10s-allam muro colado

28
1 June 27, 2013 BLUE PLAINS TUNNEL PROJECT DC Clean Rivers Project District of Columbia Water and Sewer Authority DCWater Blue Plains CSO Tunnel Washington, DC 2 Traylor/Skanska/Jay Dee Joint Venture Halcrow Inc., A CH2M Hill Company Bencor Corporation a wholly owned subsidiary of Layne

Upload: alfredo-a-lopez

Post on 15-Dec-2015

240 views

Category:

Documents


5 download

DESCRIPTION

muro colado

TRANSCRIPT

Page 1: 10S-Allam muro colado

1

June 27, 2013

BLUE PLAINS TUNNEL PROJECT

DC Clean Rivers Project

District of ColumbiaWater and Sewer Authority

DCWater Blue Plains CSO TunnelWashington, DC

2

• Traylor/Skanska/Jay Dee Joint Venture• Halcrow Inc., A CH2M Hill Company• Bencor Corporation a wholly owned subsidiary of Layne

Page 2: 10S-Allam muro colado

2

DCWater Blue Plains CSO TunnelWashington, DC• The Blue Plains Tunnel is 23’dia. and 23,600’ (4.5 miles) long including 5

shafts along the alignment on the east side of the Potomac/Anacostia River:

• Blue Plains Tunnel Discharge Pumping Station (2 shafts combined)• DS-Dewatering Shaft finished 132’ Dia 194.5’ deep.• SS-Screening Shaft finished 76’ Dia 176’ deep.• Bolling Air Force Base Drop Shaft finished 50’ Dia 146’ deep .• Poplar Point Drop Station finished 55’ Dia 139’ deep.• Main Pumping Station Drop Shaft finished 55’ Dia 123’ deep.

Aerial View of the BPT-DS-SS Site

DCWater Blue Plains CSO TunnelWashington, DC

Page 3: 10S-Allam muro colado

3

DCWater Blue Plains CSO TunnelWashington, DC

Diaphragm Walls•Access for deep tunnel•Soft ground

Other Option Considered•Ground freezing

Reason for Choosing D-Walls•Cheaper•Faster•Less Risky•More Available Contingencies

Typical Construction Procedure:• Develop Detailed Engineering Design• Site Preparation• Guide Wall Construction• Excavation• Desanding• QA/QC, Verticality Control & Verification• Reinforcing Element Fabrication & Placement• Concrete Placement • QA/QC Post Installation

DCWater Blue Plains CSO TunnelWashington, DC

Page 4: 10S-Allam muro colado

4

DCWater Blue Plains CSO TunnelWashington, DC

Ground Conditions

• Fill• 25-36 ft. deep, coarse silty sand w/gravel

• Alluvium• 17-25 ft. thick, clay to gravel• Consolidated under it’s own weight

• Potomac Group – Patapsco/Arundel Formation (P/A)• Below 51’ Dense hard soils• Stiff to hard silt/clay• Interlayers of sand/gravel

• Potomac Group – Patuxent Formation – (PTX)• Dense hard soils• Mostly sand/gravel w/interlayers of hard

silt/clay

Groundwater• Upper Aquifer – 20-30’ below ground surface• Lower Aquifer – 35’ below grade at El. -20’ MSL

7

DCWater Blue Plains CSO TunnelWashington, DC

• REQUIREMENTS• 100 year design life• Permanent ground loads

& 500 year flood level

• RESULTS• 7,000psi @ 56d• Steel fy = 60ksi• Minimum Cementitious

575 lb/yd3• w/cm ratio 0.4• High slag/fly ash

replacement• Min. cover requirement

6”

8 7/2/2013

Page 5: 10S-Allam muro colado

5

Develop Detailed Engineering Design

Designing and working out all of the details in advance will pay off with a smoother installation and minimize delays.

DCWater Blue Plains CSO TunnelWashington, DC

DCWater Blue Plains CSO TunnelWashington, DC

10

BPT - Shaft

• DS Shaft 139’ Dia.• SS Shaft 81’ Dia.

• Wall Thickness – 5’• Joining Wall – 8’-

18’

• D-Wall Panel Depth 194.5’

• Max Excavation 190’

Excavating inside the shafts

Page 6: 10S-Allam muro colado

6

DCWater Blue Plains CSO TunnelWashington, DC

117/2/2013

BPT - Shaft

• D-Wall 5’ thick• DS CIP – 3’

thick• SS CIP – 2’

thick

• Base Slabs• DS – 25’ thick• SS – 16’ thick

Design Profile of DS and SS Shafts

DCWater Blue Plains CSO TunnelWashington, DCComparison Prediction vs. Field Measurement

12

Plaxis 3DFE Mesh Shaft Wall

Page 7: 10S-Allam muro colado

7

DCWater Blue Plains CSO TunnelWashington, DCComparison Prediction vs. Field Measurement

13 7/2/2013

Lateral Wall Deflection max.Plaxis 3D =0.5”Inclinometer= 0.3”

Max. deflection occurs above the excavation level.

DCWater Blue Plains CSO TunnelWashington, DC

147/2/2013

Instrumentation for D-Walls Construction

• Inclinometers• IPI – In-Place Inc• Manual Incl

• SMPs• GMPs• UMPs• Piezometers• Extensometers

Instrumentation Around DS and SS Shafts

Page 8: 10S-Allam muro colado

8

DCWater Blue Plains CSO TunnelWashington, DC

15

Total Stress Cells

DCWater Blue Plains CSO TunnelWashington, DC

167/2/2013

Concrete Strain Gauges Rebar Strain Gauges

Coring Sample from Panel C-2

Page 9: 10S-Allam muro colado

9

DCWater Blue Plains CSO TunnelWashington, DCCHALLENGES• Heavily over-consolidated soils• Design req’d 60” wide panels• Design req’d 54” continuous wall

min and 96”for middle wall.• Tolerance of .12% for panel

deviation

17 7/2/2013

DCWater Blue Plains CSO TunnelWashington, DCCHALLENGES

• Y-Panel• Clay Soils

• Req’d centrifuges• Rebar

• 1,250 tons of rebar in DS & SS shafts

• Picks of 50 tons• GFRP at tunnel eyes• Slab Dowels

• DS - 2,620 slab dowels installed in 8’ shear key at the bottom for the base slab

• Concrete• 30,000 CY of tremie• 1,000 CY single tremie

18 7/2/2013

Page 10: 10S-Allam muro colado

10

Diaphragm Walls for Tunnel Shafts

Why use diaphragm walls in tunnel shaft construction?

The extensive use of Tunnel Boring Machines (TBM) for modern tunnel construction has produced the need for deep access shafts to allow for the lowering and removal of these machines. These shafts must be as deep as the new tunnels. Diaphragm walls installed in a circular shape have been proven as an efficient and cost effective solution for deep shafts in soils over conventional methods. These diaphragm walls can be installed using clamshells & hydromills. For deeper shafts the hydromill has proven itself as an effective tool for quickly installing diaphragm walls into any type of soil and rock so it has also been accepted as the cost effective solution for these types of deep shafts:Significant depth walls are feasible with diaphragm walls using hydromills.

Hydromills can install diaphragm walls with large wall thickness (1.5m+) to support large compressions loads as required for very deep shafts.

Can readily excavate through any rock formation and boulders.

High rate of production can permit projects to be completed much faster than conventional methods.

Brightwater Conveyance System Seattle, WA

West/East Side CSO Portland, OR

Edison Force Main, Middlesex Co, NJ

Riverbank Filtration Louisville, KY

Bay Division Pipeline Bay Tunnel, San Francisco, CA

Port Mann Main Water Supply Tunnel, Vancouver, BC

Deep Rock CSO Tunnels, Indianapolis, IN

Lower Harbor Brook CSO , Syracuse, NY

DCWASA Blue Plains CSO Tunnel, Washington, DC

Recent Projects Performed by Bencor a subsidiary of Layne

RECENT TUNNEL SHAFT PROJECTSUSING HYDROMILLS

Page 11: 10S-Allam muro colado

11

DCWater Blue Plains CSO TunnelWashington, DCMobilization of 2 Hydromills and 2 Buckets sized for this job 60” thick

DCWater Blue Plains CSO TunnelWashington, DC

Equipment excavating at BPT-DS-SS Site

2 Hydromills & 2 Buckets

Page 12: 10S-Allam muro colado

12

DCWater Blue Plains CSO TunnelWashington, DC

Verticality Checking to meet tolerances of 0.125% (3 inches maximum deviation over 195 feet depth

Koden reader and output

DCWater Blue Plains CSO TunnelWashington, DC

Analysis of collected verticality data

Closing panel verticality compared to adjacent primary panels installed

-40-30

-20-10

010

2030

40

-5-6-7-8-9-10

-11

-12

-13

-14

-15

-16

-17

-18

-19

-20

-21

-22

-23

-24

-25

-26

-27

-28

-29

-30

-31

-32

-33

-34

-35

-36

-37

-38

-39

-40

-41

-42

-43

-44

-45

-46

-47

-48

-49

-50

-51

-52

-53

-54

-55

-56

-57

-58

-59

-60

OF

F C

EN

TE

R, in

DE

PT

H, m

P-17 Towards DS Shaft P-17 Away from DS Shaft C-18 Towards DS Shaft C-18 Away from DS Shaft

Tow

ards A

way

Page 13: 10S-Allam muro colado

13

BPT- Cutoff Wall for TBM Breakout

DCWater Blue Plains CSO TunnelWashington, DC

Shaft ID = 139’ (42.4m)Depth = 194.5’ (59.3m)Thickness = 60” (1.5m)

Shaft excavations now completed

BPT- Discharge Pumping StationShaft Plan

DCWater Blue Plains CSO TunnelWashington, DC

Page 14: 10S-Allam muro colado

14

Shaft Section

DCWater Blue Plains CSO TunnelWashington, DC

Reinforcement Details

DCWater Blue Plains CSO TunnelWashington, DC

Page 15: 10S-Allam muro colado

15

Guide wall excavation and construction

BPT-DS-SS

DCWater Blue Plains CSO TunnelWashington, DC

5ft thick panel excavation using hydraulic clamshells & hydromills

BPT-DS-SS

DCWater Blue Plains CSO TunnelWashington, DC

Page 16: 10S-Allam muro colado

16

Desanding plant must be sized to produce the required slurry for a safe and efficient project

Slurry Desanding Plants

DCWater Blue Plains CSO TunnelWashington, DC

Vertical Tanks – used when limited space is available

Slurry Storage

DCWater Blue Plains CSO TunnelWashington, DC

Page 17: 10S-Allam muro colado

17

Slurry storage ponds are used if site conditions permit and if very large quantities of slurry are required

Slurry Storage

DCWater Blue Plains CSO TunnelWashington, DC

Slurry desander in operation at the Blue Plains Tunnel

DCWater Blue Plains CSO TunnelWashington, DC

Page 18: 10S-Allam muro colado

18

Full length reinforcing cages for typical primary panels are fabricated on site.

DCWater Blue Plains CSO TunnelWashington, DC

Y Panel Rebar Cage fabricated on site.

Rebar Cages for Middle Wall and Y Panel

DCWater Blue Plains CSO TunnelWashington, DC

Page 19: 10S-Allam muro colado

19

Middle Wall Rebar Cage built with 3 layers of reinforcement

Rebar Cages for Middle Wall

DCWater Blue Plains CSO TunnelWashington, DC

Full length reinforcing cages are lifted into place

DCWater Blue Plains CSO TunnelWashington, DC

Page 20: 10S-Allam muro colado

20

Concrete placed using multiple tremie pipes to complete 1032 cy “Y” panels in 10 hours

DCWater Blue Plains CSO TunnelWashington, DC

BPT- Dewatering Shaft being excavated

DCWater Blue Plains CSO TunnelWashington, DC

Page 21: 10S-Allam muro colado

21

DCWater Blue Plains CSO TunnelWashington, DC

BPT- Dewatering Shaft being excavated

BPT- Dewatering Shaft & Screening Shaft 1/3 excavated

DCWater Blue Plains CSO TunnelWashington, DC

Page 22: 10S-Allam muro colado

22

BPT- Dewatering Shaft being excavated

DCWater Blue Plains CSO TunnelWashington, DC

Lowering TBM into position inside completed shaft

DCWater Blue Plains CSO TunnelWashington, DC

Page 23: 10S-Allam muro colado

23

Lowering TBM into position inside completed shaft

DCWater Blue Plains CSO TunnelWashington, DC

Bolling Air Force Base Shaft Under Construction

BAFB Shaft Plan

Shaft ID = 55’ (16.8m)Depth = 148’ (45.1m) Thickness = 42” (1.1m)

DCWater Blue Plains CSO TunnelWashington, DC

Page 24: 10S-Allam muro colado

24

Poplar Point Shaft

Aerial View of the PPJS Site

DCWater Blue Plains CSO TunnelWashington, DC

Poplar Point Shaft

Aerial View of the PPJS Site

DCWater Blue Plains CSO TunnelWashington, DC

Page 25: 10S-Allam muro colado

25

Poplar Point Shaft

PPJS Site Preparation Guide Walls Construction

DCWater Blue Plains CSO TunnelWashington, DC

Poplar Point Shaft Under Construction

PPJS Shaft Plan

Shaft ID = 60’ (18.3m)Depth = 139’ (42.4m) Thickness = 42” (1.1m)

DCWater Blue Plains CSO TunnelWashington, DC

Page 26: 10S-Allam muro colado

26

Poplar Point Shaft Under Construction

DCWater Blue Plains CSO TunnelWashington, DC

Main Pumping Station Dewatering Shaft

Aerial View of the MPS Site

DCWater Blue Plains CSO TunnelWashington, DC

Page 27: 10S-Allam muro colado

27

MPS Shaft Plan

Main Pumping Station Dewatering Shaft

Shaft ID = 60’ (18.3m)Depth = 123’ (37.5m) Thickness = 42” (1.1m)

DCWater Blue Plains CSO TunnelWashington, DC

DCWater Blue Plains CSO TunnelWashington, DCLESSONS LEARNED

• Utilizing D-Wall in Permanent Structure• Req 100-yr design• Concrete cover• More Rebar• Cementitious content• Concrete comp. strength• Tolerances

• Excavating in stiff Clays• Desanding & centrifuges• Disposal challenges• Bentonite vs. Poly blends

54 7/2/2013

Page 28: 10S-Allam muro colado

28

DCWater Blue Plains CSO TunnelWashington, DC

LESSONS LEARNED

• Excavation• Dry

• High production• Easily repair

voids/bulges• Wet

• Slower production• More complicated• Unknown wall

condition• Repairs postponed

55 7/2/2013

DCWater Blue Plains CSO TunnelWashington, DC