Page 1: 2011-08-18 AEM Technical Update

Technical Update – August 18th, 2011

Agnico-Eagle Mines Limited

Page 2: 2011-08-18 AEM Technical Update

2

Forward Looking Statements

The information in this document has been prepared as at August 18, 2011. Certain statements contained in this document constitute “forward-looking statements” within the meaning of the United States Private Securities Litigation Reform Act of 1995 and forward looking information under the provisions of Canadian provincial securities laws. When used in this document, the words “anticipate”, “expect”, “estimate”, “forecast”, “will”, “planned”, and similar expressions are intended to identify forward-looking statements or information.

Such statements include without limitation: statements regarding timing and amounts of capital expenditures and other assumptions; estimates of future reserves, resources, mineral production, optimization efforts and sales; estimates of mine life; estimates of future internal rates of return, mining costs, cash costs, minesite costs and other expenses; estimates of future capital expenditures and other cash needs, and expectations as to the funding thereof; statements and information as to the projected development of certain ore deposits, including estimates of exploration, development and production and other capital costs, and estimates of the timing of such exploration, development and production or decisions with respect to such exploration, development and production; estimates of reserves and resources, and statements and information regarding anticipated future exploration; the anticipated timing of events with respect to the Company's minesites and statements and information regarding the sufficiency of the Company's cash resources. Such statements and information reflect the Company's views as at the date of this document and are subject to certain risks, uncertainties and assumptions, and undue reliance should not be placed on such statements and information. Many factors, known and unknown could cause the actual results to be materially different from those expressed or implied by such forward looking statements and information. Such risks include, but are not limited to: the volatility of prices of gold and other metals; uncertainty of mineral reserves, mineral resources, mineral grades and mineral recovery estimates; uncertainty of future production, capital expenditures, and other costs; currency fluctuations; financing of additional capital requirements; cost of exploration and development programs; mining risks; community protests; risks associated with foreign operations; governmental and environmental regulation; the volatility of the Company's stock price; and risks associated with the Company's byproduct metal derivative strategies. For a more detailed discussion of such risks and other factors that may affect the Company’s ability to achieve the expectations set forth in the forward-looking statements contained in this document, see the Company's Annual Report on Form 20-F for the year ended December 31, 2010, as well as the Company's other filings with the Canadian Securities Administrators and the U.S. Securities and Exchange Commission. The Company does not intend, and does not assume any obligation, to update these forward-looking statements and information. Marc Legault, a Qualified Person and the Company’s Vice-President, Project Development, reviewed the technical information disclosed herein. For a detailed breakdown of the Company’s reserve and resource position see the February 16, 2011 press release on the Company’s website. That press release also lists the Qualified Persons for each project.

Page 3: 2011-08-18 AEM Technical Update

3

Note To Investors

This document presents estimates of future "total cash cost per ounce" and "minesite cost per tonne" that are not recognized measures under United States generally accepted accounting principles ("US GAAP"). This data may not be comparable to data presented by other gold producers. These future estimates are based upon the total cash costs per ounce and minesite costs per tonne that the Company expects to incur to mine gold at the applicable projects and do not include production costs attributable to accretion expense and other asset retirement costs, which will vary over time as each project is developed and mined. It is therefore not practicable to reconcile these forward-looking non-GAAP financial measures to the most comparable GAAP measure. A reconciliation of the Company's total cash cost per ounce and minesite cost per tonne to the most comparable financial measures calculated and presented in accordance with US GAAP for the Company's historical results of operations is set forth in the notes to the financial statements included in the Company's Annual Information Form and Annual Report on Form 20-F, for the year ended December 31, 2010, as well as the Company's other filings with the Canadian Securities Administrators and the SEC.

Regarding The Use Of Non-gaap Financial Measures

LaRonde Goldex Kittila Lapa Pinos Altos Meadowbank

3

Page 4: 2011-08-18 AEM Technical Update

4

Highlights

■ LaRonde Deep – development project on time and budget

■ Goldex - Record tonnage despite soil subsidence issues – significant exploration results at depth

■ Lapa – Lower grade offset by increased tonnage

■ Meadowbank – plant exceeding tonnage expectations, focused on minimizing dilution

■ Kittila – Production resumed at Suuri Open Pit and excellent exploration results at depth on Rimpi Zone – Solid mill performance, costs improving

■ Pinos Altos – Record quarterly production of 51,067 ounces at a cash cost of $299 per ounce.

■ Meliadine – excellent exploration results – underground bulk sample started; 10 drills on site

Page 5: 2011-08-18 AEM Technical Update

5

Challenges

■Mining conditions at LaRonde and Lapa – narrow stopes

■Subsidence at Goldex with water inflow

■Equipment availability and high costs at Meadowbank

■High costs at Kittila

Page 6: 2011-08-18 AEM Technical Update

LaRonde

Page 7: 2011-08-18 AEM Technical Update

7

LaRonde YTD Highlights

■ Gold production – 64,000 oz

■ Cost per tonne - $85 vs. budget of $82

■ Cash costs $95/oz

■Mill throughput 6,543 tpd

Page 8: 2011-08-18 AEM Technical Update

8

LaRonde Extension – Project Update

■ Load out construction almost completed on Level 282

■ Crusher construction – on schedule for Q4

■ First production scheduled for November

■ On schedule – on budget

■ LOM at 6,000 tpd – evaluating possibility of 7,000 tpd

Page 9: 2011-08-18 AEM Technical Update

9

LaRonde Extension – Production

■ Production Stopes ■ Pyramid from 269 - Q2 2012 ■ Pyramid from 293 – Q3 2013

■ Production Rate Ramp-Up below

the 245 level ■ 2011 => 1 200 tpd (Q-4 2011) ■ 2012 => 2 000 tpd ■ 2013 => 4 200 tpd ■ 2014 => 6 000 tpd

278 282

257

215

269

293

311

194

245

Page 10: 2011-08-18 AEM Technical Update

10

LaRonde Extension - Crusher

Crusher (July 2011)

General Arrangement

TelSmith Crusher 48 x 52

Capacity >650 t/hr

Excavation completed in April 2011

Commissioning Q4 2011

Transfer Conveyor (July 2011)

Page 11: 2011-08-18 AEM Technical Update

Goldex

Page 12: 2011-08-18 AEM Technical Update

12

Goldex Highlights

■ Grade in line with forecast – over 13 million tonnes of broken ore in stope

■ Record milled tonnage in May-June following addition of 6th Manitou pump, recrushing of surface stock pile – will be maintained for remainder of year; YTD 8,200 tpd

■ Operating costs under budget, additional capital to manage water inflow and soil subsidence

■ Surface overburden subsidence – remediation program underway

■ Exploration results at depth could significantly increase mine life ■ Resource being calculated

■ YTD gold production – 80,500oz; cost per tonne - C$22, on budget; cash costs $408/oz

Page 13: 2011-08-18 AEM Technical Update

13

Goldex

Aug 15, 2011 Q3 QTD H1/11 YTD

Daily throughput (tpd) 8,485 8,204

Grade (g/t) 1.85 1.82

Mill recoveries (%) 94.6% 92.8%

Q3 QTD Performance Unaffected By Subsidence Issues

Page 14: 2011-08-18 AEM Technical Update

14

Overburden subsidence

5m of overburden settling over center of GEZ

Cement injection program ongoing, expected to be completed by year end

Page 15: 2011-08-18 AEM Technical Update

15

Level 38

Stope outline

Vertical Cross Section

Shear zone

Diorite

Komatiite

Page 16: 2011-08-18 AEM Technical Update

16

Drilling – Level 38

Infiltration Zone – Eastern Mining Block

Diamond drilling and proposed grouting program

Diamond drill holes

Infiltration Zone

Page 17: 2011-08-18 AEM Technical Update

17

Remediation of overburden subsidence

■ Shear zones have been characterized and defined

■ Reduce water inflow into the mine ■ Grouting from surface and underground

■ Stabilize the water table ■ Inject mine inflow back into the water table ■ Water table defined

■ Increase underground pumping capacity to secure the mine ■ Additional capacity installed in excess of inflow

■ Initial results encouraging ■ Reduction in inflow noted with increased surface injection ■ Water table rising in eastern section ■ Grouting to continue westward until end of year ■ $6.0 million of total $19 million has been spent

Page 18: 2011-08-18 AEM Technical Update

18

2011 Exploration Budget Actual Exploration (January-June 2011)

$8.4 million $3.1 million 70,200 metres DDH 26,482 metres DDH

D zone Au

(M oz) Tonnes (000s)

Gold Grade (g/t)

Inferred resources

0.75 14,361 1.62

3.02 g/t Au / 117.0 m

1.84 g/t Au / 112.5 m

1.48 g/t Au / 76.5 m

1.70 g/t Au / 69.0 m

1.50 g/t Au / 120.0 m incl. 2.40 g/t Au / 61.5 m

2.47 g/t Au / 240.0 m

2.17 g/t Au / 192.0 m

1.70 g/t Au / 192.0 m

2011 Exploration Program $8.4 million budgeted D Zone

50 to 100 m thick

Traced 350 m wide and 500+ m depth (open in all directions)

Initial inferred resource 0.75 Moz

Exploration ramp initiated

Resource conversion drilling underway

Resource expansion drilling successful at depth

Grade and thickness higher at depth

Initial mining study by end of 2011

Potential to add to reserves in 2013

Goldex - D Zone Growing at Depth

Page 19: 2011-08-18 AEM Technical Update

Lapa

Page 20: 2011-08-18 AEM Technical Update

20

Lapa Update

■ Steady state performance exceeding tonnes hoisted and tonnes milled

■ Steady state performance for development – targets exceeded despite difficult mining conditions

■ Cost per tonne below budget - C$110

■ Unit development cost below budget

■ Overall excellent performance: YTD gold production 55,500oz

Page 21: 2011-08-18 AEM Technical Update

Meadowbank

Page 22: 2011-08-18 AEM Technical Update

22

Meadowbank Update

■ Secondary crushing plant running according to plan

■ Significant improvements in mining performance although dilution still an issue

■ Declining costs per tonne over the past quarter – should see continued improvement

■ Operating staff positions are being filled

Turn around in progress but more work to do

August 15th Mill Sheet Day Month CRUSHING

Ore Tonnage (dmt) 8756 128866 Utilisation (%) 55.56

FEED Tonnage 10737 136319 Head Grade - Au (g/t) 2.58 2.69

GRINDING

Availability (%) 100.00 90.42 GRAVITY

Recovery (%) 14.27% 8.99% LEACH / CIP

Gold Leach / C.I.P. Recovery (%) 79.86% 84.96%

SUMMARY Gravity Gold Recovery (oz) 127 1061 CIP Gold Recovery (oz.) 710 10025 Mill Gold Recovery (%) 94.13% 93.95% Gold Production (oz) 837 11086

Page 23: 2011-08-18 AEM Technical Update

23

Q3 QTD Throughput Significantly Above H1 Levels

Aug 15, 2011 Q3 QTD H1/11 YTD

Daily throughput (tpd) 9,143 7,160

Grade (g/t) 2.80 3.11

Mill recoveries (%) 94.0% 93.7%

Meadowbank

Page 24: 2011-08-18 AEM Technical Update

24

Higher mill tonnage after secondary crusher start up

50 000

100 000

150 000

200 000

250 000

300 000

Mill

Tonn

es (t

/mon

th)

Meadowbank Mill_Monthly Tonnes

Realized

After Secondary Crusher Before Secondary Crusher

•Design capacity attained in August •More stable operation downstream

Page 25: 2011-08-18 AEM Technical Update

25

Mine Production

0

10 000

20 000

30 000

40 000

50 000

60 000

70 000

80 000

90 000

100 000

110 000

120 000

1-Ja

n-10

1-Fe

b-10

1-M

ar-1

0

1-A

pr-1

0

1-M

ay-1

0

1-Ju

n-10

1-Ju

l-10

1-A

ug-1

0

1-S

ep-1

0

1-O

ct-1

0

1-N

ov-1

0

1-D

ec-1

0

1-Ja

n-11

1-Fe

b-11

1-M

ar-1

1

1-A

pr-1

1

1-M

ay-1

1

1-Ju

n-11

1-Ju

l-11

1-A

ug-1

1

1-S

ep-1

1

1-O

ct-1

1

1-N

ov-1

1

1-D

ec-1

1

Tm/d

ay

Meadowbank Mine Performances Tonnes moved per day

Realized Realized Forecast Budget

2010 2011

Page 26: 2011-08-18 AEM Technical Update

26

Blast Movement Control – Improving Dilution

Agnico-Eagle Mines Limited

■ Staggered pattern has been successfully implemented in South Portage

■ Blast design is now optimized so that the movement of the muck is becoming more predictable

■ Improvements have been made to the QA/QC process, resulting in more consistent drilling and loading operations

■ Floor quality & fragmentation has improved while keeping movement under control

■ Groundwater in South Portage is still locally hindering drilling and blasting operations; a variance was obtained from the Mine Inspector to allow immediate loading of the holes as they are drilled, a practice that reduces the impact of water in the holes

Page 27: 2011-08-18 AEM Technical Update

27

Blast Movement Control – Improving Dilution

Agnico-Eagle Mines Limited

■ Dilution in flatter zones averaged 30% to 40% earlier this year – now approximately 20%

■ Objective is 12% - 15% - reserve model contains an average of 12%

■ Currently mining narrower zones in North Portage

■ Expansion into South Portage and Goose pits will provide more flexibility and higher grades

Goose Island Pit

Portage Pit

North Pit

South Pit

Page 28: 2011-08-18 AEM Technical Update

28

Blast movement monitoring

Agnico-Eagle Mines Limited

Significant reduction in blast displacement

Page 29: 2011-08-18 AEM Technical Update

29

Cost control initiatives

Agnico-Eagle Mines Limited

■ Improve equipment availability – utilization

■ Improved facilities, filling vacant positions ■ Prepare for coming winter – complete modifications

■ Higher, consistent mill throughput

■ Reduce rehandling of ore

■ Train local employees – reduce logistics costs

■ Reduce reliance on contract labour

■ Reduce fuel consumption, stockpile lower cost fuel, reduce energy consumption

■ Optimize mill (i.e. mill liners, reagents)

Portage Pit

North Pit

South Pit

Page 30: 2011-08-18 AEM Technical Update

30

Mine Manager’s Comment – Aug 15th, 2011

“Wow nice week team!!

Tonnes moved average of 87 851 t/d

More consistent direction of the blasts at an average of 5.2 meters displacement (down from 13 metres)

Mill tonnage average of 427 t/h (10,250 tpd)

Coffer dam construction ahead of schedule

We are going in the right direction! Keep it up and stay on the top of the wave

Thanks, Merci, Matna

Dominique”

Page 31: 2011-08-18 AEM Technical Update

Kittila

Page 32: 2011-08-18 AEM Technical Update

32

Kittila Highlights – H1 2011

■ Unplanned shutdowns related to scaling problems in the Autoclave – mill availability 77%

■ Total mill throughput of 233,121 dmt or 90% of design capacity despite mill availability

■ Good underground development and waste stripping performance

■ Underground ore production on plan

■ High unit costs per tonne and per ounce

■ Contractor reduction in progress

■ Excellent exploration results on Rimpi

32

Gold Brick no 400

Page 33: 2011-08-18 AEM Technical Update

33

Q3 QTD Throughput Significantly Above H1 Levels

Aug 15, 2011 Q3 QTD H1/11 YTD

Daily throughput (tpd) 3,187 2,734

Grade (g/t) 4.60 5.25

Mill recoveries (%) 84.7% 84.5%

Kittila

Page 34: 2011-08-18 AEM Technical Update

34

Kittila Open Pit

■ Ore production resumed in the Suuri pit after 2 month stop

■ Eastern wall rock stability issues addressed and Suuri ore production re-started in early June

■ Ore production from Roura good, cost adjustment for stripping

■ Ore stockpile > 300,000 tonnes

34

Roura pit

Suuri pit

Page 35: 2011-08-18 AEM Technical Update

35

Kittila Underground

■ UG development advance very good at 111% of budget – new lateral development record at 610 m in May

■ Good UG ore production -- 102% of budget ■ 350 m Service Level complete – UG

warehouse, cafeteria and shops functional

■ Cost reduction opportunities have been identified and action plans instigated ■ Contractor reduction ■ Control overtime ■ Renegotiate reagent, explosive contracts ■ Reduce company housing

35

Page 36: 2011-08-18 AEM Technical Update

36

Kittila – Growing Reserves & Resources

2011 Exploration Budget Actual Exploration (January-June 2011)

$15.6 million $7.0 million 56,200 metres DDH 28,415 metres DDH

7.10 g/t Au / 21.0 m

9.93 g/t Au / 6.2 m

5.98 g/t Au / 7.8 m

9.32 g/t Au / 11.2 m

9.50 g/t Au / 6.0 m

2011 Exploration Program $15.6 million budgeted Suuri – Roura Deep exploration ramp initiated

Resource expansion and resource to reserve conversion drilling underway

Production expansion feasibility expected in Q4, 2011

Suuri – Roura Deep exploration shaft project under evaluation

Exploration success Rimpi and Suuri - Roura Deep

Potential to enhance economics of Kittila expansion and shaft projects

Page 37: 2011-08-18 AEM Technical Update

Pinos Altos

Page 38: 2011-08-18 AEM Technical Update

38

Pinos Altos H1 Highlights

■ YTD production 99,000oz at, $28/t – significantly below budget

■ Mascota continued ramp up better than expected

38

-

10,000

20,000

30,000

40,000

50,000

60,000

Q2 2010 Q3 2010 Q4 2010 Q1 2011 Q2 2011

Mexico Division Au Ounces Production (Oz)

Actual

Page 39: 2011-08-18 AEM Technical Update

39

UG Ore Production

■ 3,000 TPD ore production was reached in June

■ Total cost per tonne was $34.96 vs. $32.47 budget

■ Q2 Meters of lateral development 1,476 m vs.1,457 m budget & unit cost of US$2,210 vs. US$2,587 budget

39

0

10

20

30

40

50

60

70

80

90

100

-

10

20

30

40

50

60

70

80

90

100

Oct2010

Nov2010

Dec2010

Jan2011

Feb2011

Mar2011

Apr2011

May2011

June2011

Tonnes USD/tonne

Ore Production & Cost per tonne performance

tonn

es

US

D/to

nne

Page 40: 2011-08-18 AEM Technical Update

40

Pinos Altos Open Pit

■ Total Open pit ore production was 783,948 tonnes at 1.065 g/t Au vs. 671,531 at 1.192 g/t. planned

■ Total Open pit unit cost was $1.33 per tonne vs. $1.29 per tonne planned

40

Page 41: 2011-08-18 AEM Technical Update

41

Mascota Operation

■ Ramp up production

■ Heap Leach Au-Oz Production 9,449 Oz vs. 6,462 Oz budget. (payable gold)

41

-

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

4,500

Jan Feb Mar Apr May Jun

Au Ounces Production 2011 (Oz)

Actual

-

20

40

60

80

100

120

140

160

180

Jan Feb Mar Apr May Jun

Ore Placed 2011 (000 tonnes)

tonnes placed

Page 42: 2011-08-18 AEM Technical Update

Exploration Upside

Page 43: 2011-08-18 AEM Technical Update

43

Meliadine Exploration Upside - 80km Strike Length

Pump Au (Moz)

Tonnes ('000)

Au (g/t)

Inferred Resources 0.10 495 6.29

Tiriganiaq Au (Moz)

Tonnes ('000)

Au (g/t)

Probable Reserves 2.60 9,467 8.54 Indicated Resources 0.81 5,407 4.66 Inferred Resources 1.91 7,883 7.55

Discovery Au (Moz)

Tonnes ('000)

Au (g/t)

Indicated Resources 0.32 1,323 7.41 Inferred Resources 0.14 498 8.97

Wolf Au (Moz)

Tonnes ('000)

Au (g/t)

Indicated Resources 0.02 183 3.79 Inferred Resources 0.16 947 5.24

F zone Au (Moz)

Tonnes ('000)

Au (g/t)

Indicated Resources 0.33 1,895 5.39 Inferred Resources 0.18 1,010 5.62

Wesmeg Au (Moz)

Tonnes ('000)

Au (g/t)

Inferred Resources 0.14 1,000 4.45

2011 Exploration Budget Actual Exploration (January-June 2011)

$64.8 million $11.7 million 90,000 metres DDH 44,173 metres DDH

Discovery

F Zone

Tiriganiaq Wesmeg Wolf

Pump

2011 Exploration budget $64.8 million for drilling, feasibility and camp Resource to reserve conversion and expansion

underway at Tiriganiaq /Wesmeg

Permitting and preparations for access road construction

Wesmeg exploration success should increase resources

Aggressive regional exploration initiated (plans to build new exploration base at Discovery)

6,000 -10,000 tpd feasibility expected 2013 10 km

Page 44: 2011-08-18 AEM Technical Update

44

Meliadine Exploration - Tiriganiaq

Tiriganiaq Longitudinal Section

Largest deposit at Meliadine Resource expansion and resource to

reserve conversion drilling underway Underground bulk sampling initiated

Ramp project to test for deeper extensions Potential to add reserves and resources

at Tiriganiaq in 2011

8.62 g/t Au / 19.3 m

10.9 g/t Au / 7.0 m

5.33 g/t Au / 4.2 m

15.14 g/t Au / 5.8 m 16.64 g/t Au / 7.4 m

7.98 g/t Au / 39.3 m

Tiriganiaq Au (Moz)

Tonnes ('000)

Au (g/t)

Probable Reserves 2.60 9,467 8.54 Indicated Resources 0.81 5,407 4.66 Inferred Resources 1.91 7,883 7.55

Page 45: 2011-08-18 AEM Technical Update

45

Tiriganiaq Schematic Cross Section

2011 Exploration Program at Tiriganiaq

Underground bulk sampling and grade confirmation drilling underway to refine feasibility resource model

Resource to reserve conversion drilling

Resource expansion drilling

Exploration ramp proposed to follow up and extend Tiriganiaq and Wesmeg (both wide open at depth)

Bulk Sample Area

Page 46: 2011-08-18 AEM Technical Update

46

Wesmeg – The most recent discovery at Meliadine

Wesmeg Longitudinal Section

Wesmeg zone Au

(M oz) Tonnes (000s)

Gold Grade (g/t)

Inferred resources

0.14 1,000 4.45

6.87 g/t Au / 4.7 m

7.02 g/t Au / 10.6 m 4.78 g/t Au / 13.5 m

5.72 g/t Au / 9.4 m

8.17 g/t Au / 5.4 m

7.02 g/t Au / 10.6 m

Initial resource in Dec’ 2010 (Wesmeg North only)

Exploration success extends Wesmeg North open pit potential more than 2.1 kilometres; Underground potential also developing

New Wesmeg South trend currently traced for 600 metres and extending at depth below 160 metres

Potential to significantly expand Wesmeg resource in 2011 and enhance feasibility

Page 47: 2011-08-18 AEM Technical Update

Appendix

Page 48: 2011-08-18 AEM Technical Update

48

Gold and Silver Reserves and Resources December 31, 2010

Tonnes (000’s)

Gold (g/t)

Gold (ounces)

(000’s)

Proven 24,869 2.29 1,832

Probable 160,944 3.76 19,467

Total Reserves 185,813 3.57 21,299

Indicated 95,135 2.10 6,437

Inferred 118,111 2.59 9,839

Tonnes (000’s)

Silver (g/t)*

Silver (ounces)

(000’s)

Proven 7,702 54.75 13,558

Probable 71,190 48.09 110,061

Total Reserves 78,892 48.74 123,620

Indicated 32,554 21.90 22,918

Inferred 37,183 19.98 23,883

*Calculated grades

Page 49: 2011-08-18 AEM Technical Update

49

Copper, Zinc and Lead Reserves and Resources

*Calculated grades

Tonnes (000’s)

Copper (%)

Copper (tonnes)

Proven 4,838 0.26 12,433

Probable 29,892 0.28 82,360

Total Reserves 34,730 0.27 94,793

Indicated 6,933 0.12 8,462

Inferred 11,526 0.27 30,820

Tonnes (000’s)

Zinc (%)

Zinc (tonnes)

Proven 4,838 2.78 134,651

Probable 29,892 0.90 269,581

Total Reserves 34,730 1.16 404,232

Indicated 6,933 1.36 94,457

Inferred 11,526 0.48 55,556

Tonnes (000’s)

Lead (%)

Lead (tonnes)

Proven 4,838 0.32 15,572

Probable 29,892 0.07 19,463

Total Reserves 34,730 0.10 35,035

Indicated 6,933 0.13 8,942

Inferred 11,526 0.05 5,463

December 31, 2010

Page 50: 2011-08-18 AEM Technical Update

A solid financial position, low-cost structure, well-funded growth projects in regions of low

political risk, and a focused, consistent strategy put Agnico-Eagle in a strong position to continue

creating exceptional per share value.

Executive and Registered Office: 145 King Street East, Suite 400

Toronto, Ontario, Canada, M5C 2Y7 Tel: 416-947-1212 Toll-Free: 888-822-6714 Fax: 416-367-4681

agnico-eagle.com

Sean Boyd Vice-Chairman and

Chief Executive Officer

Ebe Scherkus President and

Chief Operating Officer