2010 Cement Concrete Pavement Forecast CEMENT CONCRETE PAVEMENT CY TO BE PLACED IN 2010
STATEWIDE EASTERN NORTH CENTRAL NORTHWEST OLYMPIC SOUTH CENTRAL
#REF! 6,420 3,700 #REF! 13,910 #REF!
CEMENT CONCRETE PAVEMENT CY TO BE AWARDED STATEWIDE EASTERN NORTH CENTRAL NORTHWEST OLYMPIC SOUTH CENTRAL 10/1/2009 THRU 9/30/2010 92,068 6,420 3,700 8,092 0 73,856
Project Name Region SR Contract Number Award Date Awarded
CY 2008 CY
Cement Concrete Pavement
NEW PROJECTS (awarded 10-1-2007 thru 9-30-2008) I90 Spokane Port of Entry Weigh Station Eastern 90 P:609030B Dec-09 4,120 4,120 SR 2 - Euclid Avenue to Francis Ave - Paving & Safety Restoration Eastern 2 P:600228M Jun-10 2,300 2,300 Hyak To Snowshed Vic Phase 1B - Add Lanes and Bridges South Central 90 509090B Feb-10 43299 0 Lake Easton Vic to Big Creek Br Vic EB - Replace/Rehab Concrete & Safety South Central 90 509012L Mar-10 19,825 5,893 Valley Mall Blvd I/C - Rebuild I/C South Central 82 508201O Nov-09 7,245 7,245 Selah Vic - Re-Route Highway South Central 823 582301S Dec-09 1,435 1,435 US 12/SR 124 Intersection - Build Interchange South Central 12 501212I Jun-10 2,052 2,052 I-5/Reverse Express Lane to/from SR 522 Northwest 5 100525A Jan-10 25 25 I-5 Interchange - Josh Wilson Rd Northwest 11 101100F Dec-09 2,610 2,610 E Church Mountain Rd Realighment - CED Northwest 542 154229G Jan-10 120 120 Gallup Creek Bridge Replacement - CED Northwest 542 154229G Feb-10 230 230 I-5 to SR 169 Stage 2 Northwest 405 7624 Jul-09 145 15 S. Holgate Street to S. King Street Viaduct Replacement Project - Stage 2 Northwest 99 809936D Jan-10 4,962 700 US 2/97 Intersection Improvements North Central 2/97 202800D Apr-10 3,700 3,700
New Projects Total 92,068 30,445
CARRY OVER PROJECTS (awarded before 10-1-2007) Lake Easton Vic to Bullfrog I/C Vic WB - Concrete Rehab South Central 90 7757 Jun-09 19,325 7,515 Frenchtown Vicinity to Walla Walla - Add Lanes South Central 12 7474 Feb-08 3,733 420 I-5/SR16 Nalley Valley I/C Olympic 5 300567A Oct-08 16,600 13,910 SR532 Vic to Starbird Rd Vic PCCP Rehab Northwest I-5 7753 Jun-09 8,410 3,000 I-90, I-5 to 12th Ave S Seismic Retrofit Northwest 90 7629 Dec-08 41 30
Carry Over Projects Total 0
Total for New & Carry Over Projects 30,445
Note: There are no new or carry over projects in Southwest region with cement concrete pavement
For more information, please call the WSDOT Construction Office at (360) 705-7820 or visit http://www.wsdot.wa.gov/biz/construction 5/11/2010