, Procurement,
Delivery Activities
Testing, Training, & Startup
Activities
Schedule Specification Considerations
State DOT Specification
1.6 Baseline Construction Schedule
C. Schedule Submission
Current BPM Considerations
Current BPM Considerations
Process Flow/
Information Management Considerations
OWNER 1 Owner 1 Master Schedule
Added Summaries:
Cost, Critical Path, Schedule Impacts, Change Order, Contingency and Start up Plans Summaries
Live Environment/
Advanced Considerations
o System Integration of Oracle Project Management/ Contract Management or
PMWeb Softwares
o QC Items
o RFIs
o Submittals
o Contractor Claims
o Web Application
o CIP Long Term Budgets/ Goals
Advanced Considerations
Each „portlet‟ can be resized or maximized based on user preference.
This PM dashboard consists of seven „portlets‟:
The Project Gantt Chart Project Statistics Project Health
Schedule Performance Index Performance Project Notebooks
Earned Value Performance
Review Presentation Topics
Limitations/ Capabilities of P6
Accessing Current Environment
Managing schedule progress
Incorporating varied contractor schedules
into a single enterprise system
Performing schedule review/analysis
Reporting/ Tracking critical events
Potential EV analysis
Managing owner‟s long-term goals/budget
Conclusion
Understand value of an Enterprise versus Stand-alone
environment
Identify strengths and weaknesses of current processes Specifications
Data Management
Setup Standardized Structures EPS, WBS, Codes, Global v Project
Establish Key Work Flow Processes
Maintain Consistency Schedule Review
Schedule Management
Schedule Reporting
Utilize tools provided to optimize the schedule for your program
Questions and Answers
Hoping that you can use these implementation
and execution lessons learned outlined to
efficiently manage project schedules using
Primavera P6™
Thank you